Previous Issue: 20 September 2006 Next Planned Update: 15 August 2011 Revised paragraphs are indicated in the right margin Page 1 of 48 Primary contact: Branton, Minh A on phone 873-9526 Copyright©Saudi Aramco 2009. All rights reserved. Engineering Procedure SAEP-14 18 January 2009 Project Proposal Document Responsibility: Project Support and Controls Dept. Saudi Aramco DeskTop Standards Table of Contents 1 Introduction………………………………......... 2 2 Applicable Reference Documents……..….… 3 3 Proposal Contents and ER Estimate……...... 5 4 Project Improvement Effort……………….… 22 5 Reporting and Review Requirements…....... 27 6 Approvals and Waivers…………………....... 30 7 Contract Bid Package…………………….…. 33 8 Exhibits……………………………………...... 34 Exhibit I – Project Proposal Checklist………….. 36 Exhibit II – ER Estimate Package Checklist....... 38 Exhibit III – Contract Development Checklist….. 40 Exhibit IV – Benchmarking Data Sheet………… 42 Exhibit V – Bid Quantification Summary............. 46

SAEP-14.pdf

Embed Size (px)

Citation preview

  • Previous Issue: 20 September 2006 Next Planned Update: 15 August 2011 Revised paragraphs are indicated in the right margin Page 1 of 48 Primary contact: Branton, Minh A on phone 873-9526

    CopyrightSaudi Aramco 2009. All rights reserved.

    Engineering Procedure SAEP-14 18 January 2009 Project Proposal

    Document Responsibility: Project Support and Controls Dept.

    Saudi Aramco DeskTop Standards Table of Contents 1 Introduction......... 2 2 Applicable Reference Documents... 3 3 Proposal Contents and ER Estimate...... 5 4 Project Improvement Effort. 22 5 Reporting and Review Requirements....... 27 6 Approvals and Waivers....... 30 7 Contract Bid Package.. 33 8 Exhibits...... 34 Exhibit I Project Proposal Checklist.. 36 Exhibit II ER Estimate Package Checklist....... 38 Exhibit III Contract Development Checklist.. 40 Exhibit IV Benchmarking Data Sheet 42 Exhibit V Bid Quantification Summary............. 46

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 2 of 48

    1 Introduction

    This procedure outlines the requirements for preparing the Project Proposal and

    Expenditure Request (ER) Estimate package. The procedure is not intended to give

    instructions on the engineering effort, but to cover requirements that are important

    during the Project Proposal process. In summary it covers:

    Engineering specifications, standards and selected design requirements

    Quality, cost reduction and schedule improvement techniques, i.e., benchmarking, value engineering and value practices

    Project Proposal reporting, review, approval & waiver requirements

    ER Estimate preparation requirements

    Project Proposal, ER Estimate Package & Contract Development Checklists

    Contract Bid Packages

    The intent of the checklists is to insure compliance with key requirements. They are not

    intended to cover all detailed requirements of this procedure.

    1.1 Definition

    The Project Proposal is a document, which establishes the preliminary (front

    end) engineering scope definition, cost estimate basis and schedule for a

    proposed facility from the requirements included in the Design Basis Scoping

    Paper (DBSP) and the approved Project Execution Plan (SAEP-12). This

    includes the proposed facility design, general layout and the appropriate

    functional and performance specifications including the recently published

    applicable standards & codes. Project Proposal shall be of sufficient detail to

    prepare a 10% accuracy ER estimate, provide sufficient technical information

    for Saudi Aramco review and (where applicable) provide sufficient information

    to obtain detailed engineering, procurement and construction contract bids in

    accordance with the approved Contracting Plan.

    1.2 Purpose

    The Project Proposal documents the agreement on, and commitment to, the

    project scope, the project cost and design basis by the Saudi Aramco Project

    Management Team (SAPMT), Facilities Planning Department, Project Support

    & Controls Department, Proponent and other technical support groups. This is

    accomplished through careful evaluation of the project objectives during Project

    Proposal preparation to ensure the optimum results. The Project Proposal

    establishes the basis for Expenditure Request (ER) funding and is the baseline

    from which all subsequently considered scope changes are measured.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 3 of 48

    1.3 Preparation Timing

    Project Proposals must be completed and approved in time to support the

    Expenditure Request Approval (ERA) date.

    A complete ER Estimate Package must be submitted to Project Support &

    Controls Department / Project Controls & Estimating Division (PS&CD/PCED)

    at least 4 weeks prior to the 56D Estimate submittal due date to FPD Budget

    Director, as per the Capital Program ER Processing Schedule for Board

    EXCOM and local approval. Refer to Section 3.4.2 through 3.4.6 for ER

    Estimate Preparation requirements. Approved Project Proposal from SAPMT

    Department Manager, Facilities Planning and Proponent organization signatory

    is a mandatory requirement prior to issuance of the ER Estimate (Saudi Aramco

    Form 56D) to Budget Director.

    1.4 Application

    With the exception of Master Appropriation projects, Saudi Aramco requires a

    Project Proposal and ER Estimate for all Capital, Non-Capital and Expense

    Projects, valued more than $2 million, under the control of Engineering and

    Project Management (E&PM). The Project Proponent and SAPMT shall agree

    and document the level of detail needed prior to start of the Project Proposal.

    Projects that combine the preparation of DBSP and Project Proposal into one

    effort shall ensure that the requirements identified in this document which are

    relevant to the Project are met.

    2 Applicable Reference Documents

    The latest edition of the applicable reference documents shall be applied:

    Saudi Aramco Engineering Procedures

    SAEP-12 Project Execution Plan

    SAEP-13 Project Environmental Impact Assessments

    SAEP-25 Estimate Preparation Guidelines

    SAEP-31 Corporate Equipment and Spare Parts Data

    Requirements

    SAEP-140 Project Training Impact Assessment

    SAEP-302 Instructions for Obtaining a Waiver of a

    Mandatory Saudi Aramco Engineering

    Requirement

    SAEP-303 Engineering Reviews of Project and Detail Design

    Engineering Documentation

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 4 of 48

    Saudi Aramco Engineering Report

    SAER-5437 Guidelines for Conducting HAZOP Studies

    Saudi Aramco Engineering Standards (SAESs)

    Saudi Aramco Materials System Specifications (SAMSSs)

    Saudi Aramco Cost & Scheduling Manual

    Saudi Aramco Construction Safety Manual

    Saudi Aramco Safety Management System

    Saudi Aramco Form and Data Sheet

    8362-ENG Certification of Review of Saudi Aramco Materials

    Source Documents

    General Instructions

    GI-0005.002 Loss Prevention Policy Implementation

    GI-0020.500 Expenditure Control Expenditure Request Forms

    GI-0020.520 Project Change Request

    GI-0202.309 Allocation of Costs New Facilities Start-up

    GI-0202.451 Engineering Work Order Authorization for

    Preliminary Engineering Preparation

    GI-0400.001 Quality Management Roles & Responsibilities

    Design Basis Scoping Paper (DBSP) and applicable Study Documents

    Corporate Loss Prevention Manual

    Project Management Loss Prevention Program

    Supply Chain Management Manual

    DC Surplus Materials - Plant M011 of SAP system

    MVG076-01, DC Surplus Deferred Materials System

    Unrestricted Use Materials of SAP system (for SAMS Excess Materials)

    Saudi Arabian Manufactured Materials Listing from SAP

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 5 of 48

    Saudi Arabian Government Safety and Security Directives (SSDs)

    Construction Industry Institute (CII) Publications

    3 Proposal Contents and ER Estimate

    The following sections outline the items normally included in Project Proposals.

    3.1 Table of Contents

    3.2 Technical Requirements

    3.2.1 Project Summary

    This section provides a history of the existing conditions, a brief

    discussion of the proposed facilities and their justification, outlines the

    project objectives/scope and schedule, and briefly describes how these

    objectives will be achieved.

    3.2.2 Project Description

    This section provides scope and design information that establishes the

    performance specifications for the facilities, process, waivers or

    limitations. It shall address details concerning the design basis, proposed

    facilities including equipment design, capacities, location/layouts and

    other project related information. The list below provides common

    elements found in a typical scope.

    1) Facility/plant layout and location

    Note: The project scope boundaries and interfaces with other related facilities must be clarified prior to developing the scope of the project in the project proposal phase.

