78
Beuth University of Applied Sciences Department of Business Administration and Social Sciences Program: MBA Renewables Solar power for IT office buildings in India: Evaluating cost benefits and ancillary advantages Master's Thesis In order to earn the Master of Business Administration degree Submitted by: Sakthi Ganesh Jayakumar Matriculation Number: 804748 Submitted on: 27 January 2016 Supervisor: Prof. Heinrich Lüthi-Struder Evaluator: Prof. Dr.-Ing. Sven Tschirley

SolarEnergyinIT

Embed Size (px)

Citation preview

Page 1: SolarEnergyinIT

Beuth University of Applied Sciences

Department of Business Administration and Social Sciences

Program: MBA Renewables

Solar power for IT office buildings in India:

Evaluating cost benefits and ancillary

advantages

Master's Thesis

In order to earn the Master of Business Administration degree

Submitted by: Sakthi Ganesh Jayakumar

Matriculation Number: 804748

Submitted on: 27 January 2016

Supervisor: Prof. Heinrich Lüthi-Struder

Evaluator: Prof. Dr.-Ing. Sven Tschirley

Page 2: SolarEnergyinIT

I

Executive Summary

In human history the 21st century will be described as the

era of Information technology (IT). The innovations in Information

technology has benefited other areas such as Medicine, Education,

Transportation and many more. India has been one of the biggest

beneficiaries of the IT wave. However the growth of the ICT sector

in India is pulled back because of external circumstances like

problems in Power Sector. Unreliable power supply is a major

problem for the ICT sector. The main goal of this thesis is to

determine if renewable energy could solve this problem and if

renewable energy is financially feasible for the IT industry.

The results of this study shows that Solar PV is a good fit

when compared to other technologies and if the incentives and tax

concessions extended by the government are appropriately utilized

then it is financially viable for the IT companies to implement Solar

PV for captive generation. The study also shows that there are

substantial cost benefits associated with replacement of Diesel

generated electricity with the Solar PV generated electricity. The

financial analysis carried out as part of this study shows that the

Levelized Cost of Energy (LCOE) of Solar PV electricity can be as low

as INR 5-7 and the payback period of Solar PV project could be as

low as 2 years under certain conditions. The diesel replacement

scenario results show that merely by reducing the diesel generated

electricity by Solar PV, a company can save substantial amount of

money. Apart from the direct economic benefits for the company, it

is also shown that if all the existing IT companies generate 100% of

their consumption, then at least 2 million other people will be

benefited from Grid electricity.

Page 3: SolarEnergyinIT

II

List of Figures

FIGURE 1 CONTRIBUTION OF SECTORS TO THE INDIAN GDP SOURCE: PLANNING COMMISSION ....................... 5 FIGURE 2 MARKET SIZE OF IT INDUSTRY IN INDIA. SOURCE: NASSCOM, TECHSCIRESEARCH ............................ 6 FIGURE 3 GROWTH OF ELECTRICITY SECTOR IN INDIA FROM 1947-2015 SOURCE: PIE CHART: 9, CEA, INDIA . . 7 FIGURE 4 DEMAND SUPPLY GAP IN TAMIL NADU, INDIA. SOURCE: BUSINESS TODAY, JULY 22 2012 ............. 10 FIGURE 5 INDIA IT/ITES REVENUE AND EMPLOYMENT GROWTH. SOURCE: DATA COLLECTED FROM MULTIPLE

SOURCES .............................................................................................................................. 12 FIGURE 6 ELECTRICITY DEMAND GROWTH OF THE ICT SECTOR SOURCE: GREENPEACE, MAY 2015 ................ 14 FIGURE 7 RENEWABLE ENERGY INVESTMENTS BY TOP IT COMPANIES SOURCE: GREENPEACE INTERNATIONAL,

MAY 2015 .......................................................................................................................... 15 FIGURE 8 RENEWABLE ENERGY BY INSTALLED CAPACITY IN INDIA SOURCE: “CREATIVE COMMONS RENEWABLE

ENERGY SHARE INDIA 2013” BY SKYDOC28 IS LICENSED UNDER CC BY 2.0 ...................................... 16 FIGURE 9 COLOCATION DATA CENTER STATISTICS, INDIA. SOURCE: DATA CENTER MAP ............................... 19 FIGURE 10 INFORMATION TECHNOLOGY COMPANY LOCATIONS IN SOUTH INDIA. SOURCE: GOOGLE MAPS ..... 19 FIGURE 11 POWER TARIFF HIKE IN TAMIL NADU SOURCE: RECONNECT ENERGY ........................................ 22 FIGURE 12 2014 THUS FAR: THE FALL OF OIL AND ITS EFFECTS ON INDIAN FUEL PRICES, SOURCE: CAPITAL

MIND ................................................................................................................................. 23 FIGURE 13 POWER GRID TRANSMISSION SYSTEM. SOURCE: GREEN CLEAN GUIDE , AUTHOR: SHAILESH ......... 25 FIGURE 14 TYPICAL BREAKDOWN OF THE DATA CENTER ENERGY CONSUMPTION, SOURCE: ELECTRONICS COOLING

, ISSUE: DECEMBER 2010 ....................................................................................................... 29 FIGURE 15 SOLAR ASSISTED COOLING USING ARUN DISH, SOURCE: CLIQUESOLAR .................................... 30 FIGURE 16 ADVANCED SOLAR AIR CONDITIONING TECHNOLOGY IN ARAB EMIRATES, SOURCE: RAC MAGAZINE

.......................................................................................................................................... 31 FIGURE 17 SOLAR PV ROOFTOP SYSTEM IMPLEMENTED AT MURUGAN TEXTILES. SOURCE: TATA POWER SOLAR

.......................................................................................................................................... 34 FIGURE 18 SOLAR PV CAPACITY IMPLEMENTED BY INFOSYS IN DIFFERENT CITIES. SOURCE: INFOSYS ............... 36 FIGURE 19 COMPARISON OF SOLAR PV SYSTEM PERFORMANCE WITH E-W FACING PANELS WITH A SYSTEM WITH

SOUTH FACING PANELS SOURCE: ENERGETICA INDIA .................................................................... 37 FIGURE 20 RID TIED ROOF TOP SOLAR PV SYSTEM WITH FULL LOAD DG BACKUP SYSTEM SOURCE: FIRSTGREEN

CONSULTING ........................................................................................................................ 42 FIGURE 21 CONDENSED LIST OF SOLAR POLICIES IN SOUTH INDIAN STATES. SOURCE: MARCH 2015 SUMMARY

SHEET PUBLISHED BY IREEED .................................................................................................. 43 FIGURE 22 RECOMMENDED FLOW OF IMPLEMENTING SOLAR PV SYSTEM ................................................. 45 FIGURE 23 TOP VIEW OF THE INFOSYS POCHARAM CAMPUS. SOURCE: GOOGLE MAPS ............................... 48 FIGURE 24 FRONT VIEW OF INFOSYS POCHARAM CAMPUS. SOURCE: THATSOKDUDE.COM ........................... 48 FIGURE 25 SOLAR IRRADIATION DATA FOR HYDERABAD. SOURCE: GAISMA ............................................... 49 FIGURE 26 SUN RISE AND SUN SET TIMES FOR 6 MONTHS FROM THE DATE OF ACCESS SOURCE: GAISMA ........ 49 FIGURE 27 SUN RISE AND SUN SET TIMES FOR PREVIOUS 6 MONTHS FROM THE DATE OF ACCESS SOURCE:

GAISMA .............................................................................................................................. 49 FIGURE 28CONSOLIDATED LCOE VALUES FOR 4KWH PER KWP PER DAY YIELD .......................................... 55 FIGURE 29 FIGURE: 2-26 CONSOLIDATED LCOE VALUES FOR 5KWH PER KWP PER DAY YIELD ...................... 56 FIGURE 30 CONSOLIDATED SOLAR PV FINANCIAL PARAMETERS FOR 4 KWH PER KWP PER DAY YIELD ............ 57 FIGURE 31CONSOLIDATED SOLAR PV FINANCIAL PARAMETERS FOR 5 KWH PER KWP PER DAY YIELD .............. 58 FIGURE 32 TYPICAL AC AND DC POWER SYSTEMS IN DATA CENTERS. SOURCE: NTT FACILITIES, INC. TOKYO

JAPAN ................................................................................................................................. 70

Page 4: SolarEnergyinIT

III

Table Of Contents

Executive Summary ______________________________________________ 1

1. Introduction to thesis task and scientific methods __________________ 1

2. Implementation of the thesis tasks ______________________________ 3

2.1 Understanding Interdependence of Indian Economy, Power Sector and

the IT Sector ______________________________________________________ 3 2.1.1 Overview of Power Sector in India_____________________________________ 6

2.1.1.1 Existing Challenges in Indian Power sector: _________________________ 8 2.1.2 Overview of Indian IT Market: _______________________________________ 10

2.1.2.1 Effect of Growth of ICT sector on Power Sector: ____________________ 13

2.2 Overview of Renewable energy focus of India ____________________ 15

2.3 South Indian ICT Sector and Power challenges faced: _______________ 18 2.3.1 Clustered model of IT Company locations ______________________________ 18 2.3.2 Existing power supply scenario and challenges faced by IT companies: ______ 20

2.3.2.1 Impact of unreliable Power supply: ______________________________ 21 2.3.2.2 Impact of rising Electricity costs: ________________________________ 21 2.3.2.3 Impact of rising fossil fuel prices: ________________________________ 23 2.3.2.4 Impact on community: ________________________________________ 24

2.3.3 Options available for IT Companies to meet power supply requirements_____ 24 2.3.3.1 Using Grid as Primary and Diesel as secondary source _______________ 24 2.3.3.2 Purchasing power through Open Access Mechanism (OA): ___________ 25

2.3.3.2.1 Downsides associated with Open Access mechanism: _____________ 26 2.3.3.3 Investing in Renewable energy power generation ___________________ 26

2.3.3.3.1 Possible benefits in adopting renewable energy: _________________ 27

2.4 Selection of suitable renewable energy source for IT companies: _____ 27 2.4.1 Review of Solar thermal energy based models __________________________ 29

2.4.1.1 Solar Thermal Air conditioning options: ___________________________ 29 2.4.1.1.1 Solar Assisted Cooling using VAM and Arun Dish: ________________ 30 2.4.1.1.2 Solar Cooling using Micro-Concentrators and Absorption Chillers: ___ 31

2.4.2 Recommended Solar Technology suitable for ICT companies: ______________ 32

2.5 Overview of existing Solar PV implementations in India ____________ 33 2.5.1 Notable Solar PV projects in South India: ______________________________ 33

2.5.1.1 Solar PV Project Case Study 1 - Murugan Textiles:___________________ 34 2.5.1.2 Solar PV Project Case Study 2 - Infosys: ___________________________ 35

2.5.1.2.1 Special feature of Solar PV system installation at Chennai campus: __ 37

2.6 Solar PV implementation models available for IT companies: ________ 38 2.6.1 Arrangement as a captive generating plant for the roof owners ____________ 39 2.6.2 Solar Lease Model with Sale of electricity to Grid ________________________ 39

2.7 Selection of Solar PV System type suitable for IT Companies _________ 40 2.7.1 Type of Solar PV Systems, their Pros and Cons: _________________________ 40

2.7.1.1 Grid Tied Solar PV System: _____________________________________ 41 2.7.1.2 Off grid Solar PV System: _______________________________________ 41 2.7.1.3 Grid Interactive Solar PV System: ________________________________ 41

2.7.2 Suitable Solar PV System type for IT Companies _________________________ 42

2.8 Policies and Incentives available for Solar PV: _____________________ 43 2.8.1 Accelerated Depreciation Benefit: ____________________________________ 44

Page 5: SolarEnergyinIT

IV

2.9 Recommended flow for implementing Solar PV System: ____________ 44

2.10 Typical electricity consuming devices in Information Technology

companies: ______________________________________________________ 45

2.11 Analysis of financial viability of Solar PV Roof top Systems for IT

Companies: ______________________________________________________ 47 2.11.1 Method followed to select project location of example Solar PV System: __ 47 2.11.2 Selected building and Solar Potential in that location:__________________ 48 2.11.3 Overview of selected financial parameters: __________________________ 50

2.11.3.1 Levelized Cost of Energy – (LCOE) ________________________________ 50 2.11.3.2 Payback period: ______________________________________________ 51 2.11.3.3 Internal rate of return – (IRR): __________________________________ 51 2.11.3.4 Cost Benefit Analysis of Diesel Replacement: ______________________ 52

2.11.4 Assumptions made for financial analysis: ____________________________ 52 2.11.5 Detailed explanation of the Excel file layout: _________________________ 54 2.11.6 Interpretation of the financial analysis results: _______________________ 55

2.11.6.1 LCOE Analysis results: _________________________________________ 55 2.11.6.2 Payback period Calculation results: ______________________________ 56 2.11.6.3 Internal Rate of return calculations: ______________________________ 56 2.11.6.4 Cost benefit analysis of Diesel Replacement scenario results: _________ 57

2.11.7 Consolidated results and conclusions: ______________________________ 57

2.12 Analysis of Ancillary benefits of implementing Solar PV System: ______ 58 2.12.1 Ancillary benefits for the company implementing Solar PV: _____________ 58 2.12.2 Impact of Captive generation by the IT Company on the Grid: ___________ 59 2.12.3 Impact of Captive generation by the IT Company on the community: _____ 60

2.13 Risk Analysis of Solar PV System implementation Project: ___________ 61

3. Solar PV Financial viability calculation results and conclusions: ______ 67

4. Future prospects and emerging technologies relevant to ICT sector: __ 69

Page 6: SolarEnergyinIT

1 | P a g e

1. Introduction to thesis task and scientific methods

The Master’s Thesis will evaluate the financial feasibility of

integrating Renewable Energy in Information Technology (IT)

companies located in India, the advantages of implementing

renewable energy from the company’s perspective and also from

the perspective of the community. Information Technology (ICT)

sector has grown tremendously in the past 25 years in India and is

continuing to grow1. The increasing power consumption due to the

increasing population and growing industrial sectors including IT

Sector, is not matched by the increase in power generation. This

has resulted in erratic power supply even in big cities. Companies in

the ICT sector are largely dependent on two important resources:

1. Human resource 2. Computer hardware & Network equipment.

These computers and Network equipment require uninterrupted

power supply for working. The frequent power cuts prevailing in

most part of the country is detrimental to the growth of the IT

Industry which is one of the fastest growing sectors in India today.

