If you can't read please download the document
Upload
mayank-jain
View
133
Download
2
Tags:
Embed Size (px)
DESCRIPTION
Specification Instrumentation
Citation preview
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 1 of 152
CHAPTER 1: Specification for Pipes & Laying
1.1 Scope
This specification covers the general requirements for manufacture, supply,
linings, coatings laying, jointing, testing and commissioning of spiral welded
Mild steel (MS) pipeline above / below ground including appurtenances and
associated civil works required for the same.
1.2 Materials
1.2.1 The mild steel pipes shall be manufactured by using Hot Rolled (H.R.) Coil
only either as per IS-10748 Grade III or as per IS: 2062 Grade B. The pipes
shall be manufactured confirming to IS 3589/2001, Grade: Fe-410 or higher
grade steel. The general requirements relating to supply of spiral welded pipes
and their process of manufacturing shall confirm to IS: 5504. The H.R. Coil
must contain brand name of manufacturer (engraved) at suitable interval.
1.2.2 Welding Consumables - such as electrodes, filler rods and wires shall conform
to IS: 814, IS: 3613, IS: 7280 and IS: 6419, 816.
1.2.3 Cement - The cement used for lining shall be the Portland cement conforming
to IS: 269 / IS: 8041 / IS: 1489 / IS: 8112. The minimum cement content shall
be 330 kg/m3 with 43 or higher Grade of cement.
1.2.4 Sand for lining shall conform to IS 2116 as per clause A-3.1 of IS : 3589-2001
1.2.5 Water - The water used in preparation of concrete mix shall be clear, colourless
and free from injurious quantities of organic matter, alkali, salt or other
impurities that might reduce strength durability or other desirable qualities of
mortar. It shall confirm to IS: 456.
1.2.6 Before fabrication of pipes and specials / fittings is commenced, the copies of
the mill sheets and the manufacturer's test certificates for materials required for
the fabrication shall be submitted by the Contractor to the Engineer-in-Charge
or his representative for his approval and record.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 2 of 152
1.2.7 When requested by the Engineer-in-Charge or his Representative, the
Contractor shall supply free of charge to the Engineer-in-Charge, for testing
suitable samples of the materials to be used/used in the works. The cost of such
tests shall be borne by the Contractor and shall be included by him in his rates /
bid amount.
1.3 Inspection
1.3.1 All works and materials under the specification will be inspected during all
phases of manufacture and testing and such inspection shall not relieve the
Contractor of his responsibility to furnish materials and performed work in
accordance with this specification.
1.3.2 The Contractor shall notify the Engineer-in-Charge or his Representative in
advance of the production of materials and fabrication thereof, in order that the
Engineer-in-Charge may arrange for mill and shop inspection.
1.3.3 The Engineer-in-Charge or his Representative may reject any or all materials or
works that do not meet with any of the requirements of this specification. The
Contractor shall rectify or replace such rejected materials / performed work at
his own cost, to the satisfaction of the Engineer-in-Charge or his
Representative.
1.3.4 The Engineer-in-Charge or his Representative shall have free access to those
parts of all plants or any other premises and sites that are concerned with the
furnishing of materials or the performance of work under this specification.
1.3.5 The Contractor shall furnish to the Engineer-in-Charge's representative
reasonable facilities and space without charge for inspection, testing and
obtaining of any information he desires in respect of the quality of materials
used and the progress and manner of the work.
1.3.6 The Contractor shall provide 2 (two) sets of accurate 'Go' and 'No - Go' ring
gauges to measure the diameter of pipes, specials and fitting, gauges to measure
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 3 of 152
thickness of pipes & specials for the use of the Engineer-in-Charge or his
Representative at no extra cost.
1.4 Manufacture of M.S. Pipe
1.4.1 General
All pipes and specials shall be manufactured out of new mild steel Hot Rolled
(H.R.) coils only which shall be free from any cracks, surface flaws,
laminations, excessive pitting or any other defects. The pipes shall be mill
manufactured using spiral welding from coil either as per IS-10748 Grade III or
as per IS: 2062 Grade B. The Pipe should be procured from manufacturer
having in-house Plate / Coil rolling facility in the same name and style as pipe
manufacturer which should be in operation since last 5 Years. The pipe shall be
manufactured at a mill which can establish with authenticity having supplied
similar pipes in the last 3 years which are truly cylindrical, and straight in axis.
The ends shall be accurately cut and prepared for welding. No site-fabricated
pipes are allowed. The external circumference of the pipe pieces, which are to
be fixed adjacent to flange adopter with fixed outer diameter shall not deviate
from theoretical by more than 1 mm. The pipe shall be rolled several times, if
necessary, as pipe pieces should be truly cylindrical. The external
longitudinal/spiral welding of the pipe shall be ground smooth flush with
surface to the satisfaction of the Engineer-in-Charge or his Representative.
Nothing extra cost shall be charged by the Contractor for grinding work. No
negative tolerance is allowed in thickness of pipe.
Minor repair by welding or otherwise shall be permitted at the discretion of the
Engineer-in-Charge or his Representative but such repairs shall be done only
after obtaining the permission of the Engineer-in-Charge or his Representative.
Any pipe or part thereof which develops injurious defects during shop welding
or other operations shall be rejected.
1.4.2 Design
1.4.2.1 While designing the Steel Cylinder, it will be seen that no tension is taken
by the cement mortar lining / coating. The thickness of the pipe provided
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 4 of 152
shall be such that it will be able to cater to the maximum of the following
loading/pressures as given below: -
a) Class AA loading due to moving traffic + Weight of soil above the top
of the pipe + Self-Weight of the pipe and Water load in the pipe +
Internal pressure + Surge pressures.
b) Working pressure + Surge pressure.
c) It shall also be ensured by the Contractor that bending stresses do not
exceed the permissible limits when the pipes are placed on the pillars at
8.0 m centre to centre.
d) In addition to the above loads, load of water surrounding the pipe and
negative pressure due to partial vacuum shall also be considered.
e) Contractor shall also ensure that deflection shall not exceed the
permissible limits when laid under ground and when subjected to worst
loading conditions and also by placing the pipe filled with the water on
pillars at 7.0 to 8.0 m c/c.
f) Necessary precautions including providing stiffeners may be taken
against ovality in pipes under all load conditions as mentioned above.
g) The thickness of the pipe shall be maximum of designed thickness plus
corrosion allowance of 2 mm. The thickness to be adopted will be
maximum thickness of thickness as above and those specified in the
tender document.
1.4.3 Fabrication Specifications
1.4.3.1 The pipe shall be shop fabricated from a reputed manufacturer of pipes
through H.R coils only. The manufacturer should have arrangements for
testing all sorts of materials as per requirements of IS codes, etc. &
machining as well as lining by centrifugal process, out-coating etc. for
completing the work under the present contract within the contract period,
the factory shall be equipped with adequate number of various equipments
and plants such as:
o Machinery/equipments for manufacture of spiral welded pipes
o Automatic welding machines (suitable for circumferential welding)
o Facility to carry out ultra sonic testing of welds seam & body
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 5 of 152
o X-ray fluoroscopy of the weld seam
o Radiography of weld in pipe ends
o Radiography of joints at junctions of spirally weld and skelp-end weld.
o Extensive manual ultra sonic testing of weld seam & body
o Such other equipments necessary to check welding as per IS Codes
requirements
o Hydrostatic Testing Machines for carrying out tests as per relevant IS
Codes.
o Equipments for centrifugal mortar lining of pipes in factory.
o Equipment for mixing of concrete and mortar by weigh batching process
o Arrangements for curing to centrifugally applied mortar lining in shade
o Equipments/arrangements for testing of pipe shells and physical tests as
per clause of respective IS Codes
o Sand blasting equipments for cleaning the pipes to near white for
internal linings & external coatings
o Trained personals for the above jobs so that all the works could be
completed within the stipulated period
o Any other equipment required for manufacture/testing of material and
pipes even though not mentioned.
1.4.3.2 The factory shall have adequate area and shall also have stacking yard for
the stacking of plates, structural, fabricated pipes and scrap etc.
1.4.3.3 The hot rolled coil after decoiling shall be cut, straightened, and trimmed
on both sides, for cutting of mill edges and to have constant width. The
trimmed stripped edges shall be bevelled by planning tools and cleaned on
both sides by brushes for achieving good welding. The strap subsequently
shall be pressed through drive roll and pre-bending roll where edges are
bend slightly to eliminate the peaking effect in the region of weld seam. In
the pipe forming device the strip shall be formed to a pipe with high
dimensional accuracy by three rolled bending devices and outer roller cage.
