Start Up Procedures Egypt

Embed Size (px)

Citation preview

  • 8/9/2019 Start Up Procedures Egypt

    1/66

    Instruction BulletinMay 2001

    Schneider Electric Egypt ServicesProcedures for Startup and Commissioningof Electrical Equipment

  • 8/9/2019 Start Up Procedures Egypt

    2/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Table of Contents May 2001

    2000-2001 Schneider Electric All Rights Reserved2

    SECTION 1INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

    SECTION 2SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    SECTION 3AC DRIVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

    SECTION 4AIR SWITCHES: LOW VOLTAGE (BOLTED

    PRESSURE, QMB, OR EQUAL) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8

    SECTION 5AIR SWITCHES: MEDIUM VOLTAGE,

    METAL-ENCLOSED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

    SECTION 6AIR SWITCHES: HIGH AND MEDIUM VOLTAGE,

    OPEN STYLE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

    SECTION 7ANALOG METERING . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13

    SECTION 8BUSWAYS, METAL-ENCLOSED . . . . . . . . . . . . . . . . . . . .14

    SECTION 9CABLES: LOW VOLTAGE AND MEDIUM VOLTAGE . . . 15

    SECTION 10CAPACITORS: POWER FACTOR CORRECTION . . . . .16

    SECTION 11CIRCUIT BREAKERS: LOW VOLTAGE INSULATED

    CASE/MOLDED CASE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    SECTION 12CIRCUIT BREAKERS: LOW VOLTAGE POWER

    (ANSI/IEEE C37.13) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .20

    SECTION 13CIRCUIT BREAKERS: MEDIUM VOLTAGE SF6 . . . . . .22

    SECTION 14CIRCUIT BREAKERS: MEDIUM VOLTAGE

    VACUUM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24

    SECTION 15DIRECT CURRENT SYSTEMS: BATTERIES. . . . . . . . . 26

    SECTION 16EMERGENCY SYSTEMS: AUTOMATIC TRANSFER

    SWITCHES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

    SECTION 17GROUND-FAULT PROTECTION SYSTEMS . . . . . . . . .29

    SECTION 18GROUND RESISTORS . . . . . . . . . . . . . . . . . . . . . . . . . . 31

    SECTION 19GROUNDING SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . .32

    SECTION 20ISOLATED POWER SYSTEMS . . . . . . . . . . . . . . . . . . . 33

    SECTION 21MOTOR CONTROL CENTERS: LOW AND

    MEDIUM VOLTAGE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .36

    SECTION 22MOTOR STARTERS: LOW VOLTAGE. . . . . . . . . . . . . . 39

    SECTION 23MOTOR STARTERS: MEDIUM VOLTAGE . . . . . . . . . . .40

    SECTION 24OIL SWITCHES: MEDIUM VOLTAGE . . . . . . . . . . . . . . .42

    SECTION 25PROTECTIVE RELAYS . . . . . . . . . . . . . . . . . . . . . . . . . .43

    SECTION 26STEP VOLTAGE REGULATORS . . . . . . . . . . . . . . . . . .44

    SECTION 27SURGE ARRESTERS: LOW VOLTAGE SURGEPROTECTION DEVICES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46

    SECTION 28SURGE ARRESTERS: MEDIUM AND HIGH

    VOLTAGE SURGE PROTECTION DEVICES . . . . . . . . . . . . . . . . . . . . .47

    SECTION 29 SWITCHGEAR AND SWITCHBOARD ASSEMBLIES:

    LOW AND MEDIUM VOLTAGE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48

    SECTION 30TRANSFORMERS: DRY TYPE: ALL VOLTAGES -

    LARGE (GREATER THAN 167 SINGLE-PHASE AND 500KVA

    THREE-PHASE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .51

    TABLE OF CONTENTS

  • 8/9/2019 Start Up Procedures Egypt

    3/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 List of Tables

    3 2000-2001 Schneider Electric All Rights Reserved

    SECTION 31TRANSFORMERS: DRY TYPE - SMALL

    (167KVA SINGLE-PHASE, 500KVA THREE-PHASE,

    AND SMALLER) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52

    SECTION 32TRANSFORMERS, INSTRUMENT . . . . . . . . . . . . . . . . .53

    SECTION 33TRANSFORMERS: LIQUID-FILLED: ALL VOLTAGES . 55

    Table 1: US Standard Bolt Torques for Bus and Cable

    Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57

    Table 2: Insulation-Resistance Test Voltage for Electrical

    Apparatus and Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59

    Table 3: Transformer Insulation-Res. Acceptance Test Voltage

    and Min. Results. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59

    Table 4: Insulation Resistance Conversion Factors. . . . . . . . . . . . . 60

    Table 5: Power Frequency Dielectric Withstand Test . . . . . . . . . . . 61

    Table 6: Instrument Transformer Dielectric Tests . . . . . . . . . . . . . . 62

    Table 7: Schneider Molded Case Circuit Breaker Watts

    Loss/Resistance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63

    Table 8: Schneider Type DS, DSII, DSL, and DSLII Circuit

    Breaker Contact Resistance. . . . . . . . . . . . . . . . . . . . . . . . 66

    LIST OF TABLES

  • 8/9/2019 Start Up Procedures Egypt

    4/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 1Introduction May 2001

    2000-2001 Schneider Electric All Rights Reserved4

    This bulletin details the inspection and testing procedures that Schneider

    Services technicians must follow during commissioning and startup of

    electrical equipment. These inspections and tests are performed on new

    equipment, after installation and prior to energizing, in order to:

    1. check that the equipment has not been damaged during shipment or

    installation;

    2. verify that the equipment is in compliance with the purchase specification

    and design intent; and

    3. document test results that can serve as benchmarks for future tests.

    The standard deliverables to the customer are those inspections and tests

    listed under subsections A, B, and D (Instrument Transformers only) of each

    equipments startup procedures. Schneider technicians will perform the

    optional tests listed in subsections C and E (Instrument Transformers only) if

    specified by the customer at the time the order is received.

    For testing of equipment not detailed in this document,Schneider Services

    will refer to the InterNational Electrical Testing Associations (NETA)

    guidelines in Acceptance Testing Specifications for Electrical Power

    Distribution Equipment and Systems(NETA ATS 1999).

    For additional information, contact Schneider Services

    Schneider Electric has been granted permission to publish insulation

    resistance acceptance criteria as listed in the Acceptance Testing

    Specifications for Electrical Power Distribution Equipment and

    Systems(NETA ATS 1999) published by the International Electrical Testing

    Association. Publication of data taken from this document may require

    permission of Schneider Electric and InterNational Electrical Testing

    Association.

    SECTION 1INTRODUCTION

    Acknowledgement

  • 8/9/2019 Start Up Procedures Egypt

    5/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 2Safety

    5 2000-2001 Schneider Electric All Rights Reserved

    Proper safety procedures shall be reviewed and implemented before each

    activity listed in this procedure and the Schneider Field Service

    Safety, Health and Environmental Handbook. Job Safety Analysis followed

    by a toolbox/pre-job meeting shall be conducted prior to any activity listed in

    this procedure. The toolbox meeting shall be documented and attached to

    the FS101. Proper safety procedures as detailed in the Schneider

    Electric Field Services Safety, Health and Environmental Handbook,employee training, and customers requirements shall be implemented as

    dictated by each sites requirements.

    Services Employees are NOT authorized to work on live equipment. There

    may be occasions in which you are taking measurements or checking

    voltages within an energized enclosure, but you are NOT authorized to do

    Hands on Live repairs!

    Schneider does not typically perform shutdown and/or switching

    operations, because these operations may result in damage to property or

    persons downstream of the equipment as a result of conduct, errors, or

    omissions made by others. If a customer requests Schneider to

    perform such services, technicians must contact their District Manager for

    approval and proper procedures.

    Required personal protective equipment is detailed in the latest revision of

    procedure SQDS-SHE-001. A copy of this procedure may be obtained from

    the District Manager or from the Safety, Health, and Environment Manager.

    SECTION 2SAFETY

  • 8/9/2019 Start Up Procedures Egypt

    6/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 3AC Drives May 2001

    2000-2001 Schneider Electric All Rights Reserved6

    A. Physical Inspection

    1. Document equipment nameplate data on the test report. Verify

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications.

    2. Check for shipping damage: broken operators, switches, or pilot lights;

    dented or bent enclosure structures.

