Page 1: Sbc 2011

Michael Dunn FRICS FCIArb LLB LLMT: 02079 976 520 and 01274 693 622E: [email protected]

Delivering Professional Solutions to the Property Industry

JCT Standard Building Contract 2011 - SBC/Q

Page 2: Sbc 2011

Current documents

Standard Building Contract With Quantities (SBC/Q)

Standard Building Contract Without Quantities (SBC/XQ)

Standard Building Contract With Approximate Quantities (SBC/AQ)

other relevant documents 

Public Sector Supplement

Named Specialist Update

Sub contracts

Collateral warranties

SBC 2011 

2

Page 3: Sbc 2011

Appropriate 

for 

larger 

works 

designed 

and/or 

detailed 

by 

or 

on 

behalf 

of 

the 

Employer, where detailed contract provisions are necessary and the Employer is 

to provide the Contractor with drawings and 

with bills of quantities to define the quantity and quality of work (SBC/Q)

with approximate bills of quantities to define the 

quality 

and 

quantity 

of 

work 

which 

are 

to 

be 

subject 

to 

re‐measurement 

as 

there 

is 

insufficient 

time/information

to 

prepare 

the 

detailed 

drawings 

necessary 

for 

accurate 

bills 

of quantities (SBC/AQ)

with 

either 

specification 

or 

work 

schedules 

to 

define 

adequately    the 

scope 

and 

quality 

of 

work 

and 

where 

the 

degree 

of 

complexity 

is 

not 

such 

to 

require 

bills of quantities (SBC/XQ)

SBC 2011 

3

Page 4: Sbc 2011

Appropriate

where a A/CA and Quantity Surveyor are to administer the conditions

Can be used

where the Contractor is to design discrete parts of the Works (CDP)

where the works are to be carried out in sections

private and local authority employers

SBC 2011 

4

Page 5: Sbc 2011

Generally 

Recitals

) Project specific

Articles

) details at front

Contract Particulars    

) of document

Attestation Provisions 

)

Conditions

Schedules 

SBC/Q ‐

Structure 

5

Page 6: Sbc 2011

Conditions / SchedulesSection 1 

Definitions and InterpretationSection 2 

Carrying out the WorksSection 3 

Control of the WorksSection 4 

PaymentSection 5 

VariationsSection 6 

Injury Damage and InsuranceSection 7 

Assignment, Third Party Rights & Collateral WarrantiesSection 8 

TerminationSection 9 

Settlement of DisputesSchedules

1

Contractor’s Design Submission Procedure

2

Variation and Acceleration Quotation  Procedure

3

Insurance Options

4

Code of Practice

5 Third Party Rights

6 Forms of Bonds

7

Fluctuations Options

8

Supplemental Provisions 

SBC/Q 2011 ‐

Structure

6

Page 7: Sbc 2011

Recitals

description of the Works (Recital 1)

identifies the priced Bills (Contract Bills) (Recital  2)

priced Activity Schedule

identifies the Contract Drawings (Recital 3)

CIS ( Recital 4)

Information Release Schedule (Recital 5) ‐

Employer

Sections (Recital 6)

Framework Agreement (Recital 7)

Supplemental Provisions (Recital 8)

Contractor’s Designed Portion (Recitals 9 to 12)

SBC/Q 2011 ‐

Structure 

7

Page 8: Sbc 2011

Articles

Contractor’s obligation (Article 1)

Contract Sum (Article 2)

Architect / Contract Administrator (Article 3)

Quantity Surveyor (Article 4)

CDM Co‐ordinator (Article 5)

Principal Contractor (Article 6)

Adjudication (Article 7)

Arbitration  or

legal proceedings (Articles 8 & 9)

Employer’s representative (3.3) and clerk of works (3.4)

SBC/Q 2011 ‐

Structure 

8

Page 9: Sbc 2011

Contract Particulars ‐

Parts 1 & 2

Part 1: General

e.g. 