Southern Indian states of Tamil Nadu, Karnataka, Kerala, and

Andhra Pradesh (Recently bifurcated in to Telangana and Andhra

Pradesh) have nearly half of all the existing IT companies in India2.

Rest of the IT companies are spread across other parts of India.

Southern India is taken as the example region for this study. The

discussions related to current energy costs, energy demand gap,

existing policy structures etc are limited to the Southern States due

to the varied nature and the vastness of the country. However the

results from this study can be applied to other parts of India after

considering changes pertaining to those areas.

1 See Federation Of Indian Chambers of Commerce and Industry, Sector Profile: Information Technology (IT), www.ficci.com/sector/21/project_docs/ficci_website_content_-it.pdf , (25.12.2015) 2 See Wikipedia, Economy Of South India, https://en.wikipedia.org/wiki/Economy_of_South_India , (25.12.2015)

Page 7: SolarEnergyinIT

2 | P a g e

The goals of the thesis will be achieved through the following the

logical sequence:

Understanding the interdependence of Power Sector, IT

Sector and Economy

Understanding the Indian Power Sector, existing power

sector setup and the current challenges

Analysis of various renewable energy sources available for

the IT companies and selection of suitable option

Review of existing state policies with respect to renewable

energy

Evaluate the financial viability of integrating renewable

energy for a typical IT Company

Analyze the advantages of implementing the renewable

energy from company’s perspective

Analyze the positive effects on the state DISCOMs because

of the self-generation by IT companies

Analyze the impact on the community due to the reduced

burden on the Grid

With regards to the scientific methods applied, the thesis will

undertake Documentary analysis using Secondary data relevant to

integrating renewable energy to the energy mix of the IT companies

and also Cost Benefit analysis of an example project. The research

undertaken and methods applied are to provide a comprehensive

answer to the following questions:

1. Is it financially viable to implement renewable energy in

Indian IT Companies?

2. What are the ancillary benefits for the company

implementing renewable energy for their own consumption?

3. What other advantages to the society can be expected by

self-generation of electricity by IT companies?

Page 8: SolarEnergyinIT

3 | P a g e

The results of this thesis is expected to shed light on the suitable

renewable energy technology for IT companies, key requirements

for the financial viability of integrating renewable energy in IT

companies and the expected benefits from the companies

perspective and from the community’s perspective.

2. Implementation of the thesis tasks

2.1 Understanding Interdependence of Indian Economy,

Power Sector and the IT Sector

India is one of the largest democracies in the world today.

With over 1.3 billion people, it is already home to approximately

17.5% of all humans in this world. The population is growing at a

rate of 1.2% and is expected to become the most populous country

in the world by 20223. This growth in population also means that

the demand for any consumable goods and services will also

increase. The country has to grow more food, build more houses,

improve infrastructure etc. It is then no surprise that the

requirement for electricity will also increase many fold. In fact,

many states in India are already struggling to meet the electricity

demand. It has been calculated that India’s GDP is constrained by

up to 2% per annum just because of the power shortages prevalent

in many parts of the country. When we consider that the GDP is at

approximately $8 Trillion (By Purchasing Power Parity basis as of

2015), the 2% drop is a whopping $160 billion4. The projection is

that the total power demand would grow at a rate of approximately

10-12% per annum up to 2017 and this is set to widen the loss of

GDP due to power shortages unless the country finds a way to

bridge the gap between the power demand and power generation.

3 See Wikipedia, Demographics of India, https://en.wikipedia.org/wiki/Demographics_of_India , (13.10.2015) 4 See Wikipedia, Indian Power Sector Snapshot, http://www.indianpowermarket.com/2011/05/indian-power-sector-snapshot.html , (13.10.2015)

Page 9: SolarEnergyinIT

4 | P a g e

Rapid developments in the world of science and technology

has resulted in humans relying more and more on electrically

powered machines and gadgets. In the developed countries of the

world power cuts are very rare and even if it happens, it lasts only

for a short amount of time. On the other hand, developing countries

like India are caught between the economic growth and the lack of

sufficient energy required to meet the economic growth. Barely 25

years ago, only a very small percentage Indian households had a

telephone line. Today one can see that even a remote village house

has one or more mobile phones. The electricity demand of these

small gadgets is mounting more and more pressure on the grid. The

government is trying to modernize the existing grids and increase

generation to meet the demands. One of the other major areas of

concern is the transmission and distribution losses which is pegged

at approximately 23%. A recent study indicates that the losses are

as high as 50% in some parts of the country5. Some parts of the

country does not even have access to grid electricity. Nearly 300

million Indian citizens have no access to grid electricity6. This means

that every watt of grid electricity that is not drawn by the existing

grid consumer would save more than one watt for the grid and will

enable someone else to get access to that saved energy.

Traditionally India has been an Agricultural society. Even

today Agriculture is the largest employment sector in India. In

terms of GDP however, the share of Agriculture sector has been

steadily declining while the contribution from Industrial and Services

sector is steadily increasing even though in absolute numbers it has

grown in the past 65 years.

5 See The Energy and Resources Institute (TERI), Transmission and Distribution Losses (Power), www.teriin.org/upfiles/pub/papers/ft33.pdf , (8.09.2015) 6 See Wikipedia, Electricity Sector In India, https://en.wikipedia.org/wiki/Electricity_sector_in_India , (8.09.2015)

Page 10: SolarEnergyinIT

5 | P a g e

The graph below7 shows that the contribution towards GDP from

Services sector has outgrown Agricultural and Industrial sectors.

Figure 1 Contribution of sectors to the Indian GDP Source: Planning commission8

The Services sector covers a wide variety of activities such as trade,

transportation, financing, Hotels and restaurants etc. IT/ITES

sectors otherwise known as ICT sector also comes under the

services sector. ICT Sector in India is one of the fastest growing

services sectors as shown in the figure below9. ICT sector has a

huge dependency on Human resources and Electricity consuming

components such as Computers, Network devices, HVAC equipment

etc.

7 See National Informatics Center, Year-wise and Sector-wise Contribution of GDP,

https://community.data.gov.in/year-wise-and-sector-wise-contribution-of-gdp/ ,

(08.09.2015) 8 See National Informatics Center, Year-wise and Sector-wise Contribution of GDP, https://community.data.gov.in/year-wise-and-sector-wise-contribution-of-gdp/ , (08.09.2015) 9 See India Brand Equity Foundation, Service Sector In India, http://www.ibef.org/industry/services.aspx , (12.09.2015)

Page 11: SolarEnergyinIT

6 | P a g e

Figure 2 Market Size of IT industry in India. Source: Nasscom, TechsciResearch10

With the projected growth of ICT sector, it is clear that the need for

more human resource and electrical energy by the ICT sector will

continue to increase. Considering that the country does not have

enough electrical energy generation capacity to meet the current

demand, it is clear that all other possible energy generation options

should be explored to address the current needs and also to plan for

the future requirements.

2.1.1 Overview of Power Sector in India

India’s power generation largely depends on fossil fuel based

power plants. 60% of the total power generation is based on Coal.

India also produces energy through gas, Diesel, Nuclear, Hydro,

Biomass, Wind and Solar etc. This dependence on fossil fuel also

has a big economic impact in the country’s finances as major

portions of the required Oil and Coal are imported.

10 See India Brand Equity Foundation, IT & ITeS Industry in India, http://www.ibef.org/industry/information-technology-india.aspx , (26.1.2016)

Page 12: SolarEnergyinIT

7 | P a g e

Figure 3 Growth of Electricity Sector in India from 1947-2015 Source: Pie Chart: 9, CEA, India11 .

Even though the country has natural coal reserves, the gross

calorific value of the Indian coal is pretty low compared to the coal

found in other parts of the world. So more coal is required to

generate equivalent amount of electricity. For example the Indian

power plants use 0.7 kg of Indian coal to generate 1 kWh whereas

the US based power plants consume 0.45kg of coal locally mined in

the USA. The higher ash content of Indian coal also results in bigger

impact to the environment12. In terms of consumption of specific

sectors, as of 2015, the Industrial sector consumes around 42% of

the generated electricity. Domestic consumption stands around 24%

followed by the Agriculture sector at 18%13.

11 See India Environment Portal, Growth of Electricity Sector in India from 1947-2015, http://indiaenvironmentportal.org.in/content/413926/growth-of-electricity-sector-in-india-from-1947-2015/ (20.12.2015) 12 See Wikipedia, Electricity Sector In India – Coal Supply Constraints, https://en.wikipedia.org/wiki/Electricity_sector_in_India , (8.09.2015) 13 See Wikipedia, Electricity Sector In India – Demand Trends, https://en.wikipedia.org/wiki/Electricity_sector_in_India , (8.09.2015)

Coal/Lignite (164636 MW)

61%Gas (23062 MW)

8%

Hydro (41267 MW)15%

RES (35777 MW)13%

Nuclear (5780 MW)2%

Diesel (1200 MW)1%

Installed Generating Capacity as on 31.03.2015

(Total = 271722 MW)

Page 13: SolarEnergyinIT

8 | P a g e

Many Indian states extend free electricity or heavily subsidized

electricity to the Agricultural sector. Even though the original intent

was to support farmers and the agricultural sector, this scheme has

largely led to pilferage and wastage of electricity. The electricity

supply is also very unreliable due to poor infrastructure and lack of

required capacity to meet the demand. Bringing electricity to

remote villages of India is a slow process in this vast country. After

more than 60 years after independence, only recently was the

southern Indian grid got connected to the central grid. According to

the data from the World Bank, more than 20% of Indian population

does not have electricity which is approximately 1.4 billion people14.

The Government of India is taking various initiatives to

improve the supply demand gap. But considering that nearly 20% of

Indian citizens are yet to receive any grid power, Government will

have to strike a balance between improving the energy availability

for the industry vs connecting the off grid population. So the

benefits from Governmental efforts may not bring in relief for the IT

sector in the short term and may not match the pace at which the

IT sector is growing. It is in the interest of the companies

themselves to take necessary steps to secure their own energy

requirements.

2.1.1.1 Existing Challenges in Indian Power sector:

One of the major challenges in effectively utilizing the

generated electricity is the Transmission and Line losses (T & L).

India’s T&L losses stand around 23% which is one of the highest in

the world. In fact the World’s average T&L loss is only pegged at

8.9%.

14 See The World Bank, Access to Electricity (% of Population), http://data.worldbank.org/indicator/EG.ELC.ACCS.ZS , (08.09.2015)

Page 14: SolarEnergyinIT

9 | P a g e

Sample studies carried out by independent agencies such as

TERI even indicate that the losses are as high as 50% in some

states15. The T&L losses mainly stems from poor infrastructure, poor

quality of equipment, theft and pilferage. Even though the problem

is clear, there is no easy solution for this problem due to various

different aspects such as the huge investment that is required, lack

of political will to take certain hard decisions etc. Because of this

huge T&L losses, every watt of electricity that is not consumed by a

consumer is worth more than a watt.

Investment from state governments to augment the

generation capacity to meet the increasing demand is also not

adequate in general. The political class resorts to short term

measures rather than taking a long term view due to the political

reasons. The state electricity boards incur heavy financial losses due

to the political decisions made. For example, increasing consumer

electricity tariff is not done in accordance with the actual cost

incurred, as such a decision will alienate the voters from the political

party that is taking the decision. These political considerations result

in mounting losses for the State Electricity Boards (SEBs) which are

already in poor financial conditions.

Even though various Power reforms are being carried out, it will

take a while for any tangible results to be visible on the ground. All

these financial problems mean less investment for expansion by the

SEBs. For example, the figure below shows the gap between the

generation and the demand widening over a period of time in the

state of Tamil Nadu.

15 See The Energy and Resources Institute (TERI), Transmission and Distribution Losses (Power), www.teriin.org/upfiles/pub/papers/ft33.pdf , (8.09.2015)

Page 15: SolarEnergyinIT

10 | P a g e

Figure 4 Demand Supply gap in Tamil Nadu, India. Source: Business Today, July 22 201216

The supply vs demand gap in Tamil Nadu is also true for

many of the other states in India. So it is apparent that irrespective

of what the government is doing or planning to do, there is always a

scope and necessity for the private companies, individuals etc. to do

their part by reducing their consumption or generating at least

portion of their consumption locally, thereby reducing the burden on

the grid.

2.1.2 Overview of Indian IT Market:

India’s Information Technology (IT) story started at least a

decade earlier than the Globalization efforts and the associated

economic reforms that opened up the Indian market in the early

90s. The IT has grown tremendously in the past 25 years in India.

16 See Business Today, Low Voltage Story, http://www.businesstoday.in/magazine/features/tamil-nadu-electricity-board-measures-to-revive/story/185965.html , (15.09.2015)

Page 16: SolarEnergyinIT

11 | P a g e

The push to the Indian economy during the 90’s through

Globalization, coupled with the IT revolution has been the primary

drivers of India’s economic growth. This combined effect has

increased the per capita income (nominal) from US $329 in the

early 90’s to approx. US $2110 in 2016 (estimated)17 The IT

industry by 2012 contributed nearly 8% of the overall GDP18 and

continues to grow at a faster pace.

The Indian Information Technology industry is the preferred

sourcing destination for global IT companies due to the availability

of quality human resource at approximately 3-4 times cheaper cost

compared to say Europe or American market standards. The Indian

IT market is expected to triple the current annual revenue reaching

US$350 billion by FY 202519. Gartner report on public cloud predicts

that the Public Cloud market of India is set to reach US $1.9 billion

by 201920. E-commerce in India has grown many fold in the past

10 years. Home grown E-commerce companies like Flipkart,

Snapdeal etc have brought in a revolution of sorts in the retail

segment. Global companies like Amazon are not far behind ramping

up their presence in India.

