Upload
renganathan-v-sankaran
View
232
Download
0
Embed Size (px)
Citation preview
8/3/2019 Seminar Paper Corrected
1/16
INTEGRAL COACH FACTORY - MODERN TRENDS IN SUB-URBAN
ROLLING STOCKL.M.Sahore, Chief Electrical
Engineer/ICF
Indian Railways a mammoth railway system that runs across the length
and breadth of the Indian sub-continent over 65000 kms of track, carrying
12 million passengers every day. In the commercial capital of India i.e the
Mumbai megapolis alone, every day, over 6.5 million users patronise the
most intensively used sub-urban railway system in the world, the Mumbai
suburban. The population of Mumbai has gone up from 40 lakhs in 1947 to
120 lakhs in 2000 and it is expected to cross 200 lakhs by 2015. This
extraordinary growth in population has been posing a tremendous
challenge to the Indian Railways and all efforts are made to ensure that
the services on the Mumbai sub-urban commensurate this growth rate.
The Mumbai suburban railway system is the lifeline of the megapolis,
helping these 6.5 million people commute between home and work spots
everyday for the last more than eighty years. Despite being taxed to its
limits , the Mumbai suburban boasts of extremely high efficiency levelswith punctuality record showing figures in excess of 95 %.
During peak hours, despite running trains at frequencies of a train every 2
to 3 minutes, each 12 car train is packed with more than 6000 passengers,
a per coach capacity exceeding 500 passengers which translates to a
passenger loading density of a near impossible to imagine figure of 16
passengers per sq.m of area. Needless to say, transportation of local
passengers over the suburban sections of Mumbai has become the
biggest challenge of the time for Indian Railways.
The Mumbai suburban started in 1925, with a 1500 V DC system ofelectrification. With progressive growth in the population of Mumbai, the
frequency of trains and the passenger loading has been increasing year
by year. The 1500 V DC system of electrification has been getting
stretched with the need for additional substations to meet the
augmented load. Today a stage has come when the 1500 V DC system
has reached saturation. There is a need to switch over to a higher system
voltage so that the requirement of substations comes down. The 25 kV AC
system available in the rest of the electrified routes on Indian Railways, is
now being adopted in a phased manner in Mumbai. The targets for
conversion is now set on Western Railway 31.03.2009 for complete
conversion to 25kv ac single phase system in MUTP phase I whereas theconversion targets for Central Railway being 31.03.2010.
The trains running on the 1500 V DC system are with DC series traction
motors with series parallel system of control and friction brakes (electro-
pneumatic). Since, the conversion has to be done without disturbing the
existing services, the switchover to 25 kV AC calls for a rolling stock suited
for dual voltage operation. The necessity for Change in Propulsion from a
1500 V DC system to 25 KV AC system has been combined with a change
in the drive from DC drive to three phase AC drive so that the technical
8/3/2019 Seminar Paper Corrected
2/16
problems associated with the DC drive limitations could be overcome
and the following benefits of three phase technology also could be
derived :-
a) Use of VVVF based three phase drive using GTO/IGBT based converterinverters for 4 QC control.
b) Use of three phase squirrel cage type induction motors, free fromcommutation problems and need for frequent attention to brush gear
associated with DC motors.
c) Higher power is to weight ratio of AC traction motors 25 to 30 % higherpower for the AC motors
d) Availability of regenerative braking feature more than 35 % powersaving vis-a-vis DC drive in addition to reduction in wheel and brake shoe
wear. The saving in the power bill of the Railways is to the tune of Rs. 0.5
crores per rake per year. In addition, this feature has also enabledRailways to accrue carbon credit .
