85
1 CHAPTER I 1. INTRODUCTION 1.1 GENERAL Safety management system focuses on Identify action to prevent a recurrence of an accident or incident. Identify action to prevent an occurrence from happening Identify action based on trends from data of operations.

SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

Embed Size (px)

Citation preview

Page 1: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

1

CHAPTER I

1. INTRODUCTION

1.1 GENERAL

Safety management system focuses on

Identify action to prevent a recurrence of an accident or

incident.

Identify action to prevent an occurrence from happening

Identify action based on trends from data of operations.

Page 2: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

2

Fig 1.1: Safety Management System

About GIL

From the Gateway of India to India‟s first indigenously designed fast breeder reactor, Gammon

has become one of the world‟s largest physical infrastructure construction companies in India,

diversified into areas including infrastructure management, transmission lines and power sector.

SMS

Safety

performance

Framework

Safety data

Risk

management

Monitoring

&assessment

Continuous

improveme

nt

Safety

accountability

Page 3: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

3

As builders to the nation, the Company makes concrete contributions by designing and

constructing bridges, ports, thermal and nuclear power station, dams, high-rise structures,

international airports, cross country water, oil and gas pipelines, highways, chemical and

fertilizer complexes and environmental structures.

Year of establishment was 1922; Mr J. C. Gammon was the driving force behind the introduction

of prestressed concrete to India. His foresight was fundamental to the company reaching its

present stature. At present Mr. Abhijit Rajan is the Chairman and Managing Director of the

Company.

1.2 NEED OF THE STUDY

Construction industry makes significant contribution to nation economy and provides large

number of employment. As per the latest statistics released by CIDC, about 31 million people are

employed in construction sector in which close to 73% are unskilled laborers. Use of new

technologies and deployment of project management strategies has made it possible for this

industry to undertake mega projects inspite of facing number of challenges. Even though it is one

of the fastest growing sectors in India, it records maximum number of accidents and injuries than

any other industrial activity. In addition to cost of human injury and death, the accidents are

unduly expensive in terms of damage of property and delays in completion of project.

Working at height is work undertaken at a place where injury could occur should somebody fall

from it (even if it is at or below ground level) - often involving the use of scaffolds, ladders,

hoists, gantries or general roof work. Falls from height are the most common cause of fatal

injury, and the second most common cause of serious occupational injuries. Many of these

accidents could have been avoided if the right equipment had been available and correct working

practices put in place. In the construction industry in the India, falls are the leading cause of

worker fatalities. Each year, on average, between 150 and 200 workers are killed and more than

100,000 are injured as a result of falls at construction sites.

Page 4: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

4

Accidents in construction of cooling tower

Five labourers died in an accident at an under-construction power plant of Korba West Power Co

Limited in Raigrah district of Chhattisgarh Saturday morning. The labourers were on a 170-foot

high scaffolding built around a cooling tower of the power plant when the scaffolding came

crashing down. The victims were buried in the debris and cranes had to be used to recover the

bodies.

The Willow Island disaster was the collapse of a cooling tower under construction at a power

station at Willow Island, West Virginia, on Thursday, April 27, 1978. The falling concrete

caused the scaffolding to collapse. 51 construction workers were killed. It is thought to be the

largest construction accident in American history.

Construction fatality rates from falling from height

Table 1.1

Country/Region Fatalities (per Annum per 100,000 Workers) Year

India 150.3 2010

France 112.1 2010

Germany 115.4 2006

Ireland 18.0 2006

Italy 114.4 2008

Page 5: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

5

United Kingdom 13.4 2009/08

United States of America 10.8 2010

The Natural Draft Cooling Tower is a very high structure and due to its height and shape carries

a lot of hazards during the construction process and has a lot of chances of accidents .Most of

the accidents are due to workers falling from height or material falling from height. Hence there

is a need for study of the hazards present during the construction of a NDCT and give their

control measures in order to minimize the risks and prevent accidents.

1.2 OBJECTIVES OF THE STUDY

To identify the hazards present in the construction of NDCT

To identify the control measures to minimize the risks

To study about the Safety Management System followed in GIL, Raipur to control the

hazards.

To give recommendation for the improvement of the safety management system

Page 6: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

6

CHAPTER 2

2. LITERATURE REVIEW

2.1 OPERATIONS OF GIL

Besides its large scale of operations in the Construction and Infrastructure domain, Gammon has

a dominant presence in energy business in which it operates in the hydro, nuclear and thermal

power sectors. Gammon‟s association with the construction of nuclear power projects dates back

to 1959 when it completed the Pre-Stresses Concrete (PSC) Ball Tank of India‟s first Atomic

Reactor Plant in Trombay. Gammon‟s projects cover businesses and projects involving

highways, public utilities, environmental engineering and marine structures. Gammon‟s expertise

also covers the design, financing, construction and operation of modern bridges, viaducts, and

metro rail, both on a Built-Operate–Transfer (BOT) basis as well as contract execution. Gammon

is also active in the Social Infrastructure sector through its operations in the realty project

segment. Examples include residential complexes such as Pebble Bay and Godrej Woods Man

Estate in Bangalore, Godrej Kalyan in Mumbai, RNA Exotica, Mumbai; Hotel complexes such

as Hotel Leela Palace, Chennai and G Staad, Bangalore besides commercial complexes such as

Galleria Mall(INXS) in Bangalore. Gammon is also currently undertaking a major project for

ISKON at Sri Mayapur in West Bengal involving the construction of a temple complex and a

modern cultural centre.

Gammon international include a majority holding in Franco Tosi Meccanica, SAE Power lines,

and Sofinter group, Italy spanning the sectors of power and industrial boilers as well as waste

and environment management systems. Gammon has received accolades and recognitions from a

variety of reputed institutions. Examples include the Indian Concrete Institute Award for most

outstanding concrete structure presented for the segmental arch bridge across the River Beas

Page 7: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

7

(Himachal Pradesh) and the first prize for „Excellent Aesthetics‟ for the Vidyasagar Sethu

Project across the River Hoogly in Kolkata.

2.2 HISTORY

The beginning of such a formidable company is to be found in the vision of an equally

formidable man. Mr. J. C. Gammon was the driving force behind the introduction of pre-stressed

concrete to India. He designed the reinforced concrete piles of the Gateway of India. The

foundations of the arch reach deep into the bedrock. With time, he came to be known as the

„Sculptor of Concrete‟.

Areas of specialization of Gammon

Transportation

Power project

Transmission and distribution

Pipelines

Structures

Irrigation projects

Ground engineering and water supply

2.3 ABOUT THE PROJECT SITE

The cooling tower project at Raipur, Chhattisgarh was given to Gammon India Ltd by GMR

energy ltd, Chhattisgarh. The project work includes construction of two cooling towers of natural

draft counter flow type. Each cooling tower shall be designed to give desired re-cooled water

temperature under design conditions for full power operation of the unit. The NDCT package

cost is 126Cr and expenditure till date is 12.6 Cr. Readiness of unit 1 NDCT is 13.06.2013 and

unit 2 is 13.10.2013.

Following are the salient features of NDCT:

No. of NDCT‟s 2Nos

Page 8: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

8

Height of NDCT 165m

Diameter of NDCT at Bottom 124m

Diameter of NDCT at Top 70m

Qty. Of Circulating Water 87000 Cum/Hr

Hot Water Inlet Temp. 42 degree C

Re-cooled water Outlet Temp. 33 degree C

Total lift = 104, Height in one lift = 1.5mts, height of rekar column =9 mts

The width of concrete of Ring Beam = 1200 mm

The width of concrete of first lift = 1080 mm

The width of concrete of 2nd lift = 967 mm

The width of concrete of 3rd lift = 850 mm

The width of concrete of 4th lift-101th lift = 275 mm

The width of concrete of 102th lift = 375mm

The width of concrete of 103rd lift = 475mm

The width of concrete of 104th lift = 600 mm

Page 9: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

9

2.3.1 GMR PLANT LAYOUT

Fig2.1: GMR plant lay out

Total Excavation Qty in NDCT –I 22000cum

Total Reinforcement Quantity in Tower Foundation 350MT

Concrete Quantity in Tower cum Foundation 3910 MT

Pond wall/Pedestal Concrete Quantity 1160 cum.

Pond Floor Excavation Quantity 39000 cum

Pond wall/Pedestal Reinforcement Quantity 504 MT

Page 10: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

10

2.3.2 MAJOR SECTIONS OF THE SITE OF GIL

Batching plant

Storage Room

Fabrication Yard

NDCT construction area

2.4THEORY OF COOLING TOWER

Cooling towers are heat removal devices used to transfer process waste heat to the atmosphere.

Cooling towers may either use the evaporation of water to remove process heat and cool the

working fluid to near the wet-bulb air temperature or in the case of closed circuit dry cooling

towers, rely solely on air to cool the working fluid to near the dry-bulb air temperature. Common

applications include cooling the circulating water used in oil refineries, petrochemical and other

chemical plants, thermal power stations and HVAC systems for cooling buildings. Cooling

towers vary in size from small roof-top units to very large hyperboloid structures that can be up

to 200 meters tall and 100 meters in diameter, or rectangular structures that can be over 40

meters tall and 80 meters long. The hyperboloid cooling towers are often associated with nuclear

power plants, although they are also used to some extent in some large chemical and other

industrial plants. Although these large towers are very prominent, the vast majority of cooling

towers are much smaller, including many units installed on or near buildings to discharge heat

from air conditioning.

Classification of cooling towers

By build up

a) Packaged type

b) Field erected type

By heat transfer method

a) Dry cooling tower

b) Wet cooling tower

c) Closed circuit cooling tower

Page 11: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

11

By air flow generation method

1. Natural draft: Utilizes buoyancy via a tall chimney. Warm, moist air naturally rises due

to the density differential compared to the dry, cooler outside air. Warm moist air is less

dense than drier air at the same pressure. This moist air buoyancy produces an upwards

current of air through the tower.

2. Mechanical draft: Uses power-driven fan motors to force or draw air through the tower.

Induced draft: A mechanical draft tower with a fan at the discharge (at the top) which

pulls air up through the tower. The fan induces hot moist air out the discharge. This

produces low entering and high exiting air velocities, reducing the possibility of

recirculation in which discharged air flows back into the air intake. This fan/fin

arrangement is also known as draw-through.

Forced draft: A mechanical draft tower with a blower type fan at the intake. The fan

forces air into the tower, creating high entering and low exiting air velocities. The low

exiting velocity is much more susceptible to recirculation. With the fan on the air intake,

the fan is more susceptible to complications due to freezing conditions. Another

disadvantage is that a forced draft design typically requires more motor horsepower than

an equivalent induced draft design. The benefit of the forced draft design is its ability to

work with high static pressure. Such setups can be installed in more confined spaces and

even in some indoor situations. This fan/fill geometry is also known as blow through.

Fan assisted natural draft: A hybrid type that appears like a natural draft setup, though

airflow is assisted by a fan.

2.4.1 NATURAL DRAFT COOLING TOWER

For thermal power projects, the quantity of water being very large, natural draft cooling towers

are preferred; what‟s more, these are almost maintenance- free structures.

Natural draft (ND) cooling towers are majestic structures. These, in fact, have become a symbol

of power stations the world over. Their sheer size and shape make them exceptional; their design

involves considerable structural and thermo-dynamic analysis and studies. However, model

Page 12: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

12

studies need to be conducted before evolving their design and to ensure their performance. A

decrease in their efficiency from the designated range may render them unfit. During design, it

has to be stringently checked that the cooling tower is able to decrease the temperature of water

in a more-than-required quantity.

2.4.1.1 CONSTRUCTION EQUIPMENT

Cooling towers are of a large size, with a diameter in the range of a 100 m at the bottom. Their

foundations have a still larger diameter, in the range of 120 m. For such large area of

foundations, raft foundations are mostly found suitable. Only under exceptional circumstances,

as when the soil conditions are not good, are pile foundations along the periphery of cooling

towers chosen for provision. The depth of raft foundations is usually kept around 3-4 m.

Hydraulic excavators

The area of foundations being quite large and depth being 3-4 m, hydraulic excavators are most

suitable to excavate the large-sized pit to the required depth. Whenever hydraulic excavators are

used, care has to be taken to ensure that the bucket of the excavator doesn‟t cut the ground below

the required depth; otherwise, this extra cutting of soil has to be filled with concrete to provide a

solid base to foundations. In addition, tippers are required at the spot with the excavators for

transportation of excavated soil to a suitable place for its disposal.

