16
FOR CONSTRUCTION SECTION 15406 RAINWATER DISPOSAL INSTALLATION PART 1 - GENERAL 1.01 WORK INCLUDED A. Contract Documents 1. All work of this Section shall comply with the requirements of the Contract Documents for the Main Building works, with the Drawings, Schedules and with all other Contract Documents. B. Scope of Work 1. The Scope of Work of this Section shall include the design, supply and installation of pipework and fittings at locations shown on Drawings including the following areas: a. Main Retail Building b. Car Park Blocks c. Planter Box drainage d. Road/Driveway drainage e. Drainage of Ventilation/exhaust ducts/access panels in Basement f. Overhead bridges g. Toilet floor trap covers 2. The Contractor shall allow for connection of pipework to existing drains C. Related Works Specified Elsewhere 1. Related Work Specified Elsewhere a. Pavior : Section 03700 b. Waterproofing & Insulation : Section 07100 c. Sheet Metal Roofing : Section 07610 D. Quality Assurance 1. Pipework installers shall have had a minimum of five years experience in their trade. 2. All pipework and fittings supplied for this project shall conform to the latest version of relevant British and American Standards. 3. The pipework shall comply in accordance with the latest versions of the following standards or other equivalent local standard. a. Rainwater and General Plumbing: i) BS 21 Specification for pipe threads for tubes and fittings where pressure-tight joints are made on threads (metric dimensions) ii) BS 437 Specification for cast iron spigot and socket drainpipes and fittings. Burj Dubai – Dubai Mall Hotel, Dubai, United Arab Emirates Rainwater Disposal Installation MEP Spec-For Construction (Date of Issue: Jan 2006) 15406.1

Section 15406

Embed Size (px)

DESCRIPTION

Rain Water Disposal Intallation

Citation preview

SECTION 15406

SECTION 15406RAINWATER DISPOSAL INSTALLATION

PART 1 - GENERAL

1.01WORK INCLUDED

A. Contract Documents1. All work of this Section shall comply with the requirements of the Contract Documents for the Main Building works, with the Drawings, Schedules and with all other Contract Documents.

B. Scope of Work

1.The Scope of Work of this Section shall include the design, supply and installation of pipework and fittings at locations shown on Drawings including the following areas:

a. Main Retail Building

b. Car Park Blocks

c. Planter Box drainage

d. Road/Driveway drainage

e. Drainage of Ventilation/exhaust ducts/access panels in Basement

f. Overhead bridges

g. Toilet floor trap covers

2. The Contractor shall allow for connection of pipework to existing drains

C. Related Works Specified Elsewhere

1.Related Work Specified Elsewherea. Pavior:Section 03700

b. Waterproofing & Insulation:Section 07100

c. Sheet Metal Roofing:Section 07610

D. Quality Assurance

1. Pipework installers shall have had a minimum of five years experience in their trade.

2. All pipework and fittings supplied for this project shall conform to the latest version of relevant British and American Standards.

3. The pipework shall comply in accordance with the latest versions of the following standards or other equivalent local standard.

a. Rainwater and General Plumbing:

i)BS 21Specification for pipe threads for tubes and fittings where pressure-tight joints are made on threads (metric dimensions)

ii)BS 437Specification for cast iron spigot and socket drainpipes and fittings.

iii)BS 460Specification for cast iron rainwater goods.

iv)BS 1091Specification for pressed steel gutters, rainwater pipes, fittings and accessories.

v)BS 1184Specification, Copper and copper alloy traps.

vi)BS 1387Specification for screwed and socketed steel tubes and tubular and for plain end steel tubes suitable for welding or for screwing to BS21 pipe threads.

vii)BS 2494:Specification for elastomeric seals for joints in pipework and pipelines.

viii)BS 2997Specification for aluminium rainwater goods.

ix)BS 3505Specification for unplasticised polyvinyl chloride (PVC-U) pressure pipes for cold potable water

x)BS 4346 Joints and fittings for use with unplasticised PVC pressue pipes.

xi)BS 4576Unplasticised polyvinyl chloride (PVC-U) rainwater goods and accessories.

xii) BS 5481Specification for unplasticized PVC pipe and fittings for gravity sewers

xiii)BS EN 545Ductile iron pipes, fittings, accessories and their joints for water pipelines. Requirements and test methods.