e) Use of microprocessor based control system and TMS for smootheracceleration, effective monitoring of all performance and safety related
parameters for enhanced performance, safety and reliability
The development of the rolling stock for the Mumbai suburban has also
undergone a sea change in other areas too and a new look AC DC rake
equipped with world class aesthetics introduced in Mumbai area are
becoming a sort of role model to be adopted in future AC EMU stock, so
that commuters are provided with latest state of art technological
coaches. The latest features are briefly discussed below:
a) Drivers safetyThe drivers cab is in line with UIC 651 requirements with respect to
dimensions, layout of the cab, visibility from the drivers cab, drivers desk
and location of main operating equipment and control system and
drivers seat. With the provision of nose cone sliding doors on both the
entrances and routing of the cables through roof and side walls, the
dimensional requirement of head room, access, visibility and level floorhave been achieved. Wider lookout glasses are provided for better track
and signal visibility. In lieu of toughened look out glass, a polycarbonate
lookout glass which is stone proof and shatter proof has been used. With
the provision of fluorescent lamp with enclosed diffuser, a uniform level of
illumination of 200 lux has been achieved compared to 30 lux in the
existing coaches and 60 lux as prescribed in UIC. In addition to the
fluorescent tubes, spot lights also have been provided for the use of the
drivers during driving. With the provision of 2 nos. of 400mm sweep
8/3/2019 Seminar Paper Corrected
3/16
swivelling type carriage fans in the drivers coach, the ventilation
requirement has been met to ensure 55 m3 of air per min per fan.
The drivers desk and main operating equipments and control system such
as the master and braking control(MBC), brake instrumentation,
speedometer(SPM) and the man machine interface(MMI) have been
organised in such a manner that the driver need not divert his attention
while operating these equipments from observation of the tracks and
signals. The controls for head light, flasher, automatic vigilance device,lights & fans for the coaches and the indication equipments are also
suitably located to have ease of access to operate these equipments
from the drivers seat. Each of these switches, instrumentations have been
provided with bakelite indications for proper identification during
operation. Sufficient leg space have been provided for leg and knee
movement between the seat and the desk. The drivers seat has been so
designed to facilitate the vertical adjustment as well as longitudinal
adjustments duly taking into account anthropometric dimensions with
reference to the conditions of visibility of signals. The Man Machine
Interface provides graphic information regarding the working of various
equipment and amenities on the entire train formation and trouble
shooting guidance. An Automatic Warning System is provided to ensure
brake application in the event of restrictive signal.
Further to enhance the drivers comfort, cab air-conditioning is also being
planned. The front face of the EMU has been redesigned with a nose
cone design to impart a world class look which in addition has helped in
crediting more space.
b) Low Noise Pneumatic Compressors for air supply & SS pipelines:Low noise reciprocating type of compressor with 3 phase 415 V
drive, built-in inter and after coolers have been provided in these
trains. These compressors have inlet air from under frame whereas
the compressors in existing design have inlet air from passenger
area through a separate filter. These compressors deliver 920 lpm at
rated speed. Due to use of stainless steel pipelines and fittings in
new train for air supply system as well as use of regeneration
braking, the duty cycle of compressor have been in the order of
OLD DESIGN OF CAB IN DC EMU CAB DESIGN IN NEW GENERATIONEMU
8/3/2019 Seminar Paper Corrected
4/16
27% with all compressors in service. A typical comparison indicates
distinct advantage of air supply system.
Details Existing rakes New rake
Compressor
rating
9.7 kW 110 V dc 6.7 kW 3 415 V
Noise level 80 db 66 db
Duty cycle 60% 27%
Air intake / filter External In built.
c) Brake blending, Wheel slip / slide protection & Anti skid controlsThis new generation AC DC EMUs
have been provided with advanced
braking control mechanism to
achieve maximum regenerative
braking over full range of speed. This
system of regeneration braking is fully
blended with electro pneumatic (EP)brakes, so that any set of braking
effort demand in EP region is met by
maximum regenerative energy for Motor coaches and EP brakes for
trailer coaches to supplement difference between the demand
and the regenerative braking effort achieved. The system also
takes care of the condition of (i) Non-effectiveness of regenerative
braking by changing over to EP fully and (ii) EP failure condition by
changing over to automatic brakes within a preset time
automatically through BECU (brake electronic control unit).The
wheel slip and slide protection system in all modes of acceleration
and deceleration (braking) and anti skid control for regenerative
mode are integrated into traction control unit to achieve these
controls.
For EMU and main line applications, ICF has already switched over from
cast iron brake blocks to composite brake blocks which has reduced the
frequency of brake block replacement by a factor of four. This has also
considerably reduced resource requirement for maintenance as well as
maintenance costs.
d) Polycarbonate SeatsThe present desktop is provided with MS frame with powder coating and
the seat made up of compreg laminated sheet conforming to RDSO
specn. C 9407 type 1. These sheets generally require replacement due to
wear and tear.