Bar cutting and bending machines

Steel reinforcements need to be placed in the foundations, they are quite large and it is better to

use bar cutting and bending machines for this work. The same machines can later be used in

preparing the reinforcement for the cooling tower shell.

Concrete batching plant

It is generally not possible to pour the whole cooling tower raft in one pour, due to its large size.

The raft is therefore, divided into segments and poured either by supply of concrete from an

Page 13: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

13

existing concrete batching plant or by use of four or five concrete mixers for each segment.

Needle vibrators are constantly required for compaction of concrete in foundations; generally, M

20 concrete with low workability is used.

Concrete pedestals are located on the top of a circular raft for the cooling towers to provide a

solid base to the inclined columns rising at the bottom of the shell, and to create an air inlet area.

The pedestals are small structures involving around 100 cu m of concrete each; their number

varies depending upon the number of pairs of inclined columns. Each pedestal can be well

completed by using the bar bending and cutting machines for reinforcement and concrete mixers

for producing concrete. Steel formwork is used for these pedestals to minimize the leakage of

slurry.

For inclined columns

Inclined towers are the most typical component of a cooling tower, to be built with exact

precision. A slight change in their inclination alters the line of transfer of load from the shell to

the foundations and upsets calculations. The inclined columns are inclined sideways as well as to

the inside. Therefore, their layout should be done using high precision optical instruments. A

pipe scaffolding network is erected on firm ground to firmly support the shuttering for these

columns. Steel forms cutting the section in two halves are fabricated and used; these U-shaped or

semi-circular forms are easy to remove later. The forms have end flanges to be bolted in a tight

manner to make them leak-proof.

For first lift of shell

A ring beam over the inclined columns constitutes the first lift of the cooling tower shell. This

lift, in fact, acts as a starter for further laying lifts of the cooling tower shell by use of special

formwork. For the first lift, conventional scaffolding pipes and clamps are used to support the

steel shuttering and the working platform. Steel forms bent to match the true curvature of the

shell are fabricated for the inside and outside face of the shell. The ring beam for the full tower

can be laid in one go if sufficient equipment and formwork is available; in fact, it is preferable to

Page 14: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

14

lay it in one pour for a monolithic ring beam and for effective transfer of stresses. The equipment

required to lay the concrete of the ring beam run the gamut from scaffolds/staging pipes, rigid

and swivel clamps, joint pins, trough pins, base plates for pipes, vertical steel shuttering

fabricated to suit the inner and outer curvature of shell, steel plates for bottom of the ring beam,

turn buckles and side supports to keep the inner shuttering in position during pouring of concrete

and to resist concrete pressure, friction hoists to lift the buckets full of concrete to the working

platform, concrete mixers and needle vibrators, to optical instruments to check the alignment and

curvature of the ring beam and buckets and trolleys for concrete transportation.

For columns and beams

A cooling tower houses a large network of RCC columns and beams to create the supporting

structure for the cooling fills to be provided below the hot water inlet level. The level of entry of

hot water inside the cooling tower is at around 10-11 m above the ground. The cooling fill is

about 2 m below the level of its entry; thus, the fill base is about 8 to 9 m above ground level.

Adding to the depth of basin from the base of which the supporting columns are to rise, the

length of columns is in the range of 11 to 12 m. the columns are mostly rectangular in section

and erected at pre-decided locations to create a network of beams at fill level. The equipment

required in the pre-cast yard for RCC columns and beams includes steel moulds of required

sections and lengths of columns and beams, bar cutting and bending machine for preparing the

reinforcement for beams and columns, tilting type concrete mixers equipped with hoppers,

concrete carrying trolleys, needle vibrators, extra needles, curing arrangement set up including

installation of a deep bore well, provision of submersible pump, a GI pipe network for

distribution of water and hose pipes for manual sprinkling of water on the gunny bags covering

the pre-cast RCC members and mobile cranes of 10 t capacity to lift the pre-cast members from

the pre-cast yard and their unloading in the stacking cum curing yard. The cranes can be wheel-

mounted or crawler-mounted, though the latter ones are preferred. Also, low level steel trolleys

for carrying the pre-cast members from pre-cast yard to stacking yard, 25-tonne capacity trailers

for transportation of pre-cast columns and beams from the stacking yard to the inside of cooling

tower, friction hoists and manual winches for erection of RCC columns and beams inside the

Page 15: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

15

cooling towers and additional mobile cranes, (two or more), inside the cooling towers for

unloading of pre-cast members from the trailers to the ground, are required.

For shell construction

The total volume of concrete to be laid in the shell has to be worked out and the equipment

required decided accordingly. The construction of the cooling tower shell was earlier done by

conventional methods and it used to take long. These days, jump forms are used for the

construction of the shell. There is no need of removal and re-fixing of shuttering plates. These

slide up, both on the inner and outer faces, and are adjusted to suit the new inner and outer radii

of cooling tower. After the initial few lifts which require heavy concreting due to large diameter

and thickness, all further lifts can be laid in a single day, for the full periphery of the cooling

tower. This arrangement results in the construction of a 120 m high cooling tower in four to five

months, thus saving substantial time.

Jump forms

Jumpform equipment can be adjusted to suit uniform as well as variable dimensions. The

dimensions can increase or decrease as the structure is built. As the dimensions of a cooling

tower decrease up to throat level and increase thereafter, jumpform work suits it best because of

the facility it provides for adjustment to suit required parameters. Jumpform work has telescopic

railings provided on each deck to accommodate the reduction or increase in perimeter. Similarly,

the deck planks can also be adjusted. The top portion of the equipment is kept in mobile form so

that the concrete-pouring deck can be adjusted and locked in position near the periphery of the

structure. Diagonally installed spindles can adjust the form work to suit the actual profile of the

structure. Jump forms get their support for climbing from the structure itself and no scaffolding

pipe network is required to support them from the ground, nor are any layers of brackets

required, as used in conventional formwork. Anchor bolts are provided in the walls of the

structure, removed and re-fixed as the equipment rides up. Vertical rails are fixed all around the

perimeter of the structure and the equipment rides on these rails. Fixing of these rails is a

Page 16: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

16

continuous process and has to be ahead of the upward movement of the equipment. The task

seems simple but needs extra vigil to eliminate problems and bottlenecks.

Five decks

A five deck system is created in jump form work .The top deck facilitates concrete placement

and reinforcement binding work. The second deck is the main working deck for fixing shutters,

anchor bolts, form supports and sliding shutters. The work of alignment to the designed profile

of the structure, checking of parameters such as height, radius, curvature and thickness is also

carried out from this deck. The third deck allows rail extension for the upward movement of

equipment. The fourth deck is for the operation of hydraulic jacks and to ensure that the

equipment rigs are well locked in position. The fifth and last deck provides platforms for the

smooth finishing and painting of the structure. This five-tier system is provided both along the

inside as well as outside surfaces of the cooling tower.

Hydraulic system

The peripheral area of the cooling tower is divided into suitable number of segments with centre

to-centre spacing ranging from 3-8 m. Each hydraulic rig unit consists of a structural formwork

required to support the five-deck system, the shuttering form work and the hydraulic circuit. The

rig members include frames, holders, girders, longitudinal beams and bracings, handrails,

climbing rails and other steel sections and accessories. The structural framework units hang on to

the rail tracks by means of cradles. Rail tracks are fastened to the structure being built by anchor

bolts. Cradles ride up along the rails as and when the hydraulic circuit is operated, take along

with them the whole the structural framework. Each such framework carries two separate

hydraulic jacks that can be operated independently or jointly. In one stroke, the equipment rides

up by about 30 cm; each stroke hardly takes three to four minutes to operate. Power packs to

operate the hydraulic jacks are stationed on the lowermost deck. The number of jacks to be

operated by a power pack depends upon its capacity; however, it is feasible to operate 15-20

jacks through one power pack.

Page 17: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

17

Hydraulic power packs

Each power pack operates 15-20 hydraulic jacks. It is equipped with an electric motor of about

10 HP, 415 volts, 3 phase, of a reputed make like Crompton or ABB. The hydraulic pump has to

be of gear type, Bosch or some such make, with a flow capacity of 25-30 l/per minute. The

power pack should have a water cooler or heat exchanger, and oil filters in the return line. Oil

distribution and directional control valves should also be available in the pack. Oil tank of 200 l

or similar capacity should be provided.

Hydraulic hoses

The hydraulic hoses used for the transmission of hydraulic oil to the hydraulic jacks and back to

the pack should be tested under double working pressure. The bursting pressure shouldn‟t be less

than four times the working pressure. Generally, ½ inch internal diameter hoses are used. The

brand, Swastik or its equivalent should be clearly specified. The hydraulic connections should be

galvanized and tightened.

Hydraulic jacks

Hydraulic jacks used should be of double-acting type. The working pressure, cylinder inner bore

size, the stroke length, the ram diameter and the required jack capacity such as 6-10 tone, should

be worked out before providing jacks for the system. The jacks are provided both on the inner as

well as outer faces and hold the key to successful and trouble free working. A few spare jacks

should be kept at the site for replacements for leaking jacks, as such jacks refuse to take pressure

or load.

For concreting work

A tower crane should either be provided at the centre of the cooling tower for the transportation

of concrete and materials to the working deck, or diametrically opposite access towers can be

raised to facilitate concrete transportation to the top and to allow upward passage to the workers.

Page 18: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

18

A small passenger hoist can also be accommodated in these scaffolding towers. Suitable

arrangement should be made at the ground by positioning two or three mixers at each concrete

production point. The mixers can be located at ground level and provided with chutes to directly

unload the concrete in a common bucket placed over a low platform trolley moving on rails. The

trolley can be moved on the rails to the hoist point from where the buckets can be hoisted up to

the working deck. Such an arrangement can prove highly convenient and efficient.

Access towers

In case access towers are created at the site for hoisting of concrete buckets, passenger hoist and

to accommodate access ladders, huge quantities of scaffolding pipes and clamps will be required.

The length of scaffolding pipes is generally six meters, these are to be load- bearing, C class,

heavy duty, 48-60 mm in diameter, and in true plumb. Horizontal scaffolding pipes and diagonal

bracing pipes are also required. Rigid and swivel clamps are required in lakhs. Base plates for

verticals are needed to give them a wider area for dispersion of load, as are end-to-end pipe

couplers, to extend the verticals with the increase in the height of shell; two friction hoists to run

the concrete buckets to the unloading platforms created at the top and one hoist for the lifting of

materials. The hoists are to be of 5-7 tone capacity, single drum type, equipped with magnetic

brakes and use 16 mm diameter ropes. 16-22 mm diameter wire ropes are additionally required

as guide ropes for the concrete carrying buckets, as are D shackles, U-clamps, two sheave

pulleys to complete the running arrangement.

Passenger hoist

One passenger hoist is required to transport the engineers and workers to the platforms and back

to the ground level. The passenger hoist should always be of double drum type with magnetic

brakes, overload alarm and limit switches as safety guards. 22 mm diameter wire ropes should be

used to run the passenger cage. Guide ropes should keep the cage in position to avoid extra

swing or accidents. Equipment at the top deck, concrete unloading arrangements are to be

created by observing special safety measures against swaying of the buckets before tilting them

or opening their bottom flap. The scaffolding tower is to be well anchored to the completed

Page 19: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

19

portion of cooling tower and the platform receiving concrete well supported. Perforated pipes are

fixed along the outer and inner surfaces of the cooling tower to sprinkle water on the completed

portions. Booster pumps of 25 HP or so should be installed on the water tanks to lift water to

higher levels. Concrete vibrators are stationed on the working deck to fully compact the concrete

laid in the shell lifts. Plenty of spare needles should be kept available as they often need repair

and replacement during construction. Plate or form vibrators should be avoided as the work is

carried out at very high levels and high vibrations must not be allowed.

2.4.1.2Components of ND cooling tower

The following are the main components of a natural draft cooling tower:

1. Foundations

2. Cooling water basin

3. Column pedestals

4. Raker columns

5. Shell

6. Fill supporting structure

7. Fill

8. Water distribution pipe network

9. Spray nozzle network

10. Lighting system

11. Lightening protection system

12. Top platform

13. Ladders and access platforms

Page 20: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

20

Pedestrial wall Pond wall Rekar column Ring beam Footing

Fig2.2 Component of ND cooling tower

.

