6

Southern Regional Power Committee - Govt of India, Ministry of … · 2020. 5. 19. · PGCIL (SR-1) had given the following Agenda items for discussion in PCSC-90: ... Substation

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Additional Agenda for the 90th Meeting of PCSC scheduled to be held on 27th May, 2020 (through VC/Online) Page 1

    Southern Regional Power Committee Bengaluru

    Additional Agenda for the 90th Meeting of Protection Coordination

    Sub-Committee of SRPC to be held on 27th May, 2020 through VC/Online

    1. Grid Disturbance

    Sl.N

    o

    Details of Event Date &

    Time

    Reason Remarks Category

    1 Complete Outage

    of 220kV

    Shimoga Station

    of KPTCL

    19-03-2020

    at 17:08 Hr.

    During antecedent conditions,

    all the elements were

    connected to Bus-1 North bus

    at 220kV Shimoga SS.

    Triggering incident was R –N

    fault in 220 kV Shimoga-

    Varahi line-2 due to insulator

    decapping. At the same time,

    220 kV Bus-1 BBP

    maloperated at 220kV Shimoga

    SS. Since all the elements were

    connected to Bus-1, this

    resulted in the complete loss of

    supply at 220kV Shimoga SS

    160 MW GD-1

    PGCIL (SR-1) had given the following Agenda items for discussion in PCSC-90:

    2. Resonance problem in over compensated 765kV & 400kV lines

    Problem of resonance during tripping of 400kV NPKunta - Hindupur line-2 was observed at

    18:14 Hr. on 09-06-2019. R-phase to earth fault occurred in line & line tripped due to

    operation of over-voltage stg-2. Voltage swell was observed in DR (Rph to earth voltage-

    462kV and DR, EL attached) and this tripping was also discussed in 85th PCSC.

    PGCIL referred the issue was to their CC/AM & CC/Engg and they have opined that

    resonance in the 400kV NP Kunta – Hindupur Lines during Single Phase Earth Faults may be

    due to Line Reactor at Hindupur end and advised to extend trip signal to Switchable Line

    Reactors for Single Phase E/Fs.

    In view of above, PGCIL proposes to extend trip signal to Switchable Line Reactors in 400kV

    NP Kunta – Hindupur – 1 & 2 lines at Hindupur end after study by SRPC/SRLDC. For other

    Line Reactors extending trip signal shall be decided on SOS.

    The issue may be discussed is meeting

    3. Implementation of A/R of 220kV Lines through under voltage interlock with 0.85

    PU pickup at Warangal and NP Kunta Substations

  • Additional Agenda for the 90th Meeting of PCSC scheduled to be held on 27th May, 2020 (through VC/Online) Page 2

    DGA gases in 315 MVA Warangal ICT-1 is observed to be increasing due to frequent faults in 220kV Lines. To avoid further stress on ICTs and Circuit Breakers, PGCIL (SR-1) is proposing to implement A/R reclose at POWERGRID end only after successful A/R at SEB end. A/R scheme shall be implemented using under voltage interlock with 0.85 PU setting.

    The issue may be discussed in meeting for concurrence.

    4. Frequent Failure of PLCC Link of 400kV Warangal – Bhoopalapalli – 1 and 220kV

    Warangal – Nagaram D/C

    The PLCC link of 400kV Warangal – Bhoopalapalli – 1 and 220kV Warangal – Nagaram D/C is frequently failing. This may cause delayed clearance of line faults, if any. To avoid delayed clearance of line faults during PLCC failures, PGCIL (SR-1) is proposing to reduce Zone- 2 timer to 200 msec. The issue may be discussed is meeting for concurrence.

    5. Providing additional O/C Protection in Bus Sectionaliser at 400kV Nellore

    Substation

    At 400 kV Nellore Substation, 400 kV Bus is connected to 400 kV Bus of Nellore-AP station through Bus-Sectionaliser. In case of any un-cleared fault in SEB portion, all the feeders connected to 400 kV Nellore shall be isolated on operation of Remote end Zone-2 protections. To avoid black-out of station for un-cleared faults in other section, PGCIL (SR-1) proposes to provide additional O/C protection in Bus-Sectionaliser. The issue may be discussed is meeting for concurrence.

    6. Providing additional Backup Impedance Protection for ICTs

    At present back-up protection of Transformers is being provided by installing Directional over Current and Earth-fault protection. This back-up protection is being coordinated with the downstream and upstream lines distance protection zones. The co-ordination of overcurrent protection requires exact information of the station fault level and the in-feed values. In the evolving Indian Power system, with the addition of new generation and transmission, these values vary with time. Further complications arise in cases where several parallel transformers are connected at a substation and zone-3 reach of line encroaching beyond transformer into the next lower voltage level. In view of constraints being observed in co-ordination of overcurrent relays, POWERGRID is installing Impedance Relays for back-up protection of 400/220kV ICTs on HV side and for 765/400kV ICTs on both HV & IV sides. The CBIP manual of protection system mentions that under impedance relays can be used as back-up protection for the transformer. It shall consist of multi-zone impedance relay on the HV side or on LV side of the transformer looking into transformer. In the CEA technical standard also for connectivity to Grid Part-III, Sec-4, Para-2 d, it has been mentioned that the back-up protection to transformer could be provided through either back-up overcurrent relay or impedance relay.

  • Additional Agenda for the 90th Meeting of PCSC scheduled to be held on 27th May, 2020 (through VC/Online) Page 3

    In view of above, as deliberated in 88th and 89th PCSC Meetings, PGCIL have procured Impedance relays (for HV back-up protection of 400/220kV ICTs and for 765/400kV ICTs on both HV & IV sides) for commissioning in ICTs in addition to existing back-up overcurrent & earth fault protections from O&M budget of POWERGRID. As additional Back-up impedance protections is being provided for ICTs for system improvement, PGCIL requests to consider the outage of ICTs taken/being availed for retrofitting as deemed available. The issue may be discussed is meeting. **************************************************************************