Upload
nguyenquynh
View
214
Download
0
Embed Size (px)
Citation preview
S.
No Conditions of Environment Clearance
Status Status of Compliance
1 Kindly refer to your letter dated 28th April,
2011 along with project documents
including Form I. Terms of References,
Pre-feasibility Report, EIA/EMP Report,
public hearing report and subsequent
communications vide your letters dated
25th June, 2011, 30th June, 2011 and 2nd
August, 2012 on the above mentioned
subject.
Complied Noted.
2 The Ministry of Environment and Forests
has examined the application. It is noted
that the proposal is for expansion of
Specialty Chemicals Manufacturing Unit at
Plot No.166/1-3,171/1,172,167,168,
Village Padana. Gandhidham, District
Kutch. Gujarat by M/s Kutch Chemicals.
Total cost of the project is Rs.117.6 Crore.
Total plant area is 75,000 m2. Following
products will be manufactured:
Complied Proposal is for expansion of Specialty
Chemicals Manufacturing Unit at Plot
No.166/1-3.171/1,172,167,168, Village
Padana. Gandhidham, District Kutch,
Gujarat by M/s Kutch Chemicals.
Total cost of the project is INR 117.6
Crore including the cost of existing
plant. Total plant area is 75,000 m2.
At present, we are not manufacturing all
EC Products. We are only manufacturing
Acetanilide, Sulfamic Acid, Di methyl
Sulphate, Diethyl Sulphate, Di calcium
Phosphate and Power plant from
Proposed EC product list.
S
.
N
.
Products
Exist
ing
(MT
PM)
Additi
onal
(MTP
M)
Total
(MTP
M)
1
Nitro Derivates
of hydrocarbon
such as Nitro -
chloro benezene,
Nitro toluene.
Nitro Cumene,
nitro Xylene,
nitro benzene
2400 - 2400
2
Amino
Hydrocarbon
such as Chloro
aniline, toludine,
Cumidine,
Xylidine, aniline
2000 - 2000
3
Methoxylation of
nitro chloro
compound &
hydrolysis such
as Ortho
anicidine, para
100 - 100
S.
No Conditions of Environment Clearance
Status Status of Compliance
anicidine
4
Amonolysis of
nitro chloro
compound &
hydrolysis such
as Ortho nitro
aniline, Para
nitro aniline
100 - 100
5 Mono Chloro
Benzene 1000 - 1000
6 Di Chloro
Benzene 500 - 500
7 Chlorinated
paraffin wax 550 - 550
8 Acetanilide 1000 3000 4000
9 Vinyl Sulphone 500 4000 4500
1
0
Sulphonation of
PNT, ONT, VS,
Tobias, etc.
0 1500 1500
1
1
Benzene
Sulphonyl
Chloride
0 1500 1500
1
2 DASDA 0 1000 1000
1
3 V.S. Condense 0 1000 1000
1
4
Dimethyl Sulfate
(DMS) 100 3000 3100
1
5
Dimethyl Aniline
(DMA) 0 1500 1500
1
6
Diethyl Sulfate
(DES) 0 1500 1500
1
7 Sulfamic Acid 0 1000 1000
1
8
Power Plant
(Coal)
2.5
MW
(FO)
10
MW
(Coal)
12.5
MW
(FO &
Coal)
1
9
Sulphuric Acid
(98%) 7500 15000
2250
0
2
0
Oleum (23% &
65%) 0 3000 3000
S.
No Conditions of Environment Clearance
Status Status of Compliance
2
1
Liquid SO3 (70-
90%) 0 7500 7500
2
2
Chloro Sulphonic
Acid 1200 5000 6200
2
3 Thionyl Chlroide 0 5000 5000
2
4
Sodium
Bisulphite (SBS) 0 3000 3000
2
5 Calcium Chloride 0 4000 4000
2
6
Dicalcium
Phosphate (DCP) 0 1500 1500
2
7
Sulphur
Monochloride 0 200 200
2
8
Sulphuryl
Chloride 0 200 200
2
9
Alumunium
Sulphase (ALIM) 0 1000 1000
3 Multi-cyclone followed by bag filter will be
provided to the coal fired boiler.
Adequate scrubbing system will be
provided to the process vents to control
process emissions viz HCl, SO2 and NH3.
Total fresh water requirement from
Gujarat Water Infrastructure Limited will
be 1,520 m3/day after expansion.
Industrial effluent generation will be 336
m3/day after expansion.
Complied
APCM Provided in Power Plant:
S.
N
As
per
EC
Provided
at Site Details
1
Multi-
Cyclon
e +
Bag
Filter
ESP
Higher
efficient
ESP is
provided
having 3
fields and
>99%
efficiency.
Though expansion has not taken place,
existing plants is having scrubbing
system for HCl, SO2 & NH3.
Fresh Water Requirement:
S.
No
.
