Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 Review / Sprint 105 Planning April 8, 2013

Embed Size (px)

Citation preview

Page 1: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 Review / Sprint 105 PlanningApril 8, 2013

Page 2: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint Resource Pages

• For this sprint, visit: https://developer.connectopensource.org/display/NHINProgress/Sprint+104

• For next sprint, visit:https://developer.connectopensource.org/display/NHINProgress/Sprint+105

• For information on the CONNECT 4.0 release, visit:https://developer.connectopensource.org/x/N4EcBg

• For information on the CONNECT 4.1 release visit: https://developer.connectopensource.org/x/q4CrBw

2

Page 3: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 - Community Contributions

• Open forum for community members to shareo Their work of the last two weeks

o Their needs from CONNECT

o Ideas and suggestions

• Community contributionso UPMC - CONNECT 4.0 Alpha 1 / WebSphere

o SSA - CONNECT 4.0 WebSphere

o EHR Doctors – CONNECT 4.1

3

Page 4: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 Summary - Cumulative Flow

4

To Do

In Progress

QA

Done

Page 5: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 Summary - Burndown Chart

5

Page 6: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 Summary –Sprint Stats

• Points committed = 14

• Tickets committed to sprint = 27

• Tickets completed = 22

• Ticket added for 2 points of effort, totaling 16 points for sprint

• Points remaining (unclosed) at end of sprint = 5.5

• Points completed in sprint (velocity) = 9.5 (1 point moved out)

6

Page 7: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 – Themes & Tasks

• 4.0 Partner and Community Support– CMS-OFM 4.0 install on WAS 7 JDK 1.6

– Support CMS with their planned Direct Pilot

– Provide support for SSA testing of 4.0

– Community support through forum responses and guidance

• 4.1 Release Preparation– Complete functional and regression testing

– Continue with installation testing

– Complete and finalize supporting documentation

• Participation in the Healtheway Certification Testing Pilot

• Incorporate CI Testing Improvements to Additional App Servers

• Start Work on Design for Enhancements to Auditing– Was a stretch theme and didn’t make it into the sprint

7

Page 8: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 - What We are Showing Today4.0 Community and Partner Support

• Work Completed to Support the CONNECT Community and Federal Partners– CMS-OFM 4.0 install on WAS 7 JDK 1.6

• CONN-313

– Provide support for SSA testing of 4.0

– Support CMS with their planned Direct Pilot

– Community support• Forums

• Implementations

8

Page 9: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 - What We are Showing TodayCommunity Forums

• Forum Community Support – Community support through forum responses and guidance

• Binary versus source installs

• SAML Attributes

• CONNECT interoperability with Federal agencies

• Validation test suite

• Jboss install

• Direct service configuration

• GlassFish deployment challenges

– Forums + Community Support

• http://www.connectopensource.org/developer-resources/forums

9

Page 10: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 - What We are Showing TodayCONNECT 4.1

• CONNECT 4.1 Release preparation (documentation & testing)– CONN-300 – 4.1 Release Notes describing new features and additional tickets

– CONN-333 – Supporting release documentation for the community

– CONN-306 – Installation testing

– CONN-285 – Updates to the configuration instructions for Direct service

– CONN-328 – Updates to the Readme files in Github

JBoss 7.1.1 Support– Another strategic application server the community wanted CONNECT 4.0 tested

with was JBoss

– JBoss provides an open source app server that supports FIPS requirements

– Demonstration today of CONNECT running on JBoss 7.1.1

10

Page 11: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 - What We are Showing TodayCONNECT 4.1

• CONNECT 4.1 continued CI and Build Improvements– Continued build improvements

• Build time from 24 minutes to 10 minutes

• CONN-86 – Create Solaris websphere CI pipeline component

– Demonstrating today the build improvements

– Add CI Improvements to additional application servers

• CONN-75 – Automate nightly to do WebLogic deployment testing

– Benefits to the community

11

Page 12: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 104 - What We are Showing TodayCONNECT 4.1

• CONNECT 4.1

Resolved Support Tickets– CONN-336 – Certificate configuration support in CONNECT

– CONN-329 – Standard Document Query does not Policy Check on Outbound

– CONN-355 – CONNECT 4.0 is not sending the organization-id attribute statement in the SAML header

• Conformance testing impacts

12

Page 13: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Sprint 105 - Proposed Themes

• 4.1 Release – Binaries and source available

– Complete and finalize supporting documentation

• 4.2 Release– CMS-OFM 4.0 install on WAS 7 JDK 1.6 testing

– Design for Document Query specification version identification

• CONN-46 & CONN-15

• Participation in the Healtheway Certification pilot

• Partner and Community Support

• Product Backloghttps://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140

13

Page 14: Sprint 104 Review / Sprint 105 Planning April 8, 2013

CONNECT 4.0Community Announcements

• CONNECT Awareness

– Open sprint review and planning meetings Next sprint meeting will be April 22nd

– CONNECT 4.0 Blogs and Forum posts

– CONNECT User Group meeting May 21st

– Call for participation and abstracts underway

14

Page 15: Sprint 104 Review / Sprint 105 Planning April 8, 2013

Questions and Discussion

15