Upload
vrrindeh
View
236
Download
0
Embed Size (px)
Citation preview
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 1/80
SCHEME OF MINING
PART – I
CHAPTER-1.0
REVIEW OF MINING PLAN
1.1Name of Mine :
Metabodeli Iron ore mine over an area of 25 Ha.
Details of the Area:
State ChhattisgarhDistrict KankerTehsil PakhanjurForest Circle KankerForest Division Bhanupratappur (West)
Forest Range KoilibedaProtected Forest Kothodi Protected ForestVillage Metabodeli/ChargaonCompt. no. 426/1305 (7.5 Ha)
427/1306 (17.5 Ha)Ownership Protected Forest landToposheet no. 64 D/16Latitudes 200 02′ 21.96″ to 200 02′ 53.52″Longitudes 800 58′ 35.58″ to 800 59′ 09.12″
The Forest map is enclosed as Plate no. I.
Lease deed is enclosed as annexure-VI.
The Key plan is enclosed as location plan in Plate no. II.
The area is approachable from village Chargaon, SE of village a hill is at a
distance of 2 km. Chargaon is approachable by 25 km forest road from
Pondgaon, on Rajnandgaon-Durg-Rajhara-Bhanupratappur-Narayanpur-Jagdalpur
state highway. The nearest rail-head is Dalli-Rajhara at a distance of about 84
km.
Period for which the Mining Lease is granted:
HIG-21, Hudco colony Page 1 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 2/80
The Mining Lease is granted for a period of 20 years from 17/01/2002 to
16/01/2022.
1.2 Particulars of approval of Mining Plan (under MCR or MCDR, indicateapproval letter no and date)
The mining plan was approved by Indian Bureau of Mines, Nagpur vide letter No.
BST/Fe/MPLN-465/NGP dated 02-04-1996 and thereafter mining lease was
executed on 17/01/2002. Hence, the first five years of the Mining Plan was 2002-
03 to 2006-07. The subsequent Scheme of Mining for the period of 2007-08 to
2011-12 was approved by IBM Nagpur vide letter No. BST/Fe/MPLN-465/NGP
dated 24.11.2008.
1.3 Date of commencement of mining operations.
After the approval of the Mining Plan on 02/04/1996 and thereafter execution of
lease deed on 17/01/2002, the working permission was given by Collector on
28/06/2002, and mining operation started on 01/08/2002. But due to unforeseen
circumstances beyond the control of lessee, the mining operations could not be
started in full swing; as such, the proposed programme of development and
production, as mentioned in the approved mining plan/scheme of mining could
not be achieved.
1.4 (a.) Deficiencies, if any, that existed in the approved mining plan to betaken note of and rectified by incorporating suitable proposals forimplementation in the scheme of mining.
Due to naxalite problem in the vicinity of the area the targeted production as per
approved mining plan could not be achieved. Float ore in the area has been
collected looking to the condition of the area.
(b.) Review of compliance position of salient features of the Mining Plan onChapter wise basis bringing out marked deviations, if any, and
justifications / reasons thereof. Items to be covered may include
HIG-21, Hudco colony Page 2 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 3/80
exploration, mine development, exploitation, afforestation programme,reclamation & rehabilitation, control of dust, noise & ground vibrationsand any other significant feature.
Status of different parameters of mining plan vis-à-vis actual achieved
(i) Exploration:The details of the proposed programme during approved Mining Scheme period
(2007-08 to 2011-12) are given below:
YEAR ProposedBore Holes
Depth of Bore Holes Proposed Trial Pits(2.5x2.5x3.0)
2008-09 3 15.0m – 30.0m 32009-10 3 15.0m–30.0m & 60.0m 32010-11 2 15.0m–30.0m & 60.0m 2
Deviation:
In the approved Mining Plan and Scheme of Mining, eight numbers of trial pits
and eight numbers of bore holes were proposed in the area in a phase-wise
programme. Due to law and order problem (naxalite activities) exploration work
as proposed in approved mining plan could not be carried out.
(ii) Production:
Table: Float ore collection of graded iron ore during the Scheme of Mining period
(Year 2007-08 to 2011-12).
HIG-21, Hudco colony Page 3 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 4/80
Deviation:
Mining lease area is located in Naxal affected area and lot of efforts made by the
company the targeted production as per approved mining plan could not be
achieved, and only float ore has been collected.
(iii) Development of pit:
As per the approved scheme, the proposed pit size upto the end of the scheme
period will be 37,050 sq m. since, due to reasons mentioned above, the actual pit
size is only 250 sq m from the float ore was recovered.
(iv) Generation of soil/overburden:
Proposal inapproved scheme
Status of Compliance Reasons for deviations
There is nogeneration of topsoil/overburden,hence no provisionfor soil dump
No appreciable quantity of top soil is generated.
Not applicable
HIG-21, Hudco colony Page 4 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
Year Proposal givenfor approved
scheme of mining
Actual Productionof graded iron ore
Dispatchesfrom mine
2007-08 Nil 95.00 98.502008-09 49,875 T 100.00 10.202009-10 56,608 T 00.00 00.00
2010-11 59,850 T 00.00 00.002011-12 62,344 T 87.00 77.87Total 2,28,677 T 282.00 186.57
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 5/80
management.
(v) Afforestation Programme:
Table: Proposed and actual afforestation programme during the Scheme of Mining
Plan period (year 2007-08 to 2011-12).
Year Proposal inapprovedscheme
Status of Compliance
Reasons for deviations
2007-08 100 nos. Nil Due to naxal problem in the area
afforestation could not be done,
but outside the ML area
afforestation has been done.
2008-09 100 nos. Nil2009-10 100 nos. Nil
2010-11 100 nos. Nil2011-12 100 nos. Nil
However, the company has carried out plantation work in the vicinity of the lease
area and the details of afforestation carried out and cost incurred by the company
is tabulated below:
Year Name of Village No of sapling
Total costincluding other
expenses.2007-2008 --- 00.00 002008-2009 -- 00.00 002009-2010 Meerapara, Pondgaon,
Tehsil-Antagarh, Kanker1000 50,000
Chargaon Tehsil-Pakhanjore
1000 50,000
2010-2011 -- -- 002011-2012 Masbaras, Tehsil-Antagarh 2000 1,00,000Total 4,000 2,00,000
HIG-21, Hudco colony Page 5 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 6/80
(vi) Waste Management:
Proposal in approvedPlan/scheme
Status of Compliance Reasons for deviations
The generated wastematerial will bedumped as back fillingmanner.
No waste material has beengenerated.
Not applicable
(vii) Reclamation & Rehabilitation:
Proposal inapproved Plan
Status of Compliance Reasons for deviations
No proposal forreclamation
Reclamation was notrequired.
Not applicable.
(viii) Monitoring of Dust, Noise & Ground vibrations:
According to Environment protection Act, 1986, The Company has engaged
consultant M/s Enviro Analysists & Engineers Pvt Ltd., Mumbai to carry out
monitoring of Air, Water & Noise. The consultant has carried out monitoring and
analyzed the samples from surrounding the mine area. The report of the same is
enclosed as Annexure No. XI.
Since, only float ore has been collected from mine area and the mining activities
could not be done in full swing due to law & order problem, thus the impact on
environment due to mining activities is almost nil.
HIG-21, Hudco colony Page 6 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 7/80
(c.) Review of the compliance position of conditions and stipulation imposed,
if any, while approving the mining plan. In case of non-compliance /
partial compliance, detailed justifications / reasons thereof may be
furnished along with proposal for compliance in the ensuring period.
At the time of approval of Mining Plan no special conditions and stipulations were
imposed by the Indian Bureau of Mines, Nagpur.
The main condition imposed in the approval letter is that, the approval of mining
operations and associated activities are restricted to the mining lease area only.
(d.)Review of compliance of violations pointed out after inspections made
under MCDR, 1988 during last 5 years. The position emerging out of the
yearly review of the mining plans in the field shall also be taken note of
at this stage.No violations were pointed out after inspections made under MCDR, 1988 during
the last 5 years.
(e.) Any other points requiring attention in the interest of proper mine designdevelopment & conservation and environment & ecology of the area.
The development could not be undertaken due to the situations mentioned above,
hence proper mine design, development, conservation, environment & ecology of
the area could not be attended.
* * * * * * * *
HIG-21, Hudco colony Page 7 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 8/80
PART- II
CHAPTER-2.0
PROPOSAL UNDER SCHEME OF MINING FOR THE NEXT 5 YEARS
2.1 Name and Address of the Applicant:
GENERAL:
(a) Name of Lessee
Address
: M/S Jayaswal Neco Industries Ltd.F-8, MIDC, Hingna road,Nagpur (M.S.)-440016Corrospondence Address-Siltara Growth Centre, Siltara,Raipur (Chhattisgarh)-493111Phone – 07721- 264238 to 41Fax- 07721 264-270.
(b) Status of the Lessee : Public limited CompanyS.No.
Name of theBoard of
Directors
Designation Address Telephone no
01 Shri B.L. Shaw Chairman Usha sadan,246 Pt.R.S.S.marg, Civil Lines, NGP.
0712-2540298
02 Shri ArbindJayaswal
M.D. Usha sadan,246 Pt.R.S.S.marg, Civil Lines NGP.
0712-2540298
03 Shri RameshJayaswal
Jt. M.D. Usha sadan,246 Pt.R.S.S.marg, Civil Lines NGP.
0712-2540298
04 Shri B.K.Agrawal
Director 51, New Colony, ByramjiTown, NGP.
0712-2595959
05 Shri M.M.Vayas Director K-53, Marer Tower,CuffeParde, Mumbai
022-22832381
06 Shri P. K.Bhardwaj Director Plot No. 228 A, Flat No. 404,Rachana Sahil, T Point,Subhash Nagar, Nagpur
09371672229
07 Shri S.K.Sachdev
Director(IDBI)
H 53, Maker Kundan Garden,Juhu Tara Road, Santacruz
09969327982
HIG-21, Hudco colony Page 8 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 9/80
(W) Mumbai08 Shri Nirmit Ved Director
(EXIM)Export Import Bank of India,Maker Chambers IV,Nariman Point, Mumbai
09820350179
09 Shri ManishChaourasia
Director(ICICI)
Flate 206, Oberai Woods,Mohan Gokhale marg,Goregaon (E), Mumbai
09930063648
Certificate of Incorporation of the company is enclosed as Annexure No. II.
List of Board of Director is enclosed as Annexure No. III.
Mr. P. K. Bhardwaj is the nominated owner of the company; Board of Resolution is
enclosed as Annexure No. IV.
Photo ID proof of the nominated owner is enclosed as Annexure No. V.
2.2 Name and address, registration number of the recognized qualified
persons together with validity date/person employed under rule 42(1)(b) who has prepared the Mining Scheme:
Shalabh SahaHIG-21, Amdi Nagar, Hudco Sector, Bhilai,District- Durg (C.G.), Pin-490009Ph. No.- 0788-3299815 (O), 09425123191(M)Email – [email protected]
RQP/NGP/302/2003/A (valid upto – 2013.)
2.3 Mineral(s) to be mined. Iron ore
2.4 Area and date of expiry of lease. Area 25 Ha.
Date of expiry of lease – 16/01/2022.
2.5 Date of expiry of 5 years period for which was approved on the last
occasion.
The Scheme of Mining was approved for the period of 2007-08 to 2011-12.
Presently, the Scheme of Mining is being submitted for period from 2012 - 13 to
2016- 17.
HIG-21, Hudco colony Page 9 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 10/80
* * * * * * * *
CHAPTER-3.0
RESERVES
Topography:
In Metabodeli hill, the area of 25 Ha granted under M.L. represents a prominent
hilly topography with hill ranges trending North-East to South-West direction with
highest level of 578 m. The maximum contour level is 575 m in SW direction and
sloping towards all directions, minimum contour level is 425 m in northern
direction.
