118
MINISTRY OF INDUSTRY AND TRADE THE WORLD BANK RENEWABLE ENERGY DEVELOPMENT PROGRAM Credit code: IDA Cr.4564-VN ENVIRONMENTAL MANAGEMENT PLAN COC SAN SMALL HYDRO POWER PROJECT LAO CAI PROVINCE For Lao Cai Renewable Energy (Vietnam) JSC Lao Cai, September 2015 SFG2200 V2 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

SFG2200 V2 Public Disclosure Authorized

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SFG2200 V2 Public Disclosure Authorized

MINISTRY OF INDUSTRY AND TRADE THE WORLD BANK

RENEWABLE ENERGY DEVELOPMENT PROGRAM

Credit code: IDA Cr.4564-VN

ENVIRONMENTAL MANAGEMENT PLAN

COC SAN SMALL HYDRO POWER PROJECT

LAO CAI PROVINCE

For Lao Cai Renewable Energy (Vietnam) JSC

Lao Cai, September 2015

SFG2200 V2

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: SFG2200 V2 Public Disclosure Authorized

2

ABBREVIATIONS

MONRE Ministry of Natural Resource and Environment

DSP Dam safety Panel

EPC Environmental protection commitment

EMP Environmental management plan

GDoE General Directorate of Energy

SHB Sai Gon – Hanoi Joint Stock Commercial Bank

SHP Small hydropower project

MOIT Ministry of Industry and Trade

REDP Renewable Energy Development Program

QCVN Vietnamese Standard

QLMT Environmental management

UBND People Committee

VH-LS Historical – Culture

WB The World Bank

Page 3: SFG2200 V2 Public Disclosure Authorized

3

TABLE OF CONTENTS

SCREENING OF SAFEGUARD POLICIES FOR SUBPROJECT UNDER

REDP ................................................................................................................. 4

1. INTRODUCTION ............................................................................... 16

1.1. Project background .............................................................................. 16

1.2. Project Sponsor .................................................................................... 16

1.3. Objectives of the project ...................................................................... 16

1.4. Organizing the project and implementing the EMP ............................ 16

2. PROJECT DESCRIPTION .................................................................. 17

2.1. Project Location ................................................................................... 17

2.2. Project description................................................................................ 18

2.3. Construction method ............................................................................ 19

3. LEGAL AND TECHNICAL BASIS TO IMPLEMENT EMP ........... 20

3.1. Legal and technical documents ............................................................ 20

3.2. Technical basis applied in EMP ........................................................... 21

4. KEY ENVIRONMENTAL AND SOCIAL ISSUES .......................... 22

4.1. Environmental issues ........................................................................... 22

4.2. Key Social Issues ................................................................................. 38

5. MITIGATION MEASURES FOR NEGATIVE IMPACTS ............... 39

6. ENVIRONMENTAL MONITORING PLAN .................................... 60

7. COMPLANATION ON ENVIRONMENT AND PENALTY ........... 75

8. ENVIRONMENTAL MANAGEMENT CAPACITY BUILDING

PLAN .............................................................................................................. 75

8.1. Development phase .............................................................................. 75

8.2. Construction and operation phases ...................................................... 75

9. ENVIRONMENTAL MANAGEMENT COST ESTIMATION ........ 76

10. PUBLIC CONSULTATION AND DISCLOSURE ............................ 78

10.1. Public consultation ............................................................................... 78

10.2. Disclosure ............................................................................................. 82

List of reference documents ............................................................................ 83

Annex 1. List of people who prepared EMP ................................................... 84

Annex 2: Responsibility of construction supervision consultant .................... 85

Annex 3. The approval documents on EPC .................................................... 90

Annex 4. Minute of Public Consultation Meetings ........................................ 92

Annex 5: Approval for reclamation, change of land use purpose for

implementation of the Project ....................................................................... 112

Annex 6. Public consultation meeting pictures ............................................. 114

Annex 7: Site photos ..................................................................................... 116

Page 4: SFG2200 V2 Public Disclosure Authorized

4

SCREENING OF SAFEGUARD POLICIES FOR SUBPROJECT UNDER REDP

TABLE A: COC SAN HYDRO POWER PROJECT SCOPING CHECKLIST

ISSUE

RELEVANT?

OUTCOME

Is the subproject located in or near a

national park or other government

designated protected area?

NO

If a dam, is the subproject more than 15 m

in height? YES

DSP has reviewed

If a dam, is the subproject 3 million cubic

meters in capacity? NO

DSP has reviewed

Will the subproject result in change of land

use and resettlement of affected people?

YES

Agricultural land has been

acquired for project.

There is only 1 household

in project area have to

resettlement.

Compensation and

resettlement plan has been

made.

Do ethnic minorities live or use the area

affected by the project? YES

Ethnic plan has been

made.

Will the subproject affect physical or

cultural resources that may be significant? NO

Is the subproject situated on or near to an

international waterway? YES

Coc San SHP is located

on the Dum River. Dum

River is primary branch of

Thao River which rises at

the high mountain in

China and flows through

Sa Pa, Lao Cai province,

Vietnam then discharges

into Hong River

belonging to Bac Cuong

commune, Lao Cai city.

Therefore, the

international water way of

WB (OP/BP 7.05) is

applied for this project

Has an EIA/EPC been completed?

YES

EPC was approved by Bat

Xat district people

committee by Decision

No. 23/ UBND-GXN

dated 7 December, 2007

and Sa Pa district people

committee by Decision

No. 1024/UBND-TNMT

dated 11 December, 2007.

Have all Approvals from Lao Cai

Province’s People’s Committee been YES

Page 5: SFG2200 V2 Public Disclosure Authorized

5

ISSUE

RELEVANT?

OUTCOME

obtained?

Has public consultation of those people

potentially affected by the subproject been

undertaken? YES

Consultation meetings

were held by developer

with participants from

representatives of affected

households and local

authorities of Tong Sanh,

Coc San communes, Bat

Xat district, Trung Chai

commune, Sa Pa district,

Lao Cai province.

Has an environmental management plan

been completed? YES

Will the subproject affect downstream

flows, ecology and those living

downstream? YES

Consideration was taken

during preparation of

EMP

Have construction impacts been fully

mitigated? YES

Consideration was taken

during preparation of

EMP

Will the subproject result in construction of

new access roads and how will access be

managed? YES

Consideration was taken

during preparation of

EMP

Will the subproject result in construction of

new transmission line and how will be

managed? YES

Consideration was taken

during preparation of

EMP

Page 6: SFG2200 V2 Public Disclosure Authorized

6

TABLE B:

PRESCREENING DOCUMENT CHECKLIST

DOCUMENT

INCLUDED?

Feasibility Study Yes

Approved EIA Yes

Environmental Management Plan Yes

Compensation Plan Yes

Ethnic Minority Plan Yes

Approval documents of Environmental

protection commitment by Bat Xat district

people committee and Sa Pa district people

committee.

Yes

Dam safety review by Dam Safety Panel Yes

Other approvals: if required Yes

Page 7: SFG2200 V2 Public Disclosure Authorized

7

TABLE C. SCREENING OF WB’s SAFEGUARD POLICIES

Environmental Assessment (OP/BP 4.01): potential environmental impacts of the

subproject includes those relevant to land acquisition, vegetation cover loss, impact

to terrestrial ecosystem, air pollution by dust, exhaust gases, noise from

construction activities, impact of surface water quality, water usage in downstream,

aquatic bio-diversity as well as impact of landslide, erosion, sedimentation etc.

These impacts can increase cumulative effects of the whole cascade. However,

these impacts could be mitigated.

Page 8: SFG2200 V2 Public Disclosure Authorized

8

* Result from the surveys shows that land from sensitive areas is not acquired for project.

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES OR

NO (tick )

OP/BP 4.04: Natural Habitats

Natural habitats are defined as land and water areas where the ecosystems' biological

communities are formed largely by native plant and animal species, and human activity has

not essentially modified the area's primary ecological functions.

1. Is the subproject located within any National Biological

Conservation Areas, (NBCAs), and National/Provincial/District

Protected Areas (NPAS, PPAs, DPAs)? (If yes, subproject is

excluded)

Yes □ No

2. Will the subproject result in significant degradation or

conversion of habitats and/or forests in protected areas, proposed

protected areas or areas that are considered of special ecological

significance? If yes, what is the consequence?(If yes, subproject is

excluded)

Yes □ No

3. Will the subproject aim to bring about changes to the

management, protection, or utilization of natural forests or

plantations, whether they are publicly, privately, or communally

owned?(If yes, subproject is excluded)

Yes □ No

4. In the case of a biomass subproject, will the subproject

undertake commercial harvesting of forests (e.g., for fuel for

biomass plant)?

(If yes, subproject is excluded)

Yes □ No

5. Is the subproject located within the buffer zone of any National

Biological Conservation Areas, (NBCAs), and

National/Provincial/District Protected Areas (NPAS, PPAs,

DPAs)? (if yes, subproject is eligible but requires permit)

Yes □ No

6. Will the subproject affect a forested area? (If yes, subproject is

eligible but requires permit of the owner or of the district’s

People’s Committee).

Yes

No

Based on the above screening, does OP/BP 4.04 apply? No

If the answer to questions 1-4 is YES, OP/BP 4.04 will apply and the subproject is NO

ELIGIBLE for refinancing

Page 9: SFG2200 V2 Public Disclosure Authorized

9

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO (tick )

OP/BP. 4.10: Ethnic Minorities (Indigenous Peoples)

Are ethnic minority people present/reside in the project area?* YES

NO

* The project made Ethnic Minority Planning Framework to implement

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO

(tick )

OP/BP 4.11: Physical Cultural Resources Physical cultural resources include

movable or immovable objects, sites, and structures, groups of structures, natural

features and landscapes that have archeological, paleontological, historical,

architectural, religious, aesthetic or other cultural significance.

Will the subproject cause temporary or permanent relocation or

any other type of impact on physical cultural resources known to

be of local, regional or national significance based on national or

Provincial lists, proposed national or Provincial lists and/or

identified during public consultation with local affected groups?

YES

□ NO

Are any physical cultural resources considered especially

important or sensitive particularly to local groups (e.g. tomb

sites)?

YES

□ NO

Are chance find procedures in place? YES

NO □

Based on the above screening, does the physical Cultural

Resources Apply? NO

Page 10: SFG2200 V2 Public Disclosure Authorized

10

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES OR

NO

(tick )

* There is 1 household has to resettlement, the resettlement and compensation plan has

been prepared.

O.P. 4.12 Involuntary Resettlement

The Involuntary Resettlement safeguard will apply in those situations involving involuntary

taking of land and involuntary restrictions of access to legally designated parks and

protected areas. The policy aims to avoid involuntary resettlement to the extent feasible, or

to minimize and mitigate its adverse social and economic impacts.

1. Is any land used by people/organizations likely to be acquired

as a result of the subproject? Yes No □

2. Will any subproject activity involve restrictions of use on

adjoining land? Yes □ No

3. Is land ownership affected by the subproject? Yes No □

4. Will there be a loss of housing or assets or incomes of local

people/organizations? Yes No □

5. Will any social or economic activities be affected by land use

related changes? Yes No □

If the answer to any of the above questions is YES, OP/BP 4.12 Apply and a Resettlement

Plan in accordance with Resettlement Policy Framework is required.

Page 11: SFG2200 V2 Public Disclosure Authorized

11

ENVIRONEMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES OR

NO (tick )

OP/BP 4.37 Dame Safety Policy

1. Is the dam height is 15 meters or greater? Yes

No

2. Is dam storage 3 million cubic meter or more? Yes

No

3. The dam height is between 10 and 15 meters but the dam

presents special complexities (for example large flood-

handling requirement, location in a zone of high seismicity,

foundations that are complex and difficult to prepare, or

retention of toxic materials?

Yes No

4. Is the dam is expected to become a large dam during the

operation of the facility?

Yes

No

5. Based on the above screening is the REDP subproject

considered to be a large dam and will a Dam Safety

Assessment be required?*

Yes

No

Page 12: SFG2200 V2 Public Disclosure Authorized

12

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES OR

NO (tick )

* Coc San SHP is located on the Dum River. Dum River is primary tributary of Thao River

which rises at the high mountain in China and flows through Sa Pa, Lao Cai province,

Vietnam then discharges into Hong River belonging to Bac Cuong commune, Lao Cai city.

Therefore, the international water way of WB (OP/BP 7.05) is applied for this project

Overall Safeguard Compliance

Does the subproject comply with the aforementioned World

Bank Safeguards?

YES

NO □

Based on the screening results above it could conclude that Coc San project is

categorized B level of WB environmental safeguard policy.

OP/BP 7.50 Projects on International Waterways

The objective of OP/BP 7.50 is to ensure that World Bank-financed projects affecting

international waterways would not affect relations between the World Bank and its

Borrowers and between states and also not affect the efficient utilization and protection

of international waterways. It applies to projects that involve the use and/or potential

pollution of international waterways. OP/BP 7.50 does not apply to run of the river

projects.

Is the subproject the first subproject downstream of a river

that flows from another country? YES NO

Is the proposed subproject the last project on a river that flows

into another country? YES NO

Will the subproject utilize water from or into a river or river

tributary that flows to or through or forms a border with a

neighboring country?

YES NO

Will the subproject discharge water from or into a river or

river tributary that flows to or through or forms a border with

a neighboring country?

YES NO

If a biomass subproject, does the subproject utilize or

discharge water from, or into a river or river tributary that

flows to a neighboring country, or that forms a boundary with

a neighboring country.

YES NO

Page 13: SFG2200 V2 Public Disclosure Authorized

TABLE D: ENVIRONMENTAL CONCERNS AND EMP REQUIREMENTS

Issue or Environmental Concern

(Note: Social issues and concerns are dealt elsewhere)

Is Issue or Concern

Addressed in EIA or

EPC? Yes or No

(tick )

Is Issue or Concern

Addressed in EMP?

Yes or No

(tick )

Required

Action or

Follow-up

YES NO YES NO

Air quality impacts on local communities?

Noise?

Dust?

Is in a Seismically Active or Geotechnical Unstable

Area?

Affects Integrity of Protected Areas?

Impacts on Migratory, Rare, Threatened or Endangered

Species?

Impacts on Biodiversity?

Considers Downstream Impacts?

Affect Environmental Flows?

Affect Downstream Water Quality?

Affects Fish or Fisheries?

Page 14: SFG2200 V2 Public Disclosure Authorized

14

Issue or Environmental Concern

(Note: Social issues and concerns are dealt elsewhere)

Is Issue or Concern

Addressed in EIA or

EPC? Yes or No

(tick )

Is Issue or Concern

Addressed in EMP?

Yes or No

(tick )

Required

Action or

Follow-up

YES NO YES NO

Considers Off-site Impacts (e.g. Borrow Pits and

Aggregates)?

Aesthetic and Visual Impacts?

Impacts Cultural Property or Resources?

Causes Increased Erosion and Sedimentation During

Construction?

Involves Construction of New Access Roads?

Involves Construction of Worker Camp(s)?

Has Chance Find Procedures In Place for Physical and

Cultural Resources?

Has Waste Management Plan (Solid and Liquid Wastes)

in Place?

Is there a Reclamation Plan In Place?

Have Subproject Contingency and Notification Plan in

case of Accident or Event (e.g. Release)?

Has Included EMP and Environmental Protection

Measures as Part of Contract Provisions?

Page 15: SFG2200 V2 Public Disclosure Authorized

15

Issue or Environmental Concern

(Note: Social issues and concerns are dealt elsewhere)

Is Issue or Concern

Addressed in EIA or

EPC? Yes or No

(tick )

Is Issue or Concern

Addressed in EMP?

Yes or No

(tick )

Required

Action or

Follow-up

YES NO YES NO

Has EMP Monitoring and Supervision Procedures in

Place?