Page 21: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

21

CHAPTER 3

3. METHODOLOGY

3.1 GENERAL

The various procedures that are being followed to keep a check on safety at the construction

site include the following:

Safe Operating Procedure (SOP) / Methodology

HIRA (Hazard Identification and Risk Assessment) / JHA (Job Hazard Analysis)

Plant Safety Inspection

Environment Monitoring (Noise, Air & Water)

MSPR (Monthly Safety Performance Report)

Accident Investigation

Near miss and Incident reporting

Safety Committee

Safety Promotion Activity

Safety Audits as per IS

EMP (Emergency Management Plan)

Safety Alert

Traffic Management

3.2 SAFETY MANAGEMENT SYSTEM IN RAIPUR

The safety management system followed in GIL, Raipur site can be explained by the following

given procedures

Safety induction

Tool box meeting

Height pass

Page 22: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

22

Specialized training to workers

HIRAC

Safety Procedure

Safety Formats & checklist

Sub contractors, Fire Safety aspects, First Aid aspects

Incident reporting system (First Aid, Non reportable, LTA and fatal)

Accident investigation

Audits of Site & Report preparation

SRD reporting & Escalation system

Safety Committees

Safety Statics reporting to HO

MSPR

Labor camp Inspection

MOM of Site Safety Committee

Specialized training to workers

Monthly inspection and testing

3.2.1 SAFETY INDUCTION

Safety induction is given to all new staffs and workers .No staff or worker who has not been

given induction training is allowed to work at site . In the safety induction the company policy

,its objective ,its rules are explained so that each individual becomes familiar to the working

environment at site

3.2.2 TOOLBOX MEETING

Before the start of work tool box meeting is conducted where the workers all explained about the

work they have to do, the hazards present and the way to minimize the risk .It is given by the

supervisors in the presence of safety personnel and execution people. It is mandatory to conduct

tool box meeting daily otherwise the work is not allowed to start.

Page 23: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

23

Fig3.1: Tool Box meeting

3.2.3 HEIGHT PASS

In the construction field most of the work is to be done at height ,but before a worker is sent to

work at height it is ensured that he is capable to work at height .For this a competent person is

present to check the health issues of the worker and also checks whether the worker is capable to

work at height or not by acrophobia test, and no worker or staff is allowed to go to height

without showing the height pass which is given by the competent person and has to be renewed

every 6 months.

Page 24: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

24

Fig3.2: Height pass

3.2.4 SAFETY CHECKLISTS

Checklist are the other means of inspection that gives a deep understanding of technical and

other aspects of risk that may cause injury or illness. Checklists such as welding machine, cutting

machine, grinding machine and gas cutting are used in every area wherever any activity is

carrying out. Plant and machinery check lists are available and being maintained

.

GIL includes following of all the checklists:

To continually improve performance and consistency of safety, environment and

quality processes

To ensure compliance with all applicable laws

3.2.5 SUB CONTRACTORS

For sub contractors regular safety inspection, safety audits are done regularly at a particular

interval of time. Safety audit is done as per IS 14489 and based on that a report is made which

tells about where the conformities and non conformities (NC). These NC are raised to the sub-

contractor and asked to take proper action to rectify them.

Page 25: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

25

3.2.6 FIRE SAFETY ASPECTS

Fire is the rapid oxidation of a material in the exothermic chemical process of combustion,

releasing heat, light, and various reaction products. To provide guideline to ensure that proper

fire protection and prevention measures are established during execution of work all employees

are responsible for following all requirements outlined in its guideline.

3.2.7 SAFETY INSTRUCTIONS FOR PREVENTION AND FIRE PROTECTION

To prevent fire hazards, good housekeeping at all locations shall be strictly maintained.

The storage room or shed shall be of fire resistant construction.

For any Hot work jobs, Hot work permit to be obtained from concerned department.

When Hot work to be carried out at height HIRAC to be prepared and fire blanket to be

used to avoid accidental travel of sparks.

Smoking in the Office/ site premises shall be strictly prohibited.

All processes, storages, equipment‟s, plants etc. involving serious explosive and flash

fire hazard shall be located in isolated buildings where all such hazardous activities/

equipment shall be so arranged that only a minimum number of authorized employees are

exposed

In all work places having serious fire or flash fire hazards, passages between machines,

installations or piles of material shall be at least 90 cm wide. For storage piles, the

clearance between the ceiling and the top of pile should not be less than 2 meters.

Availability of sufficient quantity of fire extinguishers/ fire Buckets and Water supply at

ample pressure as per the national standards to extinguish any probable fires shall be

ensured. Portable type Fire extinguishers of class A, B, C and D shall be strategically

Page 26: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

26

placed. .

All the firefighting equipment shall be properly maintained and inspected at regular

intervals of not less than once in a month by the responsible person and record of the

same shall be maintained.

Cylinders containing compressed gas shall never be stored near highly flammable

substances, hot processes or electrical installations.

All the firefighting equipments shall be properly maintained and inspected at regular

intervals. The portable fire extinguishers shall be tested once in a month and record of the

same is to be maintained in the form firefighting equipment inspection record. Defective

or exhausted equipment shall be replaced immediately

3.2.8 GAMMON INCIDENT REPORTING SYSTEM

3.2.8.1 INCIDENT REPORTING SYSTEM (FIRST AID, NEAR MISS REPORT)

Every incident is recorded in a register and analyzed so that lesson could be learnt. Small cut or

low level injuries are recorded in first aid register with proper sequence of how it happened. Near

misses is recorded in a defined format with total sequence of event, body part injured, corrective

and preventive action taken and management remark and sent to the HO. Incidents are also

reported to the local factory inspector and police station.

3.2.8.2 ACCIDENT INVESTIGATION

Accident investigation is done by the safety in charge/safety staff with senior execution staff at

site. Witness statements, evidences, other information is collected as to reach into the root cause

of the accident. For preventing any kind of accident a declaration sheet is filled by the safety

person after inspecting the area before doing any activity. Action plan is prepared and

implemented to prevent accident.

Page 27: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

27

3.2.8.3 AUDIT OF SITES AND REPORT PREPARATION

The health and safety management audit adopts is a structured process of collecting independent

information on the efficiency, effectiveness and reliability of the total H&S management system

and drawing up plans for corrective action.

Internal audit, job safety analysis, SRD‟s, external audits, client‟s audit, and subcontractor audit

are some of the audit practices followed in Gammon and a report is prepared with the help of

those audits with conformities and non-conformities, so the existing system can continually be

improved. Daily inspection of whole site is done as to ensure safety by the safety officers.

Auditing examines each stages in the H&S management system by measuring compliance with

the controls the organization has developed, with the ultimate aim of assessing their effectiveness

and their validity for the future. Periodic workplace safety audits prevent injuries and accidents.

3.2.8.4 HIRAC

Before the start of any new work for eg Chipping work, Excavation , Concrete work or any

sort of such work , HIRAC(Hazard Identification and Risk Assessment and Control measures )

is prepared .The HIRAC is prepared in the presence of Execution Deptt, Safety personnel and

the work is carried out only after it is approved by the Project Manager

3.2.8.5 SAFETY ALERT

Whenever any accident or Fatality takes place in any site, Safety Alert is sent to all site

managers ,safety personnel and other staffs giving the complete description of accident, the

main cause of the accident found after the investigation , the preventive and corrective action

which should be taken in such cases. The Safety Alert is sent to all sites so that it could be

discussed in the Tool Box Meeting, and 3 Q Meeting.

Page 28: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

28

3.2.8.6 SRD REPORTING AND ESCALATING SYSTEM

Safety Related Deficiency process is one of the important processes being included by Gammon

India in recent years. SRD (safety related deficiencies) is a very good practice followed in

gammon. In this practice safety officer visit the construction site daily and observe the safety

related deficiencies and discuss them with the site supervisor or site in engineer. Time given is

depending upon the severity of violation. If it is immediate danger to health and life the activity

is stopped on the spot. For least risk activity time is given to site in charge for compliance, if it is

not completed in the due time then SRD will be discussed with senior in charge person

consecutively. All the SRD raised in a month are discussed and reported in the MSPR

SRD 1ST

Tier

In the first tier the unsafe act or condition is being reported to the supervisor at the site and is

expected that he will close the condition within the given date

SRD 2ND

Tier

If the SRD is not closed by the supervisor within the given date than SRD is brought under the

notice of the site in charge and is expected that it will be closed by him within a given time

period.

SRD 3RD

Tier

If the SRD is not closed by the site in charge then the same will be reported in the safety

committee meeting and the same is sent to the HO

Table 3.1: Details of SRD’s

N

O

.

Details of SRD's Locatio

n Date Due date Responsible

Compl

iance

Status

Remarks

1

Long length Planks used as

flap between two rigs of

working platform

NDCT-

I 20.10.12 07.01.13

Mr.Anindy

a Dey Open

Afert 4/5 lift the issue

will comply.

Page 29: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

29

2

Two nos. of lightening

arrester found in damaged

condition.

NDCT-

I 28.01.13 31.01.13

Mr.

B.Chetia/M

r. Anindya

Dey

Open 1st Mar'13/Mr.

B.Chetia

3

Steel bars were used for

anchoring of chain pulley

block.

NDCT-

I 28.01.13 02.02.13

Mr.Gouri

S. Bisen Open

13th Mar'13/

Mr. Anindya Dey

4

Hook latch not available of

chain pulley block which is

used for Jump form activity.

NDCT-

I 29.01.13 02.02.13

Mr.Manoj

Parmar Open

1st Mar'13/Mr. Manoj

Parmar

5

Hywa No-CG04JA/9872 &

CG04JB/3681 has no

Indicator, Reverse Hornand

no Hand brake.

NDCT-

I

29.01.13/

20.02.13

02.02.13/

22.02.13

Mr.Gouri

S.

Bisen/Anin

dya Dey

Open 1 week/

Mr. Anindya Dey

6

Distance not maintained

between empty and full gas

cylinder.

Tripath

y Fab. 29.01.13 02.02.13

Mr. Nitin

Patle Open

27th Feb'13/Mr. Nitin

Patle

7 Continuos water leakage

from water tank.

Chimne

y 29.01.13 02.02.13

Mr.

R.Borkar

Close

d

8 Hook latch not available of

tower crane.

NDCT-

II 25.01.13 06.02.13

Mr. Manoj

Parmar Open 5th March/MBP/SA

9 RCCB found not in working

condition.

Chimne

y 04.02.13 05.02.13

Mr. Daya.

Goswami Open

2nd March/Mr.

B.Chetia

1

0

Spindle speed has not

mentioned in Grinder M/c.

Chimne

y 07.02.13 09.02.13

Mr. Nitin

Patle Open 27/02/13/NP

1

1

DP test report of

30mtr,40mtr,160,200,210 &

240mtr has not submitted.

Chimne

y 07.02.13 09.02.13

Mr. Nitin

Patle

Close

d 27/02/13/NP

1

2

Landing platform has not

upto the mark @ elevation of

80 &120mtr.

Chimne

y 11.02.13 11.02.13

Mr. Rajesh

Borkar

Close

d 120mtr platform done.

1

3

Cadium has not provided of

concrete and passenger

winch.

Chimne

y 08.02.13 11.02.13

Mr.

Bhagwan

Singh

Close

d

Material not available

in store

Page 30: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

30

1

4

Hywa operator/helper

working without safety

induction and PPE's.

Documents has not

submitted tosafety dept.

NDCT-

I 20.02.13 22.02.13

Mr.

Anindya

Dey

Open 28.02.13AD

1

5

Documents of JCB has not

submitted to safety dept.also

there is reverse horn,no

indicator.

NDCT-

I 20.02.13 20.02.13

Mr.

Anindya

Dey

Open 2DAYS/SA

1

6

JCB operator /helper

working at site without

safety induction and PPE's.

NDCT-

I 20.02.13 20.02.13

Mr.

Anindya

Dey

Close

d SA/1WEEK

1

7

Unauthorized person

operates the passenger lift of

NDCT-I.

NDCT-

I 20.02.13 21.02.13

Mr. Manoj

Parmar

Close

d 27.02.13/MBP

1

8

Test date of curve hoist has

expired.

NDCT-

I 20.02.13 22.02.13

Mr. Manoj

Parmar

Close

d 27.02.13/MBP

1

9

Hook latch not available of

15 ton hydra OR01N/2624.

NDCT-

I 20.02.13 22.02.13

Mr. Manoj

Parmar Open MBP

2

0

Third party test certificate

has not available of 15 ton

hydra OR01N/2624.

NDCT-

I 20.02.13 22.02.13

Mr. Manoj

Parmar

Close

d 27.02.13/MBP

2

1

Ordinary cutting wheel is

using for cutting of SS plate

at M/s Dharam Sai Cons.

Fabrication yard.