    2) Facility/process description, design basis and performance

    specification

    3) Process Flow Diagrams (PFDs) including heat and material

    balances

    4) Major mechanical, electrical, and utility requirements (type and

    quantity)

    5) Electrical one-line diagrams electrical area classification drawings

    6) Piping and Instrumentation Diagrams (P&IDs)

    7) Temporary and permanent on-plot and off-plot facilities

    8) Site survey, topography and soil data (Geotechnical Investigation)

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 6 of 48

    9) Demolition and modifications to existing facilities/plants

    10) Operating variables (as required by OSPAS)

    11) Corrosion control

    12) Impact on and interface with other related projects

    13) Environmental Impact Assessment (see SAEP-13)

    14) Security, fire protection & safety provisions (if required, Hazard

    Identification Plan of Major Hazards, fire hazard zone drawings,

    and fire system layout drawings)

    15) Communications, including government approvals if required

    16) Control systems (including SCADA) provided with Control System

    Block Diagram or System Architecture, instrument index,

    instrument cable routing and I/O count breakdown

    17) Project Execution Plan/Schedule

    18) Training requirements

    19) Land use permits for new facility sites or addition of facilities

    within existing plants. Include Proponent approved permits for lay-

    down areas, staging areas and office sites

    20) Strategy for project compliance with Project Quality Plan

    requirements

    21) Process & utilities system definition and turnover sequence

    22) Piping, electrical and control system tie-in /hot tap plan

    23) Studies & calculations developed during Project Proposal (i.e.

    ETAP study, PHA study, process simulation, etc.). All required

    engineering studies, including those defined in DBSP, must be

    carried out regardless of contracting strategy adopted, e.g., LSTK,

    LSPB, etc.

    24) Site Investigation Report

    25) Project Risks Assessment Report

    3.2.3 Scope Change from DBSP

    A) Definition of Scope Change

    A scope change is defined as any deviation from the Approved

    DBSP. Following are examples of typical scope changes:

    1. Equipment capacity and sizing changes

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 7 of 48

    2. Addition or deletion of equipment from the original list

    provided to PS&CD in conjunction with the DBSP for

    preparation of the budget estimate

    3. Plot plan changes

    4. Process control plan or system changes (changes in I/O

    counts, type of control system, etc.)

    5. Other design changes as a result of the following:

    Environmental Impact Assessment

    Preliminary Hazard Analysis (PHA) or Hazard and Operability (HAZOP) studies

    Project risk assessment

    Underground obstructions such as rock or utilities interferences, etc.

    Building Risk Assessment or any other Loss Prevention requirements

    Savings realized from Value Engineering and other Value Practices

    Site investigations

    B) Notification of Scope Change

    SAPMT shall promptly notify FPD, in writing, of any scope

    change with the cost and schedule impact and justification as soon

    as changes are identified. This allows timely assessment by FPD

    of the impact of these changes to the project. Change will be

    incorporated in the project scope based on FPD's assessment. All

    approved scope changes shall be communicated to PS&CD.

    C) Implementation of Scope Change

    If accepted for implementation, FPD shall issue a formal letter or

    DBSP amendment to SAPMT within two (2) weeks of the initial

    submittal and distribute a copy to PS&CD.

    D) Recording of Scope Change

    All scope changes shall be recorded in a special section in the

    Project Proposal package and ER Estimate Package. This section

    shall contain a list of all scope changes with justification, cost

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 8 of 48

    impact, schedule impact, initiator organization, date

    initiated/approved and any supported cost estimate documents.

    SAPMT shall maintain the list of the scope changes and

    continuously update it from the start of Project Proposal until the

    ER Estimate is complete.

    3.2.4 Communication Requirements

    Saudi Aramco construction projects normally require both temporary

    (during construction) and permanent communication systems. As

    procurement approval for radio frequencies and materials involves long

    lead times, communication systems require early identification and

    coordination between Information Technology organization and

    SAPMT. To facilitate these requirements, the Project Proposal shall

    contain the following:

    a) Summary of temporary and permanent communication system

    requirements. Identification of additional communication facilities

    and/or modification to existing facilities necessary to meet the

    project requirements.

    b) Identification of communications requirements to be handled by

    Information Technology organization and those, which shall be

    provided and funded by the project.

    c) Schedule of communication material requirements with an

    estimated site required delivery date.

    d) Identification and implementation plans of all communication

    disaster recovery and business continuity aspects of the projects.

    3.2.5 Safety and Security Directive (SSD)

    The SSD (reference SAES-O series) shall be adhered to by all projects,

    with exception of home-ownership & utility projects, in accordance with

    the directives given to Saudi Aramco by the Saudi Arab Government's

    Supreme Commission for Industrial Security. The SAPMT shall contact

    Consulting Services Department, Dhahran and the Safety and Industrial

    Security organization to obtain current safety and security requirements

    before proceeding with Project Proposal engineering. A separate section

    in the Project Proposal shall be devoted strictly to safety and security

    requirements.

    3.2.6 Preliminary Hazard Analysis (PHA)

    The objective in performing PHA studies is to improve process safety

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 9 of 48

    and/or minimize operability problems. The SAPMT in conjunction with

    the Loss Prevention Department (LPD), and Environmental Protection

    Department (EPD) shall decide which projects and specific facilities

    require PHA studies. Duplicate facilities shall not require a new PHA

    study. Only new or upgrade facilities that use, produce, process,

    transport, or store flammable, explosive, toxic or reactive substances in

    large quantities are candidates for PHA studies.

    The PHA studies shall normally be conducted during the Project

    Proposal stage. The Hazard and Operability (HAZOP) studies, if

    required, shall be performed during the detail design when the facility

    design is firm and no major design changes are forecasted.

    For buildings, a building risk assessment shall be performed when

    required by SAES-B-014.

    Any cost impact as a result of the PHA studies or building risk

    assessment must be identified and included in the ER Estimate package.

    3.2.7 Environmental Impact Assessment (EIA)

    EIA is required at the early stage in project planning. SAEP-13, Project Environmental Impact Assessments, establishes the procedures necessary to prepare the environmental impact assessments which shall

    be submitted to Environmental Protection Department Manager by the

    30% Project Proposal stage for review and approval. EPD will forward

    the final EIA document to the Ministry of Petroleum and Mineral

    Resources for their approval. Approval by the Ministry is required for

    all capital projects prior to expenditure request. Any cost impact as a

    result of the Environmental Impact Assessment must be identified and

    included in the ER Estimate Package.

    An environmental impact assessment:

    describes and quantifies project actions

    identifies those discharges and emissions regulated by environmental standards

    predicts the environmental changes resulting from the project, and

    demonstrates compliance with applicable Saudi Aramco and/or Saudi Arab Government environmental standards and policies.

    The discovery of new information or significant project changes that

    impact a previously completed and EPD approved EIA may result in

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 10 of 48

    cancellation of the existing assessment and re-submittal of an amended

    EIA to EPD for approval.

    The full environmental report with appropriate calculations is to be

    included with the Project Proposals issued to Environmental Protection

    Department, Technical Information Center (TIC) Dhahran, and

    Corporate Information Center (ASC) Houston. All other volumes will

    contain a summary only.

    3.2.8 Obtaining a Waiver from Saudi Aramco Engineering Standards and

    Materials System Specifications.

    Identify standards, procedures, equipment and materials that will require

    a waiver prior to incorporation into the facilities.

    3.2.8.1 Projects shall meet the requirements of Mandatory Saudi

    Aramco Engineering Requirements (MSAERs), which are in

    effect on the Project Proposal approval date. Changes to

    MSAERs approved after the Project Proposal approval date

    shall be mandatory only when:

    the changes affect safety, health, environment or security highlighted by the concerned organization. In this case, the

    impact of the changes on the project should be reviewed by

    Project Management with the Proponent, Loss Prevention,

    Industrial Security Operations, Facilities Planning

    Department, Project Support and Controls Department,

    Process and Control System Department, Information

    Technology, and others to determine applicability and

    extent of implementation.

    the changes result in cost savings to the project. In this case, SAPMT, Proponent and Engineering Services shall

    review and decide on implementation.

    A Project Change Request (PCR) shall be initiated to document

    and obtain approval to implement changes after the project has

    been funded (Refer to GI-0020.520, Project Change Request).

    3.2.8.2 Include waivers (reference SAEP-302 Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering

    Requirement) that shall reduce project cost without impacting design, safety or operational integrity of the facility.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 11 of 48

    Describe the variation in sufficient detail to permit technical

    evaluation by the appropriate reviewing agency.

    Include copies of waiver applications and approvals.

    Any approved waiver that has an impact on the Project must be

    identified in the Project Proposal and ER Estimate package.

    3.2.8.3 Deviations from SSD requirements shall be submitted in a

    letter format as per SAES-O-100 (General Requirements for

    Safety & Security) that describes the variation in sufficient

    detail to permit technical evaluation by the appropriate

    reviewing agency.

