Upload
the-lima-news
View
223
Download
0
Embed Size (px)
Citation preview
8/7/2019 Sewer Overview
1/39
City of Lima, Ohio
CSO Progress Update for Council
March, 2011
8/7/2019 Sewer Overview
2/39
Lima sewer system overview
Regulatory Requirements
Sanitary Sewer Overflow (SSO) Component
Combined Sewer Overflow (CSO) Solutions
Regulatory Compliance Costs & Benefits
8/7/2019 Sewer Overview
3/39
Allentow
n Rd.
KoopRd.
15th
Street
LostCreek
ColeStreet
West
Street FindlayRoad
Lima, OHSeparate Sanitary
8/7/2019 Sewer Overview
4/39
Sewer System OverviewWhere does the water go?
Combined System
SurfaceRunoff
Gutters &Downspouts
Bathrooms, Showers,Laundry, Dishwashing, etc.
Footer
Drains
Roadway Runoff &Other Impervious
Surfaces(i.e. Parking Lots)
Combined Sewer
Industrial Wastewater
8/7/2019 Sewer Overview
5/39
Sewer System OverviewWhere does the water go?
Separate System
SurfaceRunoff
Gutters &Downspouts
Bathrooms,Showers, Laundry,Dishwashing, etc.
Footer
Drains
Roadway Runoff &Other Impervious
Surfaces(i.e. Parking Lots)
Sanitary Sewer
Industrial Wastewater
Storm Sewer
8/7/2019 Sewer Overview
6/39
Sewer System OverviewWhere does the water go?
Sewer Mains and Interceptors
NO FLOW
SeparatedSewer Area
CombinedSewer Area
WastewaterTreatment Plant
Manhole
Local Combined Sewer
InterceptingStructure
RegulatingStructure
Overflow Sewer
CSO
Interceptor Sewer
Local Sanitary Sewer
Storm Sewer
InterceptingStructure
OutfallWWTP
Effluent
8/7/2019 Sewer Overview
7/39
Sewer System OverviewWhere does the water go?
Sewer Mains and Interceptors
DRY WEATHER FLOW
SeparatedSewer Area
CombinedSewer Area
WastewaterTreatment Plant
Manhole
Local Combined Sewer
InterceptingStructure
RegulatingStructure
Overflow Sewer
CSO
Interceptor Sewer
Local Sanitary Sewer
Storm Sewer
InterceptingStructure
OutfallWWTP
Effluent
8/7/2019 Sewer Overview
8/39
Sewer System OverviewWhere does the water go?
Sewer Mains and Interceptors
WET WEATHER FLOW
SeparatedSewer Area
CombinedSewer Area
WastewaterTreatment Plant
Manhole
Local Combined Sewer
InterceptingStructure
RegulatingStructure
Overflow Sewer
CSO
Interceptor Sewer
Local Sanitary Sewer
Storm Sewer
InterceptingStructure
OutfallWWTPEffluent
8/7/2019 Sewer Overview
9/39
Sewer System OverviewWhere does the water go?
Sewer Mains and Interceptors
EXTREME WET WEATHER FLOW
SeparatedSewer Area
CombinedSewer Area
WastewaterTreatment Plant
Manhole
Local Combined Sewer
InterceptingStructure
RegulatingStructure
Overflow Sewer
CSO
Interceptor Sewer
Local Sanitary Sewer
Storm Sewer
InterceptingStructure
OutfallWWTPEffluent
8/7/2019 Sewer Overview
10/39
Lima sewer system overview
Regulatory Requirements
Sanitary Sewer Overflow (SSO) Component
Combined Sewer Overflow (CSO) Solutions
Regulatory Compliance Costs & Benefits
8/7/2019 Sewer Overview
11/39
Limas system includes: 20 CSOs, 33 SSOs, 1 WWTP Currently no SSO policy dictating frequency ofoverflows
USEPAs CSO Policy Requires Controllingoverflows to 4 events/yearCSO activation may be greater based on affordabilitycriteria
8/7/2019 Sewer Overview
12/39
Lima sewer system overview
Regulatory Requirements
Sanitary Sewer Overflow (SSO) Component
Combined Sewer Overflow (CSO) Solutions
Regulatory Compliance Costs & Benefits
8/7/2019 Sewer Overview
13/39
Allentow
n Rd.
KoopRd.