The topography of the ML area has been marked on the Surface Plan and enclosed
as Plate No. III.
Drainage:
Nearest drainage is Chargaon River towards S-E direction from the area with a
distance of 3 kms and Putunggori Nala towards northern part of the mine area
with a distance of about 2.5 Kms. The general drainage pattern of the area is
dendritic.
Regional Geology:
The regional geology of the area constitutes Archaean and Precambrian
formations represented by Bengpal group and Bailadila group respectively. The
Bengpal group comprises metasedimentary, ultramefic gabbro-anorthosites suite
of rocks. The granites are observed to be found in a predominantly gneissic area.
This group is co-related with Archaean high grade complexes.
HIG-21, Hudco colony Page 10 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 11/80
Bailadila group mainly comprises meta-sedimentary dominated by banded iron
formations, metabasics and granite which has been involved in poly-phase
deformations and green-schist to lower amphibolite grade metamorphism.
The geological succession of Iron ore deposit given by Datt (1963), Bulletin
Geological Survey of India is as follows:
TIME GROUP FORMATIONRecent Soil, high & low level laterites and
Float Iron ores
------------------- Unconformity--------------------------------------------Purana (Indravati Group) Sandstone
---------------------- Unconformity--------------------------------------------P
R
C
A
M
B
R
I
A
N
Narainpur Group Basic flow
Erosional Sandstone and
Conglomerate--------------------- Unconformity----------------------Bailadila Group Banded Iron ore formations, gray &
red shale and phyllites,chlorite schist--------------------- Unconformity----------------------Intrusives Quartz, aplite & pegmatite veins,
metabasic dykesBengpal Group Granite gneiss, migmatite & granite,
banded migmatite quartzite, tremolite
schist,
quartz mica schist, andalusite schist,
hornblend schist, and pyroxene
quartzites
-------------------------- Base not exposed--------------------------------
The plains and slopes are generally composed of granite-gneisses with enclaves of
meta-sedimentary and meta-volcanic sequence, commonly grouped under
Bengpal group.
HIG-21, Hudco colony Page 11 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 12/80
Structurally, the area is folded and cross-folded in antiforms and synforms. The
common trend of BHQ is almost NE-SW with moderately dipping towards SE,
rolling dips in BHQ are also observed.
Local Geology: The Metabodeli deposit is a prominent hill elongated in NE-SW
direction. The geological mapping conducted in the applied area, the stratigraphy
sequences are as under:
- Laterites, Soil and alluvium
- Canga and Iron-ore floats
- Insitu – massive/ laminated ore
- Banded Hematite Quartzite / Banded Magnetite Quartzite.
Float Ore:
The north-western slope is dominated by float ore covering an area of 8.80
hectares out of the total 25 hectares ML area. In most of the cases, the float ore
is observed to be embedded in the soil layer although the ore is also noticed as
recemented with laterite forming canga-ore.
Banded Hematite Quartzite:
BHQ is occurring in north-west direction in between the insitu ore and float ore.
BHQ is prominently marked forming interlayer of alternate bands of silica and
hematite of varying thickness from few mm to more than 10 mm. Being
resistance, they preserve most of the structural elements of bedding plane. The
area covering by BHQ zone is about 4 Ha.
Insitu Iron Ore:
The iron ore found in this area is mostly hematite and can be classified as massive
and laminated type of ore is found to occur on the top of the hill elongated N400S-
S400W to almost NE-SW, having strike length of about 1,100 m and width is
about 110 m. The general dip is observed to be about 400 SE. The ore occurring in
HIG-21, Hudco colony Page 12 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 13/80
this area is mainly hematite also containing magnetite and martite. The area
covering by insitu ore zone is about 12 Ha.
Lateritic Soil:
Lateritisation is a common phenomena noted in the area. Thinly laminated iron
ore are more prone to lateritisation. After lateritisation, they give rise to
lateritisated laminated and lateritic ore which is mostly found on the surface as
thin capping over laminated ores.
Some Canga ore is also noticed in very limited area. It is a broken pieces of hard
ores re-cemented in a lateritic matrix and presenting a brecciated look on the
surface.
3.1 Category wise (proved, probable and possible) reserves estimated in
the earlier mining plan with grade.
As per the earlier approved Scheme of Mining, the reserve of iron ore is as
under:
Category Reserves Insitu ore(Million Tonnes)
Float ore(Million Tonnes)
Total(Million Tonnes)
Proved MineralReserves
2.35 0.19 2.54
Probable MineralReserves 2.00 -- 2.00
Inferred MineralResources
2.16 -- 2.16
Total 6.51 0.19 6.70
The grade of iron ore available in the area as per approved Scheme of Mining is as
under:
Contents Insitu ore Float oreFe + 65 % + 65 %
Al2O3 0.73 % 0.62 %
HIG-21, Hudco colony Page 13 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 14/80
SiO2 1 % 0.75 %Phos. 0.008 % 0.03 % maxSulfur 0.006 % 0.01 % max
3.2 Depletion of reserve during the period of the Mining Plan.
Since only float ore has been collected and due to law and order problem in the
area the targeted production as per approved mining plan has not been achieved.
The mineral lifted from the mines is given in table below:
Due to naxalite activities in this region, the targeted production as per approved
scheme could not be achieved.
3.3 Additional Reserves established (with basis and parameter considered)during the period of Mining Plan.
HIG-21, Hudco colony Page 14 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
Year Actual Productionof float ore(tonnes)
2007-08 95.002008-09 100.00
2009-10 00.002010-11 00.002011-12 87.00Total 282.00
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 15/80
After the approval of the Mining Plan, no additional prospecting work was
conducted in the area, hence no additional reserve is established, only reserves
has been re-estimated and classified as per the UNFC norms.
3.4 Category wise updated reserve with grade (indicate end use grade withanalysis) as well as marginal grade.
The reserves and resources of iron ore for both insitu ore and float ore has now
been re-estimated and classified as per the UNFC norms.
Method of reserve estimation is as under:
For re-estimation of reserves, 10 cross-sections have been prepared at 100 m
interval. The proved thickness of the insitu ore has been considered as per the
bore-holes drilled during prospecting stage, since the bore-holes were not in
proper grid pattern this resources has been considered as Indicated Mineral
Resources (G-2) and below this depth further 5 m thickness of iron ore has been
taken as Inferred Mineral Resources (G-3).
The thickness of float ore has been considered as 3 m as per the Approved Mining
Plan/Scheme of Mining.
Estimation of Indicated Mineral Resources (UNFC code 332):
The area is already under mining lease of iron ore on the basis of prospecting
done, but bore-holes are not in proper grid pattern; the geological axis will come
under General Exploration (G-2).
This reserve has been considered as Indicated Mineral Resources (332 category)
as per the following criteria followed as per UNFC.
G2- Category:-
(i) The entire lease area has been covered by topographical-cum-geological
mapping with 100 m grid interval including all surface and geological features,
lithological extent, extent of mineralization, structures, location of pit,
boreholes, etc and the Surface Plan has been prepared on 1:2,000 scale with
contour interval of 5m and enclosed as Plate No. III.
HIG-21, Hudco colony Page 15 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 16/80
(ii) The study of the Regional Geology and Local geology has been carried out.
(iii) The geological mapping has been carried out in the entire lease area, properly
demarcating the lithological units between insitu ore zone, BHQ and float ore.
(iv)As per the geological mapping, insitu ore zone covers about 12 Ha area having
1,100 m length and width of about 110 m.
(v) The float ore zone covering about 8.80 Ha area upto average depth of 3 m.
(vi)The Geological Plan has been prepared on a scale of 1:2,000 and enclosed as
Plate No. IV.
(vii) Ten nos of cross-sections have been prepared in 100 m interval for the
reserve re-estimation on a scale of 1:2,000 (Enclosed as Plate No. IV A)
(viii) Four nos of inclined bore-holes were drilled during the prospecting period and
accordingly, the Mining Plan was approved.
(ix)The details of the bore-holes is as under:
BH Nos. Depth of bore
holes
(Inclined)
Thickness of
iron ore
(Inclined)
True thickness
of iron ore
(vertical)
BH-1 11.0 m 11.0 m 7.0 m
BH-2 20.0 m 17.5 m 11.0 mBH-3 35.0 m 35.0 m 17.5 m
BH-4 29.0 m 29.0 m 17.5 m
(x) On the basis of the bore-holes, the proved depth of the ore body has been
marked on the relevant cross-sections and accordingly the resource has been
re-estimated.
(xi)The chemical analyses of iron ore samples have been carried out by theLaboratory of the Directorate of geology and Mining, Jagdalpur, as per the
report Fe-content is 55-65%. The details of the report is as under:
HIG-21, Hudco colony Page 16 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 17/80
S.No.
Sample No
SiO2 % Fe2O3 % Al2O3 % TiO2 % LOI % Fe % Total
1 A 16.47 79.53 1.00 0.00 2.41 55.23 99.412 B 1.87 94.33 1.20 0.00 2.04 65.51 99.443 C 2.64 92.04 1.30 0.00 3.52 63.92 99.504 D 9.91 85.89 1.40 0.00 2.20 59.65 99.405 E 12.08 80.42 2.40 0.00 4.53 55.85 99.43
Copy of the Analysis Report is enclosed as Annexure No. XIII.
(xii) The Fe-content ranges from 55 to 65 % in the area, hence entire ore comes
above the threshold value.
(xiii) The bulk density of iron ore has been taken as 3.5.
(xiv) The physical characteristic of the iron ore of the area is colour- steel grey to
iron black, streak- cherry red, form- massive and laminated, lustre- metallic,
hardness- 5-6, sp. gr.- 4-5.
(xv) The thickness of float ore zone has been considered as 3 m.
(xvi)The recovery of the ore in float ore zone is taken as 25% of the total
excavated volume and the recovery in insitu ore zone is 90% of the total ROM.
(xvii) On the basis of above parameters, the reserves come under Indicated
Mineral Resources (332).
(xviii) The resources of insitu ore has been re-estimated as per the cross-
sectional method is as under:
SectionLine
CrossSectional Area(sq m)
Area of influence
(m)
Volume
(cu m)
B.D.
Resources(Tonnes)
NetResources
90%recovery
(tonnes)
C1-C1’ 735 150 1,10,250 3.5 3,85,875 3,47,288
C2-C2’ 990 100 99,000 3.5 3,46,500 3,11,850C3-C3’ 950 100 95,000 3.5 3,32,500 2,99,250C4-C4’ 1,425 100 1,42,500 3.5 4,98,750 4,48,875C5-C5’ 1,400 100 1,40,000 3.5 4,90,000 4,41,000C6-C6’ 2,230 100 2,23,000 3.5 7,80,500 7,02,450
HIG-21, Hudco colony Page 17 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 18/80
C7-C7’ 1,900 100 1,90,000 3.5 6,65,000 5,98,500C8-C8’ 1,640 100 1,64,000 3.5 5,74,000 5,16,600C9-C9’ 875 100 87,500 3.5 3,06,250 2,75,625C10-C10’ 1,400 150 2,10,000 3.5 7,35,000 6,61,500Total 13,545 1,100 14,61,250 -- 51,14,375 46,02,938
Say 4.60 million tonnes
(xix) The resources of float ore is as under: The surface area covered by float
ore is 88,000 sq m and average thickness has been taken as 3 m (as per the
approved Scheme of Mining) (categorized as G2).
Surface
area
(sq m)
Thickness
of float ore
zone (m)
Volume
(cu m)
Recovery of float oreboulders
25%of the total
volume
(cu m)
B.D Mineral
Resources
(Tonnes)
Mineral
Resources
(Million
tonnes)
88,000 3.0 2,64,000 66,000 3.5 2,31,000 0.23
Since inception, total production was carried out from the float ore zone only, andhence this has also been depleted from the float ore reserve. The mineral lifted
from the mines is given in table below:
HIG-21, Hudco colony Page 18 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
Year ActualProductionof float ore(tonnes)
Before 2007-08 842.002007-08 95.002008-09 100.00
2009-10 00.002010-11 00.002011-12 87.00Total 1,124.00
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 19/80
Thus, total balance float ore is 2,31,000 – 1,124 = 2,29,876 tonnes (0.23
million tonnes).