The strip edge running together along with the formed pipe shall be welded
in side at the lowest pint by submerged are welding process. This shall be
followed by outside SAW welding t a phase of 1800. This welding process
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 6 of 152
shall be fully, automatic. Each pipe shall then be hydrostatically tested in
the plant/mill and subjected to ultrasonic and radiographic testing of weld
seam and body of the pipe
1.4.4 Standard Specification for Welding in shop and field
1.4.4.1 All components of a standard shell, either straight or bent etc. shall be
welded, wherever possible by use of automatic are welding machine by
Submerged Arc welding process with alternating current. Hand welding
shall not be permitted except for sealing runs and such other minor works
at the discretion of the Engineer-in-Charge or his Representative. The
strength of the joint shall be at least equal to that of the parent material.
1.4.4.2 Samples of welded joints shall be prepared and tested in the presence of the
Engineer-in-Charge or his representative. The values once determined shall
be maintained throughout the work and if any modifications are to be
made, a written permission of the Engineer-in-Charge or his Representative
shall be obtained. Welding shall be carried out inside as well as outside.
1.4.4.3 All the shop and field welding shall conform to the requirements of IS 823
and IS 4353, IS: 816, I.S:3600 (part I).
1.4.4.4 All longitudinal and circumferential joints shall be welded as per respective
IS Codes. End preparation for such welding shall conform to IS: 2825
1.4.4.5 All circumferential welds involving plates of unequal thickness shall be so
kept that the inside surfaces of plates match to provide stream lined joints
without alternation in the internal diameter. As far as practicable welding
of dissimilar thickness of shells shall be carried out in the shops.
1.4.4.6 The welding shall be of the best workmanship free from flaws, burns, etc.
and the electrodes at the desired temperatures and dry. In order to maintain
a good standard in welding, welders shall be tested by the Contractor
before they are entrusted with the job. Qualification standard for welding
procedures welders and welding operation shall conform to the
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 7 of 152
requirements of IS: 7307 and IS: 7310. Periodical tests as regards their
competence and efficiency shall also be taken at intervals of about 6
months and those found inefficient shall be removed from the job. Only
those who pass the test shall be posted on the job. If an incompetent welder
has already welded some pipes all welding done by him previously shall be
fully checked by X-ray in addition to the regular X-ray inspections. The
defects if any shall be set right to the satisfaction of the Engineer-in-Charge
or his Representative. All such check tests and rectification of defects shall
be entirely at the cost of Contractor. No pipe or steel sections shall be
erected unless the work of the welder concerned has been proved to be
satisfactory. Site welds shall be done by specially selected welders.
1.4.4.7 A record shall be maintained showing the names of welders and operators
who have worked on each individual joint. Hand-welding if necessary shall
preferably be carried out by a pair of welders so that by observing proper
sequence distortion can be avoided. A joint entrusted to a particular
individual or a pair shall be as far as possible completed by them in all
respects including sealing run. No helper or other unauthorized person shall
be permitted to do any welding whatsoever.
1.4.4.8 The welded joint after welding should not become brittle or sensitive to
blows and there should be no loss of toughness due to welding or heat
treatment. The material after welding and heat treatment is to be tougher
than the base metal and is to retain its original ductility. No allowance will
be made for thinning or weld and the weld should at no point be less than
the nominal thickness of plate. Final welding of closure gaps should be
carried out within a temperature range of average air temperature +/- 80 C
as per Clause 6.3 of IS: 5822.
1.4.5.9 Upon receipt of the order and prior to the start of fabrication, the
Contractor shall submit to the Engineer-in-Charge or his Representative for
his approval the welding procedure method statement, he intends to use
in the workshop. Similarly, prior to the start of the filed welding, procedure
for the field welding must be submitted to Engineer-in-Charge or his
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 8 of 152
Representative for his approval. Manual welding shall be adopted only
when machine welding is not possible
1.5 Radiography of Weld in factory and field joints
1.5.1 Soon after welding, 15% of total longitudinally/spiral and circumferential
welded length of the weld at random for each pipe shall be radio graphed to
deter welding defects (except for the mill situated in habituated areas) as
per requirements of IS : 4853 and as directed by the Engineer-in-Charge or
his representative. However in such inhabited area ultrasonic testing with
graph shall be done in lieu of radiography test. This sampling will be at
random to ensure 100% coverage of junctions of longitudinal, spiral and
circumferential joints. If the results of such radiography fail to conform to
the requirements, the Contractor shall carry out at his own expense 100%
radiography test for the pertinent pipe as directed and fully satisfying the
Engineer-in-Charge or his representative. The permissible percentage
breakdown of radiography shall be as per IS Codes/Engineer-in-Charge's
instructions. Also the welded joints shall be tested as per clause 6.2, 6.2.1
and 6.2.2 of IS: 5822
1.5.2 For Mild steel pipes manufactured in factory/workshop fabricated from Hot
rolled coil jointed in field, the 15% of the field welded joints shall be
subjected to Radiography/ultrasonic test. All cross or T joints shall be radio
graphically tested. In case of field joints, if any out of the 15% of the
number of joints and T joints at random fails in Ultrasonic and radiography
test respectively, thrice the number of field joints shall be put to
radiography/ UT. Even after such radiography test, if any of the joint fails,
the radiography/UT of the 100% of the joints shall be carried out in this
stretch. All these additional testing shall be done by the Contractor at his
own risk and cost. In inhabited areas ultrasonic testing with graph shall be
done in lieu of radiographic tests.
1.5.3 The weld ripples or weld surface irregularities and slag etc., on both inside
and outside shall be removed by any suitable mechanical process to a
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 9 of 152
degree such that resulting radiographic contact due to any remaining
irregularities cannot mark or be confused with that of objectionable defect.
The radiograph shall be made in strict accordance with the latest
requirements and as per the latest and most efficient technique either with
X-ray or gamma ray equipment. The safety requirements during
radiography shall be in accordance with IS : 2598.
1.5.4 The Photographs are to be marked in such a way that the corresponding
portion of the welded seam can be readily identified. All radiographs will
be reviewed by the Engineer-in-Charge or his Representative to identify the
defect and determine those which must be removed. Defects that are not
acceptable shall be removed by chipping, machining or flame gouging to
sound metal and the resulting cavities shall be welded. After rectification,
the joint is to be radio graphed again to prove the quality of the repair. The
radiographs will be judged as acceptable by the Engineer-in-Charge or his
Representative based on the latest standards prescribed by the relevant
Indian Standards specification.
1.5.5 All X-ray shall be made with equipment and by personnel furnished by the
Contractor. The films shall be developed within 24 hours of exposure and
be readily accessible at all times for inspection by the Engineer-in-Charge
or his Representative. The Contractor shall provide for the use of the
Engineer-in-Charge or his Representative suitable X-ray viewing
equipment X-ray films shall be properly maintained by the Contractor for
handing over finally to the department on completion of the Contract. All
films shall be identified by the No. and chart prepared indicating location
of the joint each X-ray photo represents. In the event of additional
radiographic inspections required of any work associated with the pipe
erection, such inspection shall be performed by the Radiographer at the
discretion of the Engineer-in-Charge or his Representative at no extra cost
to the Engineer-in-Charge.
1.6 Radiographic Inspection
Volume-II Specif ications
Contractor Witness Divisional Engineer (PH-2) Page 10 of 152
1.6.1 General
a) The Contractor shall certify that the welding of pipes has been done only
by qualified welders with approved quality of Electrodes and electric
current (Voltage and amperage). The Contractor shall also make available
to the Engineer-in-Charge or his Representative a certified copy of the
qualification tests of each welder and welding operator. The Engineer-in-
Charge or his Representative shall have the right at any time to call for and
witness tests of welding procedure or of the ability of any welder and
welding operator.
b) Radiographic Inspection of welded joints
c) All welded joints to be radio graphed shall be examined in accordance with
IS : 2595 Code of Practice for Radiographic Testing
IS : 4853 Recommended Practice for Radiographic Inspection of Fusion
Welded Butt joints in Steel Pipes.
IS : 1182 Recommended Practices for Radiographic Examination of
Fusion Welded Butt-Joints in steel plates.
IS: 2598 Safety Code for Industrial Radiographic Practice.
