Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
www.spenergynetworks.co.uk
SP Energy Networks Our ‘Looking Forward’ Work Plan
May 2015
www.spenergynetworks.co.uk
2
Our ‘Looking Forward’ Work Plan
“Our vision is not only to be an engineering company with strong asset stewardship and world-class safety credentials, but also to deliver industry-leading customer service, trusted by its communities and stakeholders alike. Our approach to engaging with our connections stakeholders is integral to the realisation of this vision. Stakeholder input is hugely valuable and has enabled us to develop a programme of activities for improving our connections service that responds directly to their needs. Each of the actions in our Looking Forward Work Plan have been developed in partnership with our stakeholders. Our plan is certainly ambitious, but we believe it is achievable and with the continued engagement of our stakeholders we are confident that we will deliver an industry leading service.” Frank Mitchell, Chief Executive Officer, SP Energy Networks
Our aim is to deliver exceptional service at all times
SP Energy Networks (SPEN) Looking Forward Work Plan sets out what we intend to do over the next year to deliver an improved service for our distributed generation (DG), metered and unmetered stakeholders and customers. In May 2016 we will report back on how we have delivered against the activities contained within our Work Plans. Through our engagement and development of the Work Plans, we recognised that the issues that our stakeholders face are common for both licences. For that reason, this plan applies to both of our licence areas,SP Manweb PLC (in North Wales and North-west England) and SP Distribution PLC (in Central and Southern Scotland).
The key purpose of our stakeholder engagement is to help understand issues and solve problems such that we can deliver better quality services to our customers, and to network users.We do this by engaging with a broad and inclusive range of stakeholders using a variety of approaches throughout the year.
Our connections stakeholders include a wide range of customers (e.g. large demand customers, small generation and domestic customers, alternative connection providers), trade bodies and associations, local authorities, developers, contractors, government bodies and other industry stakeholders.
This Work Plan of activities seeks to deliver SPEN’s high level Connections strategy, which is to;
... provide quicker connections by reducing the time taken to provide a connection offer and the time taken to deliver a connection (Time)
... increase the overall efficiency of the process and deliver cheaper connections (Cost)
... improve our communication with our stakeholders, increase flexibility and facilitate a competitive market (Satisfaction).
Time, Cost and Satisfaction are the Key Strategic Objectives that our Work Plan of activities are aligned to.
www.spenergynetworks.co.uk
Page
CEO Foreword 2Our Work Plan Structure 4Our Work Plan Explained 5Our New Business Model 6Our Key Strategic Connections Objectives 9Stakeholder Engagement Model 10Connections Engagement Activity 11Developing our Work Plans 12We have Sought Feedback on our Work Plans... 13Our Stakeholders have Endorsed our Plans 14Opportunity to Share Best Practice with other DNO’s 15Our Principal Commitments 16Distributed Generation Work Plan 17Metered Work Plan 34Unmetered Work Plan 48Glossary of Terms 60Summary of Relevant Market Segments 61
Contents
www.spenergynetworks.co.uk
4
Work Plan Strategy
Our Work Plan is structured as follows;
Our Work Plan Structure...
We have provided 3 individual Work Plans; (1) a Distributed Generation (DG) Work Plan for customers seeking a generation connection e.g. an HV connection for a Hydro generation project; (2) a Metered Work Plan for customers seeking a demand connection e.g. a high voltage (HV) connection for an industrial premise; and (3) an Unmetered Work Plan for customers seeking an unmetered connection e.g. a low voltage (LV) connection for new street-lighting.
Whilst there are a number of similar activities within each Work Plan, through building these we recognised that there were differing needs for stakeholders depending upon the nature of the connection being sought. For that reason and through discussions with stakeholders, we decided to adopt this approach rather than provide a single Work Plan of activities.
The following page provides some narrative on the individual components of the Work Plan and how each list of activities has been set out.
Metered Work Plan
Unmetered Work Plan
DG Work Plan
Our Principal Commitments >> Our Principal Commitments that underpin all our proposed activities
>> A comprehensive list of activities that will improve the service we provide and address the issues stakeholders have raised>> The source of the feedback that has driven the action>> The relevant market segment (RMS) or segments to which the activity applies>> The Key Strategic Objective, in terms of Time, Cost and Satisfaction, that each activity is aligned to>> The timescale that the activity will be delivered (by quarter)>> The proposed Key Performance Indicator (KPI) against each activity
>> A statement from CEO Frank Mitchell, setting out our objective and high level connections strategy>> A summary of our new business model, which is enabling us to strengthen key local stakeholder relationships, be more responsive to our customer needs and firmly embed us within the communities we serve>> The Key Strategic Objectives that our Work Plans are aligned to >> The overall SPEN Stakeholder Engagement Strategy and how it links with our engagement approach for Connections stakeholders>> How we have worked with our stakeholders to develop our Work Plans>> How we have gathered feedback on our Work Plans and secured endorsement >> How we intend to work with other DNO’s to seek opportunities to share best practice
www.spenergynetworks.co.uk
5
Our Work Plan Explained...
www.spenergynetworks.co.uk
18
To ensure that the application process is as simple as possible for you, whilst still providing us with all information necessaryto deliver a connection offer that meets your needs
What we did in 2014 ... We established our Quote + product as a standard option and promoted this through our website, newsletter and direct mailing ... We simplifi ed the application forms for <100kW applications ... We published a link to the ENA technical database on our website ... We held customer surgeries on validity periods and interactivity ... We published a consultation on whether the Quote + product meets your needs
This year, you have told us:
“ We would like a simplifi ed application tailored to our needs with a more consistent approach to the information you
request ”
“ We’d love to talk more to the area guys, Knowledge is overall far better, knowing more
about the areas and issues youguys have would make us search
the right areas ”
18 Interviews515 Surveys Issued
47 Responses Received
Application Process
LV Work HV & EHV WorkAccount Managed ✓ ✓Repeat ✓ ✓One-off ✓ ✓
“ I haven’t used Quote + so far but it looksvery helpful to speed up the
connections inquiry process ”
LVWork
HV&EHV Work
“ I have not yet used the simplifi ed <100kw
application form, howeveronline would help ”
LVWork
m“ Reduce the amount of information requiredat the early stage in the process.e.g. narrative descriptions, scale drawing of wind turbine etc ”
HV&EHV Work
HV&EHV Work
www.spenergynetworks.co.uk
19
Market Segment TimeframeAction Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Leverage the benefi ts of our District Model by providing you with a more local service Our ‘Monthly Connections Surgeries’ will be replaced with monthly ‘District Days’ at Stakeholder Interview ✔ ✔ Satisfaction .
Publish dates of ‘District Days’ local depots to facilitate pre-application and application meetings
Survey Responses and record attendance
We will meet with you within fi ve working days of a request to discuss Stakeholder Interview ✔ ✔ Satisfaction . Meeting held within
your pre-application or application Stakeholder Interview 5 days of request Survey Responses
You will be assigned with a named local contact Stakeholder Interview ✔ ✔ Satisfaction . Success of contact
within one working day of your application being received
Survey Responses provided within 1 day Account Management Stakeholder Panel
Review the minimum information we request from you for the initial connection application As we did for <100kW DG projects, we will consult with you on what information Stakeholder Interview ✔ ✔ Time .
Consultation published you feel is appropriate to complete a G59 application form for >100kW but <1MW project Survey Responses
We will publish clear guidelines on our requirements for the size Stakeholder Interview ✔ ✔ Time .
Guidance published
of generation connection being sought Survey Responses
Provide a facility that allows you to submit your connection application online We will provide a simple, tailored online application facility Stakeholder Interview ✔ ✔ Time .
On-line facility available on our connections website Survey Responses
Our online application facility will validate your information Stakeholder Interview ✔ ✔ Time .
On-line facility available and provide on-screen ‘hint’ text to support you through the process Survey Responses
You will be able to upload supporting documents to assist us in Stakeholder Interview ✔ ✔ Time .
On-line facility available processing your application i.e. photos, drawings, site development plans etc. Survey Responses
An automatic email acknowledging your submitted Stakeholder Interview ✔ ✔ Time .
Automatic email provided application will be provided Survey Responses
Provide additional support to ‘one-off’ customers For customers who have not requested a quote from us in the past we will pilot a ‘buddy’ system Survey Responses ✔ ✔ Satisfaction .
Dedicated person assigned to which provides you with a local contact who will guide you through the application form
support ‘one off’ customers
Application ProcessThis year we intend to...
DG1
DG2
DG3
DG4
The number of stakeholders interviewed
Improvement activities in 2014
Verbatim comments from stakeholders (icons indicate Relevant Market Segment
(RMS) and Sector) which led to our list of actions
Source of the feedback that has driven the action
Actions: Set of activities in response to issues our stakeholders have told us
about during our engagement with them
RMS that the action is applicable to
Key Strategic Objective, in terms of Time, Cost and Satisfaction, that each
activity is seeking to improve
Key Performance Indicator (KPI) against each activity
The quarter that the activity will be delivered
The number of surveys issued and responses received or engagement activity
that has driven the action
The participants broken down by customer type and RMS covered
www.spenergynetworks.co.uk
6
Our New Business Model
Structuring our Business to get closer to our Customers and Communities we serve
SP Energy Networks (SPEN) is in the process of implementing a new geographical business model. We recognise that there was a need for us to get closer to the customer and communities we serve. The new geographical structure will allow us to: strengthen key local stakeholder relationships, be more responsive to our customer needs and firmly embed us within the communities we serve.
Our business has been divided into six Districts within Scotland (Ayrshire & Clyde South, Glasgow, Lanarkshire, Edinburgh & Borders, Central & Fife and Dumfries) and five Districts within England and Wales (Merseyside, Wirral, Mid Cheshire, North Wales and Dee Valley & Mid Wales).
Under the new structure Guy Jefferson is leading the Scotland license area (also known as SPD) and Stephen Stewart is leading our business in England and Wales (also known as Manweb or SPM).
Each of the new districts has an appointed District Manager who is responsible for overseeing all activities including operations, maintenance, connections, asset replacement and emergency response.
The new model has been built on three strategic anchors
Our transition to the new business structure is underway and will be fully in place by the end of June 2015.
Getting closer to our
customers communities and stakeholders
Creating a leading position
in engineering and asset management
Equipping our people with the skills they need
for the future
• Greater local autonomy
• More staff in local areas giving improved storm response and customer service
• Better coordination and greater flexibility to connections, faults and investment works
• Building enduring local relationships
• Improved processes and systems
• Reduce back office costs
• Improved flow of information through organisation
• Recruiting from the local area
• Bringing Graduates and Apprentices to replenish the workforce
• Becoming more customer and stakeholder facing
• Increased flexibility to deal with future demands of smart networks and the low carbon transition
Guy Jefferson Stephen Stewart
www.spenergynetworks.co.uk
7
Our District Structure - North
Ayrshire & Clyde South Graham Campbell
Customers 360k
Glasgow David Guthrie
Customers 428k
Lanarkshire Craig Arthur
Customers 311k
Central & Fife Graeme Stewart
Customers 398k
Edinburgh & Borders Ian Johnston
Customers 410k
Dumfries Iain Steele
Customers 83k
Director, SP DistributionGuy Jefferson
Lanarkshire
Ayrshire &Clyde South
Dumfries
Edinburgh & Borders
Glasgow Central & Fife
www.spenergynetworks.co.uk
8
Our District Structure - South
Director, SP Manweb Stephen Stewart
Merseyside Andrew Lloyd
Customers 550k
Wirral Jane Wilkie
Customers 375k
Mid Cheshire John Heathman
Customers 139k
North Wales Liam O’Sullivan
Customers 234k
Dee Valley & Mid Wales Gary Evans
Customers 165k
Dee Valley & Mid Wales
North Wales
Merseyside
Wirral
Mid Cheshire
www.spenergynetworks.co.uk
9
Our Key Strategic Connections Objectives Time, Cost and Satisfaction are our Key Strategic Objectives that our Work Plans are focussed on addressing. Set out below is a summary of the improvements we intend to make against the context of our performance over the last few years.
Our customers want quicker connections. This is evident from all the stakeholder engagement we have undertaken; be it through direct contact, at workshops, responses to the Broader Measure of Customer Satisfaction (BMCS) or via trade associations and industry stakeholders.
For the coming year we have set ourselves a target of improving the time to quote and time to connect following acceptance by 20% across all RMS’s. This is an ambitious target which we believe can be achieved through the actions outlined in our Work Plans and other changes to our business such as the new business model.
During the last few years we have made significant improvements and have, on average, reduced the time to quote and time to connect by 10% across all RMS’s. For some segments the improvement has been even greater than this and in others the improvement has been less; for example it has been challenging to make significant improvements in the time taken to quote DG schemes due to the substantial increase in the number of applications we have received.