Estimation of Inferred Mineral Resources (UNFC code 333):
Below the proved depth of the iron ore, further 5 m thickness of ore has been
considered under this resources.Resources of insitu ore has been re-estimated as per the cross-sectional
method is as under:
HIG-21, Hudco colony Page 19 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 20/80
SectionLine
CrossSectional Area(sq m)
Area of influence
(m)
Volume
(cu m)
B.D.
Resources(Tonnes)
NetResources
90%recovery
(tonnes)
C1-C1’ 502 150 75,300 3.5 2,63,550 2,37,195
C2-C2’ 681 100 68,100 3.5 2,38,350 2,14,515C3-C3’ 656 100 65,600 3.5 2,29,600 2,06,640C4-C4’ 0 100 0 3.5 0 0C5-C5’ 0 100 0 3.5 0 0C6-C6’ 569 100 56,900 3.5 1,99,150 1,79,235C7-C7’ 450 100 45,000 3.5 1,57,500 1,41,750C8-C8’ 398 100 39,800 3.5 1,39,300 1,25,370C9-C9’ 200 100 20,000 3.5 70,000 63,000C10-C10’ 334 150 50,100 3.5 1,75,350 1,57,815Total 3,790 1,100 4,20,800 -- 14,72,800 13,25,520
Say 1.33 million tonnes
Thus, total Iron-ore Resources are as under:
Category ResourcesTonnes Million Tonnes
Indicated Mineral Resources (332)Insitu-ore 46,02,938 4.60Float ore 2,29,876 0.23Total 48,32,814 4.83Inferred Mineral Resources (333)Insitu-ore 13,25,520 1.33Total 61,58,334 6.16
Estimation of Blocked out Reserves within the 7.5 m of non-mining zone
and due to pit slopes (Pre-Feasibility Mineral Resources 222):
After the estimation of Indicated Mineral Resources (332) as above, an exercise
has been done to bifurcate the Indicated Mineral Resources under Proved
Mineral Reserves – UNFC Code (111) for the mineable part of the mineral
resources which fall within the Ultimate Pit Limit (UPL) and is above the threshold
value of +45 % Fe-content, after conducting a Pre-Feasibility Study and Economic
Viability of the mine; and under Pre-Feasibility Mineral Resources – UNFC
Code (222) for the remaining part of the resources which either fall outside the
UPL within the statutory barrier becoming non mineable.
HIG-21, Hudco colony Page 20 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 21/80
Before exercising the above mentioned bifurcation a Pre-Feasibility Study has
been done as per the guidelines given in the MCDR 1988 and circulars issued by
the IBM (Pre-feasibility Report is enclosed as Annexure No. XV).
The Blocked out insitu ore within 7.5 m non-mining zone and due to pit
slope is as under: Section
LineCross Sectional
Area(sq m)
Area of influence
(m)
Volume
(cu m)
B.D.
Resources(Tonnes)
7.5 Pitslop
e
Total
C1-C1’ 53 8 61 150 9,150 3.5 32,025C2-C2’ 53 10 63 100 6,300 3.5 22,050C3-C3’ 53 9 62 100 6,200 3.5 21,700C4-C4’ 83 32 115 100 11,500 3.5 40,250C5-C5’ 87 30 117 100 11,700 3.5 40,950
C6-C6’ 142 97 239 100 23,900 3.5 83,650C7-C7’ 155 103 258 100 25,800 3.5 90,300C8-C8’ 134 95 229 100 22,900 3.5 80,150C9-C9’ 132 109 241 100 24,100 3.5 84,350C10-C10’ 138 120 258 150 38,700 3.5 1,35,450Total -- -- -- 1,100 1,80,250 -- 6,30,875
Say 0.631 million tonnes
Blocked out resources of float ore within the 7.5 m of non-mining zone is
as under:
Surface
area
(sq m)
Thickness
of float ore
zone (m)
Volume
(cu m)
Recovery of float oreboulders
25%of the total
volume(cu m)
B.D Mineral
Resources
(Tonnes)
Mineral
Resources
(Million
tonnes)
10,200 3.0 30,600 7,650 3.5 26,775 0.027
Thus, total blocked out Iron-ore Resources are as under:
Category ResourcesTonnes Million Tonnes
Pre-Feasibility Mineral Resources (222)
HIG-21, Hudco colony Page 21 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 22/80
Insitu-ore 6,30,875 0.631Float ore 26,775 0.027Total 6,57,650 0.658
The Reserves and Remaining Resources of iron ore after pre-feasibility study (F2)
estimated and estimation of blocked out resources are as under:
Thus, total Iron-ore Resources are as under:
Category Indicated
Mineral
Resources
(332)
Million
Tonnes
Pre-Feasibility
Mineral
Resources
(222)
Million
Tonnes
Probable
Mineral
Reserve
(122)
Million Tonnes
Insitu-ore 4.60 0.631 3.969Float ore 0.23 0.027 0.203Total 4.83 0.658 4.172Inferred Mineral Resources (333) Million TonnesInsitu-ore 1.33 -- --G. Total 6.16 -- --
HIG-21, Hudco colony Page 22 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 23/80
Total Reserves and Resource estimation table as per UNFC:
Classification Cod
e
Quantity
(million
tonnes)
Grade
Total Mineral Resources (A+B) 6.16 Fe 55-65%A.MineralReserve
(1) Proved Mineral Reserve 111---
---
(2) Probable Mineral Reserve 121---
---
(3) Probable Mineral Reserve 1224.172
---
B.RemainingResources
(1) Feasibility Mineral Resources 211---
---
(2) Prefeasibility Mineral Resources 221---
---
(3) Prefeasibility Mineral Resources 222 0.658 ---
(4) Measured Mineral Resources 331---
---
(5) Indicated Mineral Resources 332---
---
(6) Inferred Mineral Resources 3331.33
---
(7) Reconnaissance MineralResources
334---
---
Anticipated Life:
HIG-21, Hudco colony Page 23 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 24/80
On the basis of the mineable reserve of 4.172 tonnes and annual proposed
production rate of about 0.2 million tonnes, the anticipated life of the mine will be
about 20.86 years (say 21 years).
3.5 Year wise Exploration proposed to be carried out during the ensuing 5years period. Location of trial pits and/or boreholes to be depicted onthe geological plan.
The proposed exploration programme will be as under:
25 nos. of vertical bore holes have been proposed during the first year of the
scheme period at about 100 m grid interval, hence all the Insitu ore zone will
comes under proved category. In first phase bore-holes will be carried out on
strike length at about 100 m interval, thereafter, in second phase, bore-holes will
be carried out in about 50 m interval for confirming the quality of ore in dip
direction.
In the float ore zone, 24 trial pits have been proposed during the first year atabout 100 x 100 m interval to ascertain the recovery of float ore.
To know the quality of BHQ (Fe- content) as per the threshold value of minimum
45% Fe-content, 5 nos. of trenches have been proposed during the first year.
Hence, the iron ore reserves of almost the lease area will be proved during the
first year of the mining plan period. The quantity and quality of the BHQ area will
be estimated as per the analyses report of trenches.
The locations of PBHs, PTPs and PTTs are marked on the Geological Plan and
sections given in plate nos.-IV & IV A. The details are given below:
Proposal Nos Patternsize
Depth andsize
Diam of core
Type of working
Proposed costof work
HIG-21, Hudco colony Page 24 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 25/80
Bore-holes
25 100 x 100 30 m 45 mmDiamond
core drilling ` 18,75,000
trial pit 24 100 x 100 2 x 2 x 3 m -- -- ` 1,20,000Trialtrenches
5 -- 5 x 2 x 2 -- --` 35,000
Total ` 19,95,000
* * * * * * * *
CHAPTER-4.0
CONCEPTUAL MINING PLAN
Salient features of an updated/modified conceptual plan of the mine
covering the period of anticipated life of the mine, depicted on minegeological plans and sections with necessary statement annexedsupported by essential text, covering the basic & long term designfeatures of mine covering exploration, mine development, optimumexploration & utilization of the mineral, waste & sub-grade mineralmanagement, and environmental aspects. The ensuring five year detailedprogramme should but be a part of the conceptual overall mining plan.
The total lease area is 2,50,000 sqm (25 Ha). The workable area for mining will be
1,86,800 sq m (1,09,000 sq m in insitu ore + 77,800 sq m in float ore).
Out of which float ore area will be filled back, after ascertaining the non
mineralized area, with the generated waste material and ultimate pit will be about
1,09,000 sq m.
(i) Time frame of completion of mineral exploration programme in the
lease, with broad description identifying the potential area to be covered
in the given time frame.
The entire lease area will be explored as per the exploration proposed in Para 3.5
and thereafter no further exploration is required. This has been described indetails in para 3.5.
HIG-21, Hudco colony Page 25 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 26/80
(ii) Whether ultimate pit limit has been determined and demarcated on
the surface and geological plan.
The workable area for mining will be 1,84,000 sq m (1,09,000 sq m in insitu ore
+ 75,000 sq m in float ore).
Presently, about 250 sq m area covered under pit.
During this Scheme period, the pit size will be 22,800 sq m area, out of which the
mined out float ore area will be almost utilized for dumping the waste material on
footwall side.
The ultimate pit limit will covered all the in-situ ore bearing area, which is about
1,09,000 sq m.
(iii) Whether the site for disposal of waste rock and unsaleable ores has
been examined for adequacy of land and suitability of long term use in theevent of continuation of mining activity.
During the first five year of this scheme period, the waste material will be dumped
on the mined out float ore zone on footwall side, after the fully exhaustion of the
float ore and confirmation of not encountering the BHQ below the float ore.
During the first year of scheme period complete exploration will be done
delineating the shape and size of ore body and also the proved reserve and
accordingly the selection of waste dump area will be selected.
After this first five years, during the mining of insitu ore there will be no
generation of waste.
Hence, no additional area will be required for this dumping.
(iv) Whether back filling of pits after recovery of mineral upto techno-
economically feasible depth envisaged. If so describe the broad features
of the proposal.
The waste material generated during first year mining of float ore will be about
75% of the total excavation. This will be filled back in the fully excavated float ore
area so as to original surface level will be obtained.
HIG-21, Hudco colony Page 26 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 27/80
During conceptual period, the entire waste material of float ore zone will be filled
back in the fully excavated float ore area.
After leveling the float ore area, the entire area will be covered by plantation.
(v) Final slope of the faces.
The slope of the mining faces will be about 450 which will be sufficiently stable.
(vi) Afforestation.
1. The plateau slope after fully mining the ore will be taken up for plantation at a
spacing of 3 m x 3m in the entire area.
2. Plantation will be carried out on backfilled float ore area.
(vii) Post mining land use envisaged.
Description Area in sq mPresent End of the 5 year
schemeEnd of theconceptualperiod
1 Area under Pits250
250 + 22,800 =23,050
1,09,000
2 Area under roads 6,600 6,600 Nil3 Area under
Infrastructure100 1,100 Nil
4 Area undersoil/waste Dump
Nil Nil Nil
5 Area underStorage of ore
Nil 1,000 Nil
6 Area under crusher Nil Nil Nil7 Area under
magazineNil Nil Nil
8 Area underPlantation
Nil 5,000 2,50,000
Total 6,950 36,750 2,50,000
Conceptual Plan is enclosed as Plate no.-IX and sections are as Plate no.-IX A.
