SOLERA OAKMONT
CLUBHOUSE REMODEL
FINAL PROJECT UPDATE
MARCH 9-10,2020
INTRODUCTIONS
• Board of Directors:
▪ Gary Stoh, President
▪ Elaine Morgan, Vice President
▪ Greg DiGiovanni, Treasurer
▪ Pat King, Secretary
▪ Marcia Beyer-Casem
• Keystone Pacific:
▪ Susan Larson, General Manager
• Formillus Architecture:
▪ Michael Bern (Not present)
• Clifford & Cruz Inc (CCI):
▪ Joe Winkler (Not present)
PRESENTATION OBJECTIVE
PROVIDE MEMBERS:
• A final update of the Oakmont Clubhouse Remodel Project from May 2019 to present
• The revised contracted cost of the Project
• Funding information for the Project:• Funding from the Reserve Account• Funding from the Capital Improvement Fund
Account
• Project schedule
• Additional Clubhouse Planned Updates
• Answers to Members Questions
CLUBHOUSE
REMODEL PROJECTStatus from May 2019 to March 2020
CLUBHOUSE REMODEL PROJECT STATUS
June 2019
Vote held to approve Capital Improvement Funding for Clubhouse Remodel Proect
July 2019
Board decision to put remodel on hold and revise Office expansion plan
Aug-Dec 2019
Board and Formulus developed a new Office plan staying within the existing Clubhouse walls
Dec 2019
Revised Office/Oakmont Room plans submitted to the City for approval
Jan-Mar 2020
Revised Office/Oakmont Room plan approval received from the City in JanuraryRevised bid and schedule received from CCI received in FebruaryConstruction start March 16, 2020
FINAL CLUBHOUSE REMODEL FEATURES
FINAL
OAKMONT
ROOM
REMODEL
FEATURES
▪ A solid LVT floor will be installed throughout all three rooms
▪ New Audio system with in-ceiling and wall-mounted speakers. State-of-the art control system
▪ Two new ceiling-mounted projectors will be installed
▪ Two new drop-down projector screens. Replace existing screen plus one will be located in the angled ceiling soffit in Oakmont 3
▪ New Airwalls (Movable Partitions)▪ Revised ceiling to provide updated look▪ New window shades▪ Elimination of drapes▪ New LED ceiling-mounted light fixtures▪ New cabinets with solid-surface countertops▪ Stone veneer installed in the alcove walls▪ New paint scheme to provide updated look
FINAL CLUBHOUSE
REMODEL FEATURES
FINAL CLUBHOUSE
REMODEL FEATURES
FINAL OFFICE
REMODEL
FEATURES
▪ Expansion of the office space within the existing Clubhouse exterior walls has been accomplished by removing two of the three showers in the Men’s Locker room.