Section descriptions (6th

Recital)

Supplemental Provisions (8th

Recital)

Date(s) for Completion (1.1.)

liquidated damages (2.32.2)

Rectification Period  ‐

default 6 months (2.38)

frequency of interim payments i.e. due dates  (4.9.2)

insurance provision (6.7)

SBC/Q 2011 ‐

Structure

9

Page 10: Sbc 2011

SBC/Q 2011 ‐

Structure

Part 2: Third Party Rights & Collateral Warranties (7A to 7E)

Third Party Rights or Collateral Warranties? (Schedule 5 or warranties) 

from Contractor

in favour of 

purchaser & tenant

funder

collateral warranties from sub‐contractors

in favour of 

employer

purchaser & tenant

funder

10

Page 11: Sbc 2011

SBC/Q 2011 ‐

Third Party Rights /  Warranties

11

Employer

Consultant

Main Contractor

Sub-contractor

Funder

Purchaser

Tenant

Solid lines = a principal contractDashed lines = a warranty/3rd pty rights

Page 12: Sbc 2011

SBC/Q 2011 ‐

General 

Section 1 Definitions and Interpretation

Definitions (1.1) ‐

capitalised

words or terms

Interpretation (1.2 to 1.11) e.g. 

priority of Conditions (1.3)

reckoning of periods (1.5) ‐

calendar days!

Contract (Rights of Third Parties) Act 1999 (1.6)

Notices and other communications (1.7)

issuing of  A/CA Certificates (1.8)

effect of Final Certificate (1.9)

effect of other Certificates (1.10)

12

Page 13: Sbc 2011

SBC/Q 2011 ‐

Documents 

Contract Documents

Definitions (1.1)

Contract Drawings

Contract Bills  ‐

no mention of ‘specification’!

Conditions

Employer’s Requirements 

) Contractor’s

identified  in 

Contractor’s Proposals     

) Designed 

Contract Particulars 

CDP Analysis                    

) Portion

Part 1

13

Page 14: Sbc 2011

SBC/Q 2011 ‐

Documents

Discrepancies etc.

notification of discrepancies etc. in/between

Bills, Drawings, etc. (2.15)

obligation on Contractor

Contract Bills prepared to SMM (2.13 &14)

departures treated as a Variation (2.14 .3)

quality/quantity of work included within Contract Sum (4.1)

inadequacy of design in ER (2.14.2)

treated as a Variation unless addressed in CP

14

Page 15: Sbc 2011

SBC/Q 2011 ‐

Quality

Contractor’s principal obligation (2.1 and Article 1)

carry out and complete the Works in accordance with the Contract 

Documents etc.

schedules etc. issued by A/CA (2.9.1.1) 

Information Release Schedule (2.11)

further drawings or details issued by A/CA (2.12.1) 

Contractor’s Designed Portion (2.2)

complete design/select specification not stated in ER or CP 

integration  of CDP with other design  ‐

with A/CA

15

Page 16: Sbc 2011

SBC/Q 2011 ‐

Quality

Workmanship & materials  (2.3 see also 4.1)

as described in the Contract Bills

to the satisfaction of the A/CA

Employer’s Requirements / Contractor’s Proposals

standard appropriate to the Works

Contractor to provide A/CA with reasonable proof that materials/goods 

comply with Contract Documents

Contractor’s responsibility (3.6)

16

Page 17: Sbc 2011

SBC/Q 2011 ‐

CDP 

CDP identified at 9th

Recital 

Contractor’s liability (2.19)

reasonable skill and care

not liable for any design included within Employer’s Requirements (2.13.2)

