Upload
jason-cook
View
226
Download
0
Tags:
Embed Size (px)
Citation preview
SOUTH FORK IMPROVEMENTS PROGRAM – A MID-PROGRAM REPORT
Kent A. Lackey, P.E. – Black & Veatch Project Manager
NC AWWA-WEA 95TH ANNUAL CONFERENCE
AGENDA
• BACKGROUND• PROGRAM OVERVIEW• PROGRAM STATUS• EARLY SUCCESSES
2
• Winston-Salem/Forsyth County Utility Commission• Approximately 122,000 customers (3rd largest in NC)• 2 WWTPS
• Muddy Creek • 21 mgd capacity
• Archie Elledge• 30 mgd capacity
• Three Drainage Basins• South Fork• Muddy Creek• Elledge
• 49 WW Lift Stations• 1,723 miles of sewer
BACKGROUND – WASTEWATER SYSTEM
3
Archie Elledge WWTP
Muddy Creek WWTP
• introductions
BACKGROUND – LONG TERM WASTEWATER TREATMENT ANALYSIS
4
Archie Elledge WWTP
Muddy Creek WWTP
Muddy Creek Basin
South Fork Basin
Elledge Basin
South Fork PSNew MC
Transfer PS
• Where is it being generated?
• Convey all flows to plants using existing infrastructure
• Transfer flows between plants
• Transfer flows between basins
• System Equalization• Scalping within the
collection system• Future New Plant
Future Plant Option 1
Future Plant Option 1
5
• Program Owner : CCUC• Utilities Administration• Wastewater Treatment• Collection & Maintenance• Finance• City Attorney
• Program Manager: Black & Veatch• Program Management• MCCIPS and Force Main Design• Optimization Study/Design• Funding Assistance• Regulatory Permitting
• Program Consultants:• Hazen and Sawyer: Interceptor
Design/EA• Highfill Infrastructure: Kerner’s Mill
Design• Southeastern Electrical Consultants:
Kerner’s Mill PS Design• Carolina Ecosystems: Environmental
Field Support• Hydromax USA: Pipeline Inspection• Allied Associates: Surveying• Sanborn: Aerial Topography• S&ME: Geotechnical• Clemson Engineering Hydraulics:
Physical Modeling
SOUTH FORK IMPROVEMENTS PROGRAMPROGRAM PARTNERS
SOUTH FORK IMPROVEMENTS PROGRAMOVERVIEW
6
South Fork InterceptorsDesign Lead: Hazen and Sawyer
Kerner’s Mill PS and Force MainDesign Lead: Highfill
MCCIPS and Force MainAEWWTP Equalization FacilitiesAEWWTP Aeration Upgrades(New)MCWWTP Power Generation Upgrades(New)Design Lead: Black & Veatch
Linville Springs & Wexford PSDesign Lead: CCUC
SSES ProjectsDesign Lead: Several
• Study Completed in 2013-2014• Aeration/DO Evaluation• Gas Utilization Evaluation• Sidestream Treatment Evaluation for
N and P• Chlorine Control• Performance Management System
• Energy Management Via Ammonia Control
• Interplant Pumping Control System
• Result: AEWWTP Aeration Upgrade and Power Generation Projects Initiated
GENERAL PROGRAM STATUSPROJECT UPDATE – OPTIMIZATION STUDY
7
• Additional Program Projects• Process and Energy Optimization Study for AEWWTP and MCWWTP • Program Funding
• Program Funding Application and Administration for State Revolving Fund Loan
• Federal Funding Screening and Application for all 2014 CIP projects
• Other Projects Added to the Program• AEWWTP Equalization Facilities• AEWWTP Aeration Improvements• MCWWTP Power Generation Upgrades• MCWWTP Blower Upgrades Funding
SOUTH FORK PROGRAM PROJECTS
Program is currently approximately $8M under budget
• Current Anticipated Program Construction Cost: $98,320,000
• MCWWTP CIPI: $51,060,000• MCWWTP Transfer Force Main: $4,850,000• AEWWTP Day Tanks: $9,000,000• AEWWTP Aeration System: $4,700,000• South Fork Interceptor Contract 1: $12,550,000• South Fork Interceptor Contract 2: $5,360,000 (estimated)• Kerner’s Mill Force Main: $3,200,000 (estimated)• Kerner’s Mill Pump Station Upgrade: $1,600,000 (estimated)
• MCWWTP Power Generation: $6,000,000 (estimated)
PROGRAM FINANCIAL UPDATEPROGRAM BUDGET - CONSTRUCTION
9
• SRF CS370399-08• $70,500,000 Loan Granted (2% rate) • Funds MCCIPS, Force Main, AEWWTP Equalization
• SRF CS370399-09• $9,399,200 Loan Granted (2% rate)• Funds SSES Projects: Peters Creek, 21st Street, Ardmore Basin No. 1
• SRF CS370399-10• $1,079,400 Loan Granted (0% rate)• Funds AEWWTP Aeration System Upgrade
• SRF CS370399-11• $6,003,772 Loan Granted (0% rate)• Funds MCWWTP Power Generation Facilities
• Future Application• MCWWTP Blower Replacement• South Fork Interceptors
GENERAL FINANCIAL UPDATEPROGRAM FUNDING
10
• Red text indicates projects currently in construction
PROGRAM SCHEDULE UPDATE
11
Project Design Completion
Construction Start
Final Completion
MCCIPS Complete 1/28/15 5/31/17MCCIPS Force Main Complete 6/15/15 8/16/16AEWWTP Equalization System Complete 6/25/15 11/17/16AEWWTP Aeration Upgrades Complete 9/1/15 5/27/16MCWWTP Power Generation 10/31/15 2/2016 2/2017Kerner’s Mill Force Main Complete 1/2016 8/2016Kerner’s Mill Pump Station Upgrade Complete 2/2017 2/2018
South Fork Interceptor Contract 1 Complete 7/15/15 12/16/16South Fork Interceptor Contract 2 Complete 11/2015 11/2016
• Muddy Creek WWTP Consolidated Influent Pumping Station
• 82 mgd Influent PS• Expandable to 138 mgd
• Screening/Grit Removal• 9.5 mgd Transfer PS & 30” Force Main
• Expandable to 30 mgd• Odor Control• 2 - 1 MG Day Tanks• 2 – 3.9 MG Storm EQ Basins• Electrical Switchgear Replacement• NPW Pump Replacement• Demolition of Exist Primary Treatment
and Influent PS• Ferric Chloride Storage/Feed
GENERAL PROGRAM STATUSPROJECT UPDATE - MCCIPS
12
GENERAL PROGRAM STATUSPROJECT UPDATE - MCCIPS
13
• Elledge WWTP Equalization• Objective:
• Combine AEWWTP and MCWWTP Flows and Equalize Diurnal Variation
• 2 – 2.0 MG Day Tanks w/ Vertical Mixers• Rate Control Structure
• Elledge Aeration Upgrades• Objective:
• Segment Aeration Basins into 4 independent DO Control Zones
• Results:• Reduce air requirements by 7,300 scfm• Approximate Power Savings:
$186,000/yr • Approximate 3-4 yr payback
GENERAL PROGRAM STATUSPROJECT UPDATE – AEWWTP
14
• MCWWTP Power Generation• 1 - 1.1 MW Dual Fuel Engine
Generator• Self Enclosed Outdoor Unit• 800kW Capacity on Digester Gas• 1.1 MW Emergency Capacity on
Natural Gas• Power Supplied to Grid
• Digester Gas• Cleaning: particulates, moisture,
H2S• Compressor via Blowers
• Waste Heat• Hot Water for Digester Heating
• Approximately 8 yr payback
GENERAL PROGRAM STATUS PROJECT UPDATE – MCWWTP POWER GENERATION
15
• Contract 1• 23,900 LF of 54” pipe• Pipe Material: FRP with
DIP at road crossings
• Contract 2• 8,860 LF of 15-42” pipe• Pipe Material: FRP (42”),
DIP (42”), Clay (15”/18”)
GENERAL PROGRAM STATUSPROJECT UPDATE – INTERCEPTORS
16
• Pumping System Final Capacity Refined at 30% Design • Reduced due to Muddy Creek Basin Master Plan and
South Fork Basin Refinement
• Reduce PS Cost and Deferred Initial Equipment (Approx. $1M)
• No Impact to Aggressive Schedule for South Fork Basin Improvements
SOUTH FORK PROGRAM EARLY SUCCESSES
17
Basin5 yr Storm Peak Flow (mgd)
Initial 2041 Flows Final 2041 Flows
Muddy Creek Basin 110(Assume 3.4 PF) 92.9
South Fork Basin 40 35.6
Davidson County 1.5 10.0
Total 171 138.5
Program Manager was Able to Make Effective, Ongoing Decisions Based on Collective Information
• Two significant Program Interceptor Projects were Deferred ($11M)• South Fork Basin MP Re-calibration Efforts
Completed and Assessed Before Detailed Design Commenced• Reduced Program Construction and Engineering Cost• No Impact to Aggressive Schedule for South
Fork Basin Improvements
SOUTH FORK PROGRAM EARLY SUCCESSES
18
Projects Deferred
CONSOLIDATED INDUSTRIAL ALLOCATION TRACKING
19
Muddy Creek WWTP
Archie Elledge WWTP
19
Transfer Force Main
SOUTH FORK PROGRAM EARLY SUCCESSES
20
• The Program Team is Driving Effective and Open Collaboration• Multiple Projects
• MCWWTP Clarifier Improvements Project• Collection System Master Plan Project• South Fork Program
• Multiple Engineering Firms Provide Collective Decision Making• Winston-Salem• Black & Veatch• Hazen & Sawyer• Highfill Infrastructure Engineering
• Winston-Salem is Benefiting from Collective Expertise and Effective Collaboration
SOUTH FORK PROGRAM EARLY SUCCESSES
21
• Benefiting from Effective Collaboration• Exchanged Scope Between MCWWTP Clarifier Improvements Project
and Program Project• Deferred Sitework to Program; • Moved Clarifier Splitter Structure to Clarifier Project
• Evaluating and Coordinating Project Sequencing• Interceptor Designers Considered “Replace in-place” concept to
avoid considerable rock removal along alignment• Program Manager Evaluated Interceptor Sections and Impact
on MCWWTP Flows• Evaluated Early Milestones in PS Project to Incorporate Higher
Influent Flows to Allow full “replace in-place” Without Delay to Program Completion
SOUTH FORK PROGRAM EARLY SUCCESSES
22
• Significant Benefits in Bidding and Construction• Significant Contractor interest including in some cases 15 bidders for
a project.• Consolidated and coordinated construction administration efforts• Consolidated database for construction documents and records to
keep things organized for CCUC
CONCLUSIONS
23
• Unique Program Management Approach Has Created Value for CCUC• Allows for Expediting Relief of South Fork Basin While
Concurrent Projects are Completed• Allowed to Initiate Projects without “Final” design criteria in
order to Expedite Completion• Consolidated “like” Efforts Increasing Efficiency and Reducing
Cost• Greatly Reduced CCUC Staff Requirements for a Complex set of
Projects• Single Point of Responsibility with a High Level of Collaboration
Between Team Members – Increasing Quality and Value.
www.bv.com