▪ A new ADA-compliant shower with modern tile and fixtures replaces the remaining shower
▪ A new glass panel wall and door separates the Reception area from the Billiards area for noise abatement and privacy
▪ A reconfigured Reception area will provide for Member comfort
▪ Three offices accommodate the General Manager, Assistant GM and Recreation Director and provides privacy for Members when meeting with the GM or staff
▪ There is room for a small conference table in the GM’s office for most Board Executive Sessions thereby eliminating the need to use the Arts and Crafts room
▪ An open area has been configured for staff, storage, and photo IDs
▪ New Cabinets and countertops. Existing furniture will be utilized where possible
▪ LED lighting
RE-CONFIGURED
OFFICE FLOOR PLAN
FINAL OFFICE
REMODEL
FEATURES
ADA
COMPLIANT
SHOWER(Concept)
REVISED PROJECT
COST
REVISED PROJECT COST
PROJECT COST COMPARISON MAY 2019 FEB 2020
• Building Costs $395,284 $321,829• General Conditions & Supervision $ 97,290 $ 99,730• Insurance Liability (5%) $ 5,433 $ 5,800• General Contractors OHP (9%) $ 52,904 $ 48.910• Testing and Inspections $ 5,278 $ 1,556• HAVC $ 25,870 $ 61,750• Roofing (Contingency) $ 15,821• Audio/Visual System $ 40,850 $ 57,727• Office Furniture (allowance) $ 25,576 $ 25,576• Modular Unit $ 24,000 $ 13,167• Operable Partitions $ 19,470 $ 36,483 • Contingency $ 18,000 $ 18,000
TOTAL COST $709,955 $706,349
REVISED PROJECTCOST
OFFICE RECONFIGURATION CONSTRUCTION COST SAVINGS
• Building Costs $108,722
• General Conditions & Supervision $ 6,250
• General Contractors OHP (9%) $ 3,994
• Testing and Inspections $ 3,722
TOTAL COST SAVINGS $ 122,688
REVISED PROJECT COST
COST INCREASE/DECREASE ( EXCLUDES SAVINGS FROM OFFICE RECONFIGURATION)
• Demolition $ 6.335• Acoustic Ceilng $ 3,000• Flooring and Carpet $ 8,258• Painting $ 1,470• HAVC $ 35,880• Fire Alarm $ 15,973• Fire Extinguishers $ - 470• Window Treatment $ 701• Audio/Visual $ 16,877• Operable Partitions $ 17,013• Temp Utilities and Dumpsters $ 2.600• Travel and Temp Facilities $ - 410• Supplies and Misc $ 6,500• Liability Insurance $ 367• Roofing (contingency) $ 15,821• Modular Unit $ -10,833
COST INCREASE/DECREASE$119,082
REVISED PROJECT COST
REVISED FEB 2020 BID COST DIFFERENCE FROM MAY 2019 BID – SUMMARY
INCREASE/DECREASE (EXCLUDES SAVINGS
FROM OFFICE RECONFIGURATION) $119,082
SAVINGS FROM OFFICE RECONFIGURATION ($122,688)
COST DIFFERENCE -$ 3,606
REVISED
PROJECT
COST
WHILE THE COST DIFFERENCE BETWEEN THE MAY 2019 AND FEB 2020 BID FROM CCI ONLY SHOWS A SAVINGS OF $3,606 THE REASONS FOR THIS ARE:
• MOST OF THE COST THAT WAS ASSOCIATED WITH THE OFFICE EXPANSION HAS NOW BEEN RE-DIRECTED TO ENHANCE THE OAKMONT ROOMS
– TOTAL REDESIGN OF THE CEILING CONFIGURATION
– UPGRADED LVT FLOORING
