Upload
lamdiep
View
217
Download
0
Embed Size (px)
Citation preview
ukpowernetworks.co.uk
Smarter Network Storage Design and planning considerations for large-scale distribution-connected energy storage (SNS1.2)
2 | Smarter Network Storage - design and planning considerations
6.ObtainingPlanningConsents 34
6.1 PlanningConsentsatLeightonBuzzard 35
6.2 AlternativeLocationsConsideredtoMeet
SequentialTests 35
6.3 Pre-ApplicationLocalConsultation 37
6.4 ConsultationResponses 37
6.5 PreparationandSubmissionofPlanningApplication 38
6.6 NeedforCommunityInfrastructureObligations 40
6.7 KeyComponentsoftheSection106Agreement 40
7.DesignImpacts 41
7.1 BuildingExteriorCivilDesign 42
7.2 FloodMitigationDesign 44
7.3 BuildingSurroundings 44
7.4 StorageFacilityInternalCivilDesign 46
7.5 StorageFacilitySafetyDesign 47
7.6 StorageFacilityElectricalDesign 48
8.LearningObtained,Conclusion
andRecommendations 50
8.1 LearningSummary 51
8.2 Conclusion 53
Appendices 55
Appendix 1 ResidentsConsultationDocument 55
Appendix 2PlanningTimelineSummary 60
Appendix 3OriginalBuildingLayoutDesignfor
8MW/24MWh 62
Appendix 4FinalBuildingLayoutDesignfor
6MW/10MWhProject 64
Appendix 5FuturePotentialBuildingLayout
Designfor8MW/17MWhProject 66
1.Introduction 4
1.1 Background 5
1.2 ReportScopeandObjective 5
2.DesignandProcurementFundamentals 7
2.1 StateoftheBatteryStorageIndustry 10
3.DesignInputs 12
3.1 SiteSelectionforStorage–
Whencanstoragebeused? 13
3.2 SiteLocation–LeightonBuzzardPrimarySubstation 14
3.3 ApplicationRequirements 17
3.4 Safety 21
3.5 Budget 23
4.InitialDesignOutputs 24
4.1 TechnologyandSupplierSelection 25
4.2 ModuleSize 26
4.3 StorageHousing 27
5.ThePlanningProcess 29
5.1 PlanningPermission 30
5.2 Determination 30
5.3 TypeofApplication 31
5.4 Timescales 31
5.5 PlanningClassifications 31
5.6 Conditions 32
5.7 Section106Agreements 32
5.8 DevelopmentControl 32
5.9 NationallySignificantInfrastructure 33
Contents
Smarter Network Storage - design and planning considerations | 3
Figures
Figure1 InteractionofStorageDesignDriversand
KeyDesignChoice/Impact 9
Figure2 High-LevelCriteriaAppliedforInitial
SiteSelection 13
Figure3 LoadProfileforTwoHighDemandDays
in2010atLeightonBuzzardSubstation 15
Figure4 LeightonBuzzardReinforcementOptions 15
Figure5 AerialPhotographoftheLeighton
BuzzardSite 16
Figure6 IllustrationofPeakPowerandEnergy
Requirements 18
Figure7 WinterPeakDemandTrendatLeighton
BuzzardPrimary 19
Figure8 AlternativeSitesConsidered 36
Figure9 SummaryChartofConsultationResponses 39
Figure10 SupportingStudiesandDesignandAccess
StatementStructure 39
Figure11 ProposedVisualisationandElevations
withLandscaping 43
Figure12 ProposedLandscapePlanatWoodmanClose 45
Figure13 Single-LineElectricalDesign 49
Smarter Network Storage - design and planning considerations | 5
development rights by licensed DNOs; in this instance full
planning approval was required for the installation, as the
adjacent landwasandnothistorically used for operational
purposes. This provided the opportunity to generate
additional learning around the preparation and completion
of theplanningprocesswhichmaybe valuable to support
increasing deployments of storage, either by DNOs, or by
third-parties,wheretheneedforplanningconsentsislikely
tobemorecommon.
1.2ReportScopeandObjective
This report provides a summary of the key learning and
considerationsrelatingtothepracticalissuesinthedesignand
planningoflarge-scaledistribution-connectedelectricalenergy
storage. It covers the learning generated from successfully
securingplanningconsenttobuildanelectricalenergystorage
deviceatthetrialsite,adjacenttotheprimarysubstationat
LeightonBuzzard,andhowthisinfluencedthedesignsofthe
storagefacility.
Thisreportrelatestobatterystorageusingtechnologythatis
commercially available in 2013. A number of other storage
technologiesareavailableatdifferentstagesofmaturityand
all have advantages and disadvantages. The Department
forEnergyandClimateChange(DECC)has recentlyawarded
fundingwhichisseekingtoachievecostreductionsandbring
forwardotherpromisingtechnologies.
The report also provides an introduction to the planning
consentprocess,whichisrequiredformostnewstructuresand
buildings,andisalsorequiredforthechangeofuseofexisting
buildingsorsites.TheplanningsystemforEnglandandWalesis
setoutintheTownandCountryPlanningAct1990asamended
bymorerecentlegislation.
Thisdocumentformsoneoftwomaindocumentsthattogether
providetheevidencerequiredtodemonstratecompletionof
1.1Background
Energy storage is a key source of flexibility that can help
addresssomeofthechallengesassociatedwiththetransition
toalow-carbonelectricitysector.Storage,asidentifiedbythe
SmartGridForum,isoneofthekeysmartinterventionslikely
toberequired inthefuturesmartgrid.However,challenges
inleveragingthefullpotentialofstorageontransmissionand
distributionnetworkstobenefitotherindustrysegments,anda
lackofscaledemonstrationsarecurrentlyhamperingtheefficient
andeconomicuptakeofstoragebytheelectricitysector.
TheSmarterNetworkStorage(SNS)projectaimstocarryouta
rangeoftechnicalandcommercialinnovationtotacklethese
challengesandfacilitatemoreefficientandeconomicadoption
ofstorage.ItisdifferentiatedfromotherLCNFelectricalstorage
projects by its demonstration of storage across multiple
parts of the electricity system, outside the boundaries of
the distribution network. By demonstrating this multi-
purpose application of 6MW/10MWhof energy storage, the
project will explore the capabilities and value in alternative
revenue streams for storage, whilst deferring traditional
networkreinforcement.
The project aims to provide the industry with a greater
understandingandadetailedassessmentofthebusinesscase
andfulleconomicsofenergystorage,helpingtoaccommodate
increasing levels of intermittent and inflexible low carbon
generation.Theprojectwasawardedfundingof£13.2million
byOfgem,undertheLowCarbonNetworkFund(LCNF)scheme
inDecember2012andwilllastfouryears,fromJanuary2013
toDecember2016.
The energy storage facility is due to be deployed adjacent
to a typical UK Power Networks 11kV primary substation in
Leighton Buzzard where it is needed to support security of
supply.Although such substation sites are typically classified
as‘operationalland’andthereforeprovideforsomepermitted
6 | Smarter Network Storage - design and planning considerations
thefirstformalSuccessfulDeliveryRewardCriteria(SDRC9.1)
milestonefortheSNSproject.
The SDRC is designed to show that successful early capture
anddisseminationoflearningrelatedtothepracticalissuesin
thedesignandplanningoflarge-scaledistribution-connected
electricalenergystoragehastakenplace,andthisdocument
formsthemainlearningreporttobesharedwithstakeholders.
Other evidence for this SDRC comprises minutes and notes
captured from meetings with the local planning authorities
andenvironment agency, planning consents approval at the
trialsite,anddesignapprovalofthestoragefacilitywhichare
availabletoOfgemonrequest.
Thetargetaudienceforthereportisotherdistributionnetwork
operators who may be looking to deploy further electrical
energy storage capacity to support efficient distribution
network operation; however the report will also have
relevanceforthefollowingstakeholders:
• Third-party storage developers looking to develop and
deploy storage for commercial operation, including selling
flexibilityservicestoDNOs;
• LocalAuthorities,whomayincreasinglyneedtounderstand
thespecificofenergystoragetechnologiesincludedinplanning
applicationsasthenumberofUKdeploymentsincreases;and
• Storagemanufacturersandtechnologyproviders,tofacilitate
understandingofthemainconsiderationsandrequirements
indeployingtheirsolutionswithintheUKnetworkoperator
environment.
Smarter Network Storage - design and planning considerations | 7
Design and Procurement Fundamentals
2
8 | Smarter Network Storage - design and planning considerations
re-purposedfromotherrenewable(e.g.windfarm)applications,
thiswilllimitthechoiceatwhichDCbus-barvoltageissetand
istypicallynon-flexibleforaparticularmanufacturer.Inalmost
alldesigns,batterieswerestackedverticallyandconnectedin
series,sothat,ineffect,thepotentialbetweenthebottomof
thebatterystackatfloorlevelandthetopofthebatterystack
wasequaltotheDCbus-barvoltage.Assuch,thelimitedchoice
ofDCbus-barvoltagedeterminestheextenttowhichafacility
canuseheighttomitigatelandarea.Heightislimitedinthe
reversedirectionbyplanning limitationsbasedonthevisual
impacttoneighbouringbuildings,andinthecaseofSNS,the
needtoraisethebuildingoutofafloodplain.Nevertheless,in
aconstrainedfoot-print,thechoiceofDCbus-barvoltagecanbe
significantandSmarterNetworkStoragehasseenamaterial
impactof7MWhoraround25%-30%betweendesignsusing
differentcellmanufacturersandDCbus-barvoltages.Onspace
constrained sites, the recommendation is to consider theDC
bus-barvoltagewhichwillmaximisetheavailableheight.On
ruralsiteswherethebuildingheightdeterminestheextentof
visualimpact,butlandareaisbothcheaperandmorereadily
available, then consider a DC bus-bar voltage that will
minimiseheight.
Thesecondconstraintistheminimumquantumofstorageand
ratingwhichtheinstallationmusthaveineventofafailure.This
criticallydeterminesthenumberandratingofconverters,since
a space-efficient design with a single converter, if it were
achievable, offers no redundancy. The number of converters
andtheirseparationdictatesthespace(withinaconstrained
footprint)availableforenergyorMWhcapacity.
The third constraint is fire suppression arrangements and
maintenancerequirements.Theprojecthasseenacirca1MWh
impact on a space-constrained site as a result of fire
segmentationand lifting/handling requirements tomaintain
andreplacebatteryracks.Whilstthesecondcanbeviewedas
atrade-offwiththedown-timethatisacceptable;i.e.agreater
Intheprocessofplanninganddesignfordistribution-connected
storagetobeownedandoperatedbyadistributionnetwork
operator, thechoiceofsiteforstorage isclearlyasignificant
decision, and requires some very careful analysis in order to
ensurestorageislocatedappropriately.However,fordistribution
networkscalestorage,thechoiceofsiteislikelytobedrivenfirst
andforemostbynetworkneedandsotheprimaryapplication
willtypicallyberelatedtoresolutionofanetworkissue.
Thefirststeptotake,evenpriortoplanninganddesignofany
energy storage project, is to identify network issues or
operationalconstraintsthatrequireintervention,anddetermine
if energy storage could provide an effective solution as an
alternativetoconventionalupgrades.
Once a network need is identified that can be potentially
resolvedbystorage,thehighleveldesignforthestoragewill
beaffectedbyanumberofdrivers.Thesedriverswillallhave
impactsonthefinaldesignchoices,suchasthenatureofthe
storage technology, the type of supplier(s) approached and
howitisdeployed.Inturntheseimpactsmayhaveareciprocal
impactonsomeoftheotherkeydesignchoicesanddrivers.
Forexample,thechosentechnology,modulesizeandmethod
ofhousingmaywellimpactboththecoolingrequirementand
thenoiselevel.Theywillcertainlyaffectthefootprintofthe
facility and together these will impact any local planning
consentsrequired.
Thiscreatesawiderangeofinteractionsforthefundamental
selection and design of distribution network scale energy
storage. Figure 1 illustrates this interaction between drivers,
designchoicesandimpact.
ThekeyfindingsfromthedesignprocessthatSNShasgone
throughareasfollows:
TheexperienceofSNShasdemonstratedthatconvertersare
Smarter Network Storage - design and planning considerations | 9
packing density can be achieved at the expense of longer
down-timeandmorecomplicatedoperationstoreplacebattery
failures,thefirstremainsanecessitywithcurrenttechnology.
Figure 1 – Interaction of Storage Design Drivers and Key Design Choice/Impact
Drivers ApplicationRequirement
Safety Expansion Site/Location Budget
KeyDesignChoice
Technology LeadSupplier
MainHousing
ModuleSize
Impact Noise LevelCooling
RequirementFlood
MitigationPlanning
RequirementFire
SuppressionFoot print
Need
MeetingNeed
Conventional StorageOther
e.g. DG, DM
ReinforcementRequirement
10 | Smarter Network Storage - design and planning considerations
tochoosefrom;andtheextenttowhichanyindividualdesign
canbetailored(ornot)toaparticularsite.
Thelevelswhichmakeupafunctioningbatterystoragesystem
areshownbelow:
2.1StateoftheBatteryStorageIndustry
Itisimportanttostartbyclarifyingboththeelementsthatmake
upabatterystoragefacilityatdistributionscale,andthestatus
ofthesupplychain.Thisisfundamental,sinceitdeterminesthe
extenttowhichdifferentandcompetingdesignsareavailable
Level
5.
4.
3.
2.
1.
Function
Storagedispatch
Scheduling
Powerconverterfunctions
Battery Cooling Firmware
control control
system system
Batteries Cooling AC/DC
system converter
Comment
Thisallowsoneormoreancillaryservice(s)(suchasfrequency
response)tobeprovidedfromacrossafleetofstoragedevices.
Itisunlikelytobeimplementedwithoutalsohavinganinterface
tomarketmetricsandbuy/sellprices.
Thisallowsadayorweek’sworthofactivitiestobelefttorunon
thestoragedevice.
This implements ‘closed loop’ algorithmic control similar to a
heatingthermostat,allowingthesystemtorespondandadjust
tomeetaset-pointratherthansimplychargingordischarging
blindly.
This level is similar to thedriversonyourPC,needingdetailed
knowledgeofthehardwareitistalkingto.
Thephysicalhardware.
Smarter Network Storage - design and planning considerations | 11
typeofsystemintegratorconcentratingsolelyonstorage(for
example,XtremePower,ZenEnergy)andspecialistsinstorage
controlsoftware(YounicosandGreensmith).
The industry is widely accepted to be at an early stage,
withnewnichesbeginningtoemerge,butyettobeprovenas
long-termpillarsof thesupplychain;andtechnology largely
beingre-purposedfromothersectors.
Thishastwoimplications:
a) The twomost fundamental components, thebatteryand
thepowerconverter,arelikelytobeinheriteddesignsfrom
othersectors
b)DNOs and TNOs need to seek, and suppliers need
tobewillingtoprovide,informationaboutfinancialstability
throughouttheentiresupplychain
TheSNSprojectincorporatesallthevariouslevelsshowninthe
tableaboveanddoesthisthroughasupplychainconsistingof
S&CElectric,SamsungSDIandYounicos(levels1,2and3),AMT
Sybex(level4),andKiwiPower/SmartestEnergy(level5).
The supply chain as it currently stands can be broadly
characterisedasfollows:
BatteryManufacturers: Manufacturersofcell-leveltechnologies,
forexampleSamsungSDI,DowKokamandA123Systemswho
aresupplyingbatteriestoNorthernPowerGrid’sCustomerLed
NetworkRevolutionprojectfallintothiscategory.