Chimne

y 23.02.13 24.02.13

Mr. Nitin

Patle

Close

d

Page 31: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

31

Safety Committees

The safety committee is formed to review the implementation of safety issues and safety

requirement. Safety committee meeting is held once in a month. Safety committee is formed(as

per BOCW ACT 1996) with Project Manager as chairman, safety In charge is secretary and

Equal numbers of staff and workers are the committee members.

Fig3.3:Safety committee meeting

Safety Statistics Reporting To Ho

MSPR is send to HO in which all safety indicators are mentioned. This is method of reporting

the monthly statistic to head office about the man-hours worked, first aid cases etc

Job Name:-2X685 TPP GMR, RAIPUR

Job Code:-8945/47

Page 32: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

32

Table3.2: Safety statistics

SL NO DESCRIPTION FTM CUMULATIVE

1 Total Safe man Hours achieved 200480 3224176

2 No. of First-Aid Cases 01 46

3 Near Miss Incidents 00 08

4 No. of LTI’s 00 00

5 No. of Fatal Accidents 00 00

6 Lost Hours due to Accidents 00 00

7 Frequency Rate [FR] 00 00

8 Severity Rate [SR] 00 00

9 Incident Rate [IR ] 00 00

10 Incidence Rate [Fatal] 00 00

11 No. of SRD’s Raised 55 872

12 No. of SRD’s Closed 50(Carry Forward 08) 859

13 No. of SRD’s Opened 13 13

14 Safety Committee Meeting 16TH

Safety Committee

meeting was held on 30th

January’13.

16

Page 33: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

33

MSPR (Monthly Safety Performance Report)

Reporting of safety performance takes place at regular intervals. Each month, a summary of

safety performance is produced which describes the main events that have occurred during the

month, focusing on observations,SRD‟s,Inspection,Training,Near Misses. The report compares

current progress on a number of such indicators with previous years

In MSPR following things are recorded for gammon and its subcontractors. It is the monthly

safety performance briefing. It includes:

1. Safety briefing like tool box talk, 3Q meeting, motivation programs, safety competition,

awareness program, best safety performing staff/worker, induction training of

worker/staff, specialized training program, external training etc.

2. Details of manpower

3. Details of safety inspection

Number of height pass

Number of safety inspection

Medical examination

Safety committee meeting

4. HSE performance indicator(Near miss, First-Aid )

5. Man days lost

6. Frequency rate

7. Severity rate

Table3.3: MSPR report

SITE /

LOCATION GMR RAIPUR

JOB

CODE 8945/47 Month February'13

Details Of

Manpower Safety Briefing Number Attendees HSE Performance Indicators

Average No. of

HO Staff 35 Tool Box Talk 170 16239 Near Miss 1

Average No. of

LMR Staff 57 3Q Meeting 0 0

First Aid Injuries

(resumes duty instantly) 1

Page 34: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

34

Average No. of

DMR Staff 18

Motivation/

Promotions Number Attendees

Minor Injuries

(resumes duty within 48

hours)

0

Average No. of

Voucher Staff 0

Safety

Competitions

held

NIL NIL

Loss Time Injuries

(resumes duty after 48

hours)

0

Average No. of

workers (PRW /

SC)

580

Awareness

programme

held

1 All Workers FATAL

(Loss of Life. Death) 0

Total strength at

site (Avg) 690

Name of best

safety

performer

(worker)

Mr. Kishan Karmokar

(Supv.)

Illness

(Unhealthy condition of

the person affected)

0

Total Man-hours

worked for the

month

193200

Name of best

safety

performer

(Staff)

Mr. Dilip Tiwari (Foreman

Civil)

Man Day Lost

LTI 0

Total safety staff

at site

9

(Includi

ng

Safety

Co-

ordinato

r)

SHE Trainings Number Attendees FAT

AL 0

Inspections/Audit

s

Numbe

r

Induction

Trainings

(Workers)

10 108

Frequency Rate

LTI 0

Safety Inspection 64

Induction

Trainings

(Staff)

3 3 FAT

AL 0

Audits 3

Specialized

Trainings 2 31

Severity Rate

LTI 0

Persons Medically

Examined 65

External

Trainings 0 0

FAT

AL 0

Personnel issued

height pass 65 Safety Related Deficiencies Remarks

Page 35: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

35

Safety Committee

Meeting

17th

Safety

Commit

tee

meeting

was .

Carry forward

(last month) Raised Closed Open

Refer Attached

excel sheet

13 69 71 11

Project Manager Mr. Sunil G.Mahadik

Safety-in-

charge Mr.Rakesh Kumar

Note: 1) This MSPR report (soft copy in excel format) should reach H.O before 5th of every month.

2) signed copy of the same shall be maintained at site as Audit requirement

Labor Camp Inspection

Labor camp inspection is done once in a month and checked for cleanliness, electrical inspection

and healthy environment. Bleaching powder, mosquito spray are done in every month for the

wellness of health of workers.

Safety induction training given to the labor

Basic safety related training is given to every labor during the time of induction. This training is

compulsory for every worker before entering the job. It includes stating the company policy,

objectives and the location of Assembly points. It also includes the general guideline to the

workers before starting their job. Labors are made familiar with the safety PPE‟s that they have

to use at site and all safety precautions for different activities and general awareness.

Page 36: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

36

Specialized training to workers

The workers doing the Technical as well as Non-Technical works are given training at regular

intervals to make them aware of the hazards and the right procedure to do their respective

works.

Fig 3.4: Grinding safety training

Monthly inspection and testing

Earthpit testing , RCCB testing and fire extinguisher inspection is done every month and a

record is maintained to check the efficiency of the same . If the result is not found up to the

standard then SRD is given to the respective In- charges

Page 37: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

37

RCCB testing Earth Pit testing

Fire Extinguisher Inspection

Fig3.5: RCCB testing, Earth pit testing and Fire extinguisher inspection

Page 38: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

38

MOM of site safety committee

Meeting is held once in month and following issues are discussed.

1. Client raised NC‟s

2. SRD‟s (number of SRD raised, closed, open, details)

3. Safety performance indicators (Near miss, First aid, Illness, tool box)

4. Minutes recorded(details of minute recorded, responsible person, Target date, revised

date etc )

Minutes of Meeting is prepared after a safety meeting ,which includes the topics discussed and

the tentative date by which the SRDs would be closed is also given by the incharge. An example

of MOM is attached here.

Table 3.4: MOM sample

TITLE Safety committee meeting no-17

DATE 26th

February ’13

PROJECT NO / NAME:

LOCATION

8945/47,GMR Energy Chhattisgarh Limited,

Raipur

PRESENT 27

CIRCULATION All Committee Members

SL

No

DISCUSSION Action By/Date

Compliance status

1.0 REVIEW OF LAST MOM

1.1 Plywood require for flap.

Mr. Anindya Dey assured that after

another 4/5 lift this issue will comply,

till that; planks will be fixed between

two rigs.

Continue Process

1.2 Identification no. as per test

certificate should be displayed on

all tools and tackles.

Mr. Manoj Parmar/28th

Feb‟13. Open

Page 39: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

39

1.3 Labour colony toilets are not in

working condition.

Action plan/budget to be submitted by

Admin Dept.to Project In charge and

this issue will comply within

10th

March‟13/Mr. Vikash Saw

Open

1.4 At the time of Concrete pouring,

shed required for ground level

workers who hold the concrete

bucket at ± 0 level.

Mr. Niraj Sahu/27.02.2013 Open

1.5 Entry man (for maintain In time and

Out time register) required for

Chimney/NDCT 1 at night time.

Mr. Niraj Sahu agreed to

deploy one person for

maintaing entry register at

night time on 26th

February

2013.

For chimney Ambulance

Driver will deploy at in front

of chimney for entry those

workers who will go through

the man cage. /

Mr. R.Borkar will take this

responsibility.

If someone found without

entry then Rs:- 500/- will

impose against that person.

Continue Process

1.6 Earth pit no-3 & 4 yet not repaired

at chimney.

Mr. B. Chetia/ 1week Open

2.0 MOM for the month of February 2013

2.1 Discussion about MSPR/ Safety

Statistics.

Discussed with chairman regarding

safety statistics.

For information.

2.2 Discuss all Unattended SRD‟s.

(Attached excel sheet).

Chairman Instructed to all members to

comply the SRD‟s within the given

time period.

Ref:-Anx.no 3.0

Page 40: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

40

2.3 Height Pass New/Renew.

(Timing should be Mon, Wed, and

Fri at 11am to 1pm)

All agreed. For NDCT-I it was

completed and for rest

it will comply within ¾

days.

2.4 No Safe access for drinking water

tank at NDCT-I.

Mr. Vikash Saw/26th

Feb’13 Closed

2.5 Drinking water testing not done. Mr. Gopal Sarda

(Admn. In Charge)/ 10.03.13

Open

2.6 Parallel work must be stopped both

at NDCT & Chimney.

No parallel work will be allowed. In

case of chimney, work may be

allowed (according to work permit) in

opposite direction of two working

platform and Section In charge will be

the responsible person for that.

Continuous Process

2.7 Sufficient PPE‟s not available at

store.

No Induction will be carried out till

purchasing of safety Shoe.

Continuous Process

2.8 Passenger vehicle drivers are

working 24hrs/day

Two drivers will deployed for both

shift for all vehicles/Mr. Vikash

Saw/27th

Feb‟13 onwards.

Continuous Process

2.9 Fire extinguisher required for

Painting work & Sai Const.

fabrication work

Mr. Vijay Pandey/ 2nd

March‟13. Open

2.10 Documents not submitted of all

TM‟s and Hand Brake, Reverse

Horn, FE, Brake Light also not

available of all TM‟s.

One by one TM will go for repair and

it will comply within 20 days/ Mr.

Abhishek Labhe.

Open

2.11 Plug top missing from max. DB‟s. Mr. Manoj Parmar/ 28th

Feb‟13. Open

2.12 Two core connection found in

many light connections.

Mr. B.Chetia/28th

Feb‟13

Open

2.13 42nd

National Safety Day

Celebration.

Budget Approved For Information

Page 41: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

41

3.0 Unattended SRD’s

3.1 Two nos. of lightening arrester

of NDCT-I found in damaged

condition.

Fine will impose against those

respective PRW‟s and issue will

comply within 1st March‟13 by Mr.

B.Chetia.

Open

3.2 Steel bars were used for

anchoring of chain pulley block

at NDCT-I.

Wire rope sling will be used

instead of steel bars within 15 days

i.e. 13th Mar‟13 by

Mr. Anindya Dey.

Open

3.3 Hook latch not available of

Chain Pulley Block which is

used at NDCT-I.

Mr. Manoj Parmar/1st March‟13 Open

3.4 Hywa No-CG04JA/9872 &

CG04JB/3681 has no

Indicator,Reverse Hornand no

Hand brake.

Mr. Anindya Dey will responsible

for all Hywa and Earth Movers‟s

regarding all safety issues. This

issue will be closed within 1 week

otherwise work will be stopped.

Open

3.5 Distance not maintained between

empty and full gas cylinder.

Mr. Nitin Patle/27th Feb‟13 Open

3.6 Continuos water leakage from

water tank.

Mr. Vikash Saw/27th

Feb’13 Closed

3.7 Hook latch not available of

tower crane.

Mr. Manoj Parmar & Mr. Saurabh

Agrawal/ 5th March‟13.

Open

3.8 RCCB found not in working

condition.

Mr. Chetia/ 2nd

Mar‟13 Open

3.9 Spindle speed has not mentioned

in Grinder M/c.

Mr. Nitin Patle/27th Feb‟13 Open

3.10 DP test report of 30mtr,

40mtr, 160,200,210 & 240mtr

has not submitted.

Mr. Nitin Patle/27th

Feb’13 Closed

3.11 Landing platform has not up Mr. Rajesh Borkar/27th

Feb’13 Closed

Page 42: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

42

to the mark @ elevation of 80

&120mtr.

3.12 Cadmium has not provided of

concrete and passenger winch.

Mr. Manoj Parmar/1st Mar’13 Closed

3.13 Hywa operator/helper working

without safety induction and

PPE's. Documents has not

submitted to safety dept.

Mr. Anindya Dey/28th Feb‟13 Open

3.14 Documents of JCB has not

submitted to safety dept.also

there is reverse horn,no

indicator.

Mr. Saurabh Agrawal

/28th Feb‟13.

Open

3.15 JCB operator /helper working

at site without safety induction

and PPE's.

Mr. Saurabh Agrawal

/28th

Feb’13

Closed

3.16 Unauthorized person operates

the passenger lift of NDCT-I.

Mr. Manoj Parmar

/27th

Feb’13

Closed

3.17 Test date of curve hoist has

expired.