– UPGRADED AUDIO/VIDEO SYSTEM
– STONE VENEER IN THE ALCOVES
– REPLACEMENT OF FOUR A/C UNITS AND REVISED DISTRIBUTION
– UPGRADED CEILING LIGHTING FIXTURES
• LABOR AND MATERIAL COSTS HAVE ALSO INCREASED SINCE MAY 2019 AND ARE NOW REFLECTED IN THE REVISED BID
PROJECT COST
APPROXIMATE IMPACT OF THE REVISED BID ON THE OAKMONT ROOM AND OFFICE COSTS
OAKMONT OFFICEROOM
MAY 2019 COST WITHOUTCONCURRENT BUILDINGCOST SAVINGS OF ($82,366 )$282,827 $509,761
FEB 2020 OFFICE COST SAVINGS ($122,757)
FEB 2020 OAKMONT ROOMENHANCEMENT $119,082 ________
APROXIMATE RESULTANT COST $401,909 $387,004
THE COST OF THE OAKMONT ROOM UPDATE IS NOW SIGHTLY HIGHER THAN THE OFFICE EXPANSION
REVISED
PROJECT
COST
RE-CONFIGURATION OF THE OFFICE AREA AND ELIMINATION OF EXPANSION BEYOND THE EXISTING CLUBHOUSE EXTERIOR WALLS PROVIDES THE FOLLOWING BENEFITS:
• SIGNIFICANT REDUCTION IN BUILDING COST• INCREASED USE OF FUNDS FROM THE RESERVE ACCOUNT
TO OFFSET THE COST OF THE OFFICE RE-CONFIGURATION• ENCLOSED RECEPTION AREA PROVIDES MEMBER PRIVACY
AND ELIMINATION OF NOISE FROM THE BILLIARDS AREA• IMPROVED WORKING AREAS FOR THE ADMINISTRATION
STAFF• MEMBER PRIVACY WHEN MEETING WITH ADMINSTRATION
STAFF• A CONFERENCE TABLE IN THE GENERAL MANAGERS OFFICE
TO ENABLE TO BOARD TO HOLD MOST EXECUTIVE SESSIONS AND FREE UP OTHER CLUBHOUSE FACILITIES
PROJECT FUNDING
PROJECT FUNDING
THE PROJECT WILL BE FUNDED FROM THE CAPITAL IMPROVEMENT FUND AND RESERVE ACCOUNT
PROJECT
FUNDING
THE ASSOCIATION’S ANNUAL BUDGETED GROSS EXPENSES ARE COMPRISED OF 3 SEPARATE COST ACCOUNT ELEMENTS:
• Operating Budget (Management, Guard Services, Landscape, etc.)
• Reserve Account (Identified replacement items such as flooring, furniture, draperies, lighting, etc.)
• Capital Improvement Fund (New Projects)
REVISED PROJECT FUNDING FROMRESERVE ACCOUNT
May 2019 Feb 2020
• Flooring $14,385 $20,806• Acoustic Ceiling $18,144 $21,400• Cabinets & Countertops $21,080 $14,050• Window Treatments $ 4.557 $ 5,258• Operable Partitions $19,470 $36,483• Audio System $21,500 $32,000• Drywall and Framing $23,273 $27,670• Fire Sprinklers $ 7,250 $24,973• Fire Alarm $ 470 $ 470• Repaint $ 5,350 $10,170• HAVC $18,630 $61,750• Electrical $88,375 $95,400• Office Furniture $10,900 $10,900• Doors/Frames/Hardware $21,725 $10,150• Shower Remodel $26,774
TOTAL RESERVE FUNDING $275,109 $398,254
(NOTE: THE RESERVE ACCOUNT IS CURRENTLY FUNDED AT $3.436 MILLION)
REVISED PROJECT FUNDING
SUMMARY
MAY 2019 FEB 2020
TOTAL PROJECT COST $709,955 $706,349
FUNDING FROM RESERVES ($275,109) ($398,254)
FUNDING FROM CAPITALIMPROVEMENT FUND
NEEDED FOR PROJECT $434,846 $308,095
APPROVAL TO SPEND UP TO $500,000 IN CAPITAL IMPROVEMENT FUNDS OBTAINED IN JUNE 2019$191,905 IS STILL AVAILABLE FOR ADDITIONAL CAPITAL PROJECTS (NOTE: THE CURRENT CAPITAL FUND IS CURRENTLY FUNDED AT $716,000)
