Upload
gebzori
View
227
Download
0
Embed Size (px)
Citation preview
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
1/13
SA-2 (Rev.1)
The scope of work comprises the following:-
230kV New Substation and Extension/Renovation of Existing 132kV Substation at
Fenchuganj:
SECTION-I: NEW 230KV SUBSTATION
245 kV Outdoor Switchgear for 1 Breaker System
245kV outdoor switchgear comprising four (4) diameters of 1 circuit breaker system with two
2000A three phase busbars. Two (2) diameters (all fully equipped) for the connection of two (2)
230kV overhead line circuits to Comilla (North), one 235/132/33kV auto-transformer circuit bay
and one 235/132/33kV auto-transformer circuit bay for future provision with necessary 245kV
switchgear and materials.
235/133/33 kV Auto-transformers
One set of 225/300(ONAN/ONAF) MVA, 235/132/33kV, three phase auto-transformer. The three
phase transformer unit shall be equipped with winding of tertiary delta at 33kV, the connectionsbetween the tertiary delta winding and associated earthing/auxiliary transformers by means of
33kV arrangement.
33/0.4 kV Earthing/Auxiliary Transformers
The delta connected tertiary windings of each 3-phase auto-transformers shall supply a 33/0.4 kV,
auxiliary Zig-Zag transformer (one set in total) for the purpose of supplying the substation
400/230V auxiliary power requirements.
Control and Protection for 230kV System
Control, protection equipment and substation automation system (SAS) for one 235/132/33kV
auto-transformers feeder bays, two overhead line bays and one future auto-transformer bay.
Tariff metering for 230kV System
Tariff metering panel for one 235/132/33kV auto-transformers feeder bay and two (2) overhead
line bays.
Civil Works for new 230kV substation
Complete foundations necessary for the above 230kV equipment and gantries.
Complete 230kV switchyard areas including cable ducts, internal service roads, surface treatment,
drainage, site finishing works, boundary fence, guardhouse and outdoor lighting system. Included
are the 235/132/33 kV auto transformer and 33 kV earthing compounds, 245 kV switchgear area,
and new two storied control building with cable basement. The building will include control and
relay room, Communication room, battery room, office/records room, toilet, pantry, interior
lighting, ventilation, air-conditioning, lightning protection and deep tube well for supplying
drinking water.
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
2/13
SA-14 (Rev.1)
SECTION-II: EXTENSION AND RENOVATION OF EXISTING 132 KV
SUBSTATION AT FENCHUGANJ
The equipment to be supplied, installed and commissioned is shown on Bid Drawings :-
Item Description
2B 145 kV Switchgear, equipment connection and steel structures
The 145 kV switchgear shall comply with the particular requirements as
detailed in the Schedule of Technical Requirements included as Appendix A1
to this section and shall comprise the following:-
2B1 One (1) set of 145 kV, 2000A, 31.5kA, 50Hz, 650kVp BIL, live tank type,
gang operated, SF6 gas circuit breakers with spring-stored energy operating
mechanism.
2B2 Seven (7) sets of 145 kV, 1600A (for transformer bay) & 1250A (for linebays), 31.5kA, 50Hz, 650kVp BIL, live tank type, single-pole operation, SF6
gas circuit breakers with spring-stored energy operating mechanism.
2B3 Nine (9) sets of 145kV, 1600A, 31.5kA, 50Hz, 650 BIL, single throw double
air break, center rotating post type, motor operated normal disconnectors with
motor-operated earthing switches.
2B4 Nine (9) sets of 145kV, 1600A, 31.5kA, 50Hz, 650 BIL, single throw double
air break, center rotating post type, motor operated normal disconnectors with
out earthing switches.
2B5 Nine (9) sets of 145kV, 1600A, 31.5kA, 50Hz, 650 BIL, single throw double
air break, center rotating post type, motor operated tandem(series) type
disconnectors with out earthing switches.
