Safetymanagement Dutch High-Speed Line. Integral Safety Case HSL-Zuid. Amsterdam. The Hague. Schiphol Airport. Rotterdam. Breda. Antwerp. Brussels. London Paris. Project Overview. 2 x 45 km new double track high speed line 5 connections with existing infra - PowerPoint PPT Presentation
Citation preview
Hans van Zwol Msc (Manager Integral Safety Case)
8 november 2005
Safetymanagement Dutch High-Speed Line
Integral Safety Case HSL-Zuid
8 november 2005
Safetymanagement Dutch High-Speed Line 2
Project Overview
• 2 x 45 km new double track high speed line
• 5 connections with existing infra• In a highly dens populated area• 170 civil constructions• Boarding at Amsterdam, Schiphol,
Rotterdam, Breda & The Hague• 35 km Motorway reconstructions• Maintenancecontract for 25 years• Transportationconcession for 15
years• Constructioncosts € 6.779 mln.*
*(source: Statusreport VGR 17)LondonParis
AmsterdamSchiphol Airport
Rotterdam
Antwerp
Brussels
Breda
The Hague
8 november 2005
Safetymanagement Dutch High-Speed Line 3
Integral Safetyplan HSL-Zuid
• Integral: complete transportation system
• Integral: pro-action, prevention, preparation, repression en aftercare (safety-chain)
• High ambition: better than existing infra
• Functional demands: space for optimizing designs
• Partnership throughout the project• Managing interfaces• Integral Safety Case
8 november 2005
Safetymanagement Dutch High-Speed Line 4
Integral Safety Case: decomposition to subsystems and integration of subsystems
Contracts Civils
Civil Contractors
Top level safety requirements for risk (societal and individual)and emergencies (timeframe for escape- and rescueprocess)
Contracts Systems
Infraspeed
Contracts Operator
HSA
Contracts Exploit.
Prorail
Decomposed safety requirements for each subsystem includingbasic safety measures (ERTMS, Tunnelventilation, track-access)
8 november 2005
Safetymanagement Dutch High-Speed Line 5
Interface and hazardmanagement
ISC Validation
Contract Contract Contract
Safety Case Safety CaseSafety CaseISC
Verification
mitigation mitigation
hazards hazards
Interface designs, Operating scenario’s,operational procedures andFunctional Hazard Analysis
hazards
mitigation
Top level requirements
8 november 2005
Safetymanagement Dutch High-Speed Line 6
Co-operation with Local Authoritiese.g. fire-brigades
• Safety-concept in early stage of the project
• One part A for entire line, different parts B for sections and objects
• Uniformity from border to A’dam
• Co-operation in design, realization, testing (and exploitation) as an interface-party.
• Different levels of decision making (local, regional, national)
8 november 2005
Safetymanagement Dutch High-Speed Line 7
Institutional setting (EU, national)
Admission
ProRailHigh Speed Alliance
RailwayInspectorate
Infra Speed
Access agreem
ent
Infrastructure Concession
Ministry of Transport
Transport Concession
IP-contract
LocalAuthorities
HSL-Zuid Integral Safety Case
8 november 2005
Safetymanagement Dutch High-Speed Line 8
Resuming
• Integral Safety Case anticipates on EU safety directive 2004/49
• Focus on safetytargets for infrastructure and transportation
• Focus on (safety) interfaces (systems, organizations and procedures)