    3. Check for any loose assemblies, excessive dirt, dust, or moisture. Clean

    up if necessary using a shop vacuum.

    4. Tighten all power wiring connections to proper torque value. Check line

    and load side connections of all disconnect switches, breakers,

    contactors, and overloads.

    5. Check for proper wire sizing per the manufacturers recommendations.

    Check insulation integrity; tighten to the specified torque per the

    manufacturers instructions.

    6. Verify that a properly sized grounding conductor is connected to the drive

    grounding lug and terminates on a ground lug in the power distribution

    panel.

    7. Verify that wires connected between the drive and the motor are correctly

    sized per the manufacturers instructions. Verify that these wires areseparated from all other wiring (ideally in their own conduit). Note the

    length of wire between the drive and the motor on the test report.

    8. Tighten all control wiring connections to the proper torque value. Check

    and tighten the drive control terminals. Check and tighten all terminal

    block connections. Check for proper insulation strip length on customer

    supplied control wiring.

    9. Check door and disconnect switch alignment and opening/closing

    operation.

    10. Test all mechanical interlocking devices.

    11. Manually operate all contactors to verify freedom of movement.

    12. Verify that customer supplied fusing agrees with the manufacturers

    recommendations.

    13. Verify mechanical operation of isolation contactor. Tighten power and

    control connections. Verify the proper coil voltage rating.

    14. Verify that the options board is securely fastened and plug-in terminals

    are present.

    15. Check for proper heaters used in ISO/Bypass unit.

    16. Verify that the location of the drive will not be allowed to be hotter than

    100 F or colder than 32 F, and that no condensing moisture is present.

    17. Verify the type of load: constant torque or variable torque (centrifugal

    pumps and fans). Note the machines functional name on the test report.

    18. Verify that the proper Torque Type is selected (i.e., Constant, Variable, or

    Variable Low Noise).

    B. Electrical Tests

    The following tests involve the setup of the drive by using the programmable

    menus in the drive. Supply single-phase power at the rated system voltage

    level, +/-15, to the CL1 and CL2 terminals of the drive.

    1. Set the Motor Nominal Current parameter to Motor nameplate Full Load

    Amp (FLA) value.

    2. Set the High Speed Parameter to 60 Hz, or the maximum setting intended

    by the user.

    SECTION 3AC DRIVES

  • 8/9/2019 Start Up Procedures Egypt

    7/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 3AC Drives

    7 2000-2001 Schneider Electric All Rights Reserved

    3. Set the Low Speed Parameter to 0 Hz, or the minimum setting intended

    by the user.

    4. Set the Acceleration parameter to approximately 20 seconds.

    5. Set the Deceleration parameter to approximately 30 seconds.

    6. Check the Input/Output Map assignments.

    7. Set the keypad to display four table scroll.8. Set Output Phase Fault parameter to No.

    9. Operate the drive with no motor connected. Cycle the unit through several

    Start and Stop sequences, ramping to full speed and to zero. (Use

    Keypad Mode if no external Start/Stop or Speed control is available.)

    10. Return Output Phase Fault parameter to Yes.

    For the following tests, the equipment will be energized onto the power

    distribution circuit by the means provided (i.e., disconnect switch) for the

    drive. The connected motor will be bumped to verify proper rotating

    direction using the drive as well as any bypass to line feature, if provided.

    11. Measure the output of ac control transformers to be within +/-5% of

    nominal output voltage. Measure dc control supplies (for customer use),

    and verify that they are within the manufacturers recommendations.

    12. Measure the dc bus voltage and verify that it is equal to the measured

    RMS Line to Line input voltage x 1.414 +/-5%.

    13. Measure the RMS values of Line to Line voltages: L1 to L2, L1 to L3, and

    L2 to L3. Verify that they are 208, 230, or 460 Vac rms +/-10%. Phase to

    Phase voltage imbalance must be less than +/-2%. Measure L1, L2, and

    L3 to ground. Phase to ground voltage imbalance should be less than

    +/-5%. Perform measurements in standby mode, medium motor load,

    and full motor load.

    14. Verify that phase rotation in Bypass mode is per the manufacturers

    recommendations. If incorrect, swap any two line-side power wires at the

    disconnecting switch.

    15. Verify that phase rotation in AFC mode at approximately 10 Hz is per the

    manufacturers recommendations. If incorrect, swap any two wires at the

    T lead connections on the drive.

    16. Measure Output voltages at the T lead terminals of the drive with no

    motor connected (open circuit with output phase fail detection turned off)

    and the drive running at half speed and again at full speed. Verify that

    phase to phase output voltage imbalance is less than 2% at any output

    frequency. Repeat with the motor connected and running at medium

    motor load and again at full motor load.

    17. Measure the motor current in each T lead at medium motor load and

    again at full motor load. Output Phase Current imbalance must be less

    than 5% at any load. Compare readings taken to displayed value of output

    current on the Keypad. Note any discrepancies on the test report.

    18. Verify that speed control signals vary within the voltage or current range

    of the input to which they are connected. Check for proper shielding on

    wires connected to speed control inputs. Verify that signals are isolatedfrom power wires.

    19. Verify that I/O points are assigned to proper functions per factory

    drawings.

    20. Verify that Hand and Auto controls, Start, Stop, and speed input, operate

    the drive correctly.

    21. Check that all indicating lamps illuminate only for their assigned

    functions. Check all Push to Test lamps.

  • 8/9/2019 Start Up Procedures Egypt

    8/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 4Air Switches: Low Voltage (Bolted Pressure, QMB, or Equal) May 2001

    2000-2001 Schneider Electric All Rights Reserved8

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify equipment

    nameplate ratings are in accordance with the final approved and record

    drawings and specifications, if available.

    2. Inspect physical and mechanical condition.

    3. Confirm application of lubricants at manufacturer's recommendedlocations.

    4. Verify appropriate anchorage and required area clearances.

    5. Verify appropriate equipment grounding.

    6. Verify correct blade alignment, blade penetration, travel stops, and

    mechanical operation.

    7. Verify and record fuse sizes and types are in accordance with drawings

    and short-circuit and coordination studies, if available.

    8. Verify tightness of accessible bolted electrical connections by calibrated

    torque-wrench method in accordance with manufacturer's published

    data. If no manufacturer's data is available, use the values in Table 1 on

    page 57.

    9. Check all interlocking systems for correct operation and sequencing, and

    key distribution, if applicable.

    10. Verify correct phase barrier materials and installation.

    11. Inspect all indicating and control devices for correct operation.

    12. Check the condition of arc contacts and arc chutes.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance Panelboard industry standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Perform insulation-resistance tests on each pole, phase-to-phase and

    phase-to-ground with switch closed and across each open pole for one

    minute. Test voltage shall be in accordance with manufacturer's published

    data or Table 2 on page 59.

    2. Switches equipped with solenoid trip, blown main fuse detector, etc., test

    each feature for proper operation. To test blown fuse detector, activate it

    and confirm by attempting to close the breaker without reset.

    3. Sswitches, perform Blade Contact Resistance Test

    (a) With the device de-energized, operate the device closed and open

    several time using either manual or electrical means.

    (b) Apply a minimum current of 100 amperes dc through the closed

    contacts. If 100 A is not available, use the highest current available. Ifthe device does not conform to the manufacturers specification,

    obtain equipment to perform the test at 100 A or consult the factory

    with full information about the details of the test. If the continuous

    current rating is less than 100 A, then test at a level not to exceed the

    continuous current rating.

    SECTION 4AIR SWITCHES: LOWVOLTAGE (BOLTED PRESSURE, QMB,

    OR EQUAL)

  • 8/9/2019 Start Up Procedures Egypt

    9/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 4Air Switches: Low Voltage (Bolted Pressure, QMB, or Equal)

    9 2000-2001 Schneider Electric All Rights Reserved

    (c) Measure the contact resistance of each pole and compare with the

    following values:

    NOTE: Current Source Test Probes must be placed on extreme ends of

    the Jaw Terminal and the Hinge/Fuse Pad with the Potential Measuring

    Probes placed approximately one inch from each Current Source Test

    Probe, on the inside between the Current Source Test Probes.

