23
SIL Methodology Page 1 of 23

SIL Methodology

  • Upload
    hvananth

  • View
    1.747

  • Download
    12

Embed Size (px)

Citation preview

Page 1: SIL Methodology

SIL Methodology

Page 1 of 18

Page 2: SIL Methodology

CONTENTS

1.0 PURPOSE...................................................................................3

2.0 SCOPE.......................................................................................3

3.0 ABBREVIATION..........................................................................3

4.0 REFERENCES.............................................................................3

5.0 RESPONSIBILITY AND AUTHORITY...............................................3

6.0 DESCRIPTION OF ACTIVITIES.......................................................4

6.1 General...................................................................................................................................46.2 Roles and Responsibilities......................................................................................................46.3 SIL Team Composition............................................................................................................56.4 SIL Study Schedule and Pre-requisites...................................................................................56.5 SIL Methodology.....................................................................................................................66.5.1 Risk Graph Technique............................................................................................................66.5.2 Layer of Protection Analysis...................................................................................................86.6 SIL Target Level....................................................................................................................116.7 SIL Assessment Report.........................................................................................................12

7.0 SIL VERIFICATION....................................................................12

8.0 FOLLOW-UP AND CLOSE-OUT....................................................13

9.0 RECORDS.................................................................................13

10.0 APPENDICES............................................................................13

APPENDIX I–RISK GRAPH PARAMETERS AND CRITERIA........................14

APPENDIX II–LOPA SIL ASSESSMENT WORKSHEET...............................17

Page 2 of 18

Page 3: SIL Methodology

1.0 PURPOSE

The purpose of this procedure is to describe the recommended practice

for performing Safety Integrity Level (SIL) assessment & verification

studies of identified Instrumented Protective Functions.

2.0 SCOPE

This procedure applies to the performance of SIL Studies on Oil & Gas

facilities projects. The recommended practice outlined in this procedure

shall be adopted on a project where client’s specific guidelines are not

available.

3.0 ABBREVIATION

C&E Cause and Effects

E/E/PEElectrical, Electronics and Programmable Electronics

ESD Emergency Shutdown System

HSE Health Safety & Environment

IEC International Electro technical Commission

IPF Instrumented Protective Function

PCS Process Control System

PFD Probability of Failure on Demand

PEM Project Engineering Manager

PLC Programmable Logic Controller

QRA Quantitative Risk Assessment

SIL Safety Integrity Level

SISSIF

Safety Instrumented SystemSafety Instrumented Function

4.0 REFERENCES

IEC 61508, Functional safety of

electrical/electronic/programmable electronic safety-related

systems

IEC 61511, Functional Safety – safety instrumented systems for

the process industry sector

PFD data from vendors

Safety Equipment Reliability Handbook, by OREDA or any other

handbook for generic data.

Page 3 of 18

Page 4: SIL Methodology

5.0 RESPONSIBILITY AND AUTHORITY

N/A

6.0 DESCRIPTION OF ACTIVITIES

6.1 General

Instrument and control systems play a significant role in the

management of hazards on oil and gas installations. Shutdown systems

are traditionally recognised as safety systems which contribute to

reducing the likelihood and consequences of dangers to personnel, but

also limiting risks to environment, to assets and to continued

production. Therefore, instrumented protective functions need to be

reviewed through a systematic assessment process to determine any

requirement for increased reliability and/ or higher integrity and hence

reducing risks.

The main objective of the SIL study is to assess the integrity level for all

instrumented protection functions that have been provided for all

process systems, in accordance with IEC 61511.

SIL study workshop is conducted to perform a systematic review of

plant process systems to identify failures in E/E/PE safety related

control systems at each plant, which have the potential for harm to

personnel (through illness and injury or loss of life) or to the

environment (temporary or permanent). A secondary objective will be

to identify where such failures have the potential to cause significant

economic loss due to production loss and/or damage to capital

equipment. The safety and environmental harm and the economic loss

will generally arise due to loss of containment, either of the product or

of a substance hazardous to health.

