Click here to load reader
Upload
julianne-ramoneda
View
50
Download
3
Embed Size (px)
DESCRIPTION
construction
Citation preview
Activity ID Activity Name OriginalDuration
AL MUSSAFAH AAL MUSSAFAH AHALIA HOSPITALAL MUSSAFAH AHALIA HOSPITALPROJECT BENPROJECT BENCHMARK DATESPROJECT BENCHMARK DATES
XXX-0000 Commencement Date/Site Possession 0
XXX-0010 Receipt of Contract Documents & IFC Drawings 0
XXX-0020 Receipt of Building Permit 0
XXX-0030 Completion of Sub-Structure 0
XXX-0040 Completion of Superstructure 0
XXX-0050 Completion of MEP Works 0
XXX-0060 Completion of Finishes 0
XXX-0070 Project Completion 0
XXX-0080 Power On 0
GENERAL WOGENERAL WORKSGENERAL WORKSMOBILIZATION MOBILIZATION AND PREPERATORY WORKSMOBILIZATION AND PREPERATORY WORKS
PRE-0010 Mobilization 62
PRE-0020 Installation of Temp. Site O ffices and Facilities 55
PRE-0030 Pre-Construction Survey and Site Setting Out 5
PRE-0040 Geotechnical Soil Investigation 18
PRE-0050 Demolish Existing Building and Site Clearance 31
PRE-0060 Install Tower Cranes 27
TECHNICAL SUTECHNICAL SUBMITTALS & APPROVALSTECHNICAL SUBMITTALS & APPROVALSSUBMITTALSSUBMITTALSSUBMITTALS
PRE-1010 Prepare and Submit QC/QC and Safety Plans 31
PRE-1020 Prepare and Submit Construction Schedule 31
PRE-1030 Prepare and Submit Construction Methodologies 289
PRE-1040 Prepare and Submit Civil/Structural Materials 304
PRE-1050 Prepare and Submit MEP Materials and Equipment 304
PRE-1060 Prepare and Submit Conveying System 61
PRE-1070 Prepare and Submit Finishing Materials 151
PRE-1080 Prepare and Submit Shop Drawings 389
PRE-1090 Prepare and Submit As-Built Drawings 250
REVIEW AND AREVIEW AND APPROVALSREVIEW AND APPROVALSPRE-2010 Review and Approval of QC/QC and Safety Plans 31
PRE-2020 Review and Approval of Construction Schedule 31
PRE-2030 Review and Approval of Construction Methodologies 289
PRE-2040 Review and Approval of Civil/Structural Materials 304
PRE-2050 Review and Approval of MEP Materials and Equipment 304
PRE-2060 Review and Approval of Conveying System 61
PRE-2070 Review and Approval of Finishing Materials 151
PRE-2080 Review and Approval of Shop Drawings 389
PRE-2090 Review and Approval of As-built Drawings 250
PROCUREMENPROCUREMENT OF LONG LEAD ITEMSPROCUREMENT OF LONG LEAD ITEMSXXX-1020 Procurement of Conveying Systems 209
CONSTRUCTIOCONSTRUCTIONCONSTRUCTIONSTRUCTURAL STRUCTURAL WORKSSTRUCTURAL WORKS
SUB-0000 Start Structural Works 0
SUB-0005 Finish Structural Works 0
SUBSTRUCTUSUBSTRUCTURESUBSTRUCTUREPILING WORPILING WORKSPILING WORKS
SUB-0010 Exacavate to Platform Level for Bored Piling Operation 12
SUB-0015 Mobilization of Drilling Rigs (by Sub-Contractor. 12
SUB-0020 Bored Piling Operation and Pile Test 60
SUB-0030 Excavate up to Bottom of Pile Caps 30
SUB-0040 Trimming and Treatment of Pile Heads 30
SUB-0050 Fill/Compact Working Platform for Secant Piling Operation 12
SUB-0060 Secant Pile Retaining Walls 40
SUB-0070 Construct Capping Beam for Secant Pile Retaining Walls 40
SUB-0080 Parking Area - Install Suitable De-watering System (If Required) 16
CAR PARKINGCAR PARKING AREA - BASEMENT 2CAR PARKING AREA - BASEMENT 2SUB-1010 Excavation Inside Cofferdam 26
SUB-1020 Spray Gunite on Secant Pile Retaining Wall Surfaces 20
SUB-1030 Blinding and Waterproofing under Base Slab 12
SUB-1040 Waterproofing on Retaining Walls 16
SUB-1050 Construct Base Slab 20
SUB-1051 Construct Base Slab (Part 1) 7
SUB-1052 Construct Base Slab (Part 2) 7
SUB-1053 Construct Base Slab (Part 3) 7
SUB-1054 Construct Base Slab (Part 4) 7
SUB-1060 Construct Perimeter Walls, Internal Walls and Columns 20
SUB-1070 Construct Water Tank Walls and Columns (1st Lift) 10