    (d) If the resistances is below the value shown above, the condition of the

    device contacts is considered suitable for service. If the resistance

    exceeds the value above, open and close the device several more

    times. If high readings persists, increase the DC test current to a levelequivalent to the continuous current rating of the device. Contact the

    factory if nominal values of resistance cannot be achieved.

    4. Measure fuse resistance to check continuity.

    5. Test the ground fault relay by current injection to verify that the switch trips

    at the proper setting.

    6. Perform adjustments on the ground fault setting for final settings in

    accordance with the coordination study supplied by the owner, if

    applicable.

    BP Switch Rating Resistance

    800 Amp. 13 Micro-Ohms Max.

    1200 Amp. 13 Micro-Ohms Max.

    1600 Amp. 11 Micro-Ohms Max.

    2000 Amp. 8 Micro-Ohms Max.

    2500 Amp. 7 Micro-Ohms Max.

    3000 Amp. 6 Micro-Ohms Max.

    4000 Amp. 7 Micro-Ohms Max.

  • 8/9/2019 Start Up Procedures Egypt

    10/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 5Air Switches: Medium Voltage, Metal-Enclosed May 2001

    2000-2001 Schneider Electric All Rights Reserved10

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify equipment

    nameplate ratings are in accordance with the final approved or record

    drawings and specifications, if available.

    2. Inspect physical and mechanical condition.

    3. Confirm correct application of lubricants at manufacturer's recommendedlocations.

    4. Verify appropriate anchorage and required area clearances.

    5. Verify appropriate equipment grounding.

    6. Verify correct blade alignment, blade penetration, travel stops, and

    mechanical operation. Check to make sure the interrupter blade for

    type HVL switches securely latched with in the arc chute when

    the switch closes. A properly latched interrupter blade will stay latched

    within the arc chute until the main blades are about half way open in the

    opening cycle.

    7. Verify that fuse sizes and types are in accordance with drawings and

    short-circuit and coordination studies, if available.

    8. Inspect fuse holders for tightness and alignment.

    9. Verify that expulsion-limiting devices are in place on all holders having

    expulsion-type elements. Verify that they are installed to vent in the

    proper direction.

    10. Verify tightness of accessible bolted electrical connections by calibrated

    torque-wrench method in accordance with manufacturer's published

    data. If no manufacturer's data is available, use the values in Table 1 on

    page 57.

    11. Check all interlocking systems for correct operation and sequencing, and

    key distribution, if applicable.

    12. Verify correct phase-barrier materials and installation.

    13. Inspect all indicating and control devices for correct operation.

    14. Verify that the Lightning arresters have been connected, verify that they

    have the proper voltage per the manufacturers drawings.15. Inspect the linkage and gap adjustments on VISI-VAC switches to

    confirm that a sealing compound has been applied and that the

    adjustments are finger tight.

    16. Check the condition of arc contacts and arc chutes.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with Switchgear industry

    standards.

    Verify the proper selection and operation of the electrical test equipment.Record the date of the last calibration date and the date re-calibration is due.

    1. Perform insulation-resistance tests on each pole, phase-to-phase and

    phase-to-ground with switch closed and across each open pole for one

    minute. Test voltage shall be in accordance with manufacturer's published

    data or Table 2 on page 59.

    2. Perform a dielectric test (Hi-Pot) on each pole with switch closed. Test

    each pole-to-ground with all other poles grounded. Test voltage shall be

    in accordance with manufacturer's published data or Table 5 on page 61.

    SECTION 5AIR SWITCHES: MEDIUMVOLTAGE, METAL-ENCLOSED

  • 8/9/2019 Start Up Procedures Egypt

    11/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 5Air Switches: Medium Voltage, Metal-Enclosed

    11 2000-2001 Schneider Electric All Rights Reserved

    3. Verify that heaters have been connected and is operating properly.

    4. Measure fuse resistance to verify continuity.

    5. Perform a contact-resistance test for HVL/cc and Visi-Vac

    devices. Use the following procedure:

    (a) With the device de-energized, operate the device closed and open

    several times using either manual or electrical means.

    (b) Apply a minimum current of 100 amperes dc through the closed

    contacts. If 100 A is not available, use the highest current available. If

    the device does not conform to the manufacturers specification,

    obtain equipment to perform the test at 100 A or consult the factory

    with full information about the details of the test. If the continuous

    current rating is less than 100 A, then test at a level not to exceed the

    continuous current rating.

    (c) Measure the contact resistance of each pole and compare with the

    following values:

    VISI-VAC ..............85 Micro-Ohms

    HVL/cc ................. 75 Micro-Ohms

    HVL .....................no value available

    (d) If the resistance is below the value shown above, the condition of the

    device contacts is considered suitable for service. If the resistance

    exceeds the value above, open and close the device several more

    times. If high readings persist, increase the dc test current to a level

    equivalent to the continuous current rating of the device. Contact the

    factory if nominal values of resistance cannot be achieved.

    C. Optional Tests

    Check the erosion gap of VISI-VAC vacuum bottles per the manufacturers

    instructions .Adjust as necessary to meet specified gaps.

  • 8/9/2019 Start Up Procedures Egypt

    12/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 6Air Switches: High and Medium Voltage, Open Style May 2001

    2000-2001 Schneider Electric All Rights Reserved12

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify equipment

    nameplate ratings are in accordance with the final approved or record

    drawings and specifications, if available.

    2. Inspect physical and mechanical condition.

    3. Confirm correct application of lubricants at manufacturer's recommendedlocations.

    4. Verify that grounding is in accordance with industry standards and project

    specifications.

    5. Verify tightness of accessible bolted electrical connections by calibrated

    torque-wrench method in accordance with manufacturer's published

    data. If no manufacturer's data is available, use the values in Table 1 on

    page 57.

    6. Perform mechanical operator tests in accordance with manufacturer's

    instructions.

    7. Verify correct operation and adjustment of motor operator limit-switches

    and mechanical interlocks.

    8. Verify correct blade alignment, blade penetration, travel stops, arc

    interrupter operation, and mechanical operation (over toggle).

    9. Inspect fuse holders for tightness and alignment.

    10. Check the condition of arc contacts and arc chutes.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with Switchgear industry

    standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Perform insulation-resistance tests on each pole, phase-to-phase and

    phase-to-ground with switch closed and across each open pole for one

    minute. Test voltage should be in accordance with manufacturer's

    published data or Table 2 on page 59.

    2. Perform a dielectric test (Hi-Pot) on each pole with switch closed. Test

    each pole-to-ground with all other poles grounded. Test voltage shall be

    in accordance with manufacturer's published data or Table 5 on page 61.

    3. Perform a contact-resistance test across each switchblade and fuse

    holder. Investigate any value exceeding 500 micro-ohms, or any values

    that deviate from adjacent poles or similar switches by more than 25

    percent.

    SECTION 6AIR SWITCHES: HIGH ANDMEDIUM VOLTAGE, OPEN STYLE

  • 8/9/2019 Start Up Procedures Egypt

    13/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 7Analog Metering

    13 2000-2001 Schneider Electric All Rights Reserved

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify equipment

    nameplate ratings are in accordance with the final approved or record

    drawings and specifications, if available.

    2. Inspect physical and mechanical condition.

    3. Verify tightness of electrical connections.4. Verify mechanically for freedom of movement, correct travel and

    alignment, and tightness of mounting hardware.

    B. Electrical Tests

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Check calibration of meters according to the manufacturers published

    data.

    2. Electrically confirm that current transformer and voltage transformer

    secondary circuits are intact.

    C. Optional Tests

    1. Calibrate watt-hour meters according to manufacturer's published data.

    2. Verify all instrument multipliers.

    SECTION 7ANALOG METERING

  • 8/9/2019 Start Up Procedures Egypt

    14/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 8Busways, Metal-Enclosed May 2001

    2000-2001 Schneider Electric All Rights Reserved14

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify busway

    nameplate ratings in accordance with final approved or record drawings

    and specifications, if available.

    2. Inspect the busway for physical damage and correct connection in

    accordance with the single-line diagram.

    3. Inspect for appropriate bracing, suspension, alignment, and enclosure

    ground.

    4. Using the calibrated torque-wrench method, verify that the tightness of

    accessible bolted electrical connections is in accordance with the

    manufacturer's published data. If no manufacturer's data is available, use

    the values in Table 1 on page 57. For Square D, Low Voltage, I-Line

    Busway, check to see that the outer head has been broken off. Verify that

    the red plastic disk (VISI-TITE) at each bus joint is automatically

    removed when the head is broken off.

