Activity ID Activity Name OriginalDuration

AL MUSSAFAH AAL MUSSAFAH AHALIA HOSPITALAL MUSSAFAH AHALIA HOSPITALPROJECT BENPROJECT BENCHMARK DATESPROJECT BENCHMARK DATES

XXX-0000 Commencement Date/Site Possession 0

XXX-0010 Receipt of Contract Documents & IFC Drawings 0

XXX-0020 Receipt of Building Permit 0

XXX-0030 Completion of Sub-Structure 0

XXX-0040 Completion of Superstructure 0

XXX-0050 Completion of MEP Works 0

XXX-0060 Completion of Finishes 0

XXX-0070 Project Completion 0

XXX-0080 Power On 0

GENERAL WOGENERAL WORKSGENERAL WORKSMOBILIZATION MOBILIZATION AND PREPERATORY WORKSMOBILIZATION AND PREPERATORY WORKS

PRE-0010 Mobilization 62

PRE-0020 Installation of Temp. Site O ffices and Facilities 55

PRE-0030 Pre-Construction Survey and Site Setting Out 5

PRE-0040 Geotechnical Soil Investigation 18

PRE-0050 Demolish Existing Building and Site Clearance 31

PRE-0060 Install Tower Cranes 27

TECHNICAL SUTECHNICAL SUBMITTALS & APPROVALSTECHNICAL SUBMITTALS & APPROVALSSUBMITTALSSUBMITTALSSUBMITTALS

PRE-1010 Prepare and Submit QC/QC and Safety Plans 31

PRE-1020 Prepare and Submit Construction Schedule 31

PRE-1030 Prepare and Submit Construction Methodologies 289

PRE-1040 Prepare and Submit Civil/Structural Materials 304

PRE-1050 Prepare and Submit MEP Materials and Equipment 304

PRE-1060 Prepare and Submit Conveying System 61

PRE-1070 Prepare and Submit Finishing Materials 151

PRE-1080 Prepare and Submit Shop Drawings 389

PRE-1090 Prepare and Submit As-Built Drawings 250

REVIEW AND AREVIEW AND APPROVALSREVIEW AND APPROVALSPRE-2010 Review and Approval of QC/QC and Safety Plans 31

PRE-2020 Review and Approval of Construction Schedule 31

PRE-2030 Review and Approval of Construction Methodologies 289

PRE-2040 Review and Approval of Civil/Structural Materials 304

PRE-2050 Review and Approval of MEP Materials and Equipment 304

PRE-2060 Review and Approval of Conveying System 61

PRE-2070 Review and Approval of Finishing Materials 151

PRE-2080 Review and Approval of Shop Drawings 389

PRE-2090 Review and Approval of As-built Drawings 250

PROCUREMENPROCUREMENT OF LONG LEAD ITEMSPROCUREMENT OF LONG LEAD ITEMSXXX-1020 Procurement of Conveying Systems 209

CONSTRUCTIOCONSTRUCTIONCONSTRUCTIONSTRUCTURAL STRUCTURAL WORKSSTRUCTURAL WORKS

SUB-0000 Start Structural Works 0

SUB-0005 Finish Structural Works 0

SUBSTRUCTUSUBSTRUCTURESUBSTRUCTUREPILING WORPILING WORKSPILING WORKS

SUB-0010 Exacavate to Platform Level for Bored Piling Operation 12

SUB-0015 Mobilization of Drilling Rigs (by Sub-Contractor. 12

SUB-0020 Bored Piling Operation and Pile Test 60

SUB-0030 Excavate up to Bottom of Pile Caps 30

SUB-0040 Trimming and Treatment of Pile Heads 30

SUB-0050 Fill/Compact Working Platform for Secant Piling Operation 12

SUB-0060 Secant Pile Retaining Walls 40

SUB-0070 Construct Capping Beam for Secant Pile Retaining Walls 40

SUB-0080 Parking Area - Install Suitable De-watering System (If Required) 16

CAR PARKINGCAR PARKING AREA - BASEMENT 2CAR PARKING AREA - BASEMENT 2SUB-1010 Excavation Inside Cofferdam 26