Includes Costs and Time line for EMP?

Are there any other issues of concern about the

subproject that is listed in the EIA over and above the

aforementioned issues that should be addressed?

Page 16: SFG2200 V2 Public Disclosure Authorized

16

1. INTRODUCTION

1.1. Project background

Coc San Hydropower project is invested by Lao Cai Renewable Energy

(Vietnam) Joint Stock Company. It is located on the Dum River, the second

tributary of Hong River in Lao Cai province, The Dum River originates from the

high mountain at altitude of 2.200m in China, flows through Sa Pa district along

the South-West direction then pours into Hong River of Bac Cuong commune,

Lao Cai city. Coc San project locates at middle of Dum River, between Mong

Sen headwork and Coc San power plant.

The headwork of the project is located along to the National road 4D in

the direction from Lao Cai to Lai Chau. It is far from the National road 4D and

Lao Cai city towards South-West direction around 2 km and 20 km,

respectively. The entire reservoir and headwork of Coc San hydropower project

lay in communes of Coc San, Tong Sanh, Bat Xat district and Trung Chai

commune, Sa Pa district, Lao Cai province, There are many high tension poles,

telecommunication poles in the project area.

Coc San hydropower’s installed capacity is 29.7MW; average power

output is about 127.89 million kWh, with headrace structure, daily regulation,

close energy route and powerhouse. Intake and discharge of water are on the

same stream. The main parameters: catchment area: 99.6 km2, normal water

level: 702 m, dead water level: 699 m, the entire reservoir capacity: 231.6

million m3, the area of the reservoir corresponding to the normal water level:

0.481 km2, design flow (Qtk): 7.2 m

3/s; yearly average flow (Q0): 4.6 m

3/s;

assurance flow (Qđb): 0,996 m3/s.

Coc San hydropower project is in the master plan of small hydropower of

Lao Cai province and it was allowed to be prepared the investment report by the

provincial People’s Committee.

1.2. Project Sponsor

The project is expected to be refinanced from REDP funded by WB

through the SHB.

1.3. Objectives of the project

The main objective of the project is generating electricity with average

output of 127.89 million kWh, in addition to contributing to improving

infrastructure, creating revenues for local budget, restructuring the economy and

promoting social and economic development locally.

1.4. Organizing the project and implementing the EMP

Developer: Lao Cai Renewable Energy (Vietnam) Joint Stock Company.

Project design Consultancy: Energy Development and Consulting Co.

Ltd and China Institute of Water Resources and Hydropower Research (IWHR).

The developer, Lao Cai Renewable Energy (Vietnam) Joint Stock

Company will manage and monitor the project. Developer has appointed social-

Page 17: SFG2200 V2 Public Disclosure Authorized

17

environmental staff to perform tasks related to environmental protection of the

project.

Under the regulation of the World Bank: The developer is responsible for

preparation and implementation of environmental management plan.

Environmental consultant supports the investor to prepare the Environmental

Management Plan in accordance with the policy framework for environmental

safety in the REDP which has been approved by Ministry of Industry and Trade

and ratified by World Bank.

Under the regulation of Vietnam: The project has reservoir capacity of

231.6 million m3 so the developer has made report of environmental protection

commitment (EPC) and the EPC has approved by Bat Xat district people

committee under certificate No. 23/UBND-GXN dated 7 December, 2007 and

has approved by Sa Pa district people committee under certificate No.

1024/UBND-TNMT dated 11 December, 2007.

2. PROJECT DESCRIPTION

2.1. Project Location

Coc San hydropower project locates on the Dum River, belongs to Coc

San, Tong Sanh communes, Bat Xat district and Trung Chai commune, Sa Pa

district, Lao Cai province. The dam route is located at Eastern longitude

103°54′12″ and Northern latitude 22°24′52″ in Trung Chai commune, Sa Pa

district. The power house is located at Eastern longitude 103° 56’37” and

Northern latitude 22° 26’27” in Coc San commune, Bat Xat district.

The project is far from the National road 4D and Lao Cai city towards

South-West direction around 2 km and 20 km, respectively. Base on the small

hydro power master plan of Lao Cai province, Dum River consists of 3 cascades

in succession namely Chu Linh, Coc San and Coc San Ha. Chu Linh small

hydropower project is upstream with installed capacity of 11 MW and Coc San

Ha is downstream with installed capacity of 1.4 MW.

The main works consists of headwork and energy route. The headwork

includes dam, spillway on the Dum River. The close typed energy route consists

of tunnel, intake gate, penstock, well, open typed powerhouse, discharging water

into Dum River. The reservoir locates in Trung Chai commune, Sa Pa district

and the whole energy route locates in two communes of Coc San, Tong Sanh,

Bat Xat district, Lao Cai province.

The project site is far from the nearest community around 500 m. There is

not any public work or household in the project area. The project is far from the

National road 4D in directions from Lao Cai to Lai Chau about 2 km. There are

a lot of high tension poles, telecommunication poles in project area. The project

area does not lie within the range of natural protected areas and national parks.

The National Forest Hoang Lien – Sapa is far from the project’s headwork

around 40 km on the Southwest direction.

Page 18: SFG2200 V2 Public Disclosure Authorized

18

Figure 1: Location of SHP Coc San in Lao Cai province

2.2. Project description

Table 2.1: Parameters of main components of subproject

No. Parameter Unit Value

I Reservoir

1 Catchment area km2 99,6

2 Reservoir area corresponding to normal

water level

103

m2 45,3

3 Gross storage 103m

3 231,6

4 Useful storage 103m

3 103,9

II Hydrology

1 Annual average water volume 106

m3 145

2 Annual average flow rate m3 4,61

3 Normal water level m 702

Location of SHP Coc San 29.7 MW

Coc San SHP

Page 19: SFG2200 V2 Public Disclosure Authorized

19

4 Death water level m 699

5 Designed flow rate (Qtk) m3/s 8,04

6 Annual average flow rate (Q0) m3/s 4,6

7 Assurance flow (Qđb) m3/s 0,996

III Powerhouse

1 Calculated water level m 515,17

2 Installed capacity m 29,7

3 Assurance capacity MW 4,48

4 Number of unit unit 3

5 Annual electricity production 106kwh 127,89

Source: Decision on approval of basic design

2.3. Construction method

Material, equipment:

Lao Cai Renewable Energy (Vietnam) Joint Stock Company will hire contractors

to build main work items such as dam, tunnel, intake gate, powerhouse,

switchyard, transmission line, access-internal roads. Rock after excavation of dam

foundation, powerhouse foundation, tunnels will be gathered to storage sites

which are approved by local authorities. This rock will be grinded to reuse for

project construction. It is estimated that around 68,100m3 of rock will be used

for project in which 37,500m3 of rock will be reused from excavation of dam

and powerhouse foundations and underground works. The shortage of rock will

be purchased from dealers in Lao Cai city or Sa Pa district. Sand, cement, steel,

iron, and construction material will be bought at Lao Cai city or Sa Pa districts

which are around 20 km far from project site. The volume of materials will be

transported by batch in accordance with the construction schedule.

Transportation:

Access road: Access road of project is very convenient. The National road No.4D

is mainly used as access road (Lao Cai - Lai Chau direction) then go along the

communal road at Coc San commune to project site. The developer must

upgrade 2 km of this road as access road.

Switchyard and transmission lines:

Electricity supply system for construction will be taken from 35 kV voltages

transmission line nearby construction site. Besides, the backup 200 kV diesel

generator is arranged at dam site in case cut-off electricity.

Project has to build 798m of 110 kV transmission line which connects from

switchyard of power plant to the existing national grid (110 kV Lao Cai – Phong

Tho transmission line) at Lai Chau province.

Construction organization:

The Coc San hydropower project is expected to take 2.5 years to completion of

construction phase. Activities of excavation/backfilling of soil/rock at all project

Page 20: SFG2200 V2 Public Disclosure Authorized

20

components, placing large grain size concrete at dam, placing concrete at

spillway are done in dry season while steel reinforcement, on-site formwork at

powerhouse and penstock is implemented in rainy season

Water supply: Water for construction is taken from Dum River. Domestic water

is taken from slots of small streams then filtered by man-made tanks before

using.

Campsites and auxiliary facilities:

There are about 300 workers on site at peak time. 2 campsites with the area of

about 1,800 m2 are arranged at the downstream of dam. These camps are

installed solidly and have water filtration tanks and septic toilets. The auxiliary

facility with area of 4,000 m2 which is arranged at the dam site, auxiliary blocks

No. 1, 2, 3, 5, and 6 consists of steel shuttering, form-work shop, fitting shops,

water-electric base, specialized hydraulic laboratories, explosive storage. The

rock reused storages and disposal grounds with the area of 4.1ha are arranged at

downstream of powerhouse.

3. LEGAL AND TECHNICAL BASIS TO IMPLEMENT EMP

3.1. Legal and technical documents

Water Resources Law No. 17/2012/QH13 dated June 21, 2012;

Environmental Protection Law No. 55/2014 / QH13 dated June 23, 2014;

Forest development and protection Law No. 29/2004/QH11 dated December 3,

2004;

Electricity Law No. 28/2004/QH11 dated December 3, 2004 and the Electricity

Law No. 24/2012/QH13 dated November 20, 2012, amending and supplementing

a number of articles of the Electricity Law No. 28/2004/QH11;

Land Acquisition Law No. 45/2013/QH13 dated November 29, 2013

Decree No. 149/2004 /ND-CP dated July 27, 2004 of the Government on

regulating the licensing of exploration, exploitation and use of water resources,

discharge of waste water into water sources;

Decree No.197/2004 /ND-CP of the Government dated December 3, 2004 on

"Compensation, support and resettlement when the State recovers land".

Decree No. 106/2005/ND-CP dated August 17, 2005 on regulating and guiding

the implementation of some articles of Electricity Law on safety protection of

high-voltage grid

Decree No. 23/2006/ND-CP dated March 3, 2006 of the Government on

enforcement of law of protect and develop forests;

Decree No. 32/2007/ ND-CP dated March 30, 2006 of the Government on

endangered animals and plants management

Decree No. 59/2007/ND-CP dated April 9, 2007 of the Government on solid

waste management

Decree No. 72/2007/ND-CP dated May 7, 2007 of the Government on dam

safety management.

Page 21: SFG2200 V2 Public Disclosure Authorized

21

Decree No. 112/2008/ND-CP dated October 20, 2008 of the Government on the

integrated exploitation of environmental resources and hydropower reservoirs

management and protection

Decree No. 81/2009/ND-CP dated October 12, 2009 of the Government

amending and supplementing a number of articles of Decree No. 106/2005/ND-

CP of the Government dated August 17, 2005 on regulation and guiding the

implementation of some articles of electricity Law on safety high-voltage grid

protection

Decree No. 69/2009/ND-CP of the Government dated August 13, 2009

additional regulations on land use planning, land prices, land recovery,

compensation, support and resettlement.

Decree No. 18/2015/ND-CP dated February 14, 2015 of the Government on

Environmental protection planning, strategic environmental assessment,

environmental impact assessment and environmental protection plan

Decree No. 67/2012/ND-CP of the Government dated September 10, 2012

amending and supplementing a number of articles of Decree 143/2003/ND-CP of

the Government dated November 28, 2003 detailing a number of articles of the

Ordinance on exploitation and protection of irrigation building

Circular No. 24/2013/TT-BNN dated May 6, 2013 of the Ministry of Agriculture

and Rural Development regulation on alternative forest when converting forests

to other purposes

Circular No. 27/2015/TT-BTNMT May 29, 2015 of the Ministry of Natural

Resources and Environment strategic environmental assessment, environmental

impact assessment and environmental protection plan

Circular No. 12/2011/TT-BTNMT April 14, 2011 of the Ministry of Natural

Resources on hazardous waste management.

Decision of the Prime Minister No. 186/2006/QD-TTg dated August 14, 2006 on

forest management.

Decision No. 68/2008/QD-BLĐTBXH December 28, 2008 of the Ministry of

Labor, War Invalids and Social Affairs on regulation of list of equipment,

personal protective equipment for workers doing risk factors and hazardous jobs.

Decision No. 16/2008/QD-BTNMT December 31, 2009 of the Ministry of

Natural Resources and Environment on national environmental standards.

Decision No. 12/2008/QD-BTC of the Ministry of Industry and Trade dated June

17, 2008 on promulgating national standards of electrical safety.

Decision No. 18/2007/QD-PPC October 2, 2007 of Dien Bien People Committee

on regulation of environmental protection in Dien Bien province

Decision No. 19/2007/QD-PPC October 2, 2007 of Dien Bien People Committee

promulgating the regulation on management of usage of water resources in the

Dien Bien province.

3.2. Technical basis applied in EMP

QCVN 05: 2013/BTNMT - National Technical Standard on ambient air quality.

Page 22: SFG2200 V2 Public Disclosure Authorized

22

QCVN 40: 2011/BTNMT - National Technical Standard on industrial waste

water

QCVN 26: 2010/BTNMT - National Technical Standard on noise

QCVN 27: 2010/BTNMT - National Technical Standard on vibration

QCVN 25: 2009 / BTNMT- National Technical Standard on waste water of

landfills

QCVN 19: 2009/BTNMT - National Technical Standard on industrial emissions

of dust and inorganic substances

QCVN 03: 2008/BTNMT - National Technical Standard on permissible limits of

heavy metals in soil

QCVN 08: 2008/BTNMT - National Technical Standard on surface water quality

QCVN 09: 2008/BTNMT - National Technical Standard on groundwater quality

QCVN 14: 2008/BTNMT - National Technical Standard on domestic waste

water

QCVN 02: 2008/BCT - Vietnam standards on safety in the storage, transport,

usage and disposal of industrial explosives

4. KEY ENVIRONMENTAL AND SOCIAL ISSUES

4.1. Environmental issues

Table 4.1: Environmental issues of project

TT Impacts Impact description

PREPARATION AND CONSTRUCTION PHASE

1 Land acquisition Acquired land for project construction: 52.94 ha

20.33 ha for reservoir

19.66 ha for main components such as penstock,

tunnel gate, underground adits No. 1 and 2,

powerhouse, switchyard, access road etc.

12.95 ha for campsites, disposals, material

storages for project construction.

The whole of acquired land is located in

communes of Coc San, Tong Sanh, Bat Xat

district and Trung Chai commune, Sa Pa district,

Lao Cai province. Share of land use consists of

agricultural land, cultivated forest land, stream and

river land, fallow land with bush, bamboo and

bald land etc.

(Refer Table 4.2 for more detail)

Impact assessment: there is not any household has to

resettlement, a compensation plan needs to prepare to

ensure the interests for impacted households, and the

negative impact is average.

Page 23: SFG2200 V2 Public Disclosure Authorized

23

TT Impacts Impact description

2 Landslide, erosion and

sedimentation

Cause of landslide/erosion

- Construction activities of headwork such as

spillway, penstock, underground No. 1 and 2,

powerhouse, switchyard etc. need to

excavation/backfilling leading to expose of risk of

landslide/erosion at these sites.

- Process of landslide can be increased when

construction of dam and storage water in reservoir

especially at unstable ground. Furthermore, in case

of long, heavy rain and water level rising, the new

land is submerged leading to partial landslide

Project features:

- The geological feature of Mong Sen dam route is

accessed quite well. The left foundation of

powerhouse is stable. In general, work geological

condition of energy route including penstock,

powerhouse in the left side is best.

- Mong Sen reservoir is located at Mong Sen bridge

area, downstream of confluence of Ngoi Dum and

Ta Phin streams. Reservoir is mainly formed base

on stream bed and expanded toward right side so

gentle slope (100-20

0) while the left side is

mountain side with high slope (300-40

0).

- Along to Dum River from Sa Pa to Coc San

powerhouse area, the landslide phenomenon is

frequent occurrence because of high slope of

mountain sides (300-45

0). Coc San powerhouse site

usually experiences landslide. The landslide

phenomenon in vegetation cover and weathered

rock often happens during rainy season.

