Social Impact Assessment
for Tandur Bypass
Road Project
Draft Report May, 2017
Widening from
existing land to double
lane bypass Road with
paved shoulders –
Tandur Bypass
Tandur, Vikarabad
Submitted to
Submitted By
District Collector
Vikarabad
Government of Telangana
Vikarabad
Telangana.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
i
Centre for Management and Social Research Development Support Specialists
Table of Contents
Chapter Content Page No. Abbrevaiations
SOCIAL IMPACT ASSESSMENT (SIA)
Chapter 1 Project Description
Chapter 2 Applicable legislations and policies
Chapter 3 Approach And Methodology of SIA
Chapter 4 Land Assessment
Chapter 5 Estimation and Enumeration of Affected Families and Assets
Chapter 6 Socio-Economic Profile
Chapter 7 Social Impacts
SOCIAL IMPACT MANAGEMENT PLAN (SIMP)
Chapter 8 Social Impact Management Plan (SIMP)
Chapter 9 Institutional Mechanism
Chapter 10 Analysis Of Costs And Budget For Resettement Action Plan
LIST OF TABLES
Table No. Content Page No.
1.1 Mandal wise extent of land proposed for acquisition
1.2 Charecterisitics of Proposed 2 Lane Road for Tandur Bypass
3.1 Tools and methods used for data collection
3.2 SIA team and tasks carried out
4.1 Extent of Land proposed for aquisition
4.2 Details of survey No’s and to be acquired Land for the project
4.3 Usage of land in the Affected Villages by Number of Surveyed
Households
4.4 Land holding type on listed survey NOs
4.5 Size of the Land Proposed for Acquisition
4.6 Area under cultivation and cropping pattern (Khariff)
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
ii
Centre for Management and Social Research Development Support Specialists
LIST OF TABLES
Table No. Content Page No.
4.7 Type and extent of land affected by the surveyed households
4.8 Prevailing Land rates in affected villages (Rs. per acre)
5.1 Categories of Families Affected and Displaced
5.2 Number of households losing own land and private lands
5.3 Number of surveyed households losing lands and structures
5.4 Village wise other assets affected by the surveyed families
5.5 Community Properties Affected
5.6 Village wise number of trees affected in the lands
6.1 Area and Demographic Profile of the Affected Villages
6.2 Education Facilities
6.3 Literacy among the Affected Villages
6.4 Medical facilities in affected villages
6.5 Sources of Drinking Water Facility
6.6 Communication and Other Facilities in Affected Villages
6.7 Village wise number of affected families surveyed
6.8 Demographic Particulars of the Affected Population
6.9 Social Category of Affected Families
6.10 Marital Status of the Population
6.11 Type of Family
6.12 Age profile of the Affected Population
6.13 Education Level among the Affected Adult Population
6.14 Type of disability
6.15 Family members suffered due to health issues during the last six
months
6.17 Health facility visited in case of illness
6.18 Annual Income of the Households(2016-2017)
6.19 Occupation Profile of the affected adult population
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
iii
Centre for Management and Social Research Development Support Specialists
LIST OF TABLES
Table No. Content Page No.
6.20 Women’s role in the Family and Community Level Decision
making
6.21 Usage and Type of Land
6.22 Landholding Size among the Households
6.23 Source of Irrigation
6.24 Details of Asset Ownership amongst the Households
6.25 Details of Migration Amongst the Households
6.27 Pattern of the purchase of food grains by the affected families
6.28 Indebtedness among Affected Households
6.29 Usage of Loan/Purpose for which Loan was Obtained
7.1 Categories and Degree of the Impacts
8.1 Entitlement Matrix
9.1 Implementation Schedule for SIMP
10.1 Projected Number of Families Affected / Displaced
10.2 Village wise Land Rates
10.3 Estimated budget for rap implementation for proposed project
10.4 Total R&R Costs
LIST OF FIGURES
FIGURE NO CONTENT PAGE
1.1 Location Map of the Road Stretch
1.2 Typical Cross Section (Red Soil Reach)
1.3 Typical Cross Section (B.C. Soil Reach)
3.1 Process flow chart for the sia study
4.1 & 4.2 Land Acquisition Map for Kokat and Rasulpur villages
4.3 Land Acquisition Map for Antaram Village
6.2 Telangana State and Vikarabad District Map
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
iv
Centre for Management and Social Research Development Support Specialists
LIST OF TABLES
Table No. Content Page No.
PHOTO PLATES
3.1 Photographic evidence of Socio-economic Survey
3.2 Gram Sabhas
7.1 Photographs of affected structures and other assets
LIST OF ANNEXURES
Annexure I Census /Socio-economic questionnaire
Annexure II Notification for conducting SIA
Annexure III Gram Sabha proceedings and attendance sheet
Annexure IV Village wise land acquisition Maps
Annexure V List of Project Affected Families (Revenue Department)
Annexure VI Socio-economic details of PAFs
Annexure
VII
Census Details of Affected Assets
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
v
Centre for Management and Social Research Development Support Specialists
Abbreviations
COI Corridor of Impact
GDP Gross Domestic Product
INR Indian Rupees
GoI Government of India
CMSR Centre for Management and Social Research
SIA Social Impact Assessment
SEZ Special Economic Zone
R&R Resettlement and Rehabilitation
RP Resettlement Plan
RAP Resettlement Action Plan
LA Land Acquisition
GoT Government of Telangana
FGD Focussed Group Discussions
PAFs Project Affected Families
SC Scheduled Caste
ST Scheduled Tribes
BPL Below Poverty Line
APL Above Poverty Line
SHGs Self Help Groups
PAPs Project Affected Persons
RoW Right of Width
ROB Rail Over Bridge
R&B Roads and Buildings
RRS Resettlement and Rehabilitation Scheme
SPSS Statistical Package for Social Sciences
SIMP Social Impact Management Plan
RFCTLARR Act
The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement
GO Government Order
CAD Command Area Development
OBC Other Backward Caste
HH Households
PDFs Project Displaced Families
PAFs Project Affected Families
PDS Public Distribution System
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
vi
Centre for Management and Social Research Development Support Specialists
PART - I
Social Impact Assessment (SIA)
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
1
Centre for Management and Social Research Development Support Specialists
Chapter One
Project Description
Introduction
This chapter presents the background, description of the project, project benefits,
location, analysis of alternatives, rationale for public purpose, applicable policies and
laws.
Background
The intensity of traffic particularly on Tandur town has been increased into manifolds
thus rendering inadequate existing road capacity to contain the increased volume of
traffic. To cope up with this challenge Government of Telangana has taken up the
Tandur bypass road in Vikarabad district where the traffic intensity has increased
significantly thereby necessitating capacity augmentation for safe and efficient
movement of traffic. In this regard Executive Engineer, R&B Division, Vikarabad has
been entrusted with the construction of bypass road from 0/000 to 12/000 km in
Tandur town.
Description of the project
The Tandur Bypass project is a long pending dream of the surrounding community.
Approximately 12 kms long proposed Tandur bypass road runs through lands
belonging to Yalal and Tandur Mandals of Vikarabad district. Major villages across the
project stretch are Kokat and Rasulpur in Yalal mandal and Antaram and Chengole in
Tandur mandal. The land from these villages for the project is proposed to be acquired
as per the RFCTLARR, Act 2013. The project involves acquisition of lands to the extent
of 99.28 ½ acres across 4 villages situated in Yalal and Tandur Mandals. The detailed
estimate for the Tandur Bypass road from Km 0/0 to 12/791 is sanctioned by the
Government of Telangana under plan work of widening roads to double lane road vide
G.O.Rt.No.130 Dt. 27.11.2014. The estimated approximate cost of the project is Rs. 75.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
2
Centre for Management and Social Research Development Support Specialists
cr. The Revenue Department, Government of Telangana will acquire land for R&B
department. Details of land acquisition proposed is presented below :
Table 1.1 : Mandal wise extent of land proposed for acquisition
Sl.No. Name of Mandal Extent in Acres-Guntas
1. Yalal Mandal 55.01
2. Tandur Mandal 44.27 ½
Total 99.28 ½
Objectives and Importance of the Project
Tandur mandal is surrounded by number of stone industries and cement factories.
There is a continuous moment of trucks and Lorries from these industries through
Tandur town causing traffic jams, accidents and pollution. The objective of the project is
to avoid traffic congestion of heavy vehicles in Tandur town and provide better
connectivity to various regions in and around Tandur Vikarabad district, facilitate
speedy and smooth transportation of bulk goods with less interruption at a lesser
transport cost and in less time, induce socio-economic development of existing growth
centers, provide impetus for the development of new growth centers, employment
generation and as a consequence poverty alleviation in the project areas. The following
map gives an overview of connectivity of the project road (Fig 1.1):
Existing Charecterstics of the bypass section
The proposed bypass section is completely new alignment with 30m width. The
proposed project road passes through agriculture fields, barren lands and open plots.
The proposed Tandur bypass starts at Tandur chainage 0+000 (Mahboobnagar to
Chincholi SH Chainage 75/200 towards right side) and ends at Chengole village
chainage 12+000 (Gauthapur 81/800). There is no location which is covered by built up
areas, religious structures either on the edge of/ or close to the carriageway of the
proposed alignment.
Status of Right of Way (ROW )
For the entire length of alignment between Rasulpur and Gawthapur, a bare minimum
requirement of land for double lane has been proposed as per the engineering code. As
per the data obtained from R&B Department, the Right of Way (ROW) needed for all
along the project corridor is 30m. The proposed ROW at ROB locations is 45m. The
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
3
Centre for Management and Social Research Development Support Specialists
Land Acquisition Plans are prepared to have uniform ROW in accordance with the state
highway guidelines.
Fig. 1.1 : Location Map of the Road Stretch
Start Point of the Proposed Bypass Road at Rasulpoor, Yalal Mandal
End Point of the Proposed Bypass Road at
Gawtapur, Tandur Mandal
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
4
Centre for Management and Social Research Development Support Specialists
Photo Plate 1 – Start point and End points of proposed Project Road
Proposed Improvements
The Tandur bypass from Rasulpur - Gawtahpur is proposed to be constructed to two
lanes with paved shoulder. The project road will have few major bridges and minor
bridges. The numbers of culverts proposed to be constructed under project are 5. The
project road improvement has proposed two types of cross sections as depicted below.
Different cross sections have been adopted for Red soil and BC soil areas depending on
the availability of RoW and site conditions. The proposed cross sections for the project
road are given in Figure 1.2 to Figure 1.3. The detailed characteristics of the road
improvements are given in Table 1.2.
Fig. 1.2 : Typical Cross Section (Red Soil Reach)
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
5
Centre for Management and Social Research Development Support Specialists
Fig. 1.3 : Typical Cross Section (B.C. Soil Reach)
Table 1.2 : Charecterisitics of Proposed 2 Lane Road for Tandur Bypass
1 Design length 12.00 km
2 Connectivity The proposed bypass starts from Tandur chainage 0+000 (Mahboobnagar to Chincholi SH Chainage 75/200 towards right side) and ends at Chengole village chainage 12+000 (Gauthapur SH Chainage No. 81/800).
3 Terrain Plain
4 RoW
Proposed RoW 30m for Road and 45m at ROB locations
Existing RoW Nil
5 Carriage way configuration
Existing lane None
Proposed Lane Two Lane (15m)
Formation width Two lane with shoulder of 2.5 m on each side (12m)
Culverts Formation width 12m
6 Pavement Flexible
7 Subgrade CBR value proposed 10% to 12%
8 Design period 10 years
9 Pavement Composition
Sub Grade + GSB 500 mm / 200mm
WMM 250 mm
DBM + BC 50 mm + 40 mm
Total 1040mm
10 CD Structures
Bridges Major Bridges 0 Nos Minor Bridges 2 Nos
Culverts Slab 0 Nos HP 20 Nos Box 6 Nos
Rationale and Public Purpose of the Project
Section 2 (1) of RFCTLARR Act, 2013 states that the land may be acquired only for the
public purpose. The public purpose mentioned in the Act include Defence and National
Security; roads, railways, highways, and ports built by government and public sector
enterprises; land for the project affected people; planned development; and
improvement of village or urban sites and residential purposes for the poor and
landless, government administered schemes or institutions. Also include all the
activities mentioned in the notification of the Government of India in the Department of
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
6
Centre for Management and Social Research Development Support Specialists
Economic Affairs (infrastructure Section) number l3/6/2009-lNF, dated the 27th March
2012, excluding private hospitals, private educational institutions, and private hotels,
etc. The provisions of the act shall be applicable in above cases.
The main of objective of the Tandur Bypass Road is to improve the performance of the
district road transport network. All the road users including the affected persons
(PAPs) will benefit from the proposed improvement through increased comfort and
reduced travel time. The society will benefit economically from the saving in vehicle
operating costs due to enhanced speed and better geometric. The project also will open
up the areas adjacent to the project road to increased economic activity. The project is
expected to bring quite a few benefits as detailed below:
• Traffic caused in Tandur town due to heavy vehicles such a cement carrying
trucks, stones carrying trucks and other heavy vehicles will be diverted to bypass
road thereby reduces traffic jams.
• Accidents will come down drastically due to diversion of heavy vehicles from Tandur town.
• Result in lower transport costs for freight and passengers of motorized and non- motorized vehicles
• Increase in the local employment opportunities is a significant and immediate economic benefit of the project
• Local communities will have greater access to public infrastructure and increased mobility through enhanced transport facilities
The proposed land acquisition is to support the development of state transport network
thus serves the public purpose.
Examination of alternatives
Due care was taken during the detailed design of the project preparation to minimize
the loss under land acquisition. Through suitable engineering design attempts have
been made to confine the project area in the government land and in available Right of
way where feasible. This has been done with proper consultation with the local people
and affected communities. Their suggestions were taken in the project design. Measures
are also followed to minimise the resettlement like selection of the project sites covering
government land, and preferred open land instead of habitation and building structures
etc. Before finalizing the alignment, R&B department had explored two other options
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
7
Centre for Management and Social Research Development Support Specialists
regarding design and project alignment. Two alignments of bypasses have been studied
to minimize the impacts and avoid displacement.
Alignment No.1
First alignment proposed by R&B was very close (500 mtrs) to Tandur town affecting
more number of residential structures and causing large scale displacement. Apart from
residential structures, two very important irrigation tanks which cover irrigation to
approximately 100 acres lands were also obstructing the proposed road. To minimize
displacement and avoid irrigation tanks this alignment was found not feasible.
Alignment No.2
The proposed second alignment planned near warehouses at Kanjapur village causing
additional land acquisition and increase in length of alignment about 2.5 kms due to
which there will be increase in project cost and more land acquisition. Therefore this
alignment not found viable due to increase in project costs and additional land
acquisition.
Alignment No.3
The proposed alignment in semi-circle shape from Rasulpur, Kokat village, Rajiv
Colony, Bashirmiya Thanda, Antaram, Antaram Thanda, Chengole and Gauthapur
found suitable due to very minimum number of obstructions as the alignment passes
through agriculture fields and open plots. In this alignment there is only one private
residential structure affected and remaining are bore wells, tombs and a small temple.
The fundamental idea behind the present acquisition is to ensure lowest possible
displacement of people and minimal interference with residential areas. After due
consideration and confirmation of lowest impacts, present alignment has been finalized.
Ancillary infrastructural facilities and workforce requirement
During the construction phase it is estimated that there will be a requirement for more
than 500 skilled and un-skilled manpower. This workforce will be supplied by the
principal civil contractor. During operational phase, requirement of manpower (both
temporary and permanent) will be decided after the award of the contract. There is no
need for setting up of major ancillary infrastructure for the project.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
8
Centre for Management and Social Research Development Support Specialists
Chapter Two
Applicable legislations and policies Introduction
This section of the report presents various laws and regulations in the country, which
are applicable to the Tandur Bypass Road project. A detailed understanding of the
provisions mentioned in these legislations will help to identify a suitable legal
framework under which rehabilitation of project affected families can be implemented.
The applicable laws on land acquisition, rehabilitation, and resettlement of the
proposed Tandur Bypass Road project are as follows:
• Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
• Telangana Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Rules 2014
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act, 2013)
The Right to fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act (2013) is applicable to the whole of India except the state of
Jammu and Kashmir. The provisions of this Act relating to land acquisition,
compensation, rehabilitation and resettlement, shall apply, when:
• Government acquires land for its own use, hold and control, including land for
Public sector undertakings.
• Government acquires land with the ultimate purpose to transfer it for the use of
private companies for stated public purpose
• Government acquires land for Public Private Partnership Projects.
• Schedule I outlines the proposed minimum compensation based on a multiple of
market value.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
9
Centre for Management and Social Research Development Support Specialists
• Schedule II through VI outlines the resettlement and rehabilitation entitlements to
land owners and livelihood losers, which shall be in addition to the minimum
compensation per Schedule I.
Below elaborates some important provisions:
• Section 4 of Act specifies that the Social Impact Assessment shall be conducted in
consultation with concerned Gram Panchayat, Mandal Parishad, Municipality or
Municipal Corporation, as the case may be, at village level or ward level in the
affected areas, for the purposes of section 4 of the Act, followed by a public hearing
at the affected areas by giving adequate publicity about the date and time and
venue for the public hearing to ascertain the views of the affected families which
shall be recorded in writing.
• Section 16 of the Act briefs on the preparation of Resettlement and Rehabilitation
Scheme (RRS) , publication and public hearing of RSS. Relevant points include: (a)
Upon the publication of the preliminary notification by the collector, the
Administrator for Rehabilitation and Resettlement shall conduct a survey and
undertake a census of the affected families.
• A draft Rehabilitation and Resettlement Scheme shall be prepared by the
Administrator which shall include particulars of the R&R entitlements of PAPs. The
draft shall include time limit for implementing the Scheme. The Scheme shall be
discussed in the concerned Gram Sabha or Municipalities.
• A public hearing shall be conducted after adequate publicity about the date, time
and venue in the affected area. Following the public hearing, the Administrator
shall submit the draft Scheme along with a specific report on the claims and
objections raised in the public hearing to the Collector.
• As per Section 25, the Collector shall make an award within a period of twelve
months from the date of publication of the declaration and if no award is made
within that period the entire proceedings for the acquisition of the land shall lapse,
provided that the appropriate Government shall have the power to extend the
period in circumstances justifying the same and any such decision to extend the
period shall be recorded in writing and be notified and uploaded on the website of
the authority concerned.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
10
Centre for Management and Social Research Development Support Specialists
• Section 26, 28, 29 and 30 of the Act briefs on the methodology of determining the
market value of the land and other properties.
