Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Stantec Consulting Ltd 207-201 Churchill Drive Membertou NS B1S 0H1 Tel: (902) 564-1855 Fax: (902) 564-8756
February 13, 2012 File: 121410955.245
Sydney Tar Ponds Agency 1 Inglis Street PO Box 1028, Stn. A Sydney, NS B1P 6J7
Attention: Ms. Diane Ingraham, PhD., PMP, Quality Contracts Manager
Dear Ms. Ingraham:
Reference: STPA Project Element CO6A – Coke Ovens Capping Independent Quality Assurance (IQAC) November 2011 Monthly Summary Report
At the request of Sydney Tar Ponds Agency (STPA), Stantec Consulting Ltd (Stantec) has completed the following quality assurance inspection/testing services and meetings in accordance with project requirements at the above mentioned site between October 1 and November 30, 2011:
• Project Item PM-01: Eight daily field reports. • Project Item PM-02: One monthly QA report (November 2011) completed in the month of February
2012.
• Project Item PM-04: Two site meetings were attended by Stantec in the month of November 2011.
• Project Item PM-05: Other meetings and frequent opinions were provided in the month of November 2011.
• Project Item PM-10: One weekly quality QC/QA meeting was attended by Stantec in the month of November 2011.
• Project Item PM-19: Review of and data entry into CO6A September 2011 QC/QA testing summary tables.
• Project Item QCP-02: Submittal reviews (Review of November 2011 QC report including daily/test reports).
• Project Item QCP-05: Performed visual field inspections during the placement cohesive backfill soil.
• Project Item TS-20: Completed two site visits on November 3 and 9, 2011 to assess the compaction of placed cohesive backfill soil layers (6 measurements). All measured compactions of the placed soil met the specified 95% minimum compaction criterion. The test results are included in this monthly report and summarized in the QC-QA summary table section.
• Project Items TS09, TS21 and Extras: Completed two site visits on November 17 and 24, 2011 for the purpose of testing grout batches and preparation of compressive strength samples out of them (Set 1 and Set 2, each of 9 cubes). Later in December 2011, the compressive strength test results met the specified 28 Day strength criterion. All test results are included in this monthly report and summarized in the QC-QA summary table section.
• Project Item ENV-T-01: One noise monitoring event. Noise levels were within the guidelines at two of the three monitoring locations. See the Monthly Noise QA Testing Summary Table provided in this report for further information.
February 1Ms. Diane Page 2 of 2
Reference
• Projecwere
We trust thesitate to
Sincerely,
STANTEC
Rabi MoreGeotechnrabi.morellyv:\1214\active\12
3, 2012 Ingraham, PhD2
e: STPA ProjeIndepende
ct Item ENV-Twithin the acc
this informatioo contact us.
,
C CONSULTI
elly, M.Sc., Pnical and [email protected]\121410955
D., PMP, Qualit
ect Element Cnt Quality Ass
T-02: Four suceptable rang
on meets you
ING LTD
.Eng. erials Quality m -stpa combined eleme
ty Contracts M
CO6A – Coke Osurance (IQAC
urface water (tge.
r present req
Lead
ents\245 co6a\300 rep
anager
Ovens CappinC) November 2
turbidity) sam
uirements. If
porting\qa reports\co6a
g 2011 Monthly
mpling events.
you have any
Willie McProject Mwillie.mcne
a november 2011 qa m
Summary Rep
. All measure
y questions, p
cNeil, B.Tech.Manager
[email protected] report_rm_tm
port
ments record
please do not
(Env.), CET
om .docx
ded
STPA PROJECT ELEMENT CO6A: COKE OVENS SURFACE CAP
IQAC SITE TESTING SUMMARY Page 1 of 1
Date: November 3, 2011 IQAC On‐Site Rep: Enzo Poloni
Relevant Project Specification(s)
Environmental Quality Assurance
Relevant Project Specification(s) No.
QA‐EPP Project No. 121410955.245
IQAC Item No(s) / Descriptions
ENV‐T‐02 Time On‐Site: 15:00
Weather: Partly Cloudy, 7°C
Area Tested/Inspected: CO6A – Coke Oven Brook Up/Down Stream
Inspection / Testing SummaryStantec on site for 15:00 meeting Tanya Young (QC Representative) who was replaced by Devon Abbass (QC Representative) for this sampling. Sampling began downstream (ESE‐2) and then upstream (ESE‐5). Activities noted as clay infill, moving and compaction and pumping of 2 sub‐surface pipes on site. Samples analyzed at Stantec lab. Sample # GPS Co‐ordinates
(NAD 83 – Northing/Easting) General SiteDescription
Sample Results(NTU)
1 460 2732 511 3174
ESE‐5 (Upstream) 2.46
2 460 2055 511 2960
ESE‐2(Down stream) 1.23
As stated in the Environmental Protection Plan – “The upper level criteria defined as a reportable event for turbidity will be 110% of background, when background (upstream sample location) is greater than or equal to 80 Nephelometric Turbidity Units (NTU). When background is less than 80NTU, a reportable event will be greater than an increase of 8NTU above background” Turbidity values recorded above are within acceptable levels.
IQAC Review and Acceptance
IQAC On‐Site Rep (Sign/Print/Date):
/Enzo Poloni, B.Tech. (Env)
IQAC Management Review (Sign/Print/Date):
/Tanya MacDonald, B.Tech.(Env), AScT
November 3, 2011 November 4, 2011
STPA PROJECT ELEMENT CO6A: COKE OVENS SURFACE CAP
IQAC SITE TESTING SUMMARY Page 1 of 1
Date: November 10, 2011 IQAC On‐Site Rep: Enzo Poloni
Relevant Project Specification(s)
Environmental Quality Assurance
Relevant Project Specification(s) No.
QA‐EPP Project No. 121410955.245
IQAC Item No(s) / Descriptions
ENV‐T‐02 Time On‐Site: 14:55
Weather: Partly Cloudy, 7°C
Area Tested/Inspected: CO6A – Coke Oven Brook Up/Down Stream
Inspection / Testing SummaryStantec onsite at 14:55. Tanya Young (QC representative). Sampling began with downstream (ESE‐2) then upstream (ESE‐5). Clay trucking, leveling and rolling noted as activities at the time. Samples analyzed at Stantec lab. Sample # GPS Co‐ordinates
(NAD 83 – Northing/Easting) General SiteDescription
Sample Results(NTU)
1 460 2732 511 3174
ESE‐5 (Upstream) 2.34
2 460 2055 511 2960
ESE‐2(Down stream) 0.98
As stated in the Environmental Protection Plan – “The upper level criteria defined as a reportable event for turbidity will be 110% of background, when background (upstream sample location) is greater than or equal to 80 Nephelometric Turbidity Units (NTU). When background is less than 80NTU, a reportable event will be greater than an increase of 8NTU above background” Turbidity values recorded above are within acceptable levels.