The cost of connection was not an issue that was raised often during the stakeholder interviews and survey responses we received in developing our Work Plans, however it has occasionally been expressed in the responses received from the BMCS and various trade associations and working groups.
Our charges are published within the Common Connections Charging Methodology (CCCM) and are updated annually. For the majority of categories our charges have reduced in the last four years, in some cases significantly.
For example, during the last competitively tendered contract for overhead lines, by leveraging SPENs economies of scale the contract delivered a saving of circa 5% in respect of the previous contract delivering some of the most efficient costs across the UK. In cable laying, a 12% saving has been realised.
We will continue to ensure that any savings delivered through improved processes and procurement efficiencies are passed onto our customers. Indeed we have a track history of ensuring that any savings made through the delivery of a connection for a customer are passed on by way of refund, and we will continue to adopt that approach in the future.
Our aim is to deliver exceptional service at all times. Since the introduction of the BMCS survey in 2011 our results in SPD have improved by 28% and in SPM by 19%. We are now consistently seeing scores exceed 8 out of 10 for customer satisfaction when customers were asked to rate our service (with 1 being poor and 10 being excellent). This sees us competing with the best service providers across all industries in the UK.
We have achieved this by listening to our stakeholders, implementing improved systems, processes, delivering quicker and lower cost connections. We measure, understand and will continually improve the service we provide.
Major connections customers are no longer included within the BMCS however we will continue to engage with these stakeholders on a regular basis and measure our performance throughout the course of the year. We have set a target to exceed 9 out of 10 for BMCS and the same for major connections customers from now until the end of ED1 period.
Time Cost Satisfaction£€
www.spenergynetworks.co.uk
10
Using Central Strategy to deliver Connections Engagement
Stakeholder engagement is embedded in our organisation and influences both operational and strategic improvements in performance. Our stakeholder engagement looks at how we create an environment and framework within our business which allows our stakeholders to be involved and influence SP Energy Networks’ plans. The benefits to our stakeholders are clear. By being involved, they are able to bring about change and improvements to benefit their needs.
Stakeholder engagement was fundamental in the development of our business plans for the ED1 period. We see this as a key tool in evolving and shaping our future plans and improving our service.
Utilising our proven central stakeholder engagement approach and the 7 pillars which underpins the recognised AA1000 standard and core principles, we are able to address our Key Strategic Objectives within connections. Using these tools and methodology, utilising a consistent approach and engaging with a broad range of stakeholders we can focus in areas where stakeholders can really influence what we do. We see stakeholder engagement as everyone’s responsibility in our organisation.
How did we apply the 7 Pillars to our ongoing engagement?
SummaryIn the development of our Work Plans we have adopted this systematic, rigorous and centralised approach to stakeholder engagement.
To ensure that our Work Plans remain relevant we will carry out ongoing engagement activity throughout the year. We will continue to engage with our stakeholders on a regular basis to ensure our Work Plans respond to their needs and adapt as these change. We see this as a continual process and are prepared to engage, understand, respond, and feedback.
Stakeholder Engagement Model
Governance
• Overarching External Stakeholder Panel
• External Connections Stakeholder Panels
• Internal Stakeholder Action Group - Internally report on stakeholder activity, feedback and actions
• Regular Executive Review
Stakeholder Database
Engagement Planning
Systematic Approach
FeedbackLoop Resources
Assurance, Measurement, Evaluation
and Accreditation
• Stakeholder Database• Categorisation and
prioritisation of stakeholders
• Key Connection customer Account Management
• Log of Interaction and Feedback
• Annual Connections engagement plans and ownership within business
• Aligned stakeholder engagement activities to strategic business priorities
• Stakeholder groups mapped, analysed and prioritised by interest and influence.
• Adopt appropriate engagement method
• Use of SPEN toolkit and appropriate channels to engage
• Advice and Support from Central Team to ensure consistent approach
• Transparent Engagement Activity
• Continually engage, understand requirements, respond appropriately and feedback to stakeholder.
• Recurring stakeholder identification and engagement
• Central Stakeholder Team• Licence Specific Stakeholder
Engagement Teams• District Model resourced
to deliver stakeholder engagement
• Embedded Engagement Model
• Adopted the AA1000 Stakeholder Engagement standard
• Independent process assurance audit
• Confirmation of approach from Stakeholders
• Measurement of outcomes• Evaluation Framework
www.spenergynetworks.co.uk
11
Respond
Feedb
ack
Understand
Engage
To ensure that our Work Plans remain relevant we will carry out ongoing engagement activity throughout the year. We will also ensure that in order to engage with a broad and inclusive range of stakeholders, we will periodically review our stakeholder database to ensure our stakeholder mapping and prioritisation is up to date and relevant.
Connections Engagement Activity
EngageAccount Management our dedicated Account Managers engage with a range of metered, unmetered and DG customers on a daily basis
Trade Bodies, Government and Associations we take an active role in the national DG-DNO Working Group, DG-DNO Technical Sub-group, Scottish Renewables Working Group, The Energy Island Programme as well as close relationships with Scottish Government and Welsh Government. We use these relationships to gather feedback on our service and to disseminate information to their members
Industry Events we attend industry events and actively participate in forums such as the DG Forums that are facilitated by the Energy Networks Association
Customer Workshops when required we organise dedicated stakeholder workshops e.g. for DG communities, on the G59 Process and the Competitions in Connections Code of Practice
District Launch Days we will hold specific District Launch Days to launch each of our new district offices and introduce our local teams to community stakeholders
District Days our Customer Surgeries have now been renamed District Days. These monthly drop-in sessions allow our customers to visit our local offices and speak directly to our experts on technical issues or discuss their project pre-application
UnderstandStakeholder Interviews we meet with a number of our stakeholders on a one-to-one basis, asking them a series of questions about how we can improve our service. These annual interviews are organised with a select group of customers covering all of RMS’s
Surveys we issue an annual survey to major Connections customers who have requested a connection within the last year
BMCS Broader Measure of Customer Satisfaction we take into account the feedback received from our survey results
RespondLooking Forward Work Plan set outs our improvement activities based on what our customers have told us.
FeedbackNewsletter we currently issue a DG newsletter, providing customers with key updates. We will develop this so that it is relevant to all our major connections customers
Update Register we will provide customers with the ability to register for key updates such as changes to our processes and service
Website we will continually review and update the content on the SP Energy Networks website and update our Connections stakeholder pages to reflect our latest activities
Alternative Communication Methods we will continually seek new ways to communicate with you such as utilising You Tube and social media
www.spenergynetworks.co.uk
12
We have listened to our stakeholders in the development of our plans.
We recognise that often engagement and the feedback received can sometimes reflect the views of our more vocal stakeholders. In order to ensure that we gathered a wide range of views we utilised a diverse range of engagement activities and market research methods to ensure that we reached out to a broad and inclusive range of our stakeholders.
Ongoing Engagement We gathered feedback Interviews We conducted 53 interviews with our key Stakeholders on our end to end process. from our ongoing engagement activity, such as Broader Measure of Customer Satisfaction, our meetings with Trade Bodies, Government and Associations, Customer Surgeries and Customer Workshops held.
Online Survey Based on our interview responses we developed a survey asking questions about our complete connections process and issued this to 1,947 major customers who had made an application within the last year.
Developing Our Plans We analysed the responses received to formulate and create our plans. We held a number of internal stakeholder workshops with key personnel to review the market research and feedback gathered, understand the issues and develop appropriate activities. We set achievable timeframes for each of our actions, linking these back to our Key Strategic Objectives.
Developing our Work Plans
Relevant Market Segments Market Sector Total DGLV DGHV LV HV HV&EHV UMSHousing 124 3 3 3
Developers 366 3 3 3 3 3 3
Consultants 481 3 3 3 3 3 3
Local Authorities 191 3 3 3
Alternative Connection Providers 23 3 3 3 First-time customers 762 3 3 3 3 3 3
Relevant Market Segments Market Sector Total DGLV DGHV LV HV HV&EHV UMSHousing 9 3 3 3
Developers 13 3 3 3 3 3 3
Consultants 15 3 3 3 3 3 3
Local Authorities 9 3 3 3
Alternative Connection Providers 5 3 3 3 3 3 Trade Bodies, Government 2 3 3 & Associations
www.spenergynetworks.co.uk
13
On 30th April 2015 we published our Work Plans in draft. Our plans were published on our website with a link to a survey which provided an opportunity for stakeholders to provide feedback.
In addition and during the development of the Work Plans we engaged stakeholders using a variety of channels to seek feedback on our emerging Work Plans. The table below illustrates the channels used, a description of the activity, the number of stakeholders given the opportunity to respond, the responses received and some examples of the stakeholder views provided.
Our Work Plans have been revised to reflect the feedback received.
We have Sought Feedback on our Work Plans...
Channel Description Number of Number of An example of where feedback No of actions updated stakeholders given stakeholders who has driven a revision to the plan the opportunity have provided to engage feedback/attended
Survey We circulated our plans to stakeholders who had “It is all well and good for the Principal Commitments Principal Commitment participated in our interviews, responded to our 2,064 13 to refer to continuing to work with SSE and Scottish Updated (PC8) survey and have assigned SPEN Account Managers Renewables but should this not include National Grid” Stakeholder We met with our Stakeholder panel members 13 13 “As a company operating nationally we still have a Principal Commitment Panel Members individually to discuss our plans in detail requirement for a single point of contact” Included (PC7)
Customer We held six customer workshops, three in Scotland “Improved heatmaps which highlight saturated 11kV lines Information Provision Feedback and three in England and Wales. Customers who had 253 28 will help with our feasibility studies and we appreciate the Action Updated (DG6) Workshops responded to our survey and Account Managed volume of activity in creating these maps, biannual customers were invited to attend updates would be sufficient”
Scottish We participated in a joint SP Energy Networks/SSEPD “There continues to be a need for more clarity on the Transmission to Renewables workshop where Scottish Renewables members 415 13 Statement of Works process and who is responsible Distribution Interface Workshop were invited to attend for doing what” Action Included (DG27)
Stakeholder Key stakeholders who operate nationally “We recognise your drive to reduce costs for customers Principal Commitment Workshop were invited to attend a dedicated SPEN 10 8 but we are unclear on how you are going to achieve this” Included (PC10) London session in London
www.spenergynetworks.co.uk
14
Our stakeholders were asked... 1 On a scale of 1 – 10 (with 1 being low and 10 being high), do the actions proposed address the issues that you face as a customer? Average response = 8.8
2 On a scale of 1 – 10 (with 1 being low and 10 being high), if these actions are completed in the timescales proposed, do you believe that the overall service will improve? Average response = 9.3
3 On a scale of 1 – 10 (with 1 being low and 10 being high), how supportive are you of the Work Plans that we have proposed? Average response = 9.0
4 On a scale of 1 – 10 (with 1 being low and 10 being high), how ambitious do you believe our Work Plans to be? Average response = 8.8
We then asked members of our stakeholder panel if they would endorse our Work Plans
Our Stakeholders have Endorsed our Plans
Arwel Lloyd, UCML
“UCML continues to support SPEN in its determination to provide its customers with a superlative standard of service. SPEN is to be congratulated in the progress made over the last 24 months which can only auger well for the future ”
Bob Weaver, PowerCon (UK) Ltd“We believe that the actions taken do address the issues that are faced by SPEN’s customers. Whilst we confirm that there is still work in progress we would confirm that there remains a willingness on the part of SPEN and its senior management team to review and address problems that are brought to their attention.We are of the opinion that there has already been significant improvements with the service levels adopted by SPEN and further believe that if these actions are completed in the timescales proposed, that the overall service will improve still further.
