Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of San Diego Gas & Electric Company (U 902E) for Approval of SB 350 Transportation Electrification Proposals.
Application 17-01-020
And Related Matters.
Application 17-01-021 Application 17-01-022
JOINT INVESTOR-OWNED UTILITIES’ INTERIM REPORT
ON PRIORITY REVIEW PROJECTS
ANNA VALDBERG ANDREA L. TOZER
Attorneys for SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-6713 Facsimile: (626) 302-6693 E-mail: [email protected]
Dated: January 31, 2020
1
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of San Diego Gas & Electric Company (U 902E) for Approval of SB 350 Transportation Electrification Proposals.
Application 17-01-020
And Related Matters.
Application 17-01-021 Application 17-01-022
JOINT INVESTOR-OWNED UTILITIES’ INTERIM REPORT
ON PRIORITY REVIEW PROJECTS
In compliance with D.18-01-024, Southern California Edison Company (SCE) hereby
submits this interim report on the status of Priority Review Projects, on behalf of itself, San
Diego Gas & Electric Company (SDG&E), and Pacific Gas and Electric Company (PG&E),
referred to collectively as the investor-owned utilities or IOUs.1 The report is attached hereto as
Appendix A.
1 Pursuant to Rule 1.8(d), representatives for PG&E and SDG&E have authorized SCE to sign and
submit this report on their behalf.
2
Respectfully submitted, ANNA VALDBERG ANDREA L. TOZER
/s/ Andrea L. Tozer By: Andrea L. Tozer
Attorneys for SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-6713 Facsimile: (626) 302-6693 E-mail: [email protected]
January 31, 2020
Appendix A
CALIFORNIA TRANSPORTATION ELECTRIFICATION PRIORITY REVIEW
PROJECTS INTERIM EVALUATION REPORT
SB350 Transportation Electrification
Priority Review Projects
Interim Evaluation Report
January 31, 2020
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page i
Table of Contents
1. Introduction ...............................................................................................................................1
1.1 Evaluation Scope ....................................................................................................................... 4
1.2 Evaluation Approach ............................................................................................................... 15
1.3 Organization of Report ............................................................................................................ 19
2. San Diego Gas and Electric Company ......................................................................................... 21
2.1 Fleet Delivery Services ............................................................................................................ 21
2.2 Green Shuttles......................................................................................................................... 38
2.3 Airport Ground Support .......................................................................................................... 53
2.4 Port Electrification .................................................................................................................. 62
2.5 Electrify Local Highways .......................................................................................................... 74
2.6 Dealership Incentives .............................................................................................................. 82
3. Southern California Edison ........................................................................................................ 98
3.1 Port of Long Beach Rubber Tire Gantry Crane ........................................................................ 98
3.2 Port of Long Beach Terminal Yard Tractors .......................................................................... 108
3.3 Electric Transit Bus Make-Ready Program ............................................................................ 118
3.4 Urban DC Fast Charging Clusters .......................................................................................... 128
3.5 Charge Ready Home Installation Rebate Program ............................................................... 146
4. Pacific Gas and Electric ........................................................................................................... 162
4.1 Electric School Bus Renewables Integration Project – Pittsburg Unified School District ..... 162
4.2 Bus Fleet Demonstration – San Joaquin Regional Transit District ........................................ 180
4.3 Idle Reduction Technology Project – eTRUs at Albertsons Distribution Center ................... 204
4.4 Home Charger Information Resource Program .................................................................... 217
Three SMJU Priority Review Project Status Update ......................................................................... 221
Priority Review Project Cost Status Summary ................................................................................. 224
Compilation of Lessons Learned to Date ......................................................................................... 227
Acronyms and Abbreviations .......................................................................................................... 231
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page ii
List of Tables
Table 1. Fleet electrification off-road EV charging infrastructure summary PRP summary ......................... 7
Table 2. Fleet electrification medium- and heavy-duty EV charging infrastructure PRP summary ............. 8
Table 3. Public access stations PRP summary ............................................................................................. 10
Table 4. Electrification promotions PRP summary ..................................................................................... 12
Table 5. Example sources of evaluation data ............................................................................................. 15
Table 6. Types of evaluation data by PRP grouping .................................................................................... 16
Table 7. SDG&E Fleet Delivery Services PRP Proposed Costs ..................................................................... 35
Table 8. SDG&E Fleet Delivery Services PRP costs as of September 30, 2019 ............................................ 35
Table 9. SDG&E Fleet Delivery Services PRP Benefits ................................................................................. 36
Table 10. SDG&E Green Shuttles PRP proposed costs ................................................................................ 49
Table 11. SDG&E Green Shuttles PRP costs as of September 30, 2019 ...................................................... 50
Table 12. SDG&E Green Shuttle PRP benefits ............................................................................................. 51
Table 13. Banks of chargers at SDIA for SDG&E Airport GSE PRP ............................................................... 55
Table 14. SDG&E Airport Ground Support PRP proposed costs ................................................................. 59
Table 15. SDG&E Airport Ground Support PRP costs as of September 30, 2019 ....................................... 60
Table 16. SDG&E Airport Ground Support PRP Benefits ............................................................................ 61
Table 17. SDG&E Port Electrification PRP proposed costs .......................................................................... 69
Table 18. SDG&E Port Electrification PRP costs as of September 30, 2019 ................................................ 70
Table 19. SDG&E Port Electrification PRP benefits ..................................................................................... 71
Table 20. SDG&E Electrify Local Highways PRP proposed costs ................................................................. 79
Table 21. SDG&E Electrify Local Highways PRP costs as of September 30, 2019 ....................................... 80
Table 22. SDG&E Electrify Local Highways PRP benefits ............................................................................ 80
Table 23. Comparison of program activity and region characteristics ....................................................... 89
Table 24. SDG&E Dealership Incentives PRP costs ..................................................................................... 93
Table 25. PlugStar site traffic (program areas and national) ...................................................................... 94
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page iii
Table 26. SCE POLB RTG Crane PRP costs as of November 2019 .............................................................. 105
Table 27. SCE POLB RTG Crane PRP benefits summary ............................................................................ 106
Table 28. SCE POLB Terminal Yard Tractor PRP costs as of November 2019 ........................................... 115
Table 29. SCE POLB Terminal Yard Tractor PRP benefits summary .......................................................... 116
Table 30. SCE Electric Transit Bus Make-Ready PRP costs as of November 2019 .................................... 125
Table 31. SCE Electric Transit Bus Make-Ready PRP benefits ................................................................... 126
Table 32. SCE Urban DCFC Clusters PRP Costs as of November 2019 ...................................................... 143
Table 33. SCE Urban DCFC Clusters PRP benefits ..................................................................................... 144
Table 34. SCE Charge Ready Home Installation Rebate program PRP costs as of November 2019 ......... 150
Table 35. PUSD PRP costs as of October 2019 .......................................................................................... 174
Table 36. Summary of issues with project equipment and associated resolution ................................... 176
Table 37. Relevant electric bus specifications .......................................................................................... 188
Table 38. Summary of PG&E project costs through October 2019 .......................................................... 194
Table 39. RTD unanticipated challenges and maintenance issues ........................................................... 199
Table 40. Unanticipated challenges and maintenance issues encountered by Albertsons ..................... 214
Table 41: Summary of PG&E Project Costs through October 2019 .......................................................... 215
List of Figures
Figure 1. PRP timeline and current status at time of this report .................................................................. 3
Figure 2. High-level three-phase evaluation approach ................................................................................. 4
Figure 3. Potential PRP co-benefits ............................................................................................................... 5
Figure 4. PRP groupings ................................................................................................................................ 5
Figure 5. Fleet electrification projects .......................................................................................................... 6
Figure 6. Public access station projects ........................................................................................................ 9
Figure 7. Electrification promotion projects ............................................................................................... 11
Figure 8. PRP research questions ................................................................................................................ 14
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page iv
Figure 9. Individual PRP section organization ............................................................................................. 20
Figure 10. UPS BTC Power L2 EVSE from Greenlots .................................................................................... 23
Figure 11. UPS custom overhead EVSE installation with a variety of charge session activation options .. 24
Figure 12. UPS San Marcos overhead EVSE installation ............................................................................. 24
Figure 13. UPS San Marcos EVSE supporting infrastructure ....................................................................... 25
Figure 14. UPS Chula Vista EVSE supporting infrastructure ....................................................................... 25
Figure 15. UPS San Diego EVSE supporting infrastructure ......................................................................... 26
Figure 16. Lightning Systems Electric Ford Transit cargo van conversion .................................................. 27
Figure 17. SDG&E Fleet Delivery PRP timeline as of September 2018 ....................................................... 28
Figure 18. SDG&E fleet delivery services PRP timeline as of December 2019 ............................................ 29
Figure 19. SDG&E Green Shuttles participant use cases ............................................................................ 40
Figure 20. GreenPower EV Star all-electric mini electric bus specifications ............................................... 41
Figure 21. GreenPower EV Star model ....................................................................................................... 41
Figure 22. SDAP site with two GreenPower EV Stars .................................................................................. 42
Figure 23. SDAP site with two 62.5 kW DCFCs paired for 125 kW and a new transformer ....................... 42
Figure 24. SDG&E Green Shuttles PRP timeline as of September 2018 ..................................................... 44
Figure 25. SDG&E Green Shuttles PRP timeline as of December 2019 ...................................................... 45
Figure 26. A variety of available electric ground support equipment charging at a California airport ...... 53
Figure 27. SDG&E Airport Ground Support Equipment PRP timeline as of September 2018 .................... 55
Figure 28. SDG&E Airport Ground Support Equipment PRP timeline as of December 2019 ..................... 56
Figure 29. SDIA airside GSE charging – preliminary infrastructure inventory (November 8, 2016) ........... 58
Figure 30. Metro Cruise Webasto chargers and electric forklift................................................................. 64
Figure 31. SDG&E Port Electrification PRP timeline as of September 2018 ............................................... 65
Figure 32. SDG&E Port Electrification PRP timeline as of December 2019 ................................................ 66
Figure 33. Histogram of Metro Cruise electric forklift charging durations ................................................. 72
Figure 34. SDG&E Electrify Local Highways installation sites ..................................................................... 75
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page v
Figure 35. SDG&E Electrify Local Highways PRP timeline as of September 2018 ....................................... 76
Figure 36. SDG&E Electrify Local Highways PRP timeline as of December 2019 ........................................ 76
Figure 37. Locations of participating PlugStar dealerships ......................................................................... 84
Figure 38. Percent of claims submitted by trained salespeople – San Diego ............................................. 87
Figure 39. Percent of claims submitted by trained salespeople – Sacramento.......................................... 87
Figure 40. Comparison of PlugStar activity in Sacramento vs. San Diego .................................................. 88
Figure 41. Dealership claims with payment status by month for San Diego .............................................. 88
Figure 42. Original customer release form excerpt .................................................................................... 92
Figure 43. Modified customer release form excerpt emphasizing TOU rates ............................................ 92
Figure 44. Pier J electric RTG crane project site layout .............................................................................. 99
Figure 45. Linear trench being cut and configured for the connection cable .......................................... 101
Figure 46. Enclosure removed from RTG crane engine compartment to begin conversion .................... 102
Figure 47. SCE POLB RTG crane PRP timeline ........................................................................................... 103
Figure 48. POLB Pier G electric yard tractor project site location ............................................................ 109
Figure 49. BYD model 8T electric yard tractor, BYD 200 kW charger, and Cavotec automated charger arm . 110
Figure 50. SCE POLB terminal yard tractor PRP timeline .......................................................................... 112
Figure 51. SCE factsheet pages for the Electric Transit Bus PRP ............................................................... 119
Figure 52. SCE Electric Transit Bus Make-Ready PRP timeline ................................................................. 121
Figure 53. Victor Valley Transit Authority charging station installation ................................................... 124
Figure 54. SCE make-ready electrical infrastructure for the Urban DCFC Clusters Pilot .......................... 128
Figure 55. Map of area surrounding Corona Sun Square ......................................................................... 131
Figure 56. Corona Sun Square DCFC installation ...................................................................................... 132
Figure 57. Map of area surrounding Global Partners in Garden Grove .................................................... 133
Figure 58. Global Partners in Garden Grove ............................................................................................. 134
Figure 59. Map of area surrounding AAA in Upland ................................................................................. 135
Figure 60. AAA DCFC installation in Upland .............................................................................................. 136
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page vi
Figure 61. Map of area surrounding AAA in Artesia ................................................................................. 137
Figure 62. AAA site in Artesia where 2 DCFCs were installed ................................................................... 137
Figure 63. Map of area surrounding 7-Eleven in Pomona ........................................................................ 138
Figure 64. Plug-in ceremony at 7-Eleven in Pomona with 7-Eleven branded charger ............................. 139
Figure 65. 7-Eleven DCFC installation in Pomona ..................................................................................... 139
Figure 66. SCE Urban DCFC Clusters PRP timeline .................................................................................... 140
Figure 67. Participant and application data .............................................................................................. 148
Figure 68. Rebate influence on EV purchase ............................................................................................ 151
Figure 69. Rebate influence on L2 charger purchase ............................................................................... 151
Figure 70. EV purchase description........................................................................................................... 152
Figure 71. EV influence on travel behaviors ............................................................................................. 152
Figure 72. Charging and cost changes from TOU rate .............................................................................. 153
Figure 73. Number of additional trips per week ....................................................................................... 154
Figure 74. Motivation for Purchasing an EV ............................................................................................. 154
Figure 75. Benefits experienced as a result of EV purchase ..................................................................... 155
Figure 76. Participant experience with application .................................................................................. 156
Figure 77. Participant experience with contractor ................................................................................... 157
Figure 78. Participant experience with rebate ......................................................................................... 157
Figure 79. Participant experience with communications ......................................................................... 158
Figure 80. Participant experience with TOU transition ............................................................................ 158
Figure 81. Overall participant satisfaction with TOU rate ........................................................................ 159
Figure 82. Diagram of PUSD onsite energy resources .............................................................................. 164
Figure 83. Schematic of the installed project infrastructure at PUSD ...................................................... 165
Figure 84. PUSD PRP project timeline ....................................................................................................... 167
Figure 85. Evaluation criteria for PRP participants ................................................................................... 183
Figure 86. RTD Site 1 diagram ................................................................................................................... 184
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page vii
Figure 87. RTD Site 2 diagram ................................................................................................................... 185
Figure 88. RTD Site 3 diagram ................................................................................................................... 185
Figure 89. RTD PRP comparative project timeline .................................................................................... 186
Figure 90. Comparison of monthly mileage per bus, January to April 2018 ............................................ 189
Figure 91. RTD daily demand at DTC by 15-minute interval ..................................................................... 196
Figure 92. RTD demand plot from September 2018 through August 2019 .............................................. 196
Figure 93. Demand charge average value before and after implementing software management ........ 197
Figure 94. Albertson’s facility showing location and placement of eTRU ports ....................................... 207
Figure 95. eTRU PRP comparative project timeline .................................................................................. 209
Figure 96. Protocol when a compatible trailer is parked at an electrified dock to load .......................... 211
Figure 97. SafeConnect ports in use at staging area, with protective mounting system ......................... 214
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 1
1. Introduction
Meeting the state’s electrification and greenhouse gas (GHG) reduction goals is a critical step toward the
state’s long-term climate commitments set forth in the California 2005 Executive Order S-3-051, 2006
Assembly Bill 322, and 2016 California Senate Bill (SB) 323. In support of the widespread transportation
electrification goals of SB 3504, the California Public Utility Commission (CPUC) issued a Decision 18-01-
0245 in January 2018, authorizing the three large investor-owned utilities—Southern California Edison
(SCE), Pacific Gas and Electric (PG&E), and San Diego Gas and Electric Company (SDG&E)—to launch 15
pilot demonstrations of transportation electrification investments with combined budgets of $42
million. In September 2018, CPUC Decision 18-09-0346 authorized three small and multi-jurisdictional
utilities (SMJU)—PacifiCorp, Bear Valley Electric Service (BVES), and Liberty Utilities (Liberty)—to spend
up to $7.2 million on seven additional priority review projects (PRPs). The two decisions required the
utilities to select a third-party evaluator to assess the success of each PRP and determine whether and
how each PRP could be scaled for the future. In response to this mandate, the utilities issued a request
for proposals for consultants to fulfill this role. The utilities selected an evaluation team led by
Energetics and supported by the Cadmus Group, Idaho National Laboratory, National Renewable Energy
Laboratory, and DavEnergy Solutions.
The PRPs were intended to be short-term investments (no longer than 12 months), with none exceeding
$4 million and each utility PRP portfolio limited to $20 million. As approved, the PRPs were anticipated
to take 12 months for design, construction, and commissioning, followed by 12 months of data
collection. Based on this anticipated timeline, the evaluation report for all PRPs was required by
December 31, 2019.
However, these innovative transportation electrification investments were of a complex nature, and as a
result, most PRP timelines were extended. In January 2019, the utilities issued PRP interim reports,
1 State of California, Office of Governor Arnold Schwarzenegger, Executive Order S-3-06, June 1, 2005,
http://static1.squarespace.com/static/549885d4e4b0ba0bff5dc695/t/54d7f1e0e4b0f0798cee3010/142343830474
4/California+Executive+Order+S-3-05+(June+2005).pdf. 2 State of California, Assembly Bill No. 32, Chapter 488: “Air pollution: greenhouse gases: California Global
Warming Solutions Act of 2006,” September 27, 2006,
http://leginfo.legislature.ca.gov/faces/billTextClient.xhtml?bill_id=200520060AB32. 3 State of California, Senate Bill No. 32, Chapter 249: “California Global Warming Solutions Act of 2006: emissions
limit,” September 8, 2016, https://leginfo.legislature.ca.gov/faces/billTextClient.xhtml?bill_id=201520160SB32. 4 State of California, Senate Bill No. 350, Chapter 547: “Clean Energy and Pollution Reduction Act of 2015,” October
7, 2015, https://leginfo.legislature.ca.gov/faces/billNavClient.xhtml?bill_id=201520160SB350. 5 Public Utilities Commission of the State of California, Decision 18-01-024: “Decision on the Transportation
Electrification Priority Review Projects,” January 11, 2018,
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M204/K670/204670548.PDF. 6 Public Utilities Commission of the State of California, Decision 18-09-034: “Decision on the Priority Review and
Standard Review Transportation Electrification Projects,” September 27, 2018,
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M231/K030/231030113.PDF.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 2
documenting challenges to securing site host commitments for participation. Several PRPs were delayed
due to the timing of the acquisition of electrified vehicles or equipment that was not funded by the
utilities and therefore out of their direct control. Only two PRPs, containing rebates and outreach, were
on schedule for completion by the end of 2019, while a number of PRPs involving construction were just
commissioning the electric vehicle (EV) charging infrastructure installations at this time (see Figure 1 for
current status of large utilities PRPs). In June 2019, based on a joint utility request, the CPUC approved
extending the final evaluation report to January 2021 while adding an interim evaluation report in
January 2020 to summarize accomplishments and findings to date. Most of the large utility PRPs should
have 9–12 months of operational data on the use of the installed charging infrastructure for the final
evaluation report in January 2021.
PacifiCorp, BVES, and Liberty received approval to launch their PRPs nine months later than the three
large utilities and issued a joint interim report in September 2019. Given this recent update
documenting the status of their PRPs and noting challenges similar to those of the large utilities in
launching their PRPs, the SMJU PRPs will be evaluated only in the final report. All three SMJUs have PRPs
that involve infrastructure installation, none of which was completed in 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 3
Figure 1. PRP timeline and current status at time of this report
Destination Make-Ready Rebate Pilot (Bear Valley)
Demonstration and Development Program (PacifiCorp)
Outreach and Education Program (PacifiCorp)
Customer Online Resource (Liberty)
Small Business Charger Installation Rebate (Liberty)
Residential Charger Installation Rebate (Liberty)
DCFC Project (Liberty)
Home EV Charger Information Resource (PG&E)
Idle Reduction Technology (PG&E)
Electric School Bus Renewables Integration (PG&E)
Medium/Heavy Duty Fleet Customer Demo (PG&E)
Charge Ready Home Installation Rebate Program (SCE)
Urban Charge Ready DCFC (SCE)
Charge Ready Transit Bus (SCE)
Port of Long Beach Terminal Yard Tractor (SCE)
Port of Long Beach Rubber Tire Gantry Crane (SCE)
Dealership Incentives (SDG&E )
Electrify Local Highways (SDG&E )
Port Electrification (SDG&E)
Airport Ground Support Equipment (SDG&E )
Green Shuttle (SDG&E )
Fleet Delivery Services (SDG&E )
Large Utilities 12-month Report Interim Evaluation Report
Series1 Planning Implementation Data Collection
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 4
1.1 Evaluation Scope
The PRPs are intended to test new approaches to overcoming barriers to transportation electrification,
as well as to gather data on the approaches’ implementation and outcomes. As such, it is anticipated
that certain projects will be more successful in reducing barriers and accelerating transportation
electrification than others. Therefore, it is important to identify those that can be scaled up immediately
and those that would need modifications or technology improvements before they are ready to be
scaled up. The evaluation seeks to uncover robust, conclusive, and actionable lessons learned that can
be applied to the utilities’ transportation electrification standard review projects (SRPs), as well as other
future electrification efforts.
The three main steps of the evaluation approach are presented in Figure 2.. First, the relevant research
questions for each PRP are identified based on the transportation electrification goals and market
intervention approach. Next, data sources are identified, data are collected, and appropriate analyses
are conducted. Finally, the collected project information and analysis results are integrated to answer
the research questions and draw conclusions to evaluate each PRP’s success and potential for scaling up.
Figure 2. High-level three-phase evaluation approach
The PRP evaluation will quantify, as possible, direct project benefits, such as reductions in fossil fuel
usage, criteria pollutants, and GHGs, along with economic impacts based on available data. The
evaluation will also strive to measure co-benefits and identify the beneficiaries of those co-benefits to
portray a comprehensive picture of the project’s successes and use those insights to inform future
efforts.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 5
Figure 3. Potential PRP co-benefits
The PRPs comprise a diverse range of projects targeting different markets (e.g., vehicle class and
customer type). As such, the evaluation team categorized the 22 approved PRPs into three groups,
shown below, for commonality in the analysis and comparisons.
Figure 4. PRP groupings
Fleet electrification projects include known vehicles and operators using the installed EV charging
infrastructure. Available operational data includes the charging session data collected by the utilities and
vehicle or equipment telematics to the extent available to the evaluator by the fleet customers. These
data can be used to validate the fuel savings with either the vehicle mileage or vehicle operating hours
and the electricity dispensed by the charging stations. In addition, the vehicle operating practices are
typically known prior to project implementation and will serve as a baseline. It should be relatively
straightforward to determine the potential for the participating fleet to scale up their adoption of
electrified vehicles or equipment based on the available information from fleet electrification PRPs. A
brief summary of Off-Road Fleet Electrification PRPs is presented in Table 1, and a summary of Medium-
and Heavy-Duty Fleet Electrification PRPs is presented in Table 2.
• Known vehicles utilizing the installed EV charging infrastructure
Fleet Electrification
• Installed EV charging infrastructure that will serve a broad array of vehicles
Public Access Stations
• Strategies to address education- and awareness-related barriers to EV adoption
Electrification Promotions
Disadvantaged Community
Impact
Improved Grid Load
Factor
Operational Improvements
Maintenance and Fuel Savings
Time Savings (HOV Access)
Worker Health and Safety
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 6
Figure 5. Fleet electrification projects
Priority Review Project (Off-Road EV
Charging Infrastructure)
Priority Review Project (Medium- and
Heavy-Duty EV Charging
Infrastructure)
Airport Ground Support Equipment
(SDG&E) Green Shuttle (SDG&E)
Port Electrification (SDG&E) Fleet Delivery Services (SDG&E)
Port of Long Beach Rubber Tire Gantry
Crane (SCE) Charge Ready Transit Bus (SCE)
Port of Long Beach Terminal Yard Tractor
(SCE)
Medium/Heavy Duty Fleet Customer
Demo (PG&E)
Idle Reduction Technology (PG&E) Electric School Bus Renewables Integration
(PG&E)
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 7
Table 1. Fleet electrification off-road EV charging infrastructure summary PRP summary
PRP Description Proposed Deployment Approved Budget
Current Status
Airport Ground Support Equipment (SDG&E)
Phase I - retrofit existing chargers, assess charging behavior, and develop a load management plan (grid conditions, onsite solar generation) Phase II - additional charger installations if warranted
Phase I - 16 charging ports (8 dual head chargers) retrofitted with American Airlines Phase II - up to 45 additional charging ports based on 6 months of Phase I data analysis
$ 2,839,738 Phase I - 16 charging ports retrofitted (data collection started in December 2019)
Port Electrification (SDG&E)
Support electric MD/HD vehicles and forklifts to promote the development of EVs in this market segment. Analyze how grid integration for the MD/HD and forklift EV market segment can be implemented and optimized.
30-40 charging stations, data loggers and load research meters for electric trucks and forklifts. San Diego Port Tennant customers: Pasha Automotive, Metro Cruise, Dole and Four Seasons
$ 2,405,575 3 direct current fast chargers (DCFCs) installed for Pasha (3 Class 8 electric trucks) and 9 Level 2 (L2) (10 kW) chargers for 9 Metro Cruise electric forklifts; no other participants; data collection started in May 2019
Port of Long Beach Rubber Tire Gantry Crane (SCE)
Make-ready infrastructure for 9 rubber tried gantry cranes (grid-tied)
Installation of electrical supply for 9 Rubber Tire Gantry Cranes converted to electric
$ 3,038,000 Utility upgrades completed, SSA terminal modifications and first eRTG conversion by end of the first quarter (Q1) of 2020
Port of Long Beach Terminal Yard Tractor (SCE)
Make-ready infrastructure to support 20 charging stations for electric yard tractors
Electric infrastructure for 20 charging stations (200 kW) for Class 8 BYD electric yard tractors; ITS deploying 7 EVSE initially
$ 450,000 3 BYD electric trucks delivered, 6 BYD 200 kW and 1 Cavotec automated 100 kW charger installed Dec 2019
Idle Reduction Technology (PG&E)
Demonstrate idle-reduction technologies (for transport refrigeration units) and develop a handbook for other fleets based on lessons learned
25 electrified receptacles for eTRU connection (10 at docks, 15 at staging area), 15-17 kW each
$ 1,719,400 System constructed and commissioned, just starting in-use operations
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 8
Table 2. Fleet electrification medium- and heavy-duty EV charging infrastructure PRP summary
PRP Description Proposed Deployment Approved Budget
Current Status
Fleet Delivery Services (SDG&E)
Support electrification of fleet delivery vehicles by installing, owning, operating, and maintaining the charging infrastructure for up to 90 medium-duty EVs
63 L2 (17 kW) chargers at three UPS locations, 16 L2 (17 kW) chargers at Amazon location
$ 3,690,749 All chargers installed (78), all 15 Amazon EVs in operation, UPS awaiting 60 EVs (expected Q2 2020)
Green Shuttle (SDG&E)
Charging infrastructure (L2 and/or DCFC) for 1 or more shuttle companies. May incorporate solar/storage, as well as offering public charging
2 DCFCs (50kW) for San Diego Airport Parking (2 EVs), Aladdin (4 EVs), and San Diego International Airport (4 EVs + public access); 6 L2 chargers for Illumina (6 EVs), solar energy and energy storage at one site
$ 3,157,805 San Diego Airport Parking completed, Aladdin and Illumina in construction (Q1 2020 anticipated completion). Not pursuing 4th location, public access, solar energy & energy storage
Charge Ready Transit Bus (SCE)
Make-ready Infrastructure at transit agency sites, plus rebate for charging equipment
7 depot DCFCs for Victor Valley Transit (7 electric buses), 10 depot DCFCs for Porterville (10 electric buses), and 13 depot DCFCs for Foothill Transit (14 electric buses)
$ 3,978,000 Victor Valley complete (7) and operational, awaiting Porterville (10) and Foothill (13) charger installations
Medium/Heavy Duty Fleet Customer Demo (PG&E)
Demonstrate—with utility assistance of make-ready infrastructure and charger rebates—a lower total cost of ownership for MD/HD fleet EVs
Five 60 kW depot chargers, demand management and battery energy storage for existing high-power overhead chargers for San Joaquin Regional Transit District (17 EVs)
$ 3,355,000 Depot chargers installed, demand management implemented, battery storage on order, testing underway
Electric School Bus Renewables Integration (PG&E)
Deploy make-ready infrastructure, chargers, and control management for electric school buses to test managed charging to consume electricity during peak renewables generation periods
9 Level 2 (19kW) chargers and charge management software to integrate onsite renewables
$ 2,209,500 3rd of 4 experimental test phases underway
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 9
Public access station projects provide data on the electricity dispensed by the installed EV charging
infrastructure, many of which are direct current fast chargers (DCFC) at public locations, but do not yield
all the data needed to calculate reduced petroleum use. Displaced fossil fuel can be approximated based
on utilization of the PRP-deployed stations. Some electric vehicle supply equipment (EVSE) providers
may share information about their users, such as an identification number, vehicle type, and zip code of
residence, which helps determine the number of different users and their potential routes and
destinations. With the known location of the station, it is possible to make some reasonable estimates
of which geographical area is benefiting from reduced emissions, but it is not as precise as with a known
fleet vehicle. Surveys of users may provide some insights on the PRP’s impact on driving patterns and
behaviors, including baseline behavior before the charging station was available. A brief summary of
public access stations PRPs is presented in Table 3.
Figure 6. Public access station projects
Priority Review Project
Electrify Local Highways (SDG&E)
Urban Charge Ready DCFC (SCE)
Destination Make Ready (BVES)
DCFC Project (Liberty)
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 10
Table 3. Public access stations PRP summary
PRP Description Proposed Deployment Approved Budget
Current Status
Electrify Local Highways (SDG&E)
Study the charging patterns from installations, and test the standards for public charging signage, rate display, and general retail EV fuel dispensers. Stations will use a dynamic grid integrated rate.
20 L2 (6.6 kW) and 2 DCFC (50 kW) chargers each at 4 Caltrans Park and Ride locations (88 charging ports total)
$ 4,000,000 Construction started at all 4 sites with expected commissioning by end of Q1 2020
Urban Charge Ready DCFC (SCE)
Make-ready Infrastructure and charging station rebate to serve up to 50 new DCFC ports at 5 locations
5 locations with up to 50 DCFCs planned. 5 site host agreements resulted in 14 DCFCs.
$ 3,980,000 All 5 sites completed and 14 DCFCs commissioned in Nov and Dec 2019
DCFC Project (Liberty)
Deploy DCFC clusters in sites with high utilization. Procurement, installation, and maintenance of the DCFC stations, as well as the electric infrastructure upgrades and conduit as well as the DCFC charging stations would be covered by the utility
5-9 DCFC sites are expected with 1 to 4 dual port stations per location
$ 4,000,000 Developing program website and framework for early 2020 launch
Destination Make-Ready Rebate Pilot (Bear Valley)
Rebate for make-ready EV charging infrastructure (for up to 5 L2 chargers per site) with requirement to enroll in a separately metered EV TOU rate when it becomes available
50 L2 charging stations for commercial customers
$ 607,500 Contracted a program implementer, developed program website and materials, launched in Dec 2019
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 11
Electrification promotion projects target barriers to EV adoption by private owners, from challenges
installing EV home charging solutions to poor dealership experiences when purchasing EVs, so the main
data sources are the vendors and participants. While PRP participant data and information about the
accomplished effort provide good insights, there are no direct measurements of electricity dispensed to
EVs or their operations to calculate direct fuel use reductions or emission benefits. Sales data could
potentially indicate whether these PRPs influence the market, but most of these evaluations will rely on
surveys and interviews to determine success and the potential for scaling up. A brief summary of
electrification promotion PRPs is presented in Table 4.
Figure 7. Electrification promotion projects
Priority Review Project
Dealership Incentive (SDG&E) Demonstration and Development Program
(PacifiCorp)
Charge Ready Home Installation (SCE) Residential Rebate Program (Liberty)
Home EV Charger Information Resource (PG&E) Small Business Rebate Program (Liberty)
Outreach and Education Program (PacifiCorp) Customer Online Resource (Liberty)
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 12
Table 4. Electrification promotions PRP summary
PRP Description Proposed Deployment Approved Budget
Current Status
Dealership Incentives (SDG&E)
Education and training for EV salespeople; incentives of $500 split between dealership and salesperson if customer sign up for EV TOU rate
Enroll and train 200 salespeople and issue 1,500 incentives
$ 1,790,000 Program closed on December 31, 2019; final rebates processing and program reporting in Q1 2020
Charge Ready Home Installation Rebate Program (SCE)
Rebates for make-ready and permitting to install home EV Level 2 charging infrastructure. Must enroll in whole-house TOU or install a dedicated EV submeter.
Approximately 5,000 participants
$ 4,000,000 Program closed on May 31, 2019; final rebates processing and program reporting in Q4 2019
Home EV Charger Information Resource (PG&E)
Develop an EVSE installation checklist, translate it into Spanish and Chinese; develop website with an installer tool to help customers find qualified contractors and streamline the bid process
Enhanced EV information on website, checklist for EVSE and contractors, installer tool
$ 500,000 Rescoped (budget reduced to $200k) to reference external EVSE installer selection tools; updated web resource development in Q1/2 2020
Demonstration and Development Program (PacifiCorp)
Offer grant funding for make-ready, hardware, installation and upfront software purchase costs for EV charging stations.
On a quarterly basis for 15 months administer grants for non-residential customers to propose EV charging infrastructure projects
$ 270,000 One project selected for award in program's 3rd quarter
Outreach and Education Program (PacifiCorp)
Test the effectiveness of different education and outreach tactics through four distinct components
(1) customer communications (2) self-service resources/and tools, (3) technical assistance, and (4) community events
$ 170,000 Program running in parallel with and to support PacifiCorp Demonstration and Development PRP
Residential Charger Installation Rebate (Liberty)
The rebate is designed to incentivize the installation of home EV chargers by offsetting the costs of hardware, permitting, and installation costs
1,000 rebates of $1,500 $ 1,600,000 Developing program website and framework for early 2020 launch
Small Business Charger Installation Rebate (Liberty)
Rebates incentivize the installation of EV chargers by providing an offset for the hardware, permitting, and installation costs of the EV charger
100 rebates of $2,500 $ 300,000 Developing program website and framework for early 2020 launch
Customer Online Resource (Liberty)
Build-out the current website to include a web-based information resource focused on EV-related information - Customer Online Resource portal
Educate customers on EVs, charging requirements, charger locations, rebate programs, and TOU rates
$ 240,480 Developing program website and framework for early 2020 launch
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 13
Cross-Cutting Research Questions
Each PRP requires slightly different targeted evaluation approaches, and the evaluation includes PRP-
specific questions and data collection requirements. However, Figure 8 includes the overarching
research questions applicable to all projects, as well as a set of targeted questions that apply to each
PRP group. For comparison purposes, these cross-cutting questions are being analyzed across multiple
PRPs to draw conclusions about various transportation electrification technologies and approaches to
implementing charging solutions. The evaluation team reviewed the available PRP information and held
discussions with the utility staff relevant to each PRP to understand the objectives and what specific
barriers each PRP was designed and approved to investigate. Overarching research questions, as well as
specific PRP group and individual PRP research questions that the evaluation will attempt to answer,
were developed by the evaluation team and reviewed by the utilities staff.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 14
Figure 8. PRP research questions
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 15
1.2 Evaluation Approach
The evaluation of each PRP involves specific data collection tasks, identification of data sources,
collection of the data, and the analysis to evaluate success. The evaluation requires regular dialogue
with the utilities’ project managers and the PRP hosts regarding implementation progress and available
data, which the evaluation team has facilitated.
1.2.1 Data Sources
Table 5 summarizes the types of data the evaluator is relying on for the evaluation, categorized by the
source of each data type—i.e., whether data are gathered by the utilities and implementation partners
or by the evaluator via direct PRP interactions and/or from secondary data sources. Data from PRP
participants or customers either flow through the utilities or are provided directly to the evaluation
team.
Table 5. Example sources of evaluation data
Gathered by Utilities and Implementation Partners Gathered or Accessed by Evaluator
Partner/customer/vendor contact information
Advanced metering infrastructure data/submeter data (ideally submetered at charger level)
Vehicle/equipment inventory (project-related and customer total)
Operational changes or project phase testing modifications
Costs (initial and ongoing, for the utility and partner, project elements, and baseline)
Downtime and maintenance/repair of equipment
Electricity rates and costs (project-related and customer total)
Customer surveys conducted by utilities
Data in project dashboards (not accessible to evaluator)
EV charger data (EVSE network service providers)/vehicle telematics (on-board data loggers, fleet dashboard, or vehicle manufacturer)
In-depth interviews (IDIs) and surveys with project stakeholders
Intercept/online surveys
Data in project dashboards (access provided by PRP vendors)
Market data
Benchmarking (baseline data and for similar technology deployments)
Evaluations or assessments from other deployments or studies related to the PRP
The CPUC Data Collection Template7 (May 8, 2018 version) includes data fields relevant to analyzing the
impacts created by the PRPs, such as charging events, project and electricity costs, equipment
specifications, and locations served. The evaluation team is working with the utilities to compile this
information as it becomes available throughout the project. The types of data available and those
relevant for each PRP group differ, as summarized in Table 6.
7 http://www.cpuc.ca.gov/WorkArea/DownloadAsset.aspx?id=6442457045
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 16
Table 6. Types of evaluation data by PRP grouping
Fleet Electrification Public Access Station Electrification Promotion
Quantitative Data
Charging station use
Utility meter data
Facility load data
Vehicle/equipment routes and scheduled operations
Current fleet size and composition
Vehicle/equipment telematics or usage (miles or hours)
Maintenance records
Charging station use
Utility meter data
Vehicle/user information (unique ID, vehicle type, ZIP code if available)
Website analytics (if available)
Number of participants using the service (rebate or bid tool)
Qualitative Data: IDIs and Surveys of the Following Stakeholder Types
Fleet operators
Energy managers
Maintenance personnel
Drivers
Riders
Equipment suppliers
Drivers
Site hosts
Equipment suppliers
Website users and participants
Dealership personnel
1.2.2 Data Collection
In general, the data collection within each specific PRP section includes a combination of PRP
information (facts and particulars that do not change after implementation or during a test phase), PRP
data (updates, findings, and figures that are collectively gathered as the project progresses), market
research, IDIs, and surveys. Since PRPs differ, even within a PRP group or within a PRP where there are
multiple customers, not all types of data are available for each PRP.
PRP Information
The evaluation team requested key information about the project, technology, and partners during the
PRP planning and installation phases. This helped inform the market research, IDIs, surveys, and
analysis. Some examples of this information are historical data (used to establish a baseline) on the
application that is being electrified, vehicle/equipment functions (routes, duties, etc.), electricity rates,
and historical facility electricity and fleet fuel use. Specific to the PRP, the evaluation team is collecting
expenses by the utility and partner (broken out by cost categories), specifications for any project
hardware (charging stations, make-ready infrastructure, and vehicles), and details on the structure of
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 17
the PRP’s execution. While some information needs updating based on project changes, most should
not change after the 12-month test period begins.
PRP Data
During the 12-month PRP demonstration period following implementation, some data are being
collected on an ongoing basis to quantify the vehicle/equipment operations. Depending on the project,
these data come from utility meters, charging stations, vehicles/equipment, maintenance records, and
customer utility bills. While some of these data streams are duplicative (the utility meter, charging
station, and vehicle might all record energy transfer and time for each charging session), having these
data resources provides a back-up and can yield additional insights (such as the efficiency losses at each
stage). Each source can also provide additional useful data, such as the actual fuel efficiency of a vehicle
based on its data; using these data streams produces more accurate results than relying on
manufacturer or industry averages. For the Electrification Promotion PRPs, metrics include the number
of participants, duration of processes, and total rebates or applications processed.
Market Research
Market research on the technology and application is needed to calculate the resulting emission
benefits and to understand the potential for scaling up. Some of this information was collected by the
utilities or partners when developing these PRPs or during the decision to implement a transportation
electrification solution. The evaluation team is also conducting additional research into previous tests
and studies that have fuel rates, emission factors, and other information needed to quantify the
benefits. The project partners were asked to provide information about their inventory of vehicles or
equipment similar to what was electrified under the PRP, assuming those vehicles or equipment could
be electrified in the same manner. Where available, similar information from the utilities about this
inventory for their entire service territories will be used. The evaluation team is supplementing this
information with market research to understand the potential of scaling up each PRP across the utility
service territory and the entire state.
In-Depth Interviews
IDIs are a key aspect of the evaluation. Qualitative information from various stakeholder experiences is
invaluable, as these projects involve a variety of new technologies, applications, and decision makers.
The evaluation team identified the interviewees and the number of interviews for each PRP, as well as
the purpose for each. An experienced member of the evaluation team drafts the interview guide and
questions (primarily open-ended and designed to probe various issues), which are reviewed by the
respective utility, prior to conducting the interviews.
Surveys
Surveys allow information-gathering from larger populations, such as website users or public access
charger users. The evaluation team is working with utilities to identify the population, target sample
size, and purpose for each survey. For several PRPs, existing utility or implementer surveys are reviewed
and adapted by adding additional, evaluation-specific questions. Surveys are primarily administered
online, with in-person intercepts used only when needed. The evaluation team developed draft guides
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 18
for 1) administering the surveys or 2) adding questions to the utility surveys. The team is working closely
with the utilities to finalize the approach.
1.2.3 Analysis and Evaluation Reporting
The evaluation team has created a preliminary data analysis model to calculate quantitative results to
support the PRP evaluations. The data analysis model continues to be refined using PRP data collected
from each demonstration. At least two months of operational PRP data, along with the collected PRP
information, are entered into the data analysis model to obtain preliminary results. As additional
operational data are received, results are updated. When possible, 12 months of operational data will
be collected. Seasonal shifts in weather may affect heating, ventilation, and air conditioning (HVAC)
operations and battery charging efficiency which impacts vehicle or equipment energy use. Data
collected during all seasonal variations are critical to assess the overall effectiveness of the PRPs.
As part of the evaluation report, the evaluation team is identifying PRP co-benefits through IDIs and
surveys and, where possible, quantifying these benefits. For the fleet electrification projects, the
evaluation team will show disadvantaged community (DAC) benefits by documenting 1) the locations in
which the vehicles operate and 2) each location’s relationship to DAC boundaries. It is a challenge to
accurately predict maintenance savings for the life of the vehicle or equipment, since the PRP
demonstration period only covers the first year of operation, when scheduled maintenance is minimal.
Noise reduction can be quantified through the collection of decibel measurements. Long-term worker
health and safety benefits from reduced contact with toxic chemicals such as oils and petroleum fuels
are difficult to quantify during this evaluation period, but if such benefits are mentioned during IDIs or
surveys, the observations will be noted.
For public charging infrastructure projects, specific metrics are used to measure use patterns among the
various installations. The evaluation team is closely examining electrical power metrics, such as plug-in
times and durations, peak power draw, and total energy consumed, to determine system performance
along with fuel and emissions offsets.
The team is using a combination of information to better understand why charging stations might have
different utilization and charging patterns. Also, the team is assessing EV and EVSE use and will include
additional factors in analysis as appropriate, such as population density, geographical region, setting in
which the charger was installed, charging station location within a property, cost for charging, presence
of signage, and EVSE brand and network. Metrics used in the analysis can include time-of-day and day-
of-week variations, population density or the type of functions near the installation (residential,
commercial, or industrial), parking setting variations (parking garage, open lot, or curbside), location
setting variations such as cluster types (e.g., retail, workplace, leisure, or residential), and seasonal
variations. Our analyses integrates multiple metrics where appropriate (for example, the time-of-day
and day-of-week variations could be determined for different geographical settings). The performance
of individual EV charging stations can be compared to the entire group of PRP-funded charging stations
to identify which are the best and worst performers. When the PRP scope includes demand response,
the analysis includes evaluation of charging events that occur during demand response participation,
thereby determining the program’s effects on those events or the users’ charging experience.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 19
The last step in the evaluation is to draw conclusions based on all data collected and analysis of those
data. As appropriate for each PRP and PRP grouping, key performance indicators are assessed to
determine the true impacts of those activities and their potential for scaling up. CPUD developed a
standard data collection template8 and reporting template9 for each PRP which will be used by each
utility. The evaluator report shall complement these individual PRP reports, but also incorporate aspects
to compare PRPs within their grouping. Evaluation reporting for the individual PRP begins after the data
collection and analysis have been completed.
1.3 Organization of Report
This interim evaluation report documents the PRP accomplishments through December 2019 and
highlights any lessons learned based on the input collected for these pilot demonstrations of
transportation electrification interventions. For most PRPs, this report summarizes the progress from
conception to construction/implementation but does not yet include data or feedback on the first 12
months of operations following commissioning. The final costs incurred by the utilities to complete
these PRPs or the final project metrics have not been collected/assessed since the projects are on-going.
A few of the electrification promotion projects are nearing completion but still lack all the information
needed to assess success and potential for scale up.
To the extent possible, each of the following PRP sections (grouped by utility) are organized in a similar
manner as shown in Figure 9, although the uniqueness of individual projects will occasionally require
deviations to present all information that was collected and analyzed. Some subsections will not be
completed until the final evaluation report. The final report will use the same format as the interim report
unless otherwise directed by the CPUC.
8 CPUC SB 350 TE Data Collection Template.
https://www.cpuc.ca.gov/WorkArea/DownloadAsset.aspx?id=6442457045. 9 CPUC SB 350 TE Report Template. https://www.cpuc.ca.gov/WorkArea/DownloadAsset.aspx?id=6442457046.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 20
Figure 9. Individual PRP section organization
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 21
2. San Diego Gas and Electric Company
2.1 Fleet Delivery Services
2.1.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
SDG&E has partnered with delivery service businesses to support the electrification of fleet delivery
vehicles by providing electrical infrastructure upgrades and by installing, owning, operating, and
maintaining the EV charging infrastructure. Decision 18-01-02410 approved $3,690,749 in direct costs to
provide charging infrastructure to support up to 90 medium-duty electric delivery vehicles at
approximately six locations. The provided charging infrastructure will support both the regular operation
of the electric delivery vehicles and increased average daily vehicle utilization. The fleet delivery
businesses are responsible for procuring the electric delivery vehicles.
Program fleet delivery partners will use an existing time-varying rate that encourages off-peak charging.
The rate has the potential to reduce electric service costs by encouraging charging during off-peak
times, when possible. Off-peak charging improves electric system utilization. SDG&E has worked with
the fleet partners, who will develop a load management plan to efficiently integrate the new vehicle
charging loads with SDG&E’s grid. This will benefit the fleet and generate benefits to all ratepayers
through grid optimization.
This project encourages, supports, and accelerates the electrification of regional delivery vehicles by
eliminating barriers to installing charging infrastructure, including its associated cost. Fleet delivery
trucks are utilized by a wide range of businesses in the goods and services markets for their day-to-day
operations and are found throughout SDG&E’s service territory, the state of California, the nation, and
all around the world. It can be expected that the number of local delivery trucks will continue to
increase with the expansion of e-commerce.
Fleet delivery trucks are likely good candidates for transportation electrification because they operate in
urban centers, have stop-and-go driving cycles, spend a significant amount of time idling, have
predictable daily routes, and are centrally maintained and fueled. The goals of the Fleet Delivery
Services project are to:
• Prove that regional fleet delivery vehicles can be electrified without impeding their daily mission
and operations.
• Determine the charging infrastructure needs for fleet delivery vehicles with regard to utility
infrastructure and the associated number of chargers and their power levels.
10 Public Utilities Commission of the State of California, Decision 18-01-024: “Decision on the Transportation
Electrification Priority Review Projects,” January 11, 2018,
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M204/K670/204670548.PDF.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 22
• Collect data on charging utilization and costs to allow operators to minimize their electric
charging costs.
• Analyze data collected with vehicle data loggers to evaluate the performance of the vehicles,
their charging patterns and needs, and impacts on the fleet’s overall energy use.
• Assess the grid impacts from the specific fleet demonstration, including impacts at the site and
local levels.
Sites and Participants
Recruitment Process
SDG&E secured the participation of the United Parcel Service (UPS) early in the process and included the
delivery company as a participant in the original application filing. To maximize the project’s reach, the
CPUC directed SDG&E to conduct additional outreach when selecting other fleet delivery business
partner(s) to identify locally owned, minority-owned business enterprise or woman-owned business
enterprise (MBE/WBE) delivery business fleet(s). Two separate fleet delivery forums were held in
January and February 2018 to educate customers, vendors, and EV manufacturers about the program. In
February 2018, communications were sent to over 125 local businesses to promote the program.
Knowing that Amazon is very interested in transportation electrification, SDG&E reached out to
company management and informed them of the Fleet Delivery PRP opportunity to fund charging
infrastructure for EVs. Amazon often contracts with local small businesses under their Delivery Service
Partner program to provide the trucks for local Amazon package deliveries. Amazon would likely have
done a pilot like this eventually, but the PRP accelerated the timeline, enabled electrification of more
vehicles, and influenced the location of the pilot (a DAC in San Diego).The outreach also resulted in a
small local catering company (Brother’s Catering) expressing interest in participating in the program, but
the caterer decided not to move forward because of vehicle availability, costs, and operational risk.
Lesson Learned: Significantly more effort, investment, and EV availability and reduced EV costs will be necessary to sufficiently support locally owned MBE/WBE delivery business fleets in transportation electrification projects. Often, such businesses do not have the knowledge or resources to secure the grants necessary to finance this effort (upfront costs for electric delivery trucks is a barrier) or the available staffing to navigate the challenges of operating new technology. Further, smaller local companies generally do not have robust financial resources to make investments in new technologies.
Participants
SDG&E’s primary fleet partner is United Parcel Service (UPS). Three UPS locations in the San Diego
region (Chula Vista, San Marcos, and San Diego) will operate 60 electric delivery vehicles. Two of the
locations (San Marcos and San Diego) are in designated DACs based on CalEnviroScreen 3.0 for SDG&E
territory. SDG&E’s original plan was to deploy 20 alternating current L2 charging stations and one DCFC
at each UPS location (i.e., a total of 60 L2 charging stations and 3 DCFCs). Based on UPS needs, SDG&E
installed only L2 charging stations—33 at the San Diego location and 15 each at Chula Vista and San
Marcos, with one more charging station installed than the number of EVs at each location at the sites’
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 23
vehicle maintenance area. The charging stations are 70 A (16.8 kW) BTC Power units (EVP-2001-70-W-
001) that use Greenlots as the network service provider. A custom solution was designed to position
chargers in an overhead position. UPS plans to procure Workhorse all-electric E-100 delivery trucks
(specifications: 123 kWh battery pack for a range up to 100 miles with a 22 kW onboard charger). UPS
has expressed interest in installing energy storage at one location. Calstart is assisting UPS with vehicle
and charging station data collection and investigating charge management needs.
Figure 10. UPS BTC Power L2 EVSE from Greenlots
Source: Evaluator team
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 24
Figure 11. UPS custom overhead EVSE installation with a variety of charge session activation options
Source: Evaluator team
Figure 12. UPS San Marcos overhead EVSE installation
Source: Evaluator team
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 25
Figure 13. UPS San Marcos EVSE supporting infrastructure
Source: Evaluator team
Figure 14. UPS Chula Vista EVSE supporting infrastructure
Source: Evaluator team
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 26
Figure 15. UPS San Diego EVSE supporting infrastructure
Source: Evaluator team
SDG&E has also partnered with a second fleet, Amazon, to install charging infrastructure at the
company’s sorting facility in National City (two different sorting facility locations were initially
considered), which is in a DAC. Package delivery is carried out by Amazon-contracted delivery service
providers, the majority of which are locally owned small businesses. The delivery service providers are
operating the electric delivery vehicles, while Amazon is providing charging at the company facility
overnight. A total of 16 L2 charging stations were installed at the Amazon facility. As with the UPS
installations, these charging stations are BTC Power 70 A units that use Greenlots as the network service
provider. Amazon arranged procurement of 15 Lightning System Ford Transit EVs for this project.
Currently Amazon is on SDG&E’s Schedule TOU-M rate (for 20–40 kW loads) but will likely move to
ALTOU (when the EV charging causes energy use to exceed the TOU-M limit) until SDG&E can offer the
high-power EV tariff (HP-EV TOU), which was filed with the CPUC early in 2019 and is pending approval.
Greenlots is providing Amazon with a Flex Charge Manager (FCM), a computer running a Linux kernel,
which will implement load limits on the collective group of chargers (i.e., 0% during on-peak hours,
100% during off-peak hours, or a different percentage during a certain established period). The FCM is
expected also to have the capability to modify load limits per day ahead of critical peak price events.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 27
Figure 16. Lightning Systems Electric Ford Transit cargo van conversion
Source: California Air Resources Board (CARB) Hybrid and Zero-Emission Truck and Bus Voucher Incentive Project
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 28
Timeline and Status
At the Program Advisory Council (PAC) meeting on September 25, 2018, SDG&E reported that all legal
documents to proceed with the project were signed and returned by UPS and Amazon. SDG&E expected
no other project partners, having received no additional commitments from fleet delivery companies in
response to the recruitment efforts that started eight months prior. SDG&E construction staff had also
completed the site walks, and the initial designs were sent to UPS and Amazon for their review and
approval. These milestones enabled the SDG&E team to develop and share the following anticipated
project timeline, accounting for a construction freeze during the holiday season.
Figure 17. SDG&E Fleet Delivery PRP timeline as of September 2018
Source: SDG&E Q3 2018 PAC
Site design approvals, along with the selection of the charging station manufacturer and network service
provider, progressed as planned. However, UPS’s and Amazon’s selection and procurement of EVs has
taken longer than expected owing to unavailability of suitable EV models and delays in available EV
production schedules. Therefore, the construction of the charging infrastructure was pushed back
slightly to better align with the arrival of the vehicles. Construction started at Amazon in May 2019, and
the site was in service by August 2019. Amazon’s Lightning System EV deliveries started in September
2019, and the last of the 15 trucks was received the first week of December 2019. UPS was informed
that the Workhorse electric delivery trucks would not be available until the second quarter of 2020.
SDG&E started construction at the UPS Chula Vista facility in May 2019, while work at San Marcos and
San Diego facilities started in June 2019. All three sites were ready for service in October 2019.
Lesson Learned: The electric delivery vehicle market is growing and maturing but has relatively limited options. Some small manufacturers to first enter the market (e.g., Smith Electric) struggled to succeed and had to cease operations. These PRPs are procuring some of the first production vehicles from the selected manufacturers, which can have an impact on production and delivery times. Supporting the EV manufacturers, providing a market for their products, and examining vehicle performance will help advance the transition to EVs.
There should be about 10 months of operational data from the Amazon location to evaluate for the final
PRP evaluation report scheduled for January 2021, but the data from the UPS locations will be much
more limited—only 6 months of operational data or less, depending on delivery and start of in-service
operation of UPS electric trucks.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 29
Figure 18. SDG&E fleet delivery services PRP timeline as of December 2019
Source: SDG&E
2.1.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP.
• What instructions/training were drivers provided for using the EV charging stations?
• Were operational and technology opportunities to better manage charging identified, how were
they implemented, and were they effective?
• What is the appropriate ratio of charging ports to EVs?
The data sources utilized to evaluate this PRP include 1) PRP information from the approved decision,
project updates, site visits, and other available documentation, 2) market research on delivery vehicles
and early deployment efforts from other similar electrification projects across the country, 3) PRP data
from vehicle and charger operations, 4) IDIs with project partners, and 5) surveys with vehicle drivers.
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: the PRP kick-
off meeting (SDG&E and evaluator), quarterly PAC update meetings, weekly PRP updates (SDG&E and
evaluator), site visits (UPS), and other periodic calls or emails. Currently, the evaluation team has the
following information from this PRP: charging station hardware specifications, electricity tariff details,
some site photos after installation, project costs, and some high-level information on the acquired
vehicles and intended use. Over the next few months, the evaluator expects to receive more details
about several items where only high-level information was previously provided, along with construction
site plans and designs.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 30
The following sources for market research have been identified:
U.S. Department of Energy’s Alternative Fuels Data Center: Average Fuel Economy of Major
Vehicle Categories (2018)
National Renewable Energy Laboratory: Field Evaluation of Medium-Duty Plug-in Electric
Delivery Trucks (2016)
California Hybrid, Efficient and Advanced Truck Research Center: Battery Electric Parcel Delivery
Truck Testing and Demonstration (2013)
Green Biz and UPS: Curve Ahead: The Future of Commercial Fleet Electrification (2018)
SDG&E will provide PRP operational data from the utility service meters (one utility meter at each
deployment site for all charging stations at that site) for 15-minute interval data and monthly costs,
while network service provider Greenlots will provide monthly CSV files for charging station session
data. Third-party data loggers for medium-/heavy-duty (MD/HD) EVs were found to be much more
expensive than anticipated, so SDG&E is relying on vehicle manufacturer telematics systems for
collection of vehicle operational data. It is expected that the project participants will provide high-level
data on vehicle utilization and maintenance, along with any necessary maintenance of the charging
stations.
