9
MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 1 SECTION 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL PART 1: GENERAL 1.01 GENERAL REQUIREMENTS A All general provisions contained herein or within any other section of the specification shall be fully applicable to each and every other section. B Works on all installations shall be carried out in a neat, efficient and workmanlike manner, assuring satisfactory operation, maintenance and repair. Work shall be in accordance with the requirements of this specification and shall fulfill its true intent and meaning. No deviations from this specification and/or the drawings shall be made without written approval of the Engineer. C This specification and associated drawings form a composite set of documents, intended for the selection and installation of equipment having the general and specific characteristics as detailed. D Unless otherwise specifically stated, the installation shall be left complete, tested and ready for operation in all respects and fully integrated and coordinated with all other trades. E The Contractor shall submit proof, if requested by the Engineer that the materials, appliances, equipment or devices that are furnished and installed under the contract meet the requirements of the reference standards with regard to fire and safety hazards. F Contractor shall comply with all applicable SEC distribution material specification, construction and planning standards for power distribution networks and municipality specification for road lighting. Some of the specifications and standards are attached with the contract documents for guidance, however contractor shall obtain copy of all applicable specification and standards from the concerned authorities as required on site or instructed by the Engineer. G Any conflict found between this project specification and SEC or municipality specification/standards shall be immediately brought to the notice of Engineer for final decision. 1.02 SCOPE OF WORK A Work under this division of the specification shall include furnishing all labor, materials, equipment and services to install the complete electrical system, putting into operation, tested and commissioned as shown on the drawings and as specified herein. The work includes, but is not limited to, the following principal systems and equipment: 1. Incoming power supply feeders from the Saudi Electricity Company (SEC). 2. Medium voltage power distribution network including MV cables with fiber optic cable, RMUs, unit substations and accessories. 3. Low voltage power distribution network including LV cables, LV distribution pillars, kWh meter boxes, etc. 4. Low voltage emergency power generation and distribution systems including standby generator(s), enclosed transfer switches, emergency power distribution boards, separate

SECTION 26 05 00-COMMON WORK RESULTS FOR ELECTRICAL.pdf

Embed Size (px)

Citation preview

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 1

    SECTION 26 05 00

    COMMON WORK RESULTS FOR ELECTRICAL PART 1: GENERAL

    1.01 GENERAL REQUIREMENTS

    A All general provisions contained herein or within any other section of the specification shall be fully applicable to each and every other section.

    B Works on all installations shall be carried out in a neat, efficient and workmanlike manner, assuring satisfactory operation, maintenance and repair. Work shall be in accordance with the requirements of this specification and shall fulfill its true intent and meaning. No deviations from this specification and/or the drawings shall be made without written approval of the Engineer.

    C This specification and associated drawings form a composite set of documents, intended for the selection and installation of equipment having the general and specific characteristics as detailed.

    D Unless otherwise specifically stated, the installation shall be left complete, tested and ready for operation in all respects and fully integrated and coordinated with all other trades.

    E The Contractor shall submit proof, if requested by the Engineer that the materials, appliances, equipment or devices that are furnished and installed under the contract meet the requirements of the reference standards with regard to fire and safety hazards.

    F Contractor shall comply with all applicable SEC distribution material specification, construction and planning standards for power distribution networks and municipality specification for road lighting. Some of the specifications and standards are attached with the contract documents for guidance, however contractor shall obtain copy of all applicable specification and standards from the concerned authorities as required on site or instructed by the Engineer.

    G Any conflict found between this project specification and SEC or municipality specification/standards shall be immediately brought to the notice of Engineer for final decision.

    1.02 SCOPE OF WORK

    A Work under this division of the specification shall include furnishing all labor, materials, equipment and services to install the complete electrical system, putting into operation, tested and commissioned as shown on the drawings and as specified herein. The work includes, but is not limited to, the following principal systems and equipment:

    1. Incoming power supply feeders from the Saudi Electricity Company (SEC).

    2. Medium voltage power distribution network including MV cables with fiber optic cable, RMUs, unit substations and accessories.