15th
Street
LostCreek
ColeStreet
West
Street FindlayRoad
Lima, OHSeparate Sanitary
8/7/2019 Sewer Overview
14/39
Total SSO Volumes by Design Storm Size
2.38 2.78 3.32 4.30
8/7/2019 Sewer Overview
15/39
BASIN 5-Yr 10-Yr 25-Yr 100-Yr
Lost Creek $4,098,000 $4,816,000 $5,592,000 $7,297,000West Street $3,028,000 $3,457,000 $4,352,000 $5,000,000
Koop Road $4,778,000 $5,407,000 $5,672,000 $6,794,000
Allentown Road $4,527,000 $5,021,000 $5,328,000 $5,842,000
Cole Street $1,717,000 $2,101,000 $2,288,000 $2,558,000
Findlay Road $1,483,000 $1,551,000 $2,727,000 $3,157,000
15th Street $190,000 $281,000 $506,000 $714,000
Total $19,821,000 $22,634,000 $26,465,000 $31,362,000
Total Estimated Project Costs to Provide Protection forthe Specified Design Storm (Aug 2009 Dollars)
8/7/2019 Sewer Overview
16/39
Implementation: 10 - 12 Year CIP Program
8/7/2019 Sewer Overview
17/39
Lima sewer system overview
Regulatory Requirements
Sanitary Sewer Overflow (SSO) Component
Combined Sewer Overflow (CSO) Solutions
Regulatory Compliance Costs & Benefits
8/7/2019 Sewer Overview
18/39
WWTP Upgrade
CSO Storage Tank(s)
CSO Storage Tunnel
Sewer Separation
8/7/2019 Sewer Overview
19/39
WWTP capacity was compared with CSO storage needs
(either tank or tunnel) upstream to determine cost-effective
treatment/storage balance
Two main WWTP options were considered:
70 MGD Capacity
96 MGD Capacity
8/7/2019 Sewer Overview
20/39
Category Rating Criteria Category Rating Criteria
1Cost is more than 5 times higher than the lowest
cost alternative1
Extremely elaborate O&M requirements, requires
additional staff or training; cannot be expanded or
retrofitted for additional CSO control; history of
significant maintenance problems
2Cost is more than 25% higher than the lowest
cost but less than 5 times higher
2
Moderately complex, requires general training; could
be expanded on a limited basis with some difficulty;
moderately reliable
3Lowest cost alternative or alternative cost is
within 25% of the lowest cost[3
Straight-forward to operate, limited training; could be
easily expanded or retrofitted; minimal maintenance
with proven track record
1Cannot meet CSO control goal without significant
additional improvements1
Specialty Construction Firms required, highest risk
construction methods
2Meets CSO control goal with minor additional
improvements2
Mix of Specialty and Conventional Construction Firms
required, moderate risk
3 Meets CSO control goal 3
Conventional Construction Firms can perform all
work, low risk
1Discharges the largest pollutant load into the
environment
2 Discharges pollutant load between 1 and 3
3Discharges the smallest pollutant load into the
environment
1
Extreme, sustained, widespread disruption to
community, large scale surface impacts that
interrupt traffic and cause extreme levels ofnoise, odor, vibration or other inconveniences;
would result in major public opposition; requires
extensive permitting approval process
2
Moderate levels of noise, odor, vibration or other
inconveniences; has no significant history of
opposition;
3
Minimal levels of noise, odor, vibration or other
inconveniences; embraced by impacted public;
normal permit review and approval process
Cost
Conformance
with Objectives
Environmental
Issues
Public Disruption
Operational
Issues
Constructability
8/7/2019 Sewer Overview
21/39
Alternative Cost
Conforman
cew
ith
Obj
ectiv
es
Environm
ental
Issu
es
Public
Dis
ruption
Ope
ratio
nalIss
ues
Constru
ctabilit
y
TOTAL Comments
1: Tank + 70 MGD 2 3 2 2 3 2 141) Tank is easier to maintain/clean because it is not as deep as tunnel, City
owns Simmons Field, site of the major tank
2: Tank + 96 MGD 3 3 3 2 3 2 16
1) Tank is easier to maintain/clean because it is not as deep as tunnel
2) More annual volume will receive primary + disinfection than the 70 MGDoption since corresponding volume will overflow at CSOs and receive
treatment by fine screens but no disinfection.
3) City owns Simmons Field, site of major tank
3: Tunnel + 70 MGD 2 3 2 3 2 1 13
1) Tunnel construction has more risk, deep dewatering pump staiton will be
harder to maintain/service than tank pump station
2) Specialty contractor will be needed to perform work
4: Tunnel + 96 MGD 3 3 3 3 2 1 15
1) Tunnel construction has more risk, deep dewatering pump station will be
harder to maintain/service than tank pump station
2) More annual volume will receive primary + disinfection than the 70 MGD
option since corresponding volume will overflow at CSOs and receive
treatment by fine screens but no disinfection.
