SMS Training

Embed Size (px)

Citation preview

  • 8/8/2019 SMS Training

    1/24

    INTRODUCTION

    Continuous Casting Shop is a part of SMS-2 (steel melting shop-2).

    Continuous Casting Shop consumes most of the production of SMS-2.SMS2 comprises of Converter Shop & Continuous Casting Shop. The

    Converter Shop has 3 converter of 130T capacity each. Tap time of

    converter is 60 min with an average heat of nearly 120 Tons. Tapping is a

    process of pouring of hot metal into the ladle.

    The operation cycle of the converter is as follows: -

    Charging 5min

    Oxygen blowing 20min

    Sampling & temperature measurement 8min

    Correction before tapping 5min

    Tapping 5min

    Nitrogen splashing, coating 7min

    Total 50min

    The converter shop has many sections as described below:

    MIXTURE SECTION: The main function of mixture is to

    supply hot metal (pig iron) to the converter at a fairly uniform temperature &

    composition, in required quantity whenever demanded. The mixture acts as

    buffer between Blast Furnace and Converters.

  • 8/8/2019 SMS Training

    2/24

    There are two mixture of 1300 T capacity each. The pig iron reaches

    mixture in ladle of 100 T capacities. Burners are provided in the mixture to

    maintain the temperature of hot metal. Hot metal from mixture is supplied to

    the converter as per demand.

    SCRAP YARD:

    Scrap yard receives the scraps generated from all over the plant

    in wagons and truck. Two magnet cranes do the unloading / loading of

    scraps. Scraps are supplied to the converters, which is melt with hot metal.

    LADLE PREPARATION SECTION:

    The steel-casting ladle, required for tapping of steel from converter is

    prepared here. There are 26 ladles of 130 T capacities each. These entire

    ladles are of bottom purging through porous plugs and fitted with slide gate

    system for pouring of steel for casting. The ladles are lined with magnesia

    carbon bricks to with stand the heat and erosion during treatment in the

    VAD, LF, & RH units.

  • 8/8/2019 SMS Training

    3/24

    SLAG POT HANDLING SECTION:

  • 8/8/2019 SMS Training

    4/24

    The slag produced during steel making is poured out of the

    converter into 16m3 slag pots. The tilting slag car are taken by locomotives

    to slag yard where the slag cups are tilted and emptied.

    BLUK MATERIAL HANDLING SECTION:

    The following bulk material are handled in this section:

    Lime Calcined dolomite Lime stone

    Coke Raw material Iron ore

    Lime and calcined dolomite are used as fluxes, iron ore and limestone

    are used as coolants. Coke is used for preheating the converter and coating.

    These materials are and charged into the converter. Very sophisticated

    microprocessor based system, of weighing and then charging of bulk

    material into converter, is installed in the main control pulpit.

    GENERAL DESCIRPTION OF CONTINUOUS CASTING

    PROCESS: -

    Continuous Casting is a process of casting without interruption.

    Liquid steel form the converter is taken to the Argon Rising Unit. Argon is

    blown into the ladle. This homogenizes the temperature and composition of

    the molten steel. Aluminum may be added to it to reduce oxygen content.

    Ferro alloy are added are for trimming addition.

  • 8/8/2019 SMS Training

    5/24

    The molten steel in the ladle is then delivered to a reservoir above the

    continuous casting machine called a tundish. The flow of steel from the

    tundish into one or more open-ended, water-cooled copper mould is

    controlled by a stopper rod or a slide gate.

    To initiate a cast, a dummy bar is inserted into the mould and sealed

    so that the initial flow of steel is contained in the mould and a solid skin is

    formed. After the mould has been filled to desired height, the dummy bar is

    gradually withdrawn at the same rate at which casting is done.

    The initial liquid steel solidifies on a suitable attachment of thedummy bar so that the cast stand can be withdrawn through the machine.

    Solidification of a shell begins immediately at the surface of the copper

    mould and the casting speed is such that the shell thickness is capable of

    withstanding the pressure of the molten core upon exiting from the copper

    mould.

