16
Rs. Lakhs Description Ref.Year A Vessels 1 Vacuum Col reflux drum 5.17 5.50 wt., tons 1.670 1.23 4.30 2012 2 FG KOD 0.00 0.00 wt., tons 0.000 0.63 0.00 2012 3 0.00 0.00 wt., tons 0.000 1.20 0.00 2012 4 Flare KOD 0.00 0.00 wt., tons 0.000 3.42 0.00 2012 Total Vessel Cost 5.50 B Columns 1 46.078 48.80 Wt, MT, SS 0.30 11.00 400.00 2012(SS) 1 Atm distillation column 0.000 0.00 Wt, MT, SS 0.00 11.00 400.00 2004(SS) 2 Kero SS 0.000 0.00 Wt, MT, CS 0.00 11.00 400.00 2004(SS) 3 Diesel SS 0.000 0.00 Wt, MT, SS 0.00 11.00 400.00 2004(SS) 4 Column Internals 9.76 Total column cost 58.56 C Exchangers & Furnaces 1 0.00 0.00 Duty 0.1968 1.610 0.00 2012 2 HSD Product cooler 0.00 0.00 Duty 0.0600 0.180 0.00 2012 3 RCO Product Exchanger 0.00 0.00 Duty 0.4776 0.180 0.00 2012 4 Feed-HSD PA Exchanger 0.00 0.00 Duty 0.0000 0.160 0.00 2012 5 ATF product cooler 0.00 0.00 Duty 0.0000 0.22 0.00 2012 6 Diesel product cooler 0.00 0.00 Duty 0.0000 0.290 0.00 2012 7 Heavy cut cooler 0.00 0.00 Duty 0.0000 0.031 0.00 2012 8 Naphtha Product Cooler 0.00 0.00 Duty 0.0000 0.040 0.00 2012 9 Kero PA cooler 0.00 0.00 Duty 0.0000 0.310 0.00 2012 10 Diesel PA cooler 0.00 0.00 Duty 0.0000 0.180 0.00 2012 11 RCO furnace 57.64 97.40 Duty 0.25 2.0 200.00 2004 Total Exchanger Cost 97.40 D Compressors 1 0.00 0.00 Capacity, m3/h 0.00 100.00 0.00 2008 4 Instr. Air Receiver 0.00 0.00 wt., tons 0.00 1.20 0.00 2004 Total compressor cost 0.00 E Pumps 1 feed pumps (Two Nos) 0.70 1.40 Rated power, KW 0.85 4.16 1.81 2012 2 0.31 0.60 Rated power, KW 0.44 6.40 1.53 2012 3 RCO pump (Two nos.) 0.73 1.60 Rated power, KW 0.83 1.40 1.00 2012 4 Vacuum Pump 256.29 543.40 Rated power, KW 1.00 2.10 400.00 2012 5 0.00 0.00 Rated power, KW 0.00 4.16 1.81 2012 6 0.00 0.00 Rated power, KW 0.00 7.45 1.86 2012 7 0.00 0.00 Rated power, KW 0.00 8.45 2.10 2012 8 0.00 0.00 Rated power, KW 0.00 3.10 0.00 2012 9 Kero PA pumps (Two Nos) 0.00 0.00 Rated power, KW 0.00 1.80 0.00 2012 10 Diesel PA pumps (Two Nos) 0.00 0.00 Rated power, KW 0.00 3.20 0.00 2012 Table : Equipment Cost: ATF & HSD polishing at Hazira Cost at ref. Year Total cost, 2013 Ref. type for cost cal. Our equip. parameter Ref. equip. parameter Ref. Equip. cost CBD drum Vacuum distillation column Vacuum distillation condenser Instr. Air compressor, (A/B) & recever Distillate reflux pumps (Two Nos) Heavy Cut product pumps (Two Nos) Kero loading pumps (Two Nos) Diesel loading pumps (Two Nos) Heavy Cut loading pumps (Two Nos)

ST Project Economics

Embed Size (px)