Determination of Market value
The competent authority while determining the market value of the land has to
consider the higher value of the land arrived at by 3-methods of valuation vis: (i)
market value as per Indian Stamp Act, 1899 for the registration of sale deed or
agreements to sell, in the area where land is situated; or (ii) average sale price for
similar type of land, situated in the nearest village or nearest vicinity area, ascertained
from the highest 50% of sale deeds of the preceding 3 years; or (iii) consented amount
paid for PPPs or private companies. In case of rural areas, the market value of land so
determined is multiplied by a factor, to be decided by the appropriate government. A
solatium of 100% is payable on the market value of land multiplied by the factor and all
immovable properties or assets, trees and plants.
A Resettlement and Rehabilitation award detailing the entitlements to be provided as
per the Second Schedule of Act is passed by the competent authority. Possession of land
can be taken only after payment of compensation and rehabilitation and resettlement
entitlements as detailed in Second Schedule and Third Schedule. The details of
amenities to be provided in a resettlement site are detailed in the Third Schedule.
Rehabilitation and Resettlement Entitlements
The Act also provides the displaced families with certain R&R entitlements. These
include, among other things :
R&R Entitlements for Project Affected Families (PAFs) :
• Choice of Annuity : the option of choosing either mandatory employment in
projects where jobs are being created or a one-time payment of INR 5 lakh or an
inflation adjusted annuity of INR 2,000 per month per family for 20 years
• One-time Resettlement Allowance: INR 50,000 for affected families
• Cattle shed/petty shops - INR. 25,000/
• One time grant to artisan/traders/self employed - INR. 25,000/
• Fishing rights in reservoir – Affected families of irrigation or Hydel projects the
affected
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
11
Centre for Management and Social Research Development Support Specialists
• Land for land – Affected families of Irrigation projects (as far as possible) 1 acre
of land (2.5 acres for SCs/STs in command area)
• Offer for Developed Land - In case of land is acquired for urbanization purpose
20% of the developed land will be reserved and offered to the land losers.
R&R Entitlements for Project Displaced Families (PDFs):
• Provision of housing units in case of displacement :
1. If a house is lost in rural areas, a constructed house shall be provided as per
Indira Awas Yojana specifications; or if the family opts not to take the house, the
equivalent cost of the house may be offered instead.
2. If a house is lost in urban areas, a constructed house shall be provided, which
will be no less than 50 sqmts in plinth area; or if the family opts not to take the
house offered, it shall get a one-time financial assistance for house construction
which shall not be less than INR 1,50,000 / -
3. These benefits shall also be extended to any affected family which is without
homestead land and which has been residing in the area continuously for not less
than three years preceding the date of notification of the affected area
4. No family shall be given more than one house
• Subsistence Grant for Displaced Families: Each affected family which is displaced
form the land acquired shall be given a monthly subsistence allowance equivalent to
INR 3,000 per month for a period of year from the date of award.
• Transportation grant: Each affected family which is displaced shall get a onetime
financial assistance of INR 50,000/- as transportation cost for shifting of the family,
building materials, belongings and cattle.
• Stamp duty and registration fee :
1. The stamp duty and any other fees payable for registration of the land or house
allotted to the affected families shall be borne by the requiring body
2. The land for house allotted to the affected family shall be free from all
encumbrances
3. The land or house allotted may be in the joint names of wife and husband of the
affected family
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
12
Centre for Management and Social Research Development Support Specialists
Infrastructural Entitlements to Displaced families in Resettlement Colonies –
Schedule III : Every resettled area (Resettlement Colony) is to be provided with certain
infrastructural facilities. These facilities include roads, drainage, provision for drinking
water, grazing land, banks, post offices, public distribution outlets, etc.
Special provisions for Scheduled Castes and Scheduled Tribes displaced from
Scheduled Areas:
Scheduled Castes and Scheduled Tribes displaced from Scheduled Areas shall receive
an amount equivalent to INR 50,000 /- per family
• Families settled outside the district shall be entitled to an additional 25% R&R
benefits;
• Payment of one third of the compensation amount at very outset;
• Free land for community and social gatherings;
RFCTLARR (Removal of Difficulties) Order, 2015
In order to expedite land acquisition for infrastructure projects, the government
promulgated an ordinance in December 2014, amending certain provisions in the
RFCTLARR Act, 2013. Since the ordinance was to lapse, the second ordinance was
promulgated in May 2015, wherein infrastructure projects were exempted from (i) the
provisions of SIA; and (ii) the bar on acquisition of multi crop land . Further, through
the ordinance, the determination of compensation as per the First Schedule,
rehabilitation and resettlement provisions contained in the Second Schedule and
infrastructure amenities to be provided in resettlement sites as per the Third Schedule
became applicable to the exempted acts in the Fourth Schedule with effect from 1
January 2015. Since this second ordinance also was to lapse and the replacement bill
relating to the RFCTLARR (Amendment) Ordinance has been referred to the Joint
Committee of the Houses (Parliament) for examination, this order dated 28 August 2015
has been passed wherein the provisions of the RFCTLARR Act, relating to the
determination of compensation in accordance with the First Schedule, rehabilitation
and resettlement in accordance with the Second Schedule and infrastructure amenities
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
13
Centre for Management and Social Research Development Support Specialists
in accordance with the Third Schedule shall apply to all cases of land acquisition under
the enactments specified in the Fourth Schedule to the said Act with effect from 1
September 2015. Further, the exemption of SIA and acquisition of multi crop land for
infrastructure projects has been done away with; thereby SIA provisions become
applicable to Tandur Bypass Road project.
Tandur Bypass Road project Resettlement & Rehabilitation Principles
The Resettlement and Rehabilitation principles adopted for this project will provide
compensation, resettlement and rehabilitation assistance to all project affected persons
(loss of land, residences, business establishments and other such immovable
properties), including the informal dwellers / squatters in the corridor of impact
(COI).The basic resettlement principles and guidelines include:
• All PAPs are eligible for compensation for lost assets and livelihood irrespective
of ownership of title to land. However, a title will be required for payment of
compensation for land.
• All compensation will be at replacement value without considering depreciation
and salvage value.
• Cash compensation will be indexed for inflation.
• Where land acquisition is required, it will be carried out according to the
RFCTLARR, Act 2013 or direct purchase and in a way to minimize the adverse
impacts and to avoid displacement as much as possible.
• Cash compensation for the land, at replacement value, to households affected by
the loss of acquired land will be paid by the competent authority appointed
under LA and R&R Act, 2013.
• Non-titleholder (squatters and vulnerable encroachers) will be provided
replacement cost of their structures.
• Provision for multiple options for resettlement (self-relocation or assisted
relocation) of the affected residential structures, including informal
dwellers/squatters.
• Shifting assistance to the owners of residential structures and informal dwellers
/ squatter households and titleholders for shifting of household goods and
assets.
• Special measures and assistance for vulnerable groups.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
14
Centre for Management and Social Research Development Support Specialists
• PAPs will be consulted and will have opportunities to participate in planning
and implementing resettlement programs.
• Appropriate grievance redress mechanism will be established to ensure speedy
resolution of disputes, if any.
• All activities related to resettlement planning, implementation, and monitoring
would ensure involvement of women. Efforts will also be made to ensure that
vulnerable groups are included.
• Before taking possession of the acquired lands, the compensation will be paid to
the project affected.
• Provisions will be kept in the budget for those who were not present at the time
of enumeration. However, anyone moving into the project area after the cut-off
date will not be entitled to assistance.
• The Resettlement Plan will include a fully itemized budget and an
implementation schedule.
Telangana State Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2014
As required under Section 112 of the Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act 30 of 2013),
Government of Telangana has formulated its rules in line with RFCTLARR Act, 2013
and issued draft rules namely “Telangana State Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2014 on
19.12.2014. The draft rules of TSRFCTLARR 2014 are more or less same. However,
with regard to multiplication factor the act specifies that “The multiplication factor
under item(2) of the First Schedule for rural areas shall be 1.5 other than scheduled
areas and 2 for scheduled (tribal) areas subject to any further notification as may be
notified by Government”. The draft rules are still in the process of finalization.
Based on above two Acts an entitlement matrix has been prepared for Tandur Bypass
Road Project and presented in Chapter 7, Table. 7.1.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
15
Centre for Management and Social Research Development Support Specialists
Chapter Three
Approach and Methodology of SIA Introduction
This chapter presents the approach and methodology adopted for carrying out Social
Impact Assessment (SIA) in the affected villages. This includes need for SIA, scope of
SIA, approach and methodology, sample size, research tools employed, team
composition, data collection process, data sources used, schedule of consultations and
descriptions of gram sabhas conducted and their feedback.
Need for Social Impact Assessment (SIA)
To address the adverse impacts associated with the land acquisition and improve or at
least restore the living standards of the people affected, it is mandatory that the
appropriate government needs to undertake preparation of Social Impact Assessment
(SIA) and Social Impact Management Plan (SIMP) for the Affected Families (AFs) in
compliance with the of RFCTLARR Act, 2013. The proposed bypass road involves
expropriation of land from the private land owners/users. Construction of the bypass
road in this region will have significant positive impacts, but they may simultaneously
also bring negative impacts on nearby communities if proper precaution is not taken
during design and implementation stage of the project. Acquisition of land may also
cause social disruption and economic loss for Project Affected Families (PAFs). It is
therefore important that disturbances and losses of PAFs due to project are addressed
through SIA and SIMP.
Scope of SIA Study
In this context, the task of carrying out Social Impact Assessment (SIA) and Preparation
of Social Impact Management Plan (SIMP) for project has been entrusted to the Centre
for Management and Social Research, Hyderabad by the District Revenue Development
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
16
Centre for Management and Social Research Development Support Specialists
Authority, Vikarabad, vide letter No. Prcgs. No. G/127/2017 dated 13/04/2017. The
scope of the present SIA is to study :
1. Area of impact under the proposed project, including both land to be acquired
and area that will be affected by the environmental, social or other impacts of the
project.
2. Quantity and location of the land proposed to be acquired for the project.
3. The land proposed for acquisition is the bare minimum required.
4. Possible alternative sites for the project and their feasibility.
5. Whether land proposed for acquisition in scheduled are is a demonstrable last
resort.
6. The possibility of use of any public, unutilized land for the project and whether
such land is under occupation.
7. Nature of the land, the irrigation coverage for the said land and the cropping
pattern.
8. The special provisions with respect to food security have been adhered to in
proposed land acquisition.
9. Size of holdings, ownership patterns, land distribution, number of residential
houses, public and private infrastructures and assets.
10. Land prices and recent changes in ownership, transfer and use of lands over the
last three years.
11. Socio-economic survey of displaced / affected families.
Approach and Methodology
The objective of the SIA study is to have a complete understanding of socio-economic
conditions of the land losing families, displaced families, inventory of public assets
affected to identify social costs involved and to prepare social impact management plan
(SIMP) to ensure that the project addresses the adverse impacts on the livelihood of the
people and that nobody is left worse off after implementing resettlement action plan
and those affected have access to project benefits, during project construction as well as
operation stage. The SIA study followed both qualitative and quantitative approaches
and employed various research tools and techniques like Census/Socio-economic
interview schedule, focus group discussions (FGDs), in-depth interviews, and transect
walks.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
17
Centre for Management and Social Research Development Support Specialists
Sample size
There should be a comprehensive understanding of impacts on the families who will be
affected by proposed land acquisition. In the present scenario, the concept of a
representative sample is not relevant. Therefore, entire population of families who are
losing their land or dwelling or both is considered for the study. The study covered 160
households for Census survey and 143 households for socio-economic survey of 189
households as per the list provided by the district administration.
Research Tools Employed
The study involved collection of both primary and secondary data. Primary data was
collected through both qualitative and quantitative approaches. For quantitative data
collection two structured questionnaires – 1.Census survey questionnaire 2. Socio-
economic survey questionnaire were administered to all the project affected persons
and for qualitative information check lists were used for community consultations,
focus group discussions, in-depth interviews, and transect walks carried out during the
survey. Secondary data such as Land Plan Schedules, district hand book, relevant
policy documents of both state and central government, road design maps and detailed
project report were reviewed. Following table provides details of tools/methods used
and information collected from various stakeholders:
Table 3.1 : Tools and methods used for data collection
S.No Stakeholders Tool/Method used Information collected
1. Head of Project Affected Family
Socio-economic survey questionnaire
Identification of the PAFs, Socio-economic details and household information
2. Head of Project Affected Family
Census survey questionnaire
Details of land, structure and other assets affected
3. Project Affected Women Checklist for Focused Group Discussion (FGD)
Views on benefits of the project, dependency on lands, direct or indirect impact on women due to land acquisition, loss of livelihood, migration, impact on living standards, suggestions to minimize impacts, economic rehabilitation
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
18
Centre for Management and Social Research Development Support Specialists
Table 3.1 : Tools and methods used for data collection
S.No Stakeholders Tool/Method used Information collected
measures preferred and relocation issues
3. Vulnerable Groups (SC/ST PAFs)
Checklist for Focused Group Discussion (FGD)
Views on benefits of the project, dependency on lands, direct or indirect impacts perceived due to land acquisition, loss of livelihood, migration, impact on living standards, suggestions to minimize impacts, economic rehabilitation measures preferred and anticipated social issues due to relocation.
4. Members of Panchayati Raj Institutions and Community
Checklists for consultations
Perceptions on proposed project, advantages disadvantages, positive and negative impacts of the project, changes in living standards, impact on community organizations, changes in access to basic amenities, impact on common properties and civic amenities and their suggestions for mitigation of adverse impacts.
5. Officials of Revenue Department
FGDs List of project affected persons, project background, land acquisition details, compensation and R&R benefits, key contacts and village information.
6 Gram Panchayat office, MRO, MDO, DEO.
Check list for Village profile
Collection of data on demographic details, public utilities, government programmes/schemes, educational institutions and land details
SIA and Data Collection Process
The study followed sequential process consisting of the following four phases presented
in Fig. 3.1 :
1. Phase – I : Pre-survey activities 2. Phase – II : Survey Activities 3. Phase – III : Data analysis and information synthesis 4. Phase – IV : Post survey activiteis and reporting
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
19
Centre for Management and Social Research Development Support Specialists
FIG 3.1: PROCESS FLOW CHART FOR THE SIA STUDY
PHASE-I: PRE-SURVEY ACTIVITIES – FAMILIARIZATION AND GROUNDING
• Team Mobilization
• Discussions with officials
• Collection of relevant documents
• Detailed Approach & Methodology
• Preparation of survey instruments
• Reconnaissance field visit and testing of
survey instruments
• Finalization of questionnaires
• Finalisation of check lists
• Finalisation of field work plan
• Training of the field staff
• Deployment of field teams
• Information dissemination in villages
PHASE-II : SURVEY ACTIVITIES
SOCIO-ECONOMIC SURVEY
• Survey of Project Affected Families (PAFs)
• Supervision and Field verification of data
• Field level data editing
• Data checking
FGD / CONSULTATIONS
• FGDs with stakeholders
• Public Consultation meetings with PAFs
• Collection of village profile data
PHASE-III :DATA ANALYSIS AND INFORMATION SYNTHESIS
DATA ENTRY AND ANALYSIS
• Data coding, cleaning and entry
• Finalization of report structure
• Analyzing survey results
• Preparation of Draft SIA Report
PREPARATION OF DRAFT REPORT
• Content analysis
• Report writing
• Prepare and submission of the SIA report
Output: Draft Report
Output: Final Report
PHASE-IV : POST SURVEY ACTIVITIES,ANALYSIS AND REPORTING
KEY STAKEHOLDER CONSULTATION ON DRAFT
REPORT
• Discussions with officials on Draft report
• Conducting Gram Sabhas/Public hearing on
Draft Report
• Incorporation of comments and suggestions
from client/PAFs
FINAL REPORT PREPARATION
• Expert review of the report
• Finalisation of report
• Submission of Final SIA and SIMP Report
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
20
Centre for Management and Social Research Development Support Specialists
Phase – I: Pre-Survey Activities
Activity 1 : Team mobilization
As soon as the contract signing was completed a multidisciplinary team consisting of
Social Scientist, Resettlement and Rehabilitation expert, gender expert, field survey
coordinator and field investigators, database management expert, data entry operators
was mobilized in accordance with the study requirements. A team of experienced
professionals along with a number of field staff were engaged in conducting the surveys
and consultations. Team structure, profile and tasks carried by the staff is presented in
below Table 3.2.
Table 3.2 : SIA team and tasks carried out
Sl. No.
Name Designation Activities carried out
1 V. Venkata Ramana, MA Sociology Team Leader & Social Expert
Study design, guidance to team, quality check, discussions with stakeholders, training, pilot study and report writing
2 B. Karthik M.A. Sociology R&R Expert & Field Coordinator
Coordinating field investigators, quality check of questionnaires, field planning, consultations, FGDs, collection of secondary data, field planning and overall incharge of field operations
3 Jyotishri Konda M A Sociology Gender Expert
Conducting FGDs with women, report writing, interactions with PAPs
4 M. Phanibhushan M.Sc. PGDCA.
DBMS Management and Statistical Expert
Design and development of data entry application, data analysis, data cleaning, quality check, database creation, tabulation plan, safe storage of data, preparation of profile of PAPs
9 G. Venkatesh M.Sc.
Photography, Videography and Documentation expert
Video recording, documentation, collection of secondary data, data quality checking and data editing.
5 Shaik Fuzail Ahmed B.Com.
Field Investigator and Data entry operator
Data collection, editing, data entry
6 Kalaam, BA,LLB. Field Investigator and Data entry Data collection, editing, data
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
21
Centre for Management and Social Research Development Support Specialists
operator entry
7 Syed Shakeeb Hussaini, B.A.
Field Investigator and Data entry operator
Data collection, editing, data entry
8 Shaik Nehal Ahmed, B.Com.
Field Investigator and Data entry operator
Data collection, editing, data entry
10 M. Praveen Kumar B.Sc.
Field Investigator and Data entry operator
Data collection, editing, data entry
Activity 2: Initial meeting with officials
An initial meeting was conducted with the key officials of Revenue Department (Sub-
collector, DRO, MRO, DMRO, VRO, RI and Surveyors) and collected details of the
status of land acquisition, R&R and list of affected villages and families with the view
to:
a) Understand the project locations and boundaries
b) Collect information on key contact persons who would be required to be contacted during the study/field work
c) Request assistance and cooperation of relevant agencies and of other stakeholders, as the case may be
Initial meeting with officials of Revenue Department
Discussions with DRO, Vikarabad Discussions with Tahsildar- Tandur Mandal
Activity 3: Review of Project Literature
The study involves collection and review of literature and documents which are
available at different sources. The review helped the team in conceptualizing and
designing the study and also in identifying key stakeholders. Some of the documents
reviewed include the following:
1) Land Acquisition Plans
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
22
Centre for Management and Social Research Development Support Specialists
2) The Right to Fair Compensation and Transparency in Land Acquisition 2013 3) Primary Census Abstract, District Census Handbook 2011 4) District wise Socio-Economic Indicators (Directorate of Economics & Statistics,
Government of Telangana) 5) Acts and Policies of Government of India and Government of Telangana related
to R&R and Land acquisition.
