18
Sadia Garments Ltd. 390/3/C,D IT Road, West Rampura, Bangladesh (23.764006N, 90.42066E) 8 April 2014 1

Sadia Garments Ltd. - accord.fairfactories.orgaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/7613.pdf · Sadia Garments Ltd. 390/3/C,D IT Road, West Rampura, Bangladesh (23.764006N,

Embed Size (px)

Citation preview

Sadia Garments Ltd.390/3/C,D IT Road, West Rampura, Bangladesh

(23.764006N, 90.42066E)

8 April 2014

1

2

Observations

3

Highly stressed columns in Building 2

4

Highly stressed columns in Building 2

Outline calculations indicate that working stress is high in columns in Building 2.

Red brick aggregate observed in columns in Building 2.

A Detailed Engineering Assessment of the building is required (see attached Scope) . Engineer is to perform detailed calculations based on as constructed dimensions and concrete tests to prove column size and (if required).

Load management plan to be implemented (see Observation 2).

Red brick aggregate observed

5

Concentrated areas of high loading

6

Concentrated areas of high loading

Concentrated areas of high loading observed throughout buildings. No loading management system in place.

2 number 10000 litre water tanks on roof of Building 1. Water tanks also observed on roof of Buildings 2 and 3.

Building 1 water tanks

Building 2 roof storage

Building 2

7

Cracking in structural elements

8

Cracking in structural elements

Structural cracking observed in the shear zone on multiple beams at upper levels of Building 2.

Cracking in beams in Building 1 and Building 3 also observed.

Evidence of repair to beams at crack locations

9

Complete as-built drawings for Building 3

10

No structural design information or drawings was available for survey team review for Building 3.Column sizes observed in Building 1 and 2 do not match structural drawings provided for review.

Complete as-built drawings for Building 3

Building 3 permit drawing

11

Non-engineered structures

12

Escape stairs to Building 1 and Building 2 appear to be non-engineered.

Non-engineered structures

Lightweight tin roof susceptible to wind uplift. Tin shed appears to be non-engineered with no apparent lateral stability system or bracing.

Shed at roof level of Building 2

13

Priority Actions

14

Problems Observed

1. Highly stressed columns in Building 22. Concentrated areas of high loading3. Cracking in structural elements4. Structural drawings for Building 3 to be completed5. Non-engineered structures

15

Item No. Observation Recommended Action Plan Recommended Timeline

1Highly stressed columns in

Building 2

Factory Engineer to review design, loads and columns stresses in all columns. Limit loads to a maximum iof 2kPa on all floors

Immediate - Now

2Highly stressed columns in

Building 2

Verify insitu concrete stresses either by 100mm diameter cores or existing cylinder strength data for cores from minimum 4 columns.

Immediate - Now

3Highly stressed columns in

Building 2A Detail Engineering Assessment (DEA) of Building 2 to be commenced, see attached Scope.

Immediate - Now

4Highly stressed columns in

Building 2DEA to be completed. 6-weeks

5Highly stressed columns in

Building 2

Factory Engineer to design and detail strengthening/remedial works for columns, as required by DEA.

6-weeks

6Highly stressed columns in

Building 2Strengthening/remedial works to columns to be implemented.

6-weeks

7Highly stressed columns in

Building 2Strengthening/remedial works to columns to be completed.

6-months

16

This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment.The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team.

We expect that the following will be carried out:1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions , levels, foundations and framing on Plan,

Section and Elevational drawings .2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building

against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made.

3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed.4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied.5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated

loads.6. The Engineering team will prepare an assessment report that covers the following:

• As-Built drawings including• Plans at each level calling up and dimensioning all structural components • Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the

structure• Highlight any variation between As-built compared to the designed structure• Results of testing for strength and materials• Results of geotechnical assessment and testing/investigation• Details of loading, inputs and results of computer modelling• Commentary on adequacy/inadequacy of elements of the structure• Schedule of any required retrofitting required for safety or performance of Structure

Any proposals for Retrofitting to follow guidance developed in the Tripartite Document

Detail Engineering Assessment

17

Item No. Observation Recommended Action Plan Recommended Timeline

8Concentrated areas of high

loading

All uses and storage on suspended floors to be reduced to maximum of loading of 2kN/m2 (200kg/m2) until DEA is completed and load plans are developed by Factory Engineer.

Immediate - Now

9Concentrated areas of high

loading

Factory Engineer to develop a loading plan for all floor plates within Building 1, Building 2 and Building 3 accounting for usage, floor build ups, solid partition walls and areas of concentrated loading.

6-weeks

10Concentrated areas of high

loadingFactory management to implement load plans. 6-weeks

11Concentrated areas of high

loadingContinue to implement load plans. 6-months

12Cracking in structural

elements

Factory Engineer to investigate structural cracking in slabs, beams and columns (opening up of plaster and inspect) in all factory buildings.

6-weeks

13Cracking in structural

elementsRecord and monitor location, size and width of all structural cracking.

6-weeks

14Cracking in structural

elementsFactory Engineer to develop strengthening/remedial details as required. Refer to Note 1.

6-weeks

15Cracking in structural

elementsContinue to monitor structural cracking throughout factory complex.

6-months

18

Item No. Observation Recommended Action Plan Recommended Timeline

16Structural drawings for

Building 3 to be completedFactory Engineer to complete as-built drawings for Building 3.

6-months

17Structural drawings for

Building 3 to be completedFactory Engineer to update as-built drawings for Building 1 and Building 2 based on column sizes observed on site.

6-months

18Structural drawings for

Building 3 to be completed

As-built drawings for Building 1, Building 2 and Building 3 to be updated, as required, following future modifications and strengthening works to structural elements.

6-months

19 Non-engineered structures

Factory Engineer to review the adequacy of non-engineered sheds and escape stairs within the complex. Particular attention to be paid to i) lateral stability and ii) connection details.

6-months