SUB-1020 Spray Gunite on Secant Pile Retaining Wall Surfaces 20

SUB-1030 Blinding and Waterproofing under Base Slab 12

SUB-1040 Waterproofing on Retaining Walls 16

SUB-1050 Construct Base Slab 20

SUB-1051 Construct Base Slab (Part 1) 7

SUB-1052 Construct Base Slab (Part 2) 7

SUB-1053 Construct Base Slab (Part 3) 7

SUB-1054 Construct Base Slab (Part 4) 7

SUB-1060 Construct Perimeter Walls, Internal Walls and Columns 20

SUB-1070 Construct Water Tank Walls and Columns (1st Lift) 10

SUB-1080 Construct Water Tank Walls and Columns (2nd Lift) 12

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month

Commencement Date/Site Possession

Receipt of Contract Documents & IFC Drawings

Receipt of Building Permit

Completion of Sub-Structure

Completion of Superstructure

Completion of MEP Works

Completion of Finishes

Project Completion

Power On

Mobilization

Installation of Temp. Site O ffices and Facilities

Pre-Construction Survey and Site Setting Out

Geotechnical Soil Investigation

Demolish Existing Building and Site Clearance

Install Tower Cranes

Prepare and Submit QC/QC and Safety Plans

Prepare and Submit Construction Schedule

Prepare and Submit Construction Methodologies

Prepare and Submit Civil/Structural Materials

Prepare and Submit MEP Materials and Equipment

Prepare and Submit Conveying System

Prepare and Submit Finishing Materials

Prepare and Submit Shop Drawings

Prepare and Submit As-Built Drawings

Review and Approval of QC/QC and Safety Plans

Review and Approval of Construction Schedule

Review and Approval of Construction Methodologies

Review and Approval of Civil/Structural Materials

Review and Approval of MEP Materials and Equipment

Review and Approval of Conveying System

Review and Approval of Finishing Materials

Review and Approval of Shop Drawings

Review and Approval of As-built Drawings

Procurement of Conveying Systems

Start Structural Works

Finish Structural Works

Exacavate to Platform Level for Bored Piling Operation

Mobilization of Drilling Rigs (by Sub-Contractor.

Bored Piling Operation and Pile Test

Excavate up to Bottom of Pile Caps

Trimming and Treatment of Pile Heads

Fill/Compact Working Platform for Secant Piling Operation

Secant Pile Retaining Walls

Construct Capping Beam for Secant Pile Retaining Walls

Parking Area - Install Suitable De-watering System (If Required)

Excavation Inside Cofferdam

Spray Gunite on Secant Pile Retaining Wall Surfaces

Blinding and Waterproofing under Base Slab

Waterproofing on Retaining Walls

Construct Base Slab

Construct Base Slab (Part 1)

Construct Base Slab (Part 2)

Construct Base Slab (Part 3)

Construct Base Slab (Part 4)

Construct Perimeter Walls, Internal Walls and Columns

Construct Water Tank Walls and Columns (1st Lift)

Construct Water Tank Walls and Columns (2nd Lift)

Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone

Critical Milestone AMAH-1

AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE

1 of 4

Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER

Page 2: Sample Schedule (5 Storey)

Activity ID Activity Name OriginalDuration

SUB-1090 Construct Beams and Deck Slab @ -2.55 Level 18

SUB-1091 Construct Beams and Deck Slab @ -2.55 Level (Part 1) 10

SUB-1092 Construct Beams and Deck Slab @ -2.55 Level (Part 2) 10

SUB-1100 Construct Stairways and Ramp (from -5.55 to -2.55 Level) 10

CAR PARKINGCAR PARKING AREA - BASEMENT 1CAR PARKING AREA - BASEMENT 1SUB-2010 Waterproofing on Retaining Walls 10

SUB-2020 Construct Perimeter Walls, Internal Walls and Columns 16

SUB-2030 Construct Beams and Deck Slab @ +0.55 Level 16

SUB-2031 Construct Beams and Deck Slab @ +0.55 Level (Part 1) 10

SUB-2032 Construct Beams and Deck Slab @ +0.55 Level (Part 2) 10

SUB-2040 Construct Water Tank Roof Slab @ +0.55 Level 8

SUB-2050 Construct Stairways and Ramp (from -2.55 to +0.55 Level) 10

SUB-2060 Water Pr oofing to Water Tank External and Internal Surfaces 20

SUB-2070 Backfilling & Compaction Around Parking Aea to Finish Level 28

MAIN BUILDIMAIN BUILDING - BASEMENT FLOORMAIN BUILDING - BASEMENT FLOORSUB-3010 Blinding and Waterproofing under Pile Caps 15

