30
SERVO Modeller: Integrating Distributed Grid Information via CIM Session: How Utilities are using the CIM for Power System Network Model Exchange CIM Users Group European Meeting 2017 Miguel Ponce de Leon (WIT-TSSG) Paul Hayes (ESB) 15 th June 2017

SERVO Modeller: Integrating Distributed Grid Information ...cimug.ucaiug.org/Meetings/EU2017/Erlangen CIMug Presentations/CI… · SERVO Modeller: Integrating Distributed Grid Information

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

SERVO Modeller: Integrating Distributed Grid

Information via CIM

Session: How Utilities are using the CIM for Power System Network

Model Exchange

CIM Users Group European Meeting 2017

Miguel Ponce de Leon (WIT-TSSG)

Paul Hayes (ESB)

15th June 2017

Agenda

• ICT, Digitalisation ESB Networks View.

• Implementation of Common Information Model in

ESB Networks.

• Developing CIM compliant software.

• Scalable ICT for energy systems with 100% RES

– H2020 RE-SERVE.

www.tssg.org 2

ICT, Digitalisation, the enabler

of Markets and Customer

Empowerment

Paul Hayes,

Smart Networks,

ESB Networks

4 www.esbnetworks.ie

Direction and futures

• MV & HV 99% observed

• 760 Substations

• 100,000+km

• 10,000 line sensors

• LV 99% unobserved

• 252,276 Substations

• 92,326km

• 100+ sensors

5 www.esbnetworks.ie

Areas of unobserved change and the future –

Demand Response & Flexibility:

• Electrified Mobility

• Electrified Heat

• Micro Generation

• Storage

• Prosumers

• Electrify Everything!

The fundamentals:

• Frequency

• Energy

• Power

• Voltage

6 www.esbnetworks.ie

Diversity and network loading

0

5

10

15

20

25

30

35

40

45

50

0 3 6 9 12 3 6 9 120

50

100

150

1 4 7 10

Traditional assumed load profiles Future stochastic, controlled and DER type loads

Flex opportunity yet to be exposedFlex opportunity yet to realised

Current assumed flex opportunity

7 www.esbnetworks.ie

What are we attempting to understand?

Can utilities deploy software in an effort to offset the

investment in traditional assets?

vsDigital Asset Traditional Asset

8 www.esbnetworks.ie

What are we attempting to understand?

• 70 years of optimisation

• 300% increase in instantaneous demand

• Localised – we need sensors and vision

• Transform sensor data into knowledge

• Share this with all actors to:• Avoid congestion

• Control voltage

• Advise on frequency

• Procure services

• Avoid traditional investment

9 www.esbnetworks.ie

Servo – What is it?

Implementation of Common Information

Model in ESB Networks

Project SERVO - System-wide Energy

Resource and Voltage Optimisation platform

Paul Hayes, Smart Networks

ESB Networks

11 www.esbnetworks.ie

What is it?

• Implementation of IEC Standard Common Information Model

• Captures all Distribution assets and data in single model

• Enables many use cases

• Asset Management – Load visualisation, Asset reporting

• Operations – Increased visibility of LV

• Capacity optimisation – enables DSU participation, investment offset

• System Services - voltage, frequency control

13 www.esbnetworks.ie

Challenges to implementation

Existing internal Industry Stakeholders New sources of data

Many data sources with many owners!!!

SCADA

OMS

Metering

Sensors

Weather

SAP

GIS

CustomersTSO

DSO

Market

Regulator Aggregator

Generator

14 www.esbnetworks.ie

Data Sources….

110/38kV

MV/LV

38/MV

LV Customers

SCADA

Metering

SAP

GIS

OMS

SERVO

ABB software

Customized for ESB

Locked down database

MV90

Customer QH metering

TSO/DSO interface metersAsset Register

Meter Point Reference Numbers

Non-QH metering

Intergraph System

Network Topology

Accuracy of records

Oracle System

Status of Network switch gear

Outage management

Feeds Customer interface

15 www.esbnetworks.ie

Overcoming barriers

• Benefits to the business need to be demonstrated

• Briefings, presentations across business to inform

• Not replacing existing systems but enhancing them using new

technology and software

• Give examples of what can be achieved

Lessons learned along the way…….