SUB-1080 Construct Water Tank Walls and Columns (2nd Lift) 12
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month
Commencement Date/Site Possession
Receipt of Contract Documents & IFC Drawings
Receipt of Building Permit
Completion of Sub-Structure
Completion of Superstructure
Completion of MEP Works
Completion of Finishes
Project Completion
Power On
Mobilization
Installation of Temp. Site O ffices and Facilities
Pre-Construction Survey and Site Setting Out
Geotechnical Soil Investigation
Demolish Existing Building and Site Clearance
Install Tower Cranes
Prepare and Submit QC/QC and Safety Plans
Prepare and Submit Construction Schedule
Prepare and Submit Construction Methodologies
Prepare and Submit Civil/Structural Materials
Prepare and Submit MEP Materials and Equipment
Prepare and Submit Conveying System
Prepare and Submit Finishing Materials
Prepare and Submit Shop Drawings
Prepare and Submit As-Built Drawings
Review and Approval of QC/QC and Safety Plans
Review and Approval of Construction Schedule
Review and Approval of Construction Methodologies
Review and Approval of Civil/Structural Materials
Review and Approval of MEP Materials and Equipment
Review and Approval of Conveying System
Review and Approval of Finishing Materials
Review and Approval of Shop Drawings
Review and Approval of As-built Drawings
Procurement of Conveying Systems
Start Structural Works
Finish Structural Works
Exacavate to Platform Level for Bored Piling Operation
Mobilization of Drilling Rigs (by Sub-Contractor.
Bored Piling Operation and Pile Test
Excavate up to Bottom of Pile Caps
Trimming and Treatment of Pile Heads
Fill/Compact Working Platform for Secant Piling Operation
Secant Pile Retaining Walls
Construct Capping Beam for Secant Pile Retaining Walls
Parking Area - Install Suitable De-watering System (If Required)
Excavation Inside Cofferdam
Spray Gunite on Secant Pile Retaining Wall Surfaces
Blinding and Waterproofing under Base Slab
Waterproofing on Retaining Walls
Construct Base Slab
Construct Base Slab (Part 1)
Construct Base Slab (Part 2)
Construct Base Slab (Part 3)
Construct Base Slab (Part 4)
Construct Perimeter Walls, Internal Walls and Columns
Construct Water Tank Walls and Columns (1st Lift)
Construct Water Tank Walls and Columns (2nd Lift)
Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone
Critical Milestone AMAH-1
AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE
1 of 4
Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER
Activity ID Activity Name OriginalDuration
SUB-1090 Construct Beams and Deck Slab @ -2.55 Level 18
SUB-1091 Construct Beams and Deck Slab @ -2.55 Level (Part 1) 10
SUB-1092 Construct Beams and Deck Slab @ -2.55 Level (Part 2) 10
SUB-1100 Construct Stairways and Ramp (from -5.55 to -2.55 Level) 10
CAR PARKINGCAR PARKING AREA - BASEMENT 1CAR PARKING AREA - BASEMENT 1SUB-2010 Waterproofing on Retaining Walls 10
SUB-2020 Construct Perimeter Walls, Internal Walls and Columns 16
SUB-2030 Construct Beams and Deck Slab @ +0.55 Level 16
SUB-2031 Construct Beams and Deck Slab @ +0.55 Level (Part 1) 10
SUB-2032 Construct Beams and Deck Slab @ +0.55 Level (Part 2) 10
SUB-2040 Construct Water Tank Roof Slab @ +0.55 Level 8
SUB-2050 Construct Stairways and Ramp (from -2.55 to +0.55 Level) 10
SUB-2060 Water Pr oofing to Water Tank External and Internal Surfaces 20
SUB-2070 Backfilling & Compaction Around Parking Aea to Finish Level 28
MAIN BUILDIMAIN BUILDING - BASEMENT FLOORMAIN BUILDING - BASEMENT FLOORSUB-3010 Blinding and Waterproofing under Pile Caps 15
SUB-3020 Construct Pile Caps 30