The reinforcement on each side of all butt welded joints shall not exceed
1.5mm
d) A complete set of radiographs and records as described in IS: 2595 Clause
14, for each job shall be retained by the Contractor and kept on file for the
contract period. After contract period all such records shall be handed over
to the Engineer-in-Charge or his Representative at no extra cost.
e) Final acceptance of radiographs shall be based on the ability to see the
prescribed penetrameter image and the specified hole.
f) Sections of welds that are shown by radiography to have any of the
following types of imperfections shall be judged unacceptable and shall be
repaired by the Contractor at his won cost.
any type of crack, or zone of incomplete fusion or penetration,
any elongated slag inclusion which has length greater than 6 mm,
any group of slag inclusion in line that have a aggregate length greater than
thickness in a length of 12 times thickness, except when the distance
between the successive imperfections exceeds 6L where L is the length of
the longest imperfection in the group,
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 11 of 152
Rounded indications in excess of that specified by the acceptance standards
given earlier.
1.7 Tolerance
Tolerance for pipes in respect of diameter and straightness shall be in
accordance with IS: 3589 however negative tolerance in pipe wall
thickness is not permissible.
1.8 Shop Testing
1.8.1 After fabrication, but before application of lining and protective coatings
all pipes and specials shall be subjected to a shop hydraulic test as per
IS: 3589. Standard lengths of pipes shall be directly subjected to test and
non-standard pipe and elbows can be tested as standard pipe before
being cut to size.
1.8.2 Each pipe shall be filled with water and the pressure slowly and
uniformly increased by the manufacturer at hisown cost until the
required test pressure is reached.
1.8.3 The pipe to be tested shall be given a serial no. which shall be painted on
its inside together with details such as pipe No. shell thickness, diameter,
length etc. It shall be entered in the register to be maintained by the
Contractor. A copy of results of the tests shall be sent every week on
Mondays and another copy shall be sent along with the lot sent to the
site for laying. The pipe shall also be given a certification mark as per
IS Code: 3589 - 2001.
1.8.4 Prior to testing, the pipe shall be inspected thoroughly and all the
apparent defects in welding such as porosity etc. shall be repaired by
gouge and re-welding.
1.8.5 The hydraulic test shall be carried out under cover at the fabrication
shop, in the presence of and to the satisfaction of the Engineer-in-Charge
or his Representative or the inspection agency appointed by the
Engineer-in-Charge.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 12 of 152
1.8.6 For indicating the pressure inside the pipe an accurate pressure gauge of
approved make duly tested and calibrated for the accuracy of readings
shall be mounted on one of the closures which close the pipe ends.
1.8.7 The pipe shall withstand the test without showing any signs of
weakness, leakage, oozing or sweating. If any leak or sweating is
observed in the welded joints, the same shall be repaired by gouging and
re-welding after dewatering the pipe. The repaired pipe shall be re-tested
to confirm the specified pressure.
1.8.8 If any leak or sweating is observed in factory/mill made pipe shell, the
pipe under test shall be rejected temporarily. The Contractor shall stack
such rejected pipes separately in his yard. The Engineer-in-Charge or his
Representative shall inspect the same and after taking cuts if necessary,
shall determine the nature of repairs to be carried out there on and shall
then decide as to how and where they shall be used. No payment shall be
made for handling or carrying out repairs.
1.8.9 The Engineer-in-Charge or his Representative shall be supplied with two
copies of the results of all the tests carried out for which nothing shall be
paid.
1.9 Testing of Site Welded Joints
The welded joints shall be tested for Tensile test and bend test in
accordance with procedure laid down in IS No.3600 method of testing
fusion welded joints and weld metals in steel.
Test pieces shall be taken by the contractor from the welded joints at the
position on fabricated pipes pointed out by the Engineer-in-Charge or
his Representative.
The sample so taken shall then be cut to the exact shape and dimensions
and machined and handed over to the Engineer-in-Charge or his
Representative for testing. All the work upto and including machining
and arranging for test shall be done by the Contractors at his own cost.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 13 of 152
1.10 Transporting of Pipe & Specials etc.
1.10.1 All pipes and specials fabricated in the factory shall be transported to the
site of laying after shop testing & cleaning them internally. The loading
in the factory shall be carried out by means of either a crane, gantry or
with shear legs, so as not to cause any damage to the finished material.
Similarly, while unloading and stacking, great care shall be taken to
ensure that the material is not damaged or dented. The equipments to be
used for unloading will be different in different situations and in each
case the one approved by the Engineer-in-Charge or his Representative
shall be adopted. The material stacked at site shall be jointly inspected
by the Engineer-in-Charge or his Representative and Contractor and
defect or damage notice shall be repaired to the satisfaction of the
Engineer-in-Charge or his Representative before payment is admitted /
released.
1.10.2 Props of approved designs shall be fixed to the pipes during transit to
avoid undue sagging and consequent distortion. After the pipes are
carefully stacked, props may be removed and re-used for subsequent
operations. The stacking ground, both in the Contractor's yard and at the
site of laying shall be levelled and shall be selected in such a way as not
to get waterlogged during monsoon. If this cannot be done, the pipes
shall be supported on sleepers to avoid contract with wet earth and
subsequent rusting. In order to prevent sagging during transit, savings of
steel plates can be utilized by cutting to the required length and tacking
the same to the pipe ends, in place of props, if approved by the
Engineer-in-Charge or his Representative.
1.10.3 As explained in earlier paragraphs, materials such as pipes & tapers etc.
may be transported to the site of laying as soon as the material is
finished in all respects with the permission of the Engineer-in-Charge or
his Representative to avoid congestion in the Contractor's yard.
However, materials such as expansion joints, manholes with covers
composite bends, 'T' branches and other complicated materials etc. shall
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 14 of 152
be stacked in the Contractor's yard under his security arrangements until
they are required for laying (and jointing) in the field. In view of this,
the work of fabrication of such materials shall be properly synchronized
as far as possible with the laying operations.
1.10.4 Fabricated materials such as man-hole covers to be provided & fixed in
each section between the sluice valves and an other required places and
as desired by the Engineer-in-Charge and his Representative,
appurtenances such as S.V.'s P.R.V's, air valves etc. bolts, nuts, distance
pieces, flanges, saddles, collars bypass arrangements etc. shall all be
transported to the site of laying from the fabrication shop according to
the needs of the laying/operations only. As regards access roads, the
Contractor shall note that access road may lead upto some points on the
alignment. Therefore, the Contractor shall have to make his own
arrangement for connecting approaches to transport the pipes and other
equipments & specials etc. across country to the actual site of laying at
his own cost. Whatever may be the mode of transport he uses it shall be
incumbent on the Contractor to carry and stack the pipes, specials and
fitting along the alignment as close as possible to the site of laying.
1.11 Procedure for Receiving Steel Pipes
1.11.1 General
To ensure that the work of erecting pipes is not held up at any stage and
place, the Contractor shall maintain an adequate stock of standard
specials, flange rings, expansion joints, manhole covers, etc. and short
lengths of pipelines, etc. at site in his field stores, in consultation with
the Engineer-in-Charge or his Representative. Wherever possible, the
Contractor shall arrange one full month's requirement of pipes, specials,
etc. stacked along the alignment in such a way that no obstruction is
caused to the traffic, residents, or for repairs to other utilities.
1.11.2 Stacking of Pipes, Etc. and Inspection
The Contractor shall keep in each section a responsible representative of
his own to take delivery of the pipes, specials and appurtenances, etc.
transported from the fabrication stockyard or received from any other
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 15 of 152
work site to the site of laying and to stack along the route on timber
skids. Padding shall be provided between coated pipes and timbre skids
to avoid damage to the coating. Suitable gaps in the pipes stacked shall
be left at intervals to permit access from one side to the other. The pipes
specials, appurtenances so received on site shall be jointly inspected and
defects recorded, if any, such as protrusions, grooves, dents, notches,
damage to the internal coating etc., shall be pointed out immediately to
the Engineer-in-Charge or his Representative at the site and in the
acknowledgment challans. Such defects shall be rectified or repaired to
the satisfaction of the Engineer-in-Charge or his Representative entirely
at the Contractor's risk and cost. Contractor should also note that watch
and ward of all materials is of the Contractor and if something is lost
from the site and is paid, its cost shall be recovered from the Contractor.