SUB-3020 Construct Pile Caps 30

SUB-3030 Water Pr oofing at the Sides of Pile Caps 22

SUB-3040 Backfilling upto Bottom of Floor Slab 22

SUB-3050 Blinding and Waterproofing under Floor Slab 15

SUB-3060 Construct Basement Floor Slab 18

SUB-3070 Construct Perimeter Walls, Internal Walls and Columns 18

SUB-3080 Construct Beams and Deck Slab @ +0.60 F.F.L. 16

SUB-3081 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) 10

SUB-3082 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) 10

SUB-3083 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) 8

SUB-3090 Water Pr oofing at External Surfaces of Perimeter Walls 20

SUB-3100 Backfilling & Compaction Around Basement Floor to Finish Level 28

SUB-3110 Construct Stairways and Ramp (from -3.25 to +0.60 Level) 24

SUPERSTRUCSUPERSTRUCTURESUPERSTRUCTURECAR PARKINGCAR PARKING AREA - GROUND FLOORCAR PARKING AREA - GROUND FLOOR

SUP-0010 Construct Lift Shaft, Pump Room and Medical Gas Room 30

SUP-0020 Construct Columns at Service Block Area 12

SUP-0030 Construct Roof Slab at Sevice Block Area 18

SUP-0040 Construct Roof Parapet Walls at Sevice Block Area 10

MAIN BUILDIMAIN BUILDING - GROUND FLOORMAIN BUILDING - GROUND FLOORSUP-1010 Construct Internal Walls and Columns 18

SUP-1020 Construct Beams and Deck Slab @ +5.40 Level 18

SUP-1021 Construct Beams and Deck Slab @ +5.40 Level (Part 1) 10

SUP-1022 Construct Beams and Deck Slab @ +5.40 Level (Part 2) 10

SUP-1023 Construct Beams and Deck Slab @ +5.40 Level (Part 3) 8

SUP-1030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 1ST FLOORMAIN BUILDING - 1ST FLOORSUP-2010 Construct Internal Walls and Columns 18

SUP-2020 Construct Beams and Deck Slab @ +9.60 Level 18

SUP-2021 Construct Beams and Deck Slab @ +9.60 Level (Part 1) 10

SUP-2022 Construct Beams and Deck Slab @ +9.60 Level (Part 2) 10

SUP-2023 Construct Beams and Deck Slab @ +5.40 Level (Part 3) 8

SUP-2030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 2ND FLOORMAIN BUILDING - 2ND FLOORSUP-3010 Construct Internal Walls and Columns 18

SUP-3020 Construct Beams and Deck Slab @ +13.80 Level 18

SUP-3021 Construct Beams and Deck Slab @ +13.80 Level (Part 1) 10

SUP-3022 Construct Beams and Deck Slab @ +13.80 Level (Part 2) 10

SUP-3023 Construct Beams and Deck Slab @ +13.80 Level (Part 3) 8

SUP-3030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 3RD FLOORMAIN BUILDING - 3RD FLOORSUP-4010 Construct Internal Walls and Columns 18

SUP-4020 Construct Beams and Deck Slab @ +18.00 Level 18

SUP-4021 Construct Beams and Deck Slab @ +18.00 Level (Part 1) 10

SUP-4022 Construct Beams and Deck Slab @ +18.00 Level (Part 2) 10

SUP-4023 Construct Beams and Deck Slab @ +18.00 Level (Part 3) 8

SUP-4030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 4TH FLOORMAIN BUILDING - 4TH FLOORSUP-5010 Construct Internal Walls and Columns 18

SUP-5020 Construct Beams and Deck Slab @ +22.20 Level 18

SUP-5021 Construct Beams and Deck Slab @ +22.20 Level (Part 1) 10

SUP-5022 Construct Beams and Deck Slab @ +22.20 Level (Part 2) 10

SUP-5023 Construct Beams and Deck Slab @ +22.20 Level (Part 3) 8

SUP-5030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 5TH FLOORMAIN BUILDING - 5TH FLOORSUP-6010 Construct Internal Walls and Columns 18

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month

Construct Beams and Deck Slab @ -2.55 Level

Construct Beams and Deck Slab @ -2.55 Level (Part 1)

