August 27, 2015
Weekly Inspection Update Design Update Permitting Update R-O-W Update Utility Relocation Update Funding Update Schedule Review Other Items
Bridge Condition Unchanged
• Pin & Hangar Inspection scheduled for
Sunday, September 13, 2015
99% Complete ◦ Design completion by end of this month ◦ F&T finishing up detail drawings
Permitting Acquisition Remains on Schedule
UPRR
◦ UPRR continuing review process. Not anticipating major issues
Environmental – ◦ Project Considered for “Categorical Exclusion” Not considered to have a significant effect on “human environment”
Others
◦ Corps of Engineers: Submit for review by mid-September ◦ KDWR: Submit for review by mid-September
Shawnee County (NE, NW, SE Quadrants) ◦ All R-O-W has been acquired
Wabaunsee County (SW Quadrant) ◦ Wabaunsee County has contacted property owners,
staked R-O-W limits and is in process of acquiring ◦ Anticipate being completed by mid-September
No Change
◦ Will send final plans to utilities once design complete
◦ Not a critical path item at this point
TIGER Grant ◦ Comm. Buhler met with Senator Moran and USDOT Sect. Foxx
◦ Anticipate TIGER Grant award announcements in October
KDOT Request ◦Developed draft request letter and funding strategy outline to be sent to KDOT
City of Topeka (Sales Tax Extension) ◦ Interlocal Agreement Negotiations Upcoming
TASK
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Design
Right-of-Way
Utility Adjustment
SNCO / WabCo Agreement
Permitting
UPRR Agreement
SNCO BID
SNCO Award Contract
Construction
NOTE: Progress Schedule assumes NO Federal Funding
PROJECT PROGRESS SCHEDULE
2015 2016 2017
NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130
SNCO Project No. S-121015.00
KDOT Project No. 89C 0066-01
Bridge Const.
Road Tie-In, Final Grading,
Seeding
REMAINING PROJECT COSTS
2015 2016 2017 Total
Design $115,625* $115,625*
R-O-W $124,000* $124,000*
UPRR Permit $35,000* $35,000*
Utility Relocation $100,000* $100,000*
Construction $8,014,000 $12,021,000 $20,035,000
Const. Engineering $641,120 $961,680 $1,602,800
Contingencies $100,000* $641,190 $961,785 $1,702,975
TOTAL $374,625* $9,296,310 $14,044,465 $23,715,400
*Funding is Currently Available