4.In the event of conflict between Standards, the more stringent Standard will apply.

E. Submittals

1. Shop Drawings and manufacturer's data shall show plans, elevations and sections of piping layout, and shall show locations of pipe hangers, pipe guides, pipe anchors, and equipment to which the piping connects.

2. Submit certifications that the pipework and fittings supplied are in conformance with the standards set out hereunder.

3. Submit pipe joints, pipe support hangers, guides and anchor details for approval.

4. Submit pipe testing and cleaning procedures for approval.

5. Submit complete testing report after testing and commissioning.

PART 2 - PRODUCTS

2.01GENERAL REQUIREMENTS

A. Acceptable Manufacturers

1. Acceptable manufacturers, subject to compliance with specified requirements. Other manufacturers providing similar and equal product will also be given equal consideration:

a. Cast iron outlet with gravel stop and mushroom dome for planter drainage outlet and cast iron outlet for roof drainage with nickel bronze flat gratings at areas exposed to view, cast iron dome gratings at non-visible areas and nickel bronze flat gratings to floors drains (car parks and service corridors).

i) "Wade" International Ltd W-3000 Series and K Series.b.Upvc Pipe

i)Ipex

ii)Creative Polymer Industries Pte Ltd

iii)Singa Plastic Ltd

v) Splendour Corporation Pte Ltd

Stainless steel floor drain outlet for toilets.

c."SMITH" USA, stainless steel finish or approved equivalent. Selected models:

i) Model 9735- 8 Round adjustable top with solid scoriated cover and closure plug. Rough finish stainless steel body, adjustable top, secured scoriated cover and gasketed closure plug. Each complete with stainless steel closure plug with test plug, and flashing clamp with seepage holes.

B. Materials

1. All products delivered to site shall be new and properly marked to identify the grade.

2. All pipe runs shall be installed generally in accordance with the drawings but the Contractor shall include full allowance for detailed scheme development.

3. Pipework shall be installed with correct falls to ensure adequate venting and draining.

4. No welding is permitted on the pipework under any circumstances whatsoever.

5. All pipes passing through the building expansion joints shall be fixed with flexible connectors.

6. When pipework is embedded into the concrete structure all pipework including joints shall be cleaned and tested for leakage prior to the pouring of concrete.

7. UPVC pipework specification shall be in accordance with the following tables.

Table 1 - Pipework SpecificationNominalBore (mm)Above groundUndergroundHeavy Duty

100 150BS 3505BS EN 1456 BS 3505

200 and aboveBS 3505BS 5481BS3505,

Table 2 - Pipework JointsNominalBore (mm)Above groundUndergroundHeavy Duty

100 200BS 3505BS EN 1456BS 4346

250 & above-BS 5481BS 4346

Table 3 - Maximum Support SpacingsNominalSupport Centre (m)

Bore (mm)VerticalHorizontal

1001.51.2

1501.51.2

250 and above1.21.0

Table 4 Pipe Dimension Table (above ground / Non- pressure)Nominal Pipe Dia (mm)Min. Outside Dia (mm)Min. Wall thickness (mm)Max. weight per m length (kg)

1001102.419

1501603.228

2002164.044

2502676.152

3003156.073

4004009.8120

Table 5 Pipe Dimension Table (underground) (equivalent to BS EN 1456 & BS 5481)

Nominal Pipe Dia (mm)Min. Outside Dia (mm)Min. Wall thickness (mm) Max. weight per m length (kg)

1001103.218

1501604.036

2002004.955

2502506.185

3003157.7120

4004009.8150

Table 6 Pipe Dimension Table Heavy Duty (BS 3505:1986, 3506:1969)Nominal Pipe Dia (mm)Min. Outside Dia (mm)Min. Wall thickness (mm) Class CMax. weight per m length (kg) Class CMin. Wall thickness (mm) Class DMax. weight per m length (kg) Class D