Polycarbonate has been used for the passenger seat material in lieu of
compreg which will result in reduced wear and tear and maintenance.
8/3/2019 Seminar Paper Corrected
5/16
8/3/2019 Seminar Paper Corrected
6/16
outer frame rods, etc. There used to be number of complaints of thefts
and miscreants activities as no grills to prevent such activities are provided
in the windows of the coach. These windows were also very small in size
and not possible to look through them for observing the names of the
stations from the window.
Windows also had a problem of poor ventilation during rainy days
when the window glass is closed. The
size of the windows were 610 x 762 mm.
Windows of AC DC EMU:
a. Window frames Alu. IS: 733 86, 64300 WP
b. Fixed louver shutter Polycarbonate clear finish
2.5mm thick
c. Movable Glassshutter Assy. IS: 2553 (Part 1) 1990. 6mm thick.
i. Second class clear toughened safety float glassii.
First class tinted medium brown toughened safetyfloat glass.
d. Grill S.S. AISI 304. Powder coated (clear)e. Inner fame Alu. To IS: 737: 86, 31000 HZ Powder coated.f. The size is 915 x 990 mmg. 3mm Stainless Steel wire for grills to Specn. IS: 6528
f) State-of-the-art coach lighting systemIn existing DC EMU trains, the coach illumination is achieved by 26 no. of 1
x 18 W fluorescent tube in a mesh type fitting. The illumination thusachieved was around 30 lux. A scientifically designed lighting system
using Fluorescent lights with energy efficient electronic lamp ballast has
been provided in the passenger area. In the new trains, 1 x 36 w fitting
with polycarbonate diffuser is arranged in the central duct to have
uniform illumination of 300 lux. These fittings have been developed to
confirm to IP 66 to have jet washable feature. These fittings will be
requiring less maintenance due to higher IP level protection against dust
etc.
g) GPS based Passenger Information SystemA GPS based passenger information system with high quality LED
displays, high performance speakers and LED destination boards
8/3/2019 Seminar Paper Corrected
7/16
has been provided in the passenger area. The selected LEDs ensure
excellent day time visibility as well as angular vision.
The passenger information system - a complete new feature of the
new train which has the following salient facilities:
Destination indicator (head code) in drivers compartment withhigh resolution LED.
Public Address system with speakers in each coach, Microphone indrivers cab.
Auto announcement of stations and other information Visual graphic display of station names and platform in the coach
(LED type with wider view angle).
Driver guard communication Data communication through CANBUS & RS 485 communication.
Auto volume control through ambient noise monitoring
h) Ventilation systemA very serious problem on Mumbai
suburban has been that of a verysuffocating ambience in the interiors
in the event of Super Dense Crush
Passenger Loading - in a trailer
coach almost 600 passengers travel
during peak hours. A major
improvement done on the new
generation EMUs manufactured by ICF for the Mumbai suburban (MRVC)
is the provision of a forced ventilation system to get over this problem.
The Ventilation system comprises three main components or
subsystems:
1. Air handling units (AHUs) discharge outside fresh air to thesaloon area. There are two AHUs per rail coach.
2. The fresh air ducts distribute the outside fresh air evenlyover the length of the rail coach. The fresh air leaves the
duct through diffuser grills.
3. Ceiling fans tore-circulate the air in the passenger area.A ventilation system cannot guarantee the highest possible level of
comfort to rail passengers. For optimum comfort, it is not sufficient to
ensure only a defined supply of fresh air, but in addition, temperature as
well as humidity and air velocity have to be controlled. This can only be
achieved by means of an air conditioning system. The ventilation system,
however, is well suited to control the concentration of carbon di-oxide in
the breathable air, thus eliminating potential health hazards. In addition,
the dilution of body odours will significantly add to the passenger comfort.
8/3/2019 Seminar Paper Corrected
8/16
Calculation of Fresh Air Flow Rate:
Under HDCL (High density crush load) conditions, a coach may carry up
to 600 passengers.
Doors & windows are closed and no natural ventilation takes place. If no
fresh air is provided, the concentration of carbon di-oxide concentration
would reach unacceptable limits within a few minutes as a simplified
calculation shows:
The CO2 generation rate of a person is approximately 0,0003 m3/min
(ANSI/ASHRAE standard 62-2001, informative appendix C). CO2
concentrations exceeding 5000 ppm are considered dangerous for
health (ANSI/ASHRAE standard 62-2001, table B-1).