DESCRIPTION

eng

Citation preview

Page 1: ST Project Economics

Table : Equipment Cost: ATF & HSD polishing at Hazira

Rs. Lakhs

Description Ref. type for cost cal. Ref.Year

A Vessels

1 Vacuum Col reflux drum 5.17 5.50 wt., tons 1.670 1.23 4.30 2012

2 FG KOD 0.00 0.00 wt., tons 0.000 0.63 0.00 2012

3 0.00 0.00 wt., tons 0.000 1.20 0.00 2012

4 Flare KOD 0.00 0.00 wt., tons 0.000 3.42 0.00 2012

Total Vessel Cost 5.50

B Columns

1 Vacuum distillation column 46.078 48.80 Wt, MT, SS 0.30 11.00 400.00 2012(SS)

1 Atm distillation column 0.000 0.00 Wt, MT, SS 0.00 11.00 400.00 2004(SS)

2 Kero SS 0.000 0.00 Wt, MT, CS 0.00 11.00 400.00 2004(SS)

3 Diesel SS 0.000 0.00 Wt, MT, SS 0.00 11.00 400.00 2004(SS)

4 Column Internals 9.76

Total column cost 58.56

C Exchangers & Furnaces

1 0.00 0.00 Duty 0.1968 1.610 0.00 2012

2 HSD Product cooler 0.00 0.00 Duty 0.0600 0.180 0.00 2012

3 RCO Product Exchanger 0.00 0.00 Duty 0.4776 0.180 0.00 2012

4 Feed-HSD PA Exchanger 0.00 0.00 Duty 0.0000 0.160 0.00 2012

5 ATF product cooler 0.00 0.00 Duty 0.0000 0.22 0.00 2012

6 Diesel product cooler 0.00 0.00 Duty 0.0000 0.290 0.00 2012

7 Heavy cut cooler 0.00 0.00 Duty 0.0000 0.031 0.00 2012

8 Naphtha Product Cooler 0.00 0.00 Duty 0.0000 0.040 0.00 2012

9 Kero PA cooler 0.00 0.00 Duty 0.0000 0.310 0.00 2012

10 Diesel PA cooler 0.00 0.00 Duty 0.0000 0.180 0.00 2012

11 RCO furnace 57.64 97.40 Duty 0.25 2.0 200.00 2004

Total Exchanger Cost 97.40

D Compressors

1 0.00 0.00 Capacity, m3/h 0.00 100.00 0.00 2008

4 Instr. Air Receiver 0.00 0.00 wt., tons 0.00 1.20 0.00 2004

Total compressor cost 0.00

E Pumps

1 feed pumps (Two Nos) 0.70 1.40 Rated power, KW 0.85 4.16 1.81 2012

2 0.31 0.60 Rated power, KW 0.44 6.40 1.53 2012

3 RCO pump (Two nos.) 0.73 1.60 Rated power, KW 0.83 1.40 1.00 2012

4 Vacuum Pump 256.29 543.40 Rated power, KW 1.00 2.10 400.00 2012

5 0.00 0.00 Rated power, KW 0.00 4.16 1.81 2012

6 Kero loading pumps (Two Nos) 0.00 0.00 Rated power, KW 0.00 7.45 1.86 2012

7 0.00 0.00 Rated power, KW 0.00 8.45 2.10 2012

Cost at ref. Year

Total cost, 2013

Our equip. parameter

Ref. equip. parameter

Ref. Equip. cost

CBD drum

Vacuum distillation condenser

Instr. Air compressor, (A/B) & recever

Distillate reflux pumps (Two Nos)

Heavy Cut product pumps (Two Nos)

Diesel loading pumps (Two Nos)

