    Six core activities in the commissioning of the earthing system

    Six core activities in the commissioning of the earthing system (photo credit: SouthCityElectrical via Youtube)

    Testing of the earthing system

    Commissioning of new earthing system is essential as a validation step for the design and installation process and

    for the design inputs. In most cases commissioning should measure the outputs of the earthing system in terms of 

    produced voltages and current distributions rather than solely resistance.

    The commissioning should consider closely the key performance criteria identified in the hazard identification and

    treatment analysis phases.

    Commissioning will determine the earthing system initial compliance and set a benchmark or 

    baseline for ongoing supervision.

     As it is not always possible to foresee all hazard mechanisms at the design stage commissioning testing should also

    determine the need for any localised secondary mitigation and any additional requirements for telecommunication

    coordination and pipeline interference coordination or mitigation.

    The earthing system commissioning procedure normally consists of six core activities. In some instances, not all

    1

    http://electrical-engineering-portal.com/guidelines-for-installing-power-transformershttp://electrical-engineering-portal.com/commissioning-earthing-systemhttp://electrical-engineering-portal.com/

  • 8/17/2019 Six Core Activities in the Commissioning of the Earthing System

    2/5

    activities are required //

    1. Visual inspection

    2. Continuity testing

    3. Earth resistivity testing

    4. Injection testing

    1. Earth potential rise (EPR) measurement

    2. Current distribution measurement

    5. Transfer, touch and step voltage testing

    6. To be aware of 

    1. Visual inspection

    The visual inspection typically involves checks of //

    Design compliance and as-built drawing accuracy

    Condition of earthing conductors and connections

    Condition of earthing electrodes

    Presence and condition of earthing bonds to equipment

    Condition of surface layer materials if required

    Condition of access fences if required

    Presence of transfer hazards.

    2. Continuity testing

    Continuity testing is used to measure the resistance between items of plant within the main earth grid and to

    components that should be effectively bonded to the grid. This test is especially important in large earthing systems

    where visual inspection of all conductors and connections is more difficult.

     Adequate bonding is essential to ensure that personnel are working only on equipment that is

    effectively connected to the earthing system.

    Go back to Commissioning Activities ↑

    3. Earth resistivity testing

    It is often necessary to carry out earth resistivity tests in conjunction with performance assessments to allow accurate

    error corrections and safety criteria determination.

    2

  • 8/17/2019 Six Core Activities in the Commissioning of the Earthing System

    3/5

    Even where resistivity testing was undertaken at the design stage, additional testing (however brief )

    may help to define measurement errors and periodic variations.

    Go back to Commissioning Activities ↑

    4. Injection testing

    The remaining tests require the presence of a simulated power system line to ground fault. To achieve this, a circuit is

    established between the earthing system under test and a remote injection point.

    Ideally this circuit should reflect the actual fault return point. Where this is not possible post testing analysis is

    necessary to reflect the actual fault scenario or scenarios. This may include multiple points of return.

    The simulated fault is typically made sustainable by injecting a small current, commonly between 2 and 20 amps .

    The effects are made measurable, even on live systems, by injecting at a frequency away from power system

    frequency and using frequency tuneable measuring equipment.

    The test is referred to as a Low Current, Off Power Frequency Injection Test .

    Go back to Commissioning Activities ↑

    4.1 Earth potential rise (EPR) measurement

    With test current flowing through the simulated fault circuit, voltages will be present in the same locations and in

    proportion to those generated during a real earth fault . The earthing system’s EPR is measured by performing afall of potential test.

    This test requires a test lead to be run out from the earthing system to allow a series of voltage measurements to

    be made between the earthing system under test and the ground. The route and distance is chosen to minimise

    measurement errors.

    The measurements taken from the fall of potential test must be processed for the difference between test and power 

    system frequency and for distance to remote earth. They can then be used to determine the earth system impedance

    and the EPR under actual fault conditions. Adjustments should also be made for mutual earth resistance and for 

    mutual inductance as required.

    Direct remote earth measurements, such as voltage measurements to remotely earthed communications or pilot

    wires, can also supply supplementary test data. However, with single point measurement alone it is very difficult to

    correctly assess and correct the many error sources that can be part of any measurement taken.

    Go back to Commissioning Activities ↑

    4.2 Current distribution

    3

  • 8/17/2019 Six Core Activities in the Commissioning of the Earthing System

    4/5

    In the situation where fault current may leave the earthing system through paths alternate to the earth grid (such as

    cable sheaths or overhead earth wires), the current through those alternate paths should also be measured.

    This allows analysis of how fault energy is dissipated, its effect on the alternate paths (for example, cable sheath

    capacity) and calculation of the earth grid impedance from the total system impedance.

    In complex systems the results are particularly important in modelling alternate fault scenarios and 

    in-feeds not simulated during testing .

    Go back to Commissioning Activities ↑

    5. Transfer, touch and step voltage testing

    While test current is flowing in the fault circuit, measurements are made of actual transfer, touch and step

    voltages. The purpose of such measurements is to directly measure the earthing system’s outputs and the

    compliance with the determined safety criteria.

    When measuring touch and step voltages it is important to measure the prospective touch and step voltages using a

    high impedance voltmeter and to measure the effective or loaded touch and step voltages appearing across an

    appropriate resistance that represents the human body.

    Care should be taken not to confuse the prospective step and touch voltages (i.e. open circuit case) with the effective

    step and touch voltages criteria. The loaded touch and step voltage cases are more variable due to variations in

    contact resistance.

    Therefore, the loaded case is only used when necessary and precautions taken (for example, take

    multiple measurements, use electrode contact initially, and only use a weighted plate on moistened soil 

    if necessary).

    Go back to Commissioning Activities ↑

    To be aware of //

    Telecommunications coordination

    Where telecommunications equipment is installed  within the area of influence of a high voltage earthing systemconsideration is required of the hazards that may be created. In such cases notification must be given to the

    appropriate telecommunications group.

    Pipeline interference / coordination

    Where pipelines are installed within the area of influence of a high voltage earthing system consideration is require

    of the hazards that may be created. These hazards must be reviewed during commissioning. In such cases

    notification must be given to owner / operator of the pipeline.

    Go back to Commissioning Activities ↑