    5. To ensure adequate cooling, confirm that the physical orientation is in

    accordance with manufacturer's labels.

    6. Examine the outdoor busway for removal of weep-hole plugs, if

    applicable, and the correct installation of joint shield. Verify that propergasketing is in place.

    B. Electrical Tests

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Measure insulation resistance of each busway, phase-to-phase and

    phase-to-ground for one minute, in accordance with Table 2 on page 59.

    For Square D, Low Voltage, I-Line busway, with the load and line ends

    disconnected, and no overcurrent devices installed, use an insulation

    resistance tester rated at 1000 volts to ensure the system is free from

    short circuits and grounds (phase-to-phase, phase-to-neutral, and

    phase-to-ground). The megohm readings should not be less than the

    value calculated from the following formula. (If readings are less than the

    values calculated from the formula consider drying the air with in the

    building for at least a day and then remeasure. If low readings persist,

    contact the factory.)

    Megohms = 100 / length of run (in feet) or Megohms = 30.5 / length of run

    (in meters)

    2. Visual confirmation of correct phasing on each busway tie section

    energized by separate sources. (De-energized)

    C. Optional Tests

    1. Perform contact-resistance test on each connection point of non

    insulated busway. On insulated busway, measure resistance of

    assembled busway sections and compare values with adjacent phases.2. Perform a dielectric test (Hi-Pot) on each busway, phase-to-ground with

    phases not under test grounded, in accordance with manufacturer's

    published data. Apply test voltage for one minute. Use test voltage values

    as shown in Table 5 on page 61.

    SECTION 8BUSWAYS, METAL-ENCLOSED

  • 8/9/2019 Start Up Procedures Egypt

    15/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 9Cables: Low Voltage and Medium Voltage

    15 2000-2001 Schneider Electric All Rights Reserved

    A. Visual and Mechanical Inspection

    1. Verify that cable sizing and insulation temperature rating are in

    accordance with final approved or record drawings and specifications, if

    available. Note any deviations.

    2. Inspect the exposed sections of cables for physical damage and correct

    connection in accordance with single-line diagrams.

    3. Using a calibrated torque wrench, verify that the tightness of accessible

    bolted connections is in accordance with the manufacturer's published

    data. If no manufacturer's data is available, use the values in Table 1 on

    page 57.

    4. Inspect compression-applied connectors for correct cable match and

    indentation.

    5. Verify cable color coding with applicable engineer's specifications.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance industry standards.

    Verify that the opposite end of the cable run being tested is isolated form

    personnel during testing. Verify that the electrical test equipment is correctly

    selected and operates properly. Record the date of the last calibration date

    and the date re-calibration is due.

    1. Cables and leads shall be tested for continuity to ensure correct cable

    connection and phasing rotation.

    2. Perform an insulation resistance test on each conductor between one

    conductor and ground with the other conductors grounded. Each

    conductor shall be tested in the same manner.

    (a) The test shall be performed at 1000 volts dc for one minute.

    (b) Each 480V feeder cable shall be tested with the cable connected tothe racked-in but open breaker or switch at the equipment. Connection

    at the other end of each of these cables shall be as follows:

    (i) Cables to Motor Control Centers shall be connected to the bus with

    the switches or breakers in the starters open.

    (ii) Cables to motors and other equipment shall be connected to the

    motors and equipment with feeder switches open.

    C. Optional Test

    Perform a dielectric test on medium voltage shielded cable per Table 5 on

    page 61. Refer to the manufacturers published data, and perform at 5 KV

    intervals, checking leakage current and decay voltage over the specified time

    period.

    SECTION 9CABLES: LOW VOLTAGEAND MEDIUM VOLTAGE

  • 8/9/2019 Start Up Procedures Egypt

    16/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 10Capacitors: Power Factor Correction May 2001

    2000-2001 Schneider Electric All Rights Reserved16

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on the test report.

    2. Verify that the capacitor nameplate ratings are in accordance with the

    final approved or record drawings and specifications.

    3. Inspect the physical and mechanical condition of the equipment.

    4. Inspect the capacitors for the correct mounting and required clearances,per the manufacturers recommended procedures.

    5. Verify that capacitors are electrically connected in their specified

    configuration, per the manufacturers recommended procedures.

    6. Using a calibrated torque wrench, verify that the tightness of accessible

    bolted electrical connections is in accordance with the manufacturer's

    published data. If no manufacturer's data is available, use the values in

    Table 1 on page 57.

    B. Electrical Tests

    1. Perform insulation-resistance tests from terminal(s) to case for one

    minute on capacitors with more than one bushing. The test voltage and

    minimum resistance shall be in accordance with the manufacturers

    instructions or Table 2 on page 59.

    2. Measure the capacitance of all terminal combinations.

    3. Measure the resistance of the internal discharge resistors.

    SECTION 10CAPACITORS: POWERFACTOR CORRECTION

  • 8/9/2019 Start Up Procedures Egypt

    17/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 11Circuit Breakers: Low Voltage Insulated Case/Molded Case

    17 2000-2001 Schneider Electric All Rights Reserved

    A. Visual and Mechanical Inspection

    Field Testing Industrial Molded-Case Circuit Breakers)

    1. Document equipment nameplate data on test report. Verify equipment

    nameplate ratings are in accordance with the final approved or record

    drawings and specifications.

    2. Inspect circuit breaker for correct mounting.

    3. Operate circuit breaker to insure smooth operation.

    4. Inspect case for cracks or other defects.

    5. Verify tightness of accessible bolted connections and/or cable

    connections by calibrated torque-wrench method in accordance with

    manufacturer's published data. If no manufacturer's data is available, use

    the values in Table 1 on page 57.

    6. Verify that trip units, shunt trip coils, auxiliary contacts and all other

    accessories are in accordance with the job specifications.

    7. Exercise the push to trip button to verify trip and reset.

    8. If the circuit breaker contains a MICROLOGIC trip unit, perform the

    following inspections:

    a. Verify that the breaker is equipped with the correct rating plugs andcurrent sensors.

    b. Verify that the breaker has the specified trip unit, LI, LS, LSI, and

    LSIG.

    c. Verify that the breaker has the specified accessories, such as

    Auxiliary Contacts, Cell Switches, Shunt Trip Devices, and

    Undervoltage Release.

    d. Verify that the Ground Fault System has been wired in accordance

    with the specified wiring diagram, and that the Sensor Grounds are

    either present or not present as specified.

    e. Verify that the secondary control plug/connections are in accordance

    with the wiring diagram and specifications.

    9. If it is an SED or drawout MASTERPACTcircuit breaker, perform the

    following inspections:

    a. Confirm that lubricants have been correctly applied at the

    manufacturer's recommended locations.

    b. Inspect anchorage, alignment, and grounding. Inspect arc chutes.

    Inspect moving and stationary contacts for condition and alignment.

    c. Verify that all maintenance devices are available for servicing and

    operating the breaker.

    d. Perform all mechanical operator and contact alignment tests on both

    the breaker and its operating mechanism.

    e. Check cell fit and element alignment.

    f. Check the racking mechanism.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with molded case circuit breaker

    industry standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    SECTION 11CIRCUIT BREAKERS:LOW VOLTAGE INSULATED CASE/

    MOLDED CASE

  • 8/9/2019 Start Up Procedures Egypt

    18/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 11Circuit Breakers: Low Voltage Insulated Case/Molded Case May 2001

    2000-2001 Schneider Electric All Rights Reserved18

    1. Perform a contact-resistance test for Circuit breakers listed in

    Table 7 on page 63 in accordance with the following procedure.

    NOTE: The following procedure assumes the breaker is new, but may

    have carried some previous load current.

    (a) Completely de-energize the equipment.

    (b) Operate the circuit breaker manually on and off several times to

    ensure the mechanism linkages are free and operate properly. Trip

    the circuit breaker with the push to trip button if so equipped. Reset

    and turn the breaker back on. Repeat to ensure operability. If the

    circuit breaker does not trip, or if it does not reset after tripping, it must

    be replaced.

    (c) Measure the voltage drop across each pole or the resistance with a

    digital low-resistance ohmmeter.

    (d) Calculate the Resistance (if necessary) (Vdc drop/Idc rating current)

    (e) Compare the Resistance (calculated or reading) with the values listed

    in Table 7 on page 63.