We are completely supportive of the Work Plans that have been proposed by SPEN
and are happy to endorse. ”
Allan Cunningham, Morrison Construction“I think the proposed work plans will bring much improved communications and transparency, and provide valuable
assistance to customers in their dealings with SPEN ”
North Panel Members
Stephen Phimister,
TUV SUD Ltd“We find SP Energy Networks one of the better utility companies to deal with however further improvements in service and response are always welcome ”
Anonymous
“The work plans provide a clear statement of commitments
by SPEN to provide stakeholders with the necessary information, timescales and communication routes that are required in today’s world. They set out specific actions with timeframes that will improve dialogue with SPEN and give stakeholders a much clearer understanding of requirements for trouble free connection process”
George Dow, Mactaggart and Mickel“SP Energy Networks have set themselves an ambitious set of plans which if implemented would greatly improve the overall service they provide. As a member of the stakeholder panel, I have enjoyed being engaged in the process and watched the plans evolve. I am pleased to see that SP Energy Networks have engaged with
a wide range of stakeholders to ensure customer feedback plays a pivotal
role in their plans ”
Martin Reilly, Hawthorne Boyle“We are extremely supportive of SPEN’s work plans as we have been heavily involved and well engaged in the process to develop these plans. SPEN’s plans are reflective of the discussions and views presented at our stakeholder panel sessions and meetings held separately with our Account Manager. Again, I feel that the service will improve as long as the timescales are met for the actions to be completed and all the actions
are put in place. We feel that SPEN’s plans are ambitious and focus on the areas that we are
keen to see progress on ”
South Panel Members
Jody Bullock, UPL“I believe the work plans proposed by SPEN have shown a willingness to not only listen to the needs of customers but to put in place strategies which help make the connections process more
efficient and manageable ”
Frank Welsh,
Peel Utilities“I am delighted to see that
SPEN are making strenuous efforts to simplify process through their workplans, both in their approach and the challenging targets they have set themselves.The move to a district model will definitely facilitate closer working partnerships moving forward. Indeed SPEN’s workplans are a breath of fresh air and should be used as a model for the industry as a whole ”
Anonymous
“We are fully committed to collaborating with SPEN to improve
future network capacity and resilience on the Island. It is essential that necessary investments are made in advance to ensure possible construction do not hamper potential inward investment opportunities ”
Marco Campolucci-Bordi, Green Switch Solutions“We are really pleased with the SPEN work plan. It addresses all the issues and challenges that the distributed generation community is facing. SPEN is already a good DNO and with this plan it is heading
for the top. Keep up the great work ”
www.spenergynetworks.co.uk
15
SPEN recognises the importance of sharing of best practice between DNOs, other Utility providers and industry stakeholders that ultimately delivers benefit for our stakeholders and customers.
The DG-DNO Working Group established in 2012 is testament to this. This Working Group has brought together DNOs and stakeholders to share and address issues that affect Distributed Generation (DG) stakeholders nationally. It has been widely acknowledged that by sharing best practice between DNOs, stakeholders have received a better service than what might have been delivered through individual DNO’s working in isolation.
Heat Maps, Quote+ and Collaborative ConnectionsExamples of effective collaboration and those that SPEN have been directly involved in or have led, are the development of heat maps, the introduction of the ‘Quote +’ product and the use of collaborative connections (whereby a number of DG customers have had renewables connected to the network through a shared connection solution).
Opportunity to share best practice with DNOs through the development of the ICE Work Plans Recognising the mutual benefits of past successful collaboration, SPEN established two conference calls with other DNOs in March and April this year. The purpose of these joint calls was to discuss whether there was opportunity through the ICE process to share best practice and to identify any issues faced by stakeholders nationally, not just for DG stakeholders, but also for Metered and Unmetered stakeholders.SPEN are keen to ensure that any opportunity to share best practice is seized by all DNOs through ED1 and will be at the forefront at engaging with other DNOs in doing so. In our ‘Principal Commitments’ section we promise to do this.
SPEN and SSEPD have agreed to share best practice on a number of activitiesSPEN and SSEPD have agreed to work together to consider where opportunity to share best practice is available. Whilst these opportunities are not fully detailed yet, the areas that are being considered are as follows;
… The information being sought within our application forms; for Metered and Unmetered stakeholders we will work together to establish best practice in the information being sought to form an application
… The approach to engagement; for all stakeholders we will work together to consider how best stakeholders can be engaged to the benefit of both stakeholder and DNO as some stakeholders have expressed frustration at being engaged by different DNOs in similar ways
… In Scotland specifically, the Transmission system constraints that exist are widespread; for DG stakeholders, we will work together to tackle the ‘big issues’ such as the Statement of Works process, Queue Management and the ‘pass through of Transmission liabilities’
Opportunity to Share Best Practice with other DNO’s
www.spenergynetworks.co.uk
16
Our Principal Commitments Market Segment Timeframe Action All Key Strategic (Q1) (Q2) (Q3) (Q4) Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
We will collaborate with the Industry and other DNOs to address issues that are universally affecting stakeholders to ensure that best practice is shared in the application of innovative commercial 4 Satisfaction
arrangements and technology solutions to support the needs of our stakeholders.
We will continue to ensure that any opportunity to reduce the cost of connection through efficiencies 4 Cost in process and procurement of contracts are passed onto our customers.
.
We will work with other DNOs to develop and consult on the 4 Satisfaction .
Competition in Connections Industry Code of Practice (CoP).
We will reduce the overall time taken to connect by reducing the 4 Time .
average time we take to provide a quote by 20%.
We will reduce the overall time taken to connect by reducing the average period between 4 Time .
agreeing the works and completing the connection by 20%.
Our district organisational model will provide a more local service to you and we recognise that we must maintain a consistent application of process, particularly to those of you who work across our licence area.
4 Satisfaction .
We recognise that for those of you who work across our licence area, a single of point of contact is important. We will double the size of our Account Management team to enhance this service.
4 Satisfaction .
In Scotland, we recognise that our Distributed Generation (DG) stakeholders face some unique issues. We will continue to work closely with Scottish & Southern Energy Power Distribution (SSEPD), 4 Satisfaction
. National Grid Electricity Transmission (NGET) and Scottish Renewables as part of a working group to address the issues affecting our stakeholders in Scotland.
In Wales, we recognise that some of our DG customers also face some unique issues, particularly around connecting
to the higher voltage networks in the Anglesey area. We will continue to work closely with Welsh Government, Energy Island Programme and Isle of Anglesey County Council as part of a working group to address the issues 4 Satisfaction affecting our stakeholders on Anglesey and the wider North Wales area. We also work with these parties and other Local Authorities to address the issues affecting our rural customers.
We will engage with you over the course of the year to ensure 4 Satisfaction .
that we are addressing the issues that you face.
PC1
PC2
PC3
PC4
PC5
PC6
PC7
PC8
PC9
PC10
www.spenergynetworks.co.uk
Distributed Generation Work Plan
www.spenergynetworks.co.uk
18
To ensure that the application process is as simple as possible for you, whilst still providing us with all information necessary to deliver a connection offer that meets your needs
What we did in 2014 ... We established our Quote + product as a standard option and promoted this through our website, newsletter and direct mailing ... We simplified the application forms for <100kW applications ... We published a link to the ENA technical database on our website ... We held customer surgeries on validity periods and interactivity ... We published a consultation on whether the Quote + product meets your needs
This year, you have told us
“ We would like a simplified application tailored to our needs with a more consistent approach to the information you
request ”
“ We’d love to talk more to the area guys, Knowledge is overall far better, knowing more
about the areas and issues you guys have would make us search
the right areas ”
18 Interviews515 Surveys Issued
47 Responses Received
Application Process
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
“ I haven’t used Quote + so far but it looks very helpful to speed up the
connections inquiry process ”
LV Work
HV&EHV Work
“ I have not yet used the simplified <100kw
application form, however online would help ”
LV Work
“ Reduce the amount of information required at the early stage in the process. e.g. narrative descriptions, scale drawing of wind turbine etc ”
HV&EHV Work
HV&EHV Work
www.spenergynetworks.co.uk
19
Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Leverage the benefits of our District Model by providing you with a more local service Our ‘Monthly Connections Surgeries’ will be replaced with monthly ‘District Days’ at Stakeholder Interview 4 4 Satisfaction .
Publish dates of ‘District Days’ local depots to facilitate pre-application and application meetings
Survey Responses and record attendance
We will meet with you within five working days of a request to discuss Stakeholder Interview 4 4 Satisfaction . Meeting held within
your pre-application or application Stakeholder Interview 5 days of request Survey Responses
You will be assigned with a named local contact Stakeholder Interview 4 4 Satisfaction . Success of contact
within one working day of your application being received
Survey Responses provided within 1 day Account Management Stakeholder Panel
Review the minimum information we request from you for the initial connection application As we did for <100kW DG projects, we will consult with you on what information Stakeholder Interview 4 4 Time .
Consultation published
you feel is appropriate to complete a G59 application form for >100kW but <1MW project Survey Responses
We will publish clear guidelines on our requirements for the size Stakeholder Interview 4 4 Time .
Guidance published
of generation connection being sought Survey Responses
Provide a facility that allows you to submit your connection application online We will provide a simple, tailored online application facility Stakeholder Interview 4 4 Time .
On-line facility available
on our connections website Survey Responses
Our online application facility will validate your information Stakeholder Interview 4 4 Time .
On-line facility available
and provide on-screen ‘hint’ text to support you through the process Survey Responses
You will be able to upload supporting documents to assist us in Stakeholder Interview 4 4 Time .
On-line facility available
processing your application i.e. photos, drawings, site development plans etc. Survey Responses
An automatic email acknowledging your submitted Stakeholder Interview 4 4 Time .
Automatic email provided
application will be provided Survey Responses
Provide additional support to ‘first-time’ customers For customers who have not requested a quote from us in the past we will pilot a ‘buddy’ system Survey Responses 4 4 Satisfaction .
Dedicated person assigned to which provides you with a local contact who will guide you through the application form
support ‘first-time’ customers
Application ProcessThis year we intend to...
DG1
DG2
DG3
DG4
www.spenergynetworks.co.uk
20
18 Interviews
Information Provision
“ Heat maps do not give specific details about the capacity of the local transformers;
they just give general info for the infrastructure conditions which are not
so helpful sometimes ”
LV Work
“ If details of existing transformers/
substations - total capacity and headroom - could be
made available through the ‘UMV’ GIS system that would
be very helpful ”
HV&EHV Work
“ Heat maps, particularly in kmz format are the best offered by any DNO.
Only area for improvement is how regularly these are updated & made available to
stakeholders. We are all aware that this is a fairly fluid situation and making regular updates available would be helpful ”
HV&EHV Work
“ The tools that you have
available could be better advertised ”
HV&EHV Work
“ Access to real-time data (or as close to)
that can allow the customer to reach informed conclusions without having to go through the formal quote process ”
HV&EHV Work
To ensure we provide all our customers with clear and concise information and data that allows customers to undertake their own assessment of their connection needs before seeking a formal connection offer
What we did in 2014 ... We refreshed our 11kV heatmaps with updated data ... To compliment our 11kV heatmaps we published 33kV heatmaps and a version with transmission constraints considered ... We strengthened the information provided within our guidance leaflets and published these on our website
This year, you have told us
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
515 Surveys Issued 47 Responses Received
www.spenergynetworks.co.uk
21
Information ProvisionThis year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Improve the way we provide information to facilitate a better connections process We will ensure that our existing account managed portfolio are made aware of all the Stakeholder Interview 4 4 Satisfaction .
Details of available info. provided information we provide to facilitate their connection, including relevant access to our GIS maps
Survey Responses to account managed portfolio,
awareness and uptake increased
We will publicise the information that we provide through 4 4 Satisfaction . Campaign created and targeted
an awareness campaign
Survey Responses communications issued
Where you have told us that some the information we provide is difficult to understand Stakeholder Interview 4 4 Satisfaction . Simple overviews and guidance
(e.g. some of our tech. specifications) we will provide a simplified overview and offer guidance Survey Responses provided
We will provide a list and synopsis of relevant connections technical 4 4 Satisfaction . List provided and design specifications on request Survey Responses
Strengthen the content of our ‘heat maps’ and ‘contracted capacity’ registers so that they are of greater value to you when considering your projects We will update our ‘heat maps’ biannually and our ‘contracted capacity’ Survey Responses 4 4 Satisfaction . Heat maps updated biannually and register Monthly Customer Workshops contracted capacity register updated monthly
Our ‘heat maps’ and ‘contracted capacity’ resources will be combined Survey Responses 4 4 Satisfaction .