IQAC Review and Acceptance
IQAC On‐Site Rep (Sign/Print/Date):
/Enzo Poloni, B.Tech. (Env)
IQAC Management Review (Sign/Print/Date):
/Tanya MacDonald, B.Tech.(Env), AScT
November 10, 2011 November 14, 2011
STPA PROJECT ELEMENT CO6A: COKE OVENS SURFACE CAP
IQAC SITE TESTING SUMMARY Page 1 of 1
Date: November 16, 2011 IQAC On‐Site Rep: Enzo Poloni
Relevant Project Specification(s)
Environmental Quality Assurance
Relevant Project Specification(s) No.
QA‐EPP Project No. 121410955.245
IQAC Item No(s) / Descriptions
ENV‐T‐02 Time On‐Site: 11:15
Weather: Clear, 10°C
Area Tested/Inspected: CO6A – Coke Oven Brook Up/Down Stream
Inspection / Testing SummaryStantec met with Devon Abbass (QC representative) at 11:15am. Sampling began with downstream (ESE‐2) and then upstream (ESE‐5). Activities noted on site as slag laydown, leveling, and compaction on site road parallel to SPAR and sod placement along embankment at lower Coke Oven Brook. Samples analyzed at Stantec lab. Sample # GPS Co‐ordinates
(NAD 83 – Northing/Easting) General SiteDescription
Sample Results(NTU)
1 460 2731 511 3168
ESE‐5 (Upstream) 2.47
2 460 2056 511 2953
ESE‐2(Downstream) 1.28
As stated in the Environmental Protection Plan – “The upper level criteria defined as a reportable event for turbidity will be 110% of background, when background (upstream sample location) is greater than or equal to 80 Nephelometric Turbidity Units (NTU). When background is less than 80NTU, a reportable event will be greater than an increase of 8NTU above background” Turbidity values recorded above are within acceptable levels.
IQAC Review and Acceptance
IQAC On‐Site Rep (Sign/Print/Date):
/Enzo Poloni, B.Tech. (Env)
IQAC Management Review (Sign/Print/Date):
/Tanya MacDonald, B.Tech.(Env), AScT
November 16, 2011 November 17, 2011
STPA PROJECT ELEMENT CO6A: COKE OVENS SURFACE CAP
IQAC SITE TESTING SUMMARY Page 1 of 1
Date: November 24, 2011 IQAC On‐Site Rep: Enzo Poloni
Relevant Project Specification(s)
Environmental Quality Assurance
Relevant Project Specification(s) No.
QA‐EPP Project No. 121410955.245
IQAC Item No(s) / Descriptions
ENV‐T‐02 Time On‐Site: 11:04
Weather: Cloudy, ‐1°C/‐5°C
Area Tested/Inspected: CO6A – Coke Oven Brook Up/Down Stream
Inspection / Testing SummaryMet onsite with Devon Abbass at 11:04 and sampling began immediately with ESE‐2 (downstream) and then ESE‐5 (upstream). No major activities noted by QC, except for the grouting of a pit (mid site). Samples analyzed at Stantec lab. Sample # GPS Co‐ordinates
(NAD 83 – Northing/Easting) General SiteDescription
Sample Results(NTU)
1 460 2056 511 2961
ESE‐5 (Upstream) 2.91
2 460 2735 511 3172
ESE‐2(Downstream) 1.57
As stated in the Environmental Protection Plan – “The upper level criteria defined as a reportable event for turbidity will be 110% of background, when background (upstream sample location) is greater than or equal to 80 Nephelometric Turbidity Units (NTU). When background is less than 80NTU, a reportable event will be greater than an increase of 8NTU above background” Turbidity values recorded above are within acceptable levels.
IQAC Review and Acceptance
IQAC On‐Site Rep (Sign/Print/Date):
/Enzo Poloni, B.Tech. (Env)
IQAC Management Review (Sign/Print/Date):
/Tanya MacDonald, B.Tech.(Env), AScT
November 24, 2011 November 25, 2011
CONCRETETEST REPORT
Stantec Consulting Ltd207-201 Churchill Drive, Membertou, NS B1S 0H1
(TEL) 902-564-1855 (FAX) 902-564-8756
CERTIFIED LABORATORYFOR TESTING CONCRETE
On Site Inspection By Derek Corbett.
PROJECT
CLIENT
C.C.
1410955.245
Sydney Tar Ponds Agency
Sydney Tar Ponds Agency
C/O Sydney Tar Ponds Agency
1 Inglis Street, PO Box 1028
Sydney, NS
B1P 6J7
ATTN: Ms. Diane Ingraham
Sydney Tar Ponds Sydney Tar PondsSydney
1 6 2011.Nov.18 2011.Nov.17
TO
PROJECT
SET NO. NO. OF DATE DATE
SPCMNO.
DATETESTED
AGEAT
TEST(DAYS)
SPECIFIED STRENGTH DAYS CONCRETE
AIR TEMPERATURE
MAXIMUM SIZE AGGREGATE
CEMENT TYPE SLUMP
AIR %
SPEC.
SPEC. ±
±
BATCH TIME
CAST TIME
CAST BYADMIXTURES
CURING CONDITIONS
INITIAL CURING TEMP:MAXIMUM MINIMUM
LOCATION
SUPPLIER
TRUCK NO.
LOAD VOL.
WATER ADDED
COMMENTS
TICKET NO.
3 CUM. VOL. 3
AUTH. BY
PER.
A Nov.24 7 50.0x 50.0 50.0 6.5 2.6
Nov.24 7 50.0x 50.0 50.0 5.9 2.4
Nov.24 7 50.0x 50.0 50.0 7.4 3.0
Dec.15 28 50.0x 50.0 50.0 11.9 4.8
Dec.15 28 50.0x 50.0 50.0 13.2 5.3
Dec.15 28 50.0x 50.0 50.0 11.8 4.7
B
C
D
E
F
3 28
GU
20
09:02
14.0
PLASTIC
Quality Concrete - Sydn
QS44 78988
4.6 4.6
N/A
Page 1 of 1 2011.Dec.20
7.0
SYD DC
Coke Oven gasline between points 1 and 2.
20.0 20.0
Element CO6A
AVERAGEDIAMETER (mm)
ORSIDE (mm x mm)
AVERAGELENGTH ORSPAN (mm)
MAXIMUMLOAD(kN)
COMPRESSIVEOR FLEXURAL
STRENGTH(MPa) Average
°C
°C
mm
mm
MPa @
°C°C
m m
l
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on written request.
