Self Funded Project Scope & Estimated Cost/Savings
B Building Facility Improvement Measures "FIM" Description Selling Price
TotalAnnual
Operational Savings
TotalAnnualEnergy Savings
TotalAnnualSavings
Campus High School
LightingReplace MH with T8 Fluorescent-Gym 1(42-400W)(13-42W CFL Pentant)
X Replace MH with T8 Fluorescent-Gym 2(36-400W) $25,163 $71 $1,111 $1,182X Replace MH with T8 Fluorescent-Pool(12-400W) $8,388 $24 $370 $394
Replace MH with 205W CMD-Commons(16&8-250W)Replace MH with 205W CMD-Hallway(6-250W)
Replace MH with 145W CMD-Labs(81-175W)X Replace MH with 330W CMD-Librarys(24-400W) $3,744 $11 $275 $285X Exterior Lighting(16)(400Wto320WPulse Start) $7,737 $22 $475 $497
Exterior Lighting(27)(75Wto150W Pulse Start)X Water Conservation $71,620 $1,049 $6,590 $7,639X Kitchen Equipment $973 $253 $253X Ice Machine Measures $1,100 $165 $165X Pool Blanket $29,609 $3,837 $3,837X Weatherization $63,166 $3,866 $3,866
Ext. Door(s) to be weather stripped & sealed(65)Ext. Door(s) to have only the sweeps replaced(20)
Overhead Doors to be Weather-stripped & sealed(6)Roof / Level Change to be Sealed with 2 part foam(320ft)
Roof / Wall Joint to be Sealed(2060ft)
Haysville Middle SchMulti-zone unit, Chiller,Boiler,Cooling tower replacement
X RTU Replacement $170,500 $3,939 $3,047 $6,986
Lighting25W T8 Lighting(95)
X 25W T8 w White Reflectors(450) $57,237 $161 $5,387 $5,548Replace MH with T8 Fluorescent-Main Gym(21-400W)
X Replace MH with T8 Fluorescent-Aux Gym(20-400W) $13,979 $39 $617 $657X Exit Sign ,Main gym 15 W to LED $101 $0 $17 $18
Exterior lighting(20-175W MH w 150W PS)Water Conservation
X Kitchen Equipment $1,489 $238 $238X Ice Machine Measures $1,100 $162 $162
X Weatherization $14,064 $910 $910Ext. Door(s) to be weather stripped & sealed(17)
Int. Door(s) to be weather stripped & sealed(2)Roof / Wall Joint to be Sealed(640ft)
Pg 2 Pg 2
Self Funded Project Scope & Estimated Cost/Savings
B Building Facility Improvement Measures "FIM" Description Selling Price
TotalAnnual
Operational Savings
TotalAnnualEnergy Savings
TotalAnnualSavings
Haysville West Mid SchLighting
Replace MH with T8 Fluorescent(49-250W seldom used)Replace MH with 205W CMD(28-250W seldom used)
X Exterior lighting(18-70W MH w 40W Induction& 17 400W MH to 320W PS) $18,321 $52 $798 $850Water Conservation
X Kitchen Equipment $1,201 $126 $126X Weatherization $28,754 $2,308 $2,308
Ext. Door(s) to have only the sweeps replaced(33)Roof / Wall Joint to be Sealed(2200ft)
Admin OfficeLighting
X 25W T8 Lighting(1) $56 $0 $3 $3
X Cooling for Server Room $8,299 $1 $1X Expand BAS $17,658 $1,304 $1,304X Water Conservation(See Freeman Below)X Weatherization $5,099 $225 $225
Ext. Door(s) to be weather stripped & sealed(16)
Service Center LightingX Replace Ceiling Mount 4-65W Incandescent with 2-26W CFL(13) $3,675 $10 $360 $370
Exterior lighting(3-175W MH to150W PS)Exterior lighting(7 -400W MH to 320W PS)
Overhead Radiant HeatingX Weatherization $18,259 $1,406 $1,406
