Similarities of Standard Forms of Contract in Malaysia

Embed Size (px)

DESCRIPTION

similarities of standard forms of construction contract

Citation preview

  • Similarities of Standard Forms of Contract in Malaysia

    A Comparative Study on Three Standard Forms Used in Malaysia

    Seng Hansen

    Master Student of Construction Contract Management UTM

    Email: [email protected]

    Introduction: Why We Need Standardization?

    There are at least 4 standard forms of contract which are commonly used in Malaysia nowadays, namely

    PWD (Public Works Department) Standard Form of Contract, PAM (Pertubuhan Arkitek Malaysia) Standard

    Form of Contract, CIDB (Construction Industry Development Board) Standard Form of Contract, and IEM

    (Institution of Engineers Malaysia) Standard Form of Contract.

    These standard forms evolve and develop in particular manners depending on the history and development

    of construction industry in the world, especially in Malaysia. Here, the author said that the development of

    these standard forms in Malaysia depending on the development of construction industry in the world

    because of 2 (two) reasons:

    Despite of the complexity and wideness of construction industry, the industry itself is actually inter-related

    and inter-connected. Thus we can say that we are working in a specific field of work which is dynamic but

    still in one closed system. For instance, new technologies or new material used in a project will become

    widely known and accepted in short time. This transfer of technology will have effect to the standardization

    of construction industry in here we are particularly discussing the standardization of contract forms.

    Basically, Malaysia standard forms of contract adopt the international standard forms of contract. For

    instance, we can see that PAM Standard Form of Contract is originally based on JCT (Joint Contract Tribunal)

    Particulars PWD PAM CIDB

    Origin RIBA 1931 JCT 1963

    Produced by The Government (JKR) PAM CIDB

    Application For government projects, usually

    for civil engineering works

    For private building works For building works for both

    government and private

    employer

    instance, we can see that PAM Standard Form of Contract is originally based on JCT (Joint Contract Tribunal)

    Standard Form of Contract; the same with PWD Standard Form of Contract which is originally modeled from

    the English 1931 RIBA (Royal Institute of British Architects) Standard Form of Contract.

    Since the dynamic movement of construction industry will give so many interpretations in terms of

    methods, costs, scope etc, we need to limit these interpretations since the initial point of a project. This is

    materialized in contract document. Therefore, we can say that with the influence from global construction

    industry, Malaysian professionals try to make a standardization of contract in order to limit the

    interpretation of dynamic movement in construction industry.

    Table 1. Standard Forms of Contract in Malaysia

    The advantages of using standard forms of contract instead of composing a new fresh contract document

    for each project are:

    1. They are made by professionals in construction industry, therefore hopefully it can make a more clear

    understanding of contract terms (ambiguities and inconsistencies are reduced to a minimum)

    2. They give options to both parties (the employer and contractor) to choose which standard form of

    contract will be used according to strategic business plan they may have

    3. The rights and obligations of both parties are set out clearly and to the required degree of detail (fairer to

    both parties)

  • 4. Because it is standardized, frequent users are familiar with the provisions in a particular form

    5. We can save time and expense which usually incurred in preparing a new contract document

    What will be discussed in this paper is about the similarities of 3 (three) standard forms of contract used in

    Malaysia. These 3 standard forms are the most commonly used in Malaysia and have their own

    characteristics. The first is PWD form 203A (Rev. 2007) where Bills of Quantities is part of the contract.

    Because Bills of Quantities is very often used in Malaysia, the author takes PWD form 203A (Rev. 2007) as

    the representative standard form published by JKR/PWD. Secondly is PAM Contract 2006 with Quantities.

    Again, the same reason is taken. Thirdly is CIDB 2000 edition. CIDB standard form of contract consist only

    one type of contract. But there is appendix in CIDB which consist 6 option modules. Each module can be

    chosen whether they will be used or not. Generally, there will be so many similarities between these 3

    standard forms of contract since they are already standardized. The only major differences between these 3

    standard forms are their characteristics, descriptions and detailing procedures.