1001144.5136.018

1501686.624.58.840

2002187.84410.357.5

2502729.76812.889

30032311.59615.2125

PART 3 EXECUTION3.01 INSTALLATIONA. Pipe Installation1.General:

a. Install piping parallel to columns and/or walls, clear of obstructions, preserving headroom specified in all vehicular traffic areas to comply with authorities' requirements and keeping passageways clear.

b. Should structural difficulties or other work prevent running of pipes or setting of equipment at locations indicated on Drawings, necessary minor deviations will be allowed. The Contractor shall inform the SC of these deviations, acceptance shall be obtained from the SC prior to the work being carried out.

c. Cut pipes in a neat and workman like manner without damage to the pipes. Unless otherwise recommended by the manufacturer, cutting shall be done with an accepted type of mechanical cutter. Use wheel cutters where practicable. Ream pipe ends to remove burrs.

d. As soon as pipes have been installed cover openings to prevent extraneous materials causing obstructions. Leave covers in place until removal is necessary for completion of installation.

e. Attach supports only to structural framing members. Where supports are required between structural framing members, provide suitable intermediate metal framing.

f. Install piping with sufficient pitch to ensure adequate drainage.

g. Support piping independently from all equipment so that equipment is not stressed by piping weight or expansion.

h. All pipes shall be stored with closed ends, which shall not be opened until erection. Every precaution shall be taken to clean out piping before, during and after erection, and to prevent foreign material being left in the pipe.

i. Where pipes pass through a building expansion joint and/or are subjected to movement, approved flexible connections shall be provided to eliminate any stresses whatsoever which might be caused by such movement.

j. Where pipes are to be connected to existing fittings or drains that were installed by previous Contractor, the Contractor shall ensure that the pipes are compatible with the existing fittings. Joints shall be spigot and socket joints.

k. All pipework shall be installed plumb, level or true to the gradient, and shall be neatly grouped with the minimum number of crossovers and adequate provision for venting, expansion, contraction and movement. Pipework shall be substantially supported. Adequate clearance shall be maintained from all other services and from the building structure.

l. The Contractor shall check all declared invert levels before laying any underground and embedded piping and shall notify the SC immediately of any discrepancies.

m. All underground and embedded pipework shall be protected by wrapping with hessian or other acceptable material and coated with bitumen paint.

B. Pipe Hangers and Supports1.General:

a. All necessary hangers and supports, including rods, angles, channels and plates, as well as any changes from indicated design, shall have the SC's prior acceptance. All members of the hanger and support system shall be fabricated from hot dipped galvanized steel. Components such as washers, bolts, nuts, and the like shall also be of hot dipped galvanized steel.

b. Vertical piping shall be guided or supported in the centre of each riser, with approved steel brackets to prevent swaying, sagging, vibration and resonances. Avoid strains that cause lines to snake or buckle between supports or anchors.

c. Pipe hangers of same size or nearest manufactured size available as pipe or tubing on which they are to be used shall be provided.

d. Install a gasket between clamp and pipe of dissimilar material.

e. No pipe support and hangers shall be mounted on any drywall partitions.

2.Type of Devices:

1. Provide hangers and supports as illustrated on the drawings, or as required in accordance to the manufacturer's instruction.

2. Secure hangers from concrete work to metal inserts cast into/anchored to concrete. When these inserts are not available, make attachment by one of the following as directed by the SC.

i)Anchor bolts set in place with fast setting high strength grout.

ii)Controlled energy type power actuated fasteners.

3.Furnish anchors and guides for all horizontal and vertical piping for proper control of thermal movement, to prevent perforation of expansion joints and to avoid overloading of hangers and supports.

C. Cleaning1. Exercise every precaution to avoid introducing foreign matter into piping system. All piping and fittings shall be internally cleaned of oil, grease or dirt, prior to assembly into systems.

2. Following fabrication and erection, clean all piping 150mm and smaller by flushing with clean water and run to waste until thoroughly free of all dirt, oil and cuttings, and the like. Generally, each size of pipe shall be flushed separately before being jointed with larger size piping.