* * * * * * * *
HIG-21, Hudco colony Page 27 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 28/80
CHAPTER-5.0
MINING:
5.1 Salient description of the present Mining method.
As indicated in the approved scheme of mining, the mining operations will be
carried out by semi-mechanized opencast method categorized as “OTFM” under
category ‘A’, with development of regular benches of 5 m height for mining the
insitu ore zone. There is very thin capping of lateritic soil at some places, which
does not require removal. The development of quarry faces shall be made through
deployment of wagon drills of 63 mm dia for drilling and sub-sequent blasting. The
oversized boulders will be manually broken to loadable size and thereafter, loaded
by shovel / excavator into dumpers (15 T) and transported from quarry to the
temporarily stock yard on back-filled area by haulage road having 1:16 gradient as
indicated in the Development & Production plan.
The float ore occurring on the NW slope of the ore body and it is proposed to
mined out extreme northern portion during the first year. The excavation of float
ore area will be carried out by the shovel fitted with ripper. The recovery of float
ore is expected to the 25 % of the excavation and rest 75 % will be waste
(comprising of lateritic soil). After winning the float ore, the waste material will be
filled back in the excavated pit by dozer. The float ore collected by manual labour
will be dozed to form a heap so that it can be loaded by shovel into 15 T dumpers
for transportation to the steel plant.
The entire ore is above the threshold value of 45% Fe, hence there will be noreject. The entire mined out ore is of acceptable grade and there will be
HIG-21, Hudco colony Page 28 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 29/80
generation of sub-grade ore. The quality of the acceptable grade ore will vary
from 55% Fe to 65% Fe, the average being 63% Fe.
Form the second year onwards, the mining of ore zone will be carried out by top
slicing method. The mining block will be drilling by wagon drill upto 5.5 m depth
to avoid toe formation for a bench height of 5.0m.
After drilling and blasting, big boulders encountered in the blasted mass will be
reduced to loadable size (200-250mm) by manual labour. The sized ore will be
loaded by 2 m3 capacity shovel into 15 tonner tippers and temporarily stocked in
back-filled area for further sorting and sizing. Thereafter, ore will be transported
by separate trucks to the Steel Plant at Siltara, Raipur.
The proposed exploration will be carried out during the first year (2012-13) of the
scheme of mining period, if required, continuing upto second year (2013-14).
5.2 Yearly pit-wise development plan proposal for the next five years,
depicted on plans and sections (ore and overburden to be shown clearly
along with geological formations encountered depicted also the design
and layout of the mine benches in case of opencast mining).
Similarly proposals for development and/or stoping for underground
workings, year-wise, for next five years.
(a) In the ore zone, the overburden in the form of lateritic soil occurring as very
thin capping at places, hence no development is required during the mining
of iron ore. Thus, the generation of overburden will be nil.
(b) The ROM will undergo atleast two handlings and some quantity of finer
fractions will remain at quarry and other losses, it is expected that the
mining and handling loss will be about 10%.
(c) The iron ore quality is suitable for Blast furnace, Sponge iron plant, sintering
plant and pellet plant, hence, there will be no generation of sub-grade ore.
However, if any sub-grade ore is encountered, it will get blended during the
mining.
(d) In the float ore zone, after the recovery of entire float ore, the entire waste
will be dozed to the already excavated area.
HIG-21, Hudco colony Page 29 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 30/80
As already stated above, no development is required for mining of insitu ore.
5.3 Year wise production plan proposal for next five years along with grade.Blending proposal, if any, may be indicated.
Year-wise production of Marketable/Saleable ore and Rejects / waste for
Float ore (First year 2012-13):
YEAR Areamined(Sq m)
Depth(m)
Float oremixedwith
wasteROM
(cum)
Recoveryof float
ore25% of
ROM(cum)
T F ROM(Tonnes)
Waste75% of
ROM(cum)
2012-2013 10,000 3 m 30,000 7,500 3.5 26,250 22,500
Total 10,000 3 m 30,000 7,500 3.5 26,250 22,500
First Year (2012-13) Development and Production:
During the first year, the proposed exploration (bore-holes, pitting and trenching)
will be taken up on priority.
During this year, the mining will be restricted to float ore zone upto 3m depth, in
the northern slope of the area.
During this period about 10,000 sq. m area in float ore with 3.0 m depth will be
excavated. With 25% recovery of float ore and 3.5 tonnage factor (10,000 x 3 x
0.25 x 3.5 = 26,250 tonnes of float ore will be recovered. The big boulders of float
ore will be broken to handlable size.
The balance 75% material will be waste. The entire generation of waste will be
fully utilized for the back-filling the mined out float ore zone. This back-filled area
will be utilized for temporary stock yard.
HIG-21, Hudco colony Page 30 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 31/80
Year-wise production for Insitu ore (II year to V year):
YEAR Benchlevel
BenchHt.(m)
Areamined(Sq m)
VolumeROM
(cum)
B.D ROM(Tonnes)
Recovery of ore
90%of ROM
Mining/handling
loss 10% oROM
(T)
2013-2014
Hill topabove575
1 m 3,900 3,900
3.5 81,900 73,710 8,190
575 –570 5 m 3,900 19,500
-- 6 m 3,900 23,400
2014-2015
570-565
5 m 7,520 37,600
3.5 2,15,600 1,94,040 21,560
565
-560 5 m 4,800 24,000
--10 m 12,320 61,600
2015-2016
570-565 5 m 7,600 38,000
3.5 2,24,000 2,01,600 22,400
565-560
5 m 5,200 26,000
--10 m 12,800 64,000
2016-
2017
565
-560 5 m 12,800 64,000 3.5 2,24,000 2,01,600 22,400
TotalUpto560
-- 12,800 2,13,000 -- 7,45,500 6,70,950 74,550
HIG-21, Hudco colony Page 31 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 32/80
Second Year (2013-14) Development and Production:
During the second year onwards, the mining will be carried out on insitu ore zone.
The mining will be done in the two benches, first bench will be av 1.0 m height
upto a level of 575 mRL to liquidate the mound-shaped topography. The area of
excavation for ROM mining of ore will be about 3,900 sqm. The volume of ROM will
be 3,900 x 1 = 3,900 cum. The second bench will be from 575 to 570 mRL. The
area of excavation for ROM mining of ore will be about 3,900 sqm. The volume of
ROM will be 3,900 x 5 = 19,500 cum. Total ROM will be 3,900 + 19,500 = 23,400
cu m, thus the production will be 23,400 cum ×3.5 = 81,900 T, out of this, 90%
will be recovered ore will be 73,710 T.
Third Year (2014-15) Development and Production:
During this year, the mining will be carried out in the two benches of 5 m each. Infirst bench, mining will be carried out towards north-eastern direction from 570 to
565 mRL. The area of excavation for ROM mining of ore will be about 7,520 sqm.
The volume of ROM will be 7,520 x 5 = 37,600 cum.
The second bench mining will be carried out below this production, from 565 to
560 mRL. The area of excavation for ROM mining of ore will be about 4,800 sqm.
The volume of ROM will be 4,800 x 5 = 24,000 cum.
Total ROM production will be 61,600 cum × 3.5 = 2,15,600 T, out of this, 90% will
be recovered ore i.e. 1,94,040 T which will be graded production of this year.
Fourth Year (2015-16) Development and Production:
During this year, the mining will be carried out in the two benches of 5 m each. In
first bench, mining will be carried out towards south-western direction from 570 to
565 mRL. The area of excavation for ROM mining of ore will be about 7,600 sqm.
The volume of ROM will be 7,600 x 5 = 38,000 cum.
The second bench mining will be carried out below this production, from 565 to
560 mRL. The area of excavation for ROM mining of ore will be about 4,800 sqm.
The volume of ROM will be 5,200 x 5 = 26,000 cum.
HIG-21, Hudco colony Page 32 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 33/80
Total ROM production will be 64,000 cum × 3.5 = 2,24,000 T, out of this, 90% will
be recovered ore i.e. 2,01,600 T which will be graded production of this year.
Fifth Year (2016-17) Development and Production:
During this year, mining of ore will carried out further eastern direction from the
fourth year production, from 565 m which will go down upto a contour of 560 m in
bench height of 5 m. The total area of excavation for ROM mining of ore will be
about 12,800 sqm and volume will be 12,800 x 5 = 64,000 cum × 3.5 = 2,24,000
T, out of this, 90% will be recovered ore i.e. 2,01,600 T which will be graded
production of this year.
Year wise Production of iron ore will be as under:
YEARS Workingarea
ROMvolume
M3
Iron oreproduction
(T)
Ratio of ROM:Mineralised
ore2012-2013
Float oreMining
30,000 26,250 1 : 0.25
2013-2014
Insitu oreMining
23,400 73,710 1 : 0.90
2014-2015
Insitu oreMining
61,600 194,040 1 : 0.90
2015-2016 Insitu oreMining 61,600 201,600 1 : 0.90
2016-2017
Insitu oreMining
64,000 201,600 1 : 0.90
Total 2,40,600 6,97,200 ---
The year-wise balance reserve of iron ore will be as under:
Year Reserve(Milliontonnes)
Production(Milliontonnes)
Balance reserve(Million tonnes)
2012-13 4.172 0.026250 4.145750
HIG-21, Hudco colony Page 33 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 34/80
2013-14 4.145750 0.073710 4.072040
2014-15 4.072040 0.194040 3.878000
2015-16 3.878000 0.201600 3.676400
2016-17 3.676400 0.201600 3.474800
5.4 Any changes in the proposed method of Mining and development of machinery, together with reasons thereof.
The proposed method of mining will fall under Other Than Fully Mechanized
(OTFM).
Salient features of Mining:
1 Type of ore to be mined out Iron ore
2 Method of Mining OTFM3 Machineries used Wagon drills, shovel, dumpers4 Production max. (in a year) 2,00,000 T5 Average working days in a year 300 days
Drilling:
The holes will be drilled by wagon drill of 63 mm dia will be as below.
Maximum Production/year 2,00,000 TProduction/ development in a day
(by taking 300 working days in a year) 666.66 TSay 667 T
Output per hole = Spacing × burden × depth.
2.4 m × 2.2 m × 5 m 26.4 cumROM tonnes (3.5 B.D.) 92.5 TNos. of holes per day (667 / 92.5 ) 7.21 nos.
Say 7 nos.Meterage to be drilled on ore zone for 5 m bench
(5.5 m including sub-grade drilling) (7 × 5.5) 38.5 m
HIG-21, Hudco colony Page 34 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 35/80
Drilling capacity of wagon drill in a hour 6 mWorking hours per day taking utilization 50% 4 hoursWorking capacity of a wagon drill per day 6 × 4 m 24 mTherefore Nos of wagon drill required
(38.5 / 24 = 1.60, say 2) 2 no.
Blasting
For proposed production, blasting of 2 holes/day will be required. The drilling and
blasting will be done in single/multiple row pattern. Blasting will be done once in
a week depending upon the requirement.
Broad blasting parameters for 63 mm dia. wagon drill as per standard norms:
Diameter of wagon drill holes 63 mmDiameter of the cartridge 50 mmLength of the cartridge 220 mmWeight of the cartridge 625 gmCharge per hole cartridge 8.75 kgNo. of cartridge required per hole (8.75 kg /625 gm) 14 nosDelay detonator electrical 1 noSafety fuse (1.20 length) 1 noNo. of holes required to be blasted /day 2 nosExplosive required per day will be 2 x 8.75 = 17.5 kgPowder factor per kg of explosive
(92.5 / 8.75 = 10.57) About 10 TNote:
(i) For achieving 667 tonnes excavation per day drilling & blasting with delay
detonators of 7 holes ones/twice in a week will be required.
(ii) The blasting will be carried out around 7 AM or during the rest hours of 2 to
2.30 PM for safety.
(iii) Preferably wet drilling will be done for suppressing dust and muffle blasting
for suppression of noise will be carried out.
(iv) All precautions for blasting and safety measures will be taken at the time of blasting and will be carried out by qualified/certified blaster.