1.11.3 Handling of Pipes, Special Appurtenances Etc.
It is essential to avoid damage to the pipes, fittings and specials, etc. or
their coatings & lining at all stages during handling. The pipes and
specials shall be handled in such a manner as not to distort their
circularity or cause any damage to their surface treatment. Pipes shall
not be thrown down from the trucks nor shall they be dragged or rolled
along hard surfaces. Slings of canvas or equally non-abrasive materials
of suitable width of special attachment shaped to fit the pipe ends shall
be used to lift and lower the pipes to prevent damage to the coatings
provided. Great care shall be taken in handling the pipe right from the
first operation of manufacture until they are laid and jointed. The
Contractor will provide temporary props in order to prevent any sagging
of the pipes while they are stacked in their yard and while transporting
to the site of delivery, i.e. laying. The props shall be retained until the
pipes are laid. If at any time these props are found to be dislodged or
disturbed, the Contractor shall immediately reinstate them in such a way
that the true shape of the pipe shell or specials is maintained to the
satisfaction of the Engineer-in-Charge or his Representative. No
defective or damaged pipe or special shall be allowed to be used in the
work without rectification to the coating shall be repaired by the
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 16 of 152
Contractor at his own cost to the original shape and to the satisfaction of
the Engineer-in-Charge or his Representative.
1.11.4 Dents
Whenever any dent, i.e. a significant alteration of the curvature of the
pipe shell is noticed, the depth of the dent shall be measured between the
lowest point of the dent and the pipe shell curvature line. All dents
exceeding 2 percent of the outer diameter of the pipe shall be removed
by cutting out a cylindrical portion of the pipe and replacing the same by
an undamaged piece of the pipe. The Engineer-in-Charge or his
Representative may permit insert of patching if the diameter of the patch
is less than 25% of the nominal diameter of the pipe. Repairs by
hammering with or without heating shall not be permitted. Any damage
to the coating shall also be carefully examined and rectified fully by the
Contractor at his own cost as per IS: 5822.
1.11.5 Marking
1.11.5.1 The component parts of the pipes shall be carefully marked as per IS
Codes for identification in the field in such a way that these could be
located on the field.
1.11.5.2 The marking operation shall be conducted with full size rulers and
templates.
1.11.5.3 The plates used for fabrication of pipes shall be laid out in such a way
that when the shells are completed one set of original identification
markings for the material will be plainly visible. In case these markings
are unavoidably cut out, they shall be accurately transferred by the
Contractor to a location where these markings will be visible on the
completed work.
1.11.5.4 Two copies of these details shall be furnished to the owner free of cost.
1.11.5.5 No separate payment will be made for these markings and the rates
quoted shall be deemed to include the cost of such markings.
1.12 Laying of Pipeline
1.12.1 General
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 17 of 152
1.12.1.1 After having carried out excavation of trenches as is explained in these
specifications else ware the loose materials from the sides or the edges
of the trench shall be prevented from falling inside the trench. Properly
designed bedding as per site conditions for resting of the pipes shell then
be provided before starting with the laying. The excavation of trenches
for laying of M.S. pipe shall be as per Clause 4.2.1 of IS: 5822. Design
of bedding with respect to installation condition shall be submitted by
the Contractor for approval by the Engineer-in-Charge
1.12.1.2 When welding is to be carried out with pipes in the trench additional
excavation shall be provided all round the pipe at the position of the
joint for facilitating in the welding.
1.12.1.3 Unless specified otherwise, the M.S. pipeline shall be buried with
minimum cover of 1.0 meter above socket top as shown on drawings to
be submitted by the Contractor and approved by the Engineer-in-Charge.
No material shall be erected unless it has been previously passed by the
Engineer-in-Charge or his Representative.
1.12.1.4 Where pipes are to be laid to curves, the deflection at each joint shall not
exceed one degree. For sharper curves specifically made bends shall be
provided
1.12.2 Laying Programme
1.12.2.1 The Contractor shall submit a detailed bar chart for procuring and laying
of the pipelines, which shall be subject to the Engineer-in-Charges
approval. In preparing this bar chart, the Contractor shall plan his
activities such that the laying of pipes shall closely follow the
procurement schedule and no pipes shall remain stacked at site for a
period more than one month or as decided by the Engineer-in-Charge.
The Contractor shall also submit procurement schedule of pipes, specials
and fittings.
1.12.2.2 Together with the bar chart he shall also submit a methodology
describing how he will carry out this work within the contractual period
and the required resources in terms of construction equipments and other
facilities that shall be utilized to complete the works.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 18 of 152
1.12.2.3 Before commencing the work of pipe laying, the Contractor shall study
the approved plan and L-section of the pipeline for the section
concerned. He shall also study the details of laying i.e. underground or
above ground. The under ground pipeline shall be laid on properly
designed bedding as shown in the drawing submitted by the Contractor
and approved by the Engineer-in-Charge or his Representative. The
difference in depth due to uneven excavations by the Contractor shall be
made up by sand cushioning / C.C. (M-10) as per direction of Engineer-
in-Charge. For laying of pipes below ground the Contractor shall also
follow specifications/instructions as are given in these specifications for
Excavation and Barricading etc. However, no pipeline shall cross
beneath the bed of nallahs/drains the width for the pipe line bridge shall
be such as to accommodate the pipes and facilities.
1.12.2.4 All M.S. pipe laying, welding and testing etc. shall be as per Clause
contained in IS:5822 and to the satisfaction of the Engineer-in-Charge or
his representative.
1.12.2.5 Erection of pipes/fabricated shells shall be carried out by the Contractor
who shall equip himself at his own cost, with all necessary tools,
machinery, equipments, generators, testing equipments, test plates and
piping etc. and labour required for the purpose. The pipeline shall be
constructed in lengths with a separate full time gang working on each
length/section.
1.12.3 Handling of pipes and specials
Coated pipes and specials that are to be stored / kept on supports shall
bear on the uncoated ends only. If bearing of coating is employed the
supports shall be not less than 20 cm (8 inches) wide and so arranged to
prevent damage to the coating. During handling of the pipes and fittings,
coating shall be protected not less than 20 cm wide and placing strips of
heavy belting or other approved sheet materials not less than 20 cm wide
under all ropes or fastening.
1.12.4 Sand Bedding (Wherever Required)
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 19 of 152
Where site situations require necessity of Sand beddings, the sand
bedding of minimum 200 mm thickness shall be provided below pipe,
prior to laying the pipe in trenches. It shall be completed with a light
hand rammer. Any reduction in thickness due to composition shall be
made up by adding sand during ramming. For the purpose of the
bedding under this item only screened fine sand or grain size not larger
than 2mm shall be used. The sand shall be clean, uncoated and free form
clay lumps, injurious amounts of dust, soft particles, organic matter,
loam or other deleterious substances. Nothing extra shall be paid for
sand bedding or any other type of bedding for resting the pipes in
trenches.
If the sand supplied is unclean it shall be washed. In no case shall sand
containing more than 3.5% by dry volume or 5% by wet volume of clay,
loam or silt be accepted. Tests specified for determining silt in sand and
organic impurities as described in IS:383 shall apply. Sieved and washed
sand shall be stored on the works in such a manner as to prevent
intrusion of any foreign matter, including coarser particles of sand or
any clay or metal or chips. Tests as indicated above shall be performed if
called for by the Engineer-in-Charge or his Representative at the
expense of the Contractor.
During the work of providing sand bedding and laying the pipeline over
it, loose material from the sides or edges of the trench shall prevented
from falling inside the trench, by providing shoring and taking other
measures. Also where necessary, trench shall be kept dry by pumping
out seepage leakage waters continuously at no extra cost to the
Engineer-in-Charge.
1.12.5 Lowering and Jointing
Before pipes are lowered the trenches shall be examined as per Clause
4.2 & 4.2.1 of IS:5822. Also pipe handling and inspection shall be done
as per Clause 5.1 to 5.2.5. Pipe laying below ground shall be as per
Clauses 8.1.1 to 8.1.2.1 and pipe laying above ground shall be as per
Clause 8.3.1 of IS:5822.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 20 of 152
At places where shoring timbering is provided the pipe shall be lowered
into the trenches by removing only one or two struts at a time. It shall be
seen that no part of the shoring is disturbed or damaged and, if
necessary, additional temporary struts may be fixed during the lowering
operations. In case of laying of pipe is not damaged in any way during
the lowering operations. In case of laying of pipes and other situations
also it shall also be necessary to see that the coating of pipe is not
damaged in any way during the lowering and assembling. After the pipe
is lowered into the trench, it shall be laid in correct line and level by
using the leveling instruments, sight rails, theodolite etc. Care shall be
taken to see that the longitudinal joints of two consecutive pipes at each
circumferential joints are staggered by 300 as mentioned in Clause 8.1.2
of IS:5822. While assembling the pipes, the ends shall have to be
brought close enough to leave a uniform gap not exceeding 3mm. If
necessary a marginal cut may be taken to ensure a close fit of pipe faces.