The evaluator held IDIs with representatives from the SDG&E PRP management team, SDG&E
construction staff, and Amazon to further understand the background on this project and gather lessons
learned based on progress to date. Additional IDIs with the SDG&E staff, UPS, and vendors are
scheduled during the upcoming year as the EVs are put into operation. A survey or focus group
discussion facilitated with the EV drivers may also be completed.
2.1.3 Evaluation Findings
Since Amazon EVSE installations have been completed and all 15 electric trucks have been delivered
(UPS EVSE installation were completed, but their electric truck deliveries are not expected until Q2
2020), the evaluation team conducted IDIs with Amazon and therefore, most of the information and
learnings presented under this PRP for the interim report are specific to Amazon deployment.
Project Baseline
While the state governments have begun setting mandates on electrifying light-duty vehicles, there has
not yet been a government-led mandate on delivery fleet electrification. In 2019, California is proposing
the Advanced Clean Trucks Regulation, which will require half of all MD/HD vehicles to be zero-
emissions by 2030.11 This regulation will be the first of its kind and will require cooperation between
manufacturers, fleet owners, and utilities to achieve the mandate.
11 CARB, Proposed Advanced Clean Trucks Regulation, December 12, 2019,
https://ww2.arb.ca.gov/rulemaking/2019/advancedcleantrucks?utm_medium=email&utm_source=govdelivery.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 31
The electrification of commercial fleets is not only becoming more viable, thanks to market and
technology evolution, but also can be more cost-effective in reducing fuel expenses. EV battery prices
have dropped 79% since 2010. On top of that, the energy density of these batteries has increased 5%–
7% each year from 2010 to 2017.12 Along with increased storage and therefore electric range, the added
fuel efficiency can improve the economics. Compared to a typical diesel delivery vehicle, an EV’s MPG
could improve by over 200%, increasing from 7.6 MPG to 24.1 MPGe.13 Although the technology
continues to improve, there are still significant barriers that need to be addressed for successful
implementation. The initial purchase price, adequate charging infrastructure (and power level available),
and more vehicle options have each been identified as requirements for fleet electrification.
Cooperation and commitment from local utilities, who are a needed partner for electricity and
infrastructure support, will be important, as electrifying an entire 200- to 300-vehicle fleet could require
an order of magnitude more electricity on site as a diesel-operated fleet.14
Amazon distribution centers typically support 100–150 routes per day. There may be different delivery
structures for each Amazon distribution center, but they often fall into one of two groups:
1) independent delivery companies that contract with Amazon as well as other companies, and
2) Amazon delivery service partners that are more integrated into Amazon operations by using Amazon-
branded vehicles that meet established specifications and may be acquired through exclusive deals set
up by Amazon.
Amazon has a long-term strategic plan to achieve net zero carbon emissions by 2040. Under its
Shipment Zero program, the company has set a 50% net zero carbon goal by 2030, with an eye to
eventually eliminating carbon from its shipping. As a step toward these objectives, Amazon wants to
learn the right feature set for the charger infrastructure and vehicles. Amazon has been operating EVs in
Europe since 2015, with more than 150 to date, because there have been and still are more electric
options available there. Amazon has conducted some initial tests with pre-commercial electric delivery
vans at a limited number of locations with shorter routes, and the company is currently enacting a series
of small-scale deployments to understand EV and charging capabilities. Most importantly, Amazon
wants to discover unanticipated issues in these small deployments to better prepare for larger-scale
deployments.
The availability of suitable electric delivery vehicles has limited Amazon’s pursuit of transportation
electrification initiatives in the United States. The parking lot layout at distribution centers can also limit
the number of chargers that can be installed. Some delivery service partners have new conventional
vehicles and are not currently interested in getting any new vehicles, including electric ones. The length
of routes also influences which locations are best suited for EVs, as some serve more rural areas that
require far more daily miles per route. Amazon has initially placed EVs on shorter routes to test the
12 Green Biz and UPS, Curve Ahead: The Future of Commercial Fleet Electrification, 2018,
https://sustainability.ups.com/media/UPS_GreenBiz_Whitepaper_v2.pdf. 13 National Renewable Energy Laboratory, Field Evaluation of Medium-Duty Plug-in Electric Delivery Trucks,
December 2016, https://afdc.energy.gov/files/u/publication/field_evaluation_md_elec_delivery_trucks.pdf. 14 Green Biz and UPS, Curve Ahead: The Future of Commercial Fleet Electrification, 2018,
https://sustainability.ups.com/media/UPS_GreenBiz_Whitepaper_v2.pdf.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 32
vehicle range. Lightning Systems is working closely with Amazon to collect vehicle operational
information and find the most suitable routes while at the same time optimizing vehicle energy
efficiency. Amazon selected the National City location because of a good relationship with the landlord,
relatively shorter route lengths, and DAC classification aligned with SDG&E’s preferences. Based on the
site layout for the charging infrastructure, only 15 EVs were feasible for this location. Amazon currently
uses Ford Transit E250 diesel cargo vans in its National City delivery vehicle fleet.
Implementation Process
Customer education through outreach materials and staff interactions will be a key aspect for successful
similar future fleet electrification efforts. Very limited EV availability in Classes 2b through 4 is a
significant barrier. Most fleets are waiting to acquire EVs that have been successfully commercialized
with a number of fleets and see first commercial vehicle deliveries as a significant risk from a reliability
perspective, as the vehicles are the core element of their business. Most discussions with fleet
management regarding the possibility of acquiring EVs are at the basic level of whether they can meet
requirements and be reliable. Potential early adopters are interested in charging requirements and the
impact on electricity rates and costs. Only after these concerns are addressed might fleets be able to
calculate the anticipated cost per mile as compared to conventional vehicles. At this point, SDG&E does
not have enough information based on real-world use to help provide cost-per-mile information,
although this project will start providing data to develop that information. Larger entities’ adoption of
medium-duty EVs, and the successful integration of these EVs into operations, will help reduce concerns
of businesses that are not first adopters.
Based on this project’s experience, SDG&E acknowledges that it is necessary to engage with the
customers early and often to understand their intended EV use and any operational constraints that
would impact the charger location, charging logistics, and EV operation. This kind of engagement will
result in EV charging infrastructure solutions that will enable the customers to take full advantage of EV
capabilities and realize maximum benefits of EV operation. While the electrical infrastructure and
construction processes were relatively straightforward and did not present any significant challenges,
understanding how the fleets will use the vehicles and chargers is important to both the design and to
operational cost management. Had SDG&E included a field construction advisor early in the design
process to participate in the initial site walk instead of just reviewing the designs, several minor and a
few major change orders could have been avoided during the construction period.
Lesson Learned: Include field construction advisors early in the design process, and have them participate in the initial site walk to better understand the customer site and therefore be better able to accommodate anticipated EV operational needs.
As the fleets are starting to operate the vehicles and charging them when needed, the partners are
discovering that their charging choices can have a significant impact on their electricity costs (i.e.,
plugging them all in at once rather than spreading out their charging or charging during peak electricity
periods unnecessarily). This is new to the fleets whose priority is to ensure the vehicles are fully charged
when needed; this focus does impact the bottom line and is a factor when determining whether EVs can
be a cost-effective option. Therefore, it is important for the utility to work closely with the customer,
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 33
especially during the first few months of EV deployment, to monitor electricity use and suggest
strategies for optimizing it (e.g., TOU rates and managed charging).
Greenlots, the network service provider for this PRP, provided a dedicated representative to SDG&E for
this pilot. The representative is very knowledgeable about the chargers and handled charger
commissioning and any calls related to chargers installed under this PRP, which has been very helpful in
quickly resolving any issues and corresponding with SDG&E staff. This action was in response to a lesson
learned from the SDG&E Power Your Drive Pilot; during the pilot, challenges arose because Greenlots’
general help line representatives were not familiar with the program details, so having a dedicated
representative helped avoid similar issues.
SDG&E did not specify the charging station manufacturer for this PRP but did require that the
manufacturer be pre-approved in the Power Your Drive Pilot (Greenlots and ChargePoint were the two
options). Amazon staff conducted their own research based on the company’s duty cycle requirements
for any EV that might be added to the fleet. The company selected Greenlots chargers because of the
higher available power (16 kW vs 6.6 kW). Amazon had previously determined that a simple non-
networked charging station would likely suit its needs, but none were available under this PRP. The
Greenlots unit is larger and more sophisticated (LED screen) than Amazon would have likely chosen if
not participating in this PRP, but the unit will provide an opportunity to investigate authentication and
different payment methods.
Since Amazon did not know which EV model would be acquired, management requested that the design
use single-port chargers that would be placed in the center of the front of each parking space. This
placement would allow the most flexibility for the charging cord to reach the vehicle’s charging port,
regardless of its location. The proposed design also placed the new transformer and switch gear in an
existing smoking area, but Amazon was willing to move the smoking zone. The initial timing was charger
installation completion in 2018, but vehicle availability challenges delayed deployment until mid-2019.
The scope of this PRP required that customers get new meters for the charging stations rather than
using existing meters. Amazon felt it might be more advantageous to add the charging load to an
existing meter. Most of the company’s distribution centers have sufficient capacity to add the new
charging load to existing services, which would allow for energy demand management across the entire
facility. Because of the potential demand costs, Amazon requested energy management features from
Greenlots’ Sky platform to allow Amazon to manage charging. Amazon acknowledged that the charger
installation might have been more difficult if connected to the existing meter but believes that ongoing
costs would be lower using that approach.
Lesson Learned: If charging station installation programs can be made more flexible, customers may prefer the option to use either a new or existing meter—particularly those customers knowledgeable of and actively involved in energy management practices.
The charger locations were able to accommodate Amazon’s EV charging port placement, as Amazon
requested long charging cords for this purpose, and SDG&E was able to provide them. Some additional
complications arose during construction because SDG&E contractors, rather than Amazon’s direct hires,
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 34
were doing the work. This added an additional layer of authority and made it difficult to communicate
and coordinate the times when the facility power was shut off for new transformer installation. The
contractor tried to be accommodating but did not understand the level of detail that Amazon requires
to maintain its business-critical operations. All power outages affect Amazon operations, as distribution
centers are staffed 24–7 and need to prepare accordingly. (Providing advance notice of a power outage
in 15-minute increments instead of 4-hour blocks would have been helpful.) However, other than these
few concerns, Amazon felt that the construction went very well overall.
Although the PRP acquired only 15 EVs, finding a manufacturer with an EV that met Amazon’s needs and
could be delivered on the PRP timeline was challenging. Since the National City location has very limited
parking, vehicles have to be short to park and charge. Amazon selected Lightning Systems, which has the
smallest available package delivery electric vehicle in North America. (Amazon has not worked with
Lightning Systems before.) Lightning Systems also provided a larger battery option (86 kWh) to allow for
more route coverage. While the EVs come with only a 6.6 kW on-board charger, it should be sufficient
for the selected Amazon routes. Amazon’s plan going forward is to include the optional DCFC capability
on the Lightning Systems product as a backup charging option.
While some delivery fleets like Amazon have expressed interest in DCFC option, in addition to overnight
depot L2 charging, this would require added customer side and utility infrastructure and therefore
increase the overall cost of the project. Almost all electric truck offerings on the market today come
standard with L2 charging; however, there is an increasing number of manufacturers who are starting to
offer DCFC capability as an available option (can be as much as $5,000 extra). DCFC is of interest to some
fleets as it provides a redundancy for charging in case there are issues with the L2 chargers or a vehicle
does not receive a sufficient charge overnight but needs to be charged quickly in the morning to still be
able to on its route.
To offset the high EV purchase costs that remain a barrier to adoption, CARB’s Hybrid and Zero-Emission
Truck and Bus Voucher Incentive Project (HVIP) funding was used to purchase EVs. Amazon is the
responsible party for HVIP reporting, while the vehicles are registered to delivery service providers.
Amazon has access to the vehicle operational information from the Lightning Systems telematics;
however, some of the information is business confidential, such as individual routes and vehicle
efficiency. A high-level summary of operational information may be available for the evaluation.
Amazon has been provided with information about how to use Greenlots’ Sky platform, specifically the
managed charging software capabilities. Lightning Systems has provided safety, inspection, and
classroom training for Amazon drivers. Lighting Systems is also actively involved in monitoring the
vehicle operational data to advise and support Amazon.
Costs
The approved PRP had an anticipated total direct cost of $3,690,749, consisting of $3,231,963 in capital
and $458,786 in expense, as shown in Table 7.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 35
Table 7. SDG&E Fleet Delivery Services PRP Proposed Costs
Capital Costs O&M Expenses Total PRP Costs
Transformer and Install $ 248,625 $ 3,731 $ 252,356
Electrical Service $ 829,323 N/A $ 829,323
EVSE Costs $ 1,531,215 $ 35,055 $ 1,566,270
Purchased and SD Software $ 622,800 N/A $ 622,800
Measurement & Evaluation N/A $ 200,000 $ 200,000
Charging Equipment Maintenance N/A $ 15,000 $ 15,000
Billing Support N/A $ 80,000 $ 80,000
SDG&E Clean Transportation PM N/A $ 100,000 $ 100,000
First Year O&M Service Calls N/A $ 15,000 $ 15,000
First Year O&M for Charging Equipment N/A $ 15,000 $ 15,000
$ 3,231,963 $ 425,000 $ 3,695,749
The PRP direct costs as of September 30, 2019, totaled $1,316,472 out of a budgeted $3,695,749, as
shown in Table 8 (presented in categories reported by the utility).
Table 8. SDG&E Fleet Delivery Services PRP costs as of September 30, 2019
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Construction $ 630,075 $ 1,356,363
Engineering Design $ 119,079 $ 161,175
Chargers, Meter Pedestals, Transformer, and Other Materials
$ 316,554 $ 1,091,625
Internal SDG&E Labor (Program Management and Support)
$ 16,306 $ 62,257 $ 379,800
IT Costs $ 116,629 $ 622,800
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 36
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Customer Engagement and Outreach
Other $ 52,519 $ 52 $ 78,786
Direct Costs $ 1,251,162 $ 3,231,963 $ 65,310 $ 458,586
Non-Direct Costs (Indirect, AFUDC, and Property Taxes)
$ 1,232,606 $ 1,726,530 $ 67,924 $ 200,614
Total Costs $ 2,483,768 $ 4,958,493 $ 133,233 $ 659,200
Benefits
The planned/anticipated benefits in Table 9 reflect 83.3% of the benefits stated in the original testimony
because the final expected number of electric delivery trucks supported by this PRP’s charging
infrastructure has been reduced from 90 to 75.
Table 9. SDG&E Fleet Delivery Services PRP Benefits
Anticipated in Testimony
(90 vehicles)
Anticipated as Planned
(75 vehicles)
As Implemented
As Optimized
Petroleum Reduction
203,000 GGE per year 169,167 GGE per year TBD TBD
GHG Emissions 894 MT of CO2 per year
745 MT of CO2 per year
TBD TBD
Criteria Pollutants
0.81 MT of NOx per year
0.67 MT of NOx per year
TBD TBD
DAC Impact 66% (2 of 3 UPS sites), plus same DAC portion with 3 more sites
80% (60 of 75 delivery trucks have a base location in a DAC)
TBD TBD
Operations, Maintenance, and Fuel Costs
2,946 MWh of electricity per year
2,455 MWh of electricity per year
TBD TBD
Other Co-Benefits
Improved net load factor (if charging is properly managed)
Improved net load factor
TBD TBD
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 37
Operational Impacts of Project Equipment
No significant electric delivery vehicle operations under this PRP were completed as of this interim
report. This section will be completed for the final report utilizing all information and data obtained
before November 2020.
Stakeholder and Customer Feedback
No significant electric delivery vehicle operations under this PRP were completed as of this interim
report, so this feedback has not yet been captured. Feedback pertaining to the initial implementation of
this PRP is captured in the Implementation Process section of the Evaluation Methodology. This section
will be completed for the final report using all information and data obtained before November 2020.
2.1.4 Conclusions and Recommendations
Findings
Without significant electric delivery vehicle operations to date, it is too early to determine this PRP’s
success, which will be documented in the final report. However, some preliminary findings, in addition
to the lessons learned shared previously, are mentioned below:
The restriction to add only new project locations for locally owned, MBE/WBE delivery business
fleets prevented this PRP from recruiting more participants, despite several outreach methods
(forums and direct contact). The final expected number of electric delivery vehicles supported
by SDG&E charging infrastructure is only 75 of the initially proposed 90. Flexibility in pilot and
program deployment is essential to allow for accelerated EV adoption.
For these specific deployments, electric delivery vehicles and fleet operations did not require
DCFCs, so only L2 stations were deployed.
The PRP successfully installed 79 L2 charging stations, with the supporting electrical
infrastructure, at four different locations. Through this effort, SDG&E has attained relevant
installation experience, along with more accurate cost information, to help support more
delivery vehicle fleets with electrification.
Given the likely electrical infrastructure upgrade requirements for significant fleet
electrification, utilities are needed partners for electricity and for infrastructure support.
Utilities are learning alongside customers how best to integrate EVs into their fleets and
operations, as neither utilities nor customers have this experience.
Third-party onboard vehicle data loggers are preferred for independently monitoring vehicle
performance, but to reduce costs, the project will rely on the fleets to provide vehicle
performance data through use of vehicle-manufacturer-installed telematics systems.
Significantly more effort, investment, and EV availability and reduced EV costs will be necessary
to sufficiently support locally owned MBE/WBE delivery business fleets in transportation
electrification projects. Often, such businesses do not have the knowledge or resources to
secure the grants necessary to finance this effort (upfront costs for electric delivery trucks is a
barrier) or the available staffing to navigate the challenges of operating new technology.
Further, smaller local companies generally do not have robust financial resources to make
investments in new technologies.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 38
The electric delivery vehicle market is growing and maturing but has relatively limited options.
Some small manufacturers to first enter the market (e.g., Smith Electric) struggled to succeed
and had to cease operations. These PRPs are procuring some of the first production vehicles
from the selected manufacturers, which can have an impact on production and delivery times.
Supporting the EV manufacturers, providing a market for their products, and examining vehicle
performance will help advance the transition to EVs.
Include field construction advisors early in the design process, and have them participate in the
initial site walk to better understand the customer site and therefore be better able to
accommodate anticipated EV operational needs.
Including field construction advisors early in the design process and having them participate in
the initial site walk to better understand the customer site is beneficial to the implementation of
these projects as they will be better able to accommodate anticipated EV operational needs.
If charging station installation programs can be made more flexible, customers may prefer the
option to use either a new or existing meter—particularly those customers knowledgeable of
and actively involved in energy management practices.
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
2.2 Green Shuttles
2.2.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
SDG&E’s PRP filing proposed a partnership with taxi, shuttle, and transportation network companies
(TNCs) interested in the electrification of their fleets. SDG&E sought to support them with grid-
integrated charging facilities, including DCFC and L2 EVSE, and a grid integrated rate. The CPUC decision
approved only fixed-route shuttle applications. SDG&E may also install solar and energy storage at one
project location. SDG&E will work with the participating shuttle companies to determine whether
additional EV drivers, such as taxi, vanpool, or TNC drivers, can use the same charging infrastructure.
SDG&E may offer its new Public Grid Integrated Rate at the charging stations it owns. The utility
originally proposed to install, own, operate, and maintain up to five grid-integrated charging facilities
(“project charging facilities”), which will include one DCFC and two L2 EVSEs per facility, to address the
fueling needs for the EVs with rapid-charging DCFC capabilities, as well as applications that do not
require these capabilities.
This project creates the opportunity to learn important aspects of this market to inform Commission
policy as well as improve advancement from a pilot project to program scale, if deemed beneficial. The
following are key learning objectives of this project:
Utilization Optimization – The optimal charging facility-to-vehicle ratio to achieve high utilization
rates without creating inconvenience for the vehicle drivers.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 39
Location Optimization – The extent to which charging facility locations for shuttle fleets are
easily accessible, convenient, and sufficient in volume and types of chargers to meet the
operational requirements of the other potential markets (i.e., taxi, vanpool, and TNC).
Impact of the Grid-Integrated Rate – The extent to which the proposed grid-integrated rate
works to encourage off-peak charging, as well as the extent to which these operations will have
the flexibility to select those hours of the day with the lowest energy prices.
EV Adoption – The degree to which driver exposure to EVs influences EV interest and adoption
within the broader taxi, shuttle, and rideshare community. Gathering data to help inform the
total cost of ownership for fleet electrification is also key to EV adoption.
This project is an opportunity to implement system efficiencies that provide benefits to ratepayers,
while also maintaining a safe and reliable level of service. The PRP aims to provide increased exposure
to, and experience with, electric shuttle bus applications:
• SDG&E will partner with two or more shuttle companies to purchase up to four electric shuttles,
with the utility providing a financial incentive of $10,000 per electric shuttle, with no more than
two incentives per shuttle company, for agreeing to participate in the project.
• The shuttle companies will enroll in SDG&E's grid-integrated rate offering as a means to reduce
fueling costs; the shuttle company will be notified in advance, facilitating scheduling of charging
times during lower-priced, off-peak hours.
The customer educational component will help potential participants develop an understanding of the
grid, fuel cost savings benefits and advantages of charging off-peak under a grid-integrated rate (where
feasible), how the rate works at project charging facilities, SDG&E billing, and other project benefits.
Customer engagement for this project includes customer outreach with potential site hosts, outreach
through company representatives, and an overarching program-specific communication and education
campaign (e.g., using social media, web and web tools, and co-sponsored educational events and
collateral). Other forms of customer/driver engagement and education will take place in collaboration
with relevant taxi, shuttle, and TNC marketing programs, should a charging location be available to these
markets.
Sites and Participants
Recruitment Process
SDG&E account executives, shuttle manufacturers, and other resources were used to conduct outreach
to potential program participants. In January 2018, SDG&E held an external stakeholder conference for
vendors, EV shuttle manufacturers, and local customers that fit the decision requirements. As a result,
SDG&E engaged many customers and went into serious discussion with 17 customers about the
program. Customer operations included schools, workplaces, airport shuttles, and hotel shuttles.
Unfortunately, many customers could not participate in the program because of the following factors:
The procurement cycle did not align with the program (30%).
The cost of the electric shuttles was too high (20%).
The customer operations do not operate on fixed routes (10%).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 40
In the originally proposed budgets, the conduit and trench lengths were estimated on a per-site basis.
Some locations have significantly longer conduit and trench lengths than the estimated average, which
has excluded some potential customers from participating.
Participants
SDG&E received interest from four fixed-route shuttle companies to help electrify their fleets, including
two offsite airport parking shuttle fleets (San Diego Airport Parking [SDAP] and Aladdin Airport Parking
[Aladdin]), one onsite airport parking shuttle fleet (the San Diego International Airport [SDIA]-operated
fleet), and a workplace employee shuttle (Illumina, which has buses operated by ACE Parking). These
shuttle fleet project participants indicated that the originally proposed charging infrastructure
configuration of two L2 and one DCFC per site would not meet their needs. L2 charging stations are not
a suitable operational fit for the airport shuttle operations, and multiple DCFCs may be needed. The
workplace shuttle operations, on the other hand, have longer opportunities to charge outside of the
workday; however, there is no easy solution to the need to rotate the vehicles through a single DCFC, so
this workplace shuttle operation would require a one-to-one ratio of L2 charging stations to shuttle
buses. These use cases are shown in
Figure 19. SDG&E submitted an advice letter to the CPUC in Q1 of 2019 allowing for two DCFCs for three
airport shuttle sites, for a total of six DCFCs and six L2 charging stations at one workplace shuttle site;
the CPUC approved the proposed system.
Figure 19. SDG&E Green Shuttles participant use cases
Source: SDG&E Q4 2018 PAC Meeting
SDAP runs an off-site airport parking lot and shuttles its customers to and from the airport. SDAP is also
participating in SDG&E’s Power Your Drive Program (10 L2 charging ports were installed). Shuttles
operate on an eight-mile loop from the parking area to the airport and back, which takes approximately
30 minutes. Shuttles operate based on demand, up to four shuttle buses can be running during peak
time, and only one runs in off-peak hours. The shuttle buses are parked when the airport is shut down
between 12:00 AM and 4:00 AM (although delays often keep them running until 1:00 AM). In 2015 and
2016, SDAP operated three Zenith EVs with three 14 kW L2 chargers, but the vehicles experienced
significant operational issues and could not replace the operation of the diesel shuttles. For this PRP,
SDAP acquired two GreenPower electric shuttle buses. SDAP planned to use 50 kW BTC Power DCFCs
managed by Greenlots, but the GreenPower electric shuttle’s voltage requirements (800 V battery
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 41
packs) necessitated a switch to a ChargePoint CPE 250 DCFC charging station and the ChargePoint
network. While SDAP was open to having other fleets use the chargers, the site is for private use and will
not be publicly available.
Figure 20. GreenPower EV Star all-electric mini electric bus specifications
Source: CARB Hybrid Truck and Voucher Incentive Program
Figure 21. GreenPower EV Star model
Source: CARB Hybrid Truck and Voucher Incentive Program (left) and Evaluator Team (right)
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 42
Figure 22. SDAP site with two GreenPower EV Stars
Source: Evaluator Team
Figure 23. SDAP site with two 62.5 kW DCFCs paired for 125 kW and a new transformer
Source: Evaluator Team
Aladdin also runs an off-site airport parking lot and shuttles its customers to and from the airport. The
customer has about five L2 charging stations that it uses as a “value added” service to customers.
Aladdin considered Phoenix electric shuttles, but those were too tall to enter the parking garage; the
company instead placed an order with Briton for 4 Lightning System Ford E450 electric shuttles. Two
62.5 kW ChargePoint CPE 250 DCFCs will be installed to charge these vehicles. The site is for private use
and will not be publicly available.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 43
SDIA is working on procuring four electric shuttles for an inter-terminal route. The initial site evaluated
by SDG&E was the current taxi/rideshare/shuttle lot, which would have allowed charging infrastructure
at this location to be open to other taxi/rideshare/shuttles, as well as the new shuttles purchased by
SDIA. Unfortunately, this initial site will undergo major reconstruction in the near future, so installing
charging infrastructure is not feasible. Alternative locations were investigated, but no other options
were suitable; therefore, SDIA will not be a Green Shuttles PRP site.
Illumina provides shuttles to its employees to go around the main campus (5200 Illumina Way, San
Diego, California 92122), back and forth to the north campus (0.9 miles from the main campus at 4795
Executive Dr.), and back and forth to University Town Center mall (1.3 miles from the main campus at
4545 La Jolla Village Drive). Illumina is also participating in SDG&E’s Power Your Drive Program. ACE
Parking operates Illumina’s shuttle service and placed an order with Briton for 4 Lightning System Ford
E450 electric shuttles for this project. The construction plan specified BTC Power 70 A L2 charging
stations, which will be managed by Greenlots. The site is for private use and will not be publicly
available.
SDG&E investigated potential sites where EV chargers could be integrated with renewable (solar
photovoltaic [PV]) energy and an energy storage system (battery) to examine how these technologies
can be used to manage energy use and demand charges. The utility issued a request for bids to perform
the solar and storage installation and integration, and two companies responded. However, the
contractors lacked experience, and the proposed costs were high. SDG&E explored the option to
facilitate this effort using internal staff. SDAP offered the company site to demonstrate the integrated
PV and battery system, which would provide a significant opportunity to examine the interaction with
electric shuttle bus charging. System design, component specifications, and pricing led SDG&E to
determine that the integrated PV and battery system would not be cost-effective to implement. Utility
management plans to study this option by modeling the expected PV and battery system contributions
and benefits against the actual shuttle bus charging use.
Lesson Learned: The integration of a PV and battery system with EV charging could be a valuable solution to managing electrical demand. While PV is a mature technology that has been widely deployed, the integration with battery system and EV operations is new. The technological challenges associated with implementation and significant costs were likely key reasons for the limited response SDG&E received to its request for bids. Given the current costs and risks, SDG&E decided to instead model this solution. Should this prove valuable at a reasonable price point for implementation, a future deployment may be warranted (outside of the PRP).
Timeline and Status
With four potential project partners identified and the design in progress for three of those sites, SDG&E
shared the anticipated project timeline (combined for all shuttle sites) shown in Figure 24 at the
Q3 2018 PAC meeting. That timeline estimated the design, along with component specification and
procurement, would take about four months, and construction would be completed about two months
following that, so that the sites could be energized by March 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 44
Figure 24. SDG&E Green Shuttles PRP timeline as of September 2018
Source: SDG&E Q3 2018 PAC meeting
However, the type of chargers deployed at each site (and hence the PRP scope) changed, which required
discussion with the PAC, submission of an advice letter, and approval from the CPUC. This process
concluded in Q1 2019. Further challenges were experienced during the execution of project partner
contracts, which took several months longer than anticipated. The result was a significant delay to the
project timeline.
As of early December 2019, only two DCFCs at SDAP have been energized and commissioned. SDAP is
also the only project partner to acquire electric shuttle buses, with the two GreenPower EV Stars being
delivered in July 2019. These vehicles have been charging on the existing L2 chargers, but the duty cycle
requirements (up to 200 miles per day) did not allow for a diesel shuttle to be fully replaced until the
DCFCs were commissioned in December 2019. Construction at SDAP was scheduled to begin in May
2019, but when the SDIA site was found infeasible, SDG&E entered into discussions with SDAP about a
potential combined DCFC and energy storage system. However, utility management ultimately decided
not to change the proposed design. Thus, construction at SDAP started in June 2019 and was completed
within two months. When the SDAP charging infrastructure was complete and commissioning was under
way, the DCFCs installed were discovered to be incompatible with the higher 800 V battery system in
the GreenPower EV. The only approved alternative that would meet the PRP timeline was the
ChargePoint CPE 250 DCFC. Procuring and installing the new chargers took a few additional months. CPE
250 DCFCs allow for a combined output of 125 kW when connected with an optional 1,000 V pairing kit,
which SDG&E and SDAP agreed to install for this site. While the construction to accommodate the
charger pairing was completed quickly, there was a several-week delay while awaiting delivery of the
pairing kit.
Lesson Learned: EVs in smaller market segments, such as shuttle buses, are often supplied by several smaller manufacturers that are attempting to fill a market need (more established manufacturers target larger market segments). The specifications of these EVs may be unique to each manufacturer, and it is critical to verify compatibility with the planned charging infrastructure.
The contract with Aladdin was executed in May 2019. Construction began in November 2019 and is
scheduled for completion by the end of January 2020. The contract with Illumina was executed in
September 2019, and EV charger installation is scheduled for completion by the end of Q1 2020. As of
December 2019, neither partner had acquired its EVs. Based on the projected dates that the EVs with
Illumina (expected by April 2020) and Aladdin are in operation, only six months of operational data may
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 45
be available for the final evaluation of performance for those PRP sites. The SDAP site should provide
nearly a year of operational data for evaluation.
Figure 25. SDG&E Green Shuttles PRP timeline as of December 2019
Source: SDG&E
2.2.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP.
• What instructions/training were drivers given about using the charging station?
• Were operational and technology opportunities to better manage charging identified, how were
they implemented, and were they effective?
• What is the appropriate charging level and ratio of charging ports to vehicles?
• How might the integration of PV and batteries with DCFC on site affect this use case? What
different charging optimization scenarios were modeled, and what were their outcomes?
The data collection sources utilized to evaluate this PRP include 1) PRP information from the approved
decision, project updates, site visits, and other available documentation, 2) market research on shuttle
vehicles and early deployment efforts from other similar electrification projects across the country,
3) PRP data from vehicle and charger operations, 4) IDIs with project partners, and 5) surveys with
vehicle drivers.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 46
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: the PRP kick-
off meeting (SDG&E and evaluator), quarterly PAC update meetings, weekly PRP updates (SDG&E and
evaluator), site visits, and other periodic calls or emails. Currently the evaluation team has the following
information from this PRP for one project site (SDAP): charging station hardware specifications, EV
specifications, electricity tariff details, site photos, project costs, and historical usage of non-EVs in the
fleet. In Q1 2020, the evaluator expects to receive more details on construction site plans and designs,
several items mentioned where only initial high-level information was provided, along with all
information for the other project sites (Aladdin and Illumina).
The following sources for market research have been identified:
National Renewable Energy Laboratory: Analysis of Fast Charging Station Network for Electrified
Ride-Hailing Services (2018)
Calstart: Hybrid Shuttle Bus Testing and Demonstration ARBOC “Spirit of Mobility” (2014)
CARB: Economic Analysis for the Proposed Zero-Emission Airport Shuttle Regulation (2018)
CARB: Transit Fleet Cost Model (2017)
There are also several ongoing electric bus deployments at the following airports (some of which are
shuttle buses, but most use larger transit bus models): Los Angeles, Raleigh–Durham, Newark Liberty,
LaGuardia, Kansas City, John F. Kennedy, Indianapolis, Hartsfield–Jackson Atlanta, San Francisco,
Sacramento, Ontario, Oakland, Norman Y. Mineta San Jose, Long Beach, John Wayne, and Hollywood
Burbank.
SDG&E will be providing PRP operational data from its utility service meters (one utility meter at each
deployment site for all charging stations at that site) for 15-minute interval data and monthly costs,
while the network service provider is expected to send monthly CSV files for charging station session
data. Third-party data loggers for MD/HD EVs were found to be much more expensive than anticipated,
so SDG&E is relying on vehicle manufacturer telematics systems for vehicle data. It is expected that the
project participants will provide high-level data on vehicle utilization and maintenance, along with any
necessary maintenance on the charging stations.
The evaluator held IDIs with representatives from the SDG&E PRP management team and SDG&E
construction staff to further understand the background on this project and gather lessons learned
based on progress to date. Additional IDIs with the SDG&E staff, project participants, and vendors will
take place in 2020 as the EVs are put into operations. A survey or a facilitated focus group discussion
with the EV drivers is also planned.
2.2.3 Evaluation Findings
Project Baseline
Promoting the development and use of zero-emission airport ground transportation will help CARB
achieve the emission reduction strategies outlined in the Mobile Source Strategy, State Implementation
Plan, and Sustainable Freight Action Plan. Vehicles such as airport shuttles that operate on fixed routes,
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 47
have stop-and-go operations, maintain low average speeds, and are centrally maintained and fueled are
ideal candidates for targeting zero-emission electric technologies.15
The Zero-Emission Airport Shuttle Regulation, which CARB adopted in June 2019, requires that airport
shuttle operators transition to 100% zero-emission vehicle (ZEV) technologies. Airport shuttle operators
must begin adding zero-emission shuttles to their fleets in 2027 and complete the transition to ZEVs by
the end of 2035. The regulation applies to airport shuttle operators who own, operate, or lease vehicles
at any of the 13 airports regulated under the rule, shuttles with gross vehicle weight rating of 8,501 or
greater that transport passengers to and from the regulated airports, shuttles with fixed routes that
stop at rental car facilities, on-airport or off-airport parking, hotels or other similar locations, and
shuttles based within 15 miles of a regulated airport that have round-trip routes of 30 miles or less.16
SDAP currently operates four diesel shuttle buses: three Mercedes Sprinters (one 6-cylinder and two
4-cylinder) and one Ford Transit. The company fuels them with renewable diesel to meet SDIA’s
requirement for alternative-fueled shuttles. The station for this is 14 miles round trip from SDAP, and
the shuttle buses will go there at least every other day, if not every day (during the busy season). SDAP
tested Zenith electric shuttle buses in an attempt to replace the diesel shuttles but experienced many
issues. The maintenance shop across the street that the company used for the diesel shuttles helped
support those Zenith shuttles and has staff who are knowledgeable about EVs to service the new ones
(no change in current vehicle maintenance operations).
Electric shuttle bus manufacturers and therefore EV shuttle options are currently very limited, and there
are not many active demonstrations of the technology. BYD offers a 30-foot electric shuttle bus for sale
in North America. Although specific vehicle sales figures are not readily available, BYD is the largest zero-
emission bus (ZEB) manufacturer in the world, and its North American operation employs over 750
workers in its 450,000-square-foot manufacturing facility in Lancaster, California. GreenPower Motor
Company manufactures and sells two battery electric shuttle buses; the 36.5-foot Synapse shuttle bus
and the 25-foot EV Star (the EV Star is available in three trim levels, including an ADA accessible version).
The company reports strong sales and earnings, particularly in regard to the EV Star, at least two of
which were sold to SDAP. In addition to the sale of two Synapse school buses and one EV 350 transit
bus, GreenPower reported Q2 sales of 24 EV Star vehicles. Lightning Systems is a Colorado-based
manufacturer of zero-emission all-electric powertrains with offices in Loveland, Colorado, and San
Diego, California. Lightning Systems claims to improve a fleet’s operating costs while providing safety,
environmental responsibility, and advanced technology. The company offers all-electric powertrains for
the Ford Transit 350HD passenger and cargo vans, Ford E-450 shuttle bus and cutaway models, Ford F-
59 step/food van, Ford F-550 cargo trucks and buses, Chevrolet 6500XD Low Cab Forward model, and
30-foot, 35-foot, and 40-foot transit buses.
15 CARB, Zero Emission Airport Shuttle webpage, 2019, https://ww2.arb.ca.gov/our-work/programs/zero-emission-
airport-shuttle/about. 16 California Air Resources Board, Zero-Emission Airport Shuttle Regulation Factsheet (2019) LINK:
https://ww2.arb.ca.gov/sites/default/files/2019-10/asb_reg_factsheet.pdf
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 48
Interviews have not yet been conducted with Illumina and Aladdin, and therefore the interim report
includes no information about their current vehicles.
Implementation Process
The initial installation design for SDAP incorporated PV and energy storage. SDG&E issued a bid for these
systems, but all received quotes were much higher than expected and allocated in the project budget.
SDG&E decided to leverage the internal team to design these systems and then investigated the costs
for the individual components from known suppliers. Even with this approach, the equipment and
installation costs were still very high. SDG&E looked into some older assets that could potentially be
repurposed for this project to lower costs, but even this approach proved to be costly. SDG&E staff then
ran a model to determine the potential impacts of these systems and found very limited electricity
savings (~$1,500 per year). The cost differential for this application was so far off that it could not be
justified. Instead, SDG&E plans to simulate the expected impacts from PV and energy storage for this
DCFC installation and calculate the benefits if it was implemented as planned.
Lesson Learned: PV and energy storage technologies are well developed, and their application to supporting grid services has been proven. However, the integration with EV charging is entirely new, and no off-the-shelf system exists (except for limited applications of an off-grid PV, battery, and L2 charger system). On their own, these components need to be optimized to provide a positive return on investment, and the complexity of combining these into one solution adds costs and challenges the optimization strategy for maximizing benefits.
SDG&E investigated several options for an open access charging station among the potential
participants. Several had very complicated parking lot access that would have made allowing public
access challenging, and most sites rely heavily on the availability of these chargers when the batteries
get depleted, so those locations could not risk having the chargers occupied at those times. Staff were
able to identify a site that could allow public access, but unfortunately, it was the SDIA location that is
scheduled to undergo major construction. SDG&E has found that many shuttle bus operations are
interested in electrification, but it is very new to them, so they could not commit to vehicle purchases
that aligned with the PRP timeline. However, many of these customers are planning to pursue
electrification through SDG&E’s MD/HD SRP. SDG&E has found that ongoing programs are much more
helpful in recruiting new customers. Limited, short-term programs can work only for those who already
have plans to electrify their fleets, whereas long-term programs inspire more customers to take the
necessary steps toward planning for electrification so that they are ready to install charging stations in a
year or two. The PRP has created a “pipeline” of potential customers that the SRP can now support.
The ChargePoint CPE 250 DCFC EVSE comes with a 12-foot cord, but SDG&E and SDAP learned that
length is tip to tip, while the cable positioning around the vehicle and the angle to plug the cord into the
vehicle’s charging receptacle make the usable length significantly less (see Figure 23, with the EV parked
very close to the bollards).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 49
Costs
The approved PRP had an anticipated total direct cost of $3,467,205, consisting of $2,456,287 in capital
and $1,010,918 in expense, as shown in Table 10.
Table 10. SDG&E Green Shuttles PRP proposed costs
Capital Costs O&M Expenses Total PRP Costs
Transformer and Install $ 75,100 $ 2,073 $ 77,173
Electrical Service $ 440,865 N/A $ 440,865
EVSE Costs $ 1,317,522 $ 1,845 $ 1,319,367
Purchased and SD Software $ 505,400 N/A $ 622,800
Customer Engagement N/A $ 200,000 $ 200,000
Measurement and Evaluation N/A $ 410,000 $ 410,000
Billing Support N/A $ 80,000 $ 80,000
SDG&E Clean Transportation PM N/A $ 100,000 $ 100,000
First-Year O&M Service Calls N/A $ 15,000 $ 15,000
First-Year O&M for Charging Equipment N/A $ 10,000 $ 10,000
$ 2,338,887 $ 818,918 $ 3,157,805
Little to no costs were originally associated with design, engineering, and permitting. SDG&E had
originally estimated these costs would be less than $10,000 per site (some estimates did not even
account for any additional costs for this). SDG&E is finding that the actual design, engineering, and
permitting costs average about $30,000 per site.
The PRP direct costs as of September 30, 2019, totaled $713,069 out of a budgeted $3,157,805, as
shown in Table 11 Table 11. SDG&E Green Shuttles PRP costs as of September 30, 2019(presented in
categories reported by the utility).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 50
Table 11. SDG&E Green Shuttles PRP costs as of September 30, 2019
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Construction $ 763,455
Engineering Design $ 79,397 $ 109,750
Chargers, Meter Pedestals, Transformer, and Other Materials
$ 113,994 $ 842,882
Internal SDG&E Labor (Program Management and Support)
$ 6,342 $ 86,305 $ 590,000
IT Costs $ 408,202 $ 622,800
Customer Engagement and Outreach
$ 200,000
Other $ 18,829 $ 28,918
Direct Costs $ 626,764 $ 2,338,887 $ 86,305 $ 818,918
Non-Direct Costs (Indirect, AFUDC, and Property Taxes)
$ 1,305,332 $ 89,386 $ 264,238
Total Costs $ 626,764 $ 3,644,219 $ 175,691 $ 1,083,156
Benefits
The originally designed PRP estimated benefits based on the addition of 4 EV taxis, 4 electric shuttles,
and 54 taxis/TNC vehicles. The current expected impact of this PRP is 12 electric shuttles. It is not
confirmed whether the SDAP charging infrastructure would be accessible by taxis or TNC EVs. The
reduced anticipated benefits for the PRP as planned utilize the factors listed in Appendix A of SDG&E
Direct Testimony [pertaining to SB 350 Transportation Electrification Proposals] – Chapter 8 Air Quality
Impacts and Cost Effectiveness.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 51
Table 12. SDG&E Green Shuttle PRP benefits
Anticipated in Testimony
(4 shuttles and 54 taxis/TNC EVs)
Anticipated as Planned
(12 shuttles)
As Implemented As Optimized
Petroleum Reduction
114,000 GGE per year
59,000 GGE per year TBD TBD
GHG Emissions 769 MT of CO2 per year
492 MT of CO2 per year
TBD TBD
Criteria Pollutants
0.19 MT of NOx per year; 0.14 MT of VOC per year
0.13 MT of NOx per year
TBD TBD
DAC Impact SDIA is adjacent to DACs
All three sites are in DACs around SDIA
TBD TBD
Operations, Maintenance, and Fuel Costs
996 MWh of electricity per year
152 MWh of electricity per year
TBD TBD
Other Co-Benefits
Improved net load factor (if charging is properly managed)
Improved net load factor
TBD TBD
Operational Impacts of Project Equipment
No significant electric shuttle bus vehicle operations under this PRP were completed as of this interim
report. This section will be completed for the final report utilizing all information and data obtained
before November 2020.
Stakeholder and Customer Feedback
No significant electric shuttle bus vehicle operations under this PRP were completed as of this interim
report, so this feedback has not been captured. Feedback pertaining to the initial implementation of this
PRP is captured in Implementation Process section of the Evaluation Methodology. This section will be
completed for the final report utilizing all information and data obtained before November 2020.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 52
2.2.4 Conclusions and Recommendations
Findings
Without significant electric shuttle bus vehicle operations to date, it is too early to determine this PRP’s
success, which will be documented in the final report. However, some preliminary findings, in addition
to the lessons learned shared previously, are mentioned below:
Shuttle bus operations have distinct use cases that dictate specific charging infrastructure, and it
did not make sense to install both L2 and DCFC at each location.
Most shuttle bus companies have private facilities that are not equipped to allow other EVs to
charge at company sites.
Electric shuttle bus options, especially in Classes 2–4, are very limited, and there can be long
lead times for procurement. Partners had a hard time getting the EV manufacturers to commit
to vehicle delivery.
Shuttle bus companies have established procurement cycles, and offering charging
infrastructure was not enough incentive for companies to commit quickly to purchasing electric
shuttle buses had they not already had plans to do so.
Third-party onboard vehicle data loggers would be ideal for independently monitoring vehicle
performance, but they were cost-prohibitive; the PRP will instead rely on the fleets to provide
vehicle performance data through use of vehicle-manufacturer-installed telematics systems
where available.
The integration of a PV and battery system with EV charging could be a valuable solution to
managing electrical demand. While PV is a mature technology that has been widely deployed,
the integration with battery system and EV operations is new. The technological challenges
associated with implementation and significant costs were likely key reasons for the limited
response SDG&E received to its request for bids. Given the current costs and risks, SDG&E
decided to instead model this solution. Should this prove valuable at a reasonable price point for
implementation, a future deployment may be warranted (outside of the PRP).
EVs in smaller market segments, such as shuttle buses, are often supplied by several smaller
manufacturers that are attempting to fill a market need (more established manufacturers target
larger market segments). The specifications of these EVs may be unique to each manufacturer,
and it is critical to verify compatibility with the planned charging infrastructure.
PV and energy storage technologies are well developed, and their application to supporting grid
services has been proven. However, the integration with EV charging is entirely new, and no off-
the-shelf system exists (except for limited applications of an off-grid PV, battery, and L2 charger
system). On their own, these components need to be optimized to provide a positive return on
investment, and the complexity of combining these into one solution adds costs and challenges
the optimization strategy for maximizing benefits.
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 53
2.3 Airport Ground Support
2.3.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
This PRP is intended to encourage, support, and accelerate electrification of ground support equipment
(GSE) at SDIA, also known as Lindbergh Field. SDG&E proposed to increase the number of electric GSE
charging ports at SDIA by up to 45 (Phase 2), as well as retrofit 16 existing charging ports (Phase 1). The
Airport GSE Project will help incorporate additional electric charging load from electric GSE in a manner
that mitigates impacts to the grid. This project will also include integration and utilization of SDIA’s
5.5 MW PV system to the fullest extent possible. A major component of this project is SDG&E’s data
collection and analysis to better understand GSE charging load patterns and support electric GSE, as well
as the related impacts of conversion from internal combustion engine GSE equipment to electric GSE
equipment.
Electric GSE that will be supported by this project includes baggage tractors, cargo belt loaders,
pushback tractors, forklifts, and other equipment, given market availability. SDG&E will also install load
research meters and enabling technology, such as communicating chargers, to closely track
consumption patterns and allow for future managed charging and grid integration. Upon collection of
data, SDG&E will be able to better understand the increased load resulting from the adoption of electric
GSE, the time of day of the additional charging load, and the appropriate ratio of charging ports to
vehicles. With this analysis and knowledge, SDG&E can better collaborate with SDIA and airport tenants
to operate and charge electric GSE at times that are beneficial rather than detrimental to local
distribution circuits and the electric grid in general.
Figure 26. A variety of available electric ground support equipment charging at a California airport
Source: Evaluator Team
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 54
The key learnings from this project include a better understanding of the impact of electric GSE adoption
through data collection and analysis and education of stakeholders interested in electrifying GSE. Data
collection and analysis will allow stakeholders to better understand the ideal ratio of chargers to
vehicles, the ideal time to charge vehicles to avoid on-peak charging, the potential need and areas for
training employees, and other operational best practices. A comprehensive employee training program
using the equipment can demonstrate safe and easy operation of the GSE and supporting charging
stations, as well as demonstrate the importance of using grid-integrated technology to mitigate both
electricity costs and grid impacts. Emphasizing safety and electric charging protocols and discussing the
overall benefits of electrification will be key focuses of this project’s education and outreach efforts. In
addition, SDIA’s onsite solar provides a unique opportunity to examine the interaction between onsite
solar and electric GSE charging. Increased visibility of the impacts of electric GSE adoption will benefit all
stakeholders. These key learnings will enable expansion beyond SDG&E’s service territory.
Sites and Participants
Recruitment Process
SDG&E worked closely with SDIA during the application process. The strategy around the GSE
electrification project was based on a collaborative effort with SDIA. As part of Phase 1, SDG&E was
authorized to retrofit existing ports. After conducting outreach to SDIA tenants, including locally owned
and minority-owned businesses, American Airlines was selected as the candidate for those retrofits
because the airline’s existing charging equipment is outdated and less efficient and provides no data to
help guide users as to when they need to charge.
In November 2018, SDG&E spoke at the monthly airlines meeting at SDIA. SDG&E reviewed the project’s
goals, presented Phase 2 EVSE installation potential, and asked the airlines to respond to a survey. The
survey was designed to understand the airlines’ different needs, barriers, and goals of electrifying their
GSE fleets in the future. Survey results showed that infrastructure, procurement cycles, and available
electric GSE were the main barriers. SDG&E and SDIA plan to work with SDIA’s tenants to pursue funding
sources for new electric GSE, as described in SDG&E’s application and supporting testimony. These
efforts contribute to the Phase 1 goal, which is to understand whether there is a need for further
charging infrastructure at SDIA.
Participants
From 2006 to 2014, the electric GSE fleet at SDIA has seen an increase, but the total growth has not
increased at a significant rate. The technical maturity and operational capabilities of electric GSE on the
market allows for higher penetration than has been implemented at SDIA. The most recent electric GSE
charging port was installed at SDIA in 2013. SDG&E’s proposed project removes the barriers of
construction and electric GSE charger procurement from multiple airport tenants that operate at SDIA.
In Phase 1 of this PRP, SDG&E will install, own, operate, and maintain 16 charging ports and the
necessary equipment to efficiently integrate to the grid at the SDIA for American Airlines. These existing
charger retrofits will allow for the introduction of new features such as data collection and more
efficient charging. Load research meters were installed for each bank of chargers, although there is
some uncertainty regarding the reliability of the devices and their ability to communicate effectively
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 55
since they are on the restricted airside of the facility, so these meters will rely on EVSE provider
(Webasto) for charging session data.
Table 13. Banks of chargers at SDIA for SDG&E Airport GSE PRP
Terminal 2 Location Configuration Ports
Between gates 33 and 23 3 dual-port chargers 6
Between gates 23 and 25 3 dual-port chargers 6
Between gates 35 and 34 2 dual-port chargers 4
Timeline and Status
At the PAC meeting on September 25, 2018, SDG&E shared the anticipated timeline shown in Figure 27.
At this time, SDG&E had secured buy-in from American Airlines to retrofit existing equipment, and most
of the drawings for the planned work were submitted to the airport for review.
Figure 27. SDG&E Airport Ground Support Equipment PRP timeline as of September 2018
Source: SDG&E Q3 2018 PAC meeting
It took several months to work through contractual concerns over ownership (SDG&E owns the EV
chargers) and liability. Unfortunately, that process delayed the potential start of construction until June,
when SDIA and American Airlines entered a busy time of the year. Construction began in September
2019, and the charging stations were energized and commissioned in November 2019. The six months of
data collection and analysis on these 16 retrofitted chargers is expected to conclude in May 2020. This
will allow the results from Phase 1 of this project to be included in the final evaluation report.
Depending on the timing of the filing and approval of the Tier 2 advice letter that is required before
Phase 2 can commence (installation of up to additional 45 new charging stations), it is very unlikely that
there will be any results from Phase 2 included in the final evaluation report.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 56
Figure 28. SDG&E Airport Ground Support Equipment PRP timeline as of December 2019
Source: SDG&E
2.3.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP.
• Were opportunities to better manage charging identified, how were they implemented, and
were they effective?
• What integration with the SDIA solar array and any battery storage was done, and what impact
did that have on the electrical grid?
• What is the appropriate ratio of charging ports to electric GSE?
The data collection sources utilized to evaluate this PRP include 1) PRP information from the approved
decision, project updates, and other available documentation, 2) market research on ground support
equipment and early deployment efforts from other similar electrification projects across the country,
3) PRP data from vehicle and charger operations, and 4) IDIs with project partners.
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: the PRP kick-
off meeting (SDG&E and evaluator), quarterly PAC update meetings, weekly PRP updates (SDG&E and
evaluator), site visits, and other periodic calls or emails. SDG&E has provided some project costs to date
and basic charging station specifications. The evaluation team has not yet received but is expecting to
soon get the following information from this PRP: more details on charging station hardware
characteristics, electricity tariff details, site pictures before and after installation, project costs, list of
equipment using the charging stations, construction site plans and designs, and historical use of similar
conventional equipment.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 57
The following sources for market research have been identified:
National Renewable Energy Laboratory: Electric Ground Support Equipment at Airports (2017)
International Energy Agency’s Energy Technology Systems Analysis Program: Aviation
Infrastructure (2011)
U.S. Department of Energy: Cost Benefit Analysis Modeling Tool for Electric vs. ICE Airport
Ground Support Equipment - Development and Results (2007)
National Renewable Energy Laboratory and Oak Ridge National Laboratory: Athena project at
DFW airport (ongoing)
The Webasto charging stations collect session data to track utilization using cloud-based access to the
charger data. SDG&E will be collecting PRP operational data from onsite electricity data loggers,
provided the connectivity is sufficient on the airside of the terminal to transmit the data. Electricity costs
will be simulated based on the data logger data since these charging stations are not on a separate
SDG&E service. SDIA has a single SDG&E meter, and the chargers and the supporting infrastructure are
installed behind that meter. It is expected that the project participants will provide high-level data on
electric GSE utilization and maintenance, along with any necessary maintenance on the charging
stations.
The evaluator held IDIs with representatives from the SDG&E PRP management team and construction
staff to further understand the background on this project and gather lessons learned based on progress
to date. Additional IDIs with the SDG&E staff, SDIA, airport tenants, and vendors are planned in 2020 as
chargers begin to be utilized.
2.3.3 Evaluation Findings
Project Baseline
The electrification of GSE is an especially attractive option for airports across the globe. Electrified GSE
offers fuel security to airports that are already vulnerable to the price volatility of petroleum, as well as
lower maintenance costs and better performance. The number of airports electrifying GSE has been
increasing over the last decade. In 2016, 22 major airports had major electrified GSE projects in place.17
More recently, John F. Kennedy International Airport and Jet Blue have installed 118 charging ports for
the baggage tugs and belt loaders that have been electrified.18 The availability of GSE is also improving:
as of 2017, there were eight manufacturers providing various electrified GSE for airport applications.
According to the Global Airport Ground Support Vehicles Market Forecast, the GSE market is anticipated
17 National Renewable Energy Laboratory, “Electric Ground Service Equipment at Airports,” NREL/FS-5400-70359,
December 2017, https://afdc.energy.gov/files/u/publication/egse_airports.pdf. 18 Business Wire, “Jet Blue Introduces Largest Electric Ground Service Equipment,” September 26, 2019,
https://www.businesswire.com/news/home/20190926005676/en/JetBlue-Introduces-Largest-Electric-Ground-
Service-Equipment.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 58
to grow over 7% between 2019 and 2024. This report states electrified GSE will play a key role during
this growth period, particularly for baggage tugs and tractors.19
Figure 29. SDIA airside GSE charging – preliminary infrastructure inventory (November 8, 2016)
Source: San Diego International Airport
Implementation Process
SDG&E has encountered challenges in the PRP due to restrictions on how much access and control
SDG&E has on the airside of the terminal. This was anticipated but continues to create occasional
challenges when issues arise. This factor will restrict SDIA participation in the SDG&E Medium- and
Heavy-Duty SRP, and therefore the Phase 1 results are important to determining whether Phase 2 will
be considered under this PRP. The goal for Phase 1 is to utilize the collected charging session data and
develop a business case for GSE electrification. A positive business case result would be the best
justification to promote electrification to other tenants at this airport and elsewhere.
19 Business Wire, “Global Airport Ground Support Vehicles Market, Forecast to 2024,” December 2, 2019,
http://www.digitaljournal.com/pr/4523881#ixzz68g8F6FSQ.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 59
After the new chargers were installed, the airport did not immediately remove the outlets that were
previously used for charging. This ended up being very helpful when one of the charging stations was
damaged by GSE. Other SDG&E installed chargers remain operational while one is undergoing repairs.
Lesson Learned: Many initial EV deployments do not include redundancy in charging equipment, but this can be key to project success because the vehicles rely on functioning chargers for continued operation. It is very important to factor in charging redundancy for electrification deployments to ensure resilience.
SDG&E has experienced some challenges with acquiring data on these chargers because they are
located on the airside of the SDIA terminal where access is very restricted. For projects that require data
collection, SDG&E now realizes that some sort of enforcement is needed to ensure data flows. It is also
important to select technology with an established remote data access (ideally through a variety of
communication means in case circumstances, such as limited cellular reception, render one approach
infeasible).
SDIA inspectors were always available during construction and were helpful in addressing questions
regarding special construction manuals and standards that needed to be met (a requirement that was
not discussed during the planning and design review). The delays were encountered when SDIA project
manager input and approvals were required; every issue needed to be documented in detail and
required confirmation that it had been addressed.