Within one minute, 470 passengers will generate (0,0003 m3/min x
470 x 1 min) 0.141 m3 of CO2. With the given coach dimensions and
taking into account the volumetric effect of the passenger load, the
air volume in the fully-loaded coach will be approximately 50 m3.
At a CO2 generation rate of 0,141 m3/min and assuming a CO2Concentration of 500 ppm in the ambient fresh air, the maximum
permissible CO2 concentration of 5000 ppm would be exceeded
within less than 2 minutes!
A forced ventilation system is, therefore, required if no sufficient natural
ventilation can be provided. ANSI/ASHRAE standard 62-2001
recommends that the steady-state CO2 concentration in a space should
not be greater than about 700 ppm above outdoor level. If this can be
achieved, not only the CO2 concentration will be acceptable (500 ppm +
700 ppm = 1200 ppm). At the same time, odours from human bioeffluents
will be diluted to an extent that 80% of unadapted visitors to a space will
feel comfortable. The required ventilation rate (flow of fresh air) can be
determined as follows:
V = N/(CR CA)
V = Ventilation rate
N = CO2 generation rate per person
CR = CO2 concentration inside the rail car
CA = CO2 concentration in the outdoor ambient air
with
(CR - CR) = 700 ppm and
N = 0,0003 m3/min
This ventilation rate amounts to approximately 7 l/s/passenger.
With a load of 600 passengers, the ventilation system will have to provide
a flow of fresh air at a rate of (7 l/s/passenger x 600 passengers) = 4200 l/s
= 15000 m3/h.
8/3/2019 Seminar Paper Corrected
9/16
Fresh Air Duct Arrangement:
As specified in documents there is 1 duct running at the centre of the
coach.
AHU Arrangement:
Each rail coach is fitted with two roof mounted air handling units (AHUs).
The AHUs are located in roof troughs & end wall of the coaches.
Note: By using two AHUs per coach, the velocity in the fresh air duct
System is brought under control, as with only 1 AHU, the duct
Velocity would not be manageable.
8/3/2019 Seminar Paper Corrected
10/16
The AHU arrangement satisfies the permitted moving dimensions. D-seals
will be provided around the fresh air blower openings. These D- seals
will be compressed and a leak-tight connection to the duct will be
established as soon as the AHU is fastened to the coach.
Description of Main components:
In the following, the main components of the proposed ventilation system
will be described.
Air Handling Unit:
Each rail coach is provided with two air handling units (AHUs). The AHUs
will be completely interchangeable.
The AHU comprises 2 motor/blower units. The motors are RDSO-approved,
3 phase induction motors. The insulation system is capable to withstand
the voltage stress from the trains static inverter. The motor leads are
wired to quick-release connectors conforming to RDSO and Indian
Defense Standard Joint Services specification.
Electric
D-seal
Blower
500
21
32
1120
1240
86
8/3/2019 Seminar Paper Corrected
11/16
Based on the extensive experience M/s. SIDWAL has gained in the design,
manufacturing and maintenance of roof mounted railway air conditions,
the weather protection grills on the outside of the case assembly have
been selected, dimensioned and located to ensure that no rain water
can enter the fresh air duct.
The fresh air enters the blowers through air screens. They consist of
corrugated expanded aluminium sheets. The purpose is to preventforeign particles of substantial size (e.g. insects, leaves, etc.) from entering
the fresh air duct. The air screens are removable.
The AHU case assembly will be manufactured from grade 202 with 1%
nickel stainless steel. This alloy is being used in Ducting and Paneling in AC
DC EMU coaches being built at ICF. Other alloys are available on request.
Electrical Control System:
The electrical control system comprises:
Contactors to operate the blower motors MCBs and motor protection relays
No switchgear is installed inside the AHU. All switch gear are
accommodated in an existing coach control panel.
Fresh air Duct & Diffusers:
The duct is completely made of stainless steel. For the ease of
manufacturing, transport and assembly the duct is structured into
sections.
Diffuser grills are arranged along the duct length. The grills are ruggedlydesigned, made of aluminium and power-coated for enhanced corrosion
protection.