Fresh Water Requirement in
KLD
Industri
al
Domest
ic Total
As Per EC Received
1 1,470 50 1,520
* Since, no major expansion has taken
S.
No Conditions of Environment Clearance
Status Status of Compliance
Process effluent from vinyl sulphone after
recovery of sodium sulphate will be sent to
incinerator.
High TDS effluent stream will be passed
through stripper followed by Multi effect
evaporator (MEE). Condensate and low
COD/ TDS effluent stream will be treated
in effluent treatment plant (ETP).
Domestic sewage will be treated in
Sewage Treatment Plant STP, Treated
effluent will be recycled/reused within
factory premises.
No effluent will be discharged outside the
premises and 'Zero' effluent discharge
concept will be adopted.
ETP sludge process inorganic, evaporation
salt and incinerator salt will be sent to
treatment storage disposal facilities (TSDF)
for hazardous waste.
Used oil will be sold to registered
recyclers/re-processor.
Fly ash will be sent to brick
manufacturers/cement industry.
place at site till date; water requirement
is much lower than the quantity as
mentioned in EC.
S.
N
o.
Waste Water Generated in
KLD
Industri
al
Domest
ic Total
As Per EC Received
1 300 36 336
* Effluent generation is much lower than
the quantity as mentioned in EC as no
major expansion has taken place.
Effluent from existing Vinyl Sulphone
(VS) after recovery of sodium sulphate
is sent to incinerator. Same will be done,
once the expansion of VS takes place.
High TDS effluent stream is passed
through stripper followed by Multi effect
evaporator (MEE). Condensate and low
COD/ TDS effluent stream is treated in
effluent treatment plant (ETP).
STP is not installed at the site. Domestic
sewage is currently disposed off in
septic tank & soak pit.
No effluent is discharged outside the
premises and 'Zero' effluent discharge
concept is adopted.
ETP sludge process inorganic,
evaporation salt and incinerator salt is
currently being sent to treatment
storage disposal facilities (TSDF) for
hazardous waste. Logbook of ETP &
MEE is being maintained copy of the
same is attached as Annexure-1.
Maximum quantity of used oil is reused
within the plant premises and excess oil
is stored in the drums (Closing stock 0.1
S.
No Conditions of Environment Clearance
Status Status of Compliance
KL) and will be sold to registered
recyclers/re-processor.
Fly ash is sent to brick manufacturers.
4 Public hearing was conducted on 1st
February, 2011.
Complied
.
Public hearing was conducted on 1st
February, 2011. Compliance of all the
points are provided in previous EC
Compliance report (October 2016 to
March 2017)
5 All synthetic organic chemical industries
located outside the notified industrial
estate/area are listed at S.N. 5(f) under
category 'A' and appraised at Central level.
Complied
.
Noted.
6 The proposal was considered by the Expert
Appraisal Committee (lndustry-2) in its 7th,
25th and 2nd meetings held during 15th-
16th January, 2010, 28th- 30th July, 2011
and 29th - 31st October, 2012 respectively.
The Committee recommended the
proposal for environmental clearance.
Complied
.
Noted.
7 Based on the information submitted by the
project proponent, the Ministry of
Environment and Forests hereby accords
environmental clearance to above project
under the provisions of EIA Notification
dated 14th September, 2006, subject to the
compliance of the following Specific and
General Conditions.
Complied Noted.
A Specific Conditions
1 National Emission Standards for Organic
Chemicals Manufacturing Industry issued
by the Ministry vide G.S.R. 608(E) dated
21st July, 2010 and amended time to time
shall be followed by the unit.
Complied Emission standards for organic chemical
manufacturing industries is being
complied.
1) Stack Results:
Stack monitoring results are attached as
Annexure-2.
2) Waste water Analysis Results:
All values in mg/l, except pH, which has
no unit.
Where, S1: Boiler Blow down + Cooling
tower Blow down + Organic Process like
Nitration etc., S2: VS Process Stream,
S3: Condensate Recovery, S4:
Concentrated Stream
NM: Not Measurable, BDL: Below
Detection Limit
S.
No Conditions of Environment Clearance
Status Status of Compliance
Waste Water results are attached as
Annexure-3.
3) Noise Results:
Noise monitoring results for are
attached as Annexure-4.
2 Multi-cyclone followed by bag filter shall be
provided to the coal fired boiler to control
particulate emissions within permissible
limit.
The gaseous emissions shall be dispersed
through stack of adequate height as per
CPCB/GPCB guidelines.
Complied APCM Provided in Power Plant:
S.
N
As
per
EC
Provided
at Site Details
1
Multi-
Cyclon
e +
Bag
Filter
ESP
Higher
efficient
ESP is
provided
having 3
fields and
>99%
efficiency.
Though expansion has not taken place,
existing plants is having scrubbing
system for HCl, SO2 & NH3.