2B6 Two (2) sets of 145kV, 2000A, 31.5kA, 50Hz, 650 BIL, single throw double air
break, center rotating post type, motor operated normal type disconnectors for
bus-coupler bay
2B7 Twenty one (21) nos. of single-phase, 4-core, multi ratio, 145kV, 50Hz, 650
BIL post type current transformer.
2B8 Six (6) nos. of single-phase, 4-core, multi ratio, 145kV, 50Hz, 650 BIL post
type current transformer for bus-coupler bay.
2B9 Fifteen (15) nos. of single-phase, 145kV, 2-core, 50Hz, 650 BIL, inductive
type voltage transformers for line bay & busbar.
2B10 Twelve (12) nos. of single-phase, 145kV, 2-core, 50Hz, 650 BIL, capacitor
type voltage transformers.
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
3/13
SCHEDULE A
SA-15 (Rev.1)
2B11 Twenty seven (27) nos. of 120kV continuous operating voltage, 10kA nominal
discharge current, 50Hz, station class, gapless metal oxide type, single phase
surge arresters.
2B12 One (1) lot of busbar conductors (2 x 795MCM TACSR), jack bus and jumper
conductors (2 x ACSR Mallard) as required for connection of 145kV
switchgear in the technical specifications and bid drawings.
2B13 One (1) lot of insulators and fittings including all necessary clamps and
connectors required to complete 145kV switchgear extension and renovation
as specified in the technical specifications and bid drawings.
2B14 One (1) lot of gantry steel structures and equipment supports required to
complete 145kV switchgear extension and renovation as specified in the
technical specifications and bid drawings.
2B15 Sixteen (16) nos of 145kV post type support insulators.
2B16 Shifting of two (2) sets (each set per circuit) of existing switchgears, circuit
breaker & power transformer (132/33kV) with equipment support and.
Included are all necessary associated reconnection works.
2B17 Shifting of four (4) sets (each set per circuit) overhead slack span for existing
four overhead line circuits. Included are all necessary associated reconnection
works.
2F Control, Protection, Substation Automation and Metering
Protection and metering panels for all new 132kV bays are to be installed in
the existing control building. The interface panels to adapt Substationautomation system (SAS) for connection of existing and new feeders shall also
be installed in the old control room building.
The sequence of the control panels and protection panels shall mirror the
actual switchyard layout.
132 kV Circuits
The equipment to be supplied, installed and commissioned is shown on Bid
Drawings comprising the following.
2F1 Control, protection and SAS for two (2) sets of 132kV new overhead Linecircuits to Fenchuganj Power Station Substation.
2F2 Adopting new SAS for existing four overhead line bays.
2F3 Control, protection and SAS for one (1) set of 235/132/33kV AutoTransformer
circuit and associated Earthing/Auxiliary Transformer circuits. Out of two
235/132kV AutoTransformer circuit bay, one shall be kept as future provision.
2F4 Control, protection, SAS for one (1) set of Bus coupler circuit bay.
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
4/13
SA-16 (Rev.1)
2F5 Adopting new SAS for existing two 132/33kV transformer bays in one (1) lot.
2F6 Busbar protection panels for Complete switchyard.
2F7 Tariff Metering panel in one (1) lot to accommodate programmable &
recordable digital 3-phase, 4-wire import and export MWh and MVarh meters
(accuracy class 0.2) for each existing and new 132kV line and transformerfeeder. For each feeder minimum two(2) meters(main-1 & main-2) are to be
provided.
2F8 Communication interface marshalling cubicle in one (1) lot as specified in
Section-10, Volume 2 of 3 for establishment of SCADA system for NLDC
through multiplexer equipment.
2G Overhead Connection between 132kV side of the 235/132kV Power
Transformer in new 230kV Substation to Existing 132kV Substation
132 kV Circuit
2G1 Connection of the 132kV side of the 235/132kV Autotransformer in the new
230kV substation to the existing 132kV switchyard by overhead conductor.
All necessary gantry structure, conductors, insulators, fittings etc. are
requested to be supplied and installed under this scope.