SUB-3030 Water Pr oofing at the Sides of Pile Caps 22
SUB-3040 Backfilling upto Bottom of Floor Slab 22
SUB-3050 Blinding and Waterproofing under Floor Slab 15
SUB-3060 Construct Basement Floor Slab 18
SUB-3070 Construct Perimeter Walls, Internal Walls and Columns 18
SUB-3080 Construct Beams and Deck Slab @ +0.60 F.F.L. 16
SUB-3081 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) 10
SUB-3082 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) 10
SUB-3083 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) 8
SUB-3090 Water Pr oofing at External Surfaces of Perimeter Walls 20
SUB-3100 Backfilling & Compaction Around Basement Floor to Finish Level 28
SUB-3110 Construct Stairways and Ramp (from -3.25 to +0.60 Level) 24
SUPERSTRUCSUPERSTRUCTURESUPERSTRUCTURECAR PARKINGCAR PARKING AREA - GROUND FLOORCAR PARKING AREA - GROUND FLOOR
SUP-0010 Construct Lift Shaft, Pump Room and Medical Gas Room 30
SUP-0020 Construct Columns at Service Block Area 12
SUP-0030 Construct Roof Slab at Sevice Block Area 18
SUP-0040 Construct Roof Parapet Walls at Sevice Block Area 10
MAIN BUILDIMAIN BUILDING - GROUND FLOORMAIN BUILDING - GROUND FLOORSUP-1010 Construct Internal Walls and Columns 18
SUP-1020 Construct Beams and Deck Slab @ +5.40 Level 18
SUP-1021 Construct Beams and Deck Slab @ +5.40 Level (Part 1) 10
SUP-1022 Construct Beams and Deck Slab @ +5.40 Level (Part 2) 10
SUP-1023 Construct Beams and Deck Slab @ +5.40 Level (Part 3) 8
SUP-1030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 1ST FLOORMAIN BUILDING - 1ST FLOORSUP-2010 Construct Internal Walls and Columns 18
SUP-2020 Construct Beams and Deck Slab @ +9.60 Level 18
SUP-2021 Construct Beams and Deck Slab @ +9.60 Level (Part 1) 10
SUP-2022 Construct Beams and Deck Slab @ +9.60 Level (Part 2) 10
SUP-2023 Construct Beams and Deck Slab @ +5.40 Level (Part 3) 8
SUP-2030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 2ND FLOORMAIN BUILDING - 2ND FLOORSUP-3010 Construct Internal Walls and Columns 18
SUP-3020 Construct Beams and Deck Slab @ +13.80 Level 18
SUP-3021 Construct Beams and Deck Slab @ +13.80 Level (Part 1) 10
SUP-3022 Construct Beams and Deck Slab @ +13.80 Level (Part 2) 10
SUP-3023 Construct Beams and Deck Slab @ +13.80 Level (Part 3) 8
SUP-3030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 3RD FLOORMAIN BUILDING - 3RD FLOORSUP-4010 Construct Internal Walls and Columns 18
SUP-4020 Construct Beams and Deck Slab @ +18.00 Level 18
SUP-4021 Construct Beams and Deck Slab @ +18.00 Level (Part 1) 10
SUP-4022 Construct Beams and Deck Slab @ +18.00 Level (Part 2) 10
SUP-4023 Construct Beams and Deck Slab @ +18.00 Level (Part 3) 8
SUP-4030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 4TH FLOORMAIN BUILDING - 4TH FLOORSUP-5010 Construct Internal Walls and Columns 18
SUP-5020 Construct Beams and Deck Slab @ +22.20 Level 18
SUP-5021 Construct Beams and Deck Slab @ +22.20 Level (Part 1) 10
SUP-5022 Construct Beams and Deck Slab @ +22.20 Level (Part 2) 10
SUP-5023 Construct Beams and Deck Slab @ +22.20 Level (Part 3) 8
SUP-5030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 5TH FLOORMAIN BUILDING - 5TH FLOORSUP-6010 Construct Internal Walls and Columns 18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month
Construct Beams and Deck Slab @ -2.55 Level
Construct Beams and Deck Slab @ -2.55 Level (Part 1)
Construct Beams and Deck Slab @ -2.55 Level (Part 2)
Construct Stairways and Ramp (from -5.55 to -2.55 Level)
Waterproofing on Retaining Walls
Construct Perimeter Walls, Internal Walls and Columns
Construct Beams and Deck Slab @ +0.55 Level
Construct Beams and Deck Slab @ +0.55 Level (Part 1)