    (f) If the value calculated or read is higher than the values listed in Table

    7 on page 63, repeat the process starting at (c) above operating the

    breaker several times. If high readings persist, recommend that thebreaker be replaced.

    2. Perform an insulation-resistance test at 1000 volts dc from pole-to-pole

    and from each pole-to-ground with breaker closed and across open

    contacts of each phase. Insulation resistance should be greater than 100

    Megohms.

    3. Perform adjustments for final settings in accordance with coordination

    study supplied by owner, if available.

    4. Verify correct operation of any auxiliary features such as trip and pickup

    indicators, electrical close and trip operation, trip-free, and anti pump

    function.

    5. If the circuit breaker contains a MICROLOGIC trip unit, perform the

    following tests:

    a. Make adjustments for the final settings in accordance with the

    coordination study supplied by the owner, if available.

    b. Determine the minimum pickup current by secondary current

    injection, using the manufacturers specified test device and

    procedures.

    c. Determine long-time delay by secondary current injection, using the

    manufacturers specified test device and procedures.

    d. Determine short-time pickup and delay by secondary current

    injection, using the manufacturers specified test device and

    procedures.

    e. Determine ground-fault pickup and delay by secondary current

    injection, using the manufacturers specified test device and

    procedures.f. Determine the instantaneous pickup value by secondary current

    injection, using the manufacturers specified test device and

    procedures.

    g. Activate auxiliary protective devices such as undervoltage relays, to

    ensure that shunt trip devices are operating. Check the operation of

    electrically operated breakers in their cubicles.

    h. Verify auxiliary features, such as trip and pickup indicator, electrical

    close and trip operation, trip-free, and antipump function are

    operating correctly.

  • 8/9/2019 Start Up Procedures Egypt

    19/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 11Circuit Breakers: Low Voltage Insulated Case/Molded Case

    19 2000-2001 Schneider Electric All Rights Reserved

    i. Check the electric charging mechanism, if applicable.

    C. Optional Tests

    1. Perform insulation-resistance tests in accordance with Table 2 on page

    59. Do not perform this test on wiring connected to solid-state

    components.

    2. Perform long-time delay time-current characteristic tests by passing 300

    percent rated current through each pole separately unless series testing

    is required to defeat ground fault functions.

    3. Determine short-time pickup and delay by primary current injection using

    the manufacturers current specified procedures. If the procedures are

    not available, set the pickup somewhere above minimum.

    4. Determine ground-fault pickup and time delay by primary current injection

    using the manufacturers current specified procedures. If the procedures

    are not available, set the pickup somewhere above minimum.

    5. Determine instantaneous pickup current by primary injection using run-

    up or pulse method, per the manufacturers current specified procedures.

    NOTE: Values of pickup and delay found should agree with the

    manufacturers specifications.

  • 8/9/2019 Start Up Procedures Egypt

    20/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 12Circuit Breakers: Low Voltage Power (ANSI/IEEE C37.13) May 2001

    2000-2001 Schneider Electric All Rights Reserved20

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications, if available.

    2. Inspect the physical and mechanical condition of the equipment.

    3. Confirm that lubricants have been correctly applied at the manufacturer'srecommended locations.

    4. Inspect anchorage, alignment, and grounding. Inspect arc chutes.

    Inspect moving and stationary contacts for condition and alignment.

    5. Verify that all maintenance devices are available for servicing and

    operating the breaker.

    6. Perform all mechanical operator and contact alignment tests on both the

    breaker and its operating mechanism.

    7. Using the calibrated torque-wrench method, verify that the tightness of

    accessible bolted bus connections is in accordance with the

    manufacturer's published data. If no manufacturer's data is available, use

    the values in Table 1 on page 57.

    8. Check cell fit and element alignment.

    9. Check the racking mechanism.

    10. Verify that the breaker is equipped with the correct rating plugs and

    current sensors.

    11. Verify that the breaker has the specified trip unit, LI, LS, LSI, and LSIG.

    12. Verify that the breaker has the specified accessories, such as Auxiliary

    Contacts, Cell Switches, Shunt Trip Devices, and Undervoltage Release.

    13. Verify that the Ground Fault System has been wired in accordance with

    the specified wiring diagram, and that the Sensor Grounds are either

    present or not present as specified.

    14. Verify that the secondary control plug/connections are in accordance with

    the wiring diagram and specifications.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with Switchgear industry

    standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Perform a contact-resistance test. For Type DS, DS II, DSL, and

    DSL II type circuit breakers, use the following procedure:

    (a) With the breaker de-energized, operate the breaker closed and open

    several times using either manual or electr ical means.(b) Apply a minimum current of 100 amperes dc through the closed

    contacts. If 100 A is not available, use the highest current available. If

    the device does not conform to the manufacturers specification,

    obtain equipment to perform the test at 100 A, or consult the factory

    with full information about the details of the test. If the continuous

    current rating is less than 100 A, then test at a level not to exceed the

    continuous current rating.

    (c) Measure the contact resistance of each pole and compare with the

    values listed in Table 8 on page 66.

    SECTION 12CIRCUIT BREAKERS:LOW VOLTAGE POWER (ANSI/IEEE

    C37.13)

  • 8/9/2019 Start Up Procedures Egypt

    21/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 12Circuit Breakers: Low Voltage Power (ANSI/IEEE C37.13)

    21 2000-2001 Schneider Electric All Rights Reserved

    (d) If the resistance is below the value shown in Table 8 on page 66, the

    condition of the breaker contacts is considered suitable for service. If

    the resistance exceeds the value in Table 8, the contacts can be

    abraded lightly with Scotchbrite or crocus cloth to remove oxides or

    other contaminants. Excessive abrading of contacts should be

    avoided since the silver plating could be abraded away. Contact the

    factory if nominal values of resistance cannot be achieved.2. Perform an insulation-resistance test at 1000 volts dc from pole-to-pole

    and from each pole-to-ground, with the breaker closed and across open

    contacts of each phase. The minimum insulation resistance shall be in

    accordance with Table 2 on page 59.

    3. Make adjustments for the final settings in accordance with the

    coordination study supplied by the owner, if available.

    4. Determine the minimum pickup current by secondary current injection,

    using the manufacturers specified test device and procedures.

    5. Determine long-time delay by secondary current injection, using the

    manufacturers specified test device and procedures.

    6. Determine short-time pickup and delay by secondary current injection,

    using the manufacturers specified test device and procedures.

    7. Determine ground-fault pickup and delay by secondary current injection,

    using the manufacturers specified test device and procedures.

    8. Determine the instantaneous pickup value by secondary current

    injection, using the manufacturers specified test device and procedures.

    9. Activate auxiliary protective devices such as undervoltage relays, to

    ensure that shunt trip devices are operating. Check the operation of

    electrically operated breakers in their cubicles.

    10. Verify auxiliary features, such as trip and pickup indicator, electrical close

    and trip operation, trip-free, and antipump function are operating correctly.

    11. Check the electric charging mechanism, if applicable.

    C. Optional Testing

    1. Perform an insulation-resistance test in accordance with Table 2 on page59. Do not perform the test on wiring connected to solid-state

    components.

    2. Determine minimum pickup current by primary current injection, using the

    manufacturers specified procedures. If the procedures are not available,

    set the pickup somewhere above minimum.

    3. Determine long-time delay by primary current injection, using the

    manufacturers specified procedures. If the procedures are not available,

    set the delay somewhere above minimum.

    4. Determine short-time pickup and delay by primary current injection, using

    the manufacturers specified procedures. If the procedures are not

    available, set the pickup somewhere above minimum.

    5. Determine ground-fault pickup and delay by primary current injection,

    using the manufacturers specified procedures. If the procedures are not

    available, set the pickup somewhere above minimum.

    6. Determine instantaneous pickup value by primary current injection, using

    the manufacturers specified procedures. If the procedures are not

    available, set the pickup somewhere above minimum.

    7. Activate the Blown Fuse detector and confirm by attempting to close the

    breaker without reset.

    NOTE: The values of pickup and delay should agree with the manufacturers

    specifications.

  • 8/9/2019 Start Up Procedures Egypt

    22/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 13Circuit Breakers: Medium Voltage SF6 May 2001

    2000-2001 Schneider Electric All Rights Reserved22

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications, if available.