- At the Coc San powerhouse area on the right and

left sides of Dum River, landslide phenomenon

often occurs at cliff which is along National road

No. 4D and two sides of Ngoi Dum banks at

altitude of +120.0 - +300.0 with the length of 100-

200 m.

In case of exploding mine or excavation of

foundation leading to loss of gravity balance, new

landslide is possible at the powerhouse site which

has high sloping terrain. The contractor should

pay attention when construction and strict

monitoring at the sites exposing to risk of large

landslide so that could apply appropriate

mitigation measures.

Impacts of landslide/erosion:

Page 24: SFG2200 V2 Public Disclosure Authorized

24

TT Impacts Impact description

- Sedimentation of Dum River and reservoir

- Reduce water quality

- Changing of water flow in downstream

- May damage to life and assets of workers or local

people nearby

Impact assessment: Average negative impact if do

not comply strictly mitigation measures of

landslide/erosion.

3 Impacts on surface

water quality

The main reasons cause to water surface pollution

in the construction phase:

- Domestic waste water from 300 staffs/workers in

project site (at peak time).

- This type of waste water contains BOD5, residue,

TSS organic substance etc.

- In average, each worker uses 31 water litters per

day. If the domestic waste is 80% to the usage

water, the average sewage of 300 workers will be

24.8 m3 per day.

- Wastewater discharging from activities such as

concrete mixing, rock/vehicle/road washing,

vehicle/machine maintaining etc. Wastewater and

run-off water from these sites will cause pollution

of surface water of project area.

- The wastewater from auxiliary facilities contains

highly alkaline concentration. It increases the

alkalinity of Dum River water and nearby streams

if it is directly discharged into these surface water

resources,

- Run-off water runoff often sweeps a large amount

of mud/soil, spilled concrete, waste etc...so it has

high concentration of solids and other impurities. It

causes increasing turbidity in downstream of Dum

River leading sediment deposition in streams’ slot

in the region, affects to life of aquatic plants in

streams and Dum River downstream. If spilled

gasoline, solid waste and construction activities are

not properly managed, this type of waste will

negatively affect to surface water when workers

directly discharge waste to streams and reservoir...

Organic waste from the decomposition of animals

and plants when storing water of the reservoir.

Impacts of surface water pollution

- Increasing of turbidity, reducing of water quality of

Page 25: SFG2200 V2 Public Disclosure Authorized

25

TT Impacts Impact description

Dum River water.

- Affecting to life of aquatic species

Project features:

Investigation result at project site and downstream

area shows that almost households living in the

surveyed area do not use Dum River water for

domestic usage. They take water from slots of

stream in the mountain to each household by

pipes. The impacts mentioned above do not much

impact to life and human health of local residents.

Decreasing of volume of Dum River water will

negatively impact to cultivation and aquaculture

of downstream. However, this impact only occurs

in the construction phase and can be mitigated.

Impact assessment: average negative impact if do

not comply strictly mitigation measures.

4 Air pollution Causes of air pollution:

- Blasting for construction of internal road, digging

of foundations

- Rock/soil excavation and backfilling

- Material transportation

- Operation of rock grinded/screened stations;

concrete mixed workshops;

- Operation of vehicles; constructed

machines/equipment

- Construction of main components.

For above items, main tasks need to carry out as

below:

- Excavation/backfilling of rock/soil: 1,147.9 x 103

m3

- Concrete works: 73 x 103 m

3

Calculation of estimated dust quantity is emitted

from excavation and backfill activities:

- Total quantity of excavation and backfilling:

1,147.9 x 103 m

3 x 2 ton/m

3 = 2,295.8 x 10

3 tons

- Total dust quantity emits during excavation and

backfilling: 2,295.8 x 103 tons x 0,4 kg/ton =

918.32 x 103

kg

Dust is also strongly emitted from road

construction parallel with activities of rock/soil

excavation and backfilling; material/rock/soil

Page 26: SFG2200 V2 Public Disclosure Authorized

26

TT Impacts Impact description

transportation; blasting for digging foundations

The dust concentration which emits in project site

may be exceeded the permission if do not apply

mitigation measures.

Besides, the operation of constructed machines,

trucks will emit toxic gas such as CO2, CO, SO2,

NOx, dust

Sand, rock, cement, steel for project construction

will be bought from dealers at Lao Cai city or Sa

Pa district which are far from project site around

20 km. As estimated,

materials/equipment/machines that serve for

project construction is transported in sequence

along National road No 4D, internal communal

roads to project site.

All main works are quite far from internal

communal roads. There is not any public work

including road/irrigation works in project site.

Dust and toxic gas pollution emitted from

construction phase only impact to environment in

narrow space, partial, short-term and depending on

construction time.

Air pollution impacts directly to workers who

work in the construction site and communities of

Coc San commune if no appropriate mitigation

measures are applied.

Transportation of construction material, machines,

equipment will emit dust and toxic gas causing

pollution to residents who live two side of road

during transportation.

Impact assessment: negative average impact in short-

term.

5 Noise Main causes of noise pollution:

- Operation of constructed facilities

- Operation of materials/equipment transported

vehicles

- Operation of concrete mixed stations, rock

grinded/screened workshops

- Blasting, using drilling machines

According to statistic data: 8-12 tons loaded trucks

have the noise level of 91-98 dBA; excavator: 90-

96 dBA; air pressed driller: 94 dBA.

As calculation, the average noise level of

Page 27: SFG2200 V2 Public Disclosure Authorized

27

TT Impacts Impact description

machines/equipment is around 72-80 dBA in the

distance of 120-200 m. Comparing to QCVN

26:2010/BTNMT, this noise level affect to workers

who are working directly in the constructed site.

Noise pollution may cause seriously negative

impacts to workers who hand directly with

blasting, using driller if they are not quipped by

labor safe equipment. The noise level is not only

generated by blasting, driller but it is increased

strongly by phenomenon of reverberation in

narrow mountainous terrain.

The nearest distance from project site to household

nearby is 500 m. Due to all works is quite far from

communities and noise only occurs in certain daily

time so the noise only impact to workers who work

directly in the construction site.

Impact assessment: average negative impact and in

short-term. This impact may be controlled if

applying appropriate mitigation measures.

6 Pollution cause by solid

waste

Sources of solid waste:

- Dump rock/soil from construction sites, material

transportation and discarded rock/soil from

excavation, drilling, blasting etc.

- Scattering concrete: from concrete mixed stations,

constructed sites, concrete scattering in

transportation process

- Scattering steel: from constructed sites and

productive workshops

- Wood, bamboo: from constructed sites, reservoir

- Domestic solid waste: from campsites, constructed

sites

During construction phase, discarded rock/soil will

be discharged from excavation of topsoil, reservoir

vegetation clearance, from excavation of

foundation serving for construction, constructed

waste containing cement, steel, wood etc. Disposal

of constructed waste without controlling may lead

to trespass forest/cultivated land and water

pollution.

Domestic solid waste: 0.3 kg/person/day x 300

persons = 90 kg/day (at peak time)

Domestic solid waste contains different types of

waste such as food waste, paper, tin waste. It may

cause unpleasant odor in case of not well

Page 28: SFG2200 V2 Public Disclosure Authorized

28

TT Impacts Impact description

controlling.

In case if clearance of reservoir does not well

leading to disintegrate animals/vegetable bodies

that causes surface water pollution.

Impact assessment: average negative impact, short-

term, could be mitigated if appropriate mitigation

measures are applied.

7 Loss of partly vegetation

cover

Total acquisition land for project is around 52.94

ha

Since the terrain feature of project site is high

mountain and hill with high slope so the vegetation

here is not diverse. Almost the lost vegetation for

project construction is brush, grass and agricultural

trees such as paddy, maize, cassava etc.

The loss of temporary vegetation cover for

disposals, borrowed pits etc. will be restored after

construction phase...

Impact assessment: Low negative impact because

vegetation covers does not diverse with low

economic and preserved value.

8 Impacts of mining (sand,

quarry etc.)

Soil backfilling for project construction is mainly

used for embanking small dyke and road

construction. The volume of soil using for project

is not much so it is estimated that this soil will be

reused from foundation of works, no need to

quarry.

Rock is reused from excavation of foundation of

dam, tunnel, powerhouse and it is screened at site

serving for project construction.

Exploiting rock from excavation of foundation by

blasting on the surface must to use the explosive. It

may cause accident at work due to trench collapse

leading to death/wounded of workers or asset

losses in case if contractors do not comply with

safe regulations.

Blasting for exploiting rock and process of

transportation of rock, sand from the borrow pits to

project site may cause air pollution by dust, toxic

gases, noise, vibration.

Due to sloping terrain, difficult transportation and

almost none of resident live nearby exploiting site

and project site so these impacts only effect to

workers who work directly in project site and local

people who transports nearby and they could be

Page 29: SFG2200 V2 Public Disclosure Authorized

29

TT Impacts Impact description

mitigated.

Impact assessment: average negative impact and

can control by appropriate mitigation measures.

9 Impacts due to

construction of

transmission line and

access road

During construction, the developer has to upgrade

about 2 km internal road; 798 km 110 kV

transmission line to connect from the project to the

national grid.

Construction of internal roads and transmission

line may cause the following impacts:

- Acquired land must be required for these activities

leading to losing a part of vegetation. The

vegetation cover of project area does not diverse,

mainly bald hill/mountain, brush, grass, partly

agricultural trees such as paddy, maize, cassava

etc.

- The terrain of project area is mainly hill/mountain

with high slope so it is exposed to landslide

leading to risks of health and life for workers

during excavation of pole foundation if the safe

measures are not complied. There is not any

household nearby project site so landslide does not

effect to houses however, landslide or soil/rock

that are swept away to farm will effect to

cultivation.

- Acquisition land is not much. Developer only

acquires small land to build 6 high tension poles

and clearance of vegetation cover for transmission

line corridor to ensure space enough and to comply

with the transmission line safeties, protected

corridor. The length of access and internal roads is

only 2 km. There is not any resident living in the

project area so this impact is small comparing to

other hydropower projects.

- Construction process of 110 kV transmission line

and internal road will cause air pollution by dust

emission during excavation/backfilling of

soil/rock, toxic gases exhaust from operation of

vehicles/machines, noise by blasting, digging

foundation and effect to transportation safety.

These impacts are not remarkable.

- This transmission line will intersect with existing

medium and low voltage transmission lines and

telecommunication cables. It may damage these

lines leading to cut-off electricity/telecom signal

for local area or expose to risks of electrical

accidents for workers or residents. However, the

Page 30: SFG2200 V2 Public Disclosure Authorized

30

TT Impacts Impact description

length of transmission line is only 972 m so these

impacts are small.

- The transmission line does not cross the army areas

and effect to the historical/cultural monuments of

Lao Cai province.

- Terrain of project area is mainly sloping

mountain/hill so it may expose to risks of

damaging to health or life of workers/local

residents if the safe measures are not applied

during construction.

- Project area has low density of population,

inconvenient traffic system. Construction of

access/internal roads for project will facilitate for

traffic of residents since the existing road is

earthen, narrow so it is quite difficult, dangerous

for local transportation especially in rainy/flood

season.

Impact assessment: average negative impact and it

can be controlled by appropriate mitigation

measures.

10 Effect to terrestrial

ecosystem

Transportation activities in project site may divide

the moving lines of some animal species which is

living in the project site.

Construction activities and land occupation by the

project may cause decreasing of vegetation cover,

and reducing of living space of animals.

Vibration from blasting, rock breaking, operation

of construction equipment will be significantly

impact to the animals living in the project area and

in the forest around the project area. Most of them

here have no rare species, such as birds

(kingfishers, lemon ...), mammals, amphibians

within the project area and surrounding area. They

will be forced to migrate, find new habitat due to

the harassment leading to reduction of number of

species. The remaining species will have

behavioral and living habits change manifest in

order to adapt the changing environment;

Almost of animals fear the noise so the noise from

construction activities such as blasting, rock

breaking, operation of machines will impact to

animals who is living surrounding project area.

Most of them here have no rare species, mainly

bird, small animals (dog, fox, reptile etc.). They

will be forced to migrate, find new habitat due to

the harassment leading to reduction of number of

Page 31: SFG2200 V2 Public Disclosure Authorized

31

TT Impacts Impact description

species. The remaining species will have

behavioral and living habits change manifest in

order to adapt the changing environment;

The workers might exploit forestry products,

wildlife to use as fuel, food. The hunting of

workers (if possible) will reduce the number of

animals; therefore it will affect the living of

species in the area

Impact assessment: Low negative impact and it

could be controlled if appropriate mitigation

measures are applied.

11 Effect to aquatic species

and fish

Due to the specific characteristics of the

hydropower project, the construction of the energy

route and dams etc. will increase the turbidity of

the stream water at the construction site, affect to

the life of fish, aquatic plants and ecosystems of a

Dum River’s section which runs through the

project area and downstream Coc San hydropower.

Rocks will fill up the habitat, minimize the

photosynthesis capacity, reduce the vision and

predatory ability of freshwater fish, and kill eggs

of some species, living in the Dum River’s section

through the construction site. In addition, the

construction of dam will separate living space of

fish between upstream and downstream of the dam

and reduce the biodiversity of species in the

region.

The strong noise and vibration from machines,

changed water quality because of oil leakage,

domestic and construction waste may negatively

impact to life and reproduction of fish and aquatic

species. Especially, blasting operation will destroy

aquatic animals in the project area

Runoff water on the surface pulling the sand will

increase the turbidity in streams, affect lives of

plants and animals underwater : fish, shrimp, crabs,

snails, frogs, eels, moss, algae, ... the project area

and surrounding areas;

Construction activity of hydropower project

impacts significantly to regional ecosystems,

especially aquatic flora and fauna in the area. The

impact of changes in environmental quality of life

of animals and plants under water only temporary

during the construction phase and in the partial

project area (mainly at the section of the Dum

River that build headwork and power plant).

Ecosystem will gradually recover and species

Page 32: SFG2200 V2 Public Disclosure Authorized

32

TT Impacts Impact description

diversity will increase as the project goes into

operation stability.

Impact assessment: low negative impact due to

capacity of recovery of ecosystem when project

will be put into operation.

12 Effect to fish and

aquatic life

Construction materials will be bought at dealers in

Lao Cai city or Sa Pa district which are 20 km far

from project site. Machines and equipment will be

transported from Lao Cai city to the site along

National roads No. 4D and internal roads.

The transportation of construction materials and

machines at peak times might affect traffic on

National road No.4D and internal road from Lao

Cai city and Sa Pa district to project area if they are

not be coordinated appropriately.

Traffic accidents can occur to people who travel on

the roads because of operation of heavy trucks.

This effect can be minimized if traffic safety's

regulations are complied with.

Impact assessment: this impact is average negative

and short term

13 Effect on cultural/

historical properties

Result from consultation with authorities and

communities of Coc San, Tong Sanh communes,

Bat Xat district and Trung Chai commune, Sa Pa

district showed that there is not any cultural and

historical relics ranked or under management of

district and provincial People Committee or

cultural and non-cultural property related to ethnic

minority

The developer has developed implementation plans

in case of detecting the monuments of cultural

history ... in the process of building

Impact assessment: low negative impact

14 Effects to natural

preservation area/

national park

The project site is not located within the natural

preservative areas. The project site is 40 km far

from the Hoang Lien Son – Sa Pa National Forest

towards Southwest.

- Impact assessment: no negative impact

15 Risks of mine, fire,

chemical spilling and

building of underground

works

During construction phase, large volume of

materials must be mobilized for building of dam,

reservoir, energy route etc. It is forced to use

explosives, oil, petrol etc. In case if do not comply

to security measures it is easy to expose risk of

exploding, spilling out of oil, petrol cause of forest

fire, vegetation destroying, pollution of air, water,

Page 33: SFG2200 V2 Public Disclosure Authorized

33

TT Impacts Impact description

soil as well as land slide danger or labour accident

by blasting.