    3.2.9 Drawing Index and Drawings

    This section provides a list and copies of the drawings that define the

    scope of the project. It shall include key drawings such as PFDs, P&IDs,

    plant and equipment layouts, electrical one-line diagrams and other

    necessary drawings that are required to establish the design basis and

    assist in producing an ER quality estimate.

    3.2.10 Project Quality Plan

    SAPMT shall prepare a Project Quality Plan in accordance with

    GI-0400.001 (Quality Management Roles and Responsibilities). The

    SAPMT shall also ensure that the specific requirements for inspection

    are included in Schedule Q Attachment VI for all applicable contracts.

    3.3 Materials Related Requirements

    3.3.1 General

    The Project Proposal provides a table of major materials and equipment

    identified for the project. During preliminary engineering, the

    Engineering Contractor, with guidance from the SAPMT, shall review

    the Company DC (9COM) Surplus and Excess (9CAT) using SAP

    MMBE transaction to identify all acceptable or substitute materials

    which are available in Saudi Aramco inventories for possible use on the

    project, with the objective of:

    a) Incorporating materials, which require the least new cash outlay to

    Saudi Aramco

    b) Making maximum economic use of the materials available from

    surplus and excess cataloged material inventories

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 12 of 48

    c) Making maximum economic use of locally manufactured materials

    d) Providing full justification for any proposed purchases of

    contingent quantities or non-installed spares

    During Project Proposal preparation, the SAPMT shall request review,

    and may request assistance from the Materials Supply (MS) on all

    portions of the plan that involve materials related aspects of the work.

    SAPMT will continue to be responsible to ensure that the purchase order

    is in acceptable technical compliance with relevant MSAERs during the

    time the Contractor is handling the order. Purchase Orders for

    inspectable materials shall be reviewed by Inspection Department prior

    to placement, to ensure compliance with the Regulated Vendor List,

    Technical and Quality requirements.

    If procurement of major equipment and materials is on the critical path

    of the project schedule, SAPMT may elect to consider novation of these items to reduce their impact on the project schedule. Novation typically involves:

    1. placement of purchase order by the Management Contractor or

    Project Proposal Contractor with commitment only for engineering,

    and

    2. after ERA, transfer the purchase order to the successful LSTK

    Contractor on contract award.

    The purchase order transferred to the LSTK Contractor will cover the

    complete scope involving engineering and manufacture. Use of novated

    purchase orders should be approved by Services Review Committee

    (SRC) either as part of the contracting plan or as an individual item.

    3.3.2 Material Source List

    The materials source list identifies major equipment and material items.

    Where possible, an estimated dollar value and quantity required shall be

    indicated. Also indicate responsibility for inspection, expediting, traffic

    and transportation. The Project Proposal effort shall develop Quotation

    Requests (QRs) for major engineered equipment and critical items, and

    issue these QRs to vendors on a For Development Only basis to determine prices and delivery schedules. For purpose of preparing the

    ER Estimate, the major equipment list shall include account number, the

    item number, a brief description, the data sheet, a requisition number if

    available, the estimated value and other pertinent information. The

    following areas shall be segregated:

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 13 of 48

    a) Surplus Materials - 9COM Materials in Plant M011

    b) Excess Cataloged Materials - Unrestricted use 9CAT Materials in

    SAP transaction MMBE

    c) Locally manufactured materials and vendor warehoused materials

    (LDOR)

    d) Cataloged Materials Reservation (9CAT)

    e) Non-cataloged Materials (9COM)

    f) Contractor procurement Lump Sum Turnkey (LSTK) or Lump

    Sum Procure/Build (LSPB)

    g) Sole source materials and equipment

    3.3.3 Use-up Target Values

    The Surplus Inventory and the Excess Cataloged Materials Listings shall

    be reviewed to prepare the listing and estimated values of possible

    surplus and excess usage. During the Project Proposal development, this

    list shall be further refined to set the target values for use-up of those

    items that shall be reported during the life of the project. LSTK or LSPB

    contracts shall use the same format and shall estimate total commodity

    (9CAT) and engineered (9COM) material costs (regardless of originator)

    as the basis for determining use-up values. The target values are goals

    requiring extra effort to achieve rather than just a restatement of the

    original major items listed in section 3.3.2.

    3.3.4 Locally Manufactured Material

    During Project Proposal development, the SAPMT shall obtain a current

    list of approved locally manufactured products and sources from MS.

    This list shall be provided to LSTK & LSPB Contractors to encourage

    use of locally manufactured materials.

    3.3.5 Critical Plant Equipment Unit Spares

    A list of proposed installed spares for critical plant unit equipment and a

    list of non-installed capital spares proposed for entry into Saudi Aramco

    stores custody shall be provided along with the estimated cost for each

    item and justification for purchase. Comparison shall be made between

    spares specified in the Design Basis Scoping Paper and spares specified

    in the Project Proposal.

    3.3.6 Start-up Spare Parts

    Construct-only project materials furnished by Saudi Aramco need not

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 14 of 48

    address this subject because spares shall be furnished per SAEP-31

    (Corporate Spare Parts Data Requirement). For Procure/Build contracts,

    the SAPMTs shall specify start-up spare responsibility including how

    they shall be provided, the financial impact of purchase and final

    disposition of residual spares.

    The LSTK Contractor is responsible for providing start-up spares.

    Residual and/or unutilized start-up spares remain Contractor's property;

    such spares may not be purchased from the Contractor by Project

    Management. Proponent at their discretion has the option to purchase

    these residual spares against their Operating Budget for future use.

    Operations shall communicate with MS (Materials Control Department)

    to ensure the spares are reviewed against overall inventory needs, and do

    not adversely affect existing supplies. Defined start-up spares may be

    turned over to Saudi Aramco in accordance with the contract

    requirements provided that the quantities and types are in accordance

    with the Saudi Aramco stocking policy. For LSTK and LSPB contracts,

    start-up spares responsibility for free issue equipment provided by Saudi Aramco shall be stated clearly in the contract.

    SAPMT and the respective Contractors are responsible for the spare

    parts as outlined under SAEP-31. In all cases, the SAPMT/Contractors

    shall provide complete and accurate spare parts data packages necessary

    to support Saudi Aramco procurement of operating spare parts.

    3.4 Scheduling & Estimating Requirement

    3.4.1 Scheduling Requirements

    This section contains a Level III project summary schedule that shall be

    developed during the Proposal phase based on information from the

    Project Milestone Schedule, WER Schedule and other data as they

    become available during the DBSP and Project Proposal.

    Project Summary Schedule should be developed as soon as Preliminary

    Engineering starts and will be used as a working tool in the absence of a detailed schedule by Contractor. The Project Summary Schedule shall

    be used as a guide for ER estimate preparation, early identification of

    long lead material procurement items, Contracting Strategy and technical

    evaluation of Contractors and start-up planning. As-Built schedules

    from similar projects can be made available from PC&ED Scheduling

    Group to be used as a guide for the initial preparation of the Level III

    schedule.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 15 of 48

    Project Summary Schedule addresses all the project life cycle activities

    in a summary format. It must be logic driven, based on the Critical Path

    Method (CPM). The Schedule should contain sufficient detail to show

    potential material or equipment novation, long lead items, contract procurement activities, detailed engineering by discipline leading to

    major deliverables, mobilization, early works, shutdown, tie-ins, testing,

    loop checks, pre-commissioning, start-up, interface with Proponent and

    other projects.

    Project Summary Schedule shall also include ER estimate preparation

    and approval activities including Estimate Kick-off, milestone dates for

    Scope Compliance and any ER Estimate reviews or any other design

    reviews, MTOs for the relevant disciplines, equipment pricing,

    NOVATION of equipment and/or Prior Approval Expenditure Request

    (PAER), Technical Review Meetings, and the final approval of the

    Project Proposal and 56D preparation and submittal to the Facility

    Planning Department (FPD).

    The schedule shall form the basis for the original (Rev.0) Project

    Completion Schedule (PCS). The Project Summary Schedule further

    expands the level of detail while still supporting critical and key

    milestone dates defined and prescribed in the contract (Schedule B). Project Summary Schedule is expanded to include critical milestone

    dates as well as any other key milestones that are provided by

    Contractors. If novation material and equipment is included in the execution plan, the date of purchase order and required delivery date

    should be incorporated in the schedule. The schedule shall include

    review time requirements specified in SAEP-303 (Engineering Reviews

    of Project and Detail Design Engineering Documentation). Contact

    Scheduling Engineering Group of PS&CD/PCED for more detailed

    information on Project Summary Schedule.