    2. Inspect the physical and mechanical condition of the breaker.

    3. Confirm that lubricants have been correctly applied at the manufacturer'srecommended locations.

    4. Inspect anchorage and grounding.

    5. Inspect and verify that adjustments of the mechanism are in accordance

    with the manufacturer's instructions.

    6. Check indicators for gas leaks in accordance with the manufacturer's

    instructions.

    7. Verify correct operation of all air and SF6 gas pressure switches, alarms

    and cutouts. (Note: For sealed interrupters, the pressure cannot be varied

    to change the state of pressure switches.)

    8. Slow the close/open breaker and check for binding.

    9. Use the calibrated torque wrench method to verify that the tightness of

    accessible bolted connections and/or cable connections are in

    accordance with the manufacturer's published data. If no manufacturer's

    data is available, use the values in Table 1 on page 57.

    10. Record as-found and as-left counter operations.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with the equipment standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Measure contact resistances using the following procedure:

    (a) Operate the breaker closed and open several. times.

    (b) Apply 100 amperes DC and measure the resistance of each pole. If

    100 A is not available, use the highest current available. If the device

    does not conform to the manufacturers specification, obtain

    equipment to perform the test at 100 A or consult the factory with full

    information about the details of the test. If the continuous current rating

    is less than 100 A, then test at a level not to exceed the continuous

    current rating.

    (c) If the measured resistance is greater than 2000 micro-ohms, consult

    the manufacturer

    2. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and

    across open poles in accordance with Table 2 on page 59.

    3. Perform a power frequency withstand test in accordance with the

    manufacturer's instructions. For circuit breakers, perform the

    test in accordance with Table 5 on page 61.

    4. Verify trip, close, trip-free, and antipump functions.

    5. Trip the circuit breaker by operating each protective device.

    SECTION 13CIRCUIT BREAKERS:MEDIUM VOLTAGE SF6

  • 8/9/2019 Start Up Procedures Egypt

    23/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 13Circuit Breakers: Medium Voltage SF6

    23 2000-2001 Schneider Electric All Rights Reserved

    C. Optional Tests

    1. Perform an insulation-resistance test on all control wiring in accordance

    with Table 2 on page 59. Do not perform this test on wiring connected to

    solid-state relays.

    2. Perform time-travel analysis using a travel distance timer.

    3. Perform dissipation-factor/power-factor tests on breaker and bushings oneach pole with the breaker open, and on each phase with the breaker

    closed.

    4. Perform a minimum pick-up voltage test on trip and close coils.

  • 8/9/2019 Start Up Procedures Egypt

    24/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 14Circuit Breakers: Medium Voltage Vacuum May 2001

    2000-2001 Schneider Electric All Rights Reserved24

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications, if available.

    2. Inspect physical and mechanical condition.

    3. Confirm that lubricants have been correctly applied at the manufacturer'srecommended locations.

    4. Inspect anchorage, alignment, and grounding.

    5. Perform all mechanical operational tests on both the circuit breaker and

    its operating mechanism.

    6. Measure critical distances, such as contact gap, as specified by the

    manufacturers service bulletin.

    7. Use the calibrated torque wrench method to verify that the tightness of

    accessible bolted connections and/or cable connections are in

    accordance with the manufacturer's published data. If no manufacturer's

    data is available, use the values in Table 1 on page 57.

    8. Record as-found and as-left operation counter readings.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with the equipment standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Perform a contact-resistance test in accordance with the following

    procedure:

    (a) Operate the breaker closed and open several times.

    (b) Apply 100 Amperes dc and measure the contact resistance of each

    pole. If 100 A is not available, use the highest current available. If thedevice does not conform to the manufacturers specification, obtain

    equipment to perform the test at 100 A or consult the factory with full

    information about the details of the test. If the continuous current

    rating is less than 100 A, then test at a level not to exceed the

    continuous current rating.

    (c) Breaker pole units having a resistance exceeding 35 microhms shall

    be referred to the manufacturer for further evaluation.

    2. Verify the trip, close, trip-free, and antipump functions.

    3. Trip the circuit breaker by operating each protective device.

    4. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and

    across open circuit breaker separable contacts in accordance with Table

    2 on page 59.

    5. Perform a vacuum bottle integrity (over potential) test. Use an AC Hi-Pot

    across each vacuum bottle with the breaker in the open position, in strict

    accordance with manufacturer's instructions. For Metal-Clad Switchgear,

    apply the Maximum Test Voltage across the open gap in accordance with

    Table 5 on page 61 for a duration of one minute. Contact the manufacturer

    if repeated consistent breakdowns are encountered.

    SECTION 14CIRCUIT BREAKERS:MEDIUM VOLTAGE VACUUM

    HAZARD OF INJURY OR EQUIPMENT

    DAMAGE

    DC LIM Hi-Pot testing of vacuum breakers is

    not recommended.

    Read the label on the vacuum bottle forprecautions to take against the danger of x-

    ray emission while performing AC Hi-Pot

    testing.

    Failure to follow these instructions can

    result in injury or equipment damage.

    CAUTION

  • 8/9/2019 Start Up Procedures Egypt

    25/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 14Circuit Breakers: Medium Voltage Vacuum

    25 2000-2001 Schneider Electric All Rights Reserved

    C. Optional Testing

    1. Perform an insulation-resistance test on all control wiring in accordance

    with Table 2 on page 59. Do not perform this test on wiring connected to

    solid-state relays.

    2. Perform breaker travel and velocity analysis, using a travel distance timer.

    3. Perform minimum pickup voltage tests on trip and close coils.4. Perform dissipation-factor/power-factor tests on each pole with the

    breaker open, and on each phase with the breaker closed.

  • 8/9/2019 Start Up Procedures Egypt

    26/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 15Direct Current Systems: Batteries May 2001

    2000-2001 Schneider Electric All Rights Reserved26

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on the test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications.

    2. Inspect the physical and mechanical condition of the equipment.

    3. Use the calibrated torque wrench method to verify that the tightness ofaccessible bolted connections and/or cable connections are in

    accordance with the manufacturer's published data. If no manufacturer's

    data is available, use the values in Table 1 on page 57.

    4. Measure electrolyte specific gravity and temperature, and visually check

    the fill level.

    B. Electrical Tests

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Verify that all charger functions and alarms are operating properly.

    2. Measure each cell voltage and total battery voltage with the charger

    energized and in float mode of operation.

    C. Optional Tests

    1. Verify that flame arresters are present.

    2. Set the charger float and equalizing voltage levels.

    3. Perform a capacity load test in accordance with the manufacturer's

    specifications and ANSI/IEEE standards.

    ANSI/IEEE Std 450-1987. Recommended Practice for Maintenance,

    Testing and Replacement of Large Lead Storage Batteries for

    Generating Stations and Substations.

    ANSI/IEEE Std 1106-1987. Recommended Practice for

    Maintenance, Testing and Replacement of Nickel-Cadmium Storage

    Batteries for Generating Stations and Substations.

    SECTION 15DIRECT CURRENTSYSTEMS: BATTERIES

  • 8/9/2019 Start Up Procedures Egypt

    27/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 16Emergency Systems: Automatic Transfer Switches

    27 2000-2001 Schneider Electric All Rights Reserved

    A. Visual and Mechanical Inspection

    1. Compare equipment nameplate data with drawings and specifications.

    Verify that equipment nameplate ratings are in accordance with the final

    approved or record drawings and specifications.

    2. Inspect the physical and mechanical condition of the equipment.

    3. Confirm that lubricants have been correctly applied at the manufacturer'srecommended locations.

    4. Verify that manual transfer warnings are attached and visible.

    5. Verify tightness of all control connections.

    6. Use the calibrated torque wrench method to verify that the tightness of

    accessible bolted connections and/or cable connections are in

    accordance with the manufacturer's published data. If no manufacturer's

    data is available, use the values in Table 1 on page 57.

    7. Perform manual transfer operation.

    8. Verify positive mechanical interlocking between normal and alternate

    sources.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance with the equipment standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Measure contact-resistance.

    2. Perform insulation-resistance tests, phase-to-phase and phase-to-

    ground, with the switch in both source positions at the minimum dc test

    voltage appropriate for the equipments Maximum Rated Voltage, in

    accordance with Table 2 on page 59. Record the resistances.