Stantec Consulting Ltd
MOULD TYPE
TREND GRAPH
2.6
4.9
FAILURETYPE
SPECIMENTYPE
Cube Lab
CURECONDN
Lab
Cube
Cube
Cube
Cube
Cube
Lab
Lab
Lab
Lab
CONCRETETEST REPORT
Stantec Consulting Ltd207-201 Churchill Drive, Membertou, NS B1S 0H1
(TEL) 902-564-1855 (FAX) 902-564-8756
CERTIFIED LABORATORYFOR TESTING CONCRETE
On Site Inspection By Derek Corbett.
PROJECT
CLIENT
C.C.
1410955.245
Sydney Tar Ponds Agency
Sydney Tar Ponds Agency
C/O Sydney Tar Ponds Agency
1 Inglis Street, PO Box 1028
Sydney, NS
B1P 6J7
ATTN: Ms. Diane Ingraham
Sydney Tar Ponds Sydney Tar PondsSydney
2 6 2011.Nov.25 2011.Nov.24
TO
PROJECT
SET NO. NO. OF DATE DATE
SPCMNO.
DATETESTED
AGEAT
TEST(DAYS)
SPECIFIED STRENGTH DAYS CONCRETE
AIR TEMPERATURE
MAXIMUM SIZE AGGREGATE
CEMENT TYPE SLUMP
AIR %
SPEC.
SPEC. ±
±
BATCH TIME
CAST TIME
CAST BYADMIXTURES
CURING CONDITIONS
INITIAL CURING TEMP:MAXIMUM MINIMUM
LOCATION
SUPPLIER
TRUCK NO.
LOAD VOL.
WATER ADDED
COMMENTS
TICKET NO.
3 CUM. VOL. 3
AUTH. BY
PER.
A Dec.01 7 50.0x 50.0 50.0 18.0 7.2
Dec.01 7 50.0x 50.0 50.0 17.1 6.8
Dec.01 7 50.0x 50.0 50.0 17.1 6.8
Dec.22 28 50.0x 50.0 50.0 29.9 12.0
Dec.22 28 50.0x 50.0 50.0 30.1 12.0
Dec.22 28 50.0x 50.0 50.0 29.7 11.9
B
C
D
E
F
3 28
GU
20
08:29
15.0
09:40PLASTIC
Quality Concrete - Sydn
QS43 79116
5.4 5.4
N/A
Page 1 of 1 2012.Jan.05
0.0
SYD DC
Gasline between points 5 and 6.
20.0 20.0
Element CO6A
AVERAGEDIAMETER (mm)
ORSIDE (mm x mm)
AVERAGELENGTH ORSPAN (mm)
MAXIMUMLOAD(kN)
COMPRESSIVEOR FLEXURAL
STRENGTH(MPa) Average
°C
°C
mm
mm
MPa @
°C°C
m m
l
Reporting of these test results constitutes a testing service only. Engineering interpretation or evaluation of test results is provided only on written request.
Stantec Consulting Ltd
MOULD TYPE
TREND GRAPH
7.0
12.0
FAILURETYPE
SPECIMENTYPE
Cube Lab
CURECONDN
Lab
Cube
Cube
Cube
Cube
Cube
Lab
Lab
Lab
Lab
PROJECT: 121410955.245
COMPACTION SPECIFICATION SAMPLED FROM
PROCTOR TYPE 2073.0 kg/m3 OPTIMUM MOISTURE
TESTED BY GAUGE SERIAL #
DRY MOISTUREDENSITY CONTENT
(kg/m³) (%)
3‐Nov‐2011 1st lift 2022.7 10.7 200
1st lift 2106.4 10.1 200
1st lift 2051.7 9.1 200
Note: A compaction test only provides data for the specific test location and to a depth of up to 300 mm below the surface at the time of the test.Total approval of a fill project requires continuous inspection and a brief report written by a geotechnical engineer.
CHECKED BY: DATE:Rabi Morelly 3-Nov-11
3 5113217, 4602532 99.0
The measured percent compactions met the requirements of the project specifications (Minimum 95%).
PROBEDEPTH (mm)
REMARKS(%)
1 5113170, 4602561 97.6
2 5113216, 4602585 101.6
Derek Corbett DATE 3-Nov-11 14630
FIELD TEST DATA
DATE TEST NO.
TEST LOCATIONS(Northing, Easting)
APPROX.ELEVATION
PROCTOR
MATERIAL AND PROCTOR DATA
95% MATERIAL TYPE Cohesive Backfill Keltic Drive Pit
STD MAX. DRY DENSITY 10.6%
207‐200 Churchill DrMembertou, NS B1S 0H1Ph: (902) 564‐1855Fx: (902) 564‐8756
SOILS COMPACTION REPORT
CLIENT: Sydney Tar Ponds Agency CO6A - Coke Ovens Surface Cap PROJECT NO:
PROJECT: 121410955.245
COMPACTION SPECIFICATION SAMPLED FROM
PROCTOR TYPE 2073.0 kg/m3 OPTIMUM MOISTURE
TESTED BY GAUGE SERIAL #
DRY MOISTUREDENSITY CONTENT
(kg/m³) (%)
9‐Nov‐2011 Grade 2100.0 8.6 200
Grade 2012.0 9.8 200
Grade 2095.0 9.8 200
Note: A compaction test only provides data for the specific test location and to a depth of up to 300 mm below the surface at the time of the test.Total approval of a fill project requires continuous inspection and a brief report written by a geotechnical engineer.
CHECKED BY: DATE:Rabi Morelly 9-Nov-11
3 5113193, 4602688 101.1
PROBEDEPTH (mm)
REMARKS(%)
1 5113222, 4602498 101.3The measured percent compactions met the requirements of the project specifications (Minimum 95%).
2 5113188, 4602551 97.1
Derek Corbett DATE 9-Nov-11 16731
FIELD TEST DATA
DATE TEST NO.
TEST LOCATIONS(Northing, Easting)
APPROX.ELEVATION
PROCTOR
MATERIAL AND PROCTOR DATA
95% MATERIAL TYPE Cohesive Backfill Keltic Drive Pit
STD MAX. DRY DENSITY 10.6%
207‐200 Churchill DrMembertou, NS B1S 0H1Ph: (902) 564‐1855Fx: (902) 564‐8756
SOILS COMPACTION REPORT
CLIENT: Sydney Tar Ponds Agency CO6A - Coke Ovens Surface Cap PROJECT NO:
Contractor: DENKO Client: STPA Form Number: CO6A Noise November 2011Element: CO6A Oversight: AECOM/CBCL Project: Remediation of the Tar Ponds and Coke Ovens SitesMonth: November 2011 IQAC: Stantec
NOTES
EPP ENV-T-01 NoiseCBRM Noise By-
Law & NSE Criteria
once per month 21-Nov-11 <65 dBA CO6A-11-21-2011-0846-1050 460 2193511 3174 62.2dBA Pass Y Sample location is 20m South of SPAR in front of site trailer.
