Upload
stephen-byrd
View
219
Download
3
Tags:
Embed Size (px)
Citation preview
STATUS OF DAQ PROJECTSTATUS OF DAQ PROJECT
OPERA collaboration meeting, Hamburg, 3-5 June, ’04 J.Marteau
T.T. LOW VOLTAGE POWER SUPPLIES
NETWORK, RACKS & CABLING
PT DAQ DEVELOPMENTS
CONCLUSIONS
TT LOW VOLTAGE POWER SUPPLIES
POWER SUPPLIES COST : 2 options can be considered OPTION A : 1 output () for 4 boards (i.e. per corner)
• offers / SM : 72keuros to 110keuros (SCHROFF, M.E.S., CAEN, WIENER)• remark 1 : CAEN offered a special 24% discount which is over now• remark 2 : WIENER could align its price on the one of CAEN
OPTION B : 1 output () for 16 boards (i.e. per TT plane) ex. WIENER PL6021 F8-12 :6 modules with (+) & (-) outputs, max. 23A/output 1 module/planeremote control & monitoring for each moduleTCP/IP or CANbus interface6 crates / SM1 air ventilation for 5 crates 6500euros/crate + 1070euros/fan unit offer / SM : 39keuros delivery : 10-12 weeks, prototype available in 4 weeks meeting in Lyon 08 June with Wiener representatives
2 racks / SM
OPTION A : we made the proposal to put small switches in the TTplane corners, which is an economical but risky option (absence of monitoring, long term stability of the small commercial switches…) cost / SM : 16 keuros
OPTION B : we have contact with network specialists who advise to replace these small corner switches with more reliable 24&48 ports switches that can be monitored and to take custom bundle cables. for 1 SM : 12 switches 48 ports, 3 switches 24 ports CISCO systems : 2295euros & 1191euros (IN2P3 34% discount) cost / SM (estimate) : 21 keuros (including discount, 32 keuros otherwise)
NETWORK, RACKS & CABLING
NETWORK, RACKS & CABLING
48
T.T. DAQ P.T. DAQ RPC-XPC-VETO
Manager /Admin.
48
DB
192.168.1.
192.168.0.
192.168.2. 192.168.3. 192.168.4.
Internet
48
48
48
4848
48
48
48
48
48
1Gbits link100 Mbits link
Level 0 networkLevel 1 networkAdmin. networkPublic network
24
2424
adm. adm. adm.
TT DAQ 2
P.T. DAQ RPC DAQ
VLAN admin. VLAN 0
VLAN 3 VLAN 4
VLAN 1 VLAN 2
main power supply racks
each corner redistributesto 4 electronic boardsafter filtering
NETWORK, RACKS & CABLING :TT low voltage distribution
All the cables(power supplies & ethernet)will run along the end-capsin 1 large & 1 small cable trays
The connection « platine »is being designed with theCymantec company.1st prototype ready.We will define the cable lengths etc on Wall 1 mounted in Strasbourg
NETWORK, RACKS & CABLING :TT Ethernet distribution
CONTROL ROOM : A control room will be located behind the last magnet (2 barracks of 2m*3m on top of each other). The control room will host DAQ and remote Slow Control & monitoring.
RACKS DISTRIBUTION : RPCs require 16 racks in total. Magnets require 1 rack for power supplies on each side / SM, to be located in the middle of the magnet, with a total clearance of 1.7m. PTs require 6 racks in total. It has been agreed that these racks could be located in the middle of the platform (to be checked w.r.t. the temperature).Details about the racks occupancy have to be provided. 1 slot (1U) has to be left for the PT network switch. TT need 8 racks in total. They are located only on 1 side (wall side). In total 30 racks are needed and should be available from MACRO (to be checked). A cable tray of ~0.5m will collect the cables from the back of the racks.
GENERAL SKETCH FOR RACKS ORGANIZATION : see next slide.(assuming standard rack dimensions : ~0.6m width, ~1.8m height)
NETWORK, RACKS & CABLING
C.R.1
C.R.2
5000 4340 5000 43405575
max.2000
Spectro.2 T.T.2 Spectro.1 T.T.1
RP
C
RP
C
RP
C
RP
C
RP
C
RP
C
RP
CR
PC
mag
net
mag
net
P.T. racksP.T. racks
Cable tray
Cable tray
Wall side
Corridor side
NETWORK, RACKS & CABLING
NETWORK, RACKS & CABLING : RPC crates
Number of crates required for 1 spectrometer
FEB (RPC) 4 83 boards/layer 3.5 boards/layer X
2.5 boards/layer Y6 layers/crate 3 layers/crate22 layers RPC + 2 layers XPC 22 layers RPC + 2 layers XPC
FEB (XPC) 1 12 layers XPC 2 layers XPC
Controller 21 board/layer22 layers RPC + 2 layers XPC
HV (-) 11 ch/layer4 layers/board40 chs/crate22 layers RPC + 2 layers XPC
2HV (+) 3 chs/layer
40 chs/crate22 layers RPC + 2 layers XPC
Current Meter 87 chs/layer24 chs/crate22 layers RPC + 2 layers XPC
27 crates / spectrometer
NETWORK, RACKS & CABLING : RPC racks (odd)
Temperature & Reset Temperature & Reset Temperature & Reset Temperature & Reset
FAN FAN FAN FAN
Heat exchanger Heat exchanger Heat exchanger Heat exchanger
FAN FAN FAN
FAN FAN FAN FAN
Heat exchanger Heat exchanger Heat exchanger Heat exchanger
FAN FAN FAN FAN
Power Management & Alarms
CTRL
Power Management & Alarms
FEB (RPC - X+Y View)
SYS 127 (-) FEB (RPC - X+Y View)
FEB (RPC - X+Y View)
FEB (RPC - X+Y View)
FEB (RPC - X+Y View)
FEB (RPC - X+Y View)FEB (XPC) FEB (RPC - X+Y View)
Timing
Current Meter & HV Distr.
