Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
US Army Corps of Engineers
BUILDING STRONG®
Session no. A
TECHNICALITIES – SECTION 438
Kevin Araki, Bruce Chun,
Brandi Jim On, Russell Leong
U.S. Army Corps of Engineers
20 May 2010
BUILDING STRONG®
ARCHITECTURE
SPECIFICATIONS FOR
STEEL DOOR DESIGN
BUILDING STRONG®
Steel Doors and Frames
Unified Facilities Guide Specification
(UFGS) Section 08 11 13, paragraph 2.1.1
Door Classification (Levels 1, 2, 3 & 4) Level 1 – Standard Duty Doors
Level 2 – Heavy Duty Doors
Level 3 – Extra Heavy Duty Doors
Level 4 – Maximum Duty Doors
For a normal standard facility, which door classification
would you specify??
BUILDING STRONG®
Steel Doors and Frames
Approximately 20% of the projects submitted for review left
paragraph 2.1.1 unedited. All Door Levels (1, 2, 3 and 4) are
included resulting in an undefined requirement for each door.
(Further editing of Specifications needed)
Approximately 40% of the projects submitted for review specify only
Level 1 – Standard Duty Doors. (This is incorrect, Level 1 doors are
specified for use in areas of very low use (i.e. closet doors). The
majority of the door classifications specified should be either Level 2
or Level 3)
Approximately 20% of the projects submitted for review specify
Level 2 - Heavy Duty Doors and/or Level 3 – Extra Heavy Duty
Doors (In most cases, this is acceptable)
BUILDING STRONG®
Steel Doors and Frames
GUIDANCE NOTES FROM UFGS SECTION 08 11 13
BUILDING STRONG®
Steel Doors and FramesSDI 108-04 Recommended Selection and Usage Guide
for Standard Steel Doors (Table 2)
BUILDING STRONG®
Steel Doors and FramesSDI 108-04 Recommended Selection and Usage Guide
for Standard Steel Doors (Table 2)
BUILDING STRONG®
Steel Doors and FramesClassification Levels shown on Drawings and/or Specs
SPECS
DRAWINGS
BUILDING STRONG®
STRUCTURAL
CHANGES TO UFC 4-023-03
Design of Buildings to Resist
Progressive Collapse
BUILDING STRONG®
UFC 4-023-03
Progressive Collapse applies to all DoD
services and all DoD inhabited buildings 3
stories or higher.
Standoff distance is irrelevant to progressive
collapse.
Current edition of UFC 4-023-03 is 14 July
2009.
Three design approaches in UFC 4-023-03:
Tie Forces, Alternate Path Method, and
Enhanced Local Resistance.
BUILDING STRONG®
Design Requirements
Design Requirements were revised in the current
edition of the UFC:
- Previous edition (25 Jan 2005) of the UFC used
“Levels of Protection” (LOPs), determined by the
Project Planning Team, to define the progressive
collapse design requirements.
- Current edition (14 July 2009) of the UFC
correlates the level of progressive collapse, for
both new and existing structures, with the
Occupancy Category of a structure.
BUILDING STRONG®
Design Requirements Design Requirements, based on Occupancy
Category are shown in Table 2-2 of UFC 4-023-03:
BUILDING STRONG®
Occupancy Category
The Occupancy Category is taken from
UFC 3-310-01, or specified by the building owner.
The Occupancy Category Level can be considered
as a measure of the consequences of a progressive
collapse event and is based on:
The level of occupancy
The building function or criticality.
BUILDING STRONG®
Changes in UFC 4-023-03
The previous edition of the UFC required Tie Forces for
Occupancy Category II (Low Level of Protection). The
Current UFC allows the option of using Alternate Path or
Tie Force method.
The “Effective Column and Wall Height” design
requirement (laterally unsupported length equal to two
stories must be used in the design or analysis of a
column or wall) was removed in the Current UFC.
The “Upward Load on Floors and Slabs” design
requirement (slab/floor system at each bay and all floors
had to withstand a net upward load) was removed in the
Current UFC.
BUILDING STRONG®
Changes in UFC 4-023-03 (cont.)
Tie Force Method was revised such that the floor
and roof system (i.e. slabs and decks) provide and
carry the internal and peripheral tie forces. Tie
forces are not carried by the beams, girders, etc.