Page 2: ST Project Economics

Description Ref. type for cost cal. Ref.YearCost at ref. Year

Total cost, 2013

Our equip. parameter

Ref. equip. parameter

Ref. Equip. cost

8 0.00 0.00 Rated power, KW 0.00 3.10 0.00 2012

9 Kero PA pumps (Two Nos) 0.00 0.00 Rated power, KW 0.00 1.80 0.00 2012

10 Diesel PA pumps (Two Nos) 0.00 0.00 Rated power, KW 0.00 3.20 0.00 2012

11 CBD pumps (Two Nos) 0.00 0.00 Capacity, m3/h 0.00 2.00 0.00 2004

12 Flare KOD pumps (Two Nos) 0.00 0.00 Capacity, m3/h 0.00 2.10 0.00 2012

13 0.00 0.00 Capacity, m3/h 0.00 10.00 0.00 2008

Total cost 547.00

F Dryers

1 Instrument air dryer 0.00 0.00 Capacity, m3/hr 0.00 100.00 2.15 2008

2 Liquid coalescer 0.00 0.00 Capacity, bopd 0.00 2400.00 2.52 2009

Total Cost 0.00

G Storage and loading gantry

6 0.00 0.00 Storage capacity, m3 0.00 700.00 49.65 2004

Total 0.00

H Catalyst and Chemicals unit reqt. Rs./unit year

Molecular sieve 0.00 0.00 Kg 0.00 1.00 642 2009

Total 0.00I Miscelaneous

1 Cooling Tower 0.00 0.00 Capacity, m3/h 0.00 400 10.61 20042 Furnace 0.00 0.00 Heat duty,MKcal 0.00 2.0 200.00 20043 Power generation (Gas) 0.00 0.00 Capacity, KVA 0.00 500.00 185.00 2008

Lab equipments 0.00Total 0.00

J Other Utilities

0.000

Fire protection system 0.000

0.000

0.000

0.000

ETP package (20 m3/d) 0.000

Total utility 0.00

Heavy Cut loading pumps (Two Nos)

Cooling water pump A/B (Two Nos)

Heavy cut storage (2 tank of 150 m3 , 7 days storage)

Blowdown system with vaporiser

Flare connections (excluding KOD)

Chemical Injection system system

Loading bays, gantry & weigh bridge

Page 3: ST Project Economics

Table:- : Plant and Machinery Cost - ATF & HSD polishing at Hazira

Rs. Lakh

S.No. Description Fc Ic Sc Total

A

1 Vessels 5.50 5.50

2 Column 58.56 58.56

3 Exchangers & Furnace 97.40 97.40

4 Compressor 0.00 0.00

5 Pumps 547.00 547.00

6 Dryers 0.00 0.00 0.00

7 Miscellaneous 0.00 0.00

Sub Total A 0.00 708.46 0.00 708.46

B Catalyst and chemicals 0.00 0.00

C Bulk Materials

1 Piping 0.00 212.54 212.54

2 Electrical 88.56 88.56

3 Instrumentation 0.00 233.79 233.79

4 Spares 24.80 24.80

Sub Total C 0.00 559.68 0.00 559.68

D Errection

1 Mechanical 88.56 88.56

2 Electrical 17.71 17.71

3 Instrumentation 35.07 35.07

4 Civil and structural 126.81 126.81

5 77.93 77.93

Sub total D 0.00 0.00 346.08 346.08

Sub Total (A+B+C+D) 0.00 1268.14 346.08 1614.23

E Indirect Cost

1 Ocean freight 0.00 0.00

2 Custom duty 0.00 0.00

3 50.73 50.73

4 P&F 19.64 19.64

5 Excise 156.74 156.74

6 CST 13.00 13.00

7 VAT 7.32 7.32

8 Insurance 37.09 37.09

9 Work contract tax 17.11 17.11

10 Service Tax 42.78 42.78

Sub Total E 0.00 344.40 344.40

0.00 1612.54 346.08 1958.62

Fc-Foreign Component, Ic - Indian Component, Sc - Site component

Insulation, painting & fireproofing

Port handling & inland freight

Total Plant & Machinery cost

Page 4: ST Project Economics

Rs. Lakh

S.No. Description Fc Ic Total

1 Plant and Machinery 0.00 1958.62 1958.62

2 Storage & Loading 0.00 0.00

3 Other utilities 0.00 0.00

4 195.86 195.86

5 PMC 117.52 117.52

6 200.00 200.00

Sub Total (1-6) 0.00 2472.00 2472.00

10 0.00 247.20 247.20

11 Land & Site Development 0.00 0.00

12 EPC Margin 293.79 293.79

Total Project cost 0.00 3013.00 3013.00

Table:-Total Project Cost - ATF & HSD polishing at Hazira

Engg, Procurement, Construction Supervision, commissioning & Project management

Miscellaneous (Owners management, infrastructure, start-up, commissioning etc.)