    3.4.2 ER Estimate Requirements

    Project Proposals must be completed and approved in time to support the

    Expenditure Request Approval (ERA) date. A complete ER Estimate

    Package must be submitted to PS&CD, at least four (4) weeks prior to

    submittal of 56D Estimate to FPD Budget Director as per Capital

    Program ER Processing Schedules for Board, EXCOM and local

    approvals.

    SAPMT shall be responsible for preparation of the ER Estimate package:

    in accordance with SAEP-25 (Estimate Preparation Guidelines)

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 16 of 48

    in conformance with the Work Breakdown Structure and Standard Code of Accounts (SCA) established by SAPMT and PS&CD

    to achieve a quality estimate with an accuracy of (10%) of project final cost

    using the Estimating Tool Aspentech Kbase, particularly for oil and gas process facilities, as a preferred estimating software. Selection of

    any other estimating tool should be discussed with PS&CD.

    Effective January 2008, Aspentech KBase shall be used as a mandatory

    estimating tool in the preparation of the ER Estimate for oil and gas

    projects greater that $100 million. Waiving this requirement must be

    approved by the PS&CD Manager.

    The final ER Estimate shall be jointly reviewed and approved by

    PS&CD and SAPMT.

    3.4.3 ER Estimate Review Meetings

    Initial, Interim and Final ER Estimate review meetings will be held by

    members of SAPMT, Engineering Contractor, and PS&CD during the

    course of Project Proposal phase. SAPMT will be responsible for

    organizing the meetings, providing the required documents to PS&CD

    prior to review meetings and inviting all concerned parties to participate

    in the ER Estimate Review meetings.

    A) Initial Kick-off Meeting

    The initial kick-off meeting will be conducted before the 30%

    completion of Project Proposal. An ER Estimate Plan, as described

    in Section 3.4.4, shall be prepared and completed prior to the Kick-

    off Meeting. PS&CD will take an active role in defining Saudi

    Aramco ER estimate preparation requirements and providing basic

    information to the SAPMT and Contractor.

    B) Interim ER Estimate Review Meetings

    The purpose of the interim meeting is to review the progress of the

    ER estimate preparation activities. The number of interim

    meetings should be established during the initial ER Review

    meeting.

    Minimum one (1) week prior to the review meeting, SAPMT shall

    provide a complete set (hardcopy and electronic file) of the ER

    Estimate with support documents to PS&CD for review.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 17 of 48

    The interim review meeting deliverables shall include, but not be

    limited to:

    ER Estimate as developed to date, with MTOs by Area and WBS

    ER Estimate Basis

    ER Estimate Detailed Schedule

    Multiple Discipline Drawings including PFDs, P&IDs, Plot Plans, One Line Diagrams, etc.

    A list of all scope changes from the DBSP identified to date. The list will include itemized scope changes with justification

    and cost/schedule impact for each deviation item (per Section

    3.2.3)

    Major equipment quotations

    Recent quotations for Engineering and Construction rates

    All discipline Material Take-offs (MTOs) by Area and WBS

    Market Outlook study, as required

    Project Risk Assessment, as required

    C) Final ER Estimate Review Meeting

    1. A complete ER Estimate Package must be completed in

    accordance with the established ER Estimate Plan and

    submitted to PS&CD/PCED at least four (4) weeks prior to the

    56D Estimate submittal due date to FPD Budget Director.

    Refer to Section 3.4.5 for ER estimate deliverables.

    2. After receipt of the ER Estimate package, PS&CD will conduct

    a meeting with SAPMT and Engineering Contractor to review

    and finalize the estimate as deemed necessary.

    3. Minimum of two (2) weeks prior to 56D Estimate submittal due

    date to FPD Budget Director, SAPMT shall provide PS&CD

    the Project Proposal sheet approved by SAPMT, FPD and

    Proponent and a copy of the Technical Meeting minutes with a

    complete list of all finalized items with detailed cost estimate of

    impacted items. These documents are required for finalizing

    the 56D Estimate for submittal to FPD Budget Director.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 18 of 48

    When the ER Estimate is over or under by more than 10% of the

    Budget Estimate, PS&CD and SAPMT shall jointly prepare a

    scope reconciliation and comparison between the approved Budget

    and the established ER Estimate. The review shall include a list of

    all scope changes from DBSP which will be part of the ER

    Estimate package.

    D) Scope Compliance Review Meetings

    Compliance Review meetings will be conducted, as deemed

    necessary, by SAPMT in coordination with FPD and PS&CD to

    ensure that the scope of Project Proposal is in compliance with the

    approved DBSP.

    SAPMT shall prepare and provide all attendees with a complete list

    of accepted scope changes and relevant supported documents for

    the Scope Compliance Review meetings. PS&CD shall be

    responsible for validation of cost and schedule impacts for all

    scope changes.

    3.4.4 ER Estimate Plan

    SAPMT shall be responsible for developing an ER Estimate Plan which

    will be reviewed and discussed during the initial kick-off meeting. At

    the minimum, the ER Estimate Plan should contain:

    Project scope of work

    Site development plan and investigation

    A detailed schedule with major and interim milestones for completing the ER Estimate deliverables

    A quality control plan for estimate preparation

    Specific plan and methodology for performing market outlook and project risk assessment for selected projects greater than $300 million

    (refer to Section 3.4.6)

    Methodologies for developing estimate basis, material take-offs (MTOs), pricing of material and equipment, unit rate for engineering

    and construction based on current market conditions and project risk

    assessment

    Plan and methodology for developing internal and external benchmarking

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 19 of 48

    Identification of estimating software to be used for preparation of ER Estimate

    Work Breakdown Structures (WBS) and Standard Code of Accounts (SCA) to be used for the project

    A list of ER Estimate deliverables required for interim review and final review

    An organization chart of the estimating team

    Roles and responsibilities of all involved parties in developing the ER Estimate and identifying point of contact from each organization

    3.4.5 ER Estimate Deliverables

    The ER estimate will be based on 100% Project Proposal which includes

    equipment lists, equipment sizing, plot plans, P&ID, single line

    diagrams, cable schedules, instrument index summaries, I/O counts, bulk

    material take-offs, and other related project documents and drawings.

    The following major contents of deliverables should be included in the

    ER estimate package:

    Approved Project Proposal

    Drawings, specifications, reports and other relevant documents necessary to define the project requirements

    Approved Execution and Contracting Plan

    Project Summary Schedule

    An ER Estimate package which includes a hard-bound copy and an electronic copy on a CD with all required backup documents as

    specified in SAEP-25

    A complete list of all scope changes from the DBSP that will be implemented in the Project Proposal. The list will include itemized

    scope changes with justification and cost/schedule impact for each

    deviation item

    Copies of Technical Review Meeting Minutes

    Copies of ER Review Meeting Minutes with status of outstanding and implementation items

    Copies of PHA or HAZOP Meeting Minutes with summary of changes, if applicable

    For detailed listing of deliverables, refer to the Exhibit II, ER Estimate

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 20 of 48

    Package Checklist.

    3.4.6 Market Outlook Study & Project Risk Assessment

    PS&CD/PCED will coordinate with SAPMT to identify projects worth

    $300 MM or greater that will be required to do a Market Outlook Study

    and Project Risk Assessment. Market trends and project risks are

    assessed to avert potential impacts on project development and

    execution. Results of these studies shall be included in the basis of

    estimate and contingency rates shall be recommended accordingly.

    These shall include, but not be limited to, the following:

    Worldwide demand for Engineering and Construction services

    Market conditions that affect major equipment procurement pricing and delivery

    Trends related to supply and demand of major equipment and bulk material in the Middle East that could affect schedule and costs on

    the project

    Availability of Engineering Contractors to undertake LSTK contracts in Saudi Arabia

    Assessing the financial markets and institutional support for current and future Middle Eastern projects

    Project risks study on constructability, tie-in execution, environmental, security and other factors related to a specific project

    Forecast of Engineering Contractors Overhead and Profit Margins

    Any other factor that can impact the future cost of the project

    Following are some of the resources that can be used in developing a

    Market Outlook study:

    Trade Organizations

    Trade Magazines

    Financial Institutions studies and surveys

    Government studies and surveys

    Industry studies and surveys

    Manufacturers and Suppliers data

    3.5 Appendix

    The Appendix shall include letters, minutes, land use permits and other pertinent

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 21 of 48

    documents written during Project Proposal development.