The Enhanced Local Resistance (ELR)
requirements vary with the Occupancy Category.
Please refer to UFC 4-023-03 (14 July 2009) for
other changes.
BUILDING STRONG®
MECHANICAL
BUILDING AIR TIGHTNESS
REQUIREMENTS
BUILDING STRONG®
Building Air Tightness Requirements
Directive (ECB) issued 30 Oct 2009
All (FY10) new construction projects
All (FY10) renovation projects where costs
are greater/equal to 25% of replacement
Building envelope shall be designed and
constructed with a continuous air barrier to
control air leakage into (or out of) the
conditioned space
BUILDING STRONG®
Design (Drawing) Requirements
Clearly identify all air barrier components
of each envelope assembly and detail the
joints, interconnections, and penetrations
Clearly indentify the boundary limits of the
bldg air barriers, and of the zone or zones
to be tested for air tightness
Motorized dampers to close all intakes &
exhausts during inactive periods
BUILDING STRONG®
Bldg. Air Leakage Testing
Blow Door Testing:
Air leakage rate of the envelope doesn’t
exceed 0.25 CFM/sq ft @ pressure differential
of 0.3 iwg (75 Pa) i.a.w. ASTM E779 or ASTM
E1827
Accomplish tests using BOTH pressurization
and depressurization
Infrared Thermography Testing on the
completed bldg.
BUILDING STRONG®
Blow-door tests complemented by thermography
identify problems with building air tightness and
areas with poor insulation where leakage occurs
(red and white areas in photo)
BUILDING STRONG®
Identification of leakage pathways using smoke
pencil (left), theatrical fog (center), and infra-red
thermography (right).
BUILDING STRONG®
“U.S. Army Corps of Engineers
Air Leakage Test Protocol For
Measuring Air Leakage In Buildings”
Available on the Whole Building Design Guide website
http://www.wbdg.org/references/pa_dod_energy.php
BUILDING STRONG®
MECHANICAL
ENGINEERED VENT & SOVENT
TYPE SYSTEMS
BUILDING STRONG®
Guidance Inconsistency
UFC 3-420-01FA (Plumbing)-Prohibited. A
Philadelphia (one pipe), air admittance
valve system, engineered vent system, or
a sovent (aerator) type system shall not be
permitted.
MILCON Transformation-Permitted
BUILDING STRONG®
BUILDING STRONG®
Advantages:
►Allowed by Uniform Plumbing Code (UPC)
►Used in high-rise applications
►Reduced material & labor cost
Disadvantages:
►Mixed track record
►Manufacturer specific installation guidance
►Multiple systems in the same facility
►Potential for future modifications to be
connected incorrectly
BUILDING STRONG®
Resolution:
USACE HQ will revise the MILCON
Transformation requirements to reflect the
UFC prohibition.
BUILDING STRONG®
CONSTRUCTION QUALITY
MANAGEMENT
FUTURE CHANGES
BUILDING STRONG®
Engineering & Construction Bulletin
(ECB) to be issued
Joint policy by USACE and NAVFAC
Course Administration by USACE
Learning Center (ULC)
Registration
Record Keeping
BUILDING STRONG®
Recertification Options
Retake the instructor led course
Online course available at the ULC
website; Anticipated launch on 1 Oct 2010
Certificates
Valid for 5 years
Certificates may be revoked for poor
performance
BUILDING STRONG®
CIVIL
STORMWATER
BUILDING STRONG®
SECTION 438
ENERGY INDEPENDENCE
& SECURITY ACT 2007
BUILDING STRONG®
SECTION 438
Energy Independence and Security Act of 2007 (EISA 2007) now
effectively mandates LID for federal projects
SEC. 438. STORM WATER RUNOFF REQUIREMENTS FOR
FEDERAL DEVELOPMENT PROJECTS.
The sponsor of any development or redevelopment project involving
a Federal facility with a footprint that exceeds 5,000 square feet shall
use site planning, design, construction, and maintenance strategies
for the property to maintain or restore, to the maximum extent
technically feasible, the predevelopment hydrology of the property
with regard to the temperature, rate, volume, and duration of flow.
BUILDING STRONG®
DESIGN BUILD RFP
5.1.2.6 Stormwater Management. Employ design and construction
strategies (Best Management Practices) that reduce stormwater
runoff, reduce discharges of polluted water offsite and maintain or
restore predevelopment hydrology with respect to temperature, rate,
volume, and duration of flow to the maximum extent practicable.