HIG-21, Hudco colony Page 35 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 36/80
(v) During blasting, the safety zone of 750 m will be barricaded by red flags so
that unauthorized entry in the blasting zone is checked.
(vi) Blasting if carried out in mid day (2 to 2.30 PM), all the workers should take
safety shed and blasting should carried out under the supervision of Mining
Forman/Safety Engineer.
(vii) Blasting parameters are to be optimized by experimenting and to be
implemented accordingly.
(viii) All safety measures as stipulated in MMR 1961 will be strictly adhered to
during blasting.
Whether secondary blasting is needed, if so, describe it briefly.
No secondary drilling will be required. The oversize boulders will be further
reduced to loadable size by manual labour.
Loading, Haulage and Transporting:
The loadable sized ROM will be transported to the stock yard by shovel-dumper
combination for further processing.
Requirement of shovel is as under:
Annual Excavation 2,00,000 TExcavation per day (based on 300 wrg days) 667 TBucket capacity of 2 cum
Safe Loading capacity (90%) 1.8 cumSay 1.8 x 2 (B.D. for ROM) i.e. 3.6 TOne excavator can load per hour takingavailability of 4 hours / day (50 %)Loading cycle time of excavator into 15 Tdumper will be about 15 minutes. Thereforein one hour a shovel can load 4 dumpers i.e.4 x 12 T(safe loading capacity of dumper) =
48 T
One excavator can load per day taking 4
hours utilization 48 x 4
192 T
Nos. of excavator required for loading
(667/192 = 3.47)
Say 4 nos.
Requirement of dumper is as under:
Annual production 2,00,000 T
HIG-21, Hudco colony Page 36 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 37/80
Production per day (based on 300 wkg days) 667 TDumper capacity 15 TDumper capacity as safe loading (80%) 12 TNo. of trips required per day (667/12=55.58)say 56 nosTotal time taken for spotting, loading,
transporting from quarry to stock yard (distance
1.0 km), unloading at stock yard and back to the
quarry.
1hour
Availability 65%Utilization 70%Effective hours per day 8 × 0.65 × 0.70 3.64 hourHence, one dumper can make 3.64 trips in a day Say 4 tripsNo. of dumpers required (56/4) 14 nosAdditional dumper required as standby 6 nos.Hence, total dumpers required will be 14+6 20 nos.
Machineries required is as under:
S
No
Machinery Capacity Nos.
required
Mode
1 Wagon drill 63 mm dia 2 no. For drilling2 Dozer Medium 1 no. For dozing and leveling the
HIG-21, Hudco colony Page 37 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 38/80
size surface for blasting for
movement of wagon drill.
For dozing the float ore and
making a pile for shovel
loading and backfilling the
mined out float ore.3 Shovel with
ripperarrangement
2 cum 4 no. For loading of ore into
dumper
5 Dumper 15 tonner 20 nos Transporting of ore to stock
yard6 Water tanker 10,000 lit. 1 no sprinkling the water on
haulage road for dustsuppression
7 Water tanker 10,000 lit. 1 no Drinking water supply
Employment Potential
S.No.
Man power No.
1 Mines Manager First class certificateholder
01
2 Geologist M. Sc. Geology 013 Mining Foreman (certificate holder) 02
HIG-21, Hudco colony Page 38 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 39/80
4 Mining Mate (certificate holder) 025 Supervisor Experienced 036 Accountant Experienced 017 Blaster (certificate holder) 028 Blasting assistant Experienced 029 Senior mechanic Experienced 0110 Mechanical fitter Experienced 0211 Driller Experienced 0213 Dumper operator Experienced 2015 First Aider Qualified 0116 Helpers for equipments Skilled 1017 Time keeper --- 0118 Watch man for 2 shifts --- 0419 Semi-skilled labour for
sorting and sizing of ROM
Semi-Skilled 150
Total 205
Note: The semi-skilled/un-skilled labour will be required for recovery of float ore
boulders from the excavated mass by ripper fitted in shovel and reduction of
oversize boulders in float ore and blasted ROM and further sizing & sorting of ore
before transporting to the plant at the stock yard.
* * * * * * * *
CHAPTER-6.0
HANDLING OF WASTE / SUB- GRADE MATERIAL:
6.1 Rate of yearly generation of waste and Proposal for disposal of waste fornext five years (indicate sequence of dumping with necessary plans andsections).
HIG-21, Hudco colony Page 39 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 40/80
In the mining lease area, which is hilly in nature, where insitu ore is occurring, the
lateritic soil is occurring as very thin cap in some part of the area excluding the
float ore zone. Therefore, the removal of top soil for mining insitu ore is not
necessary.
In the float ore zone, the float ore is occurring with lateritic soil upto a depth of
about 3 m, wherein the recovery of float ore boulders will be about 25% and the
rest 75% of lateritic soil will be restored back into the excavated area by dozing.
The yearly generation of waste material is as under:
Year Volume of intercalated waste
(M3)
Remarks
2012-13 22,500 Volume of intercalated waste(soil mixed with laterite, intercalated
material) 75% of the excavation.Total 22,500
Note: From II year onwards there will be no generation of waste/intercalated
waste, since the mining will be confined to the insitu ore zone.
6.1.1Build up of dumps from year to year to be shown in yearly plans andsections with description of the method & manner of disposal of wasterock, designed capacity & height of individual dump and precautionsenvisaged for confinement of the dumps together with design details of
the protective works.
HIG-21, Hudco colony Page 40 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 41/80
After the float ore is mined out, the area will be concurrently backfilled by the
generated waste material. Hence, the entire waste generated during first year will
be fully utilized for backfilling the excavated area.
Hence, there will be no waste dump generated during this Scheme of Mining
period.
6.2 Rate of yearly generation of sub-grade mineral with reference tothreshold values and Proposal for stacking for next five years (submittednecessary plans and sections). (In case variation from the recommendedthreshold value of IBM, please give adequate justification and reasons).
The sub-grade material above the threshold value will be hardly 5% of the total
ROM which is below 58% Fe, which will get blended with the high grade ore.
Hence, generation of sub-grade ore will be nil.
6.3 Quantity and grade of sub-grade material available at the mine as ondate duly supported by plans and sections and descriptive inclusive of the precautions adopted for storage.
The sub-grade material will be fully blended with the higher grade ore, therefore
no sub-grade material will be available at the mine.
* * * * * * * *
CHAPTER-7.0
USE OF MINERAL
7.1 Changes proposed in use of mineral if any with reasons.
HIG-21, Hudco colony Page 41 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 42/80
The ore of Metabodeli mine will be used for blast furnace and sintering plant of the
company at Siltara, District- Raipur.
In order to utilized entire iron ore that will be produced from the other mines, the
company is proposing to set up a Pellet plant with a proposed capacity of 1.2 MTPA
and Beneficiation plant at their plant premises. The lessee is also proposing a
beneficiation plant in Bhanupratappur for up-gradation of ore produced from other
nearby mines in view of total utilization of sub-grade ore. Hence, entire iron ore
produced in his other mines will be utilized in steel plant of the company.
7.2 Changes in the specifications, if any, imposed by the user industriesand /or specifications required in case of new user industries, if any, tobe given.
The specification of iron ore at present for various units of company’s integrated
steel plant is given as under:
• For Blast Furnace----+ 62% Fe content in the size of 20-40 mm
• For DRI (Sponge Iron Plant)--+ 63% Fe content in the size of 8 to 20 mm.
• For Sinter Plant--- + 59% Fe content in the size of 5 to 8mm.
• For Pellet plant---- + 64% in the size of 0 to 5 mm.
In the crushing and screening plant at Siltara, after the crushing to maximum 40
mm size, the lumps (8 mm-40 mm) is expected to be about 60% and the
remaining -8 mm fraction in the form of fines will be about 40%.Ore below 58% Fe-content shall be upgraded in Beneficiation plant proposed at
Bhanupratappur and shall be utilized in the pellet plant.
Recently, 5 iron ore samples the Metabodeli mine have been analysed by the
laboratory of Directorate of geology and Mining, Jagdalpur, which is tabulated
below:
S.No.
Sample No
SiO2 % Fe2O3 % Al2O3 % TiO2 % LOI % Fe % Total
1 A 16.47 79.53 1.00 0.00 2.41 55.23 99.41
HIG-21, Hudco colony Page 42 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 43/80
2 B 1.87 94.33 1.20 0.00 2.04 65.51 99.443 C 2.64 92.04 1.30 0.00 3.52 63.92 99.504 D 9.91 85.89 1.40 0.00 2.20 59.65 99.405 E 12.08 80.42 2.40 0.00 4.53 55.85 99.43
Copy of the Analysis Report is enclosed as Annexure No. XIII.
7.3 Efforts made for utilization of the Sub-Grade mineral including fines.
The sub-grade ore will get automatically blended with high-grade ore to maintain
the quality specification required by the Steel plant.
* * * * * * * *
CHAPTER-8.0
MINERAL BENEFICIATION
8.1 Results of any beneficiation investigations conducted and changes madein existing mineral beneficiation plant and tailing disposals, if any, withbenefits expected (necessary flow-sheet and tailing dam designs etc. tobe submitted as applicable).
HIG-21, Hudco colony Page 43 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 44/80
No Beneficiation is required for this ore. The beneficiation process normally
involves sorting, sizing and blending at the mine site. The quality of ore fulfills the
specification required for the blast furnace; hence no additional beneficiation is
required.
At present beneficiation investigation has not been carried out. As soon as mine is
developed in full fledge, the detailed beneficiation test, if required, will be carried
out. At present the quality of ore fulfills the specification required for the blast
furnace as well as DRI; hence no beneficiation is required for ore produced from
this mine.
8.2 Beneficiation test done, if any, on sub-grade mineral including fines andproposals for installation of new or additional beneficiation facility, if any, (furnish process details in brief along with expected tailing loss).
Not applicable.
* * * * * * * *
CHAPTER-9.0
ENVIRONMENT MANAGEMENT PLAN:
1 2 3 4Salient items to
be coveredUnder columnnos.2,3 & 4 areas under
Proposals as
per approvedmining plan(indicate dateof approval of scheme of
Position at the
end of 5 year of scheme period(justification tobe given formarked
Proposal for the next 5
year scheme period
HIG-21, Hudco colony Page 44 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 45/80
mining)BST/Fe/MPLN-466/NGP dated24.11.2008.
derivation)
(i) Top soilstorage,preservation & utilization
No generation of top soil duringthe schememining period.
Not working. No top soil will begenerated in this SOM formining the insitu iron orezone.
(ii) LandReclamation andrehabilitation
Does not arisedue to slicemining.
Not working. Does not arise due to slicemining.
(iii) Waste dumpmanagement
Backfilled on thefully mined outfloat ore zone.
Not working. Backfilled on the fullymined out float ore zone.
(iv) Afforestationprogramme
100 saplings of will be planted inper year.
Not working. 100 saplings will be plantedper year of this miningscheme period.
(v) Quality of air The air will bepolluted by
excavation of ROM,transportation,drilling & blasting.
Monitoring has beencarried out in the
area. However,about 4,000 saplingwere planted in thenearby villages asCSR.
The air will be polluted tosome extent by excavation
of ROM and during thetransport of dumper fromthe haulage road. Further,pollution of air duringdrilling upto 5 m depth andblasting. This can bereduced to some extent bywet drilling, muffle blastingas well as sprinkling of water on the blasted masswhile loading and on thehaulage road.
(vi) Quality of mine water andany interferencewith surface water.
There will be nointerference of sub-surfacewater in miningpit.
Monitoring has beencarried out in thearea.
There will be nointerference of sub-surfacewater in mining pit.
Salient items to be coveredUnder column nos.2,3 & 4 are asunder
Proposals asper approvedscheme of mining(indicate dateof approval of scheme)BST/Fe/MPLN-466/NGP dated24.11.2008.