6.2 Roles and Responsibilities

The SIL team should consist of the following persons:

Chairman Responsible for chairing the SIL review

meeting and ensuring the process runs

smoothly in accordance with the procedure.

The Chairman shall ensure the team remain

focussed and do not deviate from the

objective of the study. The chairman shall

have experience of conducting a SIL or

similar studies. The Chairman shall bring the

SIL Assessment software. The SIL

Assessment and SIL Verification report shall

be prepared by the Chairman.

Page 4 of 18

Page 5: SIL Methodology

Secretary Responsible for recording the discussion of

the meeting, using the worksheets. It is

preferable that the SIL Secretary has a

technical background in Instrumentation.

Lead HSE Design EngineerThe Lead HSE (Design) Engineer on the

project shall to ensure that the SIL is

performed to the standards set out in this

procedure. The Lead HSE Engineer shall

ensure the administrative tasks necessary to

perform the SIL study completed

(organisation of team, distributing the

documents, Chairman Selection, selection of

venue, etc).

Lead Instrument Engineer Lead Instrument Engineer shall be

responsible to ensure completion of Project

design documents necessary prior to SIL

study including vendor documents. He shall

provide Chairman the list of tags, initiating

devices, final elements and service

description for each SIF to include into the

worksheets.

Lead Process Engineer Lead Process Engineer shall ensure that the

P&ID’s are updated in line with the

recommendations given in the HAZOP.

Follow-up The Follow-up Coordinator shall be nominated by Project Engineering Manager (PEM) who can make project decisions on the conflicting requirements. The co-ordinator shall act on behalf of the PEM to facilitate and expedite the satisfactory close-out of recommendations raised by the SIL study. The overall responsibility of SIL close-out process lies with PEM.

6.3 SIL Team Composition

Presence of following team members both from Contractor and the

Operating Company is essential during the full duration of the review:

Process Engineer

Control and Instrumentation Engineer

HSE/ Safety Engineer

Operation Representative

Page 5 of 18

Page 6: SIL Methodology

Other discipline engineers( Mechanical, Civil, layout etc.) shall be

available on need basis

6.4 SIL Study Schedule and Pre-requisites

The SIL study should be scheduled after completion of HAZOP study and

incorporation of major HAZOP recommendations onto the P&IDs and

Cause & Effects Charts.

The following project specific documents (latest revisions) shall be

made available prior to the SIL workshop:

Piping & Instrumentation Diagrams

Cause and Effects Chart

HAZOP Report

QRA Reports

Plot plans

6.5 SIL Methodology

The common methods used for Target Safety Integrity Level

determination are:

Risk Graph

Layer of Protection Analysis (LOPA)

Both these methods are included in the IEC61508 and IEC61511

standard.

The risk graph is a qualitative technique, the results tend to be quite

subjective and lead to SIL levels biased on the high side. The Layers of

protection analysis technique is quantitative and more accurate and it

is becoming the widely accepted technique for SIL determination.

It is advisable to consider Risk Graph method at the FEED stage and

LOPA technique during detail design phase. Appropriate methodology

should be chosen by the Project group after considering client

guidelines or advice. In the absence of Client guideline follow LOPA

methodology for Detailed Design.

6.5.1 Risk Graph Technique

The risk graph method is a qualitative approach to determine the level

of integrity required for the identified Instrumented Protective Functions

(IPF) for the project. The approach is based on the International Electro

technical Commission standard, IEC61511 [Ref. 2]

Page 6 of 18

Page 7: SIL Methodology

Risk graph analysis uses four parameters to make a SIL selection. These

parameters are consequence (C), occupancy (F), probability of avoiding

the hazard (P), and demand rate (W).

Consequence represents the average number of fatalities that are likely

to result from a hazard when the area is occupied, and should include

the expected size of the hazard and the receptor’s vulnerability to the

hazard.

Occupancy (Exposure Time Parameter) is a measure of the amount of

time that the area that would be impacted by the incident outcome is

occupied.