2H Multicore Low Volateg Power and Control Cables
One (1) lot complete set of multicore low voltage auxiliary power and control
cables between all items of equipment supplied under the Contract shall be
supplied, installed with necessary gland, terminated, and identified by colours
& tags. The overall substation cable routing and core schedules shall also beprovided.
2I Earthing and Lightning Protectionn
2I.1 One(1) lot complete design, supply and installation required for Extension and
renovation of existing earthing system and lightning protection screen
including conductors, connections, connectors and clamps to suit the
substation overall arrangement and provide supporting design calculations.
2J Batteries, Chargers and DC Distribution
2J1 Replacement of existing two(2) sets 110V alkaline batteries and chargers bynew two(2) sets 110V Ni-Cad batteries complete with chargers.
The system shall generally be as shown in Bid Drawings and shall include the
following.
(a) Two(2) sets 100% Ni-cad batteries complete, each capacity shall not be
less than 400 Ah at the 5-hour rate of discharge.
(b) Two(2) sets battery chargers complete, each float charge shall not be
less than 75A rating.
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
5/13
SCHEDULE A
SA-17 (Rev.1)
2K LV AC Distribution
2K1 Deleted
2L Civil Works and Foundations
132kV Substation
2L1 One(1) lot complete design, supply and construction of all civil items required
for the extension and renovation of existing 132kV switchyard outdoor works,
including switchyard foundations, internal service roads, cable trenches,
surfacing, drainage, boundary fence.
2N Switchyard Lighting
One(1) lot complete design and calculations, supply, installation and
commissioning of equipment to provide lighting (sodium light) for security,
roadway and switchyard and emergency DC lighting at strategic locations forequipment operations and inspections.
2P Fibre Optic Multiplexer Equipment for Teleprotection and
Communication
2P1 Fibre Optic Multiplexer Equipment
Extensions of existing AREVA, France make DIP5000 type teleprotection
equipment and MSE 5010 type Fiber Optic Multiplexer Equipment equipment
2P2 One(1) lot of optical fibre (24 cores) cables from terminal box at 132kV gantry
structure to MDF (Main distribution Frame) to be installed in communicationroom. The Contract includes supply and installation of MDF and pigtail cables
with adequate length.
2P3 Shifting, re-installation, re-testing and re-commissioning of existing wave trap,
line matching unit (LMU), PLC equipment, cable etc required for existing
four(4) nos. overhead line circuits.
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
6/13
SA-20 (Rev.1)
3J1 220V DC sources are available at the existing substation. Necessary MCBs
are required to be installed under the contract for the new line bays.
3J2 48V DC sources are available at the existing substation. Necessary MCBs are
required to be installed under the contract for the new line bays.
3K LV AC Distribution
3K1 LV AC are available in the AC Distribution board. Necessary MCBs are
required to be installed under the contract for the new line bays.
3L Civil Works, Control Building and Foundations
230kV Substation
3L1 One (1) lot complete design, supply and construction of all civil items required
for the outdoor works, including switchyard foundations, access roads, internal
service roads, cable trenches, concrete culvert, surfacing, drainage etc..
3L2 Dismantling of approximately 70m boundary wall and re-construction of the
above boundary wall in the property line..
3N Switchyard Lighting
One (1) lot complete design and calculations, supply, installation and
commissioning of equipment to provide lighting for switchyard and
emergency DC lighting at strategic locations for equipment operations and
inspections for the new line bays.
3P Fibre Optic Multiplexer Equipment for Teleprotection and
Communication
3P1 Fibre Optic Multiplexer Equipment
Extensions of existing Fiber Optic Multiplexer Equipment to accommodate
two nos. overhead lines.