    To prevent sticking of the frozen shell to the copper mould, the

    mould is oscillated during the casting operation and a lubricant is added to

    the mould, the strand is mechanically supported by rolls below the mould

    where secondary cooling is achieved by spraying cooling water or air mist

    onto the strand surface to complete the solidification process. After the stand

    has fully solidified, it is cut into desired length by cut off torch (normally an

    oxy-acetylene torch), which moves along with the stand. This final portionfor disengagement and storage of the dummy bar.

    MODIFIED SLAB CASTING MACHINE

  • 8/8/2019 SMS Training

    6/24

    Different Sections:-

    Continuous Casting consist of following sections:

    Argon rinsing Bay Tundish preparation Bay

    Casting Bay

    VAD (Vacuum Arc Degassing Unit)

    Ladle Furnace

    RH Degasser

    Discharge Bay

    Slab & Bloom Storage Yard (SBS)

    Mould Repair Shop

    Casting Powder Plant

  • 8/8/2019 SMS Training

    7/24

    DIFFRENT PARTS IN CONTINEOUS CASTING MACHINE: -

    Ladle with slide gate opening

    Lift and turn mechanism Hydraulic cylinder for opening slide gate

    Tundish car

    Stroud holding and adjusting mechanism

    Stroud

    Tundish nozzle with tundish block integral

    Stopper

    Stopper mechanism

    Nozzle (submersed)

    Mould

    Mould supporting & oscillating frame

    Foot roll integral with mould

    Five roll set

    Pinch roll set

    Dummy bar

    Roll table

    Oxyacetylene gas cutting system

    Roll cooling system

    Hydraulic system

    Roll bearing lubrication system

    Roll drive system and reducer

    Transfer car and cranes

  • 8/8/2019 SMS Training

    8/24

    BREAKDOWN MAINTENACE: -

    Break own maintenance is a process of maintaining the machine component

    and equipment as soon as it is detected. It is done so because due to failure

    of that machine component or equipment caster operation will be directly

    affected and even it may bring it to rest immediately. In it as soon as fault or

    failure is detected operation is brought to rest and that component is change

    by spare one if available.

    Before going for maintenance following steps are taken:

    Machine is switched off and operation is stopped

    Machine is allowed to cool down. It takes about 3 hours for

    cooling. It is cooled through secondary equipment and cooling water

    It may be the case that cooling of machine is not require for

    maintaining that part bur for starting the process if it is essential

    Then the water supply is stopped and takes full shut down of the

    machine. For this shut down form is filled up.

    Next step in integral inspection of machine. All pinch roll are kept in

    lifted position. Inspector goes inside the machine and check for bearings and

    rollers and breakdown & minor defect list is prepared

    Defective rollers and other broken or failed components are changed

    by spare one.

    Local alignment is checked.

    Full machine alignment is checked and correction is made for that.

  • 8/8/2019 SMS Training

    9/24

    Top sets are fixed and roll gap is fixed.

    Secondary cooling system is checked.

    A SAMPLELIST OF BREAKDOWN MAINTENANCE : -1. Tundish car (Hoist drive) : -

    Limit switch was by passed thereby damaging the locking nut of bolts

    reducer.

    2. Pinch rolls (Pinch roll stand) : -

    Pinch roll no 03 roller broken.

    3. Dummy bar unit (dummy bar unit) : -

    Dummy bar link (first) broken.

    4. Receiving roll table (Drive for roller rotation): -

    Bearing broken thereby damaging gear teeth.

    CONDITION BASED MAINTENANCE (CBM)(PROTECTIVE MAINTENANCE)

    Condition based maintenance is a type of preventive maintenance. During

    break down maintenance and after certain no of heats machine in brought to

    rest and all the components and equipments are checked and checklist is

    prepared about the defect and its extent. It is also mentioned that how long a

    defective component may work properly without breakage. According to

    that schedule of preventive maintenance is prepared. A sample checklist of

    component is as follows:

    (For slab caster at BSP Bhilai)

  • 8/8/2019 SMS Training

    10/24

    EQUIPMENT JOB

    PARENT EQUIPMENT: Lift & turn stand

    GENERAL:

    Check for smoothness of

    operations during rotation

    DRIVE FOR TURNINIG:

    Check brakes and regulation

    Check main gear auxiliary reducer bull gear reducer

    Check lubrication of bull gear

    FRAME STRUCTURE OF BODY:

    Check condition of plate form and rolling

    PARENT EQUIPMENT: Tundish car

    GENERAL:

  • 8/8/2019 SMS Training

    11/24

  • 8/8/2019 SMS Training

    12/24

    SECONDARY COOLING BUNKER:

    Check bunker plate and structure

    PARENT EQUIPMENT: Pinch Roll

    GENERAL:

    Check condition of plate form & rolling

    DRIVE FOR PINCH ROLL:

    Check the condition of PR brakes

    Check lubrication spindle pusher

    PINCH ROLL STAND: Check top frame fixing firm locking, condition of spindle locking &

    slide blocks

    Check the condition of buffer spring side pins

    Check the condition of rollers bearing & uprooting rollers

    SECONDARY COOLING SYSETM: Check rollers cooling outlet flow of water from rolls

    TIME BASED MAINTENANCE

    (CAPITAL MAINTENANCE)

    From experience and experiments it is decided that a machine will operate

    satisfactorily for certain no of heats after that machine is maintained

    completely over all machine is dismantled and goes for repair in different

  • 8/8/2019 SMS Training

    13/24

    shops. There in hops they see what are minor and major problem in the

    component or equipment & then they rectify all. The problem and

    equipment is prepared completely to work in machine. In this maintenance

    process check list of defects and maintenance is prepared.

    MAINTANANCE OF DIFFERENT PARTS OF MACHINE:

    These are mainly set of rollers and there failure criterion is different thus

    maintenance procedure is different.

    A) MAINTENANCE OF FIVE ROLL & EIGHT ROLL SET:

    FAILURE CRITERION: Following are the main failure criterion for five

    & eight roll set:

    1. Roller bending

    2.

    Bearing failure3. Misalignment

    POSSIBLE CAUSES:

    1. Bearing failure may be due to improper greasing and improper

    secondary cooling may also lead to bearing failure.

  • 8/8/2019 SMS Training

    14/24

    2. Low temperature of metal from ladle and stoppage of strand in the

    rollers and low bending strength of the rollers may lead to the permanent

    bending of rollers.

    3. Misalignment is cause by both bearing failure & roll bending.

    REPARE PROCESS:

    1. Roller set is brought from the shop is dismantled completely.

    2. All the rollers are removed form the strand and are fully opened.

    3. There are two bearing in each side of roller, which is removed by

    removing outer covering from the shaft.

    4. Bearings are checked if any problem is found bearing is removed &

    spar bearing is placed.

    5. Spar rollers are placed on the frame & tighten through bolts.

    6. In case of five roll set bottom set is bigger radius this set is first

    maintained.

    7. First and last row of rollers are maintained at a height of 310mm

    from reference plane using plate below the shaft.

    8. Above the reference plane plate of different thickness based on cross

    section required9. Then upper or smaller radius at the op is placed & is locked with

    bottom with by studs and bolts.

    10. Now rollers gap is maintained using tiller gauge & taking correction

    factor for shrinkage of slab.

  • 8/8/2019 SMS Training

    15/24

    ROLL GAP FROM TOP TO BOTTOM

    FOR FIVE ROLL SET GAP (mm)

    1 201.70

    2 201.58

    3 201.45

    4 201.33

    5 201.20

    FOR EIGHT ROLL SET GAP (mm)

    1 201.20

    2 201.13

    3 201.06

    4 200.99

    5 200.92

    6 200.85

    7 200.77

    8 200.70

    11. Only different fire roll & eight roll repair is that in eight roll set is small radius

    bottom set is larger set.

    MAINTENANCE OF PINCH ROLL:

    CRITERION OF FAILURE: Following are the main criterion for rejecting

    the roll.

  • 8/8/2019 SMS Training

    16/24

    Roller bending Max allowable 2mm

    Bearing failure

    Fire cracks Max allowable depth is 30 to 40 mm.

    Roller breakage

    Bearing surface failure of roller.

    POSSIBLE CAUSEC:

    1. Bearing failure may be due to improper lubrication bending of roll bulging of strand etc.

    2. Roller bending may be due to improper cooling of rolls bulged strand

    and stoppage of standing the roll due to stoppage of process.