    3. Low voltage power distribution network including LV cables, LV distribution pillars, kWh meter boxes, etc.

    4. Low voltage emergency power generation and distribution systems including standby generator(s), enclosed transfer switches, emergency power distribution boards, separate

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 2

    cables and raceways, etc.

    5. All kinds of underground electrical and telecom/ICT services.

    6. Low voltage system including LV power distribution boards, LV cables, panel boards, etc.

    7. All kinds of electrical raceways, cable trays, boxes and fittings.

    8. All kinds of wiring devices, disconnect switches, starters, etc.

    9. Interior, exterior, emergency, exit, street, landscape, flood, faade and other special lighting.

    10. Earthing system.

    11. Electrical installations serving all mechanical plants (HVAC & Plumbing) including all LV cabling, cable trays, disconnect switches and connections to equipment.

    12. Electrical installations serving equipment in mechanical plants such as sewage treatment plant, water treatment plant, sewage lifting station, water wells, etc.

    13. Electrical installations serving all special systems and equipment provided under other divisions of the specification such as hand dryers, motorized doors, arm barriers, water features and other electrically operated equipment.

    14. All low current systems as indicated in the tender documents.

    15. Complete testing and commissioning of all electrical works including low current systems.

    1.03 REFERENCES

    A The entire electrical installation shall comply with the requirements of the latest editions of the standards from the following institutes in all respect, including current additions and/or amendments:

    1. SBC Saudi Building Code.

    2. SASO Saudi Arabian Standards Organization.

    3. SEC Saudi Electricity Company.

    4. CITC Communication and Information Technology Commission.

    5. STC Saudi Telecom Company.

    6. GDCD General Directorate of Civil Defense.

    7. GACA General Authority of Civil Aviation.

    8. EN European Norms (standards).

    9. BS British Standards.

    10. BS 7671 Requirements for Electrical Installations (IEE Wiring Regulations).

    11. CCITT International Telegraph and Telephone Consultative Committee.

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 3

    12. CENELEC European Committee for Electro-technical Standardization.

    13. IEC International Electro-technical Commission.

    14. IEEE Institute of Electrical and Electronics Engineers.

    15. IES Illumination Engineering Society.

    16. CIBSE Chartered Institution of Building Services Engineers.

    17. ISO International Standardization Organization.

    18. NFPA National Fire Protection Association.

    1.04 ELECTRICAL SUPPLY

    A The Medium voltage electrical power supply from Saudi Electricity Company (SEC) shall be 3 phase, 13.8 kV Delta, 60 Hertz.

    B The Low voltage electrical power supply and distribution system shall be 400/230 Volts, 3 phase, 4 wire, 60 Hertz, earthed neutral system.

    1.05 LIGHTING REQUIREMENTS

    A Lighting levels shall be in accordance with appropriate standards and agreed upon with the Engineer. Low energy lighting shall be the preferred source in all areas. Based on the standards set forth by IES and CIBSE, the following maintained illumination levels are recommended:

    Area Illumination Level (Lux) Offices 500 Circulation/Corridors 150

    Workshop 300 Stores 150 Plant rooms 200 Toilets 200 Electrical/mechanical rooms 200 Streets 10 Parking areas (open) 5-10 Sports Playground 200 Stairs 150

    1.06 EARTHING REQUIREMENTS

    A The earthing system shall comply with the following:

    1. The International Electro-technical Commission (IEC).

    2. Any special requirements of the Saudi Electricity Company (SEC).

    3. Any special requirements of separate earthing for low current systems in accordance with relevant standards or manufacturers recommendations.

    4. The IEE Wiring Regulations, latest edition.

    5. Any requirements stated within the Specifications.

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 4

    B The earthing system shall take the form of (TN-C) system for the distribution systems and TN-S system in all buildings. The contractor shall ensure that the installation of earthing system complies with the requirements as given in section 26 05 26.

    C The earthing conductor (the final conductor by which the connection to the selected means of earthing is made) shall be of copper construction.

    D All extraneous conductive parts of any equipment or building installation shall be protected by equipotential bonding in accordance with IEC 60364 Electrical installations of buildings.