IT industry is the largest private sector employer in India. IT

sector has created jobs for approximately 3 Million people through

direct employment and employs close to 9 million people in indirect

employment (2014-2015). According to projections from NASSCOM,

by the year 2020 the IT/BPO industry would have reached a total

revenue of US $360-$375 billion (Approximately 10% of GDP) and

would have provided employment for close to 30 million people (5

Million direct jobs and 25 million indirect jobs).

17 See Wikipedia, India, https://en.wikipedia.org/wiki/India (08.09.2015) 18 See Statista The Statistic Portal, Contribution of Indian IT industry to India’s GDP 2013, http://www.statista.com/statistics/320776/contribution-of-indian-it-industry-to-india-s-gdp/ , (12.10.2015) 19 See India Brand Equity Foundation IBEF, IT & ITES Industry in India, http://www.ibef.org/industry/information-technology-india.aspx , (12.10.2015) 20 See Gartner, Gartner Says Indian Public Cloud Services Market Will Reach $731 Million in 2015, http://www.gartner.com/newsroom/id/3156617 , (12.10.2015)

Page 17: SolarEnergyinIT

12 | P a g e

Figure 5 India IT/ITES revenue and Employment growth. Source: Data collected from multiple sources21

The IT industry can be divided in to four major segments –

Computer Hardware companies, IT Services, Business Process

Management (BPM), Software Products & Engineering Services

companies. At the start of last decade the Indian IT industry was

majorly dependent on the foreign markets. While the Foreign clients

still make up most of the revenue, the domestic industry has grown

as well. The growth of mobile phones and the increasing number of

Internet connected consumers are driving all the different segments

to go digital. Sectors like Education, Hospitality, FMCG,

Transportation, Automotive etc are all moving to setup their shops

on the Internet.

21 See Indian IT-ITes Industry – Slide 6, Indian IT-BPO industry - FY2011-performance & future trends by NASSCOM – Slide 6, NASSCOM Delegation to Africa 2012 – Slide 11, India IT-BPM revenues: USD 118 billion in FY 2014, http://www.slideshare.net/mitul1129/indian-itites-industry , http://www.slideshare.net/nasscom-emerge/indian-itbpo-industry-fy2011performance-future-trends-by-nasscom , http://www.slideshare.net/KuzaBiashara/nasscom-delegation-to-africa-2012 , http://www.cliffcreations.com/images/poster1.jpg , (7.10.2015)

0

50

100

150

200

250

300

350

400

FY03 FY04 FY05 FY06 FY07 FY08 FY11 FY2014

FY20*

(Projectio

n)

Total Revenue (Billion USD) 16.1 21.6 3.5 4.5 47.8 64 59 118 360

Direct Employment (Millionpersons)

0.67 0.83 1.05 1.25 1.63 2.2 2.54 3.1 5

Indian IT/ITESIndustry Revenue and Employment Growth

Total Revenue (Billion USD) Direct Employment (Million persons)

Page 18: SolarEnergyinIT

13 | P a g e

This is driving growth on the IT infrastructure services and to cater

for this domestic demand, the number of data centers in India are

starting to increase. The data from Data Center Map shows that

there are 105 Co-location data centers in India22. .The recent push

to “Digital India” to provide digital services and “Start-up India” to

encourage home grown startups etc are expected to further

increase the pace of development. NASSCOM predicts that India will

have 11,500 tech start-ups by 2020 up from 3100+ startups today.

2.1.2.1 Effect of Growth of ICT sector on Power Sector:

In 2012, close to 4.7 percent of the world’s electrical energy was

consumed by ICT sector23. Considering that India is one of the top

outsourcing destinations for the global IT companies, it can be

safely assumed that the trend of ICT company electricity

consumption would be similar if not more than the global trend.

Projected growth of IT sector in India depends on maintaining the

current success and also be able to capitalize on the new

opportunities.

This means more head count and expansion of campuses which

automatically translates to more electricity consumption. Apart from

the direct consumption of power by the IT sector, it also contributes

to increase in consumption of electricity by way of improved

standard of living of IT employees. So it is evident that the growth

in ICT sector is increasing the burden on the electricity grid which is

already not able to meet the demand. The fact that the Internet has

become main stream and has entered all aspects of life means that

there is an increased use of IT hardware around the globe.

22 See Data Center Map, Colocation India, http://www.datacentermap.com/india/ , (17.10.2015) 23 Lannoo, Bart et al. (2013): Network of Excellence in Internet Science: Overview of ICT energy consumption, The EINS Consoritum, Internet-science.eu, JRA8 Internet for sustainability, WP 8, D8.1

Page 19: SolarEnergyinIT

14 | P a g e

There is also a growing awareness among IT companies regarding

their own power consumption resulting in a broad consensus

regarding the remedial measures that should be taken to reduce

and Offset the overall consumption through renewable energy. The

“Clicking Clean” report by Green Peace indicates that the

Information and Communications Technology (ICT) Sector could be

consuming up to 12% of Global electricity by 2017.

Figure 6 Electricity demand growth of the ICT Sector Source: Greenpeace, May 201524

Renowned IT companies such as Apple, Google, Microsoft,

Amazon etc are recognizing the need for clean energy and have

varying degree of plans. Some of these companies even have a goal

of 100% renewable energy consumption. The table below highlights

the renewable energy deals made by ICT companies in the past

couple of years (2014 and 2015)

24 See Greenpeace International, Clicking Clean: A guide to building the green Internet, http://www.greenpeace.org/usa/wp-content/uploads/legacy/Global/usa/planet3/PDFs/2015ClickingClean.pdf , (13.10.2015)

Page 20: SolarEnergyinIT

15 | P a g e

Figure 7 Renewable energy investments by Top IT companies Source: Greenpeace International, May 201525

It is clear that most of these power purchase agreements are

for data center operations and as Internet is largely run from data

centers, it can be expected that more such initiatives would follow.

Some of the data centers also offer their customers a renewable

option.

2.2 Overview of Renewable energy focus of India

With a total installed capacity of 250+ GW of electricity, India

is one of the top 5 power generators in the world. However still over

80% of the rural population (and close to 20% of total population)

have no access to grid electricity.

So there is a necessity for increasing the energy production to cater

for those who are living outside of the grid. Nearly 70% of the

current capacity comes from Fossil fuels. However the scenario is

changing. The recent advances in renewable energy technologies

and the falling costs have brought forward the advantages of India’s

renewable energy potential. Being a tropical country, India is

blessed with over 300 days of solar radiation.

25 See Greenpeace International, Clicking Clean: A guide to building the green Internet, http://www.greenpeace.org/usa/wp-content/uploads/legacy/Global/usa/planet3/PDFs/2015ClickingClean.pdf , (13.10.2015)

Company Name Location Renewable Source Deal Description (Year)

Google Finland/Sweden Wind energyContract for 59 MW for 10 years to Power Finland data center

(2014)

Google Netherlands Wind energy Purchased 62MW to power E600m data center (2014)

Apple United States Hydro Energy Purchased Micro-hydro project to power data center (2014)

Apple United States Solar New data center to be 100% powered by 70MW Solar (2015)

Apple United States SolarPPA worth $850M for 130MW of Solar energy to power HQ and

CA data centers.(2015)

British Telecom United Kingdom Wind energy Signed PPA worth £440 million for Wind energy (2014)

Microsoft United States Wind energySigned PPA for 175 MW od Wind energy to power the Chicago

data center for next 20 years (2014)

Yahoo United States Wind energySigned PPA for half of 48MW wind project to power Nebraska

data center. (2014)

NTT Communication India Wind energySigned PPA for powering India data center. Power is 11 - 13%

cheaper than grid power (2014)

Amazon United States Wind energy Signed PPA for 150 MW for next 13 years (2015)

Page 21: SolarEnergyinIT

16 | P a g e

It is estimated that the solar irradiance received by India can

generate approximately 5000 Trillion kwh per year26. Recent studies

have suggested that the country has a potential to generate 2000 –

3000 GW of Wind energy27. Wind energy is already one of the

biggest contributor when compared to other renewable energy

sectors. However it can been seen that only a small percentage of

the available Solar and Wind potential has been realized so far.

Figure 8 Renewable Energy by Installed Capacity in India Source: “Creative Commons Renewable energy share India 2013” by Skydoc28 is licensed under CC BY 2.0

The government has taken cognizance of these facts and is

taking lots of initiatives to improve the contribution of alternative

energy sources. The policy initiatives by the Government of India in

the past few years have been supportive of the renewable energy

technologies. In the year 2006 Government of India re-christened

the Ministry of Non-Conventional energy sources that was setup in

1992, to Ministry of New and Renewable Energy (MNRE) to give fillip

to the country’s energy security initiatives28.

26 See NREL, UPDATED India Solar Resource Maps , http://www.nrel.gov/international/ra_india.html , (20.12.2015) 27 Phadke, Amol et al., 2011. Reassessing Wind Potential Estimates for India: Economic and Policy Implications , https://ies.lbl.gov/sites/all/files/lbnl-5077e_1.pdf 28 See Ministry of New and Renewable energy (MNRE), Introduction, http://www.mnre.gov.in/mission-and-vision-2/mission-and-vision , (7.12.2015)

Page 22: SolarEnergyinIT

17 | P a g e

The main goals of this Ministry are to reduce the dependence on the

imported fossil fuel by increasing the contribution of renewable

energy, improve energy availability, and make it more affordable

and also to improve the per capita consumption on par with the

global consumption by 2050.

MNRE is the nodal Ministry of Government of India for all

matters related to the new and Renewable energy. MNRE has

initiatives in various renewable energy fields including Solar, Wind,

Geothermal, Hydro, Tidal, Biomass etc. One of the notable initiative

that is of interest is the Jawaharlal Nehru National Solar Mission

(JNNSM) that was launched in the year 2010. The National Solar

Mission (NSM) targets had a target of 20,000 MWp of Grid

connected Solar power by 2022 at that time29. Recently this target

has been revised from 20,000 MWp to 100,000 MWp of Grid

Connected solar power by the year 2022. To accelerate the progress

and to achieve this revised target, in December 2015, the

Government of India increased the budget for Grid connected

Rooftop systems from 600 Crore INR (approx. US $90 million) to

5000 Crore INR30 (approx. US $750 million). This budget will be

used as a capital subsidy for Residential, Govermental, social and

Institutional sector. It is expected that this budget will bring in

additional capacity of up to 40GW rooftop solar.

Industrial and Commercial sectors do not have access to

government subsidies. However they have a different set of

incentives such as Tax Holidays, Accelerated Depreciation, excise

duty exemptions etc. In addition to the incentive route, the

government is also driving growth of this sector by mandating

Renewable Purchase Obligations for the Distribution Companies,

Open Access Consumers and Captive users.

29 See Ministry of New and Renewable energy (MNRE), JNN Solar Mission Document, http://www.mnre.gov.in/file-manager/UserFiles/mission_document_JNNSM.pdf ,(7.12.2015) 30 See Press Information Bureau Government of India, A Big Boost for Solar Rooftops in India,

http://pib.nic.in/newsite/mbErel.aspx?relid=134026 ,(7.12.2015)

Page 23: SolarEnergyinIT

18 | P a g e

The RPO regulations are defined by respective state regulatory

commissions and may differ from one state to another31.

2.3 South Indian ICT Sector and Power challenges

faced:

2.3.1 Clustered model of IT Company locations

Most of the IT companies in India are based out of what are

classified as Tier 1 or Tier 2 cities. Tier 1 cities have a population of

above 100,000 and Tier 2 cities have a population of 50,000 to

100,00032. Evidently the Grids/Substations servicing Tier 1 and Tier

2 cities are heavily utilized due to large population. These cities are

also home to other non-IT companies like car manufacturers or

consumer goods manufacturing etc due to the available market size

and easy availability of skilled labor. The presence of human capital

attracts new employers and this in turn increases employment

opportunities attracting more and more people to these Tier 1 and

Tier 2 cities. In many cases the boundaries of these cities had to be

expanded due to growth in what was considered as periphery area

of the city. Figure below shows that out of the total 105 data

centers in India, nearly 40% are located in the South India.

31 See Ministry of New and Renewable Energy (MNRE), Analysis of State-wise RPO Regulations across India, http://mnre.gov.in/file-manager/UserFiles/Solar%20RPO/analysis-of-state-RPO-regulations.pdf , (28.10.2015) 32 See Wikipedia, Classification of Indian Cities, https://en.wikipedia.org/wiki/Classification_of_Indian_cities , (28.10.2015)

Page 24: SolarEnergyinIT

19 | P a g e

Figure 9 Colocation Data center statistics, India. Source: Data Center Map33

The figure below is a map showing the location of IT companies in

South India. The red dots represent the company locations.

Figure 10 Information Technology company locations in South India. Source: Google Maps34

From the map it can be seen that the Information technology

companies are concentrated on few locations.

33 See Data Center Map, Colocation India, http://www.datacentermap.com/india/ , (20.10.2015) 34 See Google Maps, http://tinyurl.com/SouthIndianITCompanies , (28.10.2015)

Page 25: SolarEnergyinIT

20 | P a g e

Chennai, Bangalore, Hyderabad, and Trivandrum are the major

cities in which most of the IT companies in South India are situated.

These cities come under Tier 1 cities. There are at least 1500+

software companies present in Software Technology Parks located in

these cities. There are also other IT companies which function from

residential areas and other commercial buildings due to their small

size or lack of offices in the Software Technology Parks. The IT

industry employs at least 3.5 million people (direct employment) as

per Nasscom, the apex body of IT industry in India35. At least half of

these jobs are in South India due to the large number of companies

present in this region.

2.3.2 Existing power supply scenario and challenges faced

by IT companies:

Most of the Information Technology companies are located

within Special Economic Zones (SEZs) setup for IT/ITES

industries36. SEZs have the benefit of tax holidays, good approach

roads, water supply systems, dedicated Electrical substations etc.

So information technology companies have big incentives in locating

their offices within these SEZs37. The state governments give

preferential treatment to SEZs when it comes to Power distribution.

If there is a shortage of grid electricity, SEZs are least likely to be

affected before other consumers. However they do have the

following major operational challenges:

Interruptions in Power supplied from the Grid.