Combined maps published
into a single platform
Some of you have told us that you would like our ‘heat maps’ to be available interactively Stakeholder Interview online, rather than you having to load these onto your own GIS platform. We will consult Survey Responses 4 4 Satisfaction . N/A with you to determine what you would like this facility to provide and whether it can be achieved within our existing GIS platform
Provide load information on our 33kV and 11kV networks for our customers We will publish minimum and maximum load information Stakeholder Interview 4 4 Time
33kV information available on the on all our 33kV circuits Survey Responses website Account Management
We will publish minimum and maximum load information Stakeholder Interview 4 4 Time 11kV information available on the
on all our 11kV circuits
Survey Responses website Account Management
We will investigate and issue our findings on whether similar information can be Stakeholder Interview 4 4 Time Investigation complete
provided for all our 11kV substations Survey Responses and findings published Account Management
We will investigate and issue our findings on whether similar information can be Stakeholder Interview 4 4 Time Investigation complete
provided for all our LV circuits Survey Responses and findings published
Account Management
DG5
DG6
DG7
www.spenergynetworks.co.uk
22
18 Interviews515 Surveys Issued
40 Responses Received
Communication
To communicate with our customers in the manner in which they seek, within acceptable timeframes and with the quality our customers deserve
What we did in 2014 ... We introduced ‘hot topics’ within our customer surgeries driven by your needs/requirements ... We issued a ‘getting connected’ newsletter and also provided our customers ability to register for regular updates ... We implemented a new ‘CRM’ (Customer Relationship Management) system to improve our contact with you ... We enhance our methods for communicating with stakeholders through the use of industry bodies (e.g. Scottish Renewables, Renewable UK)
This year, you have told us
“ We require clarity on minimum information required upon application, what is required and what is
actually used ”
HV&EHV Work
“ The communication has got significantly better but we still want a more local
contact with good on the ground knowledge ”
HV&EHV Work
“ The follow up on a regular basis between the applicant
and DNO officer streamlines the whole process. Productive communication
between both sides is crucial to my opinion ”
LV Work
“ Keep your regular customers updated.
Most of this survey refers to services of which we do not
know exists ”
LV Work
CHP
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
www.spenergynetworks.co.uk
23
Communication This year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Alternative methods for communicating with you We will develop YouTube clips of our key processes Industry Events 4 4 Satisfaction .
YouTube clips available
(e.g. ‘Your Works’ to Metering Process) and where to find key resources on our website Survey Responses
We will use industry bodies and trade associations
Industry Events 4 4 Satisfaction .
Circulation list developed
to distribute key messages and updates Survey Responses and messages distributed
You will be able to register your details with us to receive regular relevant updates
Survey Responses 4 4 Satisfaction .
Registration facility available online (e.g. our quarterly newsletter)
Leverage the benefits of our District Model by providing you with a more local service We will notify you with contact details
Stakeholder Interview
4 4 Satisfaction .
Communication issued
of key district personnel Survey Responses
We will update our website with contact details Stakeholder Interview 4 4 Satisfaction .
Website updated
of key district personnel Survey Responses
‘Launch Days’ will be organised in each district to introduce the team Stakeholder Interview 4 4 Satisfaction .
‘Launch days’ held at each district
and publicise the enhanced local focus that the new structure brings Survey Responses Survey Responses
Once you have accepted your connections offer, Stakeholder Interview 4 4 Satisfaction .
Contact provided within 2 days
we will confirm who your assigned Delivery contact is within two working days Survey Responses Account Management
We will extend the scope of our ‘District Days’ at our local depots to cater for Stakeholder Interview 4 4 Time .
District Days published the resolution of any technical issues you may have Survey Responses Account Management
We will commit to meeting with you within five working days Stakeholder Interview 4 4 Satisfaction .
Meeting requested and held
if you request a pre-construction meeting Survey Responses within 5 days
Account Management
We will meet with you on-site to discuss your technical issues Stakeholder Interview 4 4 Time .
Meeting offered within
within five working days of a request Survey Responses 5 working days
Account Management
DG8
DG9
www.spenergynetworks.co.uk
24
Choice
“ Would be good to have discussion with regards to DG issues to ensure that there is no
repetition plus a point of contact ”
HV&EHV Work
“ It might help if we could novate another to do contestable works and the DNO
coordinate the interface ”
HV&EHV Work
18 Interviews515 Surveys Issued
30 Responses Received
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
We want to ensure that you make the right choice when making a new connection to our network, whether that is with an alternative connection provider or otherwise
What we did in 2014 ... We implemented a full breakdown of costs within our connection offers ... Enhanced our process for inspection and monitoring of contestable works ... Introduced monthly meetings with ICP/IDNO’s to go through projects in detail and resolve any issues ... Carried out additional training and support sessions for our new RADAR system ... We introduced biannual Alternative Connection Provider workshops
This year, you have told us
“ Self determination of POCs would really help open up
the competitive market ”
HV&EHV Work
www.spenergynetworks.co.uk
25
Choice This year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Accreditation We will recognise other DNOs’ accreditations of alternative providers
Customer Workshops
4 4 Time .
Process updated and communicated and use them as evidence to provide accreditation Code of Practise
We will provide an improved accreditation training programme
Customer Workshops 4 4 Time .
Access to training provided
and access to training Code of Practise
We will also recognise other training providers Customer Workshops 4 4 Time Process updated and communicated
who provide an accredited programme Code of Practise
We will publish and communicate
Customer Workshops 4 4 Time .
Workshops held with Stakeholders
these changes to you Code of Practise
Self-Determination of Point of Connection (POC) We will provide training for the determination of the POC Customer Workshops 4 Time .
Process updated and communicated
for alternative connection providers Code of Practise
Design Approval We will review, update and add design and technical specifications Stakeholder Interview 4 Time .
Review completed and updates
where they are currently not available Customer Workshops
published
Code of Practise
Inspection & Monitoring We will develop and publish a process for the self-inspection Customer Workshops 4 4 Cost .
Process updated and communicated
of contestable works Code of Practise
We will provide a standardised mechanism for recording
Customer Workshops 4 4 Cost .
Process updated and communicated and reporting self-inspection Code of Practise
We will develop robust adoption agreements
Customer Workshops 4 4 Cost .
Adoption agreements revised to reflect the revised process Code of Practise
Link Boxes We will remove the universal requirement
Customer Workshops
4 Cost .
Process updated and communicated
for link boxes Code of Practise
We will align our link box policy with Customer Workshops 4 Cost .
Process updated and communicated
the provision of Emergency Response Code of Practise
An alternative means for recording the IDNO boundary Customer Workshops 4 Cost .
Process updated and communicated
will be developed Code of Practise
DG10
DG11
DG12
DG13
DG14
www.spenergynetworks.co.uk
26
Choice [continued]
This year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Emergency Service Provision We will provide an emergency telephone number for
Customer Workshops
4 4 Satisfaction .
Telephone number provided
the provision of Emergency Response Code of Practise
We will agree a scope of service and Customer Workshops 4 4 Satisfaction .
Scope of service agreed
communication channels with IDNOs Code of Practise
We will provide a schedule of charges Customer Workshops 4 4 Satisfaction . Schedule of charges and standards
and standards of performance Code of Practise of performance provided
Choices Available to You We will provide a list of alternative connections providers active within our area by
Customer Workshops
4 4 Satisfaction .
List published
considering who has applied for a non-contestable quote in the last twelve months Code of Practise
We will also provide a facility to allow alternative connection providers Stakeholder Interview 4 4 Satisfaction .
Online facility available
to register their details and services offered Customer Workshops Code of Practise
Develop an ‘industry portal’ that provides you with the opportunity to seek which alternative connection providers would be interested in delivering the contestable works on your project As a trial, we will ask our customers if they wish us to circulate their connection requirements Stakeholder Interview 4 4 Satisfaction
Trial commenced
to alternative connection providers who can then contact the customer directly to offer Customer Workshops an alternative quote Code of Practise
We will engage with all active alternative connection providers within our licence area Stakeholder Interview 4 4 Satisfaction Alternative connection providers
to establish their interest in being involved in this trial Customer Workshops engaged Code of Practise
Should this trial be successful, we will consider implementing a ‘bulletin board’ facility on our Stakeholder Interview 4 4 Satisfaction
Facility provided in RAdAR
current portal (RAdAR) to inform alternative connection providers of customers who have Customer Workshops requested alternative quotes Code of Practise
Part funded connections As a trial we will allow alternative connection providers to undertake part funded
Customer Workshops
4 4 Cost .
Trial undertaken
connections (e.g. reinforcement), where an appropriate opportunity arises Code of Practise
Using the findings from the trial we will develop an approach that allows alternative Customer Workshops 4 4 Cost
Enduring process implemented
connection providers to undertake part funded connections as an enduring process Code of Practise
DG15
DG16
DG17
DG18
www.spenergynetworks.co.uk
27
Enablers to Connection We want to remove, where possible, all perceived barriers to connection and will do so by listening to your feedback and seeking resolution
What we did in 2014 ... We implemented a revised upfront payment plan policy ... We improved our breakdown of costs that we provide in our connection offers ... Consulted with you on a process for stalled or heavily delayed projects ... We revised our substation enclosure policy to allow GRP enclosures to be used for 11kV connections ... We reviewed the potential use of voltage control technology on the HV network ... Explored the use of dynamic line rating technology for the 132kV and 33kV networks
This year, you have told us
“ Not aware the payment policy has
been revised”
HV&EHV Work
“ Yes, make your wayleave process consistent and transparent and more flexible. More initial dialogue at the
initial application stage to assist with focussing on what the customer needs ”
HV&EHV Work
18 Interviews515 Surveys Issued
16 Responses Received
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
“ I want to be able to choose whether I proceed with
the non-contestable work or full works from the one
connection offer ”
HV&EHV Work
“ We would like more flexibility in your terms and conditions and a faster response
when a queries is raised”
HV&EHV Work
Consultant
www.spenergynetworks.co.uk
28
Enablers to Connection This year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
The provision of Land Rights on your connection project Stakeholder Interview & Panel We will publish our approach to securing land rights Survey Responses 4 4 Satisfaction .
Policy published
on our website Account Management
We will review and, where appropriate, adapt our approach to connection quotations Stakeholder Interview & Panel and agreements to ensure there is greater clarity on the obligations of all parties under Survey Responses 4 4 Satisfaction . Revised Connection Agreements the agreement Account Management utilised
We will provide a process flow chart on our website, setting out our Stakeholder Interview & Panel 4 4 Satisfaction .
Process flow chart published
“cradle to grave” connection process, highlighting land rights Survey Responses Account Management
Our land and planning officers will be based in your local district offices (alongside your Stakeholder Interview & Panel 4 4 Satisfaction .
L&PO based locally
project manager) to ensure there is a cohesive approach to the delivery of your connection Survey Responses Account Management
Five days after we inform our Land and Planning Team of your requirements for Stakeholder Interview & Panel 4 4 Satisfaction .
L&PO advised within 5 days
a connection, we will advise you who your nominated Land Officer will be Survey Responses Account Management
Where appropriate, standardised documentation will be used Stakeholder Interview 4 4 Satisfaction .
Standardised documentation utilised
with you to achieve land rights on your projects Survey Responses Stakeholder Panel
Provide you with the ability to accept either the non-contestable works or full works on any connection offer we provide you We will extend our current ‘dual offer’ facility to all of Stakeholder Interview
4 4 Satisfaction .
Facility provided
our connections offers being requested Survey Responses
Provide flexibility in our approach to your individual project needs Stakeholder Interview Where you require clarity or discussion on our Terms & Conditions Survey Responses 4 4 Satisfaction .
Service provided
we will commit to responding to you within five working days Stakeholder Panel
We will consult with you on our revised Payment Terms policy Stakeholder Interview 4 4 Satisfaction .
Consultation paper published
to ensure that it is fit for purpose Survey Responses Stakeholder Panel
Roll-out Active Network Management (ANM) across our licence area We will identify and publish a list of GSPs for the roll-out of ANM,
National DG DNO Working 4 Time .
List of GSPs provided
taking account of the impact to the transmission network
We will communicate the policy and process for connecting under an ANM scheme National DG DNO Working
4 Time .
Policy published
using learnings from our Accelerating Renewable Connections (ARC) project
DG19
DG20
DG21
DG22
www.spenergynetworks.co.uk
29
Enablers to Connection [continued] This year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Implement ‘non-firm’ connection offers as business as usual We will consult with you on a proposed policy and process for Account Management 4 4 Time .
Consultation paper published
‘non-firm’ connections National DG DNO Working
We will review our proposals and finalise our policy and process Account Management 4 4 Time .
Review concluded
based on the feedback received during the consultation National DG DNO Working
We will publish where ‘non-firm’ offers cannot be made Account Management 4 4 Time . Areas published
within our licence area National DG DNO Working
We will implement our ‘non-firm’ connections policy and publish a list Account Management 4 4 Time . Policy published
of the information we require to provide you with a ‘non-firm’ quotation National DG DNO Working
Implement a formal policy for the termination of ‘stalled’ projects We will consult with you on our proposed criteria,
Account Management
4 4 Time .
Consultation paper published
process and policy for terminating ‘stalled’ projects National DG DNO Working
We will review our proposals and finalise our criteria, process and policy Account Management 4 4 Time .
Review concluded
based on the feedback received during the consultation National DG DNO Working
We will publish our criteria and process for Account Management 4 4 Time .
Policy published
terminating ‘stalled projects’ National DG DNO Working
We will commit to a biannual review of our contracted projects to identify Account Management 4 4 Time .