Construct Beams and Deck Slab @ +0.55 Level (Part 2)
Construct Water Tank Roof Slab @ +0.55 Level
Construct Stairways and Ramp (from -2.55 to +0.55 Level)
Water Proofing to Water Tank External and Internal Surfaces
Backfilling & Compaction Around Parking Aea to Finish Level
Blinding and Waterproofing under Pile Caps
Construct Pile Caps
Water Proofing at the Sides of Pile Caps
Backfilling upto Bottom of Floor Slab
Blinding and Waterproofing under F loor Slab
Construct Basement Floor Slab
Construct Perimeter Walls, Internal Walls and Columns
Construct Beams and Deck Slab @ +0.60 F.F.L.
Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1)
Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2)
Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3)
Water Pr oofing at External Surfaces of Perimeter Walls
Backfilling & Compaction Around Basement Floor to Finish Level
Construct Stairways and Ramp (from -3.25 to +0.60 Level)
Construct Lift Shaft, Pump Room and Medical Gas Room
Construct Columns at Service Block Area
Construct Roof Slab at Sevice Block Area
Construct Roof Parapet Walls at Sevice Block Area
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +5.40 Level
Construct Beams and Deck Slab @ +5.40 Level (Part 1)
Construct Beams and Deck Slab @ +5.40 Level (Part 2)
Construct Beams and Deck Slab @ +5.40 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +9.60 Level
Construct Beams and Deck Slab @ +9.60 Level (Part 1)
Construct Beams and Deck Slab @ +9.60 Level (Part 2)
Construct Beams and Deck Slab @ +5.40 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +13.80 Level
Construct Beams and Deck Slab @ +13.80 Level (Part 1)
Construct Beams and Deck Slab @ +13.80 Level (Part 2)
Construct Beams and Deck Slab @ +13.80 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +18.00 Level
Construct Beams and Deck Slab @ +18.00 Level (Part 1)
Construct Beams and Deck Slab @ +18.00 Level (Part 2)
Construct Beams and Deck Slab @ +18.00 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +22.20 Level
Construct Beams and Deck Slab @ +22.20 Level (Part 1)
Construct Beams and Deck Slab @ +22.20 Level (Part 2)
Construct Beams and Deck Slab @ +22.20 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone
Critical Milestone AMAH-1
AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE
2 of 4
Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER
Activity ID Activity Name OriginalDuration
SUP-6020 Construct Beams and Deck Slab @ +26.40 Level 18
SUP-6021 Construct Beams and Deck Slab @ +26.40 Level (Part 1) 10
SUP-6022 Construct Beams and Deck Slab @ +26.40 Level (Part 2) 10
SUP-6023 Construct Beams and Deck Slab @ +26.40 Level (Part 3) 8
SUP-6030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 6TH FLOORMAIN BUILDING - 6TH FLOORSUP-7010 Construct Internal Walls and Columns 18
SUP-7020 Construct Beams and Deck Slab @ +30.60 Level 18
SUP-7021 Construct Beams and Deck Slab @ +30.60 Level (Part 1) 10
SUP-7022 Construct Beams and Deck Slab @ +30.60 Level (Part 2) 10
SUP-7023 Construct Beams and Deck Slab @ +30.60 Level (Part 3) 8
SUP-7030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - 7TH FLOORMAIN BUILDING - 7TH FLOORSUP-8010 Construct Internal Walls and Columns 18
SUP-8020 Construct Beams and Deck Slab @ +34.80 Level 18
SUP-8021 Construct Beams and Deck Slab @ +34.80 Level (Part 1) 10
SUP-8022 Construct Beams and Deck Slab @ +34.80 Level (Part 2) 10
SUP-8023 Construct Beams and Deck Slab @ +34.80 Level (Part 3) 8
SUP-8030 Construct Stairways 14
MAIN BUILDIMAIN BUILDING - ROOF AND TOP ROOF FLOORMAIN BUILDING - ROOF AND TOP ROOF FLOORSUP-8040 Construct Internal Walls and Columns 8