Activity 4: Developing Study Methods and Instruments for the Study
According to the study requirement, a range of instruments were designed and used for
the study. The core instruments include:
Census/Socio-economic Survey Household Questionnaire for Project Affected Families (PAFs):
A survey schedule was prepared to capture the socio-economic status of affected
families as per the guidelines mentioned in Chapter II–Sec. 3(i) of RFCTLARR Act
(Social Impact Assessment and Consent) rules. The household survey questionnaire
was administered to all the available PAFs to obtain socio-economic profile of the PAFs.
The questionnaire and checklists used are provided in Annexure I.
Checklists for conducting consultations with Panchayat members, FGD with Women and
Community: Separate checklists were prepared for Gram Sabhas, Focus Group
Discussions and in depth interviews with each project stakeholder to be covered to
gather required information such as awareness levels of people on project benefits,
compensation and R&R issues, impact on livelihoods, impacts on individual assets,
impact on common properties and their alternative source of livelihood incase of
displacement.
Activity 5: Rapid reconnaissance to plan and schedule field activities
The initial understanding gained through a review of secondary resources and initial
discussions was followed up by a rapid preliminary field visit to affected villages was
made on 5th April, 2017 primarily to familiarize with the ground reality with respect to
the socio-economic and livelihood conditions of the Affected Families. Tentative dates
for carrying out consultations and socio-economic survey was finalized in consultation
with Gram Pachayats during the second visit on 12th April, 2017. This enabled us to
scope the activities and prepare the ground for a perfect launching of consultations and
census/socio-economic survey. This protocol helped the team in fine-tuning the survey
tools such as questionnaires and checklists. After this visit a detailed action plan was
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
23
Centre for Management and Social Research Development Support Specialists
provided to Sub-collector. Following the timelines mentioned in the action plan, SIA
notification was given by the district administration to the concerned gram panchayats,
revenue officials and concerned departments. The notification, clearly explains the
proposed project and the schedule of SIA. A copy of notification is attached as
Annexure-II
Activity 6: Scoping and other Pre-survey Activities
Recruitment and training of field personnel
During the same period, the required field researchers and investigators were recruited. Two day field based training was conducted for field staff - field supervisors, investigators at Hyderabad by the key experts of CMSR.
Training of Investigators
Phase- II: Survey Activities
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
24
Centre for Management and Social Research Development Support Specialists
Activity 7: Conducting the Census /Socio-economic Survey and Consultations
Following the testing of study instruments a full-fledged survey (100%) and
consultations was undertaken from 19th to 22nd April, 2017 by actually collecting
data/information through the study instruments from all the available project affected
persons. In addition to survey, stakeholder consultations were also carried out to cross
check the quantitative data. Through the Census /socio-economic survey the following
information was captured:
• Socio-Economic Profile: Number and age profile of the families/social /gender
category of families, literacy levels, occupation and monthly income levels, assets
owned or occupied and affected, skill set;
• Access to basic services, health status and food security;
• Participation in development schemes of the government;
• Access to employment, wage labour; Ownership of livestock, outstanding debts;
• Vulnerable persons/families: (poor, SC/ST, women headed, aged/infirm, physically
or mentally challenged) with socio-economic profile;
• Village profile, existing infrastructure facilities etc.
• Overall awareness and perceptions about the project
• Relocation options if displaced
• Compensation, Rehabilitation and resettlement options
Photo Plate 3.1 : Photographic evidence of Socio-economic Survey
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
25
Centre for Management and Social Research Development Support Specialists
Gram Sabhas in affected villages : Gram Sambhas were organized in Kokat Gram
Panchayat for Kokat and Rasulpur villages on 19th April, Antaram on 20th April, and in
Chengole village on 21st April, 2017. A separate Focused Group Discussion was also
conducted in Antaram Tanda with vulnerable group on 22nd April, 2017. District
administration circulated SIA notifications in concerned gram panchayats indicating the
schedule of gram sabhas and socio-economic survey. These notifications were also
posted on the notices boards of concerned gram panchayats.
Schedule of Gram Sabhas conducted Sl. No.
Mandal Village Venue Date No of PAPs attended
1 Yalal Kokat and Rasulpur Gram Panchayat
19.04.2017 36
2 Tandur Antram 20.04.2017 30
3 Tandur Chengole 21.04.2017 31
Photo Plate 3.2 : Gram Sabhas
Gram Sabha in Kokat and Rasulpur villages 19.04.2017
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
26
Centre for Management and Social Research Development Support Specialists
Gram Sabha in Antaram village Dt 20.04.2017
Gram Sabha in Chengole village Dt. 21.04.2017
Focussed Group Discussions with the stakeholders : As the project involved a variety of
stakeholders, such as the Panchayati Raj Institutions, and village level bodies,
vulnerable affected community. Consultations were held with all these institutions on
issues and impacts of the project. Some of the stakeholders who were consulted include
following:
o Gram Panchayat members
o Revenue officials
o R&B Department
o Peoples representatives
o Project affected persons - Vulnerable
FGD with R&B officials FGD with PAPs at Chengoloe
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
27
Centre for Management and Social Research Development Support Specialists
FGDs at Antaram Thanda
Phase III: Post Survey Activities
Activity 9: Data Entry and Analysis
Database Development
A data entry program was developed in EPI Software for the entry of the data collected
and to create a data base of the PAPs.
Data Entry and Management
The quantitative data collected by the site team from the field was entered in the
system. Once the data entered, the consultants performed a cleaning exercise in the data
set. In spite of introducing various software validations and controls, still there were
minor errors in the data collected. All such errors were thoroughly checked and
corrected before uploading the data to server for further analysis.
Data Analysis
The information collected through structured interviews and questionnaires were
systematically coded, validated, analyzed and tabulated. Wherever required, the
observations were also supported from the information collected through desk
research. The tabulation plan, covering every aspect of the study was designed with
suitable checks by using cross verification parameters. The data was first entered in
data entry package in EPI and then exported to SPSS (Statistical Package for Social
Sciences). The entered data was once again cleaned using the appropriate protocols.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
28
Centre for Management and Social Research Development Support Specialists
Activity 10: Preparation of Draft Reports
A draft Social Impact and Resettlement Action Plan has been prepared based on the
survey data, literature review and consultations. Collected data was finalised with all
the changes, analysis of collected data was done for different sections as per the SIA,
GoT guidelines presented in Chapter 3 as per rule 3(3), rule (5), (6), (7) and rule 17 in
Form – II. After approval of the preliminary report by the concerned department, the
report will be presented to the stake holders in an organised meeting to get the
feedbacks, ensuring transparency in the proceeding. The report once finalized will be
presented to the authorities for the final approval.
Activity 11 : Develop a mitigation plan
The objective of social impact assessment is to improve or at least restore the living
standards the land losers. Social impact assessment helps organizations to plan better,
implement more effectively, and successfully bring initiatives to scale. Assessment also
facilitates accountability, supports stakeholder communication, and helps guide the
allocation of scarce resources. Based on the output and results of the analysis,
mitigation measures will be incorporated. Consultations helped to identify PAPs
concerns and reactions to the project which will be addressed through an appropriate
mitigation plan.
Activity 12 : Social Impact Management plan (SIMP):
The SIMP will be prepared based on the findings of the census and socio economic
survey and consultations. This includes, entitlements, socio economic characteristics of
the project affected families, institutional mechanisms and implementation schedules,
budgets, assessment of feasible income restoration mechanisms, grievance redress
mechanism, and coordination of implementation in conjunction with civil works
procurement and construction schedules and internal and external monitoring
mechanisms. The SIMP will be structured as per the outline in RTFCTLARR, 2013 and
detailed as needed depending upon the magnitude and nature of impacts. The impacts
and mitigation measures have been presented to coordinate with the procurement and
construction schedules of the project.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
29
Centre for Management and Social Research Development Support Specialists
Activity 13 : Public Hearing and Final Report
A public hearing will be conducted to present the findings from the draft SIA and SIMP
report after intimating the affected villages. Final report will be submitted after
incorporating the inputs from the public hearing.
Schedule of SIA
Details showing the date wise work undertaken for Social Impact Assessment (SIA) Tandur Bypass Road project.
S.No. Details Date of completion Status
1 Meeting with DRO /DRDO 05.04.2017 Completed
2 Constitution of SIA team 06.04.2017 Completed
2 Meeting with District Collector and Sub-
collector 12.04.2017 Completed
3 Reconnaissance field visit by CMSR
professionals 12.04.217 Completed
4 Development of survey schedules & pilot
study 13.04.2017 Completed
5 Training/Capacity building to SIA team 14.04.2017 Completed
6 Public consultation meetings /FGDs 19th
to 21st April, 2017 Completed
9 Socio Economic Survey / Data collection 19th
to 24th
April, 2017 Completed
11 Data entry & analysis 25th
to 28th
April Completed
12 Draft report submission (English) 12.05.2017 Completed
13 Draft report submission (Telugu) 15.05.2017
14 Review of report by officials 13.05.2017
15 Issue of notification for Public Hearing
(Gram Sabha) to present SIA findings 15.05.2017
16 Public hearing / Gram Sabha 25.05.2017 to 27.05.2017
17 Draft Final SIA and SIMP Report
submission in English and Telugu 30.05.2017
18 Review of SIA and SIMP by Expert
Committee and comments 5.06.2017
19
Final SIA and SIMP Report submission
after incorporating comments and
suggestions by expert committee
10.06.2017
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
30
Centre for Management and Social Research Development Support Specialists
Limitations of the study
The field teams faced numerous challenges during data collection process.
1. List provided by the Revenue Department was not finalized and there were
discrepancies with regard to land proposed for acquisition and survey numbers
2. Plot owners details were not available. Plot owners are not available as they
spread across Vikarabad, Hyderabad, Karnataka and Tandur
3. Some PAFs showed reluctance to give personal information
4. In Antaram and Chengole villages enjoyer of the land and owner is different -
this created confusion to the land owners.
5. Timeline for completing the study in 1 month became challenging to deliver the
output
Over view of information and data sources used
• The right to fair compensation and transparency in land acquisition,
rehabilitation and resettlement act, 2013.
• Telangana State Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Rules, 2014
• Secondary information from Sub-collector’s office, Tandur, Mandal Revenue
Offices, Mandal Parishad Development Offices, R&B Department, District sub-
registrar office, Mandal Education Departments, Agriculture department and
websites.
• Social Impact Assessment & RAP for Package-1 : 4 lane bridge over River Ganga
near Sahibgunj in Jharkhand and Construction of Manihari Bypass in Bihar,
carried out by CMSR.
• A Comprehensive Guide for Social Impact Assessment, 2006, Centre for good
Governance.
• District profile, Vikarabad at www.vikarabad.telangana.gov.in
• Registration and Stamps department, Government of Telangana,
www.registration.telangana.gov.in
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
31
Centre for Management and Social Research Development Support Specialists
Findings of Gram Sabha/Public Consultations
Consultations were carried out at individual as well as Village level from 19th to 21st
April, 2017. 3 Gram Sabhas were conducted where in PAFs were sensitized about the
proposed bypass road project and provisions of RFCTLARR Act. Apart from Gram
Sabhas conducted walk-through informal group consultation at affected places along
the alignment, FGD with different groups of affected people including, In-depth
individual interviews, discussions and interviews with key informants, sharing the
opinion and preferences of the PAPs. Important issues were discussed during
consultation with the stakeholders were related to loss of livelihood, compensation for
acquired land and properties, provision of job in the project. Concerned Tehsildars,
VROs, RIs, Surveyors, Gram Panchayat members, Surpanch and PAFs were present
during the consultations. Entire proceedings of the Gram Sabha was video recorded
and attendance of the participants was also taken. Proceedings and attendance sheet
has been enclosed as Annexure-III. Important issues raised during these consultations
are presented below.
KOKAT AND RASULPUR VILLAGES :
1. In Kokat and Rasulpur villages most of the PAFs were un-aware of how much
land they are going to lose. They requested to provide details of extent of land
proposed for acquisition from each survey number and provision of
compensation.
Response: During the meeting, Tahsildar explained to all the PAFs about the
extent of land to be acquired in each survey number. The process of
compensation as per RFCTLARR Act, was explained by social expert.
2. PAFs expressed that, due to construction of bypass most of the land rates in
surrounding areas have been increased and it is difficult for the PAFs to
purchase lands in the vicinity if compensation is provided as per Government
rate. Compensation must be provided as per private market rates so that farmers
can buy lands elsewhere. Expected land rate is Rs. 50 lakhs per acre.
Response : Compensation will be determined by the competent authority as per
the procedure laid down in RFCTLARR Act, 2013. Compensation and R&R
benefits will be given as per the Act.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
32
Centre for Management and Social Research Development Support Specialists
3. In previous land acquisition the lands acquired from farmers were not utilized
for the public purpose. These lands were sold to private parties for 8 lakhs per
acre due to which farmers were deprived off. Therefore, PAFs requested to
provide land for land.
Responses : PAFs clarified that there is no scope for such things as the land will
be acquired as per the new Act.
4. Small farmer PAFs shared that land for land may be provided as their families
are entirely depended on the lands and if total land is acquired they do not have
any source of livelihood especially for widows and other vulnerable categories.
Responses : Appropriate action plan will be prepared to address this issue.
5. Farmers expressed that if their existing lands converted into plots, they may get
Rs. 1000/- to 3000/- per square yard. In such cases land costs will be more than
Rs.50 to 60 lakhs per acre. What compensation government would like to pay for
this project.?
Response : Market rate will be decided by the competent authority after detailed
investigation and SIA study. These details will be shared with public in
forthcoming meetings.
6. Around 11 ST families who are living in Bashirmiya Thanda shared that the
extent of lands owned by them is between half acre and one acre and they will
become land less if lands are acquired. They cannot afford to buy lands with the
compensation provided by government therefore lands may provided in the
Government land in Survey No.64 equal to the land acquired from them. There is
no other alternative occupation. Agriculture is the main source of income. Cash
compensation may be misused by the families.
Response : Stated that this will be brought to the notice of concerned authority
and issue will be addressed through proper mitigation plan.
7. It has been shared by the PAFs that, corrections to be made in total extent of land
to be acquired in the land acquisition plans and maps.
Response : Tahsildar clarified that it is a tentative plan and at the time of final
notification accurate details will be shared with PAFs.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
33
Centre for Management and Social Research Development Support Specialists
8. Majority PAFs stated that, it is very difficult to purchase same land. They are not
opposing the acquisition but requesting for higher compensation to all PAFs.
9. During the consultations it was also requested to show suitable livelihood
opportunities and income to the land losers in case land acquisition is
mandatory.
Response : Explained the process of compensation and informed PAFs that the
compensation is yet be decided. IGA training will be provided to livelihood
losers and other options also will be explored to address the issue.
10. One of the PAP in Kokat stated a borewell which is major source of irrigation is
getting affected. Alternative source of irrigation may be provided before
acquiring the land.
Response: Explained that compensation will be provided for the affected
borewells in the agriculture lands as per the Act.
11. Most of the farmers, expressed that the alignment is passing in between their
agriculture lands due to which the remaining lands on the both sides will be
unviable for cultivation. Requested to acquire lands from one side to help
continue their cultivation. Some of the small and marginal farmers requested to
acquire remaining land and demanded compensation for the total land.
Response: Farmers concerns were recorded and assured that this will be
brought to the notice of higher officials. It was also advised PAPs to keep the
remaining land if any as land rates along the bypass will be increased in future.
ANTARAM VILLAGE
1. In Antaram village, PAPs expectation for land compensation is between Rs. 15
and 20 lakhs per acre. They wanted to know the compensation for patta lands
and assigned lands.
2. Some opined that the land rates as per the government registration value will be very less. Therefore land rates may be considered as per the market rate. Minimum Rs. 30 lakhs may be given per acre as compensation.
Response: Explained the process adopted for determination of market value and
compensation will be paid as per the RFCTLARR Act.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
34
Centre for Management and Social Research Development Support Specialists
3. Suggested to change the alignment as farmer in the villages own very small piece
of irrigated and cultivable lands and their livelihood is depended on these lands.
Government/Forest lands existing near these agriculture lands may be acquired
and expressed that they are not going to give lands for the project.
Response: Out of the three alternative alignments explored, the present
alignment has been found suitable as it involves no displacement of residential
structures and causes minimum impacts. However, it was informed the PAPs
that their concerns were noted down and conveyed to the higher officials for
addressing the issue.
4. Temple and a structure of holy cross adjacent to proposed bypass is being
affected due to land acquisition. Alignment may be changed to avoid these structures.
Response: As per the RFCTLARR Act, temples or any religious structures affected will be reconstructed at suitable locations as suggested by the PAPs. Change of alignment is not required for this sake.
5. Will Annuity of Rs. 5 lakhs be given to all the PAPs? Is it including the compensation?
Response: Annuity of Rs. 5 lakhs will be given to all eligible PAPs as decided by the Government. It is R&R benefit and excluding the compensation.
6. PAPs expressed that they are not against the project but higher compensation may be given which is acceptable to them. Proper rehabilitation may be provided to those who are adversely affected.
Response: Justifiable compensatory measures will be taken as per the Act.
7. The proposed alignment passes from the centre of agriculture lands due this the
remaining lands will become un-usable. This issue may be resolved.
8. In Antaram Tanda, PAFs expressed that there is an important bore which is a
major source of irrigation for 11 families who are cultivating. If this is affected all
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
35
Centre for Management and Social Research Development Support Specialists
the 11 families will lose their livelihood. This bore may be excluding from the alignment.
Response: Points noted and information will be conveyed to higher officials to take appropriate measures to minimize the impacts.
Conclusion : PAPs are ready to provide lands provided government gives acceptable compensation to all. If compensation is not paid as per the aspirations of the PAPs the alignment may be changed to available government lands.
CHENGOLE VILLAGE
1. Alignment is passing over private tombs (approximately 10 Nos) in the agriculture lands therefore alignemnt may be changed to avoid them. Response: Noted contents appropriate measures will be taken.
2. One of the PAPs who lost his 40 acres of land in Allapur project stated that
compensation was insufficient. Sufficient compesantion may be paid for the Tandur bypass project. Response: As per RFCTLARR Act fair compensation and R&R assistance will be given to eligible PAPs.
3. In survey No. 129 two bores will be affected due to land acquisition which are
major source of irrigation. Can these will be avoided and preserved?
Response: According to RFCTLARR, cost of the bore will be provided with 100% solatium.
