1
STATUS OF THE INFN-LASA CONTRIBUTION TO THE PIP-II LINAC 28 June 2021 – 02 July 2021 The international effort for the PIP-II project at Fermilab has been joined by INFN with its planned contribution to the PIP-II proton linac in the low-beta section. INFN-LASA is finalizing its commitment to deliver in kind the full set of the LB650 cavities, 36 plus spares resonators with 5-cell cavities at 650 MHz and geometrical beta 0.61. All cavities, designed by INFN-LASA, will be produced and surface treated in industry to reach the unprecedented performances required by PIP-II, qualified through vertical cold test at state-of-the art infrastructures and delivered as ready for the linac at the string assembly site. The status of INFN contribution to PIP-II, the development of infrastructures and prototypes as well as the ongoing activities toward the start of series production are summarized in this paper. INFN Contribution to PIP-II INFN firstly provided a novel RF design for the LB650 cavities, fully plug compatible with the Fermilab technical interfaces and performances specifications. Cavity design meets the PIP-II project performance requirements INFN contribution aims to cover the needs of LB650 section, and this includes: 38 SC cavities required to equip 9 cryomodules with 2 spares, delivered as ready for string assembly. Qualification via vertical cold-test provided by INFN through a qualified partner cold- testing infrastructure Compliance to the PIP-II System Engineering Plan and Technical Interfaces. PIP-II LB650 Project Specifications Acc. Gradient 16.9 MV/m Q 0 > 2 10 10 RF rep rate 20 Hz to CW Beta 0.61 RT SC Low-Beta (LB650, β=0.61) cryomodule PIP-II LB650 Challenges PIP-II LB650 cavities are among the key scientifical challenges of the project, requiring: an unprecedented quality factor for these resonators. Besides accelerating mode and passband, High-Order Modes risks have been assessed so that neither instabilities nor additional cryogenic losses are posing critical issues. PIP-II operational scenario is an uncharted territory in terms of detuning control, and this requires deep understanding of Lorentz Force detuning, pressure sensitivity and mechanical leading parameters as rigidities, yield limits, stresses. Extensive finite element analysis to evaluate the challenging mutual compliancy to both PED and ASME codes. Last mode in 2 nd monopole passband, +8 MHz away from 9th ML R/Q of modes in the beta range LFD frequency shift (blue) and pressure coefficient (red) as a function of external cavity stiffness for a cold cavity. INFN Prototypes A total of 7 PIP-II LB650 cavities already produced (single and multi cell), 3 of them shared with Fermilab for a joint development effort. First INFN single-cell with baseline recipe: Developed with Zanon, novel EP and its diagnostic 200 mm bulk EP + 800 ˚C HT + final EP + 120 ˚C Vertical test at INFN-LASA Hiqh-Q treatment and re-test coming next Second INFN single-cell treated at FNAL with doping 180 mm bulk EP + 900 ˚C HT +N-Doping + final EP Test at Fermilab-VTS, project goals met Two INFN 5-cell cavities in parallel B61-EZ-001 from March at Fermilab VTS B61-EZ-002 by July at LASA test stand PIP-II Specs Single-cell VTs Pre-Production phase, 2019-2021 Electro-polishing (EP) surface treatment developed and proved with novel diagnostic tools tools for a LB650 single-cell. Ongoing extension for multi-cell. See M. Bertucci (INFN-LASA) et al. paper at this conference, THPCAV014 Test bench for chemical surface etching (EP and BCP) validation of fluid-dynamics simulation through Particle Image Velocimetry camera technique in collaboration with Politecnico di Milano. THPCAV014 Rev. Sci. Instrum. 92, 023307 (2021) Thickness removal during EP INFN cold test infrastructure at LASA is being upgraded in view of the LB650 cavities vertical tests: Cylindrical cryo-perm inner shield realized and installed in order to halve the currently measured 8 mG average remnant field in the cavity equator region. Higher cryogenic power, up to 70 W at 32 mbar, thanks to an increased primary pumping skid throughput. Sub-atmospheric refilling system installed to extend cavity testing time by means of counter-flow heat-exchanger followed by a Joule-Thomson expander. Faster cool-down rate, now limited to about 1 K/min, via a different distribution of helium gas flow around the cavity. Inner Cryoperm© magnetic shield Heat-Exchanger and its process lines Production phase, 2021-2025 Major contracts, mainly cavity material, manufacturing and cold- testing, expected to be issued by 2022 Two pre-series cavities to be qualified both as naked and as jacketed. Subsequent cavities will reach cold-testing infrastructure as ready for string assembly First Site Acceptance Review to take place under INFN responsibility at partner testing infrastructure after qualification cold-test. Final Site Acceptance Review to take place at string assembly site. Production cavities targeted to be delivered at string assembly site in 9 batches from May 2024 to July 2025 In-Kind contribution documents: Project Planning Document signed Quality Assurance Plan being finalized Risk Management Plan and Risk Register drafted and beign discussed B61-EZ-002 B61-EZ-002 B61-EZ-002 at LASA test-stand Cav N β k (%) N 2 /(βk) TESLA 9 1 1.87 4331 SNS MB 6 0.61 1.52 3883 ESS MB 6 0.67 1.55 3467 PIP-II LB 5 0.61 0.95 4331 Cell-to-cell coupling k and field-flatness sensitivity for various cavities Simulated (sx) vs. Measured (dx) velocity field during etching THPCAV014

STATUS OF THE INFN -LASA...STATUS OF THE INFN -LASA 28 June 2021 – 02 July 2021 CONTRIBUTION TO THE PIP-II LINAC The international effortfor the PIP-II project at Fermilab has been