SPAR Traffic.
EPP ENV-T-01 NoiseCBRM Noise By-
Law & NSE Criteria
once per month 21-Nov-11 <65 dBA CO6A-11-21-2011-1055-1304 460 2126511 3049 57.2dBA Pass Y
Sample location is at West side fenceline where Coke Oven Brook meets North Aligned Channel (Adjacent to CO8
Treatment Plant). Victoria Road Traffic.
EPP ENV-T-01 NoiseCBRM Noise By-
Law & NSE Criteria
once per month 21-Nov-11 <65 dBA CO6A-11-21-2011-1313-1608 460 2547 511 3276 71.5dBA Fail Y
Sample location is 50 -100m East of Site Trailer along Site Boundry with SPAR. Spreading/Leveling topsoil. SPAR Traffic
contribuiting to elevation of noise levels. STPA notified immediately.
Activities onsite at the time of the sampling events included hay spreading on banks.
QAQA Pass/Fail
Monthly Noise QA Testing Summary Table
RESULTS
Spec Description Test Type QA Frequency
Met? Y/NQA Test ResultQA Sample ID CriteriaSample LocationGPS Coordinates
NAD 83
SPECIFIED REQUIREMENTS
Date CollectedQA Frequency Spec
Section Standard
November CO6A NOISE.xls Page 1 of 1
Stantec Consulting Ltd. 207-201 Churchill Drive Membertou, NS B1S 0H1 Tel: (902) 564-1855 Fax: (902) 564-8756
February 9, 2012 File: 121410955.245
Sydney Tar Ponds Agency 1 Inglis Street PO Box 1028, Stn. A Sydney, NS B1P 6J7
Attention: Ms. Diane Ingraham, Ph.D., PMP, Quality Contract Manager
Dear Ms. Ingraham:
Reference: Materials and Geotechnical Quality Assurance of Quality Control Program Element CO6A, Sydney Tar Ponds Project, Sydney, NS Review of Contractor’s November 2011 Quality Control (QC) Report
At the request of the Sydney Tar Ponds Agency (STPA), Stantec Consulting Ltd (Stantec), acting as the project Independent Quality Assurance Consultant (IQAC), has completed a Quality Assurance Review of the Contractor’s (DENKO Mi’kmaq Enterprises LTD, and their quality control consultant (exp Services Inc. (exp)) Monthly Quality Control (QC) Report for the month of November 2011 for project Element CO6A.
Comments are prepared using a three tier system as requested by the STPA:
Level 1 - Critical comments which need to be addressed promptly. The IQAC requests responses on any critical comments within one week.
Level 2 - Comments for which a response is required. All comments for which a response is required should be responded to in the form of a written response or by providing the necessary information as requested.
Level 3 - Comments that would improve the quality of the work but for which the agency need not respond to.
Based on our review of the QC information provided from the referenced period, the IQAC offers the following comments for your considerations:
Level 2 Manufacturer quality control test certificates of installed HDPE liners in September 2011 are still not included in this monthly QC report. Also, the IQAC was not notified of these installations.
Level 2 Manufacturer quality control test certificates of installed geotextiles in November 2011 are not included in this monthly QC report.
Level 2 Manufacturer quality control test certificates of placed erosion mats are not included in this monthly QC report.
February 9, 2012
Ms. Diane Ingraham, Ph.D., PMP, Quality Contract Manager
Page 2 of 2
Reference: Materials and Geotechnical Quality Assurance of Quality Control Program
Element CO6A, Sydney Tar Ponds Project, Sydney, NS
Review of Contractor’s November 2011 Quality Control (QC) Report
Level 3 All reports should be signed by the applicable QC testing and review personnel, with names clearly printed, and dated once they are completed and reviewed.
This report covers the quality control aspects for both the geotechnical and materials portions of the project.
We trust this information meets your present needs. If you have any questions, or if we can be of further assistance, please do not hesitate to contact us at your convenience.
Sincerely,
STANTEC CONSULTING LTD
Rabi Morelly, M.Sc., P.Eng Willie McNeil, B.Tech. (Env.), CET Geotechnical & Materials Quality Lead Project Manager [email protected] [email protected]
\\cd1177-f02\workgroup\1214\active\121410xxx\121410955-stpa combined elements\245 co6a\400 reviews\qa review of qc monthly report\geo_mat qc reviews\co6a _2011_11_geo_mat iqac
review of qc report.docx
Stantec Consulting Ltd 207-201 Churchill Drive Membertou, NS B1S 0H1 Tel: (902) 564-1855 Fax: (902) 564-8756
February 15, 2012 File: 121410955.245
Sydney Tar Ponds Agency 1 Inglis Street PO Box 1028, Stn. A Sydney, NS B1P 6J7
Attention: Ms. Diane Ingraham, Ph.D., PMP, Quality Contract Manager
Dear: Ms. Ingraham
Reference: Environmental Quality Assurance of Quality Control Program Element CO6A, Sydney Tar Ponds Project, Sydney, NS Review of Contractor’s November 2011 Quality Control (QC) Report
At the request of the Sydney Tar Ponds Agency (STPA), Stantec Consulting Limited (Stantec), acting as the project Independent Quality Assurance Consultant (IQAC), has completed a Quality Assurance Review of the Contractor’s, (DENKO Mi’Kmaq Enterprises Ltd.) and their quality control consultant (exp. Global Inc.), Monthly Quality Control (QC) Report for the month of November 2011 for project element CO6A.
Comments are prepared using a three tier system as requested by the STPA:
Level 1 - Critical comments which need to be addressed promptly. The IQAC requests responses on any critical comments within one week. Level 2 - Comments for which a response is required. All comments for which a response is required should be responded to in the form of a written response or by providing the necessary information as requested. Level 3 - Comments that would improve the quality of the work but for which the agency need not respond to.
Based on our review of the QC information provided from the referenced period, the IQAC offers the following comments for your considerations:
Level 1
Environmental Inspection Logs
The footnote on Page 1 of the EILs state, “Criteria for Acceptable and Not Acceptable for each checklist item is given on Pages 3 to 6”. Pages 3 to 6 are not provided nor is the guidelines for noise or surface water provided on the EIL. As such, it cannot be determined from the EIL if the measurements Pass or Fail the guidelines.
Level 3
Environmental Inspection Logs
The Environmental Inspection Logs appear to have been scanned. Page numbers on the EILs read as “Page 1 of 2, Page 2 of 2, Page 3 of 2”. The EILs should be properly formatted so that the page numbers are consecutive.