    3.6 Numbering Project

    All Project Proposals shall be numbered by the issuing office as follows:

    Saudi Aramco APP Series (Numbers assigned by the Technical

    Information Center, Dhahran)

    ASC TPP Series (Numbers assigned by the Corporate

    Information Center, Houston)

    APP or TPP numbers shall be on the Project Proposal cover sheet.

    3.7 Training Impact Assessment

    SAEP-140 (Project Training Impact Assessment) requires that a Training Impact

    Assessment be prepared as part of the Project Proposal for all projects for which

    training programs for operations and/or maintenance personnel will be required.

    These training programs will not be provided by the project and costs for training

    are not be paid for by capital funds. (Refer to GI-0202.309, Paragraph 4.5)

    The Proponent is responsible for identifying any training requirements for a

    project by preparing a Training Requirement Statement prior to the start of the

    Project Proposal.

    If training is to be required, a Training Impact Assessment is to be prepared in

    accordance with SAEP-140. SAPMT is responsible for incorporating the

    findings of the Training Impact Assessment in the final Project Proposal.

    SAPMT may also be required to implement the findings of the Training Impact

    Assessment as included in the approved Project Proposal. These may include:

    3.7.1 Incorporating contract provisions that require the Contractor to develop

    multiple quotations for specified equipment so that the cost of training

    can be taken into consideration when selecting the life-time, low-cost

    supplier. These provisions will allow Saudi Aramco to direct the

    Contractor to place its order with one of the proposed technically

    acceptable suppliers and will provide for additional payment to the

    Contractor if the selected supplier did not offer the lowest base price to

    the Contractor.

    3.7.2 Incorporating requirements for the Contractor to include provision in its

    purchase orders for specified equipment that establish fixed prices for

    training services or material to be procured at a later date by Saudi

    Aramco. This will reduce the possibility of a supplier overcharging

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 22 of 48

    Saudi Aramco when training services or materials are procured on a

    single-source basis.

    4 Project Improvement Effort

    This section comprises of activities that on implementation would optimize project cost &

    schedule, improve quality of the Project Proposal and assure project execution success.

    4.1 Value Engineering

    Value Engineering (VE) is an organized analytical process that can be used to

    optimize the life cycle cost and performance of a facility or system. The VE

    process systematically identifies opportunities to increase value by removing

    unnecessary costs without sacrificing quality, function, or reliability.

    4.1.1 VE Study Selection Criteria

    SAPMT shall initiate a formal VE study during the Project Proposal

    development stage when:

    The estimated BI value exceeds $50 million, or

    The estimated BI value is between $10 $50 million and a VE study was not conducted during the pre-planning or DBSP development

    stage, or

    The estimated BI value is between $10 $50 million, and the pre-planning or DBSP stage VE Report recommends that a Project

    Proposal stage VE study is required.

    4.1.2 VE Study Planning & Coordination

    VE studies should be completed during the early phase of the Project

    Proposal, but not later than the 30% completion milestone date. For

    scheduling purposes only, VE studies shall be coordinated with the Capital

    Program Optimization Division of Project Support & Controls Department

    (PS&CD/CPOD). The requirements for conducting VE studies shall be

    identified in the Project Proposal Contractors scope of work.

    VE studies shall only be facilitated by either a Certified Value Specialist

    (CVS), or local Engineering Contractor personnel who have been

    certified by PS&CD/CPOD to conduct VE sessions.

    Requests for VE study guidance, and information on Consultants and

    local Engineering Contractor personnel certified to facilitate VE sessions

    should be directed to PS&CD/CPOD.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 23 of 48

    4.1.3 VE Proposal Implementation & Reporting Requirements

    The effectiveness of a VE study depends on the successful

    implementation of accepted proposals and on the prompt resolution of

    pending proposals. VE proposals that are accepted by the Proponent

    Organization and SAPMT are to be reviewed by FPD, and CSD if

    related to standards requirement, before being incorporated into the

    Project Proposal Scope of Work.

    The status and resolution of all accepted and pending VE proposals shall

    be documented in the Value Engineering Section of the Project Proposal.

    A copy of the final VE Report shall be distributed to the PS&CD/CPOD

    Division Head.

    4.2 Benchmarking

    Benchmarking is an improvement process used to discover and incorporate

    project cost, schedule, front-end loading, value improvement and operability

    into project execution strategy.

    The benchmarking process will be centralized so that all benchmarking activities

    are managed through PS&CD/PCED. Benchmarking will be conducted at

    study, late stages of the DBSP, early stages of the Project Proposal as well as

    towards the completion of a project. Projects will be selected by PS&CD for

    either external or internal benchmarking.

    The objective of Benchmarking analysis at the early stage of Project Proposal is

    to identify and compare key project parameters such as project scope, quantity,

    cost, schedule, value practices and execution strategy, against the Companys internal historical statistics of similar projects. The project data also are used for

    benchmarking against the industry world class projects with similar scope. The

    result of the benchmarking analysis can be used for improving project execution

    plan.

    4.2.1 Internal Benchmarking Requirements

    For all projects except community projects, school and home-ownership,

    SAPMT shall provide key project data to PS&CD/PCED for internal

    benchmarking purposes. A sample of benchmarking data sheet is shown

    in Exhibit IV. This internal benchmarking data will be part of the ER

    Estimate package.

    4.2.2 External Benchmarking Requirements

    PS&CD/PCED will coordinate with SAPMT to identify projects with

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 24 of 48

    value of $100 MM or greater to be benchmarked. Projects less than

    $100 MM may be benchmarked if related to core business.

    PS&CD/PCED will perform the leading role for the selection of the

    Consultant, development of benchmarking criteria, and implementation

    of the formal benchmarking study.

    The analysis starts as early as the study phase and DBSP, or at any

    appropriate stage of the Project Proposal development, but no later than

    90% Project Proposal progress, comparing key parameters of the project

    with an external industry-wide database. The analysis would address

    key project outcomes and associated risk based on the Project Proposal

    effort to date. As a minimum, the following areas should be addressed

    and compared to industry norms, the Gulf Region and Best in Class:

    Status of front-end loading (FEL), i.e., project definition, at the time the benchmark analysis is prepared

    Use of value improvement practices

    The projected total installed cost (TIC) of the project

    An analysis of the contingency requirement based on project scope and FEL

    Engineering as a percentage of TIC

    Time required for total project execution (ERA through Onstream)

    Time required for the construction phase

    Expected time required for start-up

    Long lead material deliveries comparison

    General or specific requirements included in the Project Proposal Scope of Work that are non- industry standards

    Execution strategies

    A Benchmarking section shall be included in the Project Proposal book

    to include the summary benchmarking report prepared by an outside

    Consultant or by the Engineering Contractor.

    4.3 Energy Optimization Study

    Capital projects involving the addition of or modifications to industrial

    processes with combined fuel and power consumption exceeding $2 million per

    year (combined) shall be optimized for the efficient use of thermal and electrical

    energy.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 25 of 48

    For purposes of the energy study, an industrial process is defined as one that

    includes fired heaters, boilers, pumps, compressors, steam turbines, or gas

    turbines. Non-industrial facilities such as buildings, roads, warehouses, storage

    depots, and non-process operations such as IT or instrumentation upgrades are

    excluded.

    The technical approach and work scope for the energy study should address one

    or more of the following issues:

    Process Integration, using Pinch Analysis techniques

    Equipment Load Management policies

    Adjustable Speed Drives

    Driver Selection

    4.3.1 A preliminary Process Integration study of the project facilities shall be

    conducted only when the combined fuel consumption of the in-scope

    process units exceeds 100 MM Btu/h. It is necessary only to provide the

    optimum practical utility consumption targets in comparison to the utility

    requirements for the un-optimized process design; detailed design of the

    heat exchanger network and combined heat/power system to achieve

    these targets is not required.

    4.3.2 For energy consuming or conversion equipment (pumps, compressors,

    turbines, boilers, and furnaces) in parallel operation, the study shall

    identify the optimum number of equipment that should be operated over

    the expected range of plant operating rates, considering the trade-off

    between energy consumption and meeting production goals. Load

    management policies are required only when the energy consumption for

    a particular service or application exceeds 1000 HP (if rotating

    machinery) or 16 MM Btu/h (if fuel-fired equipment).

    4.3.3 The economic feasibility of Adjustable Speed Drives (ASDs), whether

    variable frequency type or other, shall be evaluated for individual

    motors/drivers of 2000 HP or greater. Capital costs should be balanced

    against the combined energy and non-energy benefits.

    4.3.4 Rotating machinery with individual power loads of 5000 HP and higher

    shall be evaluated for selection of optimum driver type electric motor, steam turbine, or gas turbine.