Ext. Door(s) to be weather stripped & sealed(10)Overhead Doors to be Weather-stripped & sealed(6)
Grand LaneX RTU Replacement $40,191 $641 $398 $1,039X Expand BAS $30,275 $970 $970X Parking Lot Lights on BAS $1,645 $95 $95
Lighting25W T8 Lighting(1)
X 25W T8 w White Reflectors(104) $13,228 $37 $1,245 $1,282
X Water Conservation $9,559 $76 $1,139 $1,215X Weatherization $7,896 $710 $710
Ext. Door(s) to be weather stripped & sealed(10)Roof / Wall Joint to be Sealed(320ft)
Pg 3 Pg 3
Self Funded Project Scope & Estimated Cost/Savings
B Building Facility Improvement Measures "FIM" Description Selling Price
TotalAnnual
Operational Savings
TotalAnnualEnergy Savings
TotalAnnualSavings
Learning Center LightingReplace 60W T12 with25W LP Ballast(2)
Exterior lighting(7-175W MH w 150W PS)
X Expand BAS $19,147 $981 $981X Water Conservation(See Above)X Weatherization $7,279 $867 $867
Ext. Door(s) to be weather stripped & sealed(8)Roof / Wall Joint to be Sealed(480ft)
Freeman ElementaryLighting
X U34Wto25W T8 (24)&34W T12to25W T8 (6) $3,398 $10 $150 $160X Replace Ceiling Mount 4-65W Incandescent with 2-26W CFL(13) $3,675 $10 $360 $370
Exterior lighting(3-175W MH to150W PS)X Exterior lighting(7 -400W MH to 320W PS) $2,823 $8 $208 $216
Water ConservationX Kitchen Equipment $744 $88 $88X Weatherization $8,060 $440 $440
Ext. Door(s) to be weather stripped & sealed(8)Ext. Door(s) to have only the sweeps replaced(6)
Roof / Wall Joint to be Sealed(300ft)
Nelson ElementaryX Lighting
Replace MH with T8 Fluorescent(17-400W)(13-42WCFL Pentant)X Exterior lighting(5 400W MH to 320W PS) $2,418 $7 $149 $155
X Water Conservation $33,183 $503 $1,492 $1,995X Kitchen Equipment $744 $238 $238X Weatherization $40,137 $2,852 $2,852
Ext. Door(s) to be weather stripped & sealed(8)Roof / Wall Joint to be Sealed(1880ft)
Window(s) to be Sealed, 2 lines at perimeter(1320ft)
Oatville ElementaryX * RTU Replacement $54,929 $733 $649 $1,382X LightingX 25W T8 Lighting(27) $2,508 $7 $93 $100X 25W T8 w White Reflectors(41) $5,215 $15 $491 $505X Replace Recessed Fix 65W Incandescent with 18W CFL(12) $259 $1 $75 $76
34W T12 to T8 LO Wrap(1)X Water Conservation $33,104 $490 $1,506 $1,996X Kitchen Equipment $744 $238 $238X Weatherization $18,506 $1,446 $1,446
Ext. Door(s) to be weather stripped & sealed(10)Ext. Door(s) to have only the sweeps replaced(12)
Roof / Wall Joint to be Sealed(990ft)
Pg 4 Pg 4
Self Funded Project Scope & Estimated Cost/Savings
B Building Facility Improvement Measures "FIM" Description Selling Price
TotalAnnual
Operational Savings
TotalAnnualEnergy Savings
TotalAnnualSavings
Prairie Elementary
LightingReplace MH with T8 Fluorescent-Gym (20-400W not used much)
X Replace MH with 205W CMD-Food Service(12-250W) $1,781 $5 $122 $127X Replace MH with 205W CMD-Library(12-250W) $1,781 $5 $122 $127
Exterior lighting(Recessed Can 150W MH with 145W CDM ALL START(7)X Exterior lighting(7-175W MH w 150W PS& 14 400W MH to 320W PS) $9,920 $28 $449 $477
Water ConservationX Kitchen Equipment $973 $85 $85X Weatherization $20,512 $1,666 $1,666
