Sargisson BeachProperty Reclamation ProjectAn Application for Funding Submitted to the Community Preservation Committee (CPC)
PREPARED BY THE SARGISSON BEACH COMMITTEE
ANDREW DAVIS ( CHA IRMAN) , JOSH DEGEN, JOHN GIGER , CHENEY HARPER, RENA SWEZEY
FILE ID: SBC TM PRESENT JRG1A.PPTX 1
The Journey Context Challenge Opportunity Proposed Reclamation Project Deliverable Community Support
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 2
Context Sargisson Beach Made Up of Two Properties, Off Whiley Road on the shore of Knops Pond, Owned by the Town Properties Under Stewardship of Conservation Commission Sargisson Beach Provides Recreational Swimming, Paddle Propelled Small Boating, Fishing, Hiking and Picnicking Opportunities for Town Residents
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 3
Context
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 4
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 5
Our Challenge
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 6
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 7
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 8
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 9
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 10
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 11
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 12
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 13
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 14
Our Opportunity
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 15
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 16
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 17
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 18
Proposed Reclamation Project Two PhasesPhase 1, Fall 2014 ‐ Embankment PreservationPhase 2, Fall 2015 – Beach Repair and Revitalization
Estimated Total Cost: $170,500 or less
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 19
Proposed Reclamation Project, Phase 1 ‐ ScheduleWhen: Fall 2014 Duration: Mid‐October through Mid‐December (Weather Cooperating) Contingency: Early Spring, 2015, if weather prevents completion in 2014
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 20
Proposed Reclamation Project,Phase 1 ‐ Funding
SOURCE GROTON LAKES ASSOCIATION CONTRIBUTION (Already Received) CPC FUNDING PROPOAL, TOWN MEETING, ARTICLE 18, PROPOSAL D: PHASE 1 TOTAL:
AMOUNT$5,000
$109,590
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
$114,590
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 21
Phase 1 DeliverableThe shore line surrounding Sargisson Beach will be preserved for community recreational use and enjoyment into the foreseeable future.
FILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 22
Community Support
Please supportArticle 18,
CPC Proposal DFILE ID: SBC & CPS PRESENT1 JRG1A.PPTX 23