Mr. Manoj Parmar

/27th

Feb’13

Closed

3.18 Hook latch not available of 15

ton hydra OR01N/2624.

Mr. Manoj Parmar

/1st March‟13

Open

3.19 Third party test certificate has

not available of 15 ton hydra

OR01N/2624.

Mr. Manoj Parmar

/27th

Feb’13

Closed

3.20 Ordinary cutting wheel is

using for cutting of SS plate at

M/s Dharam Sai Cons.

Fabrication yard.

Mr. Nitin Patle/27th

Feb’13 Closed

Page 43: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

43

3.3. DETAILS OF THE HAZARDOUS ACTIVITIES AND THEIR

CONTROL MEASURES DURING THE CONSTRUCTION OF A

NATURAL DRAFT COOLING TOWER TAKEN IN GIL

The construction of a natural draft cooling tower has different hazardous activities involved in it.

Following are the activities involved, the hazards present in it and their control measures taken.

3.3.1 CONTROL OF DUST, GASES, FUMES HAZARDS

The gas cutting operation and welding works generate dangerous gases and fumes. The dust is

mainly caused in the batching plant area and frequent movement of site vehicles nearby working

zones

The measures taken in GIL Raipur are

1. Frequent and sufficient water sprinkling is arranged to prevent dust hazards at all the

access road of sites of dust prone areas

2. Dust mask is given to workers in dust prone areas

3. Face shield is given to workers involved in gas cutting and welding operation

3.3.2 EXCAVATION

The construction work starts from the excavation work. In this the soil is excavated and is taken

out by the help of hywa or dumpers. Different hazards present during this activity is as follows

Table2.1: Excavation hazards and control measures

Hazards Control measures

Excavator falls in to the pit. 1. Appointing signal man.

2. Operate machinery keeping safe distance to

avoid excavating area landslide.

3. Keep away from the excavated edge.

4.Provide barrier away from the edge of

excavation

Fall of persons into the pits 1. Provide proper ladder to get into the pits.

Page 44: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

44

2. Maintaining housekeeping around the pit.

3. Barricade the area.

4. Provide adequate emergency access out of

excavation

Possibility of injury while swing of the bucket 1. Barricade entire excavation area

2. Workers are provided with Helmet, safety

shoes etc.

Damage to underground electrical, Telecom

cables and water services.

1. Always look for route markers.

2. Get survey details prior to start excavation

3. Make trail pits.

4. Provide warning tapes/ cable covering mats/

concrete saddles/ sand padding.

5. Use cable detectors

6. Adhere strictly to manual excavation in case

of presence of underground cables

Workers or passersby may accidentally fall

into open, unprotected excavated pits or

vehicles may accidentally be driven into an

uncovered or inadequately barricaded pit.

1. Provide guardrail systems, fences, barricades

or covers at the edge of a well, pit, shaft and

similar excavation

2. Ensure proper and adequate illumination

3. Display sign board

Collapse of sides 1. provide appropriate shoring

2. Always ensure that trenches more than 5 feet

deep (In unstable soil, trenches less than 5 feet

deep) have shoring or are laid back to a stable

slope.

3. Install shields to restrict lateral or other

hazardous movement of soil.

4. Ensure that material and equipment used for

sheeting, sheet piling, bracing, shoring and

underpinning are in good serviceable

condition.

Page 45: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

45

5. Use timbers that are sound and free of

defects.

6. Backfill trenches as the work progresses.

7. Do not work outside of trench shields or

shoring protection in unprotected trenches.

8. Avoid jumping into or across trenches

3.3.3 PLAIN CONCRETE CEMENT

PCC is done in the base of the footing to prevent it from soil contact.

Table2.2: PCC related hazards and control measures

Hazards Control measures

Presence of Sharp stone or foreign material in

the surface,

Use of gum boot & hand gloves

Damaged or wrong shovel operation 1. Issue only appropriate tool.

2. Personnel shall know to operate the tool

3. conduct training (on job / off job)

4. Use of gum boot with steel toe.

Falling of material in deep excavated area 1. Regular daily inspection of edges.

2. Placed caution Board.

3. Use of safety helmet.

4. Restrict the area for unauthorized people

3.3.4 RAFTING

Table2.3: Rafting hazards and control measures

hazards Control measures

During the placement of steel on PCC there

can be contact / hit by rod during transfer

1. Adopt kinematic principle for manual

handling

Page 46: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

46

/unloading of reinforcement and also there may

be fall of person due to inadequate walkway

2. Weight for more than 50 kg equipment shall

be engaged for lifting

3. Walk way should be cleared from obstacle.

4. Trade test/ competency test should be done

with all workers before assigning job

5.Lifting should be carried out proper

supervision

6. Use proper ladder or work on proper

platform

7. Training to work force who engage for

performing such activity

8. Ensure adequate supervision

9. Shoulder pad used while shifting & proper

PPE used.

10. Safety shoes, hand gloves , safety harness

11. Ensure adequate illumination at the

location

Insertion of nails and Injury due to exposed

shuttering objects

1. House keeping shall be ensured.

2. Proper PPE shall be provided

3. Tagging is used in case of exposed

shuttering object

Page 47: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

47

Steel re-inforcement PCC column footing

Fig3.6 Rafting component

3.3.5 BATCHING PLANT

It is the plant area where the concrete mixture is prepared .It is the major section of the plant

because the concrete needed for all the construction work right from pcc to top shell is prepared

here. A lot of hazards are present in the operation of the batching plant. The hazards and their

control measures are

Table2.4: batching plant hazards and control measures

Hazards Control measures

Toppling of structure & use of unfit crane and

equipment causing fall of structure on person

causing major injury or fatal

1. Only designated cranes and loading

equipment with sufficient carrying capacity to

be used.

2. Loading, unloading and erection the plant

parts shall be done by experienced riggers

3. Ensure strict / direct supervision of a

competent person during erection of plant.

4. Lifting and erection sequence shall be done

as mentioned in the operation and Instruction

Page 48: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

48

manual..

5. Sling's and other lifting tools used for lifting

purpose shall be tested and certified.

6. Suitable vehicle having sufficient loading

capacity shall be used for transporting the plant

parts.

7. Equipment transported on vehicle shall be

secured and tightened properly

Unguarded Moving Part resulting into

Trapping of body parts causing Multiple injury

to person

1. Before starting the plant, it shall be ensured

that nobody is working on the plant.

2. All the gears, chains & rollers of the mixers

shall be properly guard.

3. Ensure while persons are working in

conveyor line areas, the switches and controls

shall be secured and tagged so that no one can

engage them until all personnel are clear.

4. Ensure use of PPE‟s i.e. safety helmet,

gloves, safety shoes, nose mask , ear plug etc.

Emission of dust during Cement & Aggregate

Handling & Loading Can cause

respiratory/Breathing problems to workmen

1. Wet method should be used to reduce the

dust emission before loading

2. Ensure job rotation to reduce the exposure

3. Ensure use of dust mask

Due to contact with cement the Fingers/Hands

may be affected due to chemical action of

cement & sweating.

1. Training and awareness

2. Provide safety gloves to Workmen.

Irregular movements of Loaders and Tippers

may hit the workmen caused to injury/wounds

1.Ensure Reverse horn and other safety devices

to the transit mixer,

2. Ensure alarming system during enter and

exit of the transit mixer from B/ Plant,

3. Depute Signalman,

4. Restrict the area for unauthorized entry.

Page 49: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

49

5. Ensure only trained, experienced driver,

holding a valid driving license,

6.Ensure adequate space for turning the

vehicles,

7. Ensure strict supervision,

Ensure adequate uses of PPEs such as safety

shoe, helmet and driving sit belt

Maintenance work performed by unauthorized

technician can lead to serious accident

1. Only authorized technicians shall be allowed

to carry out any repair and maintenance work.

2. Work Permit System shall be implemented

for repair and maintenance works (like, mixer

drum cleaning,

works on skip etc.)

3. During the replacement of individual parts

and large and/or heavy structural members, it

shall be

carefully attached to appropriate lifting

appliance

4. Nobody shall be allowed to stay or work

under the suspended load.

5. Ensure strict supervision during lifting

operation.

Falling of concrete at concrete batch dropping

area may cause head injury, if a person stands

at dropping area.

1.When hoppers are being loaded, personnel

should stay away from the area of falling

aggregate.

2. Restrict entering persons at dropping area by

providing necessary barricades/caution boards.

3. Ensure strict supervision

Page 50: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

50

Fig 3.7: The batching plant of Raipur

3.3.6 GAS CUTTING OPERATION

The gas cutting operation is a very hazardous work since highly flammable gas is used for

cutting operation i.e DA (Dissolved Acetylene) and oxygen and if not properly carried out can

lead to fire

The hazards and their control measures for gas cutting operation are as follows

Table2.5 Gas cutting hazards and control measures

Hazards Control Measures

Defective Hose pipe can lead to fire and

explosion causing injury or death

1. use good quality hose pipe and leak proof

hose pipe

2. check the condition of hose in regular

interval and prior to start of work

3. Use of back fire arrester (Flash back

arrester) at both the end.

Page 51: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

51

4. Use lighting torch only for ignition purpose

In the condition of non availability of flash

back arrestor burning gas may result in

possible serious injury or lead to an fatality

1. Flashback arrestor shall be installed for the

gas to be shut off.

2. Ensure correct use and maintenance of

flashback arrestor to minimize the risk of

equipment failure from flashback.

3. All oxygen/fuel gas welding, cutting and

heating systems must be fitted with flashback

arrestors to both the regulator and blowtorch

Ends.

4. Flashback arrestors must be of the correct

type and size as recommended by the

manufacturer.

Wrong gas sequence during start-up and shut

down may lead to flash back and resulting

serious injury

1. Before lighting the blowpipe, each gas hose

should be purged separately

2. Ensure flow is freely until the operator is

sure the hose contains no impurities such as

water, dirt or blockages.

3. After purging, shut each blowpipe valve.

4. only trained and experienced person shall be

engaged for gas cutting operation

Insufficient purging to clean hoses before use

may lead to fire and major injury

This operation should take place in a well

ventilated area away from any naked flame or

ignition source

In the presence of blocked, worn, undersized or

overheated blowpipe tip there can be failure of

hoses and fittings can cause workplace fire or

explosion

1. visual inspection shall be done prior to start

gas cutting operation

2. If there are any signs of leakage, fluctuating

gas supply, gas starvation or misshapen flames,

the equipment should be shut down

3. inspection & fault correction shall be done

by maintenance team.

Page 52: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

52

Hose run over by a vehicle during welding &

Kinked or restricted hoses can lead to fire

explosion & serious injury to personnel

1. Visual inspection shall be done prior to start

gas cutting operation.

2. Damaged hose shall be removed and

replaced immediately

Hoses of incorrect diameter & old gas hoses

can cause fire and serious injury to personnel

1. Ensure proper diameter of hose shall be in

use

2. Ensure periodic inspection of hose

3. Remove old hose which seems stiff and

brittle immediately and discard it.

Wrong gas pressures can lead to fire and

explosion

1. Ensure periodic check of all the pressure

gauges in regular interval

2. Damaged valves shall be replaced

immediately

3. If indicator shows pressure drop the machine

shall be stop and through check shall be done

Ultraviolet Radiation 1. Use face shield and proper apron.

2. Use of safety goggles as radiation intensity

3.3.7 WELDING OPERATION

Welding operation is done in the fabrication area as well as during the jump form construction

and erection of the same .It is very dangerous as it is done by the electricity . The hazards and

their control measures during the welding operation are as follows

Table 2.6 Welding operation hazards and control measures

Hazards Control Measures

Welding radiates invisible ultra violet and infra

red rays these radiation can damages the eyes

1. Use less hazardous materials such as:

Asbestos-free electrodes, gloves, and hot pads.

Page 53: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

53

and the skin 2. Cross Ventilation shall be done to remove

harmful fumes and gases

3.Regular medical check/ monitoring of the

welders

3. Use of proper specified shielding devices

and like safety shoes without steel toe , helmet,

face shield, gloves etc.

Leakage & cuts in hoses can cause fire hazards 1. Purge regulators immediately & then turn

off.

2. Never use grease or oil on oxygen line

connections and copper fittings

3. Use the current for which the cable is

designed.

4. Use only well maintained equipment.

5. Repair or replace damaged parts before

further use.

6. ensure periodic inspection

Personnel may hit by flying particle causing

blindness and damage.