Rising electricity costs

Rising fossil fuel costs

Impact on community due to existing practices

35 See NASSCOM, Robust growth for the Indian IT-BPM Industry , http://www.nasscom.in/robust-growth-indian-itbpm-industry , (28.10.2015) 36 See Special Economic Zones In India, Introduction , http://www.sezindia.nic.in/about-introduction.asp , (28.10.2015) 37 See Business Maps of India, Advantages of SEZ Units in India, http://business.mapsofindia.com/sez/advantages-units-india.html , (28.10.2015)

Page 26: SolarEnergyinIT

21 | P a g e

2.3.2.1 Impact of unreliable Power supply:

Even with the kind of preferential treatment for SEZs

discussed above, due to poor grid conditions and unavailability of

sufficient power, even these companies undergo scheduled and

unscheduled power cuts. These power cuts, especially the

unscheduled power cuts are a huge problem as most of the

equipment required to run the IT business depends on electricity.

The Tamil Nadu state government for example had to resort to up

to 20% - 40% peak hour power cuts for industrial consumers for

the past 4-6 years38. Apart from the scheduled power cuts as the

one mentioned above, there could be unscheduled power cuts as

well due to other aspects such as failure of transformers, failures in

generation etc. The intermittent nature of the power cuts make it

difficult to plan and budget for backup strategies.

There is no short term solution in sight to improve the

situation. Most of the southern states are dependent on fossil fuel

based power stations. Even though Wind energy in Tamil Nadu and

Hydo electric energy in Karnataka have a big presence in these

states, the demand vs generation gap keeps increasing. The recent

development of Southern Grid getting connected to the central grid

would improve the situation39. However the gap is too huge for the

power cuts to be eliminated altogether.

2.3.2.2 Impact of rising Electricity costs:

The electricity costs for consumers are heavily subsidized in

India. Even when the electricity tariffs are revised the state

governments tend to insulate the poor by additional subsidies due

to political considerations.

38 See Business Standard, Tamil Nadu announces 20% power cut for industrial & commercial users, http://tinyurl.com/TNPowercut , (25.10.2015) 39 See Power Grid Corporation Of India Limited, One Nation-One Grid, http://www.powergridindia.com/_layouts/PowerGrid/User/ContentPage.aspx?PId=78&LangID=english , (25.10.2015)

Page 27: SolarEnergyinIT

22 | P a g e

However the Industrial sector power prices continue to increase and

won’t be insulated by subsidies. The state electricity boards which

are responsible for the generation and distribution of electricity are

also in poor financial conditions due to the heavy debt they have as

a result of the subsidy regime. So to bridge the gap between the

revenue and the debt, they resort to regular revision of electricity

prices. For example, the table below shows the recent revision by

Tamil Nadu Electricity board. The electricity prices were increased

by 15% across the board.

Figure 11 Power Tariff Hike in Tamil Nadu Source: Reconnect Energy40

It should be noted that this trend of increasing electricity tariffs is

not isolated to one state. Almost all of the Indian states are pretty

much in the same situation. In fact the prices shown above is one of

the lowest tariffs among the various Indian states. Even if we

assume that the cost of fossil fuel does not increase from the

current levels, it is anticipated that the electricity prices will

continue to increase due to the debt situation, inefficiencies etc.

40 See Open-Access: A Blog by Reconnect, TNERC Hikes power tariff in the state , http://reconnectenergy.com/blog/2014/12/tnerc-hikes-power-tariff-in-the-state/ , (25.10.2015)

Page 28: SolarEnergyinIT

23 | P a g e

2.3.2.3 Impact of rising fossil fuel prices:

The IT companies largely tide over the power cuts through the use

of Diesel generators. This results in increased running costs due to

rising fuel prices and also maintenance costs of generators. In

addition, there is a tendency to cut down on certain electrical loads

when the generator is in use. For example, lifts may not work if

there is no grid electricity. The cost of Petrol and Diesel have been

de-regulated. However the government increases the excise duty

whenever there is a fall in global crude prices and uses this

additional tax to reduce the fiscal deficit. This means that the

consumers are not benefited from the falling crude prices.

Figure 12 2014 Thus Far: The Fall of Oil and Its Effects on Indian Fuel Prices, Source: Capital Mind41

From the Figure 2-10 it can be seen that only a very small

percentage of the falling crude price is passed on to the consumer.

So we can safely assume that the expenses for covering any

shortfall in grid electricity with a diesel generator will not come

down significantly in the future.

41 See Capital Mind, 2014 Thus Far: The Fall of Oil and Its Effects on Indian Fuel Prices, http://capitalmind.in/2014/12/2014-thus-far-the-fall-of-oil-and-its-effects-on-indian-fuel-prices/ , (22.12.2015)

Page 29: SolarEnergyinIT

24 | P a g e

2.3.2.4 Impact on community:

Apart from the cost impact for the companies, the increased

use of Diesel generator results in increase of air pollution and also

to noise pollution. This affects the whole community where these

companies are located. As a cascading effect, people will suffer due

to health issues, increased expenses for medical treatments etc

which will in turn put more load on the government infrastructure.

Also the diesel is still a subsidized commodity and most of the

required oil is imported. So increase in diesel consumption will

result in an even bigger increase in country’s import bill.

2.3.3 Options available for IT Companies to meet power

supply requirements

Industries that are affected by all the above mentioned

problems have only few options available.

I. Continue the current model of Electricity grid as primary

source and Diesel as backup source.

II. Purchase electricity from 3rd party generators through the

Open Access mechanism (OA)

III. Invest in Local generation through renewable sources.

IV. Of course a combination of these three options is also

feasible.

2.3.3.1 Using Grid as Primary and Diesel as secondary source

We have already discussed the various challenges in

continuing with the current model in the preceding section (2.3.2).

In short, it is expensive in the long term, has adverse impact on the

community and also unreliable.

Page 30: SolarEnergyinIT

25 | P a g e

2.3.3.2 Purchasing power through Open Access Mechanism

(OA):

The next option is to purchase electricity from 3rd party

electricity generators. The Indian Electricity Act (2003)42 introduced

the Open Access Mechanism for the first time opening up the

competition in electricity generation.

The open Access Mechanism facilitates the use of the transmission

and distribution infrastructure without any limitations provided the

associated charges are paid by the generator or the consumer. In

India the transmission of electricity is controlled by Power Grid

Corporation of India Limited which is a 100% subsidiary of the

Government of India. Distribution of electricity is largely controlled

by the state electricity distribution companies (DISCOMs) barring a

few private distribution companies in North India. So these two

areas are effectively monopolized by the Government agencies.

However in Generation, private players are present. OA mechanism

acts as a bridge between the private generators and the consumers.

OA mechanism helps to increase competition in power generation

and also gives the consumers a choice.

Figure 13 Power Grid Transmission System. Source: Green Clean Guide43 , Author: Shailesh

The various Open Access charges include Transmission charges,

wheeling charges, wheeling loss compensation, surcharge etc.

42 See Ministry Of Law and Justice, The Electricity Act 2003, http://www.cercind.gov.in/Act-with-amendment.pdf , (30.10.2015) 43 See Green Clean Guide, Introduction of Open Access Mechanism, http://greencleanguide.com/introduction-of-open-access-mechanism/ , (30.10.2015)

Page 31: SolarEnergyinIT

26 | P a g e

All these charges are largely determined by the state electricity

regulatory commissions. The inter-state open access regulations are

governed by the Central electricity regulation commission.

The OA mechanism can also be leveraged when the generator and

the consumer are the same entity. If used efficiently this can enable

the company to become independent of the grid power.

2.3.3.2.1 Downsides associated with Open Access

mechanism44:

The downsides to Open Access are that the regulations

governing the level of Open Access differ from state to state. It may

be possible in one state and may not be possible in another state.

Also, even though the minimum requirement is 1MW only for

leveraging the Open Access mechanism, the generators prefer to

sell electricity in at least in 10s of megawatts in a single contract.

So this is more suitable for heavy industries and may not be

suitable for Software companies depending on their consumption

requirement. However due to the changing regulations in this area,

it would be worthwhile to evaluate applicability of this option

depending on the location and the existing regulations at that time.

2.3.3.3 Investing in Renewable energy power generation

The next option is to invest in renewable energy generation.

Here the companies have few options. They can either invest in

local generation and consumption setup or they can also opt for

remote generation (either themselves or purchase from 3rd party)

and then combine it with the Open Access mechanism to transmit

the power to the consuming location. However with the later, they

may incur Transmission and Distribution losses which can be up to

23% or more depending on the location.

44 See Energy Next, Open Access: Advantage or Bottleneck ? , http://www.energynext.in/open-accessadvantage-bottleneck/ , (30.10.2015)

Page 32: SolarEnergyinIT

27 | P a g e

The past few years have been conducive for private investment in

renewable energy generation and the companies will be able to take

advantages of some of the incentives provided by the Government

of India. Many of the states also have introduced Feed-In-Tariffs for

renewable energy.

2.3.3.3.1 Possible benefits in adopting renewable energy:

By opting to invest in renewable energy generation, the

Information technology companies would be able to:

Reduce their dependency on unreliable grid electricity

Reduce their fossil fuel usage, thereby reducing

operating

costs and maintenance cost of diesel generators

Reduce their carbon footprint

Fulfill their Renewable purchase obligations if any

2.4 Selection of suitable renewable energy source for IT

companies:

If the company decides to purchase renewable energy from a

3rd party power generator, it does not really matter which

technology is used to generate the electricity. The only

consideration in that case would be the cost of electricity and the

reliability offered by the power producer. The other aspect to

consider would be the transmission and line losses. But the

consumer would be billed based on the consumer side on-premise

energy meter and not on the basis of source side meter. If the

company decides to go for local captive generation, the company

has quite a few options of Renewable energy source for captive

generation. Indian renewable industry has a strong presence of

Hydro electric energy, Biomass, Wind energy, Geo thermal energy,

Solar thermal and Solar PV. Out of all the possible renewable energy

sources, Solar PV and Solar Thermal are most suitable for the IT

companies because of the following reasons:

Page 33: SolarEnergyinIT

28 | P a g e

Solar PV and Solar thermal setup can be integrated in

the existing roof top without the need for significant

changes

South India has more than 300 days of good solar

radiation. So it is much more reliable than Wind

energy.

Availability of Solar energy has a higher coincidence

with the regular office hours of the IT companies

Solar projects take relatively less time to setup

Integrating the plant on the roof top allows the

companies to get a better return on their building

investment

Other options such as Wind, Biomass, hydro etc have

specific location based requirement which cannot be

guaranteed in the same area as the IT companies.

Incentives available for Solar projects is better than

other renewable energy

It is relatively easy to scale up the Solar deployment as

and when required.

Problems associated with other technologies such as

aesthetics (Wind), smell (Biomass) etc are avoided

with Solar energy

Solar projects have relatively moderate capex and

nearly zero opex.

Both Solar Thermal and Solar PV can be used to generate

Electricity. The other important form of energy required by IT

companies is Cooling/ Air conditioning. In a typical Information

technology company HVAC cooling contributes to significant

percentage of energy consumption. Figure 2-12 shows the typical

consumption of power by various different components in a data

center. It is clear from the pie chart that the consumption vy HVAC

is a significant percentage.

Page 34: SolarEnergyinIT

29 | P a g e

Figure 14 Typical breakdown of the data center energy consumption, Source: Electronics Cooling , Issue: December 201045

Most of the companies use grid electricity and Diesel generators

(during the absence of Grid electricity) to run the HVAC systems.

There are other possible but not so popular alternative methods

such as Solar Thermal to run HVAC Systems. Government of India

is taking steps to popularize alternative methods of cooling by

offering incentives and also by sponsoring R&D projects in this area.

2.4.1 Review of Solar thermal energy based models

2.4.1.1 Solar Thermal Air conditioning options:

Solar thermal Air conditioning can be a good fit for

Information Technology companies as it can offset some of the Grid

electricity costs or Diesel Generator usage. Even though this

alternative method of cooling has been available for a while,

commercial solutions are not prevalent in the industry.

Solar thermal assisted cooling solution based on Vapor Absorption

Machine (VAM) is deployed in India as a proof of concept project.

The Vapor Absorption Machine is powered by large parabolic ARUN

dish/linear Fresnel solar thermal system. Another novel system

based on flat panel micro-concentrator and Absorption Chillers is

deployed in Abu Dhabi.

45 See Electronics Cooling, Energy Consumption of Information Technology Data Centers by Madhusudan Iyengar and Roger Schmidt, http://tinyurl.com/ElectronicsCooling , (1.11.2015)

Page 35: SolarEnergyinIT

30 | P a g e

Due to less space requirements, the micro concentrator based

systems might be suitable for IT companies who will be able to

integrate it on their roof tops.

2.4.1.1.1 Solar Assisted Cooling using VAM and Arun Dish:

ARUN dishes are large Solar Concentrator dishes developed at

Clique Developments Pvt. Ltd with sponsorship from Ministry of

Non-Conventional Energy Sources (MNES)46. The schematic diagram

of the Solar Assisted cooling system using ARUN Dishes is shown in

Figure 2-13 below.

Figure 15 Solar Assisted Cooling using ARUN dish, Source: CliqueSolar47

In this model, the Solar energy is harvested through the ARUN

dishes and used to heat the water which in turn runs the 50 TR

(about 175 kw) Vapor Absorption Machine (VAM). The Vapor

Absorption Machine requires pressurized hot water at 180o C for

optimum operating conditions.

46 See CliqueSolar, Cooling Industry – Solar Assisted Cooling using ARUN dish, http://www.cliquesolar.com/Comfort.aspx , (01.11.2015) 47 See CliqueSolar, Cooling Industry – Solar Assisted Cooling using ARUN dish, http://www.cliquesolar.com/Comfort.aspx , (01.11.2015)

Page 36: SolarEnergyinIT

31 | P a g e

Nitrogen cylinders connected to the expansion tank are used to

pressurize the water to 15 bar. This results in the cooling of the

Office Room indicated in the diagram above. The return

temperature of the hot water is at 160o C. The “Global Environment

Facility Project document” published by United Nations Development

Programme (UNDP) and Ministry of Non-Conventional Energy

Sources (MNES) indicates that the simple payback for ARUN

Concentrated Solar Heating systems at furnace oil pricing of INR 36

per litre was calculated to be 4-8 years48.