Costs
The approved PRP had an anticipated total direct cost of $2,839,738, consisting of $2,405,598 in capital
and $434,140 in expense, as shown in Table 14.
Table 14. SDG&E Airport Ground Support PRP proposed costs
Capital Costs O&M Expenses Total PRP Costs
Transformer and Install N/A N/A N/A
Electrical Service $ 912,333 N/A $ 912,333
EVSE Costs $ 1,493,265 $ 22,140 $ 1,515,405
Purchased and SD Software N/A N/A N/A
Measurement and Evaluation N/A $ 200,000 $ 200,000
Billing Support N/A $ 80,000 $ 80,000
SDG&E Clean Transportation PM N/A $ 100,000 $ 100,000
First-Year O&M Service Calls N/A $ 22,000 $ 22,000
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 60
Capital Costs O&M Expenses Total PRP Costs
First-Year O&M for Charging Equipment N/A $ 10,000 $ 10,000
Total Costs $ 2,405,598 $ 434,140 $ 2,839,738
The PRP direct costs as of September 30, 2019, totaled $580,238 out of the budgeted $2,839,738, as
shown in Table 15 (presented in categories reported by the utility).
Table 15. SDG&E Airport Ground Support PRP costs as of September 30, 2019
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Construction $ 1,101,258
Engineering Design $ 52,712 $ 89,100
Chargers, Meter Pedestals, Transformer, and Other Materials
$ 200,513 $ 1,215,240
Internal SDG&E Labor (Program Management and Support)
$ 14,783 $ 85,328 $ 380,000
IT Costs $ 116,629
Other $ 110,262 $ 12 $ 54,140
Direct Costs $ 494,898 $ 2,405,598 $ 85,340 $ 434,140
Non-Direct Costs (Indirect, AFUDC, and Property Taxes)
$ 62,681 $ 1,098,365 $ 88,512 $ 191,676
Total Costs $ 557,579 $ 3,503,962 $ 173,851 $ 625,816
Benefits
The planned/anticipated benefits in Table 16 reflect the PRP’s Phase 2 benefits resulting from the
electrification of 90 airport GSE (17 belt loaders, 47 baggage tractors, 9 forklifts, and 17 push back tugs)
due to the installation of 45 new charging stations. The 16 retrofitted charging stations in Phase 1 are
only upgrading existing chargers that support current electric GSE so no additional benefits are expected
unless new chargers enable increased utilization. Phase 1 is collecting and analyzing data from existing
operations for a better understanding of the impact of electric GSE adoption – no suggested
modifications in behavior are expected unless SDG&E identifies opportunities for SDIA to improve
charging management.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 61
Table 16. SDG&E Airport Ground Support PRP benefits
Anticipated in Testimony
(45 chargers for 90 eGSE)
Anticipated as Planned
(Phase 1 – 32 existing eGSE)
As Implemented As Optimized
Petroleum Reduction
281,000 GGE per year
None TBD TBD
GHG Emissions 1,174 MT of CO2 per year
None TBD TBD
Criteria Pollutants
7.33 MT of NOx per year; 3.57 MT of VOC per year
None TBD TBD
DAC Impact SDIA (100% of this PRP) is adjacent to DACs
SDIA (100% of this PRP) is adjacent to DACs
TBD TBD
Operations, Maintenance, and Fuel Costs
4,164 MWh of electricity per year
1,481 MWh of electricity per year
TBD TBD
Other Co-Benefits
Improved net load factor (if charging is properly managed)
Improved net load factor
TBD TBD
Operational Impacts of Project Equipment
No significant electric GSE operations with the retrofitted chargers under this PRP were completed as of
this interim report. This section will be completed for the final report utilizing all information and data
obtained before November 2020.
Stakeholder and Customer Feedback
No significant electric GSE operations with the retrofitted chargers under this PRP were completed as of
this interim report, so this feedback has not been captured. Feedback pertaining to the initial
implementation of this PRP is captured in Implementation Process section of the Evaluation
Methodology. This section will be completed for the final report utilizing all information and data
obtained before November 2020.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 62
2.3.4 Conclusions and Recommendations
Findings
Without significant electric GSE operations with the retrofitted chargers to date, it is too early to
determine this PRP’s success, which will be documented in the final report. However, the following are
some preliminary findings, in addition to the lessons learned shared previously:
Airside equipment installations have restricted access that can have an impact on the ability to
make repairs or troubleshoot issues. It is critical to have reliable equipment.
Ownership and liability concerns arose with the airport, potentially due to the complicated
relationship with a separate owner (SDIA) and operator (American Airlines).
Many initial EV deployments do not include redundancy in charging equipment, but this can be
key to project success because the vehicles rely on functioning chargers for continued
operation. It is very important to factor in charging redundancy for electrification deployments
to ensure resilience.
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
2.4 Port Electrification
2.4.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
Consumption, charging, and operational data for MD/HD EVs or electric forklifts are currently
insufficient for utilities to determine how to efficiently integrate this type of charging into the electric
grid. There are some existing and grant-funded deployments of these transportation electrification
technologies within the San Diego Unified Port District (“Port District”) tidelands, but none have load
research meters that allow utilities to analyze how grid integration for the MD/HD and forklift EV market
segment can be implemented and optimized.
SDG&E proposed to install, operate, maintain, and own EV charging infrastructure, load research
meters, and data loggers for 30–40 installations within the Port District tidelands. The original intent was
that each charging infrastructure installation supporting grant-funded MD/HD EVs or electric forklifts
could include a combination of some or all of the funded components.
The primary goal of this project is to obtain a consumption, charging, and operational dataset to
facilitate development of an optimized grid integration solution for electrification of MD/HD vehicle and
forklift applications. Load research meters will collect consumption and charging data to evaluate energy
consumption relative to time and demand. Data loggers will provide operational data such as operation-
specific and EV-specific charging patterns. This information will aid in determining how to optimize grid
integration, as well as electric fuel economy, to determine optimal vehicle energy storage size and EVSE
power level.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 63
Sites and Participants
Recruitment Process
In conjunction with filing the application, SDG&E provided support and technical expertise to the Port of
San Diego and the San Diego Port Tenants Association for several transportation electrification grant
applications that would benefit various port tenants. Upon approval of this Port Electrification PRP,
SDG&E targeted the tenants, including locally owned and minority-owned businesses, that would be
recipients of grant-funded MD/HD vehicles and electric forklifts, to provide charging infrastructure
support. Additionally, SDG&E conducted outreach through various channels, including presentations at
the Port of San Diego maritime meetings, San Diego Port Tenant Association board meeting and funding
presentations, and the Regional Energy Working Group. The smaller tenants were much more hesitant
to try new technologies, and it was difficult for them to understand the economics of electrification
(costs, rates, etc.). Interest is starting to grow among the port tenants now that they see what the PRP
participants have done and learned from their experience.
Ten port tenants applied to participate in the program. While SDG&E had a targeted list of port tenants
who were designated as recipients of grant-funded vehicles, timing was an issue. A total of 20% of the
tenants received their vehicles prior to PRP approval and chose to install the infrastructure on their own
(they were content with a simpler and more temporary charging solution for the duration of the grant,
which was typically one year, rather than signing a contract to commit to the infrastructure for five
years). Another 20% of the tenants chose to install the infrastructure outside of Port Tidelands, making
them ineligible for the program. The biggest obstacle was negotiating with the customers on signing an
easement/license agreement, resulting in 30% of customers opting out of the program. There is
additional complexity for all the customers because they are tenants of the port and therefore do not
have jurisdiction of the land.
Lesson Learned: Construction projects at the port can be very challenging and costly. Concrete can be several feet deep, which complicates trenching, so it was essential to identify sites that required minimal or no trenching to align with the approved budget. The estimates also failed to account for environmental costs, which for one potential project was forecasted to be around $150,000 owing to the hazardous risk of the site; the cost precluded the site from participating in the PRP.
Participants
This PRP was conducted with Port District tenants. SDG&E has pursued installations with four
participants: Port of San Diego Cruise Ship Terminal, Pasha Automotive (Pasha), Dole Foods, and Four
Seasons. The Port of San Diego Cruise Ship Terminal and Pasha were onboard early in the PRP because
they already had plans underway to install charging infrastructure and either had, or had already
ordered, electric equipment/vehicles.
The Port of San Diego B Street Cruise Ship Terminal (Metro Cruise) uses forklifts that transfer food and
goods on and off cruise ships docked at the terminal. Metro Cruise had previously acquired the nine
electric forklifts. These were charged by regular building electrical outlets, which provided no capability
to monitor or optimize the charging behavior. Webasto (formerly AeroVironment) PosiCharge ProCoreTM
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 64
10 kW chargers were installed by SDG&E under this PRP. Metro Cruise also has five smaller electric carts
(jack pallets), which have their own chargers, but these did not qualify for the SDG&E PRP and were
installed separately by Metro Cruise.
Figure 30. Metro Cruise Webasto chargers and electric forklift
Source: Port of San Diego
Pasha, which imports over 400,000 vehicles annually, transfers new vehicles between the Port District,
where they are arrive on a ship, to a satellite storage location in Otay Mesa, California. Pasha acquired
two BYD electric drayage trucks and one BYD electric yard tractor through a California Energy
Commission (CEC) grant. Through the CEC project, Carbon BLU instrumented the three trucks with
dataloggers to report on utilization. The vehicles require proprietary BYD chargers. Three different
chargers were installed (power levels of 40, 80, and 100 kW) because the drayage trucks are different
generations of designs and the yard tractor has a different charger (100 kW) because of its very different
duty cycle. Pasha has used several small electric forklifts, but these BYD trucks are the company’s first
real EVs.
Dole Food Co. (Dole) is one of the Port District’s largest tenants, bringing in approximately 50,000
refrigerated containers a year. Dole was conducting a year-long test of two Transpower demonstration
electric trucks for its operations to determine how they work, and the company was considering
purchasing 30 electric trucks if the test was successful. During this demonstration, Dole used only
temporary chargers for the vehicles, and after a few months in operation, the vehicles were returned to
Transpower because the cost to retain the vehicles was higher than Dole was willing to invest. Dole also
received two electric yard tractors from BYD in August 2018 for a 12-month demonstration project. The
tractors were equipped with a 217 kWh battery pack powering a 180 kW motor, which delivers
1,106 lb-ft (1,500 N·m) of torque for 10+ hours of operation. Uncertain electrification plans beyond the
CEC demonstration projects, both of which were short-term, and challenges associated with addressing
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 65
the legal risk factors stalled the negotiation process with SDG&E, resulting in Dole’s being unable to
participate in this PRP. Four Seasons (for which Dole would also be the customer of record) conducts
similar activity at the Port District and was also looking to pilot one Transpower electric truck. After
several months of discussions, Four Seasons was unable to sign a contract for reasons similar to Dole’s.
Timeline and Status
In September 2018, following the program’s initial recruitment efforts, three customers were enrolled. A
contract was signed for the Cruise Ship Terminal installation, and preliminary installation designs were
sent to Dole and Pasha. Based on these milestones, SDG&E shared the anticipated schedule in Figure 31
at the quarterly PAC meeting.
Figure 31. SDG&E Port Electrification PRP timeline as of September 2018
Source: SDG&E Q3 2018 PAC meeting
The installation at the Cruise Ship Terminal was completed by the end of 2018, but the chargers were
not commissioned until March 4, 2019, when they started to be used in regular operations. The Pasha
installation was completed in January 2019 (there were some weather delays) and commissioned on
March 15, 2019. Negotiations and contract execution ended with Dole in November 2019 without
pursuing an installation. Contract discussions with Four Seasons, who expressed interest in the program,
progressed did not result in a contract. The EVs and EVSE at the Cruise Ship Terminal and Pasha have
been generating operational data, with Pasha’s truck usage limited because of operational challenges
and a technical issue with one of the vehicles. It is expected that 12 months of normal operating data
will be collected from those locations for the final evaluation.
Lesson Learned: Evaluating in-use performance of EVs in a new application for 12 months will most likely produce less than 12 months of operational data because of unexpected issues. Early commercial vehicle deployments tend to experience reliability issues, resulting in vehicle downtime to facilitate repairs. Deploying all of the EVs in regular operation can take from a couple of weeks to several months, as the fleet needs to adapt driving and charging operations to accommodate EVs.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 66
Figure 32. SDG&E Port Electrification PRP timeline as of December 2019
Source: SDG&E
2.4.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP.
• Did some EVs, equipment, or charging equipment perform better than others?
• Would similar supporting electrical infrastructure at other locations in the Port District be more
expensive? Is there a limit to the available power?
• Could these electrification efforts be economically feasible without the grants for the vehicles/
equipment and SDG&E support?
• Were opportunities to better manage charging identified? If so, were they implemented, and
were they effective?
The data collection tasks utilized to evaluate this PRP include 1) PRP information from the approved
decision, project updates, site visits, and other available documentation, 2) market research on port
vehicles and early deployment efforts from other similar electrification projects across the country,
3) PRP data from vehicle and charger operations, 4) IDIs with project partners, and 5) surveys with
vehicle drivers.
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: the PRP kick-
off meeting (SDG&E and evaluator), quarterly PAC update meetings, weekly PRP updates (SDG&E and
evaluator), site visits, and other periodic calls or emails. Currently the evaluation team has the following
information from this PRP: charging station hardware specifications, electricity tariff details, some site
photos after installation, project costs, and some high-level information on the acquired vehicles and
intended use. Over the next few months the evaluator expects to receive more details on several items
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 67
mentioned where only high-level information was provided, construction site plans and designs, and
some historical operation of the conventional-fueled vehicles used previously.
The following sources for market research have been identified:
CARB: Zero- and Near Zero-Emission Freight Facilities Project Methodology for Determining
Emission Reductions and Cost-Effectiveness (2018)
Business Wire: Commercial Vehicle Electrification, 2019: To Charge or Not to Charge (2019)
CEC and CARB demonstration project reports on Transpower and BYD electric yard trucks are
also expected to be published in 2020.
SDG&E will be providing PRP operational data from its utility service meters (one utility meter at each
deployment site for all charging stations at that site) for 15-minute interval data and monthly costs.
Metro Cruise charging station session data (not 15-minute interval data) is retrieved manually (via
Bluetooth) by SDG&E during periodic site visits while Webasto is developing a remote, cloud-based data
access. Pasha’s BYD chargers do not have the capability to track session data, but data logging of the
vehicles (which will include charging information) is conducted for the CEC grant. Unfortunately, this is
facilitated by a third-party vendor that will be sharing a complete set of data after the completion of the
12-month demonstration. While the vendor manually downloads the data from vehicle dataloggers,
additional post-processing is required to translate the data into a format usable for analysis. It is
expected that the project participants will provide high-level data on vehicle utilization and
maintenance, along with any necessary maintenance on the charging stations.
The evaluator held four separate IDIs as of writing this report with representatives from the SDG&E PRP
management team, SDG&E construction staff, Port District, and Pasha to further understand the
background on this project and gather lessons learned based on progress to date. An initial IDI with
Metro Cruise is expected early in 2020, with additional IDIs with the SDG&E staff, Port District, Pasha,
Metro Cruise, and vendors planned for mid-2020 to discuss the data findings and lessons learned
following several months of in-use operation. A survey or a facilitated focus group discussion with the EV
drivers is also planned to gauge operator satisfaction.
2.4.3 Evaluation Findings
Project Baseline
Pasha operates an 18-hour shift per day with its drayage trucks, while the use of the yard tractor
depends on the vessel(s) in port, which for some periods may require several eight-hour shifts in a row.
The first-generation BYD drayage truck has a smaller battery and can complete only one 42-mile round
trip to the storage facility before the truck needs to recharge for the second trip. The second-generation
BYD drayage truck can complete two of these 42-mile round trips and has been regularly used since it was
put in service at the end of Q3 2019. Pasha had similar-sized diesel vehicles operating in the fleet prior to
replacing them with electric trucks. The company is using this project to determine whether electric
models can meet operational requirements. Pasha recognizes that battery technology will need to
improve and vehicle acquisition costs decrease before electrifying the entire drayage truck operation,
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 68
which includes long-haul trucks that travel nationwide. However, this specific “shuttle” application is a
good starting point to test electric technology and work through some early adoption challenges.
Metro Cruise operates forklifts to serve loading and unloading needs of large cruise ships that dock at
the port. Several cruise ship operators have San Diego-based ships that will go on multi-day cruises and
return to San Diego, where they need to unload waste generated from the prior excursion and load
supplies for the next one. The loading and unloading requires several back-to-back eight-hour shifts over
the course of a few days, followed by several days before servicing the next ship. Metro Cruise was
operating propane forklifts to support these services prior to acquiring electric forklifts a couple of years
ago.
Implementation Process
SDG&E and participants for this PRP were able to use some strategic contracting strategies to simplify
the process. SDG&E used participation (licensing) agreements rather than easements to expedite the
contracting process, which was modeled after SDG&E’s Power Your Drive Program. The Port District was
also able to execute a simplified contract that did not have as many requirements because three
agreement is for less than five years (it would have otherwise needed to follow a more complicated
process with additional approvals). Had this project been a longer-term project, that would have
complicated the contracting process further. However, even despite these simplified contracting
processes, certain clauses in the agreement sparked controversy and needed to be discussed before
execution. This included indemnity and risk, particularly what happens to the equipment after five years
and who gets the environmental credits. These clauses delayed contract execution for six months, but
they are necessary in these agreements. There do not seem to be any clear regulatory requirements for
what happens to project equipment after five years, so the terms must be discussed after the initial
agreement is signed. In many cases, the EVs supported by charging infrastructure funded under this PRP
are part of a first-time customer trial, and the customers are uncertain of their future electrification
plans and charging needs.
The PRP participants, both Pasha and the Port District, appreciated SDG&E’s taking a lead on these
projects. Both participants had experience with similar efforts that required coordinating with
contractors and the utility, and both stated that SDG&E made the installation process relatively smooth.
The PRP participants noted that SDG&E’s communication regarding the construction and installation
was very good and resulted in minimal impact on terminal operations.
Design specifics can be complicated for certain locations and customers that have complex management
structures or approval chains. Trenching is a particular concern for projects at the port because of the
thickness of the concrete, which makes construction more difficult and costly. In addition, construction
could involve digging up hazardous materials, which would require costly mitigation strategies.
Installations that do not require trenching are ideal and significantly lower cost. For example, the Metro
Cruise installation needed only duct work (bollards needed to be anchored to the pavement), no
trenching, so that made the work much easier. Initially, an option was considered to provide service
from a higher electrical capacity transformer that would require trenching; however, it was determined
that the existing electrical service could meet the charging station needs. These projects can serve as a
model for others to replicate and have provided valuable experience for SDG&E. However, based on the
two implemented projects and several others that were considered for this PRP, every charging station
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 69
installation will have unique aspects that will require custom design and construction to some extent.
Despite that, SDG&E will continue to improve its design and construction approach based on these
experiences.
For Pasha’s project, while the availability of electric Class 8 trucks is limited, the CEC grant further
restricted the selection of electric truck manufacturers to BYD and Transpower. The PRP does not
provide funding for EVs, but they are a requirement for customers to participate in the projects, so often
grant funding is used to acquire the vehicles. While the manufacturers consider these EVs commercial
models, they are often very early in production, and customers often consider them to be
demonstration vehicles since they have not been deployed in significant numbers and are likely to
experience some operational issues. The BYD electric trucks came with their own proprietary charger
(which differed based on the version of the truck and date acquired), so Pasha did not have a choice;
however, it is advantageous to use the same manufacturer for the vehicle and charger to minimize
potential interoperability issues (and have one manufacturer to contact when issues arise). Pasha’s BYD
chargers were installed next to the transformers to minimize the necessary trenching. Once the
equipment was installed, the customer discovered that the chargers were facing away from the vehicles.
It was also determined that longer charging cables were needed to reach charging receptacles on the
trucks.
If SDG&E had been allowed to proceed with the company’s interpretation of the approved PRP scope
(fund and collect information from data loggers and research load meters without installing new
charging infrastructure), the PRP could have monitored the demonstration vehicles at Dole (and possibly
other Port District tenants that received EVs under the CEC grant) and gathered more EV charging and
utilization data. However, because of the CPUC’s interpretation of the Decision, dataloggers and
research grade load meters could only be used alongside charging stations installed under this PRP.
Costs
The approved PRP had an anticipated total direct cost of $2,405,575, consisting of $1,840,575 in capital
and $565,000 in expense, as shown in Table 17.
Table 17. SDG&E Port Electrification PRP proposed costs
Capital Costs O&M Expenses Total PRP Costs
Transformer and Install N/A N/A N/A $
Electrical Service $ 849,570 N/A $ 849,570
EVSE Costs $ 991,005 N/A $ 991,005
Purchased and SD Software N/A N/A N/A
Measurement and Evaluation N/A $ 150,000 $ 150,000
Education and Outreach N/A $ 110,000 $ 110,000
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 70
Capital Costs O&M Expenses Total PRP Costs
Billing Support N/A $ 80,000 $ 80,000
SDG&E Clean Transportation PM N/A $ 200,000 $ 200,000
First-Year O&M Service Calls N/A $ 15,000 $ 15,000
First-Year O&M for Charging Equipment N/A $ 10,000 $ 10,000
$ 1,840,575 $ 565,000 $ 2,405,575
Little to no costs were associated with design, engineering, and permitting. SDG&E had originally
estimated these costs would be less than $10,000 per site (some estimates did not even account for any
additional costs for this). SDG&E is finding that the actual design, engineering, and permitting costs
average about $30,000 per site.
The PRP direct costs as of September 30, 2019, totaled $811,311 out of the $2,501,798 budget, as
shown in Table 18, (presented in categories reported by the utility).
Table 18. SDG&E Port Electrification PRP costs as of September 30, 2019
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Construction $ 163,976 $ 966,045
Engineering Design $ 98,299
Chargers, Meter Pedestals, Transformer, and Other Materials
$ 270,659 $ 874,530
Internal SDG&E Labor (Program Management and Support)
$ 10,971 $ 94,041 $ 430,000
IT Costs $ 116,629
Customer Engagement and Outreach
$ 4,050 $ 110,000
Other $ 52,650 $ 35 $ 25,000
Direct Costs $ 713,185 $ 1,840,575 $ 98,126 $ 565,000
Non-Direct Costs (Indirect, AFUDC, and Property Taxes)
$ 326,353 $ 948,313 $ 97,912 $ 253,717
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 71
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Total Costs $ 1,039,538 $ 2,788,888 $ 196,038 $ 818,717
Pasha’s BYD chargers were paid for by the CEC grant, and SDG&E covered the installation costs. The CEC
grant for $900,000 covered the three vehicles and chargers.
Benefits
The planned/anticipated benefits in Table 19 were calculated based on 13 EVs (modeled as forklifts)
replacing diesel, gasoline, and propane vehicles. The final expected number of EVs supported by this
PRP’s charging infrastructure is 8 electric forklifts and 3 MD/HD electric trucks (leveraging calculation
factors used for fleet delivery vehicles).
Table 19. SDG&E Port Electrification PRP benefits
Anticipated in Testimony
(13 Forklifts)
Anticipated as Planned
(8 Forklifts and 8 MD/HD EVs)
As Implemented As Optimized
Petroleum Reduction
38,000 GGE per year 41,000 GGE per year N/A N/A
GHG Emissions 228 MT of CO2 per year
220 MT of CO2 per year
N/A N/A
Criteria Pollutants
1.00 MT of NOx per year; 0.49 MT of VOC per year
0.68 MT of NOx per year; 0.25 MT of VOC per year
N/A N/A
DAC Impact Majority of the Project is in a DAC
Both sites are in SDG&E DAC
N/A N/A
Operations, Maintenance, and Fuel Costs
344 MWh of electricity per year
474 MWh of electricity per year
N/A N/A
Other Co-Benefits
Improved net load factor (if charging is properly managed)
Improved net load factor
N/A N/A
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 72
Operational Impacts of Project Equipment
Initial operations data from Metro Cruise (Webasto charger manual session data retrievals and utility
bills) and Pasha (smart meter data and utility bills) provided some insight into operations, although the
periodic use of the EVs resulting from vehicle issues (Pasha) and off-season cruise schedules (Metro
Cruise) affected the amount of data available. In March and April (2019), each forklift charged between
20 and 24 times in this 61-day span, and the average energy transfer was 17.5 kWh. However, from May
through August (2019), the forklifts charged only 1 to 7 times each over a 123-day span. Most charging
events were shorter than one hour, as shown in Figure 33.
Figure 33. Histogram of Metro Cruise electric forklift charging durations
Source: SDG&E Metro Cruise charging session data
Utility bills for Metro Cruise and Pasha revealed very high costs per kilowatt-hour delivered to the EVs
during months with very low utilization. The chargers are designed to accommodate high utilization of
these vehicles by providing shorter charging times, but this often results in high demand costs. Even
during low utilization periods, when a faster charge is likely unnecessary, the equipment was still
drawing the maximum charge level and triggering high demand costs. More frequent charging will result
in more electricity usage without any additional demand charges and lower the overall cost per kilowatt-
hour. However, until that occurs, and even to accommodate periods of low utilization, charge
management or alternative electricity rates could help reduce consumer costs (which were too high to
justify the conversion to electricity during these months). Operational behaviors, such as limitations as
to when the vehicles are plugged in (which for some Port District tenants with union labor might be the
responsibility of someone other than drivers) can also affect the cost effectiveness of electrification.
Such operations rarely account for higher on-peak costs for electricity or accommodate the staggering of
charging across a longer period.
Additional analysis and the tracking of these initial trends over time will be completed for the final
report utilizing all information and data obtained before November 2020.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 73
Stakeholder and Customer Feedback
Feedback on the electric forklift and MD/HD vehicle operations will not be captured until later in the
project. Feedback pertaining to the initial implementation of this PRP is captured in the Implementation
Process section of the Evaluation Methodology. This section will be completed for the final report
utilizing all information and data obtained before November 2020.
2.4.4 Conclusions and Recommendations
Findings
Without significant forklift and vehicle operations to date, it is too early to determine this PRP’s success,
which will be documented in the final report. However, some preliminary findings, in addition to the
lessons learned shared previously, are mentioned below:
Charging infrastructure for nine forklift chargers and three BYD electric trucks was successfully
installed, at two separate locations within the Port District, which has provided SDG&E
additional experience in installing EV charging, along with more accurate cost information. This
experience will help SDG&E to support future electrification of Port District tenants.
Port operations and tenant locations regularly change to accommodate consumer trends and
the always-changing import/export businesses. This concerned several port tenants that were
uncomfortable committing to the program requirements, and even one of the participants,
Pasha, needs to relocate the chargers (at the company’s cost) because of tenant changes.
Several port tenants park vehicles overnight at their off-site location because of space
constraints at the port. Since the PRP requirement was to install charging stations within the
port tidelands, these tenants were unable to participate. Even if they could accommodate
parking the vehicles at the port to charge overnight, drivers might have to be shuttled back to
the warehouse at shift end (to retrieve their personal vehicles).
Third-party onboard vehicle data loggers would be ideal for independently monitoring vehicle
performance, but they were cost-prohibitive. Instead, the project will rely on the fleets to
provide vehicle performance data through other means such as vehicle maintenance records
and third-party dataloggers collecting data for other grant reporting purposes.
Construction projects at the port can be very challenging and costly. Concrete can be several
feet deep which complicates trenching. While this was not the sole disqualifying factor for
participation in the PRP, it is essential to identify sites that required minimal or no trenching to
align with the approved budget. The estimates also failed to account for environmental costs,
which for one potential project was forecasted to be around $150,000 owing to the hazardous
risk of the site; the cost precluded the site from participating in the PRP.
Evaluating in-use performance of EVs in a new application for 12 months will most likely
produce less than 12 months of operational data because of unexpected issues. Early
commercial vehicle deployments tend to experience reliability issues, resulting in vehicle
downtime to facilitate repairs. Deploying all of the EVs in regular operation can take from a
couple of weeks to several months, as the fleet needs to adapt driving and charging operations
to accommodate EVs.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 74
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
2.5 Electrify Local Highways
2.5.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
The 2016 Governor’s ZEV Action Plan tasked California’s Department of Transportation (“Caltrans”) with
installing DCFCs at some of its locations throughout the state, and Caltrans’ 2016 Sustainability
Implementation Action Plan prioritized the installation of EV charging stations on Caltrans-owned park-
and-ride facilities.
According to testimony in SDG&E’s application for approval of SB 350 Transportation Electrification
Proposals, at one of the first installations of EV charging stations at a park-and-ride facility, Caltrans
found that (1) drivers often park their cars for up to 11 hours at a time while they take mass transit or
carpool to continue their trips, and (2) the DCFCs provide charging for approximately five cars per day.
From this, Caltrans recognizes that the park-and-ride locations are good for both long-duration parking
and charging, as well as quick stops for DCFC use. However, the Department does not want to be in the
business of owning, operating, and maintaining EV charging stations; a third-party end-to-end solution
could be the best option for providing a positive customer experience.
SDG&E testimony also states that Caltrans has expressed concerns that the Department does not
currently have the resources to take on this effort and that the Department has not been able to find
the right charging installation programs that would provide an end-to-end solution through a third
party, which could take on the installation, ownership, customer service, billing, maintenance, and
operations efforts altogether. Therefore, SDG&E proposed partnering with Caltrans for this PRP to
install, own, maintain, and operate L2 and DCFCs at four Caltrans-owned park-and-ride locations. As part
of this collaboration, Caltrans would provide land rights, parking spaces, and expertise to help
streamline the design, permitting, and installation efforts.
SDG&E will study charging patterns and share the usage data for modeling charging infrastructure at
these park-and-ride locations. SDG&E will also test hourly pricing in the public domain, as well as test
the standards for public charging signage, rate display, and general retail EV fuel dispensers. This will be
the first time that SDG&E will test how to easily communicate a time-of-use (TOU) rate to the public at a
charging station.
Sites and Participants
Recruitment Process
SDG&E worked closely with Caltrans during the application process for this PRP. Most of the sites were
identified prior to the application, and SDG&E collaborated with Caltrans on site design and permitting.
This PRP had a set charging station deployment goal with a specific partner and was not established as a
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 75
project that would recruit additional partners or solicit participation by small, locally owned, minority-
owned, and women-owned businesses.
Participants
Caltrans supports more than 60 park-and-ride locations in
the San Diego region and owns 33 of these locations. Of
the 33 state-owned park-and-ride locations, Caltrans
initially identified four locations for this project, each
located within or adjacent to a DAC:
Pala: Located across the freeway from a large
DAC at the northwest corner of the I-15 freeway
and Highway 76 in northeastern San Diego
county
Oceanside Transit Center: Located across the
street from a DAC at 235 South Tremont Street in
Oceanside (northwestern San Diego county)
National City: Located within a DAC at 2300
Sweetwater Road in National City (just south of
downtown San Diego)
Chula Vista: Located on Palomar Street within a
DAC off the I-805 freeway in Southern San Diego
county
The sites in National City and Chula Vista remained in the
project implementation plans, but Pala was replaced by a
park-and-ride at 13516 Camino Canada in El Cajon off I-8, and the Oceanside location was moved from
the Transit Center to a nearby park-and-ride at 1928 South Moreno Street off I-5. Each of these park-
and-ride sites are located along major freeways within SDG&E’s territory, as well as within or adjacent to
DACs.
ChargePoint was selected to provide the EVSE and the network services following the completion of
DCFC meter testing requirements. Twenty 7.2 kW L2 stations and two 62.5 kW DCFCs (compatible with
the CHAdeMO and Combined Charging System [“CCS”] standards) will be installed at each site. SDG&E is
working with skilled contractors (affiliated with the International Brotherhood of Electrical Workers) for
the installation and maintenance of the charging equipment.
Timeline and Status
The anticipated PRP installation schedule shown in Figure 35 was presented at the quarterly PAC
meeting in September 2018. SDG&E had completed the initial designs for each selected site and
preliminarily selected a vendor to supply the EVSE and network services.
Source: SDG&E Q3 2018 PAC meeting
Figure 34. SDG&E Electrify Local Highways installation sites
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 76
Figure 35. SDG&E Electrify Local Highways PRP timeline as of September 2018
Source: SDG&E Q3 2018 PAC meeting
The project was then delayed for various reasons, and construction did not begin until November 2019.
SDG&E had to perform penetration (security) and meter testing on the DCFCs to ensure they would
meet requirements, and a contract was executed with ChargePoint in April 2019. The longest delay was
contracting land rights with Caltrans, which required involvement of several internal departments.
During the process, Caltrans brought up questions about the site designs, with specific concerns about
complexities and potential disruption to operations. Securing the necessary permits was also more
complicated than anticipated, particularly for the National City site, which required more extensive
trenching to bring power to the charger location. If the charging stations are energized and
commissioned by early Q1 2020 as expected (construction should be relatively straightforward), then at
least seven months of data should be available for analysis and inclusion in the final evaluation report.
Figure 36. SDG&E Electrify Local Highways PRP timeline as of December 2019
Source: SDG&E
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 77
2.5.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Public Access
Station PRPs, the evaluation questions listed below will be examined for this PRP.
• How do customers respond to TOU pricing?
• Given the high-occupancy vehicle (HOV) incentive for EVs, will EV drivers still be motivated to
come to the park and ride? SDG&E theorizes that many commuters use the park-and-ride lots to
gain HOV access.
• How does utilization compare between the L2 and DCFC?
• Is EV occupancy of the charger after being charged preventing others from accessing the
charging stations?
• Do some sites perform better than others, and if so, what was the reasoning behind the
difference?
The data collection sources utilized to evaluate this PRP include 1) PRP information from the approved
decision, project updates, site visits, and other available documentation, 2) market research on DCFCs
and early deployment efforts from other similar electrification projects across the country, 3) PRP data
from charger operations, 4) IDIs with project partners, and 5) surveys with vehicle drivers.
Data Sources
PRP insights have been collected through numerous PRP participant interactions: the PRP kick-off
meeting (SDG&E and evaluator), quarterly PAC update meetings, weekly PRP updates (SDG&E and
evaluator), site visits, and other periodic calls or emails. Since the construction on the four sites had not
yet commenced in November 2019, little information has been available for this PRP other than the
selected sites and charging station hardware specifications. In the first quarter of 2020, the evaluator
expects to receive more details on the station characteristics, construction site plans and designs,
electricity tariff details, some site photos before and after installation, and construction costs.
The following sources for market research have been identified:
SCE: Urban DCFC Clusters PRP
National Renewable Energy Laboratory/Idaho National Laboratory/Argonne National
Laboratory: Analysis of Fast Charging Station Network for Electrified Ride-Hailing Services (2018)
Idaho National Laboratory: What were the Cost Drivers for the Direct Current Fast Charging
Installations? (2015)
Idaho National Laboratory: Considerations for Corridor and Community DC Fast Charging
Complex System Design (2017)
Center for Sustainable Energy: California Air Resources Board Clean Vehicle Rebate Project,
Rebate Map (2019); VEIC’s Electric Vehicle DC Fast Charging on Vermont Highway
Corridors (2017)
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 78
SDG&E will be providing PRP operational data from its utility service meters (one utility meter at each
deployment site for all charging stations at that site) for 15-minute interval data and monthly costs,
while network service provider ChargePoint will send monthly CSV files with charging station session
data.
The evaluator will hold initial IDIs with representatives from the SDG&E PRP management team to
further understand the background on this project and gather lessons learned during the planning and
construction phases. Additional IDIs with the SDG&E construction staff, Caltrans, and vendors are
planned for 2020 after all four sites are commissioned. A survey of the EV drivers is also planned in
collaboration with SDG&E and ChargePoint to gauge customer satisfaction.
2.5.3 Evaluation Findings
Project Baseline
After the initial 2016 ZEV Vehicle Action Plan was announced, Governor Brown raised the bar and
increased the target number of ZEVs on the road and public EVSE across the state with the 2018 update.
Adding to the initial goal of 1.5 million ZEVs registered, the 2018 update sets an additional target of
5 million total ZEVs by 2030. This even more ambitious goal will likely require more public EVSE to be
brought online than the original target of 250,000 public stations by 2025. Of the total EVSE goal, at
least 10,000 are to be DCFC.20
Since 2016, ZEV sales have continued to increase. In 2018, ZEV sales reached about 8% of the total
market share, or about 410,000 vehicles. Early reporting for 2019 totals shows total ZEV registration up
to 655,000.21 To reach the 2030 vehicle goals, ZEV sales will need to reach 40% of the market share.
There were an estimated 18,000 public chargers (L2 and DCFC), averaging about 225 L2 stations installed
and 90 DCFCs installed per month. At the start of 2019, DCFCs made up about 15% of the total public
EVSE and were a quarter of the way to reaching the 2025 goal of 10,000 chargers.22
Implementation Process
Three of the four sites do not have any existing TE infrastructure. One site was recently constructed and
was built with TE make-ready by a contractor hired by CalTrans. This was done prior to the
commencement of this PRP. Unfortunately, the make-ready that was put in place was not sufficient to
meet the needs of the chargers and was not sufficiently protected from the elements after construction.
This make-ready will be replaced.
20 2018 Zev Action Plan Priorities Update, Governor’s Interagency Working Group on Zero-Emission Vehicles,
http://www.business.ca.gov/Portals/0/ZEV/2018-ZEV-Action-Plan-Priorities-Update.pdf. 21 EV Sales in California on the Rise, LA Times, https://www.latimes.com/business/story/2019-12-01/electric-
vehicle-sales-in-california-on-the-rise-but-is-it-enough-to-reach-the-5-million-goal-by-2030 22 CEC, ZEV Tracking Progress, https://www.energy.ca.gov/sites/default/files/2019-05/electric_vehicle.pdf
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 79
Lesson Learned: All make-ready infrastructure for future charging station installations should be upsized to account for larger power supplies and properly protected to ensure longevity.
Traffic control costs may be much higher than the $2,000 planned budget for the National City site if
open trenching is required. This site will also require paving and striping on a county road. This site also
had complications with the right-away permit. The National City site is unique as the construction is
planned in Caltrans, National City, and the San Diego County right-of-way (trenching across Sweetwater
road).
Costs
The approved PRP had an anticipated total direct cost of $4,000,000, consisting of $3,309,212 in capital
and $690,788 in expense, as shown in Table 20.
Table 20. SDG&E Electrify Local Highways PRP proposed costs
Capital Costs O&M Expenses Total PRP Costs
Transformer and Install $ 147,000 $ 3,316
$ 150,316 $ 150,316
Electrical Service $ 559,372 N/A $ 559,372
EVSE Costs $ 1,757,728 $ 32,472 $ 1,790,200
Purchased and SD Software $ 845,112 N/A $ 845,112
Customer Engagement N/A $ 200,000 $ 200,000
Measurement and Evaluation N/A $ 250,000 $ 250,000
Billing Support N/A $ 80,000 $ 80,000
SDG&E Clean Transportation PM N/A $ 100,000 $ 100,000
First-Year O&M Service Calls N/A $ 15,000 $ 15,000
First-Year O&M for Charging Equipment N/A $ 10,000 $ 10,000
$ 3,309,212 $ 690,788 $ 4,000,000
The PRP direct costs as of September 30, 2019, totaled $1,652,298 out of the budgeted $4,000,000, as
shown in Table 21, (presented in categories reported by the utility).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 80
Table 21. SDG&E Electrify Local Highways PRP costs as of September 30, 2019
Actual Capital Costs
Budgeted Capital Costs
Actual O&M Costs
Budgeted O&M Costs
Construction $ 1,285,097
Engineering Design $ 206,062 $ 134,600
Chargers, Meter Pedestals, Transformer, and Other Materials
$ 870,276 $ 1,044,403
Internal SDG&E Labor (Program Management and Support)
$ 10,666 $ 120,153 $ 430,000
IT Costs $ 408,202 $ 845,112
Customer Engagement and Outreach
$ 200,000
Other $ 36,833 $ 106 $ 60,788
Direct Costs $ 1,532,040 $ 3,309,212 $ 120,259 $ 690,788
Non-Direct Costs (Indirect, AFUDC, and Property Taxes)
$ 158,534 $ 1,720,132 $ 125,137 $ 246,693
Total Costs $ 1,690,573 $ 5,029,344 $ 245,396 $ 937,481
Benefits
SDG&E’s initial estimate of vehicle usage for each Caltrans site is one charge per day for L2 charging
stations (60% battery electric vehicles and 40% plug-in hybrid electric vehicles), and 5 charging sessions
per day for each of the DCFC stations (all battery electric vehicles), which is a total of 120 vehicles
charged per day among the four sites. The anticipated benefits from the testimony are identical to those
expected from the installations, as the same number of charging stations will be deployed.
Table 22. SDG&E Electrify Local Highways PRP benefits
Anticipated in Testimony
(120 charge events per day)
Anticipated as Planned
(120 charge events per day)
As Implemented As Optimized
Petroleum Reduction
23,000 GGE per year 23,000 GGE per year TBD TBD
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 81
Anticipated in Testimony
(120 charge events per day)
Anticipated as Planned
(120 charge events per day)
As Implemented As Optimized
GHG Emissions 155 MT of CO2 per year
155 MT of CO2 per year
TBD TBD
Criteria Pollutants
0.01 MT of NOx per year; 0.02 MT of VOC per year
0.01 MT of NOx per year; 0.02 MT of VOC per year
TBD TBD
DAC Impact 2 sites within a DAC and 2 sites adjacent to a DAC
2 sites within a DAC and 2 sites adjacent to a DAC
TBD TBD
Operations, Maintenance, and Fuel Costs
211 MWh of electricity per year
211 MWh of electricity per year
TBD TBD
Other Co-Benefits
Improved net load factor (if charging is properly managed)
Improved net load factor
TBD TBD
Operational Impacts of Project Equipment
No EVSE has been installed under this PRP as of this interim report. This section will be completed for
the final report utilizing all information and data obtained before November 2020.
Stakeholder and Customer Feedback
No EVSE has been installed under this PRP as of this interim report, so this feedback has not been
captured. Feedback pertaining to the initial implementation of this PRP is captured in the
Implementation Process section of the Evaluation Methodology. This section will be completed for the
final report utilizing all information and data obtained before November 2020.
2.5.4 Conclusions and Recommendations
Findings
With no EVSE installed to date, it is too early to determine this PRP’s success, which will be documented
in the final report.
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it would
be recommended cannot be determined at this time but will be included in the final report.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 82
2.6 Dealership Incentives
2.6.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
SDG&E’s Dealership Incentives PRP involves a turnkey program called PlugStar offered by Plug-In
America (PIA), an EV advocacy organization. The PRP goals23 are to (1) increase EV sales by up to 1,500
units, (2) provide dealerships within SDG&E’s territory the opportunity to participate (3), enroll 200
salespeople, (4) emphasize EV sales in DACs, (5) educate dealerships and their salespeople on EV
information and best EV sales practices, and (6) educate new EV owners to sign up for SDG&E’s
residential EV-TOU rate.
PlugStar works with new car dealerships and shoppers to incentivize EV sales (over an internal
combustion engine vehicle) by addressing these barriers:
Low retail satisfaction
o PlugStar improves the EV buying experience by (1) informing shoppers with a shopping
assistant website and (2) educating dealership staff on meeting the needs of EV buyers.
Poor salesperson knowledge of EVs
o PlugStar provides training for dealership staff and an EV sales tool. These trainings differ
from original equipment manufacturer (OEM) product trainings in that they address the
larger issues in the EV eco-system, such as charging.
Low commissions and profits ($150–$200) on EVs relative to extra work required
o A bonus of $500 per EV sold will be provided (split between dealership and trained
salesperson) at participating San Diego area dealerships. Sales by untrained staff at certified
dealerships result in an incentive of $125 for the dealership.
o Promotional events to drive EV sales will be held.
In 2019, the PlugStar program was offered in several markets (Los Angeles, St. Louis, New Jersey, San
Diego, Sacramento, and Boston). Only Sacramento and San Diego (this PRP) offered dealership
incentives; the others provided educational services only. SDG&E rolled out the PlugStar program as a
pilot from August 31, 2018, through January 31, 2019, with the full program incorporating lessons
learned and running through the end of 2019.
SDG&E selected PIA to implement the program through a competitive solicitation.
23 Barriers and goals taken from SDG&E’s application for approval of SB 350 Transportation Electrification
Proposals, accessed December 6, 2019,
https://www.sdge.com/sites/default/files/Direct%2520Testimony%2520Chapter%25203%2520-
%2520Priority%2520Review%2520Projects.pdf.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 83
Sites and Participants
The program manager, PIA, recruited dealerships, including several with whom PIA had existing
relationships. PIA also conducted outreach through trade associations, vehicle manufacturers, and other
channels. Five dealerships participated in the initial pilot, with 15 participating in the full-scale program.
PIA received 47 dealership applications for the SDG&E PlugStar Program. PIA went through a formal
selection process using these criteria: whether the dealer had EV inventory, onsite charging
infrastructure, and the dealer’s commitment to EVs. PIA accepted 15 dealers through the formal
selection process.
Recruiting dealerships near DACs was seen as desirable, but PIA noted in an interview that a more
comprehensive strategy for helping vehicle purchasers in DACs would be to also provide options to
purchase used vehicles, since many members of these communities have lower budgets and look to the
secondary market more often. PIA emphasized that the secondary market presented even greater
barriers for shoppers and would benefit from support in a future project; however, this PRP is focused
entirely on new EV sales.
Lesson Learned: Programs targeted to DACs will need to support secondary market transactions.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 84
Figure 37. Locations of participating PlugStar dealerships
* Indicated dealerships that participated in the initial pilot phase
Source: SDGE Q1 2019 PAC Meeting
Timeline and Status
CPUC Decision 18-01-02424 approved the SDG&E Dealership Incentives PRP in January 2018. In response
to concerns submitted by The Utility Reform Network (TURN), the CPUC modified SDG&E’s proposed
24 Public Utilities Commission of the State of California, Decision 18-01-024: “Decision on the Transportation
Electrification Priority Review Projects,” January 11, 2018,
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M204/K670/204670548.PDF
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 85
program by requiring the EV buyer/lessee to enroll in an EV-TOU rate before the dealership incentives
could be paid.
During the pilot phase, it became apparent that this program modification caused a delay in the
incentive processing and significantly reduced the number of claims paid (only 16% of claims were
approved). Some customers may be ineligible for EV-specific rates because they live in multi-unit
dwellings, and some may face higher costs on an EV-specific TOU rate than they would on other
available rates, such as California Alternate Rates for Energy or Family Electric Rate Assistance Program.
Because these and other similar factors are beyond the control of car dealers and salespeople, the
potential program participants did not feel adequately equipped to advise EV purchasers/lessees on
which utility rate would be most beneficial. PIA further commented that “the TOU requirement created
uncertainty around whether a dealer's effort would be rewarded, thereby reducing the impact of the
incentive. Moreover, due to the highly individualized nature of home energy use and costs, dealers are
not in a position to guarantee savings but rather must connect the customer with the utility to make
such a determination. Lastly, SDG&E, as well as utilities throughout the state, were already embarking
on shifting customers to TOU rates.”
Because of these limitations, SDG&E filed a Tier 2 advice letter25 in February 2019 to waive the
requirement that customers enroll in an EV-TOU rate before paying the dealership incentive. CPUC
issued Resolution E-5006 on August 1, 2019, approving this and a few other modifications, including a
modified customer release form for reaching out to purchasers/lessees for evaluation and education
follow-up. The modification was intended to emphasize to purchasers the need to contact SDG&E to
discuss whether an EV-TOU rate would be beneficial. Just as before the Tier 2 advice letter, SDG&E uses
the customer information to contact the purchaser to discuss electricity rates. Although the EV-TOU rate
waiver applied to purchases starting March 14, 2019, and after, the waiver was not formally approved
until release of Resolution E-5006. More than two-thirds of the program period had elapsed before this
issue was addressed.
In the resolution, CPUC stated concerns that this change to the PRP might not serve the interests of
ratepayers, as EV charging without enrollment in an EV-TOU rate “could cause adverse grid impacts and
ultimately increase peak load, resulting in additional ratepayer costs.” As such, the evaluation will
examine whether SDG&E is following up with vehicle purchasers to conduct education about EV-TOU
rates.
2.6.2 Evaluation Methodology
Selected Methods and Rationale
To determine the effectiveness of the PRP, the evaluation is currently procuring data about how the
program overcomes barriers to reach its goals. The evaluation will also examine other benefits of the
PRP and how SDG&E is educating and encouraging customers to choose EV-TOU rates.
25 Public Utilities Commission of the State of California, Advice Letter 3344-E, August 8, 2019, http://regarchive.sdge.com/tm2/pdf/3344-E.pdf.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 86
Data Sources
Data sources used in evaluation will include the following:
Interviews – One round of formal interviews with SDG&E program staff and PIA staff was
completed in 2019. The evaluation team will conduct a second round of interviews in 2020 after
the conclusion of the PRP. This next round of interviews will investigate additional research
questions such as the persistence of training impacts given sales staff turnover and how the
removal of the EV-TOU rate requirement affected claims after Resolution E-5006 was released in
August 2019.
Surveys – The evaluation team is working with PIA to develop surveys for dealership staff and EV
purchasers/lessees. Since PIA holds the relationship with these entities and has existing plans to
gather data on the PIA program in winter 2019–2020, the evaluation team is collaborating on
these data collection efforts to minimize the burden on customers and dealership participants.
o Dealership staff interviews will be conducted by PIA staff in person.
o Purchaser/lessee surveys will be conducted online with all customers who signed consent
forms at the time of their EV purchases.
Primary data – The evaluation team will obtain final data from PIA and SDG&E on program
activity after the PRP ends.
PlugStar.com use and traffic – PIA will provide the evaluation team with data on online activity.
Other – The evaluation team and PIA are in discussion with IHS Markit to purchase sales data
that would allow a market lift analysis comparing participating and non-participating dealership
EV sales.
2.6.3 Evaluation Findings
Claims
In 2019, there were two PlugStar programs that provided dealership incentives, one in Sacramento and
this PRP in San Diego. The program in Sacramento did not require customers to adopt an EV-TOU rate
for the dealership to receive the incentive. Furthermore, the incentive in Sacramento was $300,26 with
$200 of that going to the trained salesperson and $100 to the dealership (slightly lower than the San
Diego program, which provides $250 for the trained salesperson and $250 for the dealership). In both
programs, since January 2019, claims submitted by PlugStar dealerships for sales by untrained
salespeople receive only half the incentive amount. As a result of that policy, the percentage of claims
from trained salespeople (Figure 38 and Figure 39) rose dramatically starting in January 2019.
26 In September 2018, the Sacramento incentive was doubled ($600), which explains the high number of claims in
Sacramento for that month.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 87
Figure 38. Percent of claims submitted by trained salespeople – San Diego
Figure 39. Percent of claims submitted by trained salespeople – Sacramento
Figure 40 shows monthly PlugStar claims activity in Sacramento and San Diego (from PIA as of
December 6, 2019). Sacramento, despite being less than one half the size of the San Diego market and
having a smaller incentive, had nearly twice as many claims as San Diego; it remains to be seen whether
removing the EV-TOU rate requirement will change the trend for San Diego after August 2019, when the
resolution was released.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 88
Lesson Learned: The program in Sacramento was able to achieve greater total claims at lower incentive levels, likely because it did not have an EV-TOU requirement.
Figure 40. Comparison of PlugStar activity in Sacramento vs. San Diego
Figure 40 includes all claims submitted. The number of paid and unpaid claims for San Diego as of
August 23, 2019, is shown in Figure 41. There remain 83 unpaid claims because they were submitted
before March 14, 2019.
Figure 41. Dealership claims with payment status by month for San Diego
Source: SDG&E PAC Meeting Slides August 23, 2019
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 89
Table 23 shows a comparison of PlugStar program activity and regional characteristics from the U.S.
Census Bureau for Sacramento and San Diego counties. Most claims in Sacramento (74%) and San Diego
(63%) were submitted by trained sales staff. Although Sacramento had far greater numbers of claims on
an absolute basis, the number of claims per trained sales staff is similar for both programs. PIA believes
the number of claims per trained sales staff could be changed with increased marketing, driving more
shoppers to participating dealerships.
Lesson Learned: Trained sales staff submit claims at a greater rate (about four times greater) than untrained sales staff.
Both regions have similar mean travel times to work and levels of educational attainment, while San
Diego’s median household income is slightly higher than Sacramento’s. The population of San Diego
county is more than twice that of Sacramento county, so the potential exists for twice as much program
activity in San Diego.
Table 23. Comparison of program activity and region characteristics
Source Item Metric Sacramento San Diego
PIA Claims (Aug 31, 2018 – Oct 31, 2019*) 547 289
A Trained Claims 406 183
B Untrained Claims 141 106
C Participating Dealerships 19 15
D Trained Staff 207 87
E Total Staff 470 290
Calculated C/D Trained Staff/Dealership 11 6
D/E Percent of Staff Trained 44% 30%
(A+B)/C Claims per Dealership 29 19
A/D Claims per Trained Sales Staff 1.9 2.2
B/(E-D) Claims per Untrained Sales Staff 0.5 0.5
(Claims per Trained)/(Claims per Untrained) 3.6 4.3
Census Bureau
County Median Household Income $60,239 $70,588
Mean travel time to work (minutes) 26.9 25.7
High school graduate or higher, % of persons 25+ 87% 87%
Population July 1, 2018 1,540,975 3,343,364
*Dealerships are still submitting claims for November and December. The average lag between the sale date and
claim submission date is 9.5 days for San Diego dealerships.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 90
Sacramento has a greater number of trained sales staff per participating dealership and as a percentage
of dealership staff. While there are many factors that could contribute to this difference, PIA theorizes
there is less interest in training at San Diego dealerships due to “a much longer history of
unpredictability, and therefore unreliability, in payment of the dealer incentive claim” (as a result of the
EV-TOU rate requirement). Participating Sacramento dealerships have received incentive funds on a
consistent basis because it is not dependent on the customer signing up for the EV-TOU rate and those
sales teams have requested and received more EV training. Training rates are twice as high in
Sacramento as in San Diego (11 staff per dealership versus 6), and a much larger number of sales staff
are trained overall (207 versus 87).
Using the results in Sacramento as a proxy for the performance of the program had there not been the
EV-TOU rate requirement in San Diego, the San Diego program potentially would have achieved 2 or 2.5
times as many participating dealerships as Sacramento (based on higher population, higher incentive
level, and higher median income), with a greater number of claims per dealership.
19 dealerships in Sacramento * 2.5 * 29 claims per dealership = 1,378 potential claims
Thus, the PRP’s original goal of up to 1,500 additional EV sales appears to be an aggressive, yet
achievable, target based on a design that did not include the EV-TOU requirement.
Project Baseline/Market Lift
Market lift analysis will be completed for inclusion in the final evaluation report upon receipt of baseline
market data from IHS Markit.
Implementation Process
In interviews, PIA staff described typical challenges programs experience when engaging with
dealerships. To make an incentive program attractive for dealerships, the program must demonstrate it
makes the salespersons’ job of selling new EVs easier, which moves product faster than would otherwise
be the case. Dealerships have “evolved to rely far more on volume sales—selling the maximum number
of cars in the shortest amount of time—and manufacturer incentives to maintain profitability selling
new vehicles. Doing so presupposes the customer is already familiar with the product and that a reliable
fueling and support infrastructure is in place to support them. EVs, by contrast, require more time and
effort from dealers—largely to address familiarity, fueling and support concerns associated with this
new technology. Profits associated with EVs are also not fully understood.” In summary, dealerships are
a high-paced and numbers-driven business; inserting EVs into this environment results in more work for
the dealer for “too little reward.”
Understanding this business model, PIA designed PlugStar to address dealership needs through:
Training and resources (online tool and collateral) to help answer customers’ questions,
Rewards (incentives),
Customer leads (through the online tool and EV events), and
Recognition through awards ceremonies (such as for top dealership, most improved, most
community engagement).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 91
PIA’s recruitment strategy was to get buy-in from management by engaging them through trusted
channels, such as auto manufacturers and trade associations. Dealership trainings took place either in
three-hour multi-dealership sessions or one-hour sessions in a dealership’s location. The program also
requires at least two sales staff to attend the three-hour session for certification training of EV
specialists.
Once a participating dealership’s staff completed training, claims could be submitted for any EV sold.
Purchasers sign a consent form to provide their contact information to SDG&E during the transaction.
SDG&E staff said the utility sends a follow-up email to purchasers to provide information about EV-TOU
rates.
Communication of Program Goals and Expectations to PIA
PIA viewed the PRP’s goal of 1,500 additional EV sales as a cap on the number of incentives that PIA
could not exceed. PIA indicates that while 1,500 is an ambitious goal, it is possible that the recruited
dealerships could have achieved this result “absent the insertion of an EV-TOU requirement” with the
PlugStar training and incentive program. The EV-TOU requirement may have caused key dealerships to
decide against increasing EV supply, which would have further decreased the potential for EV sales.