Bi-annual review commenced
any ‘stalled’ projects and exercise our termination rights where appropriate National DG DNO Working
Allowing the use of ‘export management devices’ as business as usual We will publish the criteria, process and policy for the use of Account Management 4 Cost .
Policy published
‘export management devices’ on our network National DG DNO Working
Consult with you on the provision of an end-to-end online facility to manage you through the Connections process Some of you have told us that you would like us to provide you with an online facility Stakeholder Interview
Consultation and subsequent
that manages the end-to-end connections process. We will consult with you to Survey Responses 4 4 Time . findings published
determine the feasibility and value of implementing such a facility Account Management
Some of you have told us that you would like the ability to design your connection online. Stakeholder Interview Consultation and subsequent
We are due to implement an online design tool for minor connections customers in April 2015. Survey Responses 4 4 Time .
findings published
We will consult with you to determine the value in extending this facility for our major Account Management connections customers
DG23
DG24
DG25
DG26
www.spenergynetworks.co.uk
30
Distribution / Transmission Interface We want to work with customers to ensure they understand the transmission constraints we operate under, whilst working closely with the Transmission Systems Operator, National Grid Electricity Transmission Plc (NGET) to guarantee an efficient and transparent interface.
What we did in 2014 ... We continue to work with NGET in relation to the SoW process. ... We have published guidance on areas of our network which are impacted by transmission works ... We continue to work with NGET and SPT regarding queue management and the impact on shovel ready projects ... We are also working with SPT and NGET to develop commercial arrangements which will enable projects to connect in advance of the completion of transmission works
This year, you have told us
“ Upgrade work on network not happening fast enough. Not enough capacity for
number of wind turbines wanting to connect ”
“ Good practice in non-firm contracts; flexibility &
other services to the networks ” “ You need to look at queue management, capacity
register &milestones ” “ The TD/DNO
interface needs to be looked at and transmission charging reviewed ”
18 Interviews
DG DNO Working Group,Scottish Renewables
Working Group, Account Managed Portfolio
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
HV&EHV Work
Trade Body
HV&EHV Work
Trade Body
HV&EHV Work
Trade Body
HV&EHV Work
Trade Body
www.spenergynetworks.co.uk
31
Distribution / Transmission Interface This year we intend to... Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Our role in the Statement of Works process Customer Workshops We will publish our policy on the administration of the Statement of Works (SoW) Account Management 4 4 Time .
Policy published
process within your distribution connection quotation National DG DNO Working
We will host customer workshops to communicate this policy Account Management 4 4 Time .
Customer workshops held
National DG DNO Working
Our role in managing the ‘contracted queue’ impacted by requisite Transmission Works We will continue to engage with relevant stakeholders to identify
National DG DNO Working
4 4 Time . Continue to work with Industry
opportunities to allow queue progression for ‘shovel ready’ projects bodies
Similar to our internal ‘stalled’ project policy, we will work with National Grid National DG DNO Working Terms amended and obligations
to amend the terms of connection offers; placing additional obligations on 4 4 Time .
places on new developers you to advance ‘stalled’ projects and minimise future occurrences
Our role in the ‘pass through of Transmission liabilities’ (CMP223) Upon conclusion of CMP223 we will review and publish
National DG DNO Working
4 4 Cost .
Policy paper published
our policy based on the outcome
We will host customer workshops to National DG DNO Working 4 4 Cost . Customer workshops held communicate this policy
DG27
DG28
DG29
www.spenergynetworks.co.uk
32
Communities
“ Clearly communicate all the information relating to both
distribution and transmission works in the one connection offer, and follow up with a phone conversation to ensure the customer has understood the interaction
between the two ”
“ Ensure that all the payment processes
(SoW, deposit, staged payments) for the customer are aligned so that any financial dependencies between
T and D are made clear and work can be progressed in parallel ”
“ Communicate the option of having up to xkW
of permitted export while the transmission constraint is in place, and as far as possible model this on a case by case basis to ensure
as much capacity is released as possible ”
“ Develop detailed guidance on the technical requirements for
G59 generators with a capacity greater than their permitted export capacity,
but with export limiting systems to enable supply to on-site loads ”
18 Interviews
LV Work HV & EHV WorkAccount Managed 3 3Repeat 3 3First-time 3 3
To ensure we recognise community projects and provide assistance for communities who want to get a connection to the electricity network.
What we did in 2014 ... We provided a dedicated email address specifically for communities to ensure speedy and direct communication ... We held workshops in both our licensed areas for community groups to assist them through the process
This year, you have told us
DG DNO Working Group,Scottish Renewables
Working Group, Community Groups
HV&EHV Work
Community Group
HV&EHV Work
Community Group
LV Work
Community Group
HV&EHV Work
Community Group
www.spenergynetworks.co.uk
33
Market Segment Timeframe Action Source of LV HV & EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Provide additional support to our Communities For recognised communities who have not requested a quote from us in the past Industry Events
Dedicated person assigned to
we will pilot a ‘buddy’ system, providing you with a local contact who will guide you Community Representative 4 4 Satisfaction . support ‘first-time’ customers
through the application form National DG DNO Working
Leverage the benefits of our District Model by providing you with a more local service Industry Events We will host local workshops with you to help you through
Community Representative
4 4
Satisfaction .
Local workshops hosted
the connection process for your community project National DG DNO Working
We will meet with you on-site to discuss your project Industry Events 4 4 Satisfaction . On-site meetings held
within five working days of a request Community Representative National DG DNO Working
Provide a comprehensive guidance document for communities seeking a connection We will develop and publish a guide to help community organisations
Industry Events
4 4
Satisfaction .
Guidance document published
(such as Community Energy Scotland and Community Energy Wales) Community Representative communicate the connections process with local residents at the outset of a project National DG DNO Working
Communities This year we intend to...
DG30
DG31
DG32
www.spenergynetworks.co.uk
Metered Work Plan
www.spenergynetworks.co.uk
35
“ The application process is straight forward
however the time involved to get a job up and running with a dedicated
engineer is far too long ”
Application ProcessTo ensure that the application process is as simple as possible for you, whilst still providing us with all information necessary to deliver a connection offer that meets your needs
What we did in 2014 ... Introduced tailored ‘Welcome Packs’ by project type to provide relevant information depending on the type of connection being requested ... Reviewed and simplified our current application forms ... Introduced a new central email address for you to send your new enquiries ... We acknowledge receipt of your application and will contact you within three working days to discuss
This year, you have told us
“ So, ideally a bit more availability of engineering time at
the front end of enquiries (particularly for larger multi-phased) developments
would be of value ”
HV Work
HV Work
“ On application, we are both clear on what is
being requested and that it is the most appropriate request in each
circumstance ”
HV Work
“ As a local authority we previously enjoyed contact with local engineers and an
account manager. As a client it is difficult to make contact with you when our contractors or
subcontractors make applications on our behalf ”
LV Work
Consultant
29 Interviews1,209 Surveys Issued
154 Responses Received
LV Work HV Work HV&EHV EHV & AboveAccount Managed 3 3 3 3Repeat 3 3First-time 3 3
www.spenergynetworks.co.uk
36
Application ProcessThis year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work & Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Leverage the benefits of our District Model by providing you with a more local service Our ‘Monthly Connections Surgeries’ will be replaced with monthly ‘District Days’ at Stakeholder Interview 4 4 4 4 Satisfaction x
Publish dates of ‘District Days’ local depots to facilitate pre-application and application meetings
Survey Responses
and record attendance
We will meet with you within five working days of a request to discuss Account Management 4 4 4 4 Satisfaction x Meeting held within
your pre-application or application Stakeholder Interview 5 days of request Survey Responses
You will be assigned with a named local contact Stakeholder Interview & Panel 4 4 4 4 Satisfaction x Success of contact
within one working day of your application being received Survey Responses
provided within 1 day
Account Management
Review the minimum information we request from you for the initial connection application We will consult with you on what information you feel is appropriate to complete Stakeholder Interview 4 4 4 4 Time x
Consultation published
an application form for your projects Survey Responses
We will publish clear guidelines on our requirements for each Stakeholder Interview 4 4 4 4 Time x
Guidance published
application form associated with your project Survey Responses
Provide a facility that allows you to submit your connection application online We will provide a simple, tailored online application facility Stakeholder Interview 4 4 4 4 Time x
On-line facility available
on our connections website Survey Responses
Our online application facility will validate your information Stakeholder Interview 4 4 4 4 Time x
On-line facility available
and provide on-screen ‘hint’ text to support you through the process Survey Responses
You will be able to upload supporting documents to assist us in Stakeholder Interview 4 4 4 4 Time x
On-line facility available
processing your application i.e. photos, drawings, site development plans etc Survey Responses
An automatic email acknowledging your submitted application Stakeholder Interview 4 4 4 4 Time x
Automatic email provided
will be provided Survey Responses
Provide an online estimation tool We will develop a site location plan drawing tool (for up to 25 plots per customer) allowing you to Stakeholder Interview indicate your property or site and proposed connection point(s) to support your online application Survey Responses 4 4 4 4 Time x Facility available on line
We will monitor the level of demand for this tool and seek your feedback to inform Stakeholder Interview 4 4 4 4 Time x Feedback sought and
the development of any future IT online services Survey Responses findings published
Extend the principles of ‘Quote +’, our free-of-charge feasibility study offer, to all metered customers We will provide details of what capacity is currently available Stakeholder Interview 4 4 4 Time x
Information provided
i.e. where your connection will not require a reinforcement to the network Survey Responses
We will introduce a voluntary standard of 20 working days Stakeholder Interview 4 4 4 Time x
‘Quote +’ study introduced
for you to receive your ‘Quote +’ study Survey Responses
Provide additional support to ‘first-time’ customers For customers who have not requested a quote from us in the past we will pilot a ‘buddy’ system Stakeholder Interview 4 4 4 4 Satisfaction x
Dedicated person assigned to which provides you with a local contact who will guide you through the application form Survey Responses support ‘first-time’ customers
M1
M2
M3
M4
M5
M6
www.spenergynetworks.co.uk
37
“ It would be good to have guidance documents for non-domestic connections such as cable
ducting, meter installations, depth guides for underground services ”
“ We would appreciate being able to access records of
existing cables and substations and sometimes pay third parties for this
information ”
Information Provision
To ensure we provide all our customers with clear and concise information and data that allows customers to undertake their own assessment of their connection needs before seeking a formal connection offer
What we did in 2014 ... Published ‘Our Process Explained’ leaflet on our website and issue a copy with our welcome pack ... Upon request we will provide access to our cable records ... Published a ‘jargon buster’ to explain some of our most frequently used technical terms ... Provided online calculators to provide an estimate of costs prior to application ... Created and published metering guidance leaflets to assist with getting meters installed
This year, you have told us
“ We would find it handy to be able to
view the sizes of transformers on your maps ”
“ Substation load information would be useful. The Long Term Development Statement does include information on Primary SS loadings but it is unclear how up to date this
information is ”
“ We are still unclear how to be granted access to cable record plans online ”
29 Interviews1,209 Surveys Issued
129 Responses Received
LV Work HV Work HV&EHV EHV & AboveAccount Managed 3 3 3 3Repeat 3 3First-time 3 3
HV Work
ConsultantLV
WorkHV
WorkDeveloper
HV Work
ConsultantHV
WorkDeveloper
www.spenergynetworks.co.uk
38
Market Segment Timeframe Action Source of LV HV HV & EHV EHV Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work &Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Improve the way we provide information to facilitate a better connections process We will ensure that our existing account managed portfolio are made aware Stakeholder Interview Details of available information of all the information we provide to facilitate their connection, Survey Responses 4 4 4 4 Satisfaction x provided to account managed including relevant access to our GIS maps portfolio, awareness and uptake increased
We will publicise the information that we provide through Survey Responses 4 4 4 4 Satisfaction x Campaign created and targeted
an awareness campaign communications issued
Where you have told us that some of the information we provide is difficult to understand Stakeholder Interview 4 4 4 4 Satisfaction x Simple overviews and
(e.g. some of our technical specifications) we will provide a simplified overview and offer guidance Survey Responses guidance provided
We will provide a list and synopsis of relevant connections technical Stakeholder Interview 4 4 4 4 Satisfaction x
List provided
and design specifications on request Survey Responses
Provision of an on-line power conversion tool We will provide an online facility that allows you to convert your Survey Responses 4 4
Satisfaction
x On-line facility available
power requirements from kilowatts (kW) to Amps (A) and vice versa
Provide load information on our 33kV and 11kV networks for our customers Stakeholder Interview We will publish minimum and maximum load information Survey Responses 4 4 Time
33kV information available on all our 33kV circuits Account Management on the website
We will publish minimum and maximum load information Stakeholder Interview 4 4 Time
11kV information available on all our 11kV circuits Survey Responses on the website Account Management
We will investigate and issue our findings on whether similar information can be Stakeholder Interview 4 4 Time
Investigation complete provided for all our 11kV substations Survey Responses and findings published Account Management
We will investigate and issue our findings on whether similar information can be Stakeholder Interview 4 4 Time
Investigation complete provided for all our LV circuits Survey Responses and findings published Account Management
Information ProvisionThis year we intend to...