1. All persons involved with welding are

required to wear appropriate type of goggles

2. As far as possible avoid number of people

working in the area, always kept minimum

3. Follow work permit system

Welding Machine without proper earthing can

cause electrocution

1. Proper earthing shall be provided to

welding machine

2. All the connection shall be passes through

ELCB only

3. Ensure use of cable for Neutral/earth return

4. Periodic check for earthing resistance by

ELCB tester

5.Use of PPE‟ such as leather / rubber hand

gloves

Page 54: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

54

6.Do not touch an energized electrode with

bare hands.

7. Wet working conditions should be avoided

8.Wear dry, insulated gloves in good condition

and protective clothing.

Damaged welding cable and holder can lead to

electrocution

1. Ensure use of good condition cable and

holder

2. Regular inspection for any damage

3. Ensure use of safety shoes, gum boot, hand

gloves safety helmet etc.

4. Use fully insulated electrode holders.

5. Do not use worn, damaged, undersized or

poorly spliced cables.

3.3.8 GRINDING OPERATION

The hazards present in the grinding operation and their control measures are as follows

Table 2.7 Grinding operation hazards and control measures

Hazards Control Measures

Contact with Hot Metal body can lead to burn

to personnel causing minor injury

1.Ensure that the wheels do not touch the work

rest and that the gap between wheel and rest is

no greater than 3mm.

2. Let the wheels gain maximum speed before

starting to grind.

3. Maintain proper distance while grinding

4. Use proper PPE's like hand gloves, goggles

etc.

Noise generation during operation may cause

headache ,irritation etc

1.Check that wheels are running true and are

not glazed or loaded.

2. Ensure periodic check of machine

Page 55: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

55

3.Ensure proper oiling and lubrication

Contact with sharp edges may cause cut injury 1. Make a guard wherever sharp edge is there

or provide cushion

2. Cut the unwanted edge

3. Use apron , hand gloves, safety shoes

Wheels „run on‟ after switching off may cause

injury to personnel while come in contact with

it

1. Stand to the side of the wheels when starting

up and shut down

2. ensure no other person come near by the

machine

3. Operator shall be present at the machine till

wheel stop fully.

4.Never leave the machine running unattended

Unguarded Machine may cause crush injury

and part of body come in contact leads to

amputation

1. Ensure all guards and safety shields are in

position before starting the bench grinder.

2. Do not allow anyone to wear loose clothing

while working on bench grinder

Loose / improper connection & improper

insulation can lead to electrocution

1. Always use the double insulated portable

grinders.

2. Check electrical connection every time prior

to start work

3. Check ELCB and earth pit resistance in

regular basis

Operating low RPM wheel on high RPM

grinder can lead to breaking of wheel casing

injuries to eye and body

1. Ensure fixing of grinding wheel as per the

specifications

2. Provide guard for grinder

3.Use of safety helmet, safety goggle, hand

gloves etc.

Grinding having the larger gap in between

grinding wheel and tool rest can lead to finger

injury

1.Gap in between grinding wheel and tool rest

must not more than 3 mm

2. Ensure regular inspection

3.Use of safety goggle, safety helmet, hand

Page 56: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

56

gloves, face shield

4.Provide guard for moving parts

Grinding with defective grinding wheel can

cause breaking of wheel causing Multiple

injury

1. Ensure use of good condition grinding wheel

2. Ensure periodic Inspection for identifying

the defective wheel.

3.Use of safety goggles, face shield, safety

helmet

3.3.9 VEHICLE SAFETY

In the construction industry the transportation work is a major activity, like transportation of

cement bags, steel, transit mixers carrying concrete mixtures, trailers carrying scraps or steel etc

holds the major importance in construction industry. Since there are a lot of vehicular activity

there are chances of accidents .The main hazards present due to vehicular movement and their

control measures are as follows

Table 2.8 Vehicle safety

Hazards Control measures

Rash driving resulting in the equipment hitting

to the personnel causing injury and death

1. Drive slowly and follow all driving rule.

2. Ensure engagement of trained and

experienced drivers/operator

3. Monitoring for the rash driving by imposing

penalty for violation.

4. Speed lock shall be done for the vehicle for

certain speed

5 Ensure the vehicle is always following

prescribed speed limit. i.e. 20 km/hr inside the

construction site.

3. Impart training for defensive driving

Page 57: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

57

4. Speed limit boards should be displayed.

5.Speed lock shall be done for the vehicle for

certain speed

Overloading of vehicles/dumper Toppling, loss

of control over the equipment causing injury

and death

1. Ensure vehicles should be loaded as per the

loading capacity specified by the manufacturer

2. Ensure proper supervision

3. Consider condition of road before loading

the vehicle

4.Ensure use of PPE‟s for the worker/operators

i.e. safety shoes, safety helmet, reflective

jacket and seat belt etc

Inadequate space for movement for vehicles

hitting a person causing injury and death

1. Ensure adequate space for maneuvering the

equipment / vehicle

2. Provide signalman wearing reflective jacket

3. Restrict the entry for unauthorized worker

for controlling the unnecessary movement of

workforce

4. Move the vehicle in adequate space.

5.Ensure use of PPE‟s for the worker/operators

i.e. safety shoes, safety helmet, and seat belt

etc

Vehicle not having reverse horn and other

safety devices which can lead to collision with

other vehicle or person causing injury and

fatality

1. Ensure reverse horn along with other safety

devices, indicators

2. Ensure proper & timely checking of the

vehicle & preventive maintenance

3. Do not allow any vehicle without reverse

horn and safety device in site.

Extended working hours of drivers can lead to

fatigue causing injury fatality

1. Ensure no driver/operator is working beyond

the prescribed limit for working hours as per

laws

2. Ensure Job rotation for reducing fatigue

Page 58: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

58

3. Do not allow any driver or operator for over

time.

Driving with raised tipper body near over head

line leading to electrocution causing injury or

fatality

1. Ensure / seek permission of electricity board

for power shut down

2. Maintain proper distance from over head

line

3. Install goal post arrangement to avoid

contact with over head lines

4. Provide stopper with appropriate distance

5. Operators shall be instruct not to drive with

open /raised tipper body

6. Ensure / check all the electric connection of

vehicle during maintenance

7. Deployment of trained signal man and flag

man

8. Provide flag & traffic light baton for night

hours

3.3.10 TOWER CRANE OPERATION

In the construction work most of the work is done through tower crane such as concreting work,

steel lifting, planks lifting ,jump form lifting etc. There are a lot of risks in the working of tower

crane

Table 2.9 Tower crane operation

Hazards Control measures

Improper foundation not following design 1. Foundation must be check before installation

2. Follow enabling design and construct as per

Page 59: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

59

drawing

3.Soil condition shall be check.

4. Soil compaction shall done.

5. Installed shall be done as per drawing and

sequence shall be followed.

6.Proper communication shall be ensure.

7. Walk way should be cleared from obstacle.

8. Proper Lighting should be in provided.

10.Used proper PPE.

Electric overhead line 1. Ensure no electrical overhead line

2. All the electric line shall be shutdown

3. Permit to work system shall be followed

improper line & level maintained which can

cause injury

1.Identify the root cause for improper line

2. Keep all the workers away from surrounding

area of the tower crane.

3. Mechanical fittings should be fixed tightly.

4. All the arrangement shall be inspected by

competent person at every step.

5. Only authorized person shall be engaged.

Improper testing causing collapse of structure 1. Check the movement of crane as per the load

chart.

2.Check the movement of hook along the

boom of crane

3. During the testing of crane, ensure all the

worker away from surrounding.

4. Loading, unloading and erection the plant

parts shall be done by experienced riggers

5. Ensure strict / direct supervision of a

competent person during testing.

6. Lifting and erection sequence shall be done

as mentioned in the operation and Instruction

Page 60: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

60

manual.

7. Sling's and other lifting tools used for lifting

purpose shall be tested and certified.

Improper balance weight loading 1. Inspection of Safe Working Load Meter.

2. Handle the loading material with Tag Line.

3. Proper counting of load weight.

4. Operation manual shall be followed

5. only competent person shall be involved

operator falling from height 1. No other person have permission in

operators cabin.

2. Cabin must have door and it should lock

after enter in cabin.

3. Safety belt should issued for the operator.

4. Give proper access to reach the cabin.

5. The condition of ladder shall be check

regularly

Following things should be inspected daily by a competent person before the start of work

1. Location of tower

2. Location of anchor blocks

3. Tower foundation

4. Erection of tower

5. Size of guy ropes

6. Verticality of tower

7. Strengthening of tower

8. Barrication around anchor blocks

9. Lifting booms & pulleys

10. Arrangement of winches, conc. Mixer

11. Access to tower

12. Protection shed for mixer & winches

Page 61: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

61

13. Signaling system

14. Temp. Lightening arrestor

15. Aviation warning signal

16. Tower / area lighting

17. Tightness of all fasteners

Ladder Mass piece Guy rope Boom Cabin

Fig3.8 Tower crane component

The main hazards in tower cranes are during

1. Erection of tower crane

2. Telescoping (fixing of mass piece to increase the height of tower crane)

3. Fixing of guy rope(for alignment)

4. Dismantling of tower crane

3.3.11 PASSENGER HOIST

Passenger lift is used to take workers and staffs to the working height .Extra maintenance should

be done and a daily inspection should be done by a competent person before it is allowed to

work. Checklist should be there in which the competent person would sign after a thorough

inspection.

Page 62: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

62

Checklist should be of following format confirming the following specification.

1. Condition of Electrical Drives

2. Condition of gear box

3. Condition of fasteners used in couplers

4. Condition of anti drop safety device

5. Condition of electromagnetic disc, thruster brake.

6. Condition of rack and pinion

7. Condition of guide roller and its lubrications

8. Structure, man cage condition

9. Function of limit switch

10. Tightness of bolts supporting pulleys

11. Availability of lift man

12. Function of signals & its switches

13. Function of emergency stop switch

14. Function of door switches

15. Alignment Check

16. Electrical cooling fan

Passenger Hoist Shed to reach passenger hoist

Fig3.9 Passenger Hoist Component

Page 63: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

63

3.3.12 JUMPFORM

The Jumpform system is hydraulically self climbing access scaffold system suitable for the

construction of RCC shell of Natural Draught Cooling Tower. The system is self climbing,

shutter panels are lifted using Air winches hence system is very efficient, effective and fast.

For the construction of a Natural Draft Cooling Tower the most important part is the Jumpform.

In any construction work above ground level, one needs access and working platform for all

activities related to field work. In a multi storied building, one gets working platforms in the

form of floor slabs at every 3.0 meters height.

For any structure like cooling tower and such other structures, where no floor slabs are

functionally required and hence not provided, access to the level of working and a work platform

for the workmen is required to be properly designed and provided. In India, till late 70‟s,

structures required were of moderate size and height were conventional, method of M.S tubular

scaffold system erected manually was found adequate but of late, in the present scenario of

achieving the benefit of economics of scale, much larger units of equipment and resulting large

sizes of civil construction units are being planned and built. Hence, conventional system of

construction had to be replaced by modern techniques, equipments and innovative methods.

The following system “JUMPFORM” of BERRUM type describes the innovative method of

providing access scaffold and platform system developed and used for the construction of very

tall structures such as Natural Draught Cooling Tower.

An assembly of two „U‟ beams with total framework and timber platforms is known as a Rig.

The rig components are assembled at ground level and erected on to the shell in an assembled

manner. The rig then takes the support from the shell already constructed and moves upwards in

lifts of 1.5 Mtr each. Thus it enables construction up to its final height.

Brief description about the system:

List of main component of Jumpform system is as follows-

1. Structural steel U beams

Page 64: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

64

2. Inside Shutter

3. Outside Shutter

4. Shutter Bolts

5. Anchor Screws

6. Soldiers

7. Outside shutter Adjuster bolts

8. Inside shutter adjuster bolts

9. Adjustable steel pan for inside and outside shutter

10. Ladder beam

11. Air Winches

12. Temporary Shutter distance pieces

13. Support Brackets

14. Push Pull prop

15. Handrail

16. Inner Rig Post

17. Outer Rig Post

18. Hydraulic panel

19. 5 Ton capacity Jack

Brief description of unit:

Main component of Jumpform system consists of structural steel U beams of Rigs; sliding

channels anchor brackets, ladder beams, Platforms beams. One unit consists of pair of U beam

rig ,pair of sliding channels ,pair of hydraulic jacks and 6 Nos. anchors plate with 12 Nos.

anchors are to be embedded inside shell (Anchors are recoverable).

Hydraulic Device:

Hydraulic device consist of hydraulic cylinder, hydraulic panels, power pack, hydraulic hoses &

fittings.