Construct Beams and Deck Slab @ -2.55 Level (Part 2)

Construct Stairways and Ramp (from -5.55 to -2.55 Level)

Waterproofing on Retaining Walls

Construct Perimeter Walls, Internal Walls and Columns

Construct Beams and Deck Slab @ +0.55 Level

Construct Beams and Deck Slab @ +0.55 Level (Part 1)

Construct Beams and Deck Slab @ +0.55 Level (Part 2)

Construct Water Tank Roof Slab @ +0.55 Level

Construct Stairways and Ramp (from -2.55 to +0.55 Level)

Water Proofing to Water Tank External and Internal Surfaces

Backfilling & Compaction Around Parking Aea to Finish Level

Blinding and Waterproofing under Pile Caps

Construct Pile Caps

Water Proofing at the Sides of Pile Caps

Backfilling upto Bottom of Floor Slab

Blinding and Waterproofing under F loor Slab

Construct Basement Floor Slab

Construct Perimeter Walls, Internal Walls and Columns

Construct Beams and Deck Slab @ +0.60 F.F.L.

Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1)

Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2)

Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3)

Water Pr oofing at External Surfaces of Perimeter Walls

Backfilling & Compaction Around Basement Floor to Finish Level

Construct Stairways and Ramp (from -3.25 to +0.60 Level)

Construct Lift Shaft, Pump Room and Medical Gas Room

Construct Columns at Service Block Area

Construct Roof Slab at Sevice Block Area

Construct Roof Parapet Walls at Sevice Block Area

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +5.40 Level

Construct Beams and Deck Slab @ +5.40 Level (Part 1)

Construct Beams and Deck Slab @ +5.40 Level (Part 2)

Construct Beams and Deck Slab @ +5.40 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +9.60 Level

Construct Beams and Deck Slab @ +9.60 Level (Part 1)

Construct Beams and Deck Slab @ +9.60 Level (Part 2)

Construct Beams and Deck Slab @ +5.40 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +13.80 Level

Construct Beams and Deck Slab @ +13.80 Level (Part 1)

Construct Beams and Deck Slab @ +13.80 Level (Part 2)

Construct Beams and Deck Slab @ +13.80 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +18.00 Level

Construct Beams and Deck Slab @ +18.00 Level (Part 1)

Construct Beams and Deck Slab @ +18.00 Level (Part 2)

Construct Beams and Deck Slab @ +18.00 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +22.20 Level

Construct Beams and Deck Slab @ +22.20 Level (Part 1)

Construct Beams and Deck Slab @ +22.20 Level (Part 2)

Construct Beams and Deck Slab @ +22.20 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone

Critical Milestone AMAH-1

AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE

2 of 4

Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER

Page 3: Sample Schedule (5 Storey)

Activity ID Activity Name OriginalDuration

SUP-6020 Construct Beams and Deck Slab @ +26.40 Level 18

SUP-6021 Construct Beams and Deck Slab @ +26.40 Level (Part 1) 10

SUP-6022 Construct Beams and Deck Slab @ +26.40 Level (Part 2) 10

SUP-6023 Construct Beams and Deck Slab @ +26.40 Level (Part 3) 8

SUP-6030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 6TH FLOORMAIN BUILDING - 6TH FLOORSUP-7010 Construct Internal Walls and Columns 18

SUP-7020 Construct Beams and Deck Slab @ +30.60 Level 18

SUP-7021 Construct Beams and Deck Slab @ +30.60 Level (Part 1) 10

SUP-7022 Construct Beams and Deck Slab @ +30.60 Level (Part 2) 10

SUP-7023 Construct Beams and Deck Slab @ +30.60 Level (Part 3) 8

SUP-7030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - 7TH FLOORMAIN BUILDING - 7TH FLOORSUP-8010 Construct Internal Walls and Columns 18

SUP-8020 Construct Beams and Deck Slab @ +34.80 Level 18

SUP-8021 Construct Beams and Deck Slab @ +34.80 Level (Part 1) 10

SUP-8022 Construct Beams and Deck Slab @ +34.80 Level (Part 2) 10

SUP-8023 Construct Beams and Deck Slab @ +34.80 Level (Part 3) 8

SUP-8030 Construct Stairways 14

MAIN BUILDIMAIN BUILDING - ROOF AND TOP ROOF FLOORMAIN BUILDING - ROOF AND TOP ROOF FLOORSUP-8040 Construct Internal Walls and Columns 8