    3. Fire cracks due to composition of roller material & was not detect

    earlier.

    REPAIR PROCESS:

    To make the blended rollers concentric rollers are turned on lathe to

    make concentric.

    Bearing failure is maintained by replacing break bearing by spare one &

    damaged one is sent for repair.

    Roller rejected.

    From pinch rolls is used in roll table set where cutting by oxyacetylene

    is done if it is not totally breaked.

  • 8/8/2019 SMS Training

    17/24

    Breaked rolls con not be repaired thus they become scrap.

    If bearing surface is wearied due to breaked bearing or due to lack of

    lubrication it is sent to reclamation and is machined there to bring it to the

    proper size.

    .

    MAINTENANCE OF ROLL TABLE:

    Failure criterion:

    Following are the failure criterion of roll table

    a) Breakage of rolls.

    b) Excessive wear of rolls due to molten metal facing and cutting

    flame during cutting process of slab.

    Maintenance of mould: maintenance of mould is done in mould repair shop.

    Criterion of mould failure:

    Leakage of cooling water from the copper wall gap. There should be no leakage

    normal working pressure is 7kgf/cm 2 during the operation.

    Improper gap between two walls at corner. This cause bursting of skin formedduring primary cooling and can lead to breakout also. Max allowable gap for satisfactory

    operation is 0.2mm but normal practice is 0.1mm(safer side).

    Sticking of metal on walls due to break out of skin and all.

  • 8/8/2019 SMS Training

    18/24

    In case of capital it is preferred to repair because it is to bring the initial position,

    although it is capable of working satisfactorily for some more heats to secure no

    interruption in process for long time.

    Primary cooling water may not be soft thus it may case rusting in the passage and

    may create problem in proper distribution of water through out the mould walls.

    Repair process:

    Repair process of mould consist of following steps be followed:

    Dismantling of mould

    Machining copper walls

    Assembly of mould

    Check the comer gap rectify if required

    Put abestor mills board fix up sheets

    Check alignment of mould.

    Blast Furnace

    Blast furnace department consists of 7 blast furnace three of them are of 1033m 3 useful volume and production is of about 2000T/day, three of themare 1719m 3 useful volume and production of about 2500T/day, and blastfurnace no.7 is of 2000cum useful volume and produce 3500T of hotmetal/day. The annual revised rated capacity for hot metal is 4.5MT withonly five-blast operation in operation.

    There are 3 main section of the department:

    1. Raw material section

    2. Furnace section

    3. Auxiliary section

  • 8/8/2019 SMS Training

    19/24

    Raw material section:

    The raw materials used for the production of pig iron are:

    Coke (fuel), Iron Ore, Sinter (Fe-bearing material), Limestone (Flux) & Mn-

    Ore and Quartzite (additives).

    1. Fine ore : 85,000 tones

    2. Iron ore (lumps) : 1,80,000 tones

    3. Limestone : 40,000 tones

    4. Mn.Ore : 11,000 tones

    5. Quartzite : 3,000 tones

    Furnace Section:

    Blast Furnace is a vertical shaft furnace, enclose in a welded shell, lined with

    fire-clay bricks of high alumina content. The hearth bottom, hearth, bosh and

    the cylinder part of the bosh are cooled by means of plate coolers. In the

    shaft, there are cantilever cooler. The walls of the furnace top are protected

    by steel refractory lined plates. In BF#7 for cooling the shaft, there are

    inverted L shapes cooler.

    TOP CHARGING EQUIPMENT

  • 8/8/2019 SMS Training

    20/24

    The bell type chaging device (exhisting in BF 1,2 & 3) has a big bell, small bell with hoppers, gas seal, and receiving hopper; and receives raw materialfrom an oval shaped receiving hopper. In BF-3 RCU (Rotating ChargingUnit) is provided, by means of which charging can be distributed in desiredsector inside the furnace BFs. #4,5,6 & 7 are equipped with paul gate, upper sealing valve, lower material gate and lower sealing valve. This system alsohas a gearbox to operate a rotating chute. The latter distributes the materialinside the furnace peripherally in different rings. This facilities better distribution of charge inside the furnace.

