25
 Operations Management-104 1 Rec ap of Pre vious S ession Understand Quality Costs of Quality Impact of Quality on Operation s Impact of Quality on Supply Chain

Sessions 19 and 20 -Quality Control

  • Upload
    sudipta

  • View
    218

  • Download
    1

Embed Size (px)

DESCRIPTION

Quality Control

Citation preview

  • Operations Management-104 1

    Recap of Previous Session

    Understand QualityCosts of QualityImpact of Quality on OperationsImpact of Quality on Supply Chain

  • Operations Management-104

    Quality Control

    Debabrata Ghosh

    *Images available in the public domain

  • Operations Management-104 3

    The ANZ Door Manufacturing Case

    The COO of ANZ Door Manufacturing Company has recently received complaints from the sales headthat several of his team members (Salespersons) have received customer complaints over the past few months. The complaints vary from higher costs, the door not meeting the customers required specifications or door not having the required quality standards in terms of safety, durability and ease of operation.

    The COO decided to form an internal Quality Assurance Team (QAT) to study the concerns and suggest any improvement changes, if required.

    Approach:To begin with, the QAT team ran a survey of 1000 past and present customers, asking them to rate their experiences with each of the following aspects of ANZ Door's products and services:Cost of purchasing and maintaining a doorResponse time from ordering a door until its deliveryDegree of door customization permitted in accommodating individual preferencesAfter sales service qualityDoor quality in terms of its fit and finish; ease of operation and durability

  • Operations Management-104 4

    The ANZ Door Manufacturing Case

    Step 1: Based on the survey feedback, the QAT team lists the number of complaints received :

    Type of Quality Number of Complaints

    Cost 10

    Response Time 5

    Customization 4

    Service Quality 15

    Door Quality 25

    Step 2: Based on the above table, QAT team applies the Pareto Chart to prioritize customer complaints

    0 10 20 30

    Door Quality

    Service Quality

    Cost

    Response Time

    Customization

    Number of Complaints

    Number of Complaints

  • Operations Management-104 5

    The ANZ Door Manufacturing Case

    Day

    Time/Day

    1 2 3 4 5 6 7 8 9 10

    9 a.m. 81 82 80 74 75 81 83 86 88 82

    11 a.m. 73 87 83 81 86 86 82 83 79 84

    1 p.m. 85 88 76 91 82 83 76 82 86 89

    3 p.m. 90 78 84 75 84 88 77 79 84 84

    5 p.m. 80 84 82 83 75 81 78 85 85 80

    Day

    Time/Day

    11 12 13 14 15 16 17 18 19 20

    9 a.m. 86 86 88 72 84 76 74 85 82 89

    11 a.m. 84 83 79 86 85 82 86 85 84 80

    1 p.m. 81 78 83 80 81 83 83 82 83 90

    3 p.m. 81 80 83 79 88 84 89 77 92 83

    5 p.m. 87 83 82 87 81 79 83 77 84 77

    Refer to Tab: Histogram in Histogram of Door Weights.xls

  • Operations Management-104

    Assignable variation is caused

    by factors that can be clearly

    identified and possibly

    managed

    Common variation is inherent

    in the production process

    Example: A poorly trained employee that creates variation in finished product output.

    Example: The door manufacturing process is inherently variable

    Basic forms of Variation

    6

  • Operations Management-104 7

    An Understanding of standard deviation

    (2) 0.9772, or Pr(x + 2) 0.9772.

    In the ANZ Door Manufacturing Case, the QAT team would expect 99.73% of the door weights would be within +- 3 standard deviations from the mean (between 69.9 and 95.1 kg).