Impact assessment: average negative impact if do

not comply strictly labour safety measures.

OPERATION PHASE

16 Change of flow in

downstream

Coc San hydropower project is under the cascade

of Dum River including 3 power plants namely

Chu Linh, Coc San and Coc San Ha. Coc San

project is downstream of Chu Linh project. Up to

now, Chu Linh and Coc San Ha projects have not

been built.

Coc San project is categorized of headrace, daily

regulation so around 6 km length of downstream of

dam may be dry.

In dry season:

- When storing water in dam, around 6 km length of

downstream from dam to powerhouse will be dry.

- Coc San project uses daily regulated reservoir so in

dry season water from upstream of Dum River will

be storage in dam. Water then is taken through

underground tunnel to penstock and turbines to run

generators. Thus, the 6 km length of stream section

will be partially shortage of water since they will

not receive water from upstream.

- However, based on the 1/10,000 scale map, in the

area of 6 km length there are 5 branches of Dum

River with quite high flow rate which supplement

water to this area event in dry season.

- Due to the climate of Northern region of Vietnam

is rainy and humidity in the spring so dry season

usually lasts about three months from November

last year to January next year

- The affected stream section is located in the

sloping terrain with many big rocks therefore the

aquatic species cannot live here. In the other hand,

there are not any households and agricultural

activities in this section.

- In spite of reduced flow in dry season, the flow is

maintained at least of 0.55 m3/s through discharged

gate. This flow can ensure the minimum volume of

water for aquatic ecosystem of this section.

In the rainy season:

- With presence of reservoir, a part of coming water

is stored in the reservoir to the normal water level

Page 34: SFG2200 V2 Public Disclosure Authorized

34

TT Impacts Impact description

for power generation and the remaining is

discharged through spillway.

- Due to abundance of water in the rainy season so

change of water flow (water is kept in the reservoir

and then transferred to penstock) in the dry stream

section not affect to life of aquatic species.

- Natural flow: the increase of water flow only

affects to the stream section which locates from the

dam to the powerhouse. However when running

through the winding streams, velocity of water is

strongly down and it nearly returns to the natural

status without the powerhouse.

- Practices from the same projects show that a new

ecosystem is formed in this stream section and it

can adapt to the drier environment.

Regarding the section of downstream behind the

powerhouse:

- The flow is still maintained when water is kept in

the reservoir in both dry and rainy seasons so the

aquatic ecosystem will not be affected remarkably.

- Storing water in the reservoir for electricity

generation not affects to water demand of local

people in downstream since they normally take

water from the higher region for their domestic

water usage.

- The water demand of local people is not much

since low population density and stream water is

not used for agricultural and fishing activities

- Fishing depending on the Dum River’s natural

flow of downstream is generally not much affected

due to the flow through the turbines is still

maintained at 0.996 m3/s in the dry season. This

flow ensures to maintaining the environmental

flow in the downstream during low peak hours in

dry season.

- In closing, changes in flow rates, water levels and

environmental impacts only occur in stream

section which is located from behind dam to the

powerhouse. However, modification in the

downstream is not noticeable because the winding

of Dum River will lessen these impacts strongly.

Impact assessment: average negative impact since

the reservoir only regulates daily with Qtk = 7.2

m3/s, Qđb = 0.996 m

3/s and always maintain the

environmental flow of 0.09 m3/s for dry section

after the dam.

Page 35: SFG2200 V2 Public Disclosure Authorized

35

TT Impacts Impact description

17 Impairment on water

quality

In case if the waste such as domestic solid waste,

domestic waste water, lubricant contained waste

water from maintaining machines/vehicles is not

well control, it will lead to pollution of Dum

River. However, this impact is not remarkable and

could be mitigated.

In the first time of filling water, water quality

depends on result of cleaning up the reservoir. If it

is well done, pollution of water will be mitigated.

On the other hand because it is daily regulation

hydropower project (storing water and generating

electricity about 5 peak hours a day) so retention

time of water in the reservoir is short. Biomass

was not long soaked in the reservoir which

can frequently exchange water. Therefore, biomass

is slowly decomposed. Water is not polluted as the

larger reservoir which has long retention time of

water.

Experience from similar projects showed that after

about 1-2 years, the quality of the water will return

to the original status without pollution.

Impact assessment: low negative impact if

complying strictly with mitigation measures.

18 Impacts on flora - The formation of the reservoir, water storage for

Coc San hydroelectric power will contribute to

improve the microclimate conditions of the area in

a positive way. Along with the formation of the

reservoir, air humidity of the area also increases,

the air temperature is well conditioned than when

there is no reservoir, create good conditions for

vegetation, trees grow.

Impact assessment: low negative impact if

complying strictly with mitigation measures.

19 Impacts on fauna After the formation of a stable reservoir, small

animals (civets, weasels, foxes, mice ...), birds,

reptiles and amphibians ... tend to go back to living

in the area near the reservoir.

Impact assessment: low negative impact if

complying strictly with mitigation measures.

20 Impacts on fish and

aquatic species

In the early years of flooding, aquatic life is

basically the group of organisms including algae,

siliceous algae, crustaceans etc. They appear

dominantly among the floating creatures.

Density of floating creatures is higher comparing

Page 36: SFG2200 V2 Public Disclosure Authorized

36

TT Impacts Impact description

to the bottom ones. In dry seasons, density of

floating creatures is lowest in the upstream area. It

is highest in the area nearby upstream and reduces

gradually toward the downstream.

In the flood season, the density of floating

creatures is lowest in the upstream area, highest in

the area near the dam and rising gradually in

downstream.

Fish fauna: During first years of water storage, the

fish prefer flowing waters, preferred spawning

migration will be reduced in number, the floating

fish species such as carp would thrive ...

Impact assessment: average negative impact if

complying strictly with mitigation measures.

21 Noise The operation of 3 units with total installed

capacity of 29.7 MW and a number of other

devices such as oil pump will cause noise ...

Based on the experience from other hydropower

plants, Coc San hydropower is type of is

categorized of headrace, not the one that uses

differential high pressure water column, so that the

noise is not considerable (about 80 dB at 1 m

position). This will meet QCVN 26: 2010/BTNMT

national noise technical standard

Impact assessment: low negative impact if

complying strictly with mitigation measures.

22 EMF Power Plant: Operation of electrical equipment

such as generators, transformers will generate an

electromagnetic field. Electromagnetic field affects

only the workers operating the equipment if they

do not comply with adequate procedures and

regulations for operating electrical equipment.

Effects of electromagnetic fields do not affect the

community as people stay away from the plant and

these impacts could be reduced

Transmission Line: If the line operation does not

comply with the regulations for the power grid

safety corridors, it will affect public health due to

the influence of magnetic field lines, especially the

one who live or work below the wire in unsafe

distance. The statistics show that with the power

grid safety corridors, electromagnetic field

intensity will be less than 5kV/m, which meets

WHO standards. Moreover, the transmission line is

798 meters length and there is no people live or

work under this line so the influence is

Page 37: SFG2200 V2 Public Disclosure Authorized

37

TT Impacts Impact description

insignificant

Impact assessment: low negative impact if

complying strictly with mitigation measures.

23 Emergency case Dam break incident: The reasons of breaking dam:

Flow and the tide of flood exceeds the maximum

water level according to design (P = 1%); because

flood forecasting is not accuracy so the plant

operation is not prompt when flood happen;

earthquake excitation, but this possibility is not

high. Upon the occurrence of a break in the total

amount of water stored in dams (231.6 x 103 m3)

will overflow downstream, causing artificial

floods, damaging life and property of the people.

This disaster cause serious consequences leading

damage to health and life as well as assets

especially in downstream area. This disaster is

analyzed and forecast in dam safety report.

Fire incident caused by electric shock: During the

operation, electric shock or fire might happen due

to transformer malfunction of electrical distribution

stations ... it will cause casualties to the operator

and economic damage to the developer.

Labor accident: It may occur when workers do not

comply with the safety regulation during the

equipment repair and maintenance. Occupational

accidents might cause workers casualties and

damage the investor’s property

This problem can be minimized if they strictly

comply with regulations on labor safety, fire

prevention and reservoir operation

Impact assessment: average negative impact since

the frequency of accident is low. However, the

responding plans should be prepared carefully and

the training plan should be done yearly.

Table 4.2: Land acquisition by main components in detail

No. Item Value Unit

1 Reservoir + dam 20.33 ha

2

Penstock, underground tunnel,

power plant, internal road etc. 19.66 ha

3 Campsites, auxiliary facilities 12.95 ha

Total 52.94 ha

Page 38: SFG2200 V2 Public Disclosure Authorized

38

Source: Compensation plan report

Table 4.3: Permanent acquisition by land use in detail

No. Impacted land Value (m2)

1 Paddy land 175,049

2 Milpa land 153,927

3 Cultivated land 7,403

4 Agricultural land 82,190

5 Pond/lake land 2,824

6 Underground land 55,680

7 River and stream 52,346

Total 529,418

Source: Compensation plan report

4.2. Key Social Issues

Table 4.4: Key social issues

No Social issues Information

PREPARATION AND CONSTRUCTION PHASES

1 Impacts to communities

Although the project does not require

resettlement, but withdraw of productive forest

land, agricultural land and land for perennial

crops of 116 households will put pressure change

on production practices and disturb people's life.

People in the project area is mainly ethnic people

with backward customary; therefore the change

of the project will affect the livelihood of some

ethnic minorities households

The process of transporting materials and

machinery for the project may affect traffic of

section 2 km from Nation road No. 4D to the

project site especially at peak time if the vehicle

coordination is unreasonable.

2 Shuffling ordinary life of the

community because of the

It is estimated around approximately 300 staffs

and workers will be mobilized at the peak of

Page 39: SFG2200 V2 Public Disclosure Authorized

39

No Social issues Information

worker's appearance, conflicts

between construction workers

and local people

construction

Due to the small population density, the effect is

not considerable

The camp sites will be arranged separately far

from Coc San residential area

Relationship between the developer and affected

people living in areas is good. Developer has

experience in managing workers, maintaining

security and order in the area when building the

other projects before.

Security situation of Coc San commune, Bat Xat

district is quite good, social evils like drugs,

robberies, fights are rare ... so the possibility of

conflict between workers and local people is low.

3 Increase livelihood and

income for people living in

adjacent to project area

During construction phase project will attract a

large number of workers; create jobs and income

stability for a segment of the population in the

region.

Ensuring food need and a variety of other

necessities for the field will provide opportunities

for production and commercial service activities

for the inhabitants in development project area.

OPERATION PHASE

4 Positive impact on local

socio-economy

Project will provide local the stability and high

quality power

Building of Coc San hydropower project will also

contribute to restructuring the economy from

agriculture to industry and service, increase

production of the local industry, create jobs and

expand other economic activities, gradually

improve people's lives in project area

Tax revenue from water resource also supplement

the provincial budget

The reservoir may allow the development of

aquaculture in the future; create more jobs and

income for workers.

5. MITIGATION MEASURES FOR NEGATIVE IMPACTS

During construction phase, developer has to sign the contracts with contractors to

build internal roads, switchyard and transmission line, main components such as dam,

Page 40: SFG2200 V2 Public Disclosure Authorized

40

powerhouse etc. These contractors will sign the subcontracts with the sub-contractors who

provide material/equipment. The responsibilities of developer/contractors/subcontractors

who must comply with mitigation are presented in Table 5.1.

The mitigation measures must be put into the bid documents/contracts by

developer/contractors as obligation of the material provided/constructed contractors. The

Lao Cai Renewable Energy (Vietnam) Joint Stock Company also signs contract to

construction supervision consultant (CSC). The CSC is responsible for monitoring EMP

implementation of contractors. The TOR for CSC is presented in the Annex 2. Nam Mo &

Nam Non hydro power joint stock Company is responsible for joining EMP into detail

technical design and construction biding contractor. The Lao Cai Renewable Energy

(Vietnam) Joint Stock Company assigned one staff who is in charged in environmental

management of Coc San hydropower project. The environmental management staff

presides and coordinates to the relevant agencies to: (i) Monitoring the implementation of

mitigation measures following EMP and EPC; (ii) Supervising, suggesting measures to

deal with negative impacts on environment (if any); (iii) Making report on environmental

management implementation and submit to the Sa Pa and Bat Xat district’s Department of

Natural resource and Environment and leaders of Lao Cai Renewable Energy (Vietnam)

JSC, SHB Bank; (iv) Participating courses on environmental management which are held

by GDoE PMB and WB.

Page 41: SFG2200 V2 Public Disclosure Authorized

41

Table 5.1: Key Mitigation and Management Measures

Issues Mitigation and Management Measure

PREPARATION PHASE (Lao Cai Renewable Energy (Vietnam) Joint Stock Company is responsible for implementation of mitigation measures)

1. Selection of project location The dam route is located at confluence of two streams of Ngoi Dum and Ta Phin. The intersection

between reservoir and stream has U opened shape at the elevation of +684 - + 687 and width of 55-60

m. The geological condition is weathered original rock with feature of low penetration, high loaded-

resistant. Requirement of dealing with penetration is not much. Dealing with penetration in original

rock may not necessary.

Selection of project site as presented above will take full advantage of available natural terrain;

mitigate excavation of stream banks and impenetrated concrete. Concurrently, it is more convenient

to connect the traffic between National road No. 4D, internal communal roads and project site.

Supported facilities of project is chosen based on the criteria such as far from surface water resource

at least 100 m, explosive storage is arranged far from communities with minimum radius of 500 m.

Scale of road ensures road design standard TCVN 8054-2005 (width face/ foundation, slope,

visibility, radius, angle of twist, body, grooves ...)

Transmission line and switchyard are chosen following the regulations and standards presented in

Decision No 34/2006/QD-BCN on safety of low voltage works.

2. Affected people Consulting with authorities of communes of Coc San, Tong Sanh, Bat Xat district, Trung Chai

commune, Sa Pa district and affected households to propose the appropriate compensation plan

which should meet expectation of affected people.

Compensation plan and its implementation must be monitored by local authorities

Consulting with representative authorities and households of Coc San commune on the location of

disposals to prevent the negative impacts to public health.

Page 42: SFG2200 V2 Public Disclosure Authorized

42

Issues Mitigation and Management Measure

(See reports of compensation plan and ethnic plan for more details)

3. Risk of bombs and mines Hiring the functional agencies to detect bombs and mines at the following sites:

- Area of all project component sites such as: powerhouse, dam, internal road...

- Reservoir area corresponding to normal water level;

- Transmission line

- Auxiliary facilities (campsites, borrow pits, quarries, construction sites etc.)

- Compensation land areas.

CONSTRUCTION PHASE (Developer/constructed contractors/material, equipment provided sub-contractors are responsible for implementation

of mitigation measures)

4. Risks of mine Developer Coordinating with constructed contractors to prepare appropriate blasting plan.

Responsible for informing of blasting plan to local authorities and residents of Coc San, Tong Sanh

communes, Bat Xat district, Trung Chai commune, Sa Pa district that aims to avoid transportation

and animal grazing at blasting areas.

Coordinating with constructed contractors to assigning the guard, using the warning alarm and traffic

arrangement when blasting.

Monitoring safe measures relating to management and using explosives which are done by

contractors

Constructed

contractors

To discuss and inform to developer on blasting plan so that developer can inform to local authorities

and communities on time.

To comply strictly with current regulations on explosive safety

Workers using explosives must be trained and certificated by the relevant authorities

To prohibit strictly person who do not have certification handing with the explosives.