PowerConversionManufacturers:Manufacturersofinvertor
technologies.BothUKPowerNetworkspartneronitsHemsby
project (ABB) and the lead technology supplier on the SNS
project(S&CElectric)fallintothiscategory.
System Integrators: Agnostic of both AC/DC converter and
batterytechnology,thesesystemintegratorsareworkingacross
avarietyoftraditionalsubstation,generationandrenewable
generationprojects.Theymayeitherbemajorexistingplayers
inthepowerindustry,forexample:Siemens,ABB,GE,Alstrom,
orMitsubishi.Alternatively,justemergingisevidenceofanew
Smarter Network Storage - design and planning considerations | 13
c)The main constraint driving the upgrade is relieved by
arelativelysmallamountofadditionalcapacityheadroom;
and/or
d)Themainconstraintdrivingtheupgradecanbedeferredbya
reasonableamountoftime(5+years)andnootherconstraints
areforecasttomaterialisewhichmaytriggertheupgrade.
Anumberofrelativelysimplecriteriacanthereforebeapplied
to rapidly determine if storage is likely to be an effective
solution for a particular site, prior to carrying out a more
detailedassessmentoftheoverallsolutionvalue.
WithinUKPowerNetworks,allprimarysubstationgroupsare
categorisedbya Load Index factor (LI) that is ameasureof
the site demand against the firm capacity (defined as the
maximum capacity available during an N-1, or single-fault,
event).ThesefactorsrangefrombetweenLI1forsiteswith
verylittleutilisationtoLI5wherethereisaveryhighutilisation.
ThecriteriasummarisedinFigure2belowwereappliedtosites
withLIinexcessof3inordertodiscountsitesthatwerenot
likelytobenefitfromanyintervention,orwherethestorage
3.1SiteSelectionforStorage-Whencanstoragebeused?
As described earlier, the starting point for any flexible
intervention, such as storage, is to identify network issues
or operational constraints that require intervention, and
determineifenergystoragecouldprovideaneffectivesolution
asanalternativetoconventionalupgrades.
IndevelopingtheSNSproject,anumberofsitesweretherefore
identifiedinaninitialselectionexercisethathighlightedthose
requiringinvestmentforsomeformofnetworkupgradedueto
capacityconstraints.Thesecapacityconstraintscanbearesult
ofmanydifferentfactorsincludinggenerationlevels,demand
growthorevenassethealth.
Ingeneral, storage ismost likely tobeofgreatestvalue for
network upgrade deferral where several of the following
statementsapply:
a)Theupgraderequiredisparticularlycostly,complexortime
consumingtoimplement;
b)The upgrade required would add significant over-capacity
thatwouldremainun-utilisedforalongperiodoftime;
Figure 2 – High-Level Criteria Applied for Initial Site Selection
A. Determine substations that experience over-capacity of a certain duration>100%forecastcapacityfactorasat31March2015fordurationof<500MVAh
C. Filter out substations that have a high projected load growth rate>2%forecastannualloadgrowthratefrom2010/11to2014/15
B. Filter out substations that experience significant over-capacity>120%forecastcapacityfactorasat31March2015
14 | Smarter Network Storage - design and planning considerations
3.2SiteLocation-LeightonBuzzardPrimarySubstation
LeightonBuzzardemergedasthepreferredsiteatwhichtobuild
astoragedevice,andultimatelywasthesitewhereplanning
consentwasgranted,whichisdescribedlaterinthisreport.
Thisprimarysub-stationwasinneedofreinforcementwithin
thenextfewyearsduetothermalcapacityconstraintsofthe
two overhead lines feeding the site occurring at high peak-
demandtimes.PeakdemandatLeightonBuzzardhasexceeded
firmcapacitylimitsbetween9and37daysineachofthelast
fiveyears(typicallyduringperiodsofverycoldweather).The
limitedadditionalcapacityrequiredhascurrentlybeenprovided
bytransfercapacityfromneighbouringsectionsofthenetwork,
howeverpeakdemandatthislocationisforecasttocontinue
togrow,andtransfercapacityislimitedat2MVA.Thismeans
thatlimitsmayshortlybebreachedinfutureyearsandisthe
reasonanupgradeisnowrequired.ThechartinFigure3below
showsthedemandprofileacrosstwoparticularhighdemand
daysin2010,wheresitedemandexceededthefirmcapacity
ratingofthesite.
The conventional reinforcement option to upgrade the site
and mitigate this constraint was evaluated as a third 33kV
circuitfromthefeedingsite,SundonGrid,toLeightonBuzzard
primarysubstation,andathird38MVAtransformerlocatedat
Leighton Buzzard. This reinforcement would provide an
additional35.4MVAoffirmcapacityatLeightonBuzzard,which
is significantly abovepredicted requirements for themedium-
longterm.Thetraditionalreinforcementoption,andalternative
approachusingstorage,asdescribedbelow,isshowninFigure4.
The offset cost of this conventional reinforcement was also
relativelyhigh,againsuggestingthesitewasagoodmatchfor
storageandtherewaslikelytobeameaningfulcontribution
towardsthebusinesscasenecessaryfordistributionnetwork
scalestorage.
solution value was not likely to be economical in deferring
theupgrade; for example, siteswith relativelyhigh forecast
demandgrowthrates.Furtherdetailsonthisprocessandthe
intermediate results were presented in Appendix G of the
originalfundingsubmissionforSNS1.
Another main consideration in the case of the SNS project
was the known availability of land at or near the potential
siteinwhichtolocatethestoragedevice.Thiswasduetothe
requirement for a relatively rapid deployment of storage in
ordertocarryoutthetrialswithinareasonabletimeframeas
partofanLCNfundedproject.Inpracticehoweverthismaynot
necessarilybeaprimaryconsiderationattheinitialevaluation
ofnetworkissuesstageforothernetwork-basedorcommercial
deployments;aslongasthereweresomesuitablehigh-level
optionsavailable for locating theenergystoragedevice that
couldbeexplored.
For example, acquisitionof new landor thepurchase/lease
andadaptationofexistinghousingfacilitiesarestillallviable
solutions which can be factored in to a more detailed cost
benefitassessmentatalaterstage,albeitwithalikelyincrease
tothetypicaltimelineneededfordeployment.
Havingcompletedthisassessmentofnetworkissuesrequiring
intervention,anddeterminingwhichweremost likely tobe
efficientlyresolvedusingstorage,threeprimarysubstationsites
wereidentifiedforfurtherexplorationbyUKPowerNetworks:
a)LeightonBuzzardPrimary,Bedfordshire
b)MarchGrid,Cambridgeshire
c)ShepwayPrimary,Kent
Leighton Buzzard site was identified and pursued as the
preferred site for the SNS project, and is the focus of the
remainderofthisreport.
1 https://www.ofgem.gov.uk/publications-and-updates/low-carbon-networks-fund-submission-uk-power-networks-smarter-network-storage
Smarter Network Storage - design and planning considerations | 15
Figure 3 – Load Profile for Two High Demand Days in 2010 at Leighton Buzzard Substation
Figure 4 – Leighton Buzzard Reinforcement Options
ToCustomers
OverheadLines
ConventionalIntervention:3rd
LineandTx
EnergyStorage
Primary Substation 33kV to 11kV
GridSupply
GridSubstation132kVto33kV
PowerFlow
45
40
35
30
25
2000:00 12:00 00:00 12:00 00:00
MVA
Key
Demand
Firm Capacity Rating
Leighton Buzzard 20/12/10 - 21/12/10
Time
16 | Smarter Network Storage - design and planning considerations
Althoughthestoragedevicecouldtheoreticallybeconnected
totheprimarysubstationfromaremotelocation,thesitein
thiscasealsohadmorethansufficientlandadjacenttoit,on
whichto locate thestoragedevice,asshown inFigure5. In
addition,therewasfurtherlandavailabletoaccommodatea
new transformerand switchhouse for futureusewhen the
storagedevice reached theendof itsuseful lifeand further
newcapacitywaseventuallyrequired.
This site selection and identified potential location of the
storage facility served to drive some fundamental design
Inthiscase,storagecanbeusedasanalternativetobuilding
anewcircuitand transformerbygivingUKPowerNetworks
theabilitytoreduce(net)peakdemandtake-offatLeighton
Buzzardtomaintaindemandbelowthefirmcapacityrating.
Thereductionofpeakdemandcoulddelaytheneedforthis
upgradeforanumberofyears.Inaddition,weareevaluating
anup-ratingoptionoftheoverheadlineswhichwasidentified
inaparallelinnovationproject,whichifachievedmayfurther
servicethedemandanddelayorpotentiallyavoidtheneedfor
traditionalreinforcementaltogether.
Figure 5 – Aerial Photograph of the Leighton Buzzard Site
Smarter Network Storage - design and planning considerations | 17
capacity available (‘firm capacity’) at the site in the event
of a single fault (termed ‘N-1’). Licence conditions require
UK Power Networks to provide a level of security of supply
which is defined by Engineering Recommendation P 2/6.
This sets out the minimum demand that needs to be met
followingthelossofoneormorecircuitsatasiteor“Group”.
Thisrequiresalevelofredundancy,appropriatetothegroup
demand, such that in the event of one or more failures a
certain proportion of group demand can still be met. At
Leighton Buzzard only the “N-1” single failure situation
requires consideration. The site firm capacity is currently
restricted by the thermal rating of the 33kV OHLs and is
therefore35.4MVA.
At Leighton Buzzard, the P2/6 requirement is for the first
2/3rdsofgroupdemandtobemetwithin15minutes,withthe
remainingtotalgroupdemandtobemetwithin3hours.This
means that, incombinationwith the2MVAtransfercapacity
describedearlier,theallowablecapacityinordertokeepwithin
P2/6limitsis37.4MVA.
Althoughthereisthislimitedtransfercapacityavailableatsite,
itisdesirabletoavoidrelyingonreconfigurationofthenetwork
toachievethis.Ideally,thisthereforemeansthatthestorage
facilitymust,ataminimum,becapableofmaintainingpeak
demandsbelow35.4MVA.
Noteithasbeenassumedthatwithabatteryenergystorage
device installed, improved power factor can be achieved
through the independent provision of reactive power from
theinvertors.Therefore,whilstfornetworkplanningpurposes
MVAistypicallyused,itwasassumedthattheserequirements
broadlytranslatetoMW(andMWh)requirementsforbattery
choices due to a number of challenges associated with the
landadjacenttotheprimarysubstation.Primarilythesewere
theproximitytoClipstoneBrook,asmallstreamclosetothe
site,whichmeantsomeofthislandwasinahigh-riskflood
areaasdesignatedbytheEnvironmentAgencyandthefact
thatthesitewaslocatedrelativelyclosetoresidentialhousing,
ascanbeseen inFigure5.Thismeantvisualconsiderations
werelikelytobemoreimportantthanifthestoragewasto
belocatedataremote,ruralsubstationoroneinanindustrial
area,forexample.Thishasafinancialconsequenceinterms
ofmitigationforbothfloodriskandappearanceassuch,SNS
canbeseenasavaluablestresstestfortheindustryandthe
businesscaseforstorage.
3.3ApplicationRequirements
Havingdeterminedthatenergystoragemayplayavaluable
roleinsolvingaparticularnetworkissueatasuitablesite,the
nextstagewastocarryoutfurtheranalysistohelpdefinethe
technicalapplicationrequirementsforitsresolution.
Thisprocessbeginstoidentifysomeofthefurtherkeydesign
considerationsforthesolutionandisdescribedfurtherinthis
section.InthecaseofSNS,thelevelofsitedemand,technical
detailsof thefirmcapacityconstraintandexpecteddemand
growthwerekeyindeterminingtheappropriateratingofthe
energy storage system, as this was the primary or ‘anchor’
applicationinthisinstance.
3.3.1PeakShaving
As previously described, Leighton Buzzard substation
comprisestwo33/11kV38MVAtransformersfedbytwo33kV
overheadLines(OHLs)fromSundonGrid,eachwithawinter
rating of 35.4MVA that are currently the limiting factors to
18 | Smarter Network Storage - design and planning considerations
Buzzard,anassessmentofthedailydemandprofilewascarried
outtoestimatethehighestpowerandenergydemandthat
wouldberequiredtobeinjectedtokeepoverallsitedemand
within the firm capacity limits. This is illustrated further in
Figure6,whichshowsthedemandprofile(inpurple)for20
December2010;onwhichthegreatestenergyandpeakpower
wouldberequired(greenshadedareaunderthecurve)ifthis
was supplied by the storage to keep demands below firm
capacitylimits(theredline).
energy storage systems. This is because power factor will
beclosertounity,andalsoasthemarginofsafetybuiltinto
networkdesignsandcapacitythresholdswilltypicallybelarger
thananyadjustment.
Unlikeconventionalnetworkassetsanddesignphilosophies,
whichtypicallyconsiderpowercapacityonly,boththepower
and energy need to be considered for storage. In order to
assesstheminimumrequirementsforthestorageatLeighton
Figure 6 – Illustration of Peak Power and Energy Requirements
Key
MVAh overfirm
Capacity Threshold
Adjusted Total MVA
45,0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
00:0
0
01:0
0
02:0
0
03:0
0
04:0
0
05:0
0
06:0
0
07:0
0
08:0
0
09:0
0
10:0
0
11:0
0
12:0
0
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
MVA
Smarter Network Storage - design and planning considerations | 19
combination with the desired period for deferral of the
network upgrade. The inherent uncertainty in demand
growth at individual locations, and the impact of low-
carbon technology adoption on demand patterns make this
particularlychallenging.
3.3.2FutureExpansion-EstimatedLoadGrowth
Thegraph in Figure7 shows the latest longer termviewof
winter peak demand at Leighton Buzzard, including local
connectiongrowthestimates.
Inthiscase,themaximumpeakpoweroutputofthestorage
neededisapproximately40MVA(themaximumheightofthe
demandlevelabovethethreshold),andtheenergycapacity
required is approximately 12MVAh. This essentially provided
theminimumsuitableboundsof power andenergy for the
storagedevicetobeaneffectivesolutionforpeakshavingand
removingtheconstraintatthesitein2010.
To determine the upper bounds, the impact of additional
demand growth and future constraints was considered in
Figure 7 – Winter Peak Demand Trend at Leighton Buzzard Primary
48
46
44
42
40
38
36
34
32
30
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
MVA
Key
Limit to maintain P2/6 Compliance - No intervention MVA
Site Firm Capacity (N-1) - No intervention
Local Load Growth Estimates
Local Load Growth Estimates
20 | Smarter Network Storage - design and planning considerations
minimumlevelofenergydurationcanbeachieved.Thechoice
ofmaximumrealandreactivepowerandenergyistherefore
also an important factor in the overall business case for
multi-purposeusestorage.
Itbecameevidentduringtheprocurementprocessthat,inthe
caseof battery energy storage, the costwasmost sensitive
to increases inenergy storage capacity, rather than theMW
capacityrating,reflectingthefactthatthecostofthebattery
unitsistypicallyagreaterproportionofthetotalcostthanthe
inverterunits.
Following this analysis although based on earlier published
planningdate,itwasthereforedeterminedthatanappropriate
initialstorageratingwas6MW/10MWh.Thisprovidedforan
optimumamountofenergydurationtoinitiallymeetcurrent
andsomefuturepeakdemandatsite,dependingonthelevel
offutureloadgrowth,whilealsoprovidingforapeakpower
greaterthanstrictlyneededforthenetworkconstraintinorder
tomaximiseadditionalvaluestreams.