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: STATUS OF THE INFN -LASA...STATUS OF THE INFN -LASA 28 June 2021 – 02 July 2021 CONTRIBUTION TO THE PIP-II LINAC The international effortfor the PIP-II project at Fermilab has been

STATUS OF THE INFN-LASA CONTRIBUTION TO THE PIP-II LINAC28 June 2021 – 02 July 2021

The international effort for the PIP-II project at Fermilab has been joined by INFN with its planned contribution to the PIP-II proton linac inthe low-beta section. INFN-LASA is finalizing its commitment to deliver in kind the full set of the LB650 cavities, 36 plus spares resonatorswith 5-cell cavities at 650 MHz and geometrical beta 0.61. All cavities, designed by INFN-LASA, will be produced and surface treated inindustry to reach the unprecedented performances required by PIP-II, qualified through vertical cold test at state-of-the art infrastructuresand delivered as ready for the linac at the string assembly site. The status of INFN contribution to PIP-II, the development of infrastructuresand prototypes as well as the ongoing activities toward the start of series production are summarized in this paper.

INFN Contribution to PIP-IIINFN firstly provided a novel RF design for the LB650 cavities, fully plug compatible withthe Fermilab technical interfaces and performances specifications. Cavity design meetsthe PIP-II project performance requirements

INFN contribution aims to cover the needs of LB650 section, and this includes:• 38 SC cavities required to equip 9 cryomodules with 2 spares, delivered as ready for

string assembly.• Qualification via vertical cold-test provided by INFN through a qualified partner cold-

testing infrastructure• Compliance to the PIP-II System Engineering

Plan and Technical Interfaces.PIP-II LB650 Project Specifications

Acc. Gradient 16.9 MV/mQ0 > 2 1010

RF rep rate 20 Hz to CWBeta 0.61

RT

SC

Low-Beta (LB650, β=0.61)

cryomodule

PIP-II LB650 ChallengesPIP-II LB650 cavities are among the key scientifical challenges of the project, requiring:• an unprecedented quality factor for these resonators.• Besides accelerating mode and passband, High-Order Modes risks have been

assessed so that neither instabilities nor additional cryogenic losses are posing critical issues.

• PIP-II operational scenario is an uncharted territory in terms of detuning control, and this requires deep understanding of Lorentz Force detuning, pressure sensitivity and mechanical leading parameters as rigidities, yield limits, stresses.

• Extensive finite element analysis to evaluate the challenging mutual compliancy to both PED and ASME codes.

Last mode in 2nd monopole passband, +8 MHz away from 9th ML

R/Q of modes in the beta

range

LFD frequency shift (blue) and pressure coefficient (red) as a function of external cavity stiffness for a

cold cavity.

INFN PrototypesA total of 7 PIP-II LB650 cavities already produced (single and multi cell), 3 of them shared with Fermilab for a joint development effort.First INFN single-cell with baseline recipe:• Developed with Zanon, novel EP and its diagnostic• 200 mm bulk EP + 800 ˚C HT + final EP + 120 ˚C• Vertical test at INFN-LASA • Hiqh-Q treatment and re-test coming next

Second INFN single-cell treated at FNAL with doping• 180 mm bulk EP + 900 ˚C HT +N-Doping + final EP• Test at Fermilab-VTS, project goals met

Two INFN 5-cell cavities in parallel• B61-EZ-001 from March at Fermilab VTS• B61-EZ-002 by July at LASA test stand

PIP-II Specs

Single-cell VTs

Pre-Production phase, 2019-2021Electro-polishing (EP) surface treatment developed and proved with novel diagnostic tools tools for a LB650 single-cell. Ongoing extension for multi-cell.

• See M. Bertucci (INFN-LASA) et al. paper at this conference, THPCAV014

Test bench for chemical surface etching (EP and BCP) validation of fluid-dynamics simulation through Particle Image Velocimetry camera technique in collaboration with Politecnico di Milano.

THPCAV014

Rev. Sci. Instrum. 92, 023307 (2021)

Thickness removal during EP

INFN cold test infrastructure at LASA is being upgradedin view of the LB650 cavities vertical tests:

• Cylindrical cryo-perm inner shield realized and installed in order to halve the currently measured 8 mG average remnant field in the cavity equator region.

• Higher cryogenic power, up to 70 W at 32 mbar, thanks to an increased primary pumping skid throughput.

• Sub-atmospheric refilling system installed to extend cavity testing time by means of counter-flow heat-exchanger followed by a Joule-Thomson expander.

• Faster cool-down rate, now limited to about 1 K/min, via a different distribution of helium gas flow around the cavity.

Inner Cryoperm© magnetic shield

Heat-Exchanger and its process

lines

Production phase, 2021-2025Major contracts, mainly cavity material, manufacturing and cold-testing, expected to be issued by 2022

Two pre-series cavities to be qualified both as naked and as jacketed. Subsequent cavities will reach cold-testing infrastructure as ready for string assembly

First Site Acceptance Review to take place under INFN responsibility at partner testing infrastructure after qualification cold-test. Final Site Acceptance Review to take place at string assembly site.Production cavities targeted to be delivered at string assembly site in 9 batches from May 2024 to July 2025

In-Kind contribution documents:• Project Planning Document signed• Quality Assurance Plan being finalized• Risk Management Plan and Risk Register

drafted and beign discussed

B61-EZ-002

B61-EZ-002

B61-EZ-002 atLASA test-stand

Cav N β k (%) N2/(βk)TESLA 9 1 1.87 4331SNS MB 6 0.61 1.52 3883ESS MB 6 0.67 1.55 3467PIP-II LB 5 0.61 0.95 4331

Cell-to-cell coupling k and field-flatness sensitivity for various cavities

Simulated (sx) vs. Measured (dx) velocity

field during etching

THPCAV014