    =0 1 2 3-1-2-3

    95%

    99.74%

  • Operations Management-104 8

    The ANZ Door Manufacturing Case

    Step 6: Control ChartsA generic control chart : LCL = - zUCL = + z

    Average (or X-bar) and Range (or R) Control Charts:

    X-bar - Process central tendency based on estimated process mean

    RA - x = LCL

    RA + x = UCL

    2

    2

    Limits ControlChart x

    x = The average of the means of the samples

    j = Sample Numberm = Total number of samples

    i = ith observationn = Number of observations in each sub-group

    =

    Refer to Tab: X-bar and R in Histogram of Door Weights.xls

  • Operations Management-104

    Average (or X-bar) and Range (or R) Control Charts:

    R chart - Process variability based on estimated process range

    Rj = Difference between the highest and lowest measurement in the sample

    n = Number of observations in each sub-group

    RD = LCL

    RD = UCL

    3

    4

    Limits ControlChart R

    R= Average of the measurement differences R for all samples =

    n A2 D3 D4

    2 1.88 0 3.27

    3 1.02 0 2.57

    4 0.73 0 2.28

    5 0.58 0 2.11

    6 0.48 0 2.00

    7 0.42 0.08 1.92

    8 0.37 0.14 1.86

    9 0.34 0.18 1.82

    10 0.31 0.22 1.78

    11 0.29 0.26 1.74

    9

    Source: Exhibit 9A.6, Operations and Supply Management, Chase, Shankar, Jacobs and Aquilano, McGraw Hill 12th Ed., 2010

  • Operations Management-104

    Average (or X-bar) and Range (or R) Control Charts:

    UCL = 82.5 + 0.58* 10.05 = 82.5 + 5.829 = 88.33LCL = 82.5 0.58*10.05 = 76.67

    RA - x = LCL

    RA + x = UCL

    2

    2

    Limits ControlChart x

    RD = LCL

    RD = UCL

    3

    4

    Limits ControlChart R

    UCL = 2.11* 10.05 = 21.21 LCL = 0

    10

  • Operations Management-104

    Normal Behavior

    Possible problem, investigate

    UCL

    LCL

    Samples

    over time

    1 2 3 4 5 6

    UCL

    LCL

    Samples

    over time

    1 2 3 4 5 6

    Control Chart Patterns

    11

  • Operations Management-104

    Constructing p-charts

    p is the proportion of non-conforming items found in a sample. p-chart is often called fraction non-conforming chart.Assume, that k samples each of size n are collected.Let y, represent the number non-conforming in a particular sample, then proportion non-conforming is y/n.Let, pi be the fraction non-conforming in the i th sample, the average fraction non-conforming for group of k samples is

    =

    An estimate of the s.d. Is given by:

    Thus, UCL =LCL =

    + z

    - z

    12

    Q: The operators of automated sorting machines in a post office must read the ZIP code on letters and divert the letters to the proper carrier routes. Over a months study, 25 samples each of 100 letters were chosen and the number of errors were recorded. The data presented is the following:

    Refer to Tab: p-chart in Histogram of Door Weights.xls

  • Operations Management-104

    Constructing c-charts

    13

    A non-conforming item may have more than one non-conformance factor. For e.g. A customers order may have several errors such as wrong item, wrong quantity, wrong price etc. To monitor the number of non-conformances per unit, a c-chart is used.

    For a c-chart,UCL =

    LCL =

    where, sc =

    z

    z

    Refer to Tab: c-chart in Histogram of Door Weights.xls

  • Operations Management-104

    Summary of Control Charts

    14

    Type of Measurement

    Type of Attribute

    p-chart c-chart

    X-bar and R chart

    Discrete Continuous

    Proportion Non-conforming

    Non-conformances

    per unit

  • Operations Management-104

    Process Capability

    15

    Process capability is the ability of the process to meet customer specifications

    Process Control Process Capability

    Looks at internal stability Customer centric focus

    Analysis based on samples Each individual unit matters

    Pertains to production process Pertains to Design specifications

    The ANZ Door Manufacturing Case : If the design specifications given by the design team for customer use varies between 75-85 Kg, process capability studies the variability of the process with respect to these design/customer specifications.

  • Operations Management-104

    Process Capability

    16

    (b) Design specifications and process variation the same; process is capable of meeting specifications most of the time.