See paragraph 6, Project Specific requirements for additional
information.
BUILDING STRONG®
DEFINITIONS
6.x.1 Definitions.
“Maximum Extent Technically Feasible (METF)”. Project site design
options shall be evaluated to achieve the design objective to the
maximum extent technically feasible. METF criterion requires full
employment of accepted and reasonable storm water retention and
reuse technologies (e.g., bio-retention areas, permeable pavements,
cisterns / recycling, and green roofs), subject to site and regulatory
constraints (e.g., site size, soil types, vegetation, demand for
recycled water, existing structural limitations, state or local
prohibitions on water collection). All site-specific technical
constraints that prohibit the full attainment of the design
objective shall be documented. If the design objective cannot be
met within the project footprint, LID measures may be applied on
nearby parcels of DoD property (e.g., downstream from the project)
within available resources.
BUILDING STRONG®
DEFINITIONS
6.x.1 Definitions.
“Predevelopment hydrology” is defined as the pre-project hydrologic
conditions of temperature, rate, volume, and duration of storm water
flow from the project site. The analysis of the predevelopment
hydrology must include site-specific factors (such as soil type,
ground cover, and ground slope) and use modeling or other
recognized tools to establish the design objective for the water
volume to be managed from the project site.
“Predevelopment” equals Pre-project equals the vegetative state.
BUILDING STRONG®
DESIGN TEAM
6.x.3 DESIGN TEAM
• Civil Engineer;
• Site grading
• Geotechnical Engineer;
• Exfiltration; methods to maintain or enhance.
• Geotextiles;
• Geogrids
• Landscape Architect
• Plant selection for low areas with longer saturation times;
• Plant selection for high areas
• Low P-index soil
• Upper soil mix (sand, compost, etc.)
BUILDING STRONG®
DESIGN CRITERIA
6.x.4 Pollutants To Reduce. The post construction Best
Management Practices (BMPs) shall reduce Total Suspended Solids;
both dissolved and particulate nutrients; suspended petroleum;
suspended metals; and temperature.
6.x.4.a Regulated Pollutants for Project in a Watershed with
Total Maximum Discharge Loads (TMDL). This project storm
drain system does discharge to a watershed with TMDL. The
regulated pollutants are total suspended solids, nutrients, etc. This
will require additional post construction BMPs to further reduce the
pollutant loads.
• TMDLs established for North and South Fork Kaukonahua
Stream.
• TMDLs expected late 2010 or 2011 for Waikele Stream.
BUILDING STRONG®
ADDITIONAL CONSIDERATIONS
6.x.5 Operation and Maintenance Manual. Provide and O&M
manual for each post construction BMP used. Provide an estimate
of the annual maintenance costs in the O&M manual.
6.x.6 Plans and specifications. The plans and specifications shall
address protection of the BMP during construction to include
preventing damage and sediment accumulation. The plans and
specification shall address periodic and final cleaning of the BMPs
prior to project turnover.
6.x.7 Other Requirements. DOD is required to provide estimated
design and construction costs for implementing EISA Section 438.
Documented the project cost estimate as a separate line item. Final
implementation costs will be documented as part of the project
historical file. Post-construction analysis shall also be conducted to
demonstrate the effectiveness of as-built storm water features. I.e.,
apply water to the BMP and measure time to drain, etc.