3. Clean piping 200mm and larger by pulling through fibre brush or swab for entire length of each pipe size. Brushes and swabs are to be slightly larger than inside diameter of pipe being cleaned.

4. All cleaning operations, shall be continuous throughout piping installation system, except at joints required for final joining of various sections of cleaned piping. After cleaning and until above final joints are made, end of sections of piping shall be adequately and tightly sealed off to prevent any dirt, water or other foreign matter from entering ends of pipe.

5. Cleaning of pipes shall occur at the end of each day and immediately after the occurrence of rain.

D. Testing and Commissioning1. The Contractor shall carry out all necessary testing and commissioning procedures in addition to those called for elsewhere in this specification comprising tests at manufacturer's works, site tests during construction, commissioning and acceptance tests, all as specified below.

2. Testing and commissioning shall be carried out in accordance with the appropriate British Standard or BS Code of Practice.3. All tests shall be witnessed by the SC and shall be properly certified in a manner to be agreed with the SC and four copies of all certificates shall be issued to the SC on completion.

4. Provide 24 hours notice to the SC before testing.

5. Test records, certificates and performance curves shall be supplied for all tests, whether or not they have been witnessed by the SC. The information given on such test certificates and services shall be sufficient to identify the material or equipment to which the certificate refers.

6. These test records, certificates and performance curves shall be supplied for all tests, whether or not they have been witnessed by the SC. The information given on such test certificates and services shall be sufficient to identify the material or equipment to which the certificate refers.

7. Only when the installations have been so certified and all test figures and other relevant information have been recorded in the prescribed manner and accepted by the SC should the works be considered fit for handing over to the Employer.

8. The tendered sum shall be deemed to have included all costs associated with the above mentioned testing and commissioning procedures including the cost of making good any defects arising out of such tests and having the work retested. Such costs shall also include for the provision of all instruments necessary for the test.

9. The Contractor shall be responsible to supply all testing equipment necessary for the testing and commissioning of the entire system.

E. Test at Manufacturer's Work and On Site1. Manufacturer's works test shall include all tests in accordance with the relevant British or American Standards and in addition any tests called for by the SC to ensure that the plant being supplied meets the requirements of the specification. For material/equipment not covered by any British Standard or specifically mentioned in this specification the tests shall be agreed with the SC.

2. Supply and install all materials, supplies, labour and power required for hydrostatically testing all piping. Make preliminary tests and prove work satisfactory. Notify SC in ample time to be present for final testing of all piping. Repair defects disclosed by tests or, if required by SC, replace defective work with new work without additional cost. Make tests in stages if so directed by SC to facilitate work of others. Use of wicking in tightening leaking joints is not permitted.

3. The Contractor is responsible for work of other trades disturbed or damaged by tests and/or repair and replacement of his work and shall cause work so disturbed or damaged to be restored to its original condition at his own expense.

4. Supply and install all necessary testing junctions and bends for all pipework, and seal off or remove them as directed by the SC.

5. All trap seals shall be tested for stability by means of an appropriate discharge test, under which every trap must maintain at least 25mm water seal under three consecutive tests.

F. Preliminary Commissioning Checks1. The Contractor shall ensure that all equipment included under this Contract is thoroughly cleaned, lubricated and checked for serviceability immediately before setting to work. Particular attention is drawn to the removal of building debris from the pipework systems.

2. Attention is drawn to the need for thoroughly flushing out all pipework systems to ensure that all foreign matter is removed.

G. Commissioning1. When the various installations have been completed (but before the issue of the Completion Certificate) and the preliminary commissioning checks carried out, the Contractor shall set to work and regulate the system in the entire installation.

H. Final Acceptance Tests1. Following commissioning of the entire installation, the Contractor shall carry out final acceptance tests and prior to issue of the Performance Certificate in accordance with a programme to be agreed with the SC.

2. Should the results of the acceptance tests show that the pipework to perform to the performance figures as given in this specification or as accepted in the Contractor's tender, the Contractor shall adjust, modify and if necessary replace the system without further payment in order that the required performance be obtained. Should it be necessary for the Contractor to attend to items of plant as above described, he will be responsible as to cost for any damage or deterioration to the building or other services consequent on such attendance.