4. Most of the PAPs in Chengole state that land may be acquired from one side of the agiculture field to keep the other portion useful for cultivation.
Response: Noted contents appropriate measures will be taken
5. About 20 to 30 PAPs among the expressed that due to recent survey by revenue department there is a difference in survey numbers causing possession of the land by some one and enjoyer is some one else. In such cases how the compensation can be paid?
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
36
Centre for Management and Social Research Development Support Specialists
Response: Tahsildar replied that this issue has to be resolved through mutual understanding by PAPs. Compensation will be paid to the person who is in position.
6. There is a mistake in survey number. Instead of survey no. 70 it was printed as
survey no.7 due to this notices are going to wrong persons? Response: Tahsildar replied that mutation has to be done through online payment. Corrections will be done.
7. How the land compensation will be determined?
Response: Explained the process adopted for determination of market value as per Section 26,27,28,29,30 of RFCTLARR Act and compensation will be paid accordingly.
8. Is there any provision for employment to the land losers families?
Response: This project is not a job creating project. Temporary employment opportunities will be there during project construction period. Those who are interested may be given opportunity. Annuity of Rs. 5 lakhs will be given to eligible PAFs as per the Act.
9. Land compensation may be determined same to all the four affected villages.
Response: This may not be possible as market rates vary depending on the
nature of the land, village and distance from urban center etc. However, it will be brought to the notice of higher officials.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
37
Centre for Management and Social Research Development Support Specialists
Chapter Four
Land Assessment
Introduction
This chapter presents land assessment which includes area of impact, total land requirement for the project, present use of land, location of land, irrigation, cropping pattern, land holding size, ownership patterns, land prices and recent changes in ownership.
Area of Impact
Land acquisition of the proposed Tandur Bypass Road is being carried out as per
provisions of the Right to Fair Compensation and Transparency in Land Acquisition
and Rehabilitation and Resettlement 2013. Land acquisition has been proposed from
two Mandals - Yalal and Tandur. The impact of land acquisition is on Kokat, Rasulpur,
Antaram and Chengole villages and adjoining Thandas. The design has been made to
keep land requirements to the barest minimum possible by realigning the design away
from private property and human habitation. Details of village wise extent of land to be
acquired are presented in Table 4.1 below. Village wise land acquisition maps have
been prepared and they are appended as Annexure-IV.
Table 4.1 Extent of Land proposed for aquisition
Sl. No.
Name of Village Extent of land required (Acres-Guntas)
Total No of Households
No. of Survey Numbers
1 Kokat 49.06 68 30
2 Rasulpur 5.35 08 08
3 Antaram 21.11 ½ 54 36
4 Chengole 23.16 59 61
Total 99.28½ 189 105
Source : Revenue Department, Yalal and Tandur Mandals.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
38
Centre for Management and Social Research Development Support Specialists
Village wise Survey numbers and land to be acquired
Table 4.2 below presents details of survey numbers and land to be acquired.
Table 4.2 Details of survey No’s and to be acquired Land for the project
Project Affected Villages
Survey Numbers Private Land
(In A-G)
Govt. Land
(In A-G)
Forest Land
(In A-G)
Total (In A-G)
Kokat
307/2/1, 307/2/2, 278/2, 306/2/1, 306/2/2, 305/2, 299/2/1, 299/2/2, 299/2/3, 299/2/4, 299/2/5, 298/2/1, 298/2/2, 298/2/3, 297/2, 289/2, 230/2/1, 230/2/2, 231/2, 232/2, 214/2, 215/2, 216/2, 213/2/1, 213/2/2, 342/2, 4/2, 3/2, 10/2, 11/2/1, 11/2/2, 12/2, 13/2/1, 13/2/2, 52/2/1,52/2/2,52/2/3,52/2
/4,52/2/5,52/2/6,52/2/7,5
2/2/8,52/2/9,52/2/10,52/2
/11,52/2/12,52/2/13,
52/2/14, 52/2/15,
52/2/16,52/2/17,52/2/18,5
2/2/19,52/2/20,52/2/21,52
/2/22,52/2/23, 63/2/1,
63/2/2, 61/2/1, 61/2/2,
61/2/3, 61/2/4, 61/2/5,
61/2/6, 60/2/1, 60/2/2,
60/2/3, 60/2/4, 60/2/5,
60/2/6, 60/2/7, 64/2/1,
64/2/2, 72/2, 73/2/1,
73/2/2, 73/2/3,325/2
38.18 10.28 0 49.06
Rasulpur 2/2,4/2/1,4/2/2, 6/2/1, 6/2/3, 7/2/1, 7/2/2, 8/2
5.35 0 0 5.35
Antaram
290/2, 289/2, 288/2, 287/2, 293/2, 286/2, 285/2, 302/2, 307/2, 308/2, 308/3, 309/2, 38/2, 31/2, 32/2, 30/2,
20.11½ 1.00 0 21.11 ½
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
39
Centre for Management and Social Research Development Support Specialists
Table 4.2 Details of survey No’s and to be acquired Land for the project
Project Affected Villages
Survey Numbers Private Land
(In A-G)
Govt. Land
(In A-G)
Forest Land
(In A-G)
Total (In A-G)
26/2, 27/2, 28/2, 25/2, 23/2, 62/2, 63/2, 68/2, 65/2, 66/2, 76/2, 77/2, 79/2, 83/2, 82/2, 86/2, 129/2, 130/2, 132/2, 134/2, 134/3, 58/16, 58/19.
Chengole
134/2, 135/2/1, 135/2/2,135/2/3, 136/2/1, 136/2/2, 136/2/3,178/2, 137/2, 138/2/1, 138/2/2, 138/2/3, 138/2/3, 138/2/4, 138/2/5, 172/2, 169/2, 170/2, 171/2/1, 171/2/2, 95/2, 94/2, 189/2/1, 189/2/2, 189/2/3, 189/2/4, 190/2, 72/2, 71/2/1, 71/2/2, 70/2/1, 70/2/2, 70/2/3, 69/2/1, 69/2/2, 69/2/3, 69/2/4, 197/2, 68/2/1, 68/2/2, 68/2/3, 195/2/1, 195/2/2, 196/2/1, 196/2/2, 200/2, 199/2/1, 199/2/2, 198/2/1, 198/2/2, 265/2, 264/2/1, 264/2/2, 264/2/3, 264/2/4, 264/2/5, 260/2/1, 260/2/2, 260/2/3, 260/2/4, 260/2/5, 261/2/1, 261/2/2, 250/2, 248/2,
23.02 0.14 0 23.16
Total (In acres) 88.00 ½ 11.28 0 99.28 ½
Source : Revenue Department, Tandur and Yalal Mandal
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
40
Centre for Management and Social Research Development Support Specialists
Fig. 4.1& 4.2 : Land Acquisition Map for Kokat and Rasulpur villages
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
41
Centre for Management and Social Research Development Support Specialists
Fig 4.3 Land Acquisition Map for Antaram Village
Fig. 4.4 : Land Acquisition Map for Chengole village
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
42
Centre for Management and Social Research Development Support Specialists
Type and utilisation of Land proposed for Acquisition
A total acres 99.28 ½ guntas of land is proposed for acquisition, out of which acres 88.00
½ guntas belong to private/pata land and acres 11.28 guntas of land belongs to
government. The land is being utilized for agriculture/horticulture purpose, residential
plots, PWD/R&B roads and water tank. In Survey no 10 (3.35), 12 (2.11) & 52 in Kokat
and Survey no. 5 (27 Guntas) a total of acres 6.33 guntas of land has been made into
plots and sold to various private parties. From the table 4.2 above it can be noted that
highest volume of 49.06 acres of land is required from Kokat Village and lowest 5.35 is
from Rasulpur. From the table 4.3 below it is evident that most of the land is being
utilized for agriculture purposes.
Table 4.3 : Usage of land in the Affected Villages by Number of Surveyed Households
Sl.No. Village
Agricultural Non-agricultural Total
No. of HH % No. of HH % No. of HH %
1 Kokat 66 42.3 4 100.0 70 43.8
2 Rasulpur 2 1.3 0 0.0 2 1.3
3 Antaram 41 26.3 0 0.0 41 25.6
4 Chengole 47 30.1 0 0.0 47 29.4
Total 156 100.0 4 100.0 160 100.0
Land holding type (Joint and Individual)
Table No.4.4 below gives details of the nature of holdings. On the basis of census survey
it was observed that approximately 160 households were likely to be affected, as their
land/house/firm is to be acquired for the project. Out of 105 survey Nos, census survey
identified 147 households are single holders and 13 are joint holders. In total 189 Title
Holders (TH) are there as per the list of which census survey covered 160 households.
Table 4.4 : Land holding type on listed survey NOs
Sl. No
Category Project affected areas/Villages Total of 4
Villages Kokat Rasulpur Antaram Chengole
1 Total Survey Nos 30 8 36 31 105
2 Single Holding 65 2 36 44 147
3 Joint Holding 5 0 5 3 13
4 Title Holders (Nos)
70 2 41 47 160
5 Non-Title holders 0 0 0 0 0
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
43
Centre for Management and Social Research Development Support Specialists
Size of land to be acquired
From the table 4.5 it is evident that nearly 87% of the affected families are losing
agriclture land upto 1 acre. In this category majority of affected families are from Kokat
followed by Chengole. In the next category 11.6 percent of affected families are losing
land more than 1 to 2.5 acres. In this category Kokat village accounts for highest
number of families (10). In category >2.5 to 5 acres, total number of families affected is
1.3 percent. In the category 5 acres and above, a very small 0.6 percent is noted - only 1
family from Kokat village.
Table 4.5: Size of the Land Proposed for Acquisition
Extent of Land lost (Acres)
Kokat Rasulpura Antharam Chengole Total
No of HH %
No of
HH % No of HH %
No of HH %
No of HH %
Up to 1 57 81.4 1 50.0 38 92.7 43 91.5 139 86.9
>1 to 2.5 10 14.3 1 50.0 3 7.3 4 8.5 18 11.3
>2.5 to 5 2 2.9 0 0.0 0 0.0 0 0.0 2 1.3
>5 1 1.4 0 0.0 0 0.0 0 0.0 1 .6
Total 70 100.0 2 100.0 41 100.0 47 100.0 160 100.0
The land under acquisition is mostly being used for agriculture. In Kokat village a part of the acquired land is under use for non-agriculture purpose (plots).
Nature, present use and classification of land, irrigation coverage and cropping patterns
The SIA analysis revealed that majority of the land proposed for acquisition in Antaram
and Chengole is irrigated and source of irrigation is tanks, canal and bore wells. In
these villages paddy and maize are main crops cultivated in two seasons. In Kokat and
Rasulpur nature of land is dry and cultivation is done under rainfed conditions. Due to
the nature of soil and scarcity of water, paddy is cultivated very less rather people
produce redgram and cotton under rainfed conditions. The table 4.6 below shows the
village wise cropping pattern and area under cultivation. Redgram is cultivated in
about 245 acres of land followed by paddy in 151 acres, groundnut in 24.77 acres, onion
in 2 acres and cotton in 4.58 acres of land owned by the households surveyed.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
44
Centre for Management and Social Research Development Support Specialists
Table 4.6 : Area under cultivation and cropping pattern (Khariff)
Crops cultivated
Kokat Rasulpura Antharam Chengole Total
(Acres) (Acres) (Acres) (Acres) (Acres)
Redgram 200.90 8.31 11.22 24.68 245.11
Paddy 27.18 0 67.04 56.98 151.20
Groundnut 14 0 6.77 4.00 24.77
Onion 2.00 0 0 0 2.00
Cotton 4.58 0 0 0 4.58
Total 248.66 8.31 85.03 85.66 427.66
Village wise type and extent of of land affected by the surveyed households
Table 4.7 below presents the type of land owned by the households. From the table it is
evident that majority (62%) of the land is un-irrigated and among the irrigated
Chengole village has highest 31 households with 9.13 acres where as Kokat has 48
households with 27.40 acres of un-irrigated land.
Table 4.7 : Type and extent of land affected by the surveyed households
Name of Village
Irrigated Un-irrigated Total
Area (acres)
No. of HH %
Area (acres)
No. of HH %
Area (acres)
No. of HH %
Kokat 8.54 18 25.4 28.79 52 58.4 37.33 70 43.8
Rasulpura 0 0.0 1.18 2 2.2 1.18 2 1.3
Antharam 4.94 22 31.0 4.81 19 21.3 9.75 41 25.6
Chengole 9.13 31 43.7 3.89 16 18.0 13.02 47 29.4
Total 22.61 71 100.0 38.67 89 100.0 61.28 160 100.0 Land prices and recent changes in ownership, transfer and use of lands over the last 3 years
Table 4.8 below provides details of land rates as per the effective date (01.04.2013) in
Kokat, Rasulpur, Antaram, and Chengole. The data shows that land rates for dry land,
wet land and double cropped is varying from village to village. Also, land rates for all
the three categories in Antaram and Chengole is similar and lands fit for house sites is
higher in Rasulpur. During recent survey conducted by revenue department it was
found that current occupiers of certain survey number are not pattadars. They have
been cultivating in other’s survey numbers for long time. Several changes have taken
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
45
Centre for Management and Social Research Development Support Specialists
place in the ownership of lands which has not been updated by some of land owners in
revenue records.
Table 4.8 : Prevailing Land rates in affected villages (Rs. per acre)
Sl. No.
Nature of land Kokat Rasulpur Antaram Chengole
1 Dry land 200000 200000 150000 150000
2 Wet Land double crop -- -- 150000 150000
3 Agricultural Land fit for House Site
-- 300000 200000 200000
Source : Registration & Stamps Department, Government of Telangana Effective date : 01/04/2013
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
46
Centre for Management and Social Research Development Support Specialists
Chapter Five
Estimation and Enumeration of Affected Families and Assets
Introduction
This chapter sets out to present estimation and enumeration of (a) families directly
affected which includes land owners, tenants, STs and other traditional forest dwellers
who have lost any of their forest rights, dependants on common property resources,
assignees, dependants on the land for the last three years (b) families in-directly
impacted by the project and (c) Inventory of productive assets and significant lands
affected.
For assessing the project impact the survey has taken family as a unit. As per the list
provided by the revenue department total number of affected families is 189. Number
of families available for the census survey is 160 and socio-economic survey 143. This
chapter provides range and intensity of families affected and assets they lost. The
survey has categorized family as Affected Family and Displaced Family. The
definitions are as follows:
Project Affected Family
The definition of Affected Family (AF) as per the RFCTLARR Act, 2013 as follows:
i. a family whose land or other immovable property has been acquired;
ii. a family which does not own any land but a member or members of such family
may be agriculture labourers, tenants including any form of tenancy or holding
of usufruct right, share-croppers or artisans or who may be working in the
affected area for three years prior to the acquisition of the land whose primary
source of livelihood stand affected by the acquisition of land;
iii. the Schedule Tribes and other traditional forest dwellers who have lost any of
their forest rights recognized under the Scheduled Tribes and Other Traditional
Forest Dwellers Act, 2006 due to acquisition of land;
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
47
Centre for Management and Social Research Development Support Specialists
iv. family whose primary source of livelihood for three years prior to the acquisition
of the land is dependent on forests or water bodies and includes gatherers of
forest produce, hunters, fisher folk and boatmen and such livelihood is affected
due to acquisition of land;
v. a member of the family who has been assigned land by the State Government or
the Central government under any of its schemes and such land is under
acquisition;
vi. a family residing on any land in the urban areas for preceding three years or
more prior to the acquisition of the land or whose primary source of livelihood
for three years prior to the acquisition of the land is affected by the acquisition of
such land.
Project Affected Family, Displaced Family, Household and Population
According to RFCTLARR Act 2013 “Displaced Family (PDFs)” means any family who
on account of acquisition of land has to be relocated and resettled from the affected area
to the resettlement area. Families losing their dwelling and livelihood due to land
acquisition and are displaced from their habitation are considered as project displaced
households independent of whether they hold any land in the project area. The
proposed project will not result in displacement of any families or persons. The loss is
parts of unirrigated/irrigated agriculture land.
Families who are losing their income, partially or fully, due to loss of land in the
acquisition are considered as Project Affected Families (PAFs). The severity of the
effect can be further categorized based on the extent of loss of land under cultivation
(either partial or full). If a household is losing their total land under cultivation, then it
is considered as fully affected else partially affected. Following table 5.1 presents the
details of the categories of the families:
Table 5.1 : Categories of Families Affected and Displaced
S.No. Category Number Remarks
1. Affected Families 189 Who lose their land and income due to land acquisition
2. Displaced Families 0 Who lose their dwelling and livelihood
Total 189
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
48
Centre for Management and Social Research Development Support Specialists
Number of households owning private land and government land
Table 5.2 indicates that there are 137 families losing their own land and 23 families are
losing government land which they are tilling in all the villages. Approximately 40% of
the private land losers are from and nearly 65% of the households who are losing the
Government land are from Kokat village where the majority of the PAFs reside. Out of
the total privately owned land of 88 acres, the team has administered survey for 52.37
acres and the owners of remaining 35 acres are either not available or untraceable.
Table 5.2 : Number of households losing own land and private lands
Village
Private Land Government Land
Area in Acres
No of HH %
Area in Acres
No of HH %
Kokat 29.94 55 40.15 7.39 15 65.22
Rasulpura 1.18 2 1.46 0 0 0.00
Antharam 9.34 36 26.28 .41 5 21.74
Chengole 11.91 44 32.12 1.11 3 13.04
Total 52.37 137 100.00 8.91 23 100.00
Number of households losing lands and dwellings
Census survey revealed that majority 158 households are losing only lands and 2
families are losing both land and structure (a store room and shed) in the project area.
Project Displaced Families are those who will be losing their dwelling completely due to
proposed land acquisition. Loss of homestead has direct impact on their income, living
standard and sense of identity. As per the census survey none of households are going
to be displaced in the affected villages. Table 5.3 below presents the break up loss of
land and structures attached to lands.
Table 5.3 : Number of surveyed households losing lands and structures
Village
Land Land +Structure Total
Area (acres) No of HH
Area (acres) No of HH
Area (acres) Total HH
Kokat 36.11 68 1.23 2 37.33 70
Rasulpura 1.18 2 0 1.18 2
Antharam 9.75 41 0 9.75 41
Chengole 13.02 47 0 13.02 47
Total 60.05 158 1.23 2 61.28 160
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
49
Centre for Management and Social Research Development Support Specialists
Loss of farm assets
The proposed private land acquisition envisages displacement of 1 hand pump, 2
boundary walls, 19 bore wells, 1 water sump and a water pipeline foundations and 6
store rooms in surveyed villages. Table 5.4 presents details of the assets affected.