BUILDING STRONG®
Ref: NC State University, A&T State University Cooperative Extension; Urban Waterways; Permeable Pavement: Research Update and Design Implications
LOW IMPACT DEVELOPMENT
PERMEABLE PAVERS
BUILDING STRONG®
Ref: EPA 841-B-09-001; Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal Projects under Section 438 of the Energy Independence and Security Act; December 2009
EPA Technical Guidenance
BUILDING STRONG®
Ref: EPA 841-B-09-001; Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal Projects under Section 438 of the Energy Independence and Security Act; December 2009
Comparison Water Volumes
Section
438
(in)
LEED 6.1
– 1 yr 24
hr
(in)
LEED 6.1
– 2 yr 24
hr
(in)
CCH
Detention
(in)
CCH
Water
Quality
(in)
1.8 4 6 1SB
BUILDING STRONG®
Ref: http://www.aquapave.com/
PERMEABLE PAVEMENT
PARTIAL EXFILTRATION
INTERNAL
WATER
STORAGE
EXFILTRATION
BUILDING STRONG®
HAWAII EXAMPLES
POROUS CONCRETE
EWA BEACH ELEMENTARY
PCP
PCP
AC
BUILDING STRONG®
HAWAII EXAMPLES
POROUS CONCRETE – AHFH KALAKAUA
PCP
BUILDING STRONG®
BIOSWALE IN PARKING LOT
Ref: Nancy White; William F. Hunt, P.E., Ph.D.; Urban
Waterways, Designing Rain Gardens (Bio-Retention Areas),
NC State University & A&T State University
BUILDING STRONG®
LOW IMPACT DEVELOPMENT
BIOSWALE IN PARKING LOT
Ref1: Steve Thibaudeau, P.E, Putting the LID on Site Design,
COE Louisville District
Ref2: Nancy White; William F. Hunt, P.E., Ph.D.; Urban
Waterways, Designing Rain Gardens (Bio-Retention Areas),
NC State University & A&T State University
Ref1: Ref2:
GEOTEXTILE
BUILDING STRONG®
IMPROVEMENTS TO WATER QUALITY
Ref: William F. Hunt, P.E., Ph.D.; Bioretention Research
& Impacts on Design, NC State University
www.bae.ncsu.edu/stormwater
BUILDING STRONG®
Ref: Exfiltration from Pervious Concrete into a Compacted
Clay Soil, Wesley C. Wright, The University of Tennessee
MAINTAINING INSITU EXFILTRATION RATES
BUILDING STRONG®
Ref: Exfiltration from Pervious Concrete into a Compacted
Clay Soil, Wesley C. Wright, The University of Tennessee
MAINTAINING INSITU EXFILTRATION RATES
BUILDING STRONG®
Ref: Robert A. Brown, E.I.; William F. Hunt, P.E., Ph.D.; Urban
Waterways, Improving Exfiltration from BMPs: Research and
Recommendations, NC State University & A&T State
University
MAINTAINING INSITU EXFILTRATION RATES
BUILDING STRONG®
Ref: Donald D. Carpenter and Laura Hallam; An investigation
of rain garden planting mixture performance and the
implication for design; Low Impact Development 2008.
MIXTURES AFFECTING PERMEABILITY
BUILDING STRONG®
Ref: Donald D. Carpenter and Laura Hallam; An investigation
of rain garden planting mixture performance and the
implication for design; Low Impact Development 2008.
MIXTURES AFFECTING PERMEABILITY
BUILDING STRONG®
6.x.2.1 EPA 841-B-09-001; Technical Guidance on Implementing the
Stormwater Runoff Requirements for Federal Projects under Section 438 of
the Energy Independence and Security Act; December 2009.
6.x.2.2 EPA memorandum; Clarification on which stormwater infiltration
practices/technologies have the potential to be regulated as "Class V" wells
by the Underground Injection Control Program, 13 June 2008.
6.x.2.3 Memorandum for Assistant Secretary of the Army, DoD
Implementation of Storm Water Requirements under Section 438 of the
Energy Independence and Security Act (EISA); 13 October 2009.
6.x.2.4 UFC 3-230-06A; Subsurface Drainage; 16 January 2004.
6.x.2.5 Public Works Technical Bulletin 200-1-62, Low Impact Development
for Sustainable Installations: Stormwater Design and Planning Guidance for
Development Within Army Training Areas, 1 October 2008.
6.x.2.6 UFC 3-210-10, Low Impact Development, 25 October 2004.
REFERENCES
BUILDING STRONG®
6.x.2.7 Donald D. Carpenter and Laura Hallam, An investigation of rain
garden planting mixture performance and the implication for design, Low
Impact Development 2008.
6.x.2.8 Robert A. Brown, William F. Hunt, NC State University and A&T
State University Cooperative Extension, Urban Waterways, Improving
Exfiltration from BMPs: Research and Recommendations.
6.x.2.9 Interlocking Concrete Pavement Institute, Permeable Interlocking
Concrete Pavements, 3rd Edition.
STORMCON (annual)
LOW IMPACT DEVELOPMENT CONFERENCE (annual)
http://stormh2o.com/
REFERENCES
BUILDING STRONG®
QUESTIONS?