Level 1 Environmental Inspection Logs/Quality Control (QC) and Quality Assurance (QA) Environmental Testing Summary Table
The surface water measurements (turbidity) on the EIL for November 1 (1100) are different
February 15, 2012 Ms. Diane Ingraham, Ph.D., PMP, Quality Contract Manager Page 2 of 2
Reference: Environmental Quality Assurance of Quality Control Program Element CO6A Sydney Tar Ponds Project, Sydney, NS Review of Contractor’s November 2011 Quality Control (QC) Report
than those listed in the table for this event. The measurements on the EIL indicate a failure in the downstream sample; whereas, the ones listed in the table are within the acceptable guideline.
Level 3
Environmental Inspection Logs
Noise monitoring should be listed under “#13. Other Specific EM Activities” under the Daily Checklist Item list on days in which noise monitoring is undertaken.
Level 1
Environmental Inspection Logs
The turbidity measurements are checked off as “Acceptable” on the November 17 (700 and 1100) EILs. However, the downstream sample indicates an exceedence of the acceptable guideline. These events are listed in the Quality Control (QC) and Quality Assurance (QA) Environmental Testing Summary Table as a failure.
Level 1
Environmental Inspection Logs
The turbidity measurements are checked off as “Acceptable” on the November 18 (700) EIL. However the downstream sample indicates an exceedence of the acceptable guideline. This event is listed in the Quality Control (QC) and Quality Assurance (QA) Environmental Testing Summary Table as a failure.
Level 3
Environmental Inspection Logs
A noise measurement of 66.9 Leq is presented in the Sound Monitoring Results section on the November 22 (1100) EIL. The noise measurements were collected on November 21 for this week and the November 21 (1100) measurement was 66.9 Leq. As such, this measurement is likely a typo carried over from the sample event from the previous day.
We trust this information meets your present needs. If you have any questions, or if we can be of further assistance, please do not hesitate to contact us at your convenience.
Sincerely,
STANTEC CONSULTING LTD
Tanya MacDonald, B.Tech.(Env.), AScT William McNeil, B.Tech.(Env.),CET Project Environmental Manager Project Manager Tel: (902) 564-1855 Tel: (902) 564-1855 Fax: (902) 564-8756 Fax: (902) 564-8756 [email protected] [email protected]
v:\1214\active\121410xxx\121410955-stpa combined elements\245 co6a\400 reviews\qa review of qc monthly report\environmental qc reviews\2011 11 env iqac-qcreview-co6a.docx
Contractor: DENKO Mi'Kmaq Enterprises Client: STPA Quality Control (QC) and Quality Assurance (QA) Environmental Testing Summary Table Element: CO6A Oversight: Dillon Consulting
IQAC: StantecWeeklyMonthly From: 2011-10-30 To: 2011-11-26
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-10-31
CO6A-ESC 5-0720-2011-10-31CO6A-ESC 2-0720-2011-10-31CO6A-ESC 5-1115-2011-10-31CO6A-ESC 2-1115-2011-10-31CO6A-ESC 5-1510-2011-10-31CO6A-ESC 2-1510-2011-10-31
As per EPP 2011-10-31
3.31 NTU7.43 NTU2.48 NTU6.24 NTU1.86 NTU3.06 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-01
CO6A-ESC 5-0720-2011-11-01CO6A-ESC 2-0720-2011-11-01CO6A-ESC 5-1115-2011-11-01CO6A-ESC 2-1115-2011-11-01CO6A-ESC 5-1510-2011-11-01CO6A-ESC 2-1510-2011-11-01
As per EPP 2011-11-01
1.29 NTU1.37 NTU2.48 NTU6.24 NTU2.53 NTU2.85 NTU
Pass Y Samples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.2
Noise SamplingNoise Monitoring with a dosimeter or equivalent
CBRM noise by-law and NSE criteria
Daily 2011-11-02CO6A-Gate 3, 30 m South of Spar- 2011-11-02CO6A-SW corner of site, near WTP- 2011-11-02CO6A-50mE of Site Lunch Trailer -2011-11-02
CBRM noise by-law and NSE criteria 2011-11-02
69.2 Leq (dBA)64.7 Leq (dBA)72.3 Leq (dBA)
Fail (See QC Note) Y
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.Noise exceedances were due to proximity to traffic along SPAR road.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-02
CO6A-ESC 5-0720-2011-11-02CO6A-ESC 2-0720-2011-11-02CO6A-ESC 5-1115-2011-11-02CO6A-ESC 2-1115-2011-11-02CO6A-ESC 5-1510-2011-11-02CO6A-ESC 2-1510-2011-11-02
As per EPP 2011-11-02
0.63 NTU1.30 NTU2.18 NTU1.36 NTU1.48 NTU1.40 NTU
Pass Y Samples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours Once Weekly 2011-11-03
CO6A-ESC 5-0720-2011-11-03CO6A-ESC 2-0720-2011-11-03CO6A-ESC 5-1115-2011-11-03CO6A-ESC 2-1115-2011-11-03CO6A-ESC 5-1510-2011-11-03CO6A-ESC 2-1510-2011-11-03
As per EPP 2011-11-03
0.84 NTU1.04 NTU1.05 NTU1.26 NTU1.05 NTU1.04 NTU
Pass Y CO6A-ESC5-2011-11-03-1500CO6A-ESC2-2011-11-03-1500 2011-11-03 2.46 NTU
1.23 NTUPassPass Yes
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.