Table 5.4 : Village wise other assets affected by the surveyed families
Assets affected
Kokat Rasulpura Antharam Chengole Total
No. % No. % No. % No % No. %
Hand pump 1 14.29 0 0 0 0 0 0 1 4.17
Bore well 4 57.14 0 0.0% 9 100.0% 6 75.0% 19 79.17
Boundary wall of farm house 1 14.29 0 0.0% 0 0.0% 1 12.5% 2 8.33
Water sump 1 14.29 0 0.0% 0 0.0% 0 0.0% 1 4.17
Pipe line 0 0.00 0 0.0% 0 0.0% 1 12.5% 1 4.17
Total 7 100.00 0 0.0 9 100. 8 100.0 24 100.00
Loss of Common Properties
The common properties in this
category include religious
structures, government school
buildings, hospitals, bus stops etc.
During the consultations PAFs
informed that 1 holy cross, 1 temple
and part of irrigation tank will be affected due to land acquisition in the surveyed
villages. The details of affected common properties are summarized in Table 5.5
Loss of Trees
Census survey analysis shows that there will be a loss of 606 trees which includes fruit
bearing, non-fruit bearing trees belong to the affected families in the project area.
Village wise number of trees affected is presented below Table 5.6.
Table 5.5: Community Properties Affected
S.No Village Holy cross
Temple Water bodies
1. Antaram 1 0 1
2. Chengole 0 1 0
Total 2 2 1
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
50
Centre for Management and Social Research Development Support Specialists
Table 5.6 : Village wise number of trees affected in the lands
Name of Tree
Kokat Rasulpura Antharam Chengole Total
No. of Trees No. of Trees No. of Trees No. of Trees No. of Trees
Neem 49 0 32 22 103
Mango 252 0 0 1 253
Guava 1 0 0 0 1
Coconut 0 0 0 2 2
Babul 2 0 4 11 17
Teak 118 30 15 53 216
Tamarind 4 0 8 0 12
Nilagiri 0 0 2 0 2
Total 426 30 61 89 606
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
51
Centre for Management and Social Research Development Support Specialists
Chapter Six
Socio-economic Profile of the Project Area Introduction
The proposed bypass road is located in Tandur and Yalal mandals of Vikarabad district.
The present chapter gives a detail profile of the project affected villages in general and
socio-economic profile of project affected persons in particular.
District Profile - Vikarabad
Vikarabad District is the newly formed district, carved out from the erstwhile
Rangareddy District in Telangana State. It is bounded by with Sangareddy,
Rangareddy, Mahabubnagar districts of Telangana and Chincholi district of Karnataka.
The district already has good road and railway line connectivity and the headquarters is
located at a distance of 75 kms from the State capital Hyderabad and is in close
proximity to already industrialized areas like Sangareddy which is 42 Kms away
(Mominpet mandal of this district is just 18 Kms), Shadnagar at 56 Kms away
(Kulkacherla mandal is 36 Kms), Pashamylaram 47 Kms, Patancheru 52 kms, Kothur 58
kms and adjoining Chevella and Shamshabad.
The total geographical area of the district is 3,386 Sq Kms. having a unique climate, soil,
geography, flora and fauna. Total population of the district is 927140 as per census 2011.
Male and female population consists of 463350 and 463790 respectively. Sex ratio
(females per 1000 males) is 1001 and literates is 470374 out of which male literates are
273236 and females are 197138. Total literacy rate in the district is 57.91, out of which
males is 67.58 and females is 48.32. Total population of children between 0-6 age group
is 114901, out which males is 59063 and female is 55838. Sex ratio of boys and girls is
945 per 1000 males.
Project Location – Tandur and Yalal
Tandur also known as Tanduru is a municipal town and mandal in Vikarabad district
of Telangana. Tandur is 125 km from Hyderabad by bus and 110 km by train. It is well
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
52
Centre for Management and Social Research Development Support Specialists
connected with other neighbouring towns such as Zaheerabad (60 km), Sangareddy
(50 km), Mahabubnagar (80 km) and Vikarabad (40 km). The major railway station is
located on Secunderabad-Wadi section of Mumbai route. Tandur is the largest town in
Vikarabad district and it is a municipality and the headquarters of Tandur mandal in
Tandur revenue division. It is famous for stone industries, cement industries and
Redgram (Pigeon pea) production. Some of the cement factories located are Cement
Corporation of India, India Cement Industries and Penna Cements. Many education
centres are located there. Drinking water is supplied from the River Kagna, which is 4
km from the town. Tandur, one of the important towns in the district, is the industrial
hub of the district. Tandur is the main producer and distributor for blue & yellow
limestone. Tandur is also famous for Redgram (Pigeon pea) production . Laterite and
other stone mines and many toor dal mills located in and around Tandur provide
employment to many.
Fig. 6.1: Telangana State and Vikarabad District Map
Tandur madal has 38 revenue villages with 36 habitations. Total geographical area of
madal is acres 57,748 acres. Government land is acres 8773.28 guntas out of which
assigned land is 5519.17 acres and vacant land is acres 1447.11 guntas. According to
census 2011, Tandur had urban population of 65,115 - of this, 32595 (51%) were male
and 32520 (49%) female. Rural population of the mandal is 53661, out of which 26872
were male and 26789 female. Tandur has an average literacy rate of 60%, higher than
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
53
Centre for Management and Social Research Development Support Specialists
the national average of 59.5%: male literacy is 67%, and female literacy stands at 52%.
15% of the population is under 6 years of age.
Yalal Mandal
Yalal mandal has 34 revenue villages with 33 habitations. Total geographical area of
madal is acres 53041.35 guntas. Total forest area is acres 9595.31 guntas. Government
land is acres 6943.03 guntas out of which assigned land is 544 acres and vacant land is
acres 6399.03 guntas. Total population of mandal is 22007 of which male and female
population consists of 23173 and 45180 respectively. Male literates are 57% and female
is 41%. Agriculture is the main occupation of people living in Yalal , some of the crops
grown in this region include redgram, paddy, groundnut, cotton, pulses, jowar, cereals,
sweet orange, mango, sapota and tomato. Yalal includes the priests, carpenters,
blacksmiths, barbers, weavers, potters, oil pressers, leatherworkers, sweepers, water
bearers, toddy-tappers and many others.
Demographic Profile of affected villages
The demographic details of the affected villages is presented in Table 6.1 below:
Table 6.1 Area and Demographic Profile of the Affected Villages
Description
Name of the Village
Kokat/ Rasulpur
Antaram Chengole Total
Geographical Area 1800 ha 830 ha 918 ha --
Total Households 1021 1150 588 2759
Total Population 5412 5141 2606 13159
Males 2448 2548 1269 6265
Females 2964 2593 1337 6894
Scheduled Castes Population
1106 1099 733 2938
Scheduled Castes -Males 455 546 345 1346
Scheduled Castes -Females 651 553 388 1592
Scheduled Tribes population-
719 569 3 1291
Scheduled Tribes -Males 352 274 2 628
Scheduled Tribes -Females 367 295 1 663
Sex ratio 1211 1018 1054 3283 Source : Census of India, 2011.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
54
Centre for Management and Social Research Development Support Specialists
Education Facilities and Literacy
Primary schools are available in all the affected villages. The middle level schools are
not available in any of the three affected villages. Students of theses villages go to
Tandur for higher educational facilities
Table 6.2 : Education Facilities
Education facilities Kokat/ Rasulpur Antaram Chengole
Number of Primary Schools 4 1 1
Number of Middle Schools 0 0 1
Number of Higher Secondary Schools 2 0 1
Colleges/Vocational Training Centre available
1 0 0
Source : Village Panchayat.
The average literacy rate for the affected villages is 74%. The male literacy rate is high in
comparison to female literacy rate.
Table 6.3 Literacy among the Affected Villages
Name of Village Total Literacy
Rate Male Literacy
Rate Female Literacy
Rate
Kokat / Rasulpur 73.14 % 76.41 % 70.57 %
Antaram 60.53 % 68.06 % 53.24 %
Chengole 47.14 % 55.68 % 39.02 %. Source: Registrar of Census, Census of India, 2011
Medical Facilities in Project Affected Villages
According to the 2011 census, the basic medical facility, Health Sub Centre is not
available in any of the four affected villages. Other medical facilities are available at a
distance of around 10 – 12 kms (Tandur and Yalal Mandal)
Table 6.4 Medical facilities in affected villages
Medical facilities Name of the Village
Kokat/ Rasulpur
Antaram Chengole
Number of Health Sub centre 0 0 0
Allopathic Hospitals available within range 2 2 0
Primary Health Centre available within range 1 1 1 Source: Village Panchayat
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
55
Centre for Management and Social Research Development Support Specialists
Drinking Water Facilities of Affected Villages
All the affected villages have well water, tank water, tube wells and hand pumps to
fulfill the basic necessity of water requirements for the population.
Table 6.5 Sources of Drinking Water Facility
Drinking Water Facilities Name of the Village
Kokat/ Rasulpur Antaram Chengole
Well water Not Available Available Available
Tank water Available Not Available Available
Tube well Water Available Not Available Available
Hand pump Available Available Available
Source: Village Panchayat
Communication and other Infrastructure Facilities in Affected Villages
The people of affected villages mostly travel to Tandur within 10 kms for availing other
infrastructure facilities such as transport, communication, banking and other facilities.
Recreation and cultural facilities like cinema hall, sports club, auditoriums are not
available in all the 4 villages and are also not available within the range of 5-10kms.
Table 6.6 Communication and Other Facilities in Affected Villages
Facility Name of the Village
Kokat/
Rasulpur
Antaram Chengole
Communication
Phone facilities Available Available Available
Post office Available Not Available Available
Bus services Available Not Available Not Available
Pucca Road Available Available Available
Railway services available within range
Available Available Available
Banking Facilities Available Available Available
Commercial banks/Cooperative Banks
Available Available Available
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
56
Centre for Management and Social Research Development Support Specialists
Table 6.6 Communication and Other Facilities in Affected Villages
Facility Name of the Village
Kokat/
Rasulpur
Antaram Chengole
Communication
Cooperative society Available Available Available
Agricultural credit society Available Available Available
Source: Village Panchayat
Land Use Pattern in Affected Villages
Forest lands are not available in Kokat, Rasulpur and Chengole villages. The total
irrigated land is highest in Kokat village which is 3919.29 acres. In Kokat and Antaram
villages un-irrigated area is 304 acres and 374 acres, and irrigated is 520.32 and 1200
acres respectively. Irrigation facility through Tanks is available only in Antaram and
Chengole villages.
Land Use in acres Kokat Rasulpur Antaram Chengole
Irrigated Area 3919.29 520.32 1200 21
Un -irrigated Area 304.33 66.20 374 2
Cultivable Waste (including Grazing and Groves)
0 0 500 2
Forest Land 0 0 340 0
Others (Bore well – With Electricity) 0 0 99 4
Tank 0 0 300 21 Source: Revenue Department, Yalal and Tandur Mandal.
Cropping Pattern in Affected Villages
Agriculture is found to be the dominant economic activity for all the affected villages.
Only paddy is cultivated in both rabbi and khariff seasons subject to availability of
water in Antaram and Chengole. The people are completely dependent upon the rain
water for their agricultural practices in Kokat village. Pigeon pea and cotton are the
common crops cultivated. The yields of paddy vary from 10 to 12 quintals per acre. In
the consultation with the villagers it was noted that the usage of fertilizer is bare
minimum and is about 15 to 20 kg/acre and usage of pesticide is also less.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
57
Centre for Management and Social Research Development Support Specialists
Socio-economic profile of Project Affected Families
Families belong to Kokat, Rasulpur, Antaram and Chengole villages are affected by the
land acquisition for Tandur bypass road project. The socio-economic profile of affected
families is prepared based on the socio-economic survey carried out in the project area.
Through the survey, socio-economic conditions of the affected families (AFs), details of
the assets affected, their priorities, expectations and apprehensions were collected. This
helped to assess the extent of impact on each AF and plan for mitigation measures.
Before initiating the survey a complete list of affected families was collected from the
revenue department and questionnaires were administered to each affected family
those who are available and cooperated during the survey. As per the list provided by
the department, there were about 189 (84.6%) families in four villages who are loosing
lands. The census survey could cover 160 households and socio-economic survey for
143 (75.66%) households from all the 4 villages due to not availability of PAFs during
the survey period. Village wise number of affected families covered is presented in
Table 6.7
Table 6.7 : Village wise number of affected families surveyed
S. No Village Socio-economic
Survey % Census Survey
%
1 Kokat 55 38.5 70 43.8
2 Rasulpura 2 1.4 2 1.3
3 Antharam 42 29.4 41 25.6
4 Chengole 44 30.8 47 29.4
Total 143 100.0 160 100.0
Demographic Characteristics
Table 6.8 shows the demographic details of the households surveyed. Of the total
population, male constitutes 49.93 percent and female 50.07 percent. . The average size
of the household is 5.6. Around 73.48 percent of the population is above 18 years of age.
A substantial (26.51%) population is under 18 years of age. Around 7 percent of the total
population is children and infants below 5 years of age. Around 30.76 percent of
households are women headed households. Incidence of differently abled population is
about 10.28 percent.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
58
Centre for Management and Social Research Development Support Specialists
Social Group, Religion & Marital Status
Table 6.9 presents that majority (97.6%) of the surveyed households belong to other
backward caste (OBC) category and remaining belong to general caste. All the affected
families surveyed belong to Hindu religion.
Table 6.10 shows the marital status of the population. Around 55.6 percent of the
population is married and around 40 percent are single. Around 0.1 percent are
separated and 4.5 percent i.e. around 36 persons are widow/widower. The incidence of
divorced and deserted persons has been found very low among the surveyed
population.
Table 6.8 : Demographic Particulars of the Affected Population
S.No Particulars No. % to total
1. Number of household affected 143 --
2. Total population affected 807 --
3. Average household size (per HH) 5.6 --
4. Males Population 403 49.93
5. Female Population 404 50.07
6. Children below 18 years 214 26.51
7. Adults 18 years and above 593 73.48
8. Children up to 5 years 57 7.06
9. Women headed affected households 44 30.76
10. Differently abled population 83 10.28
S.No Table 6.9 : Social Category of Affected Families
Social Category No. %
1. Scheduled Caste (SC) 41 28.7
2. Scheduled Tribe (ST) 22 15.4
3. Backward Caste (BC) 58 40.6
4. General 22 15.4
Total 143 100
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
59
Centre for Management and Social Research Development Support Specialists
Table 6.10: Marital Status of the Population
S.No Marital Status No. %
1. Married 449 55.6
2. Un-married 321 39.8
3. Separated 1 .1
4. Widow 36 4.5
Total 807 100.0
Type of Family
Table 6.11 present the type of family of the affected households. With regard to the
type of family, majority of the households are joint families (71%) who live in an
individual dwelling and about one fifth (29%) of the families live as nuclear families.
This information is important while deciding the rehabilitation and resettlement
entitlements for project affected families.
Age Profile of the Population
Table 6.12 shows the age group of the households. It can be seen that majority (35.7%)
of the population is in the age group of 16-30 years. Age category 6-15 and 41-60 age
groups almost similar with 16%. Age groups of 31-40 stand at 14.6 percent. This
presents that majority of the population is in productive age group and would require
suitable rehabilitation measures. Around 9.7 percent of the population falls under above
60 age group. The incidence of children who are below 5 years is around 7.1 percent
and school going population is around 16.7 percent.
Table 6.11: Type of Family
S.No Type of Family No. %
1. Joint 102 71.3
2. Nuclear 41 28.7
Total 143 100.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
60
Centre for Management and Social Research Development Support Specialists
Education Levels among the Affected Adult Population
Table 6.13 shows the education level amongst the surveyed population. The population
below the age of 5 (7.1%) has not been considered for purposes of education levels. It
can be seen that more than a quarter of the affected population is illiterate (37.2%).
Majority of the literates, have studied upto primary school (10.7%); about 13 % up-till
high school (11%); and 9.5 % up-till middle. The people studied above 10th standard is
15 percent. Graduates constitute 7.9% and Post Graduates 1.9%.
Table 6.12 Age profile of the Affected Population
S.No Age Group
Male Female Total
No. % No. % No. %
1. 1 to 5 25 6.2 32 7.9 57 7.1
2. 6 to 15 67 16.6 68 16.8 135 16.7
3. 16 to 30 147 36.5 141 34.9 288 35.7
4. 31 to 40 58 14.4 60 14.9 118 14.6
5. 41 to 60 66 16.4 65 16.1 131 16.2
6. Above 60 40 9.9 38 9.4 78 9.7
Total 403 100.0 404 100.0 807 100.0
Table 6.13 : Education Level among the Affected Adult Population
S.No Literacy Level Male Female Total
Number % Number % Number %
1. Illiterate 107 28.3 172 46.2 279 37.2
2. Literate but no formal education 7 1.9 21 5.6 28 3.7
3. Primary – 1st to 5th 45 11.9 35 9.4 80 10.7
4. Middle – 6th to 8th 40 10.6 31 8.3 71 9.5
5. High School – 9th to 10th 55 14.6 44 11.8 99 13.2
6. Senior Secondary 77 20.4 40 10.8 117 15.6
7. Graduation 34 9.0 25 6.7 59 7.9
8. Post-Graduation 10 2.6 4 1.1 14 1.9
9. Technical/ professional education 3 .8 0 0.0 3 .4
Total 378 100.0 372 100.0 750 100.0
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
61
Centre for Management and Social Research Development Support Specialists
Village-wise presence of differently abled persons
Table 6.14 below presents details of persons differently-abled. It can be observed that
this population constitutes 3.33 percent. Out of the total surveyed families, there are 83
differently abled persons identified. Most (67.5%) of the differently-abled persons are
ophthalmology related (eye sight defect), and among the balance, 3 have psychological
disorders, 3 have hearing issues and 2 are speech challenged and 15 are orthopedic
related disorders. (Graph to be changed)
Table 6.14 : Type of disability
S. No. Type of Disability No. %
1. Orthopedic related 15 18.1
2. Eye related 56 67.5
3. Ear related 3 3.6
4. Speech related 4 4.8
5. Psychological 3 3.6
6 Others 2 2.4
Total 83 100.0
Health Status
About 38.5 percent of the affected families reported that they suffered from diseases
during last twelve months. From Table 6.15 it can be seen that major health problems
experienced by the respondents are fever (18.42%), paralysis (7.89%), followed by other
diseases. When looked into village wise health status, major health problems are similar
and fall into the same distribution as the above. About 78.3 percent of the households
possess Arogya Sree Health Insurance card.