Itshouldbenotedthatwithmanyenergystoragetechnologies,
it is possible to add further power and energy capacity
throughout its operational life, therefore capacity for future
expansionneednotbe installedondayone. In the caseof
batteryenergystoragethisispossiblethroughtheconnection
ofadditionalinvertersandbatteryracks.
Attheearlydesignstage,itwasthereforedecidedtodesign
the building to accommodate further future expansion of
bothpowerandenergytoprovidegreateroptionality in the
faceofuncertainloadgrowthandprofileshape.Basedonan
assessment of potential maximum energy and power limits
requiredtoprovideasignificantperiodofdeferral(10+years),
and using indicative estimates provided by manufacturers,
the building was initially designed to accommodate future
expansion up to 8MW/24MWh, as illustrated in Appendix 3.
Fromtheseestimates, itcanbeseenthat,duetoanumber
ofeconomicfactors,theoveralltrendindemandgrowthhas
beenareductioninoverallmaximumdemandsince2009.This
suggeststhattheminimumpowerandenergyboundsof4MVA
/12MVAhrequiredfromthe2010profileinFigure6wouldin
factalreadyprovidesomefuture-proofing.However,demand
growth is expected to return as the economic environment
improves,andsoitwasdeemedimportanttoprovidefurther
future-proofingofthesolution.
Itshouldbenotedthatthe local loadgrowthestimatesalso
showed that, without intervention, demand is expected to
exceedthesitecapacitylimitaround2016/17,andtherefore
therewasarequirementthatanysolutionshouldbecapableof
beingdeployedwithinthistimeframe.
Determininganappropriateenergycapacitytocaterforfuture
growth ischallengingbecauseoftheuncertainty intheway
that the shape of demand will change in the future. If, as
expected,electricvehiclesbecomemorecommonplace,then
thisislikelytoresultin‘peakier’demandprofilesandtheneed
forahigherpeakpowerratingforenergystoragetomitigate
resulting constraints. Alternatively, if consumption increases
relativelyproportionatelyacrossthedailyprofile,itislikelyto
beenergycapacitythatbecomesthelimitingfactor.
Itisthereforedesirabletobuildinsomeallowanceforgrowth
inboththesedimensionstoprovidethegreatestoptionality.
Naturally,providingforgreaterpowerand/orenergycapacity
hasanimpactonthecostandfootprintofanystoragesolution,
andsotheallowanceformaximumpossiblefutureexpansion
must be balanced with the overall solution value and
cost-benefitcomparedtothetraditionalupgrade.Inaddition,
many of the current ancillary services are capacity based,
whichmeansthevalue,andthereforetheadditionalbenefits
achievableisproportionaltoMWratherthanMWh,assuminga
Smarter Network Storage - design and planning considerations | 21
•Ability todeliverat least3MWoutput forat least2hours
duration(6MWh)(asrequiredbySTORservice)
These application requirements, in conjunction with the
determinedstorageratingsasdescribedinSection3.3.2,were
used to guide the procurement process and therefore were
additional key drivers in the resulting storage technology
selectionanddesign.
3.4Safety
Safetyisaprimaryconsiderationforallnetworktechnologies
andinterventionsbyDNOs,andsoalsoimpactedtheselection
of storage technologiesduring theprocurementprocessand
finaldesignsofthefacility.
There was a wide range of technology proposals that were
receivedduringthetenderprocess,whichisdescribedfurther
inSection4.1;eachofwhichhavedifferentcharacteristicsand
safetyconsiderationsassummarisedonthefollowingpage:
(Following a subsequent necessary change of battery cell
supplier, during further detailed design it became evident
thatitwasnolongerpossibletoaccommodateupto24MWh,
which led to a revised layout design as described later in
thisreport.)
3.3.3SecondaryApplications
InthecaseofSNS,asdescribedinSection3.3.1,thethermal
capacityoftheoverheadlineswastheconstrainttriggeringthe
needforreinforcementatLeightonBuzzardandshortlyfollowed
bythethermallimitofthetransformersbeingreached.
However,thereisalsoadesiretomaximisethevalueofthe
storagecapacity,anddetermineifadditionalapplicationscould
help to improve the business case for storage. In addition,
the storage is to be used as the means to explore a range
of innovative commercial arrangements for the ownership
andoperationofthestoragedevice.Assuch,theprojectwas
interestedinexploringtheuseofanytypeofstoragetechnology
ofsufficienttechnologicalreadinesstobesafelyandeffectively
deployedatdistribution-networkscale.
Theseadditionalapplicationrequirementswerespecifiedinthe
technologytenderintheformofancillaryservicesthatwere
desirableforthestoragesolutiontobecapableofperforming
andincluded:
• Short-TermOperatingReserve(STOR)
• DynamicandNon-DynamicFastFrequencyResponse(FFR)
• PowerFactorCorrection–throughtheprovisionofreactivepower
Theseadditionalservicesplaceadditionaldesignconsiderations
onthestoragesolutionintermsofthecapabilitiesandresponse
timesincluding:
•Abilitytoprovidereactivepower(VArs)(toprovidepower
factorcorrection)
•Abilitytoprovidepoweroutputresponsewithin2seconds
(asrequiredbyFFRservice)
22 | Smarter Network Storage - design and planning considerations
StorageTechnology
VanadiumRedoxFlow
LeadAcid
Sodium-nickel-chloride(NaNiCl2)
LithiumIon
SodiumSulphur(NaS)
Lithiumironphosphate(LiFePO4)
LiquidAir
Characteristics/SafetyConsiderations
Arechargeableflowbatterythatusesvanadiumionsindifferentoxidationstatesto
storechemicalpotentialenergy.Theelectrolytescontainsulphuricacid,whichisstored
inexternaltanks.Thispresentssafetyandenvironmentalconcerns,especiallyifleakage
toawatercourseispossible.
Theseuseleadplatesinanelectrolyteofsulphuricacid.Theyhavearelativelygood
efficiencyandarelowcost.Theleadandsulphuricacidaretoxicandsopresentsafety
andenvironmentalconcernsforbothnormaloperationandintheeventofleakage.
Thisisamoltensaltbatterywithgoodthermalcyclingproperties,buttherearesome
thermalmanagementsafetyconcerns.
Typicallysolidorpolymer-basedelectrolytethatresultsinlimitedriskofspillageor
leakage.Lithiumisflammable,resultinginrelativelyhighfireriskintheeventof
overchargeorcatastrophicfailureconditions.
Thisisalsoatypeofmolten-saltbattery(constructedfromliquidsodiumandsulphur)
withahighenergydensity,highefficiencyofcharge/dischargeandlongcyclelifetime.
Howevertherehavebeensomerecentsafetymanagementconcernsbecauseofthe
corrosivenatureofthecomponents.
ThisvariationofaLithium-Ionbatteryhasalowerenergydensitythanthemore
commondesignusedinconsumerelectronics.Becauseofitslowcost,non-toxicity,
thehighabundanceofironanditsexcellentthermalstabilityithasgainedmarket
andsafetyacceptance,butlimiteddeploymentsatlargescale.
Cryogenicbasedsystemoperatingatlowtemperaturesandhighpressure.
Non-hazardousandnon-toxicelectrolytematerials,althoughlowerenergydensity
thansometechnologiesresultsinalargefootprint.
Smarter Network Storage - design and planning considerations | 23
It is hoped that this learning will help to support other
distribution network operators in the economic analysis of
storagedeploymentstodetermineifitislikelytobeaviable
alternative.AspartoftheSNSproject,anInvestmentModel
Template2hasalreadybeendevelopedaspartofaconsultation
relating to the potential business models for storage, which
providesa tool forassessing thebusinesscase forastorage
installation when it is deployed for a range of system-wide
servicesundertwodifferentbusinessmodels.
An understanding of the business case for storage, and the
possible ranges of additional value that may be achieved,
will help network operators, and/or third-parties deploying
storage, to determine the upper bounds for the budget
that can be tolerated for storage to be an economic
alternativeataparticularsitefortheresolutionofaparticular
networkissue.
Itisoutofthescopeofthisreporttoevaluatethefullbusiness
casefortheinstallationatLeightonBuzzard,asfurtherlearning
isyettobegeneratedrelatingtotherealbenefitsthatcanbe
achievedfromoperationonthenetworksandintheancillary
markets.Forfurtherinformationontheoriginalassessmentof
thebusinesscase,theSNSfundingsubmission3analysedthe
estimated potential business case of the installation at this
trialsiteanddemonstratedthatwithancillaryvaluestreams,
onceprovensuccessful,itwaspossibleforthedeploymentto
providebenefitsforcustomers.
For business-as-usual deployments, it is therefore expected
that this evaluation would be carried out following site
identificationtodeterminewhetherstorageshouldbeusedto
meetthenetworkneed,andbeforeproceedingwithfurther
storagedesign.
Thespecificsitelocationwasalsoadriverintermsofsafety
considerationsbecauseoftheproximitytothewatercourseand
residentialbuildings,andduetothesitebeinginahigh-risk
flood area. This would have specific implications for safety
hazardsconnectedwith theproposed technology, in relation
toitsconstructionandimpactsconcerningitsoperationandso
forUKPowerNetworks thisguidedthe technologyselection
away from those solutions based on liquid electrolytes, or
wheretherewassome(albeitsmall)riskofhazardousliquids
beingreleased.
Naturally, the safety of employees and the public will be of
primary concern in all distribution-connected storage
deployments.Howevertheriskappetiteforcertaintechnologies
willdependontheindividualorganisationandmaybehigher
forinstallationsinremoteorhighlyisolatedlocationswherethe
consequencesofcatastrophicfailuremaybesignificantlylower.
3.5Budget
Budget is likely toplayakeypart indeterminingsomekey
design choices, including supplier selection and technology
type.For storage tobeaviablealternative theremustbea
robustbusinesscasethatprovidesforalowercostalternative,
oradditionalbenefitsovertheconventionalupgrade.
Whileitistypicallynoteconomicaltodeploystorageinisolation
(i.e.for investmentdeferralalone)foradistributionnetwork
operator,itisoneofthemainaimsofSNStogeneratelearning
relating to the wider business case for the multi-purpose
application of storage. This includes how the provision of
ancillaryservicesmaycontributetowardstheoverallbusiness
case for storage and determine whether these additional
benefits,inconjunctionwithinvestmentdeferral,providefora
viablelowercostalternative.
2 http://www.ukpowernetworks.co.uk/internet/en/community/smarter-network-storage/3 https://www.ofgem.gov.uk/publications-and-updates/low-carbon-networks-fund-submission-uk-power-networks-smarter-network-storage
Smarter Network Storage - design and planning considerations | 25
4.1TechnologyandSupplierSelection
AtthestageoftechnologyselectionapreferredsiteatLeighton
Buzzard, albeit requiring planning permission, had been
identified as previously described. Although the eventual
installation site might have had to alter, depending on the
planningconsentoutcome,itwasneverthelesshelpfultohave
suchareferencesiteandlocationtousewhenputtingtogether
thetender.
Thecapacityrequirementofthedevicehadbeenassessed,as
described in Section 3.3.2. In order to assess potential for
improvements in the future commercial operation of the
device,variations foralternativeconfigurations for increasing
the rated capacity were also sought from suppliers. Where
alternativeswereproposed,explanationoftheimplicationsof
the varying cost structures were requested so that a cost/
benefitanalysiscouldbeundertaken.
Thestoragedevicemanufacturerwoulddesign,manufacture,
workstest,supply,delivertosite,supervisetheerectionand
installation, test and cold commission the system. Further
testingwouldberequiredtodemonstratethatthecomplete
installationwilloperatesafelyandnothaveanydetrimental
impactonconnectedcustomers.Arangeoffurtherappropriate
tests from international standards would be required and
agreedwithUKPowerNetworks.Thesewouldincludepower
frequency tests as well as lightning impulse tests and the
installationwouldneedtoconformtotheDistributionandGrid
Coderequirements.
AtenderwaspreparedandissuedinApril2012,forresponses
six weeks later. Responses were received from 15 suppliers
offeringbetweenthem23differentsolutions.Allbutoneofthe
proposalswerebasedonaformofelectrochemicalbattery.The
majority,11ofthe15suppliersofferedtheirownmanufactured
battery solution, whereas the four non-manufacturers who
essentially bought in the battery technology hardware were
abletoofferamuchgreaternumberofpotentialsolutionsand
wereessentially system integratorswhowereneutralabout
thechoiceofbatterytechnology.Thetechnologyofferedranged
right across the electro-chemical batteries spectrum from
technically and commercially mature lead-acid batteries
throughnickelcadmiumtoadvancedlithium-ion.Thesolutions
offeredwereevaluatedagainstsevencriteriawithfoursuppliers
making the short-list. This was later reduced down to two
preferredsuppliersbasedonthetechnology.
Thetechnologysolutionthatratedhighestwaslithium-ion,in
partduetothesafetyfeaturesproposed.Thisappearedtohave
keybenefitswhencomparedagainstthealternativetechnologies,
andusingtheproject’sdesigninputsdescribedearlier.Ofthe
twopreferredsuppliers,thekeybenefitsthattheseproposals
containedwere:
• Proventechnologywithsuitablereferencesitesandsafety
record,usingtechnologythathadnopossibilityofpolluting
floodorrivercoursewater;
• Physical size, weight and foot print area aligned with
identifiedsitelocation;
• Quickramp-upresponsetimeofsolution,allowingforwide
rangeofapplications;
• Ability to be housed in a variety of structures, including
buildingalignedwithsitelocationrequirements;
• Abilitytoberaisedabovethegroundonstilts,tomitigate
floodingrisks;and
• Valueformoney.
Therewaslittledifferencebetweenthetwopreferredsuppliers
intermsofboththetechnologyandthepriceoffered.Onewas
abatterycellmanufacturer,whowasproposingtoappointan
established power systems company subcontractor as their
secondtiersupplier to integratethesystemandprovidethe
necessarypowerelectronics.Theotherwasapowerelectronics
systemscompanywhowouldsubcontractoutthebatterycell
26 | Smarter Network Storage - design and planning considerations
manufacturetoasubsidiaryofamajorchemicalcompanyable
toprovidethenecessarybatterycells.Thesecategorisationsare
describedearlierinSection2.1.
Followingfurthercommercialdiscussions,theleadsupplierS&C
Electric Europe was appointed. S&C Electric then formally
appointedsecond-tiersuppliersofSamsungSDI(forthebattery
cells)andYounicos(forthecontrolsystemaspects).
Whilethechoiceoftechnologymayultimatelydrivethetypeof
mainsupplierselected,itwasnotedinthefirstSNSprogress
report4thatthesupplychainforenergystoragesystems,and
batterystorage inparticular,hasbeenfoundtoberelatively
immature.Acomplexsupplychainofsecond-tiersuppliersis
required for a fully integrated storage system, covering, for
example, power-conversion equipment, battery cells and
assemblies, advanced control systems, fire-suppression and
coolingsystems.Currentlythereareexamplesofplayerswitha
historyineachoftheseareaswhoaretargetingthemarketfor
fully-integratedsystems,andallhavethepotentialtobelead
suppliers. It is not yet clear howeverwhich segment of the
supply chain will eventually dominate in the supply of
integratedsystems,soitislikelytherewillbefurthershake-ups
andconsolidationinthecomingyears.