For this purpose, only experienced cutters who can make uniform and
straight cuts shall be permitted to cut the faces of the pipes. No extra
payment shall be made for such marginal cutting. There shall be no
lateral displacement between the pipe faces to be joined. If necessary,
spiders from inside and tightening rings from outside shall be used to
bring the two ends in perfect contact and alignment. It may also be
necessary to use jacks for this purpose. In no case shall hammering or
longitudinal slitting be permitted. When the pipe is properly assembled
and checked for correct line and level, it shall be firmly supported on
wooden beams and wedges and tack welded. Some portion of the trench
may be refilled at this stage so as to prevent the pipeline from losing its
alignment. The tack welded circumferential joints shall then be welded
fully. Only experienced welders, who will be tested from time to time,
shall be permitted to carry out the welding work.
On Completion of the pipe jointing and external protection against
rusting the trench and the welding pits shall be cleaned filled and
compacted in 150mm layers as per direction of the Engineer-in-Charge.
1.12.6 Precautions against Floatation
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 21 of 152
When the pipeline laid underground in a long narrow cutting gets
submerged in water collected in the trench of cutting, it is subjected to
an uplift pressure due to buoyancy and is likely to float if completely or
partly empty. In the design of pipelines, provision is to be made to
safeguard against floatation, providing sufficient overburden or by
providing sufficient dead weight by means of blocks etc. Factor of safety
for calculation for check against floating shall be taken as 1.2.
In the case of works extending over one or more monsoon seasons,
however, special care and precautions shall be necessary during the
progress of work on this account. The Contractor shall close down pipe
laying operations well in time for the monsoon. The work of providing
blocks, refilling the earth to the required level, compacting the same, etc.
shall always be done as soon as the pipeline in the cutting has been laid.
The Contractor shall see that the water shall not be allowed to
accumulate in open trenches. Where work is in an incomplete stage,
precautionary work, such as blank-flanging in the open ends of the
pipeline and filling the pipeline with water etc. shall be taken up as
directed by the Engineer-in-Charge or his Representative.
Such works shall be to the Contractors account and no separate
payment shall be made for the same. The Contractors rate for pipe
laying shall be deemed to include such precautionary measures against
floatation.
Protection of the pipeline against floatation shall be suitably design and
adopted in the bid.
1.12.7 Refilling of trenches
On completion of the pipe laying operations in any section, for a length
of about 100m and while further work is still in progress, refilling of
trenches shall be started by the Contractor with a view of restricting the
length of open trenches. Pipe laying shall closely follow the progress of
Trench Excavation and the Contractor shall not permit unreasonably
excessive length of trench excavation to remain open while awaiting
testing to the pipeline. If the Engineer-in-Charge or his Representative
consider that the Contractor is not complying with any of the foregoing
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 22 of 152
requirements, he may prohibit further trench excavation until he is
satisfied with the progress of laying and testing of pipes and refilling of
trenches. Only soft earth and murrum of good quality free from stones
larger than 75mm in size and free from boulders, roots, vegetation etc.
shall be utilized after the lumps are broken for filing in around the pipes
for at least 30 cm all around for pipes less than 1200mm diameter and
d/4 for pipes greater than 1200 diameter. Filling shall be done in layers
not exceeding 150mm and compacted to 95 percent of the maximum dry
density as per part VII of IS: 2720. The excavated material nearest to the
trench shall be used first. Care shall be taken during backfilling, not to
injure or disturb the pipes, joints or coating. Filling shall be carried out
simultaneously on both sides of the pipes so that unequal pressure does
not occur. Walking or working on the completed pipeline unless the
trench has been filled to height of at least 30cm over the top of the pipe
except as may be necessary for tamping etc. during backfilling work.
The remaining portion of the trench may be filled in with a mixture of
hard and soft material free from boulders and clods of earth larger than
150mm in size if sufficient quantity of good earth and murrum are not
available. Filling in shall be done in layers not exceeding 150mm in
thickness accompanied by adequate watering, ramming etc. so as to be
compacted 95% of the maximum dry density as per part VII of IS:2720.
Water contents of the soil shall be as near the optimum moisture content
as possible. The trench shall be refilled so as to build up to the original
ground level, keeping due allowance for subsequent settlement likely to
take place.
To prevent buckling of pipe, pipes shall be strutted from inside while the
work of refilling is in progress, for which no separate payment shall be
made separately.
Strutting shall be done by means of strong spiders having at least 6 arms,
which shall be sufficiently stiff to resist all deformation of pipes. Spiders
shall be provided at a maximum interval of 2m. Strutting shall be done
in such a way that inside lining is not damaged.
Removal of all surplus will be the responsibility of contractor and the
same has to be removed immediately after completion of backfilling,
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 23 of 152
leveling and dressing etc. failing which it shall be removed at
contractor s cost.
If suitable material for refilling is not available from excavation the
Contractor shall bring good earth, murrum of approved quality as
directed by the Engineer-in-Charge. Nothing extra shall be paid for
bringing earth from outside for filing upto final ground level shown in
the approved L-section.
No mechanical plant other than approved compacting equipment shall
run over or operate within the trench until backfilling has reached its
final compacted level or the approval of the Engineer-in-Charge or his
Representative has been obtained.
Subsidence in filling in: should any subsidence take place either in the
filling of the trenches or near about it during the maintenance period of
12 months from the date of completion of the Contract, the Contractor
shall make good the same at his own cost or the Engineer-in-Charge
may without notice to the Contractor, make good the same in any way
and with any material that he may think proper, at the expense of the
Contractor. The Engineer-in-Charge or his Representative may also, if
he anticipates occurrence of any subsidence, employ persons to give his
timely notice of the necessity of making good the same, and the
expenses on this account shall be charged to the Contractor.
1.12.8 Welding
1.12.8.1 Unless specified otherwise all M.S. pipes and specials shall have butt-
welded joint. Where shown on drawings, flanged joints or collar sleeve
collar. Collar sleeve joints shall be provided.
1.12.8.2 The welding of pipes in the field should comply with IS: 816. Electrodes
for welding should comply with IS: 814. The welded joints shall be
tested in accordance with IS: 3600 (Part-1) and other relevant Codes.
One test specimen taken from at least one field joint out of 10 shall be
subjected to test as per Clause 6.2, 6.2.1, 6.2.2 and 6.3 of IS:5822 i.e. the
Contractor shall carry out all test for welding as are described under
Clause 6 of IS:5822.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 24 of 152
1.12.8.3 Except for routine welding of joints, no other work shall be done in the
absence of Contractor s engineer, either during the day-time or at night.
1.12.8.4 Chipping shall not be kept in arrears for more than 15 joints.
1.12.8.5 Design for saddle pieces shall first be got approved from the Engineer-
in-Charge and then the saddle pieces shall be fixed in position as per
approved drawings after checking bolts holes, by means of templates.
Entire responsibility for proper design/shape for the saddles shall be of
the Contractor.
1.12.9 Preparation of Pipe faces
Preparation of pipe faces for welding shall be done as per Clause 5.2.5
of IS:5822.
1.12.10 Saddle Supports
Unless otherwise specified pipeline shall be underground. However in
certain reaches it shall be on R.C.C. or steel saddle supports spaced at
suitable intervals. The material and construction of R.C.C./ Steel
structures such as saddles, anchor blocks, crossings etc. associated with
the work of pipeline shall conform with the relevant I.S. Codes, good
engineering practice and as directed by the Engineer-in-Charge or his
Representative. The pipes to be laid at saddle supports shall be erected at
mean temperature. Saddle supports shall either be sliding type or fixed
type, detailed design and drawings including fabrication drawing for
which shall be supplied by the Contractor. In case of sliding support, the
pipe shall be allowed to slide freely over the plate embedded in the
saddle. Alternatively to achieve fixity, the pipe shall be anchored by
providing suitable anchor bases with steel clamps.
In such areas subjected to floods the contractor shall lay pipes on pillars
having unsettlable strong footings and the invert of the pipe shall
preferably be kept about 0.3 meter above HFL subject to approval of
Flood control department or any other concerned authority. Nothing
extra shall be payable or recoverable on account of change in the
proposed invert levels or location of the pipeline, if any.