    1.07 LOW CURRENT AND SPECIAL SYSTEMS REQUIREMENTS

    A Assign a local specialist supplier/designer for all low current and special systems including earthing and lightning protection systems.

    B Specialist suppliers shall verify the design and submit shop drawings and materials based on the requirements of the construction documents and related international standards.

    C Shop drawings and as-built drawings shall be stamped by the suppliers.

    D Suppliers shall support their submittals with catalogues and satisfactory calculations.

    E Bear the cost of any extra items found necessary to provide a properly functional system.

    F Provide the latest up-to-date technology and software.

    1.08 CO-ORDINATION

    A The Contractor shall be solely responsible for the proper co-ordination of all phases of the work and timely delivery to the site of all equipment and materials for proper execution of the work.

    B Visit the site and survey in detail the as-built situation of all the areas related to the project before bidding/signing the contract.

    C Making of any hole in the existing slab or breaking of any portion of existing structural walls shall be properly coordinated with all concerned authorities/agencies and proper approval of the method statement shall be obtained from the Engineer before proceed.

    D Co-ordinate the work with all or any other disciplines to ensure proper phasing and continuity of the Works. If it becomes necessary to remake any part of these works or that of any other discipline or trade as a result of poor or badly timed co-ordination, then all costs associated with remaking those works shall be borne by the contractor.

    E Co-ordinate with all supply undertakings and authorities and include for attendance along with all costs involved in re-directing existing services.

    F Take into consideration all statutory and local requirements issued by the Saudi Electricity Company (SEC), Local Authority, Central Government, Broadcasting Authority, Communication and Information Technology Authorities along with any other requirements to be considered for the correct and legal operation of the electrical and telecommunication installation or equipment connected to the installation as part of this contract. Pay all costs due to the requirements of any authority except for connection fees.

    G The contractor shall be responsible for co-ordination with all electrical and mechanical systems suppliers and shall include in his cost all the electrical requirements (even if they

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 5

    were not mentioned in the BOQ or drawings) to provide a fully functional system as specified and as recommended by the manufacturer or applicable codes. This shall also be applicable to all ancillary systems and equipment such as security, elevators, escalators, compactors, kitchen & laundry equipment, audio-visual, BMS and all low current & special systems.

    1.09 CLIMATE CONDITIONS

    A External to buildings and in non-air conditioned spaces, all apparatus shall be rated for an ambient temperature maximum of 55 oC, minimum of 0 oC, generally dusty desert conditions, a maximum humidity of 100% rh, and an elevation of 630 meters above sea level.

    B In air conditioned buildings, all apparatus shall be rated for ambient temperature of 45 C maximum, minimum of 0 C and a maximum humidity of 90% RH.

    C When equipment is installed in direct sunlight, it shall either be shielded from direct radiation or suitably rated for additional solar gains. Cables shall always be shielded from direct sunlight.

    D All apparatus shall be rated for continuous service twenty four hours a day, seven days a week throughout its normal rated life, except for necessary routine maintenance.

    E All equipment shall be rated for very harsh and corrosive environmental conditions which persist at the project site. All buried installations shall be suitable for aggressive and salty soil conditions.

    1.10 ACCESSIBILITY

    A All works within the project and particularly above suspended ceilings or inside vertical shafts shall be installed so as to be accessible for operation, maintenance and repair. If necessary, deviations from the drawings may be made to accomplish this, but no change shall be made without written approval from the Engineer. Locations of access doors and panels shall be approved by the Engineer before installation work is commenced.

    1.11 STORAGE OF MATERIALS AND EQUIPMENT

    A Comply with section 01 61 00.

    B All material and equipment fixed or unfixed, shall be protected against corrosion, deterioration and ingress of foreign matter and moisture.

    C All material and equipment shall be kept clear of the floor or ground by means of wooden blocks and shall be protected against weather with durable waterproof wrapping and other appropriate means.

    D The contractor shall be liable for any loss due to delivery, storage or site security problems.

    1.12 PREVENTION OF NOISE AND VIBRATION

    A Provision shall be made to minimize noise and vibration. However, different manufacturer's equipment will have varying sound and vibration characteristics. The contractor shall be responsible for ensuring that equipment installed does not transmit unnecessary noise or vibration.