Basedontheexperienceofthisprocurementexercise, there
would appear to be merit in selecting a supplier who can
provide a fully integrated solution, with some maturity as
primary lead supplier. When the supplier S&C Europe was
appointed, their original battery cell second tier provider
fell out of the running through their ownparent company’s
choice. S&C however were able to find and select a
replacement second tierbattery cell supplier,whichhadnot
been identified at the start of the original procurement
process.Thereforethistime,itwaspossibletocontinuewith
the primary supplier chosen. The lack of financial strength
of suppliers in this market has been evident and
therefore significant effort should be placed on conducting
financialduediligence.
Thiscreatesprocurementchallengesforenergystoragesystems
anditwasfoundthatprocurementdatabases,suchasAchilles,
do not necessarily capture the best or latest view of the
potentialsupplierlandscape.Toovercomethis,itissuggested
that alongside existing procurement approaches, further
marketresearchiscarriedouttoidentifyandcaptureadditional
emergingplayers,aswascarriedoutinthebid-phaseofthe
SNSproject.
4.2ModuleSize
Modularityofdifferentenergystoragetechnologiesvaries,but
anotherkeyadvantageofbatteryenergystoragetechnologies,
suchasLithium-Ion,istheflexibilityinsizingandconfiguration.
Different manufacturers have different specific common
inverter or battery module sizes that provide for certain
configurationsthataremorecosteffectivethanothers.Inthe
caseoftheselectedtechnologysupplier,inverterunitsof1MW
(1.25MVA)wereavailablethatcouldbecombinedtoprovide
modular 2MW (2.5MVA) inverter units. This meant overall
solutions of 2MW increments were optimal, and helped to
determinetheoptimaldesignofthefutureexpansionofupto
8MWpowerrating.
FortheSNSsolution,initiallythreesetsof2MWinverterunits
willprovidethe6MWpoweroutput.Independentconnection
ofthese2MWunitsprovidesfortheabilitytotakeunitsoutof
serviceandstillhavepowerandenergyavailable.
Similarly,batteryenergycapacitycanbeaddedincrementally
toeachinverter,althoughitisdesirabletohaveanevenbattery
capacityacrosseachmain inverterunit tofacilitatetheeven
balancingofstateofchargeacrossthefullsystem.Thesmallest
modularunitfromSamsungisdefinedasa‘tray’andconsistsof
4 https://www.ofgem.gov.uk/electricity/distribution-networks/network-innovation/low-carbon-network-fund/second-tier-projects/uk-power-networks
Smarter Network Storage - design and planning considerations | 27
16 individual battery cells, providing for a nominal energy
capacityofaround3.5kWhpertray.FortheSNSinstallation,132
racks,comprising24trayseacharethendistributedacrossthe
inverter units to provide the total energy capacity for the
installation(includingapproximately1MWhnominaladditional
capacitytoallowfornaturaldegradation).
4.3StorageHousing
Several large-scale battery energy storage providers offer
standardised solutions based on batteries installed in ISO
shippingcontainers.
Attheidentifiedsite,theelectricalenergystoragefacilityisto
be located in close proximity to public rights of way and
residential housing, so it was determined at an early stage
that a containerised solution was unlikely to be acceptable
to the community, and also therefore to the Local Planning
Authority, and so a building-housed solution would
benecessary.
Duetothefloodriskatsite,itwasalsodeemednecessaryto
specifythatthestoragebuildingmustberaisedofftheground
toallowanyfloodwaterstoflowfreelyunderneathsoasnotto
increasefloodriskthroughdisplacingwater,oritselfbeatrisk
offlooding.
In order to ameliorate the visual impact of the proposed
development,theoverridingconsiderationwastominimise,as
faraspossible,thesizeandvolumeofthebuilding.Thesecond
designconsiderationwastodesignanyfacadeofthebuilding
suchthatitminimisedtheapparentbulkofthebuildingwhen
seenfromkeyviewpoints.
Finally, it was deemed necessary to provide some form
of effective landscape screening to the resulting
development, including the security fence around the new
substationcompound.
4.3.1StorageHousing-DesignCriteria
There were a number of design criteria that needed to be
followed, based on UK Power Networks requirements and
those anticipated to be important for securing planning
consents. A range of surveys and studies at the Leighton
Buzzardsite,wereconductedinlinewithUKPowerNetworks
civilstandardshelptodefinearangeofinitialdesigncriteria.
Thefollowingresultingconsiderationswerethereforeimportant
designfactors:
• Keepingthevolumeandheightoftheproposedsubstation
structure(s)toaminimumsoastokeepthevisualimpactof
thefacilitytoaminimum;
• Keepingthecostofconstructiontoaminimum;
• Useofgoodqualityfacingmaterialsthatwill result inthe
minimumofmaintenancebeingrequiredandextendingthe
lifeofthefacility;
• Facingmaterialsthatwillhelpthebuildingblendinwiththe
surroundingarea;
• Useoflandscapingtoameliorateanynegativevisualimpact;and
• Existing33kVunderground cables on site, so nobuildings
shouldbelocatedoverthesecables.
In order to mitigate flood risk, the following factors were
requiredinthedesign:
• Noraisingofthesitegroundlevel;
• Aclearvoidunderthebuildingtoallowforfloodwaterto
passfreelyandoccasionalaccessformaintenancepurposes;
• No amendments should be made to the cross-sectional
alignmentofthebankofClipstoneBrook;
• Notree-plantingclosetothewatercourseedge;
• Nobundingofanykindisincludedinthedesigntoprevent
displacementofpotentialfloodwaters;and
• Aneasementbetweentheperimeterfence,alonglevelground,
totheedgeofthewatercoursetoallowaccessformaintenance.
28 | Smarter Network Storage - design and planning considerations
Forvisualameliorationpurposes,itwasproposedtointroduce
landscapingalongthreeofthefourboundaries:alongWoodman
Close,alongtheboundaryfacingtheriverbank,andalongthe
boundaryparallelwiththeexistingsubstationboundary(north-
easternboundary).
Other considerations, relating to security and environmental
impactsincluded:
• Withinthesecurecompound,anyelectricalplantshouldbe
keptatleast2mawayfromthesecurityfenceinaccordance
withUKPowerNetworkscivilengineeringdesignstandards;
• Tosafeguardanareaforwild life, itwasadvisedthatany
newdevelopmentshouldbekeptfrombetween5mto8m
fromthetopoftheriverbank;
• An area of open land within the secure compound is
required for circulation and temporary storage of surface
waterrunoff;and
• No trees should be planted closer than 2m from the
demarcationfenceincasetheyareusedasclimbingaids.
Someoftheresultantarchitecturalfeaturesofthesubstation
buildingreflectthefunctionofthebuilding,namely:
• Therearenowindowstothebuilding;
• Highsecuritydoorstothebuilding;
• A3m-highsecurity‘Weldmesh’fencearoundtheperimeter
ofthecompoundforsecurity;and
• A 1.2m-high secondary ‘demarcation fence’, with a 2m
clearancebetweenitandthe‘Weldmesh’fence,withshingle
onthecompoundarea.
30 | Smarter Network Storage - design and planning considerations
although an application for a mining operation, minerals
extraction,orawastemanagementfacilitywouldbedecided
bythelocalcountycouncilinnon-metropolitanareas.Withina
national park planning applications are submitted to the
nationalparkauthority.
InthecaseofSNS,theLPAfortheLeightonBuzzardsitewas
CentralBedfordshireCouncil.
All LPA’s have their own websites which provide access to
relevantapplicationforms,contactdetailsandotherrelevant
documents. LPAs are generally receptive to pre-application
discussion inorder toclarifywhetheraproposalwill require
planningpermissionand,assumingthatitdoes,theprobability
ofsuchplanningpermissionbeinggranted.Thesepreapplication
discussionsareoftencalled“place-maker”meetings.
5.2Determination
Thelawrequiresthatallapplicationsforplanningpermission
should be decided in accordance with the policies of the
“developmentplan,”unlessmaterialplanningconsiderations
indicateotherwise.Thedecisiononanyplanningapplicationis
therefore“policy-led”ratherthan“influence-led”.Althoughthe
publicandnearbyresidentswillbeconsultedaboutalmostany
planning application, the decision will not be made on the
grounds of popularity or unpopularity. The framing of the
decisionbyreferencetopublishedplanningpolicypreventsthe
decision on a planning application being made on grounds
whichareperverseandarbitrary.
It is therefore most important that applicants for planning
permission satisfy themselves about the relevant local
developmentplanpoliciesbeforemakinganapplication.These
canalsobeviewedviatheLPA’swebsite,ortheUKGovernment’s
PlanningPortal,whichprovidesanationwideclearinghouseon
planninginformationandadviceforbothGovernmentandlocal
planningpolicies.Asapracticalmatteritisadvisabletodiscuss
5.1PlanningPermission
ObtainingplanningconsentistheprocessrequiredintheUKin
ordertobeallowedtobuildonland,orchangetheuseofland
orbuildings.WithintheUK,theoccupierofanylandorbuilding
willneedtitletothatlandorbuildingi.e.“ownership”,butwill
alsoneed“planningtitle”orplanningpermission.Planningtitle
wasgrantedforallpre-existingusesandbuildingsbytheTown
andCountryPlanningAct1947,whichcameintoeffecton1July
1948. Since that date any new development has required
planningpermission.TheplanningsystemforEnglandandWales
issetintheTownandCountryPlanningAct1990asamended.
Development as defined by law consists of any building,
engineeringorminingoperation,orthemakingofamaterial
changeofuseinanylandorbuilding.Certaintypesofoperation
suchasroutinemaintenanceofanexistingbuildingarespecifically
excludedfromthedefinitionofdevelopment.Specifiedcategories
ofminororinsignificantdevelopmentaregrantedanautomatic
planningpermissionbylaw,andthereforedonotrequireany
applicationforplanningpermission.Thesecategoriesarereferred
toaspermitteddevelopment.Electricityundertakings,suchas
licensed distribution operators are also permitted to make
developments on their own property under a General
DevelopmentOrder,undertheElectricityAct1988.Someother
developments,suchaspowerstationsandoverheadlinesrequire
consentsundertheElectricityActandnottheTownandCountry
PlanningAct.
Inthecaseofanyproposalthereisthereforeatwostagetest:
Istheproposaldefinedasdevelopmentand,iftheproposalis
development, “is it permitted development?” Only if a
development is not “permitted development” would an
applicationforplanningpermissionberequired.Anapplication
for planning permission should then be made to the Local
PlanningAuthority(LPA).
LPAs are generally the local borough or district council,
Smarter Network Storage - design and planning considerations | 31
5.3.5RemovalorAlterationofaPlanningCondition
asamatterof law,conditionsshouldonlybe imposedona
grant of planning permission when compliance with that
condition isessential tomakeanunacceptabledevelopment
acceptable,soitwouldberefusedplanningpermissionwereit
notforthatcondition.Iftheapplicantordeveloperwishedto
proceed with a development without compliance with a
condition,orperhapswiththeconditioninanalternativeform,
then an application can be made to “vary” the condition
concerned, possibly by deleting it or offering an alternative
formofwords.Note that the LPAcannotalteranyplanning
conditionwhichimposesatimelimitwhenthedevelopmentis
tobecommenced.Thatwouldrequireare-applicationforfullor
outlineplanningpermission,butsinceOctober2009ithasbeen
possibletoapplytoextendanexistingconsent.
5.4Timescales
Eachtypeofapplicationhasatimescaleforwhenadecision
has tobemade. Theseare setby theGovernmentandcan
rangefrombetweenfourweeksand16weeks.Councilsare
permitted to agreewith the developers for an extension of
time,providingbothparties canagree,although theprecise
mechanism appears to differ depending on the LPA. If the
Councilfailstomakeadecisionwithinthenecessarytimeframe
ortheagreedtimeextension,theapplicantcanappealtothe
SecretaryofStatefornon-determinationofanapplication.Full
planning or outline planning applications must ordinarily be
determinedwithineightweeksof itssubmissionunless it is
deemedtobeamajorapplication.Thistimecanincreaseto16
weeksiftheapplicationincludesanenvironmentalstatement,
althoughaswastheexperiencewithintheSNSprojectthereis
thepotentialforthesetimelinestobeextended.Thetimescale
forachangeofuseapplicationiseightweeks.
5.5PlanningClassifications
Usesoflandandbuildingsareclassifiedinto“useclasses”and
proposalswiththeLPAbeforeincurringthefeesandothercosts
that are involved in making a planning application, or the
delaysandabortivecoststhatwouldarisefromtherefusalof
planningpermission.
5.3TypeofApplication
A number of different types of planning permission can be
appliedfor:
5.3.1FullPlanningPermission
Fullplanningpermissionwouldgrantpermissionforallaspects
oftheproposeddevelopment,althoughitwouldgenerallybe
subjecttovariousconditions(seebelow).
5.3.2OutlinePlanningPermission
Thiscannotbegrantedforaproposedchangeintheuseofland
or buildings. It might be appropriate when an applicant
is seeking an agreement “in principle” to a proposed
development,withoutbeingcommittedtoaparticularformof
designorlayout.
5.3.3Approvalof“ReservedMatters”
Seekingpermissionforthoseaspectsthatwerenotdealtwith
in an outline planning permission or seeking approval of
aspectsofadevelopmentwhichwerereservedbyaplanning
conditioninanearliergrantoffullplanningpermission.
5.3.4RenewalofPlanningPermission
This would arise when an earlier outline or full planning
permissionwassubjecttoatime-limitingconditionwhichhas
since expired. In essence this requires the entire planning
application to be reviewed in light of current rather than
previousplanningpolicies.Applicationsforrenewalofanearlier
planningpermissionareusuallygrantedanew,unlesstherehas
beenasignificantchangeintherelevantmaterialconsiderations
whicharetobeweighedinthedecision.
32 | Smarter Network Storage - design and planning considerations
approvedbythelocalauthority.Someofthesewillneedtobe
compliedwithbeforeanyworkstartsonsite;otherswilltake
effectoncethedevelopmentiscommenced,orlater.
Mostconditionsimposedonagrantedplanningpermissionwill
relatetoimplementationofworkswithintheactualsiteofthe
application(theedgesofwhichmustbedefinedbyaredline
markedon an accurately scaledmapof the site, usually an
Ordnance Survey extract, accompanying the application). If
thereisaneedtocontrolaspectsofthedevelopmentwhichare
requiredtooccuroutsidethedefinedapplicationsitesuchas
relatedhighway improvements, then the implementationof
thoseaspectscanberequiredbya‘Grampiancondition’.This
wouldbeworded to theeffect that thedevelopmentbeing
permittedmustnotbecommenced(ormustnotbeoccupied,
as appropriate), until the required off-site works had been
completed.
5.7Section106Agreements
Planningconditionsareimposedtorequirethatsomethingis
done or not done by the developer in order to make the
developmentacceptable.Sometimes,planningpermissionwill
onlybegrantedsubjecttotheapplicantenteringintoalegal
agreementunderSection106oftheTownandCountryPlanning
Actrequiringthatcertainthingsbedoneormoneybepaidto
the local planning authority e.g. to contribute towards the
improvementofahighwayjunctionservingthedevelopment
before thedevelopment commences. Such contributions can
onlyberequirediftheyarenecessarytomakethedevelopment
acceptableandrelatedirectlytothedevelopmentproposed.
5.8DevelopmentControl
Developmentcontrolorplanningcontrolisthesystemoftown
andcountryplanningthroughwhichlocalGovernmentregulates
landuseandnewbuilding.Itreliesona“plan-ledsystem”whereby
development plans are formed and the public is consulted.
Subsequentdevelopmentrequiresplanningpermission,which
any change from one use class to another use class is
automatically a “material change of use” amounting to
development.Somesmallscalechangesbetweenuseclasses
arenevertheless“permitteddevelopment”andhencedonot
requireplanningpermission.Certaintypesofuseoractivitydo
notfallintoaspecificuseclassandaretermed“suigeneris”.
“Suigeneris”wastheclassificationdeemedmostappropriate
fortheapplicationattheLeightonBuzzardtrialsiteas,similar
tothenatureofthecurrentelectricityregulatoryframeworks,
theclassificationofenergystorage isnotexplicitlyorclearly
covered.Forexample,thereisaplanningpermissionuseclass
entitled‘StorageorDistribution’5,howeverthistypicallycovers
the physical storage of equipment or materials, such as oil
drums,tyresorlogistics/distributioncentresandmaytherefore
carry some negative connotations with local stakeholders
whichwouldnotnecessarilyberepresentativeoftypicalenergy
storagedeployments.
ItisnotclearifallLPA’swouldcategoriseanelectricalstorage
devicedevelopmentbyanon-DNOorelectricityutilitycompany
asrequiring“suigeneris”useandthereappearstobesome
leewayintheirassessment.Anychangeofuseof“suigeneris”
landrequiresplanningpermission.Inpracticemostusesarea
compositeof several uses so that, say, a factorymightwell
haveanancillaryofficeandperhapsstorageuses,allwithinthe
samepremises.Insuchacasehowever,theprimaryusewould
bethatofafactory(useclassB1orB2).
5.6Conditions
Planningpermission isusuallygrantedsubject toaplanning
conditionwhichrequiresthedevelopmenttobecommenced
withinthreeyears.Typicallytheywillalsoincludeanumberof
other conditions, for example the scheme to be built in
accordancewiththeapproveddrawings,treestobeplantedas
perthelandscapeschemeandreplacediftheydieinthefirst
fewyears,orthecolourandfinishofexternalmaterialstobe
5 http://www.planningportal.gov.uk/permission/commonprojects/changeofuse/
Smarter Network Storage - design and planning considerations | 33
isgrantedorrefusedwithreferencetothedevelopmentplanas
amaterialconsideration.Ifthelocalplanhaddesignatedthe
proposeddevelopmentsiteaslandforsomethingotherthan
utilityservices,aswasthecaseatLeightonBuzzard,then in
spiteofthefactthatUKPowerNetworksownedthelandand
hadalwayshelditforfutureoperationaluse,thisalternative
designation in the local plan could dissuade the planning
officersfromgrantingapproval.Tocounteractthisitisusefulto
monitorandcommentonlocalplansateachpublication.
5.9NationallySignificantInfrastructure
ThePlanningAct2008introducedanewplanningsystemfor
nationallysignificantinfrastructureprojects.TheGovernmentis
producingaseriesof twelveNationalPolicyStatementsthat
willexplainitspolicyoneachtypeofinfrastructureproject.A
numberofNationalPolicyStatementshavebeenintroduced,
coveringmajorenergyprojects(oil,gas,coal,nuclearpower
andrenewableenergyfromthingslikewindfarms),ports,and
sewagetreatment.
Developerswantingtoapplyforconsentforaprojectmustfirst
consultlocalcommunitiesandgroupsthatmaybeaffectedby
the project. Applications are generally dealt with by the
PlanningInspectorate’sNationalInfrastructureDirectorate,toa
timetabledprocedure.
PlanningInspectorstakedecisionsonbehalfoftheSecretaryof
State.TheyapplythepoliciesintheNationalPolicyStatements
when making decisions. They take into account any matter
theyconsiderimportantandrelevant.Thiscouldincludeadraft
NationalPolicyStatement,wherethefinalstatementhasnot
yetbeenadopted.
It is unlikely that the scale of most distribution-connected
energy storage would fall into the category of nationally
significantinfrastructure,andisthereforenotconsideredfurther
inthisreport.
Smarter Network Storage - design and planning considerations | 35
ofUKPowerNetworks.Itwasthereforenecessarytoprovide
additionalanalysisintothefinancialandtechnicalviabilityof
alternative theoretical locationsoverandabove thatalready
provided.Thisassessmentwascrucialtoensurethe‘sequential
test’requiredbytheNationalPlanningPolicyFrameworkwas
satisfied, which is designed to ensure that development is
locatedinthemostsustainablelocationfirst,beforeother,less
sustainablelocationsarechosen.
Ideally the best technical solution was to locate the storage
deviceimmediatelyadjacenttotheexistingprimarysub-station
asdescribedearlier.However,with thepotential offlooding
andthecloseproximityofresidentialhousingitwasnecessary
to consider potential alternatives, of which there were two.
Either locating the storage device at a normal open point,
withintheprimarynetworkoralternativelyfindingasuitable
satellitesiteatwhichtolocatethestorageandconnectingit
backtotheprimarybywayoftwoseparate11kVcircuits.
Six normal open points (NOPs) within the Leighton Buzzard
Primarygroupwereidentifiedasbeingpotentiallysuitablefor
connecting the storagedevice, theseare shown inFigure8.
However, on further analysis none of themproved suitable.
Therewaseithertoolittlelandorspaceavailable,againdueto
theurbanlocationofeachandtheirproximitytohousing,or
the existing feeders through which a device would be
connected would require significant upgrading or
replacement.Inoneinstancetherewerealsosecurityconcerns
relating to the locationof thecablesandroutesback to the
primarysubstationwhichwouldbeathighriskofdamageby
anystreetworks.
6.1PlanningConsentsatLeightonBuzzard
Worktodeveloptheplanningapplicationforthetrialsiteat
LeightonBuzzardbeganinMay2012duringtheearlyproject
bid phase, when pre-application guidance was sought from
CentralBedfordshireCouncilbasedontheinitialdesignsofthe
exteriorofthestoragehousing.Theguidanceprovidedatthis
placemakermeetingofferedtherangeofrelevantpoliciesthat
shouldbeconsideredinthefullapplicationandalsoincluded
initial comments froma rangeof keyexternal stakeholders,
suchastheEnvironmentAgencyandlocalHighwaysOfficer.
Planningconsultants,AdrianSalt&Pang,wereappointedbyUK
PowerNetworkstoassistinthisprocess,providingguidancein
compiling the planning application. In order to maintain
consistencytheyhaveremainedthemain interfacewiththe
council’sPlanningCaseOfficer.
Atanearlystage,UKPowerNetworksagreedwithitsplanning
consultantsthatplanningpermissionwouldbesoughtunder
theTownandCountyPlanningAct.astheproposeddevelopment
wasnotcoveredunder thescopeofageneraldevelopment
orderwithintheElectricityAct.
6.2AlternativeLocationsConsideredtoMeetSequentialTests
From this initial pre-application guidance, as engagement
continued with the council it became clear there were
outstanding concerns relating to the basic need for the
developmentat thespecificsiteand location identified.This
wasparticularlyduetofloodriskatthesite,andthefactthat
thelandwasreservedforgreen-spaceaccordingtothecouncil’s
LocalPlanReviewPolicy,despiteitbeingundertheownership
36 | Smarter Network Storage - design and planning considerations
Figure 8 – Alternative Sites Considered
Smarter Network Storage - design and planning considerations | 37
screeningoftheproposedbuildingwithmoreandtallertrees
tohidethebuildingasmuchaspossible.
One thirdof responsesaskedquestions relating to safety, in
particular therewasconcernoveranychemicalsused in the
storage device; regarding displaced water in the event of
flooding,intheuseofsecuritylightingorinonecaserelatingto
electricalemissions.
Regarding the specific questions that were asked in the
consultationmorethanhalfhadsuggestionsrelatingtotheuse
ofthesurpluslandandtherewereanumberofissuesraised
relatingtoacyclewaythatCentralBedfordshireCouncilwere
keenonextendingtorunbetweentheexistingsubstationand
newstoragedevelopment,andtheriver,ClipstoneBrook. In
general residents wanted the land improved and better
maintained, two specifically wanted allotments and one
wanteditleftnaturalforwildlife.
Four responses specifically did not want a cycle path along
ClipstoneBrook,whichrunsalongthesoutheasternboundary
ofthesite.Thereasonsrangedfromthepathwaywhichwould
be out of sight, encouraging various forms of antisocial
behaviour,reducingthesoakawayduringflooding,theeffect
on the wildlife and safety concerns in relation to speeding
cyclistsandsmallchildrenwhoplayinthearea.
Fourrespondentseithersupportedwhathasbeenproposedor
did not object to the principle of the development. Two
residents stated that they would be writing to Central
BedfordshireCounciltoobject,threewouldlikeustorespondto
themandtwowouldlikealocalpublicmeetingtodiscussthe
matter. Two residents wanted to know what other sites UK
PowerNetworkshadspecificallyconsidered.
6.4ConsultationResponses
AsummaryoftheresponsestotheLocalConsultationleaflet
Analternativesatellitesiteexistedatalocation2kmfromthe
LeightonBuzzardprimaryonexistingfarmland,atasiteeastof
Leighton Linslade that was designated for Industrial use.
However,thelandtherehadnotbeenacquiredbyanypotential
developernorwasthereanycertaintythatUKPowerNetworks
couldacquireanythingsuitable.Noplanningapprovalevenin
outlinehadbeengrantedandthesitewouldrequiretwonew
11kVcircuitstobeconstructed,creatingmajordisruptiontothe
roads in the centre of Leighton Buzzard. This would quickly
mitigate one of the key benefits of using storage as an
alternative to conventional reinforcement: avoiding major
disruptionfromtheneedforathirdEHVcircuitfeedingLeighton
Buzzardprimary.Theconclusionwasthatthemostappropriate
andfeasiblelocationtoinstallstoragewasasinitiallyidentified,
adjacenttotheprimarysubstationlocatedinWoodmanClose.
6.3Pre-ApplicationLocalConsultation
InNovember2012andpriortothesubmissionofaplanning
application,alocalconsultationexercisewascarriedoutwhich
involveddistributingaleaflettolocalresidentsandbusinesses.
This leaflet was distributed to approximately 100 residents,
localbusinessesandthelocalschoolintheimmediatevicinity
oftheexistingsubstation.Thecirculationlistwasadvisedbythe
Local Planning Authority, Central Bedfordshire Council. Three
local councillors were also sent a copy of the leaflet. The
consultationwasrequiredinordertoseekviewsandfeedback
ontheproposeddevelopmentwhichcouldthenbeincorporated
inthedesignsandplanningapplication.Theleaflet,whichis
giveninAppendix1,explainedtheneedforthedevelopment,
detailsofthedesignandtheimpactofthestoragesolution.
BytheendofNovember2012,17responseshadbeenreceived
andthesehighlightedanumberofkeyareasofconcernthat
were to be addressed where possible in the full planning
application, as illustrated below. The general theme of the
responsescentredontheaestheticsoftheproposedbuilding
and on safety. Two-thirds of the respondents wanted better
38 | Smarter Network Storage - design and planning considerations
• Arethereanychemicalsintheequipmentbeingusedwhich
couldcauseahealthriskiftheareaweretoflood?
• Would there be a massive discharge of electricity if an
accidentoccurred?
• WilltherebemorevehiclesparkinginWoodmanClose?
• Whatplanninghasbeendonesothattheexistinghousingis
not affected by floods? Do you intend to increase the
flooddefences?
• Canyouconfirmtherearenohealthriskslivingsoclosetoa
powerstation?
• Whateffectwill thesecurity lightinghaveon thehousing
andwilltherebeanyshadingofit?
6.4.6PropertyValues:
• House values will go down as a result of this. What
compensationwillbeavailable?
6.4.7PublicMeeting:
• Wouldtherebeapublicmeeting?
6.5PreparationandSubmissionofPlanningApplication
TheplanningapplicationforLeightonBuzzard,incorporatinga
numberofstudiesdetailedbelow,wassuccessfullycompleted
andregisteredwithCentralBedfordshireCouncilon8February
2013.EngagementcontinuedwiththeLocalPlanningAuthority,
Central Bedfordshire Council and the Environment Agency
throughouttheapplicationperiod.
Asignificantnumberofstudiesandanalyseswerecompleted
during the period May 2012 – February 2013. These were
managedbyUKPowerNetworks’ Capital Programme team,
whowillbemanagingthesiteconstructionworks.Thisensured
thatadetaileddesignandaccessstatementcouldbecompiled
for the full planning application. A summary of the various
component studies and documentation that was required is
illustratedinFigure10right.
areshownbelow.Thesearegroupedintodifferentcategories
foreaseofreviewandarealsoincludedinapiechartshownin
Figure9right.
6.4.1TheSite:
• Whydoweneedanothersubstationinthearea?
• Whydoesithavetobeinaresidentialareaandnotnearthe
developmentsitisbeingbuilttosupply?
• Fencingshouldberepairedandvandalproof,sothatpeople
donottiprubbishoruseitasa“shortcut”particularlyifthere
isacyclepath.Itshouldbehighfencing.
• Mixed feelings about having a cycle path because of the
childrenplayingthere.
• Whichothersiteswereconsidered?
6.4.2TheBuilding:
• Coulditbebuiltinbricksoitblendedinwiththehousing?
• Coulditeitherbecolouredvariousshadesofbluefromdarkto
lighterfrombottomtotoptoblendinwiththeskylineorgreen
toblendinwiththetreesandshrubberyusedtoscreenit?
• Couldmaturetreesandshrubsbeusedtoscreenthebuilding
ratherthanwaitingfornewtreestogrow?Howhighwillthe
screeningbe?
• Willtherebesolarpanelsontheroofofthebuilding?
• Whatwillhappentotheoldbuilding?
• Willthebuildingbesilent?
6.4.3TheLandscapeandWasteLand:
• Willtherebeon-goingmaintenanceofallthelandscape?
• Couldsomeofthewastelandbeusedasallotments?
6.4.4TheConstruction:
• Howlongisitgoingtotaketobuild?
• Willtherebenoiseanddisruptionwhileitisbeingbuilt?
6.4.5HealthandSafetyissues:
• WhatkindofcablingwillbeusedtoconvertDCtoACandwill
itbeunderground?
Smarter Network Storage - design and planning considerations | 39
Figure 9 – Summary Chart of Consultation Responses
Figure 10 – Supporting Studies and Design and Access Statement Structure
CONSULTATIONRESPONSES 45% Visual
9% Support/No concern (in principle)
5% Project Build (period)
25% Social impact (local)
16% Technology (safety)
Supporting Studies
PrelimContamination
Assessment Report
GeoenvironmentalAssessment Report
Local Consultation Exercise and
Analysis
Flood Risk Assessment
Ecological Study ArboricultrualReport
ArchaeologialSurvey
Construction Traffic Management Plan
Background Noise Study
Land Valuation
Design and Access Statement
Rationale forDevelopment - Analysis
of Strategic Options
Design Criteria, site Layout and Design
Landscaping Plans and Planting Specification
Environmental Impact Assessment and Sustainability
Conformity with Strategic and Local Planning Policies
S106 Agreement - Heads of Terms
40 | Smarter Network Storage - design and planning considerations
Followingre-submissionoftheplanningapplicationafterthe
initialstatutoryperiodhadexpired,ameetingwasheldwith
theCouncilon8April2013todiscussthetermsfurther.Atthis
session,thetermsofthes106agreementwerefullyagreed
andfullplanningconsentswaslaterissuedbythecouncilon7
June2013,subjecttoarangeofpre-commencementconditions
ands106terms.