The Contractor shall adopt these specifications for other pipes also
where the ground levels are low.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 25 of 152
Below the pipes the Contractor shall provide necessary bedding/ saddle
supports required as per structural designs, which shall be got approved
from the Engineer-in-Charge or his Representative.
1.13 General Sequence of Operations
Anchor blocks shall be constructed before commencing the pipe laying
work in any section as per IS:5330. The construction of the thrust/
anchor blocks shall be carried out in 3 stages: in the first stage the lower
part upto 150mm below the invert of the pipeline including concrete
chairs to support it, shall be constructed in the second stage the pipeline
on this part of the block shall be laid; and lastly, the remaining block
around and over the pipeline with clamps shall be constructed.
1.14 Specials Fabrication
1.14.1 Generals
Specials, such as tees, Y-pieces, bends (single or composite), tapers,
tees, blank flanges and gap pieces, collars, expansion joints, man-hole
covers etc. shall necessarily be in steel and shall be manufactured as per
IS : 7322 standards and applicable codes and tested in the same manner
as the pipes. Small branches, single piece bends etc. may be fabricated at
the site. Care shall be taken to ensure that the fabricated fittings have at
least the same strength as the pipeline to which they are to be joined and
tested.
1.14.2 Bends
1.14.2.1 Bends shall be fabricated taking into account the vertical and horizontal
angles for each case.
1.14.2.2 The bends shall have welded joints and the upstream and downstream
ends of each bend shall have a straight piece of variable lengths as
required at site.
1.14.2.3 Bends shall be designed with deflection angle of maximum 10 deg
between segments.
1.14.2.4 When the point of intersection of horizontal angle coincides with that of
a vertical angle, or when these points can be made to coincide, a single
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 26 of 152
combined or compound bend shall be used, designed to accommodate
both the angles. The combined bend should have a pipe angle equal to
the developed angle, arrived at from appropriate formula.
1.14.2.5 All joints in bends and other specials shall be thermally stress relieved as
per Technical requirements / IS codes.
1.14.2.6 Details of thrust collars anchor bolts, holding down straps, saddle plates
shall be furnished by the Contractor which will have to be got together
with full specifications on contractor s fabrication drawing which will
have to be got approved from the Engineer-in-Charge or his
Representative before use at site.
1.14.3 Manholes
1.14.3.1 Manholes of sizes approved by the Engineer-in-Charge shall be
provided at locations generally 1 km apart, with additional manholes at
both the sides of butterfly vales/sluice valves. Manholes in the pipeline
above ground shall be placed in suitable position as agreed to with the
Engineer-in-Charge or his representative in the top quadrant.
1.14.3.2 The contractor shall fabricate different parts of manhole in conformity
with relevant IS specification, well-established practices and as directed
by the Engineer-in-Charge or his Representative. The Contractor shall
also submit designs / drawings of the manholes with covers.
1.14.4 Closing or Make Up Sections.
Closing or makeup sections shall be fabricated by the Contractor to
permit field adjustments in pipeline length to compensate for shrinkage
in field welded joints, differences between actual and theoretical lengths
and discrepancies in measurements. The Contractor shall initially plan
the positions of closing gaps and submit proper drawings showing the
materials/specials, which he shall be providing for closing of each gap at
his own cost.
1.14.5 Heads / Clousers
Two types of closures/ heads are used in pipelines depends on their
locations viz.:
a) Closures for manhole covers and
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 27 of 152
b) Blank flanges either of flat plate design of dished hemispherical
closures. These shall be properly designed and provided by the
contractor at his own cost depending on locations where to be used.
1.14.6 Flanges
Flanges shall comply with IS: 7322. The nominal pressure rating shall
be at least equal to the highest pressure rating of pipes or fittings to
which they are attached.
Flanges shall be properly designed and provided at the end of pipes or
special where sluice valves, blank flanges, tapers and other flanged
specials have to be introduced. The Flanges received from the
manufactures will have necessary bolt holes drilled to IS: 1538 (part VI).
The contractor shall assemble the flanges in the exact position by
marginal cutting, if necessary, so as to get the desired position of the
sluice valves and other specials and fittings etc. either vertical or
horizontal and shall then fully weld the flanges from both sides in such a
manner that no part of the welding protrudes beyond the flanges and if
the Engineer-in-Charge or his representative orders that such protrusions
shall be removed, the contractor shall file or chip them off. If required
and when ordered by the Engineer-in-Charge or his representative, the
contractor shall provide and weld gusset stiffeners, as directed on site.
The drilling pattern shall be matching with the drilling pattern of flanges
of valves and other fittings.
1.14.7 Blank Flanges
Blank flanges of suitable thickness shall be provided at all ends left
unattended for the temporary closure of work and also for
commissioning a section of the pipeline or for testing the pipeline laid.
For temporary closures, non-pressure blank flanges consisting of mild
steel plates, tack welded at the pipe ends may be used. For pipes
subjected to pressure, the blank flanges or domes suitably designed as
per site requirements shall be provided.
1.15 Linings and coatings of rising main
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 28 of 152
1.15.1 These specifications cover the requirements of providing materials and
application of cement mortar lining and coating at works applied by a
centrifugal spinning process as per IS: 3589 (Annexure-A). The
waterway of the M.S. pipes & fittings shall be completely covered with
specified mortar. The mortar lining & coating shall be completely free
from cavities or visible air bubbles and pinholes and shall be thoroughly
compacted throughout. The consistency of mortar and time and speed of
centrifuging of the pipe shall be so adjusted that the segregation of the
sand and cement is not there. The mix used for cement mortar lining
shall be 1:2 (1 Cement: 2 Sand), 25mm thick with 6 mm dia longitudinal
bars (24 Nos.) & 3.15 mm hard drawn wires @ 5 cm c/c up to 30 cm on
the inner surface on the both edges of pipe. The work shall be started
only after thorough cleaning of the pipes and sand blasting to near white
(SA-2.5 Swedish standard) and obtaining the written approval of the
Engineer-in-Charge or his representative in this respect. Before starting
the cement lining work, the Contractor shall also ensure that all related
works required are completed by him. Coating outside shall be in
cement mortar 1:3, 25mm thick including the cost of lining steel of 6
mm longitudinal bars (24 Nos.) and 3.15 mm hard drawn wire wound
circumferentially @ 4 cm centre to centre on the outer surface
throughout the length.
1.15.2 General
Engineer-in-Charge or his Representative shall have the right to inspect
the sources of materials, the operation of procurement and storage of
materials, Cement mortar batching and mixing equipment and the
quality control system. Such an inspection shall be arranged and the
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 29 of 152
Engineer-in-Charge or his Representative and approval obtained prior to
starting of lining or coating work.
1.15.3 Surface Finish
The surface of cement mortar lining and coating shall be uniformly &
perfectly smooth and shall be free from voids. The lining and coating
shall not have flaky areas. It shall not be crumbly and shall not have
waves or grooves and shall also conform to Clause IS specifications.
Pipe shall not be dispatched until 21 days have elapsed since the date of
lining.
1.15.4 Keeping Circulatory During Lining or coating.
During the processes of lining or coating the surface of the MS Pipes,
the Contractor shall ensure that roundness of the pipes is maintained.
1.15.5 Hand Application of Mortar Lining and coating for field joint
a) Hand placed mortar shall have a uniform and smooth surface
with smooth transitions to adjacent centrifugally placed linings.
b) Cement mortar lining and coating of bends, specials, areas
closely adjacent to valves and other such places where
centrifugal placing may not be practical shall be performed by
hand. The Engineer-in-Charge or his Representative may order
the correction for any defect by hand application.
c) Cement mortar for hand work shall be of the same materials as
the mortar for machine placed lining or coating.
d) The areas to be lined or coated shall be thoroughly cleaned as
specified earlier and, if necessary, shall be moistened with water
/ cement grout immediately prior to placing the hand-applied
mortar.
e) Steel finishing towels shall be used for the hand application of
cement mortar, except at bends the outer edge of hand trowelled
areas may be brushed in order to reduce the abutting offset.
1.15.6 Special Requirements at Laterals and Service Connections
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 30 of 152
Lateral and connections to the pipe that is being lined or coated shall not
be left obstructed by the lining operations.
Before the lining or coating is placed, the openings in the pipeline
leading to air valves, blow offs, manholes and appurtenances, as well as
to laterals and connections that transmit pressure to carry water from the
pipeline, shall be temporarily covered or plugged with suitable devices.
These shall be removed later without damaging the Cement mortar.