M7
M8
M9
www.spenergynetworks.co.uk
39
“ It would be good to be better informed on G59 for
demand applications ”
“ Communication is key. A prestart meeting to agree dates and routes and restrictions is essential and
confirmation of actual attendance date closer to the time ”
Communication To communicate with our customers in the manner in which they seek, within acceptable timeframes and with the quality our customers deserve
What we did in 2014 ... Increased our attendance at industry events and improved our relationships with key trade bodies and trade associations ... Published on our website key contact details for our Account Managers and Heads of Design and Delivery ... Embedded into our design and delivery process key touch points in your project that your Design resource or Project Manager will contact you to discuss your project
This year, you have told us
“ I would like to contact a
designer with local knowledge ”
LV Work
HV Work
“ As a local authority we previously enjoyed contact with local engineers and
an Account Manager. As a client it is difficult to make contact with you when our contractors or subcontractors make
39
applications on our behalf ” HV
Work
“ Communication at all stages would be welcomed. Sometimes, the reassurance that
the request is being progressed allows us to pass this reassurance
on to the client ”
HV Work
LV Work
29 Interviews1,209 Surveys Issued
120 Responses Received
LV Work HV Work HV&EHV EHV & AboveAccount Managed 3 3 3 3Repeat 3 3First-time 3 3
www.spenergynetworks.co.uk
40
CommunicationThis year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV & Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Alternative methods for communicating with you We will develop YouTube clips of our key processes Stakeholder Interview 4 4 4 4 Satisfaction x
YouTube clips available
(e.g. ‘Your Works’ to Metering Process) and where to find key resources on our website
Survey Responses
We will use industry bodies and trade associations Stakeholder Interview 4 4 4 4 Satisfaction x Circulation list developed and
to distribute key messages and updates Survey Responses messages distributed
You will be able to register your details with us to receive regular relevant updates Stakeholder Interview 4 4 4 4 Satisfaction x Registration facility
(e.g. our quarterly newsletter) Survey Responses
available online
Leverage the benefits of our District Model by providing you with a more local service We will notify you with contact details Stakeholder Interview 4 4 4 4 Satisfaction x
Communication issued
of key district personnel Survey Responses
We will update our website with contact details Stakeholder Interview 4 4 4 4 Satisfaction x
Website updated
of key district personnel Survey Responses
‘Launch Days’ will be organised in each district to introduce the team Stakeholder Interview 4 4 4 4 Satisfaction x ‘Launch days’ held
and publicise the enhanced local focus that the new structure brings Survey Responses at each district
Once you have accepted your connections offer, Stakeholder Interview 4 4 4 4 Satisfaction x
Contact provided within 2 days
we will confirm who your assigned Delivery contact is within two working days Survey Responses
We will extend the scope of our ‘District Days’ at our local depots to cater for Stakeholder Interview 4 4 4 4 Time x
District Days Published
the resolution of any technical issues you may have Survey Responses
We will commit to meeting with you within five working days Stakeholder Interview 4 4 4 4 Satisfaction x Meeting requested and
if you request a pre-construction meeting Survey Responses held within 5 days
We will meet with you on-site to discuss your technical issues Stakeholder Interview 4 4 4 4 Time x Meeting offered within
within five working days of a request Survey Responses 5 working days
Provide additional support to you when there is a distributed generation element to your project, for those who are new to this process Stakeholder Interview We will host customer workshops to discuss the G83 and G59 Survey Responses 4 4 4 4 Time x
Workshop dates published
application processes that accompany your metered connection application Account Management
We will publish guidance on how to complete the G59 ENA form Stakeholder Interview 4 4 4 4 Time x
Guidance published
Survey Responses Account Management
We will provide you with access to a local distributed generation Stakeholder Interview 4 4 4 4 Time x Contact available and
specialist to answer any queries that you may have Survey Responses contact details published Account Management
M10
M11
M12
www.spenergynetworks.co.uk
41
Communication [continued]
This year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV & Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
On occasion, we recognise there can be delays to getting your meter fitted. While this is not within our direct control we will provide support and assistance We will deliver an awareness campaign through multiple channels Survey Responses 4 4 4 4 Time x
Information published that ensures customers are more aware of the information we provide
Account Management
on website
We will readily make available to you the key contacts Survey Responses 4 4 4 4 Time x Information published on
within all suppliers Account Management website and available on request
A ‘Metering Champion’ will be identified within each district that will provide Survey Responses 4 4 4 4 Time x
Metering champions appointed a point of escalation if you face difficulties getting your meter fitted Account Management
M13
www.spenergynetworks.co.uk
42
“ It would be good if you offered on online portal
providing details on ACPs. There are a number of companies that do offer
this service but at a cost ”
Consultant
Choice We want to ensure that you make the right choice when making a new connection to our network, whether that is with an alternative connection provider or otherwise
What we did in 2014 ... Introduced monthly meetings with ICP/IDNO’s to go through projects in detail and resolve any issues ... Introduced a new system RADAR, for tracking all non-contestable connection costs and requests providing the ability to self register projects ... Carried out additional training and support sessions for our new RADAR system ... We introduced biannual Alternative Connection Provider workshops
This year, you have told us
LV Work
“ Not sure of the truth but the IDNO did suggest
that SP had been slow to respond in relation to the POC ”
HV Work
29 Interviews1,209 Surveys Issued
114 Responses Received
LV Work HV Work HV&EHV EHV & AboveAccount Managed 3 3 3 3Repeat 3 3First-time 3 3
“ It would be useful if other DNOs accreditations
were accepted and any differences highlighted ”
DeveloperHV
Work
www.spenergynetworks.co.uk
44
ChoiceThis year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV & Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Accreditation We will allow alternative connection providers to work Customer Workshops 4 4 Time x
Process updated and under their own safety rules
Code of Practice
communicated
We will recognise other DNOs accreditations of alternative connection providers Customer Workshops 4 4 Time x
Process updated and and use them as evidence to provide accreditation Code of Practice communicated
We will provide an improved accreditation training programme Customer Workshops 4 4 4 4 Time x
Access to training provided
and access to training Code of Practice
We will publish and communicate Customer Workshops 4 4 4 4 Time x Workshops held with
these changes to you
Code of Practice
Stakeholders
Self-Determination of Point of Connection (POC) We will provide regular updates to the Customer Workshops 4 4 4 4 Time x
Information published
load information provided Code of Practice
We will implement a national agreement Customer Workshops 4 4 4 4 Time x Process updated and
for substation access Code of Practice communicated
We will provide training for the determination of the POC Customer Workshops 4 4 Time x
Access to training provided
for alternative connection providers Code of Practice
Alternative connection providers will be allowed to Customer Workshops 4 4 Time x Process updated and
self-determine their own POCs Code of Practice communicated
We will implement a process to provide technical support Customer Workshops 4 4 4 4 Time x Process updated and
and design advice Code of Practice communicated
Design Approval We will review, update and add design and technical specifications Customer Workshops 4 4 4 4 Time x
Review completed and where they are currently not available Code of Practice updates published
Alternative connection providers will be allowed to Customer Workshops 4 4 Time x Process updated and
undertake their own design approval of the contestable works Code of Practice communicated
We will implement a process for providing technical support Customer Workshops 4 4 4 4 Time x Process updated and
and design advice Code of Practice communicated
We will develop robust adoption agreements to reflect Customer Workshops 4 4 4 4 Time x
Adoption agreements revised
the revised process Code of Practice
Inspection & Monitoring We will develop and publish a process for the self-inspection Customer Workshops 4 4 4 4 Cost x
Process updated and of contestable works
Code of Practice
communicated
We will provide a standardised mechanism for recording Customer Workshops 4 4 4 4 Cost x Process updated and
and reporting self-inspection Code of Practice communicated
We will develop robust adoption agreements Customer Workshops 4 4 4 4 Cost x
Adoption agreements revised
to reflect the revised process Code of Practice
M14
M15
M16
M17
www.spenergynetworks.co.uk
43
Choice [continued]
This year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV & Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Link Boxes We will remove the universal requirement Customer Workshops 4 4 4
Cost x Process updated and
for link boxes Code of Practice communicated
We will align our link box policy with Customer Workshops 4 4 4 Cost x
Process updated and the provision of Emergency Response Code of Practice communicated
An alternative means for recording the IDNO boundary Customer Workshops 4 4 4 Cost x Process updated and
will be developed Code of Practice communicated
Emergency Service Provision We will provide an emergency telephone number for Customer Workshops 4 4 4 4 Satisfaction x Telephone number provided
the provision of Emergency Response Code of Practice
We will agree a scope of service and Customer Workshops 4 4 4 4 Satisfaction x
Scope of service agreed
communication channels with IDNOs Code of Practice
We will provide a schedule of charges Customer Workshops 4 4 4 4 Satisfaction x Schedule of charges & standards
and standards of performance Code of Practice of performance provided
Choices Available to You We will provide a list of alternative connection providers active within our area by Customer Workshops 4 4 4 4 Satisfaction List published
considering who has applied for a non-contestable quote in the last twelve months Code of Practice
We will also provide a facility to allow alternative connection providers Customer Workshops 4 4 4 4 Satisfaction
Online facility available
to register their details and services offered Code of Practice
Develop an ‘industry portal’ that provides you with the opportunity to seek which alternative connection providers would be interested in delivering the contestable works on your project As a trial, we will ask our customers if they wish us to circulate their connection requirements Customer Workshops 4 4 4 4 Satisfaction
Trial commenced
to alternative connection providers who can then contact the customer directly to offer Code of Practice an alternative quote Stakeholde r Interview
We will engage with all active alternative connection providers within our licence area Customer Workshops 4 4 4 4 Satisfaction Alternative connection
to establish their interest in being involved in this trial Code of Practice providers engaged Stakeholde r Interview
Should this trial be successful, we will consider implementing a ‘bulletin board’ facility on our Customer Workshops 4 4 4 4 Satisfaction
Facility provided in RAdAR
current portal (RAdAR) to inform alternative connection providers of customers who have Code of Practice requested alternative quotes Stakeholde r Interview
Part funded connections Customer Workshops As a trial we will allow alternative connection providers to undertake part funded connections Code of Practice 4 4 4 4 Cost Trial undertaken
(e.g. reinforcement), where an appropriate opportunity arises Stakeholde r Interview
Using the findings from the trial we will develop an approach that allows alternative connection Customer Workshops 4 4 4 4 Cost
Enduring process implemented
providers to undertake part funded connections as an enduring process Code of Practice Stakeholde r Interview
M18
M19
M20
M21
M22
www.spenergynetworks.co.uk
45
“ Legals is usually an extremely drawn out process. The process and timescales needs
to be reduced dramatically, as often impacts the power on date
of installations ”
Enablers to Connections We want to remove, where possible, all perceived barriers to connection and will do so by listening to your feedback and seeking resolution
What we did in 2014 ... We revised our payment plan policy offering a smaller upfront payment and future milestone ... We introduced dual offer letters for our 33kV and greater than 5MW connection offers, providing you with the ability to either accept the non-contestable or full works ... We updated our Grantors charter and published this on website ... We provided greater detail in breakdown of costs within our offer letters
This year, you have told us
“ Always takes too long, there is an inconsistency in approach
particularly with external solicitors. Always seem to start from scratch
rather than use previous agreements with landowners as starting point ”
HV Work
29 Interviews1,209 Surveys Issued
88 Responses Received
LV Work HV Work HV&EHV EHV & AboveAccount Managed 3 3 3 3Repeat 3 3First-time 3 3
DeveloperHV
WorkDeveloper
“ Please consider commencing works without
full payment up front ”
HV Work
“ If you mean providing a quote which has Contestable
and Non Contestable broken out for independent acceptance then this would
be good”
HV Work
Consultant
“ Perhaps having some kind of online project tracking would be useful”
LV Work
www.spenergynetworks.co.uk
46
Enablers to ConnectionsThis year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV & Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
The provision of Land Rights on your connection project Stakeholder Interview & Panel We will publish our approach to securing land rights Survey Responses 4 4 4 4 Satisfaction x
Policy published
on our website
Account Management
We will review and, where appropriate, adapt our approach to connection quotations Stakeholder Interview & Panel 4 4 4 4 Satisfaction x Revised Connection
and agreements to ensure there is greater clarity on the obligations of all parties Survey Responses
Agreements utilised under the agreement Account Management
We will provide a process flow chart on our website, setting out our Stakeholder Interview & Panel 4 4 4 4 Satisfaction x
Process flow chart published
“cradle to grave” connection process, highlighting land rights Survey Responses Account Management
Our land and planning officers will be based in your local district offices (alongside Stakeholder Interview & Panel 4 4 4 4 Satisfaction x