PI insurance (6.12 & 13)

as built drawings (2.40)

for CDP elements only

license to use Contractor’s Design Documents (2.41)

subject to all monies due being paid

17

Page 18: Sbc 2011

SBC/Q 2011 ‐

CDP

Contractor’s Design Submission Procedure i.e. Design Documents

2.9.5 and Schedule 1

2 copies in format set out in ER

A/CA respond within

14 days

categories A/B/C

18

Page 19: Sbc 2011

SBC/Q 2011 ‐

Sub Contracts 

Consent

to sub contract (3.7)

work / design

Listing

in Contract Bills (3.8)

list minimum of 3

domestic sub‐contractor

specialist naming supplement 

JCT Standard Sub‐Contract otherwise include (3.9) 

unfixed materials

interest on late payment

collateral warranties – 14 days

19

Page 20: Sbc 2011

SBC/Q 2011 ‐

Instructions 

A/CA’s instructions

instruction in writing (1.7)

other than in writing ( 3.12)  e.g. oral

clerk of works directions (3.4)

instructions e.g.

Variations (5.1 & 3.14)

postponement (3.15) / provisional sums (3.16) / remove non compliant 

work (3.18)

non compliance with an Instruction (3.11) i.e. 7 day notice

empowering provision (3.13)

20

Page 21: Sbc 2011

SBC/Q 2011 ‐

Instructions

A/CA’s Instructions 

Contractor to comply with instructions (3.10) save that

reasonable objection to a Variation under 5.1.2

impacts on efficacy of design (CDP element)

Variation Quotation (5.3)

what is a Variation Quotation (5.3 and Schedule 2)

within 7 days Contractor’s notice of insufficient information

21 days provide quotation to QS

open for acceptance – 7 days

acceptance by the Employer /  A/CA Confirmation Instruction

Acceleration Quotation (Schedule 2)

21

Page 22: Sbc 2011

SBC/Q 2011 ‐

Instructions 

Work not in accordance with the Contract (3.18)

remove defective work (3.18.1)

leave and adjust Contract Sum (3.18.2) ‐

Employer consultation !

inspection and tests (3.17)

other work (Schedule 4 Code of Practice)

Rectification Period (2.38) ‐

defects

schedule of defects (2.38.1)

defects prior to expiry (2.38.2)

22

Page 23: Sbc 2011

SBC/Q 2011 ‐

Instructions

A/CA Instructions

valuation of Variations (Section 5)

definition of a Variation (Section 5)

agreed between Parties failing which valued by QS (5.2)

the Valuation Rules

Bill rates / prices etc.

CDP

23

Page 24: Sbc 2011

SBC/Q 2011 ‐

Payment 

SBC/Q 2011 is a lump sum contract

adjustments to the Contract Sum (4.2,4.3, 4.4 & 4.5)

adjustments to be included within interim payments (4.4)

(note: SBC/AQ is not a lump sum contract but a re‐measurement contract)

Payment provisions have to comply with

Housing Grants Construction & Regeneration Act 1996 as amended by 

the Local Democracy, Economic Development and Construction Act 

2009 ‐

Part 8

24

Page 25: Sbc 2011

SBC/Q 2011 ‐

Payment 

Payment driven by dates ‐

due dates

interim payments / final payment

invoices?

all reference to payments exclude VAT

Provision for an advance payment (4.8)

Contract Particulars

bond (Schedule 6 Part 1)

local authorities

25

Page 26: Sbc 2011

SBC/Q 2011 ‐

Payment 

Interim Certificates issued by A/CA (4.10.1) should state

amount due (e.g. Employer to Contractor)

basis of calculation

Interim Certificates issued (4.10.1) within 5 days of the due date

(4.9) 

in Contract Particulars up to the month following practical completion

thereafter every 2 months 

upon  issue of Certificate of Making Good (2.39)

Effect of Interim Certificates (1.10)

26

Page 27: Sbc 2011

SBC/Q 2011 ‐

Payment 

Valuations for Interim Certificates prepared by 

Quantity Surveyor (4.10.2)

Make up of interim payment (4.16 and 17)

gross valuation

works completed in accordance with Contract

materials on and off site

less

(4.9.2)

advance payment

Retention

amounts previously certified

amounts paid against Interim Payment Notice / Payless Notice

27

Page 28: Sbc 2011

Contractor’s Interim Application (clause 4.11)

may submit – not mandatory

submitted not less than 7 days before the due date 

stating sum due and basis of calculation

where 

no 

or 

no   ‘valid’