    CHARGING PROGRAMME

    To facilitate smooth working of furnaces, the following charging programme is normally practiced.

    A. Programme COC / COOCC / CCOOC

    B. Programme CCOO

    Each charging cycle consist of 3 programmes of A & B exclusively or in

    combination depending on peripheral conditions. Generally in Bell-less Top

    Furnace the programme selected is B i.e. CCOO, C=COKE; O=NON-

    COKE i.e. ore, sinter, Mn ore, lime atone or quartzite.

    STOVES

    Form bottom of the furnace the hot blast is blown into the furnace

    through tuyers with the help of turbo-blowers & hot blast stove.

  • 8/8/2019 SMS Training

    21/24

    There are 3-4 stoves for each furnace. Each stove consists of a

    combustion chamber and a regenerative chamber. Stoves are kept on blast

    for 2 hrs. the following are the provision in a stove : cold blast valves (1) ,

    Hot blast valve (2) , Chimney valve (2) , By-pass chimney valve (3) , gas butter fly valve (1) , Gas burner (1) , Air fan (1).

    Blast of Air reaches as follows:

    Cold blast CB Main Stoves HB Main Bustle pipeGooseneck pipe Tuyer stock Furnace

    The liquid product of smelting namely pig iron and accumulator in the

    hearth. Slag floats on the Pig Iron because of difference in density.

    FLUSHING OF SLAG: TAPPING AND DISPOSAL OF HOT METAL

    The furnace is provided with a tap hole, which is enclosed in a steel cast

    frame and is cooled by two Tap hole coolers, which have their own supply

    of water.

    The hot metal is tapped out at an interval of 1-2 hrs depending upon the

    furnace condition. The usual way of opening the tap hole is to drill the tap

    hole until the skull is reached. Oxygen lancing is carried out melt the skull.

    The hot metal continues to flow down the bend runner form, which it is

    diverted into individual metal ladles. At the end of tapping the tap hole is

    closed with mudgun, which is electrically or hydraulically operated.

  • 8/8/2019 SMS Training

    22/24

    The hot metal ladle is a refractory lined 100 T capacity containers. It

    transport hot metal form Blast Furnace to SMSs, PCM and Foundry. The

    distribution of hot metal is 90% to SMS, 3% to foundry and rest to Pig

    Casting Machines.

    Fleets of 78-iron ladles car are available, out of which normally 48 are incirculation in cases all seven furnace are in operation.

    SPECIFICATION OF RAW MATERIALS

    Material Chemical Analysis Specification Size

    Iron Ore Fe 64.2% min 10-40 mm

    SiO 2 2.5+-0.5%

    P 0.1 % max

    Al2O 3 / SiO 2 0.88 % max

    _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

    Limestone CaO 39.5 % 0.1 % 6-50 mm

    SiO 2 6.5 +- 0.25 %

    MgO 8.5 +- 0.5 %

  • 8/8/2019 SMS Training

    23/24

    _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

    _ _ _ _

    Mn. Ore Mn 30 %min 25-80 mm

    SiO 2 30 % min

    Al2O 3 5 % min

    P 0.30 % max

    Source of Raw Materials:

    1. Iron Ore . Dalli, Rajahara Mines

    2. Lime Stone . Nandini Mines

    3. Manganese . Balaghat Mines

    4. Sinter . Sintering Plants (SP-2, SP-3)

    5. Coke . Coke Ovens (Coke sorting plants)

    6. Converter Slag . SMS l l

    Requirements for producing of one ton of Hot Metal

  • 8/8/2019 SMS Training

    24/24

    (Specific Consumption)

    Iron Ore . 459 Kg

    Lime Stone . 850 Kg(Depending on Sinter Usage)

    Manganese . 800 Kg(50% in burden)

    Sinter . 35 Kg

    Coke . 08 Kg

    Converter Slag . 30 Kg

    Services / By-Product per ton of Hot Metal

    Steam . 120 Kg

    Compressed Air . 25 M3

    Air Blast . 2600 M 3

    Electricity . 33.7 Kwh

    Water . 40 M 3

    Slag . 435 Kg

    Flue Dust . 25 Kg

    BF Gas . 1830 Kg(CV-800Kcal / M3)