Stack details are calculated as per
formula provided by CPCB for Power
Plant, H=14 (Q)^0.3, where Q = SO2
emisisons (in kg/hr). In our case, 156
TPD Coal having 0.5% sulphur content
is considered for 6.5 MW Power Plant.
S.
No
.
Stack
attache
d to
Stack
Height
Provide
d
Stack
Height
as per
CPCB
1
New
Power
Plant
60 mtrs 48 mtrs
S.
No Conditions of Environment Clearance
Status Status of Compliance
3 Two stage chilled water/caustic scrubber
shall be provided to process vents to
control HCL. Two stage scrubbers with
caustic lye media solution shall be
provided to process vents to control SO₂.
Two stage scrubbers with chilled Water
media shall be provided to process vents
to control NH₃. The scrubbing media shall
be sent to effluent treatment plant (ETP)
for treatment. Efficiency of scrubber shall
be monitored regularly and maintained
properly. At no time, the emission levels
shall go beyond the prescribed standards.
Scrubbers vent shall be provided with on-
line detection and alarm system to indicate
higher than permissible value of controlled
parameters.
Complied Expansion is not taken place for organic
products. For existing plants, chilled
water caustic scrubber to control HCl
emission, where as two stage scrubbers
with caustic lye media solution to control
SO2 and chilled water scrubbing is
provided to control the NH3 emissions.
The scrubbing media is being sent to
Effluent Treatment Plant for further
treatment. Efficiency of above scrubbers
is being monitored regularly and
maintained properly.
Online detection and alarm system will
be installed once expansion for organic
products will take place.
4 Ambient air quality data shall be collected
as per NAAQES standards notified by the
Ministry vide G.S.R. No. 826(E) dated 16th
November, 2009.
The levels of PM, SO2, NOx, VOC, HCl, NH3
and CO shall be monitored in the ambient
air and displayed at a convenient location
near the main gate of the company and at
important public places.
The company shall upload the results of
monitored data on its website and shall
update the same periodically. It shall
simultaneously be sent to the Regional
office of MOEF, the respective Zonal office
of CPCB and Gujarat Pollution Control
Board (GPCB).
Complied
.
The locations of ambient air quality
monitoring stations were decided in
consultation with the GPCB and one
stations is installed in the upwind and
downwind direction as well as where
maximum ground level concentrations
are anticipated. Ambient Air Monitoring
was carried out by Ecosystem Resource
Management Pvt. Ltd,Surat at different
location like Main Gate, Near Sulphur
Storage Area, Near VS Plant & Near
ETP.
It is found that average AAQ meets the
prescribed standards.
Results are monitored and displayed at
Main gate. One copy of result is
attached as per Annexure-5.
Six monthly compliance report having
the monitored data are uploaded on the
company’s website. The same is sent to
the Regional office of MOEF, Bhopal &
GPCB time to time. Uploaded photo of
screen shot of six monthly compliance
S.
No Conditions of Environment Clearance
Status Status of Compliance
report on website is attached as per
Annexure-5A.
5 In plant control measures for checking
fugitive emissions from all the vulnerable
sources shall be provided.
Fugitive emissions shall be controlled by
providing closed storage, closed handling
& conveyance of chemicals/materials,
multi cyclone separator and water
sprinkling system. Dust suppression
system including water sprinkling system
shall be provided at and unloading areas
to control dust emissions.
Fugitive emissions in the work zone
environment, product, raw materials
storage area etc. shall be regularly
monitored.
The emissions shall conform to the limits
stipulated by the GPCB.
Complied
Control measures provided for fugitive
emissions within existing unit is
tabulated below:
S. N.
Parameter
Location
Control Measures
1 SPM
Coal Handling
Area
• Closed conveyor belts are provided for transfer of Coal from Coal yard to Boiler.
• At crusher, water is being spread through sprinklers to avoid dusting.
• Apart from above, dust extraction system at coal crusher, bunkers is provided to avoid dusting.
2 HCl
MCB Plant, CPW Plant & VS Plant
• Water Scrubber are provided.
3 SO
2
Sulphuric Acid
Plant, VS
Plant
• In sulphuric acid plant, online SO2 analyzers are provided.
• Caustic Scrubber are provided.
4 NH
3
Chillers
• Chilled Water Scrubber are provided.
5 Cl2
Thionyl
Chloride, MCB Plant
& Chlori
ne yard
• Online gas leakage detection system and caustic scrubbers are provided.
• Scrubbing system which is being operated manually, is planned to switch over in auto mode.
6 VOC
MCB Plant,
• Online VOC detection system is provided.
Benzene UG
• Condensers are provided on vents.
S.
No Conditions of Environment Clearance
Status Status of Compliance
Tank Farm Area
Similar control measures and measures
as mentioned will be taken as and when
expansion & new plants are established.
Weekly in-house Work place monitoring
is carried out within the plant and
displayed at different locations as shown
in Annexure-6. Apart from that,
monitoring from third party is also
conducted by Third Party, M/s. ECO
Care having MoEF &CC approved
laboratory. Results of the same are also
provided in Annexure-6.