    3. Verify the settings and operation of control devices.

    4. Calibrate and set all relays and timers in accordance with Section 25

    Protective Relays on page 43.

    5. Perform the following automatic transfer tests:

    (a) Simulate loss of normal power.

    (b) Return to normal power.

    (c) Simulate loss of emergency power.

    (d) Simulate all forms of single-phase conditions.

    6. Verify that the following functions have correct timing and are operating

    properly:

    (a) Normal source voltage-sensing relays

    (b) Engine start sequence(c) Time delay upon transfer

    (d) Alternate source voltage-sensing relays

    (e) Automatic transfer operation

    (f) Interlocks and limit switch function

    (g) Time delay and retransfer upon normal power restoration

    (h) Engine cool down and shutdown feature

    SECTION 16EMERGENCY SYSTEMS:AUTOMATIC TRANSFER SWITCHES

  • 8/9/2019 Start Up Procedures Egypt

    28/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 16Emergency Systems: Automatic Transfer Switches May 2001

    2000-2001 Schneider Electric All Rights Reserved28

    7. Verify that the mechanical power is removed from the generator in the

    event of a phase to phase or phase to ground fault between the generator

    and generator protection means (i.e., Circuit Breaker or Fuses).

  • 8/9/2019 Start Up Procedures Egypt

    29/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 17Ground-Fault Protection Systems

    29 2000-2001 Schneider Electric All Rights Reserved

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications, if available.

    2. Visually inspect the components for damage and errors in polarity or

    conductor routing.

    (a) Verify that the ground connection is made ahead of the neutral

    disconnect link, and on the line side of any ground fault sensor.

    NOTE: In some cases, Generator neutrals are also bonded to ground

    in a similar fashion as service entrance bonds are used for

    commercial power connections. In these cases, neutral sensors are

    used in the bond connection and differentially connected within the

    Ground Fault detection system.

    (b) Verify that proper polarity exists for both primary and secondary

    connectors to the neutral sensors.

    (c) Verify that all phase conductors and the neutral pass through the

    sensor in the same direction for zero sequence systems.

    (d) Verify that grounding conductors do not pass through zero sequence

    sensors.(e) Verify that the grounded conductor (usually Neutral) is bonded to ground

    in accordance with the power system specifications. Bonding to ground

    is permitted at the service entrance only with the exception of double

    ended systems with a single center bond and/ or on the secondary of a

    separately derived power systems including generators. Power systems

    may have multiple service entrances and multiple bonding at the

    multiple service entrances. Bonding to ground is not permitted

    downstream of the service and separately derived equipment.

    NOTE: Refer to the special operating and testing instructions

    supplied with the equipment, if available.

    3. Verify tightness of all electrical connections, including control circuits.

    4. Verify correct operation of all functions of the self-test panel.

    5. Verify that the control power transformer has adequate capacity for the system.

    6. Set pickup and time-delay settings in accordance with the settings

    provided in the owner's specifications.

    B. Electrical Tests

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Measure the system neutral-to-ground insulation resistance with the

    neutral disconnect link temporarily removed. Replace the neutral

    disconnect link after testing.

    2. For a system: that involves only one source; is a ground fault protection

    system that uses a zero phase sequence sensor that encompasses allphase and neutral conductors; and has a test winding within the zero

    phase sequence sensor, test by injecting test current in the test winding,

    as long as the sensor is not differentially connected with another sensor.

    Such systems are typically used with fused switch systems, but are

    occassionally used with circuit breaker systems where the internal

    breaker GF protection system is not used. In this case, a primary current

    injection test method need not be used. The test is a self test that uses a

    feature integral to the unit. If instructions are not provided, use the

    technique in step 3 below.

    SECTION 17GROUND-FAULTPROTECTION SYSTEMS

  • 8/9/2019 Start Up Procedures Egypt

    30/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 17Ground-Fault Protection Systems May 2001

    2000-2001 Schneider Electric All Rights Reserved30

    3. For systems involving multiple sources or multiple levels of ground fault

    protection, perform the following pickup tests using primary current

    injection techniques. These tests shall be performed on each

    independent bus, with test current applied from each possible source.

    Example: If a power system consists of a Main, Tie, Main, and one

    generator breaker on one side, this system would contain three

    independent buses: the bus between the first Main and Tie; the busbetween the Tie and the second Main; and the bus (or conductors)

    between the generator circuit breaker and generator. Test current would

    be injected on the source side of each Main and from the generator

    terminals. A grounding test lead would then be connected between each

    of the defined bus locations and ground.

    Check the manufacturers records for special testing procedures that

    would be applicable for the particular system being tested.

    (a) Verify that the relay does not operate at 90 percent of the pickup setting.

    (b) Verify that pickup is less than 125 percent of setting, or 1200 amperes,

    whichever is smaller.

    4. For summation type systems utilizing phase and neutral current

    transformers, verify that polarities are correct by applying current to each

    phase-neutral current transformer pair. This test also applies to molded-case breakers using an external neutral current transformer.

    (a) The relay should operate when the current direction is the same

    relative to polarity marks in the two current transformers.

    (b) The relay should not operate when the current direction is opposite

    relative to polarity marks in the two current transformers.

    5. Verify non-tripping activity by applying primary current injection testing

    techniques as in number 2 above. Current setting for this test shall be

    above 125 of the relay pickup setting. The test cable would be connected

    between a phase conductor and the Neutral for that section of the gear.

    This test shall be repeated for each condition as was determined in

    number 2 above.

    6. Verify that zone selective interlock systems are operating correctly.

    Source breakers to an independent bus should receive a restraint signalwhen a ground fault is detected by a lower stream device. Complex

    systems having multiple sources and tie breakers should operate in a

    logical manner as is determined by the power system involved.

    Example: For a Main, Tie, Main system, a restraint signal emanating from

    a feeder breaker should not restrain the Main breaker on the opposite

    side, unless that Main is the only means of protecting the bus to which

    that feeder breaker is connected.

    Since there are many different types of Ground Fault systemsElegant,

    Non-Elegant, relayed tie, or non-relayed tieit is not practical to set down

    one rule of operation. Each system must be evaluated on its own merit,

    and a logical operation must be determined for each. It is suggested that

    the project engineer be consulted in determining the correct operation.

    C. Optional Tests

    1. Measure the insulation resistance of the control wiring in accordance with

    Table 2 on page 59. Do not perform tests on wir ing connected to solid-

    state relays.

    2. Measure the time delay of the relay at 150 percent or greater of pickup.

    Verify operability of I2t function, if being used, of the ground fault trip device.

    3. Verify reduced control voltage tripping capability: 55 percent for ac systems.

  • 8/9/2019 Start Up Procedures Egypt

    31/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 18Ground Resistors

    31 2000-2001 Schneider Electric All Rights Reserved

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on the test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and coordination study, if available.

    2. Inspect the physical and mechanical condition of the equipment.

    3. Verify that any shipping bracing, brackets, or fixtures are removed afterfinal placement.

    4. Use the calibrated torque wrench method to verify that the tightness of

    accessible bolted connections and/or cable connections are in

    accordance with the manufacturer's published data. If no manufacturer's

    data is available, use the values in Table 1 on page 57.

    5. Verify that all frame and enclosure grounds are correct.

    6. Verify that tap connections are as specified, if applicable.

    7. Perform a visual and mechanical inspection on all secondary wiring and

    instrument transformers per the manufacturers installation and operating

    procedures.

    B. Electrical Tests

    1. Perform an instrument transformer polarity check.

    2. Perform insulation resistance tests on each instrument transformer, each

    winding to ground at 500 volts dc. Do not perform this test on solid state

    devices. Resistance readings should be consistent with Table 2 on page

    59 for test voltages of 500 volts dc.

    3. Test all electrical controls (relays, lights, switches) to verify that they are

    operating properly.

    SECTION 18GROUND RESISTORS

  • 8/9/2019 Start Up Procedures Egypt

    32/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 19Grounding Systems May 2001

    2000-2001 Schneider Electric All Rights Reserved32

    A. Visual and Mechanical Inspection

    Verify that the ground system is in compliance with drawings and

    specifications.

    B. Electrical Tests

    NOTE: When performing dielectric tests, you must disconnect all Instrument

    and Control Transformers, Arresters, TVSS units, and other sensitive

    electronic equipment that may cause erroneous results or cause damage to

    equipment that is not rated in accordance industry standards.