    B All equipment installed in plant rooms and outside areas shall not be audible in occupied areas.

    C Any vibration isolators, isolating bases, flexible connections, silencers, other acoustic

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 6

    treatment or anti-vibration precautions necessary shall be included in the rates for equipment.

    D Submit proof of the selected noise proofing measures to the Engineer before commencement of work.

    E Submit to the Engineer for information the noise level generation by the plant selected so that structural soundproofing measures can be evaluated. This means either data on the acoustic capacity level in relation to frequency, or the sound pressure level measured at 1 meter from the plant at octave median frequencies from 63 Hz to 4000 Hz. Details of the spatial and operational conditions shall also be given.

    F All costs of noise sound level measurements and any repeat measurements, necessary if acoustic requirements are not met, shall be allowed for by the contractor.

    G Coordinate and comply with the requirements of noise control as applicable and as given in section 23 05 48.

    1.13 GUARDS

    A All moving parts of machinery shall be protected by strong guards to adequately protect all personnel working on or in the vicinity of equipment. The guards shall be constructed in such a manner that the movement of drive belts and rotation of shafts may be readily observed without removal of the guard.

    B All 'live' parts of electrical equipment shall be protected in such a way to adequately protect all personnel working on or in the vicinity of equipment from injury.

    C Wherever possible, all protective guards shall be supplied by the equipment manufacturer. All guards shall be strongly attached to equipment and shall be designed to be easily removed for access, servicing, adjustment and maintenance.

    1.14 SIGNS AND NOTICES

    A All signs and notices shall be in Arabic and English with the Arabic version being above or to the right of the English version.

    B A schedule of all signs and notices with proposed Arabic translations shall be approved by the Engineer prior to manufacture.

    1.15 MOUNTING HEIGHTS

    A Mounting heights of equipment above finished floor level shall be coordinated with architectural details and other disciplines/equipment. Any discrepancy found between these heights and other details shall be brought to the notice of the Engineer for clarification and final decision. Unless otherwise indicated on the drawings, mounting heights of electrical devices shall be as follows:

    1. Panel board: 1800 mm (Top of panel above FFL).

    2. Disconnect/Isolating switch: 1400 mm.

    3. Light switch: 1200 mm (100 mm from door frame horizontally).

    4. Dimmer switch: 1200 mm.

    5. Push button station: 1200 mm.

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 7

    6. Wall mounted telephone/intercom: 1600 mm.

    7. Fire alarm manual call point: 1400 mm.

    8. Fire alarm sounder: 2100 mm.

    9. Fire alarm panel: 1800 mm (top of panel above FFL).

    10. Power outlet: 300 mm.

    11. Data/Telephone outlet: 300 mm.

    12. TV/Radio outlet: 300 mm.

    13. Wall mounted speaker: 2100 mm.

    B Where accessories with varying mounting heights (e.g. light switch and socket outlet) are shown in approximately the same location on plan, their center lines shall be aligned vertically.

    C Where wall mounted accessories are shown adjacent to each other they shall be mounted with their wall plates separated by 50 mm.

    1.16 LABELING AND IDENTIFICATION

    A Each item of the Electrical Installation including electrical switchgear, control gear, equipment, devices, etc. shall be fitted with a non-corrodible label clearly indicating its function giving at least the following information:

    1. Manufacturers name.

    2. Country of origin.

    3. Type/model number or code.

    4. Rated voltage, current and frequency (as applicable).

    5. Short circuit breaking capacity with time.

    6. Compliance mark of the international standard(s).

    B Prior to final testing, confirm that all labeling is intact over the whole site and that all cables have been fitted with circuit markers. 13800 Volt cables shall be clearly labeled "DANGER High Voltage" every two meters of their exposed length.

    C All conductors shall have their outer covering coloured to suit the phase to which they are connected.

    D An instruction notice giving details of first aid treatment for electric shock shall be positioned in an approved position in each switch room.