PROJECT
SCHEDULE
CLUBHOUSE REMODEL SCHEDULE
March 09-16
Clubhouse Closed (3/9)Presentations to Members (3/9/3/10)Relocate Office (3/9-3/15)Module Unit Open (3/12)
March 16
Start Construction (3/16)Office Reopens (3/16)
March 19 – May 29
Demolition 3/19-3/26Construction
May 29-June 10
Completion of ConstructionClean UpFinal InspectionCertificate of Occupancy
June 12
Grand Reopening of Clubhouse
PROJECTSCHEDULE
• DURING CONSTRUCTION CCI RECOMMENDED TO THE BOARD THAT THE CLUBHOUSE BE CLOSED FOR SAFETY AND TO EXPEDITE COMPLETION OF CONSTRUCTION
• THE ADMINISTRATION OFFICE WILL BE RELOCATED TO THE ARTS AND CRAFTS ROOM . PLEASE MAKE APPOINTMENTS WITH THE MANAGEMENT STAFF DURING THE CONSTRUCTION PERIOD EITHER VIA EMAIL OR PHONE
• THE FITNESS CENTER WILL REMAIN OPEN. HOWEVER, THE HOURS WILL BE ADJUSTED TO:
– Mon-Fri 5:00 am to 7:00 pm– Sat-Sun 7:00 am to 7:00 pm
• A MODULAR UNIT WILL BE PLACED IN THE CLUBHOUSE PARKING LOT TO ALLOW FOR LIMITED CLUB AND GROUP EVENTS
SUMMARY
SUMMARY
• THE BOARD , IN RESPONSE TO MEMBER INPUT IN JULY 2019 PUT THE CLUBHOUSE REMODEL PROJECT ON HOLD IN ORDER TO DEVELOP A MORE COST-EFFECTIVE PLAN FOR THE ADMINISTRATIVE OFFICE EXPANSION
• REVISED OFFICE PLAN DEVELOPED BETWEEN AUGUST AND DECEMBER 2019
• REVISED OFFICE AND OAKMONT ROOM PLAN APPROVAL WAS RECEIVED FROM THE CITY IN JANUARY 2020
• CCI SUBMITTED A REVISED BID AND CONSTRUCTION SCHEDULE IN FEBRUARY 2020
• $308,095 IS REQUIRED FROM THE CURRENT CAPITAL IMPROVEMENT FUND TO ACCOMPLISH THE CLUBHOUSE REMODEL PROJECT VS. $434,846 IN MAY 2019, A COST SAVINGS OF $126,751
• A BALANCE OF APPROXIMATELY $192,000 WILL STILL BE AVAILABLE IN THE CAPITAL IMPROVEMENT FUND FOR FISCAL YEAR 2020-2021 WITH AN ADDITIONAL CONTRIBUTION OF $75,000 EACH FISCAL YEAR FOR FUTURE PROJECTS
ADDITIONAL PLANNED
CLUBHOUSE UPGRADES
ADDITIONAL CLUBHOUSE UPDATES
• THE BOARD IS WORKING WITH CCI TO UPDATE OTHER AREAS OF THE OAKMONT CLUBHOUSE WHILE CONSTRUCTION IS ONGOING
• CCI IS CURRENTLY DEVELOPING THE COST FOR THE ADDITIONAL WORK
• THIS ADDITIONAL WORK WILL BE FUNDED FROM THE RESERVE ACCOUNT.
• THE UPDATES ARE:
• REPLACE THE CARPET IN THE BILLIARDS AREA, MAIN LOBBY, AND LIBRARY WITH THE SAME UPGRADED CARPET AS THE OFFICE
• REPAINT THE ABOVE AREAS AND HALLWAYS TO MATCH THE NEW COLORS IN THE OAKMONT ROOMS AND OFFICE
• UPDATE THE CLUBHOUSE LIGHTING WITH NEW FIXTURES AND LED LIGHTING TO SAVE ENERGY COST
• REFURBISH THE MAIL ROOM LOBBY WITH NEW LVT FLOORING, WALL TREATMENT, AND LED LIGHTING. A NEW FOLDING ELECTRIC-OPERATED DOOR WILL ALSO BE INSTALLED IF STRUCTURALLY FEASIBLE
FOLDING ELECTRIC
ENTRY DOOR
(Concept)
YOUR BOARD OF DIRECTORS APPRECIATES YOU
TAKING TIME TO COME TO THIS PRESENTATION
AND ARE EXCITED ABOUT THE FIRST MAJOR
UPDATE TO OUR BEAUTIFUL CLUBHOUSE SINCE
IT WAS BUILT IN 2005
Q & A’S