Asummaryof theoverall timeline for theplanningprocess,
includingthemainengagementpointswiththeLPAandEAand
themainstudiescompletedisshowninAppendix2.
6.7KeyComponentsoftheSection106Agreement
ThefollowingprovisionsarecontainedwithintheSection106
AgreementmadewithCentralBedfordshireCouncil:
1.LeasetoCentralBedfordshireCounciltheremaininglandnot
usedinthedevelopmentforrecreational/leisurepurposesof
thelocalcommunity.Thisleaseisfor99yearswithabreak
clauseanytimeafter20years.
2.Transfera5mwidthstripoflandthatrunsalongthebankof
ClipstoneBrooktoCentralBedfordshireCouncilfortheiruse
inconstructingacyclewaypath,ifandwhentheysochoose.
3.UK Power Networks will during the next planting season
followingthephysicalcompletionofthedevelopment,plant
extratreescreeningroundtheexistingsubstationinorderto
improvethevisualaspectsofthewholearea.
4.UK Power Networks will reinstate fencing between the
leasedlandinpoint1aboveandtheroadWoodmanClose.
Itwillalsoprovidesomenewfencingacrossthecornerof
the existing sub-station site and South Street to aid the
Councilinbuildingacyclewayentrance.
5.UKPowerNetworkswillmakeaoneofffinancialcontribution
towardstheupkeepofthelandleasedtocentralBedfordshire
Councilinpoint1above.
The initial date set for a decision was 5 April 2013. As this
applicationwasnotconsideredtobeamajorapplicationthe
decisiondatewasbasedonthestatutoryplanningtimescales
ofeightweeks.HoweveratthebeginningofAprilthecouncil
requested thatUKPowerNetworkswithdrawand re-submit
the application to allow them more time to conclude
outstanding matters regarding the application. This included
thetermsofthes106agreementwhichwerenotyetfinalised,
asdescribedfurtherbelow.Althoughstrictlynotnecessary,asin
theory, the council could have looked to mutually agree an
extension, theapplicationwassuccessfully re-submittedand
re-registered by the Council on 12 April 2013 and this
gave Central Bedfordshire a further 8 weeks to conclude
theirenquiries.
6.6NeedforCommunityInfrastructureObligations
The pre-application guidance highlighted early-on; the
requirement to enter into a legally binding ‘section 106
agreement’ (s106)due to thescaleof thedevelopment,as
describedinSection5.7.
It was proposed this s106 should cover some suggested
communityinfrastructurecontributions,duetothelossofsome
ofthegreen-spaceforthecommunity,includinguseoftheland
ownedbyUKPowerNetworkswhichwasnotspecificallytobe
coveredwithintheapplication.
Negotiations relating to these financial contributions took
significantly longer thanexpectedwhichwas inpartdue to
feedbackreceivedduringthelocalconsultationwhichhighlighted
thatanumberofresidentswerenotinfavourofacycleway.The
provisionof a cycleway,or funding towards it,washowever
highlighted as desirable during the initial pre-application
guidancefromthecouncilbutwasnotdeemedappropriateor
relevanttothedevelopmentbyUKPowerNetworks.
42 | Smarter Network Storage - design and planning considerations
Thehighestpointofthebuildingis8.3mabovegroundlevel,
with the lowest point, where the building fronts Woodman
Close,being6.6m(thiscomparesto5.5mwhichistheheight
toeaveslevelofthehousesonWoodmanClose).
The localgroundconditionsandmassof thestoragesystem
requireapiledfoundation.Abovegroundthebuildingstructure
willbeacombinationofsteelbeamsandreinforcedconcrete.
Theexternalappearanceofthebuildingwasadjusted,having
originallybeenproposedtobecladinshadesofblue.Following
feedbackfromlocalresidents,thepatternofthecladdingwas
adjustedandthecolourisnowinshadesofgreenasshownin
thefollowingdiagrams,Figure11.
Thisgradationincolour,combinedwiththepatterning,accords
with, and reinforces, the dark colour of the proposed
landscaping,setagainstthesky.Theoveralleffectistoreduce
theapparentbulkofthebuilding.
Thissectiondescribesthefinaldesignsofthestoragefacility,
following public consultation and planning consents and
incorporatingthevariousdesigndriversdescribedaboveand
fromthewiderangeofstudiesandassessmentscarriedoutat
thelocalsite.
7.1BuildingExteriorCivilDesign
Thebuildingcomprisesamono-pitchedsingle-storeybuilding
ofapproximately40mx20minplan,basedonkeydesign
advice received from the Council during the pre-application
guidancestage.
Thesedimensionswerespecificallydesignedtoallowforthe
storagedevicetoexpandinfuture,andbasedonfurtherdetailed
layoutdesignallowthecapacityofthedevicetoincreaseby
2MWandthestoragecapacitytoextendupto17MWh.This
limitationisdescribedfurtherbelowinSection7.4.
Smarter Network Storage - design and planning considerations | 43
Figure 11 – Proposed Visualisation and Elevations with Landscaping
SOUTH-WEST ELEVATION
NORTH-EAST ELEVATION
NORTH-WEST ELEVATION - VIEW FROM WOODMAN CLOSE
SOUTH-EAST ELEVATION - VIEW FROM CLIPSTONE BROOK
44 | Smarter Network Storage - design and planning considerations
consent,afloodmaintenanceplanhasbeenputinplacethat
ensuresaprocessismappedoutfortheclearanceandremovalof
anydebrisfollowingfloodevents.Thedesignalsoincorporates
afloodalarm tobe installedat site,whichalertsUKPower
Networkscontrolengineersintheeventofafloodatsite.
Thisraisedbuildingdesignalsoneededtobebalancedwiththe
needtominimisethevisualimpactofthebuildingandkeepit
below the levels of existing housing. Fortunately, battery
energy storage technology with its flexible and modular
configurationofracksmeansthatrackheightscanbeadjusted
accordingtoneed.Themaximumheightofthebuildinginthe
SNS case is driven by the under-floor void dimension, floor
thickness and height of the battery rack and switchgear
equipmentinternaltothebuilding.
7.3BuildingSurroundings
Otherexternalelementsoftheproposeddevelopmentincludea
loadingbayandanaccessroad.Thisaccessroadwillconnecttothe
existingsiteaccess toWoodmanClose–nonewpermanent
vehicularaccessisrequired.Wherepedestrianaccessisrequired
hardpavingwillbeusedotherwisetheremaininglandwithin
the site boundary will be covered with 40mm shingle to
maintain drainage and reduce weed growth. Sustainable
drainagesystemswillbeusedtoensurethereisnoincreasein
floodrisktootherareas.
To prevent vandalism, maintain public safety and meet the
requirements of the Electricity Safety, Quality and Continuity
Regulations(2002)perimeterfencingisrequired.Thisistobe3m
high“weldmesh”typefencingcolouredHollyGreentoreinforce
the proposed landscaping and minimise the overall visual
impactofthesite.
In order to ameliorate the visual impact of the substation
buildingand the3m-highsecurity fencing,acomprehensive
landscapingschemewasdesignedandformsanintegralpart
7.2FloodMitigationDesign
The consultation with the Environment Agency during the
planningprocess led to thedesignof thebuilding raisedon
stilts to ensure that any potential flood waters were not
displaced,increasingtheriskoffloodingelsewhere.
Basedon theflood-riskassessmentworkcarriedout for the
EnvironmentAgency,the100-yearworst-casepredictedflood
levelswereestimatedataround0.66mabovethegroundlevel
ofthedevelopment.Inordertopreventanywaterdisplacement
andincreaseinfloodrisk,itwasthereforenecessarytoraise
the building by at least this amount. However, health and
safetypolicieswithinUKPowerNetworkswouldmeanthatany
voidunderthebuilding lessthan2mwouldbeclassedasa
confined space. In this case, additional measures must be
employedwhen carryingoutmaintenanceor otherwork to
ensuresafetyofoperationalstaff.Itwasthereforedesirableif
possibletoensurethevoidwasnotaconfinedspacetoensure
easiermaintenanceandaccessifneeded.Forthisreason,the
decisionwastakentoraisethebuildingby2m(atthelowest
groundlevelpoint),whichservestoprovideforeasieraccess
andmitigatesagainstthepredicted1000-yearfloodingevent.
Theunder-floorvoidtothebuildingwillbeenclosedonthree
sideswithsteelpalisadesecurity fencingbutclad toground
levelontheroadfrontageelevation.Inthiswaythebuilding
willappearsolidwhenseenfromtheroad.
TherewasinitiallysomeconcernfromtheEnvironmentAgency
regarding thepotential for debris tobecome trapped in the
palisadefencingwhichmayimpedetheflowofwatersunder
thebuildingintheeventofaflood.However,thiswasultimately
resolvedthroughbilateraldiscussionsandamendmentstothe
fencingdesignwhichincludedwidergapsbetweenpalesandan
increasedgapbetweenthegroundandbottomofthefencing.
Inaddition,aspartoftheplanningconditionsassociatedwith
Smarter Network Storage - design and planning considerations | 45
thatthereisalreadyatreescreenontheoppositesideofthe
brook, and also a requirement of the Environment
Agency to prevent blocking access to the brook for
maintenance.
The extent of landscaping was increased from that initially
developed,asa resultofadditional feedback from the local
consultation during the planning process. Due to comments
relatingtothelookoftheexistingsubstation,aspartoffurther
contributions covered in the s106 agreement, it was also
proposed to include additional landscaping of the existing
primarysubstationforthebenefitofthecommunity.
ofthedesign.Thelandscapinghasbeendesignedtoprovidea
visualscreentotheproposeddevelopment,onethatwillbe
effectivethroughouttheyearandcomprisesscreenplantingof
treesandshrubsonthreeofthefoursidesofthecompoundas
illustratedinFigure12.
A7m-wideplantingstriphasbeenlocatedalongtheWoodman
Close frontage, and a 6m-wide strip is proposed along the
north-east boundary. Both these landscaped areas would
include trees. Along the south-east boundary, the side of
ClipstoneBrook,itisproposedtointroducea3m-wideplanting
strip, but with no trees. This was as a result of the fact
Figure 12 – Proposed Landscape Plan at Woodman Close
46 | Smarter Network Storage - design and planning considerations
Forsafetyandsecuritypurposestherewillbeexternallighting
withinthesite,incasethatengineersneedtovisitthesiteout
ofhours.Inordertoreducelightpollutioninthearea,thisis
designedtofacedownwardsandbedesignedtolimitthelight
spread.Thelightscanbeoperatedmanuallywhenthereare
authorisedpersonnelonsiteandonlyforalimitedperiod.They
canalsobe triggeredautomatically ifunauthorisedaccess is
detectedtosupporttheuseofCCTVwithinthesite.
Oncethefacilityisinfulloperation,thereisnoneedforstorage
installationstobemanned,withonlyoccasionalvisitssimilarto
theexistingsubstation.Maintenanceengineerswillarriveby
van and will park within the compound. Access to the site
duringfloodconditionswillnotberequired.
7.4StorageFacilityInternalCivilDesign
Theoverallconceptforthefacilitylayoutdesignwastosplitthe
facilityintotwomainsections,withonehalfhousingthebattery
racksandonehalfhousingtheinvertersandstep-uptransformers.
Thiswastofacilitaterobustmethodsofrestrictingoperational
accesstothedifferenttypesofequipment,giventhedifferent
operational training required for the various storage system
components.Additionalseparateroomswerethenincludedforthe
HVswitchgear,SCADAandcontrolequipment,fire-suppression
equipment and Heating, Ventilation and Air Conditioning
(HVAC)equipment,basedoninitialrequirementsandestimates.
The internaldesignand layoutof thestoragefacilitydidnot
needtobepresentedaspartoftheplanningconsentprocess,
whichfocussedmoreontheexternalvisualimpacts.However,
aninitialdesignforthelayoutwasrequiredtohelpdetermine
theappropriatesizeandwasdevelopedinconjunctionwiththe
manufacturer.ThisinitiallayoutisshowninAppendix3,basedon
themaximumfutureexpansionofthestorageupto8MW/24MWh.
The final layout designs of the facility, for both the initial
configurationof6MW/10MWhandpotentialfutureexpanded
configuration are shown in Appendix 4 and Appendix 5
respectively.
7.4.1ImpactsonFutureExpansionLimit
Onceconsentswerereceived,this ineffect lockeddownthe
building dimensions and constrains the maximum space
availablefortheenergystoragesystem,iffurtherengagement
withtheCouncilwastobeavoided.
Itwasfollowingthisstagethatthebatterycellsupplierwas
changed due to financial issues with the initially appointed
supplier.Thismeantthatbatteryrackdimensionsneededtobe
amended. Further design work with the new battery racks
showedthataslightlyincreasedfootprintwasneededwhich
meantthefull24MWhcouldnownotbeaccommodatedinthe
currentbuildingsize.
Alower-voltageDC-buswaschosenwhichmeantfewercells
perrack,andhenceaslightlylowerrackheightthanoriginally
anticipated(althoughthereisthepossibilityofhigherracksin
thefuture).Alsotherequirementtoaccommodatea5-panel
11kV switchboard with overhead cable access increased the
floorspacerequirementsforauxiliaryequipment.
While technically feasible to expand the storage facility to
accommodateup to approximately 20MWhwith changes to
theinternallayoutofthestoragebuilding,aninternalreview
determinedthatthisprovidedinsufficientclearancebetween
racks to allow for safe access and replacement of battery
modules.Themaximumfuturecapacitythatthebuildingcould
safelyaccommodate,usingthissametechnology,wastherefore
deemedas8MW/17MWh,asshowninAppendix5.
BasedontheexistingdemandprofileatLeightonBuzzard,the
initial storage capacity of 10MWh is estimated to provide
sufficientenergytohandlearound3.5%proportionategrowth
from the highest historical peak demand observed in 2010.
Smarter Network Storage - design and planning considerations | 47
Analysis demonstrated that a wide range of potential peak
demandprofilescanbesupportedintothefuture,andevenwhen
limitedto8MW/17MWhthefacilitycouldprovidesupportfora
highsymmetricalmorningandeveningpeakoflimitedduration.
Itwasalsonotedthattherearelikelytobesignificantstorage
technologychangesoverthecomingyears,whichmayfurther
improvetheexpandabilityofthefacility.Forexampleanew
generationofbatterieswithhigherenergydensitymayallowa
morecompactandspace-efficientdesign.
Forthesereasons,thedesignofthebuildingtoaccommodate
atleastthemaximumpracticalnumberofbatteryracks,using
“today’s” technology was considered to be the optimum
solution. It was however proposed that the designed floor
loadingcapabilitywasnotreducedasaresultofthischange,in
order to leave flexibility to use a denser energy storage
technologyshouldchangesinbatterytechnologyallowforup
to24MWhinthefuture.
7.4.2ImpactsonInternalLayout
Anumberof furtherdesign changesweremadeduring the
designprocess,comparedtotheinitialproposedlayoutshown
inAppendix3.
Asaresultoftheplanningprocess,itwasapparentthathigh
levelsofair-conditioningrelatednoisewouldnotbeacceptable
due to theproximity to residential housing.As a result, air-
conditioningandventilationextractionpointswerepositioned
onthesouthernfaceofthebuilding,directedawayfromthe
road and residents. Significantly, thepositionof the inverter
unitsandstep-uptransformerswasthenswappedsothatthey
occupythesouthernhalfofthebuilding,withthebatteryracks
nowoccupyingthenorthernhalf.Thiswasaresultofthegreater
heat output of the inverter units requiring increased cooling
with more ventilation available on the southern face of
thebuilding.