    E Manufacturer's or contractor's names or trademarks shall not be exhibited anywhere through the installation without the prior approval and permission of the Engineer with exception that the contractor's name and address may be fixed in an approved position on the main incoming switchgear.

    F All labels shall be in English and Arabic.

    1.17 VERMIN PROOFING

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 8

    A All items of electrical equipment shall be adequately vermin proofed.

    B Where cables enter or leave the bottoms of switchboards, or pass through pipe ducts, they shall be sealed by the use of hard wood plugs treated with vermin repellent and surrounded by mastic sealant.

    C All spare pipe ducts shall be similarly sealed by the use of solid hard wood plugs.

    D Alternative methods of vermin sealing will be accepted, but the written comments of the Engineer must be obtained prior to installation.

    1.18 FIRE AND SAFETY PRECAUTIONS

    A The whole of the works shall be carried out with care and so arranged as to minimize the risk of fire and the extent of damage resulting from any outbreak of fire.

    1.19 POWER SHUT DOWN PROCEDURES

    A During the course of construction a situation may arise when a power outage or shut down of an existing facility will be required to facilitate power connection of a new installation with the existing facility in operation, or power connection between different phases of a new construction. For such situations or any other situation which requires power shut down of an existing facility under operation, submit a work plan for approval to the Engineer, indicating therein the temporary arrangements he shall make to maintain the continuity of power supply to the existing facility.

    B The activities of the work plan shall be scheduled in such a way to cause minimum inconvenience to the users or occupants of the existing facility (e.g. shut down during holiday or after working hours) and in proper coordination with all concerned authorities. The work plan shall include, but not limited to the following:

    1. List of activities prior to power shut down.

    2. List of various authorities to be coordinated prior to power shut down.

    3. Sequence of various activities for shut down of power supply.

    4. Time duration of each activity.

    5. Shut down duration for various activities.

    6. Alternate power supply arrangement to maintain continuity of power to the existing facility.

    7. Reliability of alternate power supply arrangement.

    8. Step-wise sequence of activities for restoration of power supply.

    C The cost for the provision of activities and other interim arrangements for the continuity of power supply to the existing facility during power shut down procedures shall be deemed to be included in the total price of the tender.

    1.20 PENALTY FOR DAMAGE TO EXISTING UTILITIES

    A Study the location of all existing utilities and any other facilities, and perform the Work so as not to damage them. In the event that any of such facilities are damaged by the Contractor,

  • MINISTRY OF HOUSING Western Sector Projects Sitework & Infrastructure OMRANIA and ASSOCIATES Project Specification

    COMMON WORK RESULTS FOR ELECTRICAL SECTION 26 05 00 - 9

    the same shall be immediately repaired by the contractor at his cost and responsibility.

    B In the event that the contractor damages the existing utilities or facilities listed below, the contractor shall pay to the client, in addition to the repair costs, an amount specified below:

    1. Power cable, Control cable: An amount equal to 100% of the actual repair cost of cable.

    2. Telephone cable: An amount equal to 100% of the actual repair costs.

    3. Fresh water line: An amount equal to one 100% of the actual repair costs.

    4. Sewer line: An amount equal to 100% of the actual repair costs.

    1.21 SHORT CIRCUIT AND PROTECTION STUDY

    A Obtain the services of the major electrical equipment manufacturer to provide a complete computerized study of fault current and coordination of relays, fuses, circuit breakers, and all other protective devices. The contractor shall coordinate with the Saudi Electricity Company (SEC) to include protection settings and fault levels of the SEC feeders and circuit breakers in the study.

    B The study shall include all feeders at medium voltage and low voltage system.

    C The contractor shall obtain all data, characteristic curves and all necessary information from all other trades in connection with his work to provide complete study for the system.

    D The study shall include, but not be limited to the following:

    1. Fault current available at each major equipment bus.

    2. A tabulation of all protective relay and circuit breaker trip settings and recommended fuse sizes and types.

    3. Transformer damage curves in accordance with manufacturer recommendations.

    4. Motor starting profile for largest motor in each control center.

    5. A complete set of time-current coordination curves on logarithmic scale sheets.

    E The short circuit and protection study shall be bound in a standard A4 size report. The final selection and settings of all protective devices shall be based on this study. The complete study shall be approved by the Engineer. Protective devices shall be adjusted, tested, and calibrated in the field prior to energizing the equipment per the settings listed in the study.