Table 6.15: Family members suffered due to health issues during the last six months
S. No. Type of Ailment No. %
S. No.
Type of Ailment No. %
1. Appendicitis 1 2.63
15. Leg fracture 1 2.63
2. Asthama 2 5.26
16. Mental 1 2.63
3. B.P 1 2.63
17. Nervous disease 1 2.63
4. Bone surgery 1 2.63 18. Paralysis 3 7.89
5. Cancer 1 2.63
19. Piles 1 2.63
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
62
Centre for Management and Social Research Development Support Specialists
Table 6.15: Family members suffered due to health issues during the last six months
S. No. Type of Ailment No. %
S. No.
Type of Ailment No. %
6. Chest pain 1 2.63
20. Stomach pain 1 2.63
7. Chicken pox 1 2.63
21. Diabetic 1 2.63
8. Eye operation 1 2.63
22. Typhoid, Malaria 2 5.26
9. Fever 7 18.42
23. Urine problem 2 5.26
10. Heart problem 2 5.26
24. Weakness 1 2.63
11. Infection 1 2.63
25. Platelets loss (ITP) 1 2.63
12. Knee problem 2 5.26
13. Kindney problem 2 5.26
Total 38 100.0
For a query who suffered most among
the family members during last twelve
months, it was found that women
suffered most (54.5%) followed by men
(34.5%), both men and women (1.8%),
boy child (5.5%) and both children
(3.6%).Table 5.10 shows type of health
facility visited by affected families in case
of health problems. Out of 55 families
who reported to have suffered from
diseases, it was found that more than half of the households (70%) reported that they
visit private hospitals in Hyderabad.
Income Details of the Population and Poverty levels
Table 6.17 shows the household income
of the affected families. The income
shown here is lower than the actual
income as majority of the families have
under reported their income. Of the total
population majority (23.8%) of the
households make more than INR 25000
and up to INR. 40,000 per annum. This
shows that a quarter of the population is
Table 6.16 : Health facility visited in case of illness
S.No. Type of health facility No. %
1. Local Private Medical Practitioner 3 6.5
2. Town/Area hospital (Government) 2 4.3
3. Nearest Private hospital 3 6.5
4. District hospital (Government) 3 6.5
5. District hospital (Private) 3 6.5
6. Other (Private Hospitals-Hyd) 32 69.6
Total 46 100.0
Table 6.17 Annual Income of the Households(2016-2017)
S.No Income Categories No. %
1. up to 25000 25 17.5
2. >25000 to 40000 34 23.8
3. >40000 to 60000 26 18.2
4. >60000 to 90000 19 13.3
5. >90000 to 150000 17 11.9
6. >150001 to 200000 8 5.6
7. >200000 to 300000 7 4.9
8. >300000 to 500000 2 1.4
9. >500000 5 3.5
Total 143 100.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
63
Centre for Management and Social Research Development Support Specialists
not even making the minimum wage per month. This is followed by 18.2 percent of the
population who make between INR. 40,000 and Rs. 60,000 per annum. Nearly 18
percent reported that their income is upto INR 25,000 per annum. About 13.3 percent
reported to make anywhere between Rs. 60,000-90,000; nearly 12 percent are earning
between INR 90,000 – 1,50,000 ; 12 percent of the households are earning between Rs.
1,50,001-5,00,000. Only five families reported to be earning more than Rs. 5,00,000 per
annum as their family members are into Government job, trade and business and
agriculture activity.
94.4 percent (135 HH) of households reported having ration cards. Ration card status of
the families also forms an indicator for measuring their poverty. In Telangana
households are categorized into White Ration Card holders and Pink Ration Card
holders based on their economic status. White ration card holders are households which
are below poverty line and pink ration card holders are above poverty line. Out of the
total households surveyed, 61.8 percent (92) of the households are holding white ration
card holders.
Occupation Profile of the Population
Information pertaining to the
occupation of the affected
households is shown in Table
6.18. It can be seen from the
table that a large number are
pursuing agriculture (53.3%).
People working as labour
constitute 3.8% where as
labour in agriculture is 7.5 %
and non agriculture is 6.6 %.
There are about 2.3 percent of
Government employees and private employees among the affected families. More or
less about 1 percent of the population is into self employment and 2.3 persons are doing
trade & business. A large number of the female population is engaged in household
work and maintaining livestock. Population below age of 6 years has not been
considered in this table.
Table 6.18 : Occupation Profile of the affected adult population
S.No Occupation Number of
persons %
1. Agriculture 279 53.3
2. Agriculture labour 39 7.5
3. Non agriculture labour 20 3.8
4. HH Industries/ Artisan activity 3 .6
5. Government Service 12 2.3
6. Private service 25 4.8
7. Trade & Business 12 2.3
8. Professional (doctor/engineer) 0 0.0
9 Self-employed 7 1.3
10 Others 126 24.1
Total 523 100.0
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
64
Centre for Management and Social Research Development Support Specialists
Role of Women at the Family and Community Level
Table 6.19 presents the role of
women in economic or
livelihood activity, household
decision making and
participation at Panchayat or
community level decision
makings. About 43 percent of
the women support their
families in livelihood activities
such as agriculture,
agriculture labour and non-
agriculture labor, etc. With
regard to household level
decision making about 25
percent responded that they
will be involved in decision making of children’s education, agriculture related
decisions, children’s marriage and other home needs related decision makings. At
panchayat level decision making of women shows 5.6 percent only.
Social and Cultural Organisations
All affected families fall under SC, ST, BC and General castes, giving social cohesiveness
to among the affected community. There is a significant temple named Bhukailas in
Antaram Thanda near the affected region. Major festivals celebrated in the region are
Sankanranthi, Dassura, Deepawali; but most prominent are Shiva parvathi kalyanam on
shiva rathri day, Venkateshwara jathara in August (sharavanamasam), Narasimhaswami jatara
in May month, Vuradamma jatara once in 3 years or 5 years and Mohharam festival. These
festivals are managed by committees with active participation of youth.
Table 6.19: Women’s role in the Family and Community Level
Decision making
S.No Response Number %
Do women participate in economic/livelihood activities?
1. Yes 62 43.4
2. No 81 56.6
Total 143 100.0
Do women participate in decision making at household level?
1. Yes 36 25.2
2. No 107 74.8
Total 143 100.0
Do women participate in decision making process at Panchayat or
Community Level?
1. Yes 8 5.60
2. No 121 84.61
3. Not reported 14 9.79
Total 143 100.0
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
65
Centre for Management and Social Research Development Support Specialists
Land use and Livelihood
Almost all the affected families (97.5%)
surveyed as part of the study owns
agriculture land. These people depend
on agriculture for their livelihoods.
Following the Act provisions,
appropriate time can be given to
farmers to harvest the crops before taking possession of the lands.
Size of Land holding
As per GoI classification, landholders
owning up to 2.5 acres of land are treated
as marginal farmers; between 2.5 to 5 acres
as small farmers; between 5 – 7.5 acres are
categorized as medium farmers; and those
possessing more than 7.5 acres categorized
as large farmers. It can be seen from Table
6.21, majority (66.9%) of the affected fall under marginal farmer category. Small
farmers constitute 18.1 percent. It can be inferred the agriculture is largely subsistence
in nature. This is also corroborated through consultations. About 7% of households are
owing land between 5 to 7.5 acres and 8 percent found big farmers.
Source of Irrigation
Irrigation is a key in determining agricultural
incomes. The lands owned by the majority
(53%) is unirrigated, 47% own irrigated lands.
Among all the available irrigation sources,
bore well constitute the major source (72%)
followed by canal (23%), wells (1.4%) and
tank/lake (2.8%).
Table 6.20: Usage and Type of Land
S.No Whether Yes/No No. %
1. Agricultural 156 97.5
2. Non-agricultural 4 2.5
Total 160 100.0
Table 6.21: Landholding Size among the Households
S.No Area (Acre) No. %
1. Up to 2.5 107 66.9
2. 2.5 to 5 29 18.1
3. 5 to 7.5 11 6.9
4. >7.5 13 8.1
Total 160 100.00
Table 6.22: Source of Irrigation
S.No. Irrigation Source No. %
1. Bore well 51 71.8
2. Canal 17 23.9
3. Well 1 1.4
4. Tank/lake 2 2.8
Total 71 100.0
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
66
Centre for Management and Social Research Development Support Specialists
Quality of Soil
Quality of the soil plays an important role in determining the productivity of the land
and value of the land. The health of soils has a direct relationship with the nutrition of
the food they yield. Red soil predominates in the district followed by Black Cotton
soils. The district has both red and black soils while the red soils have a share of 51 per
cent in the total area, black soils have a 40 per cent share. The remaining 9 per cent area
is under dubba (sandy loam soils). This variety of soils makes it possible to grow a big
range of crops in the district. The mandals where the soils are predominantly black are
Chevella, Shahbad, Vikarabad, Newabpet, Dharur, Pudur, Tandur, Peddemul, Yalal,
Basheerbad, Marpally, Mominpet and Bantararm. The rainfall of the district is about 780
mm per annum. It is good enough to support crops in the red soils during the rainy
season. Black soils are cropped both in the kharif as well as rabi season depending on
the depth of the soil. Soil analysis reports revealed that the soils are low to medium in
available nitrogen, medium to high in available phosphorous and medium to high in
available potash.
Details of Livestock &Household Assets Owned by Households
Table 6.22 describes the details of various livestock and other durable asset holding
amongst the affected households. It can be seen from the table that less number of the
households possesses livestock. Majority of livestock owned are milch animals like
cows (53) and buffaloes (98). On an average each household owned 3 to 3.5 milch
animals. Most of the household depend on them for milk. There are also a small
number of bullocks (73) and goats (19) amongst the households. With regard to goats on
an average each household owns 2.11. The low number of milch animals and other
livestock is an indication of a under developed animal husbandry business in the
affected village. With regard to durable assets pertaining to household a large number
of households possess LPG Stoves (121), mobile phones (194) and television (111).
Table 6.22: Details of Asset Ownership amongst the Households
S. No
Details of Livestock
No. of Livestock
No. of
HH
Average per HH
S. No
Details of Assets No. of Assets
No. of
HH
Average per HH
1. Bullocks 73 26 2.81 1. LPG stove 126 121 1.04
2. Cows 53 17 3.12 2. Bicycle 15 15 1.00
3. Buffalos 98 28 3.50 3. Two wheeler 65 60 1.08
4. Calves 2 3 .67 4. Four wheeler 10 10 1.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
67
Centre for Management and Social Research Development Support Specialists
Table 6.22: Details of Asset Ownership amongst the Households
S. No
Details of Livestock
No. of Livestock
No. of
HH
Average per HH
S. No
Details of Assets No. of Assets
No. of
HH
Average per HH
5. Goats 19 9 2.11 5. DVD Player 3 3 1.00
6. Sheep 0 2 0.00 6. Television 111 110 1.01
7. Chicken/Hens 8 5 1.60 7. Computer 6 5 1.20
8. Ploughs 1 3 .33 8. Sewing Machine 4 4 1.00
9. Bullock Carts 2 4 .50 9. Mobile/ Land Phone 194 132 1.47
10. Air Conditioner 6 5 1.20
11. Air Cooler 3 3 1.00
12. Washing Machine 5 5 1.00
13. Tractor 8 7 1.14
14. Spray pump 6 6 1.00
Migration among the population
Table 6.23 shows the details of
migration amongst the affected
population. We can see from the table
that majority (88%) of the population do
not migrate. However we see there is
10.7 percent of households migrate to other places for better livelihood opportunities
and studies.
Livelihood preferences
Proposed land acquisition impacts on the livelihood of 60% of the population who are
depended on agriculture. The remaining population is not affected as they are into non-
agriculture activities such as Government employment, private employment, self-
employment and professional activities. During consultations with the affected
population it was found that this affected population would like to prefer agriculture
labour work or buy another land as they do not posses skills for livelihood.
Food security
Food security is the most desired outcomes for any household as it linked to the overall
well being of the household. Food security is defined as a state in which "all people at
all times have both physical and economic access to sufficient food to meet their dietary
needs for a productive and healthy life" (USAID, 1992). The socio-economic survey
Table 6.23: Details of Migration Amongst the Households
S.No Details of Migration No. %
1. No migration 721 89.3
2. Out migration 86 10.7
Total 807 100.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
68
Centre for Management and Social Research Development Support Specialists
delved into the extent to which the affected families were food secure, the role of Public
Distribution System, and the coping mechanisms to face any food insecure situations.
Out of the total surveyed families, 146 families reported that they are cultivating crops.
Out of them only 74 households cultivate paddy and 65 families cultivates redgram, 19
families cultivate paddy as well as wheat, 2 families cultivate wheat as well as
vegetables and 7 families cultivate only vegetable. Analysis shows that 36% of the
families who cultivate paddy produce upto 10 quintals, another 30% produce between
11 to 20 quintals, 12% produce 21 to 30 quintals and the remaining 23% produce more
than 30 quintals. The data reveals that majority of the families who produce paddy use
it for self-consumption as well as selling. Out of the total surveyed households, majority
of the households will be affected due to land acquisition as their food security will be
disturbed. The other households are going to be affected due to loss of their
horticulture lands, loss of access to grazing lands for their milch cattle.
Table 6.24 gives the pattern of the purchase of food grains by the affected families.
During the survey it was found that 92.3 percent of the affected families have
purchased food grains during past 3 months. When inquired for how frequent they
purchased, majority 61.18 percent responded that they purchased for about three
months, 15.29 percent purchased for two months and remaining purchased for one
month. When they were asked whether any time in the last twelve months did not have
enough to eat, about 47 percent responded that they experienced such situation. Among
these category 38.64 percent (10 HH) said that they experienced such situation for 2 – 3
months and 22.7 percent (10 HH) said for more than six months. 68% of the affected
families are holding BPL card and obtaining rice, sugar, pulses, wheat and kerosene
from PDS.
Table 6.24 : Pattern of the purchase of food grains by the affected families
Have you purchased food grains during the past 3 months?
S.No. Response No.of HH %
1. Yes 85 92.39
2. No 7 7.61
Total 92 100.00
(If yes) For how many months?
S.No. Response No.of HH %
1. One Month 20 23.53
2. Two months 13 15.29
3. Three Months 52 61.18
Total 85 100.00
Is there any time of the year (last 12 months) when you don't have enough to eat?
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
69
Centre for Management and Social Research Development Support Specialists
S.No. Response No.of HH %
1. Yes 44 47.83
2. No 38 41.30
3. Don’t Know 10 10.87
Total 92 100.00
14.5 (If yes to the above) For how many months have you experienced such situation?
S.No. Response No.of HH %
1. Around one month 12 27.27
2. Around 2-3 months 17 38.64
Around 3-5 months 3 6.82
Around 6 months 2 4.55
3. More than 6 months 10 22.73
Total 44 100.0
Indebtedness amongst the Households
Indebtedness is a major socio-economic
factor that can affect the standard of
living of a household. Table 6.25 shows
the number of households that have a
substantial loans/credit pending to be
repaid. Of the total 143 households around 57 percent of the households have pending
loans. Majority of the households have availed loans from banks under crop loan.
With regard to the usage of the
debts or credit obtained from
various sources, it is found that
most (90.2%) loans were obtained
for purchasing agriculture inputs
and other related components.
Around 6 percent of the
households used the loans for domestic purposes and around 1 percent utilized for
house construction purposes, purchase of live stock and house construction. The details
pertaining to the use and purpose for which the loans were obtained are given in the
Table 6.26 above.
Table 6.25: Indebtedness among Affected Households
S.No Whether Yes/No No. %
1. Yes 82 57.3
2. No 61 42.7
Total 143 100.00
Table 6.26– Usage of Loan/Purpose for which Loan was Obtained
S.No Purpose No %
1. Agriculture 74 90.2
2. Marriage 5 6.1
3. Purchase of livestock 1 1.2
4. Bore well 1 1.2
5. House construction 1 1.2
Total 82 100.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
70
Centre for Management and Social Research Development Support Specialists
Chapter Seven
Social Impacts
Introduction
Infrastructure development projects bring numerous positive impacts but also cause
adverse social impacts in terms of loss of land assets, non-land assets and loss of
livelihood particularly the vulnerable sections of the society who are susceptible to
socio-economic risks. Assessment of such impacts and development of mitigation
measures during the project preparation help achieving the social acceptance of the
project. This section of the report presents the social impact assessment of the project
affected families. It details out the project benefits, the associated adverse impact and
measures adopted to minimize the adverse impacts.
Framework and approach to identifying the impact
Land acquisition impacts were identified through a census / socio-economic survey of
families and consultations conducted between 19th – 26th April, 2017. As per the list
provided by the revenue department total number of families affected due to this
project is 189 from 103 survey numbers who are legitimate owners. Census survey
covered 84.65% (160) affected families from Kokat, Rasulpur, Antaram and Chengole
villages. Land, livelihood, farm assets and minor structures of a family are the major
parameters, which are getting affected due to proposed acquisition. Among the affected
families, most of the households (111) are losing upto 25% of lands owned hence their
livelihood is not affected and these families have been categorized as minor impacted.
Those who losing more than 50% of lands are have been categorized as major impacted
as their income and livelihood will be affected. 20 families have been categorized as
moderately impacted as they will be losing lands between 25% to 50% of lands and will
have impact on their income. Using the above parameters the degree of impact is
presented in below Table 7.1.
Table 7.1 : Categories and Degree of the Impacts
S.No. Likely loss No. of families Degree of Impact
1. Land + Dwelling 0 Adversely Impacted - As these will be displaced fully
2. Only Dwelling 0 Severely Impacted - Displaced but livelihood is not affected
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
71
Centre for Management and Social Research Development Support Specialists
3. Land >50% 29 Major impact – Impact on livelihood and income
4. Land >25% to 50% 20 Moderate impact – Less impact on livelihood and income
5. Land upto 25% 111 Minor Impact - No impact on livelihood
Total 160
Impacts at various stages of project cycles
The social impacts of the Tandur bypass rad project have been classified into three
stages as presented below and explained in the following sections:
1. Impact during Pre-construction Stage
2. Impact during construction stage
3. Impact during operational stage
Impact during Pre-construction Stage
Impact on agriculture lands
The proposed project involves acquisition of agriculture lands which are major assets to
the farmers. As the alignment passes through middle of agriculture fields in some cases
the remaining land is becoming unviable.
Impact on private structures / assets
There is no impact on private assets such as open well, cattle shed, petty shops,
residential structures and commercial structures. However, impact is on Tomb (1),
store room (1), boundry wall (1) agriculture bores (10) Yellamma Temple in farm field
(1) Mango and other trees and a small water storage tank (Kokat).