Furthermore, PIA says that it was not clear at the outset of the program that the EV-TOU adoption was
considered the CPUC’s key metric for gauging success. After discussion with CPUC in early 2019, PIA took
several actions to support EV-TOU adoption:
1) Amending the customer release form to emphasize TOU rates (see before in Figure 42 and after
in
2) Figure 43)
3) Implementing an EV Customer Support Program (call center), which provides general
information on TOU rates and directs customers to SDG&E for more information
4) Advising on specific activities for the program and SDG&E to take more proactive steps to
convert buyers
5) Working with SDG&E to file an advice letter with CPUC to waive this program-hindering
requirement
6) Providing even more detailed training on TOU rates for dealers
7) Updating PlugStar.com with more detailed rate information, including TOU rates
8) Providing TOU rate collateral to dealers for their information and to hand to customers at the
dealership
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 92
Figure 42. Original customer release form excerpt
Source: PIA
Figure 43. Modified customer release form excerpt emphasizing TOU rates
Source: PIA
Costs
The approved PRP has an anticipated total direct cost of $1.79 million (all as O&M expense). Of that,
$750,000 was reserved for incentives, and the remaining budget was allocated for program education,
outreach, and SDG&E project management. The PRP direct costs as of September 30, 2019, totaled
$786,195 out of the $1,790,000 budget, as shown in Table 24.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 93
Table 24. SDG&E Dealership Incentives PRP costs
Actual Costs Approved Budget
Customer Engagement and Outreach $ 694,123 $ 1,603,400
SDG&E Clean Transportation PM $ 92,072 $ 186,600
Direct Costs $ 786,195 $ 1,790,000
Non Direct Costs (Indirect, AFUDC, and Property Taxes)
$ 98,090 $ 351,786
Total Costs $ 884,285 $2,141,786
Stakeholder and Customer Feedback
Dealership Review Survey
PIA deployed an online dealership review survey from August to October 2019. It received 12 reviews
for PlugStar dealerships in San Diego with an average rating of 4.75 out of 5 stars, all from EV shoppers
who completed a purchase or lease of an EV.27 Four out of twelve customers indicated they switched to
an EV-TOU rate plan after interacting with the dealership; the other eight customers have not switched
for the following reasons:
Customer already on a rate plan that costs less to charge (2)
Customer waiting for SDG&E to contact them to discuss EV-TOU rate options (2)
Customer wanted to further investigate the EV-TOU rate plan
Customer does not charge at home
Customer does not pay the power bill
Customer served by a community choice aggregator (CCA), with no available EV-TOU rate
Dealership and Sales Staff Survey Results
Initial feedback from dealership staff indicates that the training and education resources provided by the
PlugStar program were helpful. PIA surveyed participating dealership staff during the pilot phase and
27 PIA also sent the dealership review survey to their larger email list to obtain dealer reviews from non-PlugStar
dealers. PIA found the average PlugStar dealer rating for both San Diego and Sacramento was 4.6 out of 5 stars (32
respondents). This was higher than the national non-PlugStar dealer rating of 3.5 out of 5 stars (86 respondents).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 94
found that 100% would recommend the PlugStar training. Furthermore, PIA found that salespersons felt
more confident about various aspects of EVs after taking the training, including:
Electricity rates, including EV-TOU rates
Government incentives
Directing customers to qualified electricians for home charger installations
EV charging costs
PlugStar.com Web Traffic
PlugStar.com offers EV buyers information to support their EV-buying experience, including a list of
makes and models available, a vehicle cost calculator with incentives added, energy provider rates and
cost calculations to charge their EVs, a list of locally trained EV dealerships, and more. Table 25 shows
the PlugStar.com site traffic by month.
San Diego is one of the most highly trafficked regions on PlugStar.com (including traffic from
Sdge.PlugStar.com). PIA collects data from customers on visits to PlugStar.com from the customer
release form during the sales process. In San Diego, about 12% percent of EV buyers visited
PlugStar.com prior to purchasing an EV from a PlugStar dealership from August 31, 2018 – October 31,
2019.
Table 25. PlugStar site traffic (program areas and national)
Date San Diego Sacramento Total (National)
18-Sep 532 399 13.9k
18-Oct 386 389 13.8k
18-Nov 370 397 11.8k
18-Dec 631 550 13.6k
19-Jan 495 478 12.7k
19-Feb 782 508 15.8k
19-Mar 787 614 18.3k
19-Apr 983 1,063 22.6k
19-May 1,358 1,089 25.6k
19-Jun 1,244 1,060 26.9k
19 - Jul 673 747 10.4k
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 95
Date San Diego Sacramento Total (National)
19-Aug 779 725 13.1k
19-Sep 949 803 17k
19-Oct 866 1,248 14.9k
Cumulative 10,835 10,070 230k
Anecdotal Evaluation Team Member Experience
The dealership review survey results were augmented by direct experience of a team member to further
evaluate the sales process and other program aspects. In May 2019, a team member leased an EV from
a participating PlugStar dealership and signed the consent form to share contact information with
SDG&E. An SDG&E representative called in October 2019 about switching to an EV-TOU rate but was
brief and referred the EV lessee to the SDG&E website for more information. The EV lessee asked
whether SDG&E offered tools to help the customers determine whether there would be any savings
under the different EV-TOU rates based on a review of the previous 12 months of usage data. The
SDG&E representative said no such tools were available to offer this kind of service at the time.
Sales Staff Interviews
PIA will conduct sales staff interviews after program completion in Q1 2020, and a summary of the
results will be included in the final evaluation report.
EV Buyer Survey Results
PIA will conduct an EV buyer survey after program completion in Q1 2020, and a summary of the results
will be included in the final evaluation report.
EV-TOU Requirements
The original goal of the PRP was to increase EV purchases in SDG&E territory with sales staff and
dealership incentives, in addition to educating dealership staff and customers. The EV-TOU requirement
in Decision 18-01-024 added a complication to the PRP’s planned activities and the desired outcomes.
Based on interviews with SDG&E and PIA staff, there are several reasons why it is not desirable to have
salespeople explain the EV-TOU rate to shoppers and require a switch to this electricity rate for an
incentive to be issued:
Some shoppers do not plan to or are unable to charge their vehicles at their residences.
Some shoppers do not have an SDG&E account because someone else pays for their electricity.
Dealerships do not want to assume liability for providing EV buyers incorrect information, such
as which rates would save money or which buyers are eligible for which rates.
Rates are complex and difficult for salespeople to understand and then explain to customers.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 96
SDG&E has specialized staff to consult with customers about the best rate plan.
Analysis by SDG&E indicated that not all customers purchasing EVs would benefit from switching
to an EV rate plan.
2.6.4 Conclusions and Recommendations
Based on the information and feedback collected to date, some preliminary findings, in addition to the
lessons learned shared previously, are mentioned below. More market data is required to determine
whether expectations should be revised (e.g., determine what is baseline market activity), the project
should be discontinued or scaled up, or the project should be refined to focus on areas of strength (e.g.,
dealer education). The market data will be captured and analyzed in the final evaluation report.
Dealers can be trained and motivated via monetary reward to deliver simple, distilled messages
to customers about the potential to save money through enrolling in an EV-TOU rate. Beyond
this, the highly individualized nature of household energy use makes it more appropriate for
SDG&E staff to follow up with customers about whether an EV-TOU rate would result in savings
and the anticipated amount of the savings that might be realized.
Although SDG&E is following up with customers purchasing EVs, the stakeholder feedback
suggests there is a lag in this follow-up and that the information provided is generic and directs
customers seeking more information to the SDG&E website.
o Recommendation: SDG&E could augment its existing EV buyer outreach (which includes
point-of-sale/glovebox materials) by running eligibility checks for EV-TOU rates and by
providing customized analyses of purchasers’ usage under their existing rates compared to
the EV-TOU rate. This would identify customers who would benefit financially from
switching, and those customers could be sent personalized postcards or emails explaining
how changing their rate plans could result in savings, along with steps on how to switch to
the EV-TOU rate.
o Recommendation: SDG&E could take advantage of the PlugStar.com and sdge.plugstar.com
portals to provide prospective EV buyers with personalized estimates of EV-TOU savings.
The portal currently uses default EV (off-peak) rates for the user’s zip code to determine the
cost of charging; however, it does not calculate the cost difference between the EV-TOU
rate and the non-EV-TOU rate.
Given positive dealership staff survey results and customers’ high rating of participating
dealerships, it appears the education goals of the PRP are being satisfied. Additional data from
dealership surveys will be available for inclusion in the final evaluation report.
In both Sacramento and San Diego, there is a notable difference in the rate that trained and
untrained salespeople submit claims, with more claims submitted by trained salespeople.
The EV-TOU requirement substantially hindered the performance of the San Diego program,
when compared to Sacramento, and would be a barrier to scaling up the program.
The program did not meet its target of training 200 salespeople (it achieved 87 trained
salespeople); however, the results in Sacramento (200+ trained salespeople) suggest the
program may have achieved this goal had the EV-TOU requirement not been added.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 97
Program design requirements set by CPUC decisions, while well intentioned, should be
considered carefully for possible negative impacts on program effectiveness. Instead of
prescribing specific requirements, it would likely be more effective to state expectations of what
would constitute success (e.g., increasing EV sales while avoiding peak grid load increase due to
EV charging) and allow the program implementers to determine how to best proceed.
The implementer, PIA, was responsive to CPUC concerns once the company became aware of
them.
Programs targeted to DACs will need to support secondary market transactions.
The program in Sacramento was able to achieve greater total claims at lower incentive levels,
likely because it did not have an EV-TOU requirement.
Trained sales staff submit claims at a greater rate (about four times greater) than untrained
sales staff.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 98
3. Southern California Edison
3.1 Port of Long Beach Rubber Tire Gantry Crane
3.1.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
The Port of Long Beach (POLB) Rubber Tire Gantry (RTG) Crane Electrification Pilot will deploy make-
ready infrastructure to serve nine cranes at Stevedoring Services of America (SSA) Marine Terminal J.
SCE will design, install, own, and maintain the electric infrastructure, including two new distribution
substations that will serve nine new electric motorized RTG cranes.
The San Pedro Bay Ports Clean Air Action Plan 2017 Update, which was adopted by the joint Long Beach
and Los Angeles Boards of Harbor Commissioners in November 2017, builds upon previous successful
efforts to help reduce air emissions and support sustainable freight movement. The strategies in the
2017 Update are some of the boldest yet, and they will require a significant amount of cooperation from
the goods movement industry, regulatory agencies, and other stakeholders. The 2017 Update set new
goals, including a goal of 100% zero-emissions terminal equipment by 2030. The POLB has
acknowledged that this is an incredibly aggressive goal, given that not all of the necessary technology
exists yet.
The pilot supports the state’s Sustainable Freight Strategy to “reduce diesel particulate matter (PM) and
criteria pollutant emissions from compression ignition mobile cargo handling equipment that operates
at ports and intermodal rail yards in the state of California.” Electrifying RTG cranes will improve air
quality and reduce GHG emissions for the communities surrounding the port, which are mostly DACs.
RTG cranes are the second-largest source of NOx emissions at the terminal, and the technology could
have a significant impact on emissions if adopted by other port operators in California.
The POLB’s zero-emissions goal stems from influence at both local and state entities. The port wants to
be ready when requirements are in place to mandate zero-emissions equipment. The POLB tries to
secure grants and outside funding to help tenants address higher costs, while also providing assistance
as needed. It is necessary to secure support for larger-scale demonstrations that really test the
equipment in revenue service to determine durability of the equipment. Projects such as this PRP aim to
prove out the use of these technologies so others will have more confidence about adopting them. SCE
support to this electric RTG project came after the CEC award was received; however, discussions
between SCE and the POLB on this project were ongoing. This RTG project might not have happened
without SCE funding, or it would have had to be scaled down significantly. SCE’s support was critical to
the success of the overall project to electrify the RTGs.
Traditional RTG cranes have electric lift and propulsion drives, with electric energy generated by on-
board diesel reciprocating engines. SCE’s proposed project will support a customer pilot for a grid-
connected electric conversion system that removes the diesel engine and adds power transformation
and electronics fed by a motorized electric cable mechanism. The cable connects to a stationary grid-
connect mechanism that allows the RTG crane to disconnect from the cable when it needs to transfer to
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 99
the maintenance shop (using power from a temporary mobile battery system). The grid-connection
mechanism ties to a high-voltage utility connection (4,000 volts).
To support the electric RTG crane project, SCE upgraded existing facilities and installed the following
new equipment and supporting structures:
Pad-mounted switches
New 12 kV circuit (Beluga 12 kV) wharf substation
Four new 12 kV/4 kV distribution substations
One padmount capacitor bank
Four 2500 kVA 12 kV/480 V transformers
Conduit and cable
New vaults
All supporting civil and foundation structures
The new distribution substations transform the 12 kV to 4 kV and then distribute the 4 kV circuits to four
termination points—one for each RTG stacking run—for a total of four 4 kV termination points, as
shown in the figure below.
Figure 44. Pier J electric RTG crane project site layout
Source: POLB
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 100
Sites and Participants
Recruitment Process
The project supports SSA Marine Terminal J at the POLB in accelerating the conversion of the port’s
current RTG cranes to electric power by deploying the electric infrastructure necessary to serve the new
electric RTG cranes. The PRP was designed specifically for this application and customer, with no
additional recruitment of participants planned.
Participants
SCE is providing the electrical infrastructure to support the electric RTG cranes, and the POLB secured
funding for the electric RTG cranes through part of a $9.7 million grant from the CEC, as well as port
money and in-kind contributions from the private sector. Converting an RTG from diesel power to
electricity costs about $585,000. SCE’s estimated cost for the make-ready infrastructure to support the
nine RTGs is $3,038,000, or $337,556 per RTG. M.S. Hatch Consulting is assisting the POLB with
management of the RTG conversion project, including data collection and analysis for the CEC grant. As
SCE is not providing a rebate for the charging equipment in this PRP, Stevedoring Services of America
(SSA) Marine will qualify vendors, products, and services.
SSA Marine will work with technology vendor Cavotec to repower nine diesel-electric RTG cranes by
removing the on-board auxiliary diesel engines—which generate electricity for the electric lift and
propulsion drives—and replacing them with a grid-connected electric conversion system. The system
will enable disconnection from the grid and, by use of a container with an electrochemical battery pack,
enable block changing during normal operations and easy movement to the maintenance shed when
needed. A single battery container will be used to support transfer of all nine cranes and will be stored
and charged by the maintenance shed. SSA Marine will connect the electric RTG cranes to the grid at
SCE’s four 4 kV termination points. Sight, a company out of San Diego, will provide a laser guidance
system using reflective tape—the first time such a system is used in an RTG crane application.
Timeline and Status
SCE estimated the PRP portion of this project (supporting electrical infrastructure) would take
approximately 12 months to complete. The pilot was implemented in Q1 2018, with the following key
milestones to date:
Final engineering design for SCE’s new and upgraded infrastructure was completed and received
approval for construction (Q2 2018).
The POLB issued the Harbor Development Permit (November 2018).
Wharf 66/12 kV Substation upgrades were completed (Q4 2018).
SCE completed all its civil construction (Q1 2019).
The POLB installed the switchgear pads on the north side, and SCE completed the placement of
their electrical equipment (Q3 2019).
South-side switchgear pads and SCE electrical equipment were installed (October 2019).
All switchgears and equipment disconnects were energized (November 2019).
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 101
This PRP is highly dependent on the POLB and SSA Marine’s onsite work to electrify the RTG cranes. SSA
Marine requires RTG cranes in their everyday operation and needed to ensure that everything was
ready for the conversion before taking them out of service. The Cavotec parts for the conversion came
from overseas and took several months to arrive. The system must lay the electrical connection cable in
a trench that has a clearance of only two inches, so SSA Marine needed an automatic steering system.
Once that was completed, work began on cutting the approximately 7,000 feet of linear trenching that
will be needed for all the electric RTG cranes. This effort took several months, with scheduled
completion in Q1 2020. Before converting the first electrical RTG, the battery system needed to be
procured and brought onsite so that RTG could move independently of the power cable system if
needed. The battery system is scheduled to arrive in January 2020. With all supporting components in
place and SSA Marine completing a mock-up of the conversion (discovering that a larger enclosure
would be needed), the conversion of the first RTG crane to electric started in mid-November 2019 and is
expected to be completed in Q1 2020.
Figure 45. Linear trench being cut and configured for the connection cable
Source: POLB
Rubber connection
cable trench covering
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 102
Each electric RTG conversion is expected to take up to two months to complete (initial ones may take a
little longer as the conversion process is being developed) and will occur sequentially. Therefore, the
first electric RTG may be put into operation by the end of February 2020 and could provide
approximately eight months of operational data to evaluate its performance, while the last electric RTG
conversion may not be completed until November 2020 and may not contribute data to the final PRP
evaluation report. However, the RTGs have similar operations, and the analysis of one can be
extrapolated to calculate the expected benefits from all nine electrified RTGs once they are operational.
Figure 46. Enclosure removed from RTG crane engine compartment to begin conversion
Source: POLB
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 103
Figure 47. SCE POLB RTG crane PRP timeline
Source: POLB CEC Grant weekly construction meetings
3.1.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP.
• Did the technology (contained with a battery pack) adequately accommodate moves among the
berths?
• Was there wear in the cables or other issues that might limit the electric RTG crane’s useful life
more than traditional diesel-powered ones?
• Could this be economically feasible without the CEC grant and SCE support?
The data collection tasks utilized to evaluate this PRP include 1) PRP information from the approved
decision, project updates, site visits, and other available documentation, 2) market research on RTGs
and early deployment efforts from other similar electrification projects across the country, 3) PRP data
from RTG crane operations, 4) IDIs with project partners (SCE, POLB, SSA Marine), and 5) surveys with
RTG crane operators.
Data Sources
Some PRP information has been collected through numerous PRP participant interactions, including a
PRP kick-off meeting (SCE and evaluator), quarterly SCE Transportation Electrification Program Advisory
Committee meetings, periodic PRP updates (SCE and evaluator), monthly CEC project updates, site visits,
and other periodic calls or emails. Currently, the evaluation team has the following information from
this PRP: a data collection plan for the CEC project funding the electric conversion of the RTGs,
infrastructure and electric RTG specifications, electricity tariff details, and some site pictures. Over the
next few months, the evaluator expects to receive additional information on project costs, historical RTG
use, and RTG status at the time of electric conversion.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 104
The following sources for market research have been identified:
POLB: Electric Vehicle Blueprint, Identify and Plan for a Zero-Emissions Future (2019)
Papaioannou et al.: Analysis of energy usage for RTG cranes (2016)
Electric Power Research Institute, Inc. (EPRI): Evaluation of Electric Rubber-Tired Gantry Cranes
at the Port of Savannah (2014)
Knight et al.: A Consumption and Emissions Model of an RTG Crane Diesel Generator (2011)
EPRI: Electric Cable Reel Rubber-Tired Gantry Cranes: Costs and Benefits (2010)
California Air Resources Board (CARB): Zero- and Near Zero-Emission Freight Facilities Project
Methodology for Determining Emission Reductions and Cost-Effectiveness (2018)
Expected PRP operational data for this project includes utility service meter 15-minute interval data (one
for each bank of RTG connection), power analyzer data for an individual electric RTG test, monthly
electric consumption data for each converted RTG, monthly facility electricity bills, periodic hour-meter
readings for the electric RTGs, and maintenance records.
The evaluator held an IDI with POLB representatives to further understand the background on this
project and gather lessons learned to date. Additional IDIs with the SCE construction team, SCE project
managers, and vendors, as well as an operator survey, are scheduled for 2020 as the electric RTGs
become operational.
3.1.3 Evaluation Findings
Project Baseline
The RTGs take deliveries of containers from yard tractors and place them into stacks in the container
yards, where they await delivery to street trucks. Currently, all RTG cranes at the POLB are configured
with a diesel-fueled engine, driving an electric generator, which powers the RTG crane’s propulsion and
lift functions. Each 1,000-horsepower RTG burns approximately 10 gallons of diesel fuel per hour during
more than 2,000 hours of service each year. RTG cranes comprise 5% of the total heavy-duty equipment
operating at the POLB; however, because of the engine sizes and operating schedules, the cranes
represent approximately 20% of the POLB cargo-handling equipment emissions. RTGs have a useful life
of about 30 years. There are 64 RTG cranes at the POLB, and they represent a significant source of
criteria pollutant emissions. The mean annual NOx emissions from these 64 cranes is 111.3 tons. The
combined mean PM10 and PM2.5 emissions are 2.1 tons. The mean carbon dioxide equivalent (CO2e)
emissions for the 64 cranes is 11,776 tons.
SSA Marine operates a total of 15 RTG cranes at the POLB, and 28 RTG cranes statewide (including the
Port of Los Angeles and the Port of Oakland). There are a total of 118 RTG cranes located at the three
largest ports in California (Oakland, Los Angeles, and Long Beach). A successful demonstration could
lead to opportunities to introduce electric RTG cranes and subsequent reduction of a significant amount
of emissions in California. If this electric technology is adopted at all three of these major ports, it could
reduce 708 tons of NOx, 35 tons of particulate matter, and 24,780 tons of CO2 annually, which would be
equivalent to reducing more than 5% of non-road diesel NOx and PM emissions in Los Angeles County.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 105
Implementation Process
One of the key challenges for customers electrifying their fleets is the initial research and project
development phase. During the project development phase, the collaboration with the POLB, SSA
Marine, and Cavotec contributed significantly to a successful project kickoff and continued into the
execution phase. However, the newness of this technology made it challenging to acquire the desired
components for all nine cranes in a timely manner.
This project and other electrification projects from SCE demonstrate a clear path that customers can
take not only to collaborate with their local utilities but also to engage with equipment providers to
create an outcome that is beneficial for business, the environment, and the community. Ports outside of
SCE’s service territory have been in communication with SCE and the POLB on the strategies leveraged
to allow for duplication of efforts at their respective facilities. SSA Marine is now planning to implement
similar projects at its terminals in Oakland and Seattle.
Costs
The proposed total cost for the PRP make-ready infrastructure provided by SCE was $3,038,000. This
comprises capital costs entirely, as SCE does not capture the site assessment, design, and permitting
costs for the utility side, only for the customer side. Additionally, the POLB covered the cost of
switchgears and installation for the electric RTG project (~$2.84 million) and overall has spent much
more in match (CEC grant requirement) than anticipated. The SCE-incurred PRP costs as of November
2019 totaled $2,470,417 (not including the POLB-covered costs), as shown in Table 26, based on data
available to SCE.
Table 26. SCE POLB RTG Crane PRP costs as of November 2019
Cost Category Actual Costs Budgeted Costs
Site assessment, design, and permitting N/A N/A
Rebate amount paid N/A N/A
EVSE procurement N/A N/A
EVSE installation N/A N/A
Make-ready infrastructure (utility side) $2,470,417 $3,038,000
Make-ready infrastructure (customer side) N/A N/A
Other construction costs N/A N/A
Project management N/A N/A
Customer outreach (labor) N/A N/A
Outreach and education materials N/A N/A
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 106
Cost Category Actual Costs Budgeted Costs
Other program costs N/A N/A
Total Cost $ 2,470,417 $3,038,000
Benefits
This project offers many potential environmental benefits. The Assigned Commissioner’s Ruling
recognizes the potential for improvement in this transportation segment, stating, “Mobile emission
sources at ports and truck stops located in the service territories of the large three electric utilities are a
concentrated source of emissions that could be well served with targeted programs.” Accelerating
transportation electrification adoption at the POLB improves air quality and reduces GHG emissions for
all neighboring communities. These communities immediately surrounding the POLB are considered
DACs, as defined by the California Environmental Protection Agency.
SSA Marine’s nine RTG cranes fueled by diesel are the second-largest source of NOx emissions at the
terminal. Annual emission reductions per crane will be approximately 6 tons of NOx, 0.3 tons of PM, and
210 tons of CO2. The POLB and SSA Marine will operate the electric RTG cranes for a period of at least
10 years. The CEC-approved funding for this Sustainability Freight Transportation Project, consisting of
nine electric RTG crane conversions, estimated the emissions benefits slightly differently. The approval
stated the project would reduce GHG emissions by an estimated 1,140 MT of carbon dioxide equivalents
(CO2e), 24.14 MT of NOx, 1.43 MT of reactive organic gases (ROG), and 0.39 MT of PM per year.
Table 27. SCE POLB RTG Crane PRP benefits summary
Anticipated in Testimony
(9 RTG Cranes)
Anticipated in CEC Application
(9 RTG Cranes)
As Implemented
As Optimized
Petroleum Reduction 180,000 diesel gallons per year
N/A TBD TBD
GHG Emissions 1,890 tons of CO2 per year
1,140 MT of CO2 per year
TBD TBD
Criteria Pollutants 1,140 MT of CO2 per year
24 MT of NOx per year; 0.4 MT of PM per year; 1.4 MT of ROG
TBD TBD
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 107
Anticipated in Testimony
(9 RTG Cranes)
Anticipated in CEC Application
(9 RTG Cranes)
As Implemented
As Optimized
DAC Impact POLB is adjacent to DACs
POLB is adjacent to DACs
TBD TBD
Operations, Maintenance, and Fuel Costs
N/A N/A TBD TBD
Other Co-Benefits N/A N/A TBD TBD
Operational Impacts of Project Equipment
As of this interim report, no electric RTG operation has taken place, as the first crane is scheduled to be
retrofitted in Q1 2020. This section will be completed for the final report utilizing all the available
information and data obtained before November 2020.
Stakeholder and Customer Feedback
As of this interim report, no electric RTG operation has taken place to capture this feedback. Feedback
pertaining to the initial implementation of this PRP is captured in Section 0. This section will be
completed for the final report utilizing all the available information and data obtained before November
2020.
3.1.4 Conclusions and Recommendations
Findings
Without any electric RTGs converted, there is no electric RTG operation to date; it is therefore too early
to determine this PRP’s success, which will be documented in the final report. However, some
preliminary findings, in addition to the lessons learned shared previously, are mentioned below:
Customers tend to be very cautious when working on equipment that is critical to their
operations. While SSA Marine might have been able to accelerate the project timeline by doing
multiple actions in parallel (procuring the conversion components, installing the switchgear
pads, ordering the battery module, and cutting the trenches), the company chose to verify each
activity was completed before progressing to the next.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 108
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it
would be recommended cannot be determined at this time. Recommendations based on operational
data and stakeholder IDIs will be included in the final report.
3.2 Port of Long Beach Terminal Yard Tractors
3.2.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
The POLB Clean Air Action Plan sets aggressive goals to accelerate transportation electrification
technology development. To help drive the transition to zero-emissions, the port proposed that all
terminal equipment must be zero-emissions by 2030. Through this PRP, SCE will deploy the electric
infrastructure necessary to serve charging stations for new electric yard tractors, which move
intermodal containers around the facility. To accommodate the originally proposed load for 24 charging
points, SCE needs to upgrade its distribution infrastructure, including additional pad-mounted switches,
capacitor bank, and transformers. SCE will design, deploy, own, and maintain this electric infrastructure.
However, SCE will not establish technical requirements on charging equipment, as the utility will not
provide a rebate to cover these costs. The total estimated costs for this project are $450,000 for the
deployment of the infrastructure.
The objectives of the pilot are to demonstrate proposed vehicles/technologies for 12 months, convene a
Zero-Emission Port Workforce Development group to improve existing workforce development and
training programs in support of port equipment electrification, and establish the proposed technologies
as cost-competitive purchase options through development of estimates of future costs versus baseline
technology costs. The project will also support the state’s Sustainable Freight Strategy to reduce diesel
PM and criteria pollutant emissions from compression-ignition mobile cargo-handling equipment that
operates at ports and intermodal rail yards by demonstrating the feasibility of replacing diesel drive
tractors with electric drive tractors.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 109
Figure 48. POLB Pier G electric yard tractor project site location
Source: POLB
Sites and Participants
Recruitment Process
The PRP was specifically developed and approved to deploy make-ready infrastructure that serves the
International Transportation Service (ITS) Terminal’s fleet of yard tractors, currently fueled by diesel
engines. The ITS Terminal has a fleet of 120 diesel-powered yard tractors at the POLB and plans to
expand the fleet to 132 by 2020. The ITS Terminal has two areas where yard tractors are parked; the
main area accommodates 100 tractors, and a second, smaller area accommodates 24 tractors. ITS
management has selected this second area on the west side of Pier G for the pilot because of its
proximity to the pier electrical substation. The PRP supports the first of a two-phase plan by ITS to install
some initial chargers as a test. If proven successful, a Phase 2 plan will target up to 80 more chargers.
Participants
The POLB has received funding from the CEC for 12 pre-commercial terminal yard tractors. However, the
funding does not cover the supporting electric infrastructure, so this PRP will provide that for the
project. Initially, during the timeline of this PRP, ITS will deploy seven BYD Motors Inc. (BYD) electric
yard tractors, six BYD chargers, and one automated charger from Cavotec. SCE will deploy
infrastructure to serve up to 20 terminal yard tractor charging stations. The additional five electric yard
tractors in the CEC project will be demonstrated at Long Beach Container Terminal (LBCT), which is not
associated with SCE’s PRP. LBCT terminal recently underwent a significant renovation and therefore has
sufficient electrical capacity that the terminal does not require SCE upgrades.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 110
Figure 49. BYD model 8T electric yard tractor, BYD 200 kW charger, and Cavotec automated charger arm
Source: BYD (left and middle pictures) and Cavotec (right)
Six of the new battery electric yard tractors will use 200 kW charging stations from BYD. These high-
power chargers will enable ITS to overcome one of the key barriers to widespread market adoption of
zero-emissions technologies: the ratio of charge time to operating time. With a lower-power charger, ITS
might be forced to limit use of the new yard trucks to a single shift per day—a condition that would be
considered a failure right from the very start of the project. By deploying 200 kW chargers, ITS
anticipates being able to use the yard trucks for two shifts per day, meeting the real-world minimum
requirements of the marine terminal. One BYD yard tractor will include compatibility with an innovative
and automated “smart” yard tractor charging system from Cavotec to support a more convenient large-
scale charging system that is necessary to transition its fleet to zero-emissions.
To serve the estimated load for the 20 charging points (200 kW each), SCE will upgrade its distribution
infrastructure, including additional pad-mounted switches, a capacitor bank, and transformers. SCE is
responsible for the planning, design, and construction of the make-ready electrical infrastructure at both
the utility side and customer side for the ITS demonstration. The following equipment and supporting
structures are included in SCE’s design:
Two sets of pad-mounted equipment (PME): (PME 10 and PME 9)
Two 3,000 A switchgear
Meter cabinet
Pad-mounted capacitor bank
Two 2,500 kVA 12 kV/480 V transformers
Distribution conduit and cable
All supporting civil and foundation structures
480 V charging station infrastructure terminating in seven make-ready positions
Ducts and structures to support an additional 13 future EVSE installations
The customer-side electrical infrastructure will be constructed by one of SCE’s approved general
contractors under SCE’s supervision. The POLB has a consultant, Starcrest, overseeing the data
collection requirements for the CEC grant.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 111
Timeline and Status
SCE estimated that designing and deploying the infrastructure for this project would take about
12 months. The SCE installation of the electrical infrastructure under this PRP ended up taking
approximately 18 months, with the following major milestones:
The PRP was implemented in Q1 2018, following the CPUC decision in January 2018.
Final engineering design for SCE’s make-ready infrastructure was completed in Q4 2018.
The POLB and ITS reviewed and approved the design plans in November 2018.
The POLB issued the Harbor Development Permit for construction in November 2018.
The plans were submitted to the City of Long Beach Building & Safety for review and permitting
in November 2018.
Construction of the electrical infrastructure was completed in Q1 2019, with structural, fire, and
electrical approvals of completion received by the end of March 2019.
The electrical infrastructure was energized following the installation of the chargers in Q3 2019.
While this PRP was strictly supporting SCE electrical infrastructure at the POLB for this ITS yard tractor
demonstration, the project’s impacts are not realized until the equipment is fully operational. Future
SCE transportation electrification projects may involve charging equipment installation, so there is value
in observing that process at ITS through the CEC grant. BYD brought a demonstration yard tractor to ITS
in June 2019 to conduct maintenance personnel training. ITS took delivery of the first three BYD yard
tractors by the end of August, with a fourth sent to get the Cavotec funnel (which guides the automated
charger arm) installed. There was miscommunication on the required height of the automated charger
arm, which created multiple interactions about the tractor funnel’s specifications and later some
adjustments to the height of the charger itself (ultimately, the height of the mounting pad had to be
changed). Neither BYD nor Cavotec chargers were listed by a Nationally Recognized Testing Laboratory
(NRTL). As a result, BYD pursued onsite TÜV SÜD product certification for the 6 BYD chargers, and
Cavotec pursued ETI Conformity Services Field Evaluation for the Cavotec charger. The initial inspections
of both listed several concerns: enclosure not meeting National Electrical Manufacturers Association
(NEMA) 3R requirements, some individual electrical components and cables were not NRTL-listed, and
some electrical components were not rated the meet the potential power levels. In addition to finding
solutions to these issues, ordering the replacement parts, and properly installing them, follow-up
inspections were required that necessitated the coordination of the inspector, equipment
manufacturers, the POLB, and ITS. A delay of four or more months is expected from when the chargers
were first installed (August 2019) to when they will be approved for use (anticipated in December 2019).
Lesson Learned: Field certification of equipment that is not already NRTL-listed can add significant complication to a project and should be expected to delay completion by several months while any issues found in the initial inspection are being corrected. For cutting-edge transportation electrification technology, this is sometimes unavoidable but should be limited to projects classified as pre-commercial demonstrations (which the CEC grant supported) and not for commercial deployment programs.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 112
Figure 50. SCE POLB terminal yard tractor PRP timeline
Source: POLB CEC Grant Weekly Construction Meetings
3.2.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP.
• Did electric yard tractors and charging equipment perform as expected?
• How did the automated charger use compare to other chargers? What were the benefits, and
were there any downsides to the automated charger use?
• Would similar supporting electrical infrastructure at other locations in the port be more
expensive? Is there a limit to the available power?
• Could this be economically feasible without the grants for the tractors and SCE support?
The data sources used to evaluate this PRP include 1) PRP information from the approved decision,
project updates, site visits, and other available documentation, 2) market research on yard tractors and
early deployment efforts from other similar electrification projects across the country, 3) PRP data from
vehicle and charger operations, 4) IDIs with project partners, and 5) a potential survey of the tractor
operators.
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: a PRP kick-off
meeting (SCE and evaluator), quarterly PAC update meetings, periodic PRP updates (SCE and evaluator),
weekly PRP construction calls, biweekly CEC grant data collection calls, site visits, and other periodic
calls or emails. Currently, the evaluation team has the following information from this PRP: the data
collection plan for the CEC project funding the electric yard tractors, electric yard tractor characteristics
and hardware specifications, and details from other electric yard tractor efforts at the POLB through the
CEC grant and a National Renewable Energy Laboratory study in support of the POLB Port Community
Electric Vehicle Blueprint. Over the next few months, the evaluator expects to receive additional
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 113
information on project costs, pictures from the site, all specifications for the charging stations, and
historical yard tractor use.
The following sources for market research have been identified:
SDG&E: Port Electrification PRP
Transpower: Electric Yard Tractor Demonstration Project (2015)
OrangeEV: Making Electrification Work: How to Successfully Deploy HDEVs – A Yard Tractor Case
Study (2018)
San Pedro Bay Ports: Zero/Near-Zero Emissions Drayage Truck Testing & Demonstration
Guidelines (2016)
Heavy Duty Trucking: Regional Haul, Yard Tractors Are Well-Suited for Electrification (2019)
Expected PRP operational data for this project includes utility service meter 15-minute interval data (one
single meter for electrical infrastructure supporting 20 connections [seven active stations]), charging
session data from the Cavotec charger, yard tractor data from two GeoTab telematic devices (one for
the tractor with the Cavotec funnel and one other BYD tractor), and productivity data from SSA Marine
at a very high level. The evaluator also expects to receive maintenance data on the tractors and
chargers, as well as monthly electricity bills.
The evaluator held an IDI with a representative from the POLB to further understand the background on
this project and gather lessons learned to date. Additional IDIs with the SCE construction team, SCE
project managers, vendors, and operators are scheduled during the upcoming year as the yard tractors
are added to revenue service. A survey or facilitated focus group discussion with the drivers of the
electric yard tractors is also planned, if ITS can arrange for it.
3.2.3 Evaluation Findings
Project Baseline
At the POLB, yard tractors, which may also be referred to as terminal tractors, utility tractor rigs, yard
trucks, yard goats, or yard hostlers, are the most common cargo-handling equipment used in on-
terminal container movement. According to the 2017 Air Emissions Inventory, yard tractors account for
approximately 46% of total cargo-handling equipment at the POLB. The total number of yard tractors
operated within the port exceeds 650 vehicles. Over 86% of these yard tractors are currently equipped
with non-road diesel engines, making them high polluters.
Yard tractor activities in marine terminals generally fall into three main categories: ship work, rail work,
and dock work. Ship work involves the loading and unloading of containers onto and from container
vessels. Rail work comprises loading and unloading containers to and from cargo trains, while dock work
consists of moving containers within a terminal yard, such as the consolidation of containers (sometimes
referred to as housekeeping). There are approximately 1,745 diesel yard tractors located at the three
major California ports (POLB, Port of Los Angeles, and Port of Oakland). If these three major ports
convert this equipment from diesel to electric power, it would result in emissions reductions of over
4 tons of PM and nearly 300 tons of NOx annually. Learnings from this project can benefit future
electrification projects across all ports in California.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 114
This project is driven by the POLB’s Clean Air Action Plan goals to go to zero-emissions, which is
influenced by expected state and local regulations on this topic. Working toward these goals will require
a good deal of new equipment implemented in partnership with terminal operators. The operators want
to test out to see if this technology works for port operations, can pull the loads required, and is durable
enough, as port equipment is often driven into the ground. There have been smaller, short-term
demonstrations, but this is the first time a project of this scale will enter revenue service with the
intention of staying with the terminal operator for its lifetime. Such projects are needed to bring
technologies closer to commercialization for other operators to adopt and to quantify the business case
for electrification.
Implementation Process
The pilot’s ongoing success was a direct result of the collaboration between all the partners and
stakeholders during the development stage. The execution of large-scale electrification projects with
multiple stakeholders across a number of industries can be challenging. Early collaboration is critical to
success. The POLB began its electrification plan with a goal to ensure that all stakeholder groups were
involved in developing the pilot execution plan. This ensured that all parties were aware of the timeline
during each planning stage.
Procuring the electric yard tractors and installing the charging equipment was beyond the scope of SCE’s
PRP, but these efforts have a significant impact on the success of the overall goal to deploy
transportation electrification technology for emission reductions. Almost all complications and delays
associated with this project were attributed to the newness of technology available and selected for this
demonstration pilot. The process undertaken to field-certify the charging stations revealed NRTL Listing
requirements and Short Circuit Current Rating (SCCR) capacity issues that necessitated modifications to
the already installed equipment. In addition to the time for determining a solution, ordering
replacement components, and performing the correction, there are added complications for scheduling
and site access because the equipment was already at the customer location. The POLB would require
that, for future installations, any certifications are done prior to installation to minimize work and
disruptions at the customer site.
Another concern discovered post-installation was that the charging cable weight was difficult for the
equipment operators to handle. As charging powers increase, the cords quickly become heavy and
difficult to maneuver, particularly if liquid cooling is required (in this case, it was not). The length of
charging cord based on the charger positioning and location of the port on the vehicle may also affect
the weight. Some form of cable support was necessary for this installation (and will likely be needed for
many similar installations). The POLB also noted that the electrical infrastructure, charging stations, and
protective bollards took up more space than initially anticipated, which presented equipment parking
site configuration layout challenges. Several concrete pads were also very large and posed potential
tripping hazards, so post-construction modifications were necessary.
The POLB also noted that it would be helpful to determine roles and responsibilities for each project
team member early in the project. Regularly held calls helped work through any confusion or concerns,
but concerns could have been addressed more easily if roles and responsibilities were clarified at the
beginning of the project. The POLB also suggested binding agreements with all project stakeholders and
equipment end users for similar future projects.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 115
Costs
The approved total PRP cost (which is made up entirely of capital expenses) was $450,000. Customer-
side costs are estimated at $1 million and will not be included for recovery as part of this pilot. The PRP
costs as of November 2019 totaled $1,586,125 (which may not include all participant costs), as shown in
Table 28, based on data available to SCE.
Table 28. SCE POLB Terminal Yard Tractor PRP costs as of November 2019
Cost Category Actual SCE Costs Budgeted SCE Costs
Site assessment, design, and permitting
$ 38,814 N/A
Rebate amount paid N/A N/A
EVSE procurement (subject to change)
N/A N/A
EVSE installation (subject to change)
N/A N/A
Make-ready infrastructure (utility side)
$ 698,989 $ 450,000
Make-ready infrastructure (customer side)
$ 848,323 N/A
Other construction costs N/A N/A
Project management N/A N/A
Customer outreach (labor) N/A N/A
Outreach and education materials
N/A N/A
Other program costs N/A N/A
Total Cost $ 1,586,125 $ 450,000
The forecast for the customer-side construction costs was inadvertently omitted from the initial
application. The actual customer-side construction costs of approximately $900,000 were recorded to
Shareholder O&M.
The assumptions used for the original $450,000 forecast for the utility-side construction costs were
based on single-meter switchgear and standard installation conditions using PVC conduit between all
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 116
SCE structures. Cost overruns of approximately $250,000 were also recorded to Shareholder O&M and
primarily due to the following:
Load requirements on the customer side required that two-meter switchgear be installed, as
opposed to the single-meter switchgear in the original assumptions.
Customer-imposed space constraints and an asphalt cross-section that was substantially thicker
than expected resulted in higher-than-anticipated construction labor costs.
More expensive concrete cable trenches had to be custom-built at the site because of tighter-
than-expected equipment placement, which made traditional conduit placement from
transformers to the meter switchgear impossible.
Benefits
The project accelerates electrification of a key transportation segment in SCE’s service territory, with
potential for additional future conversion of yard tractors. On average, the yard tractors annually
produce 5 pounds of PM and 341 pounds of NOx. Converting yard tractors to electric drivetrains will
improve air quality and reduce GHG emissions for all neighboring communities, in particular for DACs, as
they are the most severely affected by current levels of criterial pollutants and GHG emissions.
Table 29. SCE POLB Terminal Yard Tractor PRP benefits summary
Anticipated in Testimony
(24 charging ports)
Anticipated as Planned
(7 charging ports)
As Implemented As Optimized
Petroleum Reduction
N/A N/A TBD TBD
GHG Emissions N/A N/A TBD TBD
Criteria Pollutants
120 pounds of PM per year; 8,184 pounds of NOx per year
35 pounds of PM per year; 2,387 pounds of NOx per year
TBD
DAC Impact POLB is adjacent to DACs
POLB is adjacent to DACs
TBD TBD
Operations, Maintenance, and Fuel Costs
N/A N/A TBD TBD
Other Co-Benefits
N/A N/A TBD TBD
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 117
Operational Impacts of Project Equipment
Electric yard tractor testing will comprise three primary phases:
1) Electric Yard Tractor Acceptance Testing – completion of specified testing parameters
(completed in July 2019 by BYD in Lancaster, California)
2) Controlled On-Terminal Testing – completion of typical single-shift duties
3) Revenue On-Terminal Demonstration – completion of typical operations for 12 months
No significant electric yard tractor operations under this PRP were completed as of this interim report.
This section will be completed for the final report utilizing all information and data obtained before
November 2020.
Stakeholder and Customer Feedback
Electric yard tractors have not entered SSA Marine revenue service as of this interim report to capture
this feedback. Feedback pertaining to initial PRP implementation is captured in Section 0. This section
will be completed for the final report utilizing all information and data obtained before November 2020.
3.2.4 Conclusions and Recommendations
Findings
Without any electric yard tractor operations to date, it is too early to determine this PRP’s success,
which will be documented in the final report. However, some preliminary findings, in addition to the
lessons learned shared previously, are mentioned below:
SCE’s construction of the electrical infrastructure was straightforward and completed in a timely
manner once the design was approved and permits were secured. Complications and delays
were caused by the chargers and tractors, which are beyond the project scope.
Electrical infrastructure and charging equipment can require significant space and need ample
protection, which can create a challenge for the site configuration layout. The layout must also
consider driver behavior, such as parking orientations, to best account for minimal disruptions
to current operations.
It is important to determine and clearly define roles and responsibilities for each project team
member early in the project to avoid potential complications. Where possible, secure binding
agreements with all project stakeholders and equipment end users.
Field certification of equipment that is not already NRTL-listed can add significant complication
to a project and should be expected to delay completion by several months while any issues
found in the initial inspection are being corrected. For cutting-edge transportation electrification
technology, this is sometimes unavoidable but should be limited to projects classified as pre-
commercial demonstrations (which the CEC grant supported) and not for commercial
deployment programs.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 118
Next Steps
A recommendation pertaining to this project’s potential for scale-up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
3.3 Electric Transit Bus Make-Ready Program
3.3.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
Electric bus technology is maturing, with several companies offering a range of commercially available
vehicles suited to the needs of transit agencies, with standard-based charging systems. However, the
costs and complexities associated with electric buses are significant. From siting and deploying charging
infrastructure to operational impacts (e.g., downtime for charging and training maintenance
technicians), transit agencies must overcome new challenges when they convert to operating electric
buses.
The Electric Bus Make-Ready Program, also known as the Charge Ready Transit Bus Program, will deploy
make-ready infrastructure to serve charging equipment for electric transit buses operating in SCE’s
service territory. SCE will also provide a rebate to participating customers to offset the cost of the
charging equipment and its installation.
The program will encourage system safety and reliability, as SCE will work closely with participating
customers to site, size, and deploy electric infrastructure in accordance with SCE’s transmission and
distribution standards and applicable building and electrical codes, using licensed contractors. The
objective is to help transit agencies expand the number of electric buses in operation in SCE’s service
territory.
SCE will target transit agencies operating in its service territory and solicit them for participation in the
program through SCE’s business customer division. The program was open on a first-come, first-served
basis to non-residential customers that meet the following requirements:
• Qualify as a government transit agency,
• Own or lease the participating site, or be the customer of record associated with the premises
meter (likely the property management company or the building owner or tenant), where the
charging equipment for the buses would be deployed,
• Provide agreement by the participating site’s owner to grant SCE appropriate real property
rights and continuous access to the customer participant site infrastructure,
• Acquire at least one new electric or plug-in hybrid bus used to provide transit service to the
public,
• Commit to and provide acceptable proof of qualified charging equipment and vehicle purchase
(together with actual pricing information) prior to deployment by SCE,
• Agree to take service on an eligible TOU rate, and
• Agree to participate in the pilot for its entire duration, including maintaining the charging
equipment in working order and participating in surveys and data collection.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 119
SCE estimated that the program will cost $3,978,000 to complete, including deployment costs to serve
up to 20 charge ports and customer rebates to offset the costs of qualified charging equipment and
installation.
Sites and Participants
Recruitment Process
An informational session was conducted on May 21, 2018, to solicit feedback from transit agencies and
equipment providers on the program. The Electric Bus Make-Ready Program was then launched on
June 4, 2018. The program fact sheet, participation informational package, and program application
were made available online for viewing and download. Applicants were instructed to fill out the
application and submit via email. The SCE business customer division’s account managers were also
available to guide the applicants through the submission process.
Figure 51. SCE factsheet pages for the Electric Transit Bus PRP
Source: SCE Charge Ready Website
The Electric Bus Make-Ready Program received six applications. All program applicants submitted
proposals for in-depot charging stations. The number of ports per site in applications ranged from 3 to
14. During the application review stage, SCE reviewed the applicant’s proposed site, number of charging
ports requested, proposed charging equipment, and presence of DAC routes. Further site visits were
performed to obtain cost estimates to install infrastructure at the site. The customer was also required
to submit information about its EVSE network and equipment providers to ensure that they meet the
program’s technical requirements.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 120
The program had to reject two applications, as the applicant’s charging equipment (Complete
Coachworks) did not meet technical requirements and could not be changed. One applicant with plans
to acquire 14 electric BYD buses did not move forward under this PRP because the fleet has to make
modifications to the buses to enable using ChargePoint stations (BYD chargers are not NRTL-listed), but
the applicant may apply to the Charge Ready Transport, which is SCE’s standard review program. A
seventh potential customer withdrew from the program citing procurement timing and also plans to
apply for Charge Ready Transport.
Lesson Learned: The program experienced a challenge in qualifying equipment proposed by the applicants. Because of the rapidly changing nature of the transit bus EVSE market, some EVSE providers could not meet the program technical requirements, such as the requirement that the equipment be recognized by a NRTL.
Participants
The Electric Bus Make-Ready Program resulted in agreements with three transit agency customers with
a collective total of 30 ports supporting 31 electric buses.
Foothill Transit has a fleet of 373 buses (30 of which are electric, the rest compressed natural
gas [CNG]) that has plans to go all-electric by 2030. The first deployment of electric buses was in
2014 (first fast-charge electric bus line in the United States), with an extended-range electric bus
added in 2017 and an all-electric double-decker bus in 2018. Infrastructure to support 14 new
Proterra electric buses consists of twelve 60 kW chargers and one 125 kW charger.
Porterville Transit has a fleet of 20 buses. GreenPower Motor Company will deliver 10
GreenPower EV350 40-foot zero-emission all-electric transit buses for deployment on all nine
Porterville Transit routes. Eleven 200 kW BTCPower chargers will be installed at the
maintenance facility and transit center for a total purchase price of approximately $9 million.
Victor Valley Transit Authority will be acquiring its first battery electric buses to move forward
on the agency’s commitment to operate an all-electric fleet by 2040. Victor Valley will deploy
five 35-foot and two 40-foot New Flyer Xcelsior XE models that are charged by seven 62.5 kW
ChargePoint stations.
Timeline and Status
SCE estimated that the program would take approximately 12 months from launch to completion.
Following the CPUC decision in January 2018, SCE launched the program on June 4, 2018, and executed
agreements with the three eligible transit agencies in the fourth quarter of 2018. Electrical
infrastructure designs were completed in the first quarter of 2019, with design approvals by the
participants and local permits obtained in the second quarter of 2019. SCE completed the majority of
the make-ready at each transit agency in the third quarter of 2019 (Foothill was the last to be
completed, in mid-October). Individual participants are responsible for completing the installation of the
charging stations and acquiring the buses:
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 121
Victor Valley’s charging infrastructure was installed and operational by the end of September
2019. Two New Flyer electric buses had been delivered, with five more on the way.
Porterville has received all ten GreenPower buses but still needs to finish the installation of the
charging stations (to be completed with parking lot re-pavement in January 2020).
Foothill is also still working to complete charging station installation (expected in January 2020)
but has several Proterra buses onsite already.
Figure 52. SCE Electric Transit Bus Make-Ready PRP timeline
Source: SCE
3.3.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Fleet
Electrification PRPs, the evaluation questions listed below will be examined for this PRP:
• Did some electric buses or charging equipment perform better than others?
• Could operations have benefited from on-route charging or faster charging?
The data collection tasks utilized to evaluate this PRP include 1) PRP information from the approved
decision, project updates, and other available documentation, 2) market research on transit buses and
early deployment efforts from other similar electrification projects across the country, 3) PRP data from
vehicle and charger operations, 4) IDIs with project partners, and 5) surveys with vehicle drivers.
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: PRP kick-off
meeting (SCE and evaluator), quarterly PAC update meetings, periodic PRP updates (SCE and evaluator),
site visits, and other periodic calls or emails. Currently the evaluation team has electric bus
characteristics and hardware specifications for each site. Over the next few months, the evaluator
expects to receive additional information on project costs, station characteristics, site layout, site
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 122
pictures before and after the construction work, electricity tariff details, bus route information, and
historical bus usage throughout the fleet.
In addition to the information from PG&E’s Medium and Heavy Duty PRP (San Joaquin Regional Transit
District with Proterra buses and chargers), the following sources for market research have been
identified:
Columbia University: Electric Bus Analysis for New York City Transit (2016)
National Renewable Energy Laboratory: Medium- and Heavy-Duty Vehicle Field Evaluations
(2017)
MJ Bradley & Associates: Comparison of Modern CNG, Diesel and Diesel Hybrid-Electric Transit
Buses: Efficiency & Environmental Performance (2013)
CARB: Transit Fleet Cost Model (2017)
Green Tech Media: 3 Trends Making the Case for Bus Electrification (2019)
Fast Company: Battery Electric Buses: the innovative technology that’s re-energizing urban mass
transit (2019)
Expected PRP operational data sources for this project include utility service meter 15-minute interval
data, charging station session data, monthly facility electricity bills, bus telematics, operational
summaries, and maintenance records. The evaluator plans to facilitate IDIs with the SCE construction
team, SCE project manager, participating transit agencies, and vendors during the upcoming year as the
electric buses are placed into revenue service.
3.3.3 Evaluation Findings
Project Baseline
As of December 2018, approximately 12,000 transit buses were in operation throughout California, an
inventory that has remained relatively constant over the past decade. Public and contract bus service
employment has decreased over the same period, down to about 22,100 in 2016 compared to 26,200 in
2006. Ridership over the period from 2007 to 2017 decreased from 1,000,300,000 to 802,900,000.28
Effective October 1, 2019, the Innovative Clean Transit regulation is part of a statewide effort to reduce
emissions from the transportation sector. The regulation, a replacement of the Fleet Rule for Transit
Agencies (S.2023), mandates that each of the state’s public transit agencies submit a rollout plan to
CARB to transition to an all-ZEB fleet by 2040. Starting in 2029, all transit agencies will be able to
purchase only fully electric buses. Rollout plans are due in 2020 for large transit agencies and 2023 for
small agencies. As of December 2018, eight of the ten largest transit agencies in the state were
28 California Transit Association, Interactive Repository of Facts and Figures on California Public Transit, 2019,
https://caltransit.org/about/transit-data/.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 123
operating ZEBs.29 The regulation’s mandate to transition to an all-zero-emission transit system is
projected to dramatically increase the inventory of ZEBs from an estimated 153 at the time of passage
to 1,000 buses in 2020.30
Several bus manufacturers are offering electric models, with some recent companies being formed to
serve this market exclusively. New Flyer offers CNG, hydrogen fuel cell, and battery electric buses in its
Xcelsior line, introduced in 2010, with the battery electric model introduced in 2012 and commercially
available in 2014. New Flyer has provided buses to transit fleets across North America, with 1,600 ZEBs
in service as of December 2019.31 Proterra, originally headquartered in Colorado, moved to South
Carolina in 2010 and then to the City of Burlingame, California, in 2015 when the CEC awarded the
company a $3 million grant to fund the design, development, and construction of the company's battery
electric transit bus manufacturing line. Proterra reports sales of more than 800 ZEBs to 100 communities
across 43 U.S. states and Canadian provinces.32 Chinese ZEB manufacturer BYD has a U.S. manufacturing
facility in Lancaster, California. BYD reports having nearly 40,000 ZEBs in service around the world, with
the vast majority of those sales in China.33 The company reported sales of about 722 ZEBs in the United
States as of May 2018, with anticipated growth to 1,500 annually in subsequent years.34 GreenPower
Motor Company is a Canadian ZEB manufacturer with manufacturing facility in Porterville, California.
GreenPower offers five models of battery electric transit buses, along with electric school buses and
shuttle vehicles.35 GreenPower is a relatively small manufacturer compared to New Flyer, Proterra, and
BYD, but the company increases the electrified options in an industry segment that is projected to grow
significantly over the next decade.
Implementation Process
The Electric Bus Make-Ready Program had a short timeline between the decision approving the
program, program launch, and the need to enroll customers and complete construction before program
closure. Electric transit buses have a long procurement timeline, often 12–18 months from when a new
electric transit bus is first ordered to its delivery. While many of SCE’s transit agency customers were
interested in participating in the program, their procurement schedules did not align with the PRP’s
timeline. In addition, some potential transit agency customers have electrification goals that exceed the
budget of the Electric Bus Make-Ready Program and were better suited for SCE’s Charge Ready
Transport Program.
29 CARB, Innovative Clean Transit, accessed 2019, https://ww2.arb.ca.gov/our-work/programs/innovative-clean-
transit/about. 30 CARB, California Transitioning to All-electric Public Bus Fleet by 2040, 2019,
https://ww2.arb.ca.gov/news/california-transitioning-all-electric-public-bus-fleet-2040. 31 New Flyer Industries Canada ULC, “About Us,” accessed 2019, https://www.newflyer.com/company/about/. 32 Proterra, “Our Story,” 2019, https://www.proterra.com/company/. 33 BYD North America, “About BYD,” 2019, https://en.byd.com/about/. 34 Green Biz, The World’s Biggest Electric Vehicle Company You’ve Never Heard Of, 2018,
https://www.greenbiz.com/article/worlds-biggest-electric-vehicle-company-youve-never-heard. 35 Greenpower, Inc. (2019) LINK: https://www.greenpowerbus.com/news/
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 124
The program experienced a challenge in qualifying equipment proposed by the applicants. Because of
the rapidly changing nature of the transit bus EVSE market, some EVSE providers could not meet the
program technical requirements, such as the requirement that the equipment be recognized by a NRTL.
This resulted in delays to qualify the applicant, as SCE needed to work with the applicant’s EVSE provider
to explain the purpose behind the requirements listed in the program’s technical requirements document.
When performing site design for these PRP installations, SCE learned that there were non-EV
developments or bus retrofits occurring, or in the design phase, at some customer facilities. In some
cases, these activities directly interfered with the proposed EV deployment. For future infrastructure
programs, a question about current and planned facility upgrades or retrofits should be included in the
program participation package.