Proposal for the next 5 year
scheme period
HIG-21, Hudco colony Page 45 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 46/80
( v i i )
N o i s e
l e v e l
Source of noise to beidentified Pattern of blast & design of blastwith details of sufficient no. of experimental blastsconducted to be given
Not working.
The mining equipments will beproperly maintained to minimizethe noise level.Due to the muffle blasting theadverse effect for noise pollutionwill be minimum.The equipment operators will beprovided ear plugs.
( v i i i )
V i b r a t i o n Not working. Due to muffle blasting the
vibration can be minimized andwill be within permissible limit.
(ix) Treatment of mine waterand affluent, toxic substancebefore discharge
Not working.There is no acid mine drainage andtoxic material in the mine.
(x) Recirculation of treated
water Not required Not required
(a). The status of baseline information is as under:
The environment monitoring regarding ambient air, waste and noise are being
taken on regular basis, the baseline information has been taken from the
HIG-21, Hudco colony Page 46 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 47/80
monitoring results. A copy of the monitoring results has also enclosed as Annexure
No. XI.
(i) Existing Land use Pattern indicating area already degraded due to
quarrying / pitting, dumping, roads, Processing plant, work-shop,
township etc
The detail of Present Land use as under:
Items Type of Land (Ha)
ForestLand
AgricultureLand
Barrenland & rocky land
Grassland
Anyothertype
Total
(A) Lease area 25.00 - - - - 25.00(B) mining & allied activities
i. Pits 0.0250 - - - - 0.0250ii. Dumps - - - - - -iii. Roads 0.6600 - - - - 0.6600iv. Stack Yard - -v. Site services 0.0100 - - - - 0.0100vi. Plantation - - - - - -(C) Hutments - - - - - -
(ii) Ambient air Quality:
Since, the area falls under Kothodi Protected Forest which is free from other source
of air pollution and the ambient air quality is as under:
Location Distance fromlease area
SPM PM 10 PM 2.5
Core zone
HIG-21, Hudco colony Page 47 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 48/80
Near lease area -- 126 - 138 42 - 44 18 -20Buffer zoneMetabodeli village 1.5 km NE 140 -147 44 - 46 21 – 23Chargaon village 1.0 km E 145 - 153 47 - 51 24 – 27Surwahi village 1.5 km NE 149 - 156 48 - 53 26 - 30
The results of analysis are enclosed as Annexure No. XI.
(iii) Water regime:
There is no local water regime of any importance which is passing through the
lease area. Only the rain water falling in the area flows down. Average water depth
in wells in various villages is about 10 m below the surface ground level. The water
samples were collected and analyses, the locations of sampling stations are shown
on Key Plan, Plate No. II.
Nearest drainage is Chargaon river towards S-E part of the area with a distance of
3 kms and Putunggori Nala towards northern part of the mine area with a distance
of about 2.5 Kms.
The ground water level observed in tube wells is as under:
Location Distance fromlease area
Water level
Core zone
Near lease area -- 10 – 10.20 m
Buffer zoneChargaon village 1.0 km E 9.50 – 9.70 mMetabodeli village 1.5 km NE 9.00 – 9.30 m
HIG-21, Hudco colony Page 48 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 49/80
The quality of ground water (hand pump) and surface water is as under:
Location Distancefrom leasearea
Ph TDS TotalHardness(CaCO3)
Mercury
(Hg)
Coliform
Ground waterCore zone
Near lease area -- 7.44 –
7.55
242 -
260
124 -
136
<
0.001
Nil
Buffer zoneChargaon village 1.0 km E 7.52 –
7.60
235 -
252
121 -
130
<
0.001
Nil
Surface waterChargaon Nadi -- 7.15 –
7.60
224 -
230
-- -- --
The results of analysis are enclosed as Annexure No. XI.
(iv) Ambient noise level:
Since the area is forest land, the noise levels is within the limits. The Ambient
noise level monitored during day and night are as under:
Location Distance fromlease area
dB
Day Night
Core zone
Near lease area -- 41 -42 37 - 38
Buffer zoneChargaon village 1.0 km E 42 - 44 38Metabodeli village 1.5 km NE 43 - 44 39Surwahi village 1.5 km NE 44 38
HIG-21, Hudco colony Page 49 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 50/80
The noise level measurement data is enclosed as Annexure No. XI.
(v) Flora & Fauna:
There is no flora and fauna of significant importance within the lease area. The
area is moderately forested with some variety of floral species. The forest is
tropical deciduous type. Common flora spices are: Lendua, Moyan, Haldu, Tendu,
Palas, Mahua, Amla & Neem.
It has noted that the area is devoid of high moisture in the atmosphere. Local
varieties of trees like Saja, Khamar, Haldu, Kusum are the main vegetations.
Natural fauna is field mice, rabbits & foxes. Domestic cows, buffalos and goats are
there in villages.
(vi) Climatic condition:
The climate of the region is subtropical, with hot summer between mid April to Mid-
June with temperature 20° to 43°C. Beside these months the climate is generally
pleasant in monsoon and winter with temperature 8° to 22°C.
The region receives an average rainfall of 1000 –1300 mm. with an annual
variation of 50 mm to 100 mm. during monsoon season from mid-June to
September from Southwest monsoon.
Wind speed is about 1 to 5 Kms per hour followed by 6 to 10 kms per hour.
Predominant wind direction SE in summer and NW in winter.
Humidity, in summer 89 Max to 42 Min and in winter 86 Max to 33 min.
(vii) Human settlement:
No inhabitation is within the mining lease area. The inhabitants of the settlements
in surrounding area are mostly engaged in agriculture during the field season and
remain unemployed during the rest of the year.
S.No.
Town /Village Name
No of Households
Persons Males Females
HIG-21, Hudco colony Page 50 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 51/80
1 Chargaon 173 914 454 4602 Aalkanhar 41 224 120 1043 Kadame 83 466 225 2414 Koyali Beda 514 2,523 1,269 1,2545 Kurusbodi 59 305 171 1346 Kurush Bodi 41 260 131 1297 Manhakal 47 297 157 140
8 Metabodeli 37 231 121 1109 Nawgel 16 119 65 5410 Porondi 152 883 448 43511 Sargikot 46 253 139 11412 Siksod 64 371 196 175
(ix) Public buildings, places of worship and monuments:
There is no public buildings, places of worship or monuments within the lease area
or near by the lease area.
Education: Available in village Chargaon, primary education schools facilities.
Medical: Primary health centers are available in village Chargaon.
Water supply: Mostly drinking water supply in all villages by dug wells and hand
pumps.
Bhanupratappur with a distance of about 50 kms
Antagarh with a distance of about 30 Kms
Dalli-Rajhara with a distance of about 85 Kms.
Kanker district head quarter is about 100 kms.
(x) Attach plans showing location of sampling stations:
The sampling station for air noise, and water have been marked on the
Environment Plan, Plate No. VI. And Environment Management Plan, Plate No. VII.
(xi) Does area (partly or fully) fall under notified area under Water
(Prevention and Control of Pollution) Act, 1974:
The area falls under notified area under water prevention and control of pollution
Act 1974.
HIG-21, Hudco colony Page 51 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 52/80
(b). Monitoring schedules for different environmental components after
the commencement of mining and other related activities.(for ‘A’
category mines only)
Note: Ground vibration studies are to be carried out for virgin area/ new leases
after one year from the commencement of mining activities. (for ‘A’ category
mines only)
Note: While preparing mining plans various circulars issued by CCOM particularly
the Circular no. 2/91 regarding conceptual plan, 5/91 regarding requirement of
exploration and existence of mineral, 3/92 regarding generation of baseline data
by mechanized mines etc. may also be referred and taken into account.
Since the lease is very small and manual in nature, the monitoring of environment
will be done as per the guidelines of MoEF. The environment monitoring location is
as under:
Location Distance fromlease area
Ambientair
Ambientnoise
Water
Core zone
HIG-21, Hudco colony Page 52 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 53/80
Near lease area -- √ √ √ Buffer zoneMetabodeli village 1.5 km NE √ √ √ Chargaon village 1.0 km E √ √ √ Surwahi village 1.5 km NE √ √ √ Chargaon nadi -- -- -- √
The environment monitoring schedule is as under:
Component MonitoringParameter
Monitoring Method MonitoringFrequency
Ambient AirQuality(inside mines)
SPMRSPMSO2
NO2
SPM, SO2 & NO2 –CPCB Method
(Emission Regulation– Part III)
Quarterly
Noise Levels Average Leqvalues and
Maximumvalue of SoundPressure Levelin dB(A)
CPCB method usingequipment as per IS-
9989 & IS :9779
Monthly(for day &
night time)
WorkEnvironment
1. RespirableDust2. Inhaled Dust
1. Respirable DustSampler2. Personal SamplerMonitoring Procedureas per OSHA Method
Monthly
Surface & GroundwaterQuality
Level & Quality(pH, TDS, TSS,hardness,relevant anionsand heavymetals)
Piezometric wellsStandard Methods of APHA
Six monthly
HIG-21, Hudco colony Page 53 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 54/80
* * * * * * * *
CHAPTER-10.0
OTHER INFORMATION:
Results of any investigation carried out for scientific mining, conservation
of mineral and protection of environment; future proposal, if any.
No investigation was carried out for scientific mining, conservation of mineral and
protection of environment during the earlier Mining Plan / Scheme of Mining
period.
Information on activity carried out under Corporate Social Responsibility
(CSR)
In addition to afforestation to preserve the environment in and around the mine
area the company has done CSR activity in respect of Metabodeli Iron Ore mine in
following manner:
S.No
Year Details of activity done under CSR Total cost(Lakh Rs.)
1. 2008-09 Construction of Approach road, organizing health camp,Technical education to boys & girls in the periphery of thearea, Free of medicine distribution, Digging of hand pump inthe affected area, Nurshing course, Training health workersetc.
38.48
HIG-21, Hudco colony Page 54 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 55/80
2. 2009-10 Organizing health cap, ITI training to 9 boys in the peripheryof the area, Free of medicine distribution, Digging of handpump in the affected area, Nursing course, Training healthworkers etc.
88.79
3. 2010-11 Construction of village road, Organizing health camp,nursing training to girls in the periphery of the area, Free of cost medicine distribution, Digging of hand pump in theaffected area, Nursing course, Training health workers etc.
100.00
4 2011-12 Construction of village road, Organizing health camp ,nursing training to girls in the periphery of the area, Free of cost medicine distribution, Digging of hand pump in theaffected area, Nursing course, Training health workers etc.
123.26
5 2012 tillDec 12
Organizing health camp, nursing training to girls in theperiphery of the area, Free of cost medicine distribution,Nursing course, Training health workers etc. Pojja culturalprogram
08.57
Total 359.1
* * * * * * *
PROGRESSIVE MINE CLOSURE PLAN(Part-II of the Scheme of Mining)
CHAPTER-11.0
11.1.0. INTRODUCTION:
The name of lessee, the location & extent of lease area, the type of lease
area (forest, non-forest etc), the present land use pattern, the method of
mining and mineral processing operations should be given.
(a) Name and Address of the Lessee:Name of the lessee – M/s jayaswal Neco Industries Ltd
Address – Siltara Growth center, Raipur
Status of the Lessee –
The lessee is a public limited company.
(b) The location & extent of the lease area, the type of lease (forest/Non-
forest, etc.) -
Metabodeli Iron ore mime over an area of 25 Ha.
State Chhattisgarh
HIG-21, Hudco colony Page 55 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 56/80
District KankerTehsil PakhanjurForest Circle KankerForest Division Bhanupratappur(west)Forest Range KoilibedaProtected Forest MetabodeliVillage MetabodeliCompt. no. 426/1305 (7.5 Ha)
427/1306 (17.5 Ha)Ownership Protected Forest land
The area is approachable from village Chargaon, SE of village a hill is at a
distance of 2 km. Chargaon is approachable by 25 km forest road from
Pondgaon, on Rajnandgaon-Durg-Rajhara-Bhanupratappur-Narayanpur-Jagdalpur
state highway. The nearest rail-head is Dalli-Rajhara at a distance of about 84
km.