    Verify the proper selection and operation of the electrical test equipment.

    Record the date of the last calibration date and the date re-calibration is due.

    1. Perform a fall-of-potential test or alternative in accordance with IEEE

    Standard 81-1991 on the main grounding electrode or system.

    2. Perform point-to-point tests to determine the resistance between the

    main grounding system and all major electrical equipment frames,

    system neutral, and/or derived neutral points.

    SECTION 19GROUNDING SYSTEMS

  • 8/9/2019 Start Up Procedures Egypt

    33/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 20Isolated Power Systems

    33 2000-2001 Schneider Electric All Rights Reserved

    NOTE: All equipment shall be assured to be complete

    and of acceptable quality. Inspection and testing of all applicable wiring and

    equipment must conform to Article 517 of the National Electrical Code (NEC)

    and Article 99 of the National Fire Protection Association (NFPA).

    A. Visual and Mechanical Inspection

    1. Perform a functional check of all equipment in the area.

    2. Inspect all equipment in the area for physical damage such as

    cracked meters or scratches. Any physical or electrical defect must be

    recorded and discussed with the appropriate people at the job site. If the

    damage appears to have occurred at the job site, note this on your report.

    3. Inspect the room ground and the patient reference ground if installed.

    4. Remove the stainless steel trim and the circuit breaker dead front.

    Examine the branch circuit wiring.

    5. Verify that the proper breaker identification is on the circuit schedule.

    6. Examine the receptacles, ground jacks, lights, switches, and

    miscellaneous electrical equipment for compliance to applicable

    electrical codes.

    B. Electrical Tests

    1. Measure line-to-line and line-to-ground voltage with an ac voltmeter and

    record the voltage on the data sheet.

    2. Measure the leakage current with an ac microammeter that is capable of

    being accurate within 3%. Record the value to three significant figures.

    Measure the current between L1 and ground and L2 and ground.

    NOTE: Before taking current measurements, verify that no phase

    conductor is at ground potential.

    3. Use the following formulas to determine the individual line impedance

    based on the values calculated in step 2 and line-to-line voltage

    measurement:

    Line impedance measurements will include all receptacles, but are not

    required to include lighting fixtures or components of fixtures. All

    electrical equipment connected to the isolated power system must be

    unplugged, and permanently installed equipment must be switched off.

    For isolation panels with branch-circuit interlock (x-ray panels), branch

    circuits must be measured individually. Record the circuit with the lowestcalculated impedance as the system impedance.

    For panels in which a combination of circuits may be energized (PLC

    laser panels), measure branch circuits individually; energize the

    combination of circuits that contributes the highest amount of leakage

    current. This value is used to calculate the system impedance.

    If a line impedance is below 200,000 ohms (NFPA-99 1996, 3-3.2.2.2),

    the probable cause should be determined. If you cannot correct the

    problem at this time, you must note it on the report.

    SECTION 20ISOLATED POWER

    SYSTEMS

    Z(L1 to GD) = V(L1 to L2)I(L2 to GD)

    Z(L2 to GD) = V(L1 to L2)I(L1 to GD)

  • 8/9/2019 Start Up Procedures Egypt

    34/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 20Isolated Power Systems May 2001

    2000-2001 Schneider Electric All Rights Reserved34

    4. Line Isolation Monitor (LIM) Calibration Tests: Determine the exact trip

    point of the LIM by slowly lowering the impedance between each isolated

    conductor and ground until the LIM goes into an alarm condition, and

    then measure the total hazard current with an ac milliammeter.

    Apply the following test faults between the isolated conductors and

    ground:

    Single resistive L1 to ground

    Single resistive L2 to ground

    Single resistive L3 to ground (three-phase systems)

    Balanced resistive L1 to ground and L2 to ground (one-phase systems

    only)

    Single capacitive L1 to ground

    Single capacitive L2 to ground

    Single capacitive L3 to ground (three-phase systems)

    Balanced capacitive L1 to ground (one-phase systems only)

    NOTE: The correct trip point of a 2 mA ISO-GARD (series D) LIM is

    1.95 mA, +0.15 mA. The correct trip point of a 5 mA ISO-GARD

    (series D) LIM is 4.85 mA, +0.25 mA.5. In patient care areas, determine the effectiveness of the equipment

    grounding system by using voltage and impedance measurements. Take

    these measurements with respect to a reference grounding point such as

    the ground bus in the isolation panel.

    Take voltage measurements between the reference point and the

    exposed conductive surfaces (including ground contacts of receptacles)

    in the patient care vicinity.

    NOTE: The voltage limit for new construction is 20mV.

    Take impedance measurements between the reference point and the

    grounding contact of each receptacle in the patient vicinity.

    NOTE: The impedance limit for new construction is 0.1 ohms.

    The grounding terminals of all receptacles and the conductive surfaces offixed equipment, operating at over 100 volts, must be grounded by a

    conductor sized in accordance with NEC.

    NOTE: Conductive surfaces in the patient area that arenot likely to

    become energized(such as windows, door frames, and towel

    dispensers) need not be intentionally grounded or tested. Ref: NFPA-99,

    3-3.3.2.1

    C. Hospital Staff Instruction

    Provide a thorough explanation of the isolated power systems to the

    appropriate hospital personnel. The instruction should include the following

    points:

    Basic theory of isolated power Advantages of isolated power systems versus grounded power systems

    Purpose of the Line Isolation Monitor

    Proper use of the grounding jacks

    Basic troubleshooting techniques

    Required periodic testing and record keeping

  • 8/9/2019 Start Up Procedures Egypt

    35/66

    Bulletin No. 0180IB0001R5/01 Procedures for Startup and Commissioning of Electrical Equipment

    May 2001 Section 20Isolated Power Systems

    35 2000-2001 Schneider Electric All Rights Reserved

    D. Formal Customer Report

    Provide a report of the test results to the customer within two weeks. The

    report must include the following:

    A list of the isolation panels and areas that were tested

    Any code violations that were revealed by the testing and inspection

    Recommendations for corrections of any code violations

    A list of any damaged equipment. Note if these items will be replaced

    under warranty.

    Individual data sheets for the isolated power systems

    A logbook with initial hazard current readings of the isolated systems

  • 8/9/2019 Start Up Procedures Egypt

    36/66

    Procedures for Startup and Commissioning of Electrical Equipment Bulletin No. 018IB0001R5/01

    Section 21Motor Control Centers: Low and Medium Voltage May 2001

    2000-2001 Schneider Electric All Rights Reserved36

    A. Visual and Mechanical Inspection

    1. Document equipment nameplate data on test report. Verify that

    equipment nameplate ratings are in accordance with the final approved

    or record drawings and specifications.

    2. Inspect the physical, electrical, and mechanical condition of structure and

    all electrical components.

    3. Confirm that lubricants have been correctly applied at the manufacturer's

    recommended locations.

    4. Verify appropriate anchorage, required area clearances, physical

    damage, and correct alignment and cleanliness.

    5. Inspect all doors, panels, and sections for paint, dents, scratches, fit, and

    missing hardware.

    6. Verify that fuse and/or circuit breaker sizes and types correspond to

    drawings and coordination study, if available, as well as to the circuit

    breaker's address for microprocessor-communication packages.

    7. Verify that current and potential transformer ratios correspond to

    drawings.

    8. Use the calibrated torque wrench method to verify that the tightness of

    accessible bolted connections and/or cable connections are inaccordance with the manufacturer's published data. If no manufacturer's

    data is available, use the values in Table 1 on page 57.

    9. Confirm correct operation and sequencing of electrical and mechanical

    interlock systems.

    (a) Attempt closure on locked-open devices. Attempt to open locked-

    closed devices.

    (b) Make key exchange with devices operated in off-normal positions.

    10. Inspect insulators for evidence of physical damage or contaminated

    surfaces.

    11. Verify correct barrier and shutter installation and operation.

    12. Exercise all active components.

    13. Verify that filters are in place and/or vents are clear.

    14. Test the operation, alignment, and penetration of instrument transformer

    withdrawal disconnects, current carrying and grounding, in accordance

    with Section 32Transformers, Instrument on page 53.

    15. Inspect control power transformers.

    (a) Inspect for physical damage, such as cracked insulation, broken

    leads, tightness of connections, defective wiring, and overall general

    condition.

    (b) Verify that primary and s