Interim 

Certificate 

is 

issued 

by 

A/CA 

then 

Interim 

Application becomes an Interim Payment Notice

where 

no 

Interim 

Application 

is 

submitted 

and 

no 

or 

no 

‘valid’

Interim 

Certificate 

is 

issued    the 

Contractor 

may 

submit 

an 

Interim 

Payment 

Notice 

submitted to QS 

SBC/Q 2011 ‐

Payment 

28

Page 29: Sbc 2011

Payless notice (clause 4.13)

could be issued by either Employer

or Contractor

(i.e. Final Certificate)

Employer  to Contractor

may be given by Employer or Employer’s rep or A/CA or QS

state amount due at date of notice

and basis

of calculation 

Contractor to Employer

copy to A/CA

state amount due at date of notice and basis

of calculation 

Payless 

notice 

can 

only 

be 

given 

when 

either 

an 

Interim 

Certificate 

or 

Interim/Final Payment Notice has been given

SBC/Q 2011 ‐

Payment 

29

Page 30: Sbc 2011

Amount paid to Contractor 

sum 

stated 

as 

due 

in 

the 

Interim 

Certificate  ‐

Certificate 

issued 

even 

if 

amount is zero (clause 4.12.2)

subject to the issue of a payless notice

where no or no  ‘valid’

Interim Certificate is issued  the amount stated in 

the Interim Payment Notice (clause 4.12.3)

subject to the issue of a payless notice 

where 

payless 

notice 

is 

issued 

the 

amount 

shall 

not 

be 

less 

than 

that 

stated in that notice. (clause 4.12.5)

SBC/Q 2011 ‐

Payment 

30

Page 31: Sbc 2011

SBC/Q 2011 ‐

Payment 

Retention (4.18 to 20)

default 3% ‐

bond in lieu of retention?

fiduciary interest / separate bank account / investment 

reduced by 50% following issue of Practical Completion Certificate

final balance released following issue of Certificate of Making Good 

Employer fails to make interim payment 

interest (4.12.6)

suspension (4.14)

termination (8.9.1.1)

31

Page 32: Sbc 2011

SBC/Q 2011 ‐

Payment 

32

5 days 5 days

A/CA issues 

Interim Certificate

Employer issues 

proposed 

payment notice

Employer’s 

withholding 

notice

Final date for 

payment

14 days

5 days 5 days

Due date

identified in 

Contract 

Particulars

Within the 5 day 

period A/CA issues 

Interim Certificate

Payless notice Final date for 

payment

14 days

2005 Procedure – interim payments

2011 Procedure – interim payments

Page 33: Sbc 2011

SBC/Q 2011 ‐

Payment  

33

5 days 5 days

Due date

identified in 

Contract 

Particulars

A/CA to issue 

Interim 

Certificate 

within  the 5 

days

Payless notice 

issued by •Employer •Employer’s R•A/CA•QS

Final date for 

payment

14 days

Contractor may  

issue an 

Interim Payment  

Notice

2011 Procedure – interim payments

xplusx

Important if no proper interim

certificate given

Contractor 

may  submit an 

interim 

application –

not less than 7 

days before 

due date 

Amount due?

Page 34: Sbc 2011

SBC/Q 2011 ‐

Payment 

Final adjustment (4.5)

6 month period following practical completion for Contractor to submit 

documents

after which 3 months for preparation of

loss and/or expense statement

schedule of adjustments to Contract Sum

issued by A/CA

34

Page 35: Sbc 2011

SBC/Q 2011 ‐

Final Certificate 

Final Certificate (4.15)

issued no later than 2 months from the later of

end of the Rectification Period

issue of Certificate of Making Good

issue of loss and/or expense statement / schedule of adjustments

to the 

Contract Sum

35

Page 36: Sbc 2011

SBC/Q 2011 ‐

Final Certificate 

Final Certificate should state (4.15)

adjusted Contract Sum

amount previously certified

difference owed to either the Contractor or Employer i.e. the amount 

due

the basis of the calculation 

Conclusiveness of Final Certificate (1.9)