SYS 127 (-)
Power Management & Alarms Power Management & Alarms
Current Meter & HV Distr.
Current Meter & HV Distr.
Current Meter & HV Distr.
FEB (RPC - X+Y View)
1740
mm
= 3
9 U
NETWORK, RACKS & CABLING : RPC racks (even)
Temperature & Reset Temperature & Reset Temperature & Reset Temperature & Reset
FAN FAN FAN FAN
Heat exchanger Heat exchanger Heat exchanger Heat exchanger
FAN FAN FAN
FAN FAN FAN FAN
Heat exchanger Heat exchanger Heat exchanger Heat exchanger
SLOW CONTROL
SLOW CONTROL SWITCH 48
FAN FAN FAN
CTRL
Power Management & Alarms
FEB (XPC)
Power Management & Alarms
FEB (RPC -Y View)
FEB (RPC -Y View)
SYS 127 (-)
CTRL
Current Meter & HV Distr.
Power Management & Alarms
FEB (RPC -Y View)
FEB (RPC -Y View)
Power Management & Alarms
Current Meter & HV Distr.
Current Meter & HV Distr.
Current Meter & HV Distr.
Switch required close to controllercrates
NETWORK, RACKS & CABLING : TT racks
Temperature & Reset Temperature & Reset Temperature & Reset Temperature & Reset
SWITCH 24
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
SWITCH 48
FAN FAN FAN FAN
Power Management & Alarms
L.V. POWER SUPPLIES
L.V. POWER SUPPLIES
L.V. POWER SUPPLIES
VME CLOCK
Power Management & Alarms
TT DAQ 1 P.C.
TT DAQ 2 P.C.
RPC DAQ P.C.
PT DAQ P.C.
Power Management & AlarmsPower Management & Alarms
L.V. POWER SUPPLIES
L.V. POWER SUPPLIES
L.V. POWER SUPPLIES
PT DAQ DEVELOPMENTS
TDC 1
Common STOP
Selectchip
Mezzanine :•readout sequence•zero suppress•trigger timestamps
ClockRJ45
RJ45
RJ45
16 bits BUS : signal
6 bits BUS :control
TDC 2
TDC 12
TDC 11
VME board
DESIGN OF TDC BOARD, including the Ethernet Mezzanine with MSC company (meeting in April).Collaboration of M.Braueur.
TRIGGER STRATEGY (see also talk by M.Braueur)
Trigger input (common TDC stop) : OR of 2 nearby (X)RPC planes
Trigger rate : around 14 kHz Data flow : 16 bits / channel 16 * 96 * 14 k = 22 Mbits / s / TDC board (max. 100 Mbits / s) possible reduction with zero suppress : typically 3 Mbits / s assuming 3 noisy channels per board still leads to 125 Mbits / s on the PT DAQ PC
Being close to the limit, we need the trigger strategy (including XPC & VETO) to be studied in more details (e.g. OR of N1 planes & OR of N2 planes) in terms of rates, efficiencies, hardware setting…
PT DAQ DEVELOPMENTS
SLOW CONTROL & MONITORING : Hardware setup :
HV modules (CAEN SY2527, ethernet CAEN protocol) crates (CAN bus) T sensors (CAN bus) Gas system (dedicated PC) 2-3 PCs to be connected with the DAQ Manager
Software : we agreed to use CORBA for communication with DAQ Manager : some libraries already exist for these applications also used by BMM (Brick Manipulator Manager) M.Braueur start to work on it & to compile the libraries
Since most the items (hardware & software) are common to PT & RPC, we shouldoptimize the work & avoid double developments :
combine the purchase of e.g. racks & crates (also for easier maintenance) adopt the same software environment
PT DAQ DEVELOPMENTS
BUDGET : Update of the DAQ budget performed and submitted to IN2P3 (meeting 09 June) New procedure for the public markets (January ’04) entering into application now
MEZZANINE BOARDS PRODUCTION : A serious bug has been discovered (and confirmed by AXIS) recently, concerning the RESET input on some MCM chips. This bug is not fixed by AXIS (not even in the upgraded version of the chip) This requires a new version for the mezzanine (prototype+serie) which prevents us to have the complete TT electronics ready for the 1st 12 walls installation.
CAMEROP BOARDS PRODUCTION : Final version now under tests 2 Pre-series available (4+36 boards) to be used for tests & calibration Next serie (this summer) to be installed on the 1st 12 TT walls (mezzanines will be plugged later on the CAMEROP boards : less painful solution to avoid delays).
CONCLUSIONS (I)
REQUEST : work could be easier if we could use F/E boards & LED pulsers(when it is possible to pick-up samples from the production batches)
RPC MEZZANINES (strongly required) : dedicated software version (VHDL & CORBA) needs to be developed a copy of the VME motherboard (+ F/E emulator) has been asked in order to speed up developments and tests
PT TDC BOARDS : not on the critical path for the moment.
SOFTWARE : CORBA software is improving constantly (1st versions debugged w.r.t. memoryleaks) The TTsensor / TTdaq processes defined with omniORB.4.0.3 libraries Automatic board tests program using the CORBA software Start the tests with large number of boards connected (equivalent to 1 TT wall).
CONCLUSIONS (II)