    4.3.5 Energy efficiency for individual items of equipment (e.g., motors,

    boilers, etc.) is covered separately by Saudi Aramco equipment

    standards. Evaluation of alternative equipment options is not required as

    part of the energy study scope.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 26 of 48

    The optimum time to conduct such a study is the earliest possible date after

    preliminary PFDs, including heat and material balances, are available, and the

    plant fuel/power consumption estimates have been determined. Generally, this

    would be after 30% completion of the Project Proposal, but no later than 60%

    Project Proposal completion.

    The full energy optimization study report, including all supporting data and

    calculations, must be submitted to the Energy Systems Unit of Consulting

    Services Department for review.

    4.4 Other Value Practices

    SAPMT shall implement applicable Saudi Aramco and other industry value

    practices during Project Proposal development to optimize project planning and

    execution. PS&CD/CPOD is available to assist SAPMT in selecting the

    appropriate value practices and facilitating their implementation.

    The requirements for conducting specific Value Practices shall be identified in

    the Project Proposal Contractors scope of work. Value Practice sessions shall only be facilitated by either approved Consultants, or local Engineering

    Contractor personnel who have been certified by PS&CD/CPOD. For

    information on approved Consultants and local Engineering Contractor

    personnel certified to facilitate Value Practice sessions, contact PS&CD/CPOD.

    The following value practices have shown proven payback for Saudi Aramco

    projects.

    Constructability

    Effective and timely integration of construction knowledge into the

    conceptual planning, design, construction and field operations of a project.

    Optimum timing during project proposal phase is at 30% Project Proposal.

    Project Definition Rating Index (PDRI)

    Held at 60% Project Proposal involving SAPMT, Proponent, Contractor, and

    other parties as needed to measure project proposal completeness and clarity.

    PDRI consists of about 70 elements that identify and very precisely

    describes each critical element in a preliminary engineering scope definition

    package.

    Lessons Learned

    Systematic search for applicable existing lessons learned from Saudi

    Aramco Project Management Lessons Learned database and other sources.

    Implement applicable lessons to avoid repetition of problems and build on

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 27 of 48

    successes experienced by other projects. Also collect and submit new

    lessons learned per SAEP-329 Project Close-out Report.

    Project Execution Planning Workshop (PEPW)

    Half-day workshop to promote ownership, commitment, and alignment of all

    project stakeholders including SAPMT, FPD, Proponent, Contracting, Loss

    Prevention, and other involved parties.

    Schedule Optimization

    Utilization of Schedule Reduction and Schedule Compression techniques to optimize the schedule for project completion.

    Planning for Startup

    Extensive set of tools and techniques used by all Project Stakeholders, PMT,

    Proponent, Contractors, etc., to help facilitate a successful facility start-up

    and stable long term operation.

    Scope Control & Change Management

    Scope Control is a preventative process that starts with a detailed project

    scope and ensures discipline in changing the scope during execution.

    Change Management involves establishing and clearly communicating to all

    project stakeholders a system for recognizing, evaluating, and implementing

    changes during all phases of the project.

    Other

    PS&CD will identify and implement other value practices that become

    available between revisions of SAEP-14 that offer value improvement to the

    project.

    5 Reporting and Review Requirements

    5.1 Project Proposal Distribution for Review and Meetings

    Draft Project Proposals shall be distributed for review to the appropriate

    members of Saudi Aramco Management and attendees of the Technical Review

    and Project Proposal Meetings. Distribution of the Project Proposal narrative

    shall be in electronic format (in Microsoft Word).

    The E-Review electronic review system is the Companys standard method for review of engineering drawings and documents. SAPMT should submit review

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 28 of 48

    packages through this system unless there is a compelling reason to do

    otherwise. The E-Review procedures and guidelines are provided in SAEP-303.

    The SAPMT and proponent are responsible for determining the recipients. As a

    minimum, the following represents a list of various organizations that shall be

    considered for receipt of the Project Proposal. However, only those

    organizations with direct involvement shall receive the Project Proposal.

    Executive Management:

    - Proponent Organizations, i.e.

    Ras Tanura Refining

    Northern Area Producing

    Southern Area Producing

    Jeddah/Riyadh Refining

    Yanbu Refining

    Distribution Operations

    Abqaiq Plants & Pipelines

    Gas Operations

    Medical Services

    Employee Relations

    - Petroleum Engineering and Development

    (for production-related projects)

    General Management:

    - Industrial Security Operations

    - Proponent organization

    Management:

    - Oil Supply Planning and Scheduling Department

    (for all proposals related in any way to oil, gas, NGL and/or refined product

    movement and handling)

    - Computer & Communications Engineering Department

    (for all projects involving communications)

    - Purchasing Department

    - Power Distribution Department

    (for all projects related to power facilities at 2.4 kV and above)

    - Abqaiq, Dhahran or Ras Tanura Utilities Department

    (for the area community projects only)

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 29 of 48

    - Facilities Planning Department (mandatory)

    - Project Support & Controls Department (for information only)

    - Consulting Services Department

    - Inspection Department

    - Loss Prevention Department

    - Environmental Protection Department

    - Process & Control Systems Department

    - Roads & Heavy Equipment Department

    - Industrial Security Department

    - Fire Protection Department

    5.2 Technical Review Meeting

    The Technical Review Meeting shall be held no sooner than ten (10) working

    days after distribution of the Project Proposal for review. Location, date, and

    time of the meeting shall be announced in the cover letter distributed with the

    Project Proposal. The Technical Review Meeting shall discuss all technical

    aspects of the Project Proposal, resolve technical questions, address

    environmental issues and review the Project Summary Schedule. Interim

    technical review meetings shall be conducted as required by SAPMT depending

    upon the type and complexity of the project. Items not resolved at the final

    technical review meeting shall be addressed in the Project Proposal Meeting.

    Substantive changes resulting from the technical review meeting shall be

    incorporated as appropriate into the Project Proposal documents.

    SAPMT shall prepare minutes of the Technical Review Meetings and distribute

    the minutes, electronically whenever possible, to all persons who either received

    the Project Proposal or attended the Technical Review Meeting. The minutes

    shall include the estimated cost and schedule effects of major changes from the

    DBSP/Project Proposal as originally prepared. Refer to 3.2.3 for definition of

    major scope change.

    The subject of critical plant equipment unit spares (capital spares) per section

    3.3.5 shall be addressed, and proposed purchases shall be reviewed.

    5.3 Project Proposal Meeting

    The purpose of the Project Proposal Meeting is to resolve any outstanding items

    remaining after the Technical Review Meeting and to finalize the project scope.

    The Project Proposal Meeting shall be scheduled no sooner than five (5)

    working days after distribution of the minutes of the Technical Review Meeting.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 30 of 48

    The delegated representatives of the Project Proposal approval authorities

    (section 6.1.1) shall attend this meeting in order to make decisions on matters

    not resolved in the Technical Review Meeting.

    SAPMT shall be responsible for preparing and distributing the minutes of the

    Project Proposal Meeting to those persons who either received a copy of the

    Project Proposal or attended the Project Proposal Meetings.

    For selected small projects, the Technical Review and Project Proposal

    Meetings can be combined into one meeting if concurred by Proponent and

    FPD. In this case, the reviewing organizations should send personnel authorized

    to make decisions to attend the meeting.

    5.4 Distribution & Storage of Approved Project Proposals

    Following the approval of the Project Proposal, a final approved copy shall be

    distributed as follows:

    5.4.1 ASC

    An electronic copy of every Project Proposal shall be sent to Corporate

    Information Center (CIC), Houston.

    5.4.2 Saudi Aramco

    SAPMT shall send copies of the approved Project Proposal to:

    - Facilities Planning Department (FPD) - one hard copy, to be used as

    a "working" document for five years or for the duration of the

    project, whichever is longer.

    - Technical Information Center (TIC), Room E-3100, EOB, Dhahran -

    one electronic copy for archival purpose.

    - Project Support & Controls Department (PS&CD) - one electronic

    copy, for input in the Electronic Image Document Management

    System.

    The electronic file submissions shall be on CD-ROM and contain an

    index at the beginning of each file medium to facilitate retrieval of stored

    data. The electronic text, spreadsheet, and graphical data shall be in

    Microsoft format, and drawings shall be in accordance with Saudi

    Aramco standards and formats. Scanned documents shall be in Acrobat

    format in accordance with the corporate standard maintained by

    EK&RD/Drawing Management Unit.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 31 of 48

    6 Approvals and Waivers

    6.1 Approval Process

    6.1.1 Approvals

    SAPMT shall be responsible for obtaining Saudi Aramco approval for

    the Project Proposal from the appropriate individuals listed. Executive

    Management may delegate the approval authority to General

    Management level. Obtaining these signatures constitutes full Project

    Proposal approval. The recommended order for routing and approval

    will be as follows, however, SAPMT may seek parallel approval from

    more than one organization at the same time where appropriate.

