Site Assessment Report_for Study

Embed Size (px)

DESCRIPTION

Hydro Power Project -Site assessment report

Citation preview

  • FEBRUARY 2015

    WAPCOS LIMITED(A Government of India Undertaking-

    Ministry of Water Resources, River Development & Ganga Rejuvenation)76-C, Institutional Area, Sector - 18, Gurgaon-122015

    Gurgaon - 122015

    Proposed Barrage Axis

    NORTH KARANPURA SUPER THERMAL POWER PROJECT(3X660MW)

    NTPC LIMITED(A Government of India Enterprise)

    Engineering Division

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 1 | P a g e

    1.0 BACKGROUND

    For the development of backward areas of Hazaribagh District of Bihar, construction of a

    Super Thermal Power Plant was conceived by Govt. of India way back in 1990. The

    decision to construct a 2000 MW (4X500 MW) power plant near North Karanpura in the

    then Hazaribagh District and later in Chatra District of Bihar (now in Jharkhand State)

    was primarily guided by ample availability of coal from Tandwa block of north Karanpura

    coal fields and the proximity of the coal demands of the thermal power plant. National

    Thermal Power Corporation (NTPC) was entrusted for implementing the proposed power

    project.

    During September1999, NTPC entrusted the work of preparation of Detailed

    Project Report (DPR) for Make-up Water System to WAPCOS, a Govt. of India

    Undertaking. The objectivity of DPR as envisaged by NTPC was to identify and

    ensure a permanent source of water and to conceive a suitable arrangement for

    utilization of water to meet the make-up water requirement throughout the

    operational period of the proposed thermal power plant. The DPR for this projectwas prepared by WAPCOS and submitted in 2001.

    The Power Potential Studies conducted by WAPCOS estimated the capacity of

    the project as 1980 MW against the conceived capacity of 2000 MW. The power

    plant was planned to have a closed cycle condenser for cooling and ash handling

    system with an estimated uninterrupted water requirement of about 90 cusecs

    (2.55 cumecs) by constructing a dam at village Ulrathi across river Garhi. The

    proposal envisaged water to be pumped directly from the submergence of Garhi

    dam.

    NTPC has recently taken up the execution of its coal based power project of

    3x660 MW capacity at North Karanpura in Hazaribag district of Jharkhand. The

    water for the project is envisaged to be drawn from river Garhi for the purpose of

    Water Cooling requirements for the Thermal plant.

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 2 | P a g e

    2.0 GEOLOGICAL SET-UP OF THE PROJECT AREA

    Project area is located on Gondwana Super-group of geo-chronological

    sequence. The area falls within North Karanpura Coal-fields. It forms the northern

    part of the main Karanpura basin. It is a prominent East-West trending valley

    surrounded by Pre-Cambrian metamorphic comprising Hazaribagh Plateau to the

    North and the Ranchi Plateau to the South.

    The project area in general is a wide country with Plateaus, residual hills and

    valleys. The drainage is dendritic to sub-dendritic. The Damodar River and its

    tributaries including Garhi Nadi are shallow meandering streams.

    The Gondwanas predominantly comprise Mahadevas, Raniganj, Barren

    Measures and Barakars. Gondwanas have been deposited on very uneven

    Archaean floor. Gondwandas are known habitats for huge coal deposits.

    3.0 RESERVOIR TIGHTNESSReservoir rims are made up of Gondwana rocks which on surface are covered with silty

    soil and sand derived partly from the Gondwana bed rock and partly from alluvial

    deposits. Gondwana bedrock is made up of coarse grained sandstone with interbedded

    shale, siltstone and coal and are in general impervious as far as primary permeability is

    concerned. Weathered rock mantle and fractures and fissures within the bedrock could,

    however, form conduits & passages for the movement of ground water. Open wells in this

    type of medium have been reported to show more fluctuation and get dried up very often.

    Secondly there is no major adjoining valley in close proximately to the reservoir rim into

    which the stored water could leak. However, during initial reservoir filling the reservoir

    water may charge the overburden material and fissures and joints in the rim rocks.

    4.0 COAL MEASURES

    It is pertinent to make a mention of the coal deposits in the project area. Three

    bore-holes have earlier been drilled in village Laranga on the right flank of Garhi

    River downstream of the proposed dam site. These holes have been drilled to

    depth of 300 m, 250 m and 200 m respectively. Coal seams are reported to have

    been encountered in holes around 200 m depth. These holes are reported to have

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 3 | P a g e

    started in Raniganj formation. The coal mines around Piparwar are mostly open

    cast.