Page 43: SFG2200 V2 Public Disclosure Authorized

43

Issues Mitigation and Management Measure

To disseminate frequently to workers on safe regulations in handing with explosives

Blasting should be conducted at fix time to create watchful habit for local people. The time of

blasting should be arranged at low density of traffic so that it can mitigate impacts to local

transportation. The best is lunch time (from 11 am to 1 pm).

To coordinate with developer for assigning the guard, using the warning alarm and traffic

arrangement when blasting.

5. Mining of

quarries

Developer Coordinating with contractors to inform local authorities on blasting and excavation of dam and

powerhouse foundations, tunnels.

Supervising safety of contractors in mining

Supervising environmental rehabilitation by contractors after finishing blasting and excavation.

Constructed

contractors

To comply strictly rules and regulations on technology and safety as well as environmental standards

during blasting for rock exploiting.

To ensure saving resources

Rehabilitation of environment after closing the mines (leveling and ramming the ground, plant trees

in the surface)

6. Management of

constructed &

domestic solid

waste

Developer To arrange rock/soil storage sites with the total area of 4.1 ha that locate at downstream of

powerhouse

They must meet criteria such as at least 100 m far from surface water resources, surrounded edge, do

not effect to Dum River water, cultivated land, do not locate in the areas which are exposed dangers

of landslide/erosion, should located in the hollow grounds to prevent run-off water.

Prohibit staffs/workers to discharge the domestic and constructed solid waste into non-permitted

places especially where it can easily sweep out in to surface water flows.

Monitoring the management of constructed/domestic solid waste of contractors which is presented in

Page 44: SFG2200 V2 Public Disclosure Authorized

44

Issues Mitigation and Management Measure

item No 6 below.

Prohibiting to burn solid waste to prevent risk of fire.

Constructed

contractors

Sign the contract to Urban Environmental Company, Bat Xat district to collect, treatment of the

domestic solid waste discharging from workers.

Sign the contract to functional agencies of hazardous waste to collect, treatment of construction

hazardous waste.

Top soil layer which is generated in process of foundation excavation, transmission line building is

kept in rock/soil storage sites and reused for planting trees after construction phase

Soil/rock which is generated from excavation, penstock construction etc. is kept in rock/soil storage

sites and re-used to back-filling the foundation of main components as well as borrowed pits

The discarded rock/soil at disposal sites is leveled, rammed closely. The isolated gutter is built to

collect rock/soil in case runoff water happened. Planting tree on the surface of disposals after

construction phase to mitigate sweeping out of rock/soil to stream bed

To prohibit workers discharge the domestic and constructed solid waste into non-permitted places

especially where it can easily sweep out into surface water.

Prohibiting to burn solid waste to preventing risk of fire

7. Vegetation

clearance of the

reservoirs and

construction sites

Developer To establish plan of reservoir clearance and treatment of hazardous substances before storage water

The landmarks which determine boundary of reservoir area for vegetation clearance will be marked.

Before flooding, the reservoir is cleared carefully to mitigate eutrophication and reduction of water

quality.

Prohibiting cutting off trees in the areas that are outside of the reservoir boundary.

To harvest agricultural products before flooding reservoir

Big trees must be cut off at the foot and used for making formwork. Brushwood is cleared and

Page 45: SFG2200 V2 Public Disclosure Authorized

45

Issues Mitigation and Management Measure

pulled out with the remaining part less than 20 cm.

If safe condition is ensured (without construction activities, transportation of vehicle, blasting, water

flooding and not in flood season etc.), it is allowed to local people collecting trees, products for their

usage.

Developer is responsible for coordinating with local authorities and residents in the process of

vegetation removal in the reservoir and also checking safe conditions prior to permit people

collecting trees.

Burning of disposal biomass must be followed the plan preparing by developer and ensured

compliance with regulations on forest fire prevention. Site of burning points must be far away each

other at least 500 m. Do not burn trees in strong wind conditions to avoid the spread to surrounding

areas.

8. Erosion and

sedimentation

Developer After construction phase, disposal sites and works... are backfilled by soil then rammed, pressed and

planted trees on the top to avoid erosion.

Planting trees and managing well vegetation cover at surrounded areas of reservoir especially at

semi-flooding areas to stabilize the foundation of the reservoir bank, main components and the new

sedimentation areas.

To dredge reservoir bed every 1-2 years/time

To prohibit exploiting of rock/soil or cultivation in the semi-flood areas within reservoir.

Monitoring compliance of landslide/erosion mitigation measures of contractors

Page 46: SFG2200 V2 Public Disclosure Authorized

46

Issues Mitigation and Management Measure

Constructed

contractors

During excavation of foundation it should be monitor blocks of rock which are exposed to risk of

landslide so that could provide warning and suggest the dealing measures

It should not drill/blast with large amount of rock. Should have the measures to prevent

landslide/erosion of rock which may be rolled from the top to constructing foundation. The gutters

that discharge water from the top should be dug to prevent water run into the foundation. The gutters

which could discharge water rapidly in the foundation area should be created.

The isolated gutters are built at auxiliary facilities such as material temporary loads, disposal sites etc.

to prevent run-off water which can sweep out rock/soil into stream.

After construction phase, the borrowed pits are backfilled by soil then rammed, pressed and planted

trees on the top to avoid erosion.

Activities of construction/excavation/back-filling are priority done in dry seasons.

9. Traffic and

transportation

Developer Monitoring implementation of mitigated measures which are done by contractors

Coordinating to contractors for repairing the damaged road in case the road is damaged because of

overload transportation.

Propagandize to improve awareness of compliance with traffic safe regulations for drivers

Constructed/materia

l supplied

contractors

To ensure all vehicles that use for transportation in project site have to meet standards of technical

safety and emission which are applied for vehicles.

Appropriate regulation of vehicles during construction phase to avoid traffic obstacles for local

people especially at peak time of construction.

To ensure all vehicles meeting loaded permission so that it could mitigate the damage of road.

Responsible for repairing the damaged road in case the road is damaged by contractors because of

overload transportation.

Propagandize to improve awareness of compliance with traffic safe regulations for drivers.

Page 47: SFG2200 V2 Public Disclosure Authorized

47

Issues Mitigation and Management Measure

10 Construction of

access road and

transmission line

Constructed

contractors

The roads must meet the designed standards of road presented in TCVN 8054-2005 (width of

surface/foundation, slope, radius, visibility, angle of rotation, gutter etc.).

Transmission line and switchyard are complied with the regulations and standards presented in

Decision No 34/2006/QD-BCN on safety of low voltage transmission line.

Location of high tension poles is chosen to avoid sloping points (the slope should be less than 30

degree). It should limit excavation/backfilling in case of sloping sites

The contractors are responsible for repairing the existing transmission lines or telecom lines if they

are damaged by contractors during construction and drawing the cable

Application of safe constructed measures and prevention of traffic obstacles to local people

Priority to reuse topsoil from excavation process to backfilling the foundation, do not use new soil for

that work.

Topsoil must be kept and stored in the right of way then reused to recover vegetation.

To backfill the borrowed pits, creation of the embankments, planting trees on the surface to prevent

erosion/landslide and landscape after construction phase

11. Management of

hazardous materials

(fuels, lubricants,

explosives etc.)

Constructed

contractors

To minimize storage of explosives at the construction site. In case of explosives are used and stored

in the short term it should be arrange 01 explosive storage with area of 200m2

at the left side of dam

route. It must be ensure that the storage is located more than 100 m far from surface water sources

and 500 m far from residential, camp sites. The explosive storage must be arranged stable with roof,

locked door and ventilated.

To prepare the extinguishers and oil suction apparatus in case of happening faults

To comply strictly with regulations of storage, transportation and usage of hazardous chemicals and

explosives

Labours who work directly with fuel, explosives must be trained on safe technologies relating to

chemical, explosive, fire precaution, etc.

Page 48: SFG2200 V2 Public Disclosure Authorized

48

Issues Mitigation and Management Measure

It is compulsory for workers to use the labor safe equipment when handing with hazardous

chemicals.

12. Noise Developer To monitor implementation of mitigated measures which are done by contractors

Propagandizing to improve workers’ awareness so that they do not make impact of noise to local

people.

Must coordinate to contractors to consulting authorities and local people of communes Trung Chai,

Coc San, Tong Sanh in case of necessary to blasting or construction in night time

Constructed/materia

l supplied

contractors

Requesting to check regularly on technical status of machines and equipment to ensure they meet the

noise standards which are presented in QCVN 26:2010/BTNMT to mitigate impacts to workers

The appropriate working time should be arranged, avoiding to blasting and construction in night

time.

Must coordinate to developer for permission of authorities and local people of Trung Chai commune,

Sa Pa district, Coc San, Tong Sanh communes, Bat Xat district in case of necessary to blasting or

construction in night time,

Vehicles that transport the materials, machines have to use the horn with noise level meeting the

standards of noise for transportation.

Propagandizing to improve workers’ awareness so that they do not make impact of noise to local

people.

To avoid sending vehicles during night time to mitigate noise that affects to local people living along

roads.

13. Dust Construction

contractor

For activities of excavation/leveling

- Leveling in succession

- Water spraying at works as needed on hot days

Page 49: SFG2200 V2 Public Disclosure Authorized

49

Issues Mitigation and Management Measure

- The ground in the camp sites, auxiliary and production areas is rationally arranged to avoid down

the wind dispersing of dust

For blasting activity

- To limit the dust from this process we should provide dust masks for workers in the region

For materials transportation

- Material transported vehicles must be covered by tarpaulin to avoid scattering rock/soil on the

road.

For construction activities

- To arm masks, labor protection for workers, water in the required position in the dry season to

minimize dust ...

Material supplied

contractors

Material transported trucks must be covered by tarpaulin to avoid scattering and dust.

During transportation along the roads or through the residential areas, drivers should give up way for

local people to prevent dust for them.

14. Domestic waste

water

Developer There are 2 campsites will be arranged at downstream of dam.

Each apartment is arranged septic tanks to collect and treat domestic waste water of workers. The

waste water must meet the permission standards before discharging into the environment

Construction

contractors

Propagandizing to improve workers’ awareness on environmental hygiene for workers.

To prohibit workers discharging waste into streams which leads to contaminate domestic water of the

local people

Punishing workers who do not comply with the above regulations

15. Construction

waste water

Construction

contractors

To collect grease and oil generated from car parking and equipment/machines maintenance stations

then sell to companies who treat the hazardous waste

Page 50: SFG2200 V2 Public Disclosure Authorized

50

Issues Mitigation and Management Measure

To build the pits which collect mud/sand in the following sites before discharging waste water in to

environment

16. Chance find of

cultural artifacts,

and areas/structures

of local cultural

value

Developer To prepare the chance find procedures of historical/cultural/archeological artifacts and request

constructed contractors must to comply during construction

If main components (transmission line, internal road, penstock, etc.) go through or locate in the areas

that have tombs, the developer must cooperate closely with consultant companies to adjust design

Construction

contractors

In case of any historical/cultural/archeological artifacts that may be encountered during excavation:

excavation works must be stopped. The contractors must inform immediately to developer, Coc

San/Tong Sanh/Trung Chai communal people committees, Bat Xat/Sa Pa district people committees,

Lao Cai Department of Culture, Sport and Tourism; the locale must be guarded to solve by local

authorities.

Prohibiting workers to remove any historical/cultural/archaeological artifacts. This is supposed to be

an illegal action.

Construction work will only be continued after being permitted with notice in writing from the

authorities.

Besides, the developer consults authorities and local people to find suitable solutions to move ashes

following the local customs

17. Water supply Constructed

contractors

To arrange water intake pipelines for domestic use

To build man-made tanks which use to filter for domestic usage of workers

18. Exploitation of

rock from

excavation of

foundation

Developer Coordinating with contractors to inform local authorities on plan of exploiting rock from excavation

foundation.

- Supervising safety of contractors in exploiting rock

- Supervising environmental rehabilitation by contractors after finishing.

Page 51: SFG2200 V2 Public Disclosure Authorized

51

Issues Mitigation and Management Measure

Construction

Contractors/Materia

l supplied

contractors

To establish the plan of exploiting rock from excavation foundation that provides in detail

technologies and machines as well as do procedures to getting the permission by written from local

authorities.

To comply strictly rules and regulations on technology and safety as well as environmental standards

during exploiting rock.

To ensure saving resources

Rehabilitation of environment after finishing (leveling and ramming the ground, plant trees in the

surface)

19. Safety issues in

the construction

process

Developer Coordinating with constructed contractors to establish labor safe regulations which force workers to

comply.

Assigning 01 staff to supervise labor safe issues of contractors.

- Coordinating with contractors to solve on time the risks/accidents which happen during construction.

Construction

contractor

The constructors are responsible for ensuring work safety for the whole engineers and workers on the

construction site as below:

It is mandatory for workers to attend training courses on labor safety before they are recruited to

work for company.

Supervise periodically on compliance to labor safe measures of workers at project sites.

Training courses on labor safety for workers are held periodically to improve their knowledge and

awareness in term of compliance with safe measures.

To provide necessary safe facilities for workers.

A person will be assigned to work as safe staff. He/she is responsible for supervising and speeding

up the compliance with regulations of labor safety of workers;

To have timely measures in the event of happening accidents;

Page 52: SFG2200 V2 Public Disclosure Authorized

52

Issues Mitigation and Management Measure

Do suspend all work absolutely during heavy rains or emergencies of any kind in anticipation of

landslide, accidents caused by open circuit that may lead damage for worker’s health and life

- To equip fully fire extinguishers in the building and the construction sites.

20 Management of

sanitary and safety

and prevention of

disease infection in

campsites.

Developer 01 staff that is responsible for health care of workers in the project site will be assigned by developer.

Coordinating with constructed contractors to make plan of workers’ health care during construction

phase.

Coordinating with contractors to establish the precautionary program of sexual transmitted diseases,

especially HIV/AIDS precautionary program, among labors.

- Supervising the implementation of mitigated measures in term of food safety, environmental

sanitation, disease transmitted precaution which must be done by contractors.

Constructed

contractors

01 staff that is responsible for health care of workers in the project site will be assigned by

contractors.

A first aid kit will be provided at each construction site to ensure patients can receive first aid timely

before transporting them to the medical station/hospital.

Monitoring regularly to keep sanitary in campsite, construction sites in order to precaution of

pathogenesis/disease transmission relating to digestive and respiratory system. To require workers

using mosquito nets to prevent petechial/marsh fever.

To propagandize food safety and hygiene for workers;

To build septic tanks in project site which meet environmental standards. To prohibit discharging of

domestic solid waste directly in to the environment. Domestic solid waste must be hygienically

collected, stored, transported and treated.

Coordinating with developer to establish and carry out the precautionary program of sexual

transmitted diseases, especially HIV/AIDS precautionary program, among labors.

Coordinating with developer to make and implement plan of workers’ health care during

Page 53: SFG2200 V2 Public Disclosure Authorized

53

Issues Mitigation and Management Measure

construction phase.

Provide communication/entertainment facilities for workers.

21. Worker Code Developer Coordinating with contractors to establish worker code and manage them during construction phase.

If constructed contractors recruiting workers who come from the other regions, they must be

informed to developer to register temporary residence with the authorities of Trung Chai commune,

Sa Pa district, Coc San, Tong Sanh communes, Bat Xat district.

Developer is responsible with the authorities of Trung Chai commune, Sa Pa district, Coc San, Tong

Sanh communes, Bat Xat district for all issues relating to worker management during they stay in

locality for project construction.

Constructed

contractors

Coordinating with developer to set up worker code

Responsible for worker management during construction phase

Informing to developer in case the workers coming from other regions to register temporary

residence with the authorities of Coc San, Tong Sanh, Trung Chai communes;

The following activities are prohibited on or near project site:

- Cutting of trees for any reason outside the approved construction area;

- Hunting, fishing, wildlife capture, or plant collection;

- Disturbance to anything with architectural or historical value;

- Building fires outside camp areas;

- Use of firearms (except authorized security guards);

- Use of alcohol by workers during Project hours;

- Washing car, motorbikes or machinery in streams or creeks.