    Design Specifications

    Process

    (a) Process variation exceeds design specifications; process is not capable of meeting specifications all the time.

    Design Specifications

    Process

  • Operations Management-104

    (c) Design specifications greater than process variation; process is capable of always conforming to specifications.

    Design Specifications

    Process

    Process Capability

    17

  • Operations Management-104

    Fraction of Output within specifications

    Q: The ANZ Door Manufacturing Case : Given, design specifications of the doors as 75-85 kg with 75 being the lower specification limit (LSL) and 85 being the upper specification limit (USL), what is the fraction of door output that meets the door specifications (given, production process is normal with mean = 82.5 kg and s.d. = 4.2 kg)

    18

    Ans:Prob(75

  • Operations Management-104

    Process Capability Measures

    Cp =tolerance range

    process range

    upper spec limit - lower spec limit

    6=

    19

    Process Capability Ratio

    Cpk = minimum

    x - lower specification limit

    3

    =

    upper specification limit - x

    3

    =

    ,

    Process Capability Index

    Q: The ANZ Door Manufacturing Case : Whats the process capability?

    Refer to Tab: ProcessCapability in ProcessCapability of ANZ Door Manf Company.xls

  • Operations Management-104 20

    Understanding Process capability ratio, Defects (ppm) and sigma measure

    A 3-sigma process: Cp = = 1

    A 6-sigma process: Cp = = 2

    6

    6

    6

    12

    A 3-sigma process: 0.9973 of the output falls within specifications, which means 0.0027 defects => 2700 defects in parts per million (ppm).

    A 6-sigma process: 0.999999998 of the output falls within specifications, which means 1.97318 *10^-9 defects => 0.002 defects in parts per million (ppm)

    Cp Sigma level ()Area under

    the probability density function

    Process yieldProcess fallout (in

    terms of PPM)

    0.33 1 0.6826894921 68.27% 317311

    0.67 2 0.9544997361 95.45% 45500

    1.00 3 0.9973002039 99.73% 2700

    1.33 4 0.9999366575 99.99% 63

    1.67 5 0.9999994267 99.9999% 1

    2.00 6 0.9999999980 99.9999998% 0.002 500

    60

    42

    16

  • Operations Management-104 21

    Mean shift under a Six-sigma process

    Motorola allows for a 1.5 sigma shift in mean which results in a process producing on an average 3.4 defective units per million.

    4.5 sigma process. Percentage yield is 99.99966%. Therefore, percent defective is 0.00034%. Thus, Defects in Parts per million = 3.4

  • Operations Management-104 22

    Process Capability Improvement

  • Operations Management-104 23

    Six-sigma Examples

    Mumbai Dabbawalas pick up, deliver and return tiffin lunch boxes from 200,000 homes and apartments to 80,000 office locations that are situated over 40 miles away, hardly using any fuel or modern technology. The distribution process is an ingenious combination of coding, aggregating and sorting boxes and moving them in crates through public trains, push carts and bicycles from each household to a correct office destination and back to home. The error rate in delivery is 1 in more than million trips with a cost of about $10 a month.

    Harley-Davidson, Bank of America, HSBC, Hospital Chains

  • Operations Management-104 24

    Process Capability Improvement

    The ANZ Door Manufacturing Case :

    1) Mean Shift: If the average door weight could be brought down to 80 kg thus shifting the entire distribution.

    Ans:Prob(75

  • Operations Management-104 25

    Munchies snack food company packages potato chips in a process with a process mean of 8.8 oz and a s.d. of 0.12 oz. The packages are designed for 9 oz of chips with a tolerance of 0.5 oz. The company wants to determine the capability of the current process.

    Question:

    The process mean is off the center. And the capability of the process is

    Cpk = Min[ (8.8-8.5)/(3*0.12); (9.5-8.8)/(3*0.12)]= Min[0.83,1.94]= 0.83

    Cp = (9.5-8.5)/(6*0.12) = 1.389

    What percentage of packages produced are defective?

    1- Prob(8.5