6 For further control of fugitive emissions,
following steps shall be followed :
(a) Closed handling system shall be
provided for chemicals.
(b) Reflux condenser shall be provided
over reactor.
(c) System pf leak detection and repair of
pump/pipeline based on preventive
maintenance.
(d) The acids shall be taken from storage
tanks to reactors through closed pipeline
storage tanks shall be vented through trap
receiver and condenser operated on chilled
water.
(e) Cathodic protection shall be provided
to the underground solvent storage tank.
Complied All the steps are being taken to control
the fugitive emissions in existing plant
and same will be taken as and when
expansion & new plants are established.
Photograph of benzene sensor near
existing benzene tank farm is given in
Annexure-7. Calibration certificate of
Cl2 sensors is provided in Annexure-8.
7 The gaseous emissions from DG set shall
be dispersed through adequate stack
height as per CPCB standards. Acoustic
enclosure shall be provided to the DG sets
to mitigate the noise pollution.
Complied At present no additional DG Sets are
required. Existing DG sets are provided
with acoustic enclosures and stack
height of 12 meters as per the
requirement of CPCB standards.
8 Solvent management shall be carried out
as follows:
(a) Reactor shall be connected to chilled
brine condenser system to condensate
solvent vapors and reduce solvent losses.
(b) Reactor and solvent handling pump
shall have mechanical seals to prevent
Complied During solvent storage and handling in
the existing plant, solvent management
is carried out as follows:
(a) Reactor is connected to chilled brine
condenser system to condensate solvent
vapors.
(b) Reactor and solvent handling pump
S.
No Conditions of Environment Clearance
Status Status of Compliance
leakages.
(c) The condensers shall be provided with
sufficient HTA and residence time so as to
achieve more than 95% solvent recovery.
(d) Solvents shall be stored in a separate
space specified with all safety measures.
(e) Proper earthling shall be provided in all
the electrical equipment wherever solvent
handling is done.
(f) Entire plant shall be flame proof. The
solvent storage tanks shall be provided
with breather valve to prevent losses.
have mechanical seals.
(c) The condensers are provided with
sufficient HTA and residence time.
(d) Solvents area stored in a separate
space specified with all safety measures.
(e) Proper earthling is provided in all the
electrical equipment wherever solvent
handling is done.
(f) Entire plant shall is flame proof. The
solvent storage tanks are provided with
breather valve to prevent losses.
All the similar steps will be carried out
when expansion & new plants are
established.
Photographs of earthing relay provided
at existing solvent storage tank is
provided in Annexure-9.
9 Proper hood along with suction facility and
scrubbing arrangement shall be provided
in the chlorine storage area. Alarm for
chlorine leakage if any in the liquid
chlorine storage area is provided along
with automatic start of the scrubbing
system.
Complied Photograph of hood along with suction
facility and scrubbing arrangement in
the existing chlorine storage area is
shown in Annexure-10. Sensors for
chlorine are provided in chlorine
handling units. On-site emergency plans
are made and followed.
10 Total fresh water requirement from
Gujarat Water Infrastructure Limited
should not exceed 1,520 m3/day and prior
permission shall be obtained· from the
Competent Authority.
Complied Fresh Water Requirement:
S.
No
.
Fresh Water Requirement in
KLD
Industri
al
Domest
ic Total
As Per EC Received
1 1,470 50 1,520
* Since, no major expansion has taken
place at site till date, water requirement
is much lower than the quantity as
mentioned in EC.
11 Industrial effluent shall not exceed 336
m³/day.
Complied Effluent Generation:
S.
No
.
Waste Water Generated in
KLD
Industri
al
Domest
ic Total
S.
No Conditions of Environment Clearance
Status Status of Compliance
As proposed, process effluent from vinyl
sulphone after recovery of sodium
sulphate shall be sent to incinerator.
High TDS effluent stream should be
passed through stripper followed by MEE
Condensate and low COO/Low TDS
effluent stream shall be treated in ETP.
Treated effluent shall be recycled/reused
within factory premises. 'zero' effluent
discharge concept should be adopted and
no effluent will be discharged outside the
premises.
As Per EC Received
1 300 36 336
* Effluent generation is much lower than
the quantity as mentioned in EC as no
major expansion has taken place.
Effluent from existing Vinyl Sulphone
(VS) after recovery of sodium sulphate
is sent to incinerator. Same will be done,
once the expansion of VS takes place.
High TDS effluent stream is passed
through stripper followed by Multi effect
evaporator (MEE). Condensate and low
COD/ TDS effluent stream is treated in
effluent treatment plant (ETP).
No effluent is discharged outside the
premises and 'Zero' effluent discharge
concept is adopted. And same will be
achieved once expansion & new plants
are established. Logsheet of MEE and
ETP are provided in Annexure-1.