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
7/13
SA-26 (Rev.1)
Sl. No. Description Unit Requirement
16 Whether automatic control
required and referenced voltage
Yes, 110V,
50Hz
17 Whether separate remote control
panel required Yes
18 Estimated distance between remote control point and
transformer m See drawings
19 DC supply:
Nominal
Maximum float voltage,
V
V
110
125
20 Whether provision for supervisory control required,
including AVR setting
Yes
21 Whether marshalling kiosk
required
Tankside
Cubicle
22 Number of transformers for which automatic control
is to be suitable
2 (and
provision for
future 3rd)
23 TERMINATIONS
Bushing insulators or cable boxes
on line and neutral terminals:
i) HV line
ii) Neutral
iii) LV line
iv) Tertiary winding
Bushings
Bushings
Bushings
Bushings
24 BCT PARTICULARS
i) HV (235kV) Side:Core 1 & Core 2:
1600-800-
400/1A, 30VA,
5P20.
Core 3: Ratio, burden
and accuracy
class shall be
matched with
WTI meter.
ii) LV (132kV) Side:Core 1, Core 2 :
2000-1000-
500/1A, 30VA,
5P20.
Core 3: For WTI
Core 4: For tap changer
iii)Tertiary , Core 1 & 2 800/1A, 30VA,5P20
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
8/13
SCHEDULE A
SA-27 (Rev.1)
Sl. No. Description Unit Requirement
iv)Neutral Core 1: 2000-1000-500/1A, 30VA,
5P20
25 Accommodation on tank for
outdoor weatherproof HVneutral current transformers Yes
26 Pollution category of outdoor
bushing insulators
25 mm/kV
of system rated
(highest)
voltage
27 COOLING
Number of cooler banks required
per transformer
To suit
transformer
design28 Rating of each cooler bank as
percentage of total loss at CMR % % 50
29 Standby cooling requirement One fan in each
group
30
GENERAL
Type of oil preservation system Air Cell
31 Maximum acceptable noise level 78 dBA
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
9/13
Schedule B: Bid prices SB-30 (Rev.1)
CONTRACT NO. PGCB/FEN/SS/01
SCHEDULE B7
FOR GOODS AND SERVICES SUPPLIED FROM OUTSIDE EMPLOYERS CO
7.1 BREAKDOWN OF COSTS FOR CIVIL WORKS
New 230kV Substation and Extension
of 132kV Substation at Fenchuganj
and o 230 kV Substation at Comilla(N)
Foreign Currency (F/C) Price
Sl.No.
Description of Works Unit PriceFOB
TotalPrice FOB
Insurance Freight TotalPrice CIP
Erection Total F/CCost
Localtranspo
handling
1 Outdoor Foundations
2 Transformer Bases
3 Control Building:-
3.1 Foundations
3.2 Piling
3.3 Superstructure
3.4 Brickwork
3.5 Flooring/Roofing
3.6 Doors Windows etc.
3.7 Services and Finishes
4 Cable Trenches
5 Boundary Walls & Gates
6 Surfacing and Drains
7 Septic Tank and Water Supply
8 Guard House
9 Access Road
Sub Total Price carried forward
Sub Total Price in words.........................................................................................................................................
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
10/13
Schedule B: Bid prices SB-31 (Rev.1)
CONTRACT NO. PGCB/FEN/SS/01
SCHEDULE B7
FOR GOODS AND SERVICES SUPPLIED WITHIN EMPLOYERS COUNT
7.1 BREAKDOWN OF COSTS FOR CIVIL WORKS
New 230kV Substation and Extension
of 132kV Substation at Fenchuganj
and o 230 kV Substation at Comilla
(N)
Local Currency (L/C) Price
Bangladesh Taka :
Item Description of Works Unit Price
EXW
Total Price
EXW
transport &
handling
Erection Insurance Total price
1 Outdoor Foundations
2 Transformer Bases
3 Control Building:-
3.1 Foundations
3.2 Piling
3.3 Superstructure
3.4 Brickwork
3.5 Flooring/Roofing
3.6 Doors Windows etc.
3.7 Services and Finishes
4 Cable Trenches
5 Boundary Walls & Gates
6 Surfacing and Drains
7 Septic Tank and Water Supply
8 Guard House
9 Access Road
Sub Total Price carried forward
Sub Total Price in words.........................................................................................................................................
