Document Reference: MS04-000672 Issue: 01 - Approved Document N o : MS04-000672 SSWP 027 Health and Safety Requirements for Contractors on Operational Sites Prepared: Georgina Rofique Signed Electronically: 23-Jun-2011 Checked: Magnus Hopstadius Signed Electronically: 27-Jun-2011 Approved: Kent Eriksson Signed Electronically: 29-Jun-2011

RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

Document No: MS04-000672

SSWP 027 Health and Safety Requirements for Contractors on Operational Sites

Prepared: Georgina Rofique Signed Electronically: 23-Jun-2011

Checked: Magnus Hopstadius Signed Electronically: 27-Jun-2011

Approved: Kent Eriksson Signed Electronically: 29-Jun-2011

Page 2: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

1

Revision History

Issue Date Nature And Location Of Change01 19-04-2011 Document first created for the Scandinavian market,

adapted from UK & Ireland document 01059-000654, issue 01, draft.Adjusted according to Swedish legislation and best practice. Changed the numbering in the tables.Changed the format templates for the headings.Changed the headings of 3.0 References to suit Swedish legislation.Hyperlinks updated in accordance with SSOP 000 Safety Managemnt System Introduction and Index MS04-000650.Added general information of when Nordisk Vindkrafts documents are under development, UK/Ireland documents are to be referred to.Added Generation specfic documents.Added words in the 4.0 Definitions.Changed 6.2 (Port cabins) to Swedish best practice.Customized COSHH to Swedish.Added information of Construction safety coordinator.Changed “pollutants” to “chemicals”.Added an example in the Example list of high risk operations and areas.Added ESA-education to Safety training.Changed “GP” to “medical doctor”.Deleted the “certification” in the section of First Aid.Customized Accident reporting to Swedish rules. Added info of excavation.Refererred to BS 7121 in the section 7.2 1).Customized the information in 7.2 7), 7.2 11) and 7.2 12) to Swedish rules.Customized the information of Scaffolding to Swedish rules.Customized Electrical works to Swedish rules.Customized 7.9 to Swedish rules and best practice.Added info of Vibrations according to Swedish rules.Changed “accident book” to “Nordisk Vindkraft’s templates”.Changed that Contractor shall retain accident records instead of accident book.Reviewed inline wih SSOP 011.Environmental management section removed and reference to the Environmetal procedure added.7.7.11 LPG checklist added.

Page 3: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

1

CONTENTS

1.0 PURPOSE ........................................................................................................................................1

2.0 SCOPE..............................................................................................................................................1

3.0 REFERENCES .................................................................................................................................1

3.1. Lag och förordning 1

3.2. Föreskrifter och ADI 2

3.3. Standarder 3

3.4. Branch Guides 3

3.5. Nordisk Vindkraft documents 33.5.1. Generation specific documents 3

4.0 DEFINITIONS ...................................................................................................................................4

5.0 RESPONSIBILITIES ........................................................................................................................6

5.1. Contractor responsibilities 65.1.1. Risk Assessment/Work Instructions (Method Statements) 8

6.0 HEALTH AND SAFETY MANAGEMENT ......................................................................................8

6.1. Contract management 8

6.2. Site accommodation 10

6.3. Site security 12

6.4. Quarterly meeting 12

6.5. Safety Meetings 14

6.6. Work Instructions (method statements) 15

6.7. Risk Assessment (Ref. SSOP-014) 16

6.8. Examples of high risk operations and areas 16

6.9. Safety training 176.9.1. Contractor responsibilities 176.9.2. The Company’s responsibilities 17

6.10. Safety audit (Ref. SSOP-002) 17

6.11. Alcohol, drugs and smoking policy 18

6.12. First Aid (SSOP-009) 18

6.13. Accident Reporting and Investigation (Ref SSOP-001) 19

7.0 PARTICULAR SAFETY REQUIREMENTS..................................................................................20

7.1. Excavations, barriers and existing underground services (Ref. SSOP 013 Permits to work) 20

7.2. Lifting operations (Mobile Cranes (Ref. SSOP-012); Accessories for Lifting (Ref. Lifting Operations Checklist) 22

7.3. Scaffolding / Ladders 23

7.4. Work at height 24

7.5. Company plant & apparatus 25

7.6. Electrical works 257.6.1. General (Electricity on Operational Sites) 25

Page 4: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

2

7.6.2. High voltage electrical works (Ref. SSOP 011 Management of Electrical and Mechanical Safety) 26

7.6.3. High voltage compounds (Ref. SSOP 011 Management of Electrical and Mechanical Safety) 27

7.7. Gas/ electric welding, burning and cutting 28

7.8. Protective equipment and clothing (Ref SSWP-002) 30

7.9. Transport 30

7.10. Fire 31

7.11. Working areas 32

7.12. Storage of materials 33

7.13. Contractors plant & equipment 33

7.14. Signs 34

7.15. Lighting 34

7.16. Confined Spaces 34

7.17. Noise & Disturbance 35

7.18. Hand Arm Vibration 35

8.0 ENVIRONMENTAL MANAGEMENT ............................................................................................35

9.0 SITE SAFETY RULES FOR EMPLOYEES OR CONTRACTORS .............................................35

9.1. General 35

9.2. Accidents 36

9.3. Emergencies during work 36

9.4. Wind turbines 37

9.5. Disciplinary Procedure 37

10.0 DELIVERABLES............................................................................................................................37

11.0 APPENDICES ................................................................................................................................38

Appendix 1 – Issue / Receipt for SSWP -027 39

Page 5: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

1

1.0 PURPOSE

The purpose of this procedure is to promote the Health and Safety of Contractors and Nordisk Vindkraft employees by setting out the general requirements when working on Nordisk Vindkraft Generation sites including detailed requirements to avoid danger from specific hazards.

This document should be read carefully by all persons visiting operational sites and its receipt acknowledged in writing in connection with a specific Contract. No variation will be permitted without the express permission of the Nordisk Vindkraft.

This document should be read in conjunction with the Generation Health and Safety documentation held on site.

2.0 SCOPE

This procedure should be supplied to all Contractors tendering for any of the Company’s Contracts. A copy should be issued to the Safety Representative of each Contractor on a site, at the commencement of a project, and a written receipt obtained and filed by the Site Engineer. (Refer to Appendix 1).

It should be noted that this procedure and the References given below do not cover all possible site activities and it therefore remains the Contractors responsibility to ensure that their works are carried out in a safe manner which complies with legislation current at that time.

This procedure and the References given below relate to Generation activities carried out within Scandinavia. Contractors shall be responsible for complying with equivalent and relevant legislation in force within the country in which the project is to be carried out.

3.0 REFERENCES

The following lists are not exhaustive but contain many useful references.

3.1. Lag och förordning

1) SFS 1977:1160 Arbetsmiljölagen2) SFS 1977:1166 Arbetsmiljöförordningen3) SFS 2005:395 Vägarbetstidslagen4) SFS 1982:673 Arbetstidslagen5) SFS 1997:857 Ellag6) SFS 2009:22 Starkströmsförordning7) SFS 1990:806 Elinstallatörsförordningen8) SFS 1993:1098 Förordning om elektrisk materiel9) SFS 1971:948 Väglag10) SFS 1971:954 Vägkungörelse11) SFS 1973:1149 Anläggningslag

Page 6: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

2

3.2. Föreskrifter och ADI

1) AFS 1999:03 Byggnads- och anläggningsarbete2) ADI 631 Nya regler för bättre arbetsmiljö i byggbranschen3) AFS 1990:12 Ställningar4) ADI 161 Anmäl din arbetsskada5) ADI 512 Byggnadsställningar6) ADI 616 Ergonomi i byggbranschen – förebygg de belastningsergonomiska

riskerna7) ADI 574 Förebygg före byggande8) ADI 539 Säkrare bygg och anläggningsarbete9) AFS 2003:06 Besiktning av lyftanordningar och vissa andra tekniska

anordningar10) AFS 1981:14 Skydd mot skada genom fall11) AFS 1981:15 Skydd mot skada genom ras12) AFS 2004:03 Stegar och arbetsbockar13) AFS 2006:04 Användning av arbetsutrustning14) AFS 2006:05 Användning av truckar15) AFS 2004:06 Användning av traktorer16) AFS 2003:02 Bergarbete17) AFS 1984:02 Bultpistoler18) AFS 2000:04 Kemiska arbetsmiljörisker19) AFS 1984:03 Spikpistoler20) AFS 2007:01 Sprängarbete21) AFS 2005:15 Vibrationer22) AFS 1992:09 Smältsvetsning och termisk skärning23) AFS 2006:06 Användning av lyftanordningar och lyftredskap24) AFS 2000:02 Användning av motorkedjesågar och röjsågar25) AFS 2001:03 Användning av personlig skyddsutrustning26) AFS 1993:03 Arbete i slutet utrymme27) AFS 1998:05 Arbete vid bildskärm28) AFS 2000:42 Arbetsplatsens utformning29) AFS 1998:01 Belastningsergonomi30) AFS 2005:16 Buller31) AFS 1982:03 Ensamarbete32) AFS 1999:07 Första hjälpen och krisstöd33) AFS 1997:07 Gaser34) AFS 2001:04 Gasflaskor35) AFS 1987:02 Högfrekventa elektromagnetiska fält36) AFS 1994:08 Laser37) AFS 2000:01 Manuell hantering38) AFS 2008:03 Maskiner39) AFS 2000:06 Mast och stolparbete40) AFS 2005:06 Medicinska kontroller i arbetslivet41) AFS 1996:01 Minderåriga42) AFS 1992:18 Motorbränslen43) AFS 1986:13 Oljor44) AFS 1980:14 Psykiska och sociala aspekter på arbetsmiljön45) AFS 2008:13 Skyltar och signaler46) AFS 2001:01 Systematiskt arbetsmiljöarbete47) AFS 2006:07 Tillfälliga personlyft med kranar eller truckar