Contingency

Page 5: ST Project Economics

Table:- : Operating Cost and Sales Revenue - ATF & HSD polishing at Hazira

Rs Lakh

S.No. Description Unit Unit rate, Rs Qty./year

Variable operating cost

1 Shrinkage gas COST

2 Condensate cost Barrels 0 0.00

Sub-total 1-2

3 Molecular sieves kg 0 0.00

4 Fuel Gas sm3 6.43 5918522

5 Water m3 16.38 396000

6 Steam MT 0 13305.60

7 Electricity MWH 0.04 1936

8 Methanol Barrels 0.00 0

Sub-total 3-8

Total var. opex

1 Mandays cost, Officers per year 12 0

2 Gen. administration

3 Insurance

4 Repair & maint.

5 Consummables

Total fixed cost

Total operating cost

Additional Sales Revenue gain

1 LPG MT 36100.00 0

2 Naphtha MT 36800.00 0

3 Kerosene MT 37050.00 0

4 Diesel KL 45756.00 5477.67

5 RCO (crude blending) barrels 5321 149160.00

Page 6: ST Project Economics

6 LSHS(less) Barrels 5321 184470.00

Total Aditonal Sales Revenue gain

Capital cost 3012.99832849484

Gas price, US$/mmBTU 4.2

Calorific value, Kcal/m3 NAPHTHA

1 Feed gas 9118

2 Product gas 8920

Unit Unit rate,Rs Qty,/day

1 Feed gas m3 7.14 0

2 Lean gas m3 6.43 0

Shrinkage gas COST 0

Page 7: ST Project Economics

Table:- : Operating Cost and Sales Revenue - ATF & HSD polishing at Hazira

Rs Lakh

Rs. Lakh

Variable operating cost

0.00

0.00

0.00

0.00

380.58

64.87

0.00

0.00

0.00

445.45

445.45

0.00

30.13

30.13

45.19

15.06

120.52

565.97

0.00

0.00

0.00

2506.36

7936.80

Page 8: ST Project Economics

9815.65

627.52

Qty./year

0

0

Page 9: ST Project Economics

Hazira Feed gas

Component NHV, Btu/scf Mole fraction

C1 909.40 8093.03 0.814 6590.15

C2 1618.70 14405.30 0.0659 949.31

C3 2314.90 20601.00 0.0412 848.76

iC4 3000.40 26701.47 0.0080 213.61

nC4 3010.80 26794.03 0.0101 270.62

iC5 3699.00 32918.53 0.0025 82.30

nC5 3706.90 32988.83 0.0028 92.37

nC6 4403.80 39190.76 0.0018 70.54

nC7+ 5100.80 45393.57 0.0000 0.00

n-C8 0.0000 0.00

Benzene 0.0000 0.00

Toluene 0.0000 0.00

Cyclopentane 0.0000 0.00

Mcyclopentan 0.0000 0.00

Cyclohexane 0.0000 0.00

Mcyclohexane 0.0000 0.00

CO2 0.00 0.00 0.0534 0.00

N2 0.00 0.00 0.002 0.00

Total 1.00 9117.66

Total kg mole

Fraction flow 1.000

9117.663

4.20

0.0000167

NHV, Kcal/m3

Partial heaing value, Kcal/m3

Calorific value of gas

Gas Price, US$/mmBTU

Gas Price, US$/kCal

Page 10: ST Project Economics

Rs/ US$ 47.00

Gas Price, Rs/kCal 0.00078

Gas price, US$/m3 7.14 0.00

Page 11: ST Project Economics

Product gas

Hazira lean gas

0.8812 7131.58 0.488 3952.19 0.777

0.0519 747.64 0.465 6694.81 0.157

0.014 288.41 0.045 927.04 0.042

0.0008 21.36 0.001 34.54 0.012

0.0006 16.08 0.000 3.95 0.007

0.000 0.00 0.000 0.01 0.002

