14
SPL Integration Layout act on cryo and vacuum sectorisati erground obstacles, constraints on slope and length Continuous cryostat and warm magnet options ation of the surface buildings and of the main serv liminary integration, impact of the position of the Weisz – SPL Cryogenic and vacuum sectorisation – 9 Nov 2009

SPL Integration Layout Impact on cryo and vacuum sectorisation

  • Upload
    jasia

  • View
    42

  • Download
    0

Embed Size (px)

DESCRIPTION

SPL Integration Layout Impact on cryo and vacuum sectorisation. ◊ Underground obstacles, constraints on slope and length of the SPL. ◊ Continuous cryostat and warm magnet options. ◊ Location of the surface buildings and of the main service shaft. - PowerPoint PPT Presentation

Citation preview

Page 1: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

SPL Integration LayoutImpact on cryo and vacuum sectorisation

◊ Underground obstacles, constraints on slope and length of the SPL

◊ Continuous cryostat and warm magnet options

◊ Location of the surface buildings and of the main service shaft

◊ Preliminary integration, impact of the position of the couplers

Sylvain Weisz – SPL Cryogenic and vacuum sectorisation – 9 Nov 2009

Page 2: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Linac 4

SPL tunnel

Material access and services shaftPersonnel and material access shaft

Klystron gallery

Emergency exit shaft

Transfert line to PS2

Personnel passage

Emergency exit shaft

Personnel passage

Personnel passage

Page 3: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Computer Center

n_TOF target

TI2 injection line

Underground obstacles

Page 4: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Computer Center

RP requires a shielding of 6.9m of earth to keep Bld 513 a non designated area sets the altitude of Linac4

A. Kosmicki & M. Poehler

Page 5: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

n_TOF target area

160µSr/h in Klystron gallerie for 7 1012 ppp on n_TOF target

(20 GeV, 0.33Hz)

A. Kosmicki & M. Poehler

Page 6: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

TI2 injection line to LHC

SPL tunnel or SPL to PS2 transfert line crosses TI2 from above

A. Kosmicki & M. Poehler

Page 7: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Linac 4

Computer Center

n_TOF target area

TI2 injection lineSPL tunnel – slope = 1.7%

Transfert line to PS2 – slope = 8.4%

~550m

Constraints on slope and length of the SPL

Page 8: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

10 x β=.65 moduleslength = 121 m

4 Gev version (LP): 18 x β=1 modules + 2 de-modulator modules

extraction regions to Isolde and Eurisol

5 Gev version (HP): 23 x β=1 modules + 2 de-modulator modules

extraction regions to Isolde and Eurisol SPL length = 527.38 m

SPL length = 452.58 m

SPL "baseline" layout

Cold continuous cryostat

T. Renaglia

Page 9: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

"Compact" version (gain on interconnections):

5 Gev version (HP): SPL length = 485.14 m (-42.24 m with respect to "baseline")

"Warm quadrupole" version (with separate cryoline):

5 Gev version (HP): SPL length = 535.92 m (+8.54 m with respect to "baseline")

Continuous cryostat and warm magnet options

Page 10: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

SPL tunnel

Material access and services shaftPersonnel and material access shaft

Klystron gallery

~150m

~170m

Location of the surface buildings and of the main service shaft

Page 11: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Downstream limit ofmain service shaft

A. Kosmicki & M. Poehler

Too far, assume 320m max.

Page 12: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

SPLTunnel Machine & Tunnel Services

JMB 03-07-2009

Very preliminary integration issue: Position of the power couplers

Preferred to initial model if we have many waveguide between the two tunnels

J-M. Bianco

Page 13: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Couplers from above would be accessible

Waveguide network would block access to couplers from below (+ probes, controls,water cooling pipes, etc…)Would need a larger tunnel to access from the other side of the modules (Compatibility with cryoline?)

J-M. Bianco

Page 14: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Summary◊ SPL would have a 1.7% slope ◊ 550m should be considered as a maximum length

(including debuncher and vertical bend to PS2)◊ A warm magnet option just fits in the footprint◊ Surface buildings and main shafts can be located

around the mid-point of the SPL◊ It would be a big advantage to install the power

couplers from above