Shoals Marine LabWind Turbine Construction, June 2007

William E. BemisKingsbury Director

Page 2: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Parts for the tower arrived in the evening of June 21.

Page 3: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

We transferred tower components to the barge.

Page 4: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

We barged them to the high tide pier for unloading.

Page 5: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Ross Hansen is sitting on the counterweight.

Page 6: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Kevin Carpenter on the tower during initial construction.

Page 7: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director
Page 8: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Frank, Kevin and Mike installing the stop for the mast.

Page 9: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Bob Pechie describes how to install it.

Page 10: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

View of the SML campus from the top of the tower.

Page 11: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director
Page 12: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

The first part of the mast is installed on its pivots.

Page 13: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

First section of mast being installed.

Page 14: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Second section of mast and counterweight.

Page 15: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Third section of mast being installed.

Page 16: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director
Page 17: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director
Page 18: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director
Page 19: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director
Page 20: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Generating electricity on day one: June 29, 2007.

Page 21: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

Generating electricity on day one: June 29, 2007.

And that is not all…

Page 22: Shoals Marine Lab Wind Turbine Construction, June 2007 William E. Bemis Kingsbury Director

SML’s Engineering Interns installing solar panels: July 2007.