Impact on livelihood and income
As assessed during social impact assessment study, livelihoods of 29 families will be
affected due to the loss of the land. Close to 60 % of PAPs reported agriculture as their
primary source of income and loss of cultivable land will have a direct impact on the
house hold income. PAPs believed that the land acquisition would lead to reduced
income.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
72
Centre for Management and Social Research Development Support Specialists
Photo Plate 7.1 : Photographs of affected structures and other assets
Bore in Agriculture field in Antaram Thanda Affected Yellamma Temple on Chengole
Affected Teak and other trees Affected Tombs in Agriculture field
Affected Mango trees in Kokat Affected private water storage tank
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
73
Centre for Management and Social Research Development Support Specialists
Impact on Food Security
The proposed land to be acquired is less than 10% of the district and less than 15% of
the state agricultural wet land covered in this project. Hence, there is no negative
impact and violation of food security act. Even though, As per chapter 3 para (4) of
LARR Act 2013, Provided that the provisions of this section 4 of chapter 3 shall not
apply in the case of projects that are linear in nature such as those relating to railways,
highways, major district roads & irrigation. This project will not exceed the limit for the
projects in a District or State as notified by the Appropriate Authority with in other type
of agricultural land or the total acquisition.
Impact on Scheduled Areas
According to the RTFCTLARRA under section 3 (C) sub section 3, the Scheduled Tribes
and other traditional forest dwellers who are not losing any of their forest rights
recognised under the Scheduled Tribes and Other Traditional Forest Dwellers
(Recognition of Forest Rights) Act, 2006 due to acquisition of land. No scheduled area
is affected by the acquisition.
Level and type of employment and income
Majority of PAFs are engaged in agriculture. Although in most cases agricultural land is
to be acquired, close to 76 number of the PAFs hold other land besides the land to be
acquired which possibly could be used to cultivate with assistance from compensation.
Most PAFs expected a decrease in income following acquisition.
Impact of Common property resources
No damage to Schools, religious structures, community facilities, Health care centres,
Anganavadi, playground and water tank or government buildings will be caused due
to the project. However the bypass will pass in close proximity to the water tank located
in Chengole village. Safety precautions will need to be enforced in these areas.
Impact on Public Roads and Utilities
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
74
Centre for Management and Social Research Development Support Specialists
Minimal effect on roads and public utilities is expected. The disruptions to public
services are temporary. With careful planning any unnecessary losses to public
property can be avoided. Impact on road and electricity shall be minimal where Safety
and utilities shall be taking care and replaced by the R&B department.
Impacts on the norms, beliefs, values and cultural life;
There is no expected impact on community values, beliefs and cultural life etc as there
is no displacement of families due to land acquisition.
Impact on environment
Only part of agricultural land shall be acquired for the project and limited trees shall be
cut, which shall be replanted in other forest land. There is no destruction of
environments and the eradication of wildlife in this proposed bypass road project. Road
alignments will not cover developed and deep forest areas. There is no chemical and
waste disposals hence limited environmental impact is expected.
Impact during construction stage
Influx of migrant workforce and employment opportunities for local
During the construction pahse civil contractors may hire people from far off places
which create influx of migrant workforce in the vicinity. Local people may demand for
inclusion of local community in the construction activities. However, this may not
impact the livelihood of the local community but there will be a possibility of hiring
local community in construction activities.
Health Impacts
There may be dust pollution during the constuction stage to the people who are living
in the project area. However, not major health impacts are anticipated during this phase
if precautions are taken during this stage.
Impact during operational stage
Impact on livelihood
Infrastructure facilities in the surrounding villages will be improved. Scope for self-
employment opportunities such as hotels, vegetable vendors, milk services, news paper
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
75
Centre for Management and Social Research Development Support Specialists
services, courier services and private local transportation are encouraging during the
operational stage. This will create positive impact on the livelihood.
Impacts on Culture and social, family cohesion
Social organisation, Social gathering points of women and any sites of religious and
cultural heritage are unlikely to be affected by the project. No major direct or indirect
impact on social cohesion is anticipated. None of the elements like local political
structure, economy – ecology imbalance, norms, beliefs, values and cultural life are
expected to be hindered with the project. Most families will not be dislocated and
cohesion between members is unlikely to be affected.
New patterns of social organisation and civic spaces
There is no changes and negative impact on Social organisation, Social gathering points
of women and any sites of religious and cultural heritage.
Differential Impacts
Due to relocation and land acquisition loss of income is experienced by women who are
contributing to their families through economic activities. Most of the women work as
daily wage labourers. These impacts can be coped up by providing IGA trainings.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
76
Centre for Management and Social Research Development Support Specialists
PART - II
Social Impact Management Plan
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
77
Centre for Management and Social Research Development Support Specialists
Chapter Eight
Social Impact Management Plan
Introduction
This chapter deals with approach to mitigation, measures to avoid or mitigate impacts,
compensate for impacts, institutional mechanism and roles and responsibilities of
agencies in implementing the social impact mitigation plan (SIMP).
Measures to avoid, mitigate and compensate impact
Measures have been taken to minimize the social impacts associated with land
acquisition by careful design and planning of the project. To minimize negative
impacts various two other alignments were explored by the project authorities. The
present alignment was designed carefully and aligned to avoid residential structures,
commercial entities, common properties and productive agriculture lands. However,
there may be certain unavoidable impacts which needs to be addressed with a well
designed and people centric mitigation plan to reduce friction between the
implementing authorities and community.
Approach to mitigation of social impacts
Recognising the social issues that can arise due to Tandur Bypass Road project (TBRP),
a SIMP has been prepared in line with national and state laws and policies. The SIMP
for the project is based on: The Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013. Based on the provisions of the
RFCTLARR 2013, the following principles will be adopted for mitigation of social
impacts of the project:
In accordance with the R&R measures suggested for the project, all displaced
households and persons will be entitled to a combination of compensation packages
and resettlement assistance depending on the nature of ownership rights on lost assets
and scope of the impacts including socio-economic vulnerability of the displaced
persons and measures to support livelihood restoration if livelihood impacts are
envisaged. Unforeseen impacts will also be mitigated in accordance with the principles
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
78
Centre for Management and Social Research Development Support Specialists
of the resettlement framework for this project. The displaced persons will be entitled to
the following six types of compensation and assistance packages:
1. Compensation for the loss of land, crops/ trees at their replacement cost;
2. Compensation for structures (residential/ commercial) and other immovable
assets at their replacement cost;
3. Compensation of loss business/ wage income (temporary and permanent) and
income restoration assistance;
4. Alternate housing or cash in lieu of house to physically displaces households not
having any house site;
5. Assistance for shifting and provision for the relocation site (if required), and
6. Rebuilding and/ or restoration of community resources/facilities.
Rehabilitation and Resettlement Measures as outlined in RFCTLARR Act, 2013
Compensation for Land
Land will be acquired in accordance with provisions of Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and while
determining the compensation for land, the competent authority will be guided by the
provisions of Sec 26, Sec 27, Sec 28, Sec 29 and Sec 30 of RFCTLARR Act, 2013. The
compensation includes, the multiplying factor of 2 times of higher of guideline value or
average of higher 50% of sale deed rates for last 3 years or any rates consented for PPP
or private projects. In addition, 100% solatium for involuntary acquisition of land will
be added. If the residual land remaining after acquisition is unviable, the owner of such
land/property will have the right to seek acquisition of his entire contiguous
holding/property. Interest of 12% per annum on market value for the period
commencing on and from the date of the publication of notification of the SIA study till
date of the award of the Collector or the date of taking possession of the land,
whichever is earlier
Compensation for structures and farm assets
The replacement value of houses, buildings and other immovable properties will be
determined on the basis of latest PWD Standard Schedule of Rates (SSR) as on date
without depreciation and 100% solatium will be added to the structure compensation.
While considering the PWD SSR rate, PIU will ensure that it uses the latest SSR for the
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
79
Centre for Management and Social Research Development Support Specialists
residential and commercial structures in the urban and rural areas of the region.
Wherever the SSR for current financial year is not available, the PIU will update the SSR
to current prices based on approved previous year escalations. Further, all
compensation and assistance will be paid to displaced persons at least 1 month prior to
displacement or dispossession of assets. Common properties
Compensation for properties belonging to the community or common places of worship
will be provided to enable construction of the same at new places through the local self-
governing bodies like Village Panchayat/Village council in accordance with the
modalities determined by such bodies to ensure correct use of the amount of
compensation.
Compensation for Trees
Compensation for trees will be based on their market value. Loss of timber bearing trees
will be compensated at their replacement cost and compensation for the loss of fruit
bearing trees will be decided by the PIU in consultation with the Departments of Forest
or Agriculture or Horticulture as the case may be. In line with the provision of
RFCTLARR Act 2013, 100% solatium will be added to the assessed value of the trees.
Prior to taking possession of the land or properties, the compensation will be fully paid
and displaced persons will have the opportunity to harvest crops/trees within 1-month
from the date of payment of compensation.
Even after payment of compensation, displaced persons would be allowed to take away
the materials salvaged from their dismantled houses and shops and no charges will be
levied upon them for the same. A notice to that effect will be issued intimating that
displaced persons can take away the materials so salvaged within 15 days of their
demolition; otherwise, the same will be disposed by the project authority without
giving any further notice. Trees standing on the land owned by the government will be
disposed of through prevailing practice by the concerned Revenue Department/ Forest
Department.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
80
Centre for Management and Social Research Development Support Specialists
Resettlement and Rehabilitation Assistance
Minimum R&R entitlements to be provided to the Affected/Displaced Families of the
project as per the RFCTLARR, Act 2013 are presented below:
Provision of Housing Units In Case of Displacement : If a house is lost in rural areas, a constructed house shall be provided as per the Indira Awas Yojana specifications. If a house is lost in urban areas, a constructed house shall be provided, which will be not less than 50 sqmts in plinth area.
Choice of Annuity or Employment : Employment to one family member in case of jobs are created through the project or Onetime payment of Rs.5,00,000 per affected family or Rs.2000 per month for twenty years.
Subsistence allowance: Allowance provided as per the provisions of the Act for completely displaced families to assist them during the period of transition to stability. The unit rate Rs 36000 is provided as per the provisions of the Act.
Subsistence grant for SC/STs: In addition to above, this will be provided to all the displaced SC/ST AFs. The unit rate Rs 50000 is provided as per new Act provisions.
Transportation/shifting allowance: This will be provided to completely displaced by way of losing residential/commercial structures for transporting and shifting the material. The unit rate Rs 50000 is provided as per the provisions of the new Act.
Cattle shed / Petty shops cost : This will be provided to each affected AFs who owns cattle shed / petty shop. The unit rate is Rs. 25,000.
Livelihood assistance: This will be provided to business AFs who will be losing business activity or livelihood. The unit rate is Rs 25000.
Resettlement Allowance: This allowance will be provided for all AFs losing structures/lands/Livelihood. The unit rate is Rs 50,000 provided as per provisions of new Act.
Entitlement Matrix for the Project
The Entitlement Matrix addresses three broad categories of social and economic
impacts, which require mitigation in this project.
o Loss of assets, including land and house;
o Loss of livelihood or income opportunities; and
o Collective impacts on groups, such as loss of common property resources
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
81
Centre for Management and Social Research Development Support Specialists
The first two categories represent direct project impacts on an identified population.
The affected people will be surveyed and registered, and project monitoring and
evaluation will compare long term impact against baseline socio-economic data. The
third category represents an indirect impact, where group members need not be
individually registered. Gains and losses of a group-oriented nature are not quantifiable
in terms of impact on the individual. Mitigation and support mechanisms will be
collectively oriented, and the monitoring of these development efforts will be the
impact and benefits for the groups involved.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
82
Centre for Management and Social Research Development Support Specialists
Table 8.1 : Entitlement Matrix
Sl. No
Type of Impact
Unit of Entitlement
Provisions As per new RFC&T in LARR
Act 2013
Provisions As per RFCTLARR
Telangana Rules 2014 1 Loss of Land
(agricultural, homestead, commercial or otherwise)
Title holders • Compensation at Market
Value of the Land
• The market value
specified in the Indian
Stamp Act, 1899 for the
registration of sale deeds
or agreements to sell in
the area where the land is
situated or
• The average sale price for
similar type of land
situated in the nearest
vicinity area, ascertained
from the highest 50% of
sale deeds of the
proceeding 3 years.
• Value of the assets
attached to land:
Building/Trees/Wells/Cr
op etc. as valued by
relevant Government
authority;
• Solatium: 100% of total
compensation
• Multiplier factor upto 2
• Interest of 12% per annum
on market value for the
period commencing on
and from the date of the
publication of notification
of the SIA study till date
of the award of the
Collector or the date of
taking possession of the
land, whichever is earlier
Same as in RFCTLARR Act 2013
Radial factor is 1.5 times.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
83
Centre for Management and Social Research Development Support Specialists
Sl. No
Type of Impact
Unit of Entitlement
Provisions As per new RFC&T in LARR
Act 2013
Provisions As per RFCTLARR
Telangana Rules 2014 • One-time payment of
Rs.500,000 for each affected household, or,
• Annuity policy that shall pay Rs.2000 per month for 20 years with appropriate indexation to CPIAL
2 Loss of multi-cropped land
Title holders • A multi-cropped land cannot be acquired except under exceptional circumstances
• In the event of acquisition, an equivalent area of waste land shall be developed or equivalent amount shall be deposited with state government for enhancing food security
• This provision is not applicable in case of acquisitions which are linear in nature like railways, electric lines, water canals etc.
3 Loss of House Structure Title holder
of the house
(Displaced
Family)
In addition to the In addition to compensation for land and assistances listed above under S.No.1
• Provision of Housing unit or equivalent cost of the house as per Indira Awas Yojana Specifications5
• Each displaced family from the land acquired shall be given a monthly subsistence allowance equivalent to 3000/- per month for a period of one year from the date of
Same as in RFCTLARR Act 2013
5 Under Indira AwasYojana (IAY), GoI contribution is Rs.70,000 and State contribution Rs.30,000
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
84
Centre for Management and Social Research Development Support Specialists
Sl. No
Type of Impact
Unit of Entitlement
Provisions As per new RFC&T in LARR
Act 2013
Provisions As per RFCTLARR
Telangana Rules 2014 award.
• In addition, subsistence grant of Rs. 50,000 for each affected Scheduled Tribe / Scheduled Caste family displaced from Scheduled area
• Each displaced family shall get a one-time financial assistance of 50,000/- as transportation cost
• Each displaced family shall be given a one-time Resettlement Allowance of 50, 000/- only
• The stamp duty and other fees payable for registration of the land or house allotted to the affected families shall be borne by the requiring body
4 Loss of dwelling of tenants in case of displacement
Tenant
• The benefit of housing shall be extended to any affected family which is without homestead land and which has been residing in the area continuously for a period of not less than three years preceding the date of notification of the affected area
5 Loss of Livelihood to
artisans, small traders
and others
Affected
Family
• One time Grant to Artisans, small traders and certain others of Rs. 25000/-
6 Loss of Cattle Shed /
Petty Shops
Affected
Family
• One time Financial
Assistance of Rs. 25000/-
7 Loss of agriculture Land
/ home stead land
/Structures / Trees /
Wells / Crop
Affected
Families of
SC/ST
Community
In addition to the above
benefits mentioned sl.no.1,
SC/ST families will be
entitled to the following
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
85
Centre for Management and Social Research Development Support Specialists
Sl. No
Type of Impact
Unit of Entitlement
Provisions As per new RFC&T in LARR
Act 2013
Provisions As per RFCTLARR
Telangana Rules 2014 additional benefits:
• Land to be given to each family in every project even in the case of irrigation projects equivalent to land acquired or two and half acres whichever is lower;
• One time financial assistance of Rs. 50,000 per family;
• Families settled outside the district shall be entitled to an additional 25% R&R benefits;
• Payment of one third of the compensation amount at very outset;
• Preference in relocation and resettlement in area in same compact block;
• Free land for community and social gatherings;
• In case of displacement, a Development Plan is to be prepared.
• Continuation of reservation and other Schedule V and Schedule VI area benefits from displaced area to resettlement area.
8. Relocation of displaced families
Displaced families
Provision of Infrastructural Amenities: Infrastructural facilities and basic minimum amenities as mentioned in the Third Schedule of RFCTLAR&R Act, 2013 should be provided by District Administration to ensure a reasonable standard of community life to the
Same as in
RFCTLARR Act 2013
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
86
Centre for Management and Social Research Development Support Specialists
Sl. No
Type of Impact
Unit of Entitlement
Provisions As per new RFC&T in LARR
Act 2013
Provisions As per RFCTLARR
Telangana Rules 2014 displaced people in the proposed resettlement site.
Additional Impact Mitigation Measures
Apart from compensating the impacts as mentioned above the following mitigation
measures will also be implemented as part of SIMP:
Income restoration activity training
Training on Income generation activities such as tailoring, beauty parlour, computer
operating, dairying, electrician, driving, carpentry, plumbing, nursing, mobile repair,
AC and Fridge repairing, spray painting, auto mechanism, welding, electric wiring,
masonary, horticulture, livestock farming, agro based income generation activities will
be provided to the displaced families to take up their alternative livelihood for income
generation.
Placement linked training
Placement linked training will be useful to people who have required qualifications but
do not possess necessary skills. In case of youth, who do not have qualification and
skills, they should be provided with an opportunity to enhance their education
qualification along with their skill set. To serve this twin objectives, the interested youth
shall be enrolled in the bridge courses (preferably computer oriented) which will help
them to integrate with mainstream education/skill training system. At the end of the
course, students shall be able to choose their career options according to their
preference.
Integration of Government schemes
District administration should ensure eligible basic entitlements from the government
to all the affected families. The provision of these entitlements will supplement the
income of the affected household. Out of 143 households, only 80 families are having
MGNREGA job cards and 112 families are having Arogyasri cards. Possession of a job
card provides an opportunity for 100 days of wage employment and health card helps
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
87
Centre for Management and Social Research Development Support Specialists
the affected families to access treatment from hospitals. This can supplement the income
and health of a family. It is advisable to investigate other relevant schemes which can be
targeted towards affected families.
Relocation of Community Properties
The district administration will make appropriate measures in reconstruction of
temples/religious structures, re-allocation of grazing lands. Measure will also be taken
to avoid damage to the existing water bodies or irrigation tanks.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
88
Centre for Management and Social Research Development Support Specialists
Chapter Nine
Institutional Mechanism
This chapter outlines the institutional mechanism for the implementation of the Land
Acquisition (LA) Resettlement and Rehabilitation (R&R) for this Project. The roles and
responsibilities of the various bodies involved in implementation of LA and R&R;
grievance redressal committees and monitoring mechanisms have been presented
below :
Implementation Arrangements
The following institutional arrangements have been provided for in the RFCTLARR Act
2013 and the TRFCTLARR Rules 2014 for the management of rehabilitation and
resettlement of affected families:
1) Commissioner for Rehabilitation and Resettlement: As per section 44(1) of the
RFCTLARRA 2013, the State Government shall appoint an officer of the rank of
Commissioner or Secretary of that Government for rehabilitation and resettlement of
affected families. The Commissioner shall be responsible for supervising the
formulation of rehabilitation and resettlement schemes or plans and proper
implementation of such schemes or plans. The Commissioner shall also be
responsible for the post-implementation social audit in consultation with the Gram
Sabha in rural areas and municipality in urban areas.