Figure 53. Victor Valley Transit Authority charging station installation
Source: SCE
SCE developed an EVSE Technical Requirements Document instead of an approved product list as there
were not many set charging stations dedicated for bus charging and the time of PRP development and
launch. This document was available as part of the original customer collateral online and through SCE
account managers. SCE staff met with applicants and their EVSE providers to discuss products and
review the PRP EVSE technical requirements. SCE was open to customers and vendors submitting new
products. One transit agency selected EVSE and signed the contract with SCE, but upon inspection, it
was discovered that the EVSE was not NRTL-listed, and the installation could not proceed.
SCE account manager reported that all three transit customers were very happy with the work of the
SCE project management and construction teams. In addition, they were very interested in the new
rates due to the recent removal, for a period of five years, of early demand charges.
No significant issues arose during the design and construction process that would require scope-of-work
changes. A minor filed change occurred when Foothill requested one large charger (125 kW instead of
62.5 kW) to charge a double-decker electric bus, which Proterra will soon deliver. The change was made
fairly late in the construction process, but SCE managed to accommodate it without any significant
delays in construction completion. Costs came in as expected within the original estimates.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 125
Victor Valley installed a self-contained EVSE unit with DC power and dispenser combined, while
Porterville and Foothill installed a control cabinet with remote dispensers. Foothill already had an on
route high-power overhead charger, in parallel with PRP installed an overhead gantry charging system at
the depot and is considering installation of solar generation onsite.
Costs
The approved PRP had an anticipated total cost of $3,978,000, consisting of $2,731,000 in capital and
$1,247,000 in expense. The PRP costs as of November 2019 totaled $1,325,869 (which may not include
all participant costs), as shown in Table 30, based on data available to SCE.
Table 30. SCE Electric Transit Bus Make-Ready PRP costs as of November 2019
Cost Category Actual SCE Costs Budgeted SCE Costs
Site assessment, design, and permitting
$ 120,992 N/A
Rebate amount paid 0 $ 900,000
EVSE procurement (subject to change)
N/A N/A
EVSE installation (subject to change)
N/A N/A
Make-ready infrastructure (utility side)
$ 592,868 $ 939,575
Make-ready infrastructure (customer side)
$ 456,998 $ 1,647,425
Other construction costs N/A N/A
Project management $ 96,742 $ 406,991
Customer outreach (labor)
N/A N/A
Outreach and education materials
$ 58,268 N/A
Other program costs N/A $ 84,009
Total Cost $ 1,325,869 $ 3,978,000
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 126
Site assessment, design, and permitting was budgeted under the customer-side capital expense for
make-ready infrastructure. The O&M non-labor and contract budget was budgeted under other
program costs.
Benefits
The program will help increase transit agencies’ adoption of electric commuter buses. A typical diesel-
powered commuter bus travels 36,000 miles per year at an average fuel economy of 4.8 miles per diesel
gallon. During this operation, the bus emits 2,000 g/mile of CO2, or roughly 80 MT per year, plus 0.4 MT
of NOx and 6.4 kg of PM from its tailpipe annually. Each new fully electric bus will reduce tailpipe GHG
and criteria pollutant emissions by 100% throughout its lifetime.
As a part of the application process, applicants were required to submit proof of any DAC routes that
they serve. Applicants with DACs routes and depots were prioritized in program participant selection. All
three program participants are located and have routes in DACs. Once the charging stations installed
through the program are in operation, SCE will survey participants about the percentage of routes
travelling through DACs and the number of electric miles served by buses that use these charging
stations.
Table 31. SCE Electric Transit Bus Make-Ready PRP benefits
Anticipated in Testimony
(20 ports/buses)
Anticipated as Planned
(30 ports & 31 buses)
As Implemented As Optimized
Petroleum Reduction
150,000 diesel gallons per year
232,500 diesel gallons per year
TBD TBD
GHG Emissions 1,600 MT of CO2 per year
2,480 MT of CO2 per year
TBD TBD
Criteria Pollutants
8 MT of NOx; 0.13 MT of PM
12 MT of NOx; 0.2 MT of PM
TBD TBD
DAC Impact Designed to maximize electric transit bus routes in DACS
Locations and routes in DACs for all three transit partners
TBD TBD
Operations, Maintenance, and Fuel Costs
N/A N/A TBD TBD
Other Co-Benefits
N/A N/A TBD TBD
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 127
Operational Impacts of Project Equipment
No significant electric transit bus operations with the SCE-supported make-ready for EV chargers under
this PRP were completed as of this interim report. This section will be completed for the final report
utilizing all information and data obtained before November 2020.
Stakeholder and Customer Feedback
No significant electric transit bus operations with the SCE-supported make-ready for EV chargers under
this PRP were completed as of this interim report, so this feedback could not be captured. Feedback
pertaining to the initial implementation of this PRP is captured in Section 0. This section will be
completed for the final report utilizing all information and data obtained before November 2020.
3.3.4 Conclusions and Recommendations
Findings
Without significant electric transit bus operations with the PRP installed chargers to date, it is too early
to determine this PRP’s success, which will be documented in the final report. However, some
preliminary findings, in addition to the lessons learned shared previously, are mentioned below.
The make-ready construction planning, design, and execution went smoothly, with only a minor
field change order to add a higher power charger. Make-ready costs and construction durations
were within expected budget and timelines. The infrastructure installation process was similar
to the DCFC PRP, as very similar charging equipment is being used.
The program experienced a challenge in qualifying equipment proposed by the applicants.
Because of the rapidly changing nature of the transit bus EVSE market, some EVSE providers
could not meet the program technical requirements, such as the requirement that the
equipment be recognized by a NRTL.
This PRP provided the make-ready charging infrastructure capacity only for the number of EVSEs
to be immediately installed by the three transit customers. Future electrification plans were
discussed with the customers to understand their potential make-ready charging infrastructure
needs, but serving those potential future needs was not within the project scope and would
need to be addressed under SCE Charge Ready Transport or another future program, if
available.
Next Steps
A recommendation pertaining to this project’s potential for scaling-up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 128
3.4 Urban DC Fast Charging Clusters
3.4.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
DCFC installations to date tend to support long-distance travel near highways. (Approximately 75% of
the DCFC stations in SCE’s territory are located within 0.5 miles of a major highway.) Many residential
customers do not have access to overnight off-street parking or home charging, and DCFC in urban areas
could help such a customer adopt an EV and quickly charge it near his or her home. Lack of overnight or
home charging is especially problematic for customers in multi-unit dwellings (MUDs), who could
benefit from this pilot. DCFC located in densely populated areas away from highway corridors could also
prove useful for EV drivers participating in rideshare programs.
Through the Urban DCFC Clusters Pilot, SCE will deploy and operate five DCFC sites, clustered in urban
areas. Each site may include up to five dual-port charging stations, for up to 50 DCFC ports total. SCE
intends to install, own, and maintain make-ready infrastructure (illustrated in Figure 54) at participating
customer sites. Participating customers will have the opportunity to select DCFC charging stations
qualified by SCE and receive a rebate to cover the base cost of charging stations deployed through the
pilot, including hardware and installation. Approved vendors include MaxGen (using ABB hardware and
Greenlots for networking), Greenlots (using one of several hardware options and the company’s
network), and ChargePoint (using its own hardware and network). Participating customers will be
required to provide public access to the charging stations deployed through the pilot but can determine
EV charging fees at their discretion.
Figure 54. SCE make-ready electrical infrastructure for the Urban DCFC Clusters Pilot
Source: SCE
The pilot will help determine whether urban DCFC charging stations provide a solution for customers
who do not have access to home charging. Over the course of five years, the pilot will collect customer
usage data to help develop future pilots and programs that address the EV charging needs of urban
communities. SCE intends to promote the pilot with potential participating customers, such as cities,
public parking lot operators, and EV service providers, and invite them to participate in this effort.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 129
The pilot requires participation in a demand response (DR) program and will track the DR event
participation levels. The DCFC charging stations can receive and execute real-time instructions to
throttle and/or modify the end-user pricing of EV charging load. Pilot participants will be incentivized to
participate in two types of DR events:
Load shift DR events, in which customers receive a discounted rate for charging during a time of
high solar generation and potential negative prices by shifting charging from early morning to
midday
Traditional DR events, in which customers receive incentives for consuming less energy during
peak times or during periods of steep ramping of energy demand on the grid
SCE is planning to monitor charging event details and load profiles for 12 months after installation, with
an additional three months for review and reporting.
Sites and Participants
Recruitment Process
For the Urban DCFC Clusters Pilot participants, SCE targeted non-residential customers that may meet
the pilot’s requirements. SCE’s business customer division reached out to these customers through low-
cost channels such as emails and other customer communications. SCE also solicited expertise and
proposals from EV service providers on potentially eligible sites. Non-solicited customers also had the
opportunity to apply to the pilot, which SCE promoted on its website. The website’s Charge Ready
landing page was one of the main resources for potential customers to learn about this pilot and submit
their applications. The landing page provided potential customers with a participation package and fact
sheet that explained the overall pilot and provided copies of the application, easement template, and
program agreement. Eligible site host customer requirements included the following:
Be a non-residential customer.
Own or lease the participating site, or be the customer of record associated with the premises
meter where the charging stations will be deployed.
Provide an agreement by the participating site’s owner granting SCE appropriate real property
rights and continuous access to the customer participant site infrastructure that is to be
installed, owned, and maintained by SCE.
Identify a site in or near (< 1.5 miles) a DAC with MUDs nearby.
Commit to and provide acceptable proof of qualified charging station purchase, and price paid,
prior to SCE deployment.
Agree to take service on an eligible TOU rate and participate in applicable DR program(s).
Agree to participate in the pilot for five years, including maintaining the charging stations in
working order.
Contract with a qualified EV charging network service provider to provide transactional data to
SCE.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 130
The pilot received 50 applications from 18 unique customers. To determine the most qualified
candidates for the pilot, SCE developed quantitative scoring criteria (up to 1.0 point for each of the
following for a maximum score of 4.0), based on 1) the site’s proximity to a DAC, 2) EV adoption in the
selected area, 3) population density, and 4) proximity to MUDs. Results from the initial selection process
to rank customers who applied to the pilot were as follows:
12%, or 6 sites, were located outside DAC areas and were not eligible to participate.
26%, or 13 sites, scored <3 and were deemed less than ideal to participate.
8%, or 4 sites, withdrew from the pilot.
54%, or 27 customers, met the scoring criteria.
Of the 27 customer sites passing the initial selection process, 16 customer sites were selected for the
feasibility analysis, which included preliminary engineering to determine feasibility of the site, develop
conceptual drawings, and estimate the project cost. To further narrow the list and identify the top five
sites to participate in the pilot, SCE performed a qualitative review of each site, examining (a) distance
from major freeways (further is better, as many DCFC charging stations are located along highways),
(b) site cost, (c) permitting requirement(s), (d) ease of construction, and (e) need for ADA requirements.
Participants
SCE selected five initial sites for participation in this PRP. All sites selected the 50–62.5 kW ChargePoint
DCFC (CPE 250) to install. As with SCE Charge Ready Pilot, the DCFC program had an approved product
list, and vendors could apply for inclusion on the list. The customers had to select an approved DCFC
charging station from the approved product list to participate in the program. The agreement requires
the site host to keep the charging stations operating for five years and submit charging session data to
SCE.
Two locations are shopping centers, and the other three are stand-alone businesses close to other
shopping centers and retail businesses. A total of 14 DCFCs were installed among these five locations.
SCE provided the infrastructure to the make-ready position. For the DCFC project, the make-ready is a
service disconnect adjacent to each EVSE power cabinet. The customer scope was installing the EVSE
and any required conduits/wiring/mounting fixtures and connecting to the energized service disconnect
provided by SCE.
Corona Sun Square, at 1380 West 6th Street in Corona, installed four 50 kW CPE 250 DCFCs. The Corona
Sun Square project utilized an existing transformer. The voltage of the existing transformer (208 V) was
not correct for selected DCFC installation; thus the EV infrastructure includes a 208 V to 480 V step-up
transformer. The charging fee, which is set by Corona Sun Square, was $0.50/kWh in December 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 131
Figure 55. Map of area surrounding Corona Sun Square
Source: Google Maps
Nearby MUD neighborhoods include Meadowood Apartments, Las Casitas Apartments, Village Grove
Mobile Home, Lincoln Park Apartments, Summerwood Village Apartments, and Corona Del Rey
Apartments. Nearby retail outlets include Walmart Neighborhood Market, CVS, and several restaurants.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 132
Figure 56. Corona Sun Square DCFC installation
Source: Evaluator team
Global Partners in Koreatown Shopping Center, located at 8901 Garden Grove Boulevard in Garden
Grove, installed four 50 kW CPE 250 DCFCs from ChargePoint. The charging price is $0.25/kWh, as set by
Global Partnership, LLC.
The shopping center has 21 restaurants and retail shops, such as Paris Baguette, an international
premium bakery-café chain, and Kaju Soft Tofu, a Korean comfort food restaurant. Nearby MUD
neighborhoods include Meadowbrook Garden Apartments, Franciscan Garden Apartments, and Walden
Apartments. Nearby retail outlets include H Mart, an Asian grocery store, and several other restaurants.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 133
Figure 57. Map of area surrounding Global Partners in Garden Grove
Source: Google Maps
SCE held a plug-in ceremony on October 17, 2019, in the H Mart Shopping Center in Garden Grove.
Garden Grove Mayor Steven R. Jones, CNT Properties President Charles Lee, and Korean American
Chamber of Commerce of Orange County President Ho-El Park attended, in addition to SCE staff.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 134
Figure 58. Global Partners in Garden Grove
Source: SCE Press Release and PlugShare (bottom right)
AAA – Automobile Club of Southern California, at 1021 East Foothill Boulevard in Upland, installed two
50 kW DCFCs from ChargePoint (CPE 250). The AAA Upland site utilized the existing transformer
structure but required a new upsized transformer (300 kVA, from 12 kV to 208 V). The AAA intends to
make this site free for public use. As of the end of November 2019, the SCE scope for make-ready and
customer scope for EVSE installation had been completed; however, the station was not yet available for
use and did not show up on the EV charging apps.
Nearby neighborhoods include Upland Meadows mobile home park. Nearby retail outlets include King’s
Pharmacy and a few restaurants. A YMCA is located across the street.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 135
Figure 59. Map of area surrounding AAA in Upland
Source: Google Maps
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 136
Figure 60. AAA DCFC installation in Upland
Source: Evaluator team
A second AAA – Automobile Club of Southern California location, at 18642 Gridley Road in Artesia,
installed two 50 kW DCFCs from ChargePoint (CPE 250). The AAA Artesia site required a new dedicated
transformer and structure. According to SCE, AAA intends to make this site free for public use, as with
the Upland location. As of the end of November 2019, the SCE scope for make-ready and customer
scope for EVSE installation had been completed; however, the station did not yet appear to be available
for use on the EV charging apps. There are nearby MUD complexes on 186th Street and a large mall
across the street, with several restaurants in the area.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 137
Figure 61. Map of area surrounding AAA in Artesia
Source: Google Maps
Figure 62. AAA site in Artesia where 2 DCFCs were installed
Source: Google Maps
A 7-Eleven convenience store at 806 Indian Hill Boulevard in Pomona installed two Charge Point Express
62.5 kW 250 DCFCs with a 1,000 V pairing kit, allowing for charging up to 125 kW when only one vehicle
is connected. The charging stations are the very first to be owned, operated, and branded by 7-Eleven.
The charging costs are set by the 7-Eleven for energy use and range from $0.24/kW to $0.40/kW.
Nearby MUD neighborhoods include Pama Management, Keystone Court Apartments, Vista del Cielo
Apartments, and San Antonio Vista Apartments. Several restaurants are nearby.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 138
Figure 63. Map of area surrounding 7-Eleven in Pomona
Source: Google Maps
7-Eleven and SCE held a plug-in ceremony on November 21, 2019, to celebrate the project’s completion.
The event was attended by Pomona Mayor Tim Sandoval, Pomona Chamber of Commerce’s Monique
Manzanares, Pomona Councilwoman Elizabeth Ontiveros-Cole, and Pomona Mayor Pro Tem Victor
Preciado, in addition to 7-Eleven and SCE staff.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 139
Figure 64. Plug-in ceremony at 7-Eleven in Pomona with 7-Eleven branded charger
Source: SCE News Release
Figure 65. 7-Eleven DCFC installation in Pomona
Source: Evaluator team
Timeline and Status
SCE estimated that planning and implementation (enrollment and deployment) for the Urban DCFC
Clusters Pilot would require approximately 12 months. Data collection will require 12 additional months
at each site, with 3 more months for review and reporting. SCE launched the Charge Ready Program on
June 29, 2018. The application and selection period was completed by November 2018. All five site
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 140
assessments were executed by February 2018. The design and permitting phase began after each site
host provided proof of EVSE procurement. The design phase followed SCE’s design standard review
process, which allowed participants the opportunity to review the 50% design and the 100% design for
approval. After the final design was reviewed and approved by the pilot participant, SCE submitted the
design to the authority having jurisdiction (AHJ) for review and permitting. SCE also submitted the
easement agreement to each pilot participant for execution prior to starting construction. Obtaining
design approval and securing permits took 3–4 months for these five sites; some site construction began
in June 2019. SCE’s construction phase took six weeks or less per site. The customers and their
contractors began EVSE installation after SCE completed the make-ready infrastructure and released the
site. The first location was energized in October, and all five were operational by early December.
Pending any issues, nearly 12 months of operational use will be analyzed for the final evaluation.
Figure 66. SCE Urban DCFC Clusters PRP timeline
Source: SCE
3.4.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Public Access
Station PRPs, the evaluation questions listed below will be examined for this PRP.
• Does the rebate cover all eligible costs?
• Did applicants who were not selected continue with EVSE installation?
• Are utilization patterns different in the urban setting from those for highway installations?
• Did some sites perform better than others, and what was the reasoning for any differences?
• Did the sites’ participation in DR benefit the utility? Did it negatively affect the customers?
The sources for data collection used to evaluate this PRP include 1) PRP information from the approved
decision, project updates, site visits, and other available documentation, 2) market research on DCFCs
and early deployment efforts from other similar electrification projects across the country, 3) PRP data
from charger operations, 4) IDIs with project partners, and 5) surveys with vehicle drivers.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 141
Data Sources
Some PRP information has been collected through numerous PRP participant interactions: PRP kick-off
meeting (SCE and evaluator), quarterly PAC update meetings, periodic PRP updates (SCE and evaluator),
site visits, and other periodic calls or emails. Currently the evaluation team has selected locations,
charging station hardware specifications, and some site pictures for each site. Over the next few
months, the evaluator expects to receive additional information on project costs, station characteristics,
site layout, electricity tariff details, and program selection details.
The following sources for market research have been identified:
SDG&E: Electrify Local Highways PRP
National Renewable Energy Laboratory/Idaho National Laboratory/Argonne National
Laboratory: Analysis of Fast Charging Station Network for Electrified Ride-Hailing Services (2018)
Idaho National Laboratory: What were the Cost Drivers for the Direct Current Fast Charging
Installations? (2015)
Idaho National Laboratory: Considerations for Corridor and Community DC Fast Charging
Complex System Design (2017)
Center for Sustainable Energy: California Air Resources Board Clean Vehicle Rebate Project,
Rebate Map (2019)
Vermont Energy Investment Corporation: Electric Vehicle DC Fast Charging on Vermont Highway
Corridors (2017)
Expected PRP operational data sources for this project include utility service meter 15-minute interval
data, charging station session data, monthly facility electricity bills, parking lot occupancy rates, and
maintenance records. The evaluator plans to facilitate IDIs with the SCE construction team, SCE project
manager, participating host sites, and vendors during the upcoming year. A survey may also be
facilitated with EV drivers that charge at the PRP DCFC locations. SCE was directed by the decision
approving the PRPs to work with the evaluator to develop a survey on whether DCFC clusters support EV
adoption for MUD residents and those without access to home charging. SCE and evaluator have
engaged in early discussions about the survey plans. Any survey results will be included in the final
evaluation report.
3.4.3 Evaluation Findings
Project Baseline
Since the initial 2016 ZEV Action Plan was announced, Governor Brown has raised the bar, increasing the
target number of ZEVs on the road and public EVSE across the state with the 2018 update. Adding to the
initial goal of 1.5 million ZEVs registered, the 2018 update sets an additional target of reaching 5 million
total ZEVs by 2030. This even more ambitious goal will likely require more public EVSEs to be brought
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 142
online than the original target of 250,000 public stations by 2025. Of the total EVSE goal, at least 10,000
are to be DCFC.36
Since 2016, ZEV sales have continued to increase. In 2018, ZEV sales reached about 8% of the total market
share, or about 410,000 vehicles. Early reporting for 2019 totals shows total ZEV registration up to
655,000.37 To reach the 2030 vehicle goals, however, ZEV sales will need to reach 40% of the market share.
There are an estimated 18,000 public chargers (Level 2 and DCFC), averaging about 225 Level 2 stations
installed and 90 DCFCs installed per month. At the start of 2019, DCFCs made up about 15% of the total
public EVSE and were a quarter of the way to reaching the 2025 goal of 10,000 chargers.38
Implementation Process
SCE originally planned for up to five dual-port DCFCs at each site (up to a total of 50 ports); however,
most of the applications asked for two or four ports because of the reluctance to lose parking spots. To
electrify two ports, site hosts may need to give up three or four existing parking spots (since one spot
must be ADA compliant). Retail customers requested only two ports, as they were unable or unwilling to
allocate more than two or three parking stalls for the pilot. Customers that owned or managed the
property were able to allocate more stalls but still typically requested only four ports. In future projects
with similar target audiences, SCE should consider targeting a total number of ports for the program
without defining the number of sites. This will allow the program flexibility to maximize the budget and
support increased adoption with more sites and the potential for higher port count.
Another issue SCE discovered along the way was that since many of the applicants were tenants, SCE
needed to work with the property owner to obtain an easement to install the make-ready infrastructure
and maintain the equipment and service line. This added an additional step in securing the agreements,
if all went well. Some customers were not able to obtain the necessary approval from the property owners
or property managers for their sites to participate in the pilot. Three sites withdrew from the pilot during
the agreement stage because the property owners refused to sign the pilot agreement and were unwilling
to provide the required easements. For similar future efforts, SCE should consider doing additional
outreach to target property owners and property management companies of retail shopping centers. By
targeting both property owners/management and retail businesses, SCE would likely see fewer
rejections for qualified sites and an increase in adoption and higher numbers of ports at these locations.
A senior director of Energy, Engineering and Store Planning for the 7-Eleven convenience store giant
provided a testimony of successful customer partnership: “Our collaboration with SCE through Charge
36 Governor’s Interagency Working Group on Zero-Emission Vehicles, 2018 Zev Action Plan Priorities Update,
http://www.business.ca.gov/Portals/0/ZEV/2018-ZEV-Action-Plan-Priorities-Update.pdf. 37 Rob Nikolewski, “California electric vehicle sales are up,” LA Times, December 1, 2019,
https://www.latimes.com/business/story/2019-12-01/electric-vehicle-sales-in-california-on-the-rise-but-is-it-
enough-to-reach-the-5-million-goal-by-2030. 38 CEC, ZEV Tracking Progress, December 18, 2018, https://www.energy.ca.gov/sites/default/files/2019-
05/electric_vehicle.pdf.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 143
Ready is a win–win for everyone. Fast chargers mean added convenience for EV drivers who visit our
store and cleaner air for the surrounding community.”39
According to the SCE construction manager, there were no surprises during the design and construction
phases beyond the minor field changes that are normal for construction scope. Construction costs were
within expected budget, and SCE construction of all sites was completed in six weeks or less. Upon
accounting for all PRP costs, the SCE construction team will prepare a list of lessons learned that will be
reviewed and summarized in the final evaluation report.
Costs
The approved PRP had an anticipated total cost of $3,980,000, consisting of $3,788,000 in capital and
$192,000 in expense. The PRP costs as of November 2019 totaled $865,413 (which may not include all
participant costs), as shown in Table 32, based on data available to SCE.
Table 32. SCE Urban DCFC Clusters PRP Costs as of November 2019
Cost Category Actual SCE Costs Budgeted SCE Costs
Site assessment, design, and permitting
$ 181,086 N/A
Rebate amount paid $ 0 $ 1,495,000
EVSE procurement (subject to change)
N/A N/A
EVSE installation (subject to change)
N/A N/A
Make-ready infrastructure (utility side)
$ 214,854 $ 525,625
Make-ready infrastructure (customer side)
$ 334,808 $ 1,489,016
Other construction costs
N/A N/A
39 Paul Griffo, “EV Drivers Can Now Get a Fast Charge With a Slurpee at Pomona 7-Eleven,” Energized by Edison,
November 21, 2019, https://energized.edison.com/stories/ev-drivers-can-now-get-a-fast-charge-with-a-slurpee-
at-pomona-7-eleven
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 144
Cost Category Actual SCE Costs Budgeted SCE Costs
Project management $ 126,039 $ 395,526
Customer outreach (labor)
$ 0 N/A
Outreach and education materials
$ 8,627 N/A
Other program costs N/A $ 74,833
Total Cost $ 865,413 $ 3,980,000
Site assessment, design, and permitting was budgeted under the customer-side capital expense for make-
ready infrastructure. O&M non-labor and contract budget was budgeted under other program costs.
Two sites are located in a DAC (one is adjacent to a DAC), resulting in 39% ($274,000) of the reported
capital costs to date spent in DACs.
Customers are responsible for the cost to acquire, install, and maintain the EVSE, including energy cost
and network communications for up to five years. The pilot provided a rebate to offset the base cost of
the EVSE and installation only. Customers set the rate that drivers pay to use the charging stations.
The total amount of rebate that will be paid to each customer will be based on the model, type, size, and
number of EVSE ports the customer selects. Customers will receive a rebate after SCE installs and inspects
the EVSE and the customer provides the required documentation for cost verification. The EVSE and
installation base cost for the five sites is $521,970, amounting to a rebate of approximately $37,000 per DCFC
port including installation based on 14 ports installed. No rebates have been paid to the customers yet.
Benefits
The pilot provides new charging options in certain urban areas for EV drivers, while requiring
participation in a DR program to limit grid impacts. DR is a preferred resource for meeting new
generation capacity demand in California under the state’s Energy Action Plans. The pilot also offers
potential environmental benefits. The pilot aims to increase EV adoption, which potentially increases
alternative fuels, improves air quality, and reduces GHG emissions.
Table 33. SCE Urban DCFC Clusters PRP benefits
Anticipated in Testimony
(up to 50 DCFC ports)
Anticipated as Planned
(14 DCFC ports)
As Implemented As Optimized
Petroleum Reduction
N/A N/A TBD TBD
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 145
Anticipated in Testimony
(up to 50 DCFC ports)
Anticipated as Planned
(14 DCFC ports)
As Implemented As Optimized
GHG Emissions N/A N/A TBD TBD
Criteria Pollutants
N/A N/A TBD TBD
DAC Impact N/A 3 sites in a DAC, 2 within 1.5 miles of a DAC
TBD TBD
Operations, Maintenance, and Fuel Costs
N/A N/A TBD TBD
Other Co-Benefits
N/A N/A TBD TBD
Operational Impacts of Project Equipment
No EV charging under this PRP was provided as of this interim report. This section will be completed for
the final report, utilizing all information and data obtained before November 2020.
Stakeholder and Customer Feedback
No EV charging under this PRP was provided as of this interim report, so this feedback could not be
captured. Feedback pertaining to initial project implementation is captured in Section 0. This section will
be completed for the final report, utilizing all information and data obtained before November 2020.
3.4.4 Conclusions and Recommendations
Findings
With no EV charging under this PRP being provided to date, it is too early to determine this PRP’s
success, which will be documented in the final report. However, some preliminary findings, in addition
to the lessons learned shared previously, are mentioned below.
The make-ready construction planning, design, and execution seem to have gone smoothly.
Make-ready costs and construction durations were within expected budget and timelines. With
the exception of higher power levels for DCFCs, the infrastructure installation process was
similar to the Charge Ready Pilot with which SCE has much experience based on more than
1,000 installed ports.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 146
Next Steps
A recommendation pertaining to this project’s potential for scaling up and conditions under which it
would be recommended cannot be determined at this time but will be included in the final report.
3.5 Charge Ready Home Installation Rebate Program
3.5.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
SCE staff designed the Charge Ready Home Installation Rebate Program (CRHIRP) to help new EV drivers
offset the electrical and permitting costs of installing an alternating current L2 home EVSE (commonly
referred to as a “charging station”). Eligible electrical costs included the installation of a new 240 V
circuit and breaker, along with a new or upgraded electrical panel if needed, but excluded the cost of
the L2 charging station itself.
Staff identified a lack of access to reliable daily charging stations as a key barrier to EV adoption.40 By
lowering the cost of installing L2 home charging stations, the CRHIRP should encourage more residential
customers to purchase EVs. Staff also sought to learn about L2 home charging needs, costs associated
with home EV infrastructure upgrades, customer behavior after installing L2 home charging, and
customer satisfaction with residential TOU rates.
Through the CRHIRP, SCE offered two levels of rebates to eligible customers. To be eligible for either
rebate, customers had to be California-registered EV drivers who purchased or leased an EV listed on
the HOV Eligibility List41 within six months prior to submitting their rebate applications. In addition,
customers had to have a dedicated parking space for the vehicle. Finally, for either rebate, customers
had to provide copies of all required permits obtained and receipts for the installation of the charging
station by an electrical contractor with a C-10 license or licensed electrician. Finally, each customer had
to agree that SCE may complete random spot checks at the customer residence to confirm that the work
was performed.
Once eligible, SCE customers could apply for one of two rebates:
$500 for customers who enrolled in SCE’s whole-home TOU program.
$1,500 for customers who installed a meter specifically for the EV charging station to participate
in SCE’s TOU-EV-1 rate (applied only to the EV charging) for at least 24 months.
SCE contracted with a third-party administrator, the Center for Sustainable Energy (CSE, or the Center),
to manage application processing, rebate distribution, major marketing activities, customer support, and
40 “Charge Ready Home Installation Rebate Pilot 2018 Interim Report.” Issued January 31, 2019, by Anna Valdberg
and Andrea L. Tozer, attorneys for Southern California Edison Company. 41 The HOV Eligibility List can be found on https://ww2.arb.ca.gov/carpool-stickers. Note: electric bikes,
motorcycles, scooters, and neighborhood vehicles are not eligible for the rebate.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 147
an online application portal. CSE provided regular updates to SCE (weekly during the launch and
beginning of the program, then biweekly thereafter) regarding program participation statistics
throughout the PRP duration (May 2018–May 2019).
Participation
Recruitment Process
Because CSE also manages the Clean Vehicle Rebate Project (CVRP),42 staff easily cross-promoted
CRHIRP to CVRP participants who opted in to receive more information about EV rebates. Each of these
opt-in CVRP participants received at least one email about the CRHIRP. Over the course of the CRHIRP
period, 57% (26,709 out of 45,697)43 of opt-in CVRP participants opened these emails, and 676
submitted rebate applications. The Center considered the email outreach to be the single most
successful recruitment process for the CRHIRP.
As another primary CRHIRP marketing strategy, CSE staff set up information booths at local events
within SCE territory where potential EV owners were likely to attend. These events included auto shows,
home improvement shows, large community events or festivals, and Earth Day events. In particular, the
Center prioritized events that would have attendance by a higher proportion of residents living in DACs.
At each of these events, CSE staff held conversations with individuals in English and Spanish and
distributed program materials. By the end of the program period, CSE marketed at 71 events, 56% (40
out of 71) of which were in DACs.
In addition to managing the direct email outreach to CVRP participants and attending local events, CSE
also conducted outreach to electricians, labor unions, car dealerships, automakers, and DAC property
managers. Outreach also included focused targeting of car dealerships within DACs. Overall, CSE staff
found these initiatives to be less effective. CSE staff also reported that DAC property managers indicated
that their residents had higher-priority concerns than EV adoption.
Finally, SCE completed some minor outreach through its general marketing efforts to promote EV
adoption and installation of home charging stations.
Participants
In total, SCE received 4,128 applications over the course of the program period. The applications for the
increased $1,500 rebate closed on February 28, 2019, because SCE discontinued the TOU-EV-1 rate.
Participants already enrolled in the rate will continue to be enrolled for the duration of their agreements
(24 months). CSE approved 2,670 of those applications, providing a 65% approval rate. A total of 17%
(713 out of 4,128) of the applications were considered ineligible, and 18% (745 of 4,128) were cancelled
by customers.44 Applicants reported average permit costs of $191 and average installation costs of
42 The CVRP allows California residents to receive up to $7,000 for the purchase or lease of a new eligible zero-
emission or plug-in hybrid light-duty vehicle (https://cleanvehiclerebate.org/eng). 43 Source: CSE Marketing tracking data. 44 Metrics are as of August 30, 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 148
$1,190. Other application deals—including DAC status, resident type, and EV make—are presented in
Figure 67 below.
Figure 67. Participant and application data
Source: CSE Final Dashboard (Application) Data. Percentages do not add up to 100% because of rounding.
Timeline and Status
The CPUC approved the CRHIRP in January 2018. In March 2018, SCE contracted with CSE to develop the
marketing plan, application processing operations, website, and online application portal. The online
application portal opened to the public on May 30, 2018, and the pilot accepted applications through
May 29, 2019. As of November 2019, the program was still waiting to wrap up while the final participant
checks were cashed.
3.5.2 Evaluation Methodology
Selected Methods and Rationale
In addition to the evaluation questions that apply to all PRPs and those specific to the Education and
Outreach PRPs, the evaluation questions listed below will be examined for this PRP.
• Are customers aware of permitting requirements?
• At what stages do customers drop out, and what causes customer attrition during the
application process?
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 149
The data collection sources utilized to evaluate this PRP include 1) PRP documents and application
dashboard data, 2) SCE and implementer interviews, and 3) the SCE participant survey.
Data Sources
The evaluator collected PRP information through numerous interactions, including the PRP kick-off
meeting, quarterly PAC update meetings, and other periodic calls or emails. In addition, the evaluation
team examined the following data sources: application dashboard data (e.g., days accrued between
steps taken in the application process and the number of applicants at each stage), presentations and
interim reports, marketing activities executed by the third-party administrator, and the SCE participant
survey results.
The evaluator also conducted IDIs with representatives from the SCE PRP management team and the
implementer to further understand the background on this project, identify roles and responsibilities,
assess stakeholder (SCE and implementer) experience in program delivery, and gather lessons learned.
3.5.3 Evaluation Findings
The evaluation findings presented in this interim report are based on the SCE and CSE staff interviews, SCE administered participant survey, and program document and data review.
Implementation Process
To execute the program, CSE managed the marketing, application, and rebate distribution processes
with SCE assistance and oversight. CSE created the program webpage and custom online application.
The Center also processed the submitted applications and verified that all eligibility requirements were
met before issuing the rebate check. If an applicant failed to provide any information, CSE staff followed
up to notify the applicant about what was missing and to offer help, if needed.
CSE provided biweekly status updates to keep SCE up to date on the program’s progress. To provide
transparent data to SCE, CSE staff members developed the program’s online dashboard, which delivered
key information to SCE. SCE staff could access the dashboard on demand to view details about the
number of applications at each stage (e.g., approved, check sent, canceled), average processing times,
residence types, percentage of DAC participants, and types of vehicles.
Overall, CSE staff indicated that program implementation went well. However, extensive application
requirements caused delays throughout the implementation process. SCE considered all application
requirements necessary to ensure participant safety and legality during the installation of the L2
charging stations. However, SCE staff recognized that the six-month time limit to submit an application
following an EV purchase or lease may have limited the number of eligible participants, given that an
individual may need more time to determine whether he or she needs or wants a home charging
station.
The application required six to nine separate documents (depending on applicable requirements such as
Homeowners’ Association (HOA) approval), with specific details for each kind of document. For example,
the invoice from the electrician had to have the C-10 license number listed. This delayed applications for
some applicants who had to request new invoices from their electricians. Similar problems arose for
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 150
individuals who did not need permission from their HOA or housing jurisdiction to install the charger but
were still required to provide formal documentation of HOA exemption. Occasionally, an applicant had
charging station costs embedded in the price of the vehicle and was unable to provide a separate receipt
for the cost of the charging station. SCE staff noted that these application requirements may have also
contributed to the program’s higher-than-expected drop-out rate (18%, 745 out of 4,128). Anecdotally,
CSE and SCE staff reported receiving feedback from customers who chose not to participate because
they did not use C-10 licensed electricians or did not have the proper permits.
Additionally, the application required that customers enroll in an active TOU rate plan. This meant that a
participant could not complete the application until his or her bill reflected the TOU rate. The delayed
application submission combined with some SCE processing staff limitations (including waiting for the
TOU rate to be in effect) to cause a one- to two-month delay in application approval.
Costs
Comparison of Actual and Forecast Costs
The approved PRP had an anticipated total cost of $3,999,000, consisting of $79,000 in capital and
$3,920,000 in expense. The PRP costs as of November 2019 totaled $2,113,420 (which may not include
all participant costs), as shown in Table 34, based on data available to SCE. The outreach and education
materials category includes O&M non-labor and third-party administrator contract cost.
Table 34. SCE Charge Ready Home Installation Rebate program PRP costs as of November 2019
Cost Category Actual SCE Costs Budgeted SCE Costs
Site assessment, design, and permitting N/A N/A
Rebate amount paid $ 1,399,533 $ 2,880,000
EVSE procurement (Subject to change) N/A N/A
EVSE installation (Subject to change) N/A N/A
Make-ready infrastructure (utility side) N/A N/A
Make-ready infrastructure (customer side) N/A N/A
Other construction costs N/A N/A
Project management $ 105,853 $ 262,068
Customer outreach (labor) N/A N/A
Outreach and education materials $ 608,034 $ 856,932
Other program costs N/A N/A
Total Cost $ 2,196,106 $ 3,999,000
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 151
Stakeholder and Customer Feedback
Addressing Customer Barriers to Electrification
SCE and CSE staff reported that the program was successful at overcoming the cost barrier for installing
charging infrastructure. Two data sources support their statement. In the rebate application, 70% (2,661
out of 3,785) of all applicants who answered the question indicated that the rebate had an influence on
their decision to purchase an EV.45 In the survey, 44% (474 out of 1,072) of respondents indicated the
rebate was important to their decision to purchase an EV. (Note the different population and different
wording and see Figure 68 for the survey question results.)
Figure 68. Rebate influence on EV purchase
Source: Participant Survey Question 6: “How much did this rebate influence you to purchase an electric vehicle?”
(n= 1,072)
Unless otherwise noted, the remainder of the statistics provided in this section refer to responses from
the participant surveys. A total of 93% of survey respondents (998 out of 1,071) indicated that the
program had at least some influence over their decision to install an L2 home charging station (Figure 69).
Figure 69. Rebate influence on L2 charger purchase
Source: Participant Survey Question 7: “How much did this rebate influence you to install an L2 home charging
station?” (n=1,071)
45 As noted above, the applicants include successful rebate recipients, dropouts, and ineligible customers.
14%
42%
26%
18%
0% 10% 20% 30% 40% 50%
Not at all
Was nice to have but only helped a little bit in my EVpurchase decision
Helped a fair amount to convince me to purchase an EV
Was very important in my EV purchase decision
Percentage of Survey Respondents
7%
21%
32%
40%
0% 10% 20% 30% 40% 50%
Not at all
Was nice to have but only helped a little bit in my EVpurchase decision
Helped a fair amount to convince me to purchase andEV
Was very important in my EV purchase decision
Percentage of Survey Respondents
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 152
Perceived Net Impacts
As shown in Figure 70, survey respondents commonly reported that they replaced an existing gasoline
vehicle (71%, 627 out of 877) or added an EV to the household (19%, 164 out of 877), which reduces the
number of miles they drive in their other vehicle(s) fueled by gasoline. Three of the eight survey
respondents who answered Other to this question already had at least one EV and were adding another.
Figure 70. EV purchase description
Source: Participant Survey Question 26: “Which of the following best describes your EV purchase?” (n=877)
Many survey respondents reported that they always take their EVs on local (58%, 494 out of 852) or
long-distance (41%, 348 out of 858) trips that they would have previously taken in their gasoline
vehicles. In addition, customers indicated to SCE and CSE staff that increased flexibility and convenience
in charging (being able to charge at home with the L2 charging station) has allowed them to use their
EVs more often. However, as shown in Figure 71, many survey respondents also indicated they used EVs
for local or long-distance trips that they previously would have taken using another mode of transportation,
such as walking, biking, public transit, carpool, or flying, which may have either a positive or negative
emissions impact.
Figure 71. EV influence on travel behaviors
Source: Participant Survey Question 27: “How often are the following statements true about your household
travel?”
1%
3%
6%
19%
71%
0% 20% 40% 60% 80%
Other (please specify)
Adds a vehicle to my household, and is my onlyvehicle
Replaces an existing EV owned within my household
Adds a vehicle to my household, and reduces theamount of miles I drive my other gasoline vehicle(s)
Replaces an existing gasoline vehicle owned within myhousehold
Percentage of Survey Respondents
15%
17%
41%
58%
12%
15%
30%
29%
6%
8%
12%
5%
14%
18%
15%
6%
52%
43%
3%
2%
0% 10% 20% 30% 40% 50% 60% 70%
We would have taken the local trips (<40 miles) someother way (e.g. transit, bike, walk, carpool) that we now
take in our EV (n=828)
We take long distance (>40 miles) trips in our EV thatwe would previously have taken some other way (e.g.
transit, carpool, inter-city rail, fly) (n=833)
We take long distance (>40 miles) trips in our EV thatwe would previously have taken in a gasoline vehicle
(n=858)
We would have taken the local trips (<40 miles) in agasoline vehicle that we now take in our EV (n=852)
Never Some of the time Half of the time Most of the time Always
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 153
Installing an L2 charging station can affect a customer’s charging and driving habits. Because the
program requires the applicant to enroll in a TOU rate, charging timing and cost can also change. Most
survey respondents (57%, 520 out of 911) strongly believed that enrolling in the TOU rate allowed them
to charge their EVs for less than under their old non-TOU rate. Additionally, survey respondents
reported that they pay attention to the TOU period (peak versus off-peak) when they charge their EVs
(94%, 803 out of 926; Figure 72).
Figure 72. Charging and cost changes from TOU rate
Source: Participant Survey Question 11: “Please rate how much you agree or disagree with each of the following
statements about the Time-of-Use (TOU) rate you are on.”
Most survey respondents reported taking an increased number of trips in their EVs after installing their
L2 charging stations (52%, 447 out of 862). Of those who increased the number of trips, most added one
to five additional EV trips (70%, 283 out of 405) per week (Figure 73).46,47
46 Though this question was only asked to individuals who indicated they take additional trips in their EVs, when
asked to specify, 25 (6%, 25 out of 430) indicated they take zero additional trips. These individuals have been
excluded from the total numbers and percentages in the text above. 47 Six individuals noted that they take more than 60 additional trips per week. The evaluation team hypothesizes
these individuals could be drivers for ride-share services.
17% 19%
7%
57%
87%
0% 20% 40% 60% 80% 100%
The TOU rate allows me to charge my EV cheaper than myold (non-TOU) rate (n=911)
I pay attention to what Time-of-Use period (i.e. Peak vs.Off-Peak) it is when I charge my vehicle (n=926)
Disagree Strongly - 1 2 3 4 Agree Strongly - 5
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 154
Figure 73. Number of additional trips per week
Source: Participant Survey Question 31: “How many additional trips in your electric vehicle per week do you take
now? Please enter a numerical response.” (n=405)
Perceived Co-Benefits
SCE staff, CSE staff, and survey respondents all recognized that the program promoted several co-
benefits, such as lowering the cost of installing a charging station, imparting education about at-home
charging, and providing the convenience of charging at home.
Within the application, applicants were asked to identify one factor that described why they acquired
EVs. Figure 74 shows that most applicants wanted to save money on fuel costs (32%, 1,278 out of 3,995)
or decrease their environmental impacts (29%, 1,159 out of 3,995). Note that this statistic is associated
with the overall applicant pool, rather than the survey respondents.
Figure 74. Motivation for Purchasing an EV
Source: Application Data (n=3,995)
70%
12%4%
1%0%
10%
20%
30%
40%
50%
60%
70%
80%
1 to 5 10 to 15 20 to 30 60+
Perc
enta
ge o
f S
urv
ey
Resp
ondents
Number of Additional Trips per Week
2%
3%
3%
7%
8%
17%
29%
32%
0% 10% 20% 30% 40%
Convenience of charging
Energy independence
Vehicle performance
Carpool lane access
Driving new technology
Saving money overall
Environmental impact
Saving money on fuel costs
Percentage of Applicants
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 155
Survey respondents reported the benefits they experienced from a list of seven co-benefits that could
result from purchasing an EV (Figure 75). Most survey respondents experienced six of the seven:
decreased fuel costs (91%, 806 out of 882), smoother driving with no gear shifts (80%, 708 out of 882),
faster acceleration from stop (79%, 695 out of 882), decreased vehicle maintenance costs (78%, 692 out
of 882), decreased vehicle-related noise (78%, 684 out of 882), and increased ride-share lane access
(65%, 577 out of 882). “Other” reported benefits included increased safety or advanced technology
features (19 survey respondents), better overall driving experience (17 survey respondents), creating
less pollution/having a positive environmental impact (16 survey respondents), and fewer trips to gas
stations (9 survey respondents).
Figure 75. Benefits experienced as a result of EV purchase
Source: Participant Survey Question 28: “Have you experienced any of the following as a result of purchasing your
electric vehicle?” (n=882, multiple responses allowed)
In addition to participant co-benefits, SCE staff designed the program to prioritize benefits to individuals
living in DACs. The PRP had a goal of 50% of the rebate funds going toward applicants in DACs. To
achieve this, CSE staff prioritized DAC marketing tactics, including attending events with English- and
Spanish-speaking staff and talking to businesses, property managers, and contractors within DACs.
Despite these efforts, only 7% (278 of 4,128) of all applications came from individuals living in DACs. SCE
and CSE staff found that many individuals within DACs live in MUDs. These individuals often do not have
dedicated parking spaces or may not pay their electric bills directly, both of which were requirements
for rebate eligibility. Additionally, CSE staff received feedback from DAC property managers indicating
that “residents have bigger problems than EVs.”
Stakeholder Experience
CSE staff expressed an overall positive experience working with SCE staff. Additionally, Center staff
appreciated that SCE was open and receptive to feedback and solicited input, as appropriate,
throughout the program period.
However, in their final lessons learned memo, CSE staff identified some program challenges, such as
difficulty transitioning applicants to the TOU rate, especially the TOU-EV-1 rate, which was discontinued
7%
48%
65%
78%
78%
79%
80%
91%
0% 20% 40% 60% 80% 100%
Other
Free parking/charging
Increased ride-share (HOV) lane access
Decreased vehicle related noise
Decreased vehicle maintenance costs
Faster acceleration from stop
Smoother driving with no gear shirts
Decreased cost of fueling your vehicle
Percentage of Survey Respondents
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 156
in the middle of the program. CSE reported that it was difficult to provide customers with accurate
status updates regarding their TOU rates because the Center did not have a specific point of contact at
SCE for such questions and because the Center did not have direct access to customer data. Additionally,
CSE indicated that information relayed to customers about the program’s timeline and requirements
was sometimes “lost in translation” with the SCE customer call center. In an attempt to minimize the
impact of this “translation” issue, SCE staff instructed customer call center employees to refer
customers inquiring about application requirements directly to CSE.
Customer Program Experience
Overall, from the perspectives of CSE and SCE staff, as well as from the survey respondents themselves,
customers were generally satisfied with the program. However, CSE staff reported that the permitting
process often confused applicants. Requirements from cities and towns could be unclear, and CSE had
limited resources to help assist applicants from all the numerous jurisdictions. Additionally, issues with
inconsistent invoicing and receipts from car dealerships and electricians, permission inquiries to HOAs,
and lag time for TOU rates to go into effect made it difficult for applicants to complete their applications
in a timely manner. It should be noted, however, that most of the applicants with whom CSE staff
directly interacted were more likely to be the ones with problems because those were the applicants
reaching out to CSE for assistance.
Survey respondents answered several questions about their satisfaction with the program and individual
components of the program on a scale of 1 (poor) to 5 (excellent). Most survey respondents reported
having a positive experience with the program overall (92%, 1,030 out of 1,128). A small minority of the
dissatisfied respondents cited specific drivers of their dissatisfaction, the most common being the
complexity of the application process (14 survey respondents). Other issues stemmed from customer
service (8 survey respondents), lengthy rebate delivery time (5 survey respondents), length of time to
switch to the TOU (2 survey respondents), and an increase in the electricity bill since the start of
program participation (1 survey respondent).
Within the application process, most survey respondents had an excellent experience creating an
account (69%, 738 out of 1,072), filling out the application with personal information (66%, 695 out of
1,060), uploading documents for the application (57%, 614 out of 1,070), and the overall application
experience (57%, 612 out of 1,068) (see Figure 76).
Figure 76. Participant experience with application
Source: Participant Survey Question 2: “How would you rate the following aspects of applying for the rebate?”
8%
11%
7%
6%
32%
26%
26%
24%
57%
57%
66%
69%
0% 20% 40% 60% 80% 100%
Overall application experience (n=1068)
Uploading documents for the application (n=1070)
Filling out the application personal information(n=1060)
Creating an account (n=1072)
Poor - 1 2 3 4 Excellent - 5
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 157
The majority of survey respondents also found most aspects of their electrical upgrade contractor
experience to be excellent: timeliness of the upgrade work (67%, 686 out of 1,020), competence of the
contractor (65%, 667 out of 1,026), and overall contractor experience (59%, 601 out of 1,022); however,
respondents did identify some room for improvement with price (Figure 77).
Figure 77. Participant experience with contractor
Source: Participant Survey Question 3: “How would you rate the following aspects of your electrical upgrade
contractor experience?”
In addition, survey respondents reported as excellent the amount of the rebate (49%, 530 out of 1,086)
and the timeliness of receiving the rebate (37%, 398 out of 1,082). Overall, almost half of survey
respondents (49%, 523 out of 1,079) had an excellent rebate experience (see Figure 78).
Figure 78. Participant experience with rebate
Source: Participant Survey Question 4: “How would you rate the following aspects of the rebate itself?”
More than half the survey respondents found all aspects of the communication process to be excellent:
accuracy of communications (60%, 617 out of 1,022), timeliness of communications (55%, 564 out of
1,026), amount of communications (53%, 550 out of 1,029), and the overall communications experience
(57%, 576 out of 1,014) (see Figure 79). Additionally, the majority of survey respondents had excellent
experiences with SCE’s customer service (60%, 353 out of 588).
7%
8%
21%
8%
7%
31%
32%
25%
24%
59%
39%
65%
67%
0% 20% 40% 60% 80% 100%
Overall contractor experience (n=1022)
Price of the upgrades (n=1026)
Competence of the contractor (n=1026)
Timeliness of the upgrade work (n=1020)
Poor - 1 2 3 4 Excellent - 5
6% 9%
12%
18%
16%
36%
30%
29%
49%
37%
49%
0% 20% 40% 60% 80% 100%
Overall rebate experience (n=1079)
Timeliness of receiving the rebate (n=1082)
Amount of the rebate (n=1086)
Poor - 1 2 3 4 Excellent - 5
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 158
Figure 79. Participant experience with communications
Source: Participant Survey Question 5: “How would you rate the communications throughout the process?”
Most survey respondents transitioned to the TOU rate as a part of the application process. Of those that
did transition, 51% (411 out of 813) had excellent experiences with the ease of transition and the
accuracy of billing after the transition (50%, 403 out of 810). Many survey respondents also had
excellent experiences with the timeliness of the transition (48%, 382 out of 804) and the overall
transition experience (47%, 381 out of 814) (see Figure 80). Overall, survey respondents reported being
satisfied with their TOU rates, with 62% (601 out of 967) providing a rating of 8 or higher on a scale of 1
(extremely dissatisfied) to 10 (extremely satisfied) (see Figure 81).
Figure 80. Participant experience with TOU transition
Source: Participant Survey Question 14: “How would you rate the following aspects of the transition to a Time-of-
Use rate (TOU) as part of the rebate process?”
11%
13%
13%
10%
28%
29%
27%
26%
57%
53%
55%
60%
0% 20% 40% 60% 80% 100%
Overall communications experience (n=1014)
Amount of communications (n=1029)
Timeliness of communications (n=1026)
Accuracy of communications (n=1022)
Poor - 1 2 3 4 Excellent - 5
6%
5%
13%
14%
13%
14%
31%
29%
28%
28%
47%
48%
50%
51%
0% 20% 40% 60% 80% 100%
Overall transition experience (n=814)
Timeliness of the transition (n=804)
Accuracy of the billing since the transition (n=810)
Ease of the transition (n=813)
Poor - 1 2 3 4 Excellent - 5
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 159
Figure 81. Overall participant satisfaction with TOU rate
Source: Participant Survey Question 15: “Overall, how would you rate your satisfaction with the Time-of-Use rate
plan your household is on?”
Finally, most survey respondents reported that it was easy to find a qualified electrician to install the
charging station (70%, 638 out of 908) and complete the permitting process (58%, 524 out of 901).
However, when asked what SCE could do to help address their difficulties with these aspects of the
program, 30% (65 out of 218) of survey respondents complained that city permitting is an arduous,
expensive process that is not always necessary when work is done by a licensed electrician, and they
requested relaxed permitting requirements. A total of 14% (30 out of 218) of survey respondents
indicated that providing a preferred list of contractors by area would have been helpful when they were
looking for trustworthy electricians. Finally, some individuals with HOAs would like to see more flexible
HOA requirements (14%, 31 out of 218). CSE staff and eight survey respondents noted that HOAs were
often confused by survey respondents’ requests because charging stations were installed inside garages,
where HOAs typically do not have jurisdiction. Some survey respondents provided feedback on other
aspects of the program, such as providing better program communication (12%, 27 out of 218), improving
the TOU rate (11%, 25 out of 218), increasing the amount of the rebate (5%, ten out of 218), delivering
the rebate faster (4%, eight out of 218), or making it easier to upload the application (2%, four out of 218).
Overall, the responses to these questions show that most survey respondents responded positively to
each aspect of the program evaluated (more than 50% giving a 4 or 5 out of 5 rating), including their
experience with the application process, their electrical upgrade and contractor experience, the rebate
process, SCE communications through the process, the TOU rate transition, and the program overall.
3.5.4 Conclusions and Recommendations
Findings
Throughout the last year, SCE and CSE staff identified successes and critical lessons that may be applied
to similar future endeavors. These successes and lessons are presented below as preliminary
conclusions, with supporting findings and recommendations.
3.60%1.30% 1.20%
2.60%
7.90% 6.80%
14.40%
19.90%
13.70%
28.60%
0%
10%
20%
30%
40%
1 2 3 4 5 6 7 8 9 10
Perc
enta
ge o
f R
esp
ondents
Satisfaction Rating
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 160
Although customers who successfully completed the rebate process were generally highly
satisfied with the program, the necessary requirements may have limited participation. In
particular, some application requirements were challenging for participants to complete
correctly and for the implementer to monitor. For example, requiring documented proof of a
waiver for HOA permission or city permitting created roadblocks for applicants who did not
need those documents. Other documentation, such as a separate receipt for the charging
station or C-10 license numbers on electrician invoices, caused problems for applicants who
needed special invoices printed for the program. In addition, both CSE and SCE staff reflected
that the six-month time restraint on purchase/lease date of a new EV may have limited
participation because it can take EV adopters more time to understand their charging needs.
Recommendation: If SCE explores a similar program in the future, the utility might consider
structuring requirements in a simpler format. For example, individuals who do not have HOAs or
whose cities do not require permits to install an L2 charger could potentially click a box on the
application form and sign to confirm, relieving SCE of any liability while also reducing application
processing time. Similarly, if the C-10 license number of the electrician is not already on the
invoice, an applicant could include this number on the application form itself. Finally, because
this program is not rebating the cost of the charging station, requiring proof of the charging
station cost may not be necessary, especially as applicants are required to submit other forms of
proof of the charging station installation, such as a photo and receipt for the infrastructure
work.
Despite regular communication between CSE and SCE staff, program requirements (e.g., TOU
rate) necessitated the need for greater coordination within SCE departments, as well with CSE.
During the program, SCE and CSE staff met at least biweekly to review program status, and SCE
and CSE staff both expressed general satisfaction with the communication throughout the
process. However, both also noted that there were times that additional up-front planning and
coordination were needed. For example, CSE was not able to successfully engage stakeholders
such as electricians or MUD managers, who could have become champions of the program.
There were also several unforeseen issues with validating applicants’ TOU rates during the
process, causing delays in application processing time. For example, the TOU-EV-1 rate ended in
the middle of the program, which led to internal SCE misunderstandings about how soon an
applicant had to switch to a TOU-EV-1 rate before the rate was shut off to any additional SCE
customers. CSE also noted a disconnect in the information that applicants were receiving from
SCE call center staff, though SCE did make efforts to minimize this issue by directing applicants
to contact CSE directly.