SUP-8050 Construct Beams and Deck Slab @ +38.30 Level 9

SUP-8060 Construct Stairways 8

CIVIL/ARCHITECIVIL/ARCHITECTURAL WORKSCIVIL/ARCHITECTURAL WORKSCIV-0000 Start Civil/Architectural Works 0

CIV-0005 Finish Civil/Architectural Works 0

MASONRY WOMASONRY WORKSMASONRY WORKSCIV-0010 Blockworks and Plastering Works 201

CIV-0020 Boundary Walls 61

CIV-0030 Installation External Curb Stone and Paving Blocks 31

THERMAL ANDTHERMAL AND MOISTURE PROTECTIONTHERMAL AND MOISTURE PROTECTIONCIV-1010 Waterproofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..) 231

CIV-1020 Waterproofing Works to External Surfaces 234

CIV-1030 Waterproofing Works to Roof Areas 61

FINISHING WOFINISHING WORKSFINISHING WORKSCIV-2010 Install Curtain Walls (Composite Aluminum Section and Glazing) 214

CIV-2020 Wall Finishes 214

CIV-2030 Ceiling Finishes 214

CIV-2040 Floor Finishes 214

CIV-2050 Painting Works 214

CIV-2060 Install Sanitary Fittings (Sanitary ware and Tapware) 153

CIV-2070 Other External Finishing Works 132

DOORS AND WDOORS AND WINDOWSDOORS AND WINDOWSCIV-3010 Install Powder Coated Aluminun Doors 214

CIV-3020 Install Fire Rated Wooden Doors 214

CIV-3030 Install Powder Coated Aluminum Windows 214

CIV-3040 Install Aluminum Louver Doors 138

CIV-3050 Install Electrically Operated Sliding Doors 107

CIV-3060 Instal Door Ironmongery 91

MISCELANEUOMISCELANEUOUS METAL WORKSMISCELANEUOUS METAL WORKSCIV-4010 Install Epoxy Coated Aluminum Pipe Handrails 214

CIV-4020 Install Aluminum Powder Coated Ramp Railing 31

CIV-4030 Install Aluminum Ladder Stair for Basement Floor 30

CIV-4040 Install Galvanized Ladder Stair from Roof to Top Roof 31

CIV-4050 Install Access Panel for Services Type SD1 and SD2 123

CIV-4060 Install Aluminum Kitchen Cabinet 122

CIV-4070 Install Epoxy Coated Wrought Iron for External Fence 61

CIV-4080 Install Barrier for External Access to Basement Electrical Operator 30

CIV-4090 Install Automatic Barrier and Electrical Operated Steel Gates 61

CIV-4100 Install External Galvanized Flag Pipe 20

WOOD WORKSWOOD WORKSWOOD WORKSCIV-5010 Install Bumper Guards and Corner Protection 78

CIV-5020 Install Counters for Reception and Nurse Station 200

CIV-5030 Install Corridor Handrail 153

MEP WORKSMEP WORKSMEP WORKSMEP-0000 Start MEP Works 0

AIR-CONTIONIAIR-CONTIONING AND VENTILATION SYSTEMAIR-CONTIONING AND VENTILATION SYSTEMMEP-0010 Chilled Water and Air Distribution System 242

MEP-0020 Install Galvanized Steel Sheet Rectangular Duct Works. 242

MEP-0030 Install Ventillation System 242

MEP-0040 Install Building Managemenrt System (BMS) 214

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month

Construct Beams and Deck Slab @ +26.40 Level

Construct Beams and Deck Slab @ +26.40 Level (Part 1)

Construct Beams and Deck Slab @ +26.40 Level (Part 2)

Construct Beams and Deck Slab @ +26.40 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +30.60 Level

Construct Beams and Deck Slab @ +30.60 Level (Part 1)

Construct Beams and Deck Slab @ +30.60 Level (Part 2)

Construct Beams and Deck Slab @ +30.60 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +34.80 Level

Construct Beams and Deck Slab @ +34.80 Level (Part 1)

Construct Beams and Deck Slab @ +34.80 Level (Part 2)

Construct Beams and Deck Slab @ +34.80 Level (Part 3)

Construct Stairways

Construct Internal Walls and Columns

Construct Beams and Deck Slab @ +38.30 Level

Construct Stairways

Start Civil/Architectural Works

Finish Civil/Architectural Works

Blockworks and Plastering Works

Boundary Walls

Installation External Curb Stone and Paving Blocks

Waterproofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..)