2) Administrator for Rehabilitation and Resettlement: As per section 43(1) of the
RFCTLARRA 2013, where the Appropriate Government is satisfied that there is
likely to be involuntary displacement of persons due to acquisition of land, then the
State Government shall, by notification, appoint in respect to that project, an officer
not below the rank of Joint Collector or Additional Collector or Deputy Collector or
equivalent official of Revenue Department to be Administrator for Rehabilitation
and Resettlement.
3) Powers of the Administrator for Rehabilitation and Resettlement: As per section
32 of the TRFCTLARRR 2014, the Administrator shall exercise the following powers
and have the following responsibilities:
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
89
Centre for Management and Social Research Development Support Specialists
a. To conduct a survey and undertake a census of the affected families in the
manner and within the time provided under the TRFCTLARR Rules 2014;
b. To prepare a draft Rehabilitation and Resettlement Scheme;
c. To publish the draft scheme by the mode provided under the TRFCTLARR
Rules 2014;
d. To make the draft scheme available to the concerned persons and authorities;
e. To organize and conduct public hearings on the draft scheme;
f. To provide an opportunity to the Requiring Body to make suggestions and
comments on the draft scheme;
g. To submit the draft scheme to the Collector;
h. To publish the approved Rehabilitation and Resettlement Scheme in the
affected area;
i. To assist the Collector in preparing the Rehabilitation and Resettlement
award;
j. To monitor and supervise the implementation of the Rehabilitation award;
k. To assist in post-implementation audit of Rehabilitation and Resettlement;
and
l. Any other work required to be done for Rehabilitation and Resettlement
Web based Work flow and Management Information Systems (MIS) for Land Acquisition and Rehabilitation and Resettlement
A database will be established, to monitor and regulate the land acquisition,
distribution of compensation and assistance, grievance redressal and financial progress.
The data base will be linked with the existing data base management system for the
project. The details of the PDFs and PAFs and their entitlements will be updated in the
database. LAO will be made responsible for maintenance of the data base. The Collector
will be responsible for the data security. The data amendment will be made by the LAO
after getting approval from the Collector.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
90
Centre for Management and Social Research Development Support Specialists
Disbursal of compensation & assistance amounts and handing over the land to R&B Department
It will be ensured by the PIU that all impacts related to payment of compensation and
allowances, along the stretch will be completed prior to handing over of the stretch to
the R&B Department. The contractor will issue a receipt that the respective stretch has
been obtained free of encumbrances. This is to ensure that once the land is handed over,
it is the responsibility of the contractor to protect the lands from future encroachments.
The PAF will be paid as per R&R entitlements and the subsequent amendments.
Implementation Schedule for R&R Activities
The activities considered to be undertaken in the implementation of SIMP are presented
in Table 8.3 with necessary sequencing of the activities. There will be scope for updating
the schedule during the progress of the implementation. Speedy efforts will be taken to
hand over the lands involved in the acquisition process quickly after fulfilling the
statutory requirements prescribed there in.
The handing over of the site to the contractor has been divided into three phases. The
compensation and resettlement and rehabilitation of PAFs / PDFs are expected to
complete before handing over of site to the contractor. The R&R implementation is also
divided in to three milestones in line with construction activities. The major land
acquisition and R&R activities are expected to be completed within 24 months
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
91
Centre for Management and Social Research Development Support Specialists
Table 9.1 : Implementation Schedule for SIMP
Months
S. No
Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Till Project Completion
1 Constitution of Team � �
2 Mobilization of Team �
3 Joint verification and issue of ID cards
�
4 Conducting of survey �
5 Completion of land acquisition
� � �
6 Shifting of people to alternate Resettlement sites / houses/shops
� � � �
7 Dissemination of list of entitled persons
�
8 Payment of cash allowances � � �
�
9 Training for self-employment opportunities
10 Reconstruction of community assets
� � �
11 Mobilization of impact evaluation agency
� � �
12 Mobilisation of contractors for Resettlement site development works
�
13 Handing over sites to R&B contractors for civil works
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
92
Centre for Management and Social Research Development Support Specialists
Months
S. No
Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Till Project Completion
14 Selection of representatives in GRC
�
15 Finalising estimating of impacts in all milestone stretches
�
16 Commencement of civil construction works
� � �
� Overall Project Milestones
� 1st Milestone � 2nd Milestone � 3rd Milestone
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
93
Centre for Management and Social Research Development Support Specialists
Grievance Redressal Mechanism / Dispute Settlement
As per section 51(1) of the RFCTLARRA 2013, the Appropriate Government shall, for
the purpose of providing speedy disposal of disputes relating to land acquisition,
compensation, rehabilitation and resettlement, establish one or more Authorities to be
known as “the Land Acquisition, Rehabilitation and Resettlement Authority”.
Section 52(1, 2 & 3) specifies that the Authority shall consist of one person only
(Presiding Officer) who will be appointed by the Appropriate Government in
consultation with the Chief Justice of a High Court in whose jurisdiction the Authority
is proposed to be established. The Presiding Officer must be, or have been, a District
Judge; or a qualified legal practitioner who has been practicing for not less than seven
years. The Presiding Officer shall hold office for a term of three years or until the age of
sixty-five, whichever is earlier.
The Appropriate Government shall also provide the Authority with a Registrar and
such other officers and employees as it deems fit. As per section 33 of the
TRFCTLARRR 2014, the salaries, allowances, and conditions of service of the Registrar
and other Officers and employees of the Authority shall be the same as applicable to the
officers and employees of similar grades working in the Judicial Department of the State
Government; while the salaries and allowances of the Presiding Officer shall be the
same as that applicable to a District Judge working in the State.
Any person interested who has not accepted the rehabilitation and resettlement award
may, by written application to the Collector, require that the matter be referred by the
Collector to the Authority for determination. The objection of the interested person may
concern:
a. Measurement of the land;
b. The amount of the compensation;
c. The person who is payable;
d. The rights of Rehabilitation and Resettlement; or
e. The appointment of the compensation among the interested persons
The application objecting to the award will be accepted if the application is made:
a. Within six weeks from the date of Collector’s award, in the case that the
person making the application was present or represented before the
Collector at the time when the award was made; or
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
94
Centre for Management and Social Research Development Support Specialists
b. In other cases, within six weeks of receipt of the notice from the Collector, or
within six months from the date of the Collector’s award, whichever period
shall expire first
However, the Collector may entertain an application within a further period of one year
after the expiry of the stipulated period if there is sufficient cause for not filing it within
the specified time period.
Once the Collector receives the application, he shall refer it to the Authority within a
period of thirty days from the date of receipt of the application. If the Collector fails to
refer the matter within the stipulated time period, the applicant may apply to the
Authority, requesting it to direct the Collector to make the reference.
While making the reference to the Authority, the Collector shall specify:
a. The situation and extent of the land, with particulars of any tress, buildings or
standing crops on it;
b. The names of the persons interested in the land;
c. The amount awarded for damages and paid or tendered, and the amount of
compensation awarded;
d. The amount paid or deposited under any other provisions of the
RFCTLARRA 2013; and
e. If the objection is to the amount of the compensation or the grounds on which
the amount of compensation was determined.
On receiving the reference, the Authority shall issue a notice specifying the day on
which the objection will be determined and direct that the applicant and all interested
persons appear on the notified date. The proceedings shall take place in public and all
persons entitled to appear in any Civil Court in the State shall be entitled to appear,
plead and act in such proceedings.
In determining whether the amount of compensation awarded for land acquisition and
rehabilitation and resettlement entitlements is appropriate, the Authority shall take into
consideration whether the Collector has followed the parameters set under section 26 to
section 30 of the RFCTLARRA 2013. If the Collector’s award is not upheld by the
Authority, the cost of the proceedings shall be paid by the Collector.
If the Authority believes that the compensation should have been in excess of that
awarded by the Collector, the Authority may direct the Collector to pay interest on such
excess at the rate of nine percent per annum from the date on which the Collector took
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
95
Centre for Management and Social Research Development Support Specialists
possession of the land to the date of payment of the excess amount. If the payment of
the excess amount is after the expiry of one year from the date the Collector took
possession, the interest rate applied will be fifteen percent per annum for the period
after the expiry of one year to the time the excess payment is made.
In such cases where the Authority awards compensation in excess of the amount
awarded by the Collector, any person interested in any other land covered by the same
preliminary notification, may submit a written application to the Collector to re-
determine the amount of compensation made to them. Such applications should be
made within three months of the Authority’s awards.
If the Requiring Body or any person aggrieved by the Authority’s award may file an
appeal to the High Court within sixty days from the date of the award. This period
maybe extended by a further sixty days if the High Court determines that the
appellant was prevented by sufficient cause from filing the appeal in the stipulated
period. The high Court will be require do dispose of any such appeal within six
months from the date on which the appeal is presented to the High Court.
Monitoring Mechanism
As per section 50(1 & 2) of the RFCTLARRA 2013, the State Government shall constitute
a State Monitoring Committee for reviewing and monitoring the implementation of
rehabilitation and resettlement schemes or plans. The Committee may, besides having
representatives of the concerned Ministries and Departments of the State Government,
associate with eminent experts from the relevant fields.
Further, as per section 32(1) of the TRFCTLARRR 2014, the State Monitoring Committee
shall have its first meeting for review and monitoring the implementation of the
rehabilitation and resettlement scheme within a month of the date that the said scheme
is approved and published by the Commissioner for Rehabilitation and Resettlement.
Thereafter, the meetings of the Committee shall be held once in three months to review
and monitor the implementation of the rehabilitation and resettlement schemes. The
Commissioner (R&R) shall be the Member Convener.
Section 32(2) of the TRFCTLARRR 2014 prescribes that the experts associated with the
State Monitoring Committee shall be paid an amount of INR 1,000 as sitting fee and
travelling and daily allowance at the rate admissible to the Class-I rank Officers of the
State Government for journeys outside headquarters.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
96
Centre for Management and Social Research Development Support Specialists
Chapter Ten
Analysis of Costs and Budget for Resettlement Action Plan Introduction
The cost for resettlement and rehabilitation and compensation for project affected
families, have been presented in this chapter. The unit rates of structures, land and
other social infrastructure components are also presented here. The budget mainly
includes the cost for land acquisition and R&R assistance.
The number of Project Affected Families is 189 based on the survey and discussions.
The estimated land to be acquired for the project is acres 99.28 ½ guntas of which acres
88.00½ guntas of private agriculture land and acres 11.28 guntas of government land.
The budget estimates are prepared for this number.
The R&R budget for this project is to be paid as per two policy provisions - (i)
Telangana RFCTLARR Rules and (ii) RFCTLARR, 2013.
Cost Estimates as per RFCTLARR Act, 2013
The unit costs are guided by the provisions and costs presented in the new LA and R&R
Act, 2013 (RFCTLA&RR, 2013) and also from the field assessment. The details of unit
rates adopted for different components are presented here. These budget estimates are
prepared for the estimated 189 families of Kokat, Rasulpur, Antaram and Chengole
villages. Number of families displaced and affected is presented in Table. 10.1 below:
Table 10.1 : Projected Number of Families Affected / Displaced
S. No.
Type of Families Affected No of Families %
1. No. of Families losing both dwellings and lands (Displaced)
0 0
2. No. of Families losing only Lands (Affected) 189 100.00 Total 189 100.00
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
97
Centre for Management and Social Research Development Support Specialists
Cost estimates for land
The cost for land is guided by new Act and estimated as follows. For current estimation
purpose land rates are adopted from Sub Registrar Office, Tandur, Government of
Telangana for the effective land rates year 2013. Village wise land rates and cost with
1.5 radial factors are presented in Table 10.2 :
Estimated Cost of Trees
Based on the census survey results it is projected that approximately 606 trees will be affected due to land acquisition from these two villages. Approximate estimated cost of the trees affected is Rs. 26,00,000. The costs are estimated based on the information collected from the field.
Estimated cost of Assets attached to land
According to census survey approximately 24 farm assets are going to be affected due to land acquisition from the surveyed villages. Approximate estimated cost of the farm assets affected is Rs.89,20,000. The costs are estimated based on the information collected from the field through census survey.
Table 10.2: Village wise Land Rates
S. No Village
Number of PAFs
Extent of Land to be acquired
(Acres)
Current Rate per Acre
(Rs.)
Total Amount
(Rs.)
Total Cost with 1.25
Factor
1. Kokat 68 49.06 200,000 9812000 14718000
2. Rasulpur 8 5.35 200,000 1070000 1605000
3 Antaram 54 21.11 ½ 150,000 3166500 4749750
4. Chengole 59 23.16 150,000 3474000 5211000
Total 189 99.28½ -- 17522500 26283750
As per the Act, Compensation for trees will be based on their market value. Loss of timber bearing trees will be compensated at their replacement cost and compensation for the loss of crops, fruit bearing trees will be decided by the PIU in consultation with the Departments of Forest or Agriculture or Horticulture as the case may be. In line with the provision of RFCTLARR Act 2013, 100% solatium will be added to the assessed value of the trees.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
98
Centre for Management and Social Research Development Support Specialists
As per the Act, the replacement value of houses, buildings and other immovable properties will be determined on the basis of latest PWD Standard Schedule of Rates (SSR) as on date without depreciation and 100% solatium will be added to the structure compensation by the Collector.
Estimated cost of Structures Affected
Based on the census survey approximately 2 structures will be lost due to land acquisition. The replacement cost of structure will be estimated based upon the information collected from PWD SSR rates, Government of Telangana. The existing structures are either permanent or semi-permanent. The solatium 100 percent of the SSR rate of structures is included for final compensation. Approximate estimated cost of the structures affected is Rs.5,30,000.
R&R Assistance Costs
Minimum R&R entitlements to be provided to the Affected/Displaced Families of the
project as per the RFCTLARR, Act 2013 are presented below:
Sl. No.
Entitlement Remarks
1 Provision of Housing Units In Case of Displacement :If a house is lost in rural areas, a constructed house shall be provided as per the Indira AwasYojana specifications. If a house is lost in urban areas, a constructed house shall be provided, which will be not less than 50 sqmts in plinth area.
Not applicable as there is no displacement
2 Choice of Annuity or Employment : Employment to one family member in case of jobs are created through the project or Onetime payment of Rs.5,00,000 per affected family or Rs.2000 per
Applicable
As per the Act, in determining the compensation market value of buildings or other immovable property or other assets attached to land or building which are to be acquired the Collector uses the services of competent engineer or any other specialist in the relevant field.
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
99
Centre for Management and Social Research Development Support Specialists
month for twenty years.
3 Subsistence allowance: Allowance provided as per the provisions of the Act for completely displaced families to assist them during the period of transition to stability. The unit rate Rs 36000 is provided as per the provisions of the Act.
Subsistence grant for SC/STs: In addition to above, this will be provided to all the displaced SC/ST AFs. The unit rate Rs 50000 is provided as per new Act provisions.
Not applicable as there is no displacement
4 Transportation/shifting allowance: This will be provided to completely displaced by way of losing residential/commercial structures for transporting and shifting the material. The unit rate Rs 50000 is provided as per the provisions of the new Act.
Not applicable as there is no displacement
5 Cattle shed / Petty shops cost :This will be provided to each affected AFs who owns cattle shed / petty shop. The unit rate is Rs. 25,000.
Applicable
6. Livelihood assistance: This will be provided to business AFs who will be losing business activity or livelihood. The unit rate is Rs 25000.
No business units are affected hence not applicable
7 Resettlement Allowance: This allowance will be provided for all AFs losing structures/lands/Livelihood. The unit rate is Rs 50,000 provided as per provisions of new Act.
Applicable
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
100
Centre for Management and Social Research Development Support Specialists
Component wise detailed budget estimates is provided in Table 10.3 below :
Table 10.3: ESTIMATED BUDGET FOR RAP IMPLEMENTATION FOR PROPOSED PROJECT
Sl. No. Items Unit Quantity
Per unit (In Rs.) Total Amount (Rs)
I Compensation Cost for Land
A Cost with multiplier factor of 1.50 Acres 99.28 ½ -- 26283750
B Value of Trees No. 606 -- 2600000
C Cost of Farm Assets attached to land No. 24 -- 8929000
D Cost of structures attached to land 2 530000
Sub-Total 38342750
E Solatium @100% -- -- -- 38342750
F
12% addl. market value. (on Rs. 38342750) from date of 11(1) to award -- -- -- 4601130
Total Compensation of the Land 8,12,86,630
II Rehabilitation and Resettlement Assistance
G Provision of Housing for Displaced Families
No of PAFs 0 1,00,000 0
H Choice of Annuity for all affected families (Projected)
No of PAFs 250 5,00,000 125000000
I Subsistence allowance for displaced families
No of PAFs 0 36,000 0
J Resettlement Allowance for all affected families (Projected)
No of PAFs 250 50,000 12500000
K Transportation / Shifting Allowance for displaced families (Structures)
No of PAFs 0 50,000 0
L Cattle Shed No. 0 25,000 0
M Loss of business/Livelihood No of PAFs 0 25,000 0
Sub-Total 137500000
Grand-total (I & II)
218786630
DRAFT REPORT
Social Impact Assessment for Tandur Bypass Road
101
Centre for Management and Social Research Development Support Specialists
Total Budget for four villages as per new Act
The budget of RAP includes land acquisition cost and R&R assistance. The estimated
cost of RAP is around Rs. 21.88 crores. The cost for implementation of various R & R
components for the project is presented in Table 10.4.
Table 10.4: Total R&R Costs
Sl.No. Component Amount (Rs.)
1. Land Compensation Cost 8,12,86,630
2. R&R Cost 13,75,00,000
Total 21,87,86,630
Benefits
Most of the losses will be compensated as per the provisions in the RFCT LAR&R Act,
2013. Additionally, interested members of affected families will be provided placement
linked training and employment as per the provisions. Also as mentioned in the SIMP,
interested women will be provided entrepreneurship development training to start
household enterprises support from district administration. The benefits are quantified,
wherever required, using standard denominations. It is suggested to create a detailed
household wise entitlement plan as per the provisions of the act by an expert agency or
local NGO.
Conclusion
It was observed that throughout the project that there are no adverse social costs. All
the costs mentioned above are met through RFCT LAR&R Act, 2013 or through SIMP.
The measures suggested in the act and management plan will address all the possible
impacts. The cost of implementing the measures in comparison with the project cost is
very minimal and hence, the project is viable.