Samples were collected in accordance with the EPP. Please refer to the weekly IQAC Site Testing Summary for further
details.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-04
CO6A-ESC 5-0720-2011-11-04CO6A-ESC 2-0720-2011-11-04CO6A-ESC 5-1115-2011-11-04CO6A-ESC 2-1115-2011-11-04CO6A-ESC 5-1510-2011-11-04CO6A-ESC 2-1510-2011-11-04
As per EPP 2011-11-04
0.85 NTU1.28 NTU1.22 NTU1.04 NTU1.05 NTU0.86 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-07
CO6A-ESC 5-0720-2011-11-07CO6A-ESC 2-0720-2011-11-07CO6A-ESC 5-1115-2011-11-07CO6A-ESC 2-1115-2011-11-07CO6A-ESC 5-1510-2011-11-07CO6A-ESC 2-1510-2011-11-07
As per EPP 2011-11-07
0.43 NTU0.76 NTU0.93 NTU0.69 NTU1.04 NTU0.67 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.2
Noise SamplingNoise Monitoring with a dosimeter or equivalent
CBRM noise by-law and NSE criteria
Daily 2011-11-07CO6A-Gate 3, 30 m South of Spar- 2011-11-07CO6A-SW corner of site, near WTP- 2011-11-07CO6A-50mE of Site Lunch Trailer -2011-11-07
CBRM noise by-law and NSE criteria 2011-11-07
63.5 Leq (dBA)60.6 Leq (dBA)66.5 Leq (dBA)
Fail (See QC Note) Y
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results. Noise exceedance was due to proximity of traffic along SPAR road.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-08
CO6A-ESC 5-0720-2011-11-08CO6A-ESC 2-0720-2011-11-08CO6A-ESC 5-1115-2011-11-08CO6A-ESC 2-1115-2011-11-08CO6A-ESC 5-1510-2011-11-08CO6A-ESC 2-1510-2011-11-08
As per EPP 2011-11-08
0.62 NTU0.76 NTU1.28 NTU0.91 NTU41.2 NTU0.96 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-09
CO6A-ESC 5-0720-2011-11-09CO6A-ESC 2-0720-2011-11-09CO6A-ESC 5-1115-2011-11-09CO6A-ESC 2-1115-2011-11-09CO6A-ESC 5-1510-2011-11-09CO6A-ESC 2-1510-2011-11-09
As per EPP 2011-11-09
1.27 NTU0.79 NTU1.46 NTU0.61 NTU1.04 NTU0.79 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours Once Weekly 2011-11-10
CO6A-ESC 5-0720-2011-11-10CO6A-ESC 2-0720-2011-11-10CO6A-ESC 5-1115-2011-11-10CO6A-ESC 2-1115-2011-11-10CO6A-ESC 5-1510-2011-11-10CO6A-ESC 2-1510-2011-11-10
As per EPP 2011-11-10
0.56 NTU0.66 NTU1.36 NTU0.81 NTU1.23 NTU1.06 NTU
Pass Y CO6A-ESC5-2011-11-10-1455CO6A-ESC2-2011-11-10-1455 2011-11-10 2.34 NTU
0.98 NTUPassPass Yes
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.
Samples were collected in accordance with the EPP. Please refer to the weekly IQAC Site Testing Summary for further
details.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-14
CO6A-ESC 5-0720-2011-11-14CO6A-ESC 2-0720-2011-11-14CO6A-ESC 5-1115-2011-11-14CO6A-ESC 2-1115-2011-11-14CO6A-ESC 5-1510-2011-11-14CO6A-ESC 2-1510-2011-11-14
As per EPP 2011-11-14
0.72 NTU1.63 NTU0.82 NTU1.47 NTU1.11 NTU1.21 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.2
Noise SamplingNoise Monitoring with a dosimeter or equivalent
CBRM noise by-law and NSE criteria
Daily 2011-11-14CO6A-Gate 3, 30 m South of Spar- 2011-11-14CO6A-SW corner of site, near WTP- 2011-11-14CO6A-50mE of Site Lunch Trailer -2011-11-14
CBRM noise by-law and NSE criteria 2011-11-14
78.5 Leq (dBA)65.8 Leq (dBA)71.3 Leq (dBA)
Fail (See QC Note) Y
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results. Noise exceedance was due to proximity of traffic along SPAR road and equivalent with the
background noise.
QAQA Frequency
Week 1
Date QA Result
ReceivedTest Type QA Frequency
Met? Y/N
NOTESSPECIFIED REQUIREMENTS
QC Pass/Fail
RESULTS
QA Pass/Fail Spec Description
Week 3
Week 2
Standard Date Collected QCQA Sample ID QA Test ResultQC Frequency Met? Y/NCriteria Date QC Result
Received QC Sample IDSpec Section
Form Number: 97918-QAF-073
QC Test Result
Project: Remediation of the Tar Ponds and Coke Ovens Sites
QC Frequency
CO6A Nov 2011 QCQA Env Testing.xlsForm Revision: April 07, 2010, Rev. 0 Page 1 of 2
Contractor: DENKO Mi'Kmaq Enterprises Client: STPA Quality Control (QC) and Quality Assurance (QA) Environmental Testing Summary Table Element: CO6A Oversight: Dillon Consulting
IQAC: StantecWeeklyMonthly From: 2011-10-30 To: 2011-11-26
QAQA Frequency Date QA Result
ReceivedTest Type QA Frequency
Met? Y/N
NOTESSPECIFIED REQUIREMENTS
QC Pass/Fail
RESULTS
QA Pass/Fail Spec Description Standard Date Collected QCQA Sample ID QA Test ResultQC Frequency Met? Y/NCriteria Date QC Result
Received QC Sample IDSpec Section
Form Number: 97918-QAF-073
QC Test Result
Project: Remediation of the Tar Ponds and Coke Ovens Sites
QC Frequency
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-15
CO6A-ESC 5-0720-2011-11-15CO6A-ESC 2-0720-2011-11-15CO6A-ESC 5-1115-2011-11-15CO6A-ESC 2-1115-2011-11-15CO6A-ESC 5-1510-2011-11-15CO6A-ESC 2-1510-2011-11-15
As per EPP 2011-11-15
0.63 NTU1.01 NTU0.75 NTU2.60 NTU0.87 NTU1.57 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours Once Weekly 2011-11-16
CO6A-ESC 5-0720-2011-11-16CO6A-ESC 2-0720-2011-11-16CO6A-ESC 5-1115-2011-11-16CO6A-ESC 2-1115-2011-11-16CO6A-ESC 5-1510-2011-11-16CO6A-ESC 2-1510-2011-11-16
As per EPP 2011-11-16
0.72 NTU0.99 NTU1.12 NTU0.92 NTU0.92 NTU1.00 NTU
Pass Y CO6A-ESC5-2011-11-16-1115CO6A-ESC2-2011-11-16-1115 2011-11-16 2.47 NTU
1.28 NTUPassPass Yes
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.