12 As proposed, high calorific value waste
shall be sent to cement industries.
ETP sludge, process inorganic, evaporation
salt and incinerator salt should be disposed
off to the TSDF.
The fly ash from boiler shall be sold to
brick manufacturers/cement industry.
Complied Currently no high CV waste is being
generated.
ETP sludge, process inorganic and
incinerator ash disposed off to the TSDF.
The fly ash from boiler is sold to brick
manufacturers.
13 Incinerator along with its pollution control
device shall be designed as per CPCB
guidelines.
Complied Incinerator is designed as per CPCB
guidelines. Design of incinerator is
provided in Annexure-11.
14 The company shall obtain Authorization for
collection, storage and disposal of
hazardous waste under the Hazardous
Waste (Management, Handling and Trans
Boundary Movement) Rules, 2008 and
amended as on date for management of
Hazardous wastes and prior permission
from GPCB shall be obtained for disposal
of solid / hazardous waste in the TSDF.
Complied The company has obtained CC&A as
AWH-65490 Authorization dated
30.09.2014, valid upto 18/07/2020.
Permission from GPCB is also taken for
disposal of solid / hazardous waste in
the TSDF.
S.
No Conditions of Environment Clearance
Status Status of Compliance
Measures shall be taken for firefighting
facilities in case of emergency.
Fire fighting facilities in case of
emergency are in place. Fire Hydrant
system is installed as per norms in the
whole plant.
15 The Company shall strictly comply with the
rules and guidelines under Manufacture
Storage and Import of Hazardous
chemicals (MSIHC) Rules, 1989 as
amended time to time.
All transportation of Hazardous Chemicals
shall be as per the Motor Vehicle Act
(MVA), 1989
Complied SOP is evolved & implemented for
movement of Hazardous chemicals as
enclosed as Annexure-12. All statutory
compliances for movement of Hazardous
chemicals like approval of CCE, RTO,
safe loading quantity, etc. are being
strictly followed.
16 The company shall undertake following
waste minimization measures :-
(a) Metering and control of quantities of
active ingredients to minimize waste
(b) Reuse of by-products from the process
as raw materials or as raw material
substitutes in other processes.
(c) Use of automated filling to minimize
spillage.
(d) Use of Close Feed system into batch
reactors.
(e) Venting equipment through vapour
recovery system.
(f) Use of high pressure hoses for
equipment clearing to reduce wastewater
generation
Complied Following waste minimization measures
have been taken for the existing units:
(a) Metering and control of quantities of
active ingredients to minimize waste
(b) Reuse of by-products from the
process as raw materials or as raw
material substitutes in other processes.
(c) Use of automated filling to minimize
spillage.
(d) Use of Close Feed system into batch
reactors.
(e) Venting equipment through vapour
recovery system.
(f) Use of high pressure hoses for
equipment clearing to reduce
wastewater generation.
All the steps as mentioned will be taken
as and when expansion & new plants
are established.
17 The unit shall make the arrangement for
protection of possible fire hazards during
manufacturing process in material
handling. Fire fighting system shall be as
per the norms.
Complied Fire Hydrant system is installed as per
norms in the whole plant.
Details of their components is provided
as under:
S. N. Fire Equip. Quantity
(Nos.)
1 Fire
Extingushier 250
2 Safety 40
S.
No Conditions of Environment Clearance
Status Status of Compliance
Shower
3 Sprinkler 4
Photograph is provided in Annexure-
13.
18 Training shall be imparted to all employees
on safety and health aspects of chemicals
handling.
Pre-employment and routine periodical
medical examinations for all employees
should be undertaken on regular basis.
Training to all employees on handling of
chemicals should be imparted.
Occupational health surveillance of the
workers should be done on a regular basis
and records maintained as per the
factories Act.
Complied Training is given to all employees on
safety and health aspects of chemicals
handling.
Pre-employment and routine periodical
medical examinations for all employees
are conducted regularly. Training to all
employees on handling of chemicals is
provided regularly.
Details of training & medical checkup is
provided as below:
S.
N. Type
Number of
Person
1 Medical
Checkups 389
2
Safety &
Environment
Training
2,500
hrs/year to
330 persons
Photograph of such training is given in
Annexure-14.
Occupational health surveillance of the
workers is done on regular basis and
records maintained as per the factories
Act. Details of safety equipment:
S.
N. Safety Equip.
Quantity
(Nos.)
1 Helmets 550
2 Safety Googles 550
3 Safety Shoes 550
4 Different types of
gloves 1,000
19 Occupational health surveillance of the
workers shall be done on a regular basis
and records maintained as per the
factories Act.
Complied We have own health center. For
employees and contractors, medical
tests are being conducted yearly, and
records are maintained as per the
S.
No Conditions of Environment Clearance
Status Status of Compliance
factories Act.
20 The company shall comply with the
recommendations made in the
EIA/EMP/Risk assessment report. Risk
assessment shall be included in the safety
Manual.
