Sewer Overview

Embed Size (px)

Citation preview

  • 8/7/2019 Sewer Overview

    1/39

    City of Lima, Ohio

    CSO Progress Update for Council

    March, 2011

  • 8/7/2019 Sewer Overview

    2/39

    Lima sewer system overview

    Regulatory Requirements

    Sanitary Sewer Overflow (SSO) Component

    Combined Sewer Overflow (CSO) Solutions

    Regulatory Compliance Costs & Benefits

  • 8/7/2019 Sewer Overview

    3/39

    Allentow

    n Rd.

    KoopRd.

    15th

    Street

    LostCreek

    ColeStreet

    West

    Street FindlayRoad

    Lima, OHSeparate Sanitary

  • 8/7/2019 Sewer Overview

    4/39

    Sewer System OverviewWhere does the water go?

    Combined System

    SurfaceRunoff

    Gutters &Downspouts

    Bathrooms, Showers,Laundry, Dishwashing, etc.

    Footer

    Drains

    Roadway Runoff &Other Impervious

    Surfaces(i.e. Parking Lots)

    Combined Sewer

    Industrial Wastewater

  • 8/7/2019 Sewer Overview

    5/39

    Sewer System OverviewWhere does the water go?

    Separate System

    SurfaceRunoff

    Gutters &Downspouts

    Bathrooms,Showers, Laundry,Dishwashing, etc.

    Footer

    Drains

    Roadway Runoff &Other Impervious

    Surfaces(i.e. Parking Lots)

    Sanitary Sewer

    Industrial Wastewater

    Storm Sewer

  • 8/7/2019 Sewer Overview

    6/39

    Sewer System OverviewWhere does the water go?

    Sewer Mains and Interceptors

    NO FLOW

    SeparatedSewer Area

    CombinedSewer Area

    WastewaterTreatment Plant

    Manhole

    Local Combined Sewer

    InterceptingStructure

    RegulatingStructure

    Overflow Sewer

    CSO

    Interceptor Sewer

    Local Sanitary Sewer

    Storm Sewer

    InterceptingStructure

    OutfallWWTP

    Effluent

  • 8/7/2019 Sewer Overview

    7/39

    Sewer System OverviewWhere does the water go?

    Sewer Mains and Interceptors

    DRY WEATHER FLOW

    SeparatedSewer Area

    CombinedSewer Area

    WastewaterTreatment Plant

    Manhole

    Local Combined Sewer

    InterceptingStructure

    RegulatingStructure

    Overflow Sewer

    CSO

    Interceptor Sewer

    Local Sanitary Sewer

    Storm Sewer

    InterceptingStructure

    OutfallWWTP

    Effluent

  • 8/7/2019 Sewer Overview

    8/39

    Sewer System OverviewWhere does the water go?

    Sewer Mains and Interceptors

    WET WEATHER FLOW

    SeparatedSewer Area

    CombinedSewer Area

    WastewaterTreatment Plant

    Manhole

    Local Combined Sewer

    InterceptingStructure

    RegulatingStructure

    Overflow Sewer

    CSO

    Interceptor Sewer

    Local Sanitary Sewer

    Storm Sewer

    InterceptingStructure

    OutfallWWTPEffluent

  • 8/7/2019 Sewer Overview

    9/39

    Sewer System OverviewWhere does the water go?

    Sewer Mains and Interceptors

    EXTREME WET WEATHER FLOW

    SeparatedSewer Area

    CombinedSewer Area

    WastewaterTreatment Plant

    Manhole

    Local Combined Sewer

    InterceptingStructure

    RegulatingStructure

    Overflow Sewer

    CSO

    Interceptor Sewer

    Local Sanitary Sewer

    Storm Sewer

    InterceptingStructure

    OutfallWWTPEffluent

  • 8/7/2019 Sewer Overview

    10/39

    Lima sewer system overview

    Regulatory Requirements

    Sanitary Sewer Overflow (SSO) Component

    Combined Sewer Overflow (CSO) Solutions

    Regulatory Compliance Costs & Benefits

  • 8/7/2019 Sewer Overview

    11/39

    Limas system includes: 20 CSOs, 33 SSOs, 1 WWTP Currently no SSO policy dictating frequency ofoverflows