Design Verification:
A full-scale mock-up of the complete ventilation system was set up and
tested before the final design was released for production. With help of
this mock-up, it is possible to test and verify all system components before
start of production, e.g.
the distribution of fresh air flow over the length and width of thecoach
the fresh air flow rate in different modes of operation and underdifferent operating conditions (e.g. windows open/closed).
the air velocity at diffuser grills and at defined heights from the floor the power consumption, influence of voltage variations & phase
unbalances
the sound pressure level at different modes of operation eventhough the actual coach may show somewhat different test results.
8/3/2019 Seminar Paper Corrected
12/16
Ceiling Fan arrangement:
The ceiling fans are very important for the passenger comfort. Since the
ventilation system is unable to control temperature and humidity, a high
air velocity is most welcome in a hot and humid climate.
It is important to understand that the fresh air supply system
does not much contribute to the air velocity in the passenger
area. The velocity felt by the passengers is mainly
determined
by the ceiling fan arrangement.
Measures to prevent ingress of water
The water ingress in the AHU and duct posed the biggest challenge. Most
critical location was the drawal of rain water through the intake filter of
AHU which draws air @ 15000 m3 / hr. The following measures have
helped in arresting water leakage:
1. Double gaskets have been provided all along the periphery ofthe AHU instead of only around duct cut out.
2. Sealing the metal interface as additional precaution3. Rubber skit around AHU air inlet.
Challenges of technology adoption and new practices in manufacturing
the AC DC EMU: World class cabling practices
The new look AC DC EMU had posed challenges in the form of new
equipments, new connectors, huge workload in form of volumes of wiring
and cabling activity. ICF had been traditionally manufacturing DC EMU,
AC EMUs & DEMUs with DC drives. The traction control methods followed
in these type of SPVs were traditional methods requiring comparatively
less wiring and inter vehicular couplers etc. A brief comparison of work
load in terms of man hours is given below:
Coach
type
AC
EMU
AC/DC
EMU
(BHEL)
AC/DC
EMU
(Siemens)
B Coach 5823 7595 10096
C Coach 1476 2350 3629
D Coach 1566 3980 5668
HC
Coach
1557 4149
8/3/2019 Seminar Paper Corrected
13/16
The new generation EMU deploys Train Management System (TMS) which
is achieved by integrating and multiplexing signals for control and
monitoring of the system. This new system calls for multi vehicular bus
(MVB) for achieving the control and monitoring. Thus it is extremely
important to handle and lay the special cables for this purpose.
There are 34 types of cables used in the new trains including those of
special purpose cables. In this type of train deploying multiplexing anddata transmission, the electromagnetic interface among the cables,
circuits are very important considerations as the effect of EMI can be
disastrous affecting the control of the train. In order to overcome the
problem of EMI & EMC, the circuits were categorized into A, B & C and
the minimum clearance was prescribed between them. The cables are
laid in aluminium conduits located at prescribed distance and earthing
are provided at every 1m interval to take care of shielding.
The cables have been laid in the conduits and trays with proper care of
edge protection at inlet and outlet of conduits, Abrasion resistant conduitand wrappers are used over wires while the wires are laid on end wall and
in open area. These practices protect the cables against abrasion at
sharp edges and protection against other materials. These practices are
one of the best cabling practices in railway coaches which will provide
trouble free service with respect to cables.
This train deploys various type of cables and circuits calling for new type
of I.V. couplers for connection between coaches and new type of
connectors within the coaches. A set up of a motor coach (Mock up )
has been created to achieve wiring & connection in free area (as motor
coach area is cramped with equipments). Here in mock up, a group ofworkmen lay the cable of entire coach, terminate with various types of
connectors (Harting type), marking ferrules etc. This process simplified the
wiring in high tension compartment and also cut down the belt time
drastically.
Belt time reduction
Belt time
ACEMU 25 days
AC DC (BHEL) 45 days
AC DC EMU(Siemens)
30 days
Testing & Commissioning:
Testing and commissioning has been the essential component of train
manufacturing. These new generation trains having train management
system, requires different protocol compared to the existing EMUs.
Generally the commissioning tests are divided into two parts, i.e.,
precommissioning at ICF (coach builder) and commissioning at Mumbai.
8/3/2019 Seminar Paper Corrected
14/16
The precommissioning checks involve continuity check, high voltage test
and current sharing test before control energisation.