    5.0 INVESTIGATIONS CARRIED OUT AT THE EARLIER DPR STAGE

    Geological / Geo-Technical investigationsSince the depth of the bed rock is shallow, sufficient no. of boreholes were

    made at DPR stage instead of relying on geophysical investigation. The

    boreholes along the dam axis have indicated that foundation rock, which is

    generally semi-impervious in nature, is available at shallow depth within 8 m

    and the overburden material is mostly pervious in nature. For the purpose of

    the earth materials laboratory tests were conducted for the physical and

    strength characteristics of the soils from various borrow areas. Borrow area

    investigation indicated the sufficient availability of desired quality and quantity

    of earth materials for construction purposes.

    Hydrological ObservationsNo hydrological observations on the river Garhi was available for arriving at the

    hydrological design parameters of the storage dam. A gauge-discharge site

    was established by WAPCOS on the river Garhi and daily discharge

    measurements were taken from 19.09.1999 to 19.12.1999. This actual

    discharge observations were for supplementing the other existing hydrological

    /river flow data in the upper Damodar river basin for assessing water availability

    and other hydrological studies.

    6.0 REVISED PROPOSAL FOR THE REDUCED WATER DEMAND

    Due to the changes made in the plant cooling system (from water cooling to air

    cooling), the consumptive water requirement of the plant has reduced from 90

    cusecs to 20 cusecs (18 MCM approx.). NTPC has accordingly requested

    WAPCOS to assess the possibility of constructing a low height weir / barrage for

    storage of water and pumping the same to an in-plant storage reservoir for its

    revised water requirement of 20 cusecs (18 MCM approx.). The structure is

    proposed to be located at a close proximity to the high level road Bridge Site

    across River GARHI. Water stored at the proposed barrage location shall be

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 4 | P a g e

    conveyed thru a buried pipe line to the in-plant reservoir by pumping it from the

    pump house envisaged close to the proposed weir/barrage location.

    On a request by NTPC, a Team of Experts from WAPCOS along with NTPC

    Officers visited the Site on 8th January, 2015 to assess its suitability for the

    proposed Barrage. The list of Experts is enclosed as Annexure I.

    7.0 OBSERVATIONS DURING SITE VISIT

    The proposed location of a low height weir/barrage near the road bridge site is

    around 5Kms upstream of the Dam location proposed in the DPR prepared by

    WAPCOS. Since no data/ details are available at the proposed location, the

    existing reports prepared by RITES Ltd. for the Road Bridge as well as the Data

    on the hydrological studies available in the earlier DPR prepared by WAPCOS

    Ltd. have been referred for a preliminary assessment.

    The Thermal Power Plant requires a sustained water supply and the sources like

    Ground Water option and Surface Water through direct pumping or through a

    system of infiltration galleries do not appear to provide an uninterrupted source of

    supply throughout the project operation period.

    The Detailed Hydrological studies earlier conducted by WAPCOS at DPR Stage

    confirms the sufficiency of water availability during monsoon season. Since the

    discharges available in the Garhi River during monsoon season is considerable,

    the option of creating a storage to transform the volume of water available during

    monsoon for effective utilization during non-monsoon season appears to be the

    Only Feasible Alternative. The reservoir can be impounded only during the

    monsoon months viz June to August, as flows during non-monsoon months in the

    river Garhi is very small, and will not give the required storage. It is thus

    contemplated that the impoundment will be done during the monsoon only.

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 5 | P a g e

    The team was also apprised that a Connecting road is proposed from the NH to

    the Thermal Plant which crosses the river near the Tandwa village about 1.5 km

    D/s of the existing road bridge near Surya Mandir. A bridge has already been

    proposed at this location to cross the river. The River width at the proposed

    location is about 200-250 m. The river alignment is almost straight up to about 1.5

    km U/s where the confluence of two rivers converge. The river course at the

    proposed location is well defined. The river slope is almost flat as in the plain

    area. The Slope of the river appears to be in the range of 1 in 400-500. The

    material on the river banks in the vicinity of the proposed structure appears to be

    Silty clay type soil. The water level in the river during monsoon period was

    observed to be about 3-4 m above the river bed. The river bed material similar to

    silty sand type.

    It was also informed that the River carries a lot of silt load during the monsoon

    period. No sediment inflow data are available in the Garhi catchment. Some data

    of adjoining catchment of the Barakar at Maithon reservoir are available. The

    average rate of silting at Maithon reservoir is 1.02 mm/year. The Maithon reservoir

    also lies in the Damodar river basin as that of Garhi river basin with almost similar

    catchment characteristics. A long term average silt rate of 1 mm/year appears

    reasonable and is therefore adopted for the present assessment studies.