Page 65: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

65

1. Hydraulic cylinder:

2nos of hydraulic cylinder are fitted per rig in each side frame .Hydraulic cylinder is double

acting having stroke length of 1600mm .End mountings are clevis at head end and rod eye with

spherical bearings.

2. Hydraulic Panels:

Hydraulic panels are fixed in between the two rigs.

3. Hydraulic Power Pack:

Two power packs are provided to operate the entire rigs around the circumference of the cooling

tower.

4. Hydraulic Hoses & fittings:

This is used for the easy and fast circulation of hydraulic oil through it to the hydraulic cylinder.

Working Assembly of Jumpform:

Shutter of 1.5 m Lift ht is lifted first and then platform and Jumpform unit is lifted with the help

of jacks.

a) One unit consists of two rigs or vertical posts U beams 2.5 m center to center.

b) Maximum working distance between units is 8 m c/c .Minimum working distance between

units is 4m c/c.

c) No Jumpform part remains embedded in concrete shell .Anchor provided for fixing of

Jumpform units are taken out during working /climbing of jump form system.

d) 12 nos. anchors are required for 6 Nos. anchor plates of one unit.

e) Two through hole of 25 mm dia. is required per lift per Jumpform unit for supporting and

alignment of shutters. All these holes shall be filled with Normal cement sand.

Page 66: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

66

f) For erection of Jumpform units 4.5 m height of shell including ring beam height is required

over Raker columns.

g) Units of Jumpform system with jack and hoses are to be assembled absence of crane it shall be

lifted by tower crane. In absence of crane it shall be erected manually by chain pulley blocks /

ropes etc. Existing staging arrangement of initial ring beam supports shall be used for assembly

of Jumpform units.

h) CAT heads for dismantling of Jumpform unit‟s and lowering them at ground levels shall be

provided.

i) Self Wt. of one unit of Jumpform system structural parts is 3.5 ton (approx). Weight of timber

planks for platform is separate

Sequence of operation:

1 Fixing, Stripping and Lifting of Shutter Panels:

Fixing of shutters :

1) Insert top shutter bolts (25 dia.) from inside of shell so that bolts project past outside soldiers

enough to locate wedges

2) Tight all shutter bolts so that shutters are held in position.

3) Slide inside and outside steel pan shutters down into position.

4) Place temporary distance pieces between top of inside & outside shutters.

5) Adjust inclination of shutters to correct batter using inside & outside adjusted shutter bolts

Stripping of shutters:

Stripping of shutter panels will be start after the concrete is minimum Twelve hours old.

1) Loosen the bolts through inside shutter holding anchor screws

2) Lift inside steel PAN shutters up to Top platform.

3) Remove wedges from top shutters bolts withdraw bolts to inside of shell and tilt inside

shutters to rest against scaffold rig posts.

Page 67: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

67

4) Lift out outside steel PAN shutter up to top platform.

Lifting of shutter panels:

1) Attach Air winches to ladders beams.

2) Attach hook of air winches to the lifting U bolts on top of shutter

3) Lift the shell & hoist up so that bottom of shutters is level with top of previously concreted

lift.

4) From the inside of the shell insert shutter bolts partially into holes at top of previously

concreted lift.

5) Lower shutter on air winches to allow the shutter to rest on the bolts.

Lifting Operation of Jumpform System:

1) Rig unit is assembled at the ground level and erected on the concreted portion of 4.5 m height

along the periphery of the shell at a spacing of 8m c/c using tower crane.

2) Prior to the erection of system, brackets are fixed with anchors at 1.5 m height and frame is

erected over the brackets.

3) Shutter panels are fixed using tie bolts and concreting is started.

4) After completion of initial setting of concrete, shutter panels are lifted up.

5) Start the lifting operation of the rig using the hydraulic jack operation having stroke length is

1800mm.

6) The system will be ready for the concreting of next lift.

Page 68: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

68

Outer post Inner post

Hydraulic Ram U Beam platform extension platform support angle channel spacer

Height: 8.8 Mtr Length: 6.0 Mtr Width: 1.6 Mtr

SS Spring

Safety paul

Ms roller

wedge top

Fig3.10 component of jump form

SS Spring (16mm x 130 long) is fixed to safety paul for suspension of paul during jump form

lifting.

Safety Paul plays vital role during jumpform operation, it stops guide channel by lowering down

when hydraulic jack fails during lifting operation.

Page 69: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

69

MS Roller is used for smooth sliding of guide channel during the lifting of jump form.

Top Wedge is idle in normal condition. It is locked in the middle bracket during lifting

operation, after giving load to the middle bracket actual process of lifting is started.

MS Wheel is fixed to the bottom of U-beam, it is touched against shell inner wall and is used for

smooth movement of rig during lifting

Wedge (Bottom) is locked in the bottom most bracket in normal condition, by locking itself to

the bottom bracket, the bottom bracket takes the whole load (vertical) of inner rig.

Channel guide

Guide channel is the most important component of jump form, hydraulic ram is fixed to top end

of channel guide, and bottom of ram to U-beam. Wedge of channel guide is locked in top most

MS Bracket. while actual lifting operation of rig, the bottom MS Bracket is relieved from load

and the whole load of rig transfers to the top bracket where channel guide is fixed. In idle mode,

hydraulic ram will be in open state, and during lifting operation, opened ram is closed and the

whole rig is lifted to the next level. There are 8 safety locks in each channel.

Channel Spacer

Channel Spacer (ISMC 150 x 75) is used to maintain a gap of 162mm for sliding of guide

channel during lifting and is fixed to inner post with U Beam

Inner post

MS Box 80x80x4mm Thk ( 02 Nos ) of length 6.82 Mtr each is connected with U Beam, and

platforms (top and middle) are connected with it. Ladder beam is also connected on top of Inner

Post.

Page 70: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

70

Push-pull props

Push-pull props (02 Nos.) are fixed between middle and bottom platform of inner rig. The main

function of props is to level platforms of rig at various elevations of the tower as the tower

profile is hyperbolic.

Platform support angle

ISA 65 x 65 x 8mm - 04 Nos. of length 1.590 Mtr each are used for each platform, hence for 3

platforms 12 nos are required, top and middle platform supports (MS Box) are connected with

platform support angles. The lowest platform is providing working space for the hydraulic jacks

operation through a control panel operated by workmen. An assembly of two „U‟ beams with all

the total frame work and timber platforms is known as a “RIG” and is able to attend to a working

peripheral length upto 8.0 mtr.

Outer Post

Outer postof MS Box 80x80x5.4mm - 02 Nos of length 5.07 Mtr each is connected with platform

support angles of top and middle platforms. It is terminated at bottom of middle platform. Top

end of Outer Post is also connected to the ladder beam.

Bottom platform hanger

MS Tube 48.3 OD - 02 Nos of 3.9 Mtr each is connected with Outer post and bottom platform

support angles. Top end of the hanger is connected with outer post at bottom of middle platform,

and bottom end of hanger is connected to bottom platform support angles.

Platform Support

Inner Platform Support 03 nos. of MS-Box 90mm x 90mm x 365mm of length 3.168 Mtr each is

connected to the platform support angles (shell side) for top, middle & bottom platforms.

Page 71: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

71

Outer Platform Support 03 nos. of MS-Box 90mm x 90mm x 3.65mm of length 3.096 Mtr each

is connected to the platform support angles(outer) for top, middle & bottom platforms. Distance

between top and middle platform is 2.40 Mtrs, and distance between middle and bottom platform

is 3.80 Mtrs

Hand rails

Main Handrail of MS Pipe 48.3 OD – 04 Nos, of length 3.55 Mtr each is required in inner rig.

For middle platform 01 no of handrail tube is fixed to outer post, and 01 to inner post, and for top

platform 01 no. is fixed to outer post and 01 no. is fixed to bottom platform hanger for bottom

platform. All 04 handrail tubes are fixed at the height of 1.0 Mtr from top of platform box of all

three platforms.

10 Nos. of Platform extension vertical tubes are required in inner rig.MS Pipe 48.3 OD of 1.05

Mtr length is used for platform ext. vertical tube. These tubes are welded to platform extension

box. 04 Nos each (02 for inner extensions and 02 for outer extensions) are required in middle and

bottom platform, and 02 nos (outer extension) are required in top platform.

08 nos. of Platform extension handrails are required for inner rig. MS Pipe 48.3 OD of 1.80 Mtr

length is used for platform extensions handrail. 04 nos are required in the middle platform (02

for inner extensions and 02 for outer extensions), 02 nos each are required for top and bottom

platform at outer extensions. In the total length of 1.80 Mtr, 1.5 mtr is extended along with the

platform extension , and remaining 0.30 Mtr is clamped with main handrail. Platform extension

handrail can be adjusted as required along with the platform extension.

The joint between two adjacent rigs is provided with hinged flap and thus offers lifting of

individual rigs, and continuous platform at five levels – three on working face and two on outer

side.

Brace

MS pipe of 48.3 OD is used as brace in inner rig. 02 nos. of braces of length 2.80 Mtr are used

between top and middle platform, and are connected with inner and outer post for additional

Page 72: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

72

strengthening. MS Pipe 48.3 OD of length 4.20 Mtr is used as brace between middle and bottom

platform, it is fixed diagonally between set of bottom platform hangers. This brace is also used

for additional strengthening of inner rig.

Ladders and couplers

MS Pipe 48.3 OD of length 4.88 Mtr is fabricated to form a ladder as shown in above figure, 04

nos of such ladder beams are required for one jump form.

02 nos of ladder beams are fixed to RHS inner rig posts (inner and outer post) and RHS outer rig

hanger post (inner and outer post), and 02 nos are fixed same as RHS, to LHS inner and outer rig

posts. Couplers are used for coupling the ladder beam with outer rig hanger post Ladder beam is

used to connect the outer rig with inner rig and for stacking of reinforcement. Maximum of 0.6

MT of reinforcement can be stacked on ladder beam.

Safety Tip: While picking reinforcement from ladder beam, hazard of men fall due to imbalance

is possible, and reinforcement might also fall due to improper stacking, hence PPE should be

used and reinforcement should be stacked uniformly, persons should not work under stacked

reinforcement.

Hydraulic system

Hydraulic system plays major role in jump form system. Hydraulic system is used for lifting of

rig to the upper level.

5 HP motor (1445 RPM) : 01 no.

Oil Tank (200 Ltr Cap.) : 01 no.

Directional Control Valve : 01 no.

Dial-gauge : 01 no.

Pressure regulating valve : 01 no.

Filter : 01 no.

Dowty pump (3028) : 01 no.

Oil level indicator : 01 no.

Starter : 01 no.

Page 73: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

73

One power pack of adequate capacity can serve up to 18 rigs. Two hydraulic jacks fixed on to

the rig enable lifting of the rig to required height of 1.5 M height, as maximum hydraulic ram

travel distance is 1.5 M. Thus rigs are lifted one by one, on completion of the work on the top

platforms which is used for fixing of form work & shutter.

5 HP motor with 1445 RPM is fitted on top of power pack, which enables to rotate dowty

pump for pumping of hydraulic oil.

Oil tank of 200 Ltr capacity is used for storage and supply of sufficient hydraulic oil.

Hydraulic oil of grade 68 is recommended for use.

Function of directional control valve is to direct the flow of hydraulic oil to the desired

direction to operate the control panel fitted to jumpform.

Dial guage is fitted to power pack, to display the pressure of oil. Maximum of 150 bars is

set to supply for operation.

Pressure regulating valve is used to increase/decrease the pressure of oil, and is adjusted

by looking at dial guage indicator.

Oil filter is used to filter the oil from dust and other foreign particles.

Dowty pump (3028) is fitted inside the oil tank for pumping the hydraulic oil.

Oil level indicator is made available to check the sufficient level of hydraulic oil in tank

for smooth operation of the system.

Electrical starter is used to start the motor of power pack.

Control panel

Control panel is fitted to the rig in the bottom platform for lifting operation. Every rig has

individual control panel, as the rigs are lifted individually.

Direction control valve is used for operation of the system by keeping it in operational

mode, when the lever of DC valve is kept in operational mode the oil is supplied to the

hydraulic ram, and lifting operation is done. When the lifting operation is successfully

completed, lever of DC valve is kept in non operating mode and the oil flows to the

adjacent rig for further rigs operation.

Manifold is fitted with a set of two operating levers, 01 for each hydraulic ram, these

levers are used for operating the hydraulic ram. When the DC valve is in operational

Page 74: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

74

mode, oil passes through the manifold to hydraulic ram, and when levers are operated

hydraulic ram comes into action, and lifting process is done.

