901 & 601
Specifications
Major Changes
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
2/28
901 Specifications
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
3/28
Average
Compressive
Strength, psi
(MPa)
at 28 days
Grade of
Coarse
Aggregate1
Surface
Resistivity2
(k-cm)
Maximum
Water/Cementitious
ratio, lb/lb
(kg/kg)
Air Content
(Percent by
volume)3
Slump Range 4, inches (mm)
Non-
Vibrated5Vibrated
Slip Form
Paving 6
Structural Class 7
AP1
P2
P3
S
MASS
4,500 (31.0)6,000 (41.4)8
8,500 (58.6) 8
10,000 (68.9)8
4,500 (27.6)
4,500 (31.0)
57, 67, 899
, B,D57, 67, 899, B,D
57, 67, 899, B,D
57, 67, 899, B,D
B, D
B, D
2727
27
27
27
27
0.450.44
0.40
0.40
0.53
0.53
2 - 72 - 7
2 - 7
2 - 7
2 - 7
2 - 7
2-5 (50-125)N/A
N/A
N/A
6-8 (150-200)
N/A
2-4 (50-100)5
2-6(50-150)10
2-6(50-150)10
2-6(50-150)10
N/A
2-4 (50-100)5
N/AN/A
N/A
N/A
N/A
N/A
Minor Structure Class 7
MR
3,000 (20.7)1,800 (12.4)
57, 67, 899
, B,D57, 67, B, D
N/A
N/A
0.560.70
2 - 72 - 7
2-5 (50-125)2-5 (50-125)
2-4 (50-100)5
2-4 (50-100)5
1-2.5 (25-65)N/A
Pavement Type 7
B
D
E
4,000 (27.6)4
4,000 (27.6)4
4,000 (27.6)4
B, D
B, D
57, 67, 899, B,D
N/A
N/A
N/A
0.53
0.53
0.40
27
27
2 - 7
N/A
N/A
N/A
2-4 (50-100)
2-4 (50-100)
2-4 (50-100)
1-2.5 (25-65)
1-2.5 (25-65)
1-2.5 (25-65)
Table 901-3: Master Proportion Table
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
4/28
Percent Passing
US SieveMetric
Sieve
Size 57M Size 89M Size 67
2 1/2 inch
2 inch
1 1/2 inch
1 inch
3/4 inch
1/2 inch
3/8 inch
No.4
No.8
No. 16
No. 200
63 mm
50 mm
37.5 mm
25.0 mm
19.0 mm
12.5 mm
9.5 mm
4.75 mm
2.36 mm
1.18 mm
75 m
---
---
100
90-1001
---
25-60
---
0-10
0-5
---
0-1
---
---
---
---
100
90-100
---
15-60
0-302
0-5
0-1
---
---
---
100
90-100
---
20-55
0-10
0-5
---
0-1
Table 1003-18
Gradation for Portland Cement Concrete, Uncrushed Aggregates
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
5/28
New Definitions & Requirements
Fresh concrete is defined as concrete in
a plastic state that has not achieved initial
set.
Fine aggregate must have fineness
Moduli (FM) between 2.20 and 3.00
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
6/28
Cementitious Material
Substitution The maximum substitution rate for binary mixtures
is 30 percent fly ash or 50 percent GGBFS.
The maximum substitution rate for ternary mixturescontaining Type I, II or III portland cement is 70
percent of cement. When using Type IP or ISportland cement, the maximum substitution rate forternary mixtures is 40 percent. Ternarycombinations using both class C and F fly ash areallowable. When using fly ash ternary mixtures,replace portland cement with class C and class F flyash in equal amounts. When using combinations ofGGBFS and fly ash, the amount of GGBFS must beequal to or greater than the amount of fly ash.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
7/28
Cementitious Material
Substitution
For pavement types of concrete (Types Band D), the maximum substitution rate forternary mixtures is limited to 50 percent of
cement and for binary mixtures is 30percent fly ash or 50 percent GGBFS.
The use of Type III portland cement outsideof the specified allowances for precast,
prestress, and specified HES pavementsrequires the approval of the ChiefConstruction Engineer.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
8/28
Cold Weather Limitations
Do not place concrete when the internal
temperature of the concrete is below
45F (7C) nor on frozen subgrade or into
forms that are below 32F (0C).
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
9/28
Cold Weather Limitations
PC Mixes: Discontinue concreting operationswhen a descending air temperature at thejobsite, in the shade, and away from artificialheat, reaches 35F (2C) or NOAA forecasts the
temperature to be less than 32F (0C) within the24-hour period following placement. Do notresume PC concreting operations until anascending air temperature at the jobsite, in theshade, and away from artificial heat, reaches
32F (0C); provided the high temperatureforecasted by NOAA is above 35F (2C) andremains above 32F (0C) for a minimum of 24hours.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
10/28
Cold Weather Limitations
Binary Mixes: Discontinue concretingoperations when a descending air temperatureat the jobsite, in the shade, and away fromartificial heat, reaches 40F (4C) or NOAA
forecasts the temperature to be less than 35F(2C) within the 36-hour period followingplacement. Do not resume concreting operationsuntil an ascending air temperature at the jobsite,in the shade, and away from artificial heat,
reaches 40F (4C); provided the hightemperature forecasted by NOAA is above 45F(7C) and remains above 40F (4C) for aminimum of 36 hours.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
11/28
Cold Weather Limitations
Ternary Mixes: Discontinue concretingoperations when a descending air temperatureat the jobsite, in the shade, and away fromartificial heat, reaches 45F (7C) or NOAA
forecasts the temperature to be less than 40F(4C) within the 48-hour period followingplacement. Do not resume concreting operationsuntil an ascending air temperature at the jobsite,in the shade, and away from artificial heat,
reaches 45F (7C); provided the hightemperature forecasted by NOAA is above 50F(10C) and remains above 45F (7C) for aminimum of 48 hours.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
12/28
Hot Weather Limitations
Hot weather limitations commence whenthe internal temperature of the concreteduring placement, exceeds 85 F (29C).