Recommendation: If offering a similar future program, SCE may consider designing a marketing
trategy that includes more lead time to meet with key stakeholders—such as electricians, MUD
property managers, and city officials who will be helping applicants with their permits—before
program launch. Educating these stakeholders to encourage them to become “champions” of
the program could help increase participation while simultaneously making it easier for
applicants to complete the process.
Recommendation: If offering a similar future program, SCE may explore greater internal
coordination within the departments at SCE (such as the rates, information technology, and
program departments) when there are program processes (such as the validation of customers
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 161
switching to a TOU rate) that depend on the efforts of multiple departments. This coordination
may also include any future third-party administrator who will be working with customers
individually to ensure that all data request, or status update, needs are being met.
The program successfully reduced barriers to EV adoption by providing a financial rebate for
home charging infrastructure, which resulted in positive impacts for participants. However, as
currently designed, MUD residents continued to face challenges with L2 charging station
installations. The program successfully encouraged the installation of home charging stations
and spurred residential customers to purchase EVs, as evidenced by the 70% (2,661 out of
3,785) of all applicants who indicated that the rebate had an influence on their decision to
purchase an EV. Additionally, participant feedback corresponded with SCE and CSE staff
feedback, indicating that participants now benefit from more flexible, convenient charging in
their homes. The program, as piloted, also helped confirm that at-home charging is actively
desired by EV owners. However, the implementer struggled to engage individuals living in DACs
and/or MUDs, despite targeted marketing efforts. With the program requiring an applicant to
have a dedicated parking spot for the EV for 24 months and to switch to a TOU rate, two items
that many MUD residents cannot ensure, most of the individuals in DACs or MUDs who might
have been interested in buying EVs were ineligible for this program. Additionally, despite having
Spanish-speaking individuals at marketing events and Spanish turnkey documents, there was
not a Spanish language option for the application itself.
Recommendation: If offering a similar future program, SCE may want to explore alternative
requirements and/or engagement approaches in the program design to address MUD and DAC
customer barriers and speak to key participant motivations.
Marketing effectiveness may be enhanced through more robust tracking. Although CSE
documented several marketing and outreach efforts (including sending out CVRP emails,
attending events, and visiting car dealerships), other efforts did not appear to be tracked. In
particular, conversations or meetings with other key stakeholders—such as MUD property
managers or electricians—were not tracked with sufficient detail to be thoroughly reviewed.
Recommendation: The program should include metrics for all marketing and outreach strategies
and evaluate effectiveness to ensure marketing investment focuses on the most effective
strategies.
Next Steps
As of November 2019, SCE staff were working with CSE to officially close out the program. Although SCE
staff indicated that they do not intend to scale up this program, they will continue to support EV
adoption through other initiatives and incorporate lessons learned from this program. If SCE considers
launching a similar program in the future, educating key players who would play crucial roles in the
program (such as electricians and city permitting offices) may ease the path for customer participation.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 162
4. Pacific Gas and Electric
PG&E’s PRPs comprise three infrastructure projects for MD/HD vehicles and one customer outreach and
education project. This design spread the utility’s investment across the light-, medium-, and heavy-duty
market segments. According to interviews with PG&E staff, PG&E conceived of its infrastructure PRPs as
a portfolio that would enable the utility to gain experience in the major market sectors the staff
expected to work most closely with during the SRPs. The intent was to use the PRPs to conduct
exploratory research in key market segments to understand how fleet customers are using their assets,
what the major challenges were for electrification, and whether a case could be made that
electrification was a cost-effective investment that would meet operational needs while reducing total
cost of ownership (TCO). As much as possible, PG&E aimed to have these projects demonstrate how
fleets could function as controlled loads and serve as grid assets. As such, PG&E selected three sectors
considered particularly ripe for electrification for the three infrastructure PRPs: school buses, transit
buses, and electric transport refrigeration units (eTRUs). As of Q3 2019, the top two categories of
applications to PG&E’s EV Fleet SRP were school districts and transit agencies, demonstrating the value
of PG&E’s approach to using the PRPs to develop lessons learned in how to work with such customers.48
eTRUs rank fifth, behind miscellaneous MD/HD vehicles, demonstrating that they were also an
important sector in which to develop early experience.
Additionally, PG&E’s PRPs were designed to prove the viability of concepts where existing solutions had
not yet reached full maturity and to provide positive customer experiences among early adopters.
Providing these positive customer experiences could be achieved only by more extensive assistance
through the process and was believed to be important to enhance interest in future PG&E programs,
such as the EV Fleet program. For instance, without charging management, some fleet customers were
paying substantially more per mile to operate electric buses than they would have paid for diesel
hybrids, and PG&E was in a unique position to help customers reduce charging costs. Similarly, some
fleets experienced challenges finding the right technologies to charge their buses or selecting the best
equipment and software. The hands-on approach that the PRPs enabled has provided an opportunity for
PG&E to develop knowledge and capacity to better serve future customers as they electrify their fleets.
4.1 Electric School Bus Renewables Integration Project – Pittsburg Unified School District
4.1.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
The objective of this pilot is to work with a school district to understand how electric school buses can
align charging with peak periods of renewable energy generation. Electrified transportation is seen as a
promising approach to addressing the glut of electricity supply at midday and subsequent ramping
needs in the afternoon. The duty cycle of school buses, with their predictable routes and midday break
48 PG&E Q3 2019 PAC meeting presentation.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 163
period, is well-suited to match this supply curve. There are some market programs in place that might
incentivize school bus fleet operators to provide these balancing services to the grid, such as the Excess
Supply Demand Response Pilot (XSP), and this pilot explores how well these programs fit the context of
electric school buses in practice.49 Likewise, the school district facility is equipped with both solar and
wind generators, creating a ripe environment to explore integration with onsite renewables.
This pilot was designed to address several barriers to widespread adoption of school bus electrification.
For one, this pilot aims to investigate uncertainty around technological readiness of vehicles (capacity,
range, torque, etc.) and chargers (software/hardware configuration, communication with charge
management system, ease of use, etc.). Another challenge is that school districts may not have staff
with sufficient technical expertise to make informed decisions related to procurement and
implementation of novel renewable and electrified transport infrastructure. There is also the question of
whether school bus fleets have enough operational flexibility and economic incentive to adjust their
loads dynamically and strategically to integrate renewable energy generation.
The objectives of this project are to (1) demonstrate reduced TCO by minimizing infrastructure and fuel
costs, and (2) demonstrate the ability of electrified school bus fleets to support the integration of
renewable generation from both onsite and grid resources. Managed charging and a new rate structure
can help school districts avoid charging during expensive times and capitalize on new value streams.
This evaluation is an interim report covering stages of the PRP that have been completed: scoping and
customer acquisition, project design and preparation, construction, and commissioning. The project is
now actively operating, and data collection is under way. Analysis of these data and concluding lessons
learned will be covered in the final evaluation report.
Sites and Participants
Recruitment of Site Host
PG&E aimed to partner with a school bus district that already had an electric bus or had received grant
funding and was in the process of purchasing an electric bus. By engaging both internal (PG&E’s Business
Energy Solutions Team) and external (A-Z Bus Sales) partners, PG&E was able to identify which districts
met these criteria.50
Site Host
The site host in this PRP, Pittsburg Unified School District (PUSD), is a K-12 school district serving over
11,000 students at 13 school sites in the San Francisco Bay Area. The district operates a fleet of 30 buses
49 XSP tests the capabilities of price-responsive demand-side resources to shift or increase load as a service to the
grid during times of anticipated excess supply of renewables generation and/or negative wholesale energy prices.
Depending on market conditions, participants may be asked to increase their usage during certain hours of the day
(https://www.pge.com/en_US/large-business/save-energy-and-money/energy-management-programs/energy-
incentives.page). 50See a more detailed description in PG&E’s Interim Priority Review Report:
http://docs.cpuc.ca.gov/SearchRes.aspx?DocFormat=ALL&DocID=285086006.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 164
including ten type-C (large) diesel school buses, fourteen type-A (smaller) propane-fueled buses
dedicated to transportation of special education students, three gasoline buses, two eLion type-C
electric buses purchased in 2018, and one Blue Bird type-D electric bus delivered in October 2019. Buses
are used daily for student commutes to and from school, as well as for student activities such as athletic
events and field trips. PUSD did not have any electric buses or onsite renewables before the initiation of
the project, though the district did have grant funds secured for the acquisition of electric buses.
Site
The electrical infrastructure associated with this PRP is located in the single bus yard at 3200 Loveridge
Road (Pittsburg, California), adjacent to the district’s main high school and nutrition services
department, as well as an elementary school. PG&E installed nine Clipper Creek CS-100 chargers on site.
The CS-100 chargers are behind a locked gate and can be accessed only by PUSD staff. PUSD bus drivers
are expected to plug in the electric buses when they park on site. Since there is no need for payment or
other advanced features, PUSD opted for the low-cost CS-100 chargers. District staff were particularly
interested in minimizing ongoing network costs associated with more complex networked chargers.
Given that many other districts may also opt for low-cost chargers, this site provides extra value by
partnering with vendors to test the concept of managed charging with low-cost, non-networked
chargers. Another unique aspect of the site is that PUSD built a learning center for students to engage
with the project. The district’s experience with the learning center may provide useful insights to PG&E
going forward.
An overview diagram of PUSD’s onsite energy resources is provided in Figure 82, and a satellite image of
the site with charger locations is provided in Figure 83.
Source: PG&E 2018 Interim Report
Figure 82. Diagram of PUSD onsite energy resources
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 165
Figure 83. Schematic of the installed project infrastructure at PUSD
Source: PG&E 2018 Interim Report
Recruitment of Implementers and Additional Vendors
In addition to PUSD, there were several other parties involved in the project that have provided
engineering, installation, charging services, and equipment. EVSE was provided by Clipper Creek, Liberty
Plugins provided a hardware/software solution that networks all the Clipper Creek chargers at a central
control box, and Olivine, Inc., provided optimization, volunteered geographic information (VGI)
guidance, and additional software services.
These additional charging management services were needed because the district chose to install non-
networked chargers, which could not otherwise have been used for the energy optimization and
renewables integration. PUSD and PG&E identified key requirements against which nine potential
solutions were evaluated. After product presentations were made by the vendors, PUSD and PG&E
selected Olivine and Liberty Plugins. Although Olivine and Liberty Plugins responded to the solution
separately, PUSD believed the best value came through requesting an integrated solution that involved
both vendors in the following roles:
Liberty Plugins was selected as the load management system because of its certification through
the Open Automated Demand Response (OpenADR) 2.0b protocol (which demonstrates they
can receive and act upon automated demand response messages), cost-competitiveness, and
experience working on MD/HD vehicle projects with Clipper Creek Chargers.
Olivine, Inc., offers software-as-a-service that integrates with Liberty Plugins to provide an
energy optimization platform. Olivine was selected for its experience administering PG&E’s XSP
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 166
program, OpenADR 2.0b experience (as a Demand Response Platform Provider), affordability,
and incorporation of user interface components desired by PUSD (e.g., a web widget).
Timeline
Original Planned Timeline
Figure 84 below illustrates the original timeline (pale blue fill) and the achieved timeline (medium blue
fill) for the PUSD PRP. This divergence reflects a variety of disruptions and challenges, many of which
were unforeseeable by PG&E or the site host.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 167
Figure 84. PUSD PRP project timeline
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 168
The original timeline for the PUSD PRP design and construction period was planned so one calendar year
would remain for data collection and determining lessons learned prior to project completion in 2020.
Project milestones included site enrollment, finalization of the design, completion of construction, and
commissioning of the chargers. Chargers were operational on January 12, 2019.
Explanation of Notable Timeline Alterations
There were some instances in which the actual project timeline diverged from original plans. For one,
while conversations about the project were initiated in April 2018, the project could not commence until
the contract received approval from the PUSD school board, which meets only once or twice per month.
Approval from the school board was conveyed in mid-June, slightly behind the original timeline. External
factors then caused more substantial delays. The date on which the PRP project was scheduled to be
energized was pushed back three months when PG&E resources were redirected to fire restoration
efforts. Additionally, tests of managed charging protocols that were scheduled for completion toward
the end of the 2018–2019 school year needed to be delayed an extra three months because of summer
break. This delay reflects how the unique governance and operational characteristics of schools may
constrain project implementation timelines.
Lesson Learned: Contracting, construction, and implementing test protocols with schools may require planning extra time as a buffer to reflect their unique contracting processes and seasonal operational patterns.
Planned PRP Activities and Current Status
Current Status
Currently PUSD operates three battery electric school buses. Two eLion buses were procured first and
have been owned and operated by the district since March 2018. These are 64-passenger versions of the
LionC, a Type C school bus. Initially the buses were charged on 7.2 kW AC L2 chargers that were installed
for light-duty EVs. With the commissioning of the Clipper Creek chargers in January 2019, the buses have
been served by 19 kW AC L2 chargers, and all future electric buses will use these chargers in the bus
yard. These chargers are paired with load management software and energy optimization services.
The third electric bus is a Blue Bird, which was delivered in October 2019. Another Blue Bird electric bus
is scheduled for delivery in January 2020. These vehicles are the 78-passenger Blue Bird model T3RE
3904, a Type D school bus. PUSD had planned to add an additional seven vehicles spread across four
manufacturers (Lion Electric Company, GreenPower, Blue Bird Corporation, and TransTech) to allow for
comparison. However, the district has since concluded that the Blue Bird models best suit its needs
because they have larger student capacity and longer range. Given the need for maximizing operational
flexibility, PUSD has therefore determined that it will procure the remainder of the buses from Blue Bird.
Construction Update
All PRP construction activities are complete. Construction included procurement and installation of nine
19 kW Clipper Creek CS-100 chargers. This involved putting in a new transformer, switchboard, and
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 169
electrical conduit. The project also included laying conduit for cables that would carry data from
chargers to the Liberty Plugins Hydra charge management system.
The onsite renewables generation projects are not part of the PRP, but their progress affects the
proposed PRP test phases. Both the solar and the wind systems were installed in the spring of 2019 but
have faced interconnection delays. Because of concerns about exceeding the hosting capacity on the
existing PG&E transformer, only five PV inverters for approximately 130 kW AC total were connected on
conditional Permission to Operate as of August 1, 2019, with a remaining 30 kW AC connected as of
December 3, 2019, once these concerns were resolved. The wind energy system (40 kW) is also waiting
on interconnection approval because of an issue with the certification of its inverters. The wind is not
expected to be interconnected until early 2020.
Ongoing and Upcoming Tests
Test phases have been planned to investigate how well the project can meet the PRP goals. Because the
objectives include understanding the level of complexity in charge management that can be achieved
even when employing very simple charging hardware, the tests are mostly additive in their sequencing.
Phase 0 – Baseline (Conducted January–April 2019): Once chargers were installed and commissioned,
the uncontrolled charging phase commenced. Buses began charging immediately upon being plugged in,
and there was no application of any load management practices. The purpose was to set a baseline
against which performance during the subsequent phases could be measured.
Phase 1 – Static Scheduled Charging (Conducted May 2019): This phase began by testing the integration
of the Olivine and Liberty Plugins systems. Olivine’s software platform managed bus charging according
to static schedules that were designed to align with the TOU off-peak period. During this phase, the
primary goal was to ensure that the bus energy needs were met while minimizing electricity costs, and
to further analyze the opportunity for charge flexibility in a real-world environment.
Phase 2 – Excess Supply Demand Response Pilot (XSP) Participation (Conducted August–November
2019): This phase added demand response functionality. The approach tested PUSD’s ability to
dynamically shift load to instances of consumption that would provide higher value to the grid, such as
when there is excess wholesale electricity supply. These load-shift events were announced at 5:00 PM
on the day prior to each event, triggering a signal to the charge management software directing an
adjustment to the static charging schedule that served as the default.
Phase 3 – Renewables Self Consumption (Planned for December 2019–January 2020): This phase will
focus on adjusting the static charging schedules to optimize consumption from the onsite renewable
generation. The time interval of optimization will be determined during system analysis.51 The
optimization will still retain the over-arching goal of minimizing PUSD’s electricity bill.
51 Olivine will likely target optimization over 30-minute intervals because of observed interactions between the
buses and charging hardware. In the future, Olivine envisions optimization intervals of 15 or 5 minutes, if the
hardware supports it.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 170
Phase 4 – Renewables Optimization (Planned for February–April 2020): This phase combines the
previous phases and determines whether PUSD can both charge during periods of excess onsite
renewables and also respond to XSP events. The results will help with assessing whether the district can
further lower its costs and provide more value to the grid than it did in either Phase 2 or Phase 3.
4.1.2 Evaluation Methodology
Selected Methods and Rationale
The evaluation team has been collecting a wide range of data types to answer the evaluation questions.
For this PRP, in addition to the research questions that apply to every fleet electrification PRP, the
evaluation seeks to understand the challenges and innovations associated with implementing charge
management, providing grid services, and optimizing both onsite and grid-generated energy.
Because the electric school buses have been operating only for a limited period of time and the fleet is
still implementing the test phases described above, drawing conclusions from an analysis of the charging
patterns and operational costs incurred by the fleet to date would be premature, and formal analysis
has been deferred until the final evaluation report.
Data Sources
In-depth interviews were used to better understand the decision-making process and reasoning behind
this project. PG&E staff and PUSD staff were interviewed following the installation of the nine depot
chargers to collect lessons learned on the implementation process and early operations. The evaluation
team also interviewed staff at Olivine with a focus on integrating the load management software and
energy optimization processes. The evaluation findings presented in this interim report are based
primarily on these interviews.
In addition to interviews with key actors involved in the project, the evaluation will conduct a driver
survey in 2020 to collect information on perceived co-benefits, differences between driving an electric
bus and a conventional bus, satisfaction with new electric buses, charging protocols, and necessary
changes to driver behavior.
The evaluation of this project will also incorporate assessment of quantitative data that analyzes usage
patterns and costs related to the PRP. This will include maintenance and fuel records, mileage records,
operational details such as bus assignments to routes, PG&E electricity bills, PG&E meter interval data,
PG&E’s costs to implement the PRP, equipment out-of-service dates, and many other items.
In addition to continuing to collect these types of data through the conclusion of the PRP, the evaluation
team will also conduct market research on comparable fleets. Resources discussing the state of electric
school bus technology, literature detailing TCO estimates, analyses of vehicle fuel economies and
emissions, and other relevant references will provide a baseline and context for the fleet data collected
as part of the evaluation.
4.1.3 Evaluation Findings
At this time, the project has had both successes and challenges. PG&E and PUSD worked well as a team
to overcome many challenges through each stage from planning to early operation of the buses. By
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 171
design, PG&E selected a nascent market and expected to be closely involved to guide the project. The
buses have been underutilized relative to expectations because of a combination of challenges that can
be expected from the early stages of deploying new products and other extraneous factors. Most of
these challenges have been related to the buses; in other words, they do not reflect on the quality of
the PRP efforts, but they do limit the ability of the project team to implement its test phases on the
schedule originally anticipated.
PG&E helped PUSD design a project that had low carrying costs and outlined a pathway to effective
operations going forward. Because the electric school bus industry is young, there are few well-vetted
options for charge management systems, which was known when the project was approved. This
environment of limited charge management options meant that substantial investment was required to
perform the integration that enabled the district to test its project objectives around grid optimization
and renewables optimization.
Initial feedback from PUSD suggests the buses have been quite popular among students, parents, and
bus operators because of their quiet operations. The school board is very supportive and proud of the
pilot because it aligns with the board’s environmental values and furthers the educational mission.
These benefits are expected to increase with higher utilization of the buses and associated
infrastructure as the project progresses.
Project Baseline
A major question for the evaluation is whether PG&E’s efforts caused or have the potential to advance
the electrification of school buses by addressing key barriers. To address this question, it is important to
look at the baseline of industry uptake and innovations developed through the project that possess the
potential to be applied broadly. As noted in the project narrative above, PG&E intentionally chose a
partner that already had plans to procure electric school buses, so the impact of the project is primarily
associated with operational innovations and lower TCO. PUSD staff communicated that their
participation in this PRP accelerated the district’s procurement schedule for subsequent vehicles.
The broader context of the project has been shaped by a multi-decade effort to reduce school bus fuel
consumption and emissions, driven by both regulatory requirements and financial incentives. Although
there is no regulatory requirement to electrify school buses, there are several funding programs aimed
at shifting the school bus market and technology adoption trends. This includes $130 million in
Volkswagen Mitigation Trust Funds for transit, school, and shuttle bus electrification, from which
districts can receive up to $400,000 per electric bus. There is also the Low Carbon Transportation
Investments program and the Air Quality Improvement Program through CARB; these programs support
the deployment of advanced technology and clean transportation. They are accompanied by local
funding programs through regional air districts. Cumulatively, grant programs can help school districts
address the upfront incremental cost of battery electric buses compared to diesel, gasoline, or propane
buses.
Furthermore, while electric school bus models have higher initial costs relative to their diesel
counterparts, they are expected to produce cost savings over the buses’ operational lifetimes and are
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 172
eligible for grants such that they can often reach parity with diesel buses on a TCO basis.52 School
districts that have procured electric school buses, such as Twin Rivers Unified School District, have found
their operations and maintenance needs to be about half those of their diesel counterparts; this
translates to significant savings in California’s expensive labor market.53
The PUSD PRP is representative of the situation in which many school districts may find themselves:
they have obtained funding for bus electrification but must still navigate the procurement and
installation of infrastructure, management of multiple behind-the-meter energy resources and loads,
and operational optimization. Therefore, the innovations and lessons learned from this project can be a
pathway to scale deployment of electric school buses in PG&E’s territory faster and more effectively
than districts would have achieved without PG&E’s involvement.
Implementation Process
Subsequent to the official commissioning of the charging system, time was set aside to test the system’s
integrations and set a baseline. Between January and April 2019, the following issues had to be addressed.
Faulty Breaker
The electrical infrastructure was installed with one breaker serving each Clipper Creek charger and a
breaker serving Liberty Plugins’ Hydra charge management system. One of the chargers had a faulty
breaker on the panel feeding the charger, but since the breaker was not tripping physically, it was very
hard to diagnose. Troubleshooting this issue was especially challenging because the problem could have
been associated with any of the unique equipment and software components provided by the many
vendors serving the project. This issue is not something that could have been anticipated but was
eventually resolved.
Software Compatibility
Software communication between Olivine and Liberty took more development effort than initially
anticipated, despite efforts during the procurement process to ensure compatibility between the two
systems. A key feature required of the load management system was the ability to manage charging
port activity, so the procurement specified that the solution be compliant with the OpenADR 2.0b
standard. However, there are many functionalities that can be enabled under the OpenADR standard,
and operators do not need to support all functionalities to be deemed compliant with the standard.
Olivine and Liberty were able to work through the issues and build a robust OpenADR compliant
interface and a capable charge management system.
52 “Benefits of Electric School Buses” Webinar, presented by Jim Reynolds (President & CEO, Adomani) and Robert
Lupacchino (Chief Operating Officer, First Priority GreenFleet). 53 Conversation between Michelle Levinson (Cadmus Group) and Raymond Manalo (Twin Rivers Unified School
District) on November 19, 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 173
At project initiation, much thought and effort were needed to set up the onsite communications. Because
cellular capabilities were expensive and Wi-Fi did not work at the one possible device location, the Olivine
team implemented a hard-wired ethernet solution, utilizing the district’s internet. Data were relayed from
the utility meter through a smart energy monitoring device installed by the Olivine team.54 This is an
example of the adjustments necessary throughout the implementation process to address challenges.
The selected Clipper Creek hardware does not permit electrical power throttling, but Olivine was able to
develop a workaround by modulating the duration of charging to achieve the same effect, so there was
no impact on the project. Future deployments should consider using this modified approach since power
throttling at the charger is not necessarily needed to achieve the benefits of managed charging.
More generally, Olivine and Liberty needed to collaborate to initiate the project and ensure all
infrastructure was effectively integrated. This effort can now be leveraged and repeated in future
projects, as Liberty and Clipper Creek are now able to be integrated in a quasi-turnkey way. In the
future, cooperative procurement or an approved vendor list from PG&E could be methods for school
districts to make informed procurement decisions, which would be a valuable resource for staff who
may have limited expertise in EV charging.
Lesson Learned: PG&E was insightful in scheduling a significant block of time after commissioning during which project operators could iron out issues with project hardware and software integration. The challenge of identifying the cause of issues can be compounded when there are several distinct systems integrated in a single project.
Costs
In the CPUC’s 2018 PRP decision, PG&E was approved $2.21 million for this project, consisting of
$510,000 in capitalized costs and $1.70 million in expenses. For this report, PG&E provided the total
project expenditures through October 2019. These records show that the project is on track to stay
within the allocated budget of $2.21 million.
The following categorization of costs applies to Table 35:
Design includes site assessment, electrical design, and estimating; no permitting costs were
reported.
Behind-the-Meter (BtM) infrastructure includes the following customer-side costs: charger
installation, materials, construction labor, internal labor, and burdens on costs.
To-the-Meter (TtM) infrastructure includes the following utility-side costs: materials,
construction labor, internal labor, inspection, and burdens on cost.
Chargers includes the procurement of nine Clipper Creek CS-100 chargers and the Liberty
Plugins Hydra charge management system.
54 https://rainforestautomation.com/our-products/
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 174
Outreach and Education primarily includes costs associated with the learning center.
Other Program Costs includes work conducted by Olivine and Liberty Plugins to enable integration
of their systems. Work conducted by Olivine includes design and build of real-time metering
communications, design and build of a school-bus-centric e-fleet website portal, integration with
the on-board vehicle telematics systems, modeling, design and build of a variety of charge control
optimization strategies, management and execution of test phases, operations, and support.
Project Management includes PG&E’s activities on customer outreach, planning and direction of
the implementation process, oversight for troubleshooting, budget tracking and processing of
customer reimbursements, data review and analysis, management and planning of test phases,
and coordination of stakeholders. This category also includes project management for the
design and construction of PUSD’s chargers.
Table 35. PUSD PRP costs as of October 2019
Cost Categories Amount
Design $ 49,510
BtM Infrastructure $ 78,200
TtM Infrastructure $ 192,845
Chargers $ 43,255
Outreach and Education $ 19,025
Other Program Costs $ 233,010
Project Management $ 322,919
Total $ 938,764
Comparison of Actual and Forecast Costs
Full project costs are pending as the project is ongoing. When considering recorded costs to date, there
are some deviations from forecasted costs across the cost categories detailed above, but not relative to
total approved levels for capital and non-capital costs.
Capital costs (including infrastructure, make-ready, and project management associated with the
construction components of the PRP) are on track to remain within the approved ceiling of $510,000. As
of October 2019, PG&E’s reported total capital spend was around $500,000, and no additional
capitalized costs are anticipated. Non-capital costs (including additional project management, charge
management solution development, outreach and engagement/learning center, billing and technical
support, charger incentives, load shift incentives, and O&M of make-ready infrastructure) are on track to
remain within the approved ceiling of $1.7 million.
Ongoing Operational Costs
Ongoing operational costs are bucketed within non-capital costs, covering things like O&M for behind-
the-meter infrastructure or site utility bills. As of October 2019, no such O&M costs have been incurred,
but low amounts may be required in future years. The site has incurred electricity costs associated with
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 175
operation of the project, paid for by the school district through a separate meter that is exclusively
dedicated to the chargers.
Lesson Learned: When facing procurement choices, some customers may be drawn to the simplest, least expensive technology options available. On the other hand, more advanced and costly technology options may possess features that allow for more versatile future uses. Decision makers should consider opportunity costs and the value of future-proofing their procurements so that sites are well-positioned to benefit from new markets and future value streams.
Benefits
In the CPUC’s decision authorizing this project, the Commission laid out anticipated benefits related to
technology cost reductions, improved use of existing electric infrastructure, and potentially accelerated
adoption of clean energy technologies in the MD/HD sectors. Additionally, the CPUC highlighted the
benefit of reduced exposure to particulate pollution.
The PRP’s preliminary data are too limited to understand the project’s effect on the TCO for PUSD when
comparing diesel versus electric buses. Likewise, the increase in electric load related to the project is
minimal at this point, so it is unlikely to have had a material effect on costs. While it is premature to
quantify the impacts of this project definitively, stakeholders have identified some preliminary benefits.
District officials have noted the lower decibel of EV operations has created a more pleasant environment
for both students and bus drivers. Anecdotally, PUSD described several benefits during the interview,
including an observation that students on the bus are quieter when the bus itself is quieter and that kids
and parents were excited about the buses.
Operational Impacts of Project Equipment
Because this project involves deployment of nascent technologies in novel applications, it is to be
expected that issues with project equipment might have impacts on operations. Some characteristics of
the selected equipment disrupted operations in unanticipated ways, as described below and
summarized in Table 36. For example, the two eLion buses are smaller models (64-passenger) and do
not have enough seating capacity to be heavily incorporated into the district’s regular routine. Because
of driver shortages, the district sends out its larger vehicles that can serve more students on a single trip.
Additionally, the district has not gained enough comfort with the bus ranges to send these buses on
longer field trips or athletic events. This does not mean the vehicles are performing poorly, but when it
comes to assessing the project’s impact on TCO, low mileage means the additional upfront costs of
electric buses are not getting offset by substantial fuel cost savings during operations.
Lesson Learned: School districts and other early fleet adopters may not be able to adjust operations to optimize utilization of new electric buses or access new value streams associated with participation in distributed resource markets. Versatility of selected electric buses should be carefully considered during procurement (e.g., passenger capacity, range); otherwise, expectations for utilization (number of days in use and overall mileage) should be appropriately tempered.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 176
The project also faced setbacks due to bus delivery delays and bus malfunctions. The first Blue Bird bus
was scheduled for delivery in August 2019, but it was not available until mid-fall. Maintenance issues
included a door problem with one of the eLions and HVAC issues on both the eLions. The door issue
went unresolved for three to four months, leaving only one bus available to participate in Test Phase 1.
While this ended up being a simple issue to resolve once it finally was addressed, PUSD was frustrated
with the manufacturer’s customer service. The HVAC issue requires both eLions to be brought to
Sacramento for repairs; one was repaired from early September to November 2019, and the other is
expected to be sent for the same repair soon. During the repair of the first bus, the maintenance shop
providing repairs did not have an appropriate charger on site to keep the bus powered on for
maintenance and diagnostics. The workaround involved towing the buses across Sacramento multiple
times. The Blue Bird was also sent to Sacramento for a repair in December. These problems reflect two
themes that may carry over to similar contexts:
Vehicle technicians and maintenance workers are still developing familiarity with electric school
buses.
The industry is going through growing pains as manufacturers transition from focusing on sales
to meeting the service needs of customers with vehicles in operation.
Table 36. Summary of issues with project equipment and associated resolution
Technology Issue Result/Resolution
Buses Low utilization because of relatively small passenger capacity of eLion buses
Blue Bird buses selected for subsequent procurements have larger capacities and are likely to integrate better into normal fleet operations.
Buses Mechanical issue with eLion bus door
This issue was resolved after three to four months through collaboration with customer service.
Buses HVAC systems on eLion buses not functioning properly and repair shop lacks appropriate charging infrastructure
This issue was resolved after about two months at the repair shop in Sacramento and a tow to a facility with adequate charging equipment.
Buses The ability to support delayed charging not included in bus specifications
For eLion buses, the project team developed a workaround using a “trickle charge” to keep the bus from electrically disconnecting. No solution has been found for the Blue Bird buses.
Lesson Learned: The electric school bus industry is experiencing growing pains, which affects equipment operations and maintenance.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 177
PRP Innovations to Date
As noted above, the deployment of electric buses poses new challenges for school districts,
underscoring the value of a hands-on approach to PG&E’s implementation of this PRP. The main
innovation of this PRP is to develop approaches that enable sophisticated charge management on school
buses with low-cost non-networked EVSE and enable the buses to be responsive to scheduled charging,
load control programs, and optimization with onsite renewables. This required working creatively to
address challenges.
Models of electric school buses are not often designed to accommodate delayed charging. For instance,
neither the eLion buses nor the Blue Bird buses are capable of managed charging because they both
electrically disconnect after a period of time when a charge cable is plugged in but no power is present.
This interfered with the intended approach to have an automated system take care of energy
management after the bus driver plugged in the vehicle. A workaround that solved the issue for the
eLion buses was to employ a version of the Clipper Creek firmware called “Maintenance Mode,” which
supplies a steady 1.3 kW “trickle charge” at all times.55 This adjustment means there is marginally less
SOC available for optimization or TOU arbitrage, but still enables the eLion buses to be available as a
managed load. However, this fix does not work for the Blue Bird buses, and it is not anticipated that a
solution for these buses will be developed before the end of the PRP.
Additionally, the rate of charge that electric school buses accept is relatively low, and therefore
participation in the XSP required an exception be made to the requirement of achieving 30 kW of load
increase. 56 The eLion bus power conditioning hardware is currently configured by the manufacturer to
accept only approximately 13 kW of power, even though the Clipper Creek chargers can provide 19 kW.
Because of the specific characteristics of these technologies and the limitations in their combination, the
two buses can accept a total of only around 26 kW when utilizing the vehicles as dispatchable load.
Stakeholder and Customer Feedback
The project looks to be on a path to meeting customer needs as initially scoped. Some insights have
been drawn from in-depth interviews and project meetings conducted with the participants and
implementors of the project.
Hurdles have included the imperfect substitutability of electric buses as one-for-one replacements for
diesel buses, primarily because of range limitations, rider capacity, and staffing constraints. Currently,
the district is accommodating this difference by assigning vehicles strategically based on their
capabilities but has not been able to fully assess options because of extraneous resource constraints.
55 This is a 6 A 220 V flow, about equivalent to 1.3 kW. This relatively low flow of power ensured the eLion buses remained active as charging resources whenever the vehicles were plugged in, so they were available to receive signals from the energy management system to dynamically adjust power demand. 56 PG&E, “Business energy incentive programs,” accessed 2019, https://www.pge.com/en_US/large-business/save-
energy-and-money/energy-management-programs/energy-incentives.page.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 178
As discussed earlier, initial feedback to site hosts from bus operators, parents, students, and
administrators emphasizes the value they place on the quiet and clean operation of the electric buses.
The decision makers at PUSD were motivated to participate in this project because they felt it was
aligned with the values of their community. They were interested in improving air quality, recognizing
the relationships between air quality, student respiratory health, and school attendance. PUSD aims to
be a green innovation leader and is committed to “walking the walk” when serving the community.
While the leadership is interested in capturing any potential savings the project may generate, finances
were not a driving motivation for pursuing the project.
4.1.4 Conclusions
Based on the information collected to date, the evaluation team drew several preliminary findings.
Additional data will be analyzed for the final report. This PRP illuminated several lessons that will
contribute to the success of future school bus electrification projects.
Two primary innovations are being tested in the PUSD PRP in support of the objectives of providing
reduced TCO by minimizing infrastructure and fuel costs and demonstrating the ability of electrified
school bus fleets to support the integration of renewable generation from both on-site and grid
resources. It should be noted that this PRP is a forward-looking effort, given that most school districts
likely do not currently need such an advanced approach (either because they do not have as many
behind-the-meter renewable resources or because they do not have the same scale of existing and
anticipated electric bus purchases as PUSD). However, these innovations are important proofs of
concept to move the market forward in a state-wide context in which it is expected that many more
school districts will be increasing their investments in both behind-the-meter renewables and electric
buses in the near future.
The first innovation being tested is using school buses to facilitate the integration of intermittent
renewable generation, both in the context of on-site solar and wind and in response to excess wholesale
electricity supply during high renewables events on the grid. Thus far, the PRP has demonstrated the
feasibility of using school buses for such purposes and has also demonstrated the complexity of
establishing such a project and obtaining the degree of participation hoped for from the bus
manufacturers. For one, the on-site renewables were not within PG&E’s purview for the PRP itself, and
delays in installation of some of these resources affected the ability of project implementers to maintain
the protocol test schedule originally envisioned. Additionally, operational issues with the buses and
driver staffing constraints reduced the district’s ability to fully utilize them, which limited the magnitude
of their ability to act as controllable load to date.
The second innovation tested through this PRP is the feasibility of combining low-cost, non-networked
EVSE and DER technologies to achieve this goal. When selecting system technologies, some customers
may be drawn to the simplest, least expensive options available. Thus far, the PRP has successfully
demonstrated feasibility. But joining together several distinct technology solutions that were not built
with the intention of integration can have a multiplier effect for the complexity of troubleshooting.
Furthermore, the experience has demonstrated that even when existing standards are in place (e.g.,
OpenADR), procurement of equipment and software vendors must still be explicit about the necessary
functionalities to ensure compatibility.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 179
The remainder of the PRP will provide insights into how well these two innovations function now that
several of the initial issues are resolved and more electric buses are available within the PUSD fleet.
These findings will help with the consideration of the value, costs, and replicability of approaches similar
to those deployed in this project.
More generally, pilot projects like this one help the industry build key technology integrations. This
project surfaced and resolved inevitable integration issues between buses, chargers, and charge
controllers that will be resolved more quickly in future applications than had the project not happened.
Such integrations require significant investments of time and expertise and will likely need to be
revisited for different combinations of bus models, charger models, and control hardware and software.
To the extent that industry players are watching this pilot and others like it, they may have increased
awareness of the importance of working toward integrated solutions. To the extent that school districts
are observing innovations put into action at PUSD, there is also the potential for market pull/increased
demand for these solutions. As more of these technology integrations are implemented, the low-cost
offerings should improve and become more “out-of-the-box.”
Additionally, this PRP provides insights about implementing such projects with school district customer–
partners. School districts are first and foremost concerned with serving their operational needs, which
may not allow as much flexibility in route assignment or charging patterns as would be needed to
optimize for cost. The value of participating in programs such as XSP may be less substantial and more
challenging to unlock than anticipated. Testing and refinement of protocols may require extra time
because of the annual school year cycle, since operations are substantially different during summer and
holiday months. At the same time, several attributes of school bus electrification make it a promising
target for scaling innovation: the alignment of the times that school buses are available to charge with
low-cost/cleaner time periods for the grid, the availability of incentive money that is funding bus
replacements and infrastructure, and the eagerness of these districts to work as partners. Sharing the
lessons learned and innovations demonstrated in this PRP has the potential to 1) streamline the process
for future customer–partners, 2) help school districts establish realistic expectations associated with
their electrification strategies, and 3) increase the value and cost-effectiveness of deploying electric
school buses. However, more time and data are needed to understand the full impacts of the program.
Lessons Learned
Contracting, construction, and implementing test protocols with schools may require planning
extra time as a buffer to reflect their unique contracting processes and seasonal operational
patterns.
PG&E was insightful in scheduling a significant block of time after commissioning during which
project operators could iron out issues with project hardware and software integration. The
challenge of identifying the cause of issues can be compounded when there are several distinct
systems integrated in a single project.
When facing procurement choices, some customers may be drawn to the simplest, least
expensive technology options available. On the other hand, more advanced and costly
technology options may possess features that allow for more versatile future uses. Decision
makers should consider opportunity costs and the value of future-proofing their procurements
so that sites are well-positioned to benefit from new markets and future value streams.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 180
School districts and other early fleet adopters may not be able to adjust operations to optimize
utilization of new electric buses or access new value streams associated with participation in
distributed resource markets. Versatility of selected electric buses should be carefully
considered during procurement (e.g., passenger capacity, range); otherwise, expectations for
utilization (number of days in use and overall mileage) should be appropriately tempered.
The electric school bus industry is experiencing growing pains, which affects equipment
operations and maintenance.
4.2 Bus Fleet Demonstration – San Joaquin Regional Transit District
4.2.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
Overview
As described in CPUC Decision 18-01-024, for this PRP, PG&E sought a partner who operates an MD/HD
fleet to assist in deploying EVs by leveraging the utility’s resources and expertise. Prior to the PRP,
customers seeking to build out charging infrastructure for fleet electrification would need to submit
plans to PG&E, pay for the necessary upgrades themselves, and learn on their own how to manage
charging for their new EVs. For PG&E to help the MD/HD fleet electrification market grow, it needs to
support the early adopters and ensure they have positive experiences. By supporting early adopters,
PG&E can not only develop innovations and best practices but also shape the narrative about the
processes and benefits of deploying electric MD/HD vehicles. This PRP aims to achieve a broad positive
effect on the market by discovering and showcasing best practices in infrastructure and management of
MD/HD fleet electrification.
With this pilot, PG&E proposed a dedicated “hands-on” approach, featuring extensive collaboration with
the customer, vehicle and charger manufacturers, and other partners. The project also is intended to
provide lessons learned to inform long-term, widespread MD/HD transportation electrification,
including development of PG&E’s SRP, the EV Fleet program.
With this collaborative approach, PG&E was responsible for designing and building the make-ready
infrastructure to support the new electrified fleet. The utility worked directly with the customer to find
efficiencies in site planning and infrastructure sizing for the expected load. To manage charging costs on
existing rates and to reduce peak demand use, PG&E will work with the customer and other third parties
to incorporate technology solutions—primarily charge management software and energy storage.
This evaluation is an interim report covering PRP stages completed thus far: scoping and customer
acquisition, project design and preparation, construction, and commissioning. The project is now
actively operating, and data collection is under way. Analysis of these data and concluding lessons
learned will be covered in the final evaluation report.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 181
Objectives
The project’s primary goal is to demonstrate how, with utility assistance, the TCO for MD/HD electric
fleets is lower in comparison to fossil fuel alternatives. This demonstration will help inform other
utilities, fleet operators, site hosts, and customers considering EV deployments. Specifically, the PRP will
accomplish the following:
Deploy utility-owned, make-ready infrastructure to serve expected growth in EV charging.
Provide an incentive to deploy EV chargers.
Provide technical assistance, including rate optimization, and demand management technology
to minimize operating costs of EVs.
Produce a summary handbook of lessons learned to inform fleet and other MD/HD EV
deployments.
PG&E will also look to use its non-electrification resources (such as energy efficiency, distributed
generation, and demand response products and programs, along with rate analysis) to evaluate
additional opportunities for energy management and customer bill savings. The most appropriate
customer candidate for this project is a public transit agency, given the sector’s maturity in commercially
available electric buses, external funding sources for vehicles and charging infrastructure, and EV
adoption goals. With CARB releasing its Innovative Clean Transit (ICT) regulation in December 2018, all
public transit agencies will be required to develop plans to procure electric buses and/or fuel cell buses
and transition their existing fleets by 2040.57 ICT requires transit agencies to substantially rethink their
operations, particularly as these solutions and innovations affect their traditional finance models.
This project also provides an opportunity for PG&E to gain experience working directly with transit
agencies and to capture insights that will inform implementation of the EV Fleet Program, an SRP under
SB350, and involves extensive coordination with operators of MD/HD fleets to advance fleet
electrification.
Barriers
Utility investment in MD/HD fleet electrification can address two key barriers: upfront electrical
infrastructure costs and ongoing electrical charging costs. This demonstration aims to reduce these
barriers and to provide a model for how utilities can support fleet electrification projects, providing a
case study of successful transit electrification.
To maximize PG&E’s success in future collaborations with transit agencies, those agencies must have
confidence that cost savings can be achieved when operating an electric fleet. On the current rate
structure most transit agencies use, demand charges have posed a challenge, and ongoing operational
costs have not always decreased following adoption of EVs. To this extent, PG&E has separately filed
57 CARB, “Innovative Clean Transit,” accessed 2019, https://ww2.arb.ca.gov/our-work/programs/innovative-clean-
transit.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 182
and gained approval for a commercial EV (CEV) rate, which will mitigate many challenges that transit
agencies will face in managing their charging costs.58
The learning curve for planning and operating an electric fleet poses another barrier for transit agencies
that PG&E can address. Most agencies do not know the best way to provide adequate charging
infrastructure for electric buses. Additionally, they do not have experience with the new operational
challenges associated with deploying electric buses, including understanding capabilities and limitations,
and how to effectively integrate electric buses into their regular operations. Guidance from the utility
for such implementation projects will prove crucial to advancing the MD/HD fleet electrification market.
Sites and Participants
Recruitment of Site Host
PG&E created a list of over 50 transit agencies and contacted several to track electric bus interest and
planned procurements. PG&E wanted to partner with a transit agency that already used electric buses,
as this would likely result in a smoother design and construction process for charger installation to meet
the January 2019 target completion timeframe.
PG&E then used the criteria outlined in Figure 85 to create a short list of potential transit agencies for
the project. By early February 2018, PG&E had identified the San Joaquin Regional Transit District (RTD)
as an ideal candidate for the pilot as it met all desired criteria; it had an existing fleet of 12 electric
buses, had new buses on order, and had announced a goal to electrify 100% of its fleet operating within
Stockton city limits by 2025.
58 CPUC Decision 19-10-055, http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M318/K552/318552527.PDF
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 183
Figure 85. Evaluation criteria for PRP participants59
Source: PG&E SB350 PRP Interim Report
Site Host
Prior to this project’s start, RTD was already operating two generations of legacy electric buses. These
included two 2013 prototypes from Proterra and ten 2016 Proterra electric buses with 30–50 mile
ranges that RTD began operating in September 2017. Because of their limited battery capacity, these
buses had to use on-route 500 kW overhead chargers to complete their routes; relying on overnight
depot charging was not an option.
Prior to the PRP, RTD was experiencing high electric bus costs per mile resulting from demand charges
and uncontrolled charging practices. RTD is currently a PG&E customer on the A-10 TOU rate. The A-10
TOU rate includes a demand charge (per kilowatt) and an energy charge (per kilowatt-hour).60 PG&E’s
new CEV rate, to be implemented in 2020, supports transportation electrification for commercial fleets
and has the potential to help manage costs for RTD.
In early 2018, RTD began taking proactive measures to reduce future electrical charging costs by
procuring five new electric buses with longer nominal ranges (~250 miles) that could take advantage of
overnight charging. RTD staff had not, however, yet developed a clear plan for how to charge and deploy
these buses; discussions with PG&E through this PRP enabled them to pursue a demonstration targeting
lower TCO.
59 From PG&E’s Interim Priority Review Report:
http://docs.cpuc.ca.gov/SearchRes.aspx?DocFormat=ALL&DocID=285086006 60 Full tariff details are provided here: https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_SCHEDS_A-10.pdf
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 184
RTD also has a goal to operate all routes within the City of Stockton exclusively with battery electric
buses by 2025. It seeks to better understand the requirements for scaling up and what collaboration
with PG&E is needed to upgrade its behind-the-meter and make-ready infrastructure to accommodate
RTD’s increasingly electric fleet.
Sites
This PRP involved three sites at RTD. At Site 1, the Regional Transportation Center (RTC), five 60 kW
depot chargers have been installed to charge the five longer-range electric buses overnight. Figure 86
shows a diagram of Site 1’s setup, which became operational in May 2019. A key question associated
with this site is whether the TCO for a depot charger configuration is reduced relative to the baseline of
diesel hybrid buses on the same routes.
Figure 86. RTD Site 1 diagram
Note: T = Transformer and M = Utility Electric Meter
Source: PG&E 2019 Interim Report
Site 2, the Downtown Transit Center (DTC), is the largest transit hub in Stockton and at the center of
RTD’s system. This is where RTD installed its original pantograph chargers (overhead fast chargers that
automatically couple with an apparatus on the roof of the bus when the bus pulls into its parking space
at the transit center). These two 500 kW Eaton overhead fast chargers serve electric buses operating on
four short routes. Figure 87 is a diagram of Site 2’s configuration. Although the chargers existed prior to
the PRP, PG&E deployed charge management software in October 2018 at this site to address high
demand costs. RTD is trying to determine whether managed charging will reduce electricity bills while
still serving the operational needs for electric buses on these routes.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 185
Figure 87. RTD Site 2 diagram
Note: T = Transformer and M = Utility Electric Meter
Source: PG&E 2019 Interim Report
Site 3, Union Transfer Station (UTS), is where a new Siemens overhead fast charger was installed (paid
for by RTD) and where this PG&E PRP plans to add a battery electric storage system (BESS). UTS is
located at the intersection of two key RTD bus rapid transit routes, the Metro Express Airport Corridor
and the MLK Corridor, both of which now use electric buses. A diagram of Site 3 is shown in Figure 88. A
key question here will be the degree to which energy storage can reduce operational costs.
Figure 88. RTD Site 3 diagram
Note: T = Transformer and M = Utility Electric Meter
Source: PG&E 2019 Interim Report
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 186
Timeline
Original Planned Timeline
The graph below (Figure 89) illustrates the original timeline (pale blue fill) and the achieved timeline (medium blue fill) for the MD/HD PRP. This
divergence reflects a variety of disruptions and challenges, many of which were unforeseeable on the part of PG&E or the site host.
Figure 89. RTD PRP comparative project timeline
Note: Open diamonds indicate original milestone date.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 187
The original PRP plan was to have the depot chargers operational and the BESS integrated by January
2019 to collect a full year of operational use data, prior to the original timeline for the PRP’s conclusion
in December 2019. As CPUC approved a request to extend the final evaluation report to January 2021,
PG&E will be able to obtain more than 12 months of data for demand management and depot chargers,
and several months of data should be available for the BESS solution in the final evaluation report.
Explanation of Notable Timeline Alterations
Depot chargers were delayed by about a month as a result of changes in the to-the-meter design
relative to the project manager’s schedule. The construction duration was extended because of an
increased scope of work. The project team planned to access a PG&E transformer located on a
neighboring property. It was determined, however, that a new transformer, vault, and primary riser
would offer the best option to mitigate the need for an easement. This resulted in a slight delay to the
original schedule.
To mitigate further delays, behind-the-meter construction commenced while the to-the-meter design
was revised to accommodate the change in scope. With the changed scope, four out of five chargers
were operational on March 21, 2019. The final charger, which required repair by the manufacturer, was
activated on May 4, 2019.
The BESS has been delayed substantially, with the full extent of delay still unknown, as this project
component is not yet completed. Several factors contributed to the delays. RTD and PG&E needed time
to identify the preferred location for the BESS. According to interviews with the RTD project manager,
DTC was originally RTD’s preferred location because of the large number of electric buses that charge
there and the known need to manage demand charges. Concerns emerged, however, about space
availability at DTC and the need to disrupt DTC services during the BESS installation (DTC is the busiest
bus station in RTD’s system).
PG&E recommended that the BESS installation be shifted to UTS, a greenfield site under development
for a new transit hub, with ample distribution system capacity and space for future expansion of
batteries and solar. The addition of solar falls outside of this PRP’s scope but could integrate well with
BESS in the future. The grand opening of UTS did not occur until late February 2019, and some time was
needed to operate the new station before planning the BESS installation. Before focusing on the BESS
installation, RTD had many other priorities to balance within this PRP, including managing existing
electric buses, setting new charging thresholds at DTC, constructing depot chargers at RTC, and
integrating the new electric buses into service.
A few factors also accelerated the project timeline, without which the delays would have been more
substantial. First, RTD already had longer-range electric buses with depot-charging capability on order,
so the design started immediately after signing the contract to participate in the PRP. Second, RTD could
sole-source Proterra chargers, as the district had already procured Proterra buses. If a sole-source
procurement had not been possible, RTD would have needed to issue a solicitation, which could have
added a month or more to the timeline. This efficiency could have saved even more time if RTD had
intended to use Proterra chargers all along. Originally, RTD staff expressed interest in ChargePoint
chargers because of their demand management capabilities, but ultimately Proterra equipment was
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 188
selected, which mitigates the complexity of resolving charging issues, as a single company would be
responsible for addressing these.
Planned PRP Activities and Current Status
Current Status
Currently, RTD operates three different models of Proterra electric buses, as detailed in Table 37,
charging at the three sites described above. PG&E’s construction and implementation activities have
concluded at Sites 1 and 2, with only the installation of the BESS at Site 3 remaining to complete the
PRP’s infrastructure installations. Hence, the project is shifting toward testing and advising RTD; PG&E
can learn about the bus fleet capabilities paired with the implemented charging solutions. PG&E has
worked with RTD to develop several tests of operational protocols to compare the charging costs with
diesel hybrid buses on Route 49—the route on which the new long-range Proterra buses are
being deployed.
Table 37. Relevant electric bus specifications
Manufacturer Proterra
Model BE35 Catalyst Fast Charge
Catalyst E2 Long-Range
Buses
Quantity in RTD Fleet
2 10 5
Battery Size (kWh)
78 105 440
Nominal Range (miles)
49 62 251
Charging Protocol
DC Roof-Mounted Pantograph
DC Roof-Mounted Pantograph
DC SAE Combo and DC Roof-Mounted Pantograph (can be configured for both)
Source: PG&E 2019 Interim Report
Frequently, technical and maintenance issues have prevented the electric buses from being utilized as
extensively as the fleet’s diesel hybrid and diesel buses. As shown in Figure 90, a typical diesel hybrid
bus accrues over 1,800 miles per month. As of Q1 2018, before the new long-range buses were
procured, electric buses across RTD’s fleet were averaging 1,558 miles per month. That average mileage
dropped to 1,035 per electric bus throughout 2018, rebounding to 1,348 per bus per month from
January to October 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 189
Figure 90. Comparison of monthly mileage per bus, January to April 2018
Source: PG&E Q1 2019 PAC meeting
The evaluation team’s interviews with RTD staff revealed issues with the electric buses and charging
infrastructure. For instance, the overhead chargers at DTC and UTS were down for multiple months in
summer 2019. RTD also reported that the five new buses did not have sufficient range to operate all day
on a single charge. The buses did not come close to their advertised nominal range and have been pulled
from service when they reach a 20% state of charge [SOC] so that they do not become stranded en
route. These types of issues are not surprising, given the relative early stage of electric bus deployment.
The need to address these issues underscores the value of ongoing coordination and collaboration
between PG&E and RTD.
Other issues occurred with the chargers that did not affect operations but that also needed to be
resolved. For instance, PG&E had to diagnose a problem with the RTC overnight depot chargers, as they
went down regularly during the mid-afternoon—an issue that did not affect current operations but still
needed to be fixed. PG&E determined that the problem was a power quality issue, rather than a
problem with the chargers themselves, and took corrective action.
Another example of beneficial collaboration is PG&E’s staff continuing to elevate the importance of
addressing RTD’s needs with Proterra, particularly in helping line up the buses early for the upgrade in
Proterra’s telematics system to more rapidly obtain useful data on fleet operations. Additionally, PG&E
has been able to advise RTD on rate structures, test designs, and collecting lessons learned, which will
help with planning for the expansion of the district’s electric fleet.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 190
Construction Update
As noted, Site 3 (the UTS) is the only site where PRP construction activities remain incomplete.
Construction at this site is slated for completion in mid-2020. As of November 2019, a preliminary single-
line diagram was completed for the BESS system, but the detailed design has not been completed.
Outside the scope of the PRP, RTD is installing solar and a second overhead fast charger at UTS. The
second charger is expected to be installed in February 2020, and the BESS is expected to be completed
in summer 2020.
Ongoing and Upcoming Tests
At the RTC
PG&E and RTD intend to test several options for managing the charging costs of the five new long-range
electric buses. The tests aim to answer the following two key questions:
Can the new long-range electric buses be fully charged every night at the depot and meet their
daily route needs?
o RTD verified that the electric buses can be fully charged at night, during the normal period
between daily operational times. During summer, the actual range of the buses is
substantially less than the nominal range, likely due to challenging operating conditions
associated with summer heat. Through the summer, RTD pulled buses off the route each
afternoon (typically before they depleted to less than 20%–30% SOC). Additional testing will
determine whether the buses can operate for a full day of service during the mildest
conditions with the least heating or cooling demands.
Can the fueling cost per mile be reduced through different charging protocols, and how does
this compare with diesel hybrids on the same route?
o To address this question, the buses’ fueling costs under different charging protocols are
being established over multiple electric billing periods: 1) charging only at the depot,
2) charging by overhead only (at UTS), and 3) charging at both the depot and UTS overhead
chargers.61 During all test periods, a diesel hybrid will be running simultaneously with the
electric buses on the same route for a direct cost-per-mile comparison.
At the DTC
PG&E and RTD intend to gather further information about the performance of demand management.
Can the demand management software reduce operation costs of 12 legacy electric buses
relative to uncontrolled charging and still meet RTD’s route needs?
o The demand management software is substantially reducing RTD costs when demand is
capped at 300 kW (see Benefits section under Evaluation Findings). However, this comes
61 It is not clear whether each of these protocols will prove feasible at all times of the year, and for some of these
charging protocols, spare buses may need to be pulled in midday if the SOC dips too low.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 191
with uncertainty about whether the demand management software could cause any electric
buses’ SOCs to fall too low and disable them from completing their routes (Proterra
provided guidelines to the fleet that stipulate not regularly operating the buses below 20%
SOC). Rather than throttling charging to only 300 kW, the software is designed to provide
full power charging until meeting the 300 kW demand limit across the current 15-minute
period. The system will then prevent buses from charging until the next 15-minute window.
RTD and PG&E are interested in reviewing this strategy to determine whether there might
be a better way to prioritize charging for buses that cannot afford to miss a charging session
(based on their current SOC).
At the UTS
When the BESS is interconnected, PG&E and RTD intend to answer the following questions:
To what extent can the BESS reduce charging costs at the UTS?
Do the additional savings make a BESS economical for this application? In what scenarios might
it offer benefits?
