19 februari 2020
Sediment-management
Fixed layers
Matthijs Boersema (RWS-WVL)
@ Ricardo Smit
Fixed layers in the River Waal
19 februari 2020
• Bottom groynes Erlecom - 1996 (kmr 873-876)
• Fixed layer Nijmegen - 1988 (kmr 883-885)
• Fixed layer Sint Andries - 1999 (kmr 925-928)
Thickness layer 70 cm (40-200 kg), average: 35 cm diameter
Length 2-3 km, width 100-150 m
Increasing navigation width with 50 m
How fixed layers work
19 februari 2020
1974
19 februari 2020
How fixed layers work
Fixed layer Nijmegen at kmr 883.5
Wid
th n
avig
ation c
hannel (m
)
19 februari 2020
Bed-level 2018Fixed layer
Source 1.Bodempeilingen trend 20 jaar (RWS-ON)
2.MIRT Duurzame bodemligging Rijntakken (2018)
Fixed layer Nijmegen
Hard substrate ina soft environment(…)
Bed-level trend simulations
19 februari 2020
Source 1. Measures related to the fixed layer at Nijmegen (2019)
Transport on the River Waal
19 februari 2020
• 2.80 m water depth at 1020 m3/s
• In 2018 156 days below 2.80 m
• Economic damage 65-260 M€
• 2-3 months issues with fixed layer N.CEMT-VI class
CEMT-V class
Source: Economische schade droogte, Ecorys (2019)
Measures
19 februari 2020
Measures – fixed layer Nijmegen
19 februari 2020
• DBR study (Sustainable Riverbed level Rhine Branches)
– Adaptation of fixed layer Nijmegen is urgent
• Remove
• Lower
• Longer
“Start with pilot and increase navigation
comfort over fixed layer + increase knowledge
about sediment management”
Must be part of IRM Integral managing riverbed level
Pilot fixed layer (FL) Nijmegen
19 februari 2020
Adaption FL
Sediment management
Short term (2 years)
Medium term (25 years)
Long term (>50 years)
Improve comfort
=> IRM
Measures pilot fixed layer Nijmegen
19 februari 2020
Improve comfort
squat
19 februari 2020
Groyne field nourishments (5x)
Improving nature developent, fresh sandin floodplain
3
Streamline
Sediment management
Measures pilot fixed layer Nijmegen
Step 1. flatten fixed layer
19 februari 2020
Start: asap
Difference with contract level (maximum level of the fixed layer)
at 04-09-2019
kmr: 885
kmr: 884
1974
Step 2. Fill scour hole
19 februari 2020
• Start around end 2020, beginning 2021
• Monitoring ship movement (test Twentekanaal, Tarka-sytem)
– T0 measurement
– T-after measurement
• Monitoring morphological behavior
Step 3. Groyne field nourishmentsOr other creative ideas….?
19 februari 2020
• Start end 2021
• 5000 – 20000 m3 Volume
• Monitoring morphology, waves, hydrodynamics
• Grain size / shape / etc.
• Early market involvement
Master student TUD
RHDHV, Deltares, RWS
Joint ambitoin – living lab
19-2-2020
19-2-2020
Thank you
Waterkwaliteit & natuur
• daling (grond)waterstanden• verdroging van natuur • kapitaalvernietiging recente investeringen
• afnamedekkingsgraad kabels en leidingen• stabiliteitsproblemen infrastructuur
Waterveiligheid en waterbeschikbaarheid
• geleidelijke herverdeling afvoer, minder mogelijkheid om water te sturen
• zoetwater- & hoogwaterveiligheidsissues
• 20% transportkosten over 30 jr.• kans reverse modal shift, CO2 uitstoot• concurrentiepositie NL
Infrastructuur
Effecten op functies
Bevaarbaarheid
• MIRT Onderzoek Duurzame Bodemligging Rijntakken
• Eindrapportage https://www.rijksoverheid.nl/documenten/rapporten/2019/06/06/mirt-onderzoek-duurzame-bodemligging-rijntakken
19-2-2020