SUP-8050 Construct Beams and Deck Slab @ +38.30 Level 9
SUP-8060 Construct Stairways 8
CIVIL/ARCHITECIVIL/ARCHITECTURAL WORKSCIVIL/ARCHITECTURAL WORKSCIV-0000 Start Civil/Architectural Works 0
CIV-0005 Finish Civil/Architectural Works 0
MASONRY WOMASONRY WORKSMASONRY WORKSCIV-0010 Blockworks and Plastering Works 201
CIV-0020 Boundary Walls 61
CIV-0030 Installation External Curb Stone and Paving Blocks 31
THERMAL ANDTHERMAL AND MOISTURE PROTECTIONTHERMAL AND MOISTURE PROTECTIONCIV-1010 Waterproofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..) 231
CIV-1020 Waterproofing Works to External Surfaces 234
CIV-1030 Waterproofing Works to Roof Areas 61
FINISHING WOFINISHING WORKSFINISHING WORKSCIV-2010 Install Curtain Walls (Composite Aluminum Section and Glazing) 214
CIV-2020 Wall Finishes 214
CIV-2030 Ceiling Finishes 214
CIV-2040 Floor Finishes 214
CIV-2050 Painting Works 214
CIV-2060 Install Sanitary Fittings (Sanitary ware and Tapware) 153
CIV-2070 Other External Finishing Works 132
DOORS AND WDOORS AND WINDOWSDOORS AND WINDOWSCIV-3010 Install Powder Coated Aluminun Doors 214
CIV-3020 Install Fire Rated Wooden Doors 214
CIV-3030 Install Powder Coated Aluminum Windows 214
CIV-3040 Install Aluminum Louver Doors 138
CIV-3050 Install Electrically Operated Sliding Doors 107
CIV-3060 Instal Door Ironmongery 91
MISCELANEUOMISCELANEUOUS METAL WORKSMISCELANEUOUS METAL WORKSCIV-4010 Install Epoxy Coated Aluminum Pipe Handrails 214
CIV-4020 Install Aluminum Powder Coated Ramp Railing 31
CIV-4030 Install Aluminum Ladder Stair for Basement Floor 30
CIV-4040 Install Galvanized Ladder Stair from Roof to Top Roof 31
CIV-4050 Install Access Panel for Services Type SD1 and SD2 123
CIV-4060 Install Aluminum Kitchen Cabinet 122
CIV-4070 Install Epoxy Coated Wrought Iron for External Fence 61
CIV-4080 Install Barrier for External Access to Basement Electrical Operator 30
CIV-4090 Install Automatic Barrier and Electrical Operated Steel Gates 61
CIV-4100 Install External Galvanized Flag Pipe 20
WOOD WORKSWOOD WORKSWOOD WORKSCIV-5010 Install Bumper Guards and Corner Protection 78
CIV-5020 Install Counters for Reception and Nurse Station 200
CIV-5030 Install Corridor Handrail 153
MEP WORKSMEP WORKSMEP WORKSMEP-0000 Start MEP Works 0
AIR-CONTIONIAIR-CONTIONING AND VENTILATION SYSTEMAIR-CONTIONING AND VENTILATION SYSTEMMEP-0010 Chilled Water and Air Distribution System 242
MEP-0020 Install Galvanized Steel Sheet Rectangular Duct Works. 242
MEP-0030 Install Ventillation System 242
MEP-0040 Install Building Managemenrt System (BMS) 214
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month
Construct Beams and Deck Slab @ +26.40 Level
Construct Beams and Deck Slab @ +26.40 Level (Part 1)
Construct Beams and Deck Slab @ +26.40 Level (Part 2)
Construct Beams and Deck Slab @ +26.40 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +30.60 Level
Construct Beams and Deck Slab @ +30.60 Level (Part 1)
Construct Beams and Deck Slab @ +30.60 Level (Part 2)
Construct Beams and Deck Slab @ +30.60 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +34.80 Level
Construct Beams and Deck Slab @ +34.80 Level (Part 1)
Construct Beams and Deck Slab @ +34.80 Level (Part 2)
Construct Beams and Deck Slab @ +34.80 Level (Part 3)
Construct Stairways
Construct Internal Walls and Columns
Construct Beams and Deck Slab @ +38.30 Level
Construct Stairways
Start Civil/Architectural Works
Finish Civil/Architectural Works
Blockworks and Plastering Works
Boundary Walls
Installation External Curb Stone and Paving Blocks
Waterproofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..)