- Doing maintenance (change of oils and filters) of cars and equipment outside authorized areas.

Page 54: SFG2200 V2 Public Disclosure Authorized

54

Issues Mitigation and Management Measure

- Disposing trash in unauthorized places;

- Driving in an unsafe manner in local roads.

- Having caged wild animals (especially birds) in camps.

- Working without relevant safety equipment (including boots and helmets).

- Creating nuisances and disturbances in or near communities.

- Disrespecting local customs and traditions

22 Rehabilitation of

all Project sites

after construction

phase

Developer Recover vegetation in all project components to prevent erosion in rainy season.

After construction phase, planting trees/grass in the surface of all borrow pits (disposal sites,

campsite, material temporary loadings etc.)

Planting in combination of 3 types of trees including long term trees, grass, and shrub with priority

of indigenous plants especially in re-vegetation areas.

- Landscaping at project site after construction phase.

23. Effected people

by project

Developer Arrangement jobs as well as guiding local residents on livelihoods after construction phase.

Providing documents on compensation of land and property on land to local authorities and affected

households.

Upgrading/Repairing irrigation system to ensure supplying fully water for agricultural activities of

local communities in case it is damaged by project.

To ensure hygienic environmental conditions for local residents during material transportation and

construction process.

Maintenance of flow in downstream to ensure development of aquatic life and do not affect to

fishing of local people

OPERATION PHASE (Lao Cai Renewable Energy (Vietnam) Joint Stock Company is responsible for implementation of mitigation measures)

Page 55: SFG2200 V2 Public Disclosure Authorized

55

Issues Mitigation and Management Measure

24. Noise (from the hydropower plant) Turbines and/or associated equipment should be designed to meet standards on noise (QCVN

26:2010/BTNMT)).

Design and procurement of equipment should specify requirements to meet standards of noise;

Monitoring periodically the noise level outside the fence of hydropower plant. To implement the

measures of noise reduction in the outside of hydropower plant in case it exceeds the standards.

25. Labor safety issues and worker code To arrange fire-extinguishers at necessary places

To set up the procedures of safe operation;

To arrange the first aid cabinet so that it can carry out the first aid measures on site;

To assign a staff in each shift who is responsible for labor safety

Labor code is defined similar to in the construction phase.

26. Change in downstream flows For the reservoir: the flow is controlled strictly by developer following the regulations on reservoir

operation, discharging water. Developer is responsible for informing in time on plan of water

discharging to local authorities to prevent damage of health, life or assets of downstream

communities.

Developer is responsible for informing widely to local residents, organizations and authorities on

water level fluctuation of Dum River flow in downstream to ensure safety for health and asset as well

as production and agricultural activities in the downstream area.

Developer is responsible for compensating in case of damaging to asset of communities due to

discharging flood.

For the dry stream section and downstream after the power plant: developer commits to comply

strictly the approved operation procedures of reservoir and environmental flow with maintaining

aquatic ecosystem in dry season.

During operation phase, developer will regularly coordinate to local authorities in monitoring water

Page 56: SFG2200 V2 Public Disclosure Authorized

56

Issues Mitigation and Management Measure

level and erosion to provide suitable mitigation measures.

27. Impairment of water quality To clear vegetation cover before flooding reservoir to prevent pollution of water;

Embankments are built at sites which are exposed to danger of landslide

To build separated systems of domestic and industrial waste collection and treatment which meet

permitted standards prior to discharge into the environment;

Domestic solid waste is hygienically managed then transported to the dumpsite for treatment;

Recovering vegetation at construction sites to mitigate erosion and water resource protection.

28. Plant plankton residing in the

reservoir

In case of increasing too much planktons which leads to water pollution so it is necessary to remove

vegetation from the reservoir

Pesticide is prohibited to use for planktons treatment.

29. Reservoir sedimentation Prohibition of cultivated activities in the semi flood area.

To coordinate to local authorities in supervising of prohibition of destroy forest in reservoir

surrounding area especially the semi flood area.

To monitor erosion of reservoir bank two times per year. To take the initiative in implementing

mitigation measures such as planting trees, building breakwaters at points that expose to serious

erosion.

After construction phase, the borrow pits must be rehabilitated by leveling, ramming then planting

trees on the surface to mitigate erosion and sedimentation of reservoir.

Discharging sediment through bottom culvert and dredging the reservoir if necessary.

To mitigate erosion of the river banks behind power house, the energy eliminated hole is designed to

reduce flow rate after discharging canal of power plant so that the flow returning to original flow of

river.

To monitor erosion of river banks in downstream and provide the appropriate mitigation measures

Page 57: SFG2200 V2 Public Disclosure Authorized

57

Issues Mitigation and Management Measure

such as building breakwater, dealing to breakdowns that occur by erosion.

30. Maintaining the replanted vegetation

cover

To monitor and maintain annually vegetation cover which is replanted after construction phase to

rehabilitation of environment and mitigation of erosion.

31. Management of hazardous substances

(fuel, lubricant, etc.)

The same to the measures presented in item No 11.

32. EMF To provide facilities of EMF protection and request staffs/workers who work directly in the EMF

arised areas comply strictly rules on labor safety.

As statistic data, in the safe distance of transmission line, the intensity of EMF is less than 5kV/m

that meets to WHO standards on EMF. The local resident who is living or working in the safe

distance of transmission line will not be affected by EMF.

- To supervise periodically transmission line (lowest sag) to ensure meeting the standards on EMF

safety

33. Emergency cases Storage of water and reservoir operation procedures must be complied with regulation of reservoir.

Establishing and maintaining the flood warning system. Timely inform to local government and

residents downstream of the reservoir about the procedures and fluctuating water levels of the

downstream of Dum River. Annually, the director of Coc San power plant make report and organize

the meeting with representatives from flood control steering committees of districts of Sa Pa and Bat

Xat districts, Lao Cai province to approve the detail plan of flood control. Periodically inspect all

equipment, power supplies, vehicles, communication plans, the water level measuring devices,

maneuvers and test procedures, technical flood discharging

To comply strictly rules on operation, maintaining, repairing of electrical equipment, regulations of

power plant, transmission line and switchyard

To train periodically on electrical safety, prevention of fire for staffs

To disseminate electrical safe regulations at work places for staffs.

Page 58: SFG2200 V2 Public Disclosure Authorized

58

Issues Mitigation and Management Measure

To monitor and provide regularly fire-extinguishers at necessary places and provide emergency aid

for staffs in case of fire.

Page 59: SFG2200 V2 Public Disclosure Authorized

59

Procedures in case of discovery

If the Contractor discovers archeological/historical sites, monuments and objects,

including graveyards and / or individual graves unearthed during construction, the

contractor will be responsible for:

To stop the construction activities in the chance find area.

To delineate the location or found area.

To protect the area to prevent the object from being damage and lost. For artifacts or

remains, the night guard will be allocated directly until the local government has the

responsibility or the Department of Culture and Information takeover.

Inform the Investor to notify for the local government or the nations undertaking the

cultural heritage of Viet Nam (within 24 hours)

Relevant local/central authorities will be responsible for the area protection and

conservation before providing the decision on the later appropriate procedures. Then

they will implement the preliminary evaluation on the excavated findings. The

significance and importance of these findings should be evaluated according to various

criteria relevant to cultural heritage, including aesthetic value, historical or scientific

research, economic and social values

The decision of findings treatment will be made by the responsible agency. This

decision covers the layout (such as in case of detecting the rest of the cultural or

archeological importance cannot be moved) conservation, preservation, restoration and

salvage.

If the cultural area and/or heritage evaluated by the experts and the Cultural Relics

Management agency’s regulation are valuable and should be preserved, the developer

have to change the design in accordance with the required conservation of the area

The decisions of findings management will be notified in writing by the related

agency.

Page 60: SFG2200 V2 Public Disclosure Authorized

60

6. ENVIRONMENTAL MONITORING PLAN

Table 6.1: Parties involved in environmental monitoring

No. Units Main responsibility Content and form of

report

Frequency

1 Contractor To carry out the proposed mitigation measures in

EMP

Making report of implementation of mitigation

measures to developer and CSC

Refer to the table 6.3 Submitting reports to

developer monthly

2 Developer To join EMP into detail technology design and

construction bidding contractors.

To carry out the proposed mitigation measures in

EMP

To monitor the EMP implementation of

contractors

Submit reports of implementation of mitigation

measures to SHB/GDoE PMB

Refer to the table 6.3 Submitting reports to

SHB/GDoE PMB

quarterly

3 Construction

supervision

consultant

To monitor construction activities and ensure that

the contractors comply to environmental

requirements in the contracts and EMP (Terms of

reference for CSC in monitoring EMP is presented

in the Annex 2)

To make report to developer on EMP

Refer to the table 6.4 Submitting reports to

developer monthly

Page 61: SFG2200 V2 Public Disclosure Authorized

61

implementation of contractors

4 Safeguard

Monitoring

Independent

Consultant

To monitor (by observation) and assess

environmental quality based on parameters

suggested by this EMP report.

To conduct public consultation to received

comment, assessment of local people on

environmental management of the Project.

Refer to the table 6.4 Submitting

SHB/GDoE PMB

half-yearly

Page 62: SFG2200 V2 Public Disclosure Authorized

62

Table 6.2: Environmental monitoring plan

Parameters How to monitoring

Sites of monitoring

1. CONSTRUCTION PHASE

Sitting of campsites and

material temporary loading

Visual observation the following issues:

- Camp sites

- Water supply resources

Location of campsites:

- How are they far from stream and residential areas?

- How developer arrange water supply?

- Does developer build filter tanks to filter water?

Location of borrowed pits:

- How are they far from stream and residential areas?

Location of disposals/dump sites:

- How are they far from stream/worker’s rooms

- Concrete mixed stations

- Vehicles, machines parking

- Material loading

- Equipment/machine repaired

workshops

Vegetation clearance and

topsoil stripping

Check and visual observation the following issues: The flora gathering area after

its cut-off;

Vegetation clearance plan

Measures of vegetation clearance

Page 63: SFG2200 V2 Public Disclosure Authorized

63

Parameters How to monitoring

Sites of monitoring

Topsoil stored areas (disposal sites) are applied measures of protection from

erosion/run-off water?

Does project build holes/gutters/embankments?

Topsoil temporary stored site

Work with developer

Does project has landscape rehabilitation plan/Does it implements? Work with developer

Detect bombs and mines Checking bomb and mines disarming document proposed in the project Work with developer

Domestic and constructed

solid waste management

Visual observation the following issues:

Does project generate discarded rock/soil?

Does discarded rock/soil affect water quality or flow of water?

How to collect domestic solid waste?

How to treat domestic solid waste?

How to manage dump sites?

Disposal sites

Dump sites

Topsoil storage sites

Camp sites

Removal of discarded

vegetation out of reservoir

area

Visual observation the following issues:

Checking the plan of vegetation clearance

Is it correct to cut off trees in the required areas?

Does collection of valuable wood out of the reservoir implement?

Is burning the remaining tree leaves/wood well done?

Work with Developer

Check the reservoir bed.

Erosion and sedimentation Visual observation the following issues: The construction sites

Do construction activities carry out in dry season?

Page 64: SFG2200 V2 Public Disclosure Authorized

64

Parameters How to monitoring

Sites of monitoring

Are measures to mitigate erosion/landslide applied at construction sites?

Are holes/ditches/embankments built at danger sites of landslide in construction

areas?

The sites expose risk of high

erosion/landslide

Transportation and traffic

management

The following issues should be checked:

Certification of vehicles that serve for project meet technological/emitted

standards

Attested document of vehicles/machine periodic maintenance

Do vehicles cause traffic jam or damage the road?

Contracts signed with contractors supplying materials/equipment

- Working with developer

- Dam area

- Powerhouse

Management of hazardous

substances

The following issues should be checked and assessed:

Hazardous substance storage:

- Is it lined by anti-seeped ground?

- Is it protected with cover?

- Is it locked and isolated with surrounding area?

Check permission of Lao Cai province’s Department of Industry and Trade if

explosives is stored ;

Check dissemination and material supply about toxicity, safe manual with

hazardous substance ;

- Work with Developer

Check the storage

Page 65: SFG2200 V2 Public Disclosure Authorized

65

Parameters How to monitoring

Sites of monitoring

Noise The following issues should be checked and assessed:

Does noise level at the construction sites impact on the nearest residential area?

Interview local people and leaders living in the nearest area whether the project

makes noise in rest time, evening time?

Interview local people whether developer asks their permission to work in

evening time?

If there is any claim about the noise, request developer to measure the noise level

and give appropriate measures to mitigate its impact.

Contracts signed with material supplied contractors

Project area,

The nearest residential area

Interview the local people

and authorities

Working with developer

Dust The following issues should be checked and assessed:

Is water sprayed fully in dry season at sensitive sites?

Does trucks used for transport material covering by tarpaulin?

Contracts signed with material/machine supplied contractors

Interview with local people about dust pollution cause by project

- The construction site

- Material transported trucks

- Working with developer

Page 66: SFG2200 V2 Public Disclosure Authorized

66

Parameters How to monitoring

Sites of monitoring

Water quality management The following issues should be checked and assessed:

How does sewage collection and treatment system implement at campsites? Are

there septic tanks?

Does sewage discharge directly into environment without treatment?

Do the septic tanks in campsites keep sanitary?

Are oil and grease from vehicles/machines maintenance collected?

Are ditches/pits/embankments built at borrowed pits to collect sand/soil/cement

before discharging into environment?

Is collection of over spill sewage from tunnel performed?

Is water quality measured periodically as presented in EMP/EPC?

- Campsites;

- Borrowed pits

- Vehicle maintenance area;

- Working with Developer on

document of water quality

measurement

Safety Visual observation (combine with information collection on health protection plan

and safety issues):

Is health and safety plan prepared?

Are safe tools & equipment provided to and being used by workers?

Are laborers trained and disseminated information on safety?

Are there any warming notice and boards guiding safety handling to hazardous

chemicals?

- Construction sites

- Storage area

- Working with developer

Labour health care

Are first-aid kits for labours equipped?

Do they dig well the drainage? Is there mosquito net for sleeping?

Are workers trained about food safety and prevent sexually infected diseases?

Is there any disease for labours and did they treat by local health care station?

- Camps

- Working with developer

- Interview workers

Page 67: SFG2200 V2 Public Disclosure Authorized

67

Parameters How to monitoring

Sites of monitoring

Worker code To assess implementation of regulations for workers as specified in item 19 of Table

4.1.

Chance find of cultural

artifacts, and areas/structures

of local cultural value

Observation, information collection, assessment of the below-mentioned issues:

Excavation area of soil/rock

Interview workers

Along transmission line

Let check whether contractors/ developers/ related persons inform the relevant

organizations if accidental find of articles of cultural value?

Do contractors and related persons have followed chance find procedures in

place

Are there findings on cultural property and historical heritage in the soil/rock

excavation?

How are chance find procedures in place when accidental find of articles of

cultural value?

Location of tombs or valuable structures to local people

OPERATION PHASE

Noise Observation at site, interview people to assess the following issues:

Does noise from the powerhouse affect the local people?

- The area out of the fence of

powerhouse.

If there is any claim about the noise, request the developer to measure noise at

site. - The nearest residential area

Safety and regulations to

staffs

The following issues should be checked and assessed:

Are fire extinguishers equipped at site?

Check complying regulations for people as item 19 in Table 4.1

Powerhouse area

Operation house and

workers’ houses (if any)

Page 68: SFG2200 V2 Public Disclosure Authorized

68

Parameters How to monitoring

Sites of monitoring

Management of water quality

in reservoir

The following issues should be checked and assessed:

Is there any erosion at reservoir side? Are reinforcing measures applied?