4.2.2 Evaluation Methodology
Selected Methods and Rationale
The evaluation team has been collecting a wide range of data types to answer the PRP evaluation
questions. For this PRP, in addition to the research questions that apply to every fleet electrification
PRP, the evaluation seeks to understand the challenges and innovations associated with implementing
charge management, overnight charging, and coupling the BESS with an overhead fast charger.
Data Sources
Data collection has included in-depth interviews, maintenance and fuel records, mileage records,
operational details (such as bus assignments to routes), PG&E electricity bills, PG&E meter interval data,
PG&E’s costs to implement the PRP, equipment out-of-service dates, and many other items. In addition
to continuing to collect these types of data through the conclusion of the PRP, the evaluation team will
conduct market research on comparable fleets and survey RTD bus operators.
Operational protocols and bus assignments are still being adjusted, and the fleet is designing and
implementing tests on the feasibility and cost of various operating protocols. Therefore, drawing
conclusions from analysis of charging patterns and operational costs incurred by the fleet to date would
be premature, and the formal analysis has been deferred until the final evaluation report.
4.2.3 Evaluation Findings
Project Baseline
A major question for the evaluation is whether PG&E’s efforts caused or have the potential to accelerate
electrification of vehicles in this application by addressing barriers. To address this question, it is
important to look at the baseline of industry uptake and the innovations developed through the project
that potentially could be applied broadly. As noted in the project narrative above, PG&E intentionally
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 192
chose a partner that already had plans to procure electric buses, so the project’s impact is primarily
associated with the charging innovations it demonstrates. With the new ICT regulation requiring all
agencies to plan for ZEB transitions, the innovations of this project offer a pathway to scale electric bus
deployment in PG&E’s territory more effectively than transit agencies would have achieved without
PG&E’s involvement.
Several factors in California have made electric buses more financially attractive to transit agencies. One
factor is the availability of grant programs, such as those offered through CARB, the CEC, the VW
Environmental Mitigation Trust, and others. Another potential benefit is the anticipated maintenance
savings achieved over the life of the vehicle, a particularly salient feature in a state with high labor costs.
Currently, the electric fleet must be heavily managed, which is a function of being new, but labor hours
are expected to decrease for this as well. Another factor is the ability to capture Low Carbon Fuel
Standard (LCFS) credits, which become even more valuable when agencies generate solar energy to
offset their electrical usage. When the PG&E CEV rate becomes available, that rate structure will also
make transit electrification more cost-effective for many agencies.
Transit buses present good opportunities for electrification because of their high utilization rates, fixed
routes, and return-to-base at night operations. Nonetheless, many barriers persist, including upfront
cost premiums, costly infrastructure, time-consuming processes for procurement and permitting, range
limitations for the most energy-demanding routes, resilience concerns in areas prone to power shutoffs,
and HVAC requirements in extreme weather conditions. Nevertheless, California is the leading region for
electric buses in the United States, and as of August 2019, 964 transit buses have been delivered to
agencies across the state.62 Many agencies are actively watching the results of this project and other
deployments to inform their own electrification plans.
Implementation Process
What Went Well
The recruitment process aligned well with PG&E’s goals, as RTD met all criteria that PG&E wanted in a
partner: had new electric buses on order, served DACs, had experience running electric buses, had a
demonstrated need to implement better charge management protocols, and was keenly interested in
learning and developing operational best practices to support its ultimate goal to electrify 100% of its
fleet by 2025. Having buses on order enabled an early start to the design process, and prior electric bus
experience addressed some common operational challenges in switching to this technology.
Areas for Improvement
One area for improvement is to encourage partner agencies to coordinate with PG&E as early as
possible, ideally prior to acquiring buses. This will enable PG&E to help the agencies understand their
options and determine the best charging and bus configurations. By design, PG&E partnered in this pilot
with an entity that already had made decisions about its electric bus procurement, so this was not
62 CALSTART webinar for California Transit Association:
https://caltransit.org/cta/assets/File/Webinar%20Elements/CTA-CALSTART%20Webinar%201.pdf
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 193
possible. It is, however, a recommended best practice to strive for moving forward. RTD could have
benefited from talking with PG&E earlier, as the district was not even aware that depot charging was an
option with the new electric buses. With PG&E, RTD could find the right configuration of chargers to suit
its needs.
Another challenge arose in obtaining and monitoring data when the new long-range electric buses were
first acquired. The utility meter did not operate properly for the first six months, resulting in an
electricity consumption data gap from January 18 to June 10, 2019. This prevented RTD from receiving
valuable information about the amount of electricity buses consumed and how much it would have cost.
Another issue was that Proterra’s data loggers were not able to keep up with the massive amounts of
data on its servers (a result of their significant market growth), resulting in PG&E’s and RTD’s being
unable to track real-time or historical data covering the period between early summer 2019 and late fall
2019. These issues have been resolved, and the improved access to data for the remainder of the PRP
will enable collection of more robust lessons learned.
Finally, the project’s BESS delay could have been shortened by making key design decisions for the BESS
earlier to meet PG&E interconnection application requirements. Examples include operating
requirements, requirements for the single line diagram, and inverter certification. As described in
Section 2.1.3, some delay was unavoidable because of the importance of aligning with RTD on key
decisions (e.g., site selection) for this project component. However, PG&E and RTD should have ensured
that all interconnection documentation was in place well before the intended construction start. PG&E
assisted RTD in submitting an interconnection application between late July and early August 2019, but
the complexity increased when RTD informed PG&E that it also planned for solar at the site, making it
more difficult for PG&E to expedite the application. Earlier interconnection approval could have enabled
alignment of the construction schedule for BESS installation as well as installation of the planned second
overhead charger, which had the potential to reduce disruption at the site during construction. The
construction has not yet been completed for either component.
Lesson Learned: Early partnership between the utility and transit agencies will provide opportunities for transfer of knowledge and best practices. The utility brings unique insights and can support agencies with the expertise utility staff have developed through implementing programs and projects throughout the territory.
Costs
Project Costs
Upfront project costs were incurred for each of the three sites in the PRP. As the work at Site 3 is not
complete, no budget updates are available for the BESS. The following cost categorization applies to
Table 38:
Design includes design, estimating, and permitting.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 194
Chargers includes procurement of the five 60 kW depot chargers (Proterra PCS), a five-year
warranty, and sales tax. The chargers were originally procured by RTD, who was then fully
reimbursed by PG&E.
Behind-the-meter (BtM) infrastructure includes the following customer-side costs: charger
installation, materials, construction labor, internal labor, and burdens on costs.
To-the-meter (TtM) infrastructure includes the following utility-side costs: materials,
construction labor, internal labor, inspection, and burdens on cost.
Table 38. Summary of PG&E project costs through October 2019
Design Chargers BtM Infrastructure TtM Infrastructure Total
Site 1: DTC Demand Management
In-kind from
Proterra N/A N/A N/A N/A
Site 2: RTC Depot Chargers
$ 53,020 $ 285,280 $ 147,734 $ 242,789 $ 728,824
Site 3: UTS BESS
TBD N/A (RTD paid
for its own charging)
TBD TBD TBD
Project Management Costs
$ 201,274
Total $ 53,020 $ 285,280 $ 147,734 $ 242,789 $ 923,167
It appears that the project is on track to stay within the proposed $3,355,000 estimated budget
approved by the CPUC. Based on the PG&E-provided estimates for remaining costs to close out the
project, the total forecasted cost for the project is expected to be about 60% of this budget.
In addition to costs covered or reimbursed by PG&E, other project partners have provided valuable
in-kind contributions. For instance, Proterra developed the demand management software that RTD
implemented at the DTC at no cost to RTD or the PRP. Additionally, RTD invested the administrative and
project management time of a special projects manager as well as investing the time of its core facilities
and operational staff for installing the depot chargers and implementing demand management. The
value of this leveraged labor, which RTD expected to provide, has not been quantified.
Benefits
The PRP evaluation will include an assessment of petroleum usage reduction, GHG emissions reduction,
criteria pollutants reduction, benefits to DACs, benefits to the fleet (e.g., operational cost savings from
fuel and maintenance), and any co-benefits. As data collection for this project will continue into 2020,
no final conclusions about the PRP benefits can currently be drawn. However, since preliminary data are
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 195
available on charging profiles and associated electricity costs, preliminary data on the PRP impact for
RTD’s ongoing fuel costs is provided below.
Ongoing Costs to RTD
While a full evaluation of the TCO for all electric buses deployed in RTD’s fleet falls outside the scope of
this evaluation, this evaluation seeks to quantify fueling cost savings between how RTD charged its
buses prior to PG&E’s involvement and how it did so afterward, with a particular focus on the new long-
range electric buses. There are additional sources of ongoing costs and savings that do not relate to
PG&E’s involvement, so these costs will not be assessed in depth (e.g., changes to vehicle operator
wages, maintenance costs, LCFS credits, warranty costs, end-of-life salvage values). PG&E’s PRP will
affect RTD’s fueling costs in three main ways: 1) advising RTD on rate structures; 2) modified charging
patterns at the RTC and the UTS (including battery storage at UTS); and 3) managed charging demand at
DTC.
Impact of Advising RTD on Rate Structures
During 2020, the evaluation team intends to shadow-bill RTD on the forthcoming CEV rate and provide a
comparison of RTD’s actual costs with its theoretical costs on that new rate. To take advantage of the
CEV rate, RTD will need to confirm the connected load for each of the accounts is exclusively for vehicle
charging. This is likely the case for DTC and UTS, although there may be a few minimal loads still
connected to these meters, such as a fare-vending machine, while by design RTC chargers were installed
on their own meters.
Impact on Charging Patterns at UTS and RTC
PG&E is currently designing tests that will help RTD determine whether it should operate its buses on
overnight charging at RTC, on the fast charger at UTS, or some combination of these. In addition to the
BESS (planned for UTS, which is funded by this PRP), there are plans for both RTC and UTS to have solar
interconnected in 2020, which is not included in this PRP’s budget. With this addition, the optimal
charging protocol may need to account for solar generation credits as well as for the impact on the LCFS
credit value.
Impact on Charging Patterns at DTC
PG&E noted that, prior to this PRP, RTD was routinely incurring higher costs per mile for its buses
charged via the extreme fast chargers at DTC. Preliminary data analysis shows that the software
intervention to institute demand caps at DTC was effective in reducing costs per mile for those buses,
provided that the fleet also maintained a high level of charger utilization. Figure 91 and Figure 92 show
the effectiveness of demand management in the first few months and subsequent six months,
respectively.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 196
Figure 91. RTD daily demand at DTC by 15-minute interval
Source: PG&E Q1 2019 PAC meeting
Datapoints highlighted in red are time intervals in which demand exceeded 300 kW. One month after
the demand limiting software was implemented, it was determined that the initial threshold of 250 kW
was too restrictive and affected the ability to adequately charge buses for their duties, so the threshold
was increased to 300 kW.
Figure 92. RTD demand plot from September 2018 through August 2019
Note: Datapoints highlighted in red are time intervals in which demand exceeded 300 kW.
Source: PG&E meter data
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 197
As shown in Figure 92, RTD successfully stayed under its demand management cap from October 2018
to June 2019. It appears it overrode the demand management cap at DTC in July and September 2019
for operational reasons, resulting in higher costs for those months. Despite the limitations associated
with managing bus charging patterns while attempting to maintain maximum utilization of these
resources, demand charge savings are clearly documented through RTD’s electric bills. As shown in
Figure 93, the average monthly demand charge for winter months (defined in the tariff as November
through April) dropped by 35% between winter 2017–2018 and winter 2018–2019. The same
comparison for summer months shows a 20% drop. Under the approved CEV rate, RTD can expect even
greater monthly savings, thanks to the rate structure, and can opt to subscribe to a lower kilowatt
threshold because of this software, reducing overall costs.
Figure 93. Demand charge average value before and after implementing software management
Source: PG&E utility bills
Operational Impacts of Project Equipment
RTD has been carefully tracking operational impacts of the electric buses and their chargers to gather
insights for scaling its electric bus deployment to reach its intracity fleet electric bus deployment goal by
2025. The district has dynamically modified its route assignments to learn about how it can increase the
number of miles driven on the electric buses and manage charging costs. The electric buses and charging
infrastructure have been affecting operations in three major ways: 1) their ability to meet route needs
for daily service, 2) the difference between expectations and actual capabilities for interoperability, and
3) maintenance considerations and net changes in uptime relative to the diesel hybrid buses that the
electric buses replace.
Ability to Meet Route Needs
Demand Management Software
$-
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
Pre Post
Summer month average demand charge Winter month average demand charge
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 198
Achieving the aforementioned cost savings at DTC from implementing the demand cap has required that
RTD carefully manage electric bus performance in coordination between the bus operators and the
control center. As demand management means that not all buses can charge as a matter of standard
operation, every bus operator must confirm that the SOC is sufficient to complete the next lap on the
route. When necessary, drivers now call the control center for approval to continue operating without
charging, and supervisors in the control center must manage these routes much more closely. Prior to
demand management, the operators simply pulled in and charged their buses without involving the
control center or worrying about range.
Nominal Versus Real-World Range
RTD has found the new Proterra Catalyst E2 buses are not achieving the ranges originally anticipated.
RTD staff are surprised and disappointed that the effective range is so much lower than the advertised
nominal range. In addition to expected impacts from extreme summer and winter temperatures, terrain,
and passenger loads, RTD has found that the effective range in revenue service is limited by two
additional factors: 1) the manufacturer’s recommendation not to deplete the battery below 20% SOC on
a regular basis and 2) the non-revenue service miles accrued driving the bus to the route from the depot
(and the return trip). RTD has found that the trip from the depot to the route can deplete the SOC more
than anticipated. Therefore, the district can use only 60%–70% of the battery on productive revenue
service miles after accounting for the 20% buffer and up to 10% loss before and after revenue service.
Stockton is in a climate that experiences temperature extremes, including an average high above 90°F in
July and August, which could explain the effective range being lower than anticipated. Further
information on bus performance on this route will be available in the final report.
Expectations for Interoperability
RTD staff indicated that they first learned of two interoperability limitations after they purchased buses
and installed chargers. First, after some of the initial communications between RTD staff and Protera,
RTD staff believed the 2016 short-range Catalyst FC buses would be able to use depot chargers installed
as part of the PRP, which was not the case. Although this may not have resulted in a major operational
impact, the lack of interoperability could affect future flexibility to respond to disruptions such as power
outages at other sites.
Second, when RTD deployed its 2018 long-range Catalyst E2 buses (originally configured to use depot
charging) on a route with an overhead fast charger, staff learned that the rate at which the buses
accepted an overhead fast charge was limited by the battery chemistry of the higher-capacity batteries
on the Catalyst E2 model. Particularly when the SOC fell below 45% or rose above 67%, the rate of
charging slowed substantially below the rated power of the selected charger. RTD staff do not recall
knowing about this prior to the purchase of the E2 buses in 2018 (a handout is currently available
describing the issue). The degree to which the Catalyst E2 model’s charging speeds may affect RTD’s
optimal charging protocol for these buses has yet to be determined.
This report will not verify what information and communications RTD received about interoperability
during procurement, but regardless of how the mismatch in expectations arose, this experience points
to the need for more OEM guidance, as well as careful review of specifications on the part of the
purchaser.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 199
Lesson Learned: The complexity of managing the charging protocol of multiple generations of buses with a mix of overhead fast charging and depot charging warrants more guidance from the bus manufacturer and requires sophisticated management from the transit agency.
Maintenance
RTD has observed that the percentage of days that electric buses have been available for service has
been lower than that of the diesel hybrids. In addition, the on-route chargers have frequently failed and
required maintenance. Statistics on the frequency of these challenges will be provided in the final
evaluation report after more data have been collected.
Table 39 summarizes the challenges associated with deployment of the 2018 long-range electric buses
and the charging infrastructure. The table does not provide a comprehensive depiction of all issues;
rather, it is simply a list of salient factors that RTD identified. It must be noted that adverse impacts from
these issues may diminish over time as Proterra and RTD learn more about the equipment and improve
their ability to prevent and/or to quickly diagnose problems. A full comparison of the frequency of
maintenance issues between the electric buses and the diesel hybrids does not fall within the scope of
the interim report, but preliminary information provided by RTD indicates that issues with the diesel
hybrid fleet arise approximately once per week and most frequently include issues with the following:
1) the dual power-inverter modules, 2) the hybrid energy storage systems, 3) the fuel system, 4) exhaust
gas recirculation system problems, and 5) issues with bus systems (such as doors, fareboxes, HVAC, and
radios). A more robust comparison will be provided in the final evaluation report.
Table 39. RTD unanticipated challenges and maintenance issues
Technology Issue Result/Resolution
Buses The steering column specification changed without warning.
The steering column required replacement on brand new buses.
Buses The SOC depletes faster than RTD expected under certain conditions because bus batteries did not properly interface with chargers.
Proterra recommended replacement of fans that cool the batteries (a $15,000 expense). This did not fix the problem, which ultimately was determined to be related to balancing of the batteries.
Buses The 2018 model year buses cannot charge faster than 0.7% of the battery capacity per minute on an overhead fast charger except when between 45%–67% SOC.
RTD has incorporated this knowledge into its plans for operating the 2018 buses.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 200
Technology Issue Result/Resolution
Buses There is latency between when vehicle telematics data are recorded and when they become available in the real-time tracking software (new data were unavailable between early summer and late fall).
Proterra dispatched technicians to replace its first-generation telematics system with a new system, which enabled shorter latency.
Overhead chargers
Bus operators must avoid turning too soon after disengaging with the chargers; otherwise, they will knock the paddles on the charger out of alignment.
Driver training is required.
Overhead chargers
RTD was required to change the pilot brushes monthly using in-house labor.
Proterra changed the charge head style, eliminating the need to change the pilot brushes.
Overhead chargers
PG&E’s meter was wired incorrectly and did not register RTD's usage until six months after it was in operation.
PG&E remedied the problem.
Overhead chargers
Compressors that power the pneumatic controls on the chargers failed.
Condensation was identified as a possible issue in the winter. The original compressors were exchanged with a different make and model, which significantly reduced this issue.
Overhead chargers
Previously, the charger model required frequent brush replacements.
The new design resulted in using new brushes that should last longer.
Overhead chargers
Outages in Stockton (due to fires) caused three grid areas to go offline and affected two overhead charger sites.
Spare buses were used to ensure service was not interrupted.
Depot Charger
Power quality must be high enough; otherwise, the chargers interpret this as a fault and shut down (routinely failing in mid-afternoon).
PG&E modified the supply to remove the shutdowns.
Demand management
No off-the-shelf solution was available.
RTD had to ask Proterra to develop a solution for them at DTC.
Despite this list of challenges, RTD was able to maintain its operations by having a higher-than-usual
spare ratio, which was created by delaying bus retirements. Due to these spares, RTD had available non-
electric buses to use as replacements when issues arose with the electric buses or their chargers. As the
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 201
electrification of RTD’s fleet scales up, higher reliability will be required, which may come with maturing
of the electric bus market.
Stakeholder and Customer Feedback
RTD PRP stakeholders and their management teams were interviewed individually and in a group
setting. Interviewees indicated that, in addition to the substantial financial incentive associated with this
PG&E PRP for the make-ready and the chargers, a significant participation motivator was to understand
what it would take to upgrade behind-the-meter infrastructure and make-ready infrastructure to
accommodate electrification of their fleet. Interviewees wanted to learn about working with PG&E and
the timelines involved, particularly the amount of lead time needed for PG&E to help with the make-
ready investments.
Ultimately, RTD wanted to understand how to scale the pilot to electrify 100% of its intracity fleet by
2025, in alignment with the district’s existing goals. Despite frustrations with the electric buses and
chargers, RTD staff are very satisfied with the support that PG&E has provided throughout the project,
and they note that the implementation process went as smoothly as one would expect for this sort of
infrastructure project.
Vehicle operators have been providing feedback to RTD management. Some operators try to avoid
being assigned to the electric buses, as they do not like the auto-docking process at the overhead
chargers, which slows the bus down and takes control out of the driver’s hands. Some passengers may
be anxious about timed transfers, and if the first attempt to dock fails, the bus must go around the block
and try again. When this happens, it also cuts into the operator’s scheduled break. Operators also
indicated they do not like the uncertainty associated with the SOC and not knowing whether they will
make their entire route. RTD believes operators will not mind the electric buses as much once the
district transitions to more depot charging.
These observations are only anecdotal, as reported by RTD staff to date. The evaluation team will gather
formal feedback from vehicle operators for the final evaluation report.
4.2.4 Conclusions
Below are a few preliminary findings based on the information collected to date. Additional data will be
analyzed for the final report.
Early customers in the electric bus market need more hands-on support than equipment providers are
prepared to provide. PG&E’s PRP fills this gap well, but it remains to be determined whether the amount
of support PG&E is providing RTD can be scalable to all EV Fleet program partners. From a planning
perspective, the manufacturers appear too busy meeting product demand to provide extensive fleet
advising. This has been evident, as RTD took time itself to understand the capabilities and limitations of
its new buses and chargers. RTD experienced manufacturer issues related to the electric drivetrain or
charging, along with changes in product specifications (e.g., changes to the steering column).
Furthermore, RTD was surprised by the actual range of its buses in real-world conditions. The nominal
range may lead prospective buyers to assume buses can complete routes not feasible for that bus
model, as the range in real-world conditions (and when maintaining a sufficient SOC buffer) is
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 202
substantially less. The fleet intends to emphasize realistic estimates of the real-world range during
future procurements.
From an equipment reliability perspective, the need for more hands-on support is apparent because
more problems surfaced than RTD expected, and it was not clear who was responsible for addressing
the issues. RTD originally believed the overhead chargers would be nearly maintenance-free. However,
experience revealed issues with vehicle operators knocking the paddles out of alignment, issues with
compressors for the pneumatic controls, and a need to switch to a new charger brush style, as well as
items which RTD cannot repair without Proterra’s assistance.
RTD feels it is learning in parallel with Proterra, which is slightly disconcerting. In summer 2019, all
overhead chargers at UTS and DTC were out of commission for more than a month, preventing the
shorter-range 2016 fleet from staying in service. The 2018 electric buses were still partially operational
using depot chargers but had to be pulled from their routes by mid-afternoon because of insufficient
range. Transit agencies that intend to retire diesel buses one-for-one when they purchase electric buses
will need quick resolutions to their maintenance problems, or they must maintain adequate redundancy
in buses and charging infrastructure. RTD has been fortunate in having sufficient non-electric spare
buses to operate without major interruptions, despite the reliability issues with some buses and
chargers.
The depot chargers at RTC were routinely shutting down for some period between 4:00 pm and
8:00 pm, and Proterra could not diagnose the problem. Eventually, it was diagnosed as a power quality
issue and not a problem with the chargers.
Custom solutions are still needed for each electric bus deployment. No off-the-shelf charging
management software was available for Proterra chargers when PG&E launched the PRP. Proterra was
able to develop a custom solution for the DTC site, but it does not plan to support the integration of
charging management at UTS, because of that site’s increased complexity with the BESS. Important
considerations in the development of custom solutions for each charging site include the following
factors: the ratio of buses per charger, demand charges and tariff TOU periods, other distributed energy
resources on the site, and the capabilities and configuration of the electric buses. An important
consideration is the solution’s simplicity—RTD emphasized the imperative of eliminating as many risks
as possible to maximize the chance of successful and reliable charging on every charging cycle.
Additionally, customers should expect to encounter limitations when trying to use charging system
combinations. As detailed in the Operational Impacts of Project Equipment section, RTD experienced
two unanticipated limitations to interoperability between the multiple generations of buses and
chargers in its fleet. This points to the inherent complexity of managing the charging protocol for
multiple generations of buses with a mix of overhead fast charging and depot charging. This complexity
warrants more guidance from the OEM and sophisticated management from the transit agency.
As a result of this PRP, additional knowledge and capacity is being built that will enable better
management of electric buses and related assets at RTD. Management of electricity costs is challenging,
particularly given the limited flexibility transit agencies have in their routes and operations, especially in
cases where many buses share charging across several sites, as at RTD. Shifting from managing diesel
expenses (long-term contracts can be locked in) to electricity (prices can fluctuate over the course of a
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 203
day, and a single anomaly can result in substantially higher costs) requires careful planning and
sophisticated management. Because such a high percentage of the monthly electric bill is determined by
demand, the cost per mile can be very high if buses are not heavily utilized, which was a motivator
behind development of PG&E’s approved CEV rate.
Prior to the PRP, RTD incurred high demand charges so this project implemented demand management
software. This step successfully capped demand and reduced total electricity expenditures. This is
important for PG&E because, if operational cost savings are not realized, more transit agencies may
begin to reevaluate their compliance pathways for the CARB ICT and consider a different balance
between battery electric buses and alternatives such as fuel cell buses. The test phases of this project
are enabling RTD to understand the capabilities and limitations of its buses and chargers, so it will have
more knowledge and flexibility to deploy buses in the future while managing on-time performance,
demand charges, and peak TOU periods. This knowledge will remain helpful, even as PG&E introduces
its CEV rate that significantly reduces the cost of monthly demand, which should also make
electrification more compelling for transit agencies. For agencies that do not have the benefit of
participating in a PRP that enables sophisticated charging management, this rate will be critical to
support their transition from gasoline or diesel to electricity.
Additional challenges for RTD in its future planning include the following: 1) determining the cost per
mile for a specific route, given specific charging sessions may not be easily traced back to specific buses
on specific routes; 2) determining the optimal ratio of buses to overhead chargers and depot chargers;
and 3) allocating costs (both upfront and ongoing) and optimizing charging in context with a system
using BESS, renewable generation, and multiple charging options for buses of several different vintages.
The next year will provide opportunities to evaluate these new factors once construction at UTS is
complete, now that metering issues and Proterra data availability limitations have been resolved.
The challenges encountered by RTD are not an indication of failure or improper project delivery by PG&E
and project implementors. Rather, they point to the value of the approach that PG&E proposed in its
PRP, which anticipated the need to have more extensive collaboration after installation of the physical
infrastructure. Given the relative nascency and fast growth of the battery electric bus industry, growing
pains are expected, and the utility can act as a partner to help provide positive experiences for early
adopters. The collaboration through this project to date indicates that such hands-on involvement has
provided substantial value to RTD in troubleshooting day-to-day issues, managing costs, and enhancing
its ability to gather the information necessary to effectively plan the expansion of its electric fleet.
Lessons Learned
Early partnership between the utility and transit agencies will provide opportunities for transfer
of knowledge and best practices. The utility brings unique insights and can support agencies
with the expertise utility staff have developed through implementing programs and projects
throughout the territory.
The complexity of managing the charging protocol of multiple generations of buses with a mix of
overhead fast charging and depot charging warrants more guidance from the bus manufacturer
and requires sophisticated management from the transit agency.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 204
4.3 Idle Reduction Technology Project – eTRUs at Albertsons Distribution Center
4.3.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
In its January 11, 2018 order (D.18-01-024), the CPUC approved $1.72 million for PG&E to pursue an Idle
Reduction Technology Project among its PRP efforts.63 A May 2018 advice letter (Advice 5279-E) further
detailed PG&E’s intention to focus on eTRU market.64 This interim report covers the stages of the PRP
that have been completed thus far: scoping and customer acquisition, project design and preparation,
construction, and commissioning. The project is now actively operating, and data collection is under
way. Analysis of these data and concluding lessons learned will be covered in the final evaluation report.
An eTRU is a hybrid model with electrically driven refrigeration components that can be powered by an
onboard diesel generator or through electric power, if plugged in. The objectives of the eTRU pilot
include 1) demonstrating a lower TCO for the technology through minimizing fuel and infrastructure
costs, 2) developing lessons learned that can be shared with other distribution facilities supporting
PG&E’s EV Fleet Program, and 3) reducing emissions of harmful pollutants from diesel engines.
The pilot was designed to address several barriers that may be limiting uptake and full implementation
of eTRU technology. The 2018 advice letter cited findings from CARB that “limited fueling infrastructure
exists and fueling infrastructure costs are significant.” These, along with research from EPRI, formed the
basis for PG&E’s selection of key barriers to addressed with the project:
High up-front capital costs of infrastructure and capital constraints on the part of fleet owners/
facilities
Lack of awareness and misconceptions about the return on investment of the technology
This application is a good candidate for transportation electrification because eTRU technology is
broadly available. Additionally, shifting from diesel to electric energy is expected to generate valuable
fuel cost savings and air quality improvements at distribution centers that are likely to be located in or
near DACs. The pilot aims to demonstrate the benefits of using standby electric power for eTRUs relative
to the status quo practice of idling diesel engines. It also aims to share learnings that will help other
fleets implement similar projects. The success of this PRP will pave a pathway for refrigerated
distribution centers to comply with anticipated eTRU regulations from CARB (discussed further in the
Project Baseline section of Evaluation Findings for the PRP) and for broader deployment of the
technology across the state.
63 Public Utilities Commission of the State of California, Decision 18-01-024: “Decision on the Transportation
Electrification Priority Review Projects,” January 11, 2018,
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M204/K670/204670548.PDF 64 Public Utilities Commission of the State of California, Advice Letter 5279-E, May 24, 2018,
https://www.pge.com/tariffs/assets/pdf/adviceletter/ELEC_5279-E.pdf.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 205
Sites and Participants
Recruitment of Site Host
As first proposed, the PRP scope covered a variety of potential site host types, including truck stops as
well as small, medium, and large warehouse and distribution facilities. PG&E collaborated with CARB to
generate a list of eTRU fleet owners that could be approached to host the project.
A few key factors drove the final decision to partner with the Albertsons Distribution Center in Tracy,
California:
Internal capacity: Albertsons was able to dedicate sufficient institutional resources to meet the
data collection, project management, and scoping requirements of pilot participation.
Capital flexibility: As a larger company, Albertsons has more flexibility to absorb shifts between
capital and operating budgets relative to small- or medium-sized businesses.
Rebate option: Albertsons is a transmission-level customer that had enough capacity available
on its existing service infrastructure to pursue the project completely on the customer side of
the meter, which allowed PG&E to test out a rebate approach for make-ready infrastructure.
This is an option that will be available in PG&E’s EV Fleet program, as part of its SRPs.
Aligned incentives: Unlike truck stops and smaller distribution centers, which often serve fleets
that are not owned by the same owner as the facility, the vehicles served at the Albertsons
distribution center are not owned by third-party operators. Therefore, the savings on fuel costs
over the lifetime of the project are captured by the same entity that paid for the upfront capital
expenditures. Albertsons’ operations encompass all aspects of the project value chain, ensuring
aligned incentives that encourage utilization of the infrastructure.
Streamlined implementation: As the single owner and operator for both the facility and fleet,
Albertsons presented a simplified project. There was no need to arrange a payment mechanism
for electricity supplied to eTRUs or coordinate with multiple stakeholders representing
separately owned fleets that might utilize the infrastructure.
Site and Site Host
Albertsons is a large grocery company that operates a food distribution service center in Tracy,
California. Located in a DAC, the 2.2-million-square-foot facility has 313 dock spaces and more than 400
staging spaces where loaded trailers wait until their delivery time. Albertsons is a sophisticated
electricity consumer because the distribution center requires significant energy to regulate the facility’s
temperature. Unrelated to the PRP, Albertsons hosts two 1 MW wind turbines at this site and acts as a
Direct Access customer subscribed to a unique electricity rate. In fact, Albertsons’ electricity
consumption at the Tracy facility is so significant that the facility’s staff at the site expect the load
impacts of the 25 eTRU ports to be imperceptible relative to total facility consumption.65
65 The SafeConnect plugs selected for the pilot are each capable of delivering 14–17 kW, although on average, an
eTRU would not consume the full amount of power available.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 206
As a company operating within a very competitive industry with narrow margins, Albertsons’ approach
to the PRP is different from that of public-sector fleets. Albertsons is supportive of helping to advance
transportation electrification technology for this application but must protect its business interests at
the same time. For instance, while Albertsons has indicated that it will be collaborative in sharing
information, staff have requested extra levels of review and approval before disclosing operational data
or inviting others for site tours.
Albertsons may also differ from the other PG&E PRP partners, as Albertsons had the capacity to manage
the engineering and construction process entirely internally. Albertsons managed the project, paid for
expenses as they arose, and received reimbursements from PG&E on a milestone completion basis.
A schematic of the site with charger locations can be seen in Figure 94.
Lesson Learned: Private-sector facilities and fleets may be sophisticated electricity consumers. This makes them valuable partners that can implement projects quickly, but also poses challenges associated with collecting operational data and compiling lessons learned that can apply to other site hosts.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 207
Figure 94. Albertson’s facility showing location and placement of eTRU ports
Source: PG&E SB350 2018 Interim Report66
Recruitment of Implementers and Additional Vendors
The eTRU pilot required fewer third parties to serve as implementers and vendors than PG&E’s other
PRPs, as this project has less focus on charging management or other additional features. This is
responsive to Albertsons’ needs and interests at this time, which are focused on how to install and
operate the infrastructure. Furthermore, PG&E did not need to invest substantial effort in guiding
Albertsons through the design and construction process. This was primarily because Albertsons is a
transmission-level service customer and had sufficient power available on the company’s existing
service to supply the entire power needs of this PRP. Albertsons desired to power its eTRU infrastructure
using the internal switchgear and electrical system rather than pulling a new service from PG&E. This
eliminated the need to coordinate with PG&E on to-the-meter construction.
66 From PG&E’s Interim Priority Review Report:
http://docs.cpuc.ca.gov/SearchRes.aspx?DocFormat=ALL&DocID=285086006
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 208
The two external vendors used for the project supported the construction and equipment needs.
Albertsons engaged Hansen Rice, a contractor, who had extensive experience working with the company
at that site. The contractor did not have eTRU experience, but that was not deemed to be a major
hurdle. After agreeing to participate in the PRP, Albertsons determined that SafeConnect was the
vendor best suited to provide the charging ports and receptacles. SafeConnect’s six-pin plug was
deemed satisfactory from a safety standpoint, and at the time of project initiation, SafeConnect was the
most mature vendor offering this type of product.
Another unique aspect of this PRP is that the site host owns and maintains the infrastructure. This
means that Albertsons could conduct internal coordination to deploy the project and was motivated to
wrap the project up efficiently because the company was reimbursed upon task completion. On the
other hand, PG&E faced the risk that, if the project were not a priority for the site host, implementation
could be delayed because PG&E would not have control over the schedule. This risk was mitigated by
structuring the incentive to Albertsons in milestones, releasing incentive payments after completion of
critical steps in the project, such as charger procurement, finalization of design and engineering, and
close of construction. The utility did not actively manage the design and construction of this project,
which may have limited lessons learned. However, PG&E’s engineering and construction teams were
involved in reviewing the project design and inspecting the installed equipment prior to release of
incentive payments. The utility was able to leverage these steps to mitigate the loss of insight into the
design and installation of eTRUs without actively managing the project. Ultimately, this PRP required
relatively little coordination with additional partners and vendors.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 209
Timeline
Original Planned Timeline
The table below illustrates the original timeline (pale blue fill) and the achieved timeline (medium blue fill) for the eTRU PRP. This divergence
reflects a variety of disruptions and challenges, many of which were unforeseeable on the part of PG&E or the site host.
Figure 95. eTRU PRP comparative project timeline
Note: Open diamonds indicate original milestone date.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 210
The original timeline for the eTRU PRP design and construction period planned for commissioning in
May 2019. Project milestones included site enrollment, finalization of the design, completion of
construction, and commissioning of the charging equipment. The project was commissioned in
November 2019.
Explanation of Notable Timeline Alterations
In some instances, the actual project timeline diverged from plans. Albertsons lost nearly two months
because of an issue with its switchgear. The switchgear, which already existed at the site, was rated with
sufficient electrical capacity to serve the additional load. However, a key component of the switchgear
(a safety interlock) was found to be non-operational, and the part necessary to replace it was no longer
available on the market. This caused a two-month delay as the legacy part was fabricated. Had
Albertsons’ staff tested the legacy equipment at the start of the implementation process, the issue may
have been detected early on.
The permitting process with the local AHJ also took a month longer than expected. The AHJ was
unfamiliar with this technology, which prompted additional back-and-forth between the county staff
and Albertsons. While permitting delays are likely to be out of the hands of both PG&E and site hosts, it
may be effective for state agencies such as CARB to work with AHJs to inform them of eTRU technology
to help streamline the permitting process for future eTRU projects. This could be strategically focused
on AHJs where food distribution centers are located to more effectively target permitting processes.
Albertsons estimates that, if the company were to do the project again, the timeline of the construction
process would be closer to four months rather than the seven to eight months it took this time.
Lesson Learned: Legacy equipment may not be in sufficient condition to be relied upon for new electrification infrastructure; equipment should be analyzed, and its condition should be tested. Additionally, projects can benefit from strategic sequencing of required phases or activities to reduce delays overall.
Planned PRP Activities and Current Status
Current Status
The 25 ports were electrified and ready for operational use on November 18, 2019. There are 15 ports
at loading docks and 10 ports at parking spaces used for staging. Albertsons is still reviewing preliminary
data from the first few weeks of operation and ensuring that its submeters are correctly configured.
In parallel with the decision to build the infrastructure, Albertsons prepared 270 of its newest eTRU
trailers with a SafeConnect compatible plug. Notably, these 270 are only about a third of all the trailers
operating at the site (total on site is approximately 900). Rather than retrofit the remaining older
trailers, Albertsons has decided to specify that any new trailer will be compatible with the charging ports
every time an older trailer is retired and a new one is procured.
The docks that were electrified are on the loading (outbound) side. The busiest loading docks were
selected for electrification, which enables Albertsons to maximize the amount of time that eTRU trailers
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 211
will be able to be plugged in. The protocol for when compatible eTRUs are parked at electrified docks is
shown in Figure 96.
Figure 96. Protocol when a compatible trailer is parked at an electrified dock to load
The selection of the dock for each trailer is driven by food distribution logistics. This process cannot be
adjusted to ensure that the trailers compatible with the SafeConnect system are placed at the electrified
docks. While adjusting the process would help increase electrification utilization, it would introduce too
much operational complexity to be feasible, according to Albertsons staff.
However, the selection of parking locations in the yard to stage the loaded trailers will be responsive to
the electrified parking spaces. Yard hostler operators have been instructed to park compatible trailers
(which have a large sticker on them indicating compatibility) at an available electrified space to
maximize electric usage. The amount of time a loaded trailer is parked in the staging area can be
significantly longer than the time parked at a loading dock, so this protocol is expected to have a bigger
impact.
Construction Update
All PRP construction activities are complete. Construction included procurement and installation of 25
SafeConnect eTRU ports, including replacing switchgear and running wiring and conduit to 15 docks,
running wiring and conduit across the parking facility to the staging area for 5 additional SafeConnect
dual-port units (which required 300 feet of trenching), installing protective mounting systems for the
units in the staging area, installing Eaton Power Xpert Multi-Point submeters, and commissioning the
system.
Current Learning Objectives
PG&E is using this PRP to learn more about eTRU operations and how to implement supporting electrical
infrastructure. While PG&E expects eTRUs to be a key market segment for transportation electrification,
staff hope to determine the extent of customer demand and to understand how customers are using the
technology. Since cost-effectiveness is expected to be a major driver of demand, the pilot is focused on
Empty trailers are are parked at electrified
loading docks and plugged in
eTRU runs on electricity until temperature is at
setpoint
eTRU is turned off while product is loaded
(~one hour)
Loaded trailer is moved to electrified staging area and plugged in
eTRU runs on electricity as needed to maintain
temperature while waiting for truck and
driver
Trailer heads out for delivery
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 212
reducing TCO. While PG&E originally considered investigating whether eTRUs can be leveraged as grid
assets, it is not currently anticipated that the pilot will address this question. Furthermore, interviews
with Albertsons staff have indicated that they are primarily interested in protecting their cold products,
schedules, and logistics and are therefore not interested in demand management if there is a chance
that such actions could interfere with these business priorities. Demand management that would not
affect logistics would likely require expensive additions to the project (e.g., energy storage) or switching
temporarily to diesel when needed (which would be contrary to the PRP goals).
Participation in the PRP provides Albertsons the opportunity to learn about eTRU technology and
consider its impacts on the facility’s operations. A primary goal is to learn how to do this while
protecting the “cold chain” that is the cornerstone of this business. Albertsons wants to understand how
fueling and maintenance costs differ when running eTRUs on electricity versus diesel. Likewise,
Albertsons is monitoring and addressing potential impacts on employee productivity and safety as well
as reception of the project by key staff, including fueling staff, hostler drivers, and distribution drivers.
Finally, in recognition that there will likely be future requirements in California to run eTRUs on
electricity, Albertsons is motivated to understand how to scale implementation in the future.
4.3.2 Evaluation Methodology
Selected Methods and Rationale
The evaluation team is collecting a wide range of data and information to answer the evaluation
questions set forth in the evaluation plan. For this PRP, in addition to the research questions that apply
to every PRP and each fleet electrification PRP, the evaluation seeks to understand how projects driven
entirely by the site host differ from those in which the utility has a more active management role.
Because the eTRUs at the site have been operating on electricity for only a very limited period, drawing
conclusions from an analysis of the charging patterns and operational costs incurred by the fleet to date
would be premature, and formal analysis has been deferred until the final evaluation report.
Data Sources
In-depth interviews were used to better understand the decision-making process and reasoning behind
this project. An interview with PG&E staff collected lessons learned on the implementation process,
discussed data collection, and confirmed the partner outreach and selection approach. Following
commissioning of the electrical connections, Albertsons’ staff were interviewed during a site visit and
then afterwards by phone. These interactions involved the management personnel that oversee
engineering, transportation, and distribution center operations. These conversations captured an
understanding of the barriers, expected savings from idle reduction, lessons learned from planning and
construction, seasonality of eTRU deliveries/activities, and how best to gather feedback from the staff
affected by the PRP (e.g., fueling staff, hostler drivers, distribution drivers, and maintenance staff). After
the eTRU electrical ports have been operating for several months, a survey will be fielded, and
Albertsons will help gather feedback from these stakeholders.
The evaluation of this project will also incorporate an assessment of quantitative data on usage patterns
and costs. Because the project was recently commissioned (in November 2019), the evaluation findings
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 213
presented thus far are based only on the completed interviews and information about the construction
process.
4.3.3 Evaluation Findings
Project Baseline
A major question is whether PG&E’s efforts caused or have the potential to advance the electrification
of equipment in this application by addressing critical barriers. To address this question, it is important
to look at the baseline of industry uptake and innovations developed through the project that have the
potential to be applied broadly.
The broader context of the PRP is that eTRU deployment is quite prevalent, but it is extremely rare that
the units are plugged in to utilize electricity. According to Albertsons staff, even salespeople
representing the leading eTRU manufacturers were uncertain about the necessary specifications of
charging ports to plug in these units. CARB is currently considering a suite of regulations covering
transport refrigeration unit (TRU) facilities, truck TRUs, time limits on idling, and the operation of
internal combustion engines to power TRUs.67 These various regulatory programs are aimed at shifting
the refrigerated transportation market and technology adoption trends. The Albertsons PRP is
representative of a situation—one likely to be increasingly common in the near future—in which
warehouses and distribution centers must meet a requirement to electrify but have little experience
managing the process, including procurement, installation, and operation of infrastructure. Therefore,
the potential value of this project is to provide lessons about the pathway to scale deployment of eTRUs
in PG&E’s territory faster and more effectively than facilities would achieve without PG&E’s
involvement.
Implementation Process
During the planning, design, and construction phases of the project, Albertsons and PG&E reviewed
available technologies and developed solutions that may provide useful lessons for future eTRU
projects. First, they needed to mitigate the risk that drivers would pull vehicles away from ports without
properly disconnecting chargers.68 After researching available options, Albertsons’ staff found that
SafeConnect had safeguards to mitigate this pull-away risk. Second, there is no consistent standard for
eTRU connectors. After selecting the SafeConnect system, the eTRUs needed to be retrofitted with the
SafeConnect connectors. Albertsons chose to retrofit 270 of their trailers, placing a SafeConnect
receptacle at the rear on the driver’s side so that when the vehicle is at the dock, the receptacle is close
to the plug-in point. Finally, for the staging area location, Albertsons designed a protective mounting
system comprising 4” thick steel posts driven deep into the ground on all four sides of the equipment
67 CARB, TRU Meeting & Workshops, accessed 2019, https://ww2.arb.ca.gov/our-work/programs/transport-
refrigeration-unit/tru-meetings-workshops. 68 The arc that could be created if a driver pulled away while connected to an energized 6 to 18 kW charger could
pose a significant safety risk and damage equipment.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 214
(Figure 97). This was done to ensure the SafeConnect equipment was shielded from unintended
impacts.
Figure 97. SafeConnect ports in use at staging area, with protective mounting system
Source: Albertsons staff
Lesson Learned: Project implementers should know in advance there is not a standard for eTRU connectors and receptacles, so retrofitting equipment may be necessary. Utilities should support the establishment of an industry-wide eTRU connector standard to simplify future deployments. Likewise, design guidelines and installation best practices are needed and should be shared broadly.
Table 40. Unanticipated challenges and maintenance issues encountered by Albertsons
Technology Issue Result/Resolution
Switchgear Legacy equipment failure Custom manufacture of replacement part over a two-month period
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 215
Costs
In the CPUC’s 2018 PRP decision, PG&E was approved $1.72 million for this PRP, consisting of $870,000
in capitalized costs and $850,000 in expenses. For this report, PG&E provided total project expenditures
through October 2019.
Project Costs
Table 41: Summary of PG&E Project Costs through October 2019
Cost Category Capital Expense
Project management (PG&E)69 N/A $ 80,919
Preliminary engineering and design $ 12,619 N/A
SafeConnect materials
Stations at 15 docks and 10 staging spaces
$ 73,959 N/A
Switchgear materials
Does not include switchgear repair costs Albertsons incurred
$ 47,572 N/A
Construction and installation $ 334,154 N/A
General liability and markup $ 12,822 N/A
Project total $ 562,045
The rebate was proposed to be broken into payments to be made upon completion of established
milestones:
completion of construction design,
procurement of charging equipment,
completion of construction, and
commissioning of charging equipment.
69 Albertsons’ project management costs were not funded by the PRP and are therefore not included in this
update.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 216
Comparison of Actual and Forecast Costs
Full project costs are pending as the project remains under way. It appears that the project is on track to
come in under the PRP budget of $1,719,400.
As the host has a transmission-level account, there were no utility-side make-ready infrastructure costs
(“to-the-meter” costs). Future projects may have a substantially different cost profile. Additionally, while
PG&E’s original filing suggested implementation of charge management and potentially even energy
storage, the project was scoped based on the site host’s specific needs and interests, and as a result,
these elements were not included. Costs are not expected in those cost categories, and thus the project
will come in under the approved budget.
Lesson Learned: For customer-owned and -operated projects, the utility could continue to consider ways to ease the customer’s upfront outlay of funds. (PG&E made reimbursements payable upon achievement of milestones rather than at the conclusion of the project.)
4.3.4 Conclusions
This project is still early in its lifecycle. Robust data are not currently available to support conclusions
about project benefits, metrics associated with eTRU operations on the site, or stakeholder satisfaction.
However, information has been collected about Albertsons’ motivations, the upcoming regulatory
context, and the design and construction process. Albertsons was interested in participating in the
project to gather learnings that would help it comply with the forthcoming CARB regulations.
Anticipating needs for future regulatory compliance, rather than securing an economic payback, is the
principal driver for Albertsons’ experimentation with this technology; it is likely this will be the primary
motivation for future program participants as well.
The impact of the PRP to date appears to be that it motivated Albertsons to move forward and install
and test the electrical connections in collaboration with PG&E, an action company management
intended to complete but had not prioritized. The anticipated impact of the remainder of the project is
providing lessons learned for similar fleets. In 2020, PG&E will be developing a handbook to document
the process and share lessons learned with other fleets. Considering likely future requirements in
California to run eTRUs on electricity and the limited availability of eTRU electrification case studies, this
handbook could be very valuable, particularly for operations like Albertsons. Additional considerations
will need to be explored to determine how these lessons can be extrapolated to other types of eTRU site
hosts, such as medium and small customers, customers that do not own the fleets and trailers that
operate at their sites, and customers with a lower level of energy management knowledge and
attention. Nonetheless, this project provides important lessons that can be applied to future eTRU
electrification efforts.
Lessons Learned
Private-sector facilities and fleets may be sophisticated electricity consumers. This makes them
valuable partners that can implement projects quickly, but also poses challenges associated with
collecting operational data and compiling lessons learned that can apply to other site hosts.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 217
Legacy equipment may not be in sufficient condition to be relied upon for new electrification
infrastructure; equipment should be analyzed, and its condition should be tested. Additionally,
projects can benefit from strategic sequencing of required phases or activities to reduce delays
overall.
Project implementers should know in advance there is not a standard for eTRU connectors and
receptacles, so retrofitting equipment may be necessary. Utilities should support the
establishment of an industry-wide eTRU connector standard to simplify future deployments.
Likewise, design guidelines and installation best practices are needed and should be shared
broadly.
For customer-owned and -operated projects, the utility could continue to consider ways to ease
the customer’s upfront outlay of funds. (PG&E made reimbursements payable upon
achievement of milestones rather than at the conclusion of the project.)
4.4 Home Charger Information Resource Program
4.4.1 Project Narrative
Overview, Objectives, and Barriers Being Addressed
PG&E staff initially proposed the Home Charger Information Resource (HCIR) Program to develop a web-
based resource that would help customers research their options on the level of EV charging best
matched with their driving patterns, help customers understand the process to install EV charging, and
provide a list of certified electrical contractors who could safely install residential EV charging
equipment. This webpage was intended to complement the new EV savings calculator provided by
PG&E. To promote the webpage, PG&E also planned to conduct outreach to customers who had
recently purchased EVs.
PG&E staff intended the webpage and outreach to help customers overcome informational barriers to
EV adoption by making it easy to learn about home EV charging needs, educating prospective EV
purchasers about available charging options, and advising EV owners about whether a faster charging
option makes sense. PG&E also planned to provide information to help customers understand whether
Level 1 charging could meet their typical daily mileage needs if charging exclusively off-peak, and how
the customer’s choice of Level 1 or Level 2 charging could affect ongoing customer costs of overnight
charging under the current PG&E TOU periods.
However, the CPUC’s review of the initial program design revealed multiple existing home charger
installer tools already available in the marketplace (Angie’s List, Home Advisor, Porch, and Amazon),
which fulfilled most of the functions originally proposed for PG&E’s tool. Therefore, understanding the
CPUC’s intent not to have the utilities duplicate existing tools, PG&E submitted an advice letter70
outlining a modified program objective to focus on exposing residential customers to these existing
70 Advice letter 5621-E, August 16, 2019, https://www.pge.com/tariffs/assets/pdf/adviceletter/ELEC_5621-E.pdf.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 218
market resources and presenting comprehensive information about home chargers and the installation
process.
PG&E staff are currently enhancing the EV information previously provided on the utility website. This
includes information to help customers know what to look for when purchasing a Level 2 charging
station and resources to connect customers to EVSE installation contractors. This website will be
translated into Spanish and Chinese to foster greater engagement with customers in DACs. Ultimately,
this effort intends to engage disadvantaged and minority communities, provide education on home
charger installation, and make the installation process more convenient.
Participation
PG&E is currently updating its website with plans to launch the webpage and outreach activities in early
2020. Therefore, the customer engagement process and participation are not evaluated in this report.
Timeline and Status
The CPUC approved the HCIR Program in January 2018. PG&E completed additional program scoping, as
requested by the CPUC, between April and July 2019. PG&E filed an advice letter in August, which the
CPUC approved in September 2019. PG&E intends to complete the website and launch the program
early in 2020.
4.4.2 Evaluation Methodology
Selected Methods and Rationale
The evaluator initially sought to address the common PRP evaluation questions that apply to all PRPs
and those specific to the Education and Outreach PRPs. The data collection tasks utilized to evaluate this
PRP include information review and a PG&E staff interview.
As part of revising the PRP, per the final advice letter, PG&E staff also conducted secondary research to
determine whether the content intended for the new website was already offered elsewhere. This
research considered 15 CCAs and utilities and focused on four key components:
Did the content connect readers directly to EVSE installers?
Did the content provide targeted information on home charger installation?
Was the content offered in multiple languages?
Was the content easy to understand?
PG&E’s research found that although there is well-developed content related to the availability of home
charging, no CCA or utility currently provides a comprehensive source of the content PG&E intends to
develop through this PRP.71
71 Q3 2019 Clean Transportation Program Advisory Council Meeting Presentation, October 16, 2019.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 219
Data Sources
Working closely with PG&E, the evaluation team modified the evaluation approach to reflect the
changes to program design and launch timing. The team reviewed all program-related materials.
In November 2019, the team interviewed key PG&E staff to gain insight on the progress to date for the
HCIR Program. The interview covered these topics:
Initial program design (and changes)
Electrification barriers to be addressed by the HCIR Program and what PG&E will do to address
these barriers
Future availability of analytics (number of installers listed on each home service tool, number of
installation jobs completed as a result of traffic directed from PG&E’s resource page, etc.) and
information about customer groups who completed charger installation (single-family, renter,
DAC, etc.)
Areas of success, challenges, and lessons learned from the program (including possibility of
scaling)
4.4.3 Evaluation Findings
The interim evaluation findings for the HCIR Program are based solely on the PG&E staff interview since
there are no program data to evaluate.
Stakeholder Feedback
PG&E staff reported a collaborative and positive atmosphere in pursuing the modified HCIR Program.
For example, staff noted the possibility of collaborating with the low-income and general marketing
teams within PG&E to take advantage of existing outreach activities in combination with the translation
of the website into Spanish and Chinese.
Staff said the webpage will be completed by early 2020 and will direct customers to market resources
that identify certificated installers, such as Angie’s List, Home Advisor, Porch, and Amazon. Staff noted
that the completed website will also provide customers with tools such as a savings calculator and a
checklist that includes common questions to ask an electrician. Other key information the webpage will
include is how to select the right rate plan and what level charger best suits a customer’s need. Staff said
the goal is to empower customers by giving them the knowledge and confidence to transition to an EV
and engage with technical professionals for help with the charging installation process.
Currently, PG&E staff are working with possible market resource vendors to learn what types of data are
available to track, such as the number of certified installers per market resource (e.g., a website such as
Angie’s List) and the number of customers who move from the PG&E website to the market resources
and then actually complete an installation. In addition, staff intend to track the number of visitors to the
HCIR Program website and to the translated pages. PG&E staff are also exploring other possible data to
collect, such as customer locations to identify DAC engagements with the program resources.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 220
Once the website is launched, staff will explore how to apply these new customer resources in other
PG&E programs and collect customer feedback to understand how people use the resources and what
improvements could be made.
4.4.4 Conclusions
Though the HCIR Program underwent a significant design change, which delayed its launch, PG&E staff
experienced successes and can apply lessons learned as the program moves forward.
Successes and Lessons Learned
The ability to adapt to changing market conditions is essential for any innovative program. PG&E
responded to requests from the CPUC to review the initial program concept by investigating current
market offerings. The proposed modifications maintained the objective to provide suitable information
to DAC customers in three languages (English, Spanish, and Chinese). The HCIR Program will provide
customers with resources to identify EV charger installers, comprehensive information about EVs and
charging options, questions to ask electricians, and access to a savings calculator.
PG&E can continue to revise the program after its launch, basing adjustments on the data collected
about customer responses regarding the usefulness of the new resources.
Next Steps
PG&E staff are currently working on completing the website, which will launch in early 2020. At that
time, staff will also conduct outreach to DACs to promote the website and increase EV awareness. This
outreach will include both a digital presence and hard copy materials in English, Spanish, and Chinese.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 221
Three SMJU Priority Review Project Status Update
In June 2017, PacifiCorp, BVES, and Liberty filed an application with the CPUC proposing seven PRPs to
promote transportation electrification. The CPUC approved the proposed programs in September 2018
as part of Decision 18-09-03472. That decision included a requirement to use the same third-party
evaluator selected by the three large utilities in support of their transportation electrification projects.
The SMJUs launched these PRPs well after the large utilities’ PRP start dates; therefore, this interim
evaluation report provides only a brief status update on the seven PRPs.
PacifiCorp Outreach and Education Program ($170,000)
This program was designed to promote awareness of EV ownership options to address an educational
barrier for ownership. The objective was to increase residential and commercial customers’ comfort
with, and acceptance of, electric transportation through engagement and affect current market
baselines. This would reduce a barrier to transportation electrification by improving customer
awareness of EVs and EVSE.
In April 2019, PacifiCorp began sending education emails to residential and commercial customers
through this Outreach and Education PRP. In May 2019, PacifiCorp launched, with the support of the C2
Group, the technical assistance portion of the program, and in September 2019, utility staff started
participating in community outreach events with the support of Forth Mobility (Forth). The marketing
portion seeks to address customers’ perceived barriers of operating and owning an EV by providing
information on home charging, fuel savings, emissions reduction, and available federal tax credits. The
project focuses on intervention-based activities to increase awareness and knowledge, as well as
address technology perceptions and support EV purchasing decisions. As part of this effort, EVs were
brought to community events for test drives. Online and traditional mail marketing was used to
encourage residential customers to consider EVs and commercial customers to install EVSE on their
property. The marketing materials also encourage commercial customers to apply for grant funding
provided by the PacifiCorp Demonstration and Development PRP.