    Accordingly, it is suggested that adequate silt flushing arrangement need to be

    explored and provided in the proposed Barrage after detailed investigations.

    The Area plan of the Project demarcating the Proposed Barrage location as well

    as the earlier Dam location is enclosed as Annexure-II.

    8.0 CONCLUSIONS

    The river Garhi, a tributary of the Damodar, is a non-perennial river. The flows in

    the Garhi River are mainly dependent on monsoon precipitation. The average

    annual rainfall in the region is around 1350 mm. The catchment is mostly rocky &

    sandy interspersed with jungles & bushes.

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 6 | P a g e

    Based on the hydrological data furnished in earlier DPR & RITESs reports, it is estimated

    (Refer attached Annexure-III) that adequate water can be stored during the monsoon period by

    construction of a low height barrage to meet the revised storage requirements of the plant

    (i.e 18 MCM approx.). The water after storage at the proposed structure across Garhi

    River shall be pumped to an in built reservoir and utilized for the entire life of the project

    on a continuous and sustained basis throughout the year including the non-monsoon lean

    period.

    It was observed at site and also appraised by the NTPC site officers accompanying the

    team that sound rock may be available at a depth of around 4-5 meters below the NSL at

    the proposed road bridge location. Accordingly, it is opined that a raised crested barrage

    adjoining the road bridge would be most suitable proposal for storage of water. The

    barrage could be raised over a RCC raft with a u/s and d/s cut off for achieving a safe exit

    gradient of seepage flow. Consolidation Grouting below the foundation of the Barrage

    need to be adequately planned.

    NTPC apprised to provide the guide embankment on either bank of the River as close to

    the river course as possible to minimize the submergence area. The river banks on either

    side of the river at the proposed Barrage site are proposed to be treated with stone

    pitching or boulders in wire crates up to the required height & length for containing the

    water within the guide banks. It is preliminary estimated that the embankment length may

    be around 1.50 Kms and more on each bank which can be confirmed after detailed

    topographical surveys.

    The WAPCOS team members are of the view that the Road Bridge can be located on the

    proposed Barrages Piers thereby omitting the requirement of Bridge sub-structure (i.e.

    deep Pile foundations & Pile cap etc.).

    The barrage is planned to be provided with vertical lift fixed wheel type hydraulic gates

    electrically operated by means of rope drum hoists for storage of water u/s of barrage.

    The rope drum hoists shall be placed on a raised platform over steel trestles. One set of

    stop log units operated by means of a monorail crane placed on the extended arm from

    the hoist bridge shall suffice for any emergency gate requirements (Refer sketch

    enclosed as Annexure-IV.)

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 7 | P a g e

    Since, the SEDIMENT LOAD of the river appears to be quiet high, it would be desirableto restrict the entry of silt into the pump intake. The River slope is almost flat at the

    proposed barrage location, it is apprehended that suspended silt would settle down at a

    fast rate after the structure is raised. The heavy suspended silt load shall enter the pump

    intake and may choke the suction sump and pipes. Since provision of a de-sander with a

    flushing arrangement would be a costlier option, the following alternatives are being

    proposed for removal of silt and its flushing so as to optimize the pumping operations.

    The structural arrangement as well as all other design details / parameters shall be

    worked out after further investigations including the river silt studies, in-plant reservoir

    simulation studies etc.

    1. Alternative. 1. A raised crest barrage having silt flushing bays with a depressed

    invert. The Intake for the pump house shall be located very close to the silt

    flushing bays at the right bank of the river towards the thermal plant. A raised

    crest with its top level below MDDL and above the Sluice invert is proposed all

    around the intake to the pump house for reducing the entry of silt. (Sketch 1

    enclosed as Annexure IV)

    2. Alternative .2. A deep cunnette of adequate dimensions could be provided

    towards the U/s and adjoining the raised crest all around the pump intake. The

    invert of the cunnette shall have a steep slope and connected to a pipe having a

    control valve for flushing operations towards the d/s of barrage. (Sketch 2

    enclosed as Annexure V)

    3. Alternative .3. The suction chamber below the riser pipes of the pumps could be a

    hopper shaped with provisions of flushing the silt via pipe line equipped with a

    control valve. This alternative could be planned in combination with the measures

    listed at alternative 1&2 above (Sketch 3 enclosed as Annexure VI)

    4. Alternative .4. A geotextile filter membrane could also be installed in the trash rack

    units or separately in order to restrict the entry of suspended silt load along with

    trash. Or else a system of pipes wrapped in geotextile filter material could be

    installed at various levels around an intake well for water diversions. Arrangement

    shall be provided to clean the choked geo-filter at regular intervals by back water