Page 7: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

3

48) AFS 1993:02 Våld och hot i arbetsmiljön49) AFS 1981:14 Skydd mot skada genom fall50) ELSÄK-FS 2000:1 Elsäkerhetsverkets föreskrifter om viss elektrisk materiel

samt allmänna råd om dessa föreskrifters tillämpning51) ELSÄK-FS 2006:1 Elsäkerhetsverkets föreskrifter och allmänna råd om

elsäkerhet vid arbete i yrkesmässig verksamhet52) ELSÄK-FS 2007:2 Elsäkerhetsverkets föreskrifter om behörighet för

elinstallatörer53) ELSÄK-FS 2008:1 Elsäkerhetsverkets föreskrifter och allmänna råd om

hur elektriska starkströmsanläggningar ska vara utförda.54) ELSÄK-FS 2008.2 Elsäkerhetsverkets föreskrifter och allmänna råd om

varselmärkning vid elektriska starkströmsanläggningar.55) ELSÄK-FS 2008:3 Elsäkerhetsverkets föreskrifter och allmänna råd om

innehavarens kontroll av elektriska starkströmsanläggningar56) Bilaga till IFS 2009:4 – Säkerhet vid arbete på väg

3.3. Standarder

1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska anläggningar,

Nationella bilagor3) SS-EN 43640004) British Standard: 7121 Part 3 Mobile Cranes

3.4. Branch Guides

ESA G05: Elsäkerhetsanvisningarna and associated documents

3.5. Nordisk Vindkraft documents

1) Nordisk Vindkraft Safety Management System, including all; SSOP and SSWP documents and safety templates.

2) Nordisk Vindkraft Quality Management System and associated documentation

3) Nordisk Vindkraft Environmental Management System and associated documentation

3.5.1. Generation specific documents

1) Work Control Procedure for NV Operational Wind Farms – MS04-0005622) O&M Emergency Contact Numbers for NV Managed Wind Farms MS04-

0005663) Overall Operation of a Wind Farm - MS04-000560

Page 8: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

4

4.0 DEFINITIONS

Abbreviation or term Explanation of abbreviation or term1) Company Nordisk Vindkraft and other special purpose entity by

Nordisk Vindkraft.

2) Arbetsmiljöverket The Swedish Work Environment Authority 3) Lifting

EquipmentComprises the lifting appliance (machinery which provides the effort) and lifting gear (components or items between the lifting appliance and the load).

4) Protective Clothing

Clothing provided for protection against dirty, wet or cold conditions.

5) Protective Equipment

Equipment which gives additional protection or protection from hazards which cannot be avoided by other means.

6) Safety Document

Includes Permit to Work documents, and other documents that limit access or work.

7) Permit to Work A Permit to Work system is a formal written system usedto manage certain types of work that are potentially hazardous; specifies the work to be done and precautions taken; often sets time limits (start and finish times), they may be detailed on a Permit to Work.Permits to Work allow work to start only after safe procedures have been defined and they provide a clear record that all foreseeable hazards have been considered.

8) Safety Rules The Site Rules, Safe Working Procedures including supporting Codes of Practice and Safety Instructions.

9) Site Engineer The person appointed by the Company to liaise with the Contractor on matters of health and safety. The Site Engineer may nominate a representative (Safety Supervisor) to act on their behalf.

10) Safety Supervisor

The Safety Supervisor will be a Nordisk Vindkraft employee who will assist the Site Engineer and will liaise with each Contractor on health and safety matters.

Page 9: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

5

11) Safety Representative

Every Contractor on site is required to appoint a competent person, with executive authority, to be responsible forensuring compliance with the Wind Farm Health and Safety Rules. These people are required to attend the Site Safety Meetings where they will enter discussions on health and safety matters; outline their risk assessments with details of third parties who may be affected; the information necessary to enable these third parties to ensure the health and safety of themselves and any employees; provide proof of instruction and training as required by Nordisk Vindkraft; receive any instructions from Nordisk Vindkraft as necessary to fulfil their duties as Safety Representative.

The Safety Representative appointed by each Contractor will attend each meeting unless they can provide an acceptable reason for non-attendance in which case a deputy with the same authority must attend. Where this relaxation is abused the Contractor concerned may be precluded from site activities.

The Safety Representative normally fulfils the role of the Contractors Site Engineer/ site supervisor.

12) Contractor The person or persons, firm or company, including its employees and agents or Contractors, to whom the Company has awarded a contract, which requires work to be carried out on the Companies premises or sites.

13) Work Instruction (Method Statement)

Work Instructions are documents that describe in detail how individual tasks and activities are to be carried out e.g. what is done, by whom and when it has to be completed.

Work Instructions are sometimes called Method Statements.

14) Risk Assessment

The process of analysing the level of Risk, considering whether Hazards are adequately controlled, taking into account any measures already in place and ensuring that the precautions that are in place are sufficient to prevent them.

Risk Assessments are always written down.

15) Wind Farm Health and Safety File

The Wind Farm Health and Safety File is issued to the site on completion of all construction works.

The Health and Safety File must be kept up to date by the owner.

Page 10: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

6

16) Senior Authorised Person

A Nordisk Vindkraft employee authorised by the Company to carry out duties incidental to the generation, transformation, distribution or use of electrical energy; issue and cancel electrical Permits to Work, Sanctions for Test and Limitations of Access.

17) Tool box talks A 10 to 20 minute safety talk on a particular subject such as working at height, PPE, noise, occupational health etc.This it can be verbal, use a flip chart, or other visual aids.An attendance sheet showing the topic covered must be signed by employees recording that they have been given the tool box talk and they understand what they've been told.

18) Yrkesbevis Training certificate.

19) Samordningsansvarig

Safety Co-ordinator. The responsible person for the co-ordination of the safety at a workplace where there are different contractors.

5.0 RESPONSIBILITIES

5.1. Contractor responsibilities

1) It is the responsibility of all Contractors, to comply with:

All relevant Health and Safety Acts and Regulations.

The Company Site Rules, and Safety Procedures and supporting documents currently in force.

2) Attention is drawn, in particular, to the responsibility of the Contractor’s Safety Representative or other person nominated to receive Safety Documents under these safety rules.

3) When Contractors are working on Company sites a copy of this document and the appropriate Safety Rules must be prominently displayed within the Contractor’s site premises and readily available to the Contractor’s employees.

4) Contractors may make reference to the Nordisk Vindkraft Safety Management System, including safety templates, as necessary. A copy is available from the Nordisk Vindkraft Site Engineer.

5) Contractors will comply with the Wind Farm Health and Safety rules applicable to the works being carried out. It will be necessary to provide Nordisk Vindkraft with copies of Work Instructions, test certificates, calibration certificates, waste transfer notes, Risk assessments of hazardous chemical substances, Risk Assessments, etc.

6) Contractors will be expected to have in place a safety audit programme in

Page 11: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

7

advance of works commencing. The frequency of these audits will be agreed with Nordisk Vindkraft. Copies of all audits undertaken will be supplied to Nordisk Vindkraft for filing in the Health and Safety folder on Nordisk Vindkraft ECM

7) Contractors are expected to undertake tool box talks; particularly for tasks where Project specific Risk Assessments or Work Instructions are generated.Copies of all tool box talk records must be supplied to Nordisk Vindkraft for inclusion in the Health and Safety folder on Nordisk Vindkraft ECM.

8) Contractors are expected to provide details of the employees and Contractors safety training records. This shall be done in such a way as to make information easily retrievable; i.e. a training matrix with supporting copies of training certificates and “Yrkesbevis” etc.

9) Contractors are expected to manage their contractors to ensure that safe working practices are maintained at all times. Regular audits to be carried out on contractors to ensure they are compliant with current legislation and adhering to the site rules.

10) Contractor’s must ensure that they carry both mobile phone when travelling around site. This is to ensure that they can be contacted in the event of an emergency or other site situation that requires urgent attention. Where mobile phone coverage is poor on their current network an alternative mobile phone provider must be considered or a radio carried.

11) All contractors shall promptly provide to Nordisk Vindkraft such information that might affect the health and safety of workers or members of the public. The Site Engineer shall then ensure that the information is made available to those who may be affected by it.

12) Adequate steps shall be taken by the contractors to prevent livestock getting harmed on site. Fences and walls shall be maintained and gates kept closed in order to prevent livestock escaping.

13) There is an increasing problem in communicating with people who either do not speak English and/or Swedish at all or have difficulty in speaking and/ or understanding English and/or Swedish.If people do not speak or understand any English and/or Swedish it is the responsibility of the contractor to supply an interpreter for both verbal and written communications must be used. Where people speak or read limited English and/or Swedish extra care should be taken to ensure that they fully understand the message being delivered.

