Upload
doandieu
View
223
Download
5
Embed Size (px)
Citation preview
PERMANENT INTERNATIONAL ASSOCIATION
OF NAVIGATION CONGRESSES
SHIP LIFTS
Report of a Study Commission within the framework of
Permanent Technical Committee I
SUPPLEMENT TO BULLETIN N° 65 (1989)
General Secretariat of PIANC : Residence Palace, rue de la Loi 155, B. 9
1040 BRUSSELS (Belgium)
1.S.B.N. 2-87223-006-8
All copyrights reserved
PERMANENT INTERNATIONAL ASSOCIATION
OF NAVIGATION CONGRESSES
SHIP LIFTS
Report of a Study Commission within the framework of
Permanent Technical Committee I
SUPPLEMENT TO BULLETIN N° 65 (1989)
General Secretariat of PIANC : Residence Palace, rue de la Loi 155, B. 9
1040 BRUSSELS (Belgium)
l.S.B.N. 2-87223-006-8
All copyrights reserved
Foreword
FOREWORD
During the 18th meeting of the Council of PIANC on
October 8th, 1984, it was decided that the Study of Locks,
Dry Docks and Ship Lifts should be entrusted to a new
Commission, with the same membership as the former one.
As far as ship lifts were concerned, the new Commission
would be under the aegis of the Permanent Technical
Committee nr.I (P.T.C.I). The Chairman of the Commission,
Prof. Dr. Ir. KUHN, proposed that Mr. J. SEYVERT
(Belgium), Inspector General of Public Works, Professor of
the Universite Libre of Brussels, should act as General
Reporter and Mr. SEYVERT agreed to undertake this work.
This proposal was approved by the Permanent International
Commission.
1. CONTENTS OF THE REPORT
CHAPTER 1
Circumstances under which a ship lift may be the best
solution of moving a ship from one level to another.
CHAPTER2
establishes the principles and the characteristics of ship
lifts, including their classification into lifts, inclines and
water slopes.
CHAPTERS 3, 4 AND 5
identify the specific principles and characteristics respec
tively relating to lifts, inclines and water slopes.
These three chapters do not provide an exhaustive study
or a comprehensive historical review of the various existing
or planned ship lifts throughout the world.
The interested reader will find it useful to refer to the
references listed in the bibliography.
CHAPTER6
is an extensive monograph of the main ship lifts
operating throughout the world. During its meeting in
November 1986, the Commission decided that the report
should only include detailed descriptions of the structures
built or designed after 1950, namely :
Lifts
- the floating lift of Henrichenburg (F.R.G.)
- the ship lift ofLiineburg (F.R.G.)
- the ship lift of Strepy-Thieu (Belgium)
Inclines
- the incline of Ronquieres (Belgium)
- the incline of Saint-Louis/Arzviller (France)
- the incline of Krasnolarsk (U .S.S.R.)
Water slopes
- the water slope of Montech (France)
- the water slope of Fonserannes (France).
CHAPTER7
proposes conclusions, to the extent that it is possible in
such a complex subject as ship lifts.
THE BIBLIOGRAPHY
lists general books as well as papers specifically dedi
cated to the lifts described in Chapter 6.
2. MEMBERS OF THE COMMISSION
The members of the new Commission who were active
during the preparation of this report were as follows :
Chairman
Prof. R. KUHN, Dr. Ing., Rhein-Main-Donau A.G., Pro
kurist i.r. Munich.
Reporter General
Mr. J.SEYVERT, Civil Engineering General Inspector,
Administration of Waterways, Ministry of Public Works,
Brussels, Professor of the Universite Libre of Brussels.
Secretary
Mr. A.LEFEBVRE, ,Civil Engineer, Administration of
Waterways, Ministry of Public Works, Brussels.
3
Members
Austria
Mr.W.ROEHLE, Dipl. Ing. Direktor i.r., Osterreichische
Donaukraftwerke A.G., Vienna
- Belgium
Mr.P.LAGROU, Civil Engineering General Inspector, Direc
tor General of the Central Procurement Office, Ministry of
Public Works, Professor of the Vrije Universiteit of
Brussels
Mr.C.ROTHILDE, Civil Engineering Chief Engineer
Director, Administration of Waterways, Ministry of Public
Works, Brussels
- Canada
Mr.D.J.GORMLEY, Director, Maritime Works and Tran
sport, Ministry of Public Works of Canada, Ottawa.
- France
Mr.MONADIER, Civil Engineering Chief Engineer, Com
piegne
- Federal Republic of Germany (F.R.G.)
Mr. Dipl. Ing. H.D.CLASMEIER, Nieders8chsisches Hafe
namt, Emden
- Italy
Mr.DELLA LUNA, Ingegnere Direttore, Canale Milano
Cremona-Po, Mantova
the Netherlands
Mr.F.A.van TOL, Rijkswaterstaat, Division Locks and
Weirs, Utrecht
Mr. Ir. F.C. DE WEGER, Rotterdam
Mr. VAN DER HORST MSc CE Civil Engineering Depart
ment, NBM General Contractors, the Hague
- Poland
Professor MAZURI{IEWICZ, Gdynia
4
- Portugal
Mr. D.PINTO DA SILVA, Civil Engineer, Gabinete da
Navegabilidade do Douro, Porto
- United Kingdom
Mr.D.P.BERTLIN, M .. Eng., F.I.C.E., Bletchingley, Surrey
Mr. G.P. MARTIN, B.Sc., F.I.C.E., T.F. Burns & Partners,
Hove, Sussex
- U.S.A.
Mr. John DAVIS, Consulting Engineer, Washington D.C.
Mr. YACHNIS, Dr. Sc. Chief Engineer, Department of the
Navy · Facilities Engineering Command - Alexandria -
Virginia
- u.s.s.R. Mr. SELEZNEV, Prof. River Fleet Ministry, Leningrad
3. MEETINGS OF THE COMMISSION
The 21st meeting of the initial Commission was held in
Toulouse (France) and included a visit to the water slopes of
Montech and Fonserannes.
The new Commission met six times, three of their
meetings being in Brussels, in the PIANC offices.
A meeting was held in May 1986 in the U.K.; another
meeting in Renesse (the Netherlands) in November 1985 and
the last meeting in Mi.inich (F.R.G.) in September 1987
(including a visit of the Main-Donau Canal).
During the November 1986 meeting in Brussels, one day
was dedicated to a visit to the ship lift of Strepy-Thieu, then
being constructed. Visits were also made to the ship lifts
still in operation on the Canal du Centre.
1. Introduction
5
1. INTRODUCTION
Through many generations, engineers involved in
making and modernizing waterways have been faced with
the problem of tr8:nsporting vessels from one level to
another.
In his attempt to transport as rapidly as possible ever
increasing quantities of goods, man has adapted waterway
transportation to his needs.
Low tonnage units have been replaced by faster, larger
and more economic units which can be made profitable only
by minimizing time of turn round.
Such requirements, when applied to the waterway infra
structure, involve the use of longer reaches, ps well as the
increase of the lift of the structures which make it possible
to move from one reach to another.
Moreover, the increase in the size of vessels leads to
ever increasing dimensions of the structures themselves.
The obvious solution to the problem of transporting a
vessel from one level to another is, of course, the lock.
Engineers have much experience in the design o( such
structures, which are mainly constructed of concrete masonry
with only a comparatively small amount of electro-mechanical
equipment (operation of the gates and filling and emptying
valves).
A lock with a lift of less than 15 metres does not,
generally speaking, raise any particular problem; the average
velocity of rising and descending of the water plane (vertical
velocities) with such systems are of the order of 0.50 to
2.00 m/min, which means filling and emptying times of 5 to
10 minutes.
In the case of lifts greater than 15 metres, faster filling
is necessary (3 m/min or more) if the filling and emptyning
time is to be reasonably short.
TABLE 1
Country Ri'ver Head· m Filling time Average
Lock min. Upward
Velocity
m/min.
Portugal Douro
Carrapatello 35,0 12 2,8
Valeira 33,0 11 3,0
U.S.A. Snake River
Lower Granit 32,0 s 4,0
Little Goose 30,8 11 2,8
Lower Monumental 31,4 11 2,85
Ice Harbor 31,4 11 2,85
Columbia River
John Day 34,4 20 1,72
U.S.S.R. Volga
Pavlovka 33,20 14 2,31
Dnepr·Bug
Zaporojie 39,20 12 3,27
7
Furthermore, the \Vater intake of the classical lock
increases in proportion to the lift. The intake of a substan
tial volume of water within a limited time from the
upstream reach and the release of the same volume into the
downstream reach generates a complex system of waves. Ii;
rivers with a sufficient flow, this has no significant impact.
With canals, on the contrary, with a theoretical nil flow and
a limited cross-section, such waves may be disturbing or
even dangerous both to navigation and safety in the reaches.
High lift locks are therefore a good solution for free
flowing rivers. However, even in such instances, modern
technique faces limits which cannot be accurately defined.
Beyond such limits, ship lifts should be considered.
To date, the lock with the maximum lift is that of
Ust-Kamenogorsk, on the Irtish River in the U.S.S.R.: 42 m.
This lock is equipped with an unusual filling system using a
hydraulic device to enable filling to be completed in about
4min.
Table 1 on page 7 lists all the locks (in addition to the
Ust-Kamenogorsk lock) with a lift of more than 30 m. This
list is abstracted from the appendix to the final report of
the International Commission for the Study of Locks. The
table also indicates the filling time and the average rate of
up\vard motion.
In canals, locks with saving chambers have means of
artificially fractioning the lift to limit simultaneously water
consumption and disturbance in the adjacent reaches. Locks
with water saving chambers are basically vertically superim
posed low lift locks.
8
The water saving chamber lock with the highest kno\Vn
lift is currently in operation in Uelzen (F.R.G.) on the side
canal of the River Elbe : 24 m; the filling time is 12
minutes and the average rate of upward movement 2 m/min.
The three water saving chamber locks of Hilpolstein,
Eckersmiihlen and Leerstetten now being constructed on the
Main-Donau canal will have a lift of 24.70 m.
This type of structure however has several drawbacks: a
large number of sluice valves, complicated concrete structures
and the necessity of repumping emptying water into the
upper reach with consequent increased cost of operation.
A water saving chamber lock therefore seems to be
excluded for high lifts.
* * *
In conclusion, it is nowadays possible to build in wide
waterways having a large flow, locks with up to 30 to 40 m
lifts with reasonable filling and emptying times.
In canals, \vater saving chamber locks may be con
sidered up to lifts of 25 m.
Beyond these limits, it is better to avoid the uncertain
ties of water consumption and of the rapidly varying
movement of large amounts of water by using a mobile
chamber or tank or a water wedge containing the vessel.
2. Ship lifts
9
2. SHIP LIFTS
2.1. General
Ship lifts are always more expensive than locks, both in
cost of construction and in operation and maintenance.
They require highly sophisticated structures and
advanced electro·mechanical equipment and bring a heavy
responsibility on those who design, build and operate them.
Accidents have consequences that are far more important
and severe than in the case of a lock, which explains why
relatively few ship lifts have been built.
The first lifts of any importance were built at the end
of the 18th century and in the 19th century. Their lifts are
still limited (± 30 m) and the tonnage of the vessels for
which they were built never exceeded 360 T.
Developments in the engineering techniques during this
century and especially since the 1930's, have made it
possible to build and operate very high ship lifts (up to
100 m) for large vessels (1,500 to 2,000 t).
Table 3 given on pages 12/13 lists the main lifts in
operation or under construction from 1788 to the present
day.
Modern lifts have upward velocities that usually com
pare favourably with those of the best performing locks.
Table 3 hereafter, taken from the book by H.W. Partenscky,
indicates the average rates of upward movement of the most
modern lifts.
With a lift, ships are transported either in the dry or
in a tank (steel box) filled with water or in a wedge of
water.
TABLE 2
Type of structure Location/Country First Lift Average
operation Upward
velocity
m/min
Lift Niederfinow/G.D.R. 1934 36,2 7,2
Rothensee/G.D.R. 1938 18,7 7,8
Henrichenburg/G.D.R. 1962 13,8 7,8
Liinebourg/F.R.G. 1975 38,0 12,6
Strepy-Thieu/Belgium currently
being built 73,0 10,4
Longitudinal Ronquieres/Belgium 1968 67,5 3,1
Incline IU-asnolarsk/U.S.S.R. 1968 101,0 4,6
Lateral Saint-Louis/Arzviller/
Incline France 1966 44,5 11,1
Water slope Montech/France 1973 14,3 2,85
Fonserannes/France 1983 13,6 2,0
11
T&BLE 3 LIST OF THE PRINCIPAL SHIP LIFTS IN SERVICE OR UNDER CONSTRUCTION
FROM 1788 TO THE PRESENT TIME
(after Partenscky)
Date Location . Waterway Type(s) of Lift Tank dimensions Ship structure(s) capacity
Length Width Water wt. of depth tank,
m m m m t t
1788 ENGLAND Works canal Twin inclines 21.3 ship dimensions Ketley, at Ketley Ship in dry 5.8 1, 8 5 Shropshire slope 1 :25
c. ENGLAND Shropshire 3 twin inclines up to ship dimensions 1790 Shropshire Canal Ship in dry 61.3 5,8 1. 8 5
1798 ENGLAND Somerset Dock in the wet 13.7 ship dimensions Dunkerton Canal 21.3 2.1 0.7 20 nr. Bath
1809 ENGLAND Worcester and Vertical ship 3.6 21.8 2,4 1. 4 40 Tardebigge Birmingham lifts with
Canal counter-weight wet "
1825 U.S.A. Morris Canal 23 twin inclines 11.0 ship dimensions 110 70 to Between Ship in dry to 24.0 3.2
1831 Phillips- slope 1:10 to 30.4 burg and 1: 12 New Ycirk
• 183.(l ENGLAND Grand Western Twin ship lifts 14.o 9. 1 2.2 1.0 8 TauntOn Canal (wet)
1850 SCOTLAND Monk land Twin inclines 1: 10 29.3 21.3 4.4 0.6 70 • 35 Glasgow- Canal wet converted to Blackhill dry
1860 GERMANY Oberl~n- 5 twin inclines 14.0 14 .3 5.2 84 50 • to Weichsel- discher slope 1:12; dry to
1880 Niederung Canal 25.0
1875 ENGLAND Junction of Twin ship lifts 15.4 22.8 4.8 1.4 240 100 Anderton Trent-Mersey height increased
Canal and in 1907 R. Weaver wet
1876 u.s.A. Potomac Longitudinal 11. 6 34. 1 5.1 2.4 390 135 Georgetown River slope 1:12; wet
modified to 1/2 wet
1888 FRANCE Canal de Nin ship lift 13.1 40.1 5.6 2.0 800 300 Les Fonti- Neilf'osse wet nett es •·.
1888 BELGIUM Canal du ditto 15.4 43.2 5.8 2.4 1050 360 La Louviere Centre
1893 FRANCE Canal de Longitudinal 12.2 24.0 3.8 70 Meaux l'Ourcq slope 1;25
no counter-weight; dry
1899 GERMANY Dortmund- Ship lifts; 14.0 68.0 8.6 2.5 2340 800 (F,R.) Eros Canal wet to Henrichen- 16.0 burg
1900 ENGLAND Junction Twin slopes 22.0 24.4 4.6 1.5 70 Foxton, Canal (transverse) Leicester 1 :4; wet
1904 CANADA Trent Canal Twin ship lifts; 19.8 42.4 10.0 2.7 1714 800 Peterborough wet
1907 CANADA Trent.,Canal ditto 14.8 42.4 10.0 2.7 1714 800 Kirk field
12
Date Location Waterway Type(s) of Lift Tank dimensions Ship structure(s) capacity
Length Width Water wt. of depth tank
m m m m t t
1917 BELGIUM Canal du 3 twin ship lifts; 16.9 q 1. 1 5.8 2,q 1570 360 Houdeng- Centre wet Aimeries, Bracquegnies et Thieu
193q D.R. GERMANY Havel-Oder Ship lift with 36.0 85.0 12.0 2.5 q300 1000 Niederfinow waterway counter-weight;
wet
1938 D.R. GERMANY Weser-Elbe Vertical flotation; 18.7 85.0 12.2 2,5 qooo 1000 Rothensee Canal wet
1962 F.R. GERMANY Dortmund- ditto 13.7 90.0 12.0 3.0 5000 1350 Henrichen- Ems Canal burg-Waltrop
1968 BELGIUM Brussels- Longitudinal 67.5 91.0 12.0 3.0 q500 1350 (put in Ronquieres Charleroi slope 1 : 20; wet to to op er- Canal 3,7 5200 ation)
1969 FRANCE Rhein-Marne Transverse qq,5 q2,5 5,5 3.2 894 350 Arzviller Canal slope 1:25; wet
1973 CHINA Hanjiang Ship lift dry and 33,5 32.5 10.7 150 150 Danchiangkou- River - Longitudinal 33.0 24.0 10.7 0.9 qoo 150 Dam Hubei slope 1 :7
Province
1974 FRANCE Garonne Water wedge 1 :33; 14.3 125.0 6.o max. 350 Hontech Lateral wet 3,75
Canal Dimensions refer to wedgl!!
1975 F.R. GERMANY Elbe Lateral Twin ship lifts 38.0 100.0 12.0 3,5 5700 1350 LOneburg Canal with counter-
weights; wet
1983 FRANCE canal du Water wedge 1: 20 13.6 88.o 6.0 4.4 350 Fonserannes Midi Dimensions refer to wedge
1985 u.s.s.R. Jenissej Longitudinal 101.0 90.0 12.0 3,3 6720 1500 Krasno!arsk slope 1:10; wet
under BELGIUM Canal du Twin ship lift 73.0 112. 0 12.0 3,5 7500 1350 con- Strepy-Thieu Centre with counter-st rue- weight; wet ti on
- 5 ,,.. - 4 n--, t=" ?-1
I
F- t 3 n--, i---> ?:I
p-_t 2 1 rl---<-1 -M
Fig. 2.1. Operation of a ship lift
13
l
r1-!..~=-~~=i~=:._-.;:...1 " ' ~-----------' -·- . .
Fig. 2.2. Operation of a tank on an incline
Table 3 on pages 12/13 demonstrates that during the
last 90 years lifting by a tank filled with water or by a
water wedge have been the only solutions adopted, for high
lifts, with the exception of one in the Popular Republic of
China built in 1973.
This report is exclusively concerned with ship lifts using
a tank filled with water and with water wedges.
2.2. Definition and operating principles
In a lift with a tank, the vessel is generally lifted in a
watertight tank closed by a door at each end.
The lifting of the tank proceeds either vertically Gifts,
Figure 2.1) or along an inclined plane (inclines, Figure 2.2.).
When the lift translation nears completion, the tank is
brought into communication with the adjacent reach in terms
of the following sequence (figure 2.3.) :
operation of the tank-reach sealing system
equalizing water depths in the tank and in the reach by
slightly raising the tank and reach gates;
completion of the opening of the gates;
at this stage, manoeuvring vessels is possible;
closing of the gates;
discharge of the water between the tank gate and that of
the reach (between gates water) and gradual operation of
the watertight systems between tank and reach gates;
Downstream, the reach freely communicates with the
trough. The connection between reach and wedge is brought
about by raising the shield.
•
Among the advantages of water lifts, we may mention :
a very small water consumption; this consumption is due
to the exchanges between tank or water wedge and reach
\Vhen equalizing the water depths, to the leakages in the
seals of the gates and of the shield, to the discharge of
the water between the gates (tank and reach), to the
water volumes required by the swinging movement in
hydraulic ship lifts;
when joining the tank or water wedge with the reach, the
water depth differential is generally small and the
exchange of water thus proceeds without significant distur
bance.
operation of the lo\vering of the tank. i·~· .~ .. ~ .. ,;,,;,~::--x~.-:-~:-»~:-0~···~~r:::::;;===~=Ji:::~;a!:it__ With water slopes, the vessel floats in a water wedge
contained in an inclined U-shaped trough. The water is
contained downstream by a sliding gate pushed when moving
up or retained when moving down by a driving unit (Figure
2.4).
In fact, water slopes are a specific type of incline.
Upstream, when the water depth in the water wedge
equalizes the water depth in the upper reach, communication
between reach and wedge is insured by operating the reach
gate.
14
Fig. 2,4. Operation of a water slope (Top) : The train enters the water slope (Middle) : The train pushes the water wedge (Bottom) : The water levels in the reach and wedge equalize
Reach
lift
--- -·-· - ---
Reach Tank
·- Tank
t Incline
The tank approaches the head of the reach.
-. = -...::::.:- .... : .... : ... ~::-
\ " " ·-- .... . . - ' .... -:-.-:---
The tank has come to a stop in line with the head.
Operation of the tank-reach sealing system.
Detail 1 Initiating communication between tank and reach.
Filling the space between the tank-reach gates and equalizing of tank-reach levels.
Withdrawing gates -same level in tank and reach. Manoeuvring vessels.
Detail 2 : Separating tank and reach.
Discharge of water between the gates.
--- -·-·- --
Lift Incline Departure of tank 15
Fig. 2.3
0 Useful load Total load
G) e- Transport with o,a-t---t----+--+--+-----,t----+--+--+----1--+~+--rl~a~n,k~f~1ul~lro~f~w~a~te~r-+--+----1
0,6 KAN AL
ORRIS-CANAL I 'O:'. I OBE~LAND I SCllER - ......_ I ~ I 1
~.~LASGOW-DLACKHILL ~-/~-t~-/-~-GJ"C-f-~-f-~/~-+~-+PETERBOROUGH.-~t-~l----11----1~--!~--I
l6CUIANGKOU
LuSHul
............... _jNDIERTOIN 8'1 I . --.. _Ill KIRKFJELD
0,4 t---t---t--11---t---t---+""''--=f--...-':--:;::-",::-;:":'-c;:;.':O:::::c=-+---+--f--l---+---t---1 -~LES FONTINETTES llENRJCHENBURG-
~-t~-t~-t~-tl-A-:-:L~O ·U~V~t~E~RR~EE··~v'::-:r----.~f'---=:cl---ll---1~--J~--f-JHALTROP I - · HEN JR I CHE NUUJRG-4 I'---,.__ / • Kf-R-A-SN~Orl-A-R-<SK
. -- ~OTHENSEE D I I O,l +---+---+---<f--+---+---+-1--CANAL DU CENTRE - ARZVILLER
' -· ' ' ··+• GEOR,GETOWN-9 NIEDERF INOW-• RONQUIERES .. _ ' HIEU t---T-+-+--+-+-t--'=+-+-11- I I I LfNEBUtG-" •TRrY-T ©
o . . . . Year 1820 1840 1860 1880 1900 1920 1940 1960 1960
Fig. 2.5. Useful to total loads ratio (tank + water). (from Partenscky)
One characteristic of transportation by tank is the
reduced ratio of the useful weight transported to the total
weight of the tank and water. The diagram of Figure 2.5.,
from H.W. Partenscky, shows the values of this ratio for a
few lifts. The ratio is between 0.15 and 0.35 for recent
structures as against 0.60 for lifting a vessel in the dry.
It is seen that the volumes that have to be moved for
lifting vessels are very substantial. This is \Vhy tanks are
generally balanced by counterweights, in order to reduce
operating stresses and the power required for operation; in
the specific case of hydraulic lifts, tanks balance one
another.
16
3. Lifts
17
3. LIFTS
Three types of compensated lifts are briefly described as
follows:
- Hydraulic or piston lifts, \Vhich were the first lifts used
for transporting ships afloat;
Float lifts;
Vertical lifts with counter-weights.
3.1. General characteristics of lifts
Water consumption reduced to the vOlumes between the
gates, to the volume exchange between tank and reach
\vhen they are brought into communication, to the com
pensating volume between hydraulic lifts.
During the vertical movement, ships do not usefully move;
this has no impact on the duration of the operating cycle
because of the high vertical velocities.
- Thanks to compensation, reduced operating stresses, which
are only required to overcome passive resistance and the
slight lack of equilibrium between the tank filled with
water and the compensation system.
Structures and equipment are concentrated in a limited
area, \vith easy access.
Overall loads transmitted to the ground are practically
permanent, variations being due only to the weight of the
\vater in the tanks.
- It is often possible to build a monolithic floor. This type
of structure is recommended when the foundation is of
poor quality.
During vertical movement, movements of the water plane
and ship hawser stresses are theoretically nil.
In the case of a minor lack of synchronisation during
movement, limited oscillations of the water do occur. This
also applies to ha,vser stresses, but they remain well under
the regulatory limits.
3.2. Hydraulic lifts
Two tanks filled with water are each supported on a
piston, \vhich slides in a watertight cylinder. The cylinders,
\vhich are filled with water, are connected by pipes having a
valve (Figs 3.1. and 3.2.).
The laterally guided tanks are equipped \vith vertical
lift gates at their ends.