(c) Present land-use pattern: The present land use pattern of the lease area is
as under –
S.no.
Area put to use Area (Ha.)
1 Area to be excavated 0.0250
2 Storage for top soil Nil3 Overburden/Dump Nil4 Mineral storage 0.01005 Infrastructure (workshop,
office buildings/crusher)Nil
6 Road 0.66007 Railways Nil8 Green belt Nil9 Tailing dam Nil10 Effluent treatment plant Nil11 Mineral separation plant Nil
12 Township area Nil13 Other to specify (magazine) Nil
HIG-21, Hudco colony Page 56 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 57/80
(d) The method of mining: The mining operation will be by open cast aided by
mining equipments and hence, categorized as OTFM. Mining operations are
proposed to be carried out by wagon drill, blasting, loading by shovel-dumper
combination to the steel plant through dumpers.
(e) Mineral processing operations: Not required
11.1.1. Reason for Closure: The reason for closure of mining operations
in relation to exhaustion of minerals, lack of demand, uneconomic
operations, natural calamity, directives from statutory organizations or
court etc should be specified.
The mining plan was approved by IBM, Govt. of India vide letter No.
BST/Fe/MPLN-465/NGP dated 2/4/96, and thereafter the execution of lease deedon 17/01/02, the working permission was given by collector on 28/06/02 and
mining started on 01/08/02.
The mine is not working in full swing till date due to some unavoidable
circumstances hence question for closure of the mine does not arise.
This Progressive Mine Closure plan as an integral component of the Scheme of
Mining and is being submitted for approval.
11.1.2. STATUTORY OBLIGATION: The legal operations, if any for whichthe lessee is bound to implement like special condition imposed while
execution of lease deed, while approval of Mining Plan, directives issued
by the Indian Bureau of Mines, conditions imposed by the Ministry of
Environment & Forest Govt. of India, State or Central Pollution control
Board or by any other organization describing the nature of conditions
and compliance position thereof should be indicated here (the copies of
relevant documents may be attached as Annexure).
There is no legal operation and no special condition has been imposed in mining
lease deed.
HIG-21, Hudco colony Page 57 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 58/80
The main condition imposed in approval letter of earlier scheme of mining is that
the approval of mining operations and associated activities are restricted to the
mining lease area only.
Some special conditions imposed by the State Environment Board are as under:
(i) A green belt of adequate width by planting the native plant species all around
the ML area.
(ii) Blasting operation should be carried out only during day time.
(iii) Vehicular emissions should be kept under control and regular monitoring.
(iv) Only wet drilling should be carried out.
(v) Regular monitoring of ground water level and quality shall be by established
a network of existing wells and constructing new piezometer during mining
operations.
As per the mining lease deed condition, the lessee donates for village festivals andvillage school functions regularly.
The lessee is bound to comply all the special conditions imposed while execution
of lease deed, while approval of Mining Plan, directives issued by the Indian
Bureau of Mines, conditions imposed by the Ministry of Environment & Forest
Govt. of India, State or Central Pollution control Board or by any other
organization.
11.1.3. CLOSURE PLAN PREPARATION: The names and address of the
applicant and recognized qualified person who prepared the Mine Closure
Plan and the names of executive agency if any should be furnished. A
copy of the resolution of the Board of Directors or any other appropriate
administrative authority as the case may be on the decision of the closure
of mine should be submitted.
The name and addressof the Lessee-
M/S Jayaswal Neco Industries Ltd,
F/8 MIDC Industrial Area Hingna Road, Nagpur.
Factory address- Siltara, RaipurThe name and addressof the RQP-
Shri Shalabh Saha,
HIG 21- Hudco, Bhilai, Distt.- Durg (Chhattisgarh)
HIG-21, Hudco colony Page 58 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 59/80
RQP/NGP/302/2003/A
* * * * * * * *
11.2.O. MINE DESCRIPTION:
11.2.1 GEOLOGY:
Briefly describe the topography and general geology indicating rock-types
available, the chemical composition of the rock/mineral including toxic
element, if any at the mine site:
The details is given in Chapter 3 Reserve.
11.2.2 RESERVES:
Indicate the mineral reserves available category-wise in the lease areaestimated in the last Mining plan/Scheme of mining approved along with
balance reserves at the proposed mine closure including its quality
available.(for final mining closure plan only).
The details are given in the chapter 3 Reserve.
11.2.3 MINING METHOD:
Describe in brief the mining method followed to win the mineral, extent
of mechanization, mining machinery deployed, production level etc.
This has been given in detail under chapter 5.0 Mining.
HIG-21, Hudco colony Page 59 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 60/80
11.2.4 MINERAL BENEFICIATION:
Describe in brief the mineral beneficiation practice if any indicating the
process description in sort. Indicate discharge details of any tailing /
middling and their disposal / utilization practice followed.
This mine is a captive source of Lessee’s steel plant near Siltara, Dist-Raipur(C.G.). Mineral beneficiation plant is not required for Metabodeli iron ore, since the
quality meets the specifications required for the plant. Only breaking, sizing,
sorting and blending is sufficient to meet the quality requirement of Plant.
* * * * * * * *
11.3.0. REVIEW IMPLEMENTATION OF MINING PLAN/ SCHEME OF
MINING INCLUDING FIVE YEAR PROGRESSIVE CLOSURE PLAN UPTO
FINAL CLOSURE PLAN OF MINE:
Indicate in detail the various proposals committed to be implemented
with special emphasis on the proposal for scientific mining, conservation
of minerals and protection of environment in the approved Mining
Plan/Scheme of Mining including five years Progressive Closure Plan up
to the Closure of mine vis-a vis their status of implementation. Highlight
the areas, which might have been contaminated by previous mining
activities and type of contaminants that might have been found there. Thereason for deviation from the proposal, if any, with corrective measures
taken should also be given.
The details are given in the chapter 1.4.
* * * * * * * *
HIG-21, Hudco colony Page 60 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 61/80
11.4.0. CLOSURE PLAN:
11.4.1 MINED–OUT LAND: Described the Proposals to be implemented for reclamation and
rehabilitation of mined out land including the manner in which the actual
site of the pit will be restored for future use. The proposal should be
supported with relevant plans & section depicting the method of land
restoration /reclamation/rehabilitation.
As per approved scheme of mining, the year wise development and production
could not be implemented due to unforeseen circumstances beyond the control of
lessee.
The reclamation and rehabilitation of mined–out land does not arise at this stage,
since the mining will be done in slicing method from the hill top (+ 575 m MSL)
upto the ore body contact. Thereafter, he leveling the mined–out areas and
afforestation will be done. The float ore mined out area will be filled back from the
OB and waste after entire removal of float ore, thereafter, after leveling the area
will be takenup for plantation.
HIG-21, Hudco colony Page 61 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 62/80
Proposed Plantation during this scheme of mining period will be done within the 7.5
m of non-mining zone which is as under:
Year / Activity Plantation Area
2012-2013 100 nos 1000 sq m2013-2014 100 nos 1000 sq m2014-2015 100 nos 1000 sq m2015-2016 100 nos 1000 sq m2016-2017 100 nos 1000 sq m
Total 500 nos 5000 sq m
11.4.2 WATER QUALITY MANAGEMENT:
Describe in detail the existing surface and ground water bodies available
in the lease area and the measures to be taken for protection of the same
including control of erosion, sedimentation, siltation, water-treatment,
diversion of water courses, If any, measures for protection of
contamination of ground water from leaching etc. Quantity and quality of
surface water bodies should also be indicated and corrective measures
proposed to meet the water quality, conforming the permissible limits
should also be described. Report of the hydro- geological study carried
out in the area may also be submitted. The water balance chart should be
given. If there is potential of Acid Mine Drainage the treatment method
should be given.
The nalas flowing in the lease area is seasonal and mainly carries surface run off
during the rainy season. The Metabodeli hill acts, as a divider between
watercourses in north and Chargaon River in the south the drainage pattern is
dendrictic.
Due to absence of perennial nala, there will be no impact on water regime. One
dry nala exist in SW side of lease area. As the mining of the deposit would mostly
be confined to the hill slopes, surface run–off water accumulation in the quarry
area is expected to be remote. The ground water table lies 10 m below surface
HIG-21, Hudco colony Page 62 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 63/80
ground level. Hence, that there will be no accumulation of ground water in the
quarry floor. There is no potential Acid mine drainage.
11.4.3 AIR QUALITY MANAGEMENT:Describe the existing air-quality status .The corrective measures to be
taken for prevention of pollution of air should be described.
The present air quality is free from any pollution, when the mining operation will
commence some amount of dust due to movement of dumpers, blasting of ore
body, loading & unloading of ore will be generated.
This can be reduced by sprinkling water wherever necessary such as haulage loads
and blasted mass while loading. Wet drilling , muffle blasting with delay detonators
will be used to keep the air / noise level within permissible limit.
11.4.4 WASTE MANAGEMENT:Describe the type, quality and quantity of over burden, mineral rejects etc
available and then disposal practice. If no utilization of waste material is
proposed the manner in which the waste material will be stabilized
should be described. The protective measures to be taken for
preventation of siltation erosion and dust generation from this waste
material should also be described If toxic and hazardous elements
present in the waste material the protective measures to be taken for
prevention of their disposal in the air environment beaching in the
surface and ground water etc. should be described.
HIG-21, Hudco colony Page 63 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 64/80
The waste will be generated during the mining of float ore which will be filled back
after entire recovery of float ore. The details of generation of waste material is
given in the Chapter 6.
11.4.5 TOP SOIL MANAGEMENT:
The top soil available at the site and its utilization should be described.
No top soil dump will be available in the lease area since, the hilly block containing
massive ore zone is almost free from soil cap in most of the places, however, a
very thin cap of lateritic soil available at places on the massive ore is not
removable and hence, there will be no generation of top soil during the mining of
insitu ore. For mining the float ore, the top soil mixed with laterite constituting
75% as waste after removal of about 25% of float ore will be back filled in the
excavated place by dozer.
11.4.6 TAILING DAM MANAGEMENT:
The steps to be taken for protection and stability of tailing dam,
stabilization of tailing material and its utilization periodic desalting
measures to prevent water pollution from tailings etc for arrangement for
surplus water flows along with details design structural stability studies,
the embankment seepage loss into the receiving environmental and
ground water contaminant if any should be described.
Since there will be no beneficiation plant, the question of tailing dam management
does not arise.
HIG-21, Hudco colony Page 64 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 65/80
11.4.7 INFRASTRUCTURES:
The existing infrastructure facilities available such as roads, aerial
ropeways, conveyor belts, railways, power lines, buildings & structure,
water treatment plant, transport, water supply source in the area etc. and
their future utilization should be evaluated on case to case basis. If
retained the measures to be taken for their physical stability and
maintenance should be described. If decommissioning proposed,
dismantling and disposal of building structures, transmission line, water
line, gas pipe line, water works transportation, infrastructure like roads,
rails, tanks, bridges, culverts, electrical equipment and infrastructure like
electrical cables, transformers to be described in connection with
resorting land for future use.
The M.L area in a Protected Forest Land and at present there is no infrastructure
facilities of any kind in this area.
11.4.8 DISPOSAL OF MINING MACHINERY:
The decommissioning of mining machineries and their possible post
mining utilization, if any, to be described.
The lessee has other mines also and after closure of this mine, the equipments will
be utilized in his other mines.
11.4.9 SAFETY & SECURITY:
Explain the safety measures implemented to prevent access to surface
openings, excavation etc. and arrangement proposed during the mine
abandonment plan and up to the site being opened for general public
should be described.