Thischangeoforientationhasimplicationsfortheinstallation
oftheequipmentasitwasoriginallyenvisagedthatthelarge
inverter units and transformers would be delivered through
largeaccessdoorsonthenorthsideofthebuilding,wherethe
access road allows for delivery vehicles. The battery racks,
beingmodularcanbeinstalledincrementallywithouttheneed
forlargeaccess.Thechangeoforientationmeantthiswouldno
longerbepossiblefromthesouthernside,andsoinstallationwill
nowbecarriedoutbycraningintheinvertersandtransformers
throughtheroofofthefacility,priortocompletionoftheroof.
Otherfactorsamendedduringthedesignprocessincludedthe
internalcablingforthefacility.Althoughthevoidunderneath
thebuildingtechnicallyprovidedspacetoruncablingbetween
the component parts, the high weights of the equipment
meantthatitwasdesirabletoavoidpenetrationsinthefloor
whichwouldcomprisetheintegrityofthestructure.
Each battery rack weighs around 1,500 kg, so for 10MWh
configurationtheweightofallthebatteryracksisapproximately
198,000kgand459,000kgfor24MWhofenergycapacity.Each
inverter unit is approximately 9,500kg and each step-up
transformerisapproximately7,500kg.
Tohelpavoidlargepenetrationsinthefloor,overheadcabling
linkingtheinverterstoaninsulatedoverheadDC-busbarsystem
acrossthebatteryrackswillbeused.Whilethisincreasesthe
loadingneededtobesupportedfromtheroofofthebuilding,it
preventsadditionalcostinprovidingforsignificantpenetrationsin
thefloor.AninsulatedoverheadDC-busbarsystemalsoallowsfor
simplerisolationanddisconnectionofbatteryracksfromthesystem.
7.5StorageFacilitySafetyDesign
Thesafeconstruction,operationandmaintenanceofalloperational
sitesisofutmostimportancetoUKPowerNetworksinlinewith
itsresponsibilitiesasalicensednetworkoperatorandvisionto
bean‘EmployerofChoice’.
48 | Smarter Network Storage - design and planning considerations
Thepredominantsafetyaspectsthathaveneededconsideration
duringthedesignprocessareasaresultofthehazardsandrisks
associated with new battery energy storage and inverter
technology. While the risks and mitigating safety features
associated with the ancillary plant, such as high voltage
switchgearandtransformers,isrelativelywellunderstoodby
UK Power Networks, there is less experience with those
associated with energy storage technologies, with just one
otherbatteryenergystoragefacilityinstalledonournetworks
todate.Themainriskassociatedwithlithium-ionbatterycell
technologyisfire,andinparticularuncontrolledpropagationof
firefromonecelltoanother.Whilstitwasarequirementofthe
tenderprocessthatrespondentsprovidedsolutionswhichhad
multiple layers of defence, starting with the fundamental
designofthebatterycellsthemselves,itisnecessarytocarryout
analysisofworstcase(andthereforehighlyunlikely)scenarios.
Anumberofexercisesandstudieshavebeencarriedout to
ensurethatrisksarewellunderstood,andmitigatedasfaras
possible.Thesehaveincluded:
• Astructured‘So-What-IfTest’andanalysis(SWIFTanalysis)to
helpidentifyinastructuredwaythemainhazardsandrisks
ofthecompletestoragesystem;
• HazardElimination&ManagementListreview;
• Fire Risk Assessment Review of gas analysis from cell
safetytests;
• FireEngineeringAnalysisandAssessment;and
• LiveFireTestofbatterytrays,inordertoinformmodels&
extinguisherspecifications.
Theresultsoftheseactivities,inconjunctionwiththeUKPower
NetworksFireProtectionEngineeringStandardforoperational
sites,havehelpedtoguidethesafety-relateddesignfeaturesof
thefacility,whichinclude:
• Adequatemeansofescapeforallpersonsonthepremises,
viamultipleegressroutesfromallzoneswithinthefacility;
• Azoneddesignprovidingareasofcontainment;
• Appropriatelevelsoffireresistingconstructiontocontainany
firethatoccurs.Inparticularthemainstructuralcomponents
ofthebuildingwillhave60minutesoffireresistancecapability;
• Fixedfiredetectionandsuppressionsystemforeachzone,
utilising an inert gas suppression system to contain and
controlanyfireintheeventofacatastrophicfailure;
• Themeansofescapewillbeilluminatedandprovidedwith
emergencylighting;
• Thepremiseswillbeprovidedwithautomaticdetectionand
alarm, in accordance with BS5839 Part 2, for warning all
personsonsiteincaseoffire;and
• Handheldfireextinguisherswillbeprovided,inlocationsto
beagreedwiththeapprovalAuthorities.
Itshouldbenotedthatthereareimplicationsfortheon-going
operationalcostsofstorageinstallationsofsuchmeasures,as
all necessary systems required as part of the general fire
precautions are required to be satisfactorily maintained and
periodicallytestedbyspecialistcontractorstoensureadequate
protection is maintained. However, DNOs are in a strong
positiontomitigatetheserisksandcostsgiventheirfiresafety
requirementsacrossmanyoperationalsites.
TheFireEngineeringAnalysisstudyalsoprovidedanassessment
oftheimplicationsofaworstcasescenariofire.Theanalysis
involveda3Dradiationmodeltopredicttheimpactofaworst
casefireonsurroundingassetsandproperty.Fromthestudy,it
wasconcludedthatafireinvolvingthestoragesystemisnot
expectedtoresultindamageorfirespreadtoadjacentfacilities
orproperties,andthatthesafetyfactorsincludedintheanalysis
provideadequatedemonstrationthatafirescenarionecessary
tocausefirespreadisnotcredible.Althoughnotthecaseforall
storagetechnologies,itwasalsonotedthatitisacceptableto
usewateronLithiumIonbatterycelltechnology.
7.6StorageFacilityElectricalDesign
Asimplifiedsingle-linediagramoftheelectricaldesignforthe
Smarter Network Storage - design and planning considerations | 49
Figure 13 – Single-Line Electrical Design
installationisshowninFigure13below,withtheexisting11kV
primary(LeightonBuzzardPrimary)shownatthetopleft.
Thestorageinstallationwillbenamed‘LeightonBuzzardSNS’and
is shown schematically within the box towards the bottom.
Startingfromthecommonpointofcoupling,thestoragefacility
connectstothe11kVbusbarsattheexistingprimarysubstationvia
twocablesandswitchgearwhichwillbeusedtobothprotect
thefacilityfromnetworkfaults,andvice-versa.Twopointsof
connectionaretobeprovided,oneachsideofthebussection,to
ensurethatthestoragedevicecancontributetosecurityofsupply
evenintheeventthatthebus-sectioncircuitbreakerisopen,
isolatingonehalfofthebusbar.Foradditionalredundancy,an
additionalcircuitbreakerisprovidedontheincomingfeederwithin
thestorageinstallationforfurtherprotectionandisolation.
Withinthefacility,theswitchboardhasfourpanelsforconnection
tothetransformersandinverterunits.Asdescribedpreviously,
threeindependenttransformerandinverterunitgroupswillbe
initiallyconnected,toprovidethe6MWpowerrating,withthe
optionforafourthgrouptobringthepowerratingto8MW.Each
oftheseindividualinverterfeeders,labelled‘11kVPCS0X’has
its own isolating circuit breaker to allow disconnection and
isolationofanyindividual2MWgroup.
On the DC-side, each inverter will have battery 44 racks
(consisting of 24 trays each) connected, each of which is
individuallyisolatablefromanoverheadDC-busbarsystem.This
helpstheinstallationconformtoUKPowerNetworksDistribution
SafetyRuleswhichideallyrequiresapointofisolationwherea
visualconfirmationofdisconnectioncanbeprovided.
LBPrimaryT2
LBPrimaryT1
IncomingCables/OHLsfrom
SundonGrid
“Leighton Buzzard Primary”
IncomerCB
IncomerCB
LeightonBuzzardSNSFeederCB
OutgoingCables/11kV
Feeders
BusSectionCB
LeightonBuzzardPrimaryIncomer11kV
CB
11kVPCs04CB
11kVPCs02CB
11kVPCs01CB
11kVPCs03CB PCST3
PCST2
PCST1
~~~
2 3 4 5 6 7 8 9
1
1
2
3
4
5
6
7
8
9
LeightonBuzzardPrimarySwitchboard
11kVCabling-ESSFeeder
ESSHVPanel
Internal11kVCabling-InverterFeeders
Step-UpTransformers
Inverter-TransformerLVCabling
PCS/Inverters/SMSUnits
DCCabling
BatteryRacks
“Leighton Buzzard SNS”
50 | Smarter Network Storage - design and planning considerations
Learning Obtained, Conclusion and Recommendations
8
Smarter Network Storage - design and planning considerations | 51
8.1LearningSummary
Thefollowingtablesummarisesspecificlearningthatisrelevant
tothesecuringofplanningconsentsatLeightonBuzzardand
theimpactondesign.
Ref
1.
2.
3.
4.
5.
6.
Learning
Theenergystoragesystemsupply
chainisimmatureandevolving-
existingprocurementdatabases,
suchasAchillesdonotprovidethe
bestviewofpotentialsuppliers
(thisalsoappliestootherinnovative
technologies).
Thereareseveraldifferent‘types’
oforganisationthatcansupply
energystoragesystems,buteachhas
expertiseindifferentareas.Itisnot
yetclearwhowillevolvetobethe
besttypeofleadsupplier
Highcapitalinvestmentsforstorage
technologymanufacturers,in
combinationwithweakmarket
conditionscancauseweaknesses
infinancialstability
Commerciallyavailablecreditreports
arenotadequatefinancialdue
diligence.
Theplanningconsentsprocesstakes
moreeffort,costandtimethan
expected.Thisturnedouttobelonger
thanstatutorytimescales
LPApoliciescandifferwidelybetween
areas;andpoliciescanbesetforland
thatisnotwithintheirownership
Impact
Supplierswithrelevantsolutions
maybemissed
Supplierswithrelevantsolutions
maybemissed
Riskstofinancialstabilityof
supplierpartners
Riskstofinancialstabilityof
supplierpartners
Increasedspendonplanning
process,andanextensionofthe
timerequiredtosecureplanning
consents
Inconsistenciesbetween
requirementsforstorage
deployments
PossibleSolution
Ensureareviewandmarket
researchofthecurrentmarketand
alternativepotentialsupply-chain
partnerstoensurenewplayersare
incorporated,asthemarketplaceis
changingrapidly
Ensuremarketresearchiscarried
out.Considertheadvantagesand
disadvantagesofsupplyfrom
differenttypesoforganisations
Ensurefinancialduediligenceof
technologypartners,including
sub-contractors
DNOsandTNOsneedtoseek,
andsuppliersneedtobewilling
toprovide,informationabout
financialstabilitythroughoutthe
entiresupplychain
ConsultwithLPAearlyinthe
process.Ensureadditionaltimeand
budgetisfactoredinforalternative
storageinstallationinvestigations
Supportthedisseminationof
learningandeducationaround
storagetolocalauthorities
52 | Smarter Network Storage - design and planning considerations
Ref
7.
8.
9.
10.
11.
12.
13.
14.
Learning
Thereisaneedtobemindfuloftime
constraintswhenindiscussionswith
LPAoveranysection106agreement
provision
Stakeholderconcernsintheplanning
processfromstorageweremore
focussedonlocalissues,suchascycle
ways,thanspecificsofthestorage.
Mainthemeswerelocalissues,
visualsandhouseprices
Atight-timescalecanputpressure
onnegotiationsrelatingtoplanning
obligations
Operationalsitescanpotentiallybe
retained‘operational’ifboundaries
areestablishedearly/historically,
avoidingtherequirementfor
planningpermissionforDNOs
Footprintsforsimilarbattery
technologiescandifferbetween
manufacturers.Hence,estimatesof
footprintsforacertainenergycapacity
areonlyvalidforasinglesupplier
Havingobtainedplanningconsents
forasitewilllockdowntheexternal
sizeanddesignofthebuilding
Developmentcontrolwithinlocal
plan,maydesignateintended
operationallandfornon-electricity
undertakingpurposes
Fundamentalcomponents,in
particularthebatteryandthepower
converter,arelikelytobeinherited
designsfromothersectors
Impact
Increaseintimeandcostofstorage
deployments
Highercostsofplanningpermission
obligations
Improvedtimescalesforstorage
deployments
Opportunitytoincreasethebattery
sizeinthefuturemaybelimited
Thiswilllimitmakinganychanges
totheexternalappearanceofthe
structure,unlessapprovalisobtained
fromtheLPA
Maymakeobtainingplanning
approvalharder
Limitedabilityforpurchasersto
dictateDC-busbarvoltages;which
inturnimpacttheheightand
footprintrequiredforaninstallation
PossibleSolution
Appropriatebudgetshouldbe
consideredwherenecessary
Exploreandunderstandthelocal
issuesbeforedevelopmentsand
lookforpreviousapplications/
presscomments
Ensureengagementorplanning
processbeginsearly.Ifatallpossible
buildintimeontheexpectationof
needingtoappeal.Seeplanning
timelineinAppendix2asaguide
Ifoperationalsitesarerequired
forlong-termdevelopmentthey
shouldbeutilisedwherepossible;
althoughthiswillnotbepractical
forthird-partydevelopers
Allowforsomemargininhousing
dimensionstoallowforfuture
expansion
Ifunavoidableseekapprovalfrom
theLPA
Monitorandcommentonlocal
planswhenpublished
Ensureearlyunderstandingofthe
DCvoltagesandrackconfigurations
Smarter Network Storage - design and planning considerations | 53
8.2Conclusion
SNSisaLowCarbonNetworkfundedprojectwhichisexploring
the economics of using electrical energy storage to defer
network reinforcement at a selected trial site adjacent to a
primarysubstationinLeightonBuzzard.Havingcommencedin
January2013,theprojectrunsforfouryears.Thefirsthalfofthe
project timeline concentrateson the selectionanddesignof
the storage device and the construction and installation of
thefacility.
This report has documented early learning gained from the
project,concentratingonthedesignandplanningconsiderations
which are necessary for large scale distribution connected
electrical energy storage. It provides the considerations
necessaryinsecuringplanningpermissionatthetrialsiteand
howthishasimpactedthedesignbothatLeightonBuzzardand
moregenerallytheconsiderationsthatwouldbenecessaryfor
a DNO or other storage device developer to make when
consideringtheuseofdistributionscaleelectricalstorage.
Thechoiceanddesignofastoragedeviceisdrivenbyawide
range of factors, but initially derived from the primary
requirement of meeting or deferring a reinforcement
requirement.Anumberoffactorsincludinglocation,capacity
requirementincludingpredictedandspeedofgrowth,safety
andeconomicbenefitswilldefinetheneedandselectionof
technology, who can provide it and how it should be
accommodated.Thesedesignrequirementswillcreatevarious
impacts each of which will determine more specific
requirements in the design such as footprint, cooling
requirementordetailedplanningrequirements.
Storageismostlikelytobeofvaluewheretheconventional
upgrade is complexandcostly, itwouldaddsignificantover
capacity, the constraint can be met by a small amount or
additional capacity or will defer further investment for a
reasonableperiod(5+years)oftime.