    1.22 SPARES AND CONSUMABLES

    A Provide an un-priced list of spares and consumables to manufacturers recommendation for one (1) years operation for every item of plant and system at the time of tendering.

    B Provide operation and maintenance manuals for all equipment.

    END OF SECTION

    SECTION 26 05 00GENERAL REQUIREMENTSAll general provisions contained herein or within any other section of the specification shall be fully applicable to each and every other section.Works on all installations shall be carried out in a neat, efficient and workmanlike manner, assuring satisfactory operation, maintenance and repair. Work shall be in accordance with the requirements of this specification and shall fulfill its true in...This specification and associated drawings form a composite set of documents, intended for the selection and installation of equipment having the general and specific characteristics as detailed.Unless otherwise specifically stated, the installation shall be left complete, tested and ready for operation in all respects and fully integrated and coordinated with all other trades.The Contractor shall submit proof, if requested by the Engineer that the materials, appliances, equipment or devices that are furnished and installed under the contract meet the requirements of the reference standards with regard to fire and safety ha...Contractor shall comply with all applicable SEC distribution material specification, construction and planning standards for power distribution networks and municipality specification for road lighting. Some of the specifications and standards are att...Any conflict found between this project specification and SEC or municipality specification/standards shall be immediately brought to the notice of Engineer for final decision.

    SCOPE OF WORKREFERENCESSBC Saudi Building Code.SASO Saudi Arabian Standards Organization.IEC International Electro-technical Commission.

    ELECTRICAL SUPPLYThe Medium voltage electrical power supply from Saudi Electricity Company (SEC) shall be 3 phase, 13.8 kV Delta, 60 Hertz.The Low voltage electrical power supply and distribution system shall be 400/230 Volts, 3 phase, 4 wire, 60 Hertz, earthed neutral system.

    Lighting REQUIREMENTSEARTHING REQUIREMENTSLOW CURRENT and SPECIAL SYSTEMS REQUIREMENTSThe Contractor shall be solely responsible for the proper co-ordination of all phases of the work and timely delivery to the site of all equipment and materials for proper execution of the work.Visit the site and survey in detail the as-built situation of all the areas related to the project before bidding/signing the contract.Making of any hole in the existing slab or breaking of any portion of existing structural walls shall be properly coordinated with all concerned authorities/agencies and proper approval of the method statement shall be obtained from the Engineer befor...Co-ordinate the work with all or any other disciplines to ensure proper phasing and continuity of the Works. If it becomes necessary to remake any part of these works or that of any other discipline or trade as a result of poor or badly timed co-ordin...Co-ordinate with all supply undertakings and authorities and include for attendance along with all costs involved in re-directing existing services.Take into consideration all statutory and local requirements issued by the Saudi Electricity Company (SEC), Local Authority, Central Government, Broadcasting Authority, Communication and Information Technology Authorities along with any other requirem...The contractor shall be responsible for co-ordination with all electrical and mechanical systems suppliers and shall include in his cost all the electrical requirements (even if they were not mentioned in the BOQ or drawings) to provide a fully funct...

    CLIMATE CONDITIONSExternal to buildings and in non-air conditioned spaces, all apparatus shall be rated for an ambient temperature maximum of 55 oC, minimum of 0 oC, generally dusty desert conditions, a maximum humidity of 100% rh, and an elevation of 630 meters above ...In air conditioned buildings, all apparatus shall be rated for ambient temperature of 45 C maximum, minimum of 0 C and a maximum humidity of 90% RH.When equipment is installed in direct sunlight, it shall either be shielded from direct radiation or suitably rated for additional solar gains. Cables shall always be shielded from direct sunlight.All apparatus shall be rated for continuous service twenty four hours a day, seven days a week throughout its normal rated life, except for necessary routine maintenance.