    USEPAs CSO Policy Requires Controllingoverflows to 4 events/yearCSO activation may be greater based on affordabilitycriteria

  • 8/7/2019 Sewer Overview

    12/39

    Lima sewer system overview

    Regulatory Requirements

    Sanitary Sewer Overflow (SSO) Component

    Combined Sewer Overflow (CSO) Solutions

    Regulatory Compliance Costs & Benefits

  • 8/7/2019 Sewer Overview

    13/39

    Allentow

    n Rd.

    KoopRd.

    15th

    Street

    LostCreek

    ColeStreet

    West

    Street FindlayRoad

    Lima, OHSeparate Sanitary

  • 8/7/2019 Sewer Overview

    14/39

    Total SSO Volumes by Design Storm Size

    2.38 2.78 3.32 4.30

  • 8/7/2019 Sewer Overview

    15/39

    BASIN 5-Yr 10-Yr 25-Yr 100-Yr

    Lost Creek $4,098,000 $4,816,000 $5,592,000 $7,297,000West Street $3,028,000 $3,457,000 $4,352,000 $5,000,000

    Koop Road $4,778,000 $5,407,000 $5,672,000 $6,794,000

    Allentown Road $4,527,000 $5,021,000 $5,328,000 $5,842,000

    Cole Street $1,717,000 $2,101,000 $2,288,000 $2,558,000

    Findlay Road $1,483,000 $1,551,000 $2,727,000 $3,157,000

    15th Street $190,000 $281,000 $506,000 $714,000

    Total $19,821,000 $22,634,000 $26,465,000 $31,362,000

    Total Estimated Project Costs to Provide Protection forthe Specified Design Storm (Aug 2009 Dollars)

  • 8/7/2019 Sewer Overview

    16/39

    Implementation: 10 - 12 Year CIP Program

  • 8/7/2019 Sewer Overview

    17/39

    Lima sewer system overview

    Regulatory Requirements

    Sanitary Sewer Overflow (SSO) Component

    Combined Sewer Overflow (CSO) Solutions

    Regulatory Compliance Costs & Benefits

  • 8/7/2019 Sewer Overview

    18/39

    WWTP Upgrade

    CSO Storage Tank(s)

    CSO Storage Tunnel

    Sewer Separation

  • 8/7/2019 Sewer Overview

    19/39

    WWTP capacity was compared with CSO storage needs

    (either tank or tunnel) upstream to determine cost-effective

    treatment/storage balance

    Two main WWTP options were considered:

    70 MGD Capacity

    96 MGD Capacity

  • 8/7/2019 Sewer Overview

    20/39

    Category Rating Criteria Category Rating Criteria

    1Cost is more than 5 times higher than the lowest

    cost alternative1

    Extremely elaborate O&M requirements, requires

    additional staff or training; cannot be expanded or

    retrofitted for additional CSO control; history of

    significant maintenance problems

    2Cost is more than 25% higher than the lowest

    cost but less than 5 times higher

    2

    Moderately complex, requires general training; could

    be expanded on a limited basis with some difficulty;

    moderately reliable

    3Lowest cost alternative or alternative cost is

    within 25% of the lowest cost[3

    Straight-forward to operate, limited training; could be

    easily expanded or retrofitted; minimal maintenance

    with proven track record

    1Cannot meet CSO control goal without significant

    additional improvements1

    Specialty Construction Firms required, highest risk

    construction methods

    2Meets CSO control goal with minor additional

    improvements2

    Mix of Specialty and Conventional Construction Firms

    required, moderate risk

    3 Meets CSO control goal 3

    Conventional Construction Firms can perform all

    work, low risk

    1Discharges the largest pollutant load into the

    environment

    2 Discharges pollutant load between 1 and 3

    3Discharges the smallest pollutant load into the

    environment

    1

    Extreme, sustained, widespread disruption to

    community, large scale surface impacts that

    interrupt traffic and cause extreme levels ofnoise, odor, vibration or other inconveniences;

    would result in major public opposition; requires

    extensive permitting approval process

    2

    Moderate levels of noise, odor, vibration or other

    inconveniences; has no significant history of

    opposition;

