12
1 Rwanda 8.5 MW project - the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection - the quickest power project ever in Africa? Joint presentation by: Lead investor EPC, O&M Developer

Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

  • Upload
    others

  • View
    14

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

1

Rwanda 8.5 MW project - the

first utility-scale solar plant in

East Africa12 months from PPA to

Interconnection -

the quickest power project ever in

Africa?

Joint presentation by:

Lead investor EPC, O&M Developer

Page 2: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Introduction to GWG

Gigawatt Global, a multi-national renewable energy company, is a leading frontier solar developer which developed the first utility-scale solar field in East Africa.

Page 2

Page 3: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

A solar IPP with an integrated business model

Equipment

manufacturing

Scatec Solar

Project

developmentFinancing Construction Operations

Ownership

(IPP)

• Long-term

ownership

• Investment

JV with

• Performance

• Maintenance

and repair

• Project

management

• Construction

monitoring

• Equity and

debt

structuring

• Own

development

• Local

partners

• Funding of

developers

Attractive for developers: •Take 100% equity requirements together with Norfund •Bring all required debt financing•Do full EPC, O&M and asset management

INTRODUCTION TO SCATEC SOLAR

Page 4: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

A strong position in emerging markets

CC 66

BB

AA11

22

77

5588

Established 2001

Main offices

Norway Oslo

South Africa Cape Town

United States San Francisco

Market Cap ~ 400 MUSD

Operational Power Plants

Czech Republic 20 MW

Kalkbult, RSA 75 MW

Linde, RSA 40 MW

Dreunberg, RSA 75 MW

ASYV, Rwanda 9 MW

Plants under construction

Jordan 43 MW

Red Hills, Utah 100 MW

Honduras 60 MW

11

33 44

22

33

44

55

66

77

88

AA

CC

BB

Page 4

INTRODUCTION TO SCATEC SOLAR

• 430 MW in operation / under construction

• 310 MW in emerging markets

Page 5: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

copyright: Scatec Solar Solutions GmbH

www.scatecsolar.com • [email protected]

The opportunity – SSA is finally starting to add MWs

5

Generation

capacity in SSA

Power

investment by

source

Source: Research by Anton Eberhard

Most Chinese

projects are

large hydro

Thermal +

renewable

Page 6: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Solar power is a potential game changer for Africa

“I’d put my money on the sun and solar energy.

What a source of power! I hope we don’t have to

wait until oil and coal run out before we tackle

that.”

Thomas Edison, 1931

Why solar power?

•Solar is cost competitive: Cheaper than new-build coal in

South Africa

•Simpler and faster to build than any other source – 9

months for 75 MW Kalkbut

•Scalable and flexible technology – rooftop to large-

scale, grid to off-grid

•Clean and sustainable

Why solar power?

•Solar is cost competitive: Cheaper than new-build coal in

South Africa

•Simpler and faster to build than any other source – 9

months for 75 MW Kalkbut

•Scalable and flexible technology – rooftop to large-

scale, grid to off-grid

•Clean and sustainable

Page 7: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Rwanda overview

Significant reforms in the 2000s to enable private investment

•52 / 185 in World Bank “Doing Business” report

•Corruption Index (Transparency International): 49/183

•Net FDI inflows from 8 to 110 MUSD in 2000 to 2013 (~ 15x)

•Real GDP growth 8% 2001 - 2013

•Poverty rate from 59% in 2001 to 45% in 2011

Energy facts when development was initiated

•Population of 11+ million

•Installed capacity: 110 MW

•15% of population with grid access

•40% of capacity is diesel

•Targeted capacity by June 2018: 563 MW

•Existing IPP framework + 1 prior energy deal negotiated

Page 8: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Project overview

Page 8

• Location: 60 km outside Kigali,

on Agahozo-Shalom Youth

Village land

• Capacity: 8.5 MWp, increased

grid capacity by 6%

• Annual generation: 15.5 GWh

• Technology:

• Polycrystalline modules

(BYD from China)