    - Manager, Facilities Planning Department

    - Manager, Loss Prevention Department

    - Manager, Power Distribution Department

    (for all projects having power facilities of 2.4 kV and above)

    - Manager, Consulting Services Department

    - Manager, Environmental Protection Department

    - Manager, Oil Supply Planning and Scheduling Department

    (for all proposals related in any way to oil, gas, NGL and/or refined

    product movement and handling)

    - Manager, Process and Control System Department

    (for Instrumentation & Control Systems)

    - General Manager, Industrial Security

    - Vice President, Petroleum Engineering and Development

    (for production-related projects)

    - Vice President, Engineering Services

    - Vice President/Executive Director, Proponent Organization

    - Vice President, Project Management

    6.1.2 Unresolved Items

    If unresolved items exist that would preclude obtaining approvals as

    described in section 6.1.1, SAPMT shall refer any unresolved item(s)

    through appropriate channels of authority until resolution is obtained.

    The Project Proposal minutes shall show the estimated cost and schedule

    effects of any changes from the DBSP/Project Proposal as originally

    prepared.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 32 of 48

    6.1.3 Obtaining Changes to an Approved Project Proposal

    For a project with an approved Project Proposal which has not yet

    received Expenditure Request (ER) approval, scope changes shall be as

    follows:

    SAPMT will document and estimate all scope changes approved by FPD and submit the revised ER estimate to PS&CD as an addendum

    to the approved Project Proposal

    The proposed change in the meeting minutes or an addendum shall include justification and the cost/schedule impact

    The required minimal approval authority for the proposed change is Project Manager level

    SAPMT shall distribute the approved changes to PS&CD and all those that received the original Project Proposal

    6.2 Project Proposal Waiver

    6.2.1 Request

    For selected projects, Project Management may request to waive the

    requirement for a Project Proposal / Front End Engineering Design

    (FEED) and proceed directly with detailed design using preliminary

    engineering funds. This request will permit SAPMT to use TC-68 funds

    to carry out detailed design, perform selected project proposal

    requirements and to prepare an ER quality estimate for funding approval.

    Project Proposal waiver does not exempt ER Estimate and any other

    Value Practices requirements.

    6.2.2 Approval

    The following steps are required to obtain a waiver of project proposal

    and proceed with detailed design:

    SAPMT Department Manager shall prepare a formal letter requesting to carry out detailed design during Project Proposal. The letter shall

    be addressed to Vice President, Project Management and Vice

    President Proponent. The letter should state the present situation,

    scope of work, justification for the waiver and identify what project

    proposal requirements, if any that will be performed during detailed

    design, i.e., value engineering, CII concepts, etc.

    SAPMT shall obtain Vice Presidents, Project Management and Proponent approval for this request.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 33 of 48

    On receiving approval, SAPMT shall prepare an Engineering Work Order Authorization for Project Proposal Preparation (Form 6891-

    ENG) to request approval of TC-68 funds to carry out detailed

    engineering and contract preparation based on GI-0202.451,

    (Engineering Work Order Authorization for Preliminary Engineering

    Preparation).

    Approval is accomplished on obtaining the signature on Form 6891-ENG.

    7 Contract Bid Package

    The Contract Bid Package will be developed in close coordination with the Contracting

    Department. Refer to Exhibit III, Contract Development Checklist, for key activities in

    developing Contract Bid Package.

    A complete Contract Bid Package shall be prepared in accordance with Contracting

    Manual and typically contain the following:

    Invitation for Bid documents

    Technical Proposal documents

    Commercial Proposal documents

    As part of Commercial Proposal requirements, Bidders shall be required to submit a Bid Quantification Summary as shown on Exhibit V for bid analysis purposes.

    Copies of the final Bid Quantification Summary from the awarded Contractor will

    be provided to PS&CD

    Fully developed and approved Contract documents which include Schedules A through H, and Q

    Issue for Bid package (normally prepared by Engineering Contractor) which includes,

    but is not limited to, drawings, specifications, applicable reports, and other relevant

    documents necessary to define the project requirements and clearly describes the

    contract scope of work. SAPMT should take into consideration the current project

    execution plan and responsibilities of all contractual parties when revising the Project

    Proposal package to Issue for Bid Package.

    The following Sections in the Project Proposal should be reviewed carefully to

    determine if they are applicable for inclusion in the bid package. If they are to be

    included, SAPMT shall modify as required to ensure that Contractors scope of work is clearly defined in the Issue for Bid Package:

    Project Schedule

    Training requirements

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 34 of 48

    Land Permits

    Operating Variables (as required by OSPAS)

    Strategy for projects compliance with quality requirements

    Project Risk Assessment

    Temporary construction and communications

    8 Exhibits

    The intent of the checklists is to facilitate the review and ensure all key requirements

    are considered, but not to cover all detailed requirements as stated in this procedure.

    8.1 Project Proposal Checklist

    8.2 ER Estimate Package Checklist

    8.3 Contract Development Checklist

    8.4 Sample of Benchmarking

    8.5 Bid Quantification Summary

    Revision Summary

    28 June 2000 Major revision. 29 January 2003 Editorial revisions. 15 August 2006 Major revision. 20 September 2006 Editorial revision to paragraph 3.7. 18 January 2009 Editorial revisions.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 35 of 48

    EXHIBITS

    TABLE OF CONTENTS

    EXHIBIT I PROJECT PROPOSAL CHECKLIST EXHIBIT II ER ESTIMATE PACKAGE CHECKLIST EXHIBIT III CONTRACT DEVELOPMENT CHECKLIST EXHIBIT IV BENCHMARKING DATA SHEET EXHIBIT V BID QUANTIFICATION SUMMARY SHEET

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 36 of 48

    EXHIBIT I PROJECT PROPOSAL CHECKLIST

    Item Ref.

    Section Description Included

    1 3.2.2 Project Proposal documents as described in Section 3.2.2.

    Obtain necessary land use permit

    Obtain proponent approved permits for construction site area

    Complete piping tie-in and hot tap plan

    Complete electrical and control system tie-in plan

    Prepare site investigation report

    2 3.2.4 Temporary and Permanent Project Communication Requirements

    3 3.2.5 Comply with Safety and Security Directive (SSD)

    4 3.2.6 Perform of PHA or HAZOP Study

    5 3.2.6 Perform of Building Risk Assessment

    6 3.2.7 Perform of Environmental Impact Assessment

    7 3.2.8 Apply Waivers from SA Engineering Standards and Material

    System Specification

    8 3.2.9 Include a list of drawings and drawings define project scope

    9 3.2.10 Prepare Project Quality Plan as per GI-0400.001 including

    Schedule Q Att. VI

    10 3.3.1 Identify project major material and equipment to be reviewed by

    Inspection Dept.

    11 3.3.2 Develop a Material Source List of major material and equipment

    12 3.3.3 Develop a Surplus Inventory and Excess material Listing

    13 3.3.4 Obtain a list of approved locally manufactured products and source

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 37 of 48

    Item Ref.

    Section Description Included

    14 3.3.5 Develop a list of critical plant equipment spares

    15 3.3.6 Identify required start-up spares with Proponent with concurrence

    of MS

    16 3.4.1 Prepare Level III Project Summary Schedule

    17 3.4.2 Prepare ER Estimate Package ( See Exhibit II - ER Estimate

    Package Checklist)

    18 3.7 Review Project Training Impact Assessment (SAEP-140) and

    identify required implementation

    19 4.1 Perform Value Engineering Study

    20 4.2.1 Provide project data for Internal Benchmarking

    21 4.2.2 External Benchmarking Analysis

    22 4.3 Perform Energy Optimization Study

    23 4.4 Perform Value Practices

    1. Constructability Study

    2. Project Definition Rating Index (PDRI)

    3. Lesson Learned

    4. Project Execution Planning Workshop

    5. Schedule Optimization

    6. Planning for Startup

    7. Scope Control and Change Management

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 38 of 48

    EXHIBIT II ER ESTIMATE PACKAGE CHECKLIST

    Following are minimum documents required to accompany the ER Estimate Request

    to PS&CD:

    Item Description Included

    1 100% Project Proposal package ( Project Proposal must be approved prior to

    issuance of 56D)

    2 Approved technical review meeting minutes

    3 Project Scope summary including new as well as demolition of existing

    facilities.