L&PO based locally
your project manager) to ensure there is a cohesive approach to the delivery Survey Responses of your connection Account Management
Five days after we inform our Land and Planning Team of your requirements for Stakeholder Interview & Panel 4 4 4 4 Time/Cost x
L&PO advised within 5 days
a connection, we will advise you who your nominated Land Officer will be Survey Responses Account Management
Where appropriate, standardised documentation will be used Stakeholder Interview & Panel 4 4 4 4 Time/Cost x Standardised documentation
with you to achieve land rights on your projects Survey Responses utilised Account Management
Provide you with the ability to accept either the non-contestable works or full works on any connection offer we provide you We will extend our current ‘dual offer’ facility to all of Stakeholder Interview 4 4 4 4 Satisfaction x
Facility provided
our connections offers being requested Survey Responses
Provide flexibility in our approach to your individual project needs Where you require clarity or discussion on our Terms & Conditions Stakeholder Interview & Panel 4 4 4 4 Satisfaction x
Service provided
we will commit to responding to you within five working days Survey Responses
We will consult with you on our revised Payment Terms policy Stakeholder Interview & Panel 4 4 4 4 Satisfaction x
Consultation paper published
to ensure that it is fit for purpose Survey Responses
M23
M24
M25
www.spenergynetworks.co.uk
47
Enablers to Connections [continued]
This year we intend to... Market Segment Timeframe Action Source of LV HV HV & EHV EHV & Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action Work Work Work Above Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Introduce voluntary standards for the time we take to provide offers to divert our existing assets We will provide LV Diversion quotations Stakeholder Interview 4 Time x
Voluntary standards published within 25 working days and communicated
We will provide HV Diversion quotations Stakeholder Interview 4 Time x
Voluntary standards published within 35 working days and communicated
We will provide EHV Diversion quotations Stakeholder Interview 4 4 Time x Voluntary standards published
within 35 working days and communicated
Consult with you on the provision of an end-to-end online facility to manage you through the Connections process Some of you have told us that you would like us to provide you with an online facility Stakeholder Interview
Consultation and subsequent
that manages the end-to-end connections process. We will consult with you to Survey Responses 4 4 4 4 Time x findings published
determine the feasibility and value of implementing such a facility
Account Management
Some of you have told us that you would like the ability to design your connection online. Stakeholder Interview We are due to implement an online design tool for minor connections customers in April 2015. Survey Responses 4 4 4 4 Time x
Consultation and subsequent We will consult with you to determine the value in extending this facility for our Account Management findings published major connections customers
M26
M27
www.spenergynetworks.co.uk
Unmetered Work Plan
www.spenergynetworks.co.uk
49
“ Simplify the application
form further ”
Application ProcessTo ensure that the application process is as simple as possible for you, whilst still providing us with all information necessary to deliver a connection offer that meets your needs
What we did in 2014 ... Tailored our process for Local Authority (LA) applications ... Allowed other Local Authority non-lighting works to be completed using this process ... Introduced tailored ‘Welcome Packs’ by project type to provide relevant information depending on the type of connection being requested ... Reviewed and simplified our current application forms ... Introduced a new central email address for you to send your new enquiries
This year, you have told us
“ We would like to be able to make online applications ”
6 Interviews223 Surveys Issued
34 Responses Received
UMS LA UMS Other UMS PFIAccount Managed 3 3 Repeat 3 3 3First-time 3 3
“ I would like to have direct contact with local
engineers to discuss my application ”
UMS Other
UMS Other
UMS Other
www.spenergynetworks.co.uk
50
Application ProcessThis year we intend to... Market Segment Timeframe Action Source of UMS UMS UMS Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action LA Other PFI Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Review the minimum information we request from you for the initial connection application We will consult with you on what information you feel is appropriate to complete Stakeholder Interview 4 4 4 Time x
Consultation published
an application form for your projects Survey Responses
We will publish clear guidelines on our requirements for each Stakeholder Interview 4 4 4 Time x
Guidance published
application form associated with your project Survey Responses
Review and extend the self-serve UMS principles currently offered to only Local Authorities Undertake a consultation with all Local Authorities Stakeholder Interview 4
Satisfaction x Meetings held with all
in order to ensure that the current form is ‘Fit for Purpose’ Local Authorities
Produce a guide on how to complete the current application Stakeholder Interview 4 4 4 Satisfaction x
Guide produced and published
and calculate a cost for connection
Consult with UMS customers with the ability Stakeholder Interview 4 4 4 Satisfaction x Consultation with 100%
to ‘self-serve’ customer base
We will provide you with an assigned contact to assist you with Stakeholder Interview 4 4 4 Satisfaction x
Contact details provided
the ‘self-serve’ process
Provide a facility that allows you to submit your connection application online We will provide a simple, tailored online application facility Stakeholder Interview 4 4 4 Time x
On-line facility available
on our connections website Survey Responses
Our online application facility will validate your information Stakeholder Interview 4 4 4 Time x
On-line facility available
and provide on-screen ‘hint’ text to support you through the process Survey Responses
You will be able to upload supporting documents to assist us in Stakeholder Interview 4 Time x
On-line facility available
processing your application i.e. photos, drawings, site development plans etc Survey Responses
An automatic email acknowledging your submitted Stakeholder Interview 4 Time x
Automatic email provided
application will be provided Survey Responses
UM1
UM2
UM3
www.spenergynetworks.co.uk
51
“ We still don’t always know who to contact ”
Information ProvisionTo ensure we provide all our customers with clear and concise information and data that allows customers to undertake their own assessment of their connection needs before seeking a formal connection offer
What we did in 2014 ... Published ‘Our Process Explained’ leaflet on our website and issue a copy with our welcome pack ... Upon request we will provide access to our cable records ... Published a ‘jargon buster’ to explain some of our most frequently used technical terms
This year, you have told us
“We would like to be able to
access more information from your GIS maps ”
6 Interviews223 Surveys Issued
33 Responses Received
UMS LA UMS Other UMS PFIAccount Managed 3 3 Repeat 3 3 3First-time 3 3
“We like more guidance
on your processes ” “ We would
like to receive regular progress reports
from you ”
UMS Other
UMS Other
ConsultantUMS
OtherDeveloper UMS
www.spenergynetworks.co.uk
52
Information ProvisionThis year we intend to... Market Segment Timeframe Action Source of UMS UMS UMS Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action LA Other PFI Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Improve the way we provide information to facilitate a better connections process We will ensure that all Local Authorities are made aware of all the information we provide Stakeholder Interview 4 4 4 Satisfaction x
Details of available information to facilitate their connection, including relevant access to our GIS maps
Survey Responses
provided to Local Authorities, awareness and uptake increased
Ensure that all customers are aware of the information we provide, Stakeholder Interview 4 4 4 Satisfaction x Campaign created and targeted
publicise this through an awareness campaign Survey Responses communications issued
Where you have told us that some the information we provide is difficult to understand Stakeholder Interview 4 4 4 Satisfaction x Simple overviews and
(e.g. some of our technical specifications) we will provide a simplified overview and offer guidance Survey Responses guidance provided
We will provide a list and synopsis of relevant connections technical Stakeholder Interview 4 4 4 Satisfaction x
List provided
and design specifications on request Survey Responses
UM4
www.spenergynetworks.co.uk
53
“ We like more regular
meetings with your contractors ”
CommunicationTo communicate with our customers in the manner in which they seek, within acceptable timeframes and with the quality our customers deserve
What we did in 2014 ... We introduced quarterly meetings with LA’s ... Introduced a robust process with our contractors to ensure you are better informed of programmed works ... Published on our website key contact details for our Account Managers and Heads of Design and Delivery ... Embedded into our design and delivery process key touch points in your project that your Design resource or Project Manager will contact you to discuss your project
This year, you have told us
“ We would like to work with a more
local service through application and delivery
”
6 Interviews223 Surveys Issued
30 Responses Received
UMS LA UMS Other UMS PFIAccount Managed 3 3 Repeat 3 3 3First-time 3 3
“ We would like visibility of points of
contact ” “ We would
like a single point of contact ”
UMS UMS UMSUMS
Other
“ We would like more clarity on your requirements for
site readiness with technical assistance provided ”
UMS
www.spenergynetworks.co.uk
54
CommunicationThis year we intend to... Market Segment Timeframe Action Source of UMS UMS UMS Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action LA Other PFI Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Alternative methods for communicating with you We will develop YouTube clips of our key processes Stakeholder Interview 4 4 4 Satisfaction x
YouTube clips available
(e.g. ‘Your Works’ to Metering Process) and where to find key resources on our website Survey Responses
We will use industry bodies and trade associations Stakeholder Interview 4 4 4 Satisfaction x Circulation list developed and
to distribute key messages and updates Survey Responses messages distributed
You will be able to register your details with us to receive regular relevant updates Stakeholder Interview 4 4 4 Satisfaction x Registration facility
(e.g. our quarterly newsletter) Survey Responses
available online
Leverage the benefits of our District Model by providing you with a more local service We will notify you with contact details Stakeholder Interview 4 4 4 Satisfaction x
Communication issued
of key district personnel Survey Responses
We will update our website with contact details Stakeholder Interview 4 4 4 Satisfaction x
Website updated
of key district personnel Survey Responses
‘Launch Days’ will be organised in each district to introduce the team Stakeholder Interview 4 4 4 Satisfaction x ‘Launch days’ held
and publicise the enhanced local focus that the new structure brings Survey Responses at each district
Once you have accepted your connections offer, Stakeholder Interview 4 Satisfaction x
Contact provided within 2 days
we will confirm who your assigned Delivery contact is within two working days Survey Responses
We will extend the scope of our ‘District Days’ at our local depots to cater for Stakeholder Interview 4 4 4 Time x
District days published
the resolution of any technical issues you may have Survey Responses
We will commit to meeting with you within five working days Stakeholder Interview 4 Satisfaction x
Meeting requested and if you request a pre-construction meeting Survey Responses held within 5 days
We will meet with you on-site to discuss any technical issues Stakeholder Interview 4 4 4 Time x Meeting offered within
within five working days of a request Survey Responses 5 working days of request
Consult with our Local Authorities to ensure that our communication is relevant and tailored as required Re-establish the frequency and preferred method of communication Stakeholder Interview 4
Satisfaction x Meetings held with LA
for each Local Authority and plan developed
Ensure that key UMS SPEN contacts are provided Stakeholder Interview 4 Satisfaction x
Key contacts provided
to each authority
Provide a facility for key personnel to register to be notified of faults/restoration Stakeholder Interview 4 Satisfaction x
Registration facility and major works that may affect residents available online
UM5
UM6
UM7
www.spenergynetworks.co.uk
55
ChoiceWe want to ensure that you make the right choice when making a new connection to our network, whether that is with an alternative connection provider or otherwise
What we did in 2014 ... Introduced monthly meetings with ICP/IDNO’s to go through projects in detail and resolve any issues ... Introduced a new system RADAR, for tracking all non-contestable connection costs and requests providing the ability to self register projects ... Carried out additional training and support sessions for our new RADAR system ... We introduced biannual Alternative Connection Provider workshops
This year, you have told us
6 Interviews223 Surveys Issued
31 Responses Received
UMS LA UMS Other UMS PFIAccount Managed 3 3 Repeat 3 3 3First-time 3 3
“We would like a competitive
alternative so we are able to compare costs ”
“ We would like more information on the options available for
choosing an ICP ”
“ Better information to enable us to make a choice of a connections provider ”
UMS UMS UMS
www.spenergynetworks.co.uk
56
ChoiceThis year we intend to... Market Segment Timeframe Action Source of UMS UMS UMS Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action LA Other PFI Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Accreditation We will recognise other DNOs’ accreditations of alternative providers Customer Workshops 4 4 4 Time x
Process updated and and use them as evidence to provide accreditation
Code of Practice
communicated
We will provide an improved accreditation training programme Customer Workshops 4 4 4 Time x
Access to training provided
and access to training Code of Practice
We will also recognise other training providers Customer Workshops 4 4 4 Time x Process updated and
who provide an accredited programme Code of Practice communicated
We will publish and communicate Customer Workshops 4 4 4 Time x Workshops held with
these changes to you
Code of Practice
Stakeholders
Self-Determination of Point of Connection (POC) We will implement a national agreement Customer Workshops 4 4 4 Time x
Process updated and for substation access Code of Practice communicated
We will provide training for the determination Customer Workshops 4 4 4 Time x
Access to training provided
of the POC for alternative connection providers Code of Practice
Alternative connection providers will be allowed to Customer Workshops 4 4 4 Time x Process updated and
self-determine their POCs Code of Practice communicated