Baseduponanalysisasaresultofthermalcapacityconstraints
andavailabilityspace,LeightonBuzzardemergedasthepreferred
siteatwhichtobuildthestoragedevice.Althoughalternative
siteswereconsidered,thissitewouldprovidemostneedandwas
bestplacedtodemonstratetheeconomictestsrequiredforthe
project.Thislocationwouldrequireplanningpermissionandthis
fact together with the specifics of the location drove some
fundamentaldesignchoices.Primarilytheproximityofthesite
toalocalwatercoursemeantthatthelandwaslocatedina
high-riskfloodlocation.Itwasalsolocatedclosetoresidential
housing.Thismeantthatbuildingdesignespeciallyvisualaspects
wouldbeimportant.Theinitialratingsizeofthestoragedevice
wasdeterminedtobe6MW/10MWh.Thiswouldinitiallyprovide
anoptimumamountofenergycapacityandduration.LithiumIon,
whichhadgoodsafetyfeaturesrelevanttothelocation,was
thetechnologychosenandtogetherwiththesizeofbuilding
designwouldprovidethecapabilitytoexpandthedeviceata
laterdateto8MW/17MWh.Thiswouldbelessthanoriginally
planneddue toanecessary changeofbatterymanufacturer
whichoccurredfollowingthecompetitiveprocurementprocess.
Planningpermission is requiredformostnewstructuresand
buildings,andisalsorequiredforthechangeofuseofexisting
buildingsorsites.TheplanningsystemforEnglandandWalesis
setoutintheTownandCountryPlanningAct1990.Itisalmost
certainthatanynewortemporarybuilding,forexample,the
siting of shipping containers, required to house a grid-scale
electricalenergystoragesystem,willrequireplanningconsent.
Theexceptiontothisisasitethathaspermitteddevelopment,
for example, by virtue of its operational use, such as an
operational substationwithexisting spacewithin itsexisting
curtilage. It isalmost certain thatanynewdistribution scale
storagedevicewouldrequireplanningpermission.
AplanningapplicationfortheLeightonBuzzardsitewasinitially
submittedtoCentralBedfordshireCouncilinFebruary2013.It
54 | Smarter Network Storage - design and planning considerations
followed a local consultation on the development which
concluded that some changes to the visual aspects of the
proposedbuildingand its screeningshouldbemade. Itwas
also necessary to provide significant detail on the required
development and benefits of the chosen location over
alternatives.Thesechangestogetherwithadvicereceivedfrom
theLPAandEnvironmentAgencyonprovisionsnecessary to
mitigatefloodinghadbeenincorporatedintheapplication.A
section 106 agreement was negotiated with the LPA and
becameaconditionoftheplanningapprovalthatwasfinally
granted,followinganextensiontothestatutorytimescales,in
June2013.
TheexternaldesignoftheLeightonBuzzardbuildingwasfixed
aspartoftheplanningapplication.Ithaddevelopedfromthe
equipment it was intended to house, flood mitigation
requirementsandtheneedtobuildsomethingthatwouldbe
acceptableincloseproximitytoresidentialhousing.Tofurther
mitigateanyadversevisualconcernsextratreeplantingwas
incorporatedintotheoveralldesign.
Themainlearningpointscentredaroundprocurementandthe
selectionofastoragetechnologyprovideraswellastheneed
to takedueregard inallaspectsof localauthorityplanning,
includingtheneedtobevigilantonreviewinglocalplansand
ensuringthataplanningapplicationisrobustonsubmission.
Smarter Network Storage - design and planning considerations | 55
Residents Consultation DocumentAppendix 1
56 | Smarter Network Storage - design and planning considerations
Introduction
UKPowerNetworks(Operations)Limited(“UKPowerNetworks”)
onbehalfofEasternPowerNetworksplc,thelicenseddistributor
ofelectricityintheEastofEngland,planstobuildanextension
toitsexistingsubstationatWoodmanClose,LeightonBuzzard.
Thisleafletexplainsthereasonswhyanextensiontothesubstation
isneededandgivesabriefdescriptionoftheproposals.Preliminary
advicehasbeensoughtfromCouncilofficers,Membersandthe
EnvironmentAgency.Commentsfromthelocalcommunityare
nowbeingsoughtbeforeanapplicationforplanningpermission
issubmittedtoCentralBedfordshireCouncil.
WoodmanCloseSubstation,LeightonBuzzard
The existing Woodman Close Substation is situated on the
north-eastsideofSouthStreet,betweenClipstoneBrookand
WoodmanClose,asshowninFig.1:LocationandSitePlan.The
adjoininglandwasacquiredin1970forthepurposeofproviding
electricityandpotentialfurtherexpansion.Whilstthelandwas
notrequiredforelectricitysupplypurposes,itwasleftasopen
landand,atonetime,wasusedforallotmentsbylocalresidents.
Thatusehasnowceased.
TheNeedfortheSubstationExpansion
TheWoodmanCloseSubstationisreachingitscapacitydueto
an increase in demand for electricity in the local area. To
maintainreliablepowersuppliesintothefuture,thesubstation
needstoexpand.Afterassessinganumberofpotentialsites
using a series of technical, engineering, environmental and
planningcriteria,WoodmanClosewas identifiedas theonly
suitable site toprovide thisessential infrastructure,one that
wouldincurtheleastdisruptiontotheexistingsupplyandbe
builtwithinthenecessarytimeframe.
Closeproximity to theexistingWoodmanCloseSubstation is
absolutelyessential.Asthesiteisalreadyinourownershipand
wedonotneedtoacquireadditionalland,italsoallowsusto
meettheregulatoryrequirementstodeliverbest-valuetoall
our electricity customers in Bedfordshire and the East of
England.Astheexistingandnewfacilitiescanallbeenclosed
within a secure compound, this offers the highest level of
securityforcontinuedelectricitysupplyaswellasfromtheft
andvandalism.
Proposed substation expansion for Leighton Buzzard
Fig.1 Location and Site Plan
The existing Woodman Close Substation
Smarter Network Storage - design and planning considerations | 57
Newtechnology
Theextensiontothesubstationwilluseanelectricalstorage
deviceinplaceoftraditionalsubstationequipment.Thisnew
technologyprovidesamoresustainablewaytoreinforcethe
electricity network. It reduces the need to create additional
powerlinesfeedingthesubstationandremovestheneedto
installnewtransformersonthesite.Electricalstoragesupports
the increasing use of electricity generation from wind
turbines and solar panels, smoothing out the peaks and
troughsonthelocalnetworkcausedbythevaryingstrengthof
windandsun.
Proposeddevelopment
Wearethefreeholdownerof11,000sq.mofthelandoutlinedin
blueinFig.1.Planningpermissionwillbeneededforthenewarea
ofdevelopmentfortheextensiontothesubstation.Thisarea
(outlined in red inFig.1andcoveringanareaof3,000sq.m)
adjoinstheexistingsubstationcompoundonitsnorth-eastern
boundary.
Theproposeddevelopmentincludesasingle-storeybuildingwith
afootprintofabout40mx20mandamaximumheightof8.3m
above ground level. The shape and volume of the proposed
building is dictated by the electrical plant that needs to be
housedwithinit.Thesubstationcompoundwillbesurrounded
bya3m-highsecurityfenceandlandscaping.
Floodpreventionmeasures
Except for a small part of the Woodman Close Site in the
northeastern corner that is above the flood plain, a large
proportion of the site is in a flood risk area. Consequently,
special precautions have to be taken in the design of any
developmentwhichneedstoberaisedabovepredictedflood
levels.FollowingconsultationswiththeEnvironmentAgency,
the proposed extension to the substation incorporates a
2m-highvoidbeneaththeelevatedgroundfloor,thusraising
theoverallheightto8.3mabovegroundlevel.
Designandlandscaping
Theproposedbuildinghasamono-pitchedroofandapatterned
facadeonthreesides.Thefacingmaterialwillbecolour-coated
metalpanels. Thechoiceof coloursof thebuildingcouldbe
changedasaresultofthisconsultation.
Theproposedbuildinghasanelevationaldesignthatisintended
tohelpitblendinwithitssurroundingsandtominimisethe
visualimpactasfaraspossible.Thepatterneddesignaimsto
introduce an interesting pattern to the streetscape. We
will use good quality facing material that will require
minimalmaintenance.
It is proposed to screen thedevelopmentusing landscaping
along the Woodman Close north-western elevation and the
northeasternelevationfacingtheopenland.Thisscreen,which
will be a minimum of 5m deep, will include trees and
evergreenshrubs.
Impacts
Noise
There will be no increase in noise above the present levels
resultingfromtheproposedexpansionofthesubstation.
Lighting
Minimal security lighting will be used in order to minimise
disturbance.
Wildlife
Arecentwildlifesurveyofthesitefoundnoprotectedspecies.
OurEcologisthasrecommendedthat(i)therivercorridorshould
be reserved foramphibians;and (ii)partof thevacant land
should be retained for toads, frogs and other wildlife. This
wildlife area will not be landscaped but managed to
preventovergrowth.
Fig.1 Location and Site Plan
The existing Woodman Close Substation
58 | Smarter Network Storage - design and planning considerations
ViewfromWoodmanClose
Existing
Proposed (illustrative only)
Existing
Proposed (illustrative only)
ViewfromtheVacantLand
Smarter Network Storage - design and planning considerations | 59
HealthandSafety
Thetypeofenergystoragesystemtobeinstalledemploysa
safeformoftechnology.Theextensiontothesubstationwill
exceedthestringenthealthandsafetyrequirementsandfire
preventionmeasuresrequiredforsubstations.
EMF’s
ThisfacilityisprimarilyaDirectCurrent(DC)facility,therefore
therewillbenoincreaseinthelevelofEMF’s(Electromagnetic
fields)abovethepresentlevelsfromtheproposedexpansion.
TheSubstationinOperation
Theproposedbuildingwillonlyhouseelectricalplant.Exceptfor
occasionalvisitsforinspectionandmaintenancepurposes,no
personnelwillbeworkingonthesite.Exceptduringtheconstruction
andcommissioningperiod,nolorriesarelikelytovisitthesite.
VehicularAccess
Thevehicularaccess intothenewcompoundwillbeviathe
existingsubstationaccesspoint.Therewillbeon-siteparking
foroccasionalvisitingoperators.
CommunityBenefits
The extension to the substation will include sustainable
technologytohousealowcarbon,energystoragesystem.A
keybenefittothelocalcommunityisourincreasedabilityto
providereliablepowersuppliesinthefuture.
SharedFootpathandCycleway
TheCouncilwishestosecureastripoflandalongsideClipstone
Brookforasharedfootpath/cyclewayonpartoftheEastern
PowerNetworkssite(seeFig.1).Thedetailedrouteandlease
arrangementsaretobediscussedwiththeCouncil.
AboutUKPowerNetworks
UKPowerNetworksdistributespowertoaquarterofBritain’s
populationthroughitselectricitynetworksservingtheEastof
England,SouthEastandLondon.Thecompany’s5,000employees
arededicatedtodeliveringasafe,secureelectricitysupplyto
abouteightmillionhomesandbusinessesviaitsnetworkof
substations,overheadlinesandundergroundcables.
Theindustryregulator,Ofgem,placesconditionsonUKPower
Networks,forexample,itmustensuresafeandreliablepower
supplies to its customers, and cater for future technological
changesandgrowthindemand.ThisyearUKPowerNetworks
isinvesting£360millioninitselectricitynetworksandaround
£1.8billioninthefiveyearsto2015.
NextSteps
We are currently preparing the scheme for a planning
applicationsubmission,taking intoconsiderationadvicefrom
theCouncil,theEnvironmentAgencyandthepublic.Itishoped
thatanapplicationwillbesubmittedduringNovember2012,
withtheconstructionworksstartingin2013.
YourComments
Wewelcomeyourcommentsontheproposalonissuesincluding:
• thedesignandcolourofthecladding;
• thelocationofthesharedfootpath/cycle-way;
• theuseof thesurplusEasternPowerNetwork land foras
longasitisnotneededforelectricitydistribution.
Contactus
Ifyouhaveanyqueriesorcomments,pleaseemailusat:
UKPowerNetworks
LeightonBuzzardSubstationEnquiry
c/oStrategyandRegulation,1stFloorNorth
EnergyHouse
HazelwickAvenue
Crawley
WestSussexRH101EX
Smarter Network Storage - business model consultation | 61
Planning Timeline Summary
June
12
Jul 1
2A
ug 1
2Se
p 12
Oct
12
Nov
12
Dec
12
Jan
12Fe
b 13
Mar
13
Apr
13
May
13
Jun
13
May
12
Plan
ning
Enq
uiry
initi
ated
with
Cent
ralB
eds
31/7
Pre-
App
Guid
ance
requ
este
dfr
omCe
ntra
lBed
s
16/8
Supp
ortin
gle
tter
from
Cen
tral
Bed
s
2/8
Pre-
Plan
ning
Advi
ceM
eetin
g
30/8
Full
Pre-
Appl
icat
ion
Advi
cere
ceiv
ed17
/9Pl
ace-
Mak
ers
Mee
ting
8/2
Full
Plan
ning
App
Subm
itted
13/5
Dra
ftD
ecis
ion
Not
ice
8/4
s106
Mee
ting
with
Pla
nnin
gof
ficer
s
7/6
Not
ice
ofG
rant
ofP
lann
ing.
2n
dSt
atut
ory
Appl
icat
ion
resp
onse
dead
line
5/4
1stS
tatu
tory
Ap
plic
atio
nRe
spon
sed
eadl
ine
27/3
Requ
estt
ow
ithdr
aw&
resu
bmit.
Ap
plic
atio
nre
subm
itted
18/3
EAF
eedb
ack
onfe
ncin
gad
just
men
ts30
/4Re
subm
issi
onre
spon
sefr
om
EAa
nd
sugg
este
dco
nditi
ons
26/2
EAF
eedb
ack
ona
pplic
atio
n
16/1
0UK
PNre
spon
ds
toc
once
rns
rais
ed
7/11
Loca
lRes
iden
tsCo
nsul
tatio
n
21/1
1Lo
calC
onsu
ltatio
nPe
riod
Ends
4/10
Furt
her
Guid
ance
from
Cen
tral
Be
ds
29/1
1Ta
rget
edU
KPN
resp
onse
sto
re
side
nts
29/1
1Ce
ntra
lBed
sco
mm
ents
on
UKPN
resp
onse
s
22/5
Pre-
App
Guid
ance
requ
este
dfr
omE
A
31/7
Pre-
App
Gui
danc
ere
ceiv
edfr
omE
A
16/1
Site
Sec
urity
Ass
essm
ent
19/1
2Tr
affic
Man
agem
ent
Stud
y
22/8
Geo
tech
nica
lSu
rvey
s
20/8
Arch
eolo
gica
lSu
rvey
s10
/8Ab
oric
ultu
ral
Surv
ey
4/6
Ecol
ogic
al
Stud
y
24/7
Floo
dRi
skA
sses
smen
t
17/7
Back
grou
ndN
oise
Surv
ey
23/6
Topo
grap
hica
lSu
rvey
6/7
Cont
amin
atio
nA
sses
smen
t
Plan
ning
St
udie
s
Com
ms
with
LPA
,co
mm
s w
ith E
A
and
UKP
N
Act
iviti
es
{ {01/0
5/20
1210
/06/
2013
Smarter Network Storage - business model consultation | 63
Original Building Layout Design for 8 MW/24MWh
Final Building Layout Design for 6 MW/10MWh Project
Smarter Network Storage - business model consultation | 65
Smarter Network Storage - business model consultation | 67
Future Potential Building Layout Designfor 8 MW/17MWh Project