• Single-axis trackers

(Ideematec from

Germany)

• SMA inverters from

Germany

• PPA details: 25 years

• Total project cost: 23.7 MUSD

• Location: 60 km outside Kigali,

on Agahozo-Shalom Youth

Village land

• Capacity: 8.5 MWp, increased

grid capacity by 6%

• Annual generation: 15.5 GWh

• Technology:

• Polycrystalline modules

(BYD from China)

• Single-axis trackers

(Ideematec from

Germany)

• SMA inverters from

Germany

• PPA details: 25 years

• Total project cost: 23.7 MUSD

Developer Lead investor

Page 9: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

• Aug 2013: Start of DD Process

with potential lenders

• Aug 2013: EPC tender

• Oct 2013: Active engagement

with Norfund / Scatec

• Nov 2013: Scatec EPC offer; in-

principle agreement between

parties

• Nov 2013: Mandating of FMO

and EAIF as lenders

• Dec / Jan 2014: Final agreement

between GWG, Scatec and

Norfund

• 14 Feb 2014: Financial close

• Mar 2012: Partnership w / ASYV

• Apr 2012: EOI

• Jun 2012: First engineering visit

• Nov 2012: MOU with GoR

• Dec 2012: EIA, initial design and

Grid Study completed

• Jan 2013: Feasibility and EIA

studies approved

• Feb - July 2013: PPA

negotiations with EWSA

• July 2013: PPA signed

<<<<<<<<<<<<<

12 months from PPA to Interconnection

Page 9

Project development Financing Construction Operations

• Dec 2013 – Feb 2014: Negotiations with

sub-suppliers

• Feb 2014: Site mobilization

• Mar 2014: Site preparation completed

• Apr – May 2014: Project slow down

• Jun – Jul 2014: Installation of trackers,

modules and electrical work

• 26 Jul 2014: Interconnection

• Aug 2014: Testing and Commissioning

• Sep 2014: Formal Operation Date

July 2013 – PPA Feb 2014 – Financial Close July 2014 – Interconnection

Page 10: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Summary of success factors

Page 10

• Strong local partner

• GoR a strong customer: Tight timeline, but committed to avoiding

delays and strong negotiators

• Strong legal representation– Norton Rose Fulbright

• Existing IPP framework

• Permits in good order – IFC performance standards

• From PPA to Financial Close, parallel negations but prioritization of

speed

• Debt providers (FMO/EAIF) had already worked together

• Strong equity consortium (Scatec / Norfund) which had worked

together and with track-record in Africa

• Integrated offering of Equity + EPC + O&M

• Taxes: Critical to get it right

• Grants for pre-development (OPIC / Power Africa and EEP)

Page 11: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Recommendations for future large-scale grid connected solar deployment

• Standard and bankable contractual documents

• Experienced local and international advisers

• Strong dialogue with lenders

• Direct negotiations - critical to define criteria and evaluate “value for money”

• Feed-In-Tariffs – hard to get the tariff right

• Tender programs – more complex but most relevant to achieve scale

• Leverage international efforts like IFC «Scaling Solar» and Uganda «GET FIT»

• Long-term plan with clear targets

• Continuity in program vs one-off projects

• Land constraints need to be overcome

• Clear understanding of the grid required (e.g. grid issues South Africa)

• Grant funding in early stage development

Develop bankable

framework

Develop bankable

framework

Carefully

consider

procurement

approach

Carefully

consider

procurement

approach

Create scale and

predictability

Create scale and

predictability

Other Other

Page 12: Rwanda 8.5 MW project -the first utility-scale solar plant ... Africa... · Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection

Contacts

Andrzej Golebiowski

Vice President Business Development

Country Manager South Africa

[email protected]

Mobile: + 27 79 606 0225 (ZA) / + 47 45 21 49 04 (NO)

Page 12

Chaim Motzen

Managing Director and Co-Founder

[email protected]

[email protected]

Mobile: + 972 52 352 90 87