Regardless of any hot weatherprecautions taken, reject all concreteattaining an internal temperature inexcess of 99 F (37C) during placement.
Concrete placements within these hotweather limitations shall meet thefollowing requirements:
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
13/28
Hot Weather Limitations
1. Maintain a minimum internal concretetemperature of 94F (34C) throughout the trialbatching process.
2. After initial mixing, hold the trial batch in the
mixer for 90 minutes. During this period, turn thedrum intermittently for 30 seconds every fiveminutes. In between the intermittent turning ofthe drum, cover the drum opening with animpermeable cover to prevent moisture loss and
to maintain heat. At the end of the 90-minuteperiod, remix the trial batch a minimum of oneminute and then test for slump and air content.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
14/28
Hot Weather Limitations
3. After completion of 90-minute mixing period,ensure that the trial batch has the desiredworkability, with slump, and air content withinthe specified range as shown in Table 901-3.
Allow the addition of water if the slump is belowthe target range but do not exceed the maximumwater-to-cementitious material ratio. Remix aminimum of two minutes after addition of second
water. Furthermore, ensure that concretetemperature is not less than 94F (34C) at anytime during the trial batch testing.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
15/28
MASS CONCRETE
Mass concrete is defined as a structural
concrete placement having a least
dimension of 48 inches or greater, or if
designated on the plans or in the project
specifications as being mass concrete.
Drilled shafts are exempt from mass
concrete requirements.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
16/28
MASS CONCRETE
Use Type II portland cement. Replace portlandcement with fly ash at 20 percent to 50 percentby weight or replace with slag cement at 50percent to 70 percent by weight or a ternary mix
meeting specification requirements. Certify thatthe cementitious combination generates a heatof hydration of not more than 70 calories/gram(290 kJ/kg) at 7 days as determined by ASTMC186.
Use Type B or D aggregate gradation for massconcrete. See 1003.08.3
Do not use accelerating admixtures in massconcrete.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
17/28
MASS CONCRETE
Produce a structure free from thermal
cracks. Place mass concrete continuously
to eliminate cold joints.
Control differential temperatures by
appropriate use of insulated forms,
curing blankets, or other acceptable
methods.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
18/28
MASS CONCRETE
A maximum temperature during curing of160 F (70 C) and a maximum differentialtemperature of 35 F (20 C) is allowed.
Provide temperature-monitoring devices torecord temperature development betweenthe interior and the exterior of the elementat points acceptable to the engineer.
Monitor a minimum of two independent setsof interior and exterior points for eachelement to provide redundancy.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
19/28
601 Specifications
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
20/28
601 Changes: CONCRETE PAVING
Mechanical roller or truss-type screeds are
allowed, if approved by the engineer, for
projects with: concrete pavement lane
lengths of 1500 feet (450 m) or less,continuous paving lengths less than 600 feet
(180 m), pavement gaps, intersections, or
when side clearance is restricted.
Do not operate vibrators longer than 5
seconds in one location.
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
21/28
601 Changes: SURFACE
TOLERANCE (IRI)
Equipment (TR 644)
Quality Control (ProVal 25 Sliding
Baseline)
Correction of Deficient Areas (1/4 in 10)
Acceptance
Exclusions Required Corrective Action (Must Grinds)
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
22/28
Percent of Contract Unit Price102%2 100% 98%
50% or Remove
and Replace3
Category I:
Design Speed 60
mph
IRI in/mi
(mm/km)
65
(1026)
75
(1200)
76-84
(1201-1340)
85
(1341)
Category II:
Design Speed 45
mph and < 60 mph
IRI in/mi
(mm/km)
75
(1184)
85
(1356)86-94
(1357-1499)
95
(1500)
Category III:
Design Speed < 45
mph
IRI in/mi
(mm/km) N/A
115
(1829)
116-129
(1830-2049)
130
(2050)
1Applies to each travel lane for the entire projects length2 Incentive Pay Requirements:
Must equal or be less than the average IRI indicated for bonus payment
Grinding is not allowed to achieve incentive payment but requirements for 601.03.11.3.2
must be met3At the option of the Chief Engineer
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
23/28
Any 25-foot Sliding Baseline PCCP: Longitudinal Direction
Category IIRI in/mi
(mm/km)
170
(2685)
Category IIIRI in/mi
(mm/km)
190
(3000)
Category IIIIRI in/mi
(mm/km)
210
(3315)
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
24/28
CP-01 Revisions
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
25/28
CP-01 Revisions
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
26/28
CP-01 Revisions
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
27/28
CP-01 Revisions
7/29/2019 S45_Part 6, 9 Review of Concrete Pavement Specification Changes_LTC2013
28/28