Main line comes from the power pack for flow of oil, and is connected to all the control

panel for lifting operation, at junction of rigs hydraulic hose is used to connect the main

line.

Return line returns the oil to power pack after successful completion of system operation.

Oil to hydraulic ram is supplied through main line for ram operation and returned through

return line after completion of operation, two main lines and two return lines are made

available in each control panel for two hydraulic ram.

Safety net

Safety net made of PP material of size 10 Mtr x 7 Mtr (mesh size : 75 sq.mm) is fixed to inner

rig of jumpform for arresting of men and material. Top end of the net is fixed to the top platform

handrail and bottom end is fixed to inner platform box of bottom platform. Regular cleaning of

safety net is required to maintain safe environment.

Merits of jumpform

1) This system avoids erection of scaffolding framework manually and helps to achieve very

safe construction.

2) The system does not need skilled labour and time for erection of scaffold up to the full

working height and also saves on labour and time required for its dismantling and

lowering to ground level.

3) This system on adaptation has resulted in considerable saving of construction time of

N.D Cooling Tower. The time taken for a cooling tower with conventional method used

to be double the time of the present system adopted, i.e jump form.

4) From safety point of view this system is considered to be the safest as it is providing 5

platforms (i.e 03 on the inner side and 02 on outer) throughout the circumference and has

Page 75: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

75

sufficient working space, and safety net is provided on inner and outer rig resulting safe

working atmosphere.

5) At any circumstance, if jump form collapses, it does not come to ground as ladder beam

rests on the RCC shell.

Top platform used for shutter lifting

Middle platform used for concreting work Bottom platform used for finishing work

Fig 3.11 Components of jump form

The hazards and their control measures for jumpform erection are as follows

Table2.10:Jumpform erection hazards and control measures

Hazards Control measures

Cut while contact with sharp

edges of jump form parts

1. Sharp edges shall be protected

2. Only trained person shall be allowed

3. Ensure training given to engaged person

4. Ensure implementation of PPE's like cut resistant hand

gloves, safety shoes, helmet.

Fall & Slip of Spanner 1. Material should be placed properly

Page 76: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

76

2. Engage trained workmen to execute the job.

3. Ensure safety net to catch fall of material.

Tripping due to peripheral

material

1. Ensure & maintain good housekeeping

2. All the material should be placed at the designated area.

Fall of whole assembly causing

fatal accidents

1. only tested & certified crane allowed for performing the task

2. Competent & certified crane operator should be engaged

3. Trained signal man engaged

4. Inspect the crane prior to start the work.

5. All the lifting tools and tackles must be checked and tested

e.g. D-shackles & slings etc.

6. Ensure unauthorized entry.

7. Ensure no person work under during assembly.

8. Ensure strict / proper supervision.

Improper placement of material

/ fall of loose material

1. Ensure all nut & bolts tighten properly before lifting whole

assembly.

2. Ensure designated area identified for storage of loose

material.

3. Ensure no one allowed to work below assembly area.

4. Ensure good house keeping

Failure of slings, d-shackles 1. Ensure all the slings & d-shackles shall be tested by certified

agency

2. Ensure inspection shall be done before start of work

Fall of person due improper

fixing of & anchoring

1. Ensure use of full body harness by all the person.

2. Ensure correct fixing / anchoring of point or life line rope.

3. Provide temporary working platform ad fixed properly from

both the side

4. Provide life line rope.

5. Ensure hand railing & foot railing

6. Only trained workmen engaged to execute the job.

7. Work should be done under supervision.

8. Hand Railing & foot railing will be provided on the jump

Page 77: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

77

form frame.

Jump form activities

Table2.11: Jumform activities

Do’s Don’ts

1. Do use sound planks for all working

platforms of Jump form.

2. Do daily housekeeping of all working plat

forms.

3. Do provide Top rail, mid rail & Toe guards

on JF plat forms.

4. Do use of good quality of safety nets for

inner & outer side plat forms.

5. Do daily inspection of JFs.

6. Do use of walky-talky for communication

between shell & ground

supervisor/engineer.

7. Use suitable PPE‟s like safety helmet,

Shoe, Safety Harness/belt etc.

8. Use RCCB/ELCB for all Distribution

boards on Jump Form.

9. Deploy experienced workers for Jump

form, shell concreting, shuttering & steel

fixing related activities.

10. Do inspect all lifting tools & tackles by

competent person before putting in use.

1. Do not leave openings in the plat form.

2. Do not use damaged planks for plat forms.

3. Do not use local & damaged safety nets for

Plat form JFs.

4. Do not sleep on the platform.

5. Do not store overload steel on ladder beams

of jump form.

6. Do not store loose steel on the ladder

beams.

7. Do not leave any openings without safety

net.

8. Do not horseplay on the working platforms.

9. Do not pull overloaded safety nets at the

time of cleaning, call for coworkers to pull

overloaded safety net.

10. Do not allow inexperienced for height

work.

11. Do not use damaged tools & tackles.

12. Do not start cleaning of working plat forms

of jump forms without communicating with

Page 78: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

78

11. Tie safety nets correctly in the junction of

two jump forms.

12. Provide 18mm flap of plywood between

the two jump forms with hinges.

13. Depute personnel to restrict the entry of

personnel in the restricted area.

14. Provide wooden boxes on the platforms to

store all loose materials & kept all loose

material in the provided wooden boxes.

15. Fill the gap between platform & shell with

the provision of 8mm steel mesh.

16. Check the effectiveness of safety latch,

safety springs before starting the jump

form lifting activity.

17. Provide cover all safety springs from

falling concrete for its long life &

effectively.

18. Anchor safety harness with lifelines.

19. Do use of right tools for right job.

20. Do cleaning of safety nets regularly.

21. Barricade all internal & outer periphery

area of NDCT.

22. Do use of ladders for getting up & down.

23. Do use of correct/good conditioned chain

pulley block for shuttering lifting.

24. Tie all pan shutters correctly to prevent

ground supervisors.

13. Doesn‟t use damage PPE‟s.

14. Do not lift Jump form without Safety latch

& bracket springs.

15. Do not work by drinking.

16. Do not allow parallel working (working on

the ground & work at height).

17. Do not allow to work at height without

valid height pass.

18. Do not run on the working platforms.

19. Do not store any loose material on the

working platform.

20. Do not throw any material from the height.

21. Do not use short cuts to getting up & down

from top platform to bottom platform.

22. Do not accumulate debris on the shuttering

plates.

23. Do not use platform planks to provide

support below the shuttering plate.

24. Do not leave half lifted shuttering plates.

25. Do not walk on the steel reinforcement

bundle which stored on the ladder beams.

26. Do not do any hot work on the jump form

without permission.

27. Do not put steel reinforcement vertically on

the working platforms of jump forms.

Page 79: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

79

falling from height.

25. Anchor chain pulley correctly with the

shuttering plate.

26. Follow instructions of works supervisors.

27. Do inform all near misses/incidents to

works supervisors on the time.

28. Do inform of any unsafe condition/act to

works supervisors.

28. Do not stand on the jump forms at the time

of lifting except jump form lifting

personnel.

29. Do not try to operate fire extinguisher

without valid reason.

30. Do not try to operate/handle any electrical

connection without electricians.

CHAPTER 4

4. RESULT AND DISCUSSION

4.1 Good practices followed in GIL Raipur site to prevent accidents

1) In each vehicle it is mandatory to have reverse horn, break light, hand brake ,rear view

mirror etc. also the vehicle must have PUC(pollution under control) certificate. A vehicle

without these things is not allowed to enter the site .

2) The condition of the platforms in jumpform are continuously monitored and if found in a

condition not suitable for work ,no workers are allowed to work on it unless the needful

is done

3) The jumpform are kept cleaned and housekeeping is done daily to prevent accumulation

of debris on it .

4) No one is allowed to go at height if he is not having Height Pass, despite of the fact

whether he is staff of GIL or Client

5) The height pass is renewed after every 6 months

Page 80: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

80

6) No minor worker or a mentally retarded person or person suffering from any disease is

allowed to work and is rejected during the induction training

7) No drunk worker is allowed to enter the work site and Heavy penalty is imposed to the

sub- contractor if his worker is found working after consuming alcohol.

8) The hydra is not allowed to work if not having limit switch, hook latch, reverse horn ,

load indicator .

9) The curve hoist for passenger should have third party testing certificate ,Limit switch,

emergency stop switch, alarm bell, fire extinguisher.

10) All RCCB, and earth pit resistance are inspected every month and a record is kept for the

same .

11) Mobile shed for the surveyors is given so that they can work while the work is going on

on the shell

12) No parallel work is allowed ,i.e if work is going on the shell than no one is allowed to

work under it on the ground level.

13) Tool box is done daily by the supervisors in the presence of safety personnel and daily

record is kept for the same .

14) Specialized training is given to the workers according to their job frequently

15) A lot of posters are displayed in the working are to encourage and motivate workers to

work safely

16) Prizes are given to individual workers and to the PRWs practicing safety in the working

area to motivate others workers to follow the safe working methods

Page 81: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

81

CHAPTER 5

5. SUMMARY AND CONCLUSION

The work is in progress and measures to prevent accidents are taken . Guidelines of safety

measures like checklists, work permit and other formats given by Gammon are implemented

GIL Raipur follows the best safety procedures and complies with all the safety rules and

regulation and complies with the standards of NBC and other standards which is proved by

the fact that the site has achieved the milestone of 3 million safe man hours, which also

proves that the efficiency of Safety Management System followed in Raipur .

Page 82: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

82

CHAPTER-6

RECOMMENDATION

Although the milestone of 3 million safe man hours has been achieved but there is always a

scope of improvement in the safety measures taken and the safety management system

implemented.

1. More safety audits has to be done to i.e every week there has to be a audit to find if the

safety measures taken are meeting the standards.

2. Since the most hazardous activity is the jumpform whether it is erection ,dismantling or

working on it , more training programes should be conducted to train every workers

3. Fire extinguishers has to be installed on the platforms of the jumpform or sand buckets

should be kept .i.e at least 2 fire extinguisher should be installed on each platform since

the planks and the flaps used are made of wood and can catch fire easily as welding

works are also done .

4. The platforms should be kept clean of debris and other unwanted materials i.e proper

housekeeping has to be carried out .

5. Continuous curing has to be done during the concreting works so that the waste concrete

should not form big lumps of debris

6. The safety nets should be cleaned every week and proper maintenance has to be done .

7. Proper size of Grittings should be placed in the gaps between the shell and the jumpform.

8. Every day before the start of work maintenance people should check the condition of the

jumpform and the platforms and only after they give assurance the work should be started

since after every jumpform lift there are some issues like gaps between shell and

platform, flaps between two platforms, hand railing and other issues should be solved

before the start of work

9. All the workers need to be trained to work on the platform , for eg how many people can

stand on a single platform, how much steel can be kept on each platform

10. In many industries workers meeting with accidents with vehicles while resting under or

behind it is a common, in order to prevent such accident “Delay Start Time” should be

Page 83: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

83

installed in all vehicles , i.e when the driver will start the engine ,loud alarm noise in the

form of horn will start which will make the worker who is resting to run and only after

the set delay time i.e 1 or 2 minutes the vehicle will start and move

11. Accident in batching plant is also common so Delay Start Time can be be installed to

prevent the accidents.

12. No vehicles without reverse horn, rear view mirror, helper shall be allowed to enter the

site to work

13. Awareness programes should be conducted regularly

14. Motivational activities like competition and prize distribution should be conducted to

motivate the workers.

15. All the workers should be trained to operate the fire extinguishers and for that more mock

drills should be there..

Page 84: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

84

REFERENCES

1. Gammon India Limited Data.

2. Behm M, 2005, Linking Construction Fatalities to the Design for Construction Safety

Concept, Safety Science, Number 43, Pages 589-611

3. Churcher D W, Alwani-Starr G M,Incorporating construction health and safety into the

construction”, Implementation of Health and Safety in Construction Sites, Alvels, Dias

& Coble (eds), ISBN 90-5410-847-9, 2006

4. ECI 2000 Safety and Health, Proceedings of the ECI/CIB/HSE international

Conference, London, European Construction Institute, Lough boroughed A G F Gibb,

June 245pp ECI, Publications

5. Gambatese JA, Hinze J and Haas C, Tool to Construction Worker Safety, Journal of

Architectural Engineering, Volume 3, 2010

Page 85: SAFETY MANAGEMENT IN THE CONSTRUCTION OF NATURAL DRAFT COOLING TOWER AT GMR.pdf

85

ANNEXTURE