Samples were collected in accordance with the EPP. Please refer to the weekly IQAC Site Testing Summary for further
details.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-17
CO6A-ESC 5-0720-2011-11-17CO6A-ESC 2-0720-2011-11-17CO6A-ESC 5-1115-2011-11-17CO6A-ESC 2-1115-2011-11-17CO6A-ESC 5-1510-2011-11-17CO6A-ESC 2-1510-2011-11-17
As per EPP 2011-11-17
13.8 NTU77.8 NTU6.09 NTU16.7 NTU3.92 NTU4.98 NTU
Fail (See QC Note) Y
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.Silt fencing was torn and allowing sediment through. Repairs were immediately undertaken.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-18
CO6A-ESC 5-0720-2011-11-18CO6A-ESC 2-0720-2011-11-18CO6A-ESC 5-1115-2011-11-18CO6A-ESC 2-1115-2011-11-18CO6A-ESC 5-1510-2011-11-18CO6A-ESC 2-1510-2011-11-18
As per EPP 2011-11-18
2.69 NTU14.2 NTU4.05 NTU8.24 NTU1.94 NTU3.66 NTU
Fail (See QC Note) Y
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.Silt fencing was torn and allowing sediment through. Repairs were immediately undertaken.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-21
CO6A-ESC 5-0720-2011-11-21CO6A-ESC 2-0720-2011-11-21CO6A-ESC 5-1115-2011-11-21CO6A-ESC 2-1115-2011-11-21CO6A-ESC 5-1510-2011-11-21CO6A-ESC 2-1510-2011-11-21
As per EPP 2011-11-21
1.00 NTU1.59 NTU0.85 NTU0.69 NTU1.89 NTU2.44 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.2
Noise SamplingNoise Monitoring with a dosimeter or equivalent
CBRM noise by-law and NSE criteria
Daily Once Monthly 2011-11-21CO6A-Gate 3, 30 m South of Spar- 2011-11-21CO6A-SW corner of site, near WTP- 2011-11-21CO6A-50mE of Site Lunch Trailer -2011-11-21
CBRM noise by-law and NSE criteria 2011-11-21
67.9 Leq (dBA)66.9 Leq (dBA)75.5 Leq (dBA)
Fail (See QC Note) Y
CO6A-11-21-2011-0846-1050CO6A-11-21-2011-1055-1304CO6A-11-21-2011-1313-1608
2011-11-2162.2 Leq (dBA)57.2 Leq (dBA)71.5 Leq (dBA)
PassPassFail
Yes
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results. Noise exceedance was due to background noise from traffic on SPAR as well as the generator running nearby and the results are consistent with
background noise levels.
Samples collected as per EPP. Refer to Monthly Noise QA Testing Summary Table
in this report for more information.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-22
CO6A-ESC 5-0720-2011-11-22CO6A-ESC 2-0720-2011-11-22CO6A-ESC 5-1115-2011-11-22CO6A-ESC 2-1115-2011-11-22CO6A-ESC 5-1510-2011-11-22CO6A-ESC 2-1510-2011-11-22
As per EPP 2011-11-22
0.94 NTU1.19 NTU0.89 NTU0.90 NTU2.06 NTU1.58 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-23
CO6A-ESC 5-0720-2011-11-23CO6A-ESC 2-0720-2011-11-23CO6A-ESC 5-1115-2011-11-23CO6A-ESC 2-1115-2011-11-23CO6A-ESC 5-1510-2011-11-23CO6A-ESC 2-1510-2011-11-23
As per EPP 2011-11-23
0.65 NTU0.61 NTU0.93 NTU0.95 NTU1.25 NTU5.79 NTU
Pass Y Samples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours Once Weekly 2011-11-24
CO6A-ESC 5-0720-2011-11-24CO6A-ESC 2-0720-2011-11-24CO6A-ESC 5-1115-2011-11-24CO6A-ESC 2-1115-2011-11-24CO6A-ESC 5-1510-2011-11-24CO6A-ESC 2-1510-2011-11-24
As per EPP 2011-11-24
0.86 NTU0.51 NTU0.91 NTU0.42 NTU1.01 NTU0.97 NTU
Pass Y CO6A-ESC5-2011-11-24-1104CO6A-ESC2-2011-11-24-1104 2011-11-24 2.91 NTU
1.57 NTUPassPass Yes
Samples were collected in accordance with the EPP. Please refer to the daily EIL for specific testing
results.
Samples were collected in accordance with the EPP. Please refer to the weekly IQAC Site Testing Summary for further
details.
EPP Section 4.3
Surface Water Turbidity Sampling
Turbidity Sampling with portable turbidity meter
As per EPP Every 4 Hours 2011-11-25
CO6A-ESC 5-0720-2011-11-25CO6A-ESC 2-0720-2011-11-25CO6A-ESC 5-1115-2011-11-25CO6A-ESC 2-1115-2011-11-25CO6A-ESC 5-1510-2011-11-25CO6A-ESC 2-1510-2011-11-25
As per EPP 2011-11-25
0.30 NTU1.16 NTU1.13 NTU1.14 NTU1.54 NTU1.81 NTU
Pass YSamples were collected in accordance with the EPP.
Please refer to the daily EIL for specific testing results.
Week 4
CO6A Nov 2011 QCQA Env Testing.xlsForm Revision: April 07, 2010, Rev. 0 Page 2 of 2
Contractor: DENKO Mi'Kmaq Enterprises Client: STPA Quality Control (QC) and Quality Assurance (QA) Testing Summary Table Element: CO6A Oversight: Dillon Consulting
IQAC: Stantec
WeeklyMonthly From: 30-Oct-11 To:
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
25-Oct-11Cohesive Soil Backfill
(Blackett's Lake) 25-Oct-11
95% of Maximum Standard Dry
Density95.9 - 96.9% Pass Y Testing was conducted in accordance with the
Contractor's Quality Control Plan.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
2-Nov-11Cohesive Soil Backfill
(Blackett's Lake) 02-Nov-11
95% of Maximum Standard Dry
Density98.8 - 99.6% Pass Y Testing was conducted in accordance with the
Contractor's Quality Control Plan.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
2-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)02-Nov-11
95% of Maximum Standard Dry
Density96.0 - 97.6% Pass Y Testing was conducted in accordance with the
Contractor's Quality Control Plan.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
1 test or 10% of QC tests
whichever is greater.
3-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)03-Nov-11
95% of Maximum Standard Dry
Density95.8 - 98.3% Pass Y
Placed Cohesive Soil Backfill Keltic Drive Pit
Field Compaction Tests 1-3
(3-Nov- 11)
3-Nov-11
% Compaction:97.6-101.6
% M.C.: 9.1 -10.7
Pass Y Testing was conducted in accordance with the Contractor's Quality Control Plan.
All compactions exceeded 95% of Maximum Standard Dry Density. However, all of measured moisture contents were below the specified expected moisture content limits.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
4-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)03-Nov-11
95% of Maximum Standard Dry
Density95.3 - 98.7% Pass Y Testing was conducted in accordance with the
Contractor's Quality Control Plan.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
7-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)07-Nov-11
95% of Maximum Standard Dry
Density95.2 - 96.7.% Pass Y Testing was conducted in accordance with the
Contractor's Quality Control Plan.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
8-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)08-Nov-11
95% of Maximum Standard Dry
Density93.2 - 93.9.% Pass Y
Testing was conducted in accordance with the Contractor's Quality Control Plan. It should be noted that since the moisture content varied greater than 6% from optimum, the required compaction was 92%.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
1 test or 10% of QC tests
whichever is greater.