14) Contractors have a duty to report any unsafe acts, incidents, accidents or concerns they have on site to Nordisk Vindkraft immeidieatly, this is to include other contractors. There is a no blame culture within Nordisk Vindkraft and we strive to ensure a safe site by continued improvement.

15) Persons gaining access to Nordisk Vindkraft Wind Farms must ensure they follow the Work Control Procedure for Nordisk Vindkraft Operational Wind

Page 12: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

8

Farms - MS04-000562. A copy of this is available on request.

All contractors gaining access to a Generations site must have a completed Work Control Form - MS04-000574 issued to them by Nordisk Vindkraft. Only approved and authorised persons are to gain access to Nordisk Vindkraft Operational sites.

5.1.1. Risk Assessment/Work Instructions (Method Statements)

1) The Contractor shall undertake sufficient and suitable risk assessments. Electronic copies shall be provided to Nordisk Vindkraft for review and retention on the Wind Farm Health and Safety folder on Nordisk Vindkraft ECM.

2) Where necessary Contractors shall develop suitable Work Instructions (method statements), copies of these shall be provided to Nordisk Vindkraft for review and retention.Work Instructions shall be reviewed in accordance with SSOP 014 Risk Assessment and Work Instruction. Work Instructions shall be returned to Contractors if information is missing or inadequate. In this instance the Contractor shall revise and resubmit the Work Instruction.

3) If there is no method statement or risk assessment for the works being carried out, work must not commence. Nordisk Vindkraft will carry out random inspections to ensure that an appropriate document is readily available for the work. Nordisk Vindkraft Management may stop works at any time where it is found that suitable documentation is not available. Any cost will be met by the respective contractor on site.

6.0 HEALTH AND SAFETY MANAGEMENT

6.1. Contract management

1) If the Contract work is within the scope of the AFS 1999:3 Byggnads- och anläggningsarbete or its latest review, then the appropriate requirements forthese Regulations must be managed and complied with by all parties.

2) For every contract involving work on the Company’s premises or sites Nordisk Vindkraft Site Engineer shall liaise with the Contractor on the health and safety aspects of the contract. Similarly the Contractor shall appoint a Safety Representative and advise his/her name to the Company without undue delay, including any changes of this person. The Company shall be entitled to require the Contractor to provide evidence supporting the competence of the nominated Safety Representative. The Site Engineer will inform the Safety Representative of any additional safety measures of the Company applicable to the work and of the need for compliance with the Company’s Safety Rules.

Page 13: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

9

3) For work on or adjacent to the Company’s, electricity systems of plant and apparatus directly associated with the generation, transmission or distribution of electricity, the Contractor shall propose the name of the person or persons, whom it considers to be competent to receive Safety Documents.

4) Written agreement shall be established with each Contractor on site of the area and equipment within the site for which they are responsible and procedures shall be established for the making safe of equipment at the interfaces with other Contractors e.g. use of a Permit To Work system.

5) The Contractors Safety Representative shall ensure that there is sufficient liaison between himself, his employees, Contractors and the Site Engineer to ensure that the activities of a Contractor do not present hazards to other persons on the site.

6) The Site Engineer and Regional HSQE Manager, or any person authorised by him, has authority to stop any work, if, in his opinion, it is necessary in the interests of safety.

7) The Site Engineer shall ensure that all appropriate and relevant information on hazards particular to the Company’s operations are communicated to the Contractor. Similarly, the Contractor shall advise the Site Engineer of hazards associated with his work and how they will affect others.

8) The Contractor shall provide adequate instruction and training (to recognised standards where available) for his employees and Contractors, including induction training to ensure their own safety and the safety of others on site. The induction training should include, but is not limited to, the details included in Section 9 of this document. Induction training provided shall be recorded.

The Company shall be entitled to require the Contractor to provide evidence of the competence of his staff and that such instruction and training has been given.

9) If instructed by the Site Engineer the Contractor shall ensure, as part of the Contract, that its employees and those of its agents and Contractors shall attend the premises or the site, at such reasonable times as shall be advised, to undergo any induction training/process specific to the premises or site.

10) The Contractor is required to provide adequate supervision for their works unless their contract excludes such supervision.

11) The Contractor shall not make arrangements for any of its agents or Contractors to carry out work on the Company’s premises or sites without the prior consent of the Site Engineer.

12) The Contractor’s Safety Representative shall keep adequate records of their work on site including the duration and nature of the work. These records shall be made available to the Company, as required.

13) The Contractor’s Safety Representative shall be responsible for its personnel in the event of an emergency.

Page 14: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

10

14) The Contractor shall, if requested by the Site Engineer, satisfy the Site Engineer that the Contractor, its employees, agents and Contractors are complying with the terms of this document and that they fully understand the relevant site procedures for the work to be carried out.

15) The Contractor shall ensure that visitors who attend site are accompanied at all times by a person who has received an induction. Where visitors attend site on more than one occasion they must attend a site induction. The person accompanying visitors shall ensure that the visit is recorded in the visitor's book or site diary as detailed in the site induction.At the discretion of the Site Engineer a visitor may receive a site induction, covering the relevant induction level covering the type of work they are carrying out allowing them to attend site without the need to be accompanied. All such training shall be recorded and filed in the Wind Farm Health and Safety folder and in the Health and Safety folder on Nordisk Vindkraft ECM.

16) All persons working on electrical systems under Nordisk Vindkraft rules must have been trained by Nordisk Vindkraft and given the relevant authorisations appropirate to the access/work requirements. Where persons are working under their own company Rules, they must be approved by Nordisk Vindkraft SAP prior to carrying out any works and the Contractors SAP must take full responsibility for all works carried out as authorised by Nordisk Vindkraft. Any work that is not auhtorised must not be carried out unless written authorisation is given.

6.2. Site accommodation

1) The Contractor is required to confine storage of plant, equipment and materials to areas allocated by the Site Engineer who shall also stipulate the limits within which Contractor’s employees, agents and Contractors are allowed access.

2) The Contractor must maintain high standards of housekeeping; keep its work site, vehicles and accommodation clean and tidy and free of unnecessary obstructions. All access tracks must be kept clear of materials and free fromany substance likely to cause harm to anyone or impact on the environment.

3) Provision of office, messing and showering facilities will be the responsibility of the Contractor, unless otherwise specified. Details of ground area requirements for office, lay down areas, etc, should be advised to the Site Engineer. Sufficient facilities must be provided by the Contractor in relation to the number of personnel on site, compliant with AFS 2000:42 Arbetsplatsens utformning, and the AFS 1999:03 Byggnads- och anläggningsarbete.

4) Contractors shall give one week’s notice of accommodation being delivered to site. Unless otherwise agreed with the Site Engineer, port cabins shall;

have their own jacking arrangements be constructed from materials which will give a minimum of 30

minutes fire protection and where possible be metal clad. Where

Page 15: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

11

metal clad aren’t available cabins must be no closer than 5m, plastered inside with covered windows. Use of wooden cabins must be addressed in the Fire risk assessment for the site.

be of standard sizes, sizes to be advised to the Site Engineer prior to delivery and preferably modular form.

5) Petrol or diesel engine plant must not be located inside buildings unless their exhaust systems are piped to open air or an alternative approved by the Site Engineer.LPG must not be used in cabins under any circumstances.Where plant is to be refuelled a suitable drip tray/bund must be in place. A spill kit must be readily available on site so that in the event of a spillage it can be contained/cleaned up. All spillages must be reported to the Site Engineer immediately and a cleanup operation implemented.

6) The Contractor shall notify the Site Engineer before bringing any substances to the site and shall provide a suitable assessment of risks associated with such substances and material safety data sheets when requested by the Site Engineer.

7) The Contractor must carry out any disposal of waste materials in accordance with applicable environmental legislation and the Nordisk Vindkraft Site Waste Management Plan. Upon request, waste transfer notes shall be made available to the Site Engineer for inspection.The Site Engineer must be consulted where doubt exists on the classification of any particular waste and the Site Manger will seek advice on its classification. It is of particular importance that known toxic or noxious waste must be kept separate from general waste. All waste oil must be contained in separate receptacles. Whilst awaiting collection, all waste materials must be stored at disposal points satisfactory to the Site Engineer. Discharge of oil or other pollutants to any drains, gullies, water courses or soak ways is forbidden.

8) The control building and surrounding areas shall be maintained to a high standard to provide safe, tidy and clean working conditions. All waste products will be systematically cleared and disposed of by the Contractor.It is the responsibility of the Contractor to remove or have removed any domestic waste produced to the appropriate disposal point. Arrangements for the removal of waste generated by Contract work shall be agreed by the Contractor and the Site Engineer.

9) All temporary accommodation must be removed from site as soon as practicable on termination of any contract unless agreed by Nordisk Vindkraft to leave on site.

10) It is the responsibility of the contractor to supply appropriate storage facility for all chemicals used on site. The store must be signed in accordance with the AFS 2008:13 Skyltar och signaler. A copy of the Risk assessment of hazardous chemical substances, Register of hazardous chemical substances

Page 16: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

12

and material safety data sheet must be readily available in the store of hazardous chemical substances. Appropriate fire appliances must be readily available in the store of hazardous chemical substances.The store of hazardous chemical substances must be regularly audited by the Contractor to ensure that the register and associated documentation is up to date.

11) It is the Contractors responsibility to ensure that persons on site are adequately catered for with regards washing, sustenance and cleaning materials.