HIG-21, Hudco colony Page 65 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 66/80
The ML area is hilly forested, being in the remote forest and is not connected with
public transport road hence not accessible to the general public. Further there will
be no pit formation as mining will be done in slice-mining method from the hill top
to the bottom level. Mining operation will be carried out for about 300 days / year
and hence question of its temporary closure does not arise.
11.4.10 DISASTER MANAGEMENT AND RISK ASSESSMENT:
This should deal with action plan for high risk accident like land slide,subsidence flood, inundation in underground mines, fire seismic activities,
tailing dam failure etc and emergency plan proposed for quick evacuation
ameliorative measures to be taken etc. the capacity of lessee to meet
such eventualities and the assistance to be required from the local
authority should also be described.
The mining will be carried out by slicing the hill top to the ore zone and the
benches with proper slope / gradient on the SE side.
However, the lessee is capable to meet any eventuality and provide suitable and
appropriate assistance as and when required. The reasons given above will not
take place in the mining lease area as the working will confine to open-cast semi-
mechanized method (OTFM). No emergency plan is envisaged at present.
11.4.11 CARE AND MAINTENANCE DURING TEMPORARY DISCONTINUANCE:
For every five yearly review (as given in the mining scheme), an
emergency plan for the situation of temporary discontinuation or
incomplete programme due to court order or due to statutory
requirements or any other unforeseen circumstance should include a plan
HIG-21, Hudco colony Page 66 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 67/80
indicating measures of care maintenance and monitoring of status of
unplanned discontinued mining operations expected to re-open in near
future. This should detail item-wise status, monitoring and maintenance
with periodicity and objectives.
An emergency plan for temporary discontinuation or incomplete programme due
to court order or due to statutory requirement will be drawn up and executed
depending upon the situation. Since the mining is not hazardous, the situation for
emergency plan is evinced.
However, in case of any unforeseen circumstances, causing temporary
discontinuance, the machineries will be withdrawn to a safer place and the
working and other facilities would be protected by deploying adequate number of
security guards.
* * * * * * * *
HIG-21, Hudco colony Page 67 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 68/80
11.5.0. ECONOMIC REPERCUSSIONS OF CLOSURE OF MINE AND
MANPOWER RETRENCHMENTSManpower retrenchment, compensation to be given, socio- economic
repercussions and remedial measures consequent to the closure of
mines should be described, specifically stating the following.
Manpower retrenchment is an issue that will be come up at the end of lease
period or at the time of exhaustion of iron ore deposit in the area.
11.5.1 Number of local residents employed in the mine, status of the
continuation, family occupation and scope of joining the occupation
back.
The number of local residents employed in the mine will be about 100. The local
people are in their own tradition and family occupation mostly agriculture and
collection of forest produce. These people will go back to their respective
profession/employments. But since the mining operations will be a continuous
work throughout the year, such situation may not arise because the mining
wages will be much higher than their respective professions.
HIG-21, Hudco colony Page 68 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 69/80
11.5.2 Compensation given or to be given to employee connecting with
sustenance of himself or his family members.
The retrenchments, compensation to the workers, as and when required, will be
given as per the Central Labour Legislation applicable to metalliferrous mines.
11.5.3 Satellite occupation connected to the mining industry number of
persons engaged these in continuance of such business after mine
closes.
The workers mostly work in seasonal basis and hence satellite occupations
connected to the mining industry are not considered.Hence, after the closure of the mine, there will not be any adverse impact.
11.5.4 Continued engagement of employees in the rehabilitated status of
mining lease area any other remnant activities.
There is hardly any chance of Mining Lease area getting rehabilitated and any
remnant activity, as the land is Govt. Protected Forest land.
11.5.5 Envisaged repercussion on the expectation of the society around
due to closure of mine.
The employment potential of the mine is small, hence it will have no
repercussions on the expectation of the society around due to closure of mine.
However, socio-economic condition of surrounding villages/ area will improve
positively due to higher wages in mining industry.
* * * * * * * *
HIG-21, Hudco colony Page 69 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 70/80
11.6.0. TIME SCHEDULING FOR ABANDONMENT
The detail of time schedule of all abandonment operations as proposed
as Para 4 i.e. Closer Plan should be described here. The man power and
other resources required for completion of proposed job should be
described. The schedule for such operations should also be
supplemented by PERT (Program Evaluation and Review Technique), bar
chart, etc.
Plantation:
Afforestation will be done along the northern boundary within the 7.5 m of non-
mining zone of the lease area as reclamation and rehabilitation. Proposed
Plantation in this scheme of mining period will be as under:
Year / Activity Plantation Area2012-2013
1st year 100 nos 1000 sq m2013-20142nd year
100 nos 1000 sq m
2014-2015 100 nos 1000 sq m
HIG-21, Hudco colony Page 70 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 71/80
3rd year2015-2016
4th year100 nos 1000 sq m
2016-20175th year
100 nos 1000 sq m
Total 500 nos 5000 sq m
Environment monitoring stations:
The monitoring stations for air, noise, water and soil will be established as under.
Year Stations Nos.
First year
Ambient Air Quality 04Water Quality 03Noise level Survey 03Ground vibration 02
Total 12
* * * * * * * *
HIG-21, Hudco colony Page 71 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 72/80
11.7.0. ABANDONMENT COST
Cost to be estimated based on activities required for implementing the
protective and rehabilitation measures including their maintenance and
monitoring programme.
Plantation:
The Cost estimated based on activities required for implementing the protective
and rehabilitation measures including their maintenance and monitoring
programme are as under:
Proposed Plantation in this scheme of mining period will likely to be as under:
Year / Activity Plantation Area Cost
2012-20131st year
100 nos 1000 sq m ` 4,000/-
2013-20142nd year
100 nos 1000 sq m ` 4,000/-
2014-20153rd year
100 nos 1000 sq m ` 4,000/-
2015-20164th year
100 nos 1000 sq m ` 4,000/-
2016-20175th year
100 nos 1000 sq m ` 4,000/-
500 nos 5000 sq m ` 20,000/-
Environment monitoring stations:
The cost of monitoring for air, noise, water and soil will likely to be as under.
HIG-21, Hudco colony Page 72 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 73/80
Year Stations Nos. Cost (`)
First yearAmbient Air Quality 04 60,000.00Water Quality 03 40,000.00Noise level Survey 03 20,000.00Ground vibration 02 20,000.00
Total 140,000.00
HIG-21, Hudco colony Page 73 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 74/80
* * * * * * * *
HIG-21, Hudco colony Page 74 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 75/80
HIG-21, Hudco colony Page 75 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
ITEMS DETAILS AREA (hec.)PROPOSED
QUANTITY (cum)PROPOSED
EXPENDITURE(`)
PROPOSEDYEAR 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 5th
RECLAMATION
& REHABILITIONOF MINED OUTLAND AREA
(i) Backfilling
1
. 0 0
2
. 0 0 -
- - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
(ii) Afforestrationon the backfillingarea(iii) Others (pleasespecify) e.g.(iv) Pisciculture(v) Converting intowater reservoir(vi) Picnic Spot
STABILIZATION & REHABILITIONOF DAMS(with lease)
(i) Terracing(ii) Pitching(iii) Construction of
Parapet Walls /Retaining wall attoe dump(iv) Construction of Check Dams alongslope of vallies etc.(v) Construction of Setting Ponds(Garland drain etc.)(vi) Desilting of setting ponds,channels.(vii) Afforestrationon dumps.(viii) Others (please
specify)REHABILITIONOF BARRENDAREA WITHINLEASE
(i) Afforestration(Green beltbuilding)
0 .
1 0
0 .
1 0
0 .
1 0
0 .
1 0
0 .
1 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0 -
-
4 0 0 0
4 0 0 0
4 0 0 0
4 0 0 0
(ii) Others(please specify)
ENVIRONMENTALMONITORING(Core zone & Buffer zoneseparately)
(i) Ambient AirQuality(ii) Water Quality(iii) Noise levelSurvey(iv) GroundVibration
(v) Others(please specify)TOTAL
0 .
1 0
0 .
1 0
0 .
1 0
0 .
1 0
0 .
1 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0 -
-
1 0 4 0 0 0
4 0 0 0
4 0 0 0
4 0 0 0
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 76/80
11.8.0. FINANCIAL ASSURANCES
The financial assurance can be submitted in different forms as stated in
Rule 23(F)(2) of Mineral Conservation & Development (amendment)
Rules, 2003 in the Mine Closure Plan the manners in which Financial
assurance has been submitted and its particulars have been indicated:
The Financial Assurance in the form of bank Guarantee of ` 2,00,00/- in favor of
the Regional Controller of Mines, Indian Bureau of Mines, Nagpur region will be
submitted with the final submission.
HIG-21, Hudco colony Page 76 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 77/80
Table showing the area “put to use” area to be reclaimed and financial assurance to be paid :
S.No. Head Area putOn use atthe startof Scheme
(Ha)
AdditionalRequire-mentduringschemePeriod
(Ha)
Total
(Ha)
AreaconsideredAs fullyreclaimed& Rehabilitated
(Ha)
Net areaConsideredforCalculation
(Ha)
A B C=(A+B) D E=(C-D)
1Area under
mining0.0250 2.2800 2.3050 -- 2.3050
2Storage for Top
soilNil Nil Nil -- Nil
3Overburden /
dumpsNil Nil Nil --- Nil
4Mining storage
Nil 0.1000 0.1000 --- 0.1000
5 Crusher Nil Nil Nil --- Nil
6 Infrastructure 0.0100 0.1000 0.1100 --- 0.1100
7Roads
0.6600 Nil 0.6600 --- 0.6600
8 Railways --- --- --- --- ---
9 Green Belt Nil Nil Nil --- Nil
10 Tailing pond --- --- --- --- ---
10Effluent
treatment plant--- --- --- --- ---
12Mineral
separationplant
--- --- --- --- ---
13 Township area --- --- --- --- ---
HIG-21, Hudco colony Page 77 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 78/80
14Plantation
--- 0.5000 0.5000 --- 0.5000
Grand Total 0.6950 2.9800 3.6750 --- 3.6750
Amount of Financial Assurance 3.6750 × ` 25,000 = ` 91,875/- or minimum` 2.0 lakh.
* * * * * * * *
11.9.0. CERTIFICATE:
The above mentioned actions have been taken to be stated clearly in the
mine closure plan. A certificate duly signed by the lessee to the effect
that said closure plan complies all statutory rules, regulations, orders
made by the Central or State Government, statutory organizations, court
etc. have been taken into consideration and wherever any specific
permission is required the lessee will approach the concerned
authorities. The lessee should also give an undertaking to the effect that
all the measures proposed in this closure plan will be implemented in a
time bound manner as proposed.
Certificate from the Lessee regarding submission of Mine closure plan is
enclosed.
* * * * * * * *
HIG-21, Hudco colony Page 78 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A
7/30/2019 Scheme Iron Ore
http://slidepdf.com/reader/full/scheme-iron-ore 79/80
11.10.0. PLANS, SECTIONS etc.
The chapter 1, 2, 3 and 4 should be supported with Plans and Sections.
The Closure Plan may also be submitted depicting photographs, satellite
images on compact disc etc. wherever possible.
Chapter 1: Plate No. I Khasra map enclosed, Plate No. II (Key Plan).
Chapter 3: Plate No.III (Surface Plan), Plate No. IV (Surface Geological Plan)
and Plate No. IV A (Geological Cross-Sections).
Chapter 5: Plate No. V (Composite Year Wise Development & Production Plan)
and Plate No. V A (Year Wise Development & Production Sections).
Chapter 11: Plate No.VII (Progressive Mine Closure Plan) showing area proposed
to be put to use
Photographs of mine area enclosed with this documents.
* * * * * * * *
HIG-21, Hudco colony Page 79 of 80 SHALABH SAHABhilai, Dist- Durg (C.G) RQP/NGP/302/2003/A