9-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)09-Nov-11
95% of Maximum Standard Dry
Density96.7 - 98.5.% Pass Y
Placed Cohesive Soil Backfill Keltic Drive Pit
Field Compaction Tests 1-3
(9-Nov- 11)
9-Nov-11
% Compaction:97.1-101.3
% M.C.: 8.6-9.8
Pass Y Testing was conducted in accordance with the Contractor's Quality Control Plan.
All compactions exceeded 95% of Maximum Standard Dry Density. However, all of measured moisture contents were below the specified expected moisture content limits.
31 22 16 Cohesive Soil BackfillField Compaction
and Moisture Content
ASTM D6938 Every 625 m2 for each lift
10-Nov-11Cohesive Soil Backfill
(Keltic Drive Source Pit)10-Nov-11
95% of Maximum Standard Dry
Density95.9 - 97.6.% Pass Y Testing was conducted in accordance with the
Contractor's Quality Control Plan.
03 60 00 Grout CompressiveStrength ASTM C109 Every Batch Once Every 4
Batches 17-Nov-11 2011-AF1 3.0 MPa Pending Pending Y
Grout Compressive Strength
7 and 28 Days Test Results(Cast on 17-Nov- 11)
15-Dec-11
7 Day Results:2.6 MPa2.4 MPa3.0 MPa
28 Day Results:4.8 MPa5.3 MPa4.7 MPa
Pass Y Testing was conducted in accordance with the Contractor's Grout Plan.
The specified 28 day criterion for compressive strength is 3.0 MPa
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 17-Nov-11 2011-AF2 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
8-Nov-11
Week 3
10-Nov-11
Pending
Pending
Week 2
3-Nov-11
3-Nov-11
7-Nov-11
4-Nov-11
QA Sample ID Date QA Result ReceivedQC Frequency
2-Nov-11
Form Number: 97918-QAF-059
QC Test Result QC Pass/Fail QA Pass/Fail
NOTES
Project: Remediation of the Tar Ponds and Coke Ovens Sites
26-Nov-11
QA Frequency Met? Y/N
QC Frequency Met? Y/N
RESULTS
Criteria QAQCQA Frequency
SPECIFIED REQUIREMENTS
Spec Section Spec Description QC Sample IDDate Collected
9-Nov-11
QA Test ResultDate QC Result Received
31-Oct-11
Week 1
Test Type Standard
CO6A November 2011 QC and QA Testing Summary.xlsForm Revision: April 07, 2010 Rev 4 Page 1 of 2
Contractor: DENKO Mi'Kmaq Enterprises Client: STPA Quality Control (QC) and Quality Assurance (QA) Testing Summary Table Element: CO6A Oversight: Dillon Consulting
IQAC: Stantec
WeeklyMonthly From: 30-Oct-11 To:
QA Sample ID Date QA Result ReceivedQC Frequency
Form Number: 97918-QAF-059
QC Test Result QC Pass/Fail QA Pass/Fail
NOTES
Project: Remediation of the Tar Ponds and Coke Ovens Sites
26-Nov-11
QA Frequency Met? Y/N
QC Frequency Met? Y/N
RESULTS
Criteria QAQCQA Frequency
SPECIFIED REQUIREMENTS
Spec Section Spec Description QC Sample IDDate Collected QA Test ResultDate QC Result
ReceivedTest Type Standard
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 17-Nov-11 2011-AF3 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 17-Nov-11 2011-AF4 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 17-Nov-11 2011-AF5 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 22-Nov-11 2011-AF6 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
03 60 00 Grout Compressive Strength ASTM C109 Every Batch Once Every 4
Batches 24-Nov-11 2011-AF7 3.0 MPa Pending Pending Y
Grout Compressive Strength
7 and 28 Days Test Results(Cast on 24-Nov- 11)
22-Dec-11
7 Day Results:7.2 MPa6.8 MPa6.8 MPa
28 Day Results:12.0 MPa12.0 MPa11.9 MPa
Pass Y Testing was conducted in accordance with the Contractor's Grout Plan.
The specified 28 day criterion for compressive strength is 3.0 MPa
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 24-Nov-11 2011-AF8 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
03 60 00 Grout Compressive Strength ASTM C109 Every Batch 25-Nov-11 2011-AF9 3.0 MPa Pending Pending Y Testing was conducted in accordance with the
Contractor's Grout Plan.
Pending
Pending
Pending
Pending
Pending
Pending
Week 4
Pending
CO6A November 2011 QC and QA Testing Summary.xlsForm Revision: April 07, 2010 Rev 4 Page 2 of 2
February File: 1214
Sydney T1 Inglis StPO Box 1Sydney, N
Attention
Dear Ms.
Referenc
At the reqreportableSummary
We trust thesitate to
Sincerely,
STANTEC
Willie McNProject MTel: (902) 5Fax: (902) willie.mcne
\\cd1177-f02\wo
7, 2012 410955.245
ar Ponds Agetreet 028, Stn. A
NS B1P 6J7
n: Ms. Di
Ingraham:
ce: ExtrasIndepe
quest of Sydnee extra items y Report.
this informatioo contact us.
,
C CONSULTI
Neil, B.Tech. anager 564-1855 564-8756
orkgroup\1214\active\1
Stantec Consu207-201 ChurcMembertou NSTel: (902) 564-Fax: (902) 564
ency
iane Ingraha
s Section - Sendent Qual
ey Tar Pondsto include in t
on meets you
ING LTD
(Env.), CET
m
21410xxx\121410955
ulting Ltd chill Drive S B1S 0H1 -1855
4-8756
am, PhD., CA
TPA Project ity Assuranc
s Agency (STthe EXTRAS
r present req
5-stpa combined eleme
APM, Quality
Element COce (IQAC) No
PA), Stantec section of the
uirements. If
ents\245 co6a\700 ext
Contracts M
O6A Coke Ovovember 201
Consulting Le (IQAC) Nov
you have any
tras\co6a extras sectio
Manager
vens Capping1 Monthly Su
td (Stantec) hvember 2011
y questions, p
on november 2011.do
g ummary Rep
has no Monthly
please do not
ocx
port
Stantec Consulting Ltd 207-201 Churchill Drive Membertou NS B1S 0H1 Tel: (902) 564-1855 Fax: (902) 564-8756
Sydney Tar Ponds Agency 1 Inglis Street PO Box 1028, Stn. A Sydney, NS B1P 6J7
Attention: Ms. Diane Ingraham, PhD., PMP, Quality Contracts Manager
Dear Ms. Ingraham:
Reference: Monthly Invoices As per the request of the Sydney Tar Ponds Agency, monthly invoices will be submitted in a separate submittal. Sincerely,
STANTEC CONSULTING LTD
Willie McNeil, B.Tech. (Env.), CET Project Manager Tel: (902) 564-1855 Fax: (902) 564-8756 [email protected]