Is domestic waste collected and treated prior discharging into the environment?

Is there phenomenon of eutrophication in reservoir? Does developer remove

floating vegetation from the reservoir?

In the reservoir bed

Operation house and

powerhouse

Management of hazardous

materials (fuels, lubricants,

explosives etc.)

The following issues should be checked and assessed:

Are hazardous materials stored in safe conditions?

Does the developer equip facilities, provide information and guide safe process

to hazardous materials?

In the plant and fuel, material

and chemical storage areas.

Page 69: SFG2200 V2 Public Disclosure Authorized

69

Table 6.3: Form of in-site environmental monitoring report

(Applying for contractors/developer)

Project name: Project location:

Name of Contractor:

Commencement of Project report or monthly report:

Date of report:

No. Issue Mitigation measures implemented Note

Construction phase

1 Sitting of construction camps and supported facilities

2 Vegetation clearance and topsoil stripping

3 Disarm bomb and mines

4 Domestic and constructed solid waste management

5 Removal of discarded vegetation out of reservoir area

6 Soil erosion and sedimentation

7 Transportation and traffic management

8 Management of hazardous substances

9 Noise

10 Dust

11 Water quality management

12 Safety

13 Labour health care

14 Worker code

Page 70: SFG2200 V2 Public Disclosure Authorized

70

15 Chance find of cultural artifacts, and areas/structures of local

cultural value

16 Vegetation cover including reforestation

Operation phase

1 Noise

2 Surface water quality

3 Waste water

4 Solid waste

5 Vegetation cover maintenance

6 Environmental flow

7 Management of hazardous materials

8 Safety

9 Labour health care

10 Worker code

Name of person prepared this Report: Title:

Address: Telephone:

Page 71: SFG2200 V2 Public Disclosure Authorized

71

Table 6.4: Form of EMP implementation monitoring report

(Applying for environmental monitoring report of CSC/independent monitoring consultant)

Project name: Project location:

Date of report:

No Parameter Assessment of Consultant/ community

complaints

Comments/Recommendations

Construction phase

1 Sitting of construction camps and supported facilities

2 Vegetation clearance and topsoil stripping

3 Disarm bomb and mines

4 Domestic and constructed solid waste management

5 Removal of discarded vegetation out of reservoir area

6 Soil erosion and sedimentation

7 Transportation and traffic management

8 Management of hazardous substances

9 Noise

10 Dust

11 Water quality management

12 Safety

Page 72: SFG2200 V2 Public Disclosure Authorized

72

No Parameter Assessment of Consultant/ community

complaints

Comments/Recommendations

13 Labour health care

14 Worker code

15 Chance find of cultural artifacts, and areas/structures of local

cultural value

16 Vegetation cover including reforestation

Operation phase

1 Noise

2 Surface water quality

3 Waste water

4 Solid waste

5 Vegetation cover remaining

6 Environmental flow

7 Management of hazardous materials

8 Safety

9 Labour health care

10 Worker code

Report prepared by: Address and contact information:

Page 73: SFG2200 V2 Public Disclosure Authorized

73

Table 6.5: Requirements on environmental management reporting System

No. Contents 1st reporting level

2nd

reporting level

(A copy sent to the district’s Environment Management Department )

Construction phase

1 Implementation of

mitigation measures

and on- site

environmental

management

By: Contractor

Frequency: Monthly

To: Developer

By: Developer

Frequency: Quarterly

To: SHB/GDoE

No. Contents 1st reporting level

2nd

reporting level

3nd

reporting level

(A copy sent to the district’s

Environment Management

Department )

1 Environmental

monitoring

By: CSC

Frequency: Monthly

To: Developer

By: Developer

Frequency: Quarterly

To: SHB

By: SHB

Frequency: half-yearly

To: WB/GDoE

2 Environmental

monitoring 1

st reporting level

2nd

reporting level

(A copy sent to the district’s Environment Management Department )

Page 74: SFG2200 V2 Public Disclosure Authorized

74

By: Independent Consultant

Frequency: Quarterly

To: Developer

By: Independent Consultant

Frequency: Quarterly

To: GDoE/WB

Operation phase

1 Labor safety and

environmental

monitoring

By: Developer

Frequency: Half-yearly for first

two years

To: SHB

By: SHB

Frequency: Half-yearly for first two years

To: WB/GDoE

Page 75: SFG2200 V2 Public Disclosure Authorized

75

7. COMPLANATION ON ENVIRONMENT AND PENALTY

While monitoring the scene if supervising/monitoring environmental officers discover

that there is non-compliance with regulations on the implementation of measures to

minimize environmental impacts mentioned in EMP then monitoring construction

staff/ environmental supervisor shall make the records and report the investor .The

investor will stop paying that month expense for the contractor until the contractor

performed adequate measures to minimize environmental effects. The contractor will

be extended one time (due to the construction supervision consultant / supervisor of

environmental regulate) to correct this violation. If the contractor performs the repairs

within the time extension he will not be penalized. However, if the contractor does not

conduct the repairs needed in the extension period, the contractor will have to pay for a

third party to repair the damage (this cost will be taken from retained). Investors must

make provisions for compliance and sanctions for environmental violations in the

contract with the contractor.

In case supervision staff / monitoring environmental officers find non-compliance with

the environmental regulations of the contractor, the contractor shall have to pay the

cost to repair the violation.

The investor is responsible for monitoring and implementing the EMP effectively. If

he does not fulfill the implementation of the EMP, the slow disbursement from the

project to the investors will happen

Environmental offices of the contractor will be the place to receive complaints from

citizens against environmental influences such as dust, noise, traffic safety, The

Contractor’s Chief Engineer and Personnel Assistant with the safety and environment

officers will be responsible for carrying out or giving solutions to handle the above

issues. Officer safety and environmental construction supervision consultant (or team

management environment of the investor) will be provided with copies of the

complaints of the people and must confirm that the problems are properly resolved by

the contractor in a similar incidents were discovered when examining at site.

8. ENVIRONMENTAL MANAGEMENT CAPACITY BUILDING PLAN

8.1. Development phase

Developer will send staffs who are assigned to manage environmental

protection of project to participate the WB/GDoE training courses on preparation

of EMP and public consultation.

8.2. Construction and operation phases

The assigned staffs shall join training courses on WB’s safeguard policies under

REDP. The developer will appoint 1-2 environmental staffs to attend the short-term

training courses on environment which are held by the local authorities.

Additionally, book, papers and documents will be bought by developer so that

they could update the environmental protection information.

Page 76: SFG2200 V2 Public Disclosure Authorized

76

Table 8.1: Cost estimation for environmental management capacity building

No. Activities Costs (VND)

CONSTRUCTION PHASE

1 To assign staffs to participate training courses held by WB:

2 persons x 5,000,000 VND/person/training course x 2 times

20,000,000

2 To assign staffs to attend training courses held by the local

environmental authorities.

2 persons x 1,000,000 VND/person/time x 2 time

4,000,000

3 Purchase of books, documents, papers to update information 10,000,000

TOTAL 34,000,000

OPERATION PHASE

4 Cost for annual training in the project running phase

(10,000,000 VND/year x 20 year)

200,000,000

TOTAL 234,000,000

9. ENVIRONMENTAL MANAGEMENT COST ESTIMATION

Table 9.1: Estimated cost for EMP implementation

No. Items Construction phase During operation phase

(20 years of life cycle)

1 Mitigation measures The cost is covered in investment

cost

The cost is covered in

operation cost

2 Recover vegetation at

project sites after

construction phase

VND 100,000,000

(The cost is covered in

investment cost)

3 Detect mine VND 30,000,000

(The cost is covered in

investment cost)

4 Monitoring costs for

the Project.

(By technical

supervisor of Lao Cai

Renewable Energy

(Vietnam) JSC)

The cost is covered in investment

cost

The cost is covered in

operation cost

Page 77: SFG2200 V2 Public Disclosure Authorized

77

5 Environmental quality

monitoring

2 times/year x VND10,000,000/

time x 2.5 years = VND

25,000,000

2 times/year x VND

10,000,000/time x 20

years = VND

400,000,000

6 Monitoring costs for

independent

environmental

monitoring

consultant*

Lump-sum

(2 times/year x 2 years x VND

20,000.000/time) =

VND80,000,000

7 Reforestation cost VND 400,000,000

Total VND 635,000,000 VND 400,000,000

This cost is covered in

production cost

Total VND1,035,000,000

* This cost is paid by Project Management Board under GDoE

Page 78: SFG2200 V2 Public Disclosure Authorized

78

10. PUBLIC CONSULTATION AND DISCLOSURE

10.1. Public consultation

In the preparation phase, Lao Cai Renewable Energy (Vietnam) Joint Stock

Company carried out the following tasks

1. To submit the feasibility study report and investment report to communal

people committee of Trung Chai, Sa Pa district, communal people

committees of Coc San, Tong Sanh, Bat Xat district with the purpose of

consultation on location of main components of project. Depending to the

comments, the developer can revise project documents to save cost, mitigate

compensation, resettlement as well as reduce impacts on environment and

community.

2. To survey by interview directly representatives of local authorities and

affected households. Result from survey shows that almost households and

local authorities support to construction of project because of its benefits for

local residents.

3. To survey and statistic of environmental impacts and affected households

4. To prepare EMP report

5. To organize the consultation meetings on EMP report and other related

issues at the offices of Communal People Committees of affected

communes including Trung Chai, Coc San, and Tong Sanh from July 31,

2015 to August 1, 2015. Participants consist of representatives from

developer, local authorities and households of Trung Chai, Coc San, Tong

Sanh communes, EMP, EP, RP consultants, (Minute of meetings and list of

participants are presented in the Annex 3). The main content of consultation

meetings as below:

Developer presented the main information of project

Coc San hydropower project has the capacity of 29.6 MW, annual average power

output is 138.87 million kWh, is categorized as impoundment, daily regulation by

reservoir. Main parameters: catchment area: 99.6 km2; total of flow rate: 145

million m3; reservoir area corresponding to normal water level: 4.24 ha; normal

water level: 702 m; death water level: 699 m; gross capacity of reservoir: 252.3

million m3; useful capacity: 124.6 million m

3; designed flow Q tk: 7.83 m

3/s, ensure

flow Q đb: 0.996 m3/s, voltage level: 110 kW.

To build Coc San hydropower project as the same other ones will cause some

negative/positive impacts to environment and social and these negative impacts are

unavoidable. EMP is prepared following to the World Bank safeguard policies and

commits to complying with mitigation measures.

The consultant presented the environmental negative/positive impacts and

mitigation measures which will be applied by developer during project

implementation as below:

Page 79: SFG2200 V2 Public Disclosure Authorized

79

Positive impacts:

Project will supply stable power, high quality with the total power output of

138.87 million kWh/year for the local people when project is put into

operation. It will support to develop industrial, agricultural projects in the

locality.

Formation of reservoir will facilitate for development of vegetation cover,

trees and reservoir aquatic species such as fish, snail, shrimp etc.

Income from tax of water resource usage which is provided from project will

be added to provincial budget to support increasing living standard of local

residents.

Negative impact:

Construction and operation of project must block stream, storage water, build

dam, underground tunnel, penstock, powerhouse, switchyard, transmission line etc.

that cause some unavoidable impacts as below:

37.78 ha land will be acquired permanently for formation of reservoir, dam

and building of headwork and 18.2 ha land will be acquired temporary for

auxiliary facilities among them 8.25 ha land is forest.

Construction of road and headwork must excavate/backfill soil/rock that

cause landslide at these sites

Blocking stream to build dam will impact negatively to stream water quality

by increasing turbidity.

Activities such as blasting, excavation of foundation, leveling soil/rock,

material transportation, operation of constructed machines, construction etc.

will impact to environment causing air pollution in case the mitigation

measures are not applies.

In the construction phase, the operation of constructed/transported facilities,

machines, blasting, using driller etc. will create noise that disturb to local

residents

Constructed and domestic solid waste that discharged from workers will

cause pollution of air and water stream if it is not well controlled.

In the construction phase, the aquatic species may lose temporary living

condition due to reduction of surface water quality that cause by random

spilling or rain sweeping away concrete, petrol, oil, gear, soil, rock etc.

However, this is only temporary and negligible impacts. They may be

mitigated because project has small scale and the construction time takes only 2

years.

Some key main measures to mitigate negative impacts

Environmental consultant presented briefly draft EMP which will be complied by

developer to mitigate negative impacts with some key measures as below:

Page 80: SFG2200 V2 Public Disclosure Authorized

80

The permanent and temporary acquired land due to project construction will be

compensated following compensation plan which is approved by Decision No.

4197/QD-UBND dated December 9, 2009 issued by Lao Cai people committee.

During construction phase, cultivated and public transportation acquired land

for campsites, borrowed pits; transmission line will be limited by contractors.

The contractors are responsible for inform to local authorities and residents on

blasting time so that they do not travel or release cattle in the blasting areas.

Disposals must meet criteria: far from surface water at lease 100m, do not affect

to surface water, cultivated land, do not locate on the risk of landslide, should

locate on the hollow sites to mitigate sweep away by runoff water.

To establish the worker code at construction site containing regulations such as

prohibiting workers to discard domestic/construction waste into surrounding

areas, stream or places which may sweep away to surface water.

Do not allow to burn solid waste to mitigate risks of fire.

After construction phase, the borrow pits or disposals etc. must be restored by

leveling ground then planting trees to prevent erosion.

To arrange petrol, oil storages at least 300 m far from surface water,

communities.

Developer commits to comply with EMP with the main issues presented above

Questions and answers are summarized as below:

Coc San commune, Bat Xat district:

Questions from representatives of local authorities and affected households

- Construction of project will impact negatively to surface water quality. The

breeding fish may get disease leading to low growth causing by high turbidity

of water.

- Some households lose all the cultivated land since land is acquired for

construction of project.

- The local people could not breed cattle in flooding land when reservoir is

formed.

- The developer should speed up the process of compensation so that effected

households could stabilize their living.

Answers from developer and consultant:

- Regarding to impact of surface water quality and aquaculture the impact of

surface water quality is unavoidable during construction of

hydropower/irrigation projects. However, this impact is short-term and only

occurs during construction phase especially blocking dam. This impact may be

mitigated if developer complies strictly with mitigation measures presented in

EMP. In the operation phase, this issue will be rehabilitated gradually. The

formation of reservoir will impact positively to aquaculture of local community.

Page 81: SFG2200 V2 Public Disclosure Authorized

81

- Regarding to acquisition of cultivated land and compensation: The acquisition

of cultivated land is not avoidable when building hydropower projects.

Developer prepared compensation plan following Vietnam regulations and it is

approved by local authorities. The compensated rate is depended on the current

regulations. For Coc San project, cultivated land of some households has been

acquired so their income and livelihood will be impacted negatively. Developer

also prepared EP, RP to support affected households on livelihood caused by

project building.

- Regarding to impact on cattle breeding of some households, developer will

apply the mitigation measures such as informing of blasting time, installing of

work signals to prevent accessing into work sites. Developer hope to get

supporting from local people to ensure the accidents will not occur.

Tong Sanh commune, Bat Xat district:

Questions from representatives of local authorities and affected households

- In general, the communal authorities and residents support to build project.

Construction of project will provide some benefit for local people such as

upgrading of a part of internal road. However, construction process will cause

pollution of water resource, dust etc. Developer should pay attention to deal

with this issue.

- Requested developer increases the compensation rate so that the affected

households does not handicap by project.

- During construction phase, activities of excavation/backfilling, road building

will impact negatively to water resource of local people such as block of water

pipelines that take water from stream to households. Request the developer

solves this issue.

- Request the developer provides the jobs for local people. At present, the

number of local jobless youths is quite high. Developer should arrange jobs

from power plant for them when it will be put into operation.