Complied Based on the risk assessment studies
during EIA, all the recommendations for
the existing units are taken. Once, the
expansion and new projects are
implemented the recommendations will
be complied. Safety manual includes risk
assessment details. Safety audits are
conducted at regular intervals.
21 Green belt should be developed at least in
33% of the plant area in and around the
plant premises to mitigate the effects of
fugitive emissions all around the plant as
per the CPCB guidelines in consultation
with DFO. Selection of plant species should
be as per the CPCB guidelines.
Partially
Complied
Since, the plant was commissioned in
year 2004 (before the EIA notification,
2006); land for greenbelt development
was not provided at that stage. Thus,
Greenbelt is developed in 10% of total
area. As per CPCB guidelines, species
like Neem, badam, coconut, khajur
species are developed for improving
greenbelt.
Photographs of greenbelt development
are shown in Annexure-15.
22 All the commitments made to the public
during public hearing/public consultation
meeting held on 1st February, 2011 should
be satisfactorily implemented and
adequate budget provision should be
made accordingly
Complied Agreed and is complied with.
23 At least 5% of the total cost of the project
shall be earmarked towards the Enterprise
Social Commitment based on earlier Public
Hearing Issues.
Locals need and item- wise details along
with time bound action plan shall be
prepared and submitted to the Ministry's
Regional Office at Bhopal Implementation
of such program shall be ensured
accordingly in a time bound manner.
Complian
ce in
progress
Since all the products as mentioned in
EC are not established, the total project
cost as provided in EIA, is not yet spent.
Based on the phase wise
implementation of project, 5% of
incurred project cost will be spent in 5
years in CSR Activities till 2023.
Since it is a 5 years of action plan, it will
be completed progressively over a
period of time as committed.
Therefore, compliance is in progress.
24 The Company shall submit within three
months their policy towards Corporate
Environment Responsibility which should
inter-alia address
(I) Standard operating process/procedure
to being into focus any
Complied We are submitting herewith policy of
Corporate Environment Responsibility.
Please refer Annexure-16.
S.
No Conditions of Environment Clearance
Status Status of Compliance
infringement/deviation/violation of
environmental or forest norms/conditions,
(ii) Hierarchical system or Administrative
order of the Company to deal with
environmental issues and ensuring
compliance to the environmental clearance
conditions and
(iii) System of reporting of non
compliance/violation environmental norms
to the Board of Directors of the company
and/or stakeholders or shareholders.
25 Provision shall be made for the housing for
the construction labour within the site with
all necessary infrastructure and facilities
such as fuel for cooking, mobile toilets safe
drinking water, medical health care, creche
etc. The housing may be in the form of
temporary structure to be removed after
the completion of the project. All the
construction wastes shall be managed so
that there is no impact on the surrounding
environment.
Complied No such housing was required as local
construction manpower was employed.
During construction phase of few
products & power plant, excavated soil
was reused for filling low lying area
hence there was no impact on the
surrounding environment. Other
construction waste was disposed off
properly.
B GENERAL CONDITIONS
26 The project authorities shall strictly adhere
to the stipulations made by the Gujarat
Pollution Control Board.
Complied Agreed and Shall be complied. Valid
NOC & CCA is received from GPCB.
27 No further expansion or modifications in
the plant shall be carried out without prior
approval of the Ministry of Environment
and Forests. In case of deviations or
alterations in the project proposal from
those submitted to this Ministry for-
clearance. A fresh reference shall be made
to the Ministry to assess the adequacy of
conditions imposed and to add additional
environmental protection measures
required, if any.
Complied Agreed and Shall be complied with if any
further expansion takes place in future.
28 The National Ambient Air Quality Emission
Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November.
Complied AAQM Result from Eco System Resource
Management PVt. Ltd, Surat as per
G.S.R No. 826(E) dated 16.09.2009 is
S.
No Conditions of Environment Clearance
Status Status of Compliance
2009 shall be complied. enclosed as Annexure-5.
29 The locations of ambient air quality
monitoring stations shall be decided in
consultation with the State Pollution
Control Board (SPCB) and it shall be
ensured that at least one stations is
installed in the upwind and downwind
direction as well as where maximum
ground level concentrations are
anticipated.
Complied Within the factory premises, four
locations (as mentioned in S. No. 4)
were selected as per the guidelines of
GPCB.
30 The overall noise levels in and around the
plant area shall be kept well within the
standards by providing noise control
measures including acoustic hoods.
silencers enclosures etc. on all sources of
noise generation. The ambient noise levels
shall conform to the standards prescribed
under Environment (Protection) Act. 1986
Rules. 1989 viz.75 dBA (day time) and 70
dBA (night time)
Complied We have carried out the Noise level
Monitoring in and around plant area of
Padana Village) and their report duly
signed & stamped by Sarpanch of
Padana Village is enclosed as
Annexure-17.