The probability of avoiding the hazard will depend on the methods that

are available for personnel to know that a hazard exists and also the

means for escaping from the hazard.

The demand rate is the likelihood that the accident will occur without

considering the effect of the SIF that is being studied, but including all

other non-SIS protection layers.

A combination of consequence, likelihood, occupancy, and probability of

avoidance represents a level of unmitigated risk. Once those categories

have been determined, the risk graph is used to determine that SIL that

will reduce the risk by the appropriate amount. Figure 1 contains a

typical risk graph, as presented in IEC 61511-3. The SIL is selected by

drawing a path from the starting point on the left to the boxes at the

right by following the categories that were selected for consequence,

occupancy and probability of avoidance. The combination of those three

determines the row that is selected.

Page 7 of 18

Page 8: SIL Methodology

Figure 1: Safety Integrity Level (SIL) Risk Graph (IEC 61511,

Ref. 1)

6.5.1.1 Steps

Prior to the assessment, the risk graphs will be calibrated according to

Client Risk criteria. For each loop, the SIL is determined and recorded

on worksheets as follows.

1. Identify the loop to be examined, and record the tag and P&ID

number.

2. Agree the function of the loop (i.e. what is it for?).

3. Determine the cause of demand of the loop (most commonly

control failure).

4. Identify the output actions (e.g. close specified valves).

Page 8 of 18

Page 9: SIL Methodology

5. Agree the consequence if the loop fails on demand. At this point

no credit is taken for other relevant risk reduction

measures.

6. Having gathered the above information, use combined

judgement to agree the four parameters C, F, P and W on the

safety risk graph.

7. W is the frequency of the cause of demand identified in step 3.

8. Apply the safety risk graph to determine the SIL required on

safety risk considerations.

9. Agree the economic loss parameter L and use the economic risk

graph to determine the SIL required on economic risk

considerations.

10.Agree the environmental loss parameter E and use the

environmental risk graph to determine the SIL required on

environmental risk considerations.

11.Determine the SIL required for the function identified in step 2 as

the highest of the three SILs determined in steps 7, 8, and 9.

The above listed Steps are repeated for each of the IPF loops.

The risk graph parameters and criteria to be used for this assessment

are outlined in Appendix-I of this document.

6.5.2 Layer of Protection Analysis

LOPA is one of the techniques developed in response to a requirement

within the process industry to be able to assess the adequacy of the

layers of protection provided for an activity. Initially this was driven by

industry codes of practice or guidance and latterly by the development

of international standards such as IEC61508 [Ref 1] and IEC61511 [Ref

2].

Within the LOPA methodology the concept of the Independent

Protective Layer (IPL) is well defined and important.

“An IPL is a device, system or action which is capable of preventing a

scenario from proceeding to its undesired consequence independent of

the initiating event or the action of any other layer of protection

associated with the scenario. The effectiveness and independence of an

IPL must be auditable.”

The SIL Selection is based on establishing a tolerable frequency for

each consequence resulting from an initiating event. This tolerable risk

guideline needs to be reviewed and accepted by the Company at the

start of the SIL review process.

Page 9 of 18

Page 10: SIL Methodology

Once the tolerable frequency for a SIF is established, all causes of the

initiating event are listed. For each cause of the initiating event, its

likelihood is established. The layers of protection and associated PFD for

each cause are then listed. The mitigated event frequency for each

cause is determined. After each cause is analyzed the total event

frequency due to all causes for the initiating event is determined. The

SIL is determined by comparing the established tolerable frequency

(goal) with the total mitigated event frequency.

6.5.2.1 Steps

Following are the important steps, which shall be addressed during SIL

assessment sessions

1. Identify and list all Safety Instrumented Functions for the unit(s)

2. For each SIF identified:

Define the worst consequence if the SIF failed to operate when a

demand occurs.

Categorize the consequence severity and tolerable frequency

based on the Company Risk guidelines. The tolerable frequency

will be selected from the reducible frequency band as per the

table

List all causes and likelihood for the initiating event

For each cause identify all available layers of protection and

assign failure probabilities for each layer

For each cause calculate the mitigated event frequency

considering all the layers i.e. F = Fe*PA*PB*PC*PD where F is the

mitigated event frequency, Fe is non-mitigated event frequency

based on the best industrial practices and PA/PB/PC/PD are the

PFD values for each protection layer.

Calculate the total event frequency due to all causes

Compare the tolerable frequency goal with the total event

frequency

Assign the required SIL based on the additional risk reduction

required

Document the results of each analysis in the SIL Selection and

Analysis worksheet. Include any notes and recommendations in

the worksheet. Typical SIL Assessment worksheet format is given

in Appendix II.

6.5.2.2 Independent Protection Layers (IPL)

Page 10 of 18

Page 11: SIL Methodology

An Independent Protection Layer is a specific category of safeguard.

Independent protection layers must meet the following criteria.

Specificity – An independent protection layer must be specifically

designed to prevent the consequences of one potentially hazardous

event.

Independence – The operation of the protection layer must be

completely independent from all other protection layers, no common

equipment can be shared with other protection layers.

Dependability – The device must be able to dependably prevent the

consequence from occurring. The probability of failure of an

independent protection layer must be demonstrated to be less than

10%.

Auditability – The device should be proof tested and well maintained.

These audits of operation are necessary to ensure that the specified

level of risk reduction is being achieved.

6.5.2.3 Typical Protection Layers

While no two situations are the identical, there are a few protection

layers and mitigating events that should always be considered when

performing a layer of protection analysis in the process industries.

These protection layers are shown below:

PCS Controls – In many cases the PCS control system is

designed to automatically move the process to a safe state under

abnormal conditions (Control loop or an On/Off loop). The criteria

most used to determine whether the PCS system could be used,

as a layer of protection is that a failure of the PCS system did not

contribute in causing the initiating event. (Maximum Risk

reduction credited shall be 1 in 10).

Many times, independent alarm in the PCS with operator action is

provided to mitigate certain risks. In such a situation, credit for

Alarm can be given only if the alarm signal is connected to an

entirely independent initiator and I/O, other than the one carrying

out the automatic controls. This will considerably reduce any

common mode failures. (Maximum Risk reduction credited shall

be 1 in 10).

For PCS to be credited with Two (2) IPLs, initiators, I/O cards and

final control elements must be independent of each other. Only

the logic solver part could be shared provided, logic solvers are

redundant.

If the initiating or enabling event involves the failure of a PCS

loop, then no more than one PCS loop should normally be

credited as an IPL for the same scenario.

Page 11 of 18

Page 12: SIL Methodology

Maximum total risk reduction credited for PCS as an independent

layer shall be no more than 1 in 100.

Operator Intervention – Operator intervention to manually

shut down a process when abnormal conditions are detected is a

common safeguard. In order for this safeguard to meet the level

required of an independent protection layer, the operator must

always be present, be alerted to the abnormal situation, be

trained in the proper reaction to the abnormal situation, and have

ample time to consider the alarm and respond. (Maximum Risk

reduction credited shall be 1 in 10)

Mechanical Integrity of Piping or Vessel – In many cases,

piping or a vessel will be designed to withstand the highest

temperatures and pressures generated as the result of abnormal

conditions. In these cases, the mechanical integrity of the vessel

is a protection layer. (Maximum Risk reduction credited shall be 1

in 100)

Physical Relief Device – Physical relief devices are common

safeguards and include such devices as relief valve, rupture

disks, and thermal fusible plugs. (Maximum Risk reduction

credited shall be 1 in 100)

Ignition Probability – When a flammable material is released to

the atmosphere the probability that the release will ignite will

depend on factors such as auto-ignition temperature and source

of ignition present

Other layers to be considered – Use factor, Explosion

Probability, Occupancy and External risk reduction facilities like

F& G systems, Dikes, etc.

6.6 SIL Target Level

For each of the safety instrumented function operating in demand

mode, the required SIL shall be specified in accordance with levels as

stated in table below (Ref. 2):

Table 1: Probability of Failure on Demand for the SIL1, 2, 3 and

4

Safety Integrity Level (SIL)Target average Probability of

Failure on Demand

SIL 4 10-5to< 10 –4

SIL 3 10-4 to< 10 –3

Page 12 of 18

Page 13: SIL Methodology

SIL 2 10-3 to< 10 –2

SIL 1 10-2to< 10 –1

6.7 SIL Assessment Report

The SIL Assessment Report shall be prepared by Chairman using the

company format and shall include the following as a minimum:

Executive Summary

The scope of SIL Study

List of Participants

The systems examined

The results as captured in the worksheets

Conclusions and Recommendations

7.0 SIL VERIFICATION

During EPC phase of the project, SIL verification study will be performed

if it required contractually or any specific instruction from the Company.

SIL validation is not covered under this document as it is normally

carried out during operation phase.

The outcome of the SIL assessment is followed by a SIL verification

study, where the design of the safety instrumented system (SIS) is

verified. The risk reduction performance of any given SIF depends on

the equipment chosen and the redundancy levels. The safety

performance evaluation is called SIL verification and requires reliability

analysis of the equipment with a view toward a particular failure mode

titled "failure to function on demand" or "fail danger." A piece of

equipment used to implement a SIF has a certain probability that it will

not successfully protect a process if a dangerous condition (a demand)

occurs. This average "probability of failure on demand" (PFD) is

calculated and compared with the PFD average table to obtain a

"design SIL." If the design SIL is not greater than or equal to the target

SIL, better technology or more redundancy is required.

The first step in SIL verification is gathering failure rate data and failure

mode data for the equipment selected. Thereafter, the designer

calculates PFD sub avg using simplified equations, fault-tree analysis, or

Markov analysis. There are two fundamental challenges faced during

SIL verification:

Page 13 of 18

Page 14: SIL Methodology

Gathering the failure rate/mode data and

Building a PFD sub avg model.

Failure rate data is available in a generic sense from several industry

databases, including AIChE and OREDA. Failure rate data is also

available from some manufacturers, although it is often difficult to

source.

8.0 FOLLOW-UP AND CLOSE-OUT

Upon completion of the SIL assessment workshop, the Chairman will

present the findings of the study in the form of a SIL Assessment report.

Recommendations of the SIL assessment will be generally closed out by

Instrumentation discipline.

It is important that Project allocate adequate resources to not only

perform the SIL study but to ensure that the recommendations raised in

the SIL report are satisfactorily closed out. The PEM shall be responsible

to ensure that the adequate resources are available for timely

completion of SIL study. In general almost all SIL actions belong to

instrument group, therefore as a general practice PEM will nominate

instrument engineer to own the SIL close-out responses. The PEM

nominee shall prepare & issue the SIL Close-out report.

9.0 RECORDS

N/A

10.0APPENDICES

Page 14 of 18

Page 15: SIL Methodology

APPENDIX I–RISK GRAPH PARAMETERS AND CRITERIA

(1) - IEC 61511 Safety Parameters

Personnel Safety Risk parameter Classification Comments

Consequence (C) Average

number of Fatalities This can be

calculated by determining the

average numbers present when

the area is occupied and

multiplying by the vulnerability

to the identified hazard.

The Vulnerability will be

determined by the nature of the

hazard being protected against.

The following factors are

proposed

V=0.01 Small release of

flammable or toxic material

V=0.1 Large release of

flammable or toxic material

V=0.5 As above but with a high

chance of igniting or highly

toxic.

V=1 Rupture or explosion

CA

CB

CC

CD

Minor injury

Range 0.01 to 0.1

Range >0.1 to 1.0

Range > 1.0 to 10

1. The

classification

system has been

developed to deal

with injury and

death to people.

2.For the

interpretation of

CA,

CB, CC and CD, the

consequences of

the accident and

normal healing

shall be taken into

account.

Exposure probability in the

hazardous zone (F)

This is calculated by

determining the length of time

the area is occupied during a

normal working period.

NOTE - If the time in the

hazardous area is different

depending on the shift being

operated then the maximum

should be selected.

NOTE - It is only appropriate to

use FA where it can be shown

that the demand rate is random

and not related o when

FA

FB

In the hazardous

zone. Occupancy

less than 0.1

Frequent to

permanent

exposure in the

hazardous zone.

Occupancy more

than 0.1

3. See comment 1

above.

Page 15 of 18

Page 16: SIL Methodology

Personnel Safety Risk parameter Classification Comments

occupancy could be higher than

normal. The latter is the case

with demands which occur at

equipment start-up

Possibility of avoiding the

hazardous event (P) if the

protection system fails to

operate.

PA

PB

Adopted if all

conditions in

column 4 are

satisfied

Adopted if all the

conditions are not

satisfied

4. PA should only

be selected if all

the following are

true:-

• Facilities are

provided to alert

the

operator that the

protection has

failed

• Independent

facilities are

provided to shut

down such that

the hazard can be

avoided or which

enable all persons

to escape to a safe

area

• The time

between the

operator being

alerted and a

hazardous event

occurring exceeds

1 hour or is

definitely sufficient

for the necessary

actions.

Demand rate of the unwanted

occurrence (W) given no

protection system.

To determine demand rate it is

necessary to consider all

sources of failure that will lead

W1

W2

Demand rate less

than 0.03 per year

Demand rate

between 0.3 and

5. The purpose of

the W factor Is to

estimate the

frequency of the

hazard taking

place without the

Page 16 of 18

Page 17: SIL Methodology

Personnel Safety Risk parameter Classification Comments

to a demand on the protection

system. In determining the

demand rate, limited credit can

be allowed for control system

performance and intervention.

The performance which can be

claimed if the control system is

not to be designed and

maintained according to

IEC61508, is limited to below

the performance ranges

associated with

SIL1.

W3

0.03 per year

Demand rate

between 3 and 0.3

per year

addition of the SIS

6. If the demand

rate is very high

(e.g., 10 per year)

then use failure

rate and

continuous

demand method.

(2) - IEC 61511 Asset Loss Parameters

Asset Loss Classification CommentsConsequence (C) CA

CB

CC

CD

Minor operational upset or equipment damageModerate operational upset or equipment damageMajor operational upset or equipment damageDamage to essential equipment, major economic loss

Monetary values can be assigned to each consequence parameter

Possibility of avoiding the hazardous event (P) if the protection system fails to operate.

PA

PB

Adopted if all conditions in column 4 are satisfiedAdopted if all the conditions are not satisfied

NOTE.The same conditions as personnel safety apply

(3) - IEC 61511 Environmental Parameters

Environmental Classification CommentsConsequence (C) CA

CB

CC

A release with minor damage that is not very severe but is large enough to be reported to plant management or local authorities

Moderate damage e.g. Release within the fence with significant damage

Substantial damage e.g.

A moderate leak from a flange or valve Small scale liquid spill Small scale soil pollution without affecting ground waterA cloud of obnoxious vapour travelling beyond the unit following flange gasket blow-out or compressor seal

Page 17 of 18

Page 18: SIL Methodology

Environmental Classification CommentsCD Release outside the fence

with major damage which can be cleaned up quickly without significant lasting consequencesSerious damage e.g. Release outside the fence with major damage which cannot be cleaned up quickly or with lasting consequences

failureA vapour or aerosol release with or without liquid fallout that causes temporary damage to plants or fauna Liquid spill into a river or sea A vapour or aerosol release with or without liquid fallout that causes lasting damage to plants or faunaSolids fallout (dust, catalyst, soot, ash) Liquid release that could affect groundwater

Possibility of avoiding the hazardous event (P) if the protection system fails to operate.

PA

PB

Adopted if all conditions in column 4 are satisfiedAdopted if all the conditions are not satisfied

NOTE.The same conditions as personnel safety apply

Page 18 of 18