    3

    Minimal levels of noise, odor, vibration or other

    inconveniences; embraced by impacted public;

    normal permit review and approval process

    Cost

    Conformance

    with Objectives

    Environmental

    Issues

    Public Disruption

    Operational

    Issues

    Constructability

  • 8/7/2019 Sewer Overview

    21/39

    Alternative Cost

    Conforman

    cew

    ith

    Obj

    ectiv

    es

    Environm

    ental

    Issu

    es

    Public

    Dis

    ruption

    Ope

    ratio

    nalIss

    ues

    Constru

    ctabilit

    y

    TOTAL Comments

    1: Tank + 70 MGD 2 3 2 2 3 2 141) Tank is easier to maintain/clean because it is not as deep as tunnel, City

    owns Simmons Field, site of the major tank

    2: Tank + 96 MGD 3 3 3 2 3 2 16

    1) Tank is easier to maintain/clean because it is not as deep as tunnel

    2) More annual volume will receive primary + disinfection than the 70 MGDoption since corresponding volume will overflow at CSOs and receive

    treatment by fine screens but no disinfection.

    3) City owns Simmons Field, site of major tank

    3: Tunnel + 70 MGD 2 3 2 3 2 1 13

    1) Tunnel construction has more risk, deep dewatering pump staiton will be

    harder to maintain/service than tank pump station

    2) Specialty contractor will be needed to perform work

    4: Tunnel + 96 MGD 3 3 3 3 2 1 15

    1) Tunnel construction has more risk, deep dewatering pump station will be

    harder to maintain/service than tank pump station

    2) More annual volume will receive primary + disinfection than the 70 MGD

    option since corresponding volume will overflow at CSOs and receive

    treatment by fine screens but no disinfection.

    3) Specialty contractor will be needed to perform work

    5: Complete

    Separation1 3 1 1 3 3 12

    1) High levels of public disruption, less pollutant removal than all other

    alternatives

  • 8/7/2019 Sewer Overview

    22/39

    22

  • 8/7/2019 Sewer Overview

    23/39

    *Capacity shown for each process in approximate peak flow

    Baxter Pump Sta.(56 mgd)

    Preliminary

    (96 mgd)

    Existing

    Primaries(26 mgd)

    NewPrimaries(40 mgd)

    ActivatedSludge

    (40 mgd)

    Towers(30 mgd)

    Cl2

    (40 mgd)

    54" (33 mgd)

    72" (63 mgd)

    36"(12 mgd)

    96

    26

    40

    Dry Weather

    Tower Seed

    ToRiver

    40 mgd duringwet weather

    Disinfection(56 mgd)

    30

    23

  • 8/7/2019 Sewer Overview

    24/39

    *Capacity shown for each process in approximate peak flow

    24

    Baxter Pump Sta.(56 mgd)

    Preliminary

    (96 mgd)

    Existing

    Primaries(26 mgd)

    NewPrimaries(40 mgd)

    ActivatedSludge

    (40 mgd)

    Towers(30 mgd)

    Cl2

    (40 mgd)

    54" (33 mgd)

    72" (63 mgd)

    36"(12 mgd)

    96

    26

    40

    Dry WeatherTower Seed

    ToRiver

    40 mgd duringwet weather

    Disinfection(56 mgd)

    30

  • 8/7/2019 Sewer Overview

    25/39

    *Capacity shown for each process in approximate peak flow

    25

    Baxter Pump Sta.(56 mgd)

    Preliminary

    (96 mgd)

    ExistingPrimaries(26 mgd)

    NewPrimaries(40 mgd)

    ActivatedSludge

    (40 mgd)

    Towers(30 mgd)

    Cl2

    (40 mgd)

    54" (33 mgd)

    72" (63 mgd)

    36"(12 mgd)