    Analysis of the Study: Similarities of Three Standard Forms of Contract

    1. Obligation of the Employer

    Among these 3 standard forms, all of them have the description about obligations of the employer,

    although only CIDB which expressly describe this obligation (clause 6). Both PWD and PAM do not provide a

    certain clause to state the employers obligations. However, it does not mean that there is no employers

    obligation in the contracts. The employers obligations in both contracts are spread throughout some

    clauses which implied these obligations.

    The main obligation of the employer is to pay to the contractor what has been built. Here, payment is a

    consideration which creates a legal binding between the employer and the contractor. If the employer does

    not pay to the contractor, then we can assume that the employer has entered breach of contract. In order

    to evaluate any project progress on site, the employer will then employ architect/superintending officer (for

    next we will use S.O.). All of these three standard forms have a similar procedure that is the employer will

    pay to the contractor any amount which has been evaluate by S.O. In PWD, contractor can include anypay to the contractor any amount which has been evaluate by S.O. In PWD, contractor can include any

    unfixed materials and goods intended for the Works in his payment (except unfixed material and goods

    supplied by Nominated Suppliers). For this matter, both PAM and CIDB also permit contractor to include any

    unfixed materials and goods but only in percentage (not all value). Then in PWD, contractor can submit his

    payment monthly and within 14 days S.O. shall issue an Interim Certificate, while in PAM and CIDB it is

    within 21 days. The, government then shall make a payment within specified period of time after the

    issuance of Interim Payment with the remaining xx% of the amount is being retained (for PWD 10%, for

    PAM and CIDB it is as stated in the appendix). Both in PWD and CIDB, within 3 months after the issuance of

    Certificate of Practical Completion, the contractor must submit full particulars including claims to enable

    the Final Account to be prepared by S.O. If contractor fails to submit within the stipulated period, then the

    S.O will make the assessment based on the available documents submitted by the contractor for the

    purpose of Final Account. The Government shall be discharged from all liabilities in connection with the

    claims. For this matter, PAM stated that period will be within 6 months.

    These three standard forms also provide a clause especially define about suspension for non payment. Here

    if the employer fails or neglects to pay within specified period of time after the release of Interim

    Certificate, then the contractor may give notice of his intention to suspend the Works. In PAM and CIDB this

    matter is discuss in clause 30.7 and 42.10 respectively. However we cannot find clause discussing

    suspension for non payment in PWD. In my opinion, this may be because PWD is used for government

    projects. Therefore, contractor need not be worry for the payment, since it is fund by government. It will be

    paid although takes a long time.

    In PWD clause 29 and 30, it is stated that contractor may ask for adjustment of contract sum due to some

    circumstances and fluctuation of price. In PAM, it is clearly stated that there is no such adjustment or

    alteration for contract sum. While in CIDB, there is no corresponding provision.

    Employer also has the obligation to pay contractor for any variation occurred during construction, only if the

    variation issued by the S.O. This matter is discussed in PWD in clause 24 and 25, in PAM in clause 11, and in

    CIDB in clause 28 and 29. All variation amounts shall be certified by the S.O and added to or deducted from

    the contract sum and the amount shall be adjusted accordingly.

  • In the particular events of delay and need to extent the Works schedule, employer has to give contractor an

    extension of time. All of these three standard forms stated that contractor must submit his claim for EOT

    within a specified period of time. In PAM and CIDB, if the contractor fails to submit his claim within the

    specified period of time, then contractor shall not be entitled with EOT. In PWD, there is no such

    requirement. Furthermore, in CIDB there is an explanation of specific event with continuing effect which

    will make a delay in overall project schedule.

    Contractor also entitled with claims and employer has the obligation to pay any claim made by contractor

    and has been approved by S.O. Moreover, in PAM there is mentioned that contractor can only make claim in

    such occasion as explained in clause 24.3. Also both in PAM and PWD, it is stated that if the contractor does

    not submit his claim together with the required documents within a specified period of time, then the

    contractor shall not be entitled the claim.

