Schenectady City School District Mosaic Associates Mike Fanning, AIA Turner Construction Larry E Tune, PM Phase I – Capital Project Update 16 th of November, 2016 1

Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

Schenectady City School District

Mosaic Associates

Mike Fanning, AIA

Turner Construction

Larry E Tune, PM

Phase I – Capital Project Update

16th of November, 2016

1

Page 2: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT UPDATE| Outline

• Update on Current Capital Work• Group B Projects

• Group C Projects

• Group D Projects

• Overview of Capital Projects• Timelines

• Long Range Planning

• PH II - Schedule

• Next Steps:• Critical & Milestone Dates

2SCSD Capital Project Update – 16th of November, 2016

Page 3: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

3SCSD Capital Project Update – 16th of November, 2016

• MPMS – Phases 1, 2 & 3

CAPITAL PROJECT | Group B

Work substantially complete

( Second Floor Only )

Work in progressuntil Dec 2016.

Work in progress( Second Floor Only )

Work commence Dec. 2016

Work commence June 2017

Page 4: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT | Group B

• OMS Substantially complete.

Punch List & close out in progress.

4SCSD Capital Project Update – 16th of November, 2016

Page 5: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

5

• CENTRAL PARK MIDDLE SCHOOL

SCSD Capital Project Update – 16th of November, 2016

CAPITAL PROJECT | Group C

Turnover next week

Occupied by district

Ground Floor

First Floor

Second Floor

Page 6: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT | Group C

6SCSD Capital Project Update – 16th of November, 2016

• Howe Elementary School -• Product submittal process 75%.

• Construction in progress.

Building Addition Existing Building Renovation

Page 7: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT | Group C

7SCSD Capital Project Update – 16th of November, 2016

• Van Corlaer ES -• Product submittals process 75%.

• Phase 1 December substantial completion.

• Phase 1A February substantial completion.

Page 8: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT | Group D

• Hometown Health Centers• MPMS Hometown Health; Operational 10/11/2016.

• SHS Hometown Health; Operational 10/26/2016.

8SCSD Capital Project Update – 16th of November, 2016

MPMS SHS

Page 9: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT | Group D

• Phase 1B - CPMS – Roof Repairs / Exterior Masonry• Project 1 – Roof Repair

• Approved by SED.

• Substantial completion next week.

• Project 2 – Exterior Masonry Reconstruction

• Design in progress.

9SCSD Capital Project Update – 16th of November, 2016

Page 10: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT UPDATE| Long Range Planning

• 70MM – Phase I - Capital Project:

10SCSD Capital Project Update – 16th of November, 2016

Page 11: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT UPDATE| Long Range Planning

• LRP-2• $50 M +

• Elementary School focus

• Referendum Vote – May 2017

• Admin meetings to develop planning process.

11SCSD Capital Project Update – 16th of November, 2016

Page 12: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

12SCSD Capital Project Update – 16th of November, 2016

Page 13: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

CAPITAL PROJECT UPDATE| Next Steps & Milestones

• December 2016 Finish Phase 3 at MPMS and Phase 1 at VCES.

On-going construction at OMS & CPMS

• March 2017 Adopt Phase 2 plan – (Scope & Budget)

• May 2017 Phase 2 Referendum vote.

• Summer 2017 - Ongoing construction MPMS, HOWE, VCES &

Fall 2017 CPMS exterior.

• September 2017 Reopen HOWE ES.

• November 2017 Turnover VCES elevator.

13SCSD Capital Project Update – 16th of November, 2016

Page 14: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second

THANK YOU | Any Questions?

14SCSD Capital Project Update – 16th of November, 2016

OMS COMMONS