6.3. Site security

1) Having been informed by the Site Engineer of the safe means of access to and egress from the site, the Contractor shall ensure that it is used at all times.

2) Where security is used on site it will be the duty of the gate guard to ensure all vehicles entering leaving site are logged. Ensure that all persons entering site are inducted, where it is found that persons are not inducted they must ensure that the contractor is escorted on site until such time they have been inducted.All deliveries to site must be authorised by Nordisk Vindkraft/Contractor and where there are regular deliveries.

3) Communications on site must be maintained at all times. Mobile phone coverage will vary from site to site therefore VHF radio’s must be used in conjunction with mobile phones where it is found that mobile phone coverage is poor. Radio checks must be carried out at the start of the day to ensure that all radios are charged and working. Where mobile phone coverage is poor an alternative mobile phone provider must be considered.

4) Where alarms are installed it will be the Contractors responsibility to ensure that the alarms are activated prior to leaving the site. All alarm systems will be maintained under contract to ensure servicability.

6.4. Quarterly meeting

1) If a site meeting is called by the Site Engineer, the Safety Representative shall attend the meeting at such reasonable time as the Site Engineer advises. The meeting shall include, but not be limited to; discussions on safety, fire prevention, first aid matters, safe systems of work and provision for a joint inspection of the work areas, and shall establish the following: -

The Site Engineer is satisfied with the Contractors organisational structure and general arrangements to provide adequate supervision of all works carried out.

Page 17: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

13

The Safety Representative is familiar with the location of the Contractors assigned area, services, procedures and with any requirements to ensure the safety of all persons on the site including emergency arrangements and the location and use of emergency facilities.

Security arrangements, Permit to Work and other Company Safety Documents are discussed and arrangements made to ensure full compliance.

The Safety Representative is aware of specific access limitations and arrangements are made for the implementation of the site induction course.

Known or potential hazards associated with the Contractor’s operations are notified by the Safety Representative to the Site Engineer.

The precautions to be taken by others who may be affected by the Contractors activities should be fully examined and actions then defined, notified and monitored to ensure appropriate action is taken.

The proposed equipment, protective clothing, training given (or to be given) to the Contractors employees etc and the methods of working will provide effective safeguards against environmental and working hazards likely to arise.

Proposed equipment and plant being used on site has an in date certificate of thorough examination and all portable appliances have been tested in accordance with current standards.

Where risk assessment has identified significant risk or risks, a written Work Instruction(s) (method statement(s)) must be produced.

All Hot Works must be communicated to Nordisk Vindkraft prior to being carried out.

Hot Works include:

1. All Welding2. Grinding3. Cutting where sparks occur

A system of regular communication will operate effectively between all concerned to ensure that changes in circumstances and conditions are discussed and catered for, all notices, advice, requests for approval of proposed working methods etc are acted upon.

Persons proposed work on the electrical or mechanical system are competent and appropriately authorised by their own company.

Scaffolding and excavation provisions are subject to authorisation

Page 18: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

14

from Nordisk Vindkraft prior to works commencing. All inspections and approvals must be carriedout by competent persons as required.

There is adequate provision for reporting and dealing with accidents and near misses, and that appropriate procedures are established.

Arrangements are made for the disposal of waste, including equipment, materials, substances, scrap, spoil from excavations etc and recording the quantities where required by the Site Engineer.

Safety campaigns to be discussed, safety campaigns from the HSQE Regional Manager, Nordisk Vindkraft or Sub-contractor must be agreed by all parties on how campaigns will be implemented.

6.5. Safety Meetings

1) Safety Meetings will be called by the Site Engineer concerning matters of health and safety, or combined in other site meetings. The Contractors Safety Representatives shall attend these meetings.

2) Safety meetings will be chaired by a representative of the Company, usually the Site Engineer will be held at least quarterly and minutes kept and circulated to attendees.

Contractors shall be represented at the meetings by their Safety Representative. The meetings will be held to discuss, co-ordinate, and resolve all safety matters, including actions arising from audits undertaken by the Company, and examine current and future activities on site.

3) The following information may be requested at the meeting: -

Accident statistics, including lost time, notifiable or minor Incident statistics, including near misses and property damage Number of employees/contractors on site Number of employees/contractors who have completed induction

training Names of nominated Competent Persons (e.g. HV authorised) Trained first aiders Tool box talks planned and given General work areas and tasks The interaction of Contractor activities Contractor audits carried out Site documentation

This list is not exhaustive.

4) When requested by the Site Engineer the Contractor’s Safety Representative shall provide details of work in progress. This may include;

location and description of ongoing tasks

Page 19: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

15

number of personnel involved relevant risk assessments completion dates of tasks possible effects on other working parties permits to work required findings from audits Health and safety campaigns outstanding items from previous audits objectives for coming month/s details of any accidents/incidents/near misses

6.6. Work Instructions (method statements)

1) The Contractor shall have provided with his tender, a completed health and safety questionnaire and associated information, outline Work Instructions of all major works within the Contract, a generic risk assessment for all works on site.

2) The Contractor shall;

prepare detailed Work Instructions relating specifically to the contract works and submit them, along with associated risk assessments, to the Company for evaluation prior to the work commencing

present detailed risk assessments to the Site Engineer to ensure the method statements presented have been compiled in a satisfactory manner. These must be available on site for consultation

submit any alterations to the Site Engineer for evaluation prior to the commencement of work. Method statements are requested to ensure that a supply of information between all parties on site is available and that the Company are able to undertake if necessary a co-ordinating role. If the technical content of certain method statements requires specialist input then any necessary calculations and assumptions used to produce the method statements will be provided by the Contractor

ensure that his staff are fully aware of the content of the appropriate method statements, and will monitor his staff’s compliance whilst working to the method statements

nothing in the above requirements removes the responsibilities imposed upon the Contractor within any other section of the contract documents

Page 20: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

16

6.7. Risk Assessment (Ref. SSOP-014)

1) There is a legal requirement for all Contractors to carry out a risk assessment on their work and inform their staff of any significant findings. The Contractor shall provide acceptable risk assessments for their work where a potential risk is identified. The risk assessment shall be reviewed with reference to the Company’s Safety Management System.

2) The Contractor shall be given notice of any risk assessments carried out by the Company.

3) Examples of high risk areas where detailed risk assessments and Work Instructions may be required are given in section 6.8 below.

4) The Contractor shall carry out a risk assessment for any substance to be used on site that may be hazardous to health, in accordance with the AFS 2000:04 Chemical Hazards in the Working Environment. Risk assessments and material safety data sheet shall be made available to the Site Engineer, on request.

5) Ensure that his staff are fully aware of the content of the appropriate risk assessments and will monitor his staff’s compliance whilst working to the documentation. Where staff changes occur they must be fully informed as to the content of the documentation;

6.8. Examples of high risk operations and areas

1) Examples of high risk areas where detailed Risk Assessments and Work Instructions may be required are: -

Excavation work Excavation work in areas where underground cables, pipes or drains

may be located Complex/ heavy lifting High pressure water jetting Hydraulic testing of high pressure plant Jointing of power cables Live electrical working Operations involving emission of toxic substances Operations involving flammable materials Working in gas awareness zones Operations involving high level noise Operations involving the use of solvents/degreasants Work involving harmful chemicals, substances and pollutants Removal of poisonous waste Scaffolding The use of naked flames Welding Work at heights

Page 21: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

17

Work in areas where instrument pipes and control cable may be located

Work in confined places Work involving removal of gratings, mesh or other type of floor

sections Work on high voltage apparatus, switchgear or any substations or

switch rooms Work on or near cranes Work on overhead lines Work on rotating machines Work which may interfere with normal access, walkways, transport or

overhead cranes

The above list is not exhaustive.

6.9. Safety training

6.9.1. Contractor responsibilities

1) Ensure that no direct, or contracted, employees or self employed persons commence work on site unless they have successfully completed site safety induction training and provided the Site Engineer with relevant training certificates, Professional qualifications (in Swedish: Yrkesbevis).

2) Be responsible for ensuring that all required trade specific safety training is carried out. Production of training records will be required by the Company prior to works commencing.

3) Ensure that operative only carry out tasks that they are competent to do and their training certificates are up to date.

6.9.2. The Company’s responsibilities

1) Provide site induction training for all Contractors’ Safety Representatives. Contractor’s staff will be inducted by the Company or, at the Site Engineer’s discretion, the Contractor’s Safety Representative or his nominee will be directed to provide, such training for all personnel prior to commencing site work.

2) Comply with all duties covered under the AFS 1999:03 Building and Civil Engineering at Work and other relevant legislation.

6.10. Safety audit (Ref. SSOP-002)

1) The Company shall audit all aspects of the management of safety on site, and may carry out safety surveys, inspections, tours and sampling at any time.Any deficiencies in safety management will be fully investigated.

2) The Contractor shall make available information and records, including

Page 22: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

18

training records, thorough inspection certificates as required by the auditor.

3) The Contractor shall co-operate at all times with Company requirements in such safety related matters.

4) The contractor shall carry out regular audits as agreed by both parties that must be issued to the Company in good time. Where there is a breach of any Health and Safety Legislation by any company on site this must be communicated to the Site Engineer immediately.

6.11. Alcohol, drugs and smoking policy

1) The Company operates an alcohol, drug and smoking policy. Contractor’s employees must adhere to all smoking prohibitions and restrictions as stated locally.