    96

    26

    40

    Dry WeatherTower Seed

    ToRiver

    40 mgd duringwet weather

    Disinfection(56 mgd)

    30

  • 8/7/2019 Sewer Overview

    26/39

    *Capacity shown for each process in approximate peak flow

    26

    Baxter Pump Sta.(56 mgd)

    Preliminary

    (96 mgd)

    ExistingPrimaries(26 mgd)

    NewPrimaries(40 mgd)

    ActivatedSludge

    (40 mgd)

    Towers(30 mgd)

    Cl2

    (40 mgd)

    54" (33 mgd)

    72" (63 mgd)

    36"(12 mgd)

    96

    26

    40

    Dry WeatherTower Seed

    ToRiver

    40 mgd duringwet weather

    Disinfection(56 mgd)

    30

  • 8/7/2019 Sewer Overview

    27/39

    27

  • 8/7/2019 Sewer Overview

    28/39

    Bypasses Definition Flow at WWTP receiving less than SecondaryTreatment

    (will receive primary & disinfection)Anticipated Level

    (subject to negotiations)9 events

    0.6% of total flow99.4% of total combined flow will meet

    Secondary

    Note: Above based on typical year.

    28

  • 8/7/2019 Sewer Overview

    29/39

  • 8/7/2019 Sewer Overview

    30/39

  • 8/7/2019 Sewer Overview

    31/39

  • 8/7/2019 Sewer Overview

    32/39

    131.7 MG 140.8 MG 18.1 MG 17.2 MG 0 2.3 MG

    BaxterPS

    WWTP

    Kibby

    Underground

    Storage

    Central

    Underground

    Storage

    Collet

    Underground

    Lovers

    LaneCentral

    AveMcDonelHeindelCollet

  • 8/7/2019 Sewer Overview

    33/39

    16.1 MG 15.8 MG 5.4 MG 7.8 MG 0 1.6 MG

    BaxterPS

    WWTP

    Kibby

    Underground

    Storage

    Central

    Underground

    Storage

    Collet

    Underground

    Lovers

    Lane

    Central

    Ave

    McDonelHeindelCollet

    Equalization

    Tank

    8 MG

    0.6 MG

    Storage

    Tank

  • 8/7/2019 Sewer Overview

    34/39

    Lima sewer system overview

    Regulatory Requirements

    Sanitary Sewer Overflow (SSO) Component

    Combined Sewer Overflow (CSO) Solutions

    Regulatory Compliance Costs & Benefits

  • 8/7/2019 Sewer Overview

    35/39

    Construction Cost ($M)

    Alternative 1 CSO/Yr 2 CSOs/Yr 4 -5 CSOs/Yr 7 - 9 CSOs/Yr 12 CSOs/YrTotal Sewer

    Separation

    Tank + 96 MGD At Plant $140.90 $79.90 $62.10 $49.00 $46.00

    $417.00

    Tunnel + 96 MGD At Plant $90.60 $57.10 $49.80 $44.50 $43.30

  • 8/7/2019 Sewer Overview

    36/39

    Rehabilitation (Plant & Baxter) (Done 6/11) $11.0 million

    Headworks, Primaries & Peak Wet Weather (96 mgd) $31.6 million*

    Interceptor (96 mgd) $3.2 million**

    Total $45.8 million

    36

    * 53 mgd capacity $19.9 million (maintainexisting)

    70 mgd capacity $30.0 million

    ** 53 mgd capacity $2.9 million(maintain existing)

    70 mgd capacity $3.0 million

  • 8/7/2019 Sewer Overview

    37/39

    SSO Control (5 year) $19.8M

    CSO Control (7-9 CSOs) $49.8M

    WWTP Expansion (96 MGD) $17.6M

    Repair and Replacement $TBD

    TOTAL $86.2M

  • 8/7/2019 Sewer Overview

    38/39

    Cleaner Pike Run and Ottawa River

    No CSOs to Pike Run on an annual basis

    Significant Pollution Load Reduction

    EPA Compliance

  • 8/7/2019 Sewer Overview

    39/39