    In the case of Works insurance, both in PAM and CIDB give an option whether contractor will insure the

    Works or employer (but in case for existing building or extension, the employer is the one who has the

    obligation to insure). If both parties agree that the Works insurance will be done by the employer, then the

    employer must insure the Works within specified period of time. Failure of this action may lead the

    contractor to insure the Works and he shall be entitled to have the amount of insurance added to the

    Contract Sum. See clause 20 of PAM and 38 of CIDB.

    Employer also has the obligation to give site possession to the contractor usually before the Date of

    Commencement or unless the contract otherwise provides. We can see this in PWD clause 38 and CIDB

    clause 17.2. However, there is no corresponding provision in PAM.

    Based on the authors experience, the characteristic of employer also effects to the employers obligations.

    It is true that the main obligation of the employer is to pay, but not only that. Employers should make

    payment to the contractor punctually. Contractors usually will face some difficulties to ask payment from

    private employers rather than projects fund by government. Private employers may have their own

    cashflow difficulties and strategic business plan. These reasons will eventually take effect to payment to the

    contractor. In some projects, the employers will release the payment 2 or 3 months after the payment

    certificate has been released. To overcome this problem, contractors will usually do some personalcertificate has been released. To overcome this problem, contractors will usually do some personal

    approach to the employers and take some strategies to make good their projects cashflow so that their

    projects still can run and finish on time. This impact is something that the employers usually do not concern

    about.

    2. Obligation of the Contractor

    The main obligation of the contractor is to construct the said project which has been agreed based on its

    scope and within the specified period of time and quality. This is also the general similarities of these three

    standard forms. The difference is the emphasis of the contractors obligations.

    For the contractors general obligations, we can see in PWD clause 10, PAM clause 1, and CIDB clause 7. It is

    important to notice why PAM put contractors obligations in the first clause of the contract. In my opinion, it

    means that in PAM contractor is considered as the party who need the work.

    All of these three standard forms have similar clause regarding Works Completion. In PWD this matter is

    described in clause 39 and 41; in PAM it is described in clause 15; and in CIDB it is described in clause 20,

    21, and 22. Sometimes the employer wants to take some part of the Works which are already completed.

    This is explained in clause 41 of PWD and clause 22 of CIDB as Sectional Completion.

    Before executing the Works, contractor must provide performance bond to the employer as security

    deposit. This is a common matter required by employer to the contractor. However, we can only find a

    clause specifically discuss about performance bond in PWD and PAM. While in CIDB, performance bond

    becomes part of the appendix. Therefore, it will be depend on the agreement between both parties

    whether the contractor should submit performance bond or not. See Option Module F of CIDB.

    Contractor also has the obligation to ensure the quality of his works. If there is any defect during

    construction period and after completion, contractor has the liability to make good of any such defect until

    S.O satisfy with the works. This obligation is described in PAM clause 15, in PWD clause 48, and in CIDB

    clause 15.7 and 27.

    In doing his job, S.O sometimes needs to take a test of the works done by contractor. Usually the cost of

    inspection and testing are borne by contractor. This matter is described in PWD clause 36, in PAM clause 6

    and 14, and in CIDB clause 15.

  • Contractor also has the obligation to be responsible with any indemnity and insurance of personal injury or

    death and damage to property arising from carrying out of the Works. These matters are described in PWD

    clause 14 and 15, in PAM clause 18 and 19, and in CIDB clause 35 and 36. The contractor must also provide

    insurance for his labour as described in clause 17 of PWD and clause 37 of CIDB. In my opinion, CIDB is the

    most complete standard form in terms of indemnity and insurance.

    In the case of Works insurance, both in PAM and CIDB give an option whether contractor will insure the

    Works or employer. Usually both parties will agree that contractor will provide the insurance in CAR form of

    insurance. See clause 18 of PWD, 20A of PAM and 38A of CIDB.

    There is also a specific clause regarding to antiquities such as fossils, coins etc which may be found on the

    site. In this circumstance, contractor has the obligation to take all steps which may be necessary to preserve

    and protect the object in the exact position and condition. The contractor should inform S.O immediately

    about the discovery. This obligation can be seen in clause 64 of PWD, 33 of PAM, and 39 of CIDB.