Waterproofing Works to External Surfaces

Waterproofing Works to Roof Areas

Install Curtain Walls (Composite Aluminum Section and Glazing)

Wall Finishes

Ceiling Finishes

Floor Finishes

Painting Works

Install Sanitary Fittings (Sanitary ware and Tapware)

Other External Finishing Works

Install Powder Coated Aluminun Doors

Install Fire Rated Wooden Doors

Install Powder Coated Aluminum Windows

Install Aluminum Louver Doors

Install Electrically Operated Sliding Doors

Instal Door Ironmongery

Install Epoxy Coated Aluminum Pipe Handrails

Install Aluminum Powder Coated Ramp Railing

Install Aluminum Ladder Stair for Basement Floor

Install Galvanized Ladder Stair from Roof to Top Roof

Install Access Panel for Services Type SD1 and SD2

Install Aluminum Kitchen Cabinet

Install Epoxy Coated Wrought Iron for External Fence

Install Barrier for External Access to Basement Electrical Operator

Install Automatic Barrier and Electrical Operated Steel Gates

Install External Galvanized Flag Pipe

Install Bumper Guards and Corner Protection

Install Counters for Reception and Nurse Station

Install Corridor Handrail

Start MEP Works

Chilled Water and Air Distribution System

Install Galvanized Steel Sheet Rectangular Duct Works.

Install Ventillation System

Install Building Managemenrt System (BMS)

Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone

Critical Milestone AMAH-1

AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE

3 of 4

Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER

Page 4: Sample Schedule (5 Storey)

Activity ID Activity Name OriginalDuration

MEP-0050 Install Air-Cooled Water Chillers and Pumps 92

MEP-0060 Install Fresh Air Handlling Units 61

MEP-0070 Roof Mounted Exhaust Fans 61

MEP-0080 Motor Control and Supply Distribution Panel 61

DRAINAGE ANDRAINAGE AND PLUMBING WORKSDRAINAGE AND PLUMBING WORKSMEP-1010 Installation of Internal Cold Water Pipes, Fittings and Valves 242

MEP-1020 Installation of Internal Hot Water Pipes, Fittings and Valves 242

MEP-1030 Installation of Internal Drainage Pipes and Fittings 242

MEP-1040 Installation of Drain Water Pipes and Manholes 137

MEP-1050 Install CWS Transfer Pump Set 92

MEP-1060 Install of Electric Water Heaters 92

MEP-1070 Install HWS Circulation Pump Set & CWS Booster Pump Set 92

MEP-1080 Install Central Water Filter incl. Pipes, Filter Pumps Automatic Control Panel 92

MEP-1090 Install Water Tanks Including Related Piping Works 92

MEP-1100 Install Drainage Pump Set 92

FIRE FIGHTINGFIRE FIGHTING SYSTEMFIRE FIGHTING SYSTEMMEP-2010 Install Fire Sprinkler System 242

MEP-2020 Install Fire Alarm and Fire Detection System 242

MEP-2030 Install FM-200 Clean Agent System 92

MEP-2040 Install Fire Water Pumps and Control Panels 76

MEP-2050 Install Portable Fire Extinguishers 76

MEDICAL GASMEDICAL GASESMEDICAL GASESMEP-3010 Installation Medical Gases 242

ELECTRICAL WELECTRICAL WORKSELECTRICAL WORKSMEP-4010 Install Power/Lighting Cables, Supports & Trays 242

MEP-4011 Install Electrical Service to Mechanical Works 242

MEP-4020 Install Main and Sub Distribution Boards including MCC 245

MEP-4030 Install 1500KVA Dry Type Transformer 92

MEP-4031 Install Stand by Generator 92

MEP-4040 Install Final Sub-Circuit, Fixtures and Accessories 199

MEP-4060 Install Lighting Fixtures 199

MEP-4070 Install Public Address & Voice Evacuation System 242

MEP-4080 Install SMATV System 242

MEP-4090 Telephone, Data (Structure Cabling) and CATV System 242

MEP-4100 Install Uninterruptable Power Supply (UPS) 242

MEP-4110 Install Earthing System 242

MEP-4120 Install Lightning Ptotection 90

MEP-4140 Install Nurse Call System 184

MEP-4150 Install IPTV System and Audio System 184

MEP-4160 Install CCTV System and Access Control System 184

CONVEYING SYCONVEYING SYSTEMCONVEYING SYSTEMCON-0000 Start Installation of Conveying System 0