The reaches of the canal are also equipped up· and
downstream \Vith vertical lift gates, which match the doors
of the tanks.
If the identical tanks were each filled to the same
water depth, their weights would be equal; if then the
central valve were to be opened, the hvo tanks would stop
at the same level, which would be the average level of the
upper and the lower reaches.
To ensure the proper functioning of the lift, an
additional quantity of .6. cm of water is introduced into the
tank moving downstream (on the right hand side in the
figures). This additional quantity causes a loss of balance,
much in the same way as two plates on a scale, one of
which would have a larger weight than the other one. This
brings the right hand side tank to the low position and the
left hand one to the high position. The overload correspond·
ing to the .6. cm of \vater is the driving force: it should be
just sufficient to overcome passive resistance. This operation
is called trimming.
The valve is closed as soon as trimming is completed.
The \vater overload is then released into the do\vnstream
reach as soon as the gate opens: this is the small \vater
consumption of the system.
The system operates solely by hydraulic energy.
In case of accident (e.g. accidental emptying of a tank),
the communication valve between the two cylinders is closed.
The operation can then be completed by injecting water
under pressure into the cylinder of the upgoing tank (this
water being supplied from an accumulator in the cases of
the Centre canal lifts in Belgium and those of the Trent
Severn canal in Canada). However, it is a difficult operation,
that cannot be repeated.
The main characteristics, advantages and drawbacks, of
hydraulic lifts are as follows :
two twin tanks : any incident with one entails the
impossibility to operate the other one and thus navigation
is interrupted;
the construction of shafts with a height equal to the lift
plus appropriate clearances is required;
water pressure in the cylinders is high (from 27 bar in
the Fontinettes lift to 40 bar and more with the other
lifts).
The first ship lift was designed by the English engineer
Clark.
19
20
0 Lift
Level of lower reaCh
0 .. N
i 5 Piston
20
/
linder
Fig. 3.1. Diagrammatic cross.section of a hydraulic lift
C0 Beginning of movement During movement
/.
/.
Fig. 3.2.
® End of movement
I
i I . . : I I ,
" I
This structure 'vas first operated in 1875 in England, in
Anderton, on the Trent-Mersey canal; it was designed. for
100 ton vessels and had a lift of 15.40 m.
There were a number of problems (deficient guiding of
the tanks, corrosive electrolitic action and the breaking of a
piston); it was therefore decided to convert this lift into an
incline and the original structure is no'v used only for
pleasure and sport navigation.
In 1888, a hydraulic lift with a lift of 13.10 m was
brought into service in France on the Neufosse (Pas-de
Calais) canal for 300 t ships.
In 1894, its operation was interrupted for some time
follo,ving deterioration of the foundation of the shafts; repairs
were carried out by freezing the ground. Initially, the
watertightedness of the packings was deficient; this was
made good by using hemp rope.
The Fontinettes lift was first made operational in
August 1967. It was replaced by a 144 m x 12 m lock
incorporated in the Dunkerque-Schelde connection with
dimensions sufficient for 3.000 t push tows.
In Belgium, 'vhen adapting the Centre canal for ships of
300 tons (§ 6.3), four hydraulic lifts were constructed (figure
3.3.):
1) HOudeng-Goegnies 15.40 m
fi~st operated in 1888
2) Houdeng-Aimeries 16.90 m
first operated in 1917
3) Bracquegnies 16.90 m
first operated in 1917
4) Thieu 16.90 m
first operated in 1917
These four structures are still used for commercial
navigation and marginally for pleasure and sport (without
any significant operation incident) and they will remain in
service until the funicular lift of Strepy-Thieu (§ 6.3) which
is now under construction, is operational.
In Canada, two hydraulic lifts have been built on the
Trent-Severn waterway for ships of 800 tons :
1) Peterborough 19.80 m lift
first operated in 1904
2) l(irkfield 14.30 m lift
first operated in 1907
These two structures are still in operation, but only for
the use of pleasure and sport navigation (Figure 3.4.).
In 1964, the operating gears were repla;ed by hydraulic
motors.
Hydraulic lifts have never been built for lifts in excess
of 20 m.
After the construction of the Canada lifts, no further
hydraulic lift has been considered.
3.3. Float lifts
The three known floating lifts include only one tank
(first lift of Henrichenburg; lift of Rothensee, second lift of
Henrichenburg).
The tank rests on two or more floats moving in shafts
filled with water and freely communicating with the outside
(Figure 3.5.). The floats are either watertight, as with the
above-mentioned lifts, and filled with compressed air to ensure that the walls are only submitted to tensile stresses
or designed as diving bells (no known example).
Tank lift is either by the rotation of worm screws in
the infrastructure and turning in fixed bolts attached to the
tank (Henrichenburg lift) or through the rotation of bolts
controlled from the tank and turning around fixed worm
screws attached to the infrastructure (Rothensee).
The tank is nearly totally balanced by the floats.
Devices may be incorporated to ensure this equilibrium
whatever the position of the tank and in spite of the
variation of the submerged volume of the float(§ 6.1)
Safety measures are taken to anticipate the sudden
emptying of the tank or splitting of the floats.
The hydrostratic pressure and the stresses in the floats
increase as a ratio of the lift; the same applies to the
screws, which remain mechanical devices liable to give
trouble.
With a view to doing away with the shafts or to
reducing their depths, German manufacturers have designed
lifts 'vith side floats (Faure project, Fig. 3.6.) or upper floats
(Jebens project, Fig. 3.7.). Such designs have not been
implemented so far.
The general characteristics of the existing floating lifts
are as follows :
First Henrichenburg lift (F.R.G.): first operated in 1899;
disabled in 1969 (Fig. 3.8.)
Designed for 700t vessels
14.00 m lift
Five floats
Float height : 29.50 m
- Rothensee lift CD.R.G.): first operated in 1938 (Fig. 3.9.);
Designed for 1,000 t ships
16.00m lift
1\vo floats
Float height: 36.00 m
Second Henrichenburg lift (F.R.G.): first operated in 1962
Designed for 1,000 t ships
14.00 m lift
Two floats
Float height: 35.28 m.
21
Fig. 3.3. Lift on the Centre canal (Belgium)
Fig. 3.4. Lift at Kirkfield (Canada)
22
9300 m·------• In upoer position
0 tank In lower position
;±o:TII·---bl-~-i©screw ~
.~.~-.'.·. -·
I E! ~: ~.
~I float
Fig. 3.5. Lift with floats
.~m.
© I !ft
14,00m - --
I
~-
ITDu- ''"TIDD
Fig. 3. 7. Lift with upper float
Fig. 3.6. Lift. with side floats
23
Fig. 3.8. First fioat lifi of Henrichenburg
3.4. Vertical lifts with counterweights
There are three known such lifts : Niederfinow {D.R.G.),
Liineburg {F.R.G.); Strepy-Thieu (Belgium).
The tank containing the ship is hung on cables which
pass over pulleys at the top of the structure. These cables
are tensioned by counterweights {Fig. 3.10.).
The lift of the tank is accomplished by :
either the rotation of driving pinions controlled from the
tank which mesh with fixed racks attached to the
structure {Niederfinow; Liineburg);
or through a series of driving pulleys {Strepy-Thieu).
Safety devices are installed to cope with any serious
malfunctioning(§ 6.2 and 6.3).
24
The weight of the tank is almost balanced by the
counterweight. The overall length of the cable is constant;
however, the position of the pulleys and counterweight beams
vary throughout the lift. The variable weights of these two cable sections create
some lack of balance which may be compensated through
balancing cables {Niederfinow; Liineburg) or remain uncom·
pensated (Strepy-Thieu).
The funicular lifts may have one tank (Niederfinow) or
two independent tanks {twin lifts Liineburg; Strepy-Thieu).
The general characteristics of the three currently oper-
ated high tonnage funicular lifts are as follows :
Niederfinow: first operated in 1934 {Fig. 3.11.)
Designed for 1,350 t ships
36.00 m lift
One tank
1"'1 . . . 1~+
I
Fig. 3.9. Rothensee lift
Fig. 3.11. Niederfinow lift
25
3 ack
®worm @.Pinion
~I "'o
N>
~
- Li.ineburg: first operated in 1975
Designed for 1,350 t ships
38.00 m lift
Two tanks
26
I I
v Level --upper reach
cables
I "f' Level. 1:@1owerl reacli'-1' I
Fig. 3.10. Cross-section of a funicular lift
- Str€py-Thieu: cun·ently being constructed
Designed for 2,000 t barge with its tug
73.00 m lift
Two tanks.
4. Inclines
27
4. INCLINES
With an incline (Fig. 4.1.), the tank filled \vith water
which contains the vessel(s) undergoes an oblique translation
movement; the tank rests on a large number of rollers
moving on rails which form the runway (railroad type rails
or travelling bridge crane type rails).
The tank may undergo a movement parallel with its
longitudinal axis (Fig. 4.1.), in which case the incline is of
the longitudinal type (Ronquieres, Krasnolarsk).
If, however, the tank moves along a parallel line with
respect to its transversal axis, the incline is of the trans·
verse type (Fig. 4.2.).
Inclines are designed to fit the countours of the ground :
longitudinal type inclines have a limited \vidth but require
safety measures to avoid or restrain S\vinging and moving of
the vessel in the tank.
Such problems are less acute with the transverse type
but they are more cumbersome widthwise and require a
particular layout (axes of the upper and lower reaches \vith
a displacement equal to the length of the incline).
Currently operated inclines are equipped either \Vith one
tank (Krasnoi'arsk; St Louis/Arzviller, with, in the last
named, the possibility of installing a second tank) or with
two tanks (Ronquieres).
These tanks are either tractor drawn CRonquiE!res, St
Louis/Arzviller), or self-propelled (Krasnolarsk).
In the first case, they are balanced by counterweights
(Fig. 4.3.) and their operating gear is concentrated at the
upper end.
In the second case, the tanks incorporate the driving
gear, including the driving pinions, meshing with racks
incorporated in the runway.
The general characteristics of inclines are as follo,vs :
reduced \vater consumption
\vith longitudinal inclines, the ships move usefully during
movement
with tractor-drawn and balanced tanks, the operating
stresses are minimal; with unbalanced self.propelled
tanks, operating stresses are very substantial.
with tractor drawn and balanced tanks, fittings and
equipment are concentrated at the upper head and the
equipment of the tank is limited; \vith self-propelled
tanks, the equipment in the tank is heavier and that of
the upper head is reduced;
excepting the heads, the structure of inclines is very long;
the load and pressures transmitted to the ground vary
from zero to very substantial during the movement of
the tanks; with ground of poor quality, foundation yiel
ding may be substantial: the infrastructm·e must be
designed and dimensioned con·espondingly;
in case of a constant acceleration (deceleration) when
starting (stopping) the movement, a wave regime occurs in
the tank. Its amplitude is maximum at the ends of the
tank and directly in line with the length (width) of the
tank in a longitudinal (transversal) incline and \Vith the
acceleration or deceleration. The water plane does not stay
horizontal; ships are drawn along the direction of the
slope of the water plane and hawser stresses occur. These
stresses should be limited to regulatory values.
Such phenomena are distinctly less acute with a gradual
acceleration (deceleration). They are particularly pronounced
in longitudinal inclines and a direct function of the length of
the tank. They are constrained by regulating the movement.
Before the construction of the three inclines described in
§ 6.4, 6.5 and 6.6, no incline had been built (table of
chapter 2) for ships of a tonnage of more than 300 t.
The general characteristics of the three above-mentioned
inclines are as follows :
Ronquieres (Belgium): first operation in 1968
Longitudinal type
Designed for ships of 1,350 t
68.00 m lift
5 % slope
T\vo tractor-drawn tanks
St Louis·Arzviller (France): first operation in 1969
Transversal type
Designed for ships of 300 t
44.55 m lift
41 % slope
One tractor-dra\vn tank (with a possibility to install a
second tank)
Krasnoi'arsk (U.S.S.R.): first operation in 1985
Longitudinal type
For ships up to 1500 t
100 m lift
10 % slope
One self-propelled tank
29
5 ' ---..::::.==:.:-=:;-:::~-1n--:;:;::.;:_=_~;.:;::;
''•' q ---------.<;.:-.:~::_---------1
' ::-------l
Fig.4.1. - Diagram of longitudinal incline.
(!)tank
CV width
Fig. 4.2. - Transverse type incline.
CD tank
. (!)counter-weight driving pulleys
CD ··-.,
Fig. 4.3. - Principle of the traction type tank.
30
5. Water slopes
31
5. WATER SLOPES
The operating principle is described in Chapter 2 and
illustrated in Fig. 2.4.
There are only two \vater slopes worldwide: the slopes of
Montech and of Fonserannes, both in France. They are
described in § 6. 7.
The main characteristics of \vater slopes are as follows :
- Low consumption of \vater
- During movement, the ships move usefully
The watertightness devices between the shield and the
channel are under stress throughout the movement.
These characteristics require a particular care in the
design, construction and maintenance of the channel so as to
ensure its strength and rigidity as \Vell as the perfect
maintenance of the surface of the bottom and side walls.
The structures are simple : their main element is the
channel, the upper head contains only the operating gear
of the canal gate and is thus very much like a lock head;
there is no lower head.
- The load and pressures transmitted to the ground vary.
As the driving motor is not compensated, operating
stresses are substantial; this driving unit is sophisticated
and this goes for the shield as well.
In the two existing water slopes, the driving units are
carried on pneumatic tyred \vheels.
In case of frost and glazed ice, a lack of adherence may
entail temporary interruption of operation.
Similarly, \vith very low temperatures, problems may
arise 'vith the watertight devices between the shield and the
channel.
The problem of the oscillation of the water surface and of
the ship movements in a water wedge is quite specific; it
results from the inertia of water and of the ship.
In case of acceleration when ascending, the ship starts
moving in a direction opposite to that of the shield, which
should therefore be protected against ship impact.
In case of acceleration when descending, ~he ship
remains backwards \vith respect to the shield and tends to
touch the bottom of the channel. The oscillation of the water
surface translates among other things into variations of the
water surface and variable thrust at the level of the shield.
Just as with inclines, the movement should be regulated
so as to ensure gradual acceleration and deceleration and to
avoid or limit ship impacts against the shield and to
maintain a sufficient water depth under the ship at the apex
of the water wedge. The same requirements apply to
emergency braking.
The general characteristics of the two water slopes
described under§ 6.7 are as follows:
l\1ontech : first operation: 1974
For ships up to 300 t
13.30 m lift
Slope of channel: 3 %
One driving unit
Fonscrannes : first operated: 1983
For ships up to 300 t
13.62 m lift
Slope of channel: 5 %
One driving unit.
33
6. Monographs of the lifts first operated after 1950 or currently being built
6.1. The Henrichenburg float lift
35
6.1. THE HENRICHENBURG FLOAT LIFT
(Federal Republic of Germany)
6.1.1. DESCRIPTION AND DESIGN PRINCIPLES
6.1.1.1. General Comments
6.1.1.1.1. Navigable waterways network
The main axis of the navigable waterways in Western
Germany is the Dortmund-Ems canal (D.E.K.) with its two
connections with the River Rhine, one through the Wesel
Datteln canal and the other through the Rhine-Herne
(R.H.K.) canal (Fig. 6.1.1.). The major industrial centre of
Dortmund is located in the vicinity of these waterways, to
which it is connected, near Henrichenburg, through a South
East oriented junction on the D.EJC. At this place, a
difference of level of 14 m has to be overcome.
6.1.1.1.2. History of the structures in Henrichenburg (Fig.
6.1.2.)
The first structure built to provide for this lift was a
screw driven five-float lift intended for ships of 700 t and
2 m draught (Fig. 6.1.3.). It was first operated in 1899 and
remained in service without interruption for 65 years until it
was dismantled in 1969.
As early as 1907, a second lift was studied; it was
required not only to face the increasing traffic but also to
enable the passing of vessels of greater draught. From 1908
to 1917, a lock with \vater saving chambers of 95 m x 10 m
x 3 m of water depth on the sills was built (Fig. 6.1.4.).
As a consequence of the enlargement of the Dortmund
Ems canal to cater for vessels of 82 m x 9.60 m x 2.50 m
draught and of the increasing traffic in the direction of
Dortmund, the study of a third structure was begun as early
as 1938.
Because of the larger transportation capacity of the lift
as compared \vith that of a lock with a saving chamber, the
preliminary comparative studies considered three types of
lift : incline, float lift and funicular lift.
Taking into account the local conditions, the ground
characteristics and the limited lift, the most interesting
solution both technically and financially was demonstrated to
be that with two floats (Fig. 6.1.5.).
The decision to build this structure was taken in 1958; .
it was first operated in 1962.
Fig. 6.1.1. Western Germany canal network
6.1.1.1.3. Dimensions of the structure
The structure has one lift only, with t\VO floats suppor- ·
ting and balancing the tank.
37
0 1170 100 .!OO 44:1 Sao,,,
m l
• .. 3
,.
Fig. 6.1.2. Location plan of the three Henrichenburg structures 1. 1899 lift; 2. 1917 lock with water saving chamber; 3. 1962 lift
Fig. 6.1.3. 1899 lift
38
Fig. 6.1.4. Lock with saving basins of1917
1
-15 ·16
3 ss.o
Fig. 6.1.5. 1962 lifl 1. tank chamber 2. {Wat shall 3. {Wat 4. float guide 5. bearing unit 6. tank in lower position 7. tank in upper position 8. rest of tank 9. upperstream gate of tank
10. downstream gate of tank
Dimensions:
- normal lift
- maximum lift
- useful length of the tank
- useful width of the tank
- water depth in the tank
- freeboard
- total volume of tank filled with water and of floats
13.75 m
14.50 m
90.00 m
12.00m
3.00m
0.80m
5,000 t
- working speed of tank movement
- movement duration
0.15 mis
lm48s.
13
11. manoeuring tower 12. worm screw 13. electro-mechanical equipments 14. upper head 15. guiding tower 16. gate of upper head 17. lower head 18. gate of lower head 19. synchronization shafts 20. balancing duct
Specific feature :
The design allows for a possibe settlement of 0.50 m and
a slope of 1:200, as it is built in an area of mining
subsidence. In addition, the upper head is designed to take
into account a possible lowering of 8 m of the water level in
the upper reach.
Elements of the structure (Fig. 6.1.5.) :
watertight reinforced concrete tail-gate chamber to house
the tank in the lower position;
39
10m
2 cylindrical shafts filled with \Vater, with a reinforced
concrete revetment;
2 steel cylindrical floats;
2 bearing units attached to the floats on which the tank
rests;
the tank with its upper and lower doors and with its
upper and lower sealing frames;
4 operation towers with the electro-mechanical equipment
in the heads of the towers and with the operating screws
and the guiding devices for the tank;
synchronization shafts;
the upper head with a vertical lift gate and 2 guiding
towers;
the upper head with a sector gate.
6.1.1.2. Description
6.1.1.2.1. The chamber (Fig. 6.1.6. and 6.1.7.J
The reinforced concrete chamber is watertight and capa
ble of withstanding uplift pressures.
As it must also withstand the result of mining sub
sidence, the chamber consists of sections separated by longi
tudinal and transverse joints. The joints between the sections
are partly closed (compression joints, witho1;lt intermediate
material) and partly open with a 10 min thick intermediate
plastic material.
The tightness of the joints is ensured by 2 synthetic
material strips.
The cross-section of the chamber includes a central
section reinforced by a stiffening rib and two supporting
walls or side walls.
In the vicinity of the shafts of the floats and of the
toes of the guiding towers, the cutwaters of the side walls
are connected to the walls of the shafts (Fig. 6.1.7.). Double
joints ensure the watertightness of the connection.
In the floor of the chamber, channels, sumps and pumps
ensure the collection and disposal of rainwater and of
possible seepage.
Synchronization shafts are located in accessible galleries
(Fig. 6.1.6., 6.1.13 and 6.1.14.).
6.1.1.2.2. Shafts of the floats
The foundation material consists of a layer of grey marl
under 5 to 6 m of fine sand. The upper part of the marl,
although having cracks, is sufficiently consistent not to call
for special construction techniques.
40
The main dimensions are :
diameter of floats
clearance between shafts and floats
inside diameter of shafts
outside diameter of shafts
10.00 m
0.66m
11.32 m
13.80m
floor of shafts at 53.70 m under the upper face of the
floor of tank chamber.
In the former 1899 lifts, the revetments of the shafts
were made of steel; for the new lift, an average 2 m thick
reinforced concrete floor was provided as well as side walls
made of 0.54 m thick clincker bricks outside rings and of
0.45 m thick reinforced concrete inside rings (Fig. 6.1.8.).
Dm·ing construction, the \Vater percolating through the
masonry was collected within the 0.25 m clearance between
the masonry rings and the reinforced concrete rings, without
any impediment for concreting; this space was filled with
coarse gravel and the drainage \Vater was discharged into
the shaft. Thereafter, the gravel layer was injected with
cement mortar.
Before digging the shafts, the cracked part of the marl
layer was injected \Vith cement mortar.
6.1.1.2.3. TJ1c floats and bearing tmits of tl1e tank
Each steel float consists of a closed cylindrical body
including two cells and one compensation cylinder in the
lower cell (Fig. 6.1.9.). The lower and upper closures of the
cylindrical body as well as the partition wall between the
two cells are dome shaped.
The cylindrical wall is reinforced by circular stiffeners.
The thickness of the wall plates varies from 15 to 20 mm.
However, the plate thickness of the A, B and C connections
of the cylinder to the domes reaches 45 mm.
The lower cell is filled with 4 bar compressed air, while
the upper cell is filled with 3 bar compressed air.
Under the action of this internal pressure, the walls of
the cylinder are subjected to tensile forces, which makes for
an economic construction. The design allows for greater
stresses which may be caused by leakages or exceptional
strains.
The compressed air supply to the floats is achieved by
compressors, air vessels and dryers located on the side of the ·tank.
Each float is guided longitudinally by 3 rollers located
in the same horizontal plane with a 120° displacement,
which slide along 3 vertical rails attached to the shaft wall
and transversely by pairs of rollers.
On each float, a 15.39 m long bearing unit is attached
to transmit the load from the tank to the float. Such a unit
is made of a 780 mm diameter pipe reinforced by 3 vertical
stiffening ribs as well _as horizontal stiffeners.
Fig. 6.1.6. Cross-section at mid length of chamber 1 central section 2. retaining wall 3. tank 4. synchronization shaft 5. balancing duct 6. drain
t'1 ./j~
'/
.. 1 ~
:\(\l!>~~~~~-'-~~~-H~
. '=======·f5.il11-=====::::: ..-.. 1s;aar -----
Fig. 6.1.8. Cross-section in the lower part of a float shaft 1. floor of shaft 2. clinker brick masonry 3. driven gravel filling 4. gravel drainage tube 5. reinforced concrete inner ring 6. sealing 7. anchors 8. valve sump
On the upper part of the bearing unit, a pivot pin rest
takes in the 21,600 kN weight transmitted by the tank. The
bearing unit and the tank are connected by 12 washer
spring bolts so as to ensure the connection between the tank
and the float in case of accidental filling of the float or of
emptying of the shaft (Fig. 6.1.10.).
When the bearing unit is completely submerged, the
shaft is almost completely filled with water up to its upper
end.
The thrust of one float is 24,500 kN, i.e. 49,000 kN for
the 2 floats, which compensates the overall weight of the
movable part composed of the tank, its \Vater, the 2 bearing
units and the floats.
When the floats go do\Vn, from the equilibrium position
obtaining at the upper level of the tank, the bearing
Fig. 6.1.7. Cross-section of the tank at the level of the float shafts and of the manoeuvring towers 1. retaining wall 2. float shaft 3. manoeuvring tower 4. side rest 5. worm screw 6. tank 7. supporting unit 8. pivot pin rest 9. sealing joint
Ir __ s
JJ A
ir f /1
-·-t .... I B f ·r--· ·-;:..~·
.B { I : I I'
2_ II I
3
I /-J c 'I
Fig. 6.1.9. Fl-Oat 1. upper cell - 3 bar 2. lower cell - 4 bar 3. compensation cylinder 4. supporting unit 5. guiding rollers
41
12
I I 1?,00-------~
- ........ ----6.w---~ ·---.
I J -1..:.-:::•_:-..,, -::.::;---o-c.•~T::.--=----- ~--·----~---
;j ' 7 ~ I I
! 3 1 7 ~2.22-!,S'J...:,
8
Fig. 6.1.10 Cross-section of tank at the level ofa main cross-bar and of a current cross-bar
1. main cross-bar 7. assembly bolt 2. current cross-bar 8. washer spring 3. guide rail.s 9. wire mesh grid 4. torsion box 10. wonn screw 5. pivot pin rest 11. bolt 6. supporting unit 12. walkway with canopy
elements are gradually submerged in the shafts; the hydros
tatic thrust increases; perfect equilibrium is no longer
achieved.
The equilibrium is re-established under the action of the
compensation cylinders, which act like diving bells; each of
these cylinders is made of a 1.88 m diameter tube, opened in
its lower part and closed in its upper part (Fig. 6.1.9.).
The compensation cylinder is filled 'vith air when the
float is in its upper position. When the float comes down,
the increasing hydrostatic pressure entails a reduction of the
air volume in the compensation cylinder. The loss of thrust
is therefore balanced out by the loss of weight of the
bearing unit as this unit penetrates into water.
6.1.1.2.4. TJ1e tank
Loads
The volume of the tank when filled with 'vater is
5,000 t.; it is balanced by the thrust of the floats.
The dimensioning of the operating gear of the tank
incorporates a water plane variation of ± 10 cm.
Tractive effort on a bollard:
Side impact of a ship :
Bearing system
200kN
lOOkN
The bearing system is made of the longitudinal main
beams, the main cross-bars and the current bars (Fig.
6.1.10.). The side walls of the tank, which are submitted to
42
hydrostatic pressure and ship impacts, are in fact the main
beams.
With a view to increasing the torsion strength of the
tank, a continuous caisson is required in the longitudinal
axis, under the bottom of the tank.
The 2 main cross-bars, made of double caissons, are
located at the level of the floats; these cross-bars are each
fitted in their centre with a pivoting rest on which the tank
bears. The bolts of the endless screws 'vhich ensure the
operation and the safety of the tank are located at the end
of the main cross-bars.
Auxiliary Equipment
The side gang•.vays of the tank are protected against
bad weather by weather-boards.
The control house is located at the Northern end. Under
the gan15'vays, machine houses for the operation of gates and
sealing frames as well as compressors and other ancillary
machinery are to be found.
Guide rails
At the water level, sheet pile guide rails are attached
over the whole length of the tank.
Gates of the tank
The tank is closed at each of its ends by a sector gate
incorporating a compensation caisson. These gates are oper
ated on both ends, and, when open, enter into recesses,
obtained by deepening of the tank. They are then locked
into their final travelling position.
Protection of the gates against ship impact
Ship impact protection is provided on the inner face of
each gate. This protection, made of 3 sections, is attached to
elastic bearings. When in the closed position, the protection
is some 25 cm away from the gate itself. When lowering the
gate, the shock absorber beam retracts into the frame of the
gate.
Sealing frames
On each end of the tank, a U-shaped movable sealing
frame hangs freely from 7 points and is applied against the
fixed frame and bedded in the head of the corresponding
reach (Fig. 6.1.11.). The water between the gates (tank and
reach gates) is collected through a drainage system and
either released in the open at the level of the upper head or
pumped in the lower head and discharged into the lower
reach.
10
Fig. 6.1.11.
/ /
/
/ ;:<
z.''3 1 'a ~ID-. 3
..... I .~,,..." I I
2 : A '
Sealing system between tank and upper head 1. door of tank 2. sealing frame 3. suspension of frame 4. sealing system between tank and frame 5. primary watertight frame and upper canal 6. discharge of residual water between gates 7, hydraulic jack 8. discharge of water between gates 9. heating
10. upper head
6.1.1.2.5. Operating gear
Four operating towers are placed on both ends of the
tank in the axis of the main two cross-bars (Fig. 6.1.12. and
6.1.13.).
Each tower is made of two vertical metal boxes with
standing torsion connected on their rear part through a
stiffened metal plate and at their bases and tops by
transverse box girders.
The control mechanism of the tank includes 4 screws
(1 screw per guiding tower) going through 4 bolts attached
to the ends of the main cross-bars of the tank; each screw is
controlled by an electric motor placed on top of the guiding
tower. Synchronization is achieved •vi th synchronization
shafts placed on the bottom of the chamber of the tank.
Guiding is by rails attached to the towers (2 per tower)
and by rollers attached to the main cross-bars of the tank.
The bearing arrangement of a tower is as follows :
the lower transverse beam is equipped with 2 hinged
rests; one of those is designed for vertical as well as
horizontal forces parallel and perpendicular to the longitu
dinal axis of the tank; the other one takes in vertical
f :t:::::rt-il_
rit~2t1 : )---3 ' : I :
1 I : ' : l f I !
1 !
Fig. 6.1.12. Manoeuvring equipment - overall view 1. manoeuvring tower 7. bolt 2. tank 8. control engine 3. float 9. gear 4. supporting unit 10. synchronization shaft 5. main cross-bar 11. triple gear 6. worm screw 12. angle gear
loads and only horizontal loads that are perpendicular to
the longitudinal axis of the tank.
a third rest is located at a higher level and it withstands
only horizontal forces perpendicular to the longitudinal
axis of the tank.
The system is defined in static terms.
Each 20.02 m long screw is bedded in the recess
between the two boxes of the tower. The screw is of the
V-shaped three entries thread type.
The bearings of the scre\V on the lower and upper
transverse beams of the tower are hinged so as to eliminate
tractive stresses irrespective of the direction of the movement
of the tank.
A 110 kW electric motor placed in the operating cab on
top of the tower controls the rotation of the screw· and the
movement of the tank through the bolt attached to the
latter.
Irrespective of their control function in normal operation,
the screws transmit the following loads from the tank to the
towers:
the load differential between tank and floats during
normal operation;
the exceptional stress of 12,400 kN per screw in case of
emergency : emptying of the tank; full filling of a float;
the inertia stresses during acceleration or deceleration of
the tank as well as static loads.
43
""1{288>1!
~
-··-······ i ~ :;:
1
Fig. 6.1.13. Manoeuvring tower - Framework 1. torsion caisson 2. lower box girder 3. upper box girder 4. hinged rest 5. rest takes in the horizontal stresses 6. worm screw 7. control engine 8. reducer 9. bolt
1 O. main cross-bar of tank 11. guide rail 12. synchronization shaft
6 s
-~ _1_--;--- ----a-::-. - .
Fig. 6.1.14. Tank guiding system 1. tank 2. main upstream cross-bar 3. main downstrean cross-bar 4. rollers on fixed bearings 5. rollers on elastic bearings 6. manoeuvring tower
Horizontal stresses acting on the tank are transmitted to
the towers through rollers attached to the ends of the main
cross-bars of the tank which run on rails attached to the
towers (Fig. 6.1.14.).
To allow for both longitudinal and transverse guicl-.ing, a
roller is placed on a fixed bearing in front of a roller placed
44
on an elastic bearing, so as to avoid jamming. For trans-
verse guiding, there are
for longitudinal guiding,
the upstream cross·bar.
6.l.1.2.6. Upper head
rollers on the two main cross·bars;
such rollers are provided only on
The upstream end of the chamber of the tank ends with
a 12.75 m high reinforced concrete wall; laterally, this wall
supports two 12 m high reinforced concrete walls (Fig.
6.1.15). Wing \Valls are embedded on the one hand in the
two above·mentioned walls and on the other hand in the
section of the chamber.
The two walls sustain the metal frame of the closing
gate of the upper reach.
In order to adjust the equipment of the upper head to
the possible lowering of the water level in the upper reach
(§ 6.1.1.3), two piles made of 7 reinforced concrete beams
each are provided. The space between the piles is filled with
clay and covered with a layer of plaster.
The downstream pile is equipped with a steel plate
which serves as a support for the sealing frame of the tank.
The wing walls contain the piping system for collecting
the water from between the gates, the water being thereafter
discharged downstream through another piping system.
The gate of the upper reach is a current type of
vertical lift gate, balanced by counterweights and moving
between the frame legs. This type of gate was chosen
because it adjusts without substantial modification to the
lowering of the upper water level.
Skin plating of the gate is required on the downstream
side in order to limit the volume of water between the
gates. Two electrically powered pumps ensure the equali
zation of levels between the tank and the upper reach.
On the reach side, the gate is equipped with a shock
absorber beam in three sections.
6.1.1.2.7. Lower head (Fig. 6.1.16.)
The downstream end of the chamber is made of a
U-shaped concrete block including a floor with massive side
walls; these walls are equipped with bearings and operating
gears of the gate of the lower reach.
This gate is a one way operated overhead lowering
sector gate, the frame of which includes a compensation box.
For maintaining or repairing purposes, the gate may be
lifted over the \Yater level in the downstream reach. A shock
absorber protects the gate.
At the end of the gate chamber, a well collects the
water from between the gates, which is thereafter discharged
by pu~ping into the lower reach.
l '
I
I ~ ..,;:
"' I
i ; l
I ~ .,,; -I I !
1
10
2. · 1· . .• ·. '.· i . . ' + ·. ·'1-zaa.
' , . .... •;a
Fig. 6.1.16. Lower head 1. fioat shaft 2. floor of chamber 3. floor of head 4. wing wall 5. reach gate
Fig. 6.1.15.
q
4-
3
Upper head 1. fioat shaft 2. fioor of chamber 3. reinforced concrete wall 4. reinforced concrete beam piles 5. clay filling 6. back fill 7. sheet piling 8. wing wall 9. frame post
10. vertical lift gate 11. pumps 12. plate of tank sealing frame rest 13. discharge of water between gates 14. emergency sluices
\· 9 ·.o-+t+H+t+ ,, " ,, \\
:.:.:.: L: ...
-~-Jj I '
• -· qlO- ·-· _\-poi- .
6. recess for open gate 7. control room 8. pumps well for water between the gates 9. emergency sluices
10. cable duct
45
The lower head is equipped with an emergency sluice,
made of pipe needles, which rest on a floating horizontal
pipe.
6.1.1.2.8. De-icing devices
Electric heating of ice sensitive elements is provided in
such a way that ice formation does not interfere with
operation, even with short periods of. 20° C.
Heating of the jambs of the reach gates is achieved
using 40 kW heating resistors.
The sealing frames are heated by 4 kW heating
elements
5 to 10 kW flat heating cores bedded in a silicone resin
to heat the bearing surfaces of the gate sealing system.
Connections are provided for heating gears and other
equipments.
6.1.1.3. Control of operations
Operations are controlled from two cabs located at the
Northern end of the tank. The sequence of operations
proceeds automatically with the possibility to individually
and manually control operations in case of emergency.
The normal raising and lowering velocity of the tank is
0.15 mis. The inital acceleration and final deceleration times
of the tank are 15 s each. The total movement time is 1
min48 s.
In the case of an emergency stop, the deceleration
distance is 0.375 m.
The dimensioning of the gear allows normal operation
\vith a water plane variation in the tank of ± 10 cm with
respect to the normal depth of 3.0 m.
When greater variations of water level in one of the
reaches occur, two pumps with a rate of 0.5 m3/s bedded in
the operating frames of the gates and acting both ways are
automatically triggered. As soon as the water depth in the
tank is back to normal, operation of the tank may be
started again.
Each head is provided with a 30 kN capstan, intended
to facilitate entry of ships into the tank, which is itself
46
provided with- two 30 kN capstans, similarly facilitating
leaving of the tank.
Navigation lights, loudspeakers, telephone and lighting
equipments complement the main equipment.
6.1.2. STUDY AND EXECUTION PLANNING
Spring 1955
Spring 1958
Fall 1958
November 1958
Spring 1959
Summer 1962
August 1962
start of preparatory works
tendering
order to start
beginning of foundation work
mounting of metal structures began
completion of work
first operation
On the basis of the experience gained with the oper
ation of the former lift, which has been operated without
any malfunctioning for 65 years, no particular test was
required prior to operating the ne\v structure.
6.1.3. PROBLEMS ATION
MET DURING OPER-
In 1965, the bolts (§ 6.1.1.2.4 and 5) had to be replaced
after having been worn do\vn by 7 .5 mm after 36,000
movements, which was considered to be excessive.
From then on, tolerated variations of the water plane in
the tanks were reduced from ± 10 cm to ± 5 cm; it was
hoped that this would reduce the wear on the bolts, the
useful life of which \Vas anticipated to be 25 years.
Since 1973, the bolts with washer springs (§ 6.1.1.2.3)
which connect the bearing units of the tank and the tank
itself were replaced by stro~ger elements.
The lower float has a permanent left side twist which
was caused by an overload of the guiding rollers (§ 6.1.1.2.3).
The reason for this has not been found.
Rollers and their accessories have also been replaced by
stronger units.
With the exception of the above mentioned deficiencies,
the lift operates completely · satisfactorily and has been
trouble free.
6.2. The Liineburg lift
47
6.2. THE LUNEBURG LIFT
(Federal Republic of Germany)
6.2.1. DESCRIPTION AND DESIGN PRINCIPLES
6.2.1.1. General comments
6.2.I.l.l. Siting (Fig. 6.2.IJ
The side canal on the River Elbe connects the regulated
section of this waterway upstream of Hamburg to the
Mittellandkanal. It meets the international IV class stan
dards and it is open to 1,350 d.w.t. ships. Over its 115 km
length, there is a difference of level of 61 m, of which 38 m
are through the Li.ineburg lift and 23 m through the lock
with water saving chambers of Uelzen, two structures which
are 55 km apart.
Fig. 6.2.1. Lateral canal of the River Elbe
6.2.1.1.2. Prelintinary studies
14 projects were studied for the 38 m lift structure :
9 projects for water saving chamber locks, with differences
in terms of the number and the layout of the basins and
by the design of the lock chamber
3 incline projects, of which 2 are of the longitudinal type
and 1 of the transverse type
1 water slope project
1 vertical lift project (hvin funicular lifts).
The comparative study of projects resulted in selecting
the funicular lift.
6.2.1.1.3. Characteristics of the Liineburg lift'
There are two parallel although independent lifts (Figs.
6.2.2 and 6.2.3).
!\Iain dimensions :
Lift
Useful length of tank
Useful width of tank
Working \vater depth in the tank
Freeboard
Overap volume of tank filled with water
Axis to axis distance behveen two tanks
Overall width of lifts
Overall length (excluding outer harbours)
Duration of tank movement
l\Inin structures
Each of the two lifts comprises :
38m
100 m ,m
.s.oO ,
0 Jm
0,700 t
35m
66m
116 m
3min
a reinforced concrete chamber for receiving the tank in
the lower position and protecting it against underground
water
4 towers supporting the weight of the tank and of the
counterweight and ensuring guiding and safety of the
tank
1 tank with its sealing frames and gates
2 supporting frames for the tank and for the operating
gears that incorporate the fittings of the counterweights
224 pulleys for the counterweight cables
49
Fig. 6.2.2. Lilneburg ship lift
Fig. 6.2.3. Lay.out 1. tank 5. canal bridge 2. cradle 6. upper head 3. shock absorber 7. lower head 4. counter~weight tower 8. pumping station
50
- 4 operating and guiding rails attached to the towers
- the safety gear made out of 4 worm screws retaining the
tank in case of counterweight malfunctioning or accidental
emptying
- the upper head with an access canal bridge and a vertical
lift gate
- the lower head, with a movable shield allowing it to be
adjusted to conform with water depth variations and a
vertical lift gate.
6.2.1.2. Basic arrangement
6.2.1.2.1. Tanks
Loads
The overall weight of the tank filled with water is
5,700 t; this is completely balanced by counterweights.
2 -'--·. 3 4
Water depth variations in the tank of ± 10 cm as
compared to the normal depth are accepted.
Mooring pull on a bollard 200 kN
Side impact of a ship 100 kN
Structure (Fig. 6.2.4)
The structural design is as follows: the floor is taken as
lower foundation slab, side walls as webs and upper gang
ways as upper slabs.
Torsional strength is provided by two longitudinal boxes
located under the tank floor.
Equipment
The side walls of the tank, each equipped with 5
bollards, are protected by 2 guide rails at water leveL
10
a~
0 9 0 0
·----12.oom--------------+-
Fig. 6.2.4. Cross section of tank 1. upper gangway 6. bollard 2. lower gangway 7. trolley 3. torsion caisson 8. bearing of tank 4. wear out plate 9. cradle 5. guide rail 10. counter-weight cable
51
Supporting cradles
The tank rests on two cradles through 4 bearings (Fig.
6.2.5) per cradle.
5 4 3 5 4
\ \ :A ..... ·'jA :A :A
. --CIO!f.~--·· -- . -- . -- . ~.: •. ! B '9~~~~ :A
Fig. 6.2.5. Tank supports and guides A support movable in all directions B support to take in transverse stresses C support to take in longitudinal stresses
1. upper reach 2. lower reach 3. tank 4. cradle 5. guides
Two of the 8 bearings take transverse stresses; the 6
remaining ones are movable supports.
An additional support of the upper cradle takes
longitudinal stresses.
The ends of the cradles have extensions to which
counterweight cables are attached.
The tank operating controls are fitted in the middle
section of the cradles.
3
Fig. 6.2.6. Sealing between gates 1. canal gate 2. tank door 3. caisson collecting the water from between the gates 4. sealing frame
a: pulled in; b : pushed out 5. tank 6. sealing sliding plate 7. outer seal between gates 8. sealing gates 9. lower part sealing of canal gate
10. lower part sealing of tank door 11. primary sealing between sealing frame and tank 12. secondary sealing between sealing frame and tank
52
\Vatertightncss of the butt ends of the tank (Fig. 6.2.6)
The ends of each tank are equipped with U-shaped
telescopic sealing frames. These frames also accommodate the
tank doors.
The frames are operated through two horizontal jacks
and pressed against the sealing rubber linings attached to
the corresponding head. The bearing surfaces are treated
against corrosion .
The frames displacement is 25
their final travelling position.
cm; they are locked in
The frame-tank tightness is ensured by a flat rubber
joint. An additional joint (of the keynote type) provides for
the tank-frame tightness when the frame is pushed against
the tank.
Three reversible pumps, intended to ensure the water
level regulation in the tank, are provided in the lo\ver part
of each sealing frame.
Tank gates
The gates are of the vertical lift type with a skin
plating on the outside. Guiding rollers run on rails attached
to the side walls of the sealing frames.
Each gate is protected against ship impact by a cable
stretched across the tank 3 m from the gate and 1 m
above water level. These cables pass over pulleys and are
wound round braking cylinders which are able to absorb
250 kJ.
The gates and the ship impact shock protection devices
are not equipped with any specific lifting mechanism; they
are operated simultaneously with the canal gates, as the
latter drive the tank gates through a system of hooks and
lifting lugs.
6.2.1.2.2. Towers
Each tank is guided between 4 reinforced concrete
towers (Fig. 6.2.8). The towers are connected hvo by two on
top of the tank, by a reinforced concrete gangway (Fig.
6.2.7).
Each tower comprises two counterweight chambers and a
central core; the core of one of the towers houses a
staircase; the core of the corresponding tower, on the other
side of the tank, houses a lift.
The four to\vers take in the overall mass of the tank
filled with water and of the counterweight, that is about
12,000 t. This load is transmitted over to the cable pulleys
and, thereafter, to the tower through the supporting frames.
6.2.1.2.3. Counlerweights
Each gate is compensated by 224 counterweights of 26.5
t each. A counterweight is made of a heavy 6.80 m x 3.40
m x 0.32 m concrete block; the specific mass of 3.56t/m3 is
reached by adding magnetite to the aggregate. The equili.
brium is adjusted by regulating weights.
54 mm diameter steel cables passing over 3.40 m
diameter (i.e. 63 times the cable diameter) pulleys connect
the counterweights and the supporting cradles of the tanks.
These pulleys rest on a frame that transmits loads to the
'\Valls of the tower (Fig. 6.2.7).
If a cable breaks, its load is transferred to neighbouring
cables through an appropriate frame.
3 3
D
,, D
Fig. 6.2. 7. Cross-section of Ziff 1. tank 2. cradle 3. worm screw 4. rack 5. cable pulley 6. counter-weight cable 7. counter-weight
Chains compensate the specific weight of each cable in
the various positions of the tank; chains and cables make up
a loop.
Stiffeners are placed on the side of the counterweights
to make it possible to adjust the length of the cables if
differential extensions occur.
6.2.1.2.4. Operation of the tanks
Each supporting cradle has two controlling units to
enable the tank to be balanced taking into account stresses
110
I I I I I I I I I I I I I
sf9,00
~-------- I ------ -- - -r 31,36
-1
8. setting counter-weight 9. frame for interlocking counter-weights
10. cable balancing chain 11. chain Pulley 12. connecting gallery 13. staircase 14. lift housing
53
resulting from inertia, friction and variations of ± 10 cm in
the water level in the tank (Fig. 6.2.3).
For each control unit, a 160 kW electric motor starts a
pinion which meshes with a rack attached to the tower.
This pinion is capable of a 500 kN tangential load both
ways.
It is mounted in a swinging tank and is pressed against
the rack by a hydro·pneumatic spring. When the 500 kN
load is exceeded, an automatic emergency stop is activated:
The squirrel tank rotor engines are supplied with
variable frequency and tension three.phase Current and make
it possible to regulate continuously the velocity both when
starting and when slowing down the tank. The motor to
pinion transmission is achieved through a three steps gear
and cardan shaft speed.controller. The connection between the
engine and the transmission is ensured by an elastic
coupling, the part of which located on the transmission side
is equipped with a double expanding brake. This
arrangement ensures both movement and braking.
This mechanism provides a total lifting capacity of 2
MN; the resulting maximum velocity of the tank is 0.24
mis. They operate both as engines and as generators.
A synchronization mechanism located under the tank
connects the four controlling units.
6.2.1.2.5. Guiding of the tank (Fig. 6.2.5)
The tank is guided in four positions located at the
centre of the longitudinal beams of the supporting cradles.
As far as the transverse guiding is concerned, rollers
located on both sides of the driving pinion and mounted on
the same axis ensure an adequate meshing of the pinion
with the rack while they take over the tank transverse
guiding stresses.
These rollers run on guide rails located around and
beyond the racks.
Longitudiniil guiding is by pairs of rollers attached to
the cradles which run on the above mentioned guide rails.
Longitudinal stresses are exclusively transmitted to the
C-fixed support (Fig. 6.2.5) of the upper cradle. The rollers of
the lower cradle guide the cradle itself and are only subject
to the horizontal stresses due to friction of the supports.
A primary longitudinal stress occurs when the tank
nears the end of its travel and when the communication
between reach and tank is established. This is due to
hydro.static pressure.
Fig. 6.2.8. Tank operation· perspectiue 1. counter·weight tower 2. tank 3. cradle 4. winch 5. worm screw 6. rack 7. synchronization
54
6.2.1.2.6. Safety
Compensation between the tank filled with water and
the counterweight is lost in the following instances :
emptying the tank due to lack of watertightness causing
an additional upward load;
excessive water load in the tank as compared to normal
conditions; downward additional load;
lack of tightness of the chamber which fills with water;
upward additional load when tank is in the lower
position.
The ensuing additional loads are taken over by a safet?'
device independent from the operation gear described under §
6.2.1.2.4, which is capable of retaining the tank. This device
makes it possible to bring the tank to a standstill at any
level.
It consists of 4 \vorm screws with small threads located
in the vicinity of the racks (Fig. 6.2.7 and 6.2.8.); four bolts
on these screws are attached to the bearing cradles of the
tanks and they rotate synchronically with the operating gear.
Normally, these bolts have a 30 mm clearance \vith respect
to the screws.
In the above mentioned cases of loss of balance between
tank and counterweights, the operating weight is over
stressed. The operating pinions yield automatically; the tank
is driven in the overload direction; bolts then are pressed
against the sides of the screws.
The screws are attached to the top and the toe of each
tower, so that they undergo only tensile stresses, thus
avoiding the danger of buckling.
6.2.1.2.7. Upper head (Fig. 6.2.3 and 6.2.9J
The outer harbour of the upper reach is connected to
each lift through a canal bridge. Each canal bridge rests on
the land side on a high pile founded concrete abutment and
on the lift side on a pendulum bent \Vith a 6 m overhang.
Each canal bridge ends with a guiding frame of the
upper gate. This gate is made of hvo side towers and in its
lower part of a cross-bar made of a double horizontal box;
the upper box serves as cable gallery; the lower box collects
the water from between the gates, from where they are
pumped a\vay into the upper reach.
The sealing devices between the canal and the sealing
frame of the tank are attached to the front plates of the
guiding frame.
The upper reach gates are vertical lift gates, with a
skin plating on the tank side so as to limit the volume of
water between the gates. As the plating of the upper gate of
the tanks is located on the reach side (§ 6.2.1.2.1), the
volume of water between the gates is limited to 3 m3 only.
The sealing device behveen the reach gate and the guiding
frame i~ similar to that of the tank gate.
=+-- .• ~:4.50,'. .• - - --
-----~- i
I 9
um:;!l;;;;:;;I ;;;;rr
p
3
_____:Jt 57,91
5
4 i i ..1_+38,50
__ _._l ___ ._-·_ .. _l~--,~T'"'- 2a ;b 1}3 M I
------:~ 6.00 2
!1°·55 3.92 _j ---- 36,50
Fig. 6.2.9. Upper head 1. post of guiding frame 2. strut of guiding frame 2a. cable gallery 2b.. between gates water reservoir 3. reach gate 4. tank door 5. tank 6. sealing frame 7. shock absorber of tank door 8. shock absorber of reach gate 9. canal bridge
10. fastening of pendular rest
The sealing devices and the water collection box bet
\Veen the gates are electrically heated during frost periods.
An air bubble barrier was also installed.
The control gear of the reach gate, the movement of
which also moves the tank gates, are located in cabs on the
front of the towers. Gates are compensated with counter·
weights.
The reach gate is protected against upstream going ship
impacts through a system which is similar to that of the
tank gate.
The braking cylinders and the pulleys are placed in
box-type tipping arms which are located in ad hoc recesses
provided in the side faces of the canal bridge. When the
connection between the canal bridge and the tank is esta
blished, the cable and the arms are raised. The level of the
cable may be set as a function of the variations of the
water plane in the upper reach.
55
Fig. 6.2.10. Swinging shock absorber of canal gate -1 MJ absorption capacity
6.2.1.2.8 Lower head
The lower reach joins the River Elbe, \Vhich entails a
possible variation of the lower reach water depth of 4 m.
The upper head includes a movable shield which adjusts to
such water depth variations.
This shield is made of 22 m high side towers and of a
5.28 m inner transverse retaining wall (Fig. 6.2.11).
As with the upper head, the towers ensure the guiding
of a vertical lift gate; the operating gear is located in cabs
placed on the front of the towers.
During its movement, the reach gate takes with it the
tank gate and the shock absorber.
The shield is made of a 20 mm thick plating stiffened
by 3 horizontal main beams connected by vertical needles.
The gate rests on the upper main beam of the shield.
The shield itself rests on the masonry of the lower head
through a rubber fitted tightness frame. The shield is coated
with an epoxy-tar layer intended to reduce friction during
translations.
The arrangement between the gates of the tank and of
the canal is similar to those of the upper head. Water
between the gates is collected into a sump and pumped into
the lower reach.
The three main beams of the shield transfer hydro-static
stresses to the masonry of the lo\ver head through two
vertical bearer-beams and five pairs of rollers per bearer
beam which run on rails embedded in the masonry. Spring
rollers ensure counter-guiding as well as side guiding of the
shield.
The shield including the two to\vers is operated by two
plunger-type hydraulic rams \Vhich make it possible to adjust
it to the lower reach water depth.
With a view to relieving the operating jacks when at
rest, the shield rests on two hydraulically operated jacks legs
which bear on racks embedded in the masonry.
As a safety measure, the operation of the shield may be
carried out with one single jack.
56
;:'g,;:::::~(~=~
f~"~·
·+9.00
rrrrrn I
5
•-1,60
•-7,30 =---
•+9.40 -=
.+4,80
Fig. 6.2.11. Lower head
(_~:;p::::::::::~:.-
2 -~ :
t+13,30 -----"'
[
A. Position for apron for+ 4.00 downstream water level B. Position for apron for + 8.00 downstream water level 1. apron 2. apron post 3. rea'ch gate 4. tank door 5. tank 6. sealing frame 7. shock absorber
6.2.1.2.9. Ice protection
In freezing conditions, the metal sealing elements as
well as the caissons receiving the water between the gates
are electrically heated.
The heating proceeds simultaneously through heating
plates attached to the back of the sealing elements and
through oil filled pipes provided with heating cores.
In addition, in the vicinity of the gates of the upper
canal, an air bubble barrier delays ice formation. For that
purpose, a compressor injects compressed air from a conduit
located on the floor of the canal bridge.
6.2.1.3. Operation
The two lifts are operated from a single cab.
Three modes are possible :
automatic: after mooring the ships in the tank, one
single command starts the full sequence of operations;
semi-automatic: the distinct operations are conducted sepa·
rately; sequential lockings (intended to avoid any malfunc
tioning) remain;
local: for maintaining and repairing purposes, local con·
trol stations are provided in the main machinery houses;
this makes it possible to vie\v the moving element when
it is ordered to move.
The sequence of operations is displayed on a block
diagram at the main control station.
Traffic organization is made easier by a TV and
loudspeaker nehvork in the outer harbour and on the tanks.
An intercom provides communication between the central
station and the several parts of the lift.
The maximum speed of the tank is 0.24 mis; the
average speed is 0.21 mis and the corresponding cycle is 3
min.
Acceleration and deceleration is about 0.012 mls2.
For a single ship, the lockage time is about 15 min.
6.2.2. PLANNING AND CONSTRUCTION TESTS BEFORE OPERATION
September 14,1965
September 1967
July 30;1969
October 1969
November 12,1975
November 17,1975
December 5,1975
decision to build the River Elbe by-pass
canal
opening of tenders for the construction
of the .Luneburg water fall lift
decision to build a lift
\Vork started
construction completed
acceptance of the \vork after five tests
first operation.
Navigation on the lateral canal of the River Elbe was
first authorized from the River Elbe up to the upstream side
of the new lift (Fig. 6.2.1.), six months before the official
first operation of the \vhole canal (including the Uelzen lock).
Before the first operation of this lock, the water plane
upstream of Lilneburg was dammed by a transverse dike.
' In these circumstances, the effect of waves caused by
the emptying of the lock on the water level of the open
tanks upstream could not be studied. As the upstream outer
harbour of Li.ineburg was· already under water, the test
programme, which it had been anticipated in the contract
\vould take three months, had to be reduced to five days.
This test programme consisted in simulating exceptional
operations or catastrophic circumstances.
The operational tests, including measurements on civil
engineering work and the watertightness tests were carried
out on already completed parts as \Vork went on.
For the above-mentioned reasons, weaknesses of the
structure could only be identified and repaired after bringing
into service the whole of the side canal including the Uelzen
lock.
Experience has demonstrated that the test programme
should be conducted in rational operational conditions, parti·
cularly in so far as observations follo\ving variations in
outside temperatures are concerned. A three month period is
too short, particularly if deficiences and weaknesses are to
be detected.
6.2.3. PROBLEMS ARISING DURING OPERATION
On the basis of the experience gained with the oper
ation of existing lifts, the design of the Li.ineburg lift tanks
had taken into account the existence of positive or negative
surges of ± 10 cm amplitude as a normal operational
condition.
After servicing the lift, it was found that, when one of
the tanks was in its upper position with its upper gate
open, positive surges of several decimeters amplitude occur
as a consequence of the emptying of the Uelzen lock, some
45 km upstream of Li.ineburg.
Actual stresses were thus higher than anticipated. As
early as 1969, both infrastructure and equipment had to be
modified and strengthened accordingly.
Four additional clamping devices have been mounted on
the tank bearing cradles; after the tanks come to a stop,
they immediately transfer the load differences to the
screws, thus relieving the operating gear and the racks.
The additional devices have been incorporated into the
automatic control.
The level gauges which were installed on the tanks
produced two readings along a diagonal; the average was
not reliable, wich resulted in an instability of the electric
convertors of the operating gear. T\vo additional level
gauges have been installed so as to obtain four level
readings and a reliable average between them, which
makes it possible to stabilize the regulation of the
convertors.
Initially, the convertors could operate both as engines and
as generators. To increase stability, they are nowadays
only used as engines (2 cm water overload when rising, 2
cm release when descending).
Brakes which are a crucial part of the driving
mechanism - have been equipped with constraint gauges
intended to distribute and synchronize the braking of the
four mechanisms of the tank in case of an emergency
stop.
By measuring the stresses in the levers of the brake
shoes, it is possible to set them so as to achieve braking
synchronization. Adequately distributed braking avoids, in
case of an emergency stop, deformation of the tanks and
overstressing the driving system.
On the meshing between the rack and the tank driving
pinion, the bearing distance of the teeth appeared to be
deficient in spite of the fact that the pinion rest was
mounted on a pivot pin, By introducing high strength
steel pinions and spherically rectifying the teeth of the
57
58
pinion in contact with the teeth of the rack, the
transverse distribution of the load could be optimized.
With a view to further improving the meshing conditions,
direct greasing of the edges of the teeth has been
introduced.
In case of malfunctioning, reasons should be looked for
beyond mere repairing; to that effect, a real time and
reliable recorder of operation data was installed. It was
then possible to trace exactly the causes and to detect
possible damages in good time.
The HALON fire protection installation in the machinery
houses and the central control station proved to be
efficient during a fire in one of these rooms. Damage
could be limited to the core of the fire and normal
operation resumed after only a few hours.
Ship impact protection devices at the upper head and at
the ends of the tanks have been tested; the design
assumptions have been confirmed. In the tanks, these
devices are not necessarily triggered into action for each
arriving ship, but when they do operate, they avoid
damage to the tank gates.
The ground thrusts have been measured since 1972
against one 'vall of one of the two chambers. This has
demonstrated an increase from 0.5 to 1.1 of the thrust
index K.
The advantage of having two independent tanks one of
which is permanently serviceable was clearly demonstrated
both for breakdown conditions and for maintenance pur
poses.
6.3. The Strepy-Thieu lift
. - . -.:.:..-:· .
. ... · .--- ... ··
__
.~
59
6.3. THE STREPY-THIEU LIFT
(Belgium)
6.3.1. DESCRIPTION AND DESIGN PRINCIPLES
6.3.1.1. General characteristics
When planning the Centre canal between La Louviere
and Mons (Figs. 6.3.L and 6.3.2.) to take 1,350 t ships, the
problem 'vas to construct a lift of the order of 73 m to
replace four hydraulic lifts (Chapter 3) and two 300 t ship
locks.
The following solutions were compared both from the
technical and the economic points of view:
- two twin lifts with a 36.50 m lift each
one t\vin lift 'vith a 73 m lift
a longitudinal incline with 5 o/o slope
a longitudinal incline with 10 % slope
a water slope with a slope of 3.5%.
If, in terms of economics, the most favourable solution
overall is the twin lift of 73 m, the advantage is even more
pronounced as far as the electro-mechanical equipment is
concerned.
The following table compares the investment and oper
ation costs discounted over a period of 30 years, the
operating capacity and the energy required to conduct one
movement with each solution.
Invest. operating energy Type of
& oper. capacity required structure
costs% kW kWh
73 m lift 100 2000 50 Incline, 10 o/o 135 2000 140 Incline, 5 % 145 1600 220
Water slope 150 8200 1400 Two 36 m lifs 190 4000 50
Complex of 3 locks - 15600 11700
The last solution, the complex of 3 locks, is mentioned
only to demonstrate the importance of the operating capacity
and of the energy required.
The locks considered were without water saving cham
bers. The latter would have entailed a capacity and energy
reduction of the order of 60 %. Ho\vever, the possibility of
totally compensating the economy thus realized in terms of
pumping costs by the cost of constructing these chambers
should be duly considered.
The solution which was chosen was that of tlie double
73 m lift in one step.
The final design characteristics of the structure are as
follows:
- lift
Dimensions of each of the two tanks
- useful length
- useful width
\Vater depth
total mass of tank including water
working speed of lift
total duration of lift
6.3.1.2. Basic principles
6.3.1.2.1. TJ1e lanks
The tank is made up of (Fig. 6.3.3.) :
73m
112 m
12m
3.35 m to 4.15 m
7 ,200 t to 8,400 t
0.20 mis
?min.
longitudinal caissons forming the walls of the tank
a stiffened floor
cross-beams connecting the two caissons under the tank
floor.
Gates are vertical lift gates simply made of a frame
resting on three sides and composed of a plating stiffened by
a frame and vertical beams.
The tanks are equipped with guides, bollards, buffers,
gangways, guiding devices, clamping devices and other fit
tings necessary for their proper operation.
6.3.1.2.2. Tank operation
With a view to reducing working stresses, the mass of
each gate is compensated. This compensation in the case of
a 73 m travelling lift can only be obtained through another
mass to which the tank is connected by metal cables. This
mass may be another tank or a counter\veight.
61
-=
Present canal New canal Canal bridge 10
----Former liftsr,2 ,3,4 Existing locks5'5,7~ New lift 9
Fig. 6. 3.1. Centre Canal between Obourg and La Louviere
Comparison of long itudinel sections
r--' 1 Section of Centre canal for 300 t vessels I 1.---' 2 Section of Centie canal for 1.300 t vessels
I
3 Havre IOLk
4 Obouro lock
_1~~~--...'.3800,l __ J
_1 '=I ~I
I I _ _J
l inn'' 2
lift n·• 3
Lock n• 2 Lifl n·' 4
Mons Lock n·' I
Fig. 6.3.2.
The balancing of one tank by another was not adopted
for the following reasons :
- the vertical distance between
constant, which requires a
mechanism
62
the tanks must remain
cable length adjusting
- the ro.u.te of the connecting cables is complicated, which
unfavourably impacts on the useful life of the cables
- finally and above all, the operation of one tank automati
cally entails the operation of the other one.
Fig. 6.3.3. Cross-section of a tank 1. Longitudinal caisson 2. Bottom of tank 3. Cross beam
As a result, the balancing mass is provided by a
counterweight (Figs. 6.3.4. and 6.3.5.),
One tank is supported by 144 cables with a diameter of
85mm:
112 suspension cables
32 control cables.
Suspension cables are distributed into 8 groups of 14
cables and each group is connected to a 800 t counterweight.
Each suspension cable is directly fitted to its counter,veight,
moves on a pulley and continues toward the tank, to which
it is connected by a stiffener and an oil-hydraulic jack.
Control cables (Figs. 6.3.6. and 6.3. 7 .) are distributed
into 8 groups of 4 cables and each group is connected to a
180 t counterweight. The control cables are connected to
their counterweight through stiffeners and spreader bars, the
latter also ensuring the equal distribution of load between
the cables. They then reach two driving pulleys to which
they are attached and extend in the direction of the tank, to
which they are coupled by means of a stiffener and of an
oil-hydraulic jack.
The 14 jacks of the counterweight suspension cables are
inter-connected so as to equalize tensile stress in the cables.
During operation, these jacks are normally isolated.
When the tank is stopped downstream and clamped to its
supports, the 32 jacks of the control cables are inter
connected. This inter-connection ensures that the tank keeps
in a horizontal plane during operation.
During movement, the control cable jacks are inter
connected in groups of 8 (2 x 4), each group corresponding to
a quarter section of the tank. This inter·connection results in
equal loads in the cables and driving torques in the pulleys.
The two pulleys of a control cable group are located on
both sides of a "reduced speed" controller to which they are
coupled.
The 8 "reduced speed" controllers of one lifting
mechanism are connected to a synchronization shaft which
constitutes a closed loop. 4 "high speed" controllers are
incorporated in the synchronization shaft they pull (Fig.
6.3.6.).
Each "high speed" controller is powered by a 500 kW
electric motor.
Normal braking of a tank proceeds through the electric
motors. In case of incident, disk brakes on the "high speed"
controllers take over, Finally, safety brakes made of expand
ing brakes on each of the pulleys maintain the tank in its
stopping position. They may, in absolute emergency con
ditions, be operated during the movement of the tank. In
addition, these safety brakes are capable of bringing to a
stop a tank which had lost a depth of water of 1.80 m
(2,700t).
The moving tank, the mass of water, the counterweight,
the suspension and operating cables, the lifting mechanism,
the driving electric motors and the supply make up a system
which is likely to oscillate. The mathematical analysis of the
63
4
w I I
3
' 7600m
14150
I !~~. I I w I~ I I
I I I I
t I I I I
: I I !~I I I
I
Fig. 6.3.4. Cross-section of the lift 1. Chamber 2. Central tower 3. Steel columns
13115
I a I I I
I I
4. Machine room 5. Tank
5000
6. Counter-weight
behaviour of the system and the computer simulation of its
operation have demonstrated the absolute reliability of the
solutions adopted.
Next to the main suspension and lifting - gear, other
equipment is necessary for ensuring passage of navigation,
operation and maintenance of the lift.
Among them, we shall mention :
the guiding devices
the reach-tank sealing devices
- the reach-tank communication gate operation mechanism
and their protection against boat impact
the end of travel position clamping of the tank.
6.3.1.2.3. Guiding the taul{s
Two rails attached to the central tower (Fig. 6.3.4.) act
as guides: one rail toward the upstream end of the tank and
one at its downstream end. These rails ensure both the
transverse and the longitudinal guiding of the tank. Spring
mounted guide rollers are attached to the tank.
64
2130 m
131,16 rn
~
@
50.30 m
@
Fig. 6.3.5. Diagrammatic elevation 1. Cables 2. Control of counter~weight 3. Tank 4. Drums
At the end of the tank movement, the longitudinal
guiding of the tank is taken over by devices connected to
the reaches. These devices are designed to \Vithstand the
hydrostatic thrust resulting from initiating communication
between reach and tank as well as the dynamic stresses
generated by the penetration and the possible impact of a
ship against the gate at the opposite end.
The reach.tank sealing device includes a rubber fitting
filled with compressed air which is pressed against the tank
head with a sufficient thrust to ensure watertightness.
6.3.1.2.4. Gate operation
The vertical lift reach·communication gates are equipped
\Vith a preliminary separation device.
This device is operated when opening gates as filling of
the space between the gates and equalization of water levels
in the tank and the reach are achieved through first
bringing the gates away from their seating and then slightly
lifting them. Upstream of the lift, the reach gate is
duplicated by a guard gate as a safety measure.
l
JOl!!!O
r I Ii ,Fig. 6.3.6. Winches
1. Tank 2. Winches 3. Drum
I ' J,
"
(j) I
lQG@
6.3.1.2.5. Clamping of tanks
Steadying the tank in its end of travel position is not
an easy problem. Downstream, the tank should be steadied
by a structure capable of maintaining it at rest \vhen empty.
Operations that require the emptying of the tank (control,
maintenance, repair) are indeed unavoidable. This entails
compensating for the weight of a \Vater mass of about 6,000
t at four points, two of which are located under each side of
the tank. In this way, given the considerable stiffness of the
main beams which make up the sides and the transverse
flexibility of the tank, equal distribution of the weight on
the four supports is, in practice, certain.
Each connection consists of a bolt attached to the floor
and a fitting on the tank. Each bolt is designed to take in
a 16,000 kN force.
Upstream, the tank rests on 4 bearings which may
exceptionally be required to sustain a lack of balance equal
to the weight of the water mass (accidental emptying). In
normal conditions, the tank rests on 4 bearings with a force
such that, when it is filled to its maximum level, it adheres
to the bearing. Ho,vever, this weight should be equally
distributed between the bearings if overload of one part of
the structure is to be avoided. This is achieved by equipping
each bearing with a short stroke jack and by inter
connecting the 4 bearing jacks.
4. Mechanical synchronization device
6.3.7.1 Plan
I. Upstream lay-by 2. Oo.wnstrcan1 lay-by 3. Cunul bridges 4. Lirts
6.3.7.2 Longitudiuul sectloo
Fig. 6.3.7.
65
If the stress exerted on the jacks exceeds the normal
prestress (in case of accidental emptying), safety valves
protect the jacks. These jacks withdraw until the tank has
reached its fixed bearings.
6.3.1.2.6. Electrical equipment
The electrical equipment naturally matches the mechani
cal installation. Although less spectacular than the latter, it
is just as vital.
Electric power supply is from 3 HV cabins, which are
organized in a loop and are themselves supplied by the
distributor nehvork or by the emergency set. Electric
current is first transformed and then supplied to the
different places where it is required.
The movement of the tank is through 4 electric motors.
Normally, operations are possible with three motors, while it
should be possible to complete an operation with even two
motors unserviceable. An electronic regulation system controls
the supply to the motors to obtain the required movement.
The electric equipment comprises many auxiliary units:
supply, control and locking of all the mechanical
equipment
lighting of the structure
navigation lights
electric equipment of the premises
cabling
- telecommunication, telephone and closed circuit TV
network.
Also included is a processor grouping all the controls,
readings and lights, detecting incidents and their causes, and
announcing the surveying and the maintenance works which
have to be performed to maintain the structure in proper
operation condition.
All measures are taken to ensure safety of operation
and reliability of the plant both with electrical and mechani
cal equipment.
6.3.1.2.7. Infrastructure
Overall review of the works
The Striipy lift is part of a series of works including
from upstream to downstream (Fig. 6.3.7.):
a 800 m long canal on a bank. Safety devices make it
possible to isolate this section immediately in case of the
failure of the embankment.
- the 200 m upstream lay-by
66
two canal bridges connecting this upstream lay-by to the
two lift tanks
the lift itself
the 200 m downstream lay-by
a downstream canal section in cut
the reorganization of the road network and the water
discharge arrangement.
Geology of the location
An extensive site investigation was undertaken, includ
ing sinking, borings and taking penetration and pressure
tests. This was complemented by numerous laboratory tests.
Results made it possible to determine the bearing capacity of
the grt?und, its deformability, the stability of backfill and the
possibility to use it for backfills.
The investigation demonstrated the following strata to
exist starting from the surface (Fig. 6.3.8.):
- top soil consisting of a sandy loam
a layer of flint
a thick and relatively impermeable layer of gault consist
ing of fine sand, sand with some clay or very sandy
loam, with a penetration strength of one thousand to
several thousand kN/cm2
at the level of the foundations, a thick and permeable
layer of coarse sand (Wealden), with a penetration
strength of several thousands of kN/cm2
a carboniferous layer, mainly shale and relatively imper
meable ground.
Layers of impervious and sem1-1mpervious clay have
been found between the gault and the Wealden beds as well
as in the latter.
During the investigations the first aquifer was detected
in the gault at a depth of about 66.00 m and a second
aquifer (piezometric level 2 to 3 m above the gault) in the
Wealden strata.
As the groundwater was to be lowered to a depth of
about 34 m during the construction.8.nd to 49 m permanen
tly, pumping trials were carried out.
The results of the trials were used for the study of how
the water level could be lowered and the ground water
levels maintained.
Observations made so far have confirmed forecasts resul
ting from the studies.
The structures are located in a seismic area ranging up
to grade VII on the Mercalli scale.
The stability of the structures is checked for soil
movement, characterized by a maximum 0.15g acceleration
and displacements of 5 to - 5 cm,
Liquefaction risks of the ground have also been esti
mated but appeared to be negligible.
Seismic tests have already been conducted with a view
to determining the dynamic characteristics of the ground
that sI?-ould be introduced in the mathematical models.
~
~-----~-----~"""'-
I I I ,. I ... I
UMOH ~..:::.· :.::--···· • • ·----- -- liliitWiil _____ - - - ·e!J- - - ---- -1----- · ·· r - · 7·=-~:::~==-=-1~-:--~-~~:-~-3,_~-~.:~-,.~-~-~-~-;-~-;;;:-;~~;::;;~~~~;;;;;-;i!jli;;;--~
Q)UQif~~~~-~~~:~--~~~:~~~~==~::::=~~~i.:~.:::. -~---: ::~~~ ~ ---· 1---=:-::=.:::::~~~-=~--~--:=---.::;~!.~ - -1·F----1~1----~-ill!· ~-~-~ ~~~~-~~~~~-~,~----
~7_1 >ii.{~ :-:W!.~ ~--- ~ ~-~"i~~,j_~~,~~ - -/ ....................................... . ·········~K Llf. l!•ITV<lll ~l& '!\Ai~
~BlE AlBIEN ·,_
'· ···-·--··- ···-··-····-· ....................... ····-···············-····- . -i>'-::~w;;·;~.'.'.~--~--;:---1 1---;Utr!~-·~ 11!1 I ·---------------COUCIE SEMI~!!~~~~~-----· UUQI L-----------·-------------· SABt.E WEALOIEN H'ERIEl.R
COUCHE IMf'ERMfABlE ET ~lER
l"-1
11.DOI yll-
Fig. 6.3.8. Geological strata Legends: limon = silt argile = clay silex = flint sable= sand
l' -
couche impermeable = watertight layer couche semi-impermeable = semi-watertight layer couche houiller = carboniferous layer terrain naturel = natural ground niueau piezo ... rabattement = pressure leuel in wealden pumping niueau de la nappe ... = leuel of water table in the gault before pumping courbe de rabattement = water gradient
! i1
Civil engineering
A few dimensions give an idea of the size of the
structure (Fig. 6.3.4.):
length
width
total height
130 m
81m
117 m
Structures should have a sufficient rigidity to withstand
stresses without excessive deformation or displacement which
might endanger their stability and proper operation.
The structure to be designed should not be sensitive to
thermal deformations.
The idea of two coupled structures was rapidly substi
tuted by the concept of a single structure with a single floor
and a single machine house but including two independent
tanks with their own operating gear (Figs. 6.3.4. and 6.3.9.).
The structure includes, ranked according to their impor·
tance and starting \Vith the foundations :
a reinforced concrete watertight monolith chamber
a reinforced concrete central tower
outer steel columns
a machine house supported by the central tower and the
outer columns.
)t, 11--+.--,! ··•·· ..
With a mass of about 300,000 t, the chamber and the
central tower withstand uplifts and the floor remains any
where in touch \Vith the ground both after and during
construction.
In addition, to make the structure practically insensitive
to soil settlement and to loads and deformations caused by
thermal variations, the hyper-staticity level is very lo\v. The
bottom and the ceiling of the machine house are made of
three hinged parts foliowing the longitudinal joints. The steel
columns have two hinges and the travelling bridge cranes
located in the machine rooms are isostatic.
The machine house has rooms for the staff, control
devices and for visitors.
The central to\ver contains, in addition to the inner
counterweights, gangways, staircases, passenger lifts as well
as hoists for servicing the structure.
The operating gear of the lower gate is located in a
gallery placed some 20 m above the chamber. This gallery
extends on both sides of the central tower.
Outer premises located under the downstream platform
but adjacent to the chamber accommodate dewatering pumps
as well as the emergency hydro-electric generator set which
generates the electric po\ver in case of any network
breakdown.
®
.. ;;. ·- ---f I
I --·--j
Fig. 6.3.9. Elevation
The chamber conSists of a wide rigid pedestal bearing
directly on the ground on which the load is distributed.
Effective pressures transmitted to the ground and uplifts are
limited to 10 to 30 kN/cm2 and ground settlements are
estimated to be 2 to 4 cm. The central tower is embedded in
the chamber.
Together with the latter and with the metal frame
which extends over its upper part, it makes up a bending
and torsion resistant whole, which absorbs without substan
tial displacements both vertical and horizontal loads.
68
1. Lift 2. Canal bridge 3. Steel columns
The machine room is approximately 130 m x 75 m x
20m.
It contains the whole of the electronical equipment (Fig.
6.3.10.).
Its design raised a series of technical problems, among
which the preservation of a minimum temperature, the
heating of the staff and visitors premises, the choice of the
type of structure and of the material for walls and frontage,
the effects of wind, the deformations of the floor and the
roof, lighting, the drainage and the circulation scheme for
staff and visitors.
24 180 18100 18100 24 180
© ® -D D -D --+----
I i
3 (4)_ ©
'' ®
®
Fig. 6.3.10. Diagrammatic plan of the engine room at level (131.15) 1. Drums 5. MeChanical synchronization axle 2. Low speed reducer 6. Winch 3. High speed reducer 7. Group of7 pulleys diam 4800 4. Enl(ine
The floor is made of a metal beam grid which supports
a 0.25 cm thick reinforced concrete slab. The roof is a
composite structure the reinforced concrete slab of which also
serves as footing and transverse bracing for the steel joists
Drainage (Fig. 6.3.8.)
During construction, the \Vater table was lowered by
sinking two i_:ings of wells: One, at a 68.00 m depth,
comprises five 0.40 m diameter shafts and the other one
(50.00) also has five identical shafts.
After construction , lowering the water table will be by
gravity. The proper operation of the drainage is vital for the
stability of the structure.
Aesthetics (Figs. 6.3.11., 6.3.12. and 6.3.13.)
The structure was designed to be both functional and
pleasant to look at.
Three elements were particularly significant in this
attempt: the size of the structure (it is 130 m x 81 m and
has a height of 102 m); the outstanding worldwide technical
achievement and the several functions of the structure.
It was decided to separate the functional parts (machine
room, control room and public access) from the lift itself.
Some visual elements were included in order to alleviate
the massive and monolithic look of the structure.
This applies, particularly, to the machine room. The use
of chamferred corners will make it possible to endow it with
a dynamic look as compared to a mere rectangular parallele
pided.
The canal bridges
Each tank is connected to the upstream lay-by by a
canal bridge with the same useful width as the tank but
with a draught exceeding that of the tank by 0.30 m to
lessen ship movement resistance (Figs. 6.3.9. and 6.3.14.).
The superstructure is made of 4 rolled and welded steel
spans with a bearing distance of about 42 m. It rests on a
bracket attached to the lift central tower, three piers and
one reinforced concrete abutment.
69
Fig. 6.3.11. Perspective uiew
As differential settlements are anticipated, the canal
bridge is isostatic and provided with bearing adjustment
devices.
The mass of the superstructure is 11 t/m.
The connection between the spans and the upstream
lay-by proceeds from the abutment over a length of 98 m.
The pile and abutment foundations go a long way into
the soil and have no adverse effect on the stability of the
backfill.
By placing a ship caisson on the abutment, it is
possible to put the spans in the dry for maintenance
purposes.
6.3.1.2.8. Reliability and safety measures
The operation of the lift cannot be interrupted and
should proceed totally safely.
Lifts are at least as safe as other solutions. However,
because of the high lift, the consequences of an accident may
70
be catastrophic. Safety and surveying arrangements are
.therefore absolutely necessary.
Several accident scenarios have been studied in order to
provide prevention measures.
Among these, we shall mention :
independence of the two tanks
isolation of parts of the structure.
Prevention of the following accidents has been studied :
emptying a tank in its upper or lower position
partial emptying of a tank during a lift
ship sinking in a tank with its gate open or in a canal
bridge
- uncontrolled ship seriously impacting a gate of the tank
or of the reach
immersion of half a chamber
- capacity reductions of the drains
- breakage of a gate of the upstream reach
I I
I I
I
152,00
~
131,15
'L 122,80
~ £
62,00 r-49,80
~ Fig. 6.3.12. Upstream elevation
- net\vork breakdown
- motor deficiency, suspension or control cable breakage, etc.
Arrangements have been made to control :
- water filling of the tank gates and of the canal bridges
when tanks are leaving
- horizontality of the tanks
- drainage rates and watertightness of the channels
- stability of the slopes and backfill.
Provisions of the general regulations on working con
ditions and fire prevention have been adhered to.
6.3.2. PLANNING AND CONSTRUCTION
The Belgian Administration carried out the preliminary
studies in order to identify the best solution to overcome the
Strepy-Thieu lift.
As soon as a decision was taken to build a vertical lift,
a joint venture contract was signed between the Belgian
State and a group of Belgian civil engineering, steel work,
mechanical and electrical construction companies to under
take detailed studies and to carry out works.
The contract was signed in December 1978.
Detailed studies were started in March 1979 and con
struction began in the Spring of 1982.
71
1·
.......
72
' ' \ ';:::·.:: ..... ·,. ____ , __ ..., I(
" "
I 1500
-r-·
J__
.\· .........
Fig. 6.3.13. Downstream elevation
r~30 1 4000
12.020 n
~11~ --1--. "'L
!ij I l[J
·----···-·. ---------,----· 12.s2_0 ____________ .J-1_s_o_o--i
Fig. 6.3.14 Cross-section of an approach canal bridge
152,00
1 49,30
·1
6 .. 4.. The Ronquieres incline
73
6.4. THE RONQUIERES INCLINE
(Belgium)
6.4.1. DESCRIPTION AND DESIGN PRINCIPLES
6.4.1.1. General characterislics
When designing the Charleroi to Brussels canal (Fig.
6.4.1.) for 1,350 t ships, the problem was to provide a lift of
the order of 67 m to take the place of 17 300 t locks.
( Lock 5 !--.
NlVELLES.
ECAUSSINES
1-..... ,i,LUTTRE.
- Route of existing canal 1350 t Loi::k 2
ROUX
VIESVILLE.
Loci< 3
"""''
'···-·
2 •• Route of former canal 300 t AMP REMY.
CHARL R
Fig. 6.4.1. CharleroirBrussels canal
The follo,ving solutions were considered:
a ladder of 3 or 4 locks separated by very short reaches
- 2 lifts with 1 or 2 tanks, and lifts of ± 34 m separated
by a ± 1 km long reach
1 lift with 1 or 2 tanks
1 incline 'vith 1 or 2 tanks and a slope of 5 %.
Because of the operational conditions of the waterways,
the two most satisfactory solutions that emerged were the
single lift with 2 tanks or the incline with 2 tanks.
However, a vertical lift appeared to be ill-adapted to the
local conditions.
The final choice was one of an incline of the longitudi
nal type with 2 tanks and a slope of 5% (Fig. 6.4.2.).
The final dimensions of the structure are as follows :
lift 67.05 m
slope of the incline 5 o/o
- travelling length 1,341 m
- overall length
- dimensions of the 2 tanks :
overall length
useful length
useful width
water depth
total mass of a tank, including water
time of operation
6.4.1.2. Basic arrangements
6.4.1.2.1. The tanks
1,432 m
91.12 m
87.00 m
12.00 m
3 m to 3.70 m
5,000 to 5,500 t
30min
Because of local conditions, differential settlement was
anticipated; the structure of the tank which was therefore
adopted was one which would rest elastically nearly conti
nuously on a large number of bearings (Fig. 6.4.3. and
6.4.4.). The tanks rest on springs on 2 rows of 59 axles each
or, in other words, on 236 rollers; such rollers are not fitted
with flanges so as to reduce friction.
Each tank is guided at its ends by 6 spring mounted
side rollers. Each group of guiding rollers may take a load
of 1,800 kN.
The structure of a tank consists of a 12 mm thick skin
plating . stiffened by outer cross-bars. The latter rest on 2
longitudinal box girders which transfer the load to the axles.
The mass of a tank, its rollers and the water in the
tank varies from 5,000 to 5,700 t according to the amount of
'vater in the tank.
75
' 290m · --· --~
5 6 -,----
' ":::: : •
• ...
1
[2----
76
l
A-,
·-·
'
Longitudinal section
Incline 1432 m
2 1032m
4 ----·----
8
Fig. 6.4.2.
Plan view
The incline and its surroundings 1. Part above ground level 2. Part in cutting 1,032 m 3. Foundations on wells 4. Direct foundation 5. High backfill 6. Canal bridge 7. Openings s. Upper head 9. Lower head
ELEVATION.
fi E.,
.ii- . ' ~fl
~·l--1
,~ Ir (
-~D..J Gradient 5'Yo F..J
Section AB
Section CD
Fig. 6.4.3. Tank 1. Bolting 2. Guide rollers 3. Idler rollers
;;x,p;wc <
,;;,,
9 __)
------
Section E F
11 11
Fig. 6.4.4. Axles of tank and counter-weight
The outside of the tank is coated with a thermal
4) Independent tanks partly balanced by counterweights.
5) Independent tanks totally balanced by counterweights.
Solution 5 appeared to be
4 in that it reduces
requirements.
more satisfactory
both capacity
than Solution
and energy
Solution 5 was finally adopted : independent tanks com-
pletely balanced by counterweights, where tanks and
counterweights are connected by cables controlled from
fixed \Vinches placed at the upper head.
The cables of a tank are driven by two 5.50 m diameter
Koepe-type friction drums; each tank is pulled by 8 55 m
diameter closed type continuous cables.
Coupling of the cables to the tank (Fig. 6.4.7.) is
achieved through hydraulic jacks that are inter-connected in
such a way that loads are equally distributed into the
cables. On the counter\veight side, each cable is individually
fixed to the frame.
As far as the winch control is concerned, electric control
was adopted after comparing it with oil-hydraulic control.
insulating agent. 6.4.1.2.3. The counterweights (Fig. 6.4.8.J
6.4.l.2.2. Operation of the ranks (Fig. 6.4.5. and 6.4.6.J
The following solutions \Vere successively considered:
1) Tank operated by cables without counter\veight.
Difficulties in housing the cable were foreseen.
2) Self-propelled tank without counterweight.
A lack of adherence of the tank wheels to the rails (e.g.
in case of frost) and difficulties for power intake were
foreseen.
In the two former cases, the operating capacity (3,500 kVV)
and the required energy (1,200 kWh for each up\vard
travel) were quite substantial.
3) Mutually compensating tanks
Difficulties might be expected with maintaining the ade
quate length of the cables and with the bringing to a
total stop in case of a breakdown of one tank.
With a total mass of 5,200 t, counterweights move on
runways that are located under the runways of the tanks.
They are made of two independent frames ballasted with
heavy concrete (iron fillings mix). They are supported and
guided in the same way as the tanks.
6.4.l.2.4. Runways (Fig. 6.4.4.J
The runways and the guiding structures of the tanks
were initially made of standard railroad type 50 kg/linear m
rails.
These rails were supported by individual chairs.
In the overhead section of the incline, joints are
provided in the rails every 80 m; in the buried section,
there are no joints.
Guiding rails are provided with joints every 25 m.
Fig. 6.4.5. Balancing of tanks 1. Deviation pulley 2. Drive pulley 3. Traversing jacks 4. Counter-weight 5,200 t 5. Tank 5,000 to 5, 700 t
77
1
2 "Crr::::::J#
_ __.c,,,Hl!JAR,.-Ltl\llL_
6
r---r I '
l~
{J2Q45d12115)
'
3
4 5
_JIR!ISSHS
10
8
-=-1 i ~--~ ' . bJ
Fig. 6.4.6. Driving mechanism of tanks 1. Tower 2. Walkway 3. Emergency gate 4. Canal gate 5. Tank door
6.4.l.2.5. Locking of the tanks at the ends of their travels
(Fig. 6.4.9.)
At the end of their travel, the tanks are locked to the
masonry of the corresponding head to withstand the 600 to
800 kN hydrostatic thrust resulting from the junction of
tank and reach.
Hydraulic jacks maintain the tank in its end of travel
position and compress the seals.
6.4.1.2.6. Water scaling between tank and reach
This is achieved according to the principles illustrated in
Fig. 6.4.10. and 6.4.11.
6.4.1.2.7. Tank and reach gates (Fjg. 6.4.11.J
The ends of each tank are closed by vertical lift gates
which can only be operated through the gears that are
78
6. Canal bridge 7. Cables 8. Incline 9. Drive pulleys
10. Tank
located in the frames of the upper and lower heads; such
gears control the movements of the tank gate as well as of
the end of each gate.
All the gates are equipped with stop logs protecting
them against shipping impacts. These locks are raised by
brackets attached to the gates.
The gates are partly compensated.
As a safety measure, the 28 km long upper reach is
provided, in addition to its normal closing gate, by a safety·
gate designed as a vertical lift fixed roller gate. The latter·
is not compensated so that it can be operated under any
circumstances.
6.4.1.2.8. Water and ship oscillation in the tanks • .n-rovement
of the tanks
The problem raised by water and ship oscillation in the
tanks has been theoretically studied and tested in t~e
:;///~· ,' / =
·O
0
' I I' i r
= = = = = =
Fig. 6.4. 7. Coupling of tank 1. Bottom of tank 2. Cable 3. Jack 4. Pump 5. Electric motor
laboratory. Studies and tests have resulted in the following
conclusions:
1 ° with a constant acceleration of 1 cm/s2 of the tank,
hawser stresses of 25 to 30 kN may be anticipated for a
1,350 t ship, which is acceptable;
2 ° these stresses may be reduced to 3 to 4 kN if the
acceleration is gradually applied to achieve 1 cmfs2 in
about 32 s. These 32 s corresponds to the basic oscillation
period of the water mass in the tank.
The operating gears have been designed in such a way
that the following values obtain (Fig. 6.4.12.):
acceleration period with a linear variation from 0 to 1
cm/s2;
constant 1 cm/s2 acceleration period;
deceleration until the working speed of 1.20 mis obtains;
uniform movement period;
--26m 2 ______ _
- -5,Jm. ·---··--·- - -ltJm ----
----12,5m +-------7
Fig. 6.4.8. Section of tank and counter-weight 1. 26 m from axis to axis 2. Movable bollard 3. Tank guides 4. Idler rollers 5. Concrete ballast 6, Counter-weight guides 7. Central guides
4
6
at the end of the travel, time of deceleration equal to the
time taken to accelerate.
The complete travel of the tank takes 30 min, including
the inital separation period and the final reduced speed in
the safety area.
Should hawser stresses tend to exceed the set levels, a
specific device was designed to automatically contain these
stresses.
In case of a displacement of the ships, the same device
brings them back into their initial position.
6.4.1.2.9. Electric equipment · regulation · safety
The winch 'vhich lifts one tank is powered by 6
continuous current engines, each of which is supplied by a
Ward-Leonard set.
The power of a motor is 125 kW. The number of motors
and of sets was chosen so as to reduce to a minimum the
danger of accident should a breakdown of a motor or of a
element in the set occur and to ensure as long as possible
the safe operation of the tank.
Continuation of operation should not be prevented by a
breakdown of the setor of the corresponding motor. In fact,
normal operation should proceed even in case of the break
down of two sets or of two motors.
A breakdown of three sets or of three motors should
still make it possible to bring the tank to a stop in line
with the adopted velocity law.
79
1
B
BA
11
~ 11
I
1 2
II
80
1 2
III
Fig. 6.4.9. Connecting tanks
I. The tank is pulled by the winch -The hook is raised 1. Canal 2. Tank 3. Hook 4. Joints 5. Bolting jack 6. Tank pin 7. Clearing jack 8. Cam 9. Lever
II. The hook is brought down - The winch is stopped : 1. Cana~· 2. Tank
III. The hook presses the tank against the canal The position is watertight 1. Cana~· 2. Tank
The Ward.Leonard sets are equipped with a fly wheel
which stores the kinetic energy \Vhich is necessary for the
gradual braking of the tank in case of current failure.
Each Ward-Leonard set has its O\vn regulation system. A
central system ensures the required velocity law and sees to
it that the torque is equally distributed between the motors
being used. The central system includes two sets, one of
which acts as a pilot. The pilot set continuously compares
the achieved speed and the desired speed.
80
Should a substantial difference appear behveen these two
values, it triggers the normal stopping procedure of the tank
(following the desired law). If the difference increases, the
emergency electric braking is triggered without any substan
tial impact on the contents of the tank. If the difference
further increases, mechanical brakes are applied, which then
entails brutal braking which is likely to cause damages to
the ships and to the tanks.
Finally, when a given set detects an abnormal func
tioning in the other one, the deficient set is automatically
switched off.
In this way, it should be possible to obtain maximum
operational safety.
6.4.1.2.10. Struclurc
From upstream to downstream, the following structures
may be identified (Fig. 6.4.2.):
- the upper head with its reinforced concrete structure;
the incline itself, which includes two reinforced concrete
hoppers each of \Vhich supports the running and guiding
rails of the tank and of the counterweights.
The incline comprises t\vo parts : the overhead section
(Fig. 6.4.13.) and the section in cutting (Fig. 6.4.14.);
the lower head (Fig. 6.4.15.};
The geology of the location influenced the design of the
excavation and foundations.
The geological section is shown in Fig. 6.4.16.
From the upper down to the lower head, this section
shows:
the Frasian level including schists and dolomites. The
dolomites are altered by an underground water flow;
the G~vetian level, \Vith rough red schists;
the Silurian level, \Vhich occurs as a substratum for the
whole of the site.
The soil cover consists of loam and clay and, locally,
sand lenses.
The site is very heterogeneous under the upper head,
the overhang section of the incline and the upstream side of
the section in cutting.
The upper head, the front part and 80 m of the section
in cutting were founded on deep wells.
54 wells of an overall length of 735 m \Vere sunk under
the upper head (Fig. 6.4.17.). 80 wells of an overall length
of 1,215 m \Vere sunk to accommodate the frame pile of the
overhead section and the beginning of the section in cutting.
The remaining part of the section in cutting was
founded directly on sound rock.
Well based foundations should meet two conditions : to
support very heavy concentrated loads (up to 39,000 kN}; to
undergo only slight vertical deformations, as differential
Reach
. . .••. •3. :: .
.
Detail 1
'\ -\
i I
Tank
Detail 2
-~/ \
" #. ·.<>.\ .. ! •
..... " "\
.·.,·" ,
.
Fig. 6.4.10. Scheme of watertight systems Detail 1 : Starting connection between tank and canal Detail 2 : Separating tanlt and canal
settlements should be limited to a few mm, to the extent
that the frame of the structures to be supported is rigid and
highly hyper-static, and hence very sensitive to differential
settlements.
Special attention was paid to taking maximum advan
tage of the strength of the penetrated ground, which
explains why some wells have a discontinuously shaped
profile, with a shoulder at the level of each reduction in
diameter (Fig. 6.4.18.). These shoulders made it possible to
transfer part (30 to 40 %) of the load to the neighbouring
ground and to relieve the foundation to that extent.
81
POOTES E:N POSITION DECOLLEE •
1 I • + I I I
PQRI[ DU lllEF I PCATE 00 BAC I
I ., PORTE 6N: CIJ BIEF.
F011ES EM POSITOO FERIJEE.
I I I
• "'
Hlti 'C._~ f 1 I t.AME OE CACUTCHOUC
/1,· '.· i l 1,,
I / O«. ~J ""i'r"": si:r
TETE I ¢ :')
"'~c . ' _._,,.,. .. i (2 \
[~\~l[~pfi~EVI~~ OE I l'~NTf!C-~!E~.... I
f~I I
( I
i '" I
, . . ;
I
I I .
OCUl!H DE CAOUTCHOl;l_<: ___ _
Fig. 6.4.11. Gate operating mechanism (left)- Watertightness devices (right) Legends: mecanisme de levage = lifting mechanism portes en position cMcollee = gates in parted position porte du bief = gate of the pond po rte du bac = gate of the tank portes en position fermie = gates in closed position m(lfonnerie de tete = head masonry
OE TAIL I
ETANCHEITE DES POOIES 1:U 6AC 00 OU 81Ef' 1'1/EC LEURS ENCLAVES
Qillll ETANCHEITE ENTRE BAC
ET a1tr
tuyauterie de ... ... l'entre-portes = discharge pipe works for water between the gates piece de l'enclaue =part of the recess lame de caoutchouc = rubber sheet etancheite des portes ...... enclaves = watertightness of tank doors or canal gates with their recesses boudin de caoutchouc = rubber seal
6.4.2. PROBLEMS ARISING DURING CONSTRUCTION AND OPERATION
6.4.2.2. Runways
Initially, the rails were standard (50 kg/m) railroad type.
6.4.2.1. Dimensioning of the reinforced concrete structures
The outstandingly high loads of the structures have
required, in the most sensitive areas, substantial concent·
rations of reinforcement, which, in turn, entailed concreting
difficulties and rather fast local deteriorations. Repairs are
necessary.
82
Because of the heavy loads on the rollers, numerous
cracks appeared both in the core and on the surface of the
rails, which entailed dangerous deformations (tilting).
After ten years, the runway rails \Vere substituted with
rails having a vanadium steel reinforced core (62 kg/m) with
a high fatigue strength.
The discontinuous rail bearings were damaged by verti·
cal upward reactions after the passing of the end of a tank.
,.,
'"
6 .. 4.12.1 Accoleratlon graph
1 f Accck:t~ioa (t:m/scc2 ~
fzt",u,·,._ _______ _,1!.1·---------..;32::"1'1·,.,.-.l"I· '1 I
0 19ll
3 tSpcedm/-. 6.4.tU Speeds graph
uofLf[ lil_r::• . o ... - 232~-~----------------1"'n'2• zzlM"
i Distance travelled Olstinco lrneJled
1340m. ~}2?!)M~-·
0
Fig. 6.4.12. Movement-Time graph
,.,
8 •
.___ __ _,_
""
'"
Fig. 6.4.13. Section above the ground
3 nme..m
...
I 't'
83
84
12.00 ________ .
1. Service path 2. Counte,-..weight 3. Tank guide rail 4. Counter-weight guide rail 5. Cable channel
""
Fig. 6.4.14. Section in cutting
1. Gallery 2. Tank door 3. Frame 4. Reach gate 5. Lower reach 6. Tank 2 4 7. Incline
°"'"=C------=--------~-----------~=-~--=-=---==-+-+-+==-------===-+-====--=--=----=--=----,,L.-
Fig. 6.4.15. Lower head
ouurs 11(-ll';
, ........ "'"""~"""'' ................... ·-; .. ~ . ~ . ~; ,Gtitll(N ·;
Fig. 6.4.16. Geological section - Overall longitudinal section Legends: frasnien = frasnian schiste doux = soft shale giuetien = giuetian dolomie argileuse = magnesian limestone schiste rouge = red shale silurien = silurian couches grises a vegetaux = layers of grey soil
eRUXEttES.,.
. ' .v:;=::.;-~:-: --.~\···•Gl>t:Tl(N.~ · .• ;•;i.s..;.i,..:lH,. -,.
• ... i ••9.;..,, - - _ .. _.::::= __ .· _=---_-_ ... -_'--_::.-::_--_.:.."_:-_,=·-·-"" -~~
hauls remblais = high backfill culee de raccordement = connecting abutment tour= tower pont canal = canal bridge partie airienne = section above ground partie enterree = section in cutting tete amont = upper head
schistes greso-dolomitiques = dolomitic shale and sandstone
!'F l'ldoo
I I I~-
'
I i I i I -.--
Fig. 6.4.l'Y. Upper head foundations:
P{K00-3900T) und level I. gro
-~-
' ' I
3t.Om {4,60m)
2 possible shoulder
/
v ~
' ~Qm ,., ....
Maximum useful load to be taken by foundation shafts 100,000 t o 32 shafts diam 200 m 0 22 shafts diam 300 m
Continuous rail bearings \Vere therefore constructed, on
which flexible neoprene insertions were introduced between
the rails and the concrete seating.
The expansion joints between the sections of the rails
are put under heavy stress by the passing of the rollers and
shock impacts caused damages (breakages, vibrations). New
and more appropriate units are currently being studied.
6.4,2,3, Rollers
The original rollers were made of poor quality carbon
steel which had undergone a superficial treatment. Abnormal
wear of the track occurred. It was therefore decided to
gradually replace the rollers by special totally fatigue resis
tent moulded steel rollers which guarantee an improved
resilience, an increased surface hardness and a uniform
surface treatment, which is constant over a sufficient depth.
6,4,2,4, Traction cables
The initial 55 mm diameter closed type cables had the
following drawbacks :
- relatively high cost;
Fig. 6.4.18. Foundation shaft,
occurrence of a helicoldal deformation of the cable, which
entails vibrations during passage of the pulleys and of the
sheaves. This deformation entailed an untwisting of the
external layer of wires and the dislocation of the Z wires
. of this layer.
These cables were replaced by NUFLEX type 55 mm
diameter cables, wi~h a good useful life.
Ho\vever, they have a higher extension coefficient which
requires several adjustments; they cause indentations in the
grooves of the pulleys, although this phenomenon rapidly
stabilizes.
6.4.2.5. Ward-Leonard sets - Fly wheels
Initially, each WL set was equipped with an fly wheel.
Because of incidents that have occurred with the bearings
Gamming, etc.) and of the danger in case of an axle of one
of the wheels breaking, the peripheral speed of which was
180 rn/s, the wheels were omitted.
The asynchronous type ring electric motors that were
required to start the movement of the wheels \Vere replaced
by a simpler squirrel cage asynchronous motor having a
smaller capacity.
85
6.5. The Saint-Louis-Arzviller incline
87
6.5. THE SAINT-LOUIS-ARZVILLER INCLINE
(France)
6.5.1. DESCRIPTION AND DESIGN PRINCIPLES
6.5.1.1. Characteristics
Before the building of the Arzviller incline, the Marne
to Rhine canal, with a capacity of 300 t, had 17 locks
spread over a distance of 4 kms to provide a total lift of
45.55 m (Fig. 6.5.1. and 6.5.2.).
The construction of the incline of Saint-Louis-Arzviller is
part of:
- the works intended to increase the water depth of the
Marne Rhine canal to 2.60 m;
water saving required by an often insufficient supply;
- the construction of a small sized prototype structure for
overcoming high lifts \Vith the prospect of increasing to
larger sizes later;
and, of course, the improvement of navigation conditions.
Solutions proposed by the companies that were consulted
were as follows : lift(s), water slope(s), longitudinal incline(s)
with self-propelled or tractor-dra\vn tanks; transverse
incline(s) with tractor-drawn tanks.
The Administration chose the solution of the single
compensated transverse incline equipped, in a first stage,
\Vith one single tractor-dra\vn tank and a possibility to add a
second tank at a later stage.
The dimensions of the structure are as follows (Fig.
6.5.3., 6.5.4. and 6.5.5.)'
lift
slope of the incline
horizontal projected length of the incline
length following the slope
dimensions of the tank :
overall length
useful length
useful width
water depth mass of tank water and supporting frame (trolley)
44.55 m
41 o/o
108.65 m
128.65 m
43.00 m
41.00 m
5.20m
3.20m
890 t.
Fig. 6.5.1. Location sketch plan of the Marne to Rhine canal (Revue de la Navigation)
89
I
) _]
i ~
\
, ,
\
, , I
)". /
90
~: !
'\ ' i
! J I ! l !
' i
" " " ..... -----1\~
1? ii .....
Tii ~~ :: .. ~i !j~
~::
! !~ ,,. .. "h ... "
..JJ ii ...... .,,. H .,...
"':'T' " :: • A~ •"" • .., .. q
iT'
" '• ~j
.. ~ !, ; ul .,;: u
" ;~;= . 'I ~i :;;:: aj
, ! - .. :::" ~' : ~1· ' . J , .. ::" . -
6.5.1.2. Basic arrangements
6.5.1.2.1. The lank (Fjg. 6.5.4., 6.5.5. and 6.5.6.J
The cross-section of the tank is U-shaped. It is closed at
both ends by vertical lift gates.
The inner skin plating is made of 12 mm thick plates
and is externally stiffened by longitudinal sections, trans
verse frames and transverse bracings.
Special transverse frames (Fig. 6.5.7. and 6.5.8.) have
been strengthened and arranged to accommodate certain
units:
- the bearings of the bogeys and the upstream stops;
the transverse girders which run parallel with the run
ning tracks and which support in particular the guide
rollers;
the gussets for the connecting jacks of the driving cables;
the lower berth stops.
The sides and the bottom of the tank are insulated with
50 mm thick rockwool externally protected by an anodized
bright ribbed aluminium plate.
The tank unit transfers its load to the infrastructure
through four bogies (which run on two railway tracks
separated by 0.80 m. The axles are 25.75 m apart (Fig.
6.5.6.). The bogies are incorporated into specially strength
ened transverse frames.
Each set rests on two-axle molybdenam bogies (Fig.
6.5.9.), i.e. 8 monobloc 700 mm diameter nickel-chromium
molybdenum steel rollers with a rim especially processed to
obtain a breaking strength of 1,470 N/m2 (Brinell hardness
400 to 500). The transmission of loads is isostatic and is
transferred through the equalizing bars .
The connection behveen the tank unit and each set is
ensured by a hooped neoprene bearing. The longitudinal level
oscillations of the tracks are taken up by the hinges of the
bogies; the transverse oscillations of level are taken up by
the neoprene bearing .
Between the two rollers of one single bogey, a shoe 'is
fitted which, in the event of a roller breaking, transfers the
load to the rail, thus causing a minimum lowering of the
tank structure.
The tank unit is equipped with a mechanical guiding
system (Fig. 6.5.8. and 6.5.10.) consisting of two pairs of
rollers separated by 9 m and bearing on two rails attached
to the upper part of a special girder fixed to the infrastruc
ture of the incline.
Each solid forged 1 m diameter roller rests on the rail
under the action of a pile of 'Belleville' washers which
delivers a 22 t prestress.
The guiding structure makes it possible to reduce to a
minimum any possibility of the tank skewing; at the heads,
it caters for hydro-statically induced stresses upon opening of
Fig. 6.5.3. Perspective sketch of inclines (Revue de la Navigation)
the tank gates, the thrust of the sealing frame and the
possible impact of a ship against the tank shock absorber.
Water depths in the tank vary from 2.62 m to 2.82 m
when descending and from 2.55 m to 2.62 m when ascend
ing. This reduces energy consumption and the prevailing
mass is always positive.
6.5.1.2.2. Operation of the tank
The weight of the tank is almost completely compen
sated by two counterweights connected to the tank by 28
cables. These are in two groups and operate from fixed
winches placed in the upper head machine room (Fig. 6.5.11.).
The diameter of each cable is 26 mm and its ultimate
load 660 kN, which translates into a safety factor of 5.4
when compared with its 122 kN working load.
The cables are attached to the tank by hydraulic jacks
which guarantee an equal distribution of load in the cables
and which, in the case of an accidental breakage of the
cable, avoids the chain breaking.
The jacks are operated hydraulically from the frame of
the trolley. The other ends of the cables are directly
attached to the counterweight,
Each group of cables is driven by a 3.350 m diameter
drum, operated after a double reduction by two direct
current motors.
Each of these drums carries a crown gear which meshes
with a driving pinion and rims on which the shoes of the
safety brakes press. The frames are fastened in the winch
foundation.
91
CONTIU'.·POIO!. BU; -.1.. /I CCINl'RE • ~ BAC No40NT
! ~
~ t; ~
~
!
~I ~! ~I .~1 ~I
G
; • , • • ••
Fig. 6.5.4. Plan of the structure as built (Revue de la Navigation) Legends: acces amont = upstream access groupe electrogi!ne = generating plant salle des machines = engine room treuils = winches bac amont = upper tank bac aval (projet) = (planned) lower tank suivant la pente = following gradient voie de roulement des bacs = tank runway voie de roulement des contre-poids = counter-weight runway poutre et voie de guidage = guide beam and track canal d'acces aval = downstream access canal contre-poids bac avaVamont = lower/upper tank counter-weight fosse des bacs = tank pit
6.5.1.2.3. The cOunterweiglits
The hvo counterweights are each made of a metal
structure supporting a concrete carcase reinforced with second
hand rails totalling a mass of 2 x 445 t.
The tracks, separated by 1.50 m, support bogies similar
to those of the tank unit.
In the upper part of the counterweight, the housing
accommodates a movable adjustment ballast of 40 t of 20 kg
of iron pigs.
6.5.1.2.4. The runways (Fig. 6.5.4.)
The runways of the tank unit and of the counterweight
are made of 'Rodange' n6 5 A-type rails (77 kg/m) initially
92
attached to reinforced concrete strings through spring clips
bolted onto fastening rods.
The load on each roller is of the order of 275 kN.
6.5.1.2.5. Locking of tl1e tank unit at the J1eads (Fig. 6.5.12.J
Locking hooks operated by hydraulic jacks tighten sta
ples attached to the metal frame of the tank unit to lock
the latter just in front of its stops.
6.5.I.2.6. Tank and reach gate - tank-reach sealing (Fig.
6.5.13., 6.5.14. nnd 6.5.15.)
The ends of the. tank and of the reaches are closed by
vertical lift gates ·. the sealing of which is ensured by
music-note type neoprene seals.
The gates are protected against ship impact by shock
absorbers; these are in welded steel and equipped with
hydraulic dampeners intended to absorb without any damage
the energy of a 400 t vessel moving at 0.10 mis as far as
the tank is concerned and of 0.50 mis in the canal.
Permanent deformations would be caused to the tank
beams in the case of speeds of 20 mlsec and 1.00 mis in the
canal, without however entailing any damage to the struc
tures.
Only the reach gates are equipped with an operating
mechanism.
When the gates are raised, the sealing between tank
and reaches is achieved by a sealing frame with the same
U-shape as the tank (Fig. 6.5.14.).
This metal frame rests on two rollers in its lower part
and is ~aterally guided by two rollers. It is attached to the
masonry by four drag links which
during its horizontal move (45 mm)
maintain it vertically
operated through 5-10
kN hydraulic jacks. The frame sealing is ensured by a
U-shaped neoprene rubber skirt; the sealing between frame
and tank is ensured through the jack operated compression
of a music-note type neoprene joint against a stainless steel
frame attached to the structure of the tank.
Ice protection of the sealing frame and of the gate
sealings is achieved by insulating the different units and by
heating them through electric resistances encased along the
steel flats which accommodate the seals (Fig. 6.5.15.).
6.5.1.2.7. Annlysis of movemenl of the lnnk unit
Oscillation of the water plane raises practically no
problem. Computations similar to those carried out for the
Ronquieres incline have resulted in an upper estimate of
variation of 16 mm for a normal acceleration and deceler
ation of 2 cm/s2 and 350 mm for an accidental deceleration
of.0.6 mls2 when operating the emergency mechanical brake.
"' w
..,,_\
oont<0l ,oom i 5 1
upstream canal road access
.·, tanl< run"'ilY
fram('
/\-/\ CROSS SLCTION
'''''"'
LONGITUDINl\I. SECTION 01' Tl II~ STRUCTUl{E
O 10 20 30 'O Jgm
1005
m high li~htin~ mast
operating gear
2 sets of 14 27 mm¢ cables 2 drum winches for tank (¢ 3.350 m) second tank
uppe~
gar.es gJn)?.wav
ac( f':;s r·ilniil
Fig. 6.5.5. Longitudinal and cross-sections of the structures ds built (Revue de la Navigation)
:::
l i i I i I I i
.~r frame -.:-;:::--;1 1
hat r1u11
Fig. 6.5.6. Tank - Longitudinal section at lower station (Drawing by Navigation Services - Strasbourg - June 1969)
I
f
Fig. 6.5. 7. Principle plan of translation units (Revue de la Navigation)
support
The ship is moored in the tank to the lower bollards
\Vhen the tank ascends and to the upper bollards when the
tank descends.
Fig. 6.5.16, illustrates the movement of the tank.
The duration of one operation half cycle is of the order
of 18 min, of which 4.30 min is for the movement of the
tank unit.
6.5.1.2.8. Electrical equipment - regulation ·safety
Each winch is driven by two direct current (d.c.)
variable speed and constant separate excitation motors of 88
kW and 1,500 r/min,
The peak power of the motors is 193 kW; they are
supplied with variable voltage by two Ward-Leonard type
generators.
94
Fig. 6.5.8. The guiding system (Revue de la Navigation)
The loops of the Ward-Leonard are completely separate;
in case of failure of any of the loops, the second machine is
capable of completing the travel of the tank unit.
The generators are mounted in one unit which includes
a synchronous driving motor of 220 kW and a fly wheel.
In case of overspeeding of the asynchronous group
(beyond 2,000 t/min) an overspeed relay causes the safety
brakes to operate.
The system is normally supplied with 20 kV up to a 20
k/380 V 5000 kA by a transformer.
In the case of a lengthy breakdown of the network, all
the functions which are necessary for proper working may be
taken over by a stand-by generator set housed in the
machine room consisting of a diesel motor coupled to an
alternator cooled by the upper reach water. This set is
started manually.
A small automatically started generator set of 23 kA
immediately remedies the lack of current on the 20 kV
network so as to guarantee the operation of the vital
elements of the structure.
The system incorporates many monitoring devices. Any
voltage deficiency triggers all the electrical safety devices.
In addition, no single operation, i.e. manual or automa
tic, can be carried out before the former one in the sequence
is completed and the necessary conditions are met.
Safety devices are triggered in the following circum
stances:
qso '" lJXlm
-[ ___ ~~~t_h_ra_;_1 __ X __
t ·- 110.. t ... '" -·f -'°'?.:'\t' -'"-~......JlL-i_,.,_j 2 cl•.filall-"'>.•'4.1.- .. ll>J:t J!.c1ea1an.oo. 10'4 (D - 0 ~pace betweer:i axl!!J;_Qticao.sl~.lLQII...filQups 7.BOOm
ELEVATION WITH IA SECTION A PARTIAL SECTIONS
Fig. 6.5.9. Detail of bogies (Construction - Dunod)
PLAN VIEW 6.5.10.l
(j) metal beam integral o 5'" with tank framew rk ~-------''--'-~-
,,---,...-.~,,_-.,----,...--.,.-,
/ , 0 @gui~e roil 0
=
Al
0:© 41suide beam axis: gui.de track and
Al tank ,
@guide! roller
., ..
SECTION A 6.5.10.2
@ •to
Fig. 6.5.10. Guiding gear of tank (Construction - Dunod)
- during acceleration and deceleration (control through end
of magnetic stroke circuit breakers placed along the
guiding beam),
at \Vorking speed (control through the motor driven speed
indicating dynamos),
- upon breaking of the kinematic chain (control through the
drum driven speed indicating dynamos),
- in case of deficient stretching of the driving cables
(detection through the end of stroke circuit breakers
placed on the balancing jacks).
Six stopping processes are provided according to the
nature of the detected deficiencies :
- completion of the cycle without any possibility to initiate
a new travel,
- bringing the deficient loop out of service and preventing
any ne\v start after completing the cycle,
immediate but normal braking after controlled regulation
and operation of standstill brakes in the stop position,
immediate braking by the application of a torque which
ensures an electrical braking separate from the regulation
control,
95
I ll"tl1J.ilUiUfWI .. gJIM
I I I
\ I \ I
_f3~'.~):_ : ........ 1 ... ~ ..
- [ ' l 1cJ1f/>[ [
';<C•,.tS,ot»-
Fig. 6.5.11. Sets of cables connecting tank and counter-weight - Sections of a winch drum (Construction - Dunod) Legends: v€rins superieurs!in{erieurs = upper/lower jacks chariot-bac = tank contre-poids = counter-weight
Fig. 6.5.12. Detail of tank locking hooks (Construction - Dunod) Legends: axe du crochet, bac Ct paste = axis of hook, stationary tank bac deverrouille = tank freed position theorique d'arret du bac = theoretical stopped position of tank course du crochet = hook travel jeu environ ... = clearance ± .. . verin force ... = jack thrust .. .
immediate operation of the safety brakes on a driving
pulley,
immediate operation of the safety brakes on a drum.
In addition, a delayed relay system prevents simul
taneous operation of the two braking systems.
When operating the drum brakes, the stopping distance
is 2.40 m in the most unfavourable conditions.
Usually, the operation of the safety brakes on the high
speed shafts and on the drums is initiated 'vhen all the
other arresting devices of the tank have been exhausted. The
electrical equipment is designed to minimize the possibility
of premature operation.
6.5.1.2.9. Infrastructure
From upstream to downstream, one may find in success·
ion:
96
..... ""'". I
~~~'"~""~·:~·:·~-··" tii~~iST ~ '""'•'"'"j_ ~-~ •• ~ .. o+_9, Hi'' llf*;Z"l\'=',:l+~:~'! ~! 1.;;'~:::;"·~.J" •• , .. ~~-,_...,lll~i!=-' +-.,--;-' ~~
® / heating ducts
:1; ~ .·.·· .. '
k~1l·~~;~·- ··: i
' 1>c)J'JTlrJll DE rt1lll'£TllllE ·:-i I __ _
/lcJIU'ES" £T 1>1!S'S'EJlEU£ Ell t'OUfh' IJE 1l,ELDll<1E
Fig. 6.5.15. Detail of watertight frame and joint heating system (Revue de la Navigation)
.·· ':' ~ .. --' , __
Fig. 6.5.13. Upstream gates and gangways (Construction - Dunod)
Gates closed (left) -Gates in raised position (right)
® ~~~~19 a~de~;_~c
@ s~;~~~anbde'.;r:!;~
0
[__L
<DA-A section
{i) 11n~I
" II
Fig. 6.5.14. Typical sections of watertight frames (Revue de la Navigation)
.·1---:·~1 .. ·1
the upstream c~nal
the upper head works where the machine
room and the winch foundations are to
be found;
the incline itself;
the lower head works with its tank
chamber, under the lower reach water
plane.
This structure is founded on a compact red sandstone
mass; the chamber is located under alluvia overhanging the
sandstone mass.
Sandstone is specifically very resistant when protected
from air and prone to friability and alterations when not
protected from air; besides, it is characterized by horizontal
stratifications with 10 to 30 cm sand and clays layers.
The main part of the upper head is the winch foun
dation (Fig. 6.5.17.); this has to withstand the stresses
generated by normal working conditions; furthermore, it
should, through the stops it is equipped with, retain the
winches in case the axle of the latter should break.
Located on the hillside, the foundation consists of two
symmetrical blocks connected by a reinforced concrete slab
which serves as a base for the machines.
Both the gravity and the anchorage solutions have been
considered for the winch foundations. The gravity solution
was discarded because of its high cost (excessive volume of
concrete) and of its lack of safety (insufficient shearing
strength of the rock).
97
:"'!"~·.::- ACCELERATION CHART
~0-i 7= ! :
speeds --·
F :i -- ' - i 'IT_,, u v ' ---, !
~· --=...r-=..::. 1,. _ ·- ~---·""-- ·--'SPEEDS CHART
J /: j\ ~ ~~: ~~ -_',_,,,~"~~-----'=~-----~_, . .- ?:~ ~. ~ ;.-1
DISTANCE CHART
c= =======~-=~··----=-·--·~-----"""·
Fig. 6.5.16. Charts illustrating tank movement (Construction - Dunod)
~--1
In the anchorage solution, inclined anchorages were
adopted as this enabled a two way working of the rock. The incline itself has a U-shaped cross-section (Fig.
6.5.5. and 6.5.6.).
The upper faces of the U legs support the runways of
tlie tank unit (of the two tank units in the future); the
horizontal section of the U supports the runways of the
counterweights as well as the supporting beam of the side
guide rails.
This beam is of the triangular box-type of which the
upper end connnects with the guide rails; the inside of the
triangle is an inspection passage.
Because of the steep gradient, a number of steps were
necessary to ensure sufficient adhesion of the incline to the
ground.
The lower pit of the incline (Fig. 6.5.5. and 6.5.6.) was
constructed in the dry behind a sealing diaphragm wall.
This pit serves as the acceptor for the discharge of the
water between the gates and, in case of heavy rain or
storm, of all the rain water falling on the incline.
98
Hi.~g
Fig. 6.5.17. Winch foundation: section (Revue de la Navigation)
It is equipped with three submerged pumps, each of 5
kW, which discharge into the lower reach.
6.5.2. TESTS - PROBLEMS ARISING WHEN COMMISSIONING AND DURING OPERATION
During the test period, data were recorded in the case
of normal operation as well as in the case of malfunctioning
of the tank (emergency stops, with drum braking; emergency
stops, with mechanical braking on the motors).
These tests have confirmed the average values of the
design parameters; several analyses have made it possible to
improve the choice between the different simplified models of
the mechanical operation of the system.
The inclines were first operated on January 27, 1969.
A series of measures have been taken since then to
improve safety and prevent incidents or operating difficulties
met during operation.
Among these, it is worth mentioning the following:
noise and vibrations registered during operation of the
winches have disappeared after replacing the drums and
increasing the diameter of the shaft;
the running tracks, which are subjected to heavy loads
(28 t) were directly attached to the reinforced concrete
stringers. The concrete under the rails deteriorated; after
replacing the concrete, a 8 mm thick and 200 mm wide
(width of the rail shoe) reinforced neoprene strip was
inserted between the rails and the concrete;
introduction of a mechanical clamp to the vertical lift
gates in the upper position to avoid accidental falling
back during ship passage upon entering or leaving the
tank unit.
6.6. The incline of Krasnoiarsk
99
6.6. THE INCLINE OF KRASNOIARSK
(U.S.S.R.)
6.6.1. DESCRIPTION AND DESIGN PRINCIPLES
6.6.1.l. General characteristics
When the U.S.S.R. decided to take advantage of the
Siberian rivers by building 100 m and more lift-hydraulic
complexes, the technical problem of ensuring continuity of
navigation appeared to be very complicated.
To solve this problem at the complex of Krasno'iarsk on
the Ienissei River, the solution of a lift of a specific type
was adopted.
It is located on the left bank of the river, close to the
end of the dam (Fig. 6.6.1.).
tank ara e
There are four main parts : the self-propelled tank, a
downstream incline, a turntable and an upstream incline.
Transferring a ship from downstream to upstream
proceeds as follows.
The tank filled with water is brought down to the end
of the downstream incline and submerged in the lower reach
until the water level of the tank matches that in the reach;
communication between reach and tank is achieved by
lowering the sector gate. The ship enters the tank reach and
the tank gate is closed.
The tank moves up the incline at a theoretical max
imum speed of 1 mis (60 m/min), after an initial acceleration
of 0.008 m/sec2.
@ maintenance © turntable
®upstream ·@viaduct @ ..,..,. ....... ---- CZ)downstream incline 8 large trench
·' .~ ~o:i:~
··•···
CD IENISSEI RIVER
@ ower station 100 290 300 400 5~ ...
Fig. 6.6.1. Sketch plan of lay-out
101
In the upper part of the lower incline, the end of the
tank leaves the incline and rolls onto the incline frame of
the turntable. By then the axes of the tracks of the incline
and of the truss match. The gradient of the turntable truss
matches that of the incline, i.e. 1/10.
The track of the turntable thus extends that of the
incline : by then the two tracks are close.
When the tank has come to a standstill on the
turntable, the ends of the turntable are unlocked. The
turntable then rotates by 142°. When this is complete, the
track of the turntable matches that of the upstream incline.
The entrance of the tank thus points toward the upper
reach, which is the direction to be taken by the tank. Before
the tank starts, the turntable is locked.
The tank goes down the incline toward the lower pool
with a maximum theoretical speed of l.33m/s (80 m/s). The
deceleration is 0.008 m/s2 toward the end of the travel. The
travel is completed when the water levels in the reach and
in the tank are the same. As soon as the tank has come to
a standstill, communication between reach and tank is
achieved, thus allowing the ship to leave stern-first and
another ship to enter, also stern-first; the vessel thus enters
the lower reach bows first.
The turntable and the tank are the most sophisticated
elements of the whole system.
A third incline from the turntable allows access to a
lay-by intended for maintenance and repair purposes. This
lay-by also serves as a shelter for the tank in winter when
navigation is interrupted.
G) tracks and racks
@ pantograph supportin2 mast
@control rnom /
@ pressure generalln unit housing
Fig. 6.6.2. Perspective view of tank
The dimensions of the structure are as follows :
- :lift
variation of water level in upper reach
variation of water level in lower reach
gradient of the inclines
~verall length of the inclines
upper incline
lower incline
turntable
lay-by accession incline
CD oil pressure genPrating unit
@hydraulic: motors
@sector ale
100 m
13 m
6.30 m
10 %
731 m
306 m
1,189 m
105 m
131 m
Fig. 6.6.3. Cross-section of tank
102
- characteristics of the tank
plan view of working dimensions
external dimensions
maximum water depth
total mass
water mass
90mx18m
108.20 m x 26.50 m
2.20m
6,720 t
3,560 t
characteristics of the vessels accommodated
in the tank
capacity 78 m x 15 m x 1.85 m draught
1,500 t.
6.6.1.2. Basic arrangements
6.6.1.2.1. The tank (Fig. 6.6.2. and 6.6.3.J
The tank itself consists of a horizontal pool filled with
water supported by a longitudinally triangular mesh type
frame.
The cabin with the electrical appliances and the local
control desks is located at the upper end of the tank.
The lower end of the tank is equipped with a hydrauli
cally operated sector gate.
The mesh type frame of the tank incorporates suspen
sion, running and driving devices.
Fig. 6.6.4. Details of supporting and driving gear of tank 1. Cross equalizer 2. Supporting jack 3. Hydraulic motors 4. Rack-wheel diam 1. 05 5. Racks
The tank and the supporting frame are mainly made
out of steel. One part of the non submerged section of the
tank is made of a light alloy. The weight of the tank is
6,720 t, while the water mass is 3,560 t. The overall length
of the tank is 108.20 m and its width 26.50 m. The side
walls are part of .a watertight box in which the driving
mechanism is located.
6.6.1.2.2. Driving, suspension and guiding of the tank (Fig.
6.6.4. and 6.6.5.)
The hydraulic driving system of the tank comprises 18
piston ram pumps with a rate of 58 l/s of oil under a
pressure of 105 bar and 156 radial ram hydraulic motors
each of 75 kW. Pumps and engines are connected to an
oil-pipe system. The pumps are located in a side room. The
hydraulic motors are suspended in pairs on each driving
trolley. These consist of a cast frame which bears on . a
two-wheeled bogie, hydraulic bearings and two driving gears
attached to the side ~aces of the frame. The diameter of the
rollers is 950.- mm. They have double flanges and are
mounted on ball bearings.
The hydraulic bearing is mounted on a horizontal axis,
located in the centre of the frame. In the upper part of the
pump plunger, a plate is attached with a movable system,
which connects it to the tank.. This system consists of two
rollers and two bearings with concave cylindrical surfaces.
The bored radius of the bearing units is designed so as
to allow the trolley to undergo a maximum 50 mm side
displacement on these rollers and to come back to its initial
position under the action of vertical loads as soon as the
causes of the displacement disappear.
At the same time, the lateral stability of the trolley is
ensured through supporting rollers which rest on the whole
width of the plate.
The driving system consists in a disk brake attached to
the frame of the trolley, a hydraulic motor mounted on this
brake and a rack pinion (gear attached to the lower part of
the brake shaft). The shaft of each hydraulic motor is
equipped with its own locking system, which is capable of
retaining the tank on the incline as soon as it has come to
a rest.
This system is also triggered in case of an emergency.
The end of the hydraulic motor shaft, the access of
which is perpendicular with respect to the incline, is
equipped with a 1.05 m diameter gear.
Each of these 150 gears mesh with racks placed in
pairs on both sides of the rails and ensure the power supply
when the tank is rising or the braking strength when
coming down.
To reduce the wear on the rollers and gears, the
suspension rods of the tank trolleys are designed so as to
allow vertical and transverse displacements. The vertical
movement is made possible by a hydraulic plunger system
connected to the oil pipe system. The constant pressure in
the pipes equalizes the load of each trolley irrespective of
irregularities of the runway.
103
~ II
u I. ~-1
/ --;-7
i I
.:;.1.-" >'//o,'.'' • .,.,.,.,.,.,. ,.,. • ,.,,n,.,.,
·-8-' <I @-z
104
2 --
.F'ig. 6.6.5. Tank-c<J,rrying bogie 1. F'ranie
2, Double tyre wheel 3. Brake 4. Hydraulic motor S. Driving pinion 6. Hydraulic rest 7. Roller
Each of the hydi·aulic Pmnps is driven by three-phase 800 kW synchronous motots. The revolutions of the Pump set
are kept constant. The regulation of the speed of revolution
of the hydraulic motors between 0 and 0.33 >is is achieved by varying the oil consumption of the motors .
6.6.1.2.3. Special mcchnnicnJ device for the haulfog of ships
fora the tnnk "''d shock absorber "''d moorfog systems (Fig. 6.6.6.)
The chains of the hauling system are located in special recesses inserted in the side boxes of the tank while the
controls of such mechanisms are located in the machine rooni.
Fig. 6.6.6. Mooring system 1. Jack
2. Equalizer with counter~weight 3. Eight strand block 4. Double hooh mooring ring 5. Mooring cable
Fig. 6.6. 7. Hub of the turntable 1. Upper swivelling part 6. Pin strut 2. Lower fixed ring 7. Supporting fork 3. Cone roller 8. Drum 4. Central fastening of rest 9. Base supporting ring 5. Spherical pin
1 2
II~ /1 . . 243,0
·· ------------H~~±±J---:-:-:--'f'------::::-:--f-' --rln - -- .. \
'
Fig. 6.6.8. Upstream Jetty and fioating pontoon 1. Tank 2. and 3. Positions of pontoon 4. Jetty wall
105
On the lower side of the tank, at a depth of 5,570 m,
there are three mooring rings, 'vhich are equipped with
hawser stress reducing devices.
Upon entering the tank, the ship is moored to these
hauling mechanisms. The same mechanisms then haul the
ship into the tank, slow it down and bring it to a standstill
in the pre-selected location.
The mooring system consists in a jack, a balance beam
and an 8 strand sheave, the cable of which is connected to
the mooring ring through two hooks.
The shock absorbing mooring system consists of a
hydraulic absorber which takes up the kinetic energy of the
ship 'vhich moves in the tank; it is triggered under two
circumstances : 1) normal conditions (normal acceleration and
slowing down of the tank); 2) accidental circumstances
(emergency stopping of the upgoing tank in case of current
failure). In this latter case, deceleration reaches 0.5 m/s2 and
the displacement of the ship 7 m.
All the tank operations are controlled by one operator,
from the control desk of the operating cab.
6.6.1.2.4. The turntable (Fig. 6.6.7.)
The turntable of the Krasno'iarsk lift is, just as the
tank, a unique structure. The frame of this plate is 104.6 m
long and its mass is 1,300 t. It comprises 2 sills and it
rests on a horizontal circular plate designed to support a
load of 80,000 kN, which serves as the central rotation
support.
This central support is located in the middle of the
plate and it forms the axis of rotation. It alone takes the
vertical load as well as all the horizontal loads generated by
the turntable and the tank. The design of this central
support is of the 'roller crown' type. Each end of the
underframe rests on 3 trolleys equipped with 2 flangeless
wheels. The rotation is achieved under the action of 2
driving trolleys 'vhich run on circular rails.
These trolleys are driven by hydraulic motors. The
hydraulic pumps of the plate driving system are located in
the central part of the turning beam. The circular pit which
houses the system is surrounded by a retaining wall, the
supporting faces of which also serve as foundations for the
circular rails.
6.6.1.2.5. TI1e runways
The overall length of the tracks is 1,731 m: upper
track: 306 m; lower track: 1,189 m; lay-by track : 131 m;
turntable : 105 m.
The rail gauge is 9 m.
The run,vay consists in 2 rows of rails, 4 rows of racks
and the bearings of the lower rails.
106
fD
~~2
Fig. 6.6.9. Floating pontoon a. Elevation: 1. and 2. Fenders
3. Connection 4. Mooring end
b. Plan view : 5. Hand operated capstan 6. Cable winding gear 7, Hatch 8. Projecting buffer
c. Cross-section : 9. Bridge 10. Floats 11. Mooring ring 12. Side fender 13. Jetty wall
6.6.1.2.6. Electrical power supply
Piles placed along the inclines support the lines which
supply the tank with high voltage current through a
pantograph placed above the operating cab.
6.6.1.2.7. Tlie civil engineering works
The geology is very complex : rocky indented banks;
gullies; stepped banks.
The concrete slab of the inclines is 15 m wide and
supports the rack rails. It is mainly founded directly on the
original rock. However, in the lower part of the lower
incline, the contours required that a 90 m tr~nch be dug. In
the upper part, a viaduct with a maximum height of 35 m
had to be constructed.
6.6.1.2.8. The surroundings
The upper incline includes a 330 m jetty (Fig. 6.6.8.)
intended to achieve a motionless water area, through dam
ping the effects of the water variation of the upper pool.
Other arrangements include berthing facilities, a power
cable tunnel and 2 pneumatic jetty lines.
a b
s
4
Fig. 6.6.10. Projecting buffer a. Side view b. Plan view
1. Projecting buffer 4. Counter-weight 2. Projecting buffer out of operation 5. Fastening pin 3. Turning axle
f
2
·++--
Fig. 6.6.11. Cylindrical bumper 1. Cylinder 2. Spring cushion 3. Rubber fender
3
o: 01 O>! , I
'
6. Rear stop 7. Front stop 8. Buffer groove 9. Jetty wall
The jetty is equipped with a floating pontoon for the
guiding of the ships .. e'"ntering the tank and the damping of
the ship impacts.
The metal pontoon is of the catamaran type (Fig. 6.6.9.).
For ease of docking it on the bank when navigation is
interrrupted and of adjusting its length, this pontoon is
made of 5 distinct sections connected by removable rigid
attachments.
T\vo protruding stops which slide in vertical grooves in
the jetty wall take up longitudinal shocks transferred to the
pontoon by ships (Fig. 6.6.10). These stops make it possible
to use light anchors to maintain the pontoon in the vicinity
of the jetty wall.
Early in the operation, the pontoon is brought into
position when the pool water level is at a maximum
elevation. The pontoon is then moved from time to time
along the Jetty wall by 1 m high and 10 m long steps. The
repetition of each of these operations during the navigation
period depends~ on the variation of the upper reach water
level (Fig. 6.6.8.).
The pontoon hull is equipped with shock and wear
protection devices made of side fenders and spring mounted
cylindrical shock absorbers (Fig. 6.6.11.).
After complete deformation of the shock absorber
springs, the loads induced by ship impact are transferred to
the pontoon frames through side sills.
107
6.6.2. TESTS BEFORE FIRST OPERATION
The tests which were conducted confirmed the efficiency
of the structures and equipment (power sets and equipment;
communication system; electrical and road networks)
The efficiency of a large pneumatic jetty designed to
protect the water surface in the vicinity of the incline
against waves in the pool was tested on one of the most
windy days. The jetty fully suppressed the waves on the
incline side where a calm water area was observed.
However, there were a series of defects in the hydraulic
operation units, the jack lubrication mechanisms, the trans·
ducer and relay supply circuit and the berthing
arrangements. Some of these defects were due to faulty
workmanship and to manufacturing and mounting and not
faulty design. Other defects ·were due to bad design.
Operation tests of the tank and, in particular, tests on
the automatic control of the hydraulic driving system, were
ca1Tied out. This test programme included readings of both
static and dynamic stresses induced in the metal frame of
the tank. During such tests, the tank was filled with water
to different levels including overfilling 10 and 20%.
Testing the lift \Vas carried out with ST30A oil in the
hydraulic system. The analysis of the oil demonstrated the
absence of impurity and of any indication of wear of the
hydraulic mechanism.
Since the modernization of the hydraulic driving system,
improvements brought since the initiation of the operation
tests have proven efficient; the tank acceleration and deceler
ation values are close to the design values. However, an
insufficient accuracy has been found in the brake operating
sequence upon starting and stopping.
The introduction of additional regulation appliances has
made it possible to increase considerably the process effi
ciency. However, the finalization of the system and its
coordination with the waterway automation requires
additional tests and improvements in the hydraulic auto
mation system.
Tests of the metal frame of the tank being gradually
filled with water from 0 to 2.2 m with an overfilling of up
to 2.40 m and 2.64 m have demonstrated that the ge~eral
stresses in the metal frame remained within tolerated limits
and that stresses in the elements resulting from accidental
emptying were close to design values.
108
The outstanding level of the overall design of the project
as well as the results of the operating tests have made it
possible for the State Commission to authorize the lift to be
brought into service. A 2 year experimental operational
period was authorized in order to establish that some
experimental parameters were in line with design values.
6.6.3. OPERATIONAL EXPERIENCE SINCE 1985
Throughout 1985, the tank travelled with a reduced
speed (20 m/min) as compared with the design speed.
The lift was only operated under temperatures above
0° c.
Through 154 days of service (from June 1 to November
1), 582 half-cycles of the tank (from one reach to the other)
were made : 433 with ships in the tank and 149 without.
The average duration of each half-cycle is 3 h 27 min.
During these 433 half-cycles, 535 ships \Vere caITied by
the tank, out of which 422 (79o/o) were commercial ships and
the remainder passenger ships.
Out of the 422 commercial ships, 238 {56o/o) only were
loaded (about 170,000 t).
Traffic was very irregular : 54 ships in June, 122 in
October.
All of this demonstrates the substantial traffic capacity
reserve available even with a reduced speed of the tank.
Commercial traffic may be increased by reducing dead
times : more balanced traffic, especially during the first
navigation months; ruling out of empty tank travelling; ship
entering and leaving operation duration.
The above-mentioned malfunctioning (design and fabri
cation defects) and the replacement of some equipment
should take place in the coming years. As an example,
hydiiulic motors will be replaced by more reliable, more
durable and more powerful machines.
The movement speed of the tank will thus be reduced
to a maximum of 40 m/min i.a. when coming down.
Control operations should be automated.
6. 7. The Montech and Fonserannes water slopes
109
6.7. THE MONTECH AND FONSERANNES WATER SLOPES
(Francej
6.7.1. INTRODUCTION
Before undertaking the construction of water slopes, the
French Authorities decided to have some reduced scale
models built.
In 1966, the Centre de Recherches et d'Essais of Chatou
was commissionned to conduct the mathematical study of the
hydraulic phenomena involved. The object of the study,
which also included the construction of a 1:50 scale model
was to determine how to minimize the oscillation of the
water surface.
Shortly afterwards, the decision was made to build a
1:10 reduced scale model of a large capacity 12 m wide lock.
The model was built in 1968 in V Einissieux (Rhdne) (Fig.
6. 7 .1.). These studies were concerned with the displacement
of the water wedge and the behaviour of ships. The models
were also used to develop technical details such as the
imperviousness of the shield and the ship mooring configur
ations.
Before considering a water slope for large modern canals
(12 m wide), it was considered opportune to implement this
system on Freycinet capacity (350 t canals) · units of 38.50
m x 5.50 m x 2.20 m.
As part of the modernization to 350 t of the Atlantic to
Mediterranean connection (Fig. 6.7.2.), the original locks were
extended. This provided an opportunity to confirm the tests
already undertaken, though these were in fact satisfactory.
It was decided to first construct a water slope in
Montech on the side canal of the Garonne River with a view
to testing the operational behaviour of a 6 m wide channel
and which would also avoid the extension of 5 locks.
The structure was first operated in 1974. In addition, it
served as a test model for the lateral hydraulic displacement
of a ship waiting at the upper head.
As a result of encouraging operational experience, it 'vas
decided to construct a water slope in Fonserannes, near
Beziers, on the Midi canal, which would take into account
the experience gained with Montech.
6.7.2. THE MONTECH WATER SLOPE
6. 7.2.1. Dimensions
lift 13.30 m
gradient of the channel 3o/o
working length of the slope 443 m
width of the slope 6 m
height of side walls 4.35 m
water level in the heads 2.50 m
water level in front of the mask wall 3.75 m
length of the water 'vedge 125.00 m
dimensio.ns of 350 t ships 38.50 m x 5.50 m x 2.20 m
6. 7.2.2. The driving unit (Fig. 6. 7.3. and 6.7.4.j
The choice of the characteristics of the driving unit was
based on the following principles :
- avoid external structurally induced breakdowns by adop
ting the self-propelling principle;
overdesign of the driving equipment to test it at speeds
above those adopted in v enissieux;
avoid excessive novelties and adopt classical driving units;
with a view to ensuring adequate adherence, use a heavy
unit and pneumatic tyres;
adopt a movement regulation system with a proven
efficiency.
The driving unit includes:
- two overseas railway-type self-propelled units rigidly con
nected by a back-beam stretching over the channel to
accommodate the shield thrust; a front beam to support
the shield suspension and shock-absorbing units;
- the shield itself;
- the shock absorber.
The mass of the whole of the system is 190 t.
6.7.2.2.1. The self-propelled rigs
The power of each diesel-electric self-propelled rig is 740
kW and it is supported on 4 driven bogies equipped 'vith
111
Fig. 6.7.1. The Venissieux model (River RhOne)
MONTPflLIERe
SEZIEl!S
..• FONSERANNES
ESPAGNE
Fig. 6. 7.2. Waterway joining the Atlantic to the Mediterranean Sea
112
two wheels 'vith strong pneumatic tyres. The side-guiding is
ensured by 8 vertically mounted solid rubber tyred wheels.
Each self-propelled unit is equipped with :
one 740 kW-1800 r/min diesel generator set;
one main generator coupled with a diesel unit;
one belt driven auxiliary generator;
Fig. 6. 7.3. Montech - Perspective view
two rectifier sets per generator for the supply to the
driving motors;
four driving motors powering the thrust of the driving
unit both upward and downward and also during rheosta
tic braking;
driving bogies equipped with tubeless tyre wheels with a
deflated radius of 730 mm and a 9.5 bar pressure;
the programming and regulation apparatus for driving and
rheostatic braking designed to achieve swift and gradual
movements;
a pneumatic brake with electro-pneumatic controls which
operate through the control cylinders of the 16 drum
brakes of the driving bogies.
This brake has a three-fold function :
stopping and standstill brake (normal use);
emergency brake in case of a breakdown of the rheostatic
brake;
emergency brake operated through an independent circuit
and triggered by the maximum pressure.
One of the self-propelled units is equipped with a
control cab and with an auxiliary 110 kVA generator set.
The other self-propelled unit is equipped with a hydrau
lic station (three rim pumps).
6.7.2.2.2. The water sealing bulkliead
The bulkhead comprises :
the bulkhead itself, of the sector valve type, made of a
box type beam, located at the level of the resulting
hydrostatic thrust and of a stiffened skin plating. It is
© se f-orooelled railcar
---
' .,
I; -
I -. '
"
.. I ..
1.ur 1. 1 11 1 I (1 , ; I I i;fB'** ---?,-t-. '-6-:- --· - -e;;· E:=:-===:=:::::·:=---==:::===: : I I I I-~ I i i ! ' ®
cab
(J) self-propelled railcar !
Fig. 6. 7.4. Plan view of unit
113
equipped on each lower end by a guard. The thrust is
560 kN nominal, 690 kN maximum;
the central arm, bolted to the bulkhead;
the connecting rod between the other end of the arm and
the rear beam of the driving unit;
the hydraulic set made of:
a double acting jack located within the arm and
connected to the bulkhead operating cables
a sealing pressure mechanism
a hydraulic station
a sealing system;
an operation system including the front beam of the
driving unit and the cables; the bulkhead hangs on the
front beam through this arrangement, which limits the
load transferred to the channel floor;
The double acting jack actuates the cables, which raise
or lower the bulkhead; the lifting operation takes 90 s;
a hydraulic locking system of the gate in the upper
position;
a pump and filter fitted with an overpressure water
system.
An illustration of the filling system is to be found in
Fig. 6.7.5.
Watertightness is achieved through calibrated openings
accepting normal leakages which are compensated' by water
released over the upper head through a by-pass.
\
I I \
I I
Fig. 6. 7.5. Bulkhead wate,...tightness system 1. Vertical floor bearing 2. Roller 3. Jack
114
#-® ~
(i) A-A Section
4. Guide-bar 5. Suspension rod 6. Side-wall
Openings are provided between the sealing rings pressed
against the walls of the channel and against the facing; the
vertical rings are pressed by jacks while the horizontal
sealing rings are pressed through the action of the residual
rate of the bulkhead.
In the gusset-shaped angles of the channel, the rings
are conical.
The excess pressure relief equipment dra\VS up between
the sides of the bulkhead and the side walls themselves, the
water which is roughly filtered through large-sized grids.
A water supply system cleans the seals during
movement.
6.7.2.2.3. The shock absorber beam
This beam is made of :
a U-shaped box-type frame with a walkway. Its ends are
equipped with arms hinged to the frame of the self
propelled unit, which enables it to be raised;
a shock absorber made of cables and rubber blocks and
connected to the beam through jacks;
The travel of this shock absorber is 1.65 m. It is
capable of absorbing the energy of 350 t mass travelling
with a speed of 0.4 mis.
The shock absorber also serves as a rest, through two
pneumatic devices consisting of release hooks mounted on the
ends of the jacks.
A set of hydraulic jacks for the operation of the beam
and its upper and lower locking, the shock absorber jacks
and the pumps.
6.7.2.3. Civil Engineering Works
6.7.2.3.l. The channel
The U-shaped cross-section channel is made of thin
reinforced concrete. The runways of the self-propelled rigs are
made of independent slabs, which incorporate a reinforced
concrete guide rail.
The concrete of the runways was specially processed to
ensure an adequate adherence of the tyres.
The joints in the side walls are perpendicular to the
floor; as the bulkhead is vertical, the contact between the
side \Valls and the sealing cylinders is not in terms of the
latter, which lessens the \Vear of the joints.
For the same reason, the joints in the floor are of the
rafter type.
Execution and finishing tolerances are such as to avoid
any jamming of the bulkhead and to reduce leak and wear
of the sealing rings.
The vertical flexibility of the unit, load limits as well
as the guide wheels clearance have all been incorporated
into the design of the runways.
At the lower end of the channel, freely communicating
with the lower reach, there is no gate but mere return walls
and an upraise of the channel floor \Vhich serves as a sand
trap.
6.7.2.3.2. The upper head (Fig. 6.7.6.)
D © ~:~:~~~~~
at tho Sida
Fig. 6.7.6. Upper head
(j) upstream
gate
upstream reach
From upstream to downstream, this head consists of:
a 27 m long horizontal herring-bone patterned stilling
level section;
side expansion basins;
an automatically or manually operated upstream lo\vering
gate (Fig. 6.7.7.);
an arrangement providing for the displacement of a
downstream facing waiting vessel.
6. 7.2.4. Operation
The operating cycle is as follows :
In the upstream direction
The stunt end and shock absorbers are raised; the
upstream going vessel enters the channel. The resistance
to progress is less than when entering a lock or a tank
because of the slope of the floor.
Lowering the stunt end and the shock absorbers; thi:?
sealing units are pressed against the side walls; the
operation is started.
Gradual acceleration (average 1 cm/sec2) until the oper
ating speed of 1.4 rn/s is reached.
The oscillations of the water surface are included between
the limits of + 28 cm and - 13 cm as compared to the
still water level; the oscillations between the upper end of
the \Vater \Vedge are not great. Indeed, the general
swinging of the water slope proceeds around a neutral
axis at about the mid-point of its length.
- About 5 minutes after starting, the water of the \vedge
reaches the upper head; the water energy is removed. The
level increases gradually between the stunt end and the
gate \vithout excessive wave reflection.
The water flows into the side expansion basin. Slowing
down the system is then started.
After six minutes the gate is automatically lowered and
retracts in 10 seconds.
Moorings can then be released.
The ship leaves the upper head.
The gate can then be closed.
In the downstream direction
The driving bulkhead moves down with a rheostatic
braking roughly programmed as when going up.
The nominal speed of descent is reached after 5 minutes.
An excessive disturbance of the lower reach is avoided by
slowing down the system to 3 kmJh when it is near the
lower end.
In the upper head, an arrangement allowing the separ
ation of a waiting downstream-going ship was successfully
tested.
The system works by creating transverse currents gener
ated, on the one hand, by the movement of the water
flowing through the side expansion basin and, on the
other hand, by the discharge towards the lower level
canal through remotely operated sluices situated on the
bank opposite the expansion basin.
6.7.2.5. Tests Problems to date and since first operation
6.7.2.5.1. Objeclives
The test objectives were :
to identify the power and the weight which were necess
ary for moving the end gate;
to observe the movements and mooring conditions of the
ships;
(j)I UPSTREAM
I Gl gate in close~ position
(ID cof crnte ,
·'~~~tf·t?arl;~~:2:::~~:~'.:,~11 Fig. 6. 7. 7. Gate to upper reach
115
to evaluate accurately the cycle duration;
to measure the water surface oscillations and the stresses
of the different elements;
to check the characteristics and the simplicity of the
system.
6.7.2.5.2. Test results
The friction tests showed that the adherence limit is
approximatively 0. 7 while the normal operating speed is only
about half this amount.
In the event of emergency stops which require maximum
braking, slipping on the wet tracks is impossible.
Intermediate stop tests have been conducted. These may
result from incidents or accidents. Although the operation is
automated, the operator may, in exceptional circumstances
decide to operate a gradual or emergency stop on descent or
ascent of the unit.
If the operator decides to arrest the ascending unit he
proceeds through a gradual deceleration down to 90 m/h,
when the stopping brake is actuated.
The gradual stop of the descending unit is achieved in
37 s, through the pneumatic brake.
In case of a severe accident, when a unit is ascending,
traction is interrupted on all the wheels. The stop is violent;
moorings are released; the draught is reduced by 50 cm. A
heavily loaded ship would gently touch bottom, without
however any serious consequence, as the ship's bows would
land on a soft floor with a slope of 3 o/o.
In case of a severe accident when the unit is descend
ing, complete stoppage occurs in 5 seconds and less violently
than when going up. The \vater depth at the bulkhead level
increases by 40 cm \vhile the draught decreases by 26 cm.
The oscillation of the water surface rapidly decreases.
The adherence limit is never reached during emergency
braking.
Starts in the upstream direction with a water depth of
4.10 m in front were carried out. It was noticed that it was
possible to start in the upstream direction with a normal
\vater depth of 3. 75 m \Vi th only half of the driving axles.
During operation, the separation system for ships wait
ing in the upper head appeared to be very sensitive.
It is not used any more mainly because of the lo\v
barge traffic.
Some excessively sophisticated control and adjustment
automated devices are no longer used.
6.7.3. THE FONSERANNES WATER SLOPE
With rapid developments of pleasure and sport navi
gation on the Midi canal (Fig. 6. 7 .2.), saturation of the seven
lock flight at Fonserannes was anticipated. In addition, the
116
dimensioning of , this canal to the Freycinet sizes was being
continued. It was therefore necessary to build in the vicinity
of the locks a ship lift capable of accommodating 38.50 m x
5.50 m x 2.20 m barges or 6 yachts.
The first idea was to build a 13.62 m lift lock with a
water saving chamber.
The final choice was a water slope not for economic
reasons, in the case of Fonserannes, but rather because such
a structure \vould, thanks to its prototype nature, make it
possible to test its application for higher lifts and larger
dimensions.
The design of Fonserannes takes into account the
experience gained with the operation of the Montech \vater
slope. Similarities and differences between the two structures
will be indicated later.
The present flight of locks is being maintained in
working order, on the one hand, as a by-pass in case the
water slope cannot handle all the traffic and, on the other
hand, as an outstanding example of XVIIth Century
engineering achievement (the structure was completed in
1681).
6. 7.3.1. Dimensions
Lift
Slope
Useful length of the slope
Height of the side walls
13.62 m
5%
272m
4.90m
Water depth at the forward end in the case of
a self-propelled unit 4.50m
3.10 m in case of 6 yachts
Length of the water wedge
self-propelled unit
yachts
Mass of the water wedge
self-propelled unit
yachts
Ship tonnage
90m
62m
1,200 t
600 t
350 t 38.50 m x 5.50 m x 2.20 m
6.7.3.2. The moving bulkhead (Fig. 6.7.8. and 6.7.9.)
6.7.3.2.1. General description
The moving bulkhead includes :
a frame made of 2 wall plates (one at each wall) of the
steel caisson type, with a rear cross bar on which the
front pushes, a cross-bar \Vhich accommodates the suspen
sion gear of the front and of the bumper and which
serves as a lateral bracing for the wall plates;
the front of the bulkhead;
the bumper.
The mass of the whole system is 160 t.
Each of the cross-bars is supported by 9 wheels equipped
with tyres and moves on the crown of the trench side walls
(\vhile in Montech, the two driving units are each supported
by 16 wheels which run on reinforced concrete side tracks).
Transverse guiding is ensured by 4 solid rubber tyre
vertical axis wheels (2 wheels for each wall plate).
6.7.3.2.2. The propelling system
The system is hydro-electrically self-propelled and sup
plied by the public network.
The propelling chain includes :
ten 110 kW electric motors \Vith 1,500 tr/min;
ten '!:eversible hydraulic pumps.
The set of motors is placed under a sound insulated
hood and is protected against the weather.
The pumps supply 18 hydraulic motors which are
incorporated in the rims with reducers and disk brakes (Fig.
6.7.10.·).
The system is fully reversible; the near zero operation
requires no stop at all and induces no significant heating.
When descending, the ten electric motors serve as
pumps which act through a generator, thus returning to the
public network a certain quantity of current. The movements
are extremely fast but gradual.
room
ower um sets
wheels
©front buffer
@service channel
Fig. 6. 7.8. Fonserannes - Perspective view of driving railcar
The bulkhead is controlled from a cabin located on the
rear cross-bar; this position of the cabin ensures very good
visibility both upstream and downstream when the bulkhead
is raised and when it is lo\vered.
The driver of the self-propelled unit directly commands
the major part of the operations without any intervention of
the very sophisticated automated devices used initially in
Montech.
6. 7 .3.2.3. Braking
Ordinary braking proceeds through energy recovery.
When stopped, the unit is maintained at a standstill by
mechanical brakes which act in the absence of pressure or
voltage (24 V).
When ascending, emergency stops are actuated through
the flywheels mounted on the pump sets. During emergency
stops when descending, oil is prevented from freely moving
in the pumps and constrained to go through properly gauged
pressure limitors.
After such emergency stops, mechanical brakes are
autoinatically brought into operation. These brakes may also
be operated by the operator in an emergency or in the case
of excessive speed when descending.
6. 7 .3.2.4. Comparison with iliontech
When compared with Montech, the following advantages
and differences may be listed :
two 740 kW diesel motors (1,480 kW in Montech)
ten 110 kW electric motors (1,100 k\v in Fonserannes)
supplied by the electrical network;
substitution of the 2 noisy diesel motors by very quiet
hydraulic transmission;
in Fonserannes, energy is recovered when descending,
power being returned to the electrical network;
in Montech, self-propelled units move on tracks on the
sides of the channel;
in Fonserannes, they run on the side walls of the
channel, which entails a 30 % concrete saving;
in Montech, there is a side control cab having restricted
visibility;
in Fonserannes, a central cab \vi th complete visibility.
improved aesthetics in Fonserannes.
6.7.3.2.5. The bulkhead
There is no major difference as compared with the
Montech bulkhead : the sealing system is identical \vith the
exception of the fine filtration of the injection water, \Vhich
has not been incorporated.
117
; ' 'I
.._____-f-.!__ _ -------- _, ___ 11_6SQ
I j ' . l!L_! ' I ]
@ hoko
F
, i I /-1 I I r, I . "-,, ~~
"
Fig. 6. 7.10. Eleuation of a wheel
6. 7 .3.2.6. llfooring of vessels
._ __ )~.OP ___ _.
B-B
----'""-1-'"'T
0 :
2!6!>0 - _____JI___ - - - ---- - __ '._9500 -------1----·•-l~M-- l_@C)
© ,---·---'--·-----··-
Fig. 6, 7.9. The driving uehicle
6.7.3.2.7. The buffer
The buffer is hinged to the bulkhead and has hydraulic
shock absorbers designed to absorb without damage impacts
from 350 t self-propelled units with a speed of 0.4 mis. It is
equipped with vertically mounted flexible fenders.
\ 6. 7.3.3. Civil Engineering works
6.7.3.3.l. TJ1e cJrnnnel (Fig.6.7.11.J
In principle they are identical to those at Montech but
there are no side tracks.
A 1 m x 1 m duct, parallel to the channel (Fig. 6.7.8.),
accommodates the electrical power supply rail of the
bulkhead.
6.7.3.3.2. The upper head (Fig. 6.7.12.J
B"arges are moored with release hooks which are atta
ched to the bulkhead and operated from the control cab. The channel is 6 m wide and has an overall length of
23m.
For yachts, 4 light ringing beams with several mooring
points within hand reach are used.
118
The floor of the channel, unlike Montech, does not
incorporate damping devices.
The channel includes :
Upstream, a slot for a caisson;
Two (one in Montech) valve type lowering gates which are
lowered by hydraulic rams and raised under the action of
counterweights;
A 600 mm diameter by-pass equipped with a remote
control electric servo-control valve intended to compensate
for bulkhead leakages;
- Two 200 diameter steel ducts for emptying the ram
sumps.
In Fonserannes, there is no system for releasing the
moorings of waiting vessels.
Having two gates allows the slope to be adjusted for
either commercial or pleasure and sport navigation. The
draught which is necessary for yachts is less than that
required by a barge; the wedge is therefore reduced in the,
first case, which means that less energy is required, when
ascending.
One gate only is thus used according to the volume of
the water wedge.
The existence of gates is a safety factor for the
protection of the 53 km long upper reach.
6.7.3.3.3. Lower head
The lower head (which does not exist in Montech}
consists of a 6 m wide, 24 m channel having a variable
height.
It includes :
An area at its low end for floating grounded vessels,
which has a gravity discharge \vith a 500 mm diameter
valve;
A recess for a caisson;
A gate operated by a ram which isolates the channel
when operating the bulkhead.
This gate is provided to avoid any disturbance in
lower reach on departure or arrival of the bulkhead.
6.7.3.3.4. Auxiliary equipment
the
The transformer house is located half-way up the slope.
Particular care has been taken with its architecture. Its flat
roof serves as a viewpoint for visitors.
The gate control cabins are architecturally similar.
Facilities for berthing are provided upstream and down
stream.
6. 7.3.4. Electrical power supply
Power supply is from the 20 kV/380V-l,250kVA transfor
mer station; a second 100 kVA station takes care of the
auxiliary supply.
The installed power is 1,100 kW but 700 kW meets
normal requirements.
The three phase 380 V current to the motors is through
a trolley drawn by the bulkhead, equipped so as to raise the
protection covers of the culvert and to collect the current
coming from the electrical rails connected to the transformer
house.
This system has made it possible to avoid unsightly
overhead cables.
A full load ascending the water slope uses 72 kWh and
a minimum load 36 kWh. Without a load with the bulkhead
raised takes 8 kWh.
Descending produces 40 kWh, \Vhich is fed to the public
network.
6. 7.3.5. Operation
An operating cycle proceeds in the same way as in
Montech except for two differences: the existence of two
upper gates, the most upstream one being used for barges
and the other one for yachts and the provision of a lower
gate.
Operational data are as follows :
- working speeds : 0.65 mis fully loaded (barges); 1.20 mis
partly loaded (yachts};
working acceleration and deceleration: 5 cm/s2;
accidental deceleration : 20 cm/s2 ascending; 5 cm/s2
descending;
the 272 m travel of the bulkhead takes 6 minutes.
The operational cycle is 30 minutes as compared to 80
minutes of the flight of 7 locks.
Each 15 m half-cycle allows the transportation of 1
barge or 6 yachts.
1.00
JS
' ..
' '
~
.. " " ::I -·
Fig. 6.7.11. Cross-section of channel
119
6.7.12.1 PLAN VIEW
6.7.12.2 LONGITUDINAL SECTION G) upstream control ·room
'1motJ!rn'
·1
Fig. 6. 7.12.
The \Vater slope will without any problem meet the
objective: a daily traffic of 13 barges and 200 yachts during
13 navigation hours.
6.7.3.6. Acceptance tests - Problems met with the first and subsequent operations
Tests were carried out at the end of 1983.
Shortly after the first servicing, an incident occurred
during the descent.
Following a large oil leakage on the southern runway,
wheels lost their grip, which entailed locking the mechanical
emergency brake. The southern side wheels slipped on the
oily track without braking while the northern bank mechani
cal brakes were not sufficient to stop the descent. The unit
was finally stopped in the lower head, all the tyres being
damaged.
120
Substantial changes are currently being implemented
before resuming operation during the Summer of 1987.
The main changes are :
introduction of a system intended to limit the excess
rotation speed of a wheel, compared with the average of
the other wheels;
- introduction of a hydraulic braking circuit independent of
the main circuit;
- introduction of a special rubber type of pneumatic tyre
having better adhesion;
- improvement of the profile of the runways;
- provision of drop pans and drip flaps to avoid oil leakages
onto the run\vays;
- continuous monitoring of oil levels in the tanks and in
the leakage drop pans;
- new braking blocks for each \Vheel.
7.. Conclusions
121
7. CONCLUSIONS
Water filled tank ship lifts were first introduced at the
end of the XIXth Century for lifts of the order of 20 m
on canals built in moderately hilly areas where a
crest-line had to be passed and where there were water
supply problems. They had advantages over low lift flights
of twin locks or locks very close together or independent,
a large number of which would have unduly slowed down
traffic.
Recently, ship lifts have been built for lifts usually
greater than 30 to 40 m (present maximum lift for locks)
and for large size ships (1,350 t and over).
Nowadays, ambitious projects are being considered or even
carried out to regulate large rivers as \Vell as connections
between large hydrographic basins including the crossing
of summits.
Such projects are often multipurpose : flow regulation
(control of minimum water levels; flood control); hydro
electric power supply; navigation; irrigation.
High lift ponds (100 m and over) will often be required,
which will result in complex problems in terms of
navigation :
choice of the type of lift structure : high lift lock
flights involving reducing the normal flow of traffic or
ship lift(s);
size of the structures : large rivers may often accommo
date very high tonnage ships. So far, lift tanks or
wedges for trains of 15,000 tons or more have not yet
been designed;
- allowing for flow and water level variations (10 m and
over).
There are questions as to the maximum sizes that may
be considered for a ship lift as well as the maximum lift
a given type may accommodate.
There are many problems not all of which have been
solved.
As far as the lift is considered, a Krasnoi'arsk type
self-propelled tank incline or a water slope have apparen
tly unlimited possibilities, while the capability of lifts
with tanks compensated by counterweights is constrained
by the connecting cables.
However, they seem to be a reliable solution for major
lifts, even if no a priori solution is available.
With the ship lifts currently being operated, solutions
adopted for similar lifts vary with the characteristics of
the site and of the waterway, with the experience and the
creativeness of the designers and with the techniques and
the studies and means of execution which are currently
available.
Each case has to be considered individually.
The choice of a type of ship lift is ahvays difficult and it
requires a thorough preliminary study; civil engineering
works and electro-mechanical equipment should be closely
associated with these investigations. They jointly contri
bute to the investment, operation and maintenance costs
of the structure.
A preliminary thorough comparative study of the various
available solutions is required; it should be all embracing
and include the technical as well as the economic aspects
(in this respect, see the Bibliography).
A lift is always a prototype. Forecasting the cost is
therefore very difficult. Whatever the experience of the
designer, whatever the thoroughness of the studies, it is
almost unavoidable to exceed the initial budget cost.
The most advantageous solution is never self evident.
With gently sloping ground, the incline or the \Yater
wedge might appear to be the best solution. However, if
the same ground is naturally inadequate for variable and
repeated stresses, preliminary works required to impart
the necessary bearing capacity may lead one to prefer the
lift solution. The lift solution is also to be preferred with
steep slopes or large differences of level.
Ho\vever, if two lifts are required by the site conditions,
this would double the cost of the electro-mechanical
equipment, which would entail a re-examination of the
initial choice.
Over a length limited by the characteristics and the
fabrication, implementation and adjustment techniques of
the cables, the incline provides an easy compensation of
the tank which substantially reduces the installed power
required. With the water slope, on the other hand,
compensation of the bulkhead is very difficult, and
increases the working power required. Currently operated
water slopes have been built in areas with little exposure
to ice and snow.
If the tank is compensated, should this be achieved
through separate counterweights to the extent of having a
counterweight for each cable or rather by a limited
number of counterweights hanging on several cables?
123
In case of a double structure, should the compensation of
one tank by the other not be considered?
The water levels of the upstream and the downstream
reaches often vary. If such variations are limited (less
than 1 m) at least 2 solutions are possible. Either the
lifting mechanisms are designed to make them capable of
taking up the disequilibrium entailed by the additional
water layer \Vith a corresponding increase of power or the
structure is provided with a b-directional pumping system
ensuring a constant water level in the tank whatever the
circumstances. This last solution avoids an increase of the
lifting powers but it unfortunately requires more compli
cated equipment.
With larger level variations, far more sophisticated and
often very expensive solutions have to be considered:
- movable sills for the reaches
- passing of a crest
submersion of the tank
additional structures.
When dealing with level variations in the reaches, one
should bear in mind the average level variations resulting
from navigation, from ship entrance and leaving oper
ations, from the wind induced complex wave pattern in
the reaches, from the emptying and filling operations of
locks located downstream or upstream of the lift.
Before the connection between reach and tank is achieved,
the ship should be secured against motion, possibly
through adequate mooring or locking devices.
Should the driving mechanism of the movable part be
mounted on that part or on the fixed section of the
structure?
Both solutions are equally acceptable. Notwithstanding the
obvious advantages associated \vith gears attached to the
fixed section of the structure, the self-propelled tank
solution should be preferred for an unbalanced or out of
balance tank or bulkhead, and for a submerged tank.
The lift cannot be dissociated from the \Vaterway; even if
it is far more vulnerable than the other structures, it
should by no means interfere with the continuity of
navigation, among other things under ice conditions.
124
Generally speaking, the lift should be of the double type,
which means that it should be equipped with two tanks
so as to make it possible to maintain navigation in case
of a breakdown or during maintenance of one of the two
tanks. In the same way, the particularly crucial and
sensitive equipment of each tank should be duplicated.
In the design studies, particular care should be given to
the following :
- Exceptional load conditions which occur more frequently
than \vith a lock: ground loads vary \vith inclines and
water slopes; loads depend on water levels in the canal;
temperature variations; temperature gradients; ice
impact; earthquake impact; sudden, partial or total
emptying of one tank; cable breakage; damage to the
gates; fire in a tanker in the tank; sinking ship in a
tank; fire in the fixed part of the structure; breakdown
of the gears.
- Rigidity acts positively on the proper operation of the
structure; deformable structures should not be used \vhen
settlement may occur.
Mechanical gear, suspensions (cables, jacks, springs), tanks
and the water they contain make up a whole which is
likely to oscillate. The possible dangers of such oscillations
should be checked.
The few elements discussed above are only indicative.
They are put forward to illustrate the absence of any
standard solution. Even currently discarded solutions \vill
probably be considered again and may be implemented in
the near future. Should, for instance, transportation of
ships in the dry be rejected for ever? If not, what
minimum ship dimensions will transportation afloat
require? Conventional locks offer a solution for passing
ever increasing lifts. Combined with \Vater saving cham
bers, could this not make them an attractive alternative
for other types of lifts?
In conclusion, it must be admitted that moving
several thousand tons over several tens of metres several
times a day remains a major challenge. However,
improvements will be made in the future, whatever
method is employed, be they ship lifts or some other
device.
Bibliography
125
BIBLIOGRAPHY
GENERAL REFERENCES
H. DEHNERT, Schleusen und Heberwerke. Berlin, Springer (1954).
H.W. PARTENSCKY, Binnenverkehrswasserbau. Schiffsheberwerke.
Berlin, Springer (1984).
P .l.A.N .C., Bulletins and Congress papers.
THE HENRICHENBURG FLOAT LIFT
- lnbetriebnahme des Neuen Schiffshebewerkes Henrichenburg in Wal-
trop. Herausgegeben von der Wasser- und Schiffahrts- Direktion
Miinster, (1962) 79 p.
- Schiffshebewerk Henrichenburg in Waltrop. Herausgegeben von den
an der Ausfiihrung beteiligte Stahl- und Maschinen- baufirmen. 73.
- H.J. ROLOFF, Die Tiefbau- und Stahlbau-Arbeiten filr das Schif
fshebewerk Henrichenburg in Waltrop. VDI-Z., 103, Nr. 31 (1961)
- J. ILLIGER, Das Schiffshebewerk Henrichenburg in Waltrop.
Hansa, 100, Heft 9 (1963), p. 907-914.
- H. SCHULZ, Bauliche Durchbildung der Schwimmer des Schrif
fshebewerkes Henrichenburg. Schweissen und Schneiden, 13, Heft 9
(1963), p. 396.
- J. ILLIGER und H.G. BRAUN, Schiffshebewerk Henrichenburg in
Waltrop, Tiefbau, 4, Heft 10 (1962), p. 671-691.
THE LUNEBURG FUNICULAR LIFT
- Schiffshebewerk Liineburg in Scharnebeck Wasser-und Schiffahrt
direcktion, Hamburg · Neubau abteilung fiir den Bau des Elbe ·
Seitenkanals · Neubauamt Abstiegbauwerke.
- R. WAGNER, Die Stahlconstruction des Schiffshebewerkes Liineburg
·Der Stahlbau ·July 76 ·Volume 7.
- Elbe· Seitenkanal ·Hans Christians Verlag Hamburg p. 30-39.
THE STREPY-THIEU LIFT
- M. REMOUCHAMPS. L'ascenseur de Strepy-Thieu. Bulletin n°
48/1085 de l'A.I.P.C.N. - p. 93-99.
- Ministere des Travaux Publics de Belgique - Strepy-Thieu - 1985.
THE RONQUIERES INCLINE
- J. DE RIES. Etude sur le mouvement de l'eau et les forces
d'amarrage des bateaux dans un sas mobile. Annales des Travaux
Publics de Belgique, n ° 3, 4 et 5 de 1962.
- E. V ALCKE et G. WILLEMS. Les ouvrages de navigation pour
grandes chutes · Le plan incline de Ronquieres · Livre d'hommage
AF.CAMPUS.
- G. WILLEMS, E. V ALCKE, R. ROORYCK et J. SEYVERT. Le
plan incline de Ronquieres. Rapports du XXIilme Congrils Inter-
nation de Navigation· A.l.P.C.N. Stockholm 1965.
- G. \VILLEMS. Le plan incline de Ronquiilres • Revue de la
Navigation interieure et rhenane. n° 15. septembre 1968.
- Ministere des Travaux Publics · Ronquieres 1965.
THE ST-LOUIS/ARZVILLER INCLINE
- R. DESCOMBES. • Les equipements mecaniques du plan incline
transversal d' Arzviller . Saint-Louis • La Construction, n ° 5 - mai
1971.
- M. MARCHAL . M. TIPHINE. Le plan incline d'Arzviller - Revue
de la Navigation interieure et rhenane, 25 septembre 1964.
- R. V ADOT · M. MARCHAL · R. LECLERCQ. Ouvrages de
frachissement pour grande hauteur de chute · XXIeme CongrBs
International de la Navigation (Stockholm 1965).
- E. SCHWARCZER. Le plan incline de Saint-Louis • Arzviller,
Construction, revrier 1968.
- Le plan incline transversal d' Arzviller · Saint-Louis rem place 17
ecluses • Divers auteurs . Revue de la Navigation Fluviale
europeenne. Numero special· Guin 1970).
THE KRASNOIARSK INCLINE
- M. BODNEV. Ein neues Schiffshebewerk am Jenissej. · Schiff und
Hafen - Heft 10/1967 p. 732-734.
- R. TENAUD. Ouvrages de franchissement des grandes chutes en
U.R.S.S .. Revue de la Navigation interieure et rhenane · 10 fevrier
1968. p. 74-77.
- D. WULF. Schiffshebewerk Krasnojarsk am Jenissej Zeitschrift fiir
Binnen · Schiffahrt und \Vasserstrassen - 5180 · p. 172-176.
THE WATER SLOPES
- J. AUBERT. La pente d'eau remplacera-t-elle !'ecluse ? Navi-
gation, Ports et Industrie. 10 octobre 1971. p. 591-596.
127
- J. AUBERT. Le prix des pentes d'eau . Navigation, Ports et
Industrie • 10 mai 1973 · p. 291-296.
- M. CANCELLONI et P. CHAUSSIN. La pente d'eau de Montech .
Navigation, Ports et lndustrie · 10 mai 1973 - p. 297-305.
- J. DONNAREL. La pente d'eau de Fonserannes · Acier · Stahl ·
Steel 4/1983 · p. 123-127.
- L. PARIZOT. La pente d'eau de Fonserannes - Travaux Avril 1984
. p. 37-43.
- J. AUBERT. Philosophie de la pente d'eau - Travaux Avril 1984 •
p. 44-52.
128
COMPARATIVE STUDIES: 'Locks and ship lifts'
- J. ILLIGER. Schleu.sen und Hebewerke zur iiherwindung grosser
HOhenunterschiede im Zuge von Wasserstrassen.
Zeitschrift fiir Binnenschiffahrt und Wasserstrassen 1971, Heft 2,
Seite 38 - 52.
- R. KUHN. Die Uberwindung der hohen Stufen im Scheitelbereich
des Main-Donau-Kanals. Wasser-Jahrbuch 1969, Verlag Ernst &
Sohn, Berlin-Miinchen Seite 315 · 320 .
- R. KUHN. Die Uberwindung der ho hen Stufen des Main-Donau
Kanals. VDI-Berichte (1969) Nr. 145.
}jh PRINTING PUVREZ s.a. f:jU Avanuo For.,ny 59 - 1000 BW$SOI' • 49412