2.4.1.1.2 Solar Cooling using Micro-Concentrators and

Absorption Chillers:

Chromasun, one of the commercial/industrial Solar building

solutions provider has developed Micro Concentrators that can be

easily integrated on the rooftop due to its light weight and low

profile. This system uses a 25x Fresnel reflector and generates up to

220oC. The schematic diagram of this system is shown below:

Figure 16 Advanced Solar Air conditioning Technology in Arab Emirates, Source: RAC Magazine49

Cost wise, Micro concentrators are cheaper when compared to the

Parabolic Trough or the Linear Fresnel.

48 See UNDP, Global Environment Facility Project Document, http://www.undp.org/content/dam/india/docs/market_development_and_promotion_of_solar_concentrators_based_project_document.pdf , (1.11.2015) 49 See RAC Magazine, Advanced solar air conditioning technology in Arab Emirates by Julian Milnes, http://www.racplus.com/news/advanced-solar-air-conditioning-technology-in-arab-emirates/8609581.fullarticle , (1.11.2015)

Page 37: SolarEnergyinIT

32 | P a g e

There is also a 30% capital subsidy available from the

Ministry of New and Renewable Energy (MNRE) for Solar Thermal

cooling solutions50. In addition to the capital subsidy the project

developer would be able to avail Accelerated depreciation of 80% in

the first year and the remaining 20% in the following year. So

comparatively Solar thermal has a better incentive structure from

the government.

2.4.2 Recommended Solar Technology suitable for ICT

companies:

Even though both these novel Solar thermal solutions have

been installed commercially, the lack of wide spread availability,

lack of sufficient supply, unreliable after sales support etc are

important considerations before making the decision to go with one

of these technologies or other similar Solar thermal technologies.

Also, the simple payback period of 4-8 years even including the

capital subsidy and Accelerated depreciation, does not impress

potential customers. Lack of accurate information on investment vs

benefit does not give enough confidence for the customers. The

document “Renewables beyond Electricity – Solar air conditioning &

Desalination in India” published by WWF-India and CEEW51 (Council

on Energy Environment and Water) outlines the potential market

opportunity in this space. The author concurs with the report that

better technological improvements and better policy framework are

needed before Solar thermal cooling is implemented seriously in the

commercial/industrial scenarios. In contrast, Solar PV is widely

implemented in the industrial and domestic segments. It is a proven

technology and there are lots of consultants and developers

available in the market who can help with the implementation.

50 See Ministry of New & Renewable Energy, Subsidy pattern for Solar thermal Systems/devices, http://mnre.gov.in/file-manager/UserFiles/subsidies_solar_thermal_systems_devices.pdf , (15.1.2016) 51 See Council on Energy, Environment and water, http://ceew.in/pdf/CEEW-WWF-Renewables-beyond-Electricity-Report%203Aug14.pdf , (14.1.2016)

Page 38: SolarEnergyinIT

33 | P a g e

Between these two technologies, Solar PV is more suitable for

electricity generation due to lower Levelized cost of energy

compared to Solar Thermal. According to the November 2013 study

published by Fraunhofer Institute for Solar energy Systems ISE,

LCOE for Solar PV is nearly half of Solar Thermal52. Due to lower

LCOE and reduced land requirements, at present Solar PV is more

suitable for Urban areas where the IT companies are generally

located.The costs of Solar panels are coming down and in many

parts of India the Solar electricity cost is nearly on par with the grid

electricity. In fact there are consumers who are willing to

generate/buy reliable electricity at a price slightly higher than Grid

electricity if they can get reliable power supply. So it is clear that

Solar PV is a clear choice for the IT companies till the Solar thermal

industry matures in the future.

2.5 Overview of existing Solar PV implementations in

India

2.5.1 Notable Solar PV projects in South India:

Companies around India have already begun to generate

electricity for their own consumption reducing their dependence on

the unreliable grid electricity. This enables them to run their

business much more efficient and without much down time. Also

this results in long term savings as they reduce/do away with

dependence on Diesel whose price fluctuates resulting in

unexpected economic impact for the companies. We already have

quite a few good examples of such companies in South India in

Information Technology and also even in manufacturing sector

which generally has heavy electrical load equipment. Two of these

examples are summarized below to give an overview of how Solar

PV plants are being utilized in these sectors.

52 FRAUNHOFER INSTITUT FOR SOLAR ENERGY SYSTEMS ISE (Nov 2013): Levelized Cost of Electricity Renewable energy technologies, Freiburg: https://www.ise.fraunhofer.de/en/publications/veroeffentlichungen-pdf-dateien-en/studien-und-konzeptpapiere/study-levelized-cost-of-electricity-renewable-energies.pdf , p.31 , (2.11.2015)

Page 39: SolarEnergyinIT

34 | P a g e

2.5.1.1 Solar PV Project Case Study 1 - Murugan Textiles53:

Murugan textiles is the largest Power loom producer in India.

They have been using Renewable energy for their consumption for

quite a while now. They are using Grid energy as backup energy

and Renewable energy as their primary source of energy. Their

renewable energy generation is a combination of Wind energy and

Solar energy. Solar PV contributes about 25% of their usage

through the recently setup 2MW rooftop plant and the rest comes

from their Wind energy installations. This is one of the biggest roof

top solar PV installations in South India.

Figure 17 Solar PV Rooftop System implemented at Murugan Textiles. Source: TATA Power Solar

Rooftop Solar PV Summary:

Goal : Operate Open-end Spinning machines

with Solar energy

System Size : 2000 KW

Modules : Crystalline Panels of 245Wp and 250Wp

Inverter : 30 kW (57 nos)

Roof Area : 18850 Sq m

Projected Generation : 3 million KWh per annum

Type : Captive consumption, Grid integrated

through 11KV dedicated Feeder Line

53 See TATA Power Solar, Murugan Textiles - the first power loom producer to use 100% renewable energy, http://www.tatapowersolar.com/download_pdf.php?file=images/module/case_study/Murugan_Textiles - Case_Study.pdf , (2.12.2015)

Page 40: SolarEnergyinIT

35 | P a g e

Future Plan : Expand Solar PV by another 1000 KW

Location : Tirupur, Tamil Nadu, India

Murugan Textiles anticipates the following economic benefits:

Cost savings of approx. INR 110 million in 25 years

CO2 displacement of approx. 2500 tonnes per annum54

Fixed energy costs for the next 25 years

Other benefits:

By choosing a Roof top design, they were able to utilize

the unused roof top space thereby realizing more value

of their investment in the building. Also this helped to

save close to 10 Acres of land space had they chose to

implement through a ground mounted plant.

Their estimated break even period is 6 years with the

added advantage of reliable power availability.

By designing this as a Grid integrated Captive

Generating plant, Murugan textiles is able to avail

REC55 benefits.

Will be able to benefit from the Accelerated

Depreciation incentive extended by Government of

India. Through this the company will be able to claim

80% depreciation at the end of the first year there by

reducing the project cost.

2.5.1.2 Solar PV Project Case Study 2 - Infosys56:

Infosys is one of the biggest Information technology

companies in India. Infosys employs around 180,000 + (as of Sep

2015) employees around the globe.

54 See Energetica India, Tata Power Solar commissions the largest rooftop solar plant in South India , http://www.energetica-india.net/news/tata-power-solar-commissions-the-largest-rooftop-solar-plant-in-south-india , (2.12.2015) 55 See Renewable Energy Certificate Registry Of India, Frequently Asked Questions,

https://www.recregistryindia.nic.in/index.php/general/publics/faqs , (2.12.2015)

56 See Energetica India, Shifting Towards New Dimensions in Solar Photovoltaic (PV) Roof Top Systems, http://www.energetica-india.net/download.php?seccion=articles&archivoDc8op3chKxZAqhj5rsAiGVsOlZEJSD40g1mKrDr32G3gnbZTIa3PvkdV.pdf , (3.12.2015)

Page 41: SolarEnergyinIT

36 | P a g e

It became part of RE100 companies in 201557. RE100 companies

aim to generate 100% of their energy from Renewable energy

sources. Infosys has carried out numerous Sustainability initiatives

to reduce their consumption and currently produces about 25% of

the required energy through renewable sources.

The company has a number of campuses across India and

has a combined Solar PV capacity of around 3MWp. Infosys aims to

increase this to 175 MWp by 2018. The current installations are

spread across many cities, most of which are in South India.

Infosys Campus

Location Solar PV Capacity in kWp

Chennai 1792

Trivandrum 127

Hyderabad 555

Jaipur 253

Mangalore 212

Bangalore 265

Total = 3204 Figure 18 Solar PV capacity implemented by Infosys in different cities. Source: Infosys58

The Solar PV plant in Chennai is one of the biggest so far. It

has a capacity of approx. 1.8 MWp. Before implementing Solar PV,

this campus consumed approximately 7 million KWh through Diesel

generators. In Chennai, Diesel power is at least 2-3 times costlier

compared to Grid power.

The Solar PV system helped to displace the diesel generation thus

saving considerable amount of money for the company. Infosys

team estimates the ROI for the Chennai Solar PV systems in Infosys

campus to be about 6 years. Through the use of renewable energy

and energy efficiency measures Infosys claims to have cut CO2

emissions by about 57% in the year 2013-2014 compared to 2007-

200859.

57 See Infosys Newsroom, Infosys Becomes the First Indian Company to Join RE100 Renewable Energy Campaign, https://www.infosys.com/newsroom/press-releases/Pages/join-renewable-energy-campaign.aspx , (2.12.2015) 58 See Infosys, Greenfinity. A world that runs on itself., https://www.infosys.com/sustainability/Documents/greenfinity-report.pdf , (9.11.2015) 59 See Energetica India, Shifting Towards New Dimensions in Solar Photovoltaic (PV) Roof Top Systems, http://www.energetica-

Page 42: SolarEnergyinIT

37 | P a g e

2.5.1.2.1 Special feature of Solar PV system installation at

Chennai campus:

The specialty of this campus is that the PV panels are

installed in the East – West orientation improving the space

utilization and also higher yield per sq m of installed area.

Their experience shows that by implementing the East – West

orientation instead of the traditional South orientation, there are

multiple benefits in addition to the number of modules that can be

mounted in a given space. The table below shows the technical

details from this experiment:

Orientation

Installed DC

Capacity (Kwp)

No of modules

(327 Wp)

Specific Yield (KWh/kwp/year)

PR% Energy

Generation (MWh/Year)

South Facing

235.4 720 1566 77.1 368.8

E-W facing 313.92 960 1557 77.6 488.7 Figure 19 Comparison of Solar PV System performance with E-W facing panels with a system with South Facing panels Source: Energetica India

They cite the following as the advantages observed in this

experiment:

20-30% additional modules can be installed for a given

area

Higher yield per sq.m of installed area even though the

yield per panel reduces by 2% due to the orientation

Reduction in Wind load in case of aero dynamic

structure

Even distribution of electricity throughout the day

Higher Peak hour generation (Morning and evening)

india.net/download.php?seccion=articles&archivoDc8op3chKxZAqhj5rsAiGVsOlZEJSD40g1mKrDr32G3gnbZTIa3PvkdV.pdf , (3.12.2015)

Page 43: SolarEnergyinIT

38 | P a g e

From these examples it is clear that the companies implementing

the Solar PV system are not only realizing the economic benefits,

but are also able to enjoy the additional benefits such as reliable

power, meeting their RPO quota etc.

2.6 Solar PV implementation models available for IT

companies:

IT companies can either choose to participate in the end to end

setup and maintenance or just engage a 3rd party provider to setup

the plant on an EPC/BOOT/DBOOT basis.

In the EPC model the capital costs of the project are estimated and

provided by the client. The EPC contractor executes the project as

per the scope of the client. The EPC contractor takes care of the

Engineering, Procurement and Construction aspects of the project.

In the BOOT model, the contractor builds the project as per client’s

design. Contractor will be building the project using their own funds.

After the project is implemented, the contractor can collect a fee

from the client for a specific period to recoup the investment and

optionally transfer the control of the project to the client if that was

the original agreement.

DBOOT model is similar to BOOT except that even the design phase

will be taken care by the contractor.

Ministry of New and Renewable Energy (MNRE) of Government of

India website indicates that the following models are possible60:

“(a) Solar installations owned by consumer

i) Solar Rooftop facility owned, operated and

maintained by the consumer(s).

60 See Ministry of New and Renewable Energy, Frequently Asked Questions, http://mnre.gov.in/file-manager/UserFiles/FAQs_Grid-Connected-Solar-Rooftop-Systems.pdf , (3.12.2015)

Page 44: SolarEnergyinIT

39 | P a g e

ii) Solar Rooftop facility owned by consumer but

operated and maintained by the 3rd party.

(b) Solar installations owned, operated and maintained by 3rd

Party

If the 3rd party implements the solar facility and provides services

to the consumers, combinations could be:

2.6.1 Arrangement as a captive generating plant for the roof

owners

The 3rd party implements the facility at the roof or within the

premise of the consumers; the consumer may or may not invest

any equity in the facility as mutually agreed between them. The

power is then sold to the roof owner.

2.6.2 Solar Lease Model with Sale of electricity to Grid

The 3rd party implementing the solar facility shall enter into a

lease agreement with the consumer for medium to long term basis

on rent. The facility is entirely owned by the 3rd party and

consumer is not required to make any investment in facility. The

power generated is fed into the grid and the roof top owner gets a

rent.

(c) Solar Installations Owned by the Utility

i) Solar installations owned operated and maintained by the

DISCOM

The DISCOM may own, operate and maintain the solar facility

and also may opt to sub contract the operation and

maintenance activity. The DISCOM may recover the cost in

the form of suitable tariff. The electricity generation may also

be utilized by DISCOM for fulfilling the solar renewable

purchase obligation.

ii) Distribution licensee provides appropriate viability

gap funds

The DISCOM may appoint a 3rd party to implement the

solar facilities on its behalf and provide appropriate funds or

viability gap funds for implementing such facility.”