3) Specialty contractor will be needed to perform work
5: Complete
Separation1 3 1 1 3 3 12
1) High levels of public disruption, less pollutant removal than all other
alternatives
8/7/2019 Sewer Overview
22/39
22
8/7/2019 Sewer Overview
23/39
*Capacity shown for each process in approximate peak flow
Baxter Pump Sta.(56 mgd)
Preliminary
(96 mgd)
Existing
Primaries(26 mgd)
NewPrimaries(40 mgd)
ActivatedSludge
(40 mgd)
Towers(30 mgd)
Cl2
(40 mgd)
54" (33 mgd)
72" (63 mgd)
36"(12 mgd)
96
26
40
Dry Weather
Tower Seed
ToRiver
40 mgd duringwet weather
Disinfection(56 mgd)
30
23
8/7/2019 Sewer Overview
24/39
*Capacity shown for each process in approximate peak flow
24
Baxter Pump Sta.(56 mgd)
Preliminary
(96 mgd)
Existing
Primaries(26 mgd)
NewPrimaries(40 mgd)
ActivatedSludge
(40 mgd)
Towers(30 mgd)
Cl2
(40 mgd)
54" (33 mgd)
72" (63 mgd)
36"(12 mgd)
96
26
40
Dry WeatherTower Seed
ToRiver
40 mgd duringwet weather
Disinfection(56 mgd)
30
8/7/2019 Sewer Overview
25/39
*Capacity shown for each process in approximate peak flow
25
Baxter Pump Sta.(56 mgd)
Preliminary
(96 mgd)
ExistingPrimaries(26 mgd)
NewPrimaries(40 mgd)
ActivatedSludge
(40 mgd)
Towers(30 mgd)
Cl2
(40 mgd)
54" (33 mgd)
72" (63 mgd)
36"(12 mgd)
96
26
40
Dry WeatherTower Seed
ToRiver
40 mgd duringwet weather
Disinfection(56 mgd)
30
8/7/2019 Sewer Overview
26/39
*Capacity shown for each process in approximate peak flow
26
Baxter Pump Sta.(56 mgd)
Preliminary
(96 mgd)
ExistingPrimaries(26 mgd)
NewPrimaries(40 mgd)
ActivatedSludge
(40 mgd)
Towers(30 mgd)
Cl2
(40 mgd)
54" (33 mgd)
72" (63 mgd)
36"(12 mgd)
96
26
40
Dry WeatherTower Seed
ToRiver
40 mgd duringwet weather
Disinfection(56 mgd)
30
8/7/2019 Sewer Overview
27/39
27
8/7/2019 Sewer Overview
28/39
Bypasses Definition Flow at WWTP receiving less than SecondaryTreatment
(will receive primary & disinfection)Anticipated Level
(subject to negotiations)9 events
0.6% of total flow99.4% of total combined flow will meet
Secondary
Note: Above based on typical year.
28
8/7/2019 Sewer Overview
29/39
8/7/2019 Sewer Overview
30/39
8/7/2019 Sewer Overview
31/39
8/7/2019 Sewer Overview
32/39
131.7 MG 140.8 MG 18.1 MG 17.2 MG 0 2.3 MG
BaxterPS
WWTP
Kibby
Underground
Storage
Central
Underground
Storage
Collet
Underground
Lovers
LaneCentral
AveMcDonelHeindelCollet
8/7/2019 Sewer Overview
33/39
16.1 MG 15.8 MG 5.4 MG 7.8 MG 0 1.6 MG
BaxterPS
WWTP
Kibby
Underground
Storage
Central
Underground
Storage
Collet
Underground
Lovers
Lane
Central
Ave
McDonelHeindelCollet
Equalization
Tank
8 MG
0.6 MG
Storage
Tank
8/7/2019 Sewer Overview
34/39
Lima sewer system overview
Regulatory Requirements
Sanitary Sewer Overflow (SSO) Component
Combined Sewer Overflow (CSO) Solutions
Regulatory Compliance Costs & Benefits
8/7/2019 Sewer Overview
35/39
Construction Cost ($M)
Alternative 1 CSO/Yr 2 CSOs/Yr 4 -5 CSOs/Yr 7 - 9 CSOs/Yr 12 CSOs/YrTotal Sewer
Separation
Tank + 96 MGD At Plant $140.90 $79.90 $62.10 $49.00 $46.00
$417.00
Tunnel + 96 MGD At Plant $90.60 $57.10 $49.80 $44.50 $43.30
8/7/2019 Sewer Overview
36/39
Rehabilitation (Plant & Baxter) (Done 6/11) $11.0 million
Headworks, Primaries & Peak Wet Weather (96 mgd) $31.6 million*
Interceptor (96 mgd) $3.2 million**
Total $45.8 million
36
* 53 mgd capacity $19.9 million (maintainexisting)
70 mgd capacity $30.0 million
** 53 mgd capacity $2.9 million(maintain existing)
70 mgd capacity $3.0 million
8/7/2019 Sewer Overview
37/39
SSO Control (5 year) $19.8M
CSO Control (7-9 CSOs) $49.8M
WWTP Expansion (96 MGD) $17.6M
Repair and Replacement $TBD
TOTAL $86.2M
8/7/2019 Sewer Overview
38/39
Cleaner Pike Run and Ottawa River
No CSOs to Pike Run on an annual basis
Significant Pollution Load Reduction
EPA Compliance
8/7/2019 Sewer Overview
39/39