17 www.esbnetworks.ie

EXISTING LOAD VISUALISATION TOOL (EXCEL)

18 www.esbnetworks.ie

TO BE REPLACED BY WEB BASED APPLICATION WITH

AUTOMATIC DATA FEEDS……..

Developing CIM compliant software

Miguel Ponce de Leon (WIT-TSSG) 15 June 2017

20

Kilkee 38kv Station

21

Kilkee Station Model as a Software Object (JSON)

22

Kilkee Station Model visualised as a Software Object

23

Kilkee Station Model CIM validation

• In a 100% RES environment ICT infrastructures

will be required to be Fast, Reliable, and Secure:

• In the collection of

• Large amounts of measurements from a huge number of sensors

and devices

• In the transmission of

• Commands for voltage and frequency stability management.

Slide No. 24 © RESERVE 2016-2019 All rights reserved.

SCALABLE ICT FOR ENERGY SYSTEMS WITH 100% RES

6/14/2017

• Monitored field measurements are based on publish / subscribe

model.

-All collected data is based on a Common Information Model.

• Transmission of Control Commands are based on Policy-Based

Management.

- Grid operators can define their own policies for monitoring & control of

the network, at the highest level.

-Policy as set forth by the operator at the highest level.

• Decisions can be made at the edge of the power network.

- Leading to autonomous and instant policy decisions.

Slide No. 25 © RESERVE 2016-2019 All rights reserved.

VISION FOR ICT

6/14/2017

Field Measurements are mainly based on a Pull-Push Client / Server

model.

Slide No. 26 © RESERVE 2016-2019 All rights reserved.

TODAY

6/14/2017

Sensors and devices

pull/push their data into

central control units.

Sensors and similar devices

• Problem

- There is high latency in the request–response messaging pattern for

gathering measurement data.

- Measurands are selected at deployment time

- Today, the data from all measurands are sent to the control units whether

they are needed or not.

- Many different proprietary data solutions and silos.

Slide No. 27 © RESERVE 2016-2019 All rights reserved.

FIELD MEASUREMENTS AND MONITORING TODAY

6/14/2017

Slide No. 28 © RESERVE 2016-2019 All rights reserved.

THE FUTURE

6/14/2017

One broker provided

per geographical area

Breakout Gateway

Sensor/Device

Battery/Storage

Database

Control unit

Based on a

Publish & Subscribe Model

Publish

measurement

MQTT Broker

Subscribes

to data

Subscribes

to PV measurements

Subscribes to Battery

Storage and

substation feeder

measurements Subscribes

to all measurements

• Solution

- Low latency for getting measurement data to its intended destination.

- Applications can subscribe to just the measurands they need.

- Open data solution.

- Can apply Common Information Model (CIM) to data gathering and data

storage.

Slide No. 29 © RESERVE 2016-2019 All rights reserved.

FIELD MEASUREMENTS AND MONITORING

6/14/2017

• Policy-Based Management

-A system based on policy rules which are composed of a set of conditions, a

corresponding set of actions and an execution environment.

• Real-Time Control

-Autonomous Policy based management system executing at the edge of the

network.

• Security

-Data privacy and integrity

Slide No. 30 © RESERVE 2016-2019 All rights reserved.

COMMANDS FOR VOLTAGE AND FREQUENCY

MANAGEMENT

6/14/2017

• 5G Networks provide the perfect platform for the future communications

network, thanks to

- Ultra-low latency (speed)

- Excellent support for huge number of devices (Narrowband-IoT)

- Built-in security and reliability

- 5G Breakout Gateway to de-centralize decisions to the edge of the mobile

and power networks. See next slides.

Slide No. 31 © RESERVE 2016-2019 All rights reserved.

MOBILE NETWORKS FOR 100% RES SMART GRIDS

6/14/2017

HSSSDN

controllerSDN control

plane

Core network

Radio

access

Edge cloud

Efficiency:

low latency

high

bandwidth

eNBSecurity:

traffic

remains

local

BR-GW

Packet core application

on SDN controller

BR-GW

Internet/VPN

Power Grid

Control &

Monitoring

OPEX:

simplified

packet core

on SDN controller

Slide No. 32 © RESERVE 2016-2019 All rights reserved.

5G BREAKOUT SOLUTION