2) The consumption and supplying of alcohol and drugs is prohibited on site. Misbehaviour at work such as; drunkenness or drug abuse, will be deemed gross industrial misconduct.

3) In the event of an accident occurring on site the Company may require to see the results of alcohol and drug tests.

4) Where persons are prescribed medication by their medical doctor they must ensure that they are suitable for work and inform their Line Manager or Nordisk Vindkraft Site Engineer. Where necessary the Company may require written confirmation from their medical doctor as to their suitability for work.

6.12. First Aid (SSOP-009)

1) It is the responsibility of the Contractor, under the AFS 1999:07 First Aid and Emergency Support, to provide first aid facilities and demonstrate that he has sufficient resources available to him to adequately cater for the needs of his staff. He/she shall inform his employees, agents and Contractors of the arrangements made in connection with first aid.

2) Details of the training courses and certification awarded to nominated First Aiders must be made available, if required, for the Company to examine.

3) All minor accidents must be dealt with by the facilities and persons provided by the Contractor. However, the Company facilities will be available in cases of emergency.

4) An assessment of the firrst aid requirements must be carried out to ensure that all foreseeable injuries/accidents are catered for.

Page 23: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

19

6.13. Accident Reporting and Investigation (Ref SSOP-001)

1) Employers are required (SFS 1977:1166 Arbetsmiljöförordningen section 2) to promptly report accidents at work which resulted in death or serious injury or simultaneously hit several workers to the Work Environment Authority. This also applies to incidents that resulted in serious danger to life or health.

The following information is needed when reporting to Arbetsmiljöverket: name and address on site where the incident occurred corporate identification number name of the person who is reporting and name of the injured and description of what happened.

For detailed information and the form of notification; www.av.se.

Anmälan av allvarliga tillbud, olyckor och dödsfall till Arbetsmiljöverket [Form for notification of deaths, serious accidents and serious incidents to Arbetsmiljöverket]:http://www.av.se/blanketter/paragraf2/index.aspx

Blankett för anmälning av arbetsskada (Försäkringskassan) [Form for notification of occupational injury or disease]:http://www.forsakringskassan.se/irj/go/km/docs/fk_publishing/Dokument/Blanketter/9210.pdf

Contractors shall ensure that their employees, agents and Contractors are notified of the location of the arrangements for recording accidents and that each of them should report the particulars of any accidents occurring to themselves or others.

Contractors may elect to use the templates provided by Nordisk Vindkraft for accident reporting.

2) Contractors must ensure that the Site Engineer is advised of all accidents, incidents or near misses. The Contractor shall retain accident records, along with any investigation reports, shall upon request be made available (without undue delay) for inspection by the Site Engineer.

3) Notifiable accidents, specified injuries or conditions, or dangerous occurrences which are reported by the Contractor to the Arbetsmiljöverket,according to Arbetsmiljöverket’s procedures must also, without delay, be brought to the attention of the Site Engineer and a copy of the report sent to the Arbetsmiljöverket shall be provided. Nordisk Vindkraft site engineer must then forward the copy to the HSQE dept for retention by RES and Nordisk Vindkraft.

4) Contractors must report all accidents immediately to the Site Engineer, make sure the injured person is not exposed to further injury, not move the injured party unnecessarily and stand by to assist first aiders or give details of the occurrence.

5) Near miss incidents must also be reported to the Site Engineer in order that

Page 24: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

20

steps can be taken to prevent any repetition of any incidents that could have had more serious consequences.

6) The contractors Work Environemnt responsible person/advisor must carry out a full investigation into the cause of the incident and issue a report to Nordisk Vindkraft. Where deemed necessary, Nordisk Vindkraft may carry out their own investigation in to the incident to ensure that the correct preventative measures are put in place.

7.0 PARTICULAR SAFETY REQUIREMENTS

1) This section provides general guidance to Contractors on safety procedures and standards for particular operations that must be implemented at all times when working on the Company sites or premises. (References given for the appropriate procedure within the Company Safety Management System).

7.1. Excavations, barriers and existing underground services (Ref. SSOP 013 Permits to work)

1) No excavation is permitted over live services; Nordisk Vindkraft will obtain any isolation that is required to ensure safe working. Contractors are required to give adequate notice of their intended works near to live services.Prior to the commencement of any excavations the Contractor shall liaise with Nordisk Vindkraft site management team and confirm the location of underground services on the site. The competent person will make any necessary arrangements for Safety Documents, e.g. excavation permits, to be issued prior to work commencing. The Contractor shall at his ownexpense, rectify any damage done to existing services and relieve the Company of all claims in respect of any interruptions or loss arising from such damage.NO WORK TO BE CARRIED OUT THAT IS OUTSIDE THE PERMIT TO WORK.

2) Barriers must be erected around all openings, trenches or excavations which may become a source of danger. If it is necessary to remove any open mesh floor sections, trench slabs or gully gratings the Contractor must first obtain permission from the Site Engineer, and such sections, slabs or gratings must be replaced as soon as possible. Should any floor section, slab, grating or barrier be damaged or broken the Contractor must report this to the Site Engineer and take immediate precautions to prevent danger before their replacement.

3) The Contractor must not move or alter any barriers, screens or notices placed in position by the Company, unless authorised by the Site Engineer. The Contractor shall not pass through or over such barriers without permission from the Site Engineer.

Page 25: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

21

4) Legislation requires that where ground is of such a nature or where the weather is such that a collapse might occur, and if anyone is liable to be struck or buried by a fall of earth, suitable and sufficient timbering or other supports must be required. Alternatively the sides of the excavation may be battered.

5) Close timbering may be required for excavation in such material as soft silt, clay, sand and gravel. (For guidance see detailed schedule in British Standard: Code of Practice for Earthworks BS 6031).

6) Where excavations are to be carried out in the vicinity of electric power cables the method of excavation shall be in accordance with Schakta säkrare –Säkerhet vid schaktning i jord (Safer excavation – Security at the excavation of the earth), and ESA. Further advice should be sought from a specialist should the safety measures required be unclear. Excavated material which is not required or is not suitable for backfill must be disposed of as agreed with the Site Manager. A cable avoidance tool must be used by competent persons to locate the underground services along with utilities service searches.

7) No drills, spikes or posts shall be driven into the ground without permission from the Site Engineer.

8) During the hours of darkness hazard warning lights or reflective surfaces shall be posted on barriers around excavated works.

9) Where excavations require to be supported to prevent any person being trapped or buried by an accidental collapse, fall or dislodgement of material, an inspection must be undertaken at the start of every shift.

An inspection report must be completed by the Contractor prior to work commencing for the first time; every seven days or after any substantial addition, dismantling or other alteration. Copies of completed reports shall be given to the Site Engineer.

The NV template Excavation Checklist 01627-000444 should be used to record the inspection.

10) Where plant is required to gain access in to the excavation appropriate barriers must be put in place to segregate pedestrians and plant. Appropriate signage must be put in place to clearly identify access routes. Stop blocks are to be used when vehicles are reversing up to an excavation.

11) Where excavations are flooding then appropriate pumps must be put in place to ensure water level is kept low to prevent persons from falling in and drowning. Regular inspections must be carried out to ensure stability of the excavation.

Page 26: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

22

7.2. Lifting operations (Mobile Cranes (Ref. SSOP-012); Accessories for Lifting (Ref. Lifting Operations Checklist)

1) Only certified and marked lifting equipment shall be used. The Contractor shall ensure that all lifting equipment is covered by valid test certificates, and that reports of insurance inspections carried out in accordance with legislation requirements are held on the premises or the site for all lifting equipment. It is the Contractor’s responsibility to provide a list of all such equipment, with test details, to the Site Engineer.All lifting operations must follow the guidance of British Standards 7121.

2) Lifting equipment must be stored properly when not in use, and must not be left lying about on the premises or site.

3) The ‘Safe Working Load’ must be clearly marked on all equipment and must not be exceeded.

4) Structural steelwork shall not be used for lifting points or anchorages unless, in exceptional circumstances, the prior agreement of the Site Engineer is obtained. Agreement shall not be given unless the Contractor can demonstrate that the steelwork is adequate for the intended purpose.

5) Any structural member where lifting equipment is temporarily secured must be tested as an assembly, prior to use. A test certificate must be issued and a copy passed to the Company for their records.

6) It is the Contractor’s responsibility to arrange testing, but the method of testing must be agreed with the Site Engineer prior to start of work.All statutory inspections will be carried out by a Nordisk Vindkraft approved company and tagged accordingly. Where items are out of test date then they must not be used and advice sought from Nordisk Vindkraft Site Engineer.

7) A minimum standard set for competency of the person/s carrying out such testing shall be that they are appropriately registered with the authority and suitably qualified. Evidence of this or a similar standard shall be required.

8) No person shall ride on a hoist, unless it has been designed to carry passengers, For detailed information: AFS 2006:07 Tillfälliga personlyft med kranar eller truckar.

9) A Work Instruction (method statement), lifting plan and risk assessment shall be produced in advance of any lifting operations for review by Nordisk Vindkraft as detailed in the Nordisk Vindkraft Mobile Cranes Procedure –SSOP-012 Mobile Cranes - MS04-000245

10) A checklist shall be used for all lifts (turbine section, nacelles etc) or as detailed in the Nordisk Vindkraft Checklista för mobila kranar och lyft (Lifting operations checklist) - 01627-000001. The Nordisk Vindkraft Lifting Operations Checklist shall be used except where a Contractor has their own methodology and checklist, which have been approved by the Site Engineer.