Ext. Door(s) to be weather stripped & sealed(5)Ext. Door(s) to have only the sweeps replaced(16)
Roof / Wall Joint to be Sealed(1500ft)
Rex ElementaryX Expand BAS $18,662 $480 $480
LightingX Replace MH with T8 Fluorescent(17-400W) $11,883 $33 $525 $558X Exterior lighting(21- 400W MH to 320W PS) $10,155 $29 $624 $652
Water ConservationX Kitchen Equipment $973 $238 $238X Weatherization $33,639 $2,400 $2,400
Ext. Door(s) to be weather stripped & sealed(39)Roof / Level Change to be Sealed with 2 part foam(60ft)
Roof / Wall Joint to be Sealed(1455ft)Window(s) to be Sealed, 2 lines at perimeter(1400ft)
Ruth Clark ElementaryLighting
X Replace MH with T8 Fluorescent Gym(20-400W) $13,979 $39 $617 $657X Replace Corr. 7-400W MHto320W CDM $1,057 $3 $74 $77X Replace Track Fix 4-65W Incandescent with 18W CFL(6) $129 $0 $38 $38X Replace Corr. 3-250W MHto205W CDM $445 $1 $23 $24
Water ConservationX Kitchen Equipment $228 $70 $70X Weatherization $13,234 $1,862 $1,862
Ext. Door(s) to have only the sweeps replaced(34)Roof / Wall Joint to be Sealed(1440ft)
Tri-City Day SchoolX Expand BAS $12,740 $540 $540X Water Conservation $5,142 $49 $349 $398
15.45 $1,068,193 $8,109 $61,010 $69,119
Self Funded Project Scope & Estimated Cost/SavingsJohnson Controls, Inc.
Copyright 1994-97 JC Facts II 2.51
JCFACTSJohnson Controls,
Inc. Copyright 1994-97
JC Facts II 2.51
Haysville USD 261Perry McCabe
Version 1.0
Finance Decision
Semi-annual Annual
Project Cost $1,068,193 Payments $32,988 $65,977
Annual Payments $65,977 $65,977
No. of Payments 34 17
Total Cost to Finance $1,121,603 Total Payments $1,121,603 $1,121,603
Interest Rate 0.000% Total Interest $0 $0
Term of Financing (Years) 17.00Payment Monthly
ArrearsCapital Cost Avoidence? Yes
Annual Cash Flow Analysis
Year
Annual Energy Savings
Annual Operational
Savings
Total Annual Savings
Annual Project Costs
Annual Cash Flow
Cumulative Cash Flow
Installation $16,873 $1,014 $17,886 $21,364 ($3,478) ($3,478)
1 $61,010 $8,109 $69,119 65,977 $3,142 ($336)
2 $63,234 $8,352 $71,585 65,977 $5,609 $5,273
3 $65,538 $8,602 $74,141 65,977 $8,164 $13,437
4 $67,927 $8,860 $76,787 65,977 $10,811 $24,248
5 $70,403 $9,126 $79,529 65,977 $13,552 $37,800
6 $72,968 $727 $73,695 65,977 $7,718 $45,518
7 $75,628 $748 $76,376 65,977 $10,400 $55,918
8 $78,384 $771 $79,155 65,977 $13,178 $69,096
9 $81,241 $794 $82,035 65,977 $16,058 $85,155
10 $84,202 $818 $85,020 65,977 $19,043 $104,198
11 $87,271 $842 $88,113 65,977 $22,136 $126,334
12 $90,451 $868 $91,319 65,977 $25,342 $151,676
13 $93,748 $894 $94,642 65,977 $28,665 $180,341
14 $97,165 $920 $98,085 65,977 $32,109 $212,450
15 $100,706 $948 $101,654 65,977 $35,677 $248,127
16 $104,376 $104,376 $65,977 $38,400 $286,527
17 $108,180 $108,180 $65,977 $42,204 $328,731
Totals $1,419,304 $52,393 $1,471,697 $1,142,967 $328,731 $328,731
This cashflow is indicative of the current financing conditions, assumptions and savings projections and is subject to adjustment upon final financing arrangments.
Inflation Factors