  • North Karanpura Super Thermal Power Project (6x660 MW), Jharkhand

    Site Assessment Report 8 | P a g e

    pressure slushing system or frequent replacement of the filter textile fixed in

    panels .( Sketch 4 enclosed as Annexure VII)

    5. Alternative .5 Large diameter deep wells can be raised at the middle of river width

    above the available bed rock in place of the proposed barrage structure. The

    water can be diverted during monsoon thru intakes sufficiently above the river bed

    thru a trash rack supporting structure all around the well at top level .The geo

    textile filter could also be installed in panels along with the trash rack units. The

    geotextile filters could be cleaned of choking by back water flushing arrangement

    or by provision of removable panels .The pumps can also be housed in a pump

    room located above these intake wells. (Sketch 5 enclosed as Annexure VIII)

    The alternative no. 5 appears to be cost effective option as it does not include the

    cost of the barrage and guide embankment at the river banks. However, the

    merits and demerits of all the above alternative proposals shall be worked out

    after detailed hydrological surveys and studies.

  • Annexure-I

    List of team members during the site visit on 8th January, 2015 to North Karanpura Super ThermalPower Project site

    NTPC

    Er. Manas Samantray, Sr. Manager

    WAPCOS

    Er. A.Ahluwalia, Consultant Er. D.C Mathur, Consultant Er. Kh Ashique Akbar, Engineer

  • ms07733Text BoxANNEXURE-II

  • A Inputs/AssumptionsDetails Unit Value Refered from

    1 River bed level m 433.00 approx. M/s RITES bridge documents2 Barrage U/s Raft top level m 4333 Barrage Crest level m 434.5 assumed4 Undersluice Invert El m 4335 MDDL m 434.56 FRL m 437.5 assumed7 Top El of Gate m 4398 Deck EL of Bridge m 441.00 approx. M/s RITES bridge documents9 Top of Barrage Piers at Crest location m 44410 Width of River at Proposed Barrage axis m 200 assumed as per visual observations during sitevisit11 River bed Slope 1 in 500 assumed as per M/s RITES Document & VisualObservations during Site VisitB Priliminary Assessment1 Volume of 90% dependable flow in Garhi River at OldDam Axis MCM 67.00 As per DPR

    2 volume of 90% dependable flow in Garhi River atProposed Barrage Site MCM 53.60assuming the Catchment area of the ProposedBarrage Axis is 80% of the Catchment area of theold dam location

    3 Yeraly Revised Water Requirement of the Thermal Plantas reported by NTPC MCM 18.00 Approx.

    4 FRL-MDDL m 35 MDDL-River Bed Level m 1.56 Live storage MCM 0.9

    1500.00 m FRL Line

    3.00 mFlow Barrage Axis

    Natural Embankment/Existing river bank (1.5 m ht. assumed) 1.50 m

    MDDL Line

    C Pumping Requirement

    1

    2 So, Days of Pumping operations per Year days 60 to be on the safe side (this can be modified asper requirments)3 Quantity of water to be Pumped per day MCM 0.3 based on the requirement of 18 MCM4 Pumping hours per day assumed hrs 165 Total Pumping discharge cumec 5.21

    Pumping capacity as per DPR cusec 50.00Pumping capacity as per DPR cumec 1.42

    7 Nos. of Pumps required nos. 3.68 say 4.00 nos + required nos standby pumps

    Note : The priliminary computaions provided above are based on the observations during Site Visit & limited data. The Computed designparameters may undergoes changes and other Design Parameters shall be assessed after Detail Investigations/Survey

    Preliminary Assessment of Water Availability at the Proposed BarrageAnnexure - III

    6

    Assuming that The in plant Reservoir is filled up with 18 MCM in two months (considering the uncertainty if occurred during any year),although water flow is available for five months

    Adequate Water is Avaiable for Pumping to the In plant Reservoir

    River Bed slope (1 in 500)

    750.00 m

    Guide Embankment length (tentative)=1500.00 m

  • Annexure-IV

  • Annexure-V

  • Annexure-V

    I

  • Annexure-V

    II

  • Annexure-V

    III

    Untitled.pdf (p.1-13)Final COVERPAGE .pdf (p.1)Site Assessment Report Feb 15.pdf (p.2-9)Annexure-I.pdf (p.10)Annexure-II.pdf (p.11)Annexure III _north karampura final.pdf (p.12)Annex- IV_aLTERNATIVE 1.pdf (p.13)

    SKETCH 2.pdf (p.14)SKETCH 3.pdf (p.15)SKETCH 4.pdf (p.16)SKETCH 5.pdf (p.17)