11) An annual programme for inspection and testing shall be maintained by each contractor for each site where Lifting Equipment and Lifting Accessories are

Page 27: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

23

deployed.

All Lifting Equipment must receive a thorough examination every 12 months as a minimum.

All lifting accessories must receive a thorough examination every 12 months as a minimum.

Where manufacturers guidelines stipulate more frequent inspections these must be carried out.

12) Following must be documented on the Test and Examination Record template:

Continuous maintenance and daily inspections. Periodic inspections made by a competent person. Inspection and functionally testing when taken into service after

dismantling. Operation of mechanically powered cranes for maximum loads exceeding 1.000 kg.

Other issues specified by the manufacturer.

13) All crane lifts must have a competent Appointed Persons (AP) detailed in the lifting plan. A Crane Supervisor must be on site if the AP is not available to monitor the lifting.

14) Any lifting operation that is not covered by the approved documentation must not proceed until suitable and sufficient documentation has been raised and accepted by Nordisk Vindkraft. Any lifting operations that occur outside the documentation will be in breach of legislation and the Company’s procedures and appropriate disciplinary action will be taken on individuals/company’s.

15) Relevant copies of training certificates, ”Yrkesbevis” must be issued to the Site Engineer prior to works commencing.

7.3. Scaffolding / Ladders

1) All personnel who erect and or dismantle scaffolds must have certain education and a training certificate according to AFS 1990:12 Ställningar.

All scaffolds must be controlled and marked by a “typkontroll”.

2) All scaffold structures must be designed, erected, maintained, examined and recorded in compliance with AFS 1990:12 Ställningar. In particular, workers involved in erecting or dismantling scaffold structures must, as far as is reasonably practicable, wear securely attached safety harnesses when consequences of a fall would be significant. Where necessary scaffolds must be earthed.

3) The Contractor shall obtain the authorisation of the Site Engineer for the location of any scaffold structure to be erected. Thereafter no scaffold

Page 28: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

24

structure shall be interfered with or changed without the prior-authorisation of the Site Engineer.

4) Where a Contractor wishes to use a scaffold structure erected by others then the Contractor must ensure that prior permission has been granted by the Site Engineer, the structure has been inspected for satisfactory condition within the previous seven days and that the scaffold structure will support the loads that the Contractor’s work imposes.

5) Incomplete or unsafe scaffolding must not be used and must have beenmarked stating so, by the Contractor.

6) The Contractor must ensure that all ladders brought onto the premises or site are in good condition and a system for regular inspections is in place and a register of inspections kept on the premises or site. No metal ladders shall be used in the vicinity of live overhead equipment.

7) Scaffolds will be inspected before first use and then weekly (minimum every 7 days). In addition, they will be inspected after substantial alterations and any event which could affect their stability. The results of these inspections will be entered into the site register.

An inspection report must be completed every seven days and a copy given to the Site Engineer.

7.4. Work at height

1) Before working at height or on any roof, tank etc where there is a risk of falling or serious injury occurring then the integrity of the material must be identified. Safe access and a safe work place must be provided, for example by use of crawling ladders, crawling boards, barriers, handrails, toe boards and edge protection. Materials shall be prevented from falling and notices warning of overhead work, displayed at ground level when appropriate. Where a safe workplace cannot be provided appropriate fall arrest equipment shall be provided and used.Persons using fall arrest equipment must be attached 100% of the time and this is to be achieved by use of double lanyards or other fall arrest equipment.

2) Where fall arrest equipment is being used persons must be competent in its safe use and inspections. All fall arrest equipment must be regularly inspected by competent persons. The wearer must inspect the equipment prior to use and where it is found to be defective the equipment must not be used. The equipment must be removed from site and the Sub-contractor must dispose of it in the correct manner.All fall arrest equipment must be compatible and checks must be made prior to use on any other associated equipment.

3) Fall arrest equipment must be the last resort as a control measure. Mobile Elevated Work Platforms (MEWP) or scaffolding must be used where appropriate.

Page 29: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

25

4) Ladders/step ladders must be used for light work over a short duration. Where work is required over a prolonged period appropriate work at height equipment must be used, i.e. MEWP, mobile scaffold or podium steps.

5) Contractors must ensure that all equipment supplied is compatible with with other systems used.

6) Use of fall arrest wires must only be carried out if they are within their test/thorough examination date. Persons to check tags to ensure that equipment is within date prior to use. Where items are out of date they must not be used and contact Nordisk Vindkraft Site Engineer immediately.It is the Contractors responsibility to ensure that all equipment issued to employees is compatible with systems installed. Contractors must ensure that they check compatibility of equipment used prior to use.

7) Items of safety must not be tampered with, altered or miss used and persons must be trained on their safe use.

7.5. Company plant & apparatus

1) The Contractor shall not use the Company’s plant or apparatus without the prior permission of the Site Engineer.

7.6. Electrical works

7.6.1. General (Electricity on Operational Sites)

1) All electrical installations shall comply with the Swedish electrical legislation and shall only be installed and worked on by a competent electrical craftsman.

2) The Contractor shall be responsible for providing and maintaining the whole of the installation on the load side of any point of supply made available to him by the Company and shall therefore take all reasonable precautions to ensure the safety of every person on the site, with regard to the installation. The Site Manager may require the disconnection or alteration of any parts that he considers may be dangerous.

3) The Contractor shall maintain all portable electrical equipment in good condition and hold on site a register of all portable electrical equipment, including details of routine inspections.

4) All temporary flexible cables and conductors shall be to SS-EN 4364000.

5) All wiring within site offices and other accommodation must comply with SS-EN 4364000

Page 30: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

26

6) All portable tools, hand lamps, and other apparatus, must be connected to the system by means of plugs and sockets of the type approved under SS-EN 4364000. All joints must be both electrically and mechanically sound.

7) The supply to hand held portable tools must be double-pole switched and these tools operated via a 30 ma RCD.

8) Domestic electric heaters and radiators having exposed heating elements must not be used.

9) All persons dealing with and handling electrical equipment must be trained to apply the correct treatment for electric shock.

7.6.2. High voltage electrical works (Ref. SSOP 011 Management of Electrical and Mechanical Safety)

1) All HV works must be undertaken in accordance with SSOP 011 Management of Electrical & Mechanical Safety – MS04-000250.HV > 1000V ac or >1500 dc

2) All electrical works must be carried out through Nordisk Vindkraft Site Manager (the Control Person) who shall be responsible for all works carried out on site,The Control Person shall be responsible for the following:Prior to first connection of a System the Control Person shall:i) Ensure that the following Persons are appointed for each System:· Senior Authorised Person (LV)· Senior Authorised Person (HV)· Competent Person (where required)ii) Ensure that formal safety rules have been selected for each System inaccordance with SSOP 011. The Management of Electrical and Mechanical Safety rules.iii) Ensure that the System Status Sheet has been completed and has been placed in the relevant project safety plan.iv) Ensure that all personnel referred to on the System Status Sheet are notified that the sheet has been placed in the relevant project safety plan.Prior to any Work the Control Person shall:i) Authorise and make available Plant and Apparatus. The decision to release Plant and Apparatus for Work shall take account of all safety, contractual and commercial issues.The Control Person shall remain responsible for the System until:i) relieved of the position by the Nordisk Vindkraft Project Manager, orii) the System has been permanently taken out of use, oriii) the System is no longer controlled by Nordisk Vindkraft.In each case the Control Person shall be responsible for updating the System Status Sheet and notifying all persons referred to on the sheet of the change of status.

Page 31: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

27

3) LIVE WORKINGThe following live working rules must be followed at all times and under all circumstances:· Live working on High Voltage Systems shall only be carried out in order to prove that the System is Dead.· Live working on Low Voltage Systems shall only be carried out in order to prove that the System is Dead or for diagnostic testing which cannot be undertaken by any other reasonable means.· The manipulation of exposed live parts is forbidden.· Work in close proximity to exposed live parts is forbidden.· Systems shall always be isolated in accordance with the formal safety rules in use.

4) Each Low Voltage System and High Voltage System (and its associated mechanical equipment, if any) forming part of a fixed installation that is controlled by Nordisk Vindkraft shall at all times from site establishment and construction through to and including commercial operation, maintenance, repair and demolition, be subject to control by Nordisk Vindkraft in accordance with this procedure detailed above.

7.6.3. High voltage compounds (Ref. SSOP 011 Management of Electrical and Mechanical Safety)

1) No substation boundary fence either temporary or permanent shall be disturbed under any circumstances without permission from the Site Manager.

2) Within areas where there are exposed live conductors, access equipment, cranes, vehicles and any long objects must be moved or used an electrical Permit to Work in accordance with ESA must be prepared by a Senior Authorised Person For further guidance see Trygg under ledningarna, (Safe beneath the lines), published by Sveriges Elleverantörer.

3) Entry into HV compounds or substations is controlled in accordance with SSOP 011 Management of Electrical & Mechanical Safety.