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
11/13
SA-40 (Rev.1)
APPENDIX A9
SCHEDULE OF TECHNICAL REQUIREMENTS
CONDUCTORS AND INSULATORS
No. Descriptions Unit Requirement
1. Busbar conductor for 245kV SwitchgearConductor Type TACSR
Designation 795MCM (Mallardequivalent)
Number of Conductor per phase 2
Number and Diameter of strands:
Al.
St.
Nos. x mm
Nos. x mm
-
Overall diameter mm -
Weight kg/m -
Guaranteed ultimate tensile strength kN -DC resistance at 20
oC Ohm/km -
2. Jack Bus & Jumper conductor for 245kVSwitchgear
Conductor Type ACSR
Designation Mallard
Number of Conductor per phase 2
Number and Diameter of strands:
Al.
St.
Nos. x mm
Nos. x mm
30/4.135
19/2.482
Overall diameter mm 28.95
Weight kg/m 1.839
Guaranteed ultimate tensile strength kN 170
DC resistance at 20oC Ohm/km 0.07186
3. Slack span, Jackbus & jumper conductorreplacement for 132kV Switchgear
Conductor Type ACSR
Designation Mallard
Number of Conductor per phase 2
Number and Diameter of strands:
Al.
St.
Nos. x mm
Nos. x mm
30/4.135
19/2.482
Overall diameter mm 28.95
Weight kg/m 1.839
Guaranteed ultimate tensile strength kN 170
DC resistance at 20oC Ohm/km 0.07186
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
12/13
Technical particulars & Guarantees SE-50
Sl.
No.Description Unit Bidders Data
Separate Bay controller unit provided for each bay & feeder
Type of bay controller offered HV/MV
Select Before Operate with Open Execute & Close Execute
Single bit dependence
Interlocking, bay & Station wide
Synchrocheck function:
- Maximum Voltage difference
- Maximum Frequency difference
- Maximum Phase difference
Double command blocking
Independent settable parameter groups
Local Display Unit
Sequence of event recorder:
- Events
- Time resolution
Disturbance recorder function
Comprehensive self-supervision
Battery free backup of events and disturbance records
Insulation tests
Fast disturbance tests
MTBF
MTTR
Temperature range: IEDs- Operation
- Transport and storage
Relative humidity:
- Operating max./min.
- Transport and storage
%
%
Back up control mimic -HV
Manufacturer
Name and type of product in suppliers catalogue
Origin of manufacturer
Control functionality:
Control of breaker as well as all isolators/earthing switch
(Control functionality should not be affected if bay controller fails)
Key-Locked
Interlock override function
12
Separate backup control mimic provided for each bay & feeder
13 Bay Control Unit - MV
8/6/2019 SOW & Addendum 1 VOl3OF3 Attachment Corr
13/13
Schedule I: Drawings
SI-2
(c) Short circuit test (special test) / Calculation.(ii) Circuit Breaker
(a)Lightning impulse voltage withstand dry test.(b)Power frequency voltage withstand dry test.(c)Out of phase switching test.(d)Short time withstand current test.
(iii) Disconnector(a)Lightning Impulse voltage withstand dry test.(b)Power frequency voltage withstand dry test.(c)Short time withstand current test.
(iv) Current Transformer(a)
Short time current test.(b)Impulse voltages withstand tests for current transformers for service inexposed installation.
(c)Power frequency voltage withstand test.(d)Temperature rise test.
(v) Voltage Transformer(a)Temperature rise test.(b)Impulse voltages withstand tests for voltage transformers for service in
exposed installation.
(c)Short circuit test(d)Short time over voltage test
(vi) Lightning arrester(a)Power frequency voltage withstand and lightning impulse voltage withstand
tests on complete arrester housing.
(b)Operating duty test.(c)Long duration current impulse withstand test.(d)Residual voltage test.(e)Pressure relief test.(f) Artificial pollution test.
(vii) Power Cable(a) Bending test followed by partial discharge test(b) Tan Delta measurement(c) Heating cycle voltage test(d) Impulse withstand test