Page 45: SolarEnergyinIT

40 | P a g e

Solar Energy Corporation of India (SECI) (registered under

MNRE) categorizes the consumer owned model as CAPEX model and

the 3rd party owned model as RESCO (Renewable Energy Service

Company) model61. For consumers that have adequate

manpower/expertise for O&M, rooftop access concerns, availability

of funds upfront, CAPEX model is better. Consumers in certain

Indian states that have net metering regulations can take benefit of

the same in case they have substantial excess generation. On the

other hand, consumers who prefer not to take responsibility for the

system O&M, do not have rooftop security concerns and prefer to

pay on a monthly basis rather than bulk upfront payment may

choose to go for RESCO model.

Information technology companies in general have sufficient

cash flow and would be able to invest the required CAPEX. Also the

companies themselves are in need of electricity for their own

consumption. So the first model will be suitable for IT companies.

2.7 Selection of Solar PV System type suitable for IT

Companies

2.7.1 Type of Solar PV Systems, their Pros and Cons:

The Solar PV Systems can be deployed in the following three

different models62:

Grid tied Solar PV System

Off-Grid Solar PV System

Grid Interactive Solar PV System

61 See Solar Energy Corporation of India, Frequently Asked Questions, http://seci.gov.in/upload/uploadfiles/files/FAQ.pdf , (7.12.2015) 62 See FirstGreen Consulting Private Limited, List of various Schemes of grid tied roof top solar pv system , https://firstgreenconsulting.wordpress.com/2012/06/14/list-of-various-schemes-of-grid-tied-roof-top-solar-pv-system/ , (7.12.2015)

Page 46: SolarEnergyinIT

41 | P a g e

2.7.1.1 Grid Tied Solar PV System:

In this type of Solar PV System the Solar Panels are

connected to the load via an inverter which is also continuously

monitoring the Grid connection. When the Grid goes down, the Solar

System is disconnected by the inverter and it can no longer supply

the load. This is because the inverter requires a reference voltage to

start and since the reference (grid) is no longer available, the

inverter cannot start. Advantage with this system is that when the

Solar panels do not produce enough energy required by the

connected load, the excess required power can be derived from the

Grid.

2.7.1.2 Off grid Solar PV System:

In this type of Solar PV System, the whole set up is

independent of the Grid. As long as the sun is shining the load is

serviced through the Solar panels. The Off grid system also includes

Battery storage which acts as a backup source when there is not

enough sunlight for the panels to generate the required power.

Inclusion of battery storage typically increases the system cost by at

least 30%. Also the batteries require regular maintenance and

possible replacement when it stops working.

2.7.1.3 Grid Interactive Solar PV System:

In this type of Solar PV System, the Solar PV system works

along with the Grid and also Diesel Generator or Battery backup

system. The inverter will continuously monitor the Grid availability

and when the grid becomes unavailable, the Solar System is

disconnected from the grid and the Diesel Generator would start.

Page 47: SolarEnergyinIT

42 | P a g e

The Solar System can be connected back to the AC circuit after it is

synchronized with the Diesel Generator. When the Grid becomes

available again, the Diesel generator is stopped automatically. The

schematic diagram of this setup is given below:

Figure 20 rid tied roof top solar PV system with full load DG backup system Source: FirstGreen Consulting63

This type can also be combined with partial load battery bank as

well.

2.7.2 Suitable Solar PV System type for IT Companies

The main requirement from IT companies is uninterruptable

power supply. The secondary requirement is moderate costs for the

system. The first requirement means that, Grid tied system will not

be suitable for IT companies.

63 See FirstGreen Consulting Private Limited, List of various Schemes of grid tied roof top solar pv system, https://firstgreenconsulting.wordpress.com/2012/06/14/list-of-various-schemes-of-grid-tied-roof-top-solar-pv-system/ , (7.12.2015)

Page 48: SolarEnergyinIT

43 | P a g e

With Solar Off grid system there is a danger of not enough power

when sun is not shining and also increased cost due to battery

backup. So the best model suitable for the IT companies is the Grid

interactive model as it gives the flexibility to power the load through

Solar or through Diesel generator and it is not as expensive as a

battery backup included system.

2.8 Policies and Incentives available for Solar PV:

There are two types of possible incentives available for the

consumers who wish to implement Solar PV. There are some

incentives extended by the Central Government of India. On top of

this there can be incentives depending on which state the Solar PV

system is installed. The table below shows the Solar energy related

incentives from the four southern states.

Figure 21 Condensed list of Solar policies in South Indian states. Source: March 2015 Summary sheet published by IREEED64

The central government extends the Accelerated Depreciation

benefit for Solar PV system implementations for eligible entities.

This benefit is available throughout India irrespective of other state

government level incentives.

64 See Indian Renewable Energy and Energy Efficiency Policy database, State-wise Renewable Purchase Obligation, ireeed.gov.in/summarysheet , (12.12.2015)

Tamil Nadu

One REC per MW wheeled to DISCOM ; Eligible for CDM benefits ; Tax

concessions as per Tamilnadu Industrial policy ; FIT INR 7.01 without

AD ; INR 6.28 with AD

KarnatakaTax concessions as per Karnataka Industrial policy ; FIT INR 8.40 with

AD and INR 9.56 without AD

Andhra

Electricity duty excemption for Captive consumption and 3rd party

sale; VAT for all inouts for Solar Project will be refunded ; Refund of

Stamp duty and registration charges for land purchase; Excemption

from pollution control board certification for Solar projects ; FIT INR

17.91 without AD and INR 14.95 with AD

Kerala

Energy generated is exempted from Electricity duty; Open Access

charges not applicable for Solar ; Wheeling and T&D losses not

applicable for Captive Solar generation within the state; FIT INR 15.18

Page 49: SolarEnergyinIT

44 | P a g e

2.8.1 Accelerated Depreciation Benefit:

In the context of Indian Tax System, Section 3265 of Income Tax act

provides Accelerated depreciation benefit of 80% of invested capital

into Solar PV Projects to professional companies with tax liability.

Investors can set off their tax liability on the taxable income to the

tune of 80% in the first year and subsequently 20% in the second

year. To avail the full 80% AD, the solar pv system should be

commissioned before September 30th of the financial year. If the

plant is commissioned after this date, only 40% AD can be claimed

in that year and the remaining in the following years.

2.9 Recommended flow for implementing Solar PV

System:

Successful implementation of Solar PV requires careful

preparation. The required steps to implement Solar PV are described

below:

Decide on the goal that needs to be achieved through

the Solar PV System. The goal could be to power the

office with 100% renewable energy, displace the power

generated by the diesel generator etc.

Analyze the current consumption and identify areas

which can be improved through energy efficiency

measures

Carry out Efficiency measures. Analyze the

consumption post efficiency measures and include the

capacity required for future plans.

Identify the shade free roof space that can be used for

installing the Solar PV system

65 See Income Tax India, Section - 32, Income-tax Act, 1961-2014, http://www.incometaxindia.gov.in/_layouts/15/dit/pages/viewer.aspx?grp=act&cname=cmsid&cval=102120000000037129&opt=&isdlg=1 , (22.09.2015)

Page 50: SolarEnergyinIT

45 | P a g e

At this point, if the company has sufficient expertise, a

suitable plant as per the requirement can be designed.

If there is no expertise in house, speak to vendors and

call for quotations from multiple vendors.

Select the vendor based on price, quality, warranties

etc and implement

After implementation continue monitoring the

performance and the usage pattern to identify

improvement areas and expand if required.

Figure 22 Recommended flow of implementing Solar PV System

2.10 Typical electricity consuming devices in Information

Technology companies:

Information technology companies have a huge dependency

on the electrical energy as most of their work is done on computers.

However along with the large number of computer and networking

hardware, there are other office equipment as well. From a load

standpoint we can subdivide an IT office electrical load in to the

following categories:

Light loads – Electrical appliances that require very low

starting current. The following are a list of typical light loads found

in IT Companies.

Page 51: SolarEnergyinIT

46 | P a g e

Lighting

Laptops, Desktops, Workstations and additional

monitors

Servers and Network equipment

Sever Racks, Storage racks, Network equipment racks

Printers, Fax machines and paper shredders

Security camera systems

Toaster, Coffee Machines, Microwave and dishwasher

Televisions, Projectors and Telephone systems

Vaccum cleaner

Fridge and Vending machines

Apart from these the other possible equipment that can be

present are gaming consoles, ATM machines, Hand drying

machines, fancy light signs, AV units with speakers etc.

Heavy Loads – Electrical appliances that require very high

starting current

Chiller units

Escalators/Lifts

Water pumps

Water heaters

In general the light load and the heavy load are separated in

different electrical circuits. Even within the Heavy loads the Chiller

units are sometimes separated from other loads. Depending on the

size of the company they may have an on premise datacenter or a

remote data center where all their servers and network equipment

are maintained. The Chiller equipment for the data center is highly

critical as the computer and network equipment get heated up

pretty quickly when the Chillers do not work correctly. This will

result in either the equipment performing slowly, equipment

shutdown or even a hardware failure there by impacting the

production.

Page 52: SolarEnergyinIT

47 | P a g e

In addition to these known loads, we will also need to take in to

consideration the devices that are brought in by the employees for

the personal use such as Laptops, Mobile phone, tablets, e-readers

etc. It has become very common for an employee to own at least

two or more electronic devices. It is technically possible to meet

100% of electricity requirement through Solar PV and Storage

battery systems. However it should also be economically feasible. In

the following sections the implementation costs of an example

project will be discussed and the financial indicators such as

Payback period, Levelized Cost of Energy, cost benefit etc are

calculated.

2.11 Analysis of financial viability of Solar PV Roof top

Systems for IT Companies:

In order to analyze the financial viability of Solar PV System

implementation in an IT company first an example company with

known energy consumption is selected.

Based on the location of the company, the other supporting data

such as Solar irradiance data, grid electricity cost, Cost of Diesel etc

are collected and the final analysis is made.

2.11.1 Method followed to select project location of example

Solar PV System:

For the purposes of this analysis, the Infosys, Panchoram,

Hyderabad campus was selected. Power consumption details for this

campus is taken from the report “Performance Monitoring of IGBC

Rated Buildings” available from Center for Science and

Environment66. This specific building is given a rating of Platinum by

the Indian Green Building Council. This is the highest rating given to

buildings to recognize that the building is highly energy efficient.

The report documents the energy consumption of this campus for

the year 2012 as 2,000,000 kWh.

66 See Center for Science and Environment, Performance Monitoring of IGBC Rated Buildings, https://igbc.in/igbc/html_pdfs/PM-2014N12.pdf , (20.10.2015)

Page 53: SolarEnergyinIT

48 | P a g e

The financial analysis of the Solar PV system would be done for

meeting the requirement of this building.

2.11.2 Selected building and Solar Potential in that location:

The campus is located in the city of Hyderabad which is part

of the State of Telangana (formerly Andhra Pradesh). It is located at

17°26'53.7"N 78°38'09.0"E.

Figure 23 Top view of the Infosys Pocharam Campus. Source: Google Maps67

Figure 24 Front view of Infosys Pocharam campus. Source: Thatsokdude.com68

From the top view and front view of the building it can be

seen that this is the tallest building in that location and there is no

other structure that can cast shadow on the roof of this building.

The Solar irradiation data obtained from Gaisma website shows that

the location has an average of 5.2 kWh/m2/day Solar radiation and

also it is consistently above 4 kWh throughout the year.

67 See Google Maps, Location Search, http://tinyurl.com/InfosysPocharam , (20.10.2015) 68 See Thatsokdude, Infosys To Unveil Its Largest Campus In Hyderabad’s Pocharam In Feb 2016 , http://thatsokdude.com/featured/infosys-to-unveil-its-largest-campus-in-hyderabads-pocharam-in-feb-2016/ , (20.10.2015)

Page 54: SolarEnergyinIT

49 | P a g e

Figure 25 Solar Irradiation data for Hyderabad. Source: Gaisma69

The geographical location and the availability of sufficient

Solar energy makes this location a good fit for the Roof top Solar PV

System. Further the data on Sunrise and Sunset shows that this

location gets at least 11 hours of Sunlight per day.

Figure 26 Sun rise and Sun set times for 6 months from the date of Access Source: Gaisma

Figure 27 Sun rise and Sun set times for previous 6 months from the date of Access Source: Gaisma

69 See Gaisma, Solar irradiation data, http://www.gaisma.com/en/location/hyderabad.html , (20.10.2015)

Page 55: SolarEnergyinIT

50 | P a g e

2.11.3 Overview of selected financial parameters:

The core idea behind this analysis is to determine if

implementing the Solar PV System to replace the existing

combination of Grid electricity and Diesel Generator is economically

feasible. To achieve this goal, first the data regarding the current

energy usage of the building, prevailing grid electricity rates, cost of

diesel etc were gathered. Certain parameters like contribution of

Diesel generator towards day to day operation, T&L power losses for

that region etc are assumed based on realistic average values found

from various different sources. Similarly for the Solar PV System

cost and the yield produced by the Solar PV system are calculated

based on certain facts pertaining to the project location and some

reasonable assumptions.

A list of assumptions for the specific project under analysis is

provided in a separate section of this document. To determine the

financial viability of the Solar PV project, the following parameters

were calculated:

Cost benefit of replacing portion of diesel consumption

by Solar

Levelized cost of Energy (LCOE)

Payback period

Internal Rate of Return (IRR)

LCOE, IRR and Payback period are calculated for two different

scenarios:

1) When Accelerated Benefits are availed

2) When Accelerated Benefits are not availed

From the results of the financial analysis, the conclusions are

derived and presented.

2.11.3.1 Levelized Cost of Energy – (LCOE)

LCOE is a metric used to financially compare two different

types of energy generating methods, often to compare a fossil fuel

energy generation method to a renewable energy generation

method.

Page 56: SolarEnergyinIT

51 | P a g e

LCOE method accounts for all the lifetime costs of a system

including cost of construction, maintenance, financing, tax benefits,

other incentives etc. All the costs and benefits are adjusted for

inflation by discounting them suitably.