Page 32: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

28

4) In addition to all works in HV compounds or substations requiring an electrical Permit to Work, the following additional safety steps shall apply:

Do not cross ropes or barriers used to mark out safe areas

Check the position of any overhead lines in the working area each day or when moving to a new area

Regard every overhead line or underground cable as being live

Do not take metal ladders into substation or HV compound areas

Maintain a safe distance between scaffold poles or wooden ladders with metal reinforcement in them and overhead lines. Do not carry them upright, but always parallel to the ground.

Never attempt to alter the position of a cable

Do not walk on or use exposed cables as steps or convenient methods of getting out of an excavation

Do not prod with sharp pointed tools near cable routes

Do not breach any security or perimeter fence or tip or stack material near such fences

In the event of an electrical accident or damage to an overhead or underground cable occurring, withdraw personnel from the area and cease operations until the Site Manager or Senior Authorised Person confirms it is safe to return.

5) Where walkways into sub-station compounds are required, they are to be agreed before hand by all parties and the route indentified. This must be clearly indicated with signage, posters to maximize safety from the system. This shall be included in risk assessment and method statements and signed off by the proposer. Access shall be controlled by the Site Manager.

7.7. Gas/ electric welding, burning and cutting

1) The connections to the welding equipment must be sufficient in size for the duty to be performed, properly protected against mechanical damage and in good condition. Refer to SEK Handbook 432.

2) Welding leads must be of appropriate size and in good condition. A lead must be used for the return earth path, structural steelwork or plant must not be used for this purpose.

3) The welding set should be effectively earthed at the source of supply.

4) When welding is being carried out adequate screening must be provided by

Page 33: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

29

the Contractor to prevent exposure to persons in the vicinity to the hazardous effect of ultra violet rays.

5) When gas welding/cutting operations are to be carried out in a confined space particular care must be exercised and the Confined Spaces Regulations must be complied with. No such operations shall be carried out without the prior agreement of the Site Engineer to the Contractor’s proposed working arrangements.

A permit to work shall be used.

6) Welding and burning are fire risks. The Contractor must therefore ensure that work places are kept clear of flammable materials, and screens or mats are used to prevent hot metal falling on persons or equipment.

7) Contractors shall provide suitable portable extinguishers and fire blankets for the use of their welding and burning staff. When necessary, a fire watch shall be posted.

8) Contractors shall provide suitable local exhaust ventilation (LEV) equipment to remove welding fumes at source, when required. The examination and testing records relating to LEV equipment shall be available for examination on site.

9) All personnel involved in burning/welding must wear the appropriate personal protective equipment, PPE.

10) On completion of the work, or at any time when work stops, all equipment shall be isolated and left in a safe isolated condition. In a confined space the equipment shall be removed and disconnected. Any hot metal shall be suitably identified to prevent injury.

11) When not in use gas cylinders, whether oxygen, acetylene, liquid petroleum gas or otherwise shall be closed. All gas cylinders should be fitted with flame arresters.

LPG containers will be inspected annually by a competent person and checked each time they are relocated on site using the Gasolinstallation check list 01627-000747.

12) Temporary fabrication workshops on site should be fitted with a solid steel floor and kick plates. Suitable screens, barriers and fire prevention equipment shall be provided.

13) Where the work presents any risk of fire or causes the exposure of flammable materials on the roof, or work area, the Sub-contractor shall provide suitable fire extinguishers and its employees or agents and Sub-contractors, were appropriate, must be trained in their correct use.

14) LPG heaters must not be used in enclosed areas, an alternative heater must be sourced.

Page 34: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

30

7.8. Protective equipment and clothing (Ref SSWP-002)

1) The Contractor must comply with, and ensure that its employees, agents and Contractors comply with, AFS 2001:3 Användning av personlig skyddsutrustning. All necessary PPE shall be provided by the Contractor.

2) Where protective equipment is required, the Contractor must ensure that all his staff are informed of any risks, provided with the relevant equipment and are adequately trained in the use/storage of the equipment. Where displayed, mandatory signs must be adhered to.

3) The Contractor is required to ensure that its employees, agents and Contractors are provided with and wear protective clothing and footwearand/or equipment suitable for the type of work being performed.

4) Safety helmets must be worn when climbing, if working within 50m of turbines or metmasts where people are working above you and where there is a risk of falling ice and snow.

5) Hearing protection must be worn at all times in designated noise zones.

6) Eye protection must be worn when undertaking any activity where there is a likelihood of injury to the eyes and as directed by site management.

7) Where there is significant risk of injury due to falling and or/working unprotected at heights, safety harnesses must be worn and used. All fall arrest equipment supplied must be to current AFS 1981:14 Skydd mot skada genom fall and carry the CE mark. The use of safety equipment must be enforced by the Contractor and non-compliance will be deemed to be gross industrial misconduct. Any disciplinary action should be recorded and reported to the Site Engineer. This requirement also covers scaffolding work.

7.9. Transport

1) All vehicles used on the Company’s premises or sites, and their drivers, must comply with all the requirements of the Road Traffic Acts and local instructions.

2) All drivers of vehicles must hold a relevant current driving licence. Drivers of mobile plant must have undergone appropriate training and hold a current certificate. Such licences/certificates must be available for inspection by the Company’s staff.

3) Vehicles and mobile plant should be driven carefully at all times; keeping to the site speed limits signs and signals. Drivers should pay particular attention when reversing to ensure that nobody is in danger. Vehicles driven within buildings shall be fitted with a flashing light.

4) Vehicles and mobile plant shall not be driven over trench slabs except at permanent points of crossing, or where suitable provision has been made by the Contractor. In making such provisions the Contractor shall ensure that

Page 35: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

31

the trench is bridged so that the traffic load is transferred to the adjacent sub grade at points at least 0,7m clear of the trench walls. The use of bridges over ditches and sub grade should be covered in the design.

5) When working in the vicinity of overhead lines, drivers of mobile cranes, tipping lorries and similar vehicles must take particular care, and must satisfy the Site Engineer that the precautions being taken are satisfactory. The basic safety precautions recommended are explained in the Swedish electricity legislation.

6) When mobile plant is to be used on other than designated site roadways, the routes to points of work must be approved by the Site Engineer (this is especially important for mobile crane operations). Electricity substation compounds must not be subjected to traffic loads in excess of those for which it is designed.

7) Fire points, access/exit points and roadways must be kept clear of obstruction, and cars and vehicles parked as directed by Company staff.

8) Contractors must, where appropriate, comply with the requirements of Väglag SFS 1973:948, Bilaga till IFS 2009:4, Anläggningslag SFS 1973:1149 and AFS 1999:3 Byggnads- och anläggningsarbete. It is the Contractors responsibility to ensure that sufficient signs and barriers are posted around such works to secure the safety of all persons, and that such signs and barriers are posted prior to the work commencing. The Contractors vehicles must be parked with due regard to other road or street users.

9) Site vehicles such as mobile plant and lorries must be fitted with at least one high level amber flashing beacon which must be operational when on site. The use of hazard indicators in place of high level beacons is not permitted.

10) Large mobile plant and vehicles must be fitted with automatic reversing warning devices and where possible a reversing camera. Such devices must be regularly maintained in a fully serviceable condition, including regular cleaning of devices fitted to the rear of the vehicle.

11) Large mobile plant and vehicles should be fitted with wide-angle and close-proximity mirrors. This is particularly important on the pedestrian side of the vehicle.

12) The use of mobile phones whilst driving plant and vehicles on site is strictly prohibited. Drivers must park in a safe place and turn off the plant/vehicle to use a mobile phone.

7.10. Fire

1) The fire alarm must be raised immediately, if a fire, however small, is discovered. The Contractor must, therefore, be fully conversant with the alarm system, the project Fire and Emergency Plan and muster point.

Page 36: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

32

2) The Contractor’s site premises and working areas must be kept clear of flammable materials such as waste, oily rags and similar material.

3) The Contractor must ensure that care is taken with any equipment which employs a naked flame; e.g. blowlamps, gas torches and braziers. An appropriate fire appliance must be available locally.

4) Gas cylinders must be used with care, and handled and stored in accordance with legislative requirements. AFS 2001:04 Gasflaskor shall be complied with where appropriate. Storage locations to be as agreed with the Site Engineer.

5) The use of open fires for disposal of waste materials or heating is strictly prohibited.

6) All site huts, joining shelters and similar must be in good condition and suitably maintained. They must be clearly identified with the Contractors name and equipped with fire extinguishers/fire fighting equipment appropriate to the risk.

7) The Contractor must ensure that care is taken in the positioning of scaffold boards, tarpaulins and combustible materials adjacent to boilers and steam mains.

8) The Contractor must ensure that designated escape routes are kept clear of obstruction at all times.

9) The Contractor shall ensure that only work methods, which minimise the risk of fire, are employed in the use of equipment, liquids, gases or materials which could involve danger from fire. The Contractor shall agree with the Site Engineer all necessary precautions to safeguard against damage by fire or explosion where work may involve the presence of flame or sparks.

10) When not in use, equipment and vessels which contain flammable liquids or gases must be fully and securely closed and removed to a safe place of storage. The storage area must be appropriately marked up with relevant signage in accordance with AFS 2008:13 Skyltar och signaler.

11) When not in use, equipment and vessels which contain flammable liquids or gases must be fully and securely closed and removed to a safe place of storage.

12) All hot works must be undertaken under a permit to work scheme.