    The contractor also has the obligation to execute the whole Works. If he would like to assign some duties to

    his subcontractors, first he must receive the approval of S.O. If S.O approves his assignment, the contractor

    shall still be fully responsible for the works of his subcontractors. S.O also can appoint Nominated

    Subcontractor (NSC) or Nominated Supplier (NS) with the approval from the contractor. And again, the

    contractor shall be fully responsible for the works of NSC/NS. These matters are described in PWD clause 47

    and 59, in PAM clause 17, 27 and 28, and in CIDB clause 18 and 40.

    At the end of the project, contractor should submit the as built drawing to the employer. Usually he must

    submit this drawing not later than the Date of Practical Completion of the Works or otherwise stated in the

    contract. We can see the description in CIDB clause 4.10 and PAM clause 3.10.

    3. Obligation of both parties

    Both parties also share some obligations such as confidentiality (PWD clause 68, PAM clause 3.9, CIDB

    clause 4.9), obedience of dispute resolution decision (PWD clause 65, PAM clause 34 and 35, CIDB clause

    47), compliance with the Law (PWD clause 21 and 72, PAM clause 4 and 38, clause 10 and 49), and give

    notification (PWD clause 66, PAM clause 36, CIDB clause 8).notification (PWD clause 66, PAM clause 36, CIDB clause 8).

    Conclusion

    After doing some comparison on these three standard forms of contract, we can see the characteristic of

    each standard form. The PAM standard form of contract tends to protect the employers interest, while

    PWD standard form of contract tends to protect the contractors interest. The most balanced is CIDB

    standard form of contract. But this is not the only aspects to choose which standard form of contract will be

    used by both parties. There must be many other aspects both from the employer and the contractor to

    enter into an agreement.

  • Table 2. Similarities of 3 Standard Forms of Contract in terms of Obligations

    No Particulars PWD 203A PAM 2006 CIDB 2000

    1 General Obligations of the Employer Spread Spread Clause 6

    2 Claims made by contractor Clause 44 Clause 24 Clause 31

    Clause 32

    3 Delay & Extension of Time (EOT) Clause 43 Clause 23 Clause 24

    4 Insurance by employer - Clause 20B

    Clause 20C

    Clause 38B

    Clause 38C

    5 Payment Clause 28

    Clause 31

    Clause 54

    Clause 60

    Clause 30 Clause 42

    6 Price Adjustment Clause 29

    Clause 30

    Clause 13.1 -

    7 Site Possession by contractor Clause 38 - Clause 17.2

    8 Suspension for non payment - Clause 30.7 Clause 42.10

    9 Variations Clause 24

    Clause 25

    Clause 11 Clause 28

    Clause 29

    10 General Obligations of the contractor Clause 10 Clause 1 Clause 7

    11 Antiquities Clause 64 Clause 33 Clause 39

    12 Guarantees & Bonds Clause 13 Clause 37 Module E & F

    13 Indemnity & Insurance by contractor Clause 14

    Clause 15

    Clause 16

    Clause 17

    Clause 18

    Clause 18

    Clause 19

    Clause 20A

    Clause 35

    Clause 36

    Clause 37

    Clause 38

    Clause 38A

    14 Testing & Inspections Clause 36 Clause 6.3 Clause 15.1

    Clause 15.3

    Clause 15.4

    15 Subcontractor, NSC & NS Clause 47

    Clause 59

    Clause 17

    Clause 27

    Clause 28

    Clause 40

    Module C

    16 Work Completion Clause 39

    Clause 41

    Clause 42

    Clause 15

    Clause 16

    Clause 20

    Clause 22

    Clause 23

    17 Work Defects Clause 48 Clause 15.4

    Clause 15.5

    Clause 15.6

    Clause 15.7

    Clause 27

    18 As built drawings - Clause 3.10 Clause 4.10

    19 Confidentiality Clause 68 Clause 3.9 Clause 4.9

    20 Dispute Resolution Clause 65 Clause 34

    Clause 35

    Clause 47

    21 Law Clause 21

    Clause 72

    Clause 4

    Clause 38

    Clause 10

    Clause 49

    22 Notification Clause 66 Clause 36 Clause 8