0.000 3.42 0.000 0.00 0.001

0.000 0.27 0.000 0.00 0.001

0.000 0.01 0.000 0.00 0.000

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.052 0.00 0.000 0.00 0.000

0.004 0.00 0.000 0.00 0.001

1.00 8208.77 1.00 11612.55 1.00

1.000 1.000 1.000

8208.767 11612.546 10055.512

Partial heaing value, Kcal/m3

Mole percent lean gas (LEF OH)

Partial heaing value, Kcal/m3

Mole percent lean gas (Surge gas)

Page 12: ST Project Economics

6.43 0.00 9.10 0.00 7.88

Page 13: ST Project Economics

Product gas LG Overall

6285.64 0.813 6577.30

2257.00 0.074 1059.20

861.08 0.038 780.02

332.88 0.006 166.88

183.76 0.008 207.61

64.90 0.001 47.97

42.05 0.001 45.14

22.44 0.001 35.99

5.75 0.000 0.09

0.00 0.000 0.00

0.00 0.000 0.00

0.00 0.000 0.00

0.00 0.000 0.00

0.00 0.000 0.00

0.00 0.000 0.00

0.00 0.000 0.00

0.00 0.057 0.00

0.00 0.001 0.00

10055.51 1.00 8920.20

1.000

8920.200

Partial heaing value, Kcal/m3

Mole percent lean gas (Surge gas)

Partial heaing value, Kcal/m3

Page 14: ST Project Economics

0.00 6.99

Page 15: ST Project Economics

Table A2.19: Profitability Analysis - B-55 & C-Series Condensate Processing at Uran (Refinery Scheme)

Rs. Lakhs

Description Project execution period Operating Period

1 2 1 2 3 4 5 6 7 8 9 10

A Capital cost (6%esc.) 1958.45 1117.82

B Addl. Sales revenue gain 627.52 627.52 627.52 627.52 627.52 627.52 627.52 627.52 627.52 627.52

C Salvage value 1422.14

D Variable operating cost 445.45 445.45 445.45 445.45 445.45 445.45 445.45 445.45 445.45 445.45

Fixed operating cost 120.52 120.52 120.52 120.52 120.52 120.52 120.52 120.52 120.52 120.52

Total operating cost (8%esc.) 565.97 611.25 660.15 712.96 769.99 831.59 898.12 969.97 1047.57 1131.37

E Gross Margin 61.55 16.27 -32.63 -85.44 -142.48 -204.08 -270.60 -342.45 -420.05 918.28

F Depreciation 159.09 159.09 159.09 159.09 159.09 159.09 159.09 159.09 159.09 159.09

G Net margin -97.54 -142.81 -191.71 -244.53 -301.56 -363.16 -429.69 -501.54 -579.14 759.19

H Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

I Profit before tax -97.54 -142.81 -191.71 -244.53 -301.56 -363.16 -429.69 -501.54 -579.14 759.19

J Tax liability 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

K Profit after tax -97.54 -142.81 -191.71 -244.53 -301.56 -363.16 -429.69 -501.54 -579.14 759.19

Net cash flow

Before tax -1958.45 -1117.82 61.55 16.27 -32.63 -85.44 -142.48 -204.08 -270.60 -342.45 -420.05 918.28

After tax -1958.45 -1117.82 61.55 16.27 -32.63 -85.44 -142.48 -204.08 -270.60 -342.45 -420.05 918.28

Financial parameter Before tax After tax

NPV (@12%), Rs. Lakhs -2887.15 -2887.15

IRR Err:523 Err:523

S.No.