1.15.7 Responsibility of Engineer and Contractor
The entire procedure of applying cement mortar lining or coating shall
be subject to continuous inspection by the Engineer-in-Charge or his
Representative but such inspection will not relieve the Contractor of his
responsibility to furnish material and perform work in accordance with
this specification. All cement mortar linings or coatings not applied in
accordance with this specification shall be subject to rejection by the
Engineer-in-Charge. Lining or coating so rejected shall be removed and
replaced by the Contractor at his own expense. A manual visual
inspection of the lined / coated pipe shall be by means of CC TV to
determine the quality of the lining and to identify detective areas in
linings for repair. The contractor shall procure/hire suitable equipment
required for his purpose at his own cost.
1.15.8 Defective L ining
Defects in lining or coating including but not restricted to sand pockets
such as voids, over sanded areas, blisters, cracked and dummy areas, and
thin spots shall be removed, and the area shall be repaired by hand
application to the full required thickness of the mortar lining or coating.
Defective areas encompassing the full diameter of the pipe shall be
replaced by machine whenever practical. Defective lining or coating
rejected after initial set shall be replaced or repaired by the most
practical method as determined by the Engineer-in-Charge or his
representative.
1.15.9 Guarantee
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 31 of 152
If on examination, the Engineer-in-Charge or his Representative finds in
the cement-mortar lining work within defect liability period after final
completion and acceptance of the Contract work evidence of defective
materials or workmanship as defined in this specification, then the
Contractor shall perform the remedial work at his own expense in a
manner acceptable to the Engineer-in-Charge.
The inside coating shall also not contain any constituent soluble in
drinking water or any ingredient, which could impart any taste or
whatsoever to potable water after sterilization and suitable washing of
the mains.
1.16 Cleaning and Commissioning of the Pipeline
Upon completion of a newly laid main, the main shall be initially
flushed clean and then disinfected by the Contractor at his cost as
directed by the Engineer-in-Charge or his Representative.
It is expected from the Contractor that he will lay only thoroughly
cleaned pipes during the process of laying of pipes and shall not leave
any tool or brick bats etc. in the line. Also when laying is not being done
he will keep the open ends closed with temporary blank flanges so that
nothing can enter the pipe.
For final flushing and cleaning, the department will allow water from
one of its mains for two fillings only. For third filling if required,
Contractor will be charged at prevailing commercial rate at the time of
flushing/cleaning. The main shall be flushed prior to disinfection.
1.17 Distance indicators and Markings
The Contractor shall supply and fix indicators at all points of change of
direction, at all valves and at every one Kilometer intervals along the
buried pipeline. Indicators shall consist of 10 cm x 10cm precast
concrete post 1.25 meter long, set 0.75 meter into the ground and
painted white above ground level. The description shall be written in
blue at one face of the precast post.
In case of the pipeline laid above ground details such as chainages,
invert levels of pipe, appurtenance number, pedestal / saddle number etc.
shall be suitably marked either on the pipeline or the supporting
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 32 of 152
structure etc. in distinct colour. The Bidder/Contractor shall include the
cost of this in his rates for the other items.
1.18 Application Guideline for Liquid Epoxy certified for potable Water
application - Internal Lining of Drinking Water Pipeline
1.18.1 Scope:
This specification sets minimum standard requirement for shop and field
applied solvent free liquid epoxy lining used in Potable water supply
pipelines
1.18.2 Requirements:
1.18.2.1 Equipments: equipments for the blast cleaning, Airless machine for the
application of the coatings.
1.18.2.2 Quality and safety: Material furnished shall meet the specifications. All
necessary precautions shall be taken to protect personnel and property
from accidents due to falls, hazardous materials, fire explosion, and
other dangers.
1.18.2. 3 Coating System: Solvent free liquid epoxy coating will be used.
Coating should meet following physical and performance requirements.
Sr. No.
Product Property Minimum Value accepted
Test Method
1 Dry Film Thickness Min. 406 microns* SSPC PA 2 2 Adhesion to Steel > 1400 psi ASTM D-4541 3 Volume Solid 100% 4 Relative Humidity
during application of lining
< 85 %
5 Hardness Minimum 70 . Barcol Model GYZJ 925 Impressor.
ASTM D 2583
6 Impact Resistance Direct impact approx 2 Joules
ASTM D 2794
7 Suitability for drinking water
Certification for use with potable water according NSF / ANSI Standard 61 or Australian AS/NZ 4020 or BS 6920*. With certification for the manufacturing facility as well
8 Immersion No film defect after 8000 hrs of exposure
ISO 2812 Part 2 Determination of
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 33 of 152
resistance to liquids Deionised Water @ 40C
9 Abrasion Average of 130mg weight loss per 1000 cycles using CS10 wheels and a 1Kg loading.
ASTM D4060 - "Abrasion Resistance of Coatings via the Taber Abraser"
*As per standards AWWA C210 and IS 3689
1.18.2.4 Coating Application:
1.18.2.4.1 Surface preparation: Surface shall be blast clean with abrasive blasting
materials like sand or copper slag to SSPC SP Standard 10 or SA 21/2
with surface profile 50 75 microns. Surface should be free from dust,
oil, and other contaminations. Surface should be coated within 4 hours
of blasting.
1.18.2.4.2 Application of Coatings: Prior to application of the coatings surface
should once again clean with blowing dry air to ensure the removal of
all dust and other contaminants. The coating shall be applied with airless
machine as per the recommendation of the coating manufacturer.
Desired film thickness of the coating can be built up using wet on wet
application technique with help of wet film thickness gauge to check wet
film thickness. The dry film thickness of the coating should be minimum
406 as per AWWA C210 and IS 3589 standards. Coating should be
uniform and smooth in appearance and free from defect. Coated surface
shall not be touched at least for 4 hours. The wet coating shall not be
contaminated with particles such as blowing sand, insect, or other
foreign material.
In case small areas, coating can be applied using roller and brush.
Desired dry film thickness can be achieved using wet on wet application
technique or in number of coats.
1.18.2.4.3 Inspection of the Coating: The Coating system will be inspected
visually for uniformity, thickness, blister, pinholes etc. all imperfections
shall be identified and marked for repair.
1.18.2.4.4 Electrical inspection for continuity: After curing, but prior to
installation, the coating system applied to the pipe shall be tested for pin
holes according to the procedure and using the voltage setting outlined
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 34 of 152
in NACE RP0188-99 for the specified thickness. Any pinholes indicated
by the detector shall be marked with chalk to identify the area to be
repaired.
1.18.2.4.5 Repair of the Coating: All the damage areas requiring patching shall be
cleaned of coating by hand or power tool like surface grinders with
appropriate sanding disc. Steel surface area should be dry, cleaned.
Coating will be applied with the trowel or with roller if the surface area
is very small. Patches shall overlap the surrounding undamaged coating
by minimum 19 mm (). Repair shall be subject to inspection.
1.18.2.4.6 Testing: test panels shall be made following similar surface and coating
application procedure and send to reputed laboratory to check
performance parameters like adhesion, and other properties.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 35 of 152
CHAPTER 2: Valves
2.1 SLUICE VALVE WATER APPLICATION
Up to 300 mm The sluice valves shall generally conform to IS 14846 / DIN 3352/BS 5163, with length over flanges as per PD of IS 14846 corresponding to BS EN 558 / ISO 5752 Basic Series 3:
Component Material of construction Body / Bonnet /Hand wheel Ductile Iron GGG 40 / IS 1865 Gr. 400/15 Wedge (fully rubber encapsulated)
Ductile Iron GGG 40 / IS 1865 Gr. 400/15 + EPDM
Spindle Non rising; Stainless Steel AISI 316/AISI 420 Spindle Nut (Replaceable) Aluminium Bronze, AB2 (Forged)/Brass Stem seal Multi-tiered NBR (Nitrile) O ring Fasteners High tensile steel, hot dip galvanized Flange Drilling BS EN 1092 2 PN 10 / 16 Painting / Coating Inside & Outside epoxy powder coated; DFT
minimum 250 micron, shade RAL 5005 (BLUE) 350 to 600 The sluice valves shall be Glandless and generally conform to IS 14846/BS 5163.