31 The Company shall harvest rainwater from
the roof tops of the buildings and storm
water drams to recharge the ground water
and use the same water for the process
activities of the project to conserve fresh
water.
Complied Action taken. Roof of office/plant
building are connected with suitable
pipe lines to raw water tank. We are
taking this harvested rainy water to raw
water storage tank and thereby further
use it in the plant through mixed filters.
32 Training shall be imparted to all employees
on safety and health aspects of chemicals
handling Pre-employment and routine
periodical medical examinations for all
employees shall be undertaken on regular
basis. Training to all employees on
handling of chemicals shall be imparted.
Complied Training is given to all employees on
safety and health aspects of chemicals
handling.
Pre-employment and routine periodical
medical examinations for all employees
are conducted regularly. Training to all
employees on handling of chemicals is
provided regularly.
33 Usage of Personnel Protection Equipments
(PPEs) by all employees/ workers shall be
ensured.
Complied PPEs like different types of helmets,
goggles, safety shoes, dust masks, gas
masks, hand gloves, ear plugs, ear
muffs etc. are provided to all the
employees & contractors, and its use is
ensured by doing plant round, CCTV
cameras.
S.
No Conditions of Environment Clearance
Status Status of Compliance
34 The company shall also comply with all the
environmental protection measures and
safeguards proposed in the documents
submitted to the Ministry. All the
recommendations made in the EIA/EMP in
respect of environmental management risk
mitigation measures and public hearing
relating to the project shall be
implemented.
Complied Agreed and being complied with.
35 The company shall undertake all relevant
measures for improving the social
economic conditions of the surrounding
area. CSR activities shall be undertaken by
involving local villages and administration.
Complied Based on the phase wise
implementation of project*, 5% of
incurred project cost will be spent in 5
years in the Health & Hygiene, Safe
Drinking Water, Educational Activities,
Sanitation & Drainage System, Skill
Development/ Training Program &
developing Eco development Activities.
36 The company shall undertake eco-
developmental measures including
community welfare measures in the
project area for the overall improvement of
the environment.
Complied Eco development activities of nearby
areas are initiated. Accordingly Neem,
Pipal, badam are planted in village
Padana.
37 A separate Environmental Management
Cell equipped with full fledged laboratory
facilities shall be set up to carry out the
Environmental Management and
Monitoring functions.
Complied Environmental Management Cell is in
place as shown in Annexure-18.
38 The company shall earmark sufficient
funds towards capital cost and recurring
cost per annum to implement the
conditions stipulated by the Ministry of
Environment and Forests as well as the
State Government along with the
implementation schedule for all the
conditions stipulated herein. The funds so
earmarked for environment management/
pollution control measures shall not be
diverted for any other purpose.
Complied The state has stated in their CTO dated
12.09.2017 (general condition No. 12)
that we have to follow EMP requirement
as stated in EC dated 10th May, 2013.
Issued by MoEF. Therefore, there is no
separate EMP requirement for state and
MoEF.
39 A copy of the clearance letter shall be sent
by the project proponent to concerned
Panchayat, Zila Parisad/Municipal
Corporation. Urban local Body and the
local NGO if any, from who suggestions /
representations, if any, were received
Complied We do agree that there is some delay in
meeting with requisite compliance.
The EC copy is provided to Gram
Panchayat office of Padana Village on
14.05.2017 & their acknowledgement
S.
No Conditions of Environment Clearance
Status Status of Compliance
while processing the proposal. confirmation duly signed & stamped
Is enclosed as Annexure-19.
Therefore, now Compliance is fully met
with EC requirement.
40 The project proponent shall also submit six
monthly reports on the status of
compliance of the stipulated Environmental
Clearance conditions including results to
monitored data (both in hard copies as
well as by e-mail) to the respective
Regional Office of MoEF, the respective
Zone Office of CPCB and the Gujarat
Pollution Control Board. A copy of
Environmental Clearance and six monthly
compliance status report shall be posted
on the website of the company.
Complied We are hereby submitting six monthly
EC compliance reports for the duration
of April-2017 to September-2017.
41 The environmental statement for each
financial year ending 31st March in Form-v
as is mandated shall be submitted to the
concerned State Pollution Control Board as
prescribed under the Environment
(Protection) Rules. 1986, as amended
subsequently. shall also be put on the
website of the company along with the
status of compliance of environmental
clearance conditions and shall also be sent
to the respective Regional Offices of MoEF
by e-mail.
Complied
.
We are submitting Form-V regularly to
GPCB on XGN Portal. It is also
forwarded to RO, MoEF& CC by e-mail.
It is also uploaded on KCIL’s website.