𝐿𝐶𝑂𝐸 = 𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑑𝑖𝑠𝑐𝑜𝑢𝑛𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠

𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑑𝑖𝑠𝑐𝑜𝑢𝑛𝑡𝑒𝑑 𝑒𝑛𝑒𝑟𝑔𝑦 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑒𝑑

LCOE calculations in this example are made under two specific

scenarios:

Scenario 1: Company is able to avail Accelerated depreciation

benefit.

Scenario 2: Company is not able to avail Accelerated

depreciation benefit.

This is done to analyze the impact of Accelerated Depreciation

benefit on the LCOE. Only companies implementing the project in

their books can avail Accelerated depreciation benefit.

2.11.3.2 Payback period:

Investors are always interested in knowing how many years it

will take them to recoup their investments and start making profit

on investment. In this example there is no explicit Income for the

company from this project. However by avoiding the consumption of

grid electricity, the company would be reducing their electricity bill

for the grid electricity. The amount of money the company would

save is taken as their income for that year and is compared against

the cost of Solar PV system to determine the payback period. The

payback period is calculated for both the AD benefit scenarios

discussed above.

2.11.3.3 Internal rate of return – (IRR):

The Internal rate of return of a project is the rate at which

the Net Present value of all the costs becomes equal to the Net

Present Value of all the benefits. The Net Present Value function is

given as:

Page 57: SolarEnergyinIT

52 | P a g e

𝑁𝑃𝑉 = ∑𝐶𝑛

(1 + 𝑟)𝑛

𝑁

𝑛=0

Where

N Total number of periods

Cn Cash flow in period n.

r Discount rate.

IRR is the Discount rate at which NPV becomes Zero. If IRR is

higher than the Cost of Capital then we can consider that as an

acceptable investment.

2.11.3.4 Cost Benefit Analysis of Diesel Replacement:

The higher diesel costs in India compared to the Grid

electricity prices make it apparent that using Diesel generators to

tide over the power cuts is an expensive method. In this specific

analysis, the cost benefit of replacing a portion of the diesel

generated electricity with the Solar generation is calculated.

It is assumed that 10% of the overall yearly consumption of

electricity is met by diesel generators. The calculation is done for

10% replacement of this Diesel electricity by the Solar PV system.

The result shows the amount of money the company would be able

to save over the life time of the project by replacing just 10% of the

diesel electricity. The cost of Solar PV electricity is taken as the

LCOE of “Option 1 Scenario 1” which is Solar PV System installation

cost of 0.075 Million INR per kWp and Accelerated Depreciation

benefits availed in 80%-20% ratio.

2.11.4 Assumptions made for financial analysis:

There are several assumptions made for calculating the

Levelised Cost of Energy, Payback period and Cost benefit analysis

of Diesel replacement.

It is assumed that the solar power generated per day

per kWp is 4 kWh.

Page 58: SolarEnergyinIT

53 | P a g e

It is assumed that this building’s electricity

consumption is entirely during day time operation and

the building incurs negligible night time electricity

consumption.

Based on current market data, setting up of Solar PV

system costs anywhere from INR 75,000 – 100,000 per

KWp depending on various factors. For the purposes of

financial calculations, two different costs (INR 75,000

and INR 90,000) are assumed and corresponding

Levelised Cost of Energy is calculated.

The Solar PV System is assumed to be commissioned

before September month of the financial year if

availing the Accelerated Depreciation benefit. In this

scenario 80% of Solar PV System cost can be

depreciated during the first year and 20% in the

second year.

It is assumed that the Solar PV plant has a life time of

25 years

Inverter cost is assumed to be 23% of the total PV

plant cost and also it is assumed that the inverters

have to be replaced after every 10 years

Maintenance cost of the Solar PV power plant is

assumed to be 1% of the total plant cost and the

maintenance cost escalation is 5% every year.

70% debt and 30% equity model is assumed with 12%

debt Interest rate and a repayment period of 7 years.

It is assumed that the Equity is company’s own cash

and there is no Interest on Equity.

Corporate tax is assumed to be 35% (Maximum level).

Discount rate is assumed to be 12% for the LCOE

calculations.

Panel degradation is assumed to be 1% per annum and

a loss of 3% in generation is assumed due to lower

load on holidays and similar factors.

Page 59: SolarEnergyinIT

54 | P a g e

For calculating the benefit of replacing 10% of diesel

power by Solar power, the following reasonable

assumptions based on current data are made:

(i) Cost of diesel per litre is INR 50

(ii) Diesel required to generate 1 kWh electricity is

0.294 litres

(iii) Diesel cost escalation per year is 3%

(iv) Diesel generator is used to meet 10% of the

total electricity required

(v) 10% of Diesel generation is replaced by Solar PV

System.

2.11.5 Detailed explanation of the Excel file layout:

Under these assumptions, the financial calculations of the

above mentioned financial parameters were carried out using the

Microsoft Excel Program. The excel file forms the core financial

calculation document of this thesis and is attached with the main

document for reference. The excel file titled

“PVSystemCalculations.xlsx” has 7 different sheets namely:

Input – System Details – This sheet tabulates the various

different variables which are used in the calculations on the other

sheets. These variables can be adjusted to determine the results

under various different circumstances.

Option 1 Scenario 1 – This sheet calculates the LCOE under

the condition where the Solar PV System setup cost is 0.075 Million

INR and that the company implementing the Solar project is able to

fully avail the Accelerated Depreciation benefit.

Option 1 Scenario 2, Option 2 Scenario 1 & Option 2 Scenario

2 – Similar to the sheet discussed in point 2, all these three sheets

show the LCOE under various combinations of Solar PV cost and AD

benefits.

Diesel Replacement Benefit – This sheet calculates the life

time savings of replacing portion of the diesel generated electricity

by Solar generated electricity. Cost of Solar is taken as the LCOE of

Option 1 Scenario 1

Page 60: SolarEnergyinIT

55 | P a g e

Payback Calculation – This sheet calculates the number of

years it will take to break even under each of the scenarios. The

year in which the project turns to profit is highlighted in green. The

Internal Rate of Return is also calculated in this sheet and is shown

as IRR for each scenario.

2.11.6 Interpretation of the financial analysis results:

2.11.6.1 LCOE Analysis results:

From the analysis we have got the following consolidated

results for the Levelized cost of energy.

Solar PV System cost

per kWp (Million INR)

Avail Accelerated

depreciation?

LCOE

(INR)

0.075 Yes 6.66

0.075 No 7.6

0.09 Yes 8.22

0.09 No 9.55

Figure 28Consolidated LCOE values for 4KWh per kWp per day yield

From the table above we can see that the LCOE in the best case

scenario is INR 5.74 per kWh and in the worst case scenario INR

9.55 per kWh. The current tariff of Grid Electricity in the State of

Telangana is INR 9.70/- for units above 500 per month70.

Comparing the LCOE of Solar PV System to the Grid electricity

prices, it is clear that even in the worst case scenario of the four

scenarios considered, Solar energy is cheaper than the Grid

electricity. In fact this calculation was also under the assumption of

the lower range of the possible yield of 4 KWh per kWp per day.

Based on the location where this Solar PV System is assumed to be

implemented, yield above 4 KWh is expected. Changing the “Power

generated per kWp in a day (in KWh)” value in the “Input – System

Details” sheet of PVSystemFinancials.xlsx to 5 KWh, results in the

following values:

70 See Telangana Discom, Retail Supply Tariff Schedule for FY 2015-16, https://tssouthernpower.com/CPDCL_Home.portal;jsessionid=9hJLWySDLdwqsmpyPcPfZ1yLL11P8z1gpPz2yNYBcTQw19GTPvH2!309511689?_nfpb=true&_pageLabel=CPDCL_Home_portal_page_1215 , (5.1.2016)

Page 61: SolarEnergyinIT

56 | P a g e

Solar PV System cost

per kWp (Million INR)

Avail Accelerated

depreciation? LCOE (INR)

0.075 Yes 5.11

0.075 No 6.37

0.09 Yes 6.35

0.09 No 7.64

Figure 29 Figure: 2-26 Consolidated LCOE values for 5KWh per kWp per day yield

From the results obtained above it is very clear that Levelized cost

of energy obtained from Solar PV is less than the Grid electricity

prices even when the lowest yield figures are assumed.

2.11.6.2 Payback period Calculation results:

The investment payback calculations of the project under

various different scenarios were calculated. The results show that

the Accelerated Depreciation (AD) benefit from Government of India

makes a huge difference in the results. In the best case scenario

where AD is fully available we see that the project will break even

between year 6 and 7 (discounted) and will make profit thereafter.

In the worst case scenario where AD is not available, it can take up

to 23 years (discounted) for the investor to recoup the initial

investment. From these results it is clear that the financial viability

of the Solar PV project greatly depends on the Accelerated

Depreciation benefit available for the companies. As in the case of

LCOE, modifying the yield to 5 kWh per day also has a positive

impact on the payback calculations. The best case scenario

improves to 2 years (discounted) and the worst case scenario to 10

years (discounted) which is still very attractive for any investor.

2.11.6.3 Internal Rate of return calculations:

The Internal Rate of return is consistently higher for all the

four scenarios indicating that the investment is expected to give

good returns.

Page 62: SolarEnergyinIT

57 | P a g e

The lowest IRR (12.45%) for the worst case scenario under 4kWh

yield is marginally better than the assumed discount rates. The

highest IRR (53.26%) is seen for the best case scenario under the 5

kWh yield. The consolidated table in Figure 2-27 and 2-28 shows

the list of IRRs under varying conditions.

2.11.6.4 Cost benefit analysis of Diesel Replacement scenario

results:

The LCOE calculations were made under the assumption that

the entire yield of the Solar PV was used only to offset the Grid

electricity. However due to unreliable grid electricity scenario, most

of the IT companies maintain Diesel Generators for captive power

generation. To cover this scenario, the financial benefits of replacing

10% of Diesel power is calculated. The calculations show that the

Information Technology Company would have saved approximately

INR 2.2 Million over the life time of the Solar PV project. From these

results we can conclude that the more diesel energy is replaced by

Solar energy, the better the returns are for the company.

2.11.7 Consolidated results and conclusions:

The consolidated results of LCOE and Payback period under

various scenarios is given in the tables below for two different yield

assumptions:

Under 4 kWh per kWp per day yield conditions:

Figure 30 Consolidated Solar PV financial parameters for 4 KWh per kWp per day yield

Solar PV System cost per

kWp (Million INR)

Avail Accelerated

depreciation?

LCOE

(INR)

Payback

periodIRR

0.075 Yes 6.66 7 30.34%

0.075 No 7.96 12 18.70%

0.09 Yes 8.22 12 18.47%

0.09 No 9.55 23 12.45%

Page 63: SolarEnergyinIT

58 | P a g e

Under 5 kWh per kWp per day yield conditions:

Figure 31Consolidated Solar PV financial parameters for 5 KWh per kWp per day yield

We can derive the following conclusions from these results:

Accelerated Benefit incentive provided by Government

of India is critical for realizing faster and better returns

from the Solar PV investment.

Solar PV systems implemented in higher solar yield

locations can break even at a much faster rate than the

ones with average yield.

Replacing Diesel Generated electricity by Solar

electricity is beneficial than replacing Grid generated

electricity by Solar generated electricity.

Higher IRR values indicate that the investment in Solar

PV plants add value to the company’s wealth in the

long run.

The financial analysis results of this example project can be adapted

to any IT building analysis in India provided adjustments to the

parameters are made as per the location of the building.

2.12 Analysis of Ancillary benefits of implementing Solar

PV System:

2.12.1 Ancillary benefits for the company implementing Solar PV:

Apart from the financial aspects of the project, there are

other important factors to consider as well. Every major corporation

wants to showcase their commitment towards environmental

protection through projects like these. These additional benefits

may not be readily quantifiable. However they do make a positive

impact.

Solar PV System cost per

kWp (Million INR)

Avail Accelerated

depreciation?

LCOE

(INR)

Payback

periodIRR

0.075 Yes 5.11 2 53.26%

0.075 No 6.37 7 29.21%

0.09 Yes 6.35 5 33.81%

0.09 No 7.64 10 20.35%

Page 64: SolarEnergyinIT

59 | P a g e

By integrating the Solar PV system to the energy mix, the ICT

Company under discussion will be able to realize the following

benefits:

The stability of operations will improve as the

dependency of unreliable grid electricity has been

reduced

Reduction in the Noise pollution and air pollution due to

reduced dependence of diesel generators for power

Improved working environment quality for the

employees of the company due to reduced air and

noise pollution within the company premises.

Company is able to meet the Renewable Purchase

Obligation targets set by the government.

Company has reduced its carbon foot print by reducing

the grid energy which contributes to greenhouse gas

emissions and also by generating clean energy.

2.12.2 Impact of Captive generation by the IT Company on

the Grid:

It was discussed earlier that the T&L losses in India are at an

average of 23%. If we take this in to account, the 2 Million kWh of

electricity per annum that is not drawn by this company from the

grid is worth 2.59 Million kWh per annum for the Grid. This energy

can be then diverted to other consumers reducing the gap between

the supply and demand. In addition, as most of the Grid electricity

is based on imported Coal or Oil, the reduced demand results in

Forex savings for the country. As noted earlier, in many parts of

India the losses are higher than the assumed average. So the local

generation of electricity by any private entity is a good news for the

grid.

Page 65: SolarEnergyinIT

60 | P a g e

2.12.3 Impact of Captive generation by the IT Company on

the community:

Electric Power consumption data from World Bank shows that

India’s per capita Electricity consumption was at 744 kWh per year

during the period 2011-2015. This means that the IT company

which saved 2.59 Million kWh per annum for the grid is indirectly

helping at least around 3500 people who never had access to

electricity before, to get access to that electricity for one complete

year (assuming that the same T&L loss of 23% was incurred in

delivering the electricity to this new set of consumers). The number

of beneficiaries will be definitely higher than this as the consumption

of these new consumers will be far less than the national average

figures.

IT companies are projected to employ 5 Million people by

2020. If all of these IT companies generate 100% of their own

consumption, assuming that the per employee consumption per

year reflects the consumption of an Infosys employee71 before

energy efficiency measures (297 kWh/year per m2), at least 2

million people from rural population would be benefitted.

