Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
OSRAM Continental |
SAP PLM INFO DAYS
APRIL 16, 2019
SAP MODEL COMPANY ON S/4HANA FOR PLM
OSRAM Continental |
AGENDA
MODULE 2. DOCUMENT MANAGEMENT 2SAP PLM INFO DAYS
1. OSRAM CONTINENTAL GMBH
2. SYSTEM LANDSCAPE
3. IMPLEMENTATION STEPS
4. TRANSITION PHASE
5. SAP S/4HANA LP1 PLM + ERP TIMELINE
6. PROJECT RESULTS WAVE 1
7. NEXT STEPS
8. SUMMARY
OSRAM Continental | NAME OF THE PRESENTATION | MONTH DAY, YEAR 3SAP PLM INFO DAYS
1. OSRAM CONTINENTAL GMBHTWO STRONG PARTNERS CREATE INNOVATIVE PRODUCTS
Intelligente, innovative Lichtlösungen für die Automobilindustrie: www.youtube.com/watch?v=oeteeCrzUXM
OSRAM Continental |
1. OSRAM CONTINENTAL GMBHTWO STRONG PARTNERS COMBINE COMPETENCIES
› Founded: 1918
› Headquarters: Munich
› Locations: 120
› Employees: 26,370
› Sales: EUR 3.8 bn1
› Founded: 1871
› Headquarters: Hanover
› Locations: 4272
› Employees: 220,1372
› Sales: EUR 40.5 bn2
1) As of September 30, 2016
2) As of December 31, 2016
3) Solid State Lighting
Business area:
Automotive SSL³
Lighting Solutions
Business area:
Automotive Lighting
ElectronicsOSRAM Continental GmbH
since July 2018
SAP PLM INFO DAYS
OSRAM Continental |
1. OSRAM CONTINENTAL GMBH
NAME OF THE PRESENTATION | MONTH DAY, YEAR 5
WORLDWIDE PRESENCE AT DAY 1
SAP PLM INFO DAYS
OSRAM Continental |
2. SYSTEM LANDSCAPE
NAME OF THE PRESENTATION | MONTH DAY, YEAR 6
BUILDING UP ONE OSRAM CONTINENTAL SAP SYSTEM –FOCUS PLM
Heterogeneous system landscape at Continental
ERP Systems per location
Heterogeneous system landscape at OSRAM
OSRAM Continental SAP(based on S/4HANA)
• PLM (Model Company R&D)− mCAD CATIA V5− mCAD SolidWorks− ZUKEN
• Logistics• Finance• QM/IQOS• …….
in p
rogre
ss
one single SAP system for all applications implementation in short cycles
rapid set up
Targets
SAP PLM INFO DAYS
OSRAM Continental |
3. IMPLEMENTATION STEPS
NAME OF THE PRESENTATION | MONTH DAY, YEAR 7
PROOF OF CONCEPT FOR SAP PLM
SCHEDULE
• 3 weeks to build the IT infrastructure
• 2 weeks to set up the R&D Model company
• 8 weeks of concept phase (16th August to 9th October)
with 16 days of workshop and 2 days of concept review
APPROACH
• R&D model company installation (rel. 1709)
• Challenging the set up with business requirements
• Instant implementation
TARGET
• Harmonized OSRAM Continental business processes
• Planning & scheduling of implementation
• Scoping the implementation steps
CONDITIONS
• Different grace periods on usage of the mother companies'
systems
SAP PLM INFO DAYS
OSRAM Continental |
3. IMPLEMENTATION STEPS
NAME OF THE PRESENTATION | MONTH DAY, YEAR 8
PROOF OF CONCEPT SCOPE
PROOF OF CONCEPT WITH PLM CORE PROCESSES, with reference to• ECTR (Engineering Control Center) including integration of CATIA V5 and validation for SolidWorks
• SAP objects
• Document Management
• Bill of Material
• Material Master
• Classification
• Workflow
• Engineering change management
• Process to handle change request and change order with respective workflow scenarios
• Change Master
OUT OF SCOPE WITH FURTHER PLM RELATED PROCESSES, such as• SAP Product Lifecycle Costing (SAP PLC)
• Project & Portfolio Management (SAP PPM)
• Product Data Distribution/Replication from PLM system to ERP system
• Authorization concept
• Data Migration
• Archiving concept
• ….
SAP PLM INFO DAYS
OSRAM Continental |
3. IMPLEMENTATION STEPS
NAME OF THE PRESENTATION | MONTH DAY, YEAR 9
WAVE 1: INITIAL IMPLEMENTATION AND CONTINENTAL DATA MIGRATION
SAP PLM INFO DAYS
OSRAM Continental |
3. IMPLEMENTATION STEPS
NAME OF THE PRESENTATION | MONTH DAY, YEAR 10
PROJECT ORGANIZATION
SAP PLM INFO DAYS
OSRAM Continental |
4. TRANSITION PHASE
NAME OF THE PRESENTATION | MONTH DAY, YEAR 11SAP PLM INFO DAYS
STEP BY STEP MIGRATION OF BUSINESS PROCESSES INTO ONE SYSTEM
OSRAM Continental SAP(based on S/4HANA)
08/2018 11/2018 06/2019 12/2019 06/2020
Heterogeneous system landscape at Continental
Heterogeneous system landscape at OSRAM
Different PLM Solutions
Different PLM Solutions
Wave 1
(11/2018 – 04/2019)Wave 2 (06/2019 – 01/2020)
PoC
(08 – 10/2018)Wave 3 Wave 4 Wave 5
PLM
ERPWave 1 ERP 1 roll-in
(04/2019-02/2020)Wave 2 ERP 2 + 3 roll-in (03/2020 – 11/2020)
Initial set-up
ERP roll-in preparation(07/2018-03/2019)
ERP per location
…
OSRAM Continental |
6. PROJECT RESULTS WAVE 1
NAME OF THE PRESENTATION | MONTH DAY, YEAR 12
ARCHITECTURE
SAP PLM INFO DAYS
SAP ERP
mCAD
CATIA V5
mCAD
SolidWorks*
eCAD
ZUKEN
Content Server
SEALConversion
Server
SAP PLM
PSS*EngineeringBOMs
ManufacturingBOMs
Linkage*
* Next steps
NWBC / GUIFIORICustomer
interface*
ECTR
Doc. stamping /
PDF conversion
Project / Change Management
OSRAM Continental |
6. PROJECT RESULTS WAVE 1
NAME OF THE PRESENTATION | MONTH DAY, YEAR 13
UI STRATEGY
SAP PLM INFO DAYS
ECTR* for CAD Users NWBC* for Non CAD Users
FIORI: for selected business applications (Financial Closing Cockpit, Export Control)
NWBC: flexible adjustment in case of required SAP GUI transactions and OSRAM Continental specific reports
*NetWeaver Business Client*Engineering Control Center
OSRAM Continental |
6. PROJECT RESULTS WAVE 1
NAME OF THE PRESENTATION | MONTH DAY, YEAR 14
KEY OBJECTS WITHIN S/4HANA PLM
SAP PLM INFO DAYS
mCAD / ECTR
Material MasterDocument Management
eCAD / ZUKEN
OSRAM Continental |
6. PROJECT RESULTS WAVE 1
NAME OF THE PRESENTATION | MONTH DAY, YEAR 15
KEY OBJECTS WITHIN S/4HANA PLM
SAP PLM INFO DAYS
Engineering Change Management
DocumentsMaterials
Authorization Groups to control access to Document Info Records
Bill of Material Classification
Authorization
OSRAM Continental |
6. PROJECT RESULTS WAVE 1
NAME OF THE PRESENTATION | MONTH DAY, YEAR 16
TRAINING CONCEPT
SAP PLM INFO DAYS
KEY USER TRAINING (on-site in Munich, 3 days)
• SAP PLM, OSRAM Continental PLM strategy and adjusted
processes were presented and trained
• Slides and exercises
KEY USERS ARE…
…the multipliers into the organization
…the 1st level support in the locations
…the testers in the integration tests
…they take over the role of a trainer for the End User Trainings
END USER TRAINING is split into
• Classroom trainings
• Virtual trainings
• Hand-outs
In total we trained 28 key users from 10 locations
OSRAM Continental |
7. NEXT STEPS
NAME OF THE PRESENTATION | MONTH DAY, YEAR 17
GO LIVE WAVE 1 – PLANNING WAVE 2 – OSRAM DATA MIGRATION
SAP PLM INFO DAYS
Go Live Wave 1 Planning Wave 2
OSRAM Continental |
8. SUMMARY
NAME OF THE PRESENTATION | MONTH DAY, YEAR 18
LESSONS LEARNED
SAP PLM INFO DAYS
• Model Company approach speeds up specification and implementation (hybrid project methodology)
• Easy move to S/4HANA environment
• Covering the challenge of a new and growing organization, new process and system implementation
• “White card” by management
• “Start up” spirit coming along with a high acceptance level
• Challenging data carve out in respect of legal, data separation and data download from mother company systems
OSRAM Continental |
THANK YOU!
19SAP PLM INFO DAYS
ANDREAS BRECKELOSRAM Continental GmbHHead of Information TechnologyResearch & Development
ELKE WIMMEROSRAM Continental GmbHIT R&DSAP PLM Project Manager