We will implement a process to provide technical support Customer Workshops 4 4 4 Time x Process updated and
and design advice Code of Practice communicated
Design Approval We will review, update and add design and technical specifications Customer Workshops
4 4 4 Time x Review completed and
where they are currently not available Code of Practice updates published
Alternative Connection providers will be allowed to undertake their own design approval Customer Workshops 4 4 4 Time x Process updated and
of the contestable works Code of Practice communicated
We will implement a process for providing technical support Customer Workshops 4 4 4 Time x Process updated and
and design advice Code of Practice communicated
We will develop robust adoption agreements to reflect Customer Workshops 4 4 4 Time x
Adoption agreements revised
the revised process Code of Practice
UM8
UM9
UM10
www.spenergynetworks.co.uk
57
Choice [continued]
This year we intend to... Market Segment Timeframe Action Source of UMS UMS UMS Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action LA Other PFI Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
Inspection & Monitoring We will develop and publish a process for the self-inspection Customer Workshops 4 4 4 Cost x
Process updated and of contestable works
Code of Practice
communicated
We will provide a standardised mechanism for recording Customer Workshops 4 4 4 Cost x Process updated and
and reporting self-inspection Code of Practice communicated
We will develop robust adoption agreements Customer Workshops 4 4 4 Cost x
Adoption agreements revised
to reflect the revised process Code of Practice
Choices Available to You We will provide a list of alternative connections providers active within our area by Customer Workshops 4 4 4 Satisfaction x
List published
considering who has applied for a non-contestable quote in the last twelve months
Code of Practice
We will also provide a facility to allow alternative connection providers Customer Workshops 4 4 4 Satisfaction x
Online facility available
to register their details and services offered Code of Practice
Develop an ‘industry portal’ that provides you with the opportunity to seek which alternative connection providers would be interested in delivering the contestable works on your project As a trial, we will ask our customers if they wish us to circulate their connection Customer Workshops requirements to alternative connection providers who can then contact the customer Code of Practice
4 4 4 Satisfaction Trial commenced
directly to offer an alternative quote Stakeholder Interview
We will engage with all active alternative connection providers within our licence area Customer Workshops 4 4 4 Satisfaction Alternative connection
to establish their interest in being involved in this trial Code of Practice Stakeholder Interview providers engaged
Should this trial be successful, we will consider implementing a ‘bulletin board’ facility Customer Workshops 4 4 4 Satisfaction
Facility provided in RAdAR
on our current portal (RAdAR) to inform alternative connection providers of customers Code of Practice who have requested alternative quotes Stakeholder Interview
UM11
UM13
UM12
www.spenergynetworks.co.uk
58
“ We would like clarity on your land
rights policy ”
Enablers to Connection We want to remove, where possible, all perceived barriers to connection and will do so by listening to your feedback and seeking resolution
What we did in 2014 ... Mutually agree to consolidated billing when requested ... Introduced new management reporting system with early warning indicators to ensure work prioritised and progressed in correct timescales ... We updated our Grantors charter and published this on website ... We provided greater detail in breakdown of costs within our offer letters
This year, you have told us
“ We would like you to look at updating your LA process
”
6 Interviews223 Surveys Issued
30 Responses Received
UMS LA UMS Other UMS PFIAccount Managed 3 3 Repeat 3 3 3First-time 3 3
“ Provide greater flexibility in the terms of you offer ”
UMS UMS UMS
“ SPENs T&Cs for wayleaves could be more flexible and time
required for wayleaves to be put in place improved ”
UMS Other
Consultant
www.spenergynetworks.co.uk
59
Enablers to ConnectionThis year we intend to... Market Segment Timeframe Action Source of UMS UMS UMS Key Strategic (Q1) (Q2) (Q3) (Q4) 2016 KPI Action LA Other PFI Objective Apr-Jun Jul-Sep Oct-Dec Jan-Mar
The provision of Land Rights on your connection project Stakeholder Interview & Panel We will publish our approach to securing land rights on our website Survey Responses 4 4 4 Satisfaction
Policy published
Account Management
We will review and, where appropriate, adapt our approach to connection quotations Stakeholder Interview & Panel 4 4 4 Satisfaction x Revised Connection
and agreements to ensure there is greater clarity on the obligations of all parties Survey Responses Agreements utilised under the agreement Account Management
We will provide a process flow chart on our website, setting out our “cradle to grave” Stakeholder Interview & Panel 4 4 4 Satisfaction
Process flow chart published
connection process, highlighting land rights Survey Responses Account Management
Our land and planning officers will be based in your local district offices Stakeholder Interview & Panel 4 4 4 Satisfaction
L&PO based locally
(alongside your project manager) to ensure there is a cohesive approach Survey Responses to the delivery of your connection Account Management
Five days after we inform our Land and Planning Team of your Stakeholder Interview & Panel 4 4 4 Satisfaction
L&PO advised within 5 days
requirements for a connection, we will advise you who your nominated Survey Responses Land Officer will be Account Management
Where appropriate, standardised documentation will be used Stakeholder Interview & Panel 4 4 4 Satisfaction Standardised documentation
with you to achieve land rights on your projects Survey Responses utilised Account Management
Provide you with the ability to accept either the non-contestable works or full works on any connection offer we provide you We will extend our current ‘dual offer’ facility to all of Stakeholder Interview 4 4 4 Satisfaction x
Facility provided
our connections offers being requested Survey Responses
Provide flexibility in our approach to your individual project needs Where you require clarity or discussion on our Terms & Conditions Stakeholder Interview & Panel 4 4 4 Satisfaction x
Service provided
we will commit to responding to you within five working days Survey Responses
Consult with you on the provision of an end-to-end online facility to manage you through the Connections process Some of you have told us that you would like us to provide you with an online facility Stakeholder Interview 4 4 4 Time
Consultation and subsequent that manages the end-to-end connections process. We will consult with you to Survey Responses findings published determine the feasibility and value of implementing such a facility
Some of you have told us that you would like the ability to design your connection online. Stakeholder Interview Consultation and subsequent
We are due to implement an online design tool for minor connections customers in April 2015. Survey Responses 4 4 4 Time
findings published
We will consult with you to determine the value in extending this facility for our major connections customers
UM14
UM16
UM15
UM17
www.spenergynetworks.co.uk
60
Glossary of TermsTerm DefinitionAccreditation The appropriate qualifications to allow alternative connection providers to operate on our electrical
networkANM Active Network Management; using technology to enable generators to connect in constrained areas
on a commercially un-firm basis ARC Accelerating Renewables Connections; SPEN ‘Low Carbon Networks’ funded project to consider
innovative methods for connecting DG quicker and cheaperAVR Automatic Voltage Regulator; this is a device which can be deployed on our overhead line network and
controls the voltage to ensure the network remains within statutory limitsBudget Quote A budget quote is provided to aid customers with up front planning of projects and is a simple review of
the network within the vicinity of the proposed development and does not include detailed modelling of the system. A budget quote cannot be contracted
BMCS Broader Measures of Customer ServiceCCCM Common Connection Charging MethodologyCIC Competition in Connections; ability for a customer to seek connection to the network using a Lloyds
accredited ICP of your choiceCIC Industry Code of Practice This is a proposed industry standard which is being developed jointly by DNOs and OFGEM. The code
is aimed at making it easier for alternative connection providers to get their customers connected and better inform customers of their choices
Collaborative Connections These are connections where multiple customers are brought together to benefit from shared connection costs and shared assets to maximise the amount of generation connected in any part of our network
Contestable When we talk about contestable work, these are the ‘off the system’ works, which can be completed by either ourselves or a Lloyds accredited ICP of your choice
Contracted Capacity Register This lists generators that are contracted but not physically connected to our networkCRAM Connection Registration and Management. This was a legacy IT system utilised to manage CIC enquires
where a Lloyds accredited ICP of your choice was being employed to complete the contestable worksCRM Under our SP brand name of Athos, CRM is our new Customer Relationship Management system which
will help us better serve our customersCustomer A customer is defined as someone who is or has applied for a connection to our networkCustomer Surgeries These are held monthly for any customers who wished to discuss a project with us at any time in the
processDG Distributed Generation; this is the connection of generation to any point of the distribution system,
from 230V up to 33,000V in Scotland or 132,000V in England & WalesDNO Distribution Network Operators, responsible for owning operating, and maintaining the electrical
network in their licensed geographical areaDual Offers These are formal offers which facilitate the acceptance of either the full works or just the non-
contestable works, with the contestable works completed by a Lloyds accredited ICP of your choiceExport Management Device These are devices which seek to manage the local demand alongside any generator, essentially
restricting export to our network Feasibility Study A feasibility study is a chargeable service to run a number of network models and advise what capacity
is available where on parts of our network. This does not facilitate a connection offer, and does not carry any contractual link to a formal connection offer
Term DefinitionFormal Connection Offer A formal Connection offer facilitates a contract between us and the applicant to accept our offer and
progress the construction works associated with the connectionG59 G59 is the industry standard for generators greater than 16 amp per phaseG83 G83 is the industry standard for small scale embedded generators for connections up to 16 amp
per phase, 3.68 kW single phase connection or when multiple generators are to be connectedGRP Enclosures ‘Glass Reinforced Plastic’ enclosures. Our traditional solution for a substation which requires a battery
set is a brick building. GRP solutions utilise glass reinforced plastic technologies (GRP) to provide substation enclosures that can provide similar environments to brick-built substations
GSPs A Grid Supply Point is the point at which electricity enters the distribution network, leaving the transmission network
Heat-maps These are maps of our HV network, colour coded based on the available capacity on any given circuitICP Independent Connection ProviderIDNO Independent Distribution Network Operators develop, own, operate and maintain local electricity
distribution networksIFI Innovation Funding Incentive (IFI) was introduced by Ofgem to encourage Electricity Distribution,
Electricity Transmission Network Operators to apply technical innovation in the pursuit of investment in and operation of their networks. It will be replaced by the Network Innovation Allowance (NIA) in 2015
Jointing Jointing is a method of connecting two sections of cable togetherLCNF Low Carbon Networks (LCN) Fund was established by Ofgem as part of the electricity distribution
price control that runs until 31 March 2015. The fund offers capital to support projects sponsored by the Distribution Network Operators (DNOs) to try out new technology, operating and commercial arrangements
Link boxes A link box provides a point of isolation at the interface of an IDNO ( Independent Network Operators) and a DNO network
Market Segment This is the regulatory terminology which defines DGLV and DGHVMetering This is the mechanism for settlement to ensure your generation receives the correct rates for your tariff
and is a key part of the balancing and settling arrangements, which are laid down in the Balancing and Settlement Code (BSC), and is administered by ELEXON
Non-Contestable Where we talk about on-site works, these are typically within either the customers land boundaries or the CDM boundary within which a Principle Contractor operates
On-site On-site works are typically within either the customers land boundaries or the CDM boundary within which a Principle Contractor operates
POCs Point of Connection to the electrical networkQuote + Quote + is a new product which we are currently trialling, which provides options for our customers
quickly whilst maintaining queue positionRAdAR Register of Adopted Asset Requests; this is our current IT system utilised to manage CIC enquires where
a Lloyds accredited ICP of your choice is being employed to complete the contestable worksSoW The Statement of Works process should be followed when it is identified that a generator seeking
a connection to a DNO’s network may have an impact on the transmission networkSubstation A part of our network where DG is connected and we transfer power across boundaries, either by
voltage level or a customer’s point of common couplingWayleaves This is the process which secures the legal right for apparatus to be installed an any given location
and secures the connection to your site for a defined period of time
www.spenergynetworks.co.uk
61
Summary of Relevant Market Segments
Low Voltage (LV) work: LV connection activities involving only LV work, other than in respect of the Excluded Market Segment
High Voltage (HV) work: LV or HV connection activities involving HV work (including where that work is required in respect of connection activities within an Excluded Market Segment).
HV and Extra High Voltage (EHV) work: LV or HV connection activities involving EHV work.
EHV work and above: extra high voltage and 132kV connection activities.
LV work: low voltage connection activities involving only low voltage work.
HV and EHV work: any connection activities involving work at HV or above.
Local Authority (LA) work: new connection activities in respect of LA premises.
Private finance initiatives (PFI) work: new connection activities under PFIs.
Other work: all other non-LA and non-PFI unmetered connections work.
MeteredDemand Connections
Metered Distributed Generation (DG)
Unmetered Connections