- Activity of transportation of constructed material will cause pollution of dust

that impacts to local people who are living nearby the roads. Developer should

apply the mitigation measures to reduce dust.

Answers from developer and consultant:

- Regarding to question of environmental pollution: as presenting by consultant,

construction of project will impact negatively to surrounding area such as

pollution of dust, water resource etc. Developer prepared EMP and tries to take

mitigation measures proposed in EMP. During construction phase, developer

suggests the local people to contact the local authorities and environmental staff

of project if project causing pollution. The developer commits to deal with

pollution.

- Regarding to question of increasing compensation: developer prepared

compensation plan and it was approved by local authorities. The local

authorities also participate in process of identifying the compensation boundary.

The compensation rate is in accordance to governmental regulations. If there is

any complaint on account, developer will coordinate to communal authorities

Page 82: SFG2200 V2 Public Disclosure Authorized

82

and affected households to solve further. Regarding to information of

compensated price, developer will provide to affected households through

communal authorities.

- Regarding to question of providing jobs for local residents: developer records

and try to arrange jobs for them in our permission conditions.

- Regarding to question of blocking water pipelines of local people: developer

records and commits to rehabilitate them.

Trung Chai commune, Sa Pa district:

Questions from representatives of local authorities and affected households

- The compensation plan has been approved; request developer improves the

compensation progress so that affected households could stabilize their living

soon.

- Construction of project acquires quite lot of forest land and impacts to life of

local people such as they will not breed their cattle, lose benefit from forest

land, requested that developer support to local people.

Answer from developer and consultant:

- Regarding to question of improving progress of compensation: developer

records and commits to coordinate to communal authorities to solve this issue

to support affected households stabilize their life.

- Regarding to question of negative impact of local people by losing of forest

land: developer records and we prepared EP, RP to support affected households

on their livelihood so that they could stabilize their life soon. Developer expects

that local residents support to construction of project.

6. Editing EMP with considered the recommendations of people and affected

communal government in the community consultation meeting as well as in the

investigation of affected households.

7. Sending EMP to communal people committees of Coc San, Tong Sanh,

Trung Chai communes for comments

8. Editing EMP according to the comments

10.2. Disclosure

As policy of WB’s disclosure, developer will implement steps as below:

- To provide EMP (approval by WB) in Vietnamese version to Sa Pa and Bat Xat

DONREs, Sa Pa and Bat Xat District people committees, Coc San, Tong Sanh,

Trung Chai communal people committees.

- The approved EMP in Vietnamese version will be disclosure at project site

during project implementation.

- To provide EMP in both English and Vietnamese versions to Information

Development Centre, 63 Ly Thai To street, Hanoi so that they are accessed by

NGOs and communities. EMP in English version is sent to WB Info shop for

disclosure.

Page 83: SFG2200 V2 Public Disclosure Authorized

83

List of reference documents

1 The compensation Plan of the project, Lao Cai Renewable Energy (Vietnam)

Joint Stock Company

2 Investment Report of Coc San hydropower project, Lao Cai Renewable

Energy (Vietnam) Joint Stock Company

3 The World Bank’s Safeguard policies;

4 Environmental Protection Commitment of Coc San small hydropower project

5 Environmental safeguard framework for Vietnam Renewable Energy

Development Project- MOIT 2008, revised 2014.

6 Statistical yearbook- statistic publishing house

Page 84: SFG2200 V2 Public Disclosure Authorized

84

Annex 1. List of people who prepared EMP

No. Name Title

1 Ms. Ta Thi Quynh Nhu Project manager

2 Mr. Phan Tuan Anh Technical staff

3 Ms. Hoang Hong Hanh Environmental staff

4 Ms. Chu Lan Phuong Environmental consultant

Page 85: SFG2200 V2 Public Disclosure Authorized

85

Annex 2: Responsibility of construction supervision consultant

Target

The CSC supports the EMP efficiently during construction of Coc San hydropower

project.

To achieve the target of diminishing the environmental negative impacts of the project,

the contractor needs to comply with this management plan. Therefore, implementing

him environmental management plan will relate to the following units:

The safe and environmental supervising officers of the contractor are responsible for

supervising the EMP and problems about safety and environment of the construction

The safe and environmental supervising officers of CSC is responsible for the

construction inspection and guarantee that the contractor will comply with the requests

in the contract and EMP

Tasks:

Overall responsibilities of the safe and environmental supervising officers including

supervision and inspection of construction activities to ensure that the mitigation

measures are implemented as appropriate in the plan so that environmental

management and the negative impact of the project on the environment is diminished.

The contractor is responsible for ensuring compliance with the environmental

management plan of the project and the contract conditions during construction under

the supervision of safety and the environment officer. Therefore, safety and the

environment officer is an independent supervisory personnel to ensure compliance

with the environmental management plan and ensure the full implementation of the

contractor for environmental issues

Personnel monitoring and environmental safety will examine monitor and implement

the environmental review for tenders and contracts for road construction. Supervisors

on safety and the environment have much knowledge and experience in monitoring

and verification of environmental issues and advise investors on implementation issues

of the project environment project. Personnel monitoring and environmental safety

should be familiar with the project work through the review of relevant reports,

including the report on environmental impact assessment (EIA) Coc San hydropower

project, environmental Management plan as well as the relevant technical standards

and contract documents.

Being a part of the construction examiner group, safety and environmental staff is

obliged to the following tasks

Phase 1: Preparation

Objective of Phase 1 is to make foundation for successful implementation of the

project. During this period, supervisors, safety and environment must: (i) consider the

DTM, environmental management plan, project design and technical standards to

assert not to miss these mitigation measures ; (ii) prepare guidelines for contractors in

the implementation of Environmental Management Plan; and (iv) develop and

implement training programs for activities related to construction.

Main tasks for this phase are:

Page 86: SFG2200 V2 Public Disclosure Authorized

86

Desk study: supervisors on safety and the environment will review the DTM,

environmental management plan, project design and technical standards and certify in

writing expressly not to omit any mitigation measures. If problems arise, safety and

environment officers propose to the investor for additional updates in the

environmental management plan, project design and technical standards of this issue.

When the Investors, Board of Management and the World Bank project GDoE ratify,

personnel monitoring and environmental safety will conduct additional updates

environmental management plan

Environmental supervision directory: The safety and environment officers need to

create an examination directory during the construction for supervising the

implementation of the contractor. This includes the core issue of the project, the

requested mitigation measures and implementation plan

Diary: safety and environment supervising staff of the Contractor shall keep diaries to

record events or changes possibly implicate the assessment of environmental impact

and non-compliance attached to the proposals. Diaries must be always ready to serve

when the supervisory staff support as mentioned in the environmental management

plan and contract suggest. Safety and environment staff of the investor will verify this

diary.

Environmental training : Environmental safety staff of the investors are obliged to

design and implement a comprehensive training program for the Supervision Engineer,

Owner, environmental safety officers of the contractor (and workers as part of training

for supervisors, safety and environment), the environmental requirements of the

project and methods for monitoring and evaluation, especially should pay attention to:

Environmental management plan: the requirements of the Environmental Management

Plan, approved check list in supervising environmental, environmental sample

monitoring and processing methods for non-compliance with the management plan

environment and all the issues will be mentioned. Special attention should be paid to

the specific terms of the contract emphasized on compliance with the environmental

management plan

Health and safety: Health and safety requirements of the project must be apparently

verified and coordinated to the contractors and the investor (included in the technical

standard environment for the contractors

At the end of training, the contractor will sign a confirmation through training grasp of

environmental regulations, the environmental management plan and compliance

framework, on the health and safety obligations. Construction supervisors must sign

the certification through training understand the oversight responsibilities.

Phase 2 Construction activities supervision

Safety and environment officer of the investors will represent the Owner and

monitoring Chief Engineer:

Examining and monitoring independently the implementation of the

Environmental management plan

Performing random checks and review the profiles of environmental safety staff

of the Contractor

Proceeding the inspection frequently in the building section

Page 87: SFG2200 V2 Public Disclosure Authorized

87

Reviewing the implementation of the mitigation measures is not right with the

environmental management plan and contract documents

Reviewing the effectiveness of the mitigation measures and the implementation

of environmental problems;

Reviewing the terms acceptable environmental construction methodology

(including temporary works and permanent works), designs and related

submissions. If necessary, staff safety and the environment have to research and

propose solutions to the environmental impacts discussed with the designers,

contractors and Investors

Verifying survey cases of non-compliance of environmental quality and

effectiveness of the remedial measures;

Providing feedback to the Owner and Chief Engineer under the supervision of

the process of non-compliance with the Environmental Management Plan;

Organizing training programs, including team environmental safety staff of the

contractors, evaluating issues identified an improve environmental compliance

method;

To conduct the contractors to repairs within the prescribed time, conducting

additional monitoring, if required, in accordance with the provisions of the

contract and procedures in case of non-compliance and complaints

To conduct the contractor to take measures to minimize the impact and comply

with the environmental management process required in the case of non-

compliance and inconsistency

To conduct the contractor to stop the construction activities which can cause

negative effects, and / or if the contractor fails to perform the requirements of

the Environmental Management Plan / not conduct operations as directed the

supervisor of environmental safety.

Review of the plan at site: To ensure the consistency throughout the project, safety

and the environment staff must consider the entire plan could affect the environment.

These plans include, but are not limited to: plan pits and dumps. Supervisors on safety

and the environment will be considered and approved the environmental management

of the project and plans to restore the landscape of the contractor. What parts of the

plan does not comply with the environmental management plan, environmental impact

assessment, personnel and environmental safety of the investors will work with the

Chief Engineer and the Contractor to take appropriate measures.

Health and Safety: To ensure consistency throughout the project, the environmental

safety officer must consider the entire safety plan of the contractor, and on the basis of

this plan, with the data of the investor's input, to create a comprehensive plan for

safety projects. Comprehensive Plan about project safety must include processes such

as blast management and safety in the construction process, preventing landslides / soil

erosion during the rainy season, these plans must be reviewed on an annual basis and

must be updated as necessary.

The supervisors on safety and the environment must ensure compliance with the

provisions of health and safety in the contract documents. This Compliance includes,

but is not limited to: (i) the construction activities; (ii) dissemination of education on

Page 88: SFG2200 V2 Public Disclosure Authorized

88

HIV / AIDS; (iii) comply with the labor law of Vietnam; and (iv) traffic safety. For the

prevention of HIV /AIDS, it is recommended that developer not only focuses on the

construction site, but also pays attention to the nearby communities.

In case of violation in the requirements of technical standards, or contractual

conditions or non-compliance with the environmental management plan, safety and the

environment monitor immediately notify to the Chief Engineer of the Contractor ,

Chief Engineer supervision and investor. Safety and the environment supervisors must

also report violations to the Investor as part of the monthly report.

Diary of safety and the environment staff must always be ready to provide, upon

request by the support team of project management

Safety and the environment supervisors have to regularly review records of the

Contractor to ensure that all records are updated in accordance with reality and meet

the requirements of the Environmental Management Plan (etc. the records of

complaints about environmental issues).

The unintended effect: In case of the incident which was not anticipated in the

environmental management plan and DTM, safety and the environment monitors must

be closely coordinated with the investor, the contractor and the project manager to

confirm that the problem has been resolved. Safety and the environment supervisors

must update Environmental Management Plan and implement guidelines, based on

that training for contractor personnel

Monthly Payment: safety and the environment monitoring officer must certify the

monthly payment for activities related to the environment as proposed by the

Monitoring Officer safety and the environment to the investor.

Roadwork’s and landscaping restore: safety and the environment monitoring

officer must closely monitor the operation to restore the site and landscaping in areas

such as land mines, quarries, wash stations vehicles, to ensure that activities are carried

out according to acceptable standards. Safety and the environment supervisors must be

consistent with the contractor about the recovery plan which should be implemented

before the end of construction activities.

Human Resource for the Project: safety and environmental supervisors and building

monitors group is expected to be mobilized 1 month prior to construction

commencement. In January, the safety and environmental monitor will be familiar

with the project, project design, specifications, contract documents, environment

protection commitment, environment management plan and other reports and

documents related to the project. Based on the review, monitoring officer safety and

the environment will report a summary of the issues that may arise in the process of

implementing the environmental management plan and the conditions of the contract

the recommend the Manager the best option to improve the process of implementing

the environmental management plan.

Supervisors and safety are expected to be mobilized in the early stages of the contract

to prepare the guidelines, documentation, training,

Report: environmental safety officers must make a minimum of the following

documents: ...

Weekly reports on issues of non-compliance;

Page 89: SFG2200 V2 Public Disclosure Authorized

89

Monthly report summarizes the main issues and findings during surveillance

activities;

Quarterly report from the contractor's monthly report

Reports and data must be provided as required by the project manager.

At the end of the project, safety and environment monitoring staff set up a final report

summarizing main findings, non-compliance, solutions, etc. as well as guidance on

implementing orientation this mission later.

Page 90: SFG2200 V2 Public Disclosure Authorized

90

Annex 3. The approval documents on EPC

Page 91: SFG2200 V2 Public Disclosure Authorized

91

Page 92: SFG2200 V2 Public Disclosure Authorized

92

Annex 4. Minute of Public Consultation Meetings

Page 93: SFG2200 V2 Public Disclosure Authorized

93

Page 94: SFG2200 V2 Public Disclosure Authorized

94

Page 95: SFG2200 V2 Public Disclosure Authorized

95

Page 96: SFG2200 V2 Public Disclosure Authorized

96

Page 97: SFG2200 V2 Public Disclosure Authorized

97

Page 98: SFG2200 V2 Public Disclosure Authorized

98

Page 99: SFG2200 V2 Public Disclosure Authorized

99

Page 100: SFG2200 V2 Public Disclosure Authorized

100

Page 101: SFG2200 V2 Public Disclosure Authorized

101

Page 102: SFG2200 V2 Public Disclosure Authorized

102

Page 103: SFG2200 V2 Public Disclosure Authorized

103

Page 104: SFG2200 V2 Public Disclosure Authorized

104

Page 105: SFG2200 V2 Public Disclosure Authorized

105

Page 106: SFG2200 V2 Public Disclosure Authorized

106

Page 107: SFG2200 V2 Public Disclosure Authorized

107

Page 108: SFG2200 V2 Public Disclosure Authorized

108

Page 109: SFG2200 V2 Public Disclosure Authorized

109

Page 110: SFG2200 V2 Public Disclosure Authorized

110

Page 111: SFG2200 V2 Public Disclosure Authorized

111

Page 112: SFG2200 V2 Public Disclosure Authorized

112

Annex 5: Approval for reclamation, change of land use purpose for implementation

of the Project

Page 113: SFG2200 V2 Public Disclosure Authorized

113

Page 114: SFG2200 V2 Public Disclosure Authorized

114

Annex 6. Public consultation meeting pictures

Meeting in Tong Sanh Meeting in Tong Sanh

Public consultation meeting in Tong Sanh on 01/08/2015

Meeting in Trung Chai Meeting in Trung Chai

Public consultation meeting in Trung Chai on 31/07/2015

Page 115: SFG2200 V2 Public Disclosure Authorized

115

Public consultation meeting in Coc San on 31/07/2015

Page 116: SFG2200 V2 Public Disclosure Authorized

116

Annex 7: Site photos

Dum River Dam site before construction Vegetation cover at project site

Dam overview from centerline

Page 117: SFG2200 V2 Public Disclosure Authorized

117

Upstream Dam overview Downstream Dam overview

Powerhouse overview from 110 KV switchyard Pipeline around units no. 2 & 3, ready for concrete

Formwork installation at generator & unit no. 01 area

Page 118: SFG2200 V2 Public Disclosure Authorized

118

Tunnel – Inclined tunnel no. 2 Tunnel – Inclined tunnel 3 – Pipe installation

Inclined tunnel no. 3 – Pipe installation & concrete

work

110KV transmission line