42 The project proponent shall inform the
public that the project has been accorded
environmental clearance by the Ministry
and copies of the clearance letter are
available with the SPCB/Committee and
may also be seen at Website of the
Ministry at www.moef.nic.in. This shall be
advertised within seven days from the date
of issue of the clearance letter, at least in
two local newspapers that are widely
circulated in the region of which one shall
be in the vernacular language of the
locality concerned and a copy of the same
shall be forwarded to the concerned
Regional Office of the Ministry.
Complied EC was not received within the seven
days of the date of issue. Once EC was
received, it did not have complete
product list. By-product list was missing.
Thus, EC was amended and received on
28th March, 2017. Advertisement of the
same was published in Times of India
and Gujarat Samachar, Kutch Edition on
14th April, 2017. Letter was provided to
the concerned authorities and pubic with
the copies of advertisements.
We have also submitted copy of
advertisement in Gujarat Samachar and
Times of India. Please refer Annexure-
20.
S.
No Conditions of Environment Clearance
Status Status of Compliance
43 The project authorities shall inform the
Regional office as well as the Ministry. The
date of financial closure and final approval
of the project by the concerned authorities
and the date of start of the project.
Complied Agreed. Financial closure and final
approval for the expansion unit will be
informed to Regional office as well as
the Ministry.
M/S. KCIL EC COMPLIANCE REPORT
Annexure-1: Log sheets of ETP & MEE
Log sheet of ETP
M/S. KCIL EC COMPLIANCE REPORT
Log sheet of MEE Plant
M/S. KCIL EC COMPLIANCE REPORT
M/S. KCIL EC COMPLIANCE REPORT
Log sheets of incinerator
M/S. KCIL EC COMPLIANCE REPORT
Annexure-2: Stack Analysis Results
M/S. KCIL EC COMPLIANCE REPORT
Annexure-3: Waste water Analysis Results
M/S. KCIL EC COMPLIANCE REPORT
Annexure-4: Noise Monitoring Results
M/S. KCIL EC COMPLIANCE REPORT
Annexure-5: AAQM Results
&
Annexure-5A: Screen shot of uploaded report
M/S. KCIL EC COMPLIANCE REPORT
Annexure-6: Work place monitoring Results
M/S. KCIL EC COMPLIANCE REPORT
M/S. KCIL EC COMPLIANCE REPORT
Annexure-7: Photograph of Benzene Sensor
M/S. KCIL EC COMPLIANCE REPORT
Annexure-8: Certificate of Cl2 Sensor
M/S. KCIL EC COMPLIANCE REPORT
M/S. KCIL EC COMPLIANCE REPORT
Annexure-9: Photograph of earthing relay
M/S. KCIL EC COMPLIANCE REPORT
Annexure-10: Photograph of Hood along with Suction facility and Scrubbing
System
M/S. KCIL EC COMPLIANCE REPORT
Annexure-11: Design details of Incinerator
Sr.
No. Description Details
1 Type Vertical
2 Capacity 2,000 Lit/Hr
3 Size - Diameter 1.0 meter
4 Incinerator Height 5.0 meter
5 Inlet feed rate 2,000 Lit/Hr
6 Fuel Consumption 250 Lit/Hr
7 Fuel LDO
8 LDO Feed System Pumping
9
Nozzle
LDO
Mother liquor
Lap – 1 (2 Nos.)
Lap – 2 (2 Nos.)
10 Operating Temperature 800 – 1,100 °C
11 Scrubber Ventury Scrubber
12 Stack Height 20 meter
M/S. KCIL EC COMPLIANCE REPORT
18
Annexure-12: SOP for Hazardous chemicals
M/S. KCIL EC COMPLIANCE REPORT
19
M/S. KCIL EC COMPLIANCE REPORT
20
M/S. KCIL EC COMPLIANCE REPORT
21
M/S. KCIL EC COMPLIANCE REPORT
22
M/S. KCIL EC COMPLIANCE REPORT
23
M/S. KCIL EC COMPLIANCE REPORT
24
Annexure-13: Photographs of Fire Hydrant System
M/S. KCIL EC COMPLIANCE REPORT
25
Annexure-14: Photographs of Safety trainings
M/S. KCIL EC COMPLIANCE REPORT
26
M/S. KCIL EC COMPLIANCE REPORT
27
Annexure-15:
Photographs of Greenbelt development
Photograph-1
Photograph-2
New Plantation at Outer Periphery of the plant
Photograph-3
Photograph-4
M/S. KCIL EC COMPLIANCE REPORT
28
Annexure-16: Corporate Environment Policy
M/S. KCIL EC COMPLIANCE REPORT
29
Annexure-17: Noise level Certificate from Padana Gram Panchayat
M/S. KCIL EC COMPLIANCE REPORT
30
Annexure-18: Environment Management Cell
M/S. KCIL EC COMPLIANCE REPORT
31
Annexure-19: Acknowledgement letter from Padana Gram Panchayat
M/S. KCIL EC COMPLIANCE REPORT
32
M/S. KCIL EC COMPLIANCE REPORT
33
Annexure-20: EC Advertisement in News Paper