Considering that at least 300 Million people in India are without

electricity, this is a very significant percentage that can be easily

achieved.

In addition to the savings in electricity, implementing Solar

PV system will also contribute towards reduction in air and noise

pollution levels which would otherwise be incurred to generate the

required power through Thermal power stations or through Diesel

generator. Each MW of grid electricity in India produces the

equivalent of 0.8 tonnes of CO2. So by not drawing 2 Million kWh of

electricity from the grid, the company would have avoided 207200

tonnes of CO2 per year. The effects of such a pollution if not

reduced by Solar PV, will result in increased health costs for the

community.

71 See Infosys, Greenfinity. A world that runs on itself., https://www.infosys.com/sustainability/Documents/greenfinity-report.pdf , (9.11.2015)

Page 66: SolarEnergyinIT

61 | P a g e

In addition poor health situation will result in the reduction of

productivity of the country’s human resource. So it is clear that by

expanding the usage of renewable energy, apart from the direct

financial benefits realized by the company, there can be various

other ancillary benefits that can be realized by the community in

general.

2.13 Risk Analysis of Solar PV System implementation

Project:

There are risks associated with any project implementation.

Implementation of Solar PV project is no different. The risks and

their associated mitigation steps that are discussed in this section

are kept to be as generic as possible so that these can be adapted

to any Solar PV System project planned at any part of India.

S.N

o

Risk

Category

Risk

identificatio

n and

Analysis

Impa

ct

(1 -

10)

Probabili

ty

Risk

Scor

e

Risk

Mitigation

plan

1

Project

Manageme

nt

Delay in

Governmen

t

permissions

delaying

the project

9 50% 4.5

Include a

reasonable

time buffer in

the project

timeline to

accommodate

for the delay.

Regularly

followup with

the

concerned

department

to keep track

of the

approval

process

Page 67: SolarEnergyinIT

62 | P a g e

2

Project

Manageme

nt

Equipment

damange

due to

mishandling

or during

transportati

on

9 40% 3.6

Take

appropriate

Insurance

cover for

damages to

equipment.

Factor in the

insurance

costs in the

financial

calculations

3

Project

Manageme

nt

Lower plant

output due

to faulty

constructio

n practices

of sub

contractors

8 40% 3.2

Engage with

contractor

with good

track record

and negotiate

a precise

contract with

the sub

contractor

with the help

of legal

teams.

Include

clauses in the

contract to

penalise the

sub

contractor in

case of non

delivery/deliv

ery without

certain level

of quality.

Allocate a

resource with

specific

domain

knowledge to

supervise and

track the

progress.

Page 68: SolarEnergyinIT

63 | P a g e

4

Project

Manageme

nt

Poor

coordinatio

n between

multiple

vendors

8 40% 3.2

Identify

appropriate

point of

contacts and

laydown

escalation

rules to

address the

concerns

quickly. Meet

all the

vendors

regularly to

keep track of

the

implementati

on. Make

sure every

vendor is

aware of who

else is

dependent on

them and

how their

work

timelines

affect the

work of other

teams

5 Financial

Lack of

funds in

timely

manner

10 30% 3

Allocate and

keep a

contigency

fund to cater

for the delay.

Factor in such

a delay in the

financial

calculations.

Page 69: SolarEnergyinIT

64 | P a g e

6 Financial

Governmen

t policy

change

results in

Accelerated

Depreciatio

n benefit

10 30% 3

Changes to

Government

policies in

India in

general do

not happen

overnight.

Changes will

also be

applicable for

future

projects

rather than

applying

retrospectivel

y. If the

policy change

happens

during the

planning/desi

gn phase,

rework the

financial

calculations

to avail newly

announced

benefits in

the place of

AD or explore

other possible

benefits like

the

Generation

Based

Incentive

(GBI) that

can be

claimed when

AD cannot be

claimed.

Page 70: SolarEnergyinIT

65 | P a g e

7 Financial

Not able to

avail full

Accelerated

depreciatio

n benefit on

the first

year

9 30% 2.7

Plan the

project

deadline well

before the

Accelerated

Depreciation

timeline for

the year

(before Sep

30th).

Prepare

secondary

financial

analysis

where the full

AD benefit is

not taken in

the first year

to understand

if the

financial

impact on

project

returns is

acceptable

Page 71: SolarEnergyinIT

66 | P a g e

8 Operations

Faulty

design

resulting in

reduced

system

output

9 30% 2.7

Engage with

reputed

consulting

companies

who have

prior track

record

implementing

the scale of

project under

plan. Review

the design

once finalized

by engaging

OEM partners

and get their

technical

opinion about

the

performance

of their

components

in the

proposed

design.

9 Operations

Equipment

malfunction

due to

manufacturi

ng defect

8 30% 2.4

Purchase

quality

equipment

from reputed

manufacturer

s with

appropriate

warranty.

Page 72: SolarEnergyinIT

67 | P a g e

10 Operations

Due to

inclement

weather the

output of

the system

is

consistently

lower for

longer

period

5 10% 0.5

Reduced

output of

Solar PV

system will

not impact

the operation

as more

power would

be drawn

from the Grid

or generated

by Diesel

generator if

the Grid is

not available.

Factor in

additional

possible

losses in the

financial

calculations

to determine

the financial

benefits of

the project.

3. Solar PV Financial viability calculation results and

conclusions:

The goal of this thesis is to determine answers for the

following questions:

I. Is it financially viable to implement renewable energy

in Indian IT Companies?

II. What are the other possible benefits for the company

implementing renewable energy for their own

consumption?

III. What ancillary advantages can be expected by self-

generation of electricity by IT companies?

Page 73: SolarEnergyinIT

68 | P a g e

Based on the results of the financial analysis of the example

Solar PV implementation project by an ICT company, we can

conclude that it is financially feasible to implement Solar PV systems

for captive generation. The analysis clearly shows that the Solar PV

power has achieved grid parity in some places and for industrial and

commercial purposes it is even lower than the grid costs and much

lower than the diesel generated electricity costs. The recent multiple

MW capacity Solar PV bids won by companies show that the

financial results obtained in this thesis are realistic and may even be

considered as based on conservative assumptions. The intention

was certainly to give a balanced view instead of making all best

case assumptions. The trend in the Indian Solar PV market indicates

that the Solar PV might achieve grid parity for Industrial and

commercial applications throughout the country faster than

anticipated before.

When we discuss the non-financial benefits for the company,

the company will be able to realize additional benefits such as

reduced dependency on unreliable grid power, improved working

conditions for the employees, reduced carbon footprint etc. The

additional benefits have ripple effects that will ultimately help the

company as well as the society around it.

On the other hand ancillary benefits which are indirect results

of such a project is an added bonus. It was shown that the example

project could free up electricity for an additional 3500 people who

do not have access to grid electricity. By extrapolating the numbers

it is determined that atleast 2 million citizens could be added to the

grid when all the ICT companies generate 100% of their electricity.

Page 74: SolarEnergyinIT

69 | P a g e

In a vast country like India which is struggling with large

population and substantial section of population under poverty line,

Individuals and corporates will have to contribute to assist the

government. This analysis shows just by reducing their own

dependence on the fossil fuel resources, they will be contributing to

the growth of the country. Initiatives like these which are beneficial

for the corporates and also for the government should be

encouraged. Improving the government policies to encourage these

types of initiatives will go a long way to make the country to

achieve energy self-sufficiency. When energy costs become lower,

the country can move forward at a faster pace.

4. Future prospects and emerging technologies

relevant to ICT sector:

The electrical grid power and the building power delivery

infrastructure in most parts of the world is suitable for Alternative

Current. Traditionally this has worked well as it is more efficient to

transfer AC power over long distances. So the power can be

produced far away from the actual consumer and transported as

required. This lead to market conditions where more and more

devices that operate on AC power became available. The

innovations and growth in electronics sector has resulted in an

increase of devices that actually work on DC power but are modified

to work on AC power due to the existing infrastructure. Each of

these devices have a built in rectifier circuit that converts the AC

power from the power outlet to the usable DC power. This

conversion of power from AC to DC results in power loss. This is

applicable to most of the devices that are used in everyday life like

Mobile phones, Laptops, Televisions etc. The concept of running

devices using Direct Current is not new per se. This was a really old

argument between Mr. Thomas Alva Edison and Mr. Nikola Tesla.

The type of devices available those days were more suitable for

Alternating Current and hence AC became the accepted standard.

Page 75: SolarEnergyinIT

70 | P a g e

But with changing times, we now have more devices that run on DC

power. So it makes sense to use DC power directly without

conversion.

Most of the core equipment used in ICT companies such as

Desktop computers, laptops and Networking devices etc run on DC

power. So there is an inhernet power loss with the way we have

been operating these devices. This scenario is undergoing a change

due to the popularity of Captive generation using Solar PV Systems.

Solar PV system generated power is already DC power. So

theoretically all these devices would be able to work without the AC

to DC adapters. Unfortunately the existing infrastructure can only

handle AC power. So the Solar generated DC power is converted to

AC first then it again gets converted to DC at the device level if

required. Some companies are already experimenting even

commercially deploying DC based power infrastructure. The figure

below shows the traditional power setup where ICT equipment are

powered by AC power (top) and the proposed DC approach

(bottom) to power the ICT equipment in the data center.

Figure 32 Typical AC and DC power systems in Data centers. Source: NTT Facilities, Inc. Tokyo Japan72

72 Hirose, Keiichi (2011). DC Powered Data Centers in the world , http://ze.bot.free.fr/NTT_DC_Datacenter.pdf

Page 76: SolarEnergyinIT

71 | P a g e

There are already a few Data centers around the world which have

commercially implemented this idea. The Japanese telecom giant

NTT’s data center at Atsugi city, Tokyo is the first DC powered data

center servicing external customers. The joint study73 between the

Electric Power Research Institute (EPRI) and Duke Energy, USA,

shows that DC Power system consumes 15% less power compared

to typical double conversion UPS AC power system. They also cite

the following advantages of using DC power system:

Reduced losses

Increased reliability

Reduced cooling requirement

Higher equipment densities resulting in lower land

requirement for data center

Simpler power supplied and Reduced equipment

failures due to Heat

The preliminary results of this study show that the efficiency

of the DC power system is close to 28% better than the existing AC

power systems at a cheaper cost.

Technology improvements like this are suitable for emerging

economy like India. In developed countries like the United States,

they will have to consider the cost of removing the existing

infrastructure and putting in place the new infrastructure. But in

emerging economies like India, there are lots of places where this

will be implemented for the first time as there is no existing

infrastructure and hence the concerns related to “replacement

costs” won’t be applicable. The number of opportunities in the

emerging economies like India for such new technology would be

much greater than the developed economies. Electricity is one

commodity that has not changed much for several decades now. But

the recent trends show that we might be at the start of a new era in

the world of electricity and power generation.

73 See Duke Energy, Duke Energy - EPRI DC Powered Data Center Demonstration Executive Summary, http://docplayer.net/912930-Duke-energy-epri-dc-powered-data-center-demonstration-executive-summary.html , (20.1.2016)

Page 77: SolarEnergyinIT

72 | P a g e

References

A review of Solar Photovoltaic Levelized Cost of Electricity - K. Branker, M.

J.M. Pathak, J. M. Pearce, “A Review of Solar Photovoltaic Levelized Cost of

Electricity”, Renewable & Sustainable Energy Reviews 15, pp.4470-4482

(2011). http://dx.doi.org/10.1016/j.rser.2011.07.104

Clicking Clean - Greenpeace International,

http://www.greenpeace.org/usa/global-warming/click-clean/ (13.10.2015)

EHTP Units - Software Technology Parks of India, Bangalore,

www.blr.stpi.in/images/pdf/ehtpunits140613.pdf (10.1.2016)

Energy Statistics 2015,

mospi.nic.in/Mospi_New/upload/Energy_stats_2015_26mar15.pdf

(16.11.2015)

India Energy Outlook , World energy outlook special report,

https://www.iea.org/publications/freepublications/publication/IndiaEnergy

Outlook_WEO2015.pdf , (16.11.2015)

India Solar PV Advisor - A comprehensive guide for developers and

investors, www.eai.in/ref/services/Preview_of_India_Solar_PV_Advisor.pdf

, (10.10.2015)

Investopedia, http://www.investopedia.com , (20.01.2016)

Make In India - Renewable Energy,

http://www.makeinindia.com/sector/renewable-energy , (9.10.2015)

Making Sense of the Green Rating of Buildings,

http://www.cseindia.org/userfiles/Making%20sense%20of%20green%20b

uilding%20rating.pdf , (9.10.2015)

Renewable Energy Mechanism In India,

https://www.recregistryindia.nic.in/pdf/REC_india.pdf , (11.11.2015)

Renewables beyond electricity - Solar Air conditioning & Desalination in

India, http://ceew.in/pdf/CEEW-WWF-Renewables-beyond-Electricity-

Report%203Aug14.pdf , (14.1.2016)

Solar Power for PC Deployments: Enabling ICT beyond the grid,

www.intel.com/Assets/PDF/casestudies/WA-324794.pdf , (15.09.2015)

Tamil Nadu , Comprehensive Tarrif Order on Solar Power,

http://tnerc.tn.nic.in/orders/Tariff%20Order%202009/2014/solar%20orde

r/Order%20No%204%20of%202014%20dated%2012-09-2014.pdf ,

(17.10.2015)

The Indian Market for Renewable Energy - The 100 GW Solar Initiative,

https://www.efficiency-from-

germany.info/ENEFF/Redaktion/DE/Downloads/Publikationen/Praesentation

en/2015-06-10-intersolar-05-il-fs-energy-dev-india.html , (17.09.2015)

The Rising Sun - Distruption on the Horizon,

https://assets.kpmg.com/content/dam/kpmg/pdf/2015/11/rising-sun-

disruption-horizon-ENRich-2015.pdf , (14.09.2015)

Page 78: SolarEnergyinIT

73 | P a g e

Utility Scale Solar Power Plants,

http://www.ifc.org/wps/wcm/connect/04b38b804a178f13b377ffdd29332b5

1/SOLAR%2BGUIDE%2BBOOK.pdf?MOD=AJPERES , (8.11.2015)