CON-0010 Install Parking Lift Type (L3) 60

CON-0020 Install Bed Lifts Type (L1) 183

CON-0030 Install Passenger Lifts Type (L2) 183

CON-0040 Install Service Lifts Type (L4) 183

SPECIAL CONSSPECIAL CONSTRUCTIONSPECIAL CONSTRUCTIONSPC-0010 Install Car park Shade from Steel Pipe & Polypropylene Cover 101

PROVISIONAL PROVISIONAL ITEMS - INDICATIVE ONLYPROVISIONAL ITEMS - INDICATIVE ONLYSPC-0015 Install Swimming Pool System in 7th Floor 150

SPC-0020 Install Window Washing System 101

SPC-0030 Install Kitchen Equipment with Freezer, Fridge and Oven 101

SPC-0040 Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machine

101

SPC-0060 Install Stainless Steel Design Space Frame for Building Facade' 71

TESTING, COMTESTING, COMMISSIONING AND POWER ONTESTING, COMMISSIONING AND POWER ONTST-0000 Install Temporary Power & Water Supply 20

TST-0010 Testing and Commissioning 24

TST-0020 Inspection/Snags and Approvals 14

TST-0030 Temporary Power ON 0

TST-0040 Final Inspection and Approval 6

TST-0050 Connection to Main Services (by Statutory) 6

TST-0060 Building Completion Certificate 6

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27Month

Install Air-Cooled Water Chillers and Pumps

Install Fresh Air Handlling Units

Roof Mounted Exhaust Fans

Motor Control and Supply Distribution Panel

Installation of Internal Cold Water Pipes, F it tings and Valves

Installation of Internal Hot Water Pipes, F it tings and Valves

Installation of Internal Drainage Pipes and Fittings

Installation of Drain Water Pipes and Manholes

Install CWS Transfer Pump Set

Install of Electric Water Heaters

Install HWS Circulation Pump Set & CWS Booster Pump Set

Install Central Water Filter incl. Pipes, Filter Pumps Automatic Control Panel

Install Water Tanks Including Related Piping Works

Install Drainage Pump Set

Install Fire Sprinkler System

Install Fire Alarm and Fire Detection System

Install FM-200 Clean Agent System

Install Fire Water Pumps and Control Panels

Install Portable Fire Extinguishers

Installation Medical Gases

Install Power/Lighting Cables, Supports & Trays

Install Electrical Service to Mechanical Works

Install Main and Sub Distribution Boards including MCC

Install 1500KVA Dry Type Transformer

Install Stand by Generator

Install Final Sub-Circuit, Fixtures and Accessories

Install Lighting Fixtures

Install Public Address & Voice Evacuation System

Install SMATV System

Telephone, Data (Structure Cabling) and CATV System

Install Uninterruptable Power Supply (UPS)

Install Earthing System

Install Lightning Ptotection

Install Nurse Call System

Install IPTV System and Audio System

Install CCTV System and Access Control System

Start Installation of Conveying System

Install Parking Lift Type (L3)

Install Bed Lifts Type (L1)

Install Passenger Lifts Type (L2)

Install Service Lifts Type (L4)

Install Car park Shade from Steel Pipe & Polypropylene Cover

Install Swimming Pool System in 7th Floor

Install Window Washing System

Install Kitchen Equipment with Freezer, Fridge and Oven

Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machine

Install Stainless Steel Design Space Frame for Building Facade'

Install Temporary Power & Water Supply

Testing and Commissioning

Inspection/Snags and Approvals

Temporary Power ON

Final Inspection and Approval

Connection to Main Services (by Statutory)

Building Completion Certificate

Actual WorkRemaining WorkCritical Remaining WorkMilestoneActual Milestone

Critical Milestone AMAH-1

AL MUSSAFAH AHALIA HOSPITALPRELIMINARY SCHEDULE

4 of 4

Date Revision Checked Approved30-Nov-11 ISSUED FOR TENDER