36
SOLERA OAKMONT CLUBHOUSE REMODEL FINAL PROJECT UPDATE MARCH 9 - 10,2020

SOLERA OAKMONT CLUBHOUSE REMODEL FINAL PROJECT … · 2020. 3. 11. · • Office Furniture (allowance) $ 25,576 $ 25,576 • Modular Unit $ 24,000 $ 13,167 • Operable Partitions

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • SOLERA OAKMONT

    CLUBHOUSE REMODEL

    FINAL PROJECT UPDATE

    MARCH 9-10,2020

  • INTRODUCTIONS

    • Board of Directors:

    ▪ Gary Stoh, President

    ▪ Elaine Morgan, Vice President

    ▪ Greg DiGiovanni, Treasurer

    ▪ Pat King, Secretary

    ▪ Marcia Beyer-Casem

    • Keystone Pacific:

    ▪ Susan Larson, General Manager

    • Formillus Architecture:

    ▪ Michael Bern (Not present)

    • Clifford & Cruz Inc (CCI):

    ▪ Joe Winkler (Not present)

  • PRESENTATION OBJECTIVE

    PROVIDE MEMBERS:

    • A final update of the Oakmont Clubhouse Remodel Project from May 2019 to present

    • The revised contracted cost of the Project

    • Funding information for the Project:• Funding from the Reserve Account• Funding from the Capital Improvement Fund

    Account

    • Project schedule

    • Additional Clubhouse Planned Updates

    • Answers to Members Questions

  • CLUBHOUSE

    REMODEL PROJECTStatus from May 2019 to March 2020

  • CLUBHOUSE REMODEL PROJECT STATUS

    June 2019

    Vote held to approve Capital Improvement Funding for Clubhouse Remodel Proect

    July 2019

    Board decision to put remodel on hold and revise Office expansion plan

    Aug-Dec 2019

    Board and Formulus developed a new Office plan staying within the existing Clubhouse walls

    Dec 2019

    Revised Office/Oakmont Room plans submitted to the City for approval

    Jan-Mar 2020

    Revised Office/Oakmont Room plan approval received from the City in JanuraryRevised bid and schedule received from CCI received in FebruaryConstruction start March 16, 2020

  • FINAL CLUBHOUSE REMODEL FEATURES

  • FINAL

    OAKMONT

    ROOM

    REMODEL

    FEATURES

    ▪ A solid LVT floor will be installed throughout all three rooms

    ▪ New Audio system with in-ceiling and wall-mounted speakers. State-of-the art control system

    ▪ Two new ceiling-mounted projectors will be installed

    ▪ Two new drop-down projector screens. Replace existing screen plus one will be located in the angled ceiling soffit in Oakmont 3

    ▪ New Airwalls (Movable Partitions)▪ Revised ceiling to provide updated look▪ New window shades▪ Elimination of drapes▪ New LED ceiling-mounted light fixtures▪ New cabinets with solid-surface countertops▪ Stone veneer installed in the alcove walls▪ New paint scheme to provide updated look

  • FINAL CLUBHOUSE

    REMODEL FEATURES

  • FINAL CLUBHOUSE

    REMODEL FEATURES

  • FINAL OFFICE

    REMODEL

    FEATURES

    ▪ Expansion of the office space within the existing Clubhouse exterior walls has been accomplished by removing two of the three showers in the Men’s Locker room.

    ▪ A new ADA-compliant shower with modern tile and fixtures replaces the remaining shower

    ▪ A new glass panel wall and door separates the Reception area from the Billiards area for noise abatement and privacy

    ▪ A reconfigured Reception area will provide for Member comfort

    ▪ Three offices accommodate the General Manager, Assistant GM and Recreation Director and provides privacy for Members when meeting with the GM or staff

    ▪ There is room for a small conference table in the GM’s office for most Board Executive Sessions thereby eliminating the need to use the Arts and Crafts room

    ▪ An open area has been configured for staff, storage, and photo IDs

    ▪ New Cabinets and countertops. Existing furniture will be utilized where possible

    ▪ LED lighting

  • RE-CONFIGURED

    OFFICE FLOOR PLAN

  • FINAL OFFICE

    REMODEL

    FEATURES

  • ADA

    COMPLIANT

    SHOWER(Concept)

  • REVISED PROJECT

    COST

  • REVISED PROJECT COST

    PROJECT COST COMPARISON MAY 2019 FEB 2020

    • Building Costs $395,284 $321,829• General Conditions & Supervision $ 97,290 $ 99,730• Insurance Liability (5%) $ 5,433 $ 5,800• General Contractors OHP (9%) $ 52,904 $ 48.910• Testing and Inspections $ 5,278 $ 1,556• HAVC $ 25,870 $ 61,750• Roofing (Contingency) $ 15,821• Audio/Visual System $ 40,850 $ 57,727• Office Furniture (allowance) $ 25,576 $ 25,576• Modular Unit $ 24,000 $ 13,167• Operable Partitions $ 19,470 $ 36,483 • Contingency $ 18,000 $ 18,000

    TOTAL COST $709,955 $706,349

  • REVISED PROJECTCOST

    OFFICE RECONFIGURATION CONSTRUCTION COST SAVINGS

    • Building Costs $108,722

    • General Conditions & Supervision $ 6,250

    • General Contractors OHP (9%) $ 3,994

    • Testing and Inspections $ 3,722

    TOTAL COST SAVINGS $ 122,688

  • REVISED PROJECT COST

    COST INCREASE/DECREASE ( EXCLUDES SAVINGS FROM OFFICE RECONFIGURATION)

    • Demolition $ 6.335• Acoustic Ceilng $ 3,000• Flooring and Carpet $ 8,258• Painting $ 1,470• HAVC $ 35,880• Fire Alarm $ 15,973• Fire Extinguishers $ - 470• Window Treatment $ 701• Audio/Visual $ 16,877• Operable Partitions $ 17,013• Temp Utilities and Dumpsters $ 2.600• Travel and Temp Facilities $ - 410• Supplies and Misc $ 6,500• Liability Insurance $ 367• Roofing (contingency) $ 15,821• Modular Unit $ -10,833

    COST INCREASE/DECREASE$119,082

  • REVISED PROJECT COST

    REVISED FEB 2020 BID COST DIFFERENCE FROM MAY 2019 BID – SUMMARY

    INCREASE/DECREASE (EXCLUDES SAVINGS

    FROM OFFICE RECONFIGURATION) $119,082

    SAVINGS FROM OFFICE RECONFIGURATION ($122,688)

    COST DIFFERENCE -$ 3,606

  • REVISED

    PROJECT

    COST

    WHILE THE COST DIFFERENCE BETWEEN THE MAY 2019 AND FEB 2020 BID FROM CCI ONLY SHOWS A SAVINGS OF $3,606 THE REASONS FOR THIS ARE:

    • MOST OF THE COST THAT WAS ASSOCIATED WITH THE OFFICE EXPANSION HAS NOW BEEN RE-DIRECTED TO ENHANCE THE OAKMONT ROOMS

    – TOTAL REDESIGN OF THE CEILING CONFIGURATION

    – UPGRADED LVT FLOORING

    – UPGRADED AUDIO/VIDEO SYSTEM

    – STONE VENEER IN THE ALCOVES

    – REPLACEMENT OF FOUR A/C UNITS AND REVISED DISTRIBUTION

    – UPGRADED CEILING LIGHTING FIXTURES

    • LABOR AND MATERIAL COSTS HAVE ALSO INCREASED SINCE MAY 2019 AND ARE NOW REFLECTED IN THE REVISED BID

  • PROJECT COST

    APPROXIMATE IMPACT OF THE REVISED BID ON THE OAKMONT ROOM AND OFFICE COSTS

    OAKMONT OFFICEROOM

    MAY 2019 COST WITHOUTCONCURRENT BUILDINGCOST SAVINGS OF ($82,366 )$282,827 $509,761

    FEB 2020 OFFICE COST SAVINGS ($122,757)

    FEB 2020 OAKMONT ROOMENHANCEMENT $119,082 ________

    APROXIMATE RESULTANT COST $401,909 $387,004

    THE COST OF THE OAKMONT ROOM UPDATE IS NOW SIGHTLY HIGHER THAN THE OFFICE EXPANSION

  • REVISED

    PROJECT

    COST

    RE-CONFIGURATION OF THE OFFICE AREA AND ELIMINATION OF EXPANSION BEYOND THE EXISTING CLUBHOUSE EXTERIOR WALLS PROVIDES THE FOLLOWING BENEFITS:

    • SIGNIFICANT REDUCTION IN BUILDING COST• INCREASED USE OF FUNDS FROM THE RESERVE ACCOUNT

    TO OFFSET THE COST OF THE OFFICE RE-CONFIGURATION• ENCLOSED RECEPTION AREA PROVIDES MEMBER PRIVACY

    AND ELIMINATION OF NOISE FROM THE BILLIARDS AREA• IMPROVED WORKING AREAS FOR THE ADMINISTRATION

    STAFF• MEMBER PRIVACY WHEN MEETING WITH ADMINSTRATION

    STAFF• A CONFERENCE TABLE IN THE GENERAL MANAGERS OFFICE

    TO ENABLE TO BOARD TO HOLD MOST EXECUTIVE SESSIONS AND FREE UP OTHER CLUBHOUSE FACILITIES

  • PROJECT FUNDING

  • PROJECT FUNDING

    THE PROJECT WILL BE FUNDED FROM THE CAPITAL IMPROVEMENT FUND AND RESERVE ACCOUNT

  • PROJECT

    FUNDING

    THE ASSOCIATION’S ANNUAL BUDGETED GROSS EXPENSES ARE COMPRISED OF 3 SEPARATE COST ACCOUNT ELEMENTS:

    • Operating Budget (Management, Guard Services, Landscape, etc.)

    • Reserve Account (Identified replacement items such as flooring, furniture, draperies, lighting, etc.)

    • Capital Improvement Fund (New Projects)

  • REVISED PROJECT FUNDING FROMRESERVE ACCOUNT

    May 2019 Feb 2020

    • Flooring $14,385 $20,806• Acoustic Ceiling $18,144 $21,400• Cabinets & Countertops $21,080 $14,050• Window Treatments $ 4.557 $ 5,258• Operable Partitions $19,470 $36,483• Audio System $21,500 $32,000• Drywall and Framing $23,273 $27,670• Fire Sprinklers $ 7,250 $24,973• Fire Alarm $ 470 $ 470• Repaint $ 5,350 $10,170• HAVC $18,630 $61,750• Electrical $88,375 $95,400• Office Furniture $10,900 $10,900• Doors/Frames/Hardware $21,725 $10,150• Shower Remodel $26,774

    TOTAL RESERVE FUNDING $275,109 $398,254

    (NOTE: THE RESERVE ACCOUNT IS CURRENTLY FUNDED AT $3.436 MILLION)

  • REVISED PROJECT FUNDING

    SUMMARY

    MAY 2019 FEB 2020

    TOTAL PROJECT COST $709,955 $706,349

    FUNDING FROM RESERVES ($275,109) ($398,254)

    FUNDING FROM CAPITALIMPROVEMENT FUND

    NEEDED FOR PROJECT $434,846 $308,095

    APPROVAL TO SPEND UP TO $500,000 IN CAPITAL IMPROVEMENT FUNDS OBTAINED IN JUNE 2019$191,905 IS STILL AVAILABLE FOR ADDITIONAL CAPITAL PROJECTS (NOTE: THE CURRENT CAPITAL FUND IS CURRENTLY FUNDED AT $716,000)

  • PROJECT

    SCHEDULE

  • CLUBHOUSE REMODEL SCHEDULE

    March 09-16

    Clubhouse Closed (3/9)Presentations to Members (3/9/3/10)Relocate Office (3/9-3/15)Module Unit Open (3/12)

    March 16

    Start Construction (3/16)Office Reopens (3/16)

    March 19 – May 29

    Demolition 3/19-3/26Construction

    May 29-June 10

    Completion of ConstructionClean UpFinal InspectionCertificate of Occupancy

    June 12

    Grand Reopening of Clubhouse

  • PROJECTSCHEDULE

    • DURING CONSTRUCTION CCI RECOMMENDED TO THE BOARD THAT THE CLUBHOUSE BE CLOSED FOR SAFETY AND TO EXPEDITE COMPLETION OF CONSTRUCTION

    • THE ADMINISTRATION OFFICE WILL BE RELOCATED TO THE ARTS AND CRAFTS ROOM . PLEASE MAKE APPOINTMENTS WITH THE MANAGEMENT STAFF DURING THE CONSTRUCTION PERIOD EITHER VIA EMAIL OR PHONE

    • THE FITNESS CENTER WILL REMAIN OPEN. HOWEVER, THE HOURS WILL BE ADJUSTED TO:

    – Mon-Fri 5:00 am to 7:00 pm– Sat-Sun 7:00 am to 7:00 pm

    • A MODULAR UNIT WILL BE PLACED IN THE CLUBHOUSE PARKING LOT TO ALLOW FOR LIMITED CLUB AND GROUP EVENTS

  • SUMMARY

  • SUMMARY

    • THE BOARD , IN RESPONSE TO MEMBER INPUT IN JULY 2019 PUT THE CLUBHOUSE REMODEL PROJECT ON HOLD IN ORDER TO DEVELOP A MORE COST-EFFECTIVE PLAN FOR THE ADMINISTRATIVE OFFICE EXPANSION

    • REVISED OFFICE PLAN DEVELOPED BETWEEN AUGUST AND DECEMBER 2019

    • REVISED OFFICE AND OAKMONT ROOM PLAN APPROVAL WAS RECEIVED FROM THE CITY IN JANUARY 2020

    • CCI SUBMITTED A REVISED BID AND CONSTRUCTION SCHEDULE IN FEBRUARY 2020

    • $308,095 IS REQUIRED FROM THE CURRENT CAPITAL IMPROVEMENT FUND TO ACCOMPLISH THE CLUBHOUSE REMODEL PROJECT VS. $434,846 IN MAY 2019, A COST SAVINGS OF $126,751

    • A BALANCE OF APPROXIMATELY $192,000 WILL STILL BE AVAILABLE IN THE CAPITAL IMPROVEMENT FUND FOR FISCAL YEAR 2020-2021 WITH AN ADDITIONAL CONTRIBUTION OF $75,000 EACH FISCAL YEAR FOR FUTURE PROJECTS

  • ADDITIONAL PLANNED

    CLUBHOUSE UPGRADES

  • ADDITIONAL CLUBHOUSE UPDATES

    • THE BOARD IS WORKING WITH CCI TO UPDATE OTHER AREAS OF THE OAKMONT CLUBHOUSE WHILE CONSTRUCTION IS ONGOING

    • CCI IS CURRENTLY DEVELOPING THE COST FOR THE ADDITIONAL WORK

    • THIS ADDITIONAL WORK WILL BE FUNDED FROM THE RESERVE ACCOUNT.

    • THE UPDATES ARE:

    • REPLACE THE CARPET IN THE BILLIARDS AREA, MAIN LOBBY, AND LIBRARY WITH THE SAME UPGRADED CARPET AS THE OFFICE

    • REPAINT THE ABOVE AREAS AND HALLWAYS TO MATCH THE NEW COLORS IN THE OAKMONT ROOMS AND OFFICE

    • UPDATE THE CLUBHOUSE LIGHTING WITH NEW FIXTURES AND LED LIGHTING TO SAVE ENERGY COST

    • REFURBISH THE MAIL ROOM LOBBY WITH NEW LVT FLOORING, WALL TREATMENT, AND LED LIGHTING. A NEW FOLDING ELECTRIC-OPERATED DOOR WILL ALSO BE INSTALLED IF STRUCTURALLY FEASIBLE

  • FOLDING ELECTRIC

    ENTRY DOOR

    (Concept)

  • YOUR BOARD OF DIRECTORS APPRECIATES YOU

    TAKING TIME TO COME TO THIS PRESENTATION

    AND ARE EXCITED ABOUT THE FIRST MAJOR

    UPDATE TO OUR BEAUTIFUL CLUBHOUSE SINCE

    IT WAS BUILT IN 2005

  • Q & A’S