The steps later followed are
i. Loading of softwareii. 110 V dc (control ckt) proving test also known as static
control test
iii. 3 phase testsiv. brake testsv. HV (1500 dc, 25 kV AC) static testvi. HV dynamic test at Basic unit level followed by Rake
level.
In addition Rake protocol is also done during rake test which includes PIS,
changeover etc. These trains are tested during precommissioning in form
of Basic units comprising of 3 coaches, i.e., each 3 coach (BU) has one
Motor coach in the middle and two trailer coach on either end. The End
basic units (EBU) have driving coach as one of the trailer coach whereas
the middle basic units (MBU) have one NDTC (a trailer coach havingcompressor) as one of the component. Thus for completing one rake
formation, four BUs (2 EBUs + 2 MBUs) have to be pre-commissioned and
the rake is formed thereafter.
The precommissioning period have been also brought down from 7 days
to 3 days for BUs and 10 days to 5 days for rakes. Thus substantial
reduction in precommissioning time has helped in reducing the net time
taken in turning out the rake from coach builders (ICF) premises.
Energy conservation:
The present Mumbai Suburban system is run on DCEMU rakes on Central
and Western Railways. These trains are provided with Rheostatic control
and Electro pneumatic braking through Friction Brake Blocks. The specific
energy consumption for these DCEMUs is in the order of 40 KWH / 1000
GTKM. The 3 phase AC DC EMUs with regenerative braking has a specific
energy consumption of 29.5 KWH/GTKM.
The data on the W.Rly indicate that the regeneration is on an average
greater than 35%. The projected figures of energy consumption / saving
in the EMU rakes in Mumbai area will bea. Present consumption (204 rakes) : 55 Cr. Units (KWH)
b. After MUTP 1 if present D.C. EMU
Technology were continued (253 rakes) 75 Cr. Units (KWH)
c. After MUTP-1 with New technology EMU
rakes having regenerative braking
are introduced (253 rakes) : 55 Cr. Units (KWH)
d. Energy Saving inspite of increase in
rake holding from 204 to 253 : 20 Cr. Units (KWH)
8/3/2019 Seminar Paper Corrected
15/16
2.0 Benefits of Carbon Credits: Credit accruals;This is the first project in transport sector to be qualified for carbon
credit.
Reduction in Carbon consumption:
Coal : 4.6 x 108 Kg
LPG : 14.26 x 108 Ltr.
Crude Oil : 21.46 x 108 Ltr.
Natural Gas : 21.6 x 108 m3
Reduction in Pollution:
CO2 : 2.092 x 108 Kg
SO2 : 18 x 108 gm
SPM : 5 x
108 gm
Soot Carbon :
0.2 x 108 gm
NO : 20 x108 gm
Cost of the rakes:
The cost of the rakes is also
important aspect of the manufacturing process. Due the advanced
features of the propulsion system and use of FRP paneling, stainless steel
for roof panels, hand hold, partition and luggage rack, seat frames and
polycarbonate for seats, the cost of these rakes are higher compared to
existing DC EMU rakes. The largest metro in India has witnessed new type
of EMUs during the last few years with 3 phase propulsion system. Acomparison of cost per 12 car equivalent is given below:
Cost / 12 Car Feature
New AC/DC
EMU, MUTP
Phase I
INR. 25 Cr. 3 propulsion, + Air ventilation
(2007) (Corton steel coach
body)
DMRC Phase I INR 84Cr 3 propulsion + air conditioning
+ auto door closure+ stainless
steel coach body (2004)
A brief of Public Reaction as first AC DC EMU rake with Siemens electrics
rolled out to Mumbai area.
This train has passed through a critical review by traveling public and
media in Mumbai. The leading national dailies and local dailies have
quoted the public responses.
Well lit, well ventilated commuter friendly. Silver bullet. A popular name given by the public.
8/3/2019 Seminar Paper Corrected
16/16
Future generation is here It is quite spacious ,airy and bright
With the introduction of more and more AC DC EMU rakes with Siemens
electrics, the image of suburban trains is changing, ending the ordeal of
esteemed commuters. Till today 19 rakes have been inducted in the
Mumbai area, providing additional service. By the end of the current
financial year, a total of 50 rakes would be inducted which will ease out
the congestion and crowding.