Component Material of construction Body / Door / Dome Ductile Iron GGG 40 / IS 1865 Gr. 400/15 Spindle Non rising; Stainless Steel AISI 316/420 Body seat / Door face (rings to be press fitted and riveted; no screws allowed)
Gun metal: IS 318 Gr. LTB 2/Resilient seat
Rivets Soft annealed brass Spindle Nut Gun metal: IS 318 Gr. LTB 2/Brass Stem seal (glandless) EPDM/NBR Fasteners Carbon steel, hot dip Galvanised Flange Drilling IS 1538 Table 4 & 6 or BSEN 1092-2 PN 10 / 16
Accessories: Ball thrust bearings Required: SKF or equivalent Enclosed spur gear box If Required: CI with IP 54 protection;
Make - MASTERGEAR INDIA / AUMA 700 to 1500 The sluice valves shall generally conform to IS 14846.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 36 of 152
Component Material of construction Body / Door / Dome Ductile Iron GGG 40 / IS 1865 Gr. 400/15 or 500/7 Spindle Non rising; Stainless Steel AISI 316 / 410 Body seat / Door face (rings to be press fitted and riveted; no screws allowed)
Gun metal: IS 318 Gr. LTB 2
Rivets Soft annealed brass Spindle Nut Gun metal: IS 318 Gr. LTB 2
Stem seal Gland & Stuffing box type with hemp packing Fasteners Carbon steel Flange Drilling IS 1538 Table 4 & 6 PN 10 / 16
Accessories: Back Seat Bush Required: Halprene on bronze Ball thrust bearings Required: SKF or equivalent Enclosed spur / worm gear box Required: CI with IP 54 protection;
Make - MASTERGEAR INDIA / AUMA PAINTING & COATING (for 350 mm and above): Pre inspection: 1st Step Surface Preparation Blast cleaning to near white - SA 2 Grade
Post inspection, if applicable 2nd Step Application of Finish Coat One coat of epoxy coating (Shade: RAL 5005, Blue) Note: Liquid epoxy coating should be done by appropriate equipment
inside a proper paint booth, conforming to AWWA C 213. Manufacturer should be able to provide certificate from WRAS
(U.K.) stating suitability of the above paint in drinking water application.
The total DFT should not be less than 250 micron. Note: Manual operation by hand wheel (thru intermediate enclosed spur gear box, if applicable). Motorised operation by means of electrical actuator (thru intermediate gear box, if applicable). GENERAL
Volume-II Specif ications
Contractor Witness Divisional Engineer (PH-2) Page 37 of 152
1. Hydro testing:
PN 1.0 PN 1.6 Criterion Seat test (Kg/cm) 10 16 Drop - tight Body test (Kg/cm) 15 24 No leakage and deformation
2. Torque / Operating effort / Operating time: Manufacturer to furnish data and if
required supporting calculation for review / approval.
2.2 NON RETURN VALVES - WATER APPLICATION
The valves shall generally conform to IS 5312 Part 1 (Single Door Type) for sizes 50 to 1200 mm and IS 5312 Part II (Multi Door Type) for sizes above 1200 mm . The valve shall be suitable for mounting on a horizontal pipeline and flow direction shall be clearly embossed on the valve body. No spring loaded/ spring return action or external dampening arrangement is acceptable. Valves of multidoor type shall be additionally provided with a supporting foot. All faces and seat rings shall be riveted (350 NB & above) to the machined surface in the casting. The door shall be integral with the hinge and shall have a flat seating face. Minimum two (2) nos. suspension lugs shall be cast integrally on the diaphragm plate and shall be of adequate strength.
Component Material of construction Body / Door (& Diaphram)
Ductile Iron GGG 40 / IS 1865 Gr. 400/15 or 500/7
Hinge pin (single door ) / Stub pin (multidoor type )
SS AISI 410/SS AISI 420
Seat rings & Face rings / seal Resilient (EPDM) seal (upto 300 mm); Gun metal : IS 318 Gr. LTB 2 (350 mm and above)/Nickle weld overlay above 350 mm
Rivets Soft annealed brass Fasteners Carbon steel (galvanized) Flange Drilling IS 1538 Table 4 & 6/ BS En 1092 - 2 PN 10 / 16 By pass arrangement Optional Painting & Coating: Pre inspection:
1st Step Surface Preparation Blast cleaning to near white - SA 2 Grade
Post inspection, if applicable 2nd Step Application of Finish Coat One coat of epoxy power coating Note: Liquid epoxy coating should be done by appropriate equipment inside
a proper paint booth, conforming to AWWA C 213.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 38 of 152
Manufacturer should be able to provide certificate from WRAS (U.K.) stating suitability of the above paint in drinking water application.
The total DFT should not be less than 250 micron. General 1. Hydro testing:
PN 1.0 PN 1.6 Criterion Seat test (Kg/cm) 10 16 Drop - tight Body test (Kg/cm) 15 24 No leakage and deformation
2.3 BUTTERFLY VALVE (GENERAL PURPOSE)
Up to 300 mm Flangeless wafer butterfly valve meeting the following
Bi directional shut off valve PN 10 / 16 Ductile body with fully vulcanized liner seat preventing corrosion between liner
and body Disc in SS CF8 For manual operation: Lever upto 200 ; above with Worm Gear box Suitable for easy installation between all kinds of flanges IS, BS No need of separate gasket for installation Motorised operation with Single / Three Phase electrical actuator.
All dimensions in mm NB 40 50 65 80 100 125 150 200 250 300 End to End 32 42 44 44 50 56 56 60 68 78 Top Flange F05 F05 F05 F05 F05 F07 F07 F07 F10 F10
350 and above The butterfly valves shall generally conform to BS EN 593, with length over flanges as per double flanged Long (BS EN 593 / BS EN 558 / ISO 5752 Basic Series 14), bubble tight shut off; resilient seal; integral body seat; double eccentric design. Nickeled weld overlay.
Component Material of construction Body / Disc Ductile Iron GGG 40 / IS 1865 Gr. 400/15 or 500/7 Stub Shafts SS AISI 431/420 Bearings Steel backed Teflon (co-efficient of bearing friction
not more than 0.1)/Bronze Body seat Integral Ni Cu alloy weld deposited, micro finished Disc seal EPDM
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 39 of 152
Disc seal retaining ring SS 304 / Ductile iron Shaft seal Halprene/EPDM Internal Fasteners SS Flange Drilling BS EN 1092 - 2 PN 10 / 16
Mandatory accessories: Enclosed worm gear box with additional spur gear boxes, if required
Required: CI/DI with IP 54 protection; Make - MASTERGEAR INDIA / AUMA/VAG
Mechanical Position Indicator Yes Limit stops Yes Operation Manual operation by hand wheel.
Motorised operation by means of electrical actuator.
PAINTING & COATING: Pre inspection: 1st Step Surface Preparation Blast cleaning to near white - SA 2 Grade
Post inspection, if applicable 3rd Step Application of Finish Coat One coat of epoxy coating (Shade: RAL 5005, Blue) Note: Liquid epoxy coating should be done by appropriate equipment
inside a proper paint booth, conforming to AWWA C 213. Manufacturer should be able to provide certificate from WRAS
(U.K.) stating suitability of the above paint in drinking water application.
The total DFT should not be less than 250 micron. General 1. Hydro testing:
PN 1.0 PN 1.6 Criterion Seat test (Kg/cm) 10 16 Drop - tight Body test (Kg/cm) 15 24 No leakage and deformation
2. Torque / Operating effort / Operating time: Manufacturer to furnish data and if required supporting calculation for review / approval.
Volume-II Specifications
Contractor Witness Divisional Engineer (PH-2) Page 40 of 152
2.4 AUTOMATIC AIR VALVES
KINETIC AIR VALVE (IS 14845) Body / Cover / Cowl DI IS 210 Gr. FG 200/ H.P. Orifice & Plug Bronze L.P. Seat ring Nitrile Rubber (Dexine) L.P. Ball Vulcanite Covered Timber H.P. Ball Rubber Covered Timber Isolating Sluice Valve CIDF as per IS 14846 with CI Cap Fasteners Carbon Steel PN 10
COMBINATON AIR VALVE Single chamber double orifice automatic triple function DI Air valves. L.P. & H.P. Chamber / Cover / L.P. seat retainer
Ductile Iron GGG 40 / IS 1865 Gr. 400/15 or 500/7
Cowl Carbon Steel H.P. Orifice EPDM L.P. Seat ring EPDM Floats (LP & HP Chambers) SS 304 Ferrule SS Isolating Sluice Valve with Cap
DIDF with resilient wedge
Fasteners Carbon Steel PN 10 / 16
GUIDELINE FOR USAGE
Valve size For Mains size 50 Upto 200 80 225 - 350 100 400 - 500 150 600 - 900 200 1000 - 1200
For mains size larger than 1200 NB, it is recommended tha