Final date for payment – 28 days (4.15)

36

Page 37: Sbc 2011

SBC/Q 2011 ‐

Payment 

37

5 days

Issue FC no later than 2mths after later of•end of RP.•issue of CMG•issue of ‘final account’due date is date of issue or expiry of 2 months

Payless notice from

Employer or

Contractor

Final date for payment

28 daysplus ‘X’

Final payment

If no FC issued

Contractor may issue a

‘Final Payment Notice’

‘x’ days

Page 38: Sbc 2011

SBC/Q 2011 ‐

Time 

‘Start’

and completion

Contract Particulars (1.1 & 2.4)

Possession and progress (2.4 & 2.5)

Contractor takes possession

until practical completion

Contractor to proceed regularly and diligently

deferred possession by Employer

– for up to 6 weeks (2.5)

Completion in Sections

Recital 6

Contract Particulars ‐

insert details for Sections

clauses drafted as ‘…the Works or of any Section…’ e.g. 2.30.

38

Page 39: Sbc 2011

SBC/Q 2011 ‐

Time 

Employer occupies site or earlier use of  Works (2.6)

storage / other use

contractor’s consent

insurer aware and adjustment for premium

Partial Possession (2.33 to 2.37)

consent of the Contractor

A/CA’s statement ‐

not a certificate

deemed practical completion

insurance / Rectification Period / liquidated damages / Retention

39

Page 40: Sbc 2011

SBC/Q 2011 ‐

Time 

Practical Completion Certificate (2.30)

A/CA’s opinion

what amounts to practical completion?

CDP

‘as built’

drawings (2.40)

CDM Regulations (3.23.4)

Non Completion Certificate (2.31)

what if an eot is subsequently granted?

40

Page 41: Sbc 2011

SBC/Q 2011 ‐

Time 

Liquidated damages (2.32)

rate in the Contract Particulars (per day /  per week or part thereof)

recover as a debt or by deduction from payments

Non Completion Certificate issued

notice that may

withhold

Payless Notice (4.12)

41

Page 42: Sbc 2011

SBC/Q 2011 ‐

Time

Adjustment of Completion Date  (2.26 to 2.29)

Pre Agreed Adjustment / Relevant Omission

Contractor’s notice ‐

required particulars

A/CA is to 

respond within 12 weeks

allocated time to each Relevant Event ! (2.28.3)

review period (12 weeks following practical completion)

Relevant Events ‐

14 nr

sweep‐up provision includes Architect / QS (2.29.7)

Contractor’s programme (2.9.1.2.)

42

Page 43: Sbc 2011

SBC/Q 2011 ‐

Loss and/or Expense

Loss and/or expense (4.23 to 4.26)

purpose?

entitlement in principle / quantum

Relevant Matters

5 number

includes any act impediment etc. by Employer includes A/CA  and QS

43

Page 44: Sbc 2011

SBC/Q 2011 ‐

Insurance of the Works

Insurance of the Works (6.7)

Option A ‐

new works by Contractor

Joint Names (6.8) / All Risks (6.8)

Option B

new works by Employer

Joint Names / All Risks

Option C

Existing Structures and Works

existing structures  ‐

Joint Names / Specified Perils (6.8)

new works   ‐

Joint Names / All Risks

44

Page 45: Sbc 2011

SBC/Q 2011 ‐

Dispute Resolution

Supplemental Provisions –

negotiation by senior executives (paragraph 6)

Reference to mediation (9.1)

Adjudication (9.2)

Legal Proceedings now default  (Article 9)

Contract Particulars

Arbitration (Article 8 &  9.3 to 9.8)

45

Page 46: Sbc 2011

Delivering Professional Solutions to the Property Industry

QuestionsQuestions

46