    4 Internal/External Benchmarking data

    5 Piping and Instrument Diagrams (P&IDs)

    6 Plot plan showing major facilities/buildings

    7 Proposed Piping lay-out and routing

    8 Electrical scope with one-line diagrams, MTO quantities for Transformers,

    Switchgear, etc,

    9 Field Instrument specifications and Data Sheets

    10 Control system (DCS) scope with I/O counts, Block Flow Diagrams and Vendor

    Quotations

    11 Communications System scope including, MTO and quotations

    12 Fire Protection, Safety and Security requirements

    13 Building/Equipment data sheets

    14 Material specifications including Materials Diagram.

    15 DC Surplus, etc,

    16 Identify Start-Up and Capital Spares

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 39 of 48

    Item Description Included

    17 Catalyst, Chemicals & Licensor Fee costs.

    18 HAZOP Review report if applicable.

    19 Site survey and soil data report

    20 List of Deviations from DBSP with cost/schedule impact

    21 Copy of Approved Waivers

    22 SAPMT/PMC, Insp., CMT & other related costs

    23 Exploratory Trenching

    24 Environmental Assessment (Contamination)

    25 Approved Project Schedule

    26 Approved Project Execution Plan

    27 Contracting and Material Procurements Plans. Identify customs duties.

    28 Detail Engineering Equivalent A size Drawings count and man hours

    29 Detail Design Location i.e., (IK or OOK)

    30 Draft ER brief and BISI from FPD

    31 Facility Location and Camp Requirements

    32 Identify Commissioning and As-Built Requirements

    33 Quality Material take-off (MTO)

    34 Process Equipment list, sizes, capacities & specifications.

    35 Recent (valid for 3 months) quotations for major equipment & material

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 40 of 48

    EXHIBIT III CONTRACT DEVELOPMENT CHECKLIST

    Following are the list of key activities for developing the contract package.

    Item Description Included

    Contracting Strategy

    1

    Develop and Approve Contracting Strategy Required as part of the Abbreviate PEP for all projects (SAEP-12). Strategy is to be updated if there are changed

    during the progress of the project.

    2

    Enter and maintain data on all contract action covered by the Contracting

    Strategy in to the PMIS Contracting Action Development and Administration

    (CADA) module.

    Pro Forma Contract & Specific Instructions to Bidders (SIB)

    3 Complete preliminary Evaluation Plan so appropriate technical and commercial

    questions are included in the SIB.

    4 Secure approvals for all singe source procurement and included appropriate

    language in Schedule H.

    5 Complete Schedule Q language in accordance with approved Quality Plan (GI 400.001) and review proposed language with Inspection as needed.

    6 Include language relating to approved training requirements, if any

    (SAEP-140).

    7 Review any language related to contractor-supplied LAN and PC equipment

    with the appropriated IT office(s).

    8 Include requirements for bidder price breakdowns as part of the Commercial

    Proposals and quantity lists as part of the Technical Proposals.

    Hypothetical Quantities and Bid Conditioners

    9 Prepare hypothetical quantities to be used to evaluate rates proposed by the

    bidders (e.g., change order rates).

    10 Prepare, in conjunction with other members of the Bid Review Team, data to be

    used for allowed bid conditioner (e.g., different PMT cost for various locations).

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 41 of 48

    Item Description Included

    Review of Contract and Contract Supplement as Part of the Bid Review Team

    11

    Ensure the Contract is structured correctly for SAP SRV releases (for lump

    sum, three items lump sum price, change orders, and other expenditures; and use of VAL with the amount in the quantity column).

    12

    Ensure that that AEL includes reasonable amounts for all applicable Other Expenditures (e.g., incidental services, Saudi manufacturer equalization, stand-by time, reimbursable start-up and commissioning assistance, variations from

    target quantities, etc.).

    13 Ensure the Contract Supplement includes an appropriate Change Order limit

    (percent).

    14 After award of the contract, provide copies of the bidders price breakdowns and quantity lists to PS&CD.

    Note: For a project using an LSTK contracting strategy, these actions are required during or just after the Project

    Proposal period. For other strategies (e.g., GES + LSPB) some of the activities take place at later stages of

    the project.

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 42 of 48

    EXHIBIT IV BENCHMARKING DATA SHEET for

    CRUDE PRODUCTION FACILITY (GOSP)

    BUDGET ITEM (BI) : ERA :

    JOB ORDER (JO) : ERC :

    DESCRIPTION :

    AREA NAME PARAMETER UOM QUANTITY COST UNIT COST

    INLET FACILITY

    QUANTITY OF SCRAPER TRAPS EACH $ $

    QUANTITY & SIZE (INCHES) OF TRAP A EACH

    QUANTITY & SIZE (INCHES) OF TRAP B EACH

    QUANTITY & SIZE (INCHES) OF TRAP C EACH

    TOTAL INSTALLED COST (INLET FACILITY) DOLLARS $ $

    PRODUCTION TRAP

    UNIT CAPACITY MBD $ $

    NUMBER OF HIGH PRESSURE TRAPS EACH

    NUMBER OF INTERMEDIATE PRESSURE TRAPS EACH

    NUMBER OF LOW PRESSURE TRAPS EACH

    WATER CUT % VOL

    GAS OIL RATIO

    CRUDE TYPE (AL/AM/AXL/ASL) or API

    TOTAL INSTALLED COST (PRODUCTION TRAP) DOLLARS $ $

    GAS GATHERING

    UNIT CAPACITY MMSCFD $ $

    HP COMPRESSORS QUANTITY EACH

    HP COMP DRIVER TYPE (MOTOR/CGT) EACH

    IP COMPRESSORS QUANTITY EACH

    IP COMP DRIVER TYPE (MOTOR/CGT) EACH

    LP COMPRESSORS QUANTITY EACH

    LP COMP DRIVER TYPE (MOTOR/CGT) EACH

    HP COMPRESSORS TOTAL HP HP

    IP COMPRESSORS TOTAL HP HP

    LP COMPRESSORS TOTAL HP HP

    TOTAL INSTALLED COST (GAS GATHERING) DOLLARS $ $

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 43 of 48

    WET CRUDE HANDLING &

    WOSEP

    NUMBER DESALTING STAGES EACH

    UNIT CAPACITY MBD $ $

    TOTAL INSTALLED COST (WET CRUDE HANDLING & WOSEP) DOLLARS $ $

    CONDENSATE STABILIZATION

    UNIT CAPACITY MBD $ $

    TOTAL INSTALLED COST (CONDENSATE STABILIZATION) DOLLARS $ $

    CRUDE STABILIZATION UNIT CAPACITY MBD $ $

    WATER INJECTION FACILITY

    UNIT CAPACITY MBD $ $

    QUANTITY OF PUMPS EACH

    PUMPS TOTAL HP HP

    PUMP DRIVER TYPE (MOTOR/CGT) EACH

    TOTAL INSTALLED COST (WATER INJECTION FACILITY) DOLLARS $ $

    COGENERATION FACILITY ISO RATING MW $ $

    PIPERACK & PIPING

    TONNAGE STEEL (PIPERACK) TONS $ $

    TONNAGE PIPE TONS $ $

    WIDTH OF PIPERACK LM

    LENGTH OF PIPERACK LM

    HEIGHT PIPERACK LM

    LEVELS OF PIPERACK EACH

    TOTAL LENGTH OF ALL PIPES LM

    TOTAL INSTALLED COST (PIPERACK) DOLLARS $ $

    TOTAL INSTALLED COST (PIPING) DOLLARS $ $

    SUPPORT INFRASTRUCTURE

    SITE PREPARATION SM $ $

    CONCRETE CM $ $

    STRUCTURAL STEEL TONS $ $

    FENCING LM $ $

    CONTROL BUILDINGS (ALL BLDGS) SM $ $

    PIBS (ALL BLDGS) SM $ $

    OTHER TYPES OF BUILDING SM $ $

    SUBSTATION SM $ $

    TOTAL INSTALLED COST (SUPPORT BLDGS ONLY) DOLLARS $ $

    TOTAL INSTALLED COST (INFRASTRUCTURE) DOLLARS $ $

  • Document Responsibility: Project Support and Controls Dept. SAEP-14

    Issue Date: 18 January 2009

    Next Planned Update: 15 August 2011 Project Proposal

    Page 44 of 48

    OFFSITES & UTILITIES

    BOILER QTY EACH $ $

    BOILER CAPACITY LBS/HR

    BOILER PRESSURE PSIG

    COOLING TOWER CAPACITY GPM $ $

    AIR COMPRESSOR QTY EACH $ $

    A