Upload
dominh
View
216
Download
0
Embed Size (px)
Citation preview
Meeting with BMRCL/KPTCL held on 31st December 2015 Page 1
SOUTHERN REGIONAL POWER COMMITTEE BENGALURU
Record Notes of the Meeting to discuss disruption of power supply affecting
BMRCL services
A Meeting to discuss disruption of power supply affecting BMRCL services was
held on 31st December 2015 with participation from BMRCL, KAR SLDC, KPTCL,
SRLDC & SRPC. The list of the participants is at Annexure-I.
Shri S.R. Bhat, Member Secretary, SRPC welcomed the participants to the
Meeting. He stated that BMRCL services were affected on 21st December 2015 and on
17th December 2015 due to power supply issues. He quoted the media reports which
stated that the problem was reportedly not in the grid side. He expressed concern and
emphasized that the issue needs to be deliberated to ensure that the services of BMRCL
are not affected either due to grid side problem or due to electrical side problems in
BMRCL network.
Agenda was taken-up for discussion. BMRCL point-wise reply of the agenda
items is at Annexure-II.
Disruption of BMRCL services/failure of Grid supply
Following were the major interruptions in BMRCL services :
07th April, 2014 - 675 passengers refunded fare amount after power outage for an hour.
15th April, 2015 - 72 passengers evacuated after power outage in same stretch.
17th Dec, 2015 - Services hit for 11hrs on Yeshwantpur – Mantri square Sampige road stretch due to power failure.
21st Dec, 2015 - Disruption of services on the Metro’s Green Line from 1.03 pm to 1.53 pm between Yeshwantpur and Mantri Square Sampige Road stations.
The list of Grid power supply failures of reach-1 and Peenya RSS failure
details were furnished( in Annexure-II). It was confirmed that there was no
de-boarding of the passengers from train due to incoming KPTCL/BESCOM
supply.
Meeting with BMRCL/KPTCL held on 31st December 2015 Page 2
It was confirmed by BMRCL that the incidents of 17th and 21st December were
due to internal grid problem of BMRCL and the grid supply from
KPTCL/BESCOM was intact. The designer and M/s. ABB have been called to
carry out the root cause analysis and identify and implement the remedial
measures. Once the report is finalized, it would be shared with SRPC/SRLDC.
KPTCL suggested that relay setting also needed to be reviewed, tested and
verified during this exercise. BMRCL agreed to carry out the same and would
furnish compliance report.
It was noted that as per Scheme, only faulty section should have been cut off in
the BMRCL network and this issue also needed to be addressed by the
designer/ABB.
Provision of DG of suitable capacity to ensure that the Metro train reaches the Railway Station
In earlier meetings BMRCL had been suggested to consider provision of DG of
suitable capacity so as to ensure that the Metro train reaches the nearest
Station in line with the Enquiry Committee recommendations. BMRCL vide
letter dated 14th February 2014 (Annexure-III) had informed that there was
no provision to extend DG supply to Traction network. This was an
internationally accepted practice. However, provision for ventilation and
passenger evacuation was ensured.
In the meeting, Dy.CEE (U/S), BMRCL stated that they had again contacted
Delhi Metro and there was no provision/plan for DG for traction loads. For
traction power supply, the redundancy of power system, through multiple
number of Receiving Sub-Station (one in each corridor) has been ensured in
BMRCL.
SRPC/SRLDC stated that keeping in view with the regional grid condition,
recommendations of Enquiry Committee, natural calamities like TN Flood,
Hud Hud cyclone etc. BMRCL and other Metros of SR were being advised to go
for DG for traction loads. BMRCL representative’s were suggested to appraise
their Management about the necessity/requirement and suitable call needs to
be taken.
Meeting with BMRCL/KPTCL held on 31st December 2015 Page 3
Intermediate power source at Majestic
Dy.CEE (U/S), BMRCL informed that based on the power supply simulation
study for Metro System by expert agencies, the location of intake power supply
from KPTCL and the location of receiving Sub-Station (one in each corridor)
was decided and it is designed for reliable operations.
However, the inter-linking sub-station of BMRCL at Majestic would be ready
by March 2016. Power supply through cables from receiving station could be
extended to other receiving station through Majestic SS of one stretch.
BMRCL was requested to revert back on whether supply from any of the
receiving stations could be extended to any of the other receiving station.
SRLDC observed that whether charging of such long cables was possible due to
capacitive switching. BMRCL agreed to revert back on this.
Two independent sources of power at BMRCL Receiving Stations
The diagram of infeed of BMRCL Receiving Stations furnished by BMRCL is
available in Annexure-II.
The power supply from Metro diagram furnished by SRLDC is at Annexure-
IV.
KPTCL informed that all the stations were having alternate supply (except 66
kV Welcast) to BMRCL at 66 kV and 220 kV levels. The supply could be
switched to alternate supply in less than 500 msec. Besides the alternate
supply, they were having redundant supply which could be made available in
around 5 minutes. This was being tested periodically and suitable instructions
have been communicated to the sub-stations.
KPTCL informed that few days back, Yelahanka 220 kV SS (two 220 kV buses
and 2 x 150 MVA transformers) have been energized and were idle
charged.220 kV Neelmangla - Hoody line had been LILOed at Yelahanka. The
station was under testing and it could be loaded shortly. Welcast SS was
planned to be connected to Yelahanka SS. Later this station was planned to be
connected to 400 /220 kV SS of PGCIL.
Mock Black start exercises
Meeting with BMRCL/KPTCL held on 31st December 2015 Page 4
Since the problem was in BMRCL network it was recommended that a mock
exercise of extending the supply from Main/Alternate/Redundant to different
TSS of BMRCL and further down- stream (DC system) would be carried out on
21st January 2016.
The exercise could be taken up during the time when Metro services are not
available in co-ordination with SLDC, BESCOM & KPTCL SS. Compliance
Report in this regard would be furnished to SRPC/SRLDC by BMRCL/SLDC.
It was agreed that mock exercise would be held in each quarter and report
would be furnished by BMRCL/SLDC to SRPC/SRLDC.
Other issues
BMRCL informed that Mr. G. Mani, DGM (Traction) was the new Nodal
Officer. BMRCL was requested to communicate the details like address, phone
number, mobile number, fax number, e-mail id etc of the Nodal Officer to
SLDC/SRLDC/SRPC.
BMRCL was requested to furnish the details of second in command.
SLDC & BMRCL confirmed that the hot line was working and healthiness was
being ensured.
Member Secretary, SRPC thanked the participants for their valued contribution
and requested BMRCL & KPTCL to address the issues at the earliest.
-----------------------------------------