The program also offers self-service resources and tools that help customers better understand total
lifecycle costs and savings potential by examining vehicle options, utility bill impacts, and incentives. In
addition, commercial customers may request technical assistance, provided by the C2 Group, to
complete feasibility assessments for customers’ EVSE projects. Each assessment involves a desk review
and an onsite tour of the property. Every customer receives an assessment report when the site review
is complete.
72 Public Utilities Commission of the State of California, Decision 18-09-034: “Decision on the Priority Review and
Standard Review Transportation Electrification Projects,” September 27, 2018,
http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M231/K030/231030113.PDF.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 222
PacifiCorp Demonstration and Development Program ($270,000)
This program was designed to provide competitive grant funds to non-residential applicants for
installing EV charging stations on their property. The program helps commercial customers overcome
up-front cost barriers and empowers them to develop projects that addresses additional barriers, such
as lack of awareness, lack of public EVSE, and limited EVSE access for low-income and underserved
communities. The program allows commercial customers to apply for grant funding to cover some or all
upfront costs for installing EVSE. Applications are accepted quarterly, and a webinar is held halfway
through the grant submittal period to answer any questions applicants may have before submitting their
applications. Qualifying applications are scored by Nexant, which supports the Demonstration and
Development PRP as the grant evaluator. Nexant also recommends to PacifiCorp which applicants
should receive grant funding.
After an initial ramp-up period, PacifiCorp fully launched the Demonstration and Development program
in the second quarter of 2019. During the 2019 fourth quarter grant cycle, the first grant was awarded,
and the grantee will have one year to complete the EVSE installation project.
Liberty Residential Charger Installation Rebate Program ($1.6 million),
Liberty Small Business Charger Installation Rebate Program ($300,000), and
Liberty Customer Online Resource Project ($240,480)
Liberty will offer $1,500 rebates for residential customers (up to 1,000) and $2,500 for small business
customers (up to 100) to pay for networked EV charging equipment and installation by a certified
electrician. An online application portal for residential and small business rebate programs has been
developed. The portal utilizes the PowerClerk platform, which Liberty also uses to administer its Solar
Incentive Program. Outreach will be conducted via the Liberty email list, bill inserts, community forums,
local media, and an EV summit. There has been considerable interest in the program from both
residential and small business customers.
Liberty DC Fast Charger Program ($4 million)
Based on the estimated cost of make-ready infrastructure, Liberty anticipates construction of
approximately nine project sites, with rebate funding available ($1.8 million approved) to support
numerous EVSE per project site. A request for proposals was issued in September 2019 to gather current
pricing on EVSE qualified for the program. This will be used to set the base cost for rebates and
participation payments. Respondents provided price quotations by power output tier (50–99 kW, 100–
149 kW, and 150+ kW), following prescriptive requirements for qualifying equipment.
The existing A-1 small commercial rate (with no demand charges) will be used for the DC fast chargers
installed under this program. This is proposed as a bridge solution until Liberty submits an application
for a commercial EVSE rate, which is currently under development. Potential site locations have been
gathered, with numerous site hosts actively considering installations. Host agreements are under
development. The City of Portola will be the first site considered under the program. An online
application portal for Liberty’s DC Fast Charger Program, very similar to the one used for residential and
small business charger installation programs, is under development.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 223
BVES Destination Make-Ready Program ($607,500)
BVES will install, own, and operate the make-ready infrastructure needed to install up to 50 L2 charging
stations at destination centers in its service territory. Out of all participating sites, the goal is to have
20% of them be small businesses, so BVES is planning to reach out to the small businesses in Q1 2020 to
encourage them to apply for the program. All participants are required to maintain the charging stations
in operating condition for at least 10 years. This program is applicable to commercial customers and
works in conjunction with EV-TOU tariffs. The commercial program would provide rebates for the
infrastructure construction needed in order to install 1-5 L2 charging stations per property. Commercial
customers are required to purchase a networked L2 charging station and provide BVES with the charging
session data for at least the first 2 years of operation.
BVES has contracted with CSE to coordinate transportation electrification program outreach and
implementation. Outreach program is performed by BVES’ customer service team with the assistance of
regulatory affairs staff regarding the applicable tariffs. The required program documentation has been
completed. These documents include the application, license agreement, terms and conditions, website
landing page, interest form, program handbook, and a Bear Valley licensed C-10 electrician list. BVES
also conducted an EV survey in July 2019. The program was launched on December 11, 2019, by holding
community outreach and contractor meetings for electricians and commercial customers. The program
is anticipated to run from January 2020 through January 2022 or until funds are exhausted.
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 224
Priority Review Project Cost Status Summary
Note: Costs to date are as of Q4 2019 when the PRPs were at different stages of completion and therefore not many PRPs have all costs
accounted for yet.
PRP Proposed Deployment Approved Budget
Current Status Costs to Date
San Diego Gas and Electric Company
Fleet Delivery Services (SDG&E)
63 L2 (17 kW) chargers at three UPS locations, 16 L2 (17 kW) chargers at Amazon location
$3,690,749 All chargers installed (78), all 15 Amazon EVs in operation, UPS awaiting 60 EVs (expected Q2 2020)
$1,316,472
Green Shuttles (SDG&E)
2 DCFCs (50kW) for San Diego Airport Parking (2 EVs), Aladdin (4 EVs), and San Diego International Airport (4 EVs + public access); 6 L2 chargers for Illumina (6 EVs), solar energy and energy storage at one site
$3,157,805
San Diego Airport Parking completed, Aladdin and Illumina in construction (Q1 2020 anticipated completion). Not pursuing 4th location, public access, solar energy & energy storage
$713,069
Airport Ground Support Equipment (SDG&E)
Phase I - 16 charging ports (8 dual head chargers) retrofitted with American Airlines Phase II - up to 45 additional charging ports based on 6 months of Phase I data analysis
$2,839,738 Phase I - 16 charging ports retrofitted (data collection started in December 2019)
$580,238
Port Electrification (SDG&E)
30-40 charging stations, data loggers and load research meters for electric trucks and forklifts. San Diego Port Tennant customers: Pasha Automotive, Metro Cruise, Dole and Four Seasons
$2,405,575
3 direct current fast chargers (DCFCs) installed for Pasha (3 Class 8 electric trucks) and 9 Level 2 (L2) (10 kW) chargers for 9 Metro Cruise electric forklifts; no other participants; data collection started in May 2019
$811,311
Electrify Local Highways (SDG&E)
20 L2 (6.6 kW) and 2 DCFC (50 kW) chargers each at 4 Caltrans Park and Ride locations (88 charging ports total)
$4,000,000 Construction started at all 4 sites with expected commissioning by end of Q1 2020
$1,652,298
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 225
PRP Proposed Deployment Approved Budget
Current Status Costs to Date
Dealership Incentives (SDG&E)
Enroll and train 200 salespeople and issue 1,500 incentives
$1,790,000 Program closed on December 31, 2019; final rebates processing and program reporting in Q1 2020
$786,195
Southern California Edison
Port of Long Beach Rubber Tire Gantry Crane (SCE)
Installation of electrical supply for 9 Rubber Tire Gantry Cranes converted to electric
$3,038,000 Utility upgrades completed, SSA terminal modifications and first eRTG conversion by end of the first quarter (Q1) of 2020
$2,470,417
Port of Long Beach Terminal Yard Tractor (SCE)
Electric infrastructure for 20 charging stations (200 kW) for Class 8 BYD electric yard tractors; ITS deploying 7 EVSE initially
$450,000 3 BYD electric trucks delivered, 6 BYD 200 kW and 1 Cavotec automated 100 kW charger installed Dec 2019
$1,586,125
Charge Ready Transit Bus (SCE)
7 depot DCFCs for Victor Valley Transit (7 electric buses), 10 depot DCFCs for Porterville (10 electric buses), and 13 depot DCFCs for Foothill Transit (14 electric buses)
$3,978,000 Victor Valley complete (7) and operational, awaiting Porterville (10) and Foothill (13) charger installations
$1,325,869
Urban Charge Ready DCFC (SCE)
5 locations with up to 50 DCFCs planned. 5 site host agreements resulted in 14 DCFCs.
$3,980,000 All 5 sites completed and 14 DCFCs commissioned in Nov and Dec 2019
$865,413
Charge Ready Home Installation Rebate Program (SCE)
Approximately 5,000 participants $4,000,000 Program closed on May 31, 2019; final rebates processing and program reporting in Q4 2019
$2,113,420
Pacific Gas and Electric
Electric School Bus Renewables Integration (PG&E)
9 Level 2 (19kW) chargers and charge management software to integrate onsite renewables
$2,209,500 3rd of 4 experimental test phases underway $938,764
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 226
PRP Proposed Deployment Approved Budget
Current Status Costs to Date
Medium/Heavy Duty Fleet Customer Demo (PG&E)
Five 60 kW depot chargers, demand management and battery energy storage for existing high-power overhead chargers for San Joaquin Regional Transit District (17 EVs)
$3,355,000 Depot chargers installed, demand management implemented, battery storage on order, testing underway
$923,167
Idle Reduction Technology (PG&E)
25 electrified receptacles for eTRU connection (10 at docks, 15 at staging area), 15-17 kW each
$1,719,400 System constructed and commissioned, just starting in-use operations
$562,045
Home EV Charger Information Resource (PG&E)
Enhanced EV information on website, checklist for EVSE and contractors, installer tool
$500,000
Rescoped (budget reduced to $200k) to reference external EVSE installer selection tools; updated web resource development in Q1/2 2020
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 227
Compilation of Lessons Learned to Date
Program Design
If charging station installation programs can be made more flexible, customers may prefer the option to
use either a new or existing meter—particularly those customers knowledgeable of and actively
involved in energy management practices. (SDG&E Fleet Delivery Services)
Evaluating in-use performance of EVs in a new application for 12 months will most likely produce less
than 12 months of operational data because of unexpected issues. Early commercial vehicle
deployments tend to experience reliability issues, resulting in vehicle downtime to facilitate repairs.
Deploying all of the EVs in regular operation can take from a couple of weeks to several months, as the
fleet needs to adapt driving and charging operations to accommodate EVs. (SDG&E Port Electrification)
Programs targeted to DACs will need to support secondary market transactions. The dealership
incentive program in Sacramento was able to achieve greater total claims at lower incentive levels that
the San Diego program, likely because it did not have an EV-TOU requirement. Trained sales staff submit
claims at a greater rate (about four times greater) than untrained sales staff. (SDG&E Dealership
Incentives)
DCFC applications asked only for two or four ports because of the reluctance to lose parking spots. To
electrify two ports, site hosts may need to give up three or four existing parking spots (since one spot
must be ADA compliant). In future projects with similar target audiences, utilities should consider
targeting a total number of ports for the program without defining the number of sites. This will allow
the program flexibility to maximize the budget and support increased adoption with more sites and the
potential for higher port count. (SCE Urban DC Fast Charging Clusters)
Consider structuring requirements for rebates in a simpler format for alternative situations (e.g.,
individuals who do not have HOAs or whose cities do not require permits to install an L2 charger or
allowing applicants to write in the electrician’s C-10 license number if not on an invoice) to reduce some
administrative burden on utilities and staff for addressing these items. A marketing strategy that
includes more lead time to meet with key stakeholders—such as electricians, MUD property managers,
and city officials who will be helping applicants with their permits—before program launch might be
useful. Also helpful would be greater internal coordination within the utility departments (such as the
rates, information technology, and program departments) when there are program processes (such as
the validation of customers switching to a TOU rate) that depend on the efforts of multiple
departments. (SCE Charge Ready Home Installation Rebate Program)
PG&E was insightful in scheduling a significant block of time after commissioning during which project
operators could iron out issues with project hardware and software integration. The challenge of
identifying the cause of issues can be compounded when there are several distinct systems integrated in
a single project. (PG&E Electric School Bus Renewables Integration Project)
Early partnership between the utility and transit agencies will provide opportunities for transfer of
knowledge and best practices. The utility brings unique insights and can support agencies with the
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 228
expertise utility staff have developed through implementing programs and projects throughout the
territory. (PG&E Bus Fleet Demonstration)
For customer-owned and -operated projects, the utility could continue to consider ways to ease the
customer’s upfront outlay of funds. (PG&E Idle Reduction Technology Project)
The ability to adapt to changing market conditions is essential for any innovative program. (PG&E Home
Charger Information Resource Program)
PRP Participant Recruitment
Significantly more effort, investment, and EV availability and reduced EV costs will be necessary to
sufficiently support locally owned MBE/WBE delivery business fleets in transportation electrification
projects. Often, such businesses do not have the knowledge or resources to secure the grants necessary
to finance this effort (upfront costs for electric delivery trucks is a barrier) or the available staffing to
navigate the challenges of operating new technology. Further, smaller local companies generally do not
have robust financial resources to make investments in new technologies. (SDG&E Fleet Delivery
Services)
Private-sector facilities and fleets may be sophisticated electricity consumers. This makes them valuable
partners that can implement projects quickly, but also poses challenges associated with collecting
operational data and compiling lessons learned that can apply to other site hosts. (PG&E Idle Reduction
Technology Project)
Electric Vehicle/Equipment Availability
The electric delivery vehicle market is growing and maturing but has relatively limited options. Some
small manufacturers to first enter the market (e.g., Smith Electric) struggled to succeed and had to cease
operations. These PRPs are procuring some of the first production vehicles from the selected
manufacturers, which can have an impact on production and delivery times. Supporting the EV
manufacturers, providing a market for their products, and examining vehicle performance will help
advance the transition to EVs. (SDG&E Fleet Delivery Services)
EVs in smaller market segments, such as shuttle buses, are often supplied by several smaller
manufacturers that are attempting to fill a market need (more established manufacturers target larger
market segments). The specifications of these EVs may be unique to each manufacturer, and it is critical
to verify compatibility with the planned charging infrastructure. (SDG&E Green Shuttles)
Field certification of equipment that is not already NRTL-listed can add significant complication to a
project and should be expected to delay completion by several months while any issues found in the
initial inspection are being corrected. For cutting-edge transportation electrification technology, this is
sometimes unavoidable but should be limited to projects classified as pre-commercial demonstrations
(which the CEC grant supported) and not for commercial deployment programs. (SCE Port of Long Beach
Terminal Yard Tractor)
The program experienced a challenge in qualifying equipment proposed by the applicants. Because of
the rapidly changing nature of the transit bus EVSE market, some EVSE providers could not meet the
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 229
program technical requirements, such as the requirement that the equipment be recognized by a NRTL.
(SCE Electric Transit Bus Make-Ready Program)
When facing procurement choices, some customers may be drawn to the simplest, least expensive
technology options available. Decision makers should consider opportunity costs and the value of
future-proofing their procurements so that sites are well-positioned to benefit from new markets and
future value streams. (PG&E Electric School Bus Renewables Integration Project)
The electric school bus industry is experiencing growing pains, which affects equipment operations and
maintenance. (PG&E Electric School Bus Renewables Integration Project)
Project implementers should know in advance there is not a standard for eTRU connectors and
receptacles, so retrofitting equipment may be necessary. Utilities should support the establishment of
an industry-wide eTRU connector standard to simplify future deployments. Likewise, design guidelines
and installation best practices are needed and should be shared broadly. (PG&E Idle Reduction
Technology Project)
Project Implementation
Including field construction advisors early in the design process and having them participate in the initial
site walk to better understand the customer site is beneficial to the implementation of these projects as
they will be better able to accommodate anticipated EV operational needs. (SDG&E Fleet Delivery
Services)
PV and energy storage technologies are well developed, and their application to supporting grid services
has been proven. However, the integration with EV charging is entirely new, and no off-the-shelf system
exists (except for limited applications of an off-grid PV, battery, and L2 charger system). On their own,
these components need to be optimized to provide a positive return on investment, and the complexity
of combining these into one solution adds costs and challenges the optimization strategy for maximizing
benefits. (SDG&E Green Shuttles)
The integration of a PV and battery system with EV charging could be a valuable solution to managing
electrical demand. The technological challenges associated with implementation and significant costs
were likely key reasons for the limited response SDG&E received to its request for bids. Given the
current costs and risks, SDG&E decided to instead model this solution. Should this prove valuable at a
reasonable price point for implementation, a future deployment may be warranted (outside of the PRP).
(SDG&E Green Shuttles)
Many initial EV deployments do not include redundancy in charging equipment, but this can be key to
project success because the vehicles rely on functioning chargers for continued operation. It is very
important to factor in charging redundancy for electrification deployments to ensure resilience. (SDG&E
Airport Ground Support)
Construction projects at the port can be very challenging and costly. Concrete can be several feet deep,
which complicates trenching, so it was essential to identify sites that required minimal or no trenching
to align with the approved budget. The estimates also failed to account for environmental costs, which
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 230
for one potential project was forecasted to be around $150,000 owing to the hazardous risk of the site;
the cost precluded the site from participating in the PRP. (SDG&E Port Electrification)
Existing make-ready infrastructure at one location was expected to simplify implementation but
unfortunately it was not sized properly or sufficiently protected from the environment and was
therefore unusable. Any future make-ready infrastructure should be upsized to account for larger power
supplies and properly protected to ensure longevity. (SDG&E Electrify Local Highways)
Customers tend to be very cautious when working on equipment that is critical to their operations.
These partners often chose to verify each activity was completed before progressing to the next (e.g.,
don’t want to start any construction work, including scheduling, until all equipment is procured to
ensure there are no delays once starting that might disrupt operations longer than necessary). (SCE Port
of Long Beach Rubber Tire Gantry Crane)
Contracting, construction, and implementing test protocols with schools may require planning extra
time as a buffer to reflect their unique contracting processes and seasonal operational patterns. (PG&E
Electric School Bus Renewables Integration Project)
School districts and other early fleet adopters may not be able to adjust operations to optimize
utilization of new electric buses or access new value streams associated with participation in distributed
resource markets. Versatility of selected electric buses should be carefully considered during
procurement (e.g., passenger capacity, range); otherwise, expectations for utilization (number of days in
use and overall mileage) should be appropriately tempered. (PG&E Electric School Bus Renewables
Integration Project)
The complexity of managing the charging protocol of multiple generations of buses with a mix of
overhead fast charging and depot charging warrants more guidance from the bus manufacturer and
requires sophisticated management from the transit agency. (PG&E Bus Fleet Demonstration)
Legacy equipment may not be in sufficient condition to be relied upon for new electrification
infrastructure; equipment should be analyzed, and its condition should be tested. Additionally, projects
can benefit from strategic sequencing of required phases or activities to reduce delays overall. (PG&E
Idle Reduction Technology Project)
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 231
Acronyms and Abbreviations
A Ampere(s)
AC Alternating Current
ADA Americans with Disabilities Act of 1990
AFUDC Allowance for Funds Used During Construction
AHJ Authority Having Jurisdiction
BESS Battery Electric Storage System
BtM Behind the Meter
BVES Bear Valley Electric Service
BYD BYD Motors Inc.
Caltrans California Department of Transportation
CARB California Air Resources Board
CCA Community Choice Aggregator
CEC California Energy Commission
CEV Commercial Electric Vehicle (rate)
CNG Compressed Natural Gas
CO2 Carbon Dioxide
CO2e Carbon Dioxide Equivalent
CPUC California Public Utility Commission
CRHIRP Charge Ready Home Installation Rebate Program
CSE Center for Sustainable Energy
CSV Comma-Separated Values (computer spreadsheet-type file)
CVRP Clean Vehicle Rebate Project
DAC Disadvantaged Community
DC Direct Current
DCFC Direct Current Fast Charging/Charger
DR Demand Response
DTC Downtown Transit Center
EPRI Electric Power Research Institute, Inc.
eTRU Electric Transport Refrigeration Unit
EV Electric Vehicle
EVSE Electric Vehicle Supply Equipment
FCM Flex Charge Manager
g Gram(s)
GGE Gasoline Gallon Equivalent
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 232
GHG Greenhouse Gas
GSE Ground Support Equipment
HCIR Home Charger Information Resource
HDEV Heavy-Duty Electric Vehicle
HOA Homeowners' Association
HOV High-Occupancy Vehicle
HVAC Heating, Ventilation, and Air Conditioning
HVIP Hybrid and Zero-Emission Truck and Bus Voucher Incentive Project
ICT Innovative Clean Transit
IDI In-Depth Interview
ITS International Transportation Service
kg Kilogram(s)
kV Kilovolt(s)
kVA Kilovolt-Ampere(s)
L2 Level 2
LBCT Long Beach Container Terminal
LCFS Low Carbon Fuel Standard
MBE Minority-Owned Business Enterprise
MD/HD Medium- and Heavy-Duty
MPG Miles per Gallon
MPG3 Miles per Gallon Gasoline Equivalent
MT Metric Tonne(s)
MUD Multi-Unit Dwelling
MW Megawatt(s)
MWh Megawatt-Hour(s)
N·m Newton Metre
NOx Nitrous Oxide(s)
NREL National Renewable Energy Laboratory
NRLT Nationally Recognized Testing Laboratory
O&M Operations and Maintenance
OEM Original Equipment Manufacturer
OpenADR Open Automated Demand Response
PAC Program Advisory Council
PG&E Pacific Gas and Electric
PIA Plug-In America
PM Particulate Matter
California Transportation Electrification Priority Review Projects January 31, 2020 Interim Evaluation Report
Page 233
PME Pad-Mounted Equipment
POLB Port of Long Beach
PRP Priority Review Project
PUSD Pittsburg Unified School District
PV Photovoltaic(s)
PVC Polyvinyl Chloride
Q Quarter
ROG Reactive Organic Gas(es)
RTC Regional Transportation Center
RTD San Joaquin Regional Transit District
RTG Rubber Tire Gantry
SB Senate Bill
SCCR Short Circuit Current Rating
SCE Southern California Edison
SDAP San Diego Airport Parking
SDG&E San Diego Gas and Electric Company
SDIA San Diego International Airport
SMJU Small and Multi-Jurisdictional Utilities
SOC State of Charge
SRP Standard Review Project
SSA Stevedoring Services of America
TCO Total Cost of Ownership
TNC Transportation Network Company
TOU Time of Use
TRU Transport Refrigeration Unit
TtM To the Meter
UPS United Parcel Service
UTS Union Transfer Station
V Volt(s)
WBE Woman-Owned Business Enterprise
XSP Excess Supply Demand Response Program
ZEB Zero-Emission Bus
ZEV Zero-Emission Vehicle
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
Application of San Diego Gas & Electric Company (U 902E) for Approval of SB 350 Transportation Electrification Proposals.
Application 17-01-020
And Related Matters.
Application 17-01-021 Application 17-01-022
CERTIFICATE OF SERVICE
I hereby certify that, pursuant to the Commission’s Rules of Practice and Procedure, I have this day served a true copy of JOINT INVESTOR-OWNED UTILITIES’ INTERIM REPORT ON PRIORITY REVIEW PROJECTS on all parties identified on the attached service list(s) for A.17-01-020, et al. Service was effected by one or more means indicated below:
Transmitting the copies via e-mail to all parties who have provided an e-mail address.
Placing the copies in sealed envelopes and causing such envelopes to be delivered by US Mail to the offices of the Commissioners(s) or other addresses(s).
ALJ Sasha Goldberg CPUC 505 Van Ness Avenue San Francisco, CA 94102
Executed January 31, 2020, at Rosemead, California.
/s/ Sandra Sedano Sandra Sedano Legal Administrative Assistant SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue Rosemead, California 91770
CPUC Home
CALIFORNIA PUBLIC UTILITIES COMMISSIONService Lists
PROCEEDING: A1701020 - SDG&E - FOR APPROVAL FILER: SAN DIEGO GAS & ELECTRIC COMPANY LIST NAME: LIST LAST CHANGED: DECEMBER 10, 2019
Download the Comma-delimited File About Comma-delimited Files
Back to Service Lists Index
Parties
JAY FRIEDLAND NORMAN HAJJA ZERO MOTORCYCLES RECARGO, INC. EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000 FOR: ZERO MOTORCYCLES FOR: REGARCO, INC.
JOE HALSO EDWARD L. HSU ASSOCIATE ATTORNEY SR COUNSEL SIERRA CLUB SOUTHERN CALIFORNIA GAS COMPANY 1536 WYNKOOP ST., STE. 312 555 WEST 5TH STREET, GT14E7 DENVER, CO 80202 LOS ANGELES, CA 90013 FOR: SIERRA CLUB FOR: SOUTHERN CALIFORNIA GAS COMPANY
ADRIANO MARTINEZ THOMAS ASHLEY ATTORNEY AT LAW VP - GOVN'T AFFAIRS & PUBLIC POLICY EARTHJUSTICE GREENLOTS 800 WILSHIRE BLVD., SUITE 1000 925 N. LA BREA AVE., 6TH FL LOS ANGELES, CA 90017 LOS ANGELES, CA 90038 FOR: EAST YARD COMMUNITIES FOR FOR: GREENLOTS ENVIRONMENTAL JUSTICE AND CENTER FOR COMMUNITY ACTION AND ENVIRONMENTAL JUSTICE
KATHERINE STAINKEN MINH LE POLICY DIR. GEN. MGR. - OFFICE OF SUSTAINABILITY PLUG IN AMERICA COUNTY OF LOS ANGELES 6380 WILSHIRE BLVD., STE. 1000 1100 NORTH EASTERN AVENUE LOS ANGELES, CA 90048 LOS ANGELES, CA 90063-3200
Page 1 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
FOR: PLUG IN AMERICA FOR: COUNTY OF LOS ANGELES
TERRY O'DAY JESSALYN ISHIGO VP ENVIRONMENTAL BUSINESS DEVELOPMENT OFF. EVGO SERVICES LLC AMERICAN HONDA MOTOR CO., INC. 11390 WEST OLYMPIC BLVD 1919 TORRANCE BLVD. LOS ANGELES, CA 90064 TORRANCE, CA 90501 FOR: EVGO SERVICES LLC FOR: AMERICAN HONDA MOTOR CO., INC.
MAX BAUMHEFNER WAYNE NASTRI ATTORNEY EO - MANAGEMENT DISTRICT NATURAL RESOURCES DEFENSE COUNCIL SOUTH COAST AIR QUALITY 111 SUTTER ST., 21ST FL. 21865 COPLEY DRIVE SAN FRANCISCO, CA 91404 DIAMOND BAR, CA 91765-0940 FOR: NATURAL RESOURCES DEFENSE COUNCIL FOR: SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT
ANDREA TOZER DONALD KELLY SR. ATTORNEY EXE. DIRECTOR SOUTHERN CALIFORNIA EDISON COMPANY UTILITY CONSUMERS' ACTION NETWORK 2244 WALNUT GROVE AVE / PO BOX 800 3405 KENYON ST., STE. 401 ROSEMEAD, CA 91770 SAN DIEGO, CA 92110 FOR: SOUTHERN CALIFORNIA EDISON COMPANY FOR: UTILITY CONSUMERS' ACTION NETWORK (UCAN)
LISA MCGHEE DESMOND WHEATLEY OPERATIONS MGR. CEO SAN DIEGO AIRPORT PARKING CO. ENVISION SOLAR INTRERNATIONAL, INC. 2771 KURTZ ST. 5660 EASTGATE DRIVE SAN DIEGO, CA 92110 SAN DIEGO, CA 92121 FOR: SAN DIEGO AIRPORT PARKING COMPANY FOR: ENVISION SOLAR INTERNATIONAL, INC.
JOHN W. LESLIE, ESQ JOHN A. PACHECO ATTORNEY SR. COUNSEL DENTONS US LLP SAN DIEGO GAS & ELECTRIC COMPANY EMAIL ONLY 8330 CENTURY PARK CT., CP32 EMAIL ONLY, CA 92121 SAN DIEGO, CA 92123 FOR: SHELL ENERGY NORTH AMERICA (US), FOR: SAN DIEGO GAS & ELECTRIC COMPANY L.P.
SACHU CONSTANTINE STEPHEN G. DAVIS DIR. OF POLICY CEO CENTER FOR SUSTAINABLE ENERGY OXYGEN INITIATIVE 9325 SKY PARK COURT, SUITE 100 65 ENTERPRISE SAN DIEGO, CA 92123 ALISO VIEJO, CA 92656 FOR: CENTER FOR SUSTAINABLE ENERGY (CSE) FOR: EXYGEN INITIATIVE (FORMERLY KNGRID)
MICHAEL CHIACOS TADASHI GONDAI DIR - ENERGY PROGRAMS DIR OF LEGAL AFFAIRS COMMUNITY ENVIRONMENTAL COUNCIL NATIONAL ASIAN AMERICAN COALITION 26 W. ANAPAMU ST., 2ND FLR. 15 SOUTHGATE AVE., STE. 200 SANTA BARBARA, CA 93101 DALY CITY, CA 94015 FOR: COMMUNITY ENVIRONMENTAL COUNCIL FOR: THE NATIONAL ASIAN AMERICAN COALITION AND THE NATIONAL DIVERSITY COALITION
Page 2 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
DAVID SCHLOSBERG MILA A. BUCKNER DIR - ENERGY MARKET OPER ATTORNEY EMOTORWERKS ADAMS BROADWELL JOSEPH & CARDOZO 846 BRANSTEN ROAD 601 GATEWAY BLVD., STE. 1000 SAN CARLOS, CA 94070 SOUTH SAN FRANCISCO, CA 94080 FOR: ELECTRIC MOTORWERKS, INC. FOR: COALITION OF CALIFORNIA UTILITY EMPLOYEES
AUSTIN M. YANG ELISE TORRES DEPUTY CITY ATTORNEY STAFF ATTORNEY CITY AND COUNTY OF SAN FRANCISCO THE UTILITY REFORM NETWORK 1 DR. CARLTON B. GOODLETT PL, RM 234 785 MARKET STREET, SUITE 1400 SAN FRANCISCO, CA 94102-4682 SAN FRANCISCO, CA 94103 FOR: CITY & COUNTY OF SAN FRANCISCO FOR: TURN
JAMES BIRKELUND CHRISTOPHER WARNER PRESIDENT & GEN. COUNSEL PACIFIC GAS AND ELECTRIC COMPANY SMALL BUSINESS UTILITY ADVOCATES 77 BEALE STREET, B30A 548 MARKET STREET, STE 11200 SAN FRANCISCO, CA 94105 SAN FRANCISCO, CA 94104 FOR: PACIFIC GAS AND ELECTRIC COMPANY FOR: SMALL BUSINESS UTILITY ADVOCATES
LARISSA KOEHLER NORA SHERIFF, ESQ. SENIOR ATTORNEY COUNSEL ENVIRONMENTAL DEFENSE FUND BUCHALTER, A PROFESSIONAL CORPORATION 123 MISSION STREET, 28TH FL. 55 SECOND STREET, STE. 1700 SAN FRANCISCO, CA 94105 SAN FRANCISCO, CA 94105 FOR: ENVIRONMENTAL DEFENSE FUND FOR: CALIFORNIA LARGE ENERGY CONSUMERS ASSOCIATION (CLECA)
EVELYN KAHL DANIEL ROCKEY ATTORNEY PARTNER BUCHALTER, A PROFESSIONAL CORPORATION BRYAN CAVE LEIGHTON PAISNER LLP 55 SECOND STREET, SUITE 1700 THREE EMBARCADERO CENTER, 7TH FLOOR SAN FRANCISCO, CA 94105-3493 SAN FRANCISCO, CA 94111 FOR: CLEAN ENERGY FUELS FOR: LYFT, INC.
IRENE K. MOOSEN BEAU WHITEMAN ATTORNEY AT LAW SR. MGR., EV INFRASTRUCTURE LAW OFFICE OF IRENE K. MOOSEN TESLA MOTORS, INC. 53 SANTA YNEZ AVENUE 3500 DEER CREEK ROAD SAN FRANCISCO, CA 94112 PALSO ALTO, CA 94304 FOR: LOCAL GOVERNMENT SUSTAINABLE FOR: TESLA, INC. ENERGY COALITION (LGSEC)
CHRIS KING A J HOWARD GLOBAL CHIEF REGULATORY OFFICER OLIVINE, INC. SIEMENS SMART GIRD SOLUTIONS 2010 CROW CANYON PLACE, STE. 100 4000 E 3RD AVE., STE. 400 SAN RAMO, CA 94583 FOSTER CITY, CA 94404 FOR: OLIVINE, INC. FOR: SIEMENS
HOWARD V. GOLUB JIMMY O'DEA, PH.D
Page 3 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
ATTORNEY VEHICLES ANALYST BEST BEST & KRIEGER LLP UNION OF CONCERNED SCIENTISTS 2001 NORTH MAIN STREET, SUITE 390 500 12TH STREET, STE. 340 WALNUT CREEK, CA 94596 OAKLAND, CA 94607 FOR: CITY OF LONG BEACH CALIFORNIA, A FOR: UNION OF CONCERNED SCIENTISTS MUNICIPAL CORPORATION, ACTING BY AND THROUGH ITS BOARD OF HARBOR COMMISSIONERS
JOEL ESPINO ALEX J. MORRIS LEGAL COUNSEL SR. DIR., POLICY & REGULATORY AFFAIRS THE GREENLINING INSTITUTE CALIFORNIA ENERGY STORAGE ALLIANCE 360 14TH STREET, 2ND FL. 2150 ALLSTON WAY, SUITE 400 OAKLAND, CA 94612 BERKELEY, CA 94704 FOR: THE GREENLINING INSTITUTE FOR: CALIFORNIA ENERGY STORAGE ALLIANCE (CESA)
GREGORY MORRIS RYAN SCHUCHARD DIRECTOR POLICY DIR. GREEN POWER INSTITUTE CALSTART 2039 SHATTUCK AVENUE, STE 402 501 CANAL BLVD., NO. G BERKELEY, CA 94704 RICHMOND, CA 94804 FOR: THE GREEN POWER INSTITUTE FOR: CALSTART
CHRISTINA JAWORSKI JAMES HALL SR. ENVIRONMENTAL PLANNER GENERAL MOTORS LLC SANTA CLARA VALLEY TRANSP. AUTHORITY 1115 11TH STREET 3331 NORTH FIRST ST., BLDG B-2 SACRAMENTO, CA 95814 SAN JOSE, CA 95134 FOR: GENERAL MOTORS LLC FOR: SANTA CLARA VALLEY TRANSPORTATION AUTHORITY (VTA)
MICHAEL PIMENTEL SCOTT BLAISING LEGISLATIVE / REGULATORY ADVOCATE ATTORNEY CALIFORNIA TRANSIT ASSOCIATION BRAUN BLAISING SMITH WYNNE P.C. 1415 L STREET 915 L STREET, STE. 1480 SACRAMENTO, CA 95814 SACRAMENTO, CA 95814 FOR: CALIFORNIA TRANSIT ASSOCIATION FOR: MARIN CLEAN ENERGY AND SONOMA CLEAN POWER
SCOTT BLAISING STEVEN P. DOUGLAS COUNSEL SR. DIR - ENVIRONMENTAL AFFAIRS BRAUN BLAISING SMITH WYNNE P.C. ALLIANCE OF AUTOMOBILE MANUFACTURERS 915 L STREET, SUITE 1480 1415 L STREET, STE. 1190 SACRAMENTO, CA 95814 SACRAMENTO, CA 95814 FOR: CITY OF LANCASTER FOR: ALLIANCE OF AUTOMOBILE MANUFACTURERS
TANNER KELLY TOVAH TRIMMING DEWEY SQUARE GROUP, LLC CALIF PUBLIC UTILITIES COMMISSION 1020 16TH STREET, SUITE 20 LEGAL DIVISION SACRAMENTO, CA 95814 300 Capitol Mall FOR: ELECTRIC VEHICLE CHARGING Sacramento, CA 95814 ASSOCIATION (EVCA) FOR: PUBLIC ADVOCATES OFFICE (FORMERLY ORA)
Page 4 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
LYNN HAUG LAURA FERNANDEZ ATTORNEY ATTORNEY ELLISON SCHNEIDER HARRIS & DONLAN LLP BRAUN BLAISING MCLAUGHLIN & SMITH, P.C. 2600 CAPITOL AVE., STE. 400 915 L STREET, STE. 1480 SACRAMENTO, CA 95816 SACRAMENTO, CA 95822 FOR: CHARGEPOINT, INC. FOR: SILICON VALLEY CLEAN ENERGY AUTHORITY
Information Only
ANGIE BOAKES BARBARA R. BARKOVICH ELECTRIC MOBILITY GENERAL MGR. CONSULTANT SHELL INT'L. PETROLEUM CO., LIMITED BARKOVICH & YAP, INC. EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000
BONNIE DATTA CAMILLE STOUGH SR. DIR - AMERICAS & ASIA PACIFIC ASSOCIATE SIEMENS ADAMS BROADWELL JOSEPH & CARDOZO EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000
CATHERINE BUCKLEY COLEY GIROUARD PACIFIC GAS AND ELECTRIC COMPANY ASSOCIATE, PUC PROGRAM EMAIL ONLY ADVANCED ENERGY ECONOMY EMAIL ONLY, CA 00000 EMAIL ONLY EMAIL ONLY, CA 00000
CURT BARRY DAVE PACKARD SR WRITER / EDITOR CHARGEPOINT, INC. INSIDE WASHINGTON PUBLISHERS EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000
DONALD LIDDELL EBCE REGULATORY DOUGLASS & LIDDELL EAST BAY COMMUNITY ENERGY EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000
ETHAN SPRAGUE JOHN SAVAGE FREEWIRE TECHNOLOGIES PACIFIC GAS AND ELECTRIC COMPANY EMAIL ONLY EMAIL ONLY EMAIL ONLY, AA 00000 EMAIL ONLY, CA 00000
JUSTIN REGNIER KAVYA BALARAMAN EXE. DIV STAFF WRITER / REPORTER CALIFORNIA PUBLIC UTILITIES COMMISSION CALIFORNIA ENERGY MARKETS EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000
KINSHUK CHATTERJEE MARISSA WILLIAMS CENTER FOR SUSTAINABLE ENERGY AIR POLLUTION SPECIALIST / ECARS
Page 5 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
EMAIL ONLY CALIFORNIA AIR RESOURCES BOARD EMAIL ONLY, CA 00000 EMAIL ONLY EMAIL ONLY, CA 00000
PAUL D. HERNANDEZ RACHEL KELLER PUBLIC POLICY & GOV. RELATIONS CASE COORDINATOR ENVOY TECHNOLOGIES INC. PACIFIC GAS AND ELECTRIC COMPLANY EMAIL ONLY EMAIL ONLY EMAIL ONLY, CA 00000 EMAIL ONLY, CA 00000
REGULATORY CLERK SAM HOUSTON BRAUN BLAISING SMITH WYNNE, PC CLEAN VEHICLES ANALYST EMAIL ONLY UNION OF CONCERNED SCIENTISTS EMAIL ONLY, CA 00000 EMAIL ONLY EMAIL ONLY, CA 00000
TONY RAFATI MRW & ASSOCIATES, LLC POLICY MANAGER- CLEAN TRANSPORTATION EMAIL ONLY SAN DIEGO GAS & ELECTRIC EMAIL ONLY, CA 00000 EMAIL ONLY EMAIL ONLY, CA 00000
DAVIS WRIGHT TREMAINE LLP EDWARD LOVELACE, PH.D EMAIL ONLY CHIEF TECHNOLOGY OFFICER EMAIL ONLY, CA 00000 XL HYBRIDS 145 NEWTON STREET BOSTON, MA 02135
JONATHAN ARNOLD GREGORY REISS DEUTSCHE BANK SECURITIES INC. CENTENUS GLOBAL MANAGEMENT, LP 60 WALL STREET 437 MADISON AVENUE, SUITE 19B NEW YORK, NY 10005 NEW YORK, NY 10022
JAMIESON WARD JOSEPH LOPES CENTENUS GLOBAL MANAGEMENT, LP PRINCIPAL CONSULTANT 437 MADISON AVENUE - SUITE 19B DNV GL - ENERGY NEW YORK, NY 10022 15 GLEN STREET, SUITE 201B GLEN COVE, NY 11542
CATHERINE M. WILMARTH KAY DAVOODI ATTORNEY ACQ-UTILITY RATES AND STUDIES OFFICE ALLIANCE OF AUTOMOBILE MANUFACTURERS NAVAL FACILITIES ENGINEERING COMMAND HQ 803 7TH ST NW, SUITE 300 1322 PATTERSON AVE.,SE-BLDG. 33. STE1000 WASHINGTON, DC 20001 WASHINGTON, DC 20374-5018 FOR: ALLIANCE OF AUTOMOBILE FOR: FEA MANUFACTURERS
LARRY ALLEN DAN FENG DEPARTMENT OF THE NAVY SR. ENGINEER 1322 PATTERSON AVE., SE STE. 1000 DNV GL WASHINGTON, DC 20374-5018 1560 WILSON BLVD., STE. 800 FOR: FEA ARLINGTON, VA 22209
Page 6 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
JASON SYMONDS BLAKE ELDER DNV GL CLEAN ENERGY SPECIALIST 1560 WILSON BLVD., STE. 800 EQ RESEARCH ARLINGTON, VA 22209 401 HARRISON OAKS BLVD., STE. 100 CARY, NC 27513
MAURICE BRUBAKER JOE MOCK BRUBAKER AND ASSOCIATES, INC. SOUTHERN CALIFORNIA GAS COMPANY PO BOX 412000 555 W. FIFTH ST., GT14D6 ST LOUIS, MO 63141-2000 LOS ANGELES, CA 90013
MEGHA LAKHCHAURA BREA CHILDS DIR LITIGATION ASSISTANT EVBOX INC. EARTHJUSTICE 525 S HEWITT STREET, LACI 800 WILSHIRE BLVD., SUITE 1000 LOS ANGELES, CA 90013 LOS ANGELES, CA 90017
SARA GERSEN LUJUANA MEDINA STAFF ATTORNEY MANAGER EARTHJUSTICE COUNTY OF LOS ANGELES 800 WILSHIRE BLVD., STE. 1000 1100 NORTH EASTERN AVENUE LOS ANGELES, CA 90017 LOS ANGELES, CA 90063
CASE ADMINISTRATION CASE ADMINISTRATION SOUTHERN CALIFORNIA EDISON COMPANY SOUTHERN CALIFORNIA EDISON COMPANY 2244 WALNUT GROVE AVENUE, PO BOX 800 8631 RUSH STREET, GO4, 2ND FL. ROSEMEAD, CA 91770 ROSEMEAD, CA 91770
LISA MAU COURTNEY COOK REGULATORY PARALEGAL / OFFICE ADMIN. SOUTHERN CALIFORNIA EDISON UTILITY CONSUMERS' ACTION NETWORK 2244 WALNUT GROVE AVE. 3405 KENYON STREET, SUITE 401 ROSEMEAD, CA 91773 SAN DIEGO, CA 92110
DAVID CROYLE EDWARD LOPEZ EXECUTIVE DIRECTOR EXECUTIVE DIR UTILITY CONSUMERS' ACTION NETWORK UTILITY CONSUMERS’ ACTION NETWORK 3405 KENYON STREET, STE. 401 3405 KENYON ST. SUITE 401 SAN DIEGO, CA 92110 SAN DIEGO, CA 92110
JANE KRIKORIAN SEPHRA NINOW, J. D. MGR - REGULATORY DIR - REGULATORY UTILITY CONSUMERS' ACTION NETWORK CENTER FOR SUSTAINABLE ENERGY 3405 KENYON STREET, STE. 401 3980 SHERMAN ST., STE. 170 SAN DIEGO, CA 92110 SAN DIEGO, CA 92110
SAN DIEGO AIRPORT PARKING COMPANY JOE KAATZ 2771 KURTZ ST. STAFF ATTORNEY SAN DIEGO, CA 92110 UNIVERSITY OF SAN DIEGO SCHOOL OF LAW 5998 ALCALA PARK SAN DIEGO, CA 92110-2492 FOR: ENERGY POLICY INITIATIVES CENTER
Page 7 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
MARCIE MILNER CHRISTOPHER A. SUMMERS VP - REGULATORY AFFAIRS REGULATORY BUSINESS MGR. SHELL ENERGY NORTH AMERICA (US), L.P. SAN DIEGO GAS & ELECTRIC COMPANY 4445 EASTGATE MALL, SUITE 100 8330 CENTURY PARK CT., CP32F SAN DIEGO, CA 92121 SAN DIEGO, CA 92123
DEAN A. KINPORTS JENNIFER WRIGHT REGULATORY CASE MGR. REGULATORY CASE MGR. SAN DIEGO GAS & ELECTRIC COMPANY SAN DIEGO GAS & ELECTRIC COMPANY 8330 CENTURY PARK COURT, CP32F 8330 CENTURY PARK COURT, CP32F SAN DIEGO, CA 92123 SAN DIEGO, CA 92123
RANDY SCHIMKA JEREMY WAEN SAN DIEGO GAS & ELECTRIC COMPANY MGR. - REGULATORY AFFAIRS 8674 CENTURY PARK CT, MS CP42K PENINSULA CLEAN ENERGY SAN DIEGO, CA 92123 2075 WOODSIDE RD. REDWOOD CITY, CA 94061
SUE MARA MARC MONBOUQUETTE CONSULTANT SR.MGR - REG & GOV'T AFFAIRS RTO ADVISORS, LLC ENEL X NORTH AMERICA, INC. 164 SPRINGDALE WAY 846 BRANSTEN ROAD REDWOOD CITY, CA 94062 SAN CARLOS, CA 94070
STEVE TABER MARC D. JOSEPH ENERGY MARKETS ATTORNEY AT LAW EMOTORWERKS ADAMS BROADWELL JOSEPH & CARDOZO 846 BRANSTEN ROAD 601 GATEWAY BLVD., STE. 1000 SAN CARLOS, CA 94070 SOUTH SAN FRANCISCO, CA 94080 FOR: COALITION OF CALIFORNIA UTILITY EMPLOYEES
RACHAEL KOSS BILLY BLATTNER ATTORNEY SAN DIEGO GAS & ELECTRIC COMPANY ADAMS BROADWELL JOSEPH & CORDOZO 601 VAN NESS AVE., STE. 2060 601 GATEWAY BLVD., STE. 1000 SAN FRANCISCO, CA 94102 SOUTH SAN FRANCISCO, CA 94080
ANTHONY MANZO DANIELLE DOOLEY CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION LEGAL DIVISION ENERGY INFRASTRUCTURE BRANCH ROOM 5125 AREA 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
JOSHUA HUNEYCUTT SARAH OWENS CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION PRESIDENT BATJER COMMISSIONER RECHTSCHAFFEN AREA ROOM 5200 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
ERIC BORDEN MARCEL HAWIGER ENERGY POLICY ANALYST ATTORNEY
Page 8 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
THE UTILITY REFORM NETWORK THE UTILITY REFORM NETWORK 785 MARKET STREET, STE. 1400 785 MARKET STREET, SUITE 1400 SAN FRANCISCO, CA 94103 SAN FRANCISCO, CA 94103
MILES MULLER BENJAMIN ELLIS ATTORNEY ATTORNEY NATURAL RESOURCES DEFENSE COUNCIL BUCHALTER, A PROFESSIONAL CORPORATION 111 SUTTER STREET, 21ST FL. 55 SECOND STREET, SUITE 1700 SAN FRANCISCO, CA 94104 SAN FRANCISCO, CA 94105
BUCHALTER DOCKET JOHANNA FORS BUCHALTER REGULATORY AFFAIRS 55 SECOND STREET, SUITE 1700 PACIFIC GAS AND ELECTRIC COMPANY SAN FRANCISCO, CA 94105 77 BEALE STREET, B10A SAN FRANCISCO, CA 94105
KAREN SHEA LISA M. RAYMOND CASE MGR., CUSTOMER PROGRAM BUCHALTER PACIFIC GAS AND ELECTRIC COMPANY 55 SECOND STREET, SUITE 1700 77 BEALE STREET, B9A SAN FRANCISCO, CA 94105 SAN FRANCISCO, CA 94105
MICHAEL ALCANTAR MICHAEL CADE ATTORNEY AT LAW ANALYST BUCHALTER, A PROFESSIONAL CORPORATION BUCHALTER, A PROFESSIONAL CORPORATION 55 SECOND STREET, SUITE 1700 55 SECOND STREET, SUITE 1700 SAN FRANCISCO, CA 94105 SAN FRANCISCO, CA 94105
BUCHALTER, A PROFESSIONAL CORPORATION LILLIAN RAFII 55 SECOND STREET, SUITE 1700 ATTORNEY SAN FRANCISCO, CA 94105 BUCHALTER, A PROFESSIONAL CORPORATION 55 SECOND STREET, STE. 1700 SAN FRANCISCO, CA 94105-3493
FRANCESCA WAHL ADENIKE ADEYEYE SR. POLICY ASSOCIATE, BUS. DEVELOPMENT SR. RESEARCH & POLICY ANALYST TESLA, INC. EARTHJUSTICE 444 DE HARO STREET, STE. 101 50 CALIFORNIA ST., STE. 500 SAN FRANCISCO, CA 94107 SAN FRANCISCO, CA 94111
MALOU SANA PAUL R. CORT BRYAN CAVE LLP EARTHJUSTICE THREE EMBARCADERO CENTER, 7TH FLOOR 50 CALIFORNIA ST., STE. 500 SAN FRANCISCO, CA 94111 SAN FRANCISCO, CA 94111 FOR: LYFT, INC.
THOMAS W. SOLOMON RACHELLE CHONG ATTORNEY AT LAW COUNSEL WINSTON & STRAWN LLP LAW OFFICES OF RACHELLE CHONG 101 CALIFORNIA STREET 345 WEST PORTAL AVENUE, STE. 110 SAN FRANCISCO, CA 94111 SAN FRANCISCO, CA 94127
RITA LIOTTA CASE COORDINATION
Page 9 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
FEDERAL EXECUTIVE AGENCIES PACIFIC GAS AND ELECTRIC COMPANY 1 AVENUE OF THE PALMS, STE. 161 EMAIL ONLY SAN FRANCISCO, CA 94130 EMAIL ONLY, CA 94177 FOR: FEA
SARAH VAN CLEVE HOWARD V. GOLUB ENERGY POLICY ADVISOR ATTORNEY TESLA, INC. BEST BEST & KRIEGER LLP 3500 DEER CREEK ROAD 2001 NORTH MAIN STREET, STE. 390 PALO ALTO, CA 94304 WALNUT CREEK, CA 94596 FOR: CITY OF OAKLAND, CALIFORNIA, A MUNICIPAL CORPORATION, ACTING BY AND THROUGH ITS BOARD OF PORT OF HARBOR COMMISSIONERS
DONNELL CHOY MELISSA BRANDT DEPUTY PORT ATTORNEY SR. DIR - PUBLIC AFFAIRS & GEN. COUNSEL PORT OF OAKLAND EAST BAY COMMUNITY ENERGY 530 WATER STREET, 4TH FL. 1111 BROADWAY, STE 3000 OAKLAND, CA 94607 OAKLAND, CA 94607
PAUL NELSON PAUL D. HERNANDEZ CONSULTANT POLICY MGR. BARKOVICH & YAP, INC. CENTER FOR SUSTAINABLE ENERGY PO BOX 11031 426 17TH STREET, STE. 700 OAKLAND, CA 94611 OAKLAND, CA 94612
RACHEL GOLDEN DAVID MARCUS SR. CAMPAIGN REP. 1541 JUANITA WAY SIERRA CLUB BERKELEY, CA 94702 2101 WEBSTER, STE. 1300 FOR: COALITION OF CALIFORNIA UTILITY OAKLAND, CA 94612 EMPLOYEES
TAM HUNT C. C. SONG CONSULTING ATTORNEY REGULATORY ANALYST 2039 SHATTUCK AVENUE, SUITE 402 MARIN CLEAN ENERGY BERKELEY, CA 94704 1125 TAMALPAIS AVE. FOR: THE GREEN POWER INSTITUTE SAN RAFAEL, CA 94901 FOR: MCE
PHILLIP MULLER JOHN NIMMONS SCD ENERGY SOLUTIONS COUNSEL 436 NOVA ALBION WAY JOHN NIMMONS & ASSOCIATES, INC. SAN RAFAEL, CA 94903 175 ELINOR AVE., STE. G MILL VALLEY, CA 94941
ANNE SMART ANTHONY HARRISON VP, PUBLIC POLICY DIR - PUBLIC POLICY CHARGEPOINT, INC. CHARGEPOINT 254 EAST HACIENDA AVENUE 254 E. HACIENDA AVENUE CAMPBELL, CA 95008 CAMPBELL, CA 95008
NEWONDA NICHOLS RENEE SAMSON PROGRAM MGR., UTILITY SOLUTIONS DIR - UTILITY SOLUTIONS
Page 10 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
CHARGEPOINT, INC. CHARGEPOINT, INC. 254 EAST HACIENDA AVE. 245 E. HACIENDA AVENUE CAMPBELL, CA 95008 CAMPBELL, CA 95008
ART DOUWES JAMES WILHELM OPERATIONS MGR. SR. MECHANICAL ENGINEER VTA BUS MAINTENANCE ENGINEERING VTA BUS MAINTENANCE ENGINEERING 3331 NORTH FIRST STREET, BUILDING B-1 3331 NORTH FIRST STREET, BUILDING B-1 SAN JOSE, CA 95134 SAN JOSE, CA 95134
STEVEN S. SHUPE AUDRA HARTMANN GENERAL COUNSEL PRINCIPAL SONOMA CLEAN POWER AUTHORITY SMITH, WATTS & HARTMANN 50 SANTA ROSA AVE., 5TH FL. 925 L STREET, SUITE 220 SANTA ROSA, CA 95404 SACRAMENTO, CA 95814
DELANEY L. HUNTER JOHN SHEARS MANAGING PARTNER RENEWABLE TECHNOLOGIES GONZALEZ, QUINTANA, HUNTER & CRUZ, LLC THE CENTER FOR ENERGY EFFICIENCY AND 915 L STREET, STE. 1270 1100 11TH ST., SUTE. 311 SACRAMENTO, CA 95814 SACRAMENTO, CA 95814 FOR: SANTA CLARA VALLEY TRANSPORTATION FOR: CEERT AUTHORITY
ANDREW B. BROWN RONALD LIEBERT ATTORNEY ATTORNEY AT LAW ELLISON SCHNEIDER HARRIS & DONLAN LLP ELLISON SCHNEIDER HARRIS & DONLAN LLP 2600 CAPITOL AVE., STE. 400 2600 CAPITOL AVENUE, STE. 400 SACRAMENTO, CA 95816 SACRAMENTO, CA 95816
CATHIE ALLEN ELI MORRIS DIR - REGULATORY AFFAIRS PACIFICORP PACIFICORP 825 NE MULTNOMAH, STE. 2000 825 NE MULTNOMAH ST., STE 300 PORTLAND, OR 97232 PORTLAND, OR 97232
ETTA LOCKEY SR. COUNSEL PACIFICORP 825 NE MULTNOMAH ST., STE. 1500 PORTLAND, OR 97232
State Service
MATTHEW WILLIAMS ALAN BACH AIR POLLUTION SPECIALIST CALIF PUBLIC UTILITIES COMMISSION CALIFORNIA AIR RESOURCES BOARD ENERGY INFRASTRUCTURE BRANCH EMAIL ONLY AREA EMAIL ONLY, CA 00000 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214
AUDREY NEUMAN BENJAMIN GUTIERREZ CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
Page 11 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
PROCUREMENT STRATEGY AND OVERSIGHT BRANC ELECTRICITY PRICING AND CUSTOMER PROGRAM ROOM 4-A AREA 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
CAROLYN SISTO CHLOE LUKINS CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION PROCUREMENT STRATEGY AND OVERSIGHT BRANC ENERGY INFRASTRUCTURE BRANCH AREA ROOM 4102 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
DAVID PECK FIDEL LEON DIAZ CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION PRESIDENT BATJER ENERGY INFRASTRUCTURE BRANCH ROOM 5215 AREA 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
JENNIFER KALAFUT JOSEPH A. ABHULIMEN CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION ENERGY EFFICIENCY BRANCH ENERGY INFRASTRUCTURE BRANCH ROOM 4002 ROOM 4209 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
JUNAID RAHMAN LIAM WEAVER CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION RISK ASSESSMENT & SAFETY ADVISORY ENERGY SAFETY & INFRASTRUCTURE BRANCH AREA AREA 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
NATHAN CHAU RICK TSE CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION ELECTRICITY PRICING AND CUSTOMER PROGRAM ELECTRIC SAFETY AND RELIABILITY BRANCH AREA AREA 2-D 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214 FOR: ORA
SARA M. KAMINS SASHA GOLDBERG CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION PROCUREMENT STRATEGY AND OVERSIGHT BRANC ADMINISTRATIVE LAW JUDGE DIVISION AREA ROOM 5021 505 VAN NESS AVENUE 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
TIM G. DREW NOEL CRISOSTOMO CALIF PUBLIC UTILITIES COMMISSION AIR POLUTION SPECIALIST ENERGY INFRASTRUCTURE BRANCH CALIFORNIA ENERGY COMMISSION AREA 4-A 1516 9TH STREET 505 VAN NESS AVENUE SACRAMENTO, CA 95814 SAN FRANCISCO, CA 94102-3214
Page 12 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm
TOP OF PAGE BACK TO INDEX OF SERVICE LISTS
Page 13 of 13CPUC - Service Lists - A1701020
1/31/2020https://ia.cpuc.ca.gov/servicelists/A1701020_84073.htm