    All equipment shall be rated for very harsh and corrosive environmental conditions which persist at the project site. All buried installations shall be suitable for aggressive and salty soil conditions.ACCESSIBILITYAll works within the project and particularly above suspended ceilings or inside vertical shafts shall be installed so as to be accessible for operation, maintenance and repair. If necessary, deviations from the drawings may be made to accomplish this...

    STORAGE OF MATERIALS AND EQUIPMENTComply with section 01 61 00.All material and equipment fixed or unfixed, shall be protected against corrosion, deterioration and ingress of foreign matter and moisture.All material and equipment shall be kept clear of the floor or ground by means of wooden blocks and shall be protected against weather with durable waterproof wrapping and other appropriate means.

    PREVENTION OF NOISE AND VIBRATIONProvision shall be made to minimize noise and vibration. However, different manufacturer's equipment will have varying sound and vibration characteristics. The contractor shall be responsible for ensuring that equipment installed does not transmit unn...All equipment installed in plant rooms and outside areas shall not be audible in occupied areas.Any vibration isolators, isolating bases, flexible connections, silencers, other acoustic treatment or anti-vibration precautions necessary shall be included in the rates for equipment.Submit proof of the selected noise proofing measures to the Engineer before commencement of work.Submit to the Engineer for information the noise level generation by the plant selected so that structural soundproofing measures can be evaluated. This means either data on the acoustic capacity level in relation to frequency, or the sound pressure l...All costs of noise sound level measurements and any repeat measurements, necessary if acoustic requirements are not met, shall be allowed for by the contractor.

    GUARDSAll moving parts of machinery shall be protected by strong guards to adequately protect all personnel working on or in the vicinity of equipment. The guards shall be constructed in such a manner that the movement of drive belts and rotation of shafts ...All 'live' parts of electrical equipment shall be protected in such a way to adequately protect all personnel working on or in the vicinity of equipment from injury.Wherever possible, all protective guards shall be supplied by the equipment manufacturer. All guards shall be strongly attached to equipment and shall be designed to be easily removed for access, servicing, adjustment and maintenance.

    SIGNS AND NOTICESAll signs and notices shall be in Arabic and English with the Arabic version being above or to the right of the English version.A schedule of all signs and notices with proposed Arabic translations shall be approved by the Engineer prior to manufacture.

    MOUNTING HEIGHTSMounting heights of equipment above finished floor level shall be coordinated with architectural details and other disciplines/equipment. Any discrepancy found between these heights and other details shall be brought to the notice of the Engineer for...

    LABELING AND IDENTIFICATIONEach item of the Electrical Installation including electrical switchgear, control gear, equipment, devices, etc. shall be fitted with a non-corrodible label clearly indicating its function giving at least the following information:Prior to final testing, confirm that all labeling is intact over the whole site and that all cables have been fitted with circuit markers. 13800 Volt cables shall be clearly labeled "DANGER High Voltage" every two meters of their exposed length.All conductors shall have their outer covering coloured to suit the phase to which they are connected.An instruction notice giving details of first aid treatment for electric shock shall be positioned in an approved position in each switch room.Manufacturer's or contractor's names or trademarks shall not be exhibited anywhere through the installation without the prior approval and permission of the Engineer with exception that the contractor's name and address may be fixed in an approved pos...All labels shall be in English and Arabic.

    VERMIN PROOFINGAll items of electrical equipment shall be adequately vermin proofed.Where cables enter or leave the bottoms of switchboards, or pass through pipe ducts, they shall be sealed by the use of hard wood plugs treated with vermin repellent and surrounded by mastic sealant.All spare pipe ducts shall be similarly sealed by the use of solid hard wood plugs.Alternative methods of vermin sealing will be accepted, but the written comments of the Engineer must be obtained prior to installation.

    FIRE AND SAFETY PRECAUTIONSThe whole of the works shall be carried out with care and so arranged as to minimize the risk of fire and the extent of damage resulting from any outbreak of fire.

    SPARES AND CONSUMABLESProvide an un-priced list of spares and consumables to manufacturers recommendation for one (1) years operation for every item of plant and system at the time of tendering.Provide operation and maintenance manuals for all equipment.