13) Contractors shall comply with AFS 1999:3 Byggnads- och anläggningsarbeteor any subsequent amendment to or revised Edition thereof current at the commencement of a contract

7.11. Working areas

Page 37: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

33

1) Working areas may not be for the exclusive use of one Contractor, but, where necessary, shall be shared with others. Contractors must ensure that their actions, or omissions, will not adversely affect others working in the area.

2) Contractors shall maintain the whole area of his operations in a clean, tidy and safe condition by arranging his materials and plant in an orderly manner. All rubbish, waste material, scrap material, debris and the like shall be systematically cleared from the working area as it is accumulated.

3) The Contractor shall take reasonable precautions to keep all public or private roads and walkways clear of any spillage from his traffic. All such spillage shall be cleared immediately.

7.12. Storage of materials

1) The Contractor shall:

Store all materials in a safe and tidy manner at designated areas only.

At the end of the Contract, reinstate to the satisfaction of the Site Engineer, the area allocated to him.

Where required, store chemicals in suitable containers within a bund that is capable of storing 110% of the chemical, provide appropriate spill kits and PPE

2) The Company shall:

Accept no responsibility for the safe keeping of such materials.

Reserve the right to relocate material storage areas.

7.13. Contractors plant & equipment

1) All tools and equipment necessary to carry out the work will be supplied by the Contractor, unless otherwise stated within the Contract documentation.

2) The Contractor shall ensure that all plant provided by him is; entirely suitable for the intended purpose, is serviceable, and complies with appropriate regulations and is only operated by authorised competent persons. Damaged or unserviceable equipment shall be removed from site at the earliest opportunity.

3) The Contractor is responsible for ensuring that all plant and equipment which is subject to current legislation has up to date Test Certificates and Inspection

Page 38: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

34

Records.

4) All scaffolding, staging, ladders, and similar, provided by the Contractor, shall comply with all applicable regulations.

5) The Contractor shall be responsible for the safe and secure storage of all his tools and equipment at site.

6) Current test certificates in accordance with statutory requirements for all items of lifting equipment used on the site shall be made available for inspection by the Site Engineer. No site tests shall be carried out without adequate notification to the Site Engineer.

7.14. Signs

1) The Contractor shall supply, install and remove (when no longer applicable) all safety signage required to adequately warn, inform or remind their own workers and third-parties about safety information. All signs provided by the Contractor shall comply with the current Safety Sign Regulations.

7.15. Lighting

1) Adequate lighting for access and working shall be provided by the Contractor. All mains powered portable lighting shall be supplied from the standard 230V ac sockets and shall be to current ELSÄK-FS Regulations.

2) All portable lighting must be positioned to give adequate light and prevent shadowing around the work area.

7.16. Confined Spaces

1) AFS 1993:3 Arbete i slutet utrymme must be complied with and the Contractor must carry out a site specific risk assessment for any work where the Regulations apply.

2) Where it is necessary to undertake work in a confined space a Permit to Work shall be employed. For detailed information: SSOP 013 Permits to work.

3) The contractor is to ensure that all persons working in confined spaces are trained and adequately resourced.

4) Nacel working and access shall be carried out in accordance with SSWP 028 Work in Nacells.

Page 39: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

35

7.17. Noise & Disturbance

1) Contractors shall conform to AFS 2005:16 Buller throughout the contract. Contractors’ noise assessments shall be made available to the Site Engineer.

7.18. Hand Arm Vibration

1) Contractors must according to AFS 2005:15 Vibrationer; plan, assess and identify measures to eliminate or reduce risks from exposure to hand-arm vibration so that they can protect their employees from risks to their health.The risk assessment will include an estimate of daily exposure to vibration. The estimate of the daily exposure should be conducted by an expert person.

Where the risks are low, the actions you take may be simple and inexpensive, but where the risks are high, you should manage them using a prioritized action plan to control exposure to hand-arm vibration.

Contractors’ hand-arm vibration assessment shall be made available to the Site Engineer.

8.0 ENVIRONMENTAL MANAGEMENT

Refer to the Envronmental Requirements of Contractors MS04-000995.

9.0 SITE SAFETY RULES FOR EMPLOYEES OR CONTRACTORS

1) The Company’s Site Engineer will provide induction training as a minimum to the Contractors Safety Representatives. The Safety Representatives, with the Site Engineers permission, shall induct all other employees.

The Contractor shall ensure that the Site Rules and any other safety provisions are brought to the attention of and complied with by its employees, agents and Contractors and displayed in the Contractors site office, where a site office exists.

A copy of the project specific Site Rules will be issued to everyone at induction.

9.1. General

1) 1. Nordisk Vindkraft O & M Emergency contact numbers for Nordisk Vindkraft operational sites are located on template - MS04-000566

Page 40: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

36

9.2. Accidents

1) All employees, agents and Sub-contractors must:

Know the procedure for obtaining assistance in the event of an accident.

In the even of an accident;

Make sure injured persons and themselves are not exposed to further injuries.

Not move injured persons unnecessarily.

Stand by to assist first-aiders or to give details of the occurrence.

Report all accidents immediately to the Site Engineer; ensure that appropriate records be kept on site. Use Nordisk Vindkraft’s templates.

Where appropriate take photographs or the immediate area

Undertake an accident investigation and report findings/outcomes to Nordisk Vindkraft Site Engineer.

9.3. Emergencies during work

1) All employees, agents and Contractors will be briefed on the Construction Fire and Emergency Plan for the site. Copies will be posted on the site.

2) All employees, agents and Contractors must:

Know the fire and emergency procedures for the site.

Raise the alarm immediately, if a fire is discovered.

Evacuate the area immediately, if the fire is uncontrollable.

Know how to use your company’s fire fighting equipment and, if trained in using it, make sure that you have an escape route in the event that the fire becomes uncontrollable.

Know where the muster point is.

3) Each Contractors Safety Representative shall be responsible for accounting for all their employees and shall report to the Fire Marshal if that everyone working for that Contractor is/is not accounted for.

The role of Fire Marshall will be fulfilled by the Site Engineer, unless he has delegated it to another member of Nordisk Vindkraft staff.

Page 41: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

37

4) Contractors shall comply fully with periodic drills organised by the Company to test awareness of the evacuation procedure included in the Fire and Emergency Plan.

9.4. Wind turbines

1) Climbing wind turbines is only permitted if:

You have been trained and authorised to climb a turbine, or are accompanied by someone who is, and;

Authorised to do so by the turbine supplier. At least two people are present, one of whom can operate the turbine. Adequate safety harnesses, lanyards etc are available. Meteorological and atmospheric conditions permit Persons are medically and physically fit to climb

9.5. Disciplinary Procedure

In the event of violation of site rules, non-compliance with this working procedure, negligence, unsafe act or omission or misconduct by a Contractor, the Site Manger shall have the right to impose a disciplinary sanction on the person and/or their Safety Representative in order to act as a deterrent or warning.

Three levels of sanction are available to the Site Engineer as described below in ascending order of severity:

1) Verbal Warning - The person will be given a verbal warning that will be recorded and copied to their Safety Representative

2) Written Warning - The person will be given a written warning, which shall be copied to their Safety Representative

3)Exclusion – The person will be shall be required to leave site for the duration of the remainder of the project, with a written record of the exclusion being issued subsequently to the person, copied to their Safety Representative

While the Site Engineer, acting reasonably and with due discretion, may apply any sanction at any stage to any person, it is expected that the sanction of exclusion from site shall be used in instances of repeated or major non-compliance and/or gross misconduct, normally endangering the safety of others working on site.

10.0 DELIVERABLES

The following shall, be retained as safety records.

Page 42: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

38

1) Issue/ Receipts for SSWP-027 shall be filed in the Wind Farm Project HSQE folder

11.0 APPENDICES

Page 43: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

39

Appendix 1 – Issue / Receipt for SSWP -027

Page 44: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

1

SAFETY REQUIREMENTS FOR CONTRACTORS

ISSUE DOCUMENT

Issued to ...............................................................................................

Contract Number and Description............................................................................................

............................................................................................................................................

........................................................................................................................................................

Location ................................................................................................

The person named below is the Company Project Manager responsible for overall management of the contract.

Project Manager ......................................................................Telephone ..............................

The person named below is the Company Site Engineer responsible for local management of the contract, who will be permanently on site.

Site Engineer ........................................................................Mobile ..................................

Other Site Telephones .......................................................................................................

The Site Engineer should always be the first point of contact, if for any reason, he is not available you should contact the Company Project Manager.

The Company Safety Management System and Site Rules are available/displayed at :

......................................................................................................................................................

Page 45: RSWP 027 Safety Requirements For Contractors on …1) Swedish Standard: SS-EN 50 110-1 Skötsel av elektriska anläggningar 2) Swedish Standard: SS-EN 50 110-2 Skötsel av elektriska

Document Reference: MS04-000672 Issue: 01 - Approved

2

SAFETY REQUIREMENTS FOR CONTRACTORS

RECEIPT DOCUMENT

RENEWABLE ENERGY SYSTEMS COPY

(To be detached and retained by the Site Engineer when this document is issued to a Contractor on site)

I acknowledge receipt of the safe works procedure - Safety Requirements for Contractors.

Contract Number and Description.................................................................................................................................................................................................................................................

........................................................................................................................................................

Location ......................................................................................

Signed .........................................................................................

Contracting Company ............................................................................................................

Date ............................................................................................

Contracting Company Head Office Telephone ..........................................................................

Local/site Telephone Number .......................................................