I. Rejection of Plant

1. Any part of the system or pipework or component which fails to comply with the requirements of this specification in any respect whatsoever at any stage of manufacture, test, erection or on completion at site may be rejected by the SC either in whole or in part as he considers necessary. After adjustment or modification if so directed by the SC, the Contractor shall submit the items for further inspection and/or tests. Pipework or components with defects of such a nature that the requirements of this Specification cannot be fulfilled by adjustment or modification shall be replaced by Contractor at his own expense.

PART 4 CONNECTION TO EXTERNAL DRAINAGE SYSTEM

A. Excavation and Backfiling1. Excavation for pipe trenches shall not be less than 600mm wider than the internal diameter of the pipes and the ground under pipe beds shall be carefully graded. Proper necessary shoring, planking or strutting shall be constructed and maintained to ensure that the trench will not collapse.

2. Surplus excavation soil shall be removed from the site.

3. All excavations shall be kept free from water at all times by pumping, bailing or temporary drainage.

4. In the event of the excavations being made deeper than necessary they shall be filled to the proper level with lean concrete.

5. Allowance shall be made for removing all rock or construction debris met with in the course of excavation with picks, wedges, levers and sledgehammers and compressor drills. No blasting will be allowed.

6. Sleeve have been cast into the existing diaphragm walls. The Contractor shall carry out any remedial works required to penetrate the walls if the sleeves have been mis-aligned. The Contractor shall waterproof the pipe penetrations through the wall to the satisfaction of the Engineer.

7. Fill with selected materials, free from lumps exceeding 75mm in size and from stones, and compact in layers not exceeding 150mm in depth to a level of 300mm above the top of the pipes. The remainder of the trench shall be backfilled to the surrounding level with approved excavated material.

8. Trenches shall be left open for the inspection of the Engineer and the Local Authority's inspector and shall not be covered up until the drains have been properly tested and approved.

B. Concreting Works1. The components of the reinforced concrete shall be as follows :

a. Cement shall be of approved type and comply with BS 12. It shall be fresh when delivered. Cement of different brands shall not be mixed with one another. Cement which has set in the bag upon opening, shall not be used.

b. Sand or fine aggregate shall be cleaned, graded natural sand. Sand with coagulated lumps and having a portion of silt exceeding 10% shall be rejected.

c. Coarse aggregate shall be cleaned, crushed stone and shall be free from dust, clay or other deleterious materials.

d. Water shall be that obtained from the supply mains and not from excavation or drains.

e. Reinforcement used shall be hard-drawn steel wire BRC fabric mesh complying with BS 1221 and BS 785 for mild steel rods. BRC mesh and steel bars shall be free from rust or mill scale.

2. Concrete beds shall be 150mm thick and shall have at least 150mm width at each side of the external diameter of the pipe barrels when laid. Unless otherwise specified, the concrete shall be 1:2:4.3. For pipes to be haunched, the concrete shall be carried up for the full width of the bed to the level of the horizontal diameter of the pipe and shall be splayed from this level and carried upwards to meet the pipe barrel tangentially.4. All pipe work passing under driveways are to be surrounded with concrete which shall be carried up from the bed in a square section with a minimum of 150mm thickness over the barrel of the pipes.

C. Pipe Laying1. The pipe shall be laid singly with the whole length of the barrel of each pipe on a solid bed. No pipes shall be joined together before having been laid.

2. Where pipes are to be laid without concrete, joint holes shall be formed in the bottom of the trench ahead of the work in order that joints may be properly made. The joint holes shall be as short as practicable.

3. Where pipes are to be concreted, the concrete shall be spread over the floors of the trenches and headings to half the thickness of the bed finally required. This concrete shall be brushed and washed down with clean water immediately before pipe laying is commenced. As each pipe is laid the barrel shall be lumped into a dumpling of plastic concrete, to the correct line and level. After the dumplings have been set and the joints have been made and tested, the remainder of the concrete shall be placed and lumped solid.

4. The socket shall face up the gradient. The spigot of each pipe shall be well-driven home into the socket of the pipe previously laid and the joint completed as specified and the bore of the pipe cleared of any obstruction before the next pipe is laid. Care shall be taken that there is no irregularity in the invert of the joints.

5. The level of each pipe shall be tested by a straight edge laid in the invert of the pipe previously laid and on the nearest level peg. If the bottom of the trench has been taken too low, it shall be made up with concrete or cement mortar.

6. Where it is required to shorten any pipe, it shall be cut off square and cleanly, and cast iron pipes shall be cut only with approved pipe-cutting machines.

7. In the event of any pipe being fractured from any cause whatsoever after having been properly laid the pipe, in every instance, shall be replaced to the satisfaction of the Engineer.

8. Where laid in hardcore or fill, cast iron pipes subjected to a superimposed load shall be supported from natural ground level throughout their lengths by walls and haunching.

9. Where laid in hardcore or fill and not subjected to a superimposed load, or where laid above ground, cast iron pipes shall be supported on piers behind the socket of each pipe and at intervals or not more than 2700mm.10. In soft or yielding ground where there is permanent ground water and subject to the approval of the Engineer, pipes shall be laid on "bakau" piles and a bed of reinforced concrete 150mm thick. For tender purposes, based on piles of 4.5m length at 300 centres of at least 75mm diameter, the Contractor shall provide a unit rate estimate. The design of the concrete bed, reinforcement and other details shall be to the requirement of the Local Authority.

11. Piles laid through or under walls, shall be laid in such a manner than the weight of the wall shall not bear on the pipes.

12. Pipes laid in injurious soil or materials shall be protected as shown or as directed by the Engineer.

D. Existing Services Interference with Traffic an Adjoining Properties1. The Contractor shall liaise with the relevant Service Departments, for the location of all pipes, cables, mains, ducts, posts, manholes, boxes, etc along beneath the road reserves or in any other part of the work in order to ensure that all service requirements are met before commencement of the work.

2. The Contractor shall apply to the Police Department and other relevant authorities where necessary to procure all permits before proceeding with the works.

3. The Contractor shall obtain up-to-date information or drawings from the respective Authorities with regard to the existence of other services along or beneath the road.

4. The Contractor shall be held responsible for any damage done during the progress of works and shall meet all costs and repairs and reinstatement due to such damage.

5. The Contractor shall notify the SC/Engineer and any relevant authorities immediately of any existing services which will be affected by the works and shall immediately provide adequate supports and protection of same to the satisfaction of the SC/Engineer at his own expense.

6. All operations necessary for the execution of the works shall be carried out in such a manner so as not to interfere unnecessarily or improperly with public convenience.

7. The Contractor shall, when required by the SC or by the Authority, apply and operate suitable methods of traffic control at his own expenses. If so required, flashing warning lights and notice shall be displayed at the Contractor's expense.

E. Restoration of Surface1. The Contractor shall be responsible and liable for the restoration of any apron or road paving bitumen surfacing etc, or any turf removed or damaged as a result of this.

2. Any aprons, roads, paths, and the like so affected shall be restored with materials of the same nature and of equal quality as those contained in the original pavement and to the same standard of construction and the same depth so as to produce at the end of the Maintenance period, a finished surface at least equal in all respects to that existing before the commencement of the works comprising this.

3. Should the Contractor fail to properly restore and maintain surfaces affected by his operations, the SC shall have the authority to employ others to make good the surfaces affected and the cost of such labour, transport and materials employed shall be paid for by the Contractor.

F. Connection to Existing Drains

1. Where indicated on the drawings the Contractor shall allow to break into the existing street drains. The Contractor shall obtain approval from the Local Authorities prior to the works.

2. The Contractor shall minimize the extent of demolition required to allow the pipe to pass into the drain. The Contractor shall install the pipe as indicated on the drawings.

3. The Contractor shall reinstate the drain to the approval of Local Authorities.END OF SECTIONBurj Dubai Dubai Mall Hotel, Dubai, United Arab Emirates

Rainwater Disposal Installation

MEP Spec-For Construction (Date of Issue: Jan 2006)

15406.2