Waterproofing Works to External Surfaces
Waterproofing Works to Roof Areas
Install Curtain Walls (Composite Aluminum Section and Glazing)
Wall Finishes
Ceiling Finishes
Floor Finishes
Painting Works
Install Sanitary Fittings (Sanitary ware and Tapware)
Other External Finishing Works
Install Powder Coated Aluminun Doors
Install Fire Rated Wooden Doors
Install Powder Coated Aluminum Windows
Install Aluminum Louver Doors
Install Electrically Operated Sliding Doors
Instal Door Ironmongery
Install Epoxy Coated Aluminum Pipe Handrails
Install Aluminum Powder Coated Ramp Railing
Install Aluminum Ladder Stair for Basement Floor
Install Galvanized Ladder Stair from Roof to Top Roof
Install Access Panel for Services Type SD1 and SD2
Install Aluminum Kitchen Cabinet
Install Epoxy Coated Wrought Iron for External Fence
Install Barrier for External Access to Basement Electrical Operator
Install Automatic Barrier and Electrical Operated Steel Gates
Install External Galvanized Flag Pipe
Install Bumper Guards and Corner Protection
Install Counters for Reception and Nurse Station
Install Corridor Handrail
Start MEP Works
Chilled Water and Air Distribution System
Install Galvanized Steel Sheet Rectangular Duct Works.
Install Ventillation System
Install Building Managemenrt System (BMS)
Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone
Critical Milestone AMAH-1
AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE
3 of 4
Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER
Activity ID Activity Name OriginalDuration
MEP-0050 Install Air-Cooled Water Chillers and Pumps 92
MEP-0060 Install Fresh Air Handlling Units 61
MEP-0070 Roof Mounted Exhaust Fans 61
MEP-0080 Motor Control and Supply Distribution Panel 61
DRAINAGE ANDRAINAGE AND PLUMBING WORKSDRAINAGE AND PLUMBING WORKSMEP-1010 Installation of Internal Cold Water Pipes, Fittings and Valves 242
MEP-1020 Installation of Internal Hot Water Pipes, Fittings and Valves 242
MEP-1030 Installation of Internal Drainage Pipes and Fittings 242
MEP-1040 Installation of Drain Water Pipes and Manholes 137
MEP-1050 Install CWS Transfer Pump Set 92
MEP-1060 Install of Electric Water Heaters 92
MEP-1070 Install HWS Circulation Pump Set & CWS Booster Pump Set 92
MEP-1080 Install Central Water Filter incl. Pipes, Filter Pumps Automatic Control Panel 92
MEP-1090 Install Water Tanks Including Related Piping Works 92
MEP-1100 Install Drainage Pump Set 92
FIRE FIGHTINGFIRE FIGHTING SYSTEMFIRE FIGHTING SYSTEMMEP-2010 Install Fire Sprinkler System 242
MEP-2020 Install Fire Alarm and Fire Detection System 242
MEP-2030 Install FM-200 Clean Agent System 92
MEP-2040 Install Fire Water Pumps and Control Panels 76
MEP-2050 Install Portable Fire Extinguishers 76
MEDICAL GASMEDICAL GASESMEDICAL GASESMEP-3010 Installation Medical Gases 242
ELECTRICAL WELECTRICAL WORKSELECTRICAL WORKSMEP-4010 Install Power/Lighting Cables, Supports & Trays 242
MEP-4011 Install Electrical Service to Mechanical Works 242
MEP-4020 Install Main and Sub Distribution Boards including MCC 245
MEP-4030 Install 1500KVA Dry Type Transformer 92
MEP-4031 Install Stand by Generator 92
MEP-4040 Install Final Sub-Circuit, Fixtures and Accessories 199
MEP-4060 Install Lighting Fixtures 199
MEP-4070 Install Public Address & Voice Evacuation System 242
MEP-4080 Install SMATV System 242
MEP-4090 Telephone, Data (Structure Cabling) and CATV System 242
MEP-4100 Install Uninterruptable Power Supply (UPS) 242
MEP-4110 Install Earthing System 242
MEP-4120 Install Lightning Ptotection 90
MEP-4140 Install Nurse Call System 184
MEP-4150 Install IPTV System and Audio System 184
MEP-4160 Install CCTV System and Access Control System 184
CONVEYING SYCONVEYING SYSTEMCONVEYING SYSTEMCON-0000 Start Installation of Conveying System 0
CON-0010 Install Parking Lift Type (L3) 60
CON-0020 Install Bed Lifts Type (L1) 183
CON-0030 Install Passenger Lifts Type (L2) 183
CON-0040 Install Service Lifts Type (L4) 183
SPECIAL CONSSPECIAL CONSTRUCTIONSPECIAL CONSTRUCTIONSPC-0010 Install Car park Shade from Steel Pipe & Polypropylene Cover 101
PROVISIONAL PROVISIONAL ITEMS - INDICATIVE ONLYPROVISIONAL ITEMS - INDICATIVE ONLYSPC-0015 Install Swimming Pool System in 7th Floor 150
SPC-0020 Install Window Washing System 101
SPC-0030 Install Kitchen Equipment with Freezer, Fridge and Oven 101
SPC-0040 Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machine
101
SPC-0060 Install Stainless Steel Design Space Frame for Building Facade' 71
TESTING, COMTESTING, COMMISSIONING AND POWER ONTESTING, COMMISSIONING AND POWER ONTST-0000 Install Temporary Power & Water Supply 20
TST-0010 Testing and Commissioning 24
TST-0020 Inspection/Snags and Approvals 14
TST-0030 Temporary Power ON 0
TST-0040 Final Inspection and Approval 6
TST-0050 Connection to Main Services (by Statutory) 6
TST-0060 Building Completion Certificate 6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month
Install Air-Cooled Water Chillers and Pumps
Install Fresh Air Handlling Units
Roof Mounted Exhaust Fans
Motor Control and Supply Distribution Panel
Installation of Internal Cold Water Pipes, F it tings and Valves
Installation of Internal Hot Water Pipes, F it tings and Valves
Installation of Internal Drainage Pipes and Fittings
Installation of Drain Water Pipes and Manholes
Install CWS Transfer Pump Set
Install of Electric Water Heaters
Install HWS Circulation Pump Set & CWS Booster Pump Set
Install Central Water Filter incl. Pipes, Filter Pumps Automatic Control Panel
Install Water Tanks Including Related Piping Works
Install Drainage Pump Set
Install Fire Sprinkler System
Install Fire Alarm and Fire Detection System
Install FM-200 Clean Agent System
Install Fire Water Pumps and Control Panels
Install Portable Fire Extinguishers
Installation Medical Gases
Install Power/Lighting Cables, Supports & Trays
Install Electrical Service to Mechanical Works
Install Main and Sub Distribution Boards including MCC
Install 1500KVA Dry Type Transformer
Install Stand by Generator
Install Final Sub-Circuit, Fixtures and Accessories
Install Lighting Fixtures
Install Public Address & Voice Evacuation System
Install SMATV System
Telephone, Data (Structure Cabling) and CATV System
Install Uninterruptable Power Supply (UPS)
Install Earthing System
Install Lightning Ptotection
Install Nurse Call System
Install IPTV System and Audio System
Install CCTV System and Access Control System
Start Installation of Conveying System
Install Parking Lift Type (L3)
Install Bed Lifts Type (L1)
Install Passenger Lifts Type (L2)
Install Service Lifts Type (L4)
Install Car park Shade from Steel Pipe & Polypropylene Cover
Install Swimming Pool System in 7th Floor
Install Window Washing System
Install Kitchen Equipment with Freezer, Fridge and Oven
Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machine
Install Stainless Steel Design Space Frame for Building Facade'
Install Temporary Power & Water Supply
Testing and Commissioning
Inspection/Snags and Approvals
Temporary Power ON
Final Inspection and Approval
Connection to Main Services (by